FORM –1 & 1 A

FOR

“GRAND HORIZON”

At

S.No 34/1/4, 39/1A + 39/2/5/1/ , Vadgaon Budruk, Road, 411041

By

M/s Grenesis Constro Pvt. Ltd.

FORM –1

FOR

“GRAND HORIZON”

At

S.No 34/1/4, 39/1A + 39/2/5/1/ , Vadgaon Budruk, Sinhagad Road, Pune 411041

By

M/s Grenesis Constro Pvt. Ltd.

Form1 Grenesis Constro Pvt.Ltd.

(See paragraph - 6)

FORM 1 (I) Basic Information Sr.No. Item Details 1. Name of the project “Grand Horizon” 2. S. No. in the schedule 8 (a) 3. Proposed capacity/area/length/tonnage Total Plot area :10,120 m2 to be handled/command area/lease area/number of wells to be drilled 4. New/Expansion/Modernization New 5. Existing Capacity/ Area etc. Not Applicable 6. Category of project i.e.’ A’ or ‘B’ 8 (B2) 7. Does it attract the general condition? No If yes, please specify. 8. Location Latitude :180 28’24.91N Longitude :730 49’21.50 E Plot/Survey/Khasra No. S.No 34/1/4, 39/1A + 39/2/5/1 Village Vadgaon Budruk, Tehsil Haveli District Pune State 9. Nearest railway station nagar railway station :6.39 kms Nearest airport 16.46 kms 10. Nearest Town, city, PMC District headquarters Along with distance in kms. 11. Village Panchayats, Zilla Parishad, PMC Municipal Corporation, Local body (complete postal address with telephone nos. to be given) 12. Name of the applicant M/s. Grenesis Constro Pvt. Ltd. 13. Registered Address A/501, Thakkar's House, K.P Co‐Op Housing Society , G.T Road, Camp, Pune‐01 14. Address for correspondence A/501, Thakkar's House, K.P Co‐Op Housing Society , G.T Road, Camp, Pune‐01 Name Mr.Pramod Korgaonkar Designation (Owner/Partner/CEO) Power of Attorney Holder Address Same as above Pin Code 411 001 E-mail [email protected] Telephone No. 020‐26334876 Fax No. 020‐26334876 15. Details of Alternative Sites examined, No if any. Location of these sites should be shown on a topo-sheet. 16. Interlinked Projects Not applicable 17. Whether separate application of Not applicable interlinked project has been submitted? 18. If yes, date of submission Not applicable Form1 Grenesis Constro Pvt.Ltd.

Sr.No. Item Details 19. If no, reason Not applicable 20. Whether the proposal involves approval/clearance under: if yes, details of the same and their status to No be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z Notification, 1991? 21. Whether there is any Government No Order/Policy relevant/ relating to the site? 22. Forest land involved (hectares) No 23. Whether there is any litigation No pending against the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Order /directions of the Court, if any and its relevance with the proposed project.

(II). Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.1 Permanent or temporary change No Development will be carried in line with the in land use, land cover or topography & without disturbing natural topography including increase drainage pattern. Project falls under Residential in intensity of land use (with Zone of PMC. DP is attached as Annexure-1 respect to local land use plan) 1.2 Clearance of existing land, No -- vegetation and building? 1.3 Creation of new land uses? No -

1.4 Pre-construction investigation Yes Pre-construction investigation will be carried out e.g. bore houses, soil testing? as per relevant standards 1.5 Construction works? Yes 1 Building ,Commercial - Building - 1

1.6 Demolition works? No ‐ 1.7 Temporary sites used for Yes Sheds of Temporary labour camp for construction works or housing construction workers on site with security. of construction workers? 1.8 Above ground building, structures No Excavation in the form of rubble and soil. Part or earthworks including linear of this soil and rubble will be used for back structures, cut and fill or filling and remaining material will be disposed excavations. by covered trucks to our proposed site.

Form1 Grenesis Constro Pvt.Ltd.

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.9 Underground works including No. -- mining or Tunneling? 1.10 Reclamation works? No --

1.11 Dredging? No --

1.12 Offshore structures? No --

1.13 Production and manufacturing No -- processes? 1.14 Facilities for storage of goods or Yes During construction phase temporary storage materials? facilities are created to store the construction raw material. 1.15 Facilities for treatment or Yes Facilities are provided for collection, treatment disposal of solid waste or liquid and disposal for solid and liquid waste effluents? 1.16 Facilities for long term housing No -- of operational workers? 1.17 New road, rail, or sea traffic No -- during construction or operation? 1.18 New road, rail, air waterborne No -- or other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic Movements? 1.20 New or diverted transmission No -- lines or pipelines? 1.21 Impoundment, damming, No -- culverting, realignment or other change to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No -- 1.23 Abstraction or transfers of water No - from ground or surface waters? 1.24 Changes in water bodies or the Yes By considering the runoff prior to development land surface affecting drainage and runoff after development there is some or run-off? increment in runoff of storm water.

