ECPVSC Paper 16/2009-10 For Discussion

Buildings Energy Efficiency Funding Schemes under the Environment and Conservation Fund

Purpose

This paper seeks Members’ agreement to approve 91 funding applications and not to accept 39 funding applications for the Energy-cum-carbon Audits Projects (ECA) and Energy Efficiency Projects (EEP) of the Buildings Energy Efficiency Funding Schemes (BEEFS) under the Environment and Conservation Fund (ECF).

Summary

2. As at 20 January 2010, a total of 199 and 824 applications were received for ECA and EEP respectively. Since the circulation of ECPVSC Paper 13/2009-10 on 4 December 2009, 130 funding applications have been vetted. Out of these 130 applications, 91 funding applications are recommended for approval, 30 funding applications are recommended not to accept due to the inadequate information received for assessment while the remaining are not eligible applications and have been rejected.

3. In addition to the above, 17 funding applications were withdrawn by the applicants which are listed below.

Projects withdrawn by the applicants

Project No. Applicant Funding Sought Energy-cum-carbon Audit The Incorporated Owners of $228,000.00 - Mountain Shore (Ref. ECA 0003)

Energy-cum-carbon Audit The Incorporated Owners of $23,000.00 - Kinox Centre Kinox Centre (Ref. ECA-0015)

Energy-cum-carbon Audit The Incorporated Owners of $43,000.00 - Ventris Place Ventris Place

- 1 - ECPVSC Paper 16/2009-10 For Discussion

Project No. Applicant Funding Sought (Ref. ECA-0016)

Energy-cum-carbon Audit The Incorporated Owners of $20,000.00 - Block P, Q, R, Site 2, Block P, Q, R, Site 2, Aberdeen Centre Aberdeen Centre (Ref. ECA 0041)

Energy-cum-carbon Audit The Incorporated Owners of $45,000.00 - Greenland Villas Greenland Villas (Ref. ECA-0095)

Energy-cum-carbon Audit Well Born Real Estate $20,750.00 - Regence Royale Management Limited - (Ref. ECA-0107) Regence Royale

Energy-cum-carbon Audit Owners Committee of $23,000.00 - Gardenview Heights Gardenview Heights (Ref. ECA-0113)

Energy Efficiency Project- The Owners' Committee of $141,473.50 Beverly Commercial Beverly Commercial Centre Centre (Ref. EEP-0181)

Energy Efficiency Project- The Incorporated Owners of $4,983,350.00 Beverly Hill Beverly Hill (Ref. EEP-0211)

Energy Efficiency Project- The Incorporated Owners of $80,500.00 Case Marina II Casa Marina II (Ref. EEP 0230)

Energy Efficiency Project- The Incorporated Owners of $1,000.00 Greenland Villas Greenland Villas (Ref. EEP 0263)

Energy Efficiency Project- The Incorporated Owners of $1,000.00 Greenery Villa Phase I Greenery Villa Phase I (Ref. EEP 0281)

Energy Efficiency Project- Owners' Committee of Curio $8,062.50

- 2 - ECPVSC Paper 16/2009-10 For Discussion

Project No. Applicant Funding Sought Curio Court Court (Ref. EEP 0467)

Energy Efficiency Project- Coral Garden Owners' $16,610.00 Coral Garden Committee (Ref. EEP 0474)

Energy Efficiency Project - The Incorporated Owners of $325,800.00 Wang Fung Building Wang Fung Building (Ref. EEP0528)

Energy Efficiency Project - The Incorporated Owners of $5,475.00 Wun Sha Tower Wun Sha Tower (Ref. EEP0529)

Energy Efficiency Project - The Incorporated Owners of $39,425.00 China Centre China Hong Kong Centre (Ref. EEP0542)

Total : $6,005,446.00

4. The following nine ineligible applications have been rejected with the reason that the buildings concerned have neither Owners’ Corporation, nor Owners’ Organisation nor Residents’ Organisation established.

