NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

The Facility Status Update describes the current status of facilities that were applied for, are under construction or have been placed on-stream since the 2018 Annual Plan was issued on December12, 2018, and maintains a record of the facilities two years prior to the current year. Periodic updates are being provided based on the level of activity occurring with respect to facilities. Facilities with (AP) after the project name refer to facilities in the ATCO Pipelines footprint.

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2015 Meter Station and Barich Q4 2017 Complete Aug 31, 2015 - Initial 5.8 Associated Lateral Bigstone East TTFP Notification Abandonment Bigstone East B Clyde North Craigend North Oct 19, 2015 - NEB East Application Filed Devenish South Link to Application Daysland Hamlin Jones Lake East Killam North Minnow Lake South Sales Niobe Creek Niton North Pleasant West Valhalla East Woking Nosehill Creek Lateral 2016 Meter Station and Coleman Q3 2017 Complete Nov 1, 2016 - Initial TTFP 6.7 Associated Lateral Enchant to Notification Abandonment Grew Lake Grew Lake East Q1 2018 Hotchkiss Dec 13, 2016 - NEB Hotchkiss East Application Filed Link to Application Rambling Creek East Sharrow South No. 2

Steele Lake

1 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2016 Pipeline Crossfield Lat Lp Q3 2017 Complete Dec 19, 2016 - Initial 5.6 Decommissioning Mitsue Lat Lp to TTFP Notification Program Big Bend Lat Ricinus Lat Q4 2019 Sedalia North Lat Jan 23, 2017 - NEB Tangent Lat Application Filed (Tangent M/S) Link to Application Atmore Lat (Atmore M/S) Bassano South Lat

2 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2017 Meter Stations and Meter Stations Q3 2018 Under Jun 29, 2017 - Initial TTFP 16.4 Laterals Abandonment w/Laterals to Construction Notification Program Q4 2019 Acadia East Acadia North Aug 21, 2017 - NEB Application Filed Bear Canyon West Link to Application Big Bend East Blueberry Hill Blue Jay Hines Creek West Last Lake Lawrence Lake Manir Mills Tangent East

Stand-Alone Meters

Elinor Lake East Mega River Mega River No. 2 Rod Lake Rod Lake Sales Rossbear Lake Snowfall Creek Squirrel Mountain Owl Lake South Owl Lake South No. 2 Owl Lake South No. 3

Stand-Alone Laterals

Alderson Lateral Kaybob South Lateral McNeill X-Over

3 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2017 NGTL System 15 MW Nov 2017 In-Service Nov 6, Oct 30, 2014 - TTFP 79 - Class 5 53 Camp not required, prime costs lower Expansion Project: 2017 Presentation, 2014 Annual Alces River Compressor Plan Station Unit Addition Link to Annual Plan

Mar 31, 2015 - NEB 85 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 67 - Class 3 Update

Jan 2018 Appendix 2 53 - EAC Update (Estimate at Complete) 2017 NGTL System 36 km NPS 48 Nov 2017 In-Service Sep 11, Oct 30, 2014 - TTFP 207 - Class 5 213 Expansion Project: 2017 Presentation, 2014 Annual Mainline Plan Loop No. 2 (McLeod Link to Annual Plan River Section) Mar 31, 2015 - NEB 228 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 247 - Class 3 Update

Jan 2018 Appendix 2 213 - EAC Update (Estimate at Complete)

4 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2017 NGTL System 20 km NPS 24 Apr 2017 In-Service May Oct 30, 2014 - TTFP 77 - Class 5 75 Expansion Project: 13, 2017 Presentation, 2014 Annual Kettle River Lateral Loop Plan (Christina River Section) Link to Annual Plan

Mar 31, 2015 - NEB 76 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 81 - Class 3 Update

Sep 19, 2017 - Appendix 2 77 - Class 3 Update

Oct 18, 2017 - Appendix 2 75 - EAC Update (Estimate at Complete) 2017 NGTL System 56 km NPS 30 Apr 2017 In-Service May Oct 30, 2014 - TTFP 215 - Class 5 196 Favourable construction conditions Expansion Project: 12, 2017 Presentation, 2014 Annual Liege Lateral Loop No.2 Plan (Pelican Lake Section) Link to Annual Plan

Mar 31, 2015 - NEB 233 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 248 - Class 3 Update

Jun 13, 2017 - TTFP Update

Sep 19, 2017 - Appendix 2 193 - Class 3 Update

Oct 18, 2017 - Appendix 2 196 - EAC Update (Estimate at Complete)

5 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2017 NGTL System 27 km NPS 36 Apr 2017 In-Service May 7, Oct 30, 2014 - TTFP 110 - Class 5 133 Unfavourable construction conditions Expansion Project: 2017 Presentation, 2014 Annual Northwest Mainline Loop Plan No. 2 (Bear Canyon Link to Annual Plan Section) Mar 31, 2015 - NEB 116 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 111 - Class 3 Update

Jun 13, 2017 - TTFP Update

Oct 18, 2017 - Appendix 2 133 - EAC Update (Estimate at Complete) 2017 NGTL System 58 km NPS 36 Apr 2017 In-Service Jun 2, Oct 30, 2014 - TTFP 384 - Class 5 310 185 Unfavourable construction conditions and increased prime Expansion Project: 2017 Presentation, 2014 Annual costs. Plan Northwest Mainline Loop 33 km NPS 36 Apr 2018 In-Service Mar 30, Link to Annual Plan (Boundary Lake Section) 2018 Mar 31, 2015 - NEB 442 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 424 - Class 3 Update

Jun 13, 2017 - TTFP Update

Sep 4, 2018 - Appendix 2 495 - EAC Update (Estimate at Complete)

6 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2017 NGTL System 30 MW Nov 2017 In-Service Dec 7, Oct 30, 2014 - TTFP 115 - Class 5 91 Camp and prime costs lower Expansion Project: 2017 Presentation, 2014 Annual Otter Lake Compressor Plan Station Unit Addition Link to Annual Plan

Mar 31, 2015 - NEB 113 - Class 4 Application Filed Link to Application

Mar 14, 2017 - TTFP 116 - Class 3 Update

Jan 2018 - Appendix 2 91 - EAC Update (Estimate at Complete)

7 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2018 Meter Station and Meter Stations Q3 2019 Proposed Aug 16, 2018 - Initial 17.9 Laterals Abandonment w/Laterals to TTFP Notification Program AECO A Q4 2021 AECO I Sept 28, 2018 - NEB 18.1 Andrew Application filed Chard Link to Application Donnelly Esther Border Meadow Creek Mons Lake Mons Lake East Princess South Retlaw Rock Island Lake Rumsey West Saddle Lake West West Viking

Stand-Alone Meter Stations Rock Island Lake South No. 2

Stand-Alone Laterals Boundary Lake South Flat Lake Lateral Ext. Marten Hills White Earth Creek

8 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2018 Pipelines and Pipeline Laterals Q3 2019 to Approved May 17, Nov 14, 2018 - Initial 14.3 Associated Facilities Baxter Lake Q4 2020 2019 TTFP Notification Decommissioning Calling Lake East Program Calling Lake South East Lat Loop Dec 7, 2018 - TTFP 28 - Class 5 Edgerton Notification Update Flat Lake Lat Loop Flat Lake Lat Ext Dec 18, 2018 - NEB Judy Creek Sales Application Filed North Lat Ext Loop Link to Application Wainwright Wapiti Zama Lake