1.25 Transport of personnel or Yes There will be transport of construction materials. materials for construction, It will be planned during non peak hours. operation or decommissioning? 1.26 Long-term dismantling or No -- decommissioning or restoration works?

Form1 Grenesis Constro Pvt.Ltd.

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.27 Ongoing activity during No -- decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in Yes There will be influx 2340 nos of people in either temporarily or proposed project, which includes permanent permanently? population. 1.29 Introduction of alien species? No --

1.30 Loss of native species or genetic No -- diversity? 1.31 Any other actions? No --

2.0 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Sr. Information/checklist Yes Details thereof (with approximate quantities No. confirmation / No /rates, wherever possible) with source of information data 2.1 Land especially undeveloped or Yes Total Plot Area under development:10,120m2 agricultural land (ha) 2.2 Water (expected source & Yes During construction: Potable water shall be competing users) unit : KLD supplied as per requirement. During Operation: Source of water: Local Authority Quantity of water: ~204 m3/day 2.3 Minerals (MT) No 2.4 Construction material – stone, Yes List of raw materials used during construction aggregates, and / soil (expected phase is enclosed herewith. Annexure -2 source – MT) 2.5 Forests and timber (source – MT) No

2.6 Energy including electricity and Yes Source: MSEDCL fuels (source, competing users) Unit: fuel (MT), energy (MW) 2.7 Any other natural resources (use No - appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Form1 Grenesis Constro Pvt.Ltd.

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, No -- which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of No -- disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. No -- by changing living conditions? 3.4 Vulnerable groups of people No -- who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No --

4. Production of solid wastes during construction or operation or decommissioning (MT/month):

Details thereof (with approximate quantities / Sr. Information/Checklist Yes / rates, wherever possible) with source of No. confirmation No information data 4.1 Spoil, overburden or mine No Not applicable. wastes 4.2 Municipal waste (domestic Yes Total solid waste Generation:1036 Kg/Day and or commercial wastes) 4.3 Hazardous wastes (as per No Being a construction project, no Hazardous Waste Hazardous waste Management is expected. Rules) 4.4 Other industrial process wastes No -- 4.5 Surplus product No -- 4.6 Sewage sludge or other sludge Yes Dried sludge from STP will be used as manure for from effluent treatment. the plants. 4.7 Construction or demolition No - wastes. 4.8 Redundant machinery or No -- equipment. 4.9 Contaminated soils or other No -- materials. 4.10 Agriculture wastes. No -- 4.11 Other solid wastes. No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data

Form1 Grenesis Constro Pvt.Ltd.

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 5.1 Emissions from combustion of Yes D.G. Sets as per CPCB norms will be used during fossil fuels from stationary or power failure. mobile sources 5.2 Emissions from production No - processes 5.3 Emissions from materials handling Yes Fugitive dust emission due to handling and including storage or transport loading/unloading expected during construction. Frequent water sprinkling will be done to minimize the fugitive emissions 5.4 Emissions from construction Yes The project may cause rise in dust levels during activities including plant and construction phase. Precautions would be taken to equipment reduce dust generation during construction phase: Use of RMC will eliminate the handling of cement, sand and concrete thus dust emission will be minimized. Water sprinkling will be done at regular intervals to reduce control of dust generation. 5.5 Dust or odours from handling of Yes Dust generation will be controlled as described materials including construction above. materials, sewage and waste Proper ventilation will be provided around STP. 5.6 Emissions from incineration of No -- waste 5.7 Emissions from burning of waste No -- in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No --

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 6.1 From operation of equipment Yes During construction phase vibration & noise e.g. engines, ventilation plant, pollution may occur, necessary precaution shall crushers. be taken at source, along path & at receptor. 6.2 From industrial or similar No - processes. 6.3 From construction or Yes During construction phase vibration & noise demolition. pollution may occur, necessary precaution shall be taken at source, along path & at receptor 6.4 From blasting or piling. No -- 6.5 From construction or operational Yes There will be transport of materials for traffic. construction work. Precautions will be taken to reduce the impact of the vehicular movement such as vehicular trips will not be at peak traffic hours. 6.6 From lighting or cooling No -- systems. 6.7 From any other sources. No --

Form1 Grenesis Constro Pvt.Ltd.

