BY SPEED Steel Authority of Limited POST Steel Plant Rourkela – 769011 Fax : 0661-2510183

Ref.No. : 691/EE/59/251, Date : 12/05/2018. Dear Sir,

Sub : Implementation Status of Env. Clearance Conditions issued to RSP.

Ref. : EC vide ref.no. F No. J -11011/757/2007-IA II(I), dated 29/01/2008, extension order dated 05/07/2013 & amendment order dated 26/03/2014.

# # #

This has reference to the aforesaid Environment Clearance (EC) accorded to Rourkela Steel Plant (RSP) for its Expansion project, its extension order and amendment w.r.t. water consumption . The implementation status of the various Special and General Conditions mentione d in EC order for the period of Oct.,2017 - March.,2018 is enclosed.

As desired earlier, the quality of sewage generated from Rourkela Steel Plant, which is finally treated at Lagoon, is given at Annexure-13. As suggested by Addl. Director(S), MoEF, during his visit to RSP on 10 th & 11 th October , 2014, monitoring of the following Environmental Parameters has been carried out and the monitoring data is given at Annexure-15 to Annexure -19, enclosed.

Annexure-15 : Special Noise Monitoring at Ambient Air Stations at Ground Level . Annexure-16 : Work zone dust special monitoring during Oct.,2017 - March.,2018 Annexure-17 : Expenditure on various Pollution Control Systems installed in different plant units Annexure-18 : List of ESPs installed in different departments and PG Test Status Annexure-19 : Details of micro fine dust generation from ESPs of Expansion Project.

As desired, all the points mentioned in your letter File No. 101-320/15/EPE, dated 26/02/2018, have been addresse d and accordingly this report has been updated. With warm regards, Yours faithfully, For Rourkela Steel Plant,

(S N Xess) Dy. General Manager Environmental Engg. Department Note : Soft copy mailed to roez.bsr [email protected] ; [email protected] To, The Chief Conservator of Forests, Eastern Regional Office, Ministry of Environment & Forests, A/3, Chandrasekharpur, Bhubaneswar. – 751023.

Environmental Engg. Department, 1 st Floor of OHSC Building, Rourkela Steel Plant, Rourkela Phone : 0661-2510395 Fax : 0661-2510183 Regd.. OfOffice : Ispat Bhawan, Lodi Road, New Delhi – 110 003

Steel Authority of India Limited Rourkela Steel Plant’s Expansion Project (Environment Clearance vide ref.no. F No. J-11011/757/2007-IA II(I), dated 29/01/2008 & EC extension up to 29/01/2018 vide order , dated 05/07/2013 & Amendment order dated 26/03/2014) Half Yearly Report (Oct.,2017 - March ., 2018) Contact Persons : Sri S N Xess, DGM (Env.Engg.) Phone : 0661-2447258 Sri V V R Murty, DGM(Env.Engg.) Phone : 0661-2448254

Special Conditions

SN. CONDITION STATUS/ ACTION PLAN

RSP has 6 no. of coke oven batteries. Battery No. 1, 3, 4 & 5 have been rebuilt All the existing batteries shall be rebuilt by & commissioned in the years 2007, 2016, 2010 & 2000 respectively. Battery No. 2012 meeting all the pollution control 6 is a new Green field Battery which was commissioned on 01/04/2014, under i) norms as per CPCB guidelines and a this Expansion Project. commitment in this regard shall be submitted to the Ministry Coke Oven Battery No. 2 was put down since March, 2016 as it has outlived its life and due for rebuilding. Presently no repair/rebuilding activity is going on.

The industry shall follow coke oven RSP is following the Coke Oven Standards and will continue to follow as per E(P) standards as per E(P) Rules. VOCs from the Rules. VOCs are being monitored at Coke Ovens stacks using a portable VOC ii) coke oven shall be monitored and analyzer. The monitoring results along with interpretation are given at controlled as per CPCB guidelines. Annexure- 1.

All out efforts are being made to further reduce waste generation, reduce all Efforts shall be made to further reduce the stack emissions, thereby to improve ambient air quality. A report is being existing ambient air and stack emissions submitted to CPCB and SPCB once in a month regularly giving the status of stack iii) and waste generation and a report emissions, ambient air quality & solid waste utilization. A report showing the submitted to the Ministry, its Regional stack emissions, ambient air quality and solid waste utilization for the period of Office at Bhubaneswar, CPCB and OPCB. Oct.,2017 - March,2018 along with interpretation are given at Annexure-2, 3 & 4 respectively.

RSP has installed state of the art pollution control systems like Dry fog dust Efforts shall be made to reduce RSPM suppression systems, Electro Static Precipitators, Bag Houses etc., along with levels in the ambient air and a time bound online stack monitoring systems during the implementation of expansion action plan shall be submitted. On-line project to keep the stack emissions less than 100 mg/NM 3. All the existing stack monitoring facilities for all the stacks pollution control equipment like Bag Houses and ESP are being revamped so that and sufficient air pollution control iv) the stack emissions will further come down, the ambient air quality will improve methods shall be provided to control and RSPM levels in ambient air quality will come down. The monthly status emissions below 100 mg/Nm 3 viz. ESP and report covering stack emissions and ambient air quality is being submitted to bag filters etc. and data submitted to the CPCB and SPCB, on monthly basis, regularly. The ambient air quality & stack Ministry’s Regional Office at emissions during Oct.,2017 - March.,2018 along with interpretation are given at Bhubaneswar, CPCB and OSPCB Anex-2 & 3.

Three no. of ESPs were provided in Sinter Plant#3, & 4 no. of ESPs were Electrostatic precipitator (ESP) shall be provided in Steel Melting Shop, which are in effective operation. SPCB, Odisha provided to Sinter plant, Power Plant and issued consent to operate for 4.2 MTPA RSP. Blast Furnace (BF) to control gaseous emissions from all the vents/stacks within CDI has been provided in Blast Furnace No. 4 & #5. Three no. of new ESPs were 100 mg/Nm 3. Coal dust injection (CDI) provided in Blast Furnace#4 & 5. shall be provided to Blast furnace plants. Bag filter shall be provided to lime 6 no. of Bag houses are provided in Calcining Plant#2 expansion and v) Calcining Plant, new vertical shaft kiln and HPLA system along with Bag Houses & Dry fog & Wet fog dust suppression Dolomite plant. Emissions shall be systems are provided in Coke Oven Battery#6, which are under effective controlled from the Cast house and Stock operation. house within permissible limits. High Pressure Liquor Aspiration (HPLA) system The stack emissions i.e., at the outlet of pollution control systems are regularly shall be provided to new Coke Oven monitored and cross checked with its design norms. Preventive and corrective Battery actions are being taken for maximizing the efficiency of ESPs based on the monitoring results.

2

SN. CONDITION STATUS/ ACTION PLAN

Presently RSP is monitoring BaP & PAH in the ambient air and Regular monitoring of the Benzo(a)Pyrene, Poly stack emissions of Coke Ovens once in a year. The PAH levels along Aromatic Hydrocarbons (PAHs) and Volatile Organic with interpretations are given at Annexure-5. vi) Compounds (VOCs) in the ambient air and stack emissions shall be carried out. VOCs in stacks and ambient air are monitored and the results along with interpretation are given at Annexure- 1 & 2.

Secondary fugitive emissions from all the sources including blast furnace and sinter plant shall be RSP is following all the CPCB guidelines / code of practices in vii) controlled within the latest permissible limits issued by controlling secondary fugitive emissions. the Ministry and regularly monitored. Guidelines / Code of Practice issued by the CPCB shall be followed.

Total make up water requirement of the Plant from Brahamani River shall not exceed *2,27,352 m3/day and prior permission shall be obtained from the concerned No ground water is being used. department. No ground water shall be used for the plant. The effluent shall be treated in the effluent The wastewater is being treated in the dedicated wastewater treatment plant. Maximum treated wastewater shall treatment plant, which are installed in different departments, and be recycled and reused in the process for cooling, gas the treated water is being recycled back to the process. The viii) cleaning plant (GCP), steel making, slag granulation wastewater is being discharged only after confirming to the plant (SGP), dust suppression, green belt development statutory norms through meticulous sampling and analysis. The etc. The excess wastewater shall be discharged only quality of finally treated effluent going to river during after conforming all the parameters to the prescribed Oct.,2017 - March,2018 along with interpretation is given at standards within the permissible limits of OPCB. Annexure-6.

*MoEF’s Corrigendum dated 26 th March, 2014.

As proposed, 90% of the solid waste shall be recycled The utilization of total solid wastes have already been enhanced and reused and remaining shall be disposed off in by maximizing the utilization of BFc slag for cement making. SMS secured landfill designed as per the specifications of the slag utilization is being increased by enhancing its utilization in CPCB. BF slag shall be granulated and used in base mix preparation (Sinter making) in blast furnaces, as rail environment-friendly manner. Slag from SMS-I & II shall ballast, road making and its use for development of land areas ix) be used for making road embankments. Iron ore fines, inside the plant premises. All the metallic scrap is being recycled Fluxes cinder, Mill scales and Scrap etc. shall be recycled back to SMS. All the waste oil is being sold to the outside parties and reused in Sintering Plant. SMS scrap shall be who are having valid registration with statutory agencies. The solid recycled in Steel Melting Shop. All the waste oil shall be waste utilization during Oct.,2017 - March.,2018 is given sold to recyclers/re-processors. at Annexure-4.