Associated Facilities Edgerton Rec Judy Creek Sales Zama Lake No. 1 Rec Zama Lake No. 2 Rec Wapiti Rec PTI 360m Cross-over 2021 NGTL System 30 MW Apr 2021 Applied for Jun Feb 13, 2018 - TTFP 120 - ROT 116 Expansion Project: 20, 2018 Facility Update Beiseker Compressor Station Unit Addition Jun 20, 2018 - NEB 116 - Class 5 Application Filed Link to Application 2021 NGTL System 30 MW Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 166 - ROT 116 Expansion Project: 20, 2018 Presentation, 2017 Annual Didsbury Compressor Plan Station & Coolers Link to Annual Plan

Jun 20, 2018 - NEB 116 - Class 5 Application Filed Link to Application

9 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2021 NGTL System 49 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 270 - ROT 287 Expansion Project: 20, 2018 Presentation, 2017 Annual Edson Mainline Loop Plan No.4 (Brewster) Link to Annual Plan

Feb 13, 2018 - TTFP Facility Update

Jun 20, 2018 - NEB 287 - Class 5 Application Filed Link to Application 2021 NGTL System 32 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 156 - ROT 179 Expansion Project: 20, 2018 Presentation, 2017 Annual Edson Mainline Loop Plan No.4 (Dismal Creek) Link to Annual Plan

Jun 20, 2018 - NEB 179 - Class 5 Application Filed Link to Application 2021 NGTL System 42 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 232 - ROT 232 Expansion Project: 20, 2018 Presentation, 2017 Annual Edson Mainline Loop Plan No.4 (Robb) Link to Annual Plan

Feb 13, 2018 - TTFP Facility Update

Jun 20, 2018 - NEB 232 - Class 5 Application Filed Link to Application 2021 NGTL System 69 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 332 - ROT 377 Expansion Project: 20, 2018 Presentation, 2017 Annual Grande Prairie Mainline Plan Loop No.2 (Deep Valley) Link to Annual Plan

Jun 20, 2018 - NEB 377 - Class 5 Application Filed Link to Application

10 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2021 NGTL System 57 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 298 - ROT 327 Expansion Project: 20, 2018 Presentation, 2017 Annual Grande Prairie Mainline Plan Loop No.2 (Karr) Link to Annual Plan

Feb 13, 2018 - TTFP Facility Update

Jun 20, 2018 - NEB 327 - Class 5 Application Filed Link to Application 2021 NGTL System 14 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 73 - ROT 80 Expansion Project: 20, 2018 Presentation, 2017 Annual Grande Prairie Mainline Plan Loop No.2 (Colt Section) Link to Annual Plan

Jun 20, 2018 - NEB 80 - Class 5 Application Filed Link to Application 2021 NGTL System 18 km NPS 48 Apr 2021 Applied for Jun Jul 21, 2017 - TTFP 107 - ROT 107 Expansion Project: 20, 2018 Facility Update Grande Prairie Mainline Loop No.3 (Elmworth Dec 4, 2017 - TTFP Section 2) Presentation, 2017 Annual Plan Link to Annual Plan

Jun 20, 2018 - NEB 107 - Class 5 Application Filed Link to Application 2021 NGTL System 26 km NPS 48 Apr 2021 Applied for Jun Jul 21, 2017 - TTFP 176 - ROT 176 Expansion Project: 20, 2018 Facility Update Grande Prairie Mainline Loop No.3 (Elmworth Dec 4, 2017 - TTFP Section 3) Presentation, 2017 Annual Plan Link to Annual Plan

Jun 20, 2018 - NEB 176 - Class 5 Application Filed Link to Application

11 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 2021 NGTL System 36 km NPS 48 Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 152 - ROT 187 Expansion Project: 20, 2018 Presentation, 2017 Annual Grande Prairie Mainline Plan Loop No.4 (Valhalla) Link to Annual Plan

Jun 20, 2018 - NEB 187 - Class 5 Application Filed Link to Application 2021 NGTL System Control Valve Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 5 5 Expansion Project: Addition 20, 2018 Presentation, 2017 Annual January Creek Control Plan Valve Addition Link to Annual Plan

Jun 20, 2018 - NEB 5 Application Filed Link to Application 2021 NGTL System 30 MW Apr 2021 Applied for Jun Dec 4, 2017 - TTFP 145 - ROT 119 Expansion Project: 20, 2018 Presentation, 2017 Annual Compressor Plan Station Unit Addition Link to Annual Plan

Jun 20, 2018 - NEB 119 - Class 5 Application Filed Link to Application ABC Export Expansion 18 km NPS 48 Nov 2022 Proposed Nov 12, 2019 - TTFP 128 - ROT 128 Tranche 1 Presentation, 2019 Annual Plan Edson Mainline No. 4 (Raven River) ABC Export Expansion TBD Nov 2022 Proposed Nov 12, 2019 - TTFP 8 8 Tranche 1 Presentation, 2019 Annual Plan ABC Border Meter Station Expansion

12 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 ABC Export Expansion 10 km NPS 48 Nov 2023 Proposed Nov 12, 2019 - TTFP 65 - ROT 65 Tranche 2 Presentation, 2019 Annual Plan WAML Loop No. 2 (Longview) ABC Export Expansion 7 km NPS 48 Nov 2023 Proposed Nov 12, 2019 - TTFP 83 - ROT 83 Tranche 2 Presentation, 2019 Annual Plan WAML Loop No. 2 () ABC Export Expansion 23 km NPS 48 Nov 2023 Proposed Nov 12, 2019 - TTFP 209 - ROT 209 Tranche 2 Presentation, 2019 Annual Plan WAML Loop No. 2 (Turner Valley) Albersun Pipeline Asset 179 km TBD In-Service Oct 1, May 12, 2015 - TTFP 28 - Class 5 30 Purchase 2018 Presentation

Apr 27, 2016 - NEB 30 - Class 4 Application Filed Link to Application Montana Border 2-1280U Jul 2020 Proposed Sep 18, 2019 - Initial TTFP 4.6 4.6 Sales Meter Station Ultrasonic Meter Notification Replacement Oct 3, 2019 - CER Application Filed Link to Application Anderson Lake Receipt 10104U Sep 2020 Applied for Oct Oct 8, 2019 - Initial TTFP 4 4 Meter Station Ultrasonic Meter 22, 2019 Notification Oct 22, 2019 - CER Application Filed Link to Application Berland River Compressor 30 MW TBD Deferred Dec 4, 2017 - TTFP 145 - ROT Station Unit Addition Presentation, 2017 Annual Plan Link to Annual Plan

13 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Bonanza Receipt Meter 2-1284U Aug 2018 In-Service Aug 8, Oct 16, 2017- Initial TTFP 5.5 5.5 Station Expansion Ultrasonic Meter 2018 Notification

Nov 3, 2017 - NEB Application Filed Link to Application Boulder Creek South 4 km NPS 8 Jun 2017 In-Service Jun 9, Mar 8, 2016 - TTFP 37 - Class 5 33 Lateral 17 km NPS 6 2017 Presentation

May 16, 2016 - NEB 31 - Class 4 Application Filed Link to Application

May 1, 2018 - Appendix 2 33 - EAC Update (Estimate at Complete) Buffalo Creek 30 MW Nov 2020 Under Dec 7, 2015 - TTFP 139 - ROT 159 Compressor Station Unit Construction Presentation, 2015 Annual Addition Plan Link to Annual Plan

Aug 16, 2016 - TTFP Presentation (Status Update/Deferral)