Projects Rejected with Ineligible Applicant Organisation

Project No. Application Funding Sought EEP0511 Fung's House, Energy Efficiency $73,040.00 Project

EEP0512 Chun Wah Commercial Building / $16,830.00 Kam Wing Commercial Building, Energy Efficiency Project

EEP0513 Claymore Lodge, Energy Efficiency $63,665.00 Project

- 3 - ECPVSC Paper 16/2009-10 For Discussion

Project No. Application Funding Sought EEP0514 Kam Lung Commercial Centre, $28,125.00 Energy Efficiency Project

EEP0515 , Energy Efficiency $32,700.00 Project

EEP0516 Humphreys Building, Energy $26,900.00 Efficiency Project

EEP0521 Albron Court, Energy Efficiency $139,735.00 Project

EEP0622 Tai Yip Building, Energy Efficiency $138,000.00 Project

EEP0748 International Christian School, $16,000.00 Energy Efficiency Project

Total : $534,995.00

5. The following 30 applications have been rejected with the reason that inadequate information have been received from the applicants despites at least two reminder letters and a conclusion letter were sent. Thus, the information provided in the application is inadequate for the assessment to proceed further.

Projects Rejected with Inadequate Information

Project No. Application Funding Sought EEP0098 Nam Cheong Estate, Energy $56,074.00 Efficiency Project

EEP0101 Man Yuen Building, Energy $135,810.00 Efficiency Project

EEP0117 Celestial Garden, Energy Efficiency $500,000.00 Project

EEP0143 Juniper Villa, Energy Efficiency $3,200.00

- 4 - ECPVSC Paper 16/2009-10 For Discussion

Project No. Application Funding Sought Project

EEP0159 New Man Lee Building, Energy $33,965.00 Efficiency Project

EEP0162 Kwai Fung Building, Energy $29,405.00 Efficiency Project

EEP0164 Green Court, Energy Efficiency $18,855.00 Project

EEP0167 Manhattan Plaza, Energy Efficiency $1,500,000.00 Project

EEP0183 Chatham Commercial Building, $471,800.00 Energy Efficiency Project EEP0205 Lung Poon Court, Energy Efficiency $171,520.50 Project

EEP0265 , Energy Efficiency $7,900,000.00 Project

EEP0278 Luk Hop Industrial Building, Energy $308,260.00 Efficiency Project

EEP0283 Kam On Garden, Energy Efficiency $26,100.00 Project

EEP0298 Royal Green, Energy Efficiency $321,851.75 Project

EEP0358 No.33, 35, 35A Tung Choi Street, $1,490.00 Energy Efficiency Project

EEP0370 The Legend, Energy Efficiency $318,180.00 Project

EEP0395 Hoi Kwong Court, Energy $196,000.00 Efficiency Project

- 5 - ECPVSC Paper 16/2009-10 For Discussion

Project No. Application Funding Sought EEP0399 98-100 Chun Yueng Street, Energy $49,600.00 Efficiency Project

EEP0410 No.1 Garden Terrace, Energy $49,000.00 Efficiency Project

EEP0411 Wyndham Mansion, Energy $99,200.00 Efficiency Project

EEP0415 Westlands Centre, Energy Efficiency $539,000.00 Project

EEP0445 Winfield Building, Energy $53,776.00 Efficiency Project

EEP0446 Hampton Place, Energy Efficiency $200,000.00 Project

EEP0447 Golden Hill Mansion, Energy $8,000.00 Efficiency Project

EEP0448 Kathy's Court, Energy Efficiency $7,000.00 Project

EEP0471 Rambler Club and Carpark, Energy $50,345.00 Efficiency Project

EEP0472 Mount Parker Lodger, Energy $3,750,000.00 Efficiency Project

ECA0154 5 nos. of tower of Serviced $80,000.00 Apartments of , Energy-cum-Carbon Audits

ECA0155 Rambler Club and Carpark, $80,000.00 Energy-cum-Carbon Audits

ECA0184 Pacific Mansion, $19,905.00 Energy-cum-Carbon Audits

Total : $16,978,337.25

- 6 - ECPVSC Paper 16/2009-10 For Discussion

Recommendations

6. The following 91 funding applications with the applied funding of value not exceeding HK$2.0 million are recommended for the consideration of the Committee.

