North East Expressway Phase 1: Under Development Connects Commonwealth to Norzagaray, Bulacan Project type Expressway Length 19 km Cost PhP 8 billion Source of funds PPP, unsolicited Proponent Ausphil Tollways Corporation Start of Construction TBD Status Active

Target completion August 2021 Photo Source: DPWH Developments Project Description: • As of July 2019, ongoing review of Feasibility Study The North Luzon East Expressway (NLEE) Stage 1 (La Mesa Parkways • May 2018: DPWH re-presented the project to NEDA-ICC Project) uses ROW of the Metropolitan Waterworks and Sewerage • Q4 2016: initial scheduled start of construction System (MWSS) from Commonwealth Ave. to Norzagaray, Bulacan • July 2010: San Miguel acquires majority stake of Ausphil. with an interchange at San Jose del Monte, Bulacan. The project • 2007: notice to proceed awarded by MWSS intends to provide a more efficient route between of • 2001: Australian-Filipino consortium Ausphil Tollways Corporation proposed project Bulacan and Nueva Ecija with .

Updated on September 15, 2019 North Luzon East Expressway Phase 2: Under Development Connects Norzagaray, Bulacan to Nueva Ecija North Luzon East Expressway Project type Expressway Stage 2 Length 91 km Cost PhP 45 billion Source of funds PPP, unsolicited Proponent Ausphil Tollways

Start of Construction TBD North Luzon East Expressway Stage 1 Status Active

Target completion TBD Photo Source: DPWH Developments Project Description: • As of July 2019, ongoing review of Feasibility Study The second stage of the planned North Luzon East Expressway (NLEE) will connect the first stage of the NLEE to the Central Luzon Link Expressway in Cabanatuan, Nueva Ecija (currently under construction).

Updated on September 15, 2019 Tarlac-Pangasinan-La Union Expressway (TPLEX)

Under Construction Connects SCTEX in Tarlac to Pangasinan to La Union Project type Expressway Length 89 km Cost US$ 488 million Source of funds PPP, solicited Proponent San Miguel Infrastructure Start of Construction 2010 Status Partially operational

Target completion September 2019 Photo Source: BusinessWorld Developments Project Description: The 11-km extension from Pozzorubio, Pangasinan to Rosario, La • September 2019: Target opening of Rosario exit • December 2017: Partial operations to Pozzorubio, Pangasinan Union to the existing 78-km Tarlac-Pangasinan-La Union expressway • December 2014: Partial operations to Urdaneta, Pangasinan began is the final section of the expressway that connects SCTEX in • November 2013: Partial operations to Tarlac City Concepcion, Tarlac to Pangasinan and La Union. • January 2010: Phase 1 construction began

Updated on July 24, 2019 TPLEX Extension Under Development Extends TPLEX from Rosario to San Fernando, La Union Project type Expressway Length 54 km Cost PhP 24 billion Source of funds PPP, unsolicited Proponent San Miguel Infrastructure Start of Construction TBA Status Active

Target completion TBA Photo Source: BusinessWorld Developments Project Description: The 54 km extension of TPLEX from its current terminus at Rosario, La • December 2018: SMC granted OPS by DPWH Union to San Fernando, La Union will decongest McArthur Highway • August 2018: San Miguel Infrastructure has submitted a PPP and provide safe, high-speed access into La Union, which has proposal to extend the expressway by 59 km to San Juan, La become one of the frequently visited tourist destinations in Northern Union. Luzon. • February 2018: SMC submitted proposal to DPWH

Updated on June 21, 2019 NLEX Harbor Link Segment 8.1: Completed Connects Segment 8.1 to MacArthur Highway Project type Expressway Length 3 km Cost PhP 2 billion Source of funds PPP Proponent Metro Pacific Start of Construction April 2009 Status Operational

Date of completion June 2010 Photo Source: NLEX Developments Project Description: NLEX Segment 8.1, or the NLEX-Mindanao Avenue Link, is the first • June 2010: project completion segment of the 27-km NLEX Harbor Link that connects Mindanao • April 2009: groundbreaking ceremony Ave. in City to the SMART Connect Interchange of NLEX.