Dec 4, 2017 - TTFP

Presentation (Status

Update), 2017 Annual Plan

Link to Annual Plan

Oct 1, 2018 - NEB 159 - Class 4 Application Filed Link to Application

14 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Christina Lake North 2-1210U Mar 2018 In-Service Mar 8, Jul 20, 2017 - Initial TTFP 4.4 4.4 Sales Meter Station Ultrasonic Meter 2018 Notification Expansion Aug 18, 2017 - NEB Application Filed Link to Application Clark Lake South Receipt 1010-4U Jun 2019 In-Service May Aug 13, 2018 - Initial 4.4 4.4 Meter Station Ultrasonic Meter 31, 2019 TTFP Notification

Sep 4, 2018 - NEB Application Filed Link to Application Clearwater West 30 MW Apr 2020 Under Jul 21, 2017 - TTFP 117 - ROT 118 Expansion: Construction Facility Update Clearwater Compressor Station Unit Addition Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Jun 4, 2018 - NEB 118 - Class 4 Application Filed Link to Application Clearwater West 13 km NPS 48 Apr 2020 Under Dec 4, 2017 - TTFP 59 - ROT 77 Expansion: Construction Presentation, 2017 Annual Grande Prairie Mainline Plan Loop No.2 () Link to Annual Plan

Jun 4, 2018 - NEB 77 - Class 4 Application Filed Link to Application

15 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Clearwater West 24 km NPS 48 Apr 2020 Under Jul 21, 2017 - TTFP 150 - ROT 130 Expansion: Construction Facility Update Grande Prairie Mainline Loop No.3 (Elmworth Dec 4, 2017 - TTFP Section 1) Presentation, 2017 Annual Plan Link to Annual Plan

Jun 4, 2018 - NEB 130 - Class 4 Application Filed Link to Application Clearwater West 30 MW Apr 2020 Under Jul 21, 2017 - TTFP 111 - ROT 126 Expansion: Construction Facility Update Wolf Lake Compressor Station Unit Addition Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Jun 4, 2018 - NEB 126 - Class 4 Application Filed Link to Application Clearwater Compressor 30 MW Nov 2021 Applied for Sep Dec 4, 2017 - TTFP 145 - ROT 128 Station Unit Addition & 26, 2019 Presentation, 2017 Annual Coolers Plan

Link to Annual Plan

Jul 20, 2018 - TTFP Update

Sep 26, 2018 - CER 128 - Class 5 Application Filed Link to Application Cold Lake Border Sales 1010U Apr 2021 Applied for Aug Aug 9, 2019 - Initial TTFP 3.2 3.2 Meter Station Ultrasonic Meter 23, 2019 Notification Replacement Aug 23, 2019 - NEB Application Filed Link to Application

16 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Cousins West Sales Meter 4 LVS Aug 2017 In-Service Aug 9, May 11, 2017 - Initial 1.4 1.4 Station 2017 TTFP Notification Cutbank River Lateral 18 km NPS 30 Q2 2021 Proposed Nov 14, 2018 - TTFP 97 - ROT 97 Expansion 13 km NPS 16 Presentation, 2018 Annual Plan Link to Annual Plan Cutbank River North 660U-2 Apr 2020 Approved Oct 15, May 22, 2019 - Initial 3.2 3.2 Receipt Meter Station Ultrasonic Meter 2019 TTFP Notification Jun 25, 2019 - NEB Application Filed Link to Application Dawson Creek Receipt 2-1610-4U Q1 2017 In-Service Mar 27, Dec 23, 2015 - Initial 5.6 5.6 Meter Station 2017 TTFP Notification

Apr 27, 2016 - NEB Application Filed Link to Application Dawson Creek No. 2 10104U Oct 2020 Proposed Dec 2, 2019 - Initial TTFP 4.4 4.4 Receipt Meter Station Notification Dawson Creek East No. 2 662U Jul 2020 Proposed Sep 20, 2019 - Initial TTFP 3.8 3.8 Receipt Meter Station Ultrasonic Meter Notification

Oct 8, 2019 - CER Application Filed Link to Application Dismal Creek North 1010-4U Oct 2018 In-Service Nov 29, Nov 22, 2017 - NEB 3.2 3.2 Receipt Meter Station 2018 Application Filed Link to Application

Nov 24, 2017 - Initial TTFP Notification

17 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Dorscheid Receipt Meter 662U Dec 2019 Under Jan 16, 2019 - Initial TTFP 3.2 3.2 Station Ultrasonic Meter Construction Notification Feb 26, 2019 - NEB Application Filed Link to Application Drywood Compressor Nov 2018 In-Service Oct 30, Nov 14, 2017 - Initial 15 7 Station Coolers 2018 TTFP Notification Dec 11, 2017 - NEB 7 Application Filed Link to Application Edson Control Valve Control Valve Apr 2019 In-Service May 5, Dec 4, 2017 - TTFP 5 6.7 Addition Installation 2019 Presentation, 2017 Annual Plan Link to Annual Plan

May 29, 2018 - NEB 6.7 Application Filed Link to Application Edson Mainline 45 km NPS 48 Apr 2022 Applied for Apr 3, Nov 14, 2018 - TTFP 269 - ROT 269 Expansion Project: Edson 2019 Presentation, 2018 Annual Mainline Loop No.4 Plan (Alford Creek) Link to Annual Plan

Apr 3, 2019 - NEB 269 - Class 5 Application Filed Link to Application Edson Mainline 40 km NPS 48 Apr 2022 Applied for Apr 3, Nov 14, 2018 - TTFP 240 - ROT 240 Expansion Project: Edson 2019 Presentation, 2018 Annual Mainline Loop No.4 (Elk Plan River) Link to Annual Plan

Apr 3, 2019 - NEB 240 - Class 5 Application Filed Link to Application

18 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Emerson Creek 2-30 MW Units Apr 2023 Proposed Nov 12, 2019 - TTFP 257 - ROT 257 Compressor Station Presentation, 2019 Annual Plan

Empress Area Extraction 240 m Pipeline plus Q3 2018 In-Service Jun 28, Sep 8, 2017 - Initial TTFP 17 - CIAC Connections Project Valve Assemblies 2018 Notification

Oct 5, 2017 - NEB Application Filed Link to Application Abandonment 84 km NPS 10/6 Q4 2019 Applied for Oct Oct 3, 2018 - Initial TTFP 18.2 31, 2018 Notification

Oct 31, 2018 - NEB Application Filed Link to Application Farrell Lake CS Yard Piping Nov 2018 In-Service Aug 30, Mar 27, 2018 - Initial 9.1 9.1 Modifications Modifications 2018 TTFP Notification Forestburg Lateral Loop 8.2 km NPS10 Q4 2019 In-Service Nov 7, Oct 10, 2018 - Initial TTFP 21.5 21.8 2019 Notification

Forestburg East Sales 2-1080U In-Service Nov 9, Nov 8, 2018 - NEB 21.8 Meter Station Ultrasonic Meter 2019 Application Filed Link to Application Gold Creek South Receipt 882 Apr 2018 In-Service Mar 23, Jul 26, 2018 - Initial TTFP 3.0 3.0 Meter Station Expansion Orifice Meter 2018 Notification

Aug 19, 2017 - NEB Application Filed Link to Application Gold Creek South Receipt 10104U Jul 2019 Under Oct 26, 2018 - Initial TTFP 3.5 3.5 Meter Station Expansion Ultrasonic Meter Construction Notification No. 2 Nov 14, 2018 - NEB Application Filed Link to Application