Regular ground water samples are being collected from waste Ground water monitoring around the solid waste disposal areas, Secured Land Fills etc., and the report are being disposal site / secured landfill (SLF) shall be carried out submitted to MoEFCC’s regional office at Bhubaneswar, CPCB & x) regularly and report submitted to the Ministry’s SPCB on monthly basis. The ground water quality during Regional Office at Bhubaneswar / CPCB and OPCB. Oct.,2017 - March.,2018 along with interpretation is given at Annexure-7.

An action plan for the disposal of fly ash, granulated All the Blast Furnace Slag is being granulated through in-house slag and SMS slag shall be submitted to the Ministry within 3 granulation units and used for making slag cement. months. All the BF slag generated shall be granulated

and provided to cement manufacturers for further State of the art technologies are being adopted in steel making so utilization and should not be disposed off anywhere xi) that the SMS slag generation rate will be minimized. The SMS slag else. SMS slag shall also be properly utilized. All the is being utilized for Sinter Making through base mix, charged into char from DRI plant shall be utilized in AFBC boiler of Blast Furnaces in place of lime stone and also used for pavement power plant and no char shall be disposed off anywhere making and as rail ballast and also used for development of land else. All the fly ash shall be utilized as per the Fly Ash inside the plant premises. Notification, 1999 and subsequently amended in 2003.

3

SN. CONDITION STATUS/ ACTION PLAN

There is no additional fly ash generation after implementation of proposed modernization cum expansion project as the additional power is being obtained from Top Recovery Turbine (14 MW) & Power Blowing Station of Blast Furnace No. 5 (36 MW), Back An action plan for the disposal of fly ash, granulated Pressure Turbo Generator (6.4 MW) of COB#7 and remaining 110 and SMS slag shall be submitted to the Ministry within 3 MW power is being obtained from State Grid. months. All the BF slag generated shall be granulated

and provided to cement manufacturers for further As per the present agreement with NTPC, the joint venture power utilization and should not be disposed off anywhere xi) company NSPCL is managing the fly ash, generated from captive else. SMS slag shall also be properly utilized. All the power plant of RSP. The fly ash is being utilized for construction of char from DRI plant shall be utilized in AFBC boiler of new Ash Pond “D”, dyke height raising of Ash Pond “C”. power plant and no char shall be disposed off anywhere

else. All the fly ash shall be utilized as per the Fly Ash Dry fly ash is being given to local entrepreneurs for brick making Notification, 1999 and subsequently amended in 2003. free of cost. All the fly ash is being utilized as per the Fly Ash Notification, 1999, amended from time to time.

There is no char generation in Rourkela Steel Plant

RSP is developing green belt in consultation with DFO through State Forest Department. 62,446 no. of saplings have been planted Green belt shall be developed in 33 % area within and during 2017-18 & 1 lakh saplings have been distributed in the xii) around the plant premises as per the CPCB guidelines in peripheral villages free of cost, and so far more than 44.50 lakh consultation with DFO. trees have already been planted, covering more than 33% of the area. Recommendations of the State Forest Department shall be obtained regarding impact of the proposed The findings of EIA/EMP were submitted to State Forest xiii) expansion of the plant on the Sona Parbat RF, North Department. DFO, Rourkela has authenticated the report and the Chirobeda RF and South Chirobeda RF and copy of the letter from DFO is enclosed at Annexure-8. implemented.

RSP is strictly following all the CREP action points and will continue All the recommendations mentioned in the CREP xiv) to follow the same. The status of implementation is being guidelines for the steel plants shall be implemented submitted t to SPCB, CPCB, MoEF on monthly basis.

4 GENERAL CONDITIONS

SN. CONDITION STATUS/ ACTION PLAN

The project authorities must strictly adhere to the RSP strictly adheres to the stipulations made by State i) stipulations made by the Orissa Pollution Control Board Pollution Control Board, Odisha and State Government. (OPCB) and the State Government

No further expansion or modifications in the plant should be ii) carried out without prior approval of the Ministry of RSP is following strictly. Environment and Forests.

The gaseous emissions from various process units shall conform to the load/mass based standards notified by this Ministry on 19th May, 1993 and standards prescribed from time to time. The state Board may specify more stringent RSP is following all the standards notified by the MoEF and standards for the relevant parameters keeping in view the State Pollution Control Board from time to time. On line nature of the industry and its size and location. At no time, iii) continuous monitoring systems are installed in fifteen no. of the emission level shall go beyond the prescribed standards. stacks of different units and the data has been uplinked with On-line continuous monitoring system shall be installed in CPCB and SPCB servers. stacks to monitor SPM and interlocking facilities shall be provided so that process can be automatically stopped in case emission level exceeds the limit. NOx burners shall be installed to control NOx levels

At least four ambient air quality-monitoring stations shall be RSP established 6 no. of ambient air quality monitoring established in the downward direction as well as where stations, covering all directions, in consultation with State maximum ground level concentration of SPM, SO2 and NOX Pollution Control Board. The ambient air quality data is being iv) are anticipated in consultation with the OPCB. Data on submitted to MoEF, its regional office at Bhubaneswar, CPCB ambient air quality and stack emission shall be regularly & SPCB, every month through monthly report. The ambient submitted to this Ministry including its Regional Office at air quality for the period Oct.,2017 - March.,2018 along with Bhubaneswar / OPCB / CPCB once in six months data interpretation is given at Annexure – 2.

In-plant control measures for checking fugitive emissions from all the vulnerable sources like Coke oven area, Sinter plant, Blast Furnace area etc. shall be adopted. Further, specific measures like water sprinkling shall be carried out at Fugitive emissions are being monitored regularly at Coke the stock piles of raw material, stacker, reclaimer, transfer Ovens, Sinter Plant, Blast Furnaces etc. RSP has adopted all points etc. Dust extraction system and bag filters shall be air pollution control measures like ESPs, Bag houses, dust provided to the sinter plant, stock house, blast furnace and extraction systems, dry fog dust suppression systems, dust steel melting shop etc. Fume extraction system in steel v) suppression by water sprinkling etc., at different places to refining units shall also be provided. Centralized dedusting control dust emissions. All the emissions are being regularly system i.e. collection of fugitive emissions through suction monitored and records are being maintained. The fugitive hood and subsequent treatment through bag filter or any emissions monitored during Oct.,2017 - March,2018 along other device and finally emitted through a stack of with data interpretation is given at Annexure-9. appropriately designed and height conforming to the standards for induction furnaces in the industry shall be provided. Fugitive emissions shall be controlled, regularly monitored and records maintained.

Industrial wastewater shall be properly collected, treated so The industrial wastewater is being properly collected & as to conform to the standards prescribed under GSR 422 (E) treated in dedicated wastewater treatment plants and the vi) dated 19th May, 1993 and 31st December, 1993 or as treated effluent is being utilized for plant purposes to the amended form time to time. The treated wastewater shall be maximum extent. utilized for plantation purpose.

5

SN. CONDITION STATUS/ ACTION PLAN

Suitable noise control measures/technologies are being The overall noise levels in and around the plant area shall be incorporated in different noise generating sources itself so kept well within the standards (85 dBA) by providing noise that the noise levels will be maintained below the standards control measures including acoustic hoods, silencers, (85 dBA) in and around the plant area and the ambient noise vii) enclosures etc. on all sources of noise generation. The levels of 75 dBA during day time and 70 dBA during nighttime ambient noise levels should conform to the standards has been achieved. The monitored noise levels at various prescribed under EPA Rules, 1989 viz. 75 dBA (daytime) and ambient air quality monitoring stations during Oct.,2017 - 70 dBA (nighttime). March.,2018 along with data interpretation are given at Annexure-2.

The company shall develop surface water harvesting 3 no. of Rain Water Harvesting systems units have been viii) structures to harvest the rain water for utilization in the lean constructed and put into operation. season besides recharging the ground water table.

RSP established Occupational Health Service Center (OHSC) Occupational Health Surveillance of the workers shall be done inside the plant itself with dedicated team of doctors, and ix) on a regular basis and records maintained as per the Factories other skilled medical staff. Health checkup of all the workers Act. is carried out by OHSC once in a year and the records are being kept.

RSP is implementing all the action points mentioned under Recommendations made in the CREP guidelines issued for the x) CREP for Steel Industry. The status is being submitted on steel plants shall be implemented. monthly basis to all statutory authorities.

RSP is being complying with all the environmental protection measures and safeguards recommended in EIA/EMP report.

The project proponent shall also comply with all the RSP has established a separate department called “CSR- environmental protection measures and safeguards Corporate Social Responsibility” to take care the socio recommended in the EIA / EMP report. Further, the company economic developmental activities in the surrounding villages xi) shall undertake socio economic development activities in the through economic up-liftment programmes, community surrounding villages like community development development programmes, educational programmes, skill programmes, educational programmes, drinking water supply development programmes etc. and health care etc.

The highlights of CSR activities during 2017-18 are given at Annexure-14.