Projects recommended to be approved

Funding Project Title Organization Duration Sought Energy Efficiency The Incorporated Owners February 2010 to Project – Yu Tin of Yue Tin Court September 2010 See Note 1 Court (8 months) (Ref. EEP0053) (Annex I )

Energy Efficiency The Incorporated Owners June 2010 to Project – The of October 2010 Cliveden (5 months) (Ref. EEP0073) (Annex II )

Energy Efficiency The Incorporated Owners June 2010 to Project – Rosedale of Tuen Mun Rosedale October 2010 Gardens Gardens (5 months) (Ref. EEP0075) (Annex III )

Energy Efficiency The Incorporated Owners April 2010 to Project – Hong of Hong Kong Plaza September 2010 Kong Plaza (6 months) (Ref. EEP0094) (Annex IV)

Energy Efficiency Owners' Committee of April 2010 to Project – Ginza Ginza Plaza September 2010 Plaza (Ref. (6 months) EEP0095) (Annex V )

- 7 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency Woodland Crest Owners' September 2010 Project – Woodland Committee to March 2012 Crest (31 months) (Ref. EEP0109) (Annex VI)

Energy Efficiency The Incorporated Owners April 2010 to Project – On Ning of On Ning Garden April 2011 Garden (13 months) (Ref. EEP0118) (Annex VII)

Energy Efficiency The Incorporated Owners February 2010 to Project – Covent of Covent Garden March 2011 Garden (14 months) (Ref. EEP0119) (Annex VIII)

Energy Efficiency - Lot 57 January 2010 to Project – Park Owners' Committee December 2010 Central (12 months) (Ref. EEP0133) (Annex IX )

Energy Efficiency The Incorporated Owners February 2010 to Project – Yuen Long of Yuen Long Yee Fung June 2011 Yee Fung Garden Garden (17 months) (Ref. EEP0134) (Annex X)

Energy Efficiency The Incorporated Owners January 2010 to Project – Glamour of Tai Wai Glamour September 2010 Garden Garden (9 months) (Ref. EEP0140) (Annex XI)

- 8 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency The Incorporated Owners February 2010 to Project – Shatin of Shatin Lodge June 2010 Lodge (5 months) (Ref. EEP0146) (Annex XII)

Energy Efficiency The Incorporated Owners February 2010 to Project – Wah Lok of Wah Lok Industrial June 2010 Industrial Centre Centre (5 months) (Ref. EEP0155) (Annex XIII)

Energy Efficiency The Incorporated Owners March 2010 to Project – Genius of Genius Court July 2010 Court (5 months) (Ref. EEP0176) (Annex XIV)

Energy Efficiency The Incorporated Owners May 2010 to Project – Hing Lee of Hing Lee Building August 2010 Building (Shanghai Street) (4 months) (Ref. EEP0180) (Annex XV)

Energy Efficiency The Incorporated Owners January 2010 to Project – Effort of Effort Industrial August 2010 Industrial Building Building (8 months) (Ref: EEP0189) (Annex XVI)

Energy Efficiency The Incorporated Owners February 2010 to Project – Yip Fung of Yip Fung Industrial August 2010 Industrial Building Building (7 months) (Ref: EEP0191) (Annex XVII)

- 9 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency The Incorporated Owners March 2010 to Project – Mai Wah of Mai Wah Industrial September 2010 Industrial Building Building (7 months) (Ref: EEP0196) (Annex XVIII)

Energy Efficiency East Point City Owners' February 2010 to Project – Block 1-8, Committee July 2010 East Point City (6 months) (Residential) (Ref: EEP0212) (Annex XIX)

Energy Efficiency The Incorporated Owners January 2010 to Project – Grenville of Grenville House June 2010 House (6 months) (Ref: EEP0232) (Annex XX)

Energy Efficiency The Incorporated Owners March 2010 to Project – Fortune of Fortune House September 2010 House (Fanling) (7 months) (Ref: EEP0244) (Annex XXI)

Energy Efficiency The Incorporated Owners June 2010 to Project – Mountain of Mountain Lodge December 2010 Lodge (7 months) (Ref: EEP0255) (Annex XXII)

Energy Efficiency Owners’ Committee of February 2010 to Project – Grandiose July 2010 (Ref: EEP0257) (6 months) (Annex XXIII)

- 10 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency Telford Garden Owners' February 2010 to Project – Telford Committee May 2012 Garden (28 months) (Ref: EEP0258) (Annex XXIV)

Energy Efficiency Owners’ Committee of February 2010 to Project – Liberte’ Liberte' December 2010 (Ref: EEP0279) (11 months) (Annex XXV)