19 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Gold Creek West Receipt 12124U Apr 2019 In-Service Jan 21, Apr 6, 2018 - Initial TTFP 4.9 4.9 Meter Station Ultrasonic Meter 2019 Notification Apr 30, 2018 - NEB Application Filed Link to Application Goodfish Compressor 30 MW Nov 2020 Under Feb 13, 2018 - TTFP 120 - ROT 115 Station Unit Addition Construction Facility Update

Oct 1, 2018 - NEB 115 - Class 4 Application Filed Link to Application Grace Creek North 660-2 Feb 2018 In-Service Mar 7, Jun 1, 2017 - Initial TTFP 2.0 2.0 Receipt Meter Station Orifice Meter 2018 Notification Jul 6, 2017 - NEB Application Filed Link to Application Grande Prairie Mainline 35 km NPS 48 Nov 2019 Under Jul 21, 2017 - TTFP 108 - ROT 237 Loop No. 2 (McLeod Construction Facility Update River North Section) Nov 14, 2017 - TTFP 155 - ROT Facility Update

Jun 20, 2018 - NEB 237 - Class 4 Application Filed Link to Application Grande Prairie Mainline 33 km NPS 48 Apr 2023 Proposed Nov 12, 2019 - TTFP 204 - ROT 204 Loop No. 4 (Valhalla Presentation, 2019 Annual North Section) Plan

Grey Owl Creek North 882 Apr 2018 In-Service Mar 27, Jun 1, 2017 - Initial TTFP 3.2 3.2 Receipt Meter Station Orifice Meter 2018 Notification Expansion Jun 29, 2017 - NEB Application Filed Link to Application

20 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Grey Owl Creek Receipt 1212-4U Oct 2017 In-Service Sep 18, Jan 31, 2017 - Initial TTFP 3.6 3.6 Meter Station Expansion Ultrasonic Meter 2017 Notification

Mar 10, 2017 - NEB Application Filed Link to Application Groundbirch Mainline 24 km NPS 42 Nov 2022 Proposed Nov 12, 2019 - TTFP 143 - ROT 143 Loop (Saturn Section) Presentation, 2019 Annual Plan

Groundbirch Mainline 24 km NPS 42 Nov 2020 Approved Oct 24, Jul 21, 2017 - TTFP 107 - ROT 140 Loop (Sunrise Section) 2019 Facility Update

Dec 4, 2017 - TTFP 155 - ROT Presentation, 2017 Annual Plan Link to Annual Plan

Oct 3, 2018 - TTFP 135 - ROT Facility Update

Apr 29, 2019 - NEB 140 - Class 4 Application Filed Link to Application Hermit Lake No. 2 Sales 2-860T Dec 2016 In-Service Jan 23, Aug 24, 2016 - Initial 1.8 1.8 Meter Station Turbine Meter 2017 TTFP Notification

Hidden Lake North C/S Yard Piping Apr 2018 In-Service Apr 20, Aug 25, 2017 - Initial 5 5 Modifications Modifications and 2018 TTFP Notification Wheel Change

21 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Hythe Lateral Loop No. 2 14 km NPS 24 Q4 2018 In-Service Oct 31, Dec 7, 2015 - TTFP 41 - Class 5 41 2018 Presentation, 2015 Annual Plan Link to Annual Plan

Aug 16, 2016 - TTFP Presentation (Status Update/Deferral)

Sep 12, 2017 - TTFP 42 - Class 5 Presentation (Scope/Status Update)

Nov 1, 2017 - NEB 40 - Class 4 Application Filed Link to Application

May 7, 2019 - Appendix 2 EAC - 41 Update (Estimate at Complete) Inland Looping (AP) 19 km NPS 20 Feb 2017 In-Service Feb 19, Oct 22, 2013 - TTFP 42 2017 Presentation, 2013 Annual Plan Link to Annual Plan

Oct 30, 2014 - TTFP Presentation, 2014 Annual Plan Link to Annual Plan

Jan 18, 2016 - AUC Application Filed Link to Application Ipiatik Lake Sales Meter Modifications Apr 2018 In-Service Feb 2, Sep 6, 2017 - Initial TTFP 1.3 1.3 Station Modifications 2018 Notification

Sep 29, 2017 - NEB Application Filed Link to Application

22 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Urban Pipeline 14.7 km NPS 10 2020 Proposed Aug 7, 2018 - Initial TTFP 31.2 Upgrade (AP) 2.4 km NPS 6 Notification

Jul 30, 2018 - GRA Application Filed Link to Application Livingstone Creek Receipt 2-1064U Aug 2015 In-Service Aug 7, Oct 23, 2014 - Initial TTFP 7.1 7.1 Meter Station Ultrasonic Meter 2015 Notification

Livingstone Creek No. 2 2-1064U Mar 2017 In-Service Mar 3, Nov 19, 2014 - NEB Receipt Meter Station Ultrasonic Meter 2017 Application Filed Link to Application Livingstone Creek Receipt 10104U Nov 2018 In-Service Nov 14, Mar 1, 2018 - Initial TTFP 3.1 3.1 Meter Station Expansion 2018 Notification

Mar 26, 2018 - NEB Application Filed Link to Application Liza Lake Sales Meter NPS 3 Positive Dec 2018 In-Service Dec 18, Oct 16, 2018 - Initial TTFP 2.1 2.1 Station Displacement Meter 2018 Notification, Streamlining Order Lodgepole Compressor 5 MW Nov 2017 In-Service Dec 16, Dec 7, 2015 - TTFP 62 - ROT 48 Favourable material and prime costs Station Unit Addition and 2017 Presentation, 2015 Annual Interconnect Plan Link to Annual Plan

Feb 12, 2016 - NEB 66 - Class 5 Application Filed Link to Application

Apr 2018 - Appendix 2 48 - EAC Update (Estimate at Complete)

23 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Compressor 3.5 MW Q2 2017 In-Service May 5, Sep 15, 2015 - TTFP 61 - Class 5 61 Station 2017 Presentation

Oct 30, 2015 - NEB 67 - Class 4 Application Filed Link to Application

Aug 29, 2017 - Appendix 2 61 - EAC Update Medicine Hat Expansion 58 km NPS 24 Apr 2023 Proposed Nov 12, 2019 -TTFP 189 - ROT 189 Presentation, 2019 Annual Plan Medicine Hat and Suffield Lateral Loop Meikle River D & 30 MW Q1-Q3 2017 In-Service Sep 10, Oct 30, 2014 - TTFP 135 - ROT 126 Material issues, construction and ISD delays Goodfish Compressor 2017 Presentation, 2014 Annual Stations: Plan Goodfish Compressor Link to Annual Plan Station Dec 18, 2014 - NEB 103 - Class 5 Application Filed Link to Application

Oct. 12, 2016 – TTFP Presentation (Facility Status Update)

Dec 11, 2017 - Appendix 2 126 - EAC Update (Estimate at Complete)

24 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Meikle River D & 33 MW Q1-Q3 2017 In-Service Oct 4, Oct 30, 2014 - TTFP 136 - ROT 124 Goodfish Compressor 2017 Presentation, 2014 Annual Stations: Plan Meikle River D Link to Annual Plan Compressor Station Dec 18, 2014 - NEB 114 - Class 5 Application Filed Link to Application

Oct. 12, 2016 - TTFP Presentation (Facility Status Update)