Updated on December 12, 2018 NLEX Harbor Link Segment 8.2: Under Construction Connects NLEX to Commonwealth Project type Expressway Length 8 km Cost PhP 7 billion Source of funds PPP Proponent Metro Pacific Start of Construction Q1 2019 Status Active

Target completion Q2 2021 Photo Source: DPWH Developments Project Description: NLEX Segment 8.2 is the fourth and final segment of the 27-km NLEX- Harbor Link project to be constructed. The four-lane road will connect NLEX, from Segment 8.1, to Commonwealth Ave.

Updated on December 11, 2018 NLEX Harbor Link Segment 9: Completed Connects Segment 8.1 to MacArthur Highway NAIA 3 Project type Expressway Length 2 km Cost PhP 2 billion Source of funds PPP Proponent Metro Pacific Start of Construction April 2013 Status Operational

Date of completion March 2015 Photo Source: BusinessWorld Developments Project Description: NLEX Segment 9, or the NLEX Karuhatan Link, is the second segment • March 2015: segment opened to the public of the 27-km NLEX Harbor Link that connects MacArthur Highway to • April 2013: groundbreaking ceremony the SMART Connect Interchange.

Updated on December 10, 2018 NLEX Harbor Link Segment 10: Under Construction Connects McArthur Highway to R10 NAIA 3 Project type Expressway Length 6 km Cost PhP 16 billion Source of funds PPP Proponent Metro Pacific Start of Construction 2014 Status Partially operational

Target completion December 2019 Photo Source: DPWH Developments Project Description: NLEX Segment 10, the third segment of the 27-km NLEX Harbor Link • December 2019: target completion of project • February 2019: opened to public for partial operations Project, is a four lane, 6 km elevated expressway that connects • December 2018: target completion until C3 Road Interchange McArthur Highway at the end of NLEX Segment 9 to R10 Road, the • November 25, 2018: 86% Completed main road used for trucks coming from the North and South Ports of • October 2018: completion of ROW Acquisition Manila. • May 2014: start of Construction

Updated on March 5, 2019 NLEX – SLEX Connector Road Under Development Connects Skyway Stage 3 to C3 in Caloocan Project type Expressway Length 8 km Cost US$ 466 million Source of funds PPP Proponent Metro Pacific Start of Construction September 2019 Status Active

Target completion Q2 2021 Photo Source: DPWH Developments Project Description: The NLEX – SLEX Connector Road is an elevated 8-km, 4-lane toll • September 2019: Target start of construction work • February 28, 2019: groundbreaking ceremony road extending from NLEX southward from the the end of Segment • 2018: Undergoing ROW acquisition 10 in C3 Road, Caloocan City to Skyway Stage 3 at Sta. Mesa, • September 2017: detailed engineering design completed Manila. The road will cut travel time from SLEX to NLEX from 2 hours • September 2016: project awarded to just 20 minutes and benefit at least 35,000 vehicles per day. • December 2015: NEDA Board Approval • May 2010: approved by DOTC DPWH Sec. Villar said that the project will reduce at least 50,000 • 2010: proposal submitted by Metro Pacific vehicles from EDSA. Updated on August 26, 2019 C5 Expressway Under Development Connects Cavitex to NLEX over C5 road NAIA 3 Project type Expressway Length 27 km Cost PhP 93 billion Source of funds PPP, unsolicited Proponent Metro Pacific Target Construction TBD Status Active

Target completion TBD Photo Source: MPTC Developments Project Description: The C5 Expressway is a 27 km, all-elevated expressway, which will be • May 2018: DPWH confirmed completeness of proposal built above the existing C5 road and connect NLEX Segment 8.2 to • August 2017: MPIC submitted unsolicited proposal to DPWH Cavitex-C5 South Link. It is divided into two phases: (1) Cavitex-C5 South Link to Pasig Blvd. and (2) Pasig Blvd. to NLEX Segment 8.2. The expressway will cut travel time from end-to-end of C5 from two hours to 30 minutes.