Energy Efficiency Owners' Committee of March 2010 to Project – King's King's Park Hill August 2010 (6 Park Hill months) (Ref. EEP0304) (Annex XXVI)

Energy Efficiency Jasper Court Owners' March 2010 to Project – Jasper Committee July 2011 Court (Ref. (17 months) EEP0314) (Annex XXVII)

Energy Efficiency The Incorporated Owners March 2010 to Project – Mirador of Mirador Mansion July 2010 Mansion (5 months) (Ref. EEP0316) (Annex XXVIII)

Energy Efficiency The Incorporated Owners March 2010 to Project – Hollywood of Hollywood Terrace July 2011 Terrace (17 months) (Ref. EEP0319) (Annex XXIX)

Energy Efficiency The Incorporated Owners April 2010 to Project – King's of King's Park Villa September 2010 Park Villa (6 months) (Ref. EEP0320)

- 11 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought (Annex XXX)

Energy Efficiency The Incorporated Owners October 2010 to Project – Silver of Silver Mansion February 2011 Mansion (5 months) (Ref. EEP0330) (Annex XXXI)

Energy Efficiency Owners' Committee of April 2010 to Project – The The Vineyard August 2010 Vineyard (5 months) (Ref. EEP0333) (Annex XXXII)

Energy Efficiency Metropolis Plaza Owners' March 2010 to Project – Metropolis Committee March 2011 Plaza (13 months) (Ref. EEP0335) (Annex XXXIII)

Energy Efficiency The Incorporated Owners October 2010 to Project – Central of Central Mansion October 2011 Mansion (13 months) (Ref. EEP0345) (Annex XXXIV)

Energy Efficiency The Incorporated Owners May 2010 to Project – Hiu Lai of Hiu Lai Court October 2010 Court (6 months) (Ref. EEP0356) (Annex XXXV)

Energy Efficiency Greenknoll Court February 2010 to Project – Greenknoll Owners' Committee January 2011 Court (12 months) (Ref.EEP0357) (Annex XXXVI)

- 12 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency The Incorporated Owners February 2010 to Project – Heng Shan of Heng Shan Centre May 2010 Centre (4 months) (Ref: EEP0367) (Annex XXXVII)

Energy Efficiency The Owners' Committee June 2010 to Project – Celeste of Celeste Court September 2010 Court (4 months) (Ref: EEP0398) (Annex XXXVIII)

Energy Efficiency The Incorporated Owners April 2010 to Project – Hung Fuk of Hung Fuk Court June 2010 Court (3 months) (Ref: EEP0400) (Annex XXXIX)

Energy Efficiency The Incorporated Owners March 2010 to Project – Pao Fung of Pao Fung Mansions, May 2010 Mansions Nam Cheong Street (3 months) (Ref: EEP0408) (Annex XL)

Energy Efficiency Royal Palms Estate February 2010 to Project – Royal Owners' Committee May 2011 Palms Estate (16 months) (Ref: EEP0421) (Annex XLI)

Energy Efficiency Tai Po Centre Owners' February 2010 to Project – Tai Po Committee October 2010 Centre Phase 1 (9 months) (Ref: EEP0426) (Annex XLII)

- 13 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency Tai Po Centre Owners' February 2010 to Project – Tai Po Committee October 2010 Centre Phase 2 (9 months) (Ref: EEP0427) (Annex XLIII)

Energy Efficiency Tai Po Centre Owners' February 2010 to Project – Tai Po Committee October 2010 Centre Phase 3 (9 months) (Ref: EEP0428) (Annex XLIV)

Energy Efficiency Tai Po Centre Owners' February 2010 to Project – Tai Po Committee October 2010 Centre Phase 4 (9 months) (Ref: EEP0429) (Annex XLV)

Energy Efficiency Tai Po Centre Owners' February 2010 to Project – Tai Po Committee October 2010 Centre Phase 5 (9 months) (Ref: EEP0430) (Annex XLVI)

Energy Efficiency Tai Po Centre Owners' February 2010 to Project – Tai Po Committee October 2010 Centre Phase 6 (9 months) (Ref: EEP0431) (Annex XLVII)

Energy Efficiency The Incorporated Owners February 2010 to Project –Lai Yan of Lai Yan Lau Phase I August 2010 Lau (7 months) Phase I (Ref: EEP0435) (Annex XLVIII)