Jan 2018 Appendix 2 124 - EAC Update (Estimate at Complete) Mildred Lake East Sales 660U Sep 2019 Under Nov 30, 2018 - Initial 3.2 4.1 Meter Station Ultrasonic Meter Construction TTFP Notification Feb 13, 2019 - TTFP 4.1 Notification Amendment Feb 14, 2019 - NEB Application Filed Link to Application Minnow Lake West 2-1064U Nov 2018 In-Service Nov 1, Aug 28, 2017- Initial TTFP 4.4 4.4 Receipt Meter Station Ultrasonic Meter 2018 Notification Expansion Sep 14, 2017 - NEB Application Filed Link to Application Moody Creek Compressor Station Dec 2019 Completed Oct 2, Apr 4, 2019 - Initial TTFP 1.0 1.0 Station Decommissioning decommissioning and 2019 Notification equipment transfer to Saturn Compressor Station Mulligan Lake 3-3016UB Apr 2020 Cancelled Jun 12, 2018 - Initial TTFP 8.7 Interconnect Meter Station Ultrasonic Meter Notification

25 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Muriel Creek Sales Meter NPS 3 Positive Mar 2019 In-Service Mar 1, Jul 16, 2018 - Initial TTFP 2.1 2.1 Station Displacement Meter 2019 Notification Aug 9, 2018 - TTFP Facility Update (Streamlining Order) North Central Corridor 31 km NPS 48 Apr 2020 Under Dec 7, 2015 - TTFP 200 - ROT 170 Loop (North Star Section Construction Presentation, 2015 Annual 1) Plan Link to Annual Plan

Aug 16, 2016 - TTFP Presentation (Status Update/Deferral)

Jul 21, 2017 - TTFP Facility Update

Dec 4, 2017 - TTFP 193 - ROT Presentation, 2017 Annual Plan Link to Annual Plan

Oct 30, 2018 - NEB 170 - Class 4 Application Filed Link to Application North Corridor Expansion 30 MW Apr 2022 Applied for Apr 4, Nov 14, 2018 - TTFP 138 - ROT 138 Project: Hidden Lake 2019 Presentation, 2018 Annual North Compressor Station Plan Unit Addition Link to Annual Plan

Apr 4, 2019 - NEB 138 - Class 5 Application Filed Link to Application

26 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Corridor Expansion 24 km NPS 48 Apr 2022 Applied for Apr 4, Nov 14, 2018 - TTFP 155 - ROT 155 Project: North Central 2019 Presentation, 2018 Annual Corridor Loop (North Star Plan Section 2) Link to Annual Plan

Apr 4, 2019 - NEB 155 - Class 5 Application Filed Link to Application North Corridor Expansion 32 km NPS 48 Apr 2022 Applied for Apr 4, Nov 14, 2018 - TTFP 205 - ROT 205 Project: North Central 2019 Presentation, 2018 Annual Corridor Loop (Red Earth Plan Section 3) Link to Annual Plan

Apr 4, 2019 - NEB 205 - Class 5 Application Filed Link to Application North Corridor Expansion 25 km NPS 36 Apr 2022 Applied for Apr 4, Nov 14, 2018 - TTFP 134 - ROT 134 Project: Northwest 2019 Presentation, 2018 Annual Mainline Loop No.2 (Bear Plan Canyon North Extension Link to Annual Plan Section)

Apr 4, 2019 - NEB 134 - Class 5 Application Filed Link to Application North Heart River Receipt 442 Jul 2018 In-Service Jun 8, Nov 20, 2017 - Initial 2.7 2.7 Meter Station Orifice Meter 2018 TTFP Notification

Dec 4, 2017 - NEB Application Filed Link to Application

27 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Montney Project: 15 MW TBD Deferred Oct 22, 2013 - TTFP 72 - ROT Aitken Creek Compressor Bi-directional Presentation, 2013 Annual Station 5 Plan Link to Annual Plan

Nov 8, 2013 - NEB Application Filed Link to Application

Mar 20, 2017 - NEB 98 - Class 4 Variance Application Link to Application North Montney Project: 2-15 MW Units Nov 2019 In-Service Oct 25, Oct 22, 2013 - TTFP 103 - ROT 131 Groundbirch Compressor Bi-directional 2019 Presentation, 2013 Annual Station 5 Plan Link to Annual Plan

Nov 8, 2013 - NEB Application Filed Link to Application

Mar 20, 2017 - NEB 135 - Class 4 Variance Application Link to Application

Aug 7, 2018 - Appendix 2 131 - Class 3 Class Estimate Update North Montney Project: 182 km NPS 42 Sep 2019 Under Oct 22, 2013 - TTFP 762 - ROT 1270 Elevated prime contractor costs due to unfavorable market North Montney Mainline Construction Presentation, 2013 Annual conditions (Aitken Creek Section) 5 Plan Link to Annual Plan

Nov 8, 2013 - NEB Application Filed Link to Application

Mar 20, 2017 - NEB 930 - Class 4 Variance Application Link to Application

Aug 7, 2018 - Appendix 2 1,270 - Class 3 Class Estimate Update

28 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Montney Project: 24 km NPS 42 Apr 2020 Certificate Oct 22, 2013 - TTFP 196 Elevated prime contractor costs due to unfavorable market North Montney Mainline Approval Presentation, 2013 Annual conditions (Kahta Section - South) 5 Jun 10, 2015 Plan Link to Annual Plan

Variance Nov 8, 2013 - NEB Application NEB Application Filed Approval Order Link to Application Received May 23, 2018 Mar 20, 2017 - NEB 174 - Class 4 Variance Application Link to Application

Aug 7, 2018 - Appendix 2 196 - Class 4 Class Estimate Update

North Montney Project: 95 km NPS 42 TBD Deferred Oct 22, 2013 - TTFP North Montney Mainline Presentation, 2013 Annual (Kahta Section - North) 5 Plan Link to Annual Plan

Nov 8, 2013 - NEB Application Filed Link to Application

Mar 20, 2017 - NEB 331 - Class 4 Variance Application Link to Application

29 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Montney Project: Certificate Oct 22, 2013 - TTFP 66 - Class 5 Remaining North Approval Presentation, 2013 Annual Montney Mainline Jun 10, 2015 Plan Receipt Meter Stations Link to Annual Plan Included in Certificate 5 TBD TBD

Kahta Creek Nov 8, 2013 - NEB 34 - Class 4 Kahta Creek North Application Filed Buckinghorse River Link to Application Mason Creek Beatton River Lily Halfway River Aitken Creek West Aitken Creek East

Mackie Creek TBD TBD 8 Interconnect

Receipt Meter Stations Subject to Variance Application

Blair Creek 2-16104U Ultrasonic Apr 2020 Variance Mar 20, 2017 - NEB 39 - Class 4 67 Gundy 2-1284U Ultrasonic Sep 2019 Application NEB Variance Application Kobes 2-1064U Ultrasonic Apr 2021 Approval Order Link to Application Altares 2-1064U Ultrasonic Sep 2019 Received May 23, Aitken Creek Interconnect 2-2416U Ultrasonic Sep 2019 2018 Apr 27, 2017 - TTFP (bi-directional storage) Notifications Variance Application NEB GIC Approval Received – Jul 3, New Receipt Meter 2018 May 18-25, 2017 - NEB Stations Applications Filed 28 - ROT

Mackie Creek North 662 Orifice Meter Sep 2019 Applied for May Link to Application Altares South 882 Orifice Meter Sep 2019 18-25, 2017 Link to Application Townsend 882 Orifice Meter Sep 2019 Link to Application Townsend No. 2 882 Orifice Meter Sep 2019 Variance Link to Application Gundy West 882 Orifice Meter Sep 2019 Application NEB Link to Application Old Alaska 882 Orifice Meter Sep 2019 Approval Order Link to Application Aitken Creek South 2-1284U Ultrasonic Sep 2019 Received May 23, Link to Application Aitken Creek West No. 2 442 Orifice Meter Apr 2020 2018 Link to Application