The project authorities shall utilize Rs. 614.00 Crs. and Rs. 36.00 Crs. earmarked total capital cost and recurring cost/annum for environment pollution control measures RSP has not diverted the funds allocated for pollution control respectively judiciously to implement the conditions measures and implement all the conditions stipulated by stipulated by the Ministry of Environment and Forests as well xii) MoEF and State Government. The implementation schedule as the State Government. An implementation schedule for of various conditions stipulated in EC is enclosed at implementing all the conditions stipulated herein shall be Annexure-10. submitted to the Ministry’s Regional Office at Bhubaneswar. The funds so provided shall not be diverted for any other purpose.

The Regional Office of this Ministry at Bhubaneswar/CPCB/OPCB will monitor the stipulated The compliance report is being submitted once in six months, xiii) conditions. A six monthly compliance report and the regularly. monitored data along with statistical interpretation shall be submitted to them regularly.

6

SN. CONDITION STATUS/ ACTION PLAN

RSP has released an advertisement In the following news The Project Proponent shall inform the public that the project papers. has been accorded environmental clearance by the Ministry and copies of the clearance letter are available with the 1) The Times of India, Bhubaneswar edition dated OPCB/Committee and may also be seen at Website of the 07/02/2008. (English) Ministry of Environment and Forests at http:/envfor.nic.in. 2) Samaj, Rourkela dated 07/02/2008 (Oriya) xiv) This shall be advertised within seven days from the date of issue of the clearance letter, at least in two local newspapers Copies of the paper advertisement were submitted to MoEF that are widely circulated in the region of which one shall be regional office vide letter no. 691/EE/59/354-355, dated in the vernacular language of the locality concerned and a 08/02/2008. copy of the same shall be forwarded to the Regional office. Copy of the news paper cutting is enclosed at Annexure-11.

Project authorities shall inform the Regional Office as well as the Ministry, the date of financial closure and final approval The project was sanctioned by SAIL on 23/06/2007. Copy of xv) of the project by the concerned authorities and the date of the sanction order is enclosed at Annexure-12. The land commencing the land development work started in November,2008. development work.

Additional Conditions

(Reference : Letter of Dr. V P Upadhyay, Director(S) addressed to Managing Director, RSP 106-9/EPE, dtd. 08/06/2011)

SN. CONDITION STATUS/ ACTION PLAN Ambient air quality is monitored continuously using 4 no. of AAQMS- automatic ambient air quality monitoring stations installed at Sector-2, Sector-22 of Steel Township and along the plants boundary one at ERWPP and another at SSSY area. Continuous monitoring of stack emissions as well as ambient All these four stations have been uplinked with SPCB & CPCB air quality (as per notified standards) shall be carried out and servers. In addition to this, ambient air quality is regularly continuous records maintained. Based on the monitored monitored at six number of ambient air stations located along (i) data, necessary corrective measures as may be required from plant’s boundary. Stack emissions are also monitored time to time shall be taken to ensure that the levels are regularly. Continuous records are maintained for ambient air within permissible limits. The results of monitoring shall also quality and stack emissions and necessary corrective actions be put on the website of the company in the public domain are taken to contain pollution.

The monitoring results are uploaded to SAIL’s official Web Site at www.sail.co.in (Web page  Environment Management under Rourkela Steel Plant)

The six monthly monitoring reports as well as the monitored The monitored data as per Env. Clearance conditions are data on various parameters as stipulated in the environment submitted to State Pollution Control Board, Odisha on clearance conditions shall be put on the website of the (ii) monthly basis, regularly. The half yearly compliance report company and also regularly updated. The monitored data for the period Oct.,2017 - March,2018 will be uploaded to shall also be submitted to respective State Pollution Control SAIL’s website by 01/6/2018. Board/ UTPCC and the Regional Office of MoEF.

The ambient air quality data and stack emission data is displayed in the form of two number of Flex Board of 8’ x 5’ The ambient air quality data as well as the stack emission size, in front of Main Gate of RSP. The data is updated on data will also be displayed in public domain at some quarterly basis. (iii) prominent place near the main gate of the company and updated in real time. The environment data is being continuously displayed through LED based electronic display board which was installed at Main gate of RSP.

7 Annexure-1 Data interpretation of Monitoring results of VOC in Stack & Work zone of Coke Ovens (Oct.,2017 - March.,2018) Oct Change Apr.- Stack Oct., Nov., Dec., Jan., Feb., March., 2017.,- w.r.t. SN. Department Sept., connected to 2017 2017 2017 2018 2018 2018 March., Apr.-Sept., 2017 2018 2017 1. Battery#1 BDL BDL BDL BDL BDL BDL BDL BDL No change 2. Battery#2 S/D S/D S/D S/D S/D S/D S/D S/D No change 3. Battery#3 BDL S/D S/D S/D S/D BDL BDL BDL No change Coke Ovens 4. Battery#4 BDL BDL BDL BDL BDL BDL BDL BDL No change 5. Battery#5 BDL BDL BDL BDL BDL BDL BDL BDL No change 6. Batery#6 BDL BDL BDL BDL BDL BDL BDL BDL No change 7. Process ESP BDL S/D BDL BDL BDL BDL BDL BDL No change Sinter 8. Addl. ESP BDL S/D BDL BDL BDL BDL BDL BDL No change Plant#1 9. Old ESP BDL S/D BDL BDL BDL BDL BDL BDL No change 10. Process ESP BDL BDL BDL BDL BDL BDL BDL BDL No change Sinter Space De 11. Plant#2 BDL BDL BDL BDL BDL BDL BDL BDL No change dusting ESP 12. Process ESP-1 BDL BDL BDL BDL BDL BDL BDL BDL No change 13. Sinter Process ESP-2 BDL BDL BDL BDL BDL BDL BDL BDL No change Plant#3 Plant de- 14. BDL BDL BDL BDL BDL BDL BDL BDL No change dusting ESP 15. TA Line BDL BDL BDL BDL BDL BDL BDL BDL No change 16. Decarb Line BDL BDL BDL BDL BDL BDL BDL BDL No change Silicon Steel 17 Pickling line BDL BDL BDL BDL BDL BDL BDL BDL No change Mill Ammonia 18. BDL BDL BDL BDL BDL BDL BDL BDL No change cracking unit 19. MP Boiler#1 BDL BDL S/D BDL BDL BDL BDL BDL No change 20. MP Boiler#2 BDL BDL BDL BDL BDL BDL BDL BDL No change 21 Captive MP Boiler#3 BDL BDL BDL BDL BDL BDL BDL BDL No change Power 22. HP Boiler#1 BDL S/D S/D S/D BDL S/D S/D BDL No change Plant#1 23. HP Boiler#2 BDL BDL BDL BDL S/D BDL BDL BDL No change 24. HP Boiler#5 BDL BDL BDL BDL BDL BDL BDL BDL No change 25. HP Boiler#6 BDL BDL BDL BDL BDL BDL BDL BDL No change

Work zone Monitoring : Apr.- Oct 17.,- Change w.r.t. Depart- Oct., Nov., Dec., Jan., Feb., March. SN. Work zone location Sept., March., Apr.-Sept., ment 2017 2017 2017 2018 2018 , 2018 2017 2018 2017 Ram side – at Central 1. <1 <1 <1 <1 <1 <1 <1 <1 No change control room Coke side – at Central -1.61 % (Lower) 2. 6.2 – 8.8 7.3 8.6 8.5 6.4 6.1 7.1 6.1 – 8.6 control room -2.27 % (Upper) Coke Near Wharf – at +3.27% (Lower) 3. 6.1 – 8.9 8.7 8.8 8.3 7.4 6.5 6.3 6.3 – 8.8 Ovens Central Control room -1.12% (Upper) +6.66% (Lower) 4. Near Quenching Tower 6.0 – 9.0 8.8 8.6 8.5 6.4 6.5 6.4 6.4 – 8.8 -2.22% (Upper) +1.56 % (Lower) 5. Coke Oven top 6.4 – 8.7 8.2 8.6 8.5 6.9 6.5 6.7 6.5 – 8.6 -1.14 % (Upper) (Units : all are in micrograms/m3) %Change is calculated for Lower limit and Upper limit of the range. BDL : Below detectable limit <1 & S/D : Shutdown

8

Annexure - 2 Data interpretation of Monitoring results of Ambient Air Quality in Rourkela Steel Plant (Oct.,2017 - March., 2018)

LOCA- PM 2.44. Arse- Ben- PAH Min. / Max PM 10 SO 2 NOx CO Pb NH 3 Nickel Noise VOC TION 45 nic zene BaP

April. – 1009 - 0.02 - 8.3 - 70.1 – 30 - 44 37-81 23 - 39 23 - 43 BDL BDL BDL BDL EED Sept.,2017 1152 0.06 11.5 70.4 1 Building Oct .,2017 – 1060 - 0.04 – 11.4 – 71.4 – 32 - 46 49 - 63 24 - 39 28 - 36 BDL BDL BDL BDL March.,2018 1120 0.08 13.4 71.8 % Lower limit +6.66% +32.4% +4.34% +21.7% +5.05% +100% +37.3% +1.85% - - - - - Change Upper Limit +4.54% -22.2% 0% -16.2% -2.77% +33.3% +16.5% +1.98%