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea :

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No - spillage of hazardous materials.

7.2 From discharge of sewage or No Sewage will be reused for flushing and gardening other effluents to water or the within the premises. Excess treated sewage will be land (expected mode and disposed to sewer line. place of discharge).

7.3 By deposition of pollutants No emitted to air into the land or into water. 7.4 From any other sources. No - 7.5 Is there a risk of long term No - build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment :

Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, No -- fires etc from storage, handling, use or production of hazardous substances 8.2 From any other causes. No -- 8.3 Could the project be affected Yes On site/ Off site Emergency Plan shall be prepared by natural disasters causing in consultation with Local body, NGO’s, environmental damage (e.g. Stakeholders. floods, earthquakes, landslides, cloudburst)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality:

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of supporting facilities, ancillary development or development stimulated by the Form1 Grenesis Constro Pvt.Ltd.

Sr. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data project which could have impact on the environment e.g.: •Supporting infrastructure (roads, power supply, waste or waste water Yes Project will help for Infrastructure augmentation. treatment, etc.) • housing development • extractive industries • supply industries • other

9.2 Lead to after-use of the site, which No -- could have an impact on the environment 9.3 Set a precedent for later Yes Will create job opportunity for support staff like developments Security, Maintenance, household workers etc. 9.4 Have cumulative effects due to Yes Impacts on water availability, storm water proximity to other existing or drainage, availability of electricity, traffic planned projects with similar congestion etc. effects

(II) Environmental Sensitivity Sr. Areas Name/ Aerial distance (within 15 km.) No. Identity from Proposed project location boundary 1 Areas protected under international NO - conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or No - sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, important or No - sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or No - underground waters 5 State, National boundaries No - 6 Routes or facilities used by the public Sinhagad Road Approx 0.06 km for access to recreation or other tourist, pilgrim areas 7 Defence installations 8 Densely populated or built-up area Yes Pune

Form1 Grenesis Constro Pvt.Ltd.

Sr. Areas Name/ Aerial distance (within 15 km.) No. Identity from Proposed project location boundary 9 Areas occupied by sensitive man- No - made land uses (hospitals, schools, places of worship, community facilities) 10 Areas containing important, high No -- quality or scarce resources (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution No -- or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard No -- which could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

Form1 Grenesis Constro Pvt.Ltd.

Form1 Grenesis Constro Pvt.Ltd.

LIST OF RAW MATERIALS

Sr.No. Name Units

1 Cement bags

2 White Cement bags

3 Steel Metal tonnes

4 Metal cuft

5 Sand cuft

6 Bricks/siporex no.

7 Binding wire kg.

8 Tiles Granite/Marble sq.ft

9 Paint lts

10 Plaster sq.mtrs

11 Wood kg.

12 Aluminium kg.

FORM-1 A

1 LAND ENVIRONMENT Attach panoramic view of the project site and the vicinity 1.1 Will the existing landuse get  Being in a Residential Zone of PMC division, No significantly altered from the Change in Existing Land Use project that is not consistent  Google Image & Google Map – Annexure 3 with the surroundings?  Google Image with 500m Radius Annexure 4 (Proposed landuse must  Contour Plan Annexure-5 conform to the approved Master Plan/ Development Plan of the area. Change of landuse if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location (ii) (ii) surrounding features of the proposed site (within 500 meters) (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans 1.2 List out all the major project  Area of Plot: 10,120.00 m2 requirements in terms of the  B/up Area :- 7040.25 m2 land area, built up area, water  Total Construction: 26,432.28 m2. consumption, power  Water Consumption :204 KLD requirement, connectivity,  Power Requirement :- Adequate power will be community facilities, parking supplied as per requirement needs etc  Connectivity :-  Nearest Airport : Lohegaon 16.46  Nearest Railway Station :- 6.39 Km. ,  Nearest Highway : Mumbai Pune Highway NH-4  Community Facility: - Amenity and Open Space will be provided as per Local Rules.  Parking Needs :- As per Development Control Rules of Local Authority 1.3 What are the likely impacts of Significant impact expected without mitigation. the proposed activity on the Hence, adequate measures are proposed to mitigate existing facilities adjacent to negative impacts on community facilities. the proposed site? (Such as