30 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Montney Project: 15 MW Apr 2020 Under Oct 22, 2013 - TTFP 70 - ROT 94 Elevated prime contractor costs due to unfavorable market Saturn Compressor Bi-directional Construction Presentation, 2013 Annual conditions Station 5 Plan Link to Annual Plan

Nov 8, 2013 - NEB Application Filed Link to Application

Mar 20, 2017 - NEB 86 - Class 4 Variance Application Link to Application

Aug 7, 2018 - Appendix 2 94 - Class 4 Class Estimate Update North Montney Project: 15 MW TBD Deferred Oct 22, 2013 - TTFP 63 - ROT Saturn Compressor Bi-directional Presentation, 2013 Annual 5 Plan Station – Unit 2 Link to Annual Plan

Nov 8, 2013 - NEB Application Filed Link to Application

Mar 20, 2017 - NEB Variance Application Link to Application

31 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Path Delivery 15 MW Nov 2019 Under Mar 14, 2017 - TTFP 100 - ROT 81 Project: Construction Update Amber Valley Compressor Station Unit Jun 13, 2017 - TTFP Addition Update

Jul 21, 2017 - TTFP 89 - ROT Facility Update

Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Feb 16, 2018 - NEB 81- Class 4 Application Filed Link to Application

32 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 North Path Delivery Modifications to Q2 2020 Under Dec 7, 2015 - TTFP 16 17 Project: Enable Series Construction Presentation, 2015 Annual Meikle River Compressor Operation Plan Station Series Link to Annual Plan Modifications Aug 16, 2016 - TTFP Presentation (Status Update/Deferral)

Mar 14, 2017 - TTFP Update

Jun 13, 2017 - TTFP Update

Jul 21, 2017 - TTFP 17 Facility Update

Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Feb 16, 2018 - NEB 17 Application Filed Link to Application North Path Delivery 28 km NPS 36 Nov 2019 In-Service Sep 25, Jul 21, 2017 - TTFP 99 - ROT 109 Project: 2019 Facility Update Northwest Mainline Loop No. 2 (Bear Canyon North Dec 4, 2017 - TTFP 109 - Class 4 Section) 6 Presentation, 2017 Annual Plan Link to Annual Plan

Feb 16, 2018 - NEB 109 - Class 4 Application Filed Link to Application

33 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Northwest Mainline Loop 23 km NPS 36 Apr 2019 In-Service Mar 23, Jul 21, 2017 - TTFP 115 - ROT 98 (Boundary Lake North 2019 Facility Update Section) Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Dec 15, 2017 - NEB 105 - Class 4 Application Filed Link to Application

Jun 2019 Appendix 2 98 - EAC Update (Estimate at Complete) Peace River Mainline 266 km NPS 20 Dec 2020 Approved Mar 14, Oct 22, 2013 - TTFP 29.7 - Class 4 Abandonment (Meikle 2.3 km NPS 4 2018 Presentation, 2013 Annual River to Valleyview Plan Section) Link to Annual Plan

Oct 30, 2014 - TTFP Presentation, 2014 Annual Plan Link to Annual Plan

Jul 22, 2016 - TTFP Presentation (Filing/Scope Change)

Aug 18, 2016 - NEB Application Filed Link to Application

34 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Pembina- 58 km NPS 30 Apr-2020 Approved Aug 6, May 8, 2018 - Initial TTFP 155 Transmission Project (AP) 2019 Notification

Aug 1, 2018 - AUC 157 Application Filed Link to Application

Nov 30, 2018 - AUC 230 Project Update Filed Link to Update Pipestone Creek Receipt 662U Nov 2019 In-Service Oct 22, Feb 1, 2019 - Initial TTFP 3.1 3.1 Meter Station Ultrasonic Meter 2019 Notification Feb 19, 2019 - NEB Application Filed Link to Application Prairie Creek Receipt NPS 8 Separator Dec 2019 Under Oct 2, 2019 - Initial TTFP 1.3 1.3 Meter Station Expansion Installation Construction Notification, Streamlining Order Pipestone Compressor 30 MW TBD Deferred Dec 4, 2017 - TTFP 145 - ROT Station Unit Addition & Presentation, 2017 Annual Coolers Plan Link to Annual Plan Princess Compressor Decommissioning of Feb 2017 Completed Jul 6, Jan 4, 2017 - Initial TTFP 11.0 Station A and D A and D Buildings 2017 Notification Decommissioning Jan 20, 2017 - NEB Streamlining Order Notification Link to Notification Princess Compressor 30 MW TBD Deferred Nov 14, 2018 - TTFP 137 - ROT Station Unit Addition & Presentation, 2018 Annual Coolers Plan Link to Annual Plan

35 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Redwater Cogen Delivery 2-440T Dec 2018 In-Service Jan 1, Aug 7, 2018 - Initial TTFP 1.1 #2 Station (AP) Turbine Meter 2019 Notification

Jul 30, 2018 GRA Application Filed Link to Application Resthaven Receipt Meter 2-1280U Apr 2018 In-Service Feb 27, May 11, 2017 - Initial 4.3 4.3 Station Expansion Ultrasonic Meter 2018 TTFP Notification

May 26, 2017 - NEB Application Filed Link to Application Rodney Creek Receipt 660-2 Aug 2018 In-Service Dec 14, Nov 6, 2017 - Initial TTFP 2.2 2.2 Meter Station Orifice Meter 2018 Notification

Nov 22, 2017 - NEB Application Filed Link to Application Saddle Hills Compressor 30 MW Nov 2022 Proposed Nov 12, 2019 - TTFP 159 - ROT 159 Station Unit Addition Presentation, 2019 Annual Plan

Saddle Lake Lateral Loop 20 km NPS 20 Apr 2021 Applied for Aug Feb 13, 2018 - TTFP 42 - ROT 64.9 (Cold Lake Section) 23, 2019 Facility Update Aug 23, 2019 - NEB 64.9 - Class 4 Application Filed Link to Application Saddle West Expansion: Control Valve Jun 2019 In-Service May Jul 21, 2017 - TTFP 4.4 4.3 Clarkson Valley Control Installation 30, 2019 Facility Update Valve Oct 2, 2017 - NEB 4.5 Application Filed Link to Application

Aug 7, 2018 - Appendix 2 4.3 Class Estimate Update

36 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Saddle West Expansion: 25 km NPS 36 Jun 2019 In-Service Jan 12, Dec 5, 2016 - TTFP 96 - ROT 134 Gordondale Lateral Loop 2019 Notification, 2016 Annual No. 3 Plan Link to Annual Plan

Oct 2, 2017 - NEB 98 - Class 4 Application Filed Link to Application

Aug 7, 2018 - Appendix 2 130 - Class 3 Class Estimate Update

May 2019 Appendix 2 134 - EAC Update (Estimate at Complete) Saddle West Expansion: 30 MW Jun 2019 In-Service Oct 3, Dec 5, 2016 - TTFP 101 - ROT 142 Elevated prime contractor costs due to unfavorable market Latornell Compressor 2019 Notification, 2016 Annual conditions Station Unit Addition Plan Link to Annual Plan