April. – 1028 - 0.02 - 8.5 – 71.2 – 33 - 44 36 - 82 26 - 41 28 - 45 BDL BDL BDL BDL Sept.,2017 1252 0.06 12.6 72.0 RDCIS 1 Building Oct .,2017 – 1060 - 0.05 – 11.6 – 71.4 – 30 - 42 51 - 62 27 - 39 27 - 36 BDL BDL BDL BDL March.,2018 1090 0.08 13.2 71.8

Lower limit -9.09% +41.6% +3.84% -3.57% +3.11% +150% +36.4% +0.28% % Change - - - - - Upper Limit -4.54% -24.3% -4.87% -20% -12.9% +33.3% +4.76% -0.27% April. – 1035 - 0.04 – 9.2 – 71.5 – 35 - 47 35 - 86 31 - 48 35 - 49 BDL BDL BDL BDL Sept.,2017 1378 0.07 13.4 71.7 PMPH 1 Building Oct .,2017 – 1080 - 0.05 – 11.2 – 71.4 – 32 - 48 51 - 68 29 - 39 27 - 36 BDL BDL BDL BDL March.,2018 1120 0.08 13.6 71.8

Lower limit -8.57% +45.7% -6.45% -22.8% +4.34% +25% +21.7% -0.13% % Change - - - - - Upper Limit +2.12% -20.9% -18.7% -26.5% -18.7% +14.2% +1.4% +0.13% April. – 1359 - 0.04 – 11.5 – 72.1 – 44 - 58 50 - 88 35 - 73 46 - 73 BDL BDL BDL BDL BOD Sept.,2017 1834 0.16 16.6 72.6 1 Building Oct .,2017 – 1060 - 0.05 – 12.2 – 71.2 – 38 - 48 51 - 64 31 - 39 28 - 36 BDL BDL BDL BDL March.,2018 1120 0.08 14.2 71.7 Lower limit -13.6% +2% --11.4% -39.1% -22.0% +25% +6.08% -1.24% % Change - - - - - Upper Limit -17.2% -27.2% -46.5% -50.6% -38.9% -50% -14.4% -1.23% April. – 1424 - 0.05 – 11.2 – 72.3 – TOP#2 45 - 58 53 - 88 46 - 76 48 - 78 BDL BDL BDL BDL Sept.,2017 1875 0.15 17.5 72.8 Admn. NT Oct .,2017 – 1070 - 0.05 – 12.1 – 71.6 – Building 40 - 54 52 - 76 32 - 41 29 - 37 BDL BDL BDL BDL March.,2018 1120 0.09 13.8 71.8

Lower limit -11.1% -1.88% -30.4% -39.5% -24.8% 0% +8.03% -0.96% % Change - - - - - Upper Limit -6.89% -13.6% -46.0% -52.5% -40.2% -40% -21.1% -1.37%

April. – 1229 - 0.05 – 10.5 – 72.0 – OBBP 43 - 52 48 - 85 42 - 69 43 - 68 BDL BDL BDL BDL Sept.,2017 1594 0.15 15.8 72.3 1 Admn. Oct .,2017 – 1050 - 0.05 – 11.4 – 71.4 – Building 39 - 52 49 - 64 29 - 39 28 - 34 BDL BDL BDL BDL March.,2018 1120 0.07 12.8 71.8 Lower limit -9.30% +2.08% -30.9% -34.8% -14.5% 0% +8.57% -0.83% % Change - - - - - Upper Limit 0% -24% -43.4% -50% -29.7% -53.3% -18.9% -0.69%

60 100 80 80 4000 1.0 400 6 1.0 20 ng/m3 75 dB(A) 5 µµµg/m3 - Norm µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 ng/m3 ng/m3

Units : All are in micro grams/m 3 except BaP which is in ng/m 3 Note: %Change is calculated for Lower limit and Upper limit of the range. PAH (Bap) is done once in a year. BDL : Below detectable limit <1 & S/D : Shutdown

9 Monitoring Results of AAQM Stations in RSP & Townships

(Oct.,2017 - March., 2018)

Apr.- Oct 17.,- Oct., Nov., Dec., Jan., Feb., March., Change w.r.t. AAQMS Location Sept., March., 2017 2017 2017 2018 2018 2018 Apr.-Sept., 2017 2017 2018

3 Parameter : PM 2.5 (Norm : 60 µg/m )

Sector#2, Rourkela +14.28% (Lower) 21 - 48 24 28 36 35 37 36 24 - 37 Steel Town (North) -22.91% (Upper) Rourkela Fertilizer -66.47% (Lower) 23 - 34 7.71 25 33 32 33 41 7.71 - 41 Township (South) +20.58% (Upper) -26.31% (Lower) ERWPP Area (West) 19 - 46 16.48 14 38 39 42 44 14 - 44 -4.34% (Upper) -62.89% (Lower) SSSY Area (East) 28 - 48 10.39 23 35 36 44 46 10.39 - 46 -4.16% (Upper) 3 Parameter : PM 10 (Norm : 100 µg/m )

Sector#2, Rourkela +10.86% (Lower) 46 - 74 51 55 60 58 60 58 51 - 60 Steel Town (North) -18.91% (Upper) Rourkela Fertilizer -32.05% (Lower) 39 - 68 26.5 56 56 54 58 54 26.5 - 58 Township (South) -14.70% (Upper) +1.60% (Lower) ERWPP Area (West) 56 - 76 56.9 79 71 74 62 66 56.9 - 79 +3.94% (Upper) -24.25% (Lower) SSSY Area (East) 54 - 78 40.9 53 69 70 68 69 40.9 - 70 -10.25% (Upper)

3 Parameter : SO 2 (Norm : 80 µg/m )

Sector#2, Rourkela -67.27% (Lower) 22 - 32 23 7.2 31 30 34 32 7.2 - 34 Steel Town (North) +6.25% (Upper) Rourkela Fertilizer +10.52% (Lower) 19 - 32 39.7 21 28 29 30 31 21 – 39.7 Township (South) +24.06% (Upper) -65.48% (Lower) ERWPP Area (West) 31 - 62 10.7 16 34 34 32 34 10.7 - 34 -45.16% (Upper) -55.23% (Lower) SSSY Area (East) 21 - 45 9.4 11 34 35 35 32 9.4 - 35 -22.22% (Upper)

Parameter : NOx (Norm : 80 µg/m 3)

Sector#2, Rourkela -60.76% (Lower) 26 - 35 22 10.2 34 29 32 30 10.2 - 32 Steel Town (North) -8.57% (Upper) Rourkela Fertilizer -58.33% (Lower) 24 - 34 14 10 33 32 28 29 10 - 33 Township (South) -2.94% (Upper) -63.23% (Lower) ERWPP Area (West) 34 - 52 12.5 26 39 36 30 32 12.5 - 39 -25% (Upper) -45.83% (Lower) SSSY Area (East) 24 - 53 61.8 13 31 34 34 30 13 – 61.8 +16.60% (Upper)

Parameter : Carbon Monoxide (Norm : 4000 µg/m 3)

Sector#2, Rourkela +1.30% (Lower) 538 - 578 548 603 545 680 760 740 545 - 603 Steel Town (North) +4.32% (Upper) Rourkela Fertilizer -23.84% (Lower) 499 - 568 557 380 538 660 748 738 380 - 748 Township (South) +31.69% (Upper) +1.77% (Lower) ERWPP Area (West) 564 - 629 618 966 574 710 782 920 574 - 920 +46.26% (Upper) -2.40% (Lower) SSSY Area (East) 582 - 718 657 638 568 678 724 782 568 - 782 +8.91% (Upper)