Updated on February 20, 2019 Metro Manila Skyway Stage 3: Under Construction Buendia Avenue Makati to Balintawak, Quezon City Project type Expressway Length 15 km Cost PhP 37 billion Source of funds PPP Proponent San Miguel Infrastructure Start of Construction February 2014 Status Partially Operational - 65% Completed

Target completion Q1 2020 Photo Source: Rappler

Project Description: Developments The last stage of the Metro Manila Skyway is a 15-km 6-lane elevated • July 2019: 3.7 km Buendia-Paco segment opened. • April 2019: 65% completed toll road connecting SLEX to Balintawak in Quezon City and NLEX, • February 2018: Sevilla Bridge closed for renovation passing through Central Metro Manila Area. Its completion is • June 2018: Meralco completes relocation work expected to relieve traffic on EDSA by at least 100,000 vehicles. • July 2018: exit ramp to Java St. Makati temporarily opened. • September 2018: bridge connecting San Juan and Manila closed for Skyway Stage 3 has 8 access ramps: (1) Buendia Ave, (2) President demolition. Quirino Ave, (3) Plaza Dilao, (4) Nagtahan/Aurora Blvd, (5) E Rodriguez Ave, (6) Quezon Ave, (7) Sgt. Rivera St, (8) NLEX. Drone video footage of construction progress as of September 2019 Updated on September 15, 2019 Batasan Interchange Metro Manila Skyway  NLEX C5 - Stage 4: Under Development Interchange Tumana Interchange Connects Skyway to Batasang Pambansa Complex Project type Expressway Marcos Highway Interchange

Length 34 km Ortigas Avenue Interchange Cost PhP 45 billion Source of funds PPP C5 – Diego Silang Proponent San Miguel Infrastructure Interchange Start of Construction 2019 C6 – Taguig Status SLEX-FTI Interchange Active Interchange Target completion April 2021 Photo Source: DPWH Developments Project Description: Skyway Stage 4 (Southeast Metro Manila Expressway/C6 • July 2019: On-going civil works in C5 • April 2019: on-going ROW acquisition Expressway) is a 34 km toll expressway. It will cross eastern Manila • January 2018: groundbreaking ceremony and part of , beginning at the future SLEX-FTI interchange in • June 2016: issuance of Notice to Proceed Taguig near the existing Skyway, and ending in the Batasang • August 2014: approval of Supplemental Toll Operations Agreement by Office Pambansa Complex in Quezon City. of the President DPWH Sec. Villar said that this project will remove at least 100,000 cars from EDSA. Updated on July 10, 2019 NAIA Expressway Phase II Completed Connects CAVITEX to NAIA Project type Expressway Length 8 km Cost US$ 361 million Source of funds PPP, solicited Proponent San Miguel Infrastructure Start of Construction January 2014 Status Operational

Date Completed June 2017 Photo Source: Mark Villar Official FB page Developments Project Description: Phase II of the NAIA Expressway (NAIAX) completes the 12 km NAIAX • June 2, 2017: NAIAX fully opened to motorists • December 2016: access ramps to CAVITEX opened system that connects Skyway and CAVITEX to the Ninoy Aquino • September 2016: Macapagal Blvd to NAIA Terminals 1 and 2 segment International Airport terminals and PAGCOR Entertainment City opened to all motorists • January 2016: construction of Phase II begins • May 2012: NAIAX Phase II approved by NEDA Board • May 2009: Phase 1 of NAIAX completed

Updated on November 9, 2018 CAVITEX – C5 South Link Expressway Under Construction Connects CAVITEX to SLEX and C5 NAIA 3 Project type Expressway Length 8 km Cost PhP 10 billion Source of funds PPP Proponent Metro Pacific Start of Construction 2016 Status Partially Operational

