June 19, 2015 Decision 20532-D01-2015

Cenovus FCCL Ltd. 500 Centre Street S.E. PO Box 766 Calgary, Alberta T2P 0M5

Attention: Marie Gallant Manager, Power

Kodiak 1210S Substation Proceeding 20532 Application 20532-A001

Time extension

1. Cenovus FCCL Ltd. (Cenovus), by Application 20532-A001 registered with the Alberta Utilities Commission on 9, 2015, requested approval of a time extension in order to complete construction of Kodiak 1210S substation located at the Foster Creek industrial site approximately 70 kilometres north of La Corey, Alberta, within the Cold Lake Air Weapons Range.

2. The proposed work is related to facilities previously approved by the Commission in Permit and Licence U2014-390,1 where 31, 2015 was stipulated as the deadline date to complete the construction of Kodiak 1210S substation.

3. Cenovus stated that the commissioning of Kodiak 1210S substation has been delayed due to Cenovus internal business decisions regarding construction scheduling of associated facilities. Cenovus stated that it has considered the impact of the construction delays and requested a time extension until , 2017, to complete the construction of Kodiak 1210S substation.

4. Cenovus has provided information respecting the need, nature and the duration of the requested time extension. Based upon the information provided, Cenovus has demonstrated that the requested time extension is of a minor nature.

5. The Commission approves a time extension to May 31, 2017, for the completion of the construction of the Kodiak 1210S substation.

1 Substation Permit and Licence U2014-390, Proceeding 3271, Application 1610633, September 29, 2014.

Alberta Utilities Commission , 2015 Page 2 of 2

6. Permit and Licence 20532-D02-2015 is attached.

Alberta Utilities Commission

(original signed by)

Wade Vienneau Executive Director, Facilities Division On behalf of the Alberta Utilities Commission

Attachment