10 Annexure - 3 Monitoring of Stack Emissions (SPM in mg/NM3) (Oct.,2017 - March., 2018) Apr.- Oct 17,- Change w.r.t. Depart- Stack Oct., Nov., Dec., Jan., Feb., March. SN. NORM Sept., March., Apr.-Sept., ment connected to 2017 2017 2017 2018 2018 , 2018 2017 2018 2017 +13.6% (Lower) 1. Battery#1 22 - 48 33 44 40 25 33 48 25 - 48 +0% (Upper) 2. Battery#2 S/D S/D S/D S/D S/D S/D S/D S/D - -71.4% (Lower) 3. Battery#3 35 - 37 10 17 37 22 24 34 10 - 37 Coke 0% (Upper) 50 +20.6% (Lower) 4. Ovens Battery#4 29 - 46 38 43 44 42 37 35 35 - 44 -4.34% (Upper) -45.9% (Lower) 5. Battery#5 37 - 47 48 48 20 43 38 45 20 - 48 +2.12% (Upper) -60% (Lower) 6. Battery#6 15 - 41 16 06 10 14 18 15 06 - 18 -56.0% (Upper) +45.4% (Lower) 6. Process ESP 22 - 39 41 32 34 52 38 37 32 - 52 +33.3% (Upper) Sintering -8.77% (Lower) 7. Addl. ESP 150 57 - 98 57 69 64 76 62 52 52 - 76 Plant#1 -22.4% (Upper) +13.5% (Lower) 8. Old ESP 37 - 85 64 52 48 42 38 34 42 - 64 -24.7% (Upper) -25% (Lower) 9. Process ESP 20 - 56 23 16 17 16 31 15 15 - 23 Sintering -58.9% (Upper) 150 Plant#2 Space De -65.3% (Lower) 10. 26 - 92 41 53 9 23 72 86 9 - 86 dusting ESP -6.52% (Upper) Process ESP - -46.1% (Lower) 11. 13 - 59 20 10 11 38 13 7 7 - 38 1 -35.5% (Upper) Sintering Process ESP - -60% (Lower) 12. 150 15 - 29 17 06 13 35 15 7 6 - 35 Plant#3 2 +20.6% (Upper) Plant De +165% (Lower) 13. 29 - 96 119 102 77 93 85 104 77- 119 dusting ESP +23.9% (Upper) 0% (Lower) 14. TA Line 150 16 - 28 22 18 S/D S/D 17 16 16 - 22 -21.4% (Upper) +223% (Lower) 15. Decarb Line 150 17 - 78 71 62 79 89 55 69 55 - 89 Silicon +14.1% (Upper) Steel -3.57% (Lower) 16. Mill Pickling line 50 28 - 37 37 33 27 49 34 27 27 - 49 +32.4% (Upper) Ammonia -7.14% (Lower) 17 150 14 - 28 20 18 13 46 21 14 13 - 46 cracking unit +64.2% (Upper -30% (Lower) 18. MP Boiler#1 10 - 12 30 22 19 29 7 21 7 - 30 +150% (Upper) +75% (Lower) 19. MP Boiler#2 08 - 59 24 20 22 21 14 20 14 - 24 100 -59.3% (Upper) +40% (Lower) 20. MP Boiler#3 05 - 78 9 7 13 8 S/D S/D 07 - 13 -83.3% (Upper) Captive -25% (Lower) 21. Power HP Boiler#1 8 8 S/D S/D S/D S/D 6 6 - 8 Plant#1 0% (Upper -93.6% (Lower) 22. HP Boiler#2 95 - 98 S/D S/D 6 6 7 23 6 - 23 -76.5% (Upper) 100 -82% (Lower) 23. HP Boiler#5 50- 88 8 9 79 41 56 85 9 - 79 -10.2 % (Upper) -46.1% (Lower) 24. HP Boiler#6 26 - 97 86 34 49 54 91 14 14 - 91 -6.18% (Upper) Note: %Change is calculated for Lower limit and Upper limit of the range.

11 Annexure - 4

Solid Waste Utilization in Rourkela Steel Plant (Oct.,2017 - March., 2018) ( Unit : % ) Change Apr.- Oct 17,- Name of the Oct., Nov., Dec., Jan., Feb., March., w.r.t. SN. Sept., March., Solid Waste 2017 2017 2017 2018 2018 2018 Apr.-Sept., 2017 2018 2017 +18.53% Blast furnace 84.36 – 1. 100 100 100 100 100 100 100 – 100 (Lower) slag 100 0% (Upper) +0.46% 15.03 – 15.10 – (Lower) 2. SMS slag 19.16 14.75 16.25 15.10 17.24 32.24 35.84 32.24 -10.04% (Upper)

3. Lime dust 100 100 100 100 100 100 100 100 No change

0% (Lower) Blast Furnace Nil - 4. 3.43 Nil 15.62 Nil 47.92 48.73 Nil - 48.73 +43.23% flue dust 34.00 (Upper) Blast furnace 5. 100 100 100 100 100 100 100 100 No change sludge -67.35% 9.16 – 2.99 – (Lower) 6. SMS Sludge 26.92 2.99 31.62 91.23 11.86 63.29 48.92 91.23 +86.48% (Upper) Broken 7. Refractory/Fire 100 100 100 100 100 100 100 100 No change clay bricks

8. Mill scale 100 100 100 100 100 100 100 100 No change

-8.89% Total Solid 71.19 – 64.86 – (Lower) 64.86 70.54 69.47 73.24 74.12 83.08 Waste 76.89 83.07 +8.03% (Upper)

Note: %Change is calculated for Lower limit and Upper limit of the range.

12 Annexure - 5

PAH & BaP monitoring Sampling was done during Analysis was done at Environment Laboratory, RDCIS, SAIL, Ranchi (Sampling and Analysis are done during 17/02/2018 – 19/03/2018)

STACK COKE OVEN WORKZONE AMBIENT AIR QUALITY EMISSIONS PARA- BATT#3 TOP#2 OBBP SN. BATT#3 BATT#3 BATT#3 EED RDCIS PMPH BOD Coke Coke METER Near Admn. Admn. Oven Ram Wharf Build- Build- Build Build- Oven Oven Quenching Build- Build- Top Side Side ing ing -ing ing Batt.#3 Batt.#4 Tower ing ing 1. PHN NT 13 79 157 8 6 4 NT 12 13 425 468

2. ANT 26 12 2 2 NT NT NT NT NT NT 163 42

3. FLT 66 23 1 4 NT 1 NT NT NT NT 237 185

4. PYR 600 860 101 71 8 27 15 NT 11 22 2220 NT

5. BAA 595 1146 48 22 4 5 7 3 5 NT 3994 1491

6. CHR 271 272 88 73 3 8 10 NT NT NT 3201 1718

7. BBF 345 117 49 60 3 6 NT NT NT NT 396 1287

8. BKF 153 67 27 57 4 7 1 1 27 NT 2959 2888 BaP 9. 540 297 63 26 1 1 1 1 1 1 2153 1987 (ng/m3) 10. DBA 68 66 56 186 4 8 1 NT NT 2 2305 596

11. BGP 66 258 135 47 5 NT NT NT NT NT 3846 NT

12. IPY 30 93 44 22 2 NT NT NT NT NT 1545 3408

Norms 5000 2000 2000 2000 1 1 1 1 1 1 - - (ng/m3)

(Units : All are in nano grams /m3 except SPM which is in micro grams/m3) BDL : Below detectable limit.

Note : For uniformity all the figs. are given in nano grams/m3

13 Annexure - 6

Quality of final treated effluent going to river Brahmani from RSP (Oct.,2017 - March.,2018) Apr.- Oct 17,- Oct., Nov., Dec., Jan., Feb., March. Change w.r.t. SN. PARAMETER NORM Sept., March., 2017 2017 2017 2018 2018 , 2018 Apr.-Sept., 2017 2017 2018 7.37 – 7.2 – -2.30% (Lower) 1. pH 6 – 8.5 7.2 7.6 7.9 8.07 7.57 7.7 7.9 8.07 +2.15% (Upper) Total Suspended 22.25 – -3.26% (Lower) 2. 100 23 – 38 26.2 28 26 22.25 34.7 43.3 Solids (TSS) 43.3 +13.9% (Upper) 31 – 0% (Lower) 3. Chloride as (Cl) 1000 31 – 35.5 32.5 31 31 32 32.7 32 32.7 -7.88% (Upper) 51.3 - -10% (Lower) 4. Sulphate as SO 1000 57 - 76.5 62.7 64.7 61 58 60 51.3 4 64.7 -15.42% (Upper) 0.60 – 0.40 – -33.33% (Lower) 5. Free Ammonia 5.0 0.40 1.62 1.47 0.72 1.45 0.78 0.81 1.62 +100% (Upper) 11.07 – 11.2 – +1.17% (Lower) 6. Ammonia as NH -N 50 13.97 12.5 11.2 11.75 14.17 13.8 3 13.8 14.17 +2.68% (Upper) 0.13 – 0.12 – -7.69% (Lower) 7. Phenol 1.0 0.157 0.12 0.17 0.15 0.14 0.14 0.17 0.17 0% (Upper) 0.08– 0.07– -12.5% (Lower) 8. Cyanide 0.2 0.09 0.08 0.10 0.07 0.102 0.07 0.105 0.102 -2.85% (Upper) Bioch. Oxygen +25 % (Lower) 9. 30 8 -9 11 14 13 10 18 14 10 - 18 Demand (BOD 3) +100% (Upper) Chemical Oxygen -9.67% (Lower) 10. 250 31 – 38 32 43 48 28 49 48 28 - 49 Demand (COD) +28.94% (Upper) 0.0123– 0.0120– -2.43% (Lower) 11. Copper 3.0 0.0125 0.0124 0.0121 0.0123 0.0121 0.0120 0.0128 0.0125 -2.34% (Upper) 0.1286 – 0.128 0.127 0.126 0.126 0.1260 – -2.02% (Lower) 12. Zinc 5.0 0.1262 0.1260 0.1382 1 6 5 1 0.1281 -7.30% (Upper) 3.25 – -1.51% (Lower) 13. Oil & Grease 10.0 3.3 – 4 3.25 5.75 5 3.5 4.75 4.5 5.75 +43.75% (Upper) 14. Boron 2.0 NT NT NT NT NT NT NT NT NT Total Residual 15. 1.0 NT NT NT NT NT NT NT NT NT Chlorine 16. Arsenic 0.2 NT NT NT NT NT NT NT NT NT 17. Cadmium 2.0 NT NT NT NT NT NT NT NT NT 18. Chromium Cr +6 0.10 NT NT NT NT NT NT NT NT NT 0.0021 – 0.0011 – -47.61% (Lower) 19. Total Chromium 2.0 0.0014 0.0013 0.0012 0.0013 0.0011 0.0012 0.0028 0.0014 -50% (Upper) 0.0122 – 0.0121 – -0.81% (Lower) 20 Lead 0.1 0.0124 0.0121 0.0123 0.0121 0.0122 0.0124 0.0127 0.0124 -2.36% (Upper) 21. Selenium 0.03 NT NT NT NT NT NT NT NT NT 0.0011 – 0.0011 – 0% (Lower) 22. Mercury 0.01 0.0012 0.0013 0.0011 0.0012 0.0014 0.0012 0.0018 0.0014 -22.22% (Upper) Dissolved 0.04 – 0.05 – +25% (Lower) 23. 5.0 0.05 0.05 0.05 0.05 0.05 0.05 Phosphates 0.05 0.05 0% (Upper) Total Kjeladal 9.6 – 14.3 – +48.95% (Lower) 24. 100 16.6 14.3 15.1 15.3 15.2 15.6 Nitrogen 11.6 16.6 +43.10% (Upper) 0.01511 0.01481– +2.02% (Lower) 25. Nickel 3.0 0.01551 0.01513 0.01512 0.01511 0.01513 0.01521 – 0.01551 0% (Upper) 0.01551 2.37 – 2.25 – -5.06% (Lower) 26. Iron 3.0 2.57 2.9 2.9 2.25 2.7 2.63 2.93 2.9 -1.02% (Upper) 2.95 – 3.32 – +12.54% (Lower) 27. Nitrates 10.0 3.55 3.62 3.5 3.32 3.55 3.63 3.7 3.63 -1.89% (Upper) % Change is calculated based on Lower & Upper limits of range -- All units are in mg/lit except pH