Oct 2, 2017 - NEB 118 - Class 4 Application Filed Link to Application

Aug 7, 2018 - Appendix 2 142 - Class 3 Class Estimate Update Saddle West Expansion: 33 MW Jun 2019 In-Service Sep 14, Feb 14, 2017 - TTFP 116 - ROT 139 Elevated prime contractor costs due to unfavorable market Nordegg Compressor 2019 Update conditions Station Unit Addition Jul 21, 2017 - TTFP 112 - ROT Facility Update

Oct 2, 2017 - NEB 111 - Class 4 Application Filed Link to Application

Aug 7, 2018 - Appendix 2 139 - Class 3 Class Estimate Update

37 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Saddle West Expansion: 30 MW Jun 2019 In-Service Oct 3, Dec 5, 2016 - TTFP 74 - ROT 145 Elevated prime contractor costs due to unfavorable market Saddle Hills Compressor 2019 Presentation, 2016 annual conditions Station Unit Addition and Plan Control Valve Link to Annual Plan Modifications Jun 13, 2017 - TTFP 119 - Class 5 Update

Oct 2, 2017 - NEB 118 - Class 4 Application Filed Link to Application

Aug 7, 2018 - Appendix 2 145 - Class 3 Class Estimate Update Saddle West Expansion: 30 MW Jun 2019 In-Service Sep 14, Dec 5, 2016 - TTFP 116 - ROT 142 Elevated prime contractor costs due to unfavorable market Swartz Creek Compressor 2019 Presentation, 2016 Annual conditions Station Unit Addition Plan Link to Annual Plan

Oct 2, 2017 - NEB 116 - Class 4 Application Filed Link to Application

Aug 7, 2018 - Appendix 2 142 - Class 3 Class Estimate Update Saturn No. 2 Receipt 2-1060U-4 Apr 2018 In-Service Mar 31, Aug 9, 2017 - Initial TTFP 3.8 3.8 Meter Station Ultrasonic Meter 2018 Notification

Aug 29, 2017 - NEB Application Filed Link to Application Scotford PDH Delivery 860T Jul 2020 Proposed May 1, 2018 - Initial TTFP 2.6 (Includes Meter Station (AP) Turbine Meter Notification $1.7M CIAC) Sheerness No. 2 Sales 2-1210U Nov 2019 In-Service Nov 26, Mar 8, 2019 - Initial TTFP 4.2 4.2 Meter Station Ultrasonic Meter 2019 Notification Apr 1, 2019 - NEB Application Filed Link to Application

38 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Smoky River Lateral Loop 10 km NPS24 Apr 2019 In-Service Mar 25, Dec 5, 2016 - TTFP 54 - Class 5 89 2019 Presentation, 2016 Annual Plan 18 km NPS 24 In-Service Jun 4, 2019 Link to Annual Plan

Sep 12, 2017 - TTFP 118 - Class 5 Presentation (Scope/Status Update)

Nov 29, 2017 - NEB 91 - Class 4 Application Filed Link to Application

Nov 19, 2019 - Appendix 2 89 - EAC Update (Estimate at Complete) Smoky River Sales Meter 660U Mar 2020 Applied for Aug Jul 23, 2019 - Initial TTFP 2.9 2.9 Station Ultrasonic Meter 12, 2019 Notification Aug 12, 2019 - NEB Application filed Link to Application South Airdrie Lateral - 8.7 km NPS 6 Q3 2019 Proposed Aug 7, 2018 - Initial TTFP 1.9 Pipeline Acquisition (AP) Notification

Jul 30, 2018 GRA Application Filed Link to Application Stoney Transit/North Gate 4.3 km NPS 8 Q1 2019 In-Service Mar 8, Dec 4, 2017 - TTFP 8 Connection Piping (AP) 2019 Presentation, 2017 Annual Plan Link to Annual Plan

May 25, 2018 - AUC Application Filed Link to Application Sturgeon Refinery Process 2-AAT 140 Meter Nov 2016 In-Service Feb 15, Jun 9, 2016 - AUC 6.5 Delivery and Lateral (AP) 1 km NPS 12 2017 Application Filed Link to Application

39 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Sunchild Receipt Meter 880U-4 Apr 2020 Approved Nov 4, Jun 5, 2019 - Initial TTFP 4 4 Station Ultrasonic Meter 2019 Notification Jul 8, 2019 - NEB Application Filed Link to Application Sundre Crossover 20 km NPS 42 Apr 2018 In-Service Apr 8, Dec 7, 2015 - TTFP 240 - ROT 99 2018 Presentation, 2015 Annual Plan Link to Annual Plan

May 17, 2016 - TTFP 137 - Class 5 Presentation (Scope Change)

Nov 2016 - Appendix 2 113 - Class 4 Class Estimate Update

Mar 24, 2017 - NEB 99 - Class 3 Application Filed Link to Application

Jul 21, 2017 - TTFP Facility Update Tony Creek No. 2 Receipt 2-1064U Oct 2017 In-Service Oct 5, Mar 3, 2017 - Initial TTFP 3.8 3.8 Meter Station Ultrasonic Meter 2017 Notification

Mar 17, 2017 - NEB Application Filed Link to Application Tony Creek No. 2 Receipt 16164U Aug 2019 In-Service Jul 23, Oct 15, 2018 - Initial TTFP 6.0 5.7 Meter Station Expansion Ultrasonic Meter 2019 Notification

Nov 13, 2018 - NEB 5.7 Application Filed Link to Application

40 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Towerbirch Expansion NEB Aug 18, 2015 - TTFP 470 - Class 5 334 Favourable prime and material costs Recommendation Presentation Oct 6, 2016 Sep 2, 2015 - NEB 439 - Class 4 GIC Certificate Application Filed Mar 10, 2017 Link to Application

Groundbirch Mainline 55 km NPS 36 Nov 2017 In-Service Oct 30, Mar 2016 - Appendix 2 Loop 2017 Update for Cost to Complete Tower Lake Section 32 km NPS 30 Nov 2017 In-Service Oct 1, 2017 Jun 13, 2017 - TTFP 383 - Class 3 Update Tower Lake Receipt 2-1284U Nov 2017 In-Service Sep 29, Meter Station Ultrasonic Meter 2017 Jan 2018 Appendix 2 334 - EAC Update (Estimate at Dawson Creek North No. 2-1284U Apr 2018 In-Service Nov 15, Complete) 2 Receipt Meter Station Ultrasonic Meter 2017

Dawson Creek North 2-1284U Sep 2018 In-Service Oct 30, Receipt Meter Station Ultrasonic Meter 2017

Dawson Creek East 882 Orifice Meter Jul 2017 In-Service Jul 20, Receipt Meter Station 2017

Groundbirch East Receipt 1-2412U Nov 2017 In-Service Aug 15, Meter Station Expansion Ultrasonic Meter 2017

Turin East Transmission 10.5 km NPS 4 2018 In-Service Jan 13, Aug 16, 2017 - AUC 5.6 Loop (AP) 2018 Application filed Link to Application Urban Pipeline 19 km NPS 20 Q4 2017 In-Service Dec 19, Oct 30, 2014 - TTFP 90 Replacement Project: 1 km NPS 16 2017 Presentation UPR - West Connector (AP) May 6, 2016 - AUC 88 Application Filed Link to Application

41 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Urban Pipeline Control Station 2019 Proposed Oct 30, 2014 - TTFP 14.2 Replacement Project: Presentation UPR – NE Connector (AP) Urban Pipeline 21 km NPS 20 Q2 2017 In-Service Apr 1, Jul 10, 2012 - TTFP 93 Replacement Project: 2017 Presentation Southwest Edmonton Connector – UPR (AP) Jun 2, 2015 - AUC Application Filed Link to Application Valhalla North Receipt 882 Oct 2018 In-Service Aug 20, Nov 27, 2017 - Initial 3.1 3.0 Meter Station Expansion 2018 TTFP Notification