Target completion Q4 2020 Photo Source: BusinessWorld Developments Project Description: The east-west CAVITEX-C5 South Link connects major districts in the • July 2019: 2 km Merville-C5 section opened. • April 2019: 89% Completion Makati and Taguig area to , Las Pinas, and Paranaque and • March 2019: target start of operations for first three out of the four segments will service an estimated 45,000 vehicles per day. • October 2018: 52% Construction completed of Segment 3A-1 (Merville to SLEX/C5 Road) • May 2016: groundbreaking ceremony

Video footage of construction progress as of June 2019 Video footage of partial operations as of July 2019 Updated on July 23, 2019 Cavite-- Expressway Under Development Connects Cavite and to Batangas NAIA 3 Project type Expressway Length 50 km Cost PhP 22 billion Source of funds PPP, unsolicited Proponent Metro Pacific Target Construction 2019 Status Active

Target completion Q2 2022 Photo Source: MPTC Developments Project Description: The Cavite-Tagaytay-Batangas Expressway or CTBex connects • Q4 2019: Target date for Swiss Challenge CALAX at Silang, Cavite to , Batangas and decongests the • July 2018: DPWH awarded original proponent status (OPS) to Tagaytay area. Once completed, CTBex will cut travel time from Metro Pacific Tollways South Corporation Dasmarinas City, Cavite to Nasugbu, Batangas to 44 minutes, while Sta. Rosa, Laguna to Tagaytay City will take 46 minutes.

Updated on September 6, 2019 Cavite-Laguna Expressway (CALAX) Under Construction Connects CAVITEX in Cavite to SLEX in Laguna Project type Expressway Length 45 km Cost PhP 36 billion Source of funds PPP, solicited Proponent Metro Pacific Start of Construction Q2 2017 Status Active Photo Source: Metro Pacific Investments Corp. Target completion 2020 Developments Project Description: • September 2019: a 10-km segment is expected to be opened • June 2019: 39% of Laguna segment completed The Cavite-Laguna Expressway or CALAX connects CAVITEX in • April 2019: 31% of Laguna segment completed , Cavite to SLEX in Mamplasan, Laguna and is expected to • March 2019: Groundbreaking ceremony (Cavite) reduce travel time from Cavite to Laguna by 45 minutes. • August 2018: 18.83% of Laguna segment completed • June 2017: Groundbreaking ceremony (Laguna) There will be 9 exits: Kawit, Open Canal, Governor’s Drive, Silang • June 2015: Notice of award for Metro Pacific West, Silang East, and Sta. Rosa-Tagaytay in Cavite and Laguna • November 2013: NEDA Board approval Boulevard, Laguna Technopark, and Mamplasan in Laguna. • August 2013: ICC approval

Video footage of construction progress as of June 2019 Updated on July 12, 2019 South Luzon Expressway – Toll Road 4 Under Construction Extends SLEX to , Quezon Project type Expressway Length 67 km Cost PhP 13 billion Source of funds PPP, solicited Proponent San Miguel Start of Construction March 2019 Status Active

Target completion August 2021 Photo Source: DPWH Developments Project Description: The south Luzon Expressway - Toll Road 4 (TR4) will extend the existing • March 2019: Groundbreaking ceremony and start of construction • Q2 2019: adjusted start of construction following ROW concerns SLEX, which ends in Sto. Tomas, Batangas, to Lucena City, Quezon. • September 2018: scheduled start of construction The project involves building six new exits: (1) Makban and (2) San • 2015: second groundbreaking by President Aquino Pablo in Laguna and (3) , (4) Candelaria, (5) , and (6) • 2010: first groundbreaking by President Arroyo Lucena City in Quezon. The Extension project will cut travel time between Sto. Tomas and Lucena from three hours to just an hour.

Updated on September 6, 2019