14 Annexure – 7

Ground Water Quality at Waste Disposal Sites (Oct.,2017 - March., 2018 )

1) Location of Sampling : Sitalpara Dump yard

Apr.- Oct 17,- PARA- Oct., Nov., Dec., Jan., Feb., March Change w.r.t. SN. NORM Sept., March., METER 2017 2017 2017 2018 2018 ., 2018 Apr.-Sept., 2017 2017 2018 +1.63% (Lower) 1. pH 6 – 8.5 6.1 – 6.3 6.3 6.2 6.4 6.3 6.2 6.3 6.2 – 6.3 0% (Upper) Turbidity 0% (Lower) 2. 5 5.0 – 6.0 5.0 5.0 6.0 5.0 5.0 5.0 5.0 – 6.0 (NTU) 0% (Upper) Total +9.16% (Lower) 3. Hardness 300 120 - 144 136 134 132 134 131 132 131 - 136 -5.55% (Upper) as CaCO 3 0.28 – 0.26 – -7.14% (Lower) 4. Iron 0.3 0.27 0.29 0.29 0.28 0.27 0.26 0.42 0.29 -30.95% (Upper) +19.23% (Lower) 5. Chlorides 250 26 – 38 31 36 34 32 31 31 31 - 36 -5.26% (Upper) Dissolved +8.02% (Lower) 6. 500 162 - 197 192 201 196 176 175 178 175 - 201 solids +2.03% (Upper) -6.25% (Lower) 7. Sulphate 200 32- 38 32 34 30 36 35 34 30- 36 -5.26% (Upper) +5% (Lower) 8. Nitrate 45 2.0 – 2.5 2.6 2.4 2.1 2.3 2.2 2.1 2.1 – 2.6 +4%(Upper) 0.30 – 0.30 – 0% (Lower) 9. Fluoride 1.0 0.33 0.30 0.35 0.34 0.32 0.31 0.35 0.35 0% (Upper) (All units are in mg/lit except pH & Turbidity) 2) Location of Sampling : Blast Furnace Dump yard

Apr.- Oct 17,- PARAME Oct., Nov., Dec., Jan., Feb., March Change w.r.t. SN. NORM Sept., March., 2017 2017 2017 2018 2018 ., 2018 Apr.-Sept., 2017 TER 2017 2018 0% (Min) 1. pH 6 – 8.5 6.1 – 6.5 6.2 6.1 6.3 6.2 6.1 6.2 6.1 – 6.3 -3.07% (Max) Turbidity +32.25% (Min) 2. 5 3.1- 4.0 4.1 4.4 4.9 4.8 4.6 4.7 4.1- 4.9 (NTU) +2.25% (Max) Total +20.54% (Min) 3. Hardness 300 116 - 130 146 236 234 232 227 224 146 - 236 +81.53% (Max) as CaCO 3 0.24 – 0.26 – +8.33% (Min) 4. Iron 0.3 0.28 0.28 0.28 0.29 0.27 0.26 0.27 0.29 +7.40% (Max) +61.1% (Min) 5. Chlorides 250 36 – 46 60 62 61 60 59 58 58 – 61 +32.60% (Max) Dissolved +29.6% (Min) 6. 500 182 - 190 236 386 388 364 362 359 236 - 388 solids +104.21% (Max) +50% (Min) 7. Sulphate 200 40 - 72 62 68 71 64 61 60 60 - 71 -1.38% (Max) +84.61% (Min) 8. Nitrate 45 1.3 – 1.6 2.4 5.0 4.6 4.2 4.1 4.0 2.4 – 5.0 +212.5% (Max) 0.26– 0.41– +57.69% (Min) 9. Fluoride 1.0 0.45 0.44 0.46 0.44 0.42 0.41 0.29 0.46 +58.62% (Max) (All units are in mg/lit except pH & Turbidity) % Change is calculated based on Lower & Upper limits of range

15

Annexure-8

16

Annexure - 9

Fugitive emission (SPM) levels monitored inside RSP (Shop Floor) (Oct.,2017 - March., 2018)

Change Apr.- Oct 17,- Location of Oct., Nov., Dec., Jan., Feb., March., w.r.t. SN. Department Sept., March., monitoring 2017 2017 2017 2018 2018 2018 Apr.-Sept., 2017 2018 2017 +27.73% Blast Furnaces 1168 - 1492 – (Lower) 1. Cast House 1492 1512 1526 1564 1573 1584 (PM10) 1492 1584 +6.16% (Upper) -19.40% Steel Melting In front of 1938 - 1562 – (Lower) 2. 1562 2476 1584 2549 2694 2948 Shop#1(PM10) BOF 2030 2948 +45.22% (Upper) -31.66% Steel Melting In front of 2154 – 1472 – (Lower) 3. Shop#2 1486 2732 1472 2720 3200 2766 BOF 2202 3200 -45.32% (PM10) (Upper) Unit : Norm 4000 4000 4000 4000 4000 4000 4000 4000 µg/m3 (Units : µg/m3)

% Change is calculated based on Lower & Upper limits of range

17

Annexure-10

Rourkela Steel Plant Status of the Implementation Schedule

SN. CONDITION IMPLEMENTATION SCHEDULE RSP has 6 no. of coke oven batteries. Battery No. 1, 3, 4 & 5 have been rebuilt & commissioned in the years 2007, 2016, 2010 & 2000 respectively. Battery No. 6 is a new Green field Battery which was commissioned on 01/04/2014, under this Expansion 1. Rebuilding of Coke Oven Batteries Project.

Coke Oven Battery No. 2 was put down since March, 2016 as it has outlived its life and due for rebuilding. Presently no repair/rebuilding activity is going on. PAH and BaP in the Coke Oven area are being monitored once in a year. VOCs in Monitoring of VOCs, PAH and BaP in 2. Coke Oven Stacks, ambient & work zone were monitored and analysis results stacks and ambient air. along with data interpretation are given at Annexure- 1 & 5. Monthly report covering Stack Reports are being sent to SPCB & CPCB since April, 2008 onwards every month, 3. Emissions, Ambient air quality and regularly. Six monthly reports are being sent to MoEFCC regularly. Waste utilization Monitoring of Ground water quality Ground water quality at waste disposal sites is being monitored and the six 4. at waste disposal sites – once in six monthly report of ground water quality along with data interpretation is given at months Annexure-7.

Blast Furnace Slag : In-house Slag granulation facilities have already been installed at Blast Furnace no. 1, 4 & 5. The granulated slag is being sent to cement plants for production of slag cement. The present BFc Slag utilization is more than 90% .

SMS Slag : State of the art technologies are adopted in steel making so that the SMS slag generation rate will be minimized. The SMS slag is being utilized for Sinter Making through base mix, charged into Blast Furnaces directly to replace lime stone and also used for pavement making and rail ballast and also used for Enhancement of waste utilization to reclaiming low lying areas inside plant premises. 5. 90%. Fly Ash : There is no additional fly ash generation after commissioning of proposed Expansion project as the additional power is being obtained from Top Recovery Turbine & Power Blowing Station of Blast Furnace No. 5 (36 MW) and remaining 110 MW power will be purchased from State Grid. As per the present agreement with NTPC, the joint venture power company NSPCL is managing the fly ash generated from captive power plant of RSP. The fly ash will be utilized for construction of new Ash Pond “D”, dyke height raising of existing Ash Ponds and fly ash will be given to local entrepreneurs for utilization. All the fly ash will be utilized as per the Fly Ash Notification, 1999, amended thereon.

Development of Green Belt to cover RSP has already developed Greenbelt in 2252 Acres of land which is covering 6. 33% of the total area in and around more than 33% of the total area. RSP has planted more than 44.50 lakh trees so the plant. far including 50000 no. of saplings planted during 2017-18 till date.