Dec 19, 2017 - NEB 3.0 Application Filed Link to Application Vermillion Compressor 1 MW Apr 2021 Proposed Feb 13, 2018 - TTFP TBD Station Unit Addition Facility Update (AP) Vetchland Compressor 30 MW TBD Deferred Dec 4, 2017 - TTFP 145 - ROT Station Unit Addition & Presentation, 2017 Annual Coolers Plan Link to Annual Plan

Nov 14, 2018 - TTFP 137 - ROT Presentation, 2018 Annual Plan Link to Annual Plan Wainwright Compressor 0.4 MW Jul 2017 In-Service Jul 18, Dec 5, 2016 - TTFP 2.0 2.3 Station Unit Replacement 2017 Presentation, 2016 Annual Plan Link to Annual Plan

Feb. 27, 2017 - TTFP 2.3 Notification

42 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 West Path Delivery 30 MW Jun 2020 Under Jul 21, 2017 - TTFP 116 - ROT 114 Project: Construction Facility Update Burton Creek Compressor Station Unit Addition Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Feb 12, 2018 - NEB 114 - Class 4 Application Filed Link to Application West Path Delivery 30 MW Jun 2020 Under Jul 21, 2017 - TTFP 132 - ROT 106 Project: Construction Facility Update Turner Valley Compressor Station Unit Addition 7 Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Feb 12, 2018 - NEB 106 - Class 4 Application Filed Link to Application West Path Delivery 22 km NPS 42 Jun 2020 Approved Apr 11, Jul 21, 2017 - TTFP 176 - ROT 189 Project: 2019 Facility Update Western Alberta System Mainline Loop Rocky Dec 4, 2017 - TTFP View Section Presentation, 2017 Annual Plan Link to Annual Plan

Feb 12, 2018 - NEB 189 - Class 4 Application Filed Link to Application Wiau Lake North Sales 2-640T Jul 2019 In-Service Feb 8, May 22, 2018 - Initial 2.4 2.4 Meter Station Turbine Meter 2019 TTFP Notification Jun 11, 2018 - NEB Application Filed Link to Application

43 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Wildrose Receipt Meter 2-2012U May 2018 In-Service Oct 1, Jul 12, 2017 - Initial TTFP 8.3 8.3 Station Ultrasonic Meter 2018 Notification

Sep 27, 2017 - NEB Application Filed Link to Application Wilkin Lake Sales Meter LVS-4 Dec 2018 In-Service Nov 15, Mar 12, 2018 - Initial 2.0 2.0 Station Turbine Meter 2018 TTFP Notification

Mar 28, 2018 - NEB Application Filed Link to Application Wilson Ridge Receipt 10104U Feb 2019 In-Service Jan 22, Mar 1, 2018 - Initial TTFP 3.9 3.9 Meter Station Ultrasonic Meter 2019 Notification Apr 11, 2018 - NEB Application Filed Link to Application Winchell Lake 30 MW Nov 2019 In-Service Nov 8, Jul 21, 2017 - TTFP 116 - ROT 99 Compressor Station Unit 2019 Facility Update Addition Dec 4, 2017 - TTFP Presentation, 2017 Annual Plan Link to Annual Plan

Mar 8, 2018 - NEB 99 - Class 4 Application Filed Link to Application Approved Aug 30, 2018 Wolf Lake South Receipt 1010-4U Sep 2019 In-Service Sept 18, Nov 29, 2018 - Initial 3.8 3.8 Meter Station Ultrasonic Meter 2019 TTFP Notification

Dec 18, 2018 - NEB Application Filed Link to Application

44 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

Cost by In-Service Year 3 ($Millions) Target In- Forecast Cost Applied-for Facilities Description Service Date Status References 1 2 ($Millions) 2017 2018 2019 2020 2021 2022 2023 Variance Explanation 4 Woodenhouse 30 MW Nov 2018 In-Service Nov 24, Oct 30, 2014 - TTFP 136 - Class 5 130 Compressor Station Unit 2018 Presentation, 2014 Annual Addition Plan

Link to Annual Plan

Dec 7, 2015 - TTFP Presentation, 2015 Annual Plan Link to Annual Plan

Nov 7, 2016 - NEB 138 - Class 4 Application Filed Link to Application

Feb 2017 - Appendix 2 130 - Class 4 Class Estimate Update Worsley McLennan 10.7 km NPS 6 2017 In-Service Mar 21, Aug 2, 2017 - AUC 7.8 Transmission Loop (AP) 2018 Application Filed Link to Application Total Costs by In-Service Year 3 1823 565 2896 1845 2601 1579 1007

1. Hyperlinks to AUC filings require an AUC eFiling login which can be obtained by contacting the AUC. 2. For NGTL projects greater than $25 million, the estimate type for the forecasted costs have been provided. The typical expected accuracy for the various estimate types are shown in the table below. These accuracy ranges are for projects with established technological complexity and can be greater depending on area knowledge, technological complexity, level of expertise, and certainty of facility scope. Forecasted costs reflect the dollar value, economic conditions, and estimation procedures at the time the estimates were completed. Estimate Type Expected Accuracy Range Rule of Thumb (ROT) (-50% to +100%) Class 5 (-20% to +30%) Class 4 (-15% to +20%) Class 3 (-10 to +10%)

45 NOVA Gas Transmission Ltd. Appendix 2: 2019 Facility Status Update (December)

3. Total Costs by In-Service Year are a summation of the last provided costs of all NGTL capacity capital projects with expected or realized in-service dates within a calendar year. Costs for non NGTL capacity capital projects, such as ATCO Pipelines, CIAC, decommissioning or abandonment projects, are excluded. These annual summations of costs will not match other regulatory filings with different costs bases. 4. Variance explanations are provided for all NGTL capacity capital projects with EAC costs equal to or greater than $25 million with a variance greater than 10% between the EAC and applied-for costs. 5. The North Montney Project was filed as a Section 52 application on November 8, 2013 comprised of the following facilities: North Montney Mainline (Aitken Creek Section), North Montney Mainline (Kahta Section), Aitken Creek Compressor Station, Saturn Compressor Station, Groundbirch Compressor Station, 14 receipt meter stations, a bi-directional storage meter station (Aitken Creek Interconnect) and a delivery meter station (Mackie Creek Interconnection). The NMML Variance was filed March 20, 2017 to vary Condition 4 in the Certificate and Order and to extend the Sunset Clause for the NMML. The Variance also includes the details on eight additional meter stations required for the new receipt contracts. North Montney costs are escalated to the year of in-service for each respective facility. The original Kahta Section was 119 km of NPS 42 with a ROT cost estimate of $530Million. Variance Application NEB Approval Order Received May 23, 2018. Altares, Altares South, Gundy, Gundy West, Old Alaska, Mackie Creek North, Townsend, Townsend No. 2 and Aitken Creek South receipt meter stations are currently under construction. 6. Northwest Mainline Loop No. 2 (Bear Canyon North Section) is the combination of two previously presented facilities; Northwest Mainline Loop No. 2 (Bear Canyon North Section) and the Northwest Mainline Loop (Peace River Crossing Project). 7. Turner Valley Compressor Station Coolers has been combined with Turner Valley Compressor Station Unit Addition.