open spaces, community facilities, details of the existing landuse, disturbance to the local ecology). 1.4 Will there be any significant No, there will not be any significant land disturbance. land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given). 1.5 Will the proposal involve No, the proposal won’t involve alteration of natural alteration of natural drainage drainage systems. systems? (Give details on a contour map showing the natural drainage near the proposed project site) 1.6 What are the quantities of Top Soil Preservation:- Retained for Landscape earthwork involved in the Refilling: - for Plinth and Back Filling construction activity-cutting, Reuse :- for Sub-Base Work of Internal Road filling, reclamation etc. (Give Balance will disposed to authorized Land Fill Site details of the quantities of earthwork involved, transport of fill materials from outside the site etc.) 1.7 Give details regarding water Potable water shall be arranged as per requirement. supply, waste handling etc Solid waste will be handed over to Authorised during the construction period contractor for proper disposal. 1.8 Will the low lying areas & No wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity) 1.9 Whether construction debris & No waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal) 2 WATER ENVIRONMENT 2.1 Give the total quantity of water Sr. Description Quantity of Source of requirement for the proposed No water water supply project with the breakup of required requirements for various uses. m3/day How will the water 1. Operation phase requirement met? State the a. Domestic 204 Local body sources & quantities and purpose furnish a water balance b. Flushing 104 Treated statement purpose water from STP c. Gardening 5 Treated purpose water from STP Total 314 Total water requirement = 314 Treated sewage available for recycling = 240 After recycling treated sewage for gardening (5) and flushing (104) Net water requirement = 204 Source: From Local body

From local body = 204

Flushing = Gardening = 5 Domestic- 204 104

Total sewage=267 5 Recycled: Recycled: 104 104 Recycled: treated sewage available 240 li 608

Excess treated sewage 131 will be drained to the sewer line.