3 no. of Rainwater recharge systems have been constructed and put in operation. Development of Rain water 2 nos. in Coke Oven Batt#6, 1 no. in front of RCL. This is in addition to 3 no. of 7. harvesting systems. RWH systems developed at Ispat General Hospital, Ispat English Medium School, Sector#20 and Town Engg. Campus building of Rourkela Steel Plant.

18

Annexure-11

19 Annexure-12

20 Annexure – 13 Quality of RSP’s finally treated Sewage Apr.- Oct 17,- Oct., Nov., Dec., Jan., Feb., March. Change w.r.t. SN. PARAMETER NORM Sept., March., 2017 2017 2017 2018 2018 , 2018 Apr.-Sept., 2017 2017 2018 7.37 – 7.2 – -2.30% (Lower) 1. pH 6 – 8.5 7.2 7.6 7.9 8.07 7.57 7.7 7.9 8.07 +2.15% (Upper) Total Suspended 22.25 – -3.26% (Lower) 2. 100 23 – 38 26.2 28 26 22.25 34.7 43.3 Solids (TSS) 43.3 +13.9% (Upper) 31 – 0% (Lower) 3. Chloride as (Cl) 1000 31 – 35.5 32.5 31 31 32 32.7 32 32.7 -7.88% (Upper) 51.3 - -10% (Lower) 4. Sulphate as SO 1000 57 - 76.5 62.7 64.7 61 58 60 51.3 4 64.7 -15.42% (Upper) 0.60 – 0.40 – -33.33% (Lower) 5. Free Ammonia 5.0 0.40 1.62 1.47 0.72 1.45 0.78 0.81 1.62 +100% (Upper) 11.07 – 11.2 – +1.17% (Lower) 6. Ammonia as NH -N 50 13.97 12.5 11.2 11.75 14.17 13.8 3 13.8 14.17 +2.68% (Upper) 0.13 – 0.12 – -7.69% (Lower) 7. Phenol 1.0 0.157 0.12 0.17 0.15 0.14 0.14 0.17 0.17 0% (Upper) 0.08– 0.07– -12.5% (Lower) 8. Cyanide 0.2 0.09 0.08 0.10 0.07 0.102 0.07 0.105 0.102 -2.85% (Upper) Bioch. Oxygen +25 % (Lower) 9. 30 8 -9 11 14 13 10 18 14 10 - 18 Demand (BOD 3) +100% (Upper) Chemical Oxygen -9.67% (Lower) 10. 250 31 – 38 32 43 48 28 49 48 28 - 49 Demand (COD) +28.94% (Upper) 0.0123– 0.0120– -2.43% (Lower) 11. Copper 3.0 0.0125 0.0124 0.0121 0.0123 0.0121 0.0120 0.0128 0.0125 -2.34% (Upper) 0.1286 – 0.128 0.127 0.126 0.126 0.1260 – -2.02% (Lower) 12. Zinc 5.0 0.1262 0.1260 0.1382 1 6 5 1 0.1281 -7.30% (Upper) 3.25 – -1.51% (Lower) 13. Oil & Grease 10.0 3.3 – 4 3.25 5.75 5 3.5 4.75 4.5 5.75 +43.75% (Upper) 14. Boron 2.0 NT NT NT NT NT NT NT NT NT Total Residual 15. 1.0 NT NT NT NT NT NT NT NT NT Chlorine 16. Arsenic 0.2 NT NT NT NT NT NT NT NT NT 17. Cadmium 2.0 NT NT NT NT NT NT NT NT NT 18. Chromium Cr +6 0.10 NT NT NT NT NT NT NT NT NT 0.0021 – 0.0011 – -47.61% (Lower) 19. Total Chromium 2.0 0.0014 0.0013 0.0012 0.0013 0.0011 0.0012 0.0028 0.0014 -50% (Upper) 0.0122 – 0.0121 – -0.81% (Lower) 20 Lead 0.1 0.0124 0.0121 0.0123 0.0121 0.0122 0.0124 0.0127 0.0124 -2.36% (Upper) 21. Selenium 0.03 NT NT NT NT NT NT NT NT NT 0.0011 – 0.0011 – 0% (Lower) 22. Mercury 0.01 0.0012 0.0013 0.0011 0.0012 0.0014 0.0012 0.0018 0.0014 -22.22% (Upper) Dissolved 0.04 – 0.05 – +25% (Lower) 23. 5.0 0.05 0.05 0.05 0.05 0.05 0.05 Phosphates 0.05 0.05 0% (Upper) Total Kjeladal 9.6 – 14.3 – +48.95% (Lower) 24. 100 16.6 14.3 15.1 15.3 15.2 15.6 Nitrogen 11.6 16.6 +43.10% (Upper) 0.01511 0.01481– +2.02% (Lower) 25. Nickel 3.0 0.01551 0.01513 0.01512 0.01511 0.01513 0.01521 – 0.01551 0% (Upper) 0.01551 2.37 – 2.25 – -5.06% (Lower) 26. Iron 3.0 2.57 2.9 2.9 2.25 2.7 2.63 2.93 2.9 -1.02% (Upper) 2.95 – 3.32 – +12.54% (Lower) 27. Nitrates 10.0 3.55 3.62 3.5 3.32 3.55 3.63 3.7 3.63 -1.89% (Upper) % Change is calculated based on Lower & Upper limits of range -- All units are in mg/lit except pH

21

Annexure-14

Rourkela Steel Plant RSP’s CSR Initiatives during 2017-18

Bringing cheers to the most marginalized local stake holders in and around Steel Plant is the main objective of RSP which is being fulfilled through CSR activities. RSP established a separate department called “CSR” for carrying out various activities under Corporate Social Responsibility. The main focus of CSR activities are on, A) Education B) Infrastructure C) Health D) Support for disabled/under privileged E) Income generation & livelihood F) Water supply and sanitation G) Sports and culture H) Women empowerment

The different developmental activities taken up under different heads are,

1. EDUCATION:

• The Akshaya Patra Project, Rourkela, a CSR endeavour of RSP regarding hygienic and nutritious mid -day meals for students, continued to supply hygienic mid -day meals to schools in Rourkela Municipality, Bisra Block & Lathikata Block. • 11 no. of tribal students from peripheral areas of RSP have been sponsored for free education at Kalinga Institute of Social Sciences (KISS), Bhubaneswar. • “Deepika Ispat Sikshya Sadan”, a special school functioning for underprivileged children of Rourkela and neighbouring area (Class-1 to 10) with free e ducation, uniform, educational kits, books & mid -day refreshments. • Financial assistance provided to 15 no of class X passed out students of “Deepika Ispat Sikshya Sadan pursuing ITI course & +2 course.

2. INFRASTRUCTURE

• Sinking/repair of tube wells in slums areas of Rourkela. • Public Toilet at Bargaon, Sundargarh, is completed. • Construction of Entrance Gate and area development at Rourkela Railway Station. • Construction of open market platform & development work at vegetable market & co nstruction of toilet block at Loknath market, Sector -22.

22

• Construction of ramp for Missionaries of Charity at Nirmal Bhawan Hansen’s Care Centre. • Construction of Community Centre at Laing (Mahuldihi) • Solar lighting system and pumping system at Telijore Health Centre is completed. • Repair and renovation works in Model Steel Villages are in progress.

3. HEALTH • Free bi-weekly medical aid centres operated in 34 peripheral locations (i.e. 68 camps a week). • Free health centres operated at Ispat Sanjeevani, Sector -6; Chikatmati Village & Jalda RS colony six days a week.

• The following specialized projects, for providing free treatment/surgical procedures for targeted persons, are continuing at IGH. • Project Sunayana for treatment of vision impaired. • Project Sushruti for treatment of hearing impaired. • Project Sneha for Leprosy patients. • Project Akshay for tuberculosis. • Project Surabhi for women with gynaecological disorders. • Project Swabalam ban for persons with cleft lip, clubbed feet, hair lip, congenital cataract disorders. • Project Charaka for general surgical services.

• Single day multidisciplinary medical camps were organized at 4 locations, i.e. Proj. UP School, Assurchhapar, in Lath ikata Block, Janata High School, Ratakhandi, in Kuarmunda Block and Govt. High School, Loaram, in Nuagaon Block, Kokerama UP school in Bisra block. Medical Specialist coverage was given in disciplines such as Paediatrics, Medicines, Surgery, Ophthalmology , Dermatology, ENT, Gynecology, etc. 1594 patients were treated in these camps.

• Health promotional activities are continuing in slum areas of township periodically through Deepika Mahila Sanghati. • Reproductive & Child Health (RCH) and Family Welfare (FW) activities at IGH are being conducted. • The Ispat Drustidaan Eye Bank is functional at Ispat General Hospital.

23

4. SUPPORT FOR THE DISABLED/ UNDERPRIVILGED:

• Free monthly camps were conducted for Community Based Rehabilitation of physically/ mentally challenged persons at Bondamunda, Jalda, Kuarmunda and Kalunga.

• Mid Day Meals provided through Akshay Patra Foundation (fully sponsored by RSP) continued to Radhakrishna Drustihin Vidyalaya, Lathikata; Home & Hope, Asha, Rourkela, in addition to the Deepika Ispat Sikhya Sadan.