- 14 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency Grand Horizon Owners' March 2010 to Project – Grand Committee August 2010 Horizon (6 months) (Ref: EEP0437) (Annex XLIX)

Energy Efficiency The Incorporated Owners January 2010 to Project – Cascades of Cascades April 2010 (Ref: EEP0464) (4 months) (Annex L)

Energy Efficiency The Incorporated Owners March 2010 to Project – Po Hei of Po Hei Court December 2010 Court (10 months) (Ref: EEP0465) (Annex LI)

Energy Efficiency The Incorporated Owners March 2010 to Project – Happy of Happy Villa (Lai King December 2010 Villa Hill Road) (10 months) (Ref: EEP0466) (Annex LII)

Energy Efficiency The Harbourside Owners' May 2010 to Project – The Committee December 2010 Harbourside (8 months) (Ref: EEP0473) (Annex LIII)

Energy Efficiency The Incorporated Owners January 2010 to Project – Kam Fai of Kam Fai Garden December 2010 Garden (12 months) (Ref: EEP0477) (Annex LIV)

Energy Efficiency The Incorporated Owners February 2010 to Project – Fook Sing of Fook Sing Mansion June 2010 Mansion (5 months) (Ref: EEP0479)

- 15 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought (Annex LV)

Energy Efficiency The Incorporated Owners March 2010 to Project- of Siu On Court June 2010 Siu On Court (4 months) (Ref: EEP0484) (Annex LVI)

Energy Efficiency The Incorporated Owners February 2010 to Project – Hong Shui of Hong Shui Court October 2010 Court (9 months) (Ref: EEP0500) (Annex LVII)

Energy Efficiency The Incorporated Owners April 2010 to Project – Academic of Academic Terrace November 2010 Terrace (8 months) (Ref: EEP0505) (Annex LVIII)

Energy Efficiency The Incorporated Owners June 2010 to July Project – Manor of Manor Centre 2011 Centre (14 months) (Ref: EEP0506) (Annex LIX)

Energy Efficiency The Incorporated Owners May 2010 to Project – Euro Trade of Euro Trade Centre September 2010 Centre (5 months) (Ref. EEP0518) (Annex LX)

Energy Efficiency The Incorporated Owners May 2010 to Project – South of South China Building September 2010 China Building (5 months) (Ref. EEP0519) (Annex LXI)

- 16 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency The Incorporated Owners March 2010 to Project – Ho Ming of Ho Ming Court November 2010 Court (9 months) (Ref. EEP0524) (Annex LXII)

Energy Efficiency The Incorporated Owners February 2010 to Project – Wiseman of Wiseman Building September 2010 Building (8 months) (Ref. EEP0527) (Annex LXIII)

Energy Efficiency The Incorporated Owners March 2010 to Project – Cheong of Cheong Wah New April 2010 Wah New Building Building (2 months) (Ref. EEP0530) (Annex LXIV)

Energy Efficiency The Incorporated Owners March 2010 to Project – Peridot of Peridot Court June 2010 Court (4 months) (Ref. EEP0533) (Annex LXV)

Energy Efficiency The Incorporated Owners January 2010 to Project – Sino of Sino Centre September 2010 Centre (9 months) (Ref. EEP0539) (Annex LXVI)

Energy Efficiency The Incorporated Owners February 2010 to Project – Tanner of Tanner Garden May 2010 Garden (4 months) (Ref. EEP0540) (Annex LXVII)

Energy Efficiency The Incorporated Owners March 2010 to Project – Belair of Belair Garden February 2011 Garden (12 months)

- 17 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought (Ref. EEP0546) (Annex LXVIII)

Energy Efficiency The Incorporated Owners March 2010 to Project – Lascar of Lascar Court June 2010 Court (4 months) (Ref. EEP0549) (Annex LXIX)

Energy Efficiency Owners’ Committee of June 2010 to Project – Mount Mount Beacon November 2010 Beacon (6 months) (Ref. EEP0554) (Annex LXX)

Energy Efficiency The Incorporated Owners April 2010 to Project – King Shan of King Shan Court October 2010 Court (7 months) (Ref. EEP0572) (Annex LXXI)