5. INCOME GENERATION & LIVELIHOOD: • Under employability skills enhancement programs in health sector, the training programs conducted at IGH included the followings: • Medical Attendant Training • Advanced Specialised Nursing Training • Advanced Specialised Physiotherapy Training • Audiology & speech therapy Training • Anaesthesia/OT assistant Training • Data entry operator/Medical transcr iption training • Hospital administration training

6. WATER SUPPLY & SANITATION :

• Comprehensive Water & Sanitation Project: 5 Model Steel Villages of RSP have been identified for taking up Water & Sanitation Facility. Works completed in Chikatmati A & B, Laing Colony, Kapatmunda and Bankibahal villages.

• Under Mission project in 9 villages in Kuarmunda Block are covered under the project. Water supply work is in progress in 5 villages named Bhagatolla, Madatolla, Belpada, Sarandamal & Bhaludumer .

24

7. SPORTS & CULTURE:

SAMVARDHAN (Rural Sports): • 2016-17 Final round Samvardhan Rural Football Tournament was conducted at Ispat Stadium in December 2017. • Zonal level Samvardhan Rural Football Tournaments for 2017 -18 were conducted in four peripheral Blocks i.e. at Dalposh (Bisra Block), Lindra (Nuagaon Block), Kanarsuan (Lathikata Block) and Bankibahal (Kuarmunda Block).

CULTURE : • Zonal level Cultural programs through Synergy:The Lok Sanskrutik Mahostav was conducted at Jagdishpur in Kuarmunda Block, Karkatta in Nuagaon Block, Jabaghat in Bisra Block and Asurchhapal in Lathikata Block. • The Final round of Synergy:The Lok Sanskruti k Mahostav was conducted at Bhanja Cultural Trust, Sector -5, Rourkela on 24/3/2018.

8. WOMEN EMPOWERMENT :

• Handloom Centre: Handloom training is continuing at the Handloom Centre, Sector -2. The girls from peripheral areas are being trained in identifying yarn, separation of hank, finding & joining loose ends, usage of Chatta & Asari, Bobbin & Charkha, Bobbin machine, Warping Machine, starching, reed joining, sizing, dyeing, weft lining, reed fitting in looms, weaving, badhi preparation, tie & dye, weaving. The trainees are now able to weave handkerchieves, bed sheets, and different types of fabrics including sarees.

• Project Kishori (Science & Technology Empowerment of village women): The project is continuing in 10 peripheral villages. 9 tra ining programs in different modules such as leadership, group management, training methodology & evaluation artificial jewelry, bamboo crafts, mushroom cultivation, handicrafts, paper crafts health and hygiene, women’s rights, land and water management, Co mmon Facility Centre Orientation etc. were conducted for the beneficiaries.

The products of WRCs and Handloom Centre were put up for exhibition -cum-sale by the SHGs in Pallishree Mela-2017-18, Cuttack, Rourkela, Keonjhar and Delhi.

• A White Phenyl Pro duction Center has been established at Deepika Mahila Jagruti Sansthan, Sec -2 and is in operation. • A low cost Sanitary Napkins Production Center has been established at Deepika Mahila Jagruti Sansthan, Sec - 2 and is in operation.

25

• MISCELLANEOUS : • Awareness program conducted on Health & Hygiene specific to menstrual hygiene & use of sanitary napkins for Class IX –X girl students of Govt. High Schools in Kuarmunda Block.

• Swachhta Hi Seva campaign organized in 4 peripheral villages .

26 Annexure-15

Special Noise Monitoring at Ambient Air Stations at Ground Level (Oct.,2017 - March., 2018)

Noise Noise LOCA-TION Min. / Max Day time Night time

Oct. – Mar.,2017 70.1 – 70.4 66.5 – 66.9 EED Building

April. – Sept.,2017 71.4 – 71.8 66.4 – 68.4

Lower limit +1.85% -0.15% % Change Upper Limit +1.98% +2.24%

Oct. – Mar.,2017 71.2 – 72.0 66.8 – 67.6 RDCIS Building April. – Sept.,2017 71.4 – 71.8 66.2 – 67.2

Lower limit +0.28% -0.89% % Change Upper Limit -0.27% -0.59%

Oct. – Mar.,2017 71.5 – 71.7 66.9 – 67.8 PMPH Building April. – Sept.,2017 71.4 – 71.8 63.6 – 68.2

Lower limit -0.13% -4.93% % Change Upper Limit +0.13% +0.58%

Oct. – Mar.,2017 72.1 – 72.6 68.0 – 68.8 BOD Building April. – Sept.,2017 71.2 – 71.7 66.2 – 67.2

Lower limit -1.24% -2.64% % Change Upper Limit -1.23% -2.32%

TOP#2 Admn. Oct. – Mar.,2017 72.3 – 72.8 68.2 – 68.9 Building April. – Sept.,2017 71.6 – 71.8 64.6 – 68.2

Lower limit -0.96% -5.27% % Change Upper Limit -1.37% -1.01%

OBBP Admn. Oct. – Mar.,2017 72.0 – 72.3 67.2 – 67.8 Building April. – Sept.,2017 71.4 – 71.8 65.2 – 66.5

Lower limit -0.83% -2.97% % Change Upper Limit -0.69% -1.91%

Norm 75 dB(A) 70 dB(A)

27 Annexure-16

Work zone dust special monitoring

(Oct.,2017 - March., 2018)

PM10 Dust Date of Noise SN. Department Location of monitoring concentration in Monitoring dB(A) mg/m3 1. Ram car side 13.11.2017 1.812 78.6

2. Guide car side 13.11.2017 0.781 76.1 In front of Control room on 3. Coke Oven 13.11.2017 1.952 77.3 Battery#6 road 4. CDCP area 15.11.2017 0.936 81.6

5. COB#6 oven top 15.11.2017 0.691 77.4

6. Ram car side 22.01.2018 2.431 82.6

7. Coke Oven Guide car side 22.01.2018 2.956 75.3 Battery#4 8. Quenching tower area 22.01.2018 2.973 81.3 9. Oven top 22.01.2018 3.961 80.4 Cast House during tapping 10. 14.02.2018 2.246 77.6 -- SMS#2 side Blast Cast House during tapping 11. 14.02.2018 2.581 75.7 Furnace#5 – SP#2 side 12 Entrance to Cast House 14.02.2018 1.191 75.4 Sintering 13 Sinter machine floor 29.01.2018 2.942 71.2 Plant#3

28

Annexure-17

Expenditure on various Pollution Control Systems installed in different plant units

Expenditure in Rs. SN. Department Pollution Control Equipment installed Lakhs

Land Based Pushing Emission Control 1. System 2. Multi Cyclone and Bag Houses for CDCP

3. Dust suppression system in Wagon Tippler Wet fog dust suppression system in coke 4. handling system 44000 Coke Oven Battery#6 5. Zero leak doors 6. HPALA system and on main charging

7. Door and Door frame cleaning machines

8. H2S recovery system Heat recovery in CDCP for power generation 9. through Back Pressure Turbine. 10. Process ESPs – 2 units

11. Plant De-dusting ESP Sintering Plant#3 4700 12. Bag houses for lime unit

13. Bag house for granulator Cast House De-fuming systems - 2 no. of 14. Electro Static Precipitators 15. Stock House de dusting system – ESP

16. Wet fog dust suppression system

17. Blast Furnace#5 Dust catcher 8000

18. Wet scrubber

19. Clarifiers – 2 nos.

20. Belt press systems – 2nos.

21. Dog House with 2 no. of ESPs

22. 2 no. of Bag Houses for LHF#2A & #2B

23. BOF#3 & Caster#3 in ESP for LHF#3 Steel Melting 12000 24. Shop#2 Bowl classifier

25. Clarifiers

26. Belt press systems

29 Expenditure in Rs. SN. Department Pollution Control Equipment installed Lakhs

27. Scale pit with Oil skimmers Sedimentation tank with Oil skimmer – 2 28. sets 29. New Plate Mill Pressure Filters 10

30. Clarifloculator

31. Sludge drying bed – 2 compartments Calcining Plant#2 32. Bag Houses – 6 nos. 10 Expansion 33. OBBP Expansion Dry fog dust suppression systems 500

Total 61600

30 Annexure-18

List of ESPs installed in different departments and PG Test Status

SN. ESP located at PG Test carried out Efficiency

1) Sintering Plant#3 – Process ESP Yes 99.9% 2) Sintering Plant#3 - Plant Dedusting ESP Yes 99.8% Blast Furnace No.5 – Cast House 3) Yes 99.8% Defuming system – 2 nos. 4) Blast Furnace No.5 – Stock House Yes 99.6% Captive Power Plant#1 – ESP provided to 5) Yes 99.6% MP Boiler#3 Captive Power Plant#1 – ESP provided to 6) Yes 99.5% HP Boiler#5 Captive Power Plant#1 – ESP provided to 7) Yes 99.5% HP Boiler#6

31

Annexure-19

Microfine dust generation from ESPs of Expansion Project

1) SP#3 Process ESPs -- 30 TPD 2) SP#3 Plant de-dusting ESP – 15 TPD 3) BFc Stock House ESP -- 15 TPD 4) BFc Cast House ESPs -- 15 TPD 5) SMS#2 LHF#3 ESP – 5 TPD 6) SMS#2 Dog House ESP – 20 TPD Total dust generation -- 100 TPD

32