Energy Efficiency The Incorporated Owners March 2010 to Project – Tai Ping of Tai Ping Estate April 2011 Estate (14 months) (Ref. EEP0578) (Annex LXXII)

Energy Efficiency The Arch Owners’ July 2010 to Project – The Arch Committee December 2010 (Ref. EEP0579) (6 months) (Annex LXXIII)

Energy Efficiency The Waterfront Owners’ May 2010 to Project – The Committee December 2010 Waterfront (8 months) (Ref: EEP0623) (Annex LXXIV)

- 18 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy Efficiency The Incorporated Owners March 2010 to Project – Scenic of Scenic Gardens November 2010 Gardens (9 months) (Ref: EEP0643) (Annex LXXV)

Energy Efficiency The Incorporated Owners June 2010 to Project – Hang Tsui of Hang Tsui Court September 2010 Court (4 months) (Ref: EEP0646) (Annex LXXVI)

Energy-cum-carbon Owners’ Committee of March 2010 to Audit – Hong Kong June 2013 Parkview (40 months) (Ref. ECA0011) (Annex LXXVII)

Energy-cum-carbon The Incorporated Owners March 2010 to Audit – Grandeur of Grandeur Garden June 2013 Garden (40 months) (Ref. ECA0052) (Annex LXXVIII)

Energy-cum-carbon The Incorporated Owners May 2010 to Audit – Lung Poon of Lung Poon Court August 2013 Court (Blocks A-F) (Blocks A-F) (40 months) (Ref. ECA0060) (Annex LXXIX)

Energy-cum-carbon Owners’ Committee of January 2010 to Audit – Grand Del Grand Del So April 2013 So (40 months) (Ref. ECA0070) (Annex LXXX)

Energy-cum-carbon The Incorporated Owners February 2010 to Audit –Ting Nga of Ting Nga Court April 2013 Court (39 months)

- 19 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought (Ref. ECA0100) (Annex LXXXI)

Energy-cum-carbon Owners’ Committee of March 2010 to Audit – Grand June 2013 Waterfront (40 months) (Ref. ECA0124) (Annex LXXXII)

Energy-cum-carbon The Incorporated Owners June 2010 to Audit – Royal of Royal Jubilee December 2013 Jubilee (43 months) (Ref. ECA0131) (Annex LXXXIII)

Energy-cum-carbon Owners’ Committee of February 2010 to Audit – Greenknoll Greenknoll Court May 2013 Court (40 months) (Ref. ECA0132) (Annex LXXXIV)

Energy-cum-carbon Wonderland Villas Estate February 2010 to Audit – Wonderland Owners’ Committee May 2013 Villas (40 months) (Ref. ECA0138) (Annex LXXXV)

Energy-cum-carbon Owners’ Committee of February 2010 to Audit – Convention Convention Plaza March 2013 Plaza Apartments Apartments (38 months) (Ref. ECA0153) (Annex LXXXVI)

Energy-Cum-carbon Coronet Court Owners' January 2010 to Audit – Coronet Committee April 2013 Court (40 months) (Ref: ECA0157) (Annex LXXXVII)

- 20 - ECPVSC Paper 16/2009-10 For Discussion

Funding Project Title Organization Duration Sought Energy-Cum-carbon Owners' Committee of January 2010 to Audit – New New Mandarin Plaza April 2013 Mandarin Plaza (40 months) (Ref: ECA0169) (Annex LXXXVIII)

Energy-Cum-carbon The Incorporated Owners January 2010 to Audit – of Harbour Centre Tower April 2013 Harbour Centre 2 (40 months) Tower 2 (Ref: ECA0185) (Annex LXXXIX)

Energy-cum-carbon City Committee March 2010 to Audit – City One, Shatin April 2013 Shatin (38 months) (Ref. ECA0188) (Annex XC)

Energy-cum-carbon The Incorporated Owners March 2010 to Audit – Yue Tin of Yue Tin Court June 2013 Court (40 months) (Ref. ECA0190) (Annex XCI)

$20,972,493.75

Advice sought

7. Members are invited to support the recommendations as detailed in paragraphs 6.

The Electrical and Mechanical Services Trading Fund January 2010

Note 1 : Please refer to the website of the Buildings Energy Efficiency Funding Schemes www.building-energy-funds.gov.hk

- 21 -