All quantities are in m3/day 2.2 What is the capacity Required water supply from the local authority.. (dependable flow or yield) of the proposed source of water? 2.3 What is the quality of water Drinking water quality of Class A as per Indian required, in case, the supply is Standard (2296 -1982) shall be maintained. not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality) 2.4 How much of the water Total treated water available for recycled water: requirement can be met from 385m3/day the recycling of treated Secondary requirements met: wastewater? (Give the details  Flushing :- 104 KLD of quantities, sources and  Gardening :- 5 KLD usage) Excess treated waste water shall be disposed off to the external sewer line. 2.5 Will there be diversion of No water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption) 2.6 What is the incremental No increase in pollution load as wastewater shall be pollution load from wastewater treated to MPCB standards. About 373m3/day generated from the proposed treated wastewater will be recycled and during activity? (Give details of the monsoon balance shall be disposed off to existing quantities and composition of sewer line. wastewater generated from the no. details values units proposed activity) untreated treated 1. pH 6.5 – 8.5 6.5 – 7.5 2. Total 150-200 <10 mg/lit Suspende d solids 3. Chemical 350-450 <30 mg/lit Oxygen Demand 4. BOD 200-250 <10 mg/lit 5. Oil & 10-15 <5 mg/lit Grease 2.7 Give details of the water Water harvesting system will be installed and the requirements met from water harvested water will be used to recharge the ground harvesting? Furnish details of water. the facilities created. 2.8 What would be the impact of Total Runoff from the project site: Prior to the land use changes occurring Development = 0.03 m3/sec due to the proposed project on Total Runoff from the project site: After the runoff characteristics Development = 0.16 m3/sec (quantitative as well as (Considering different coefficients for paved area, qualitative) of the area in the unpaved area, podium and terrace) post construction phase on a Hence Incremental Run off = 0.13m³/sec. long term basis? Would it Capacity of storm water drains is sufficient to take aggravate the problems of the runoff from the site. flooding or water logging in It is proposed to recharge the rain water through any way? recharge pits. The overflow of SWD shall be taken to the discharge into storm water drain. 2.9 What are the impacts of the  Ground water table will increase due to proposed proposal on the ground water? recharge pits/Bores. (Will there be tapping of  There will not be ground water tapping. ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any) 2.10. What precautions/measures  Proper material stacking and storage will be are taken to prevent the maintained during rainy season run-off from construction  Proposed to channelize the run off in to impervious activities polluting land & pit for storage and use. aquifers? (Give details of  During heavy rainfall, run-off will be drained to the quantities and the measures nearest storm water drain. taken to avoid the adverse impacts) 2.11 How is the storm water from Internal storm water drains will be constructed in within the site managed?(State accordance to regulations. The storm water collected the provisions made to avoid through the storm water drains shall be diverted to flooding of the area, details of recharge pit. the drainage facilities provided along with a site layout indication contour levels) 2.12 Will the deployment of During construction phase, toilets with connection construction laborers to external sewers shall be created to keep hygienic particularly in the peak period conditions at site. lead to unsanitary conditions Regular segregation and disposal of solid waste around the project site (Justify shall be done. with proper explanation) First aid and medical facilities will be provided to all workers. Proper housekeeping will be maintained throughout the premises. 2.13 What on-site facilities are  Wastewater generation:- 267 m3/day provided for the collection,  Treatment capacities with technology: 300 m3. treatment & safe disposal of MMBR Technology sewage? (Give details of the  Facilities for recycling: Flushing, Gardening quantities of wastewater  Disposal: generation, treatment capacities (a): Sludge40.05 Kg/day – Use as manure with technology & facilities for (b): Surplus Treated waste water: - 373 m3/day, recycling and disposal) Disposed off as per SPCB norms. 2.14 Give details of dual plumbing  Recycling of treated sewage for flushing with dual system if treated waste used is plumbing and gardening. used for flushing of toilets or  Color coding for dual plumbing system shall be any other use. done as per standard practices 3. VEGETATION 3.1 Is there any threat of the There is no threat to the biodiversity due to the project to the biodiversity? project under reference. (Give a description of the local ecosystem with its unique features, if any) 3.2 Will the construction involve No tree cutting. extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project) 3.3 What are the measures Project proponents have proposed indigenous proposed to be taken to species plantation on ground and on the periphery minimize the likely impacts on of the project site. important site features (Give (Refer Annexure 5) details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale) 4. FAUNA 4.1 Is there likely to be any No displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details. 4.2 Any direct or indirect impacts No on the avifauna of the area? Provide details 4.3 Prescribe measures such as Not Applicable corridors, fish ladders etc to mitigate adverse impacts on fauna 5 AIR ENVIRONMENT 5.1 Will the project increase No perceptible change is anticipated in AAQ due to atmospheric concentration of Project as it being a residential development. AAQ gases & result in heat islands? was monitored during April 2015 and values are (Give details of background air given in quality levels with predicted Table.: Average AAQ around the Project Site values based on dispersion Period: April 2015 models taking into account the increased traffic generation as Monitoring PM10 SO2 NOx a result of the proposed Station µg/m3 µg/m3 µg/m3 constructions) Base station: Project 89 38 27 Site 5.2 What are the impacts on During construction phase, air borne dust, is the generation of dust, smoke, main pollutant, which may be generated during odorous fumes or other construction activities. Other emissions, SO2 NOx hazardous gases? Give details and CO, due to vehicular movement, construction in relation to all the machinery, etc are expected. However, it will be meteorological parameters temporary. Proper upkeep and maintenance of vehicles, sprinkling of water on roads and construction site are some of the measures that would reduce the impact of dust during construction phase. Sources of Air pollution during Operational phase  The gaseous emissions from vehicles.  Emissions from DG set Mitigation Measures:  The traffic congestion will be avoided by proper parking arrangement.  Regular PUC checkup for vehicles.  CPCB specs DG sets with tall stack. DG set will be maintained properly. 5.3 Will the proposal create No. Off Street Parking within Project Site will shortage of parking space for propose as per Prevailing Development Control vehicles? Furnish details of the Regulations. present level of transport . infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site 5.4 Provide details of the Refer Annexure 5 Master layout indicating Traffic movement patterns with Movement Plan. internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category 5.5 Will there be significant Insignificant increase in noise level during increase in traffic noise & construction period is expected but it will be for short vibrations? Give details of the duration. Post construction, no increase in Noise level sources and the measures is expected. proposed for mitigation of the above 5.6 What will be the impact of DG D.G. Sets with inbuilt acoustic enclosures and roof sets & other equipment on top discharge meeting CPCB specs will be noise levels & vibration in & installed. Hence no increase in Noise or vibration is ambient air quality around the expected. project site? Provide details Tree plantation would act as noise barrier and will reduce the noise level. 6. AESTHETICS 6.1 Will the proposed No constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents? 6.2 Will there be any adverse No impacts from new constructions on the existing structures? What are the considerations taken into account? 6.3 Whether there are any local No, there are no such local considerations. considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out 6.4. Are there any anthropological No such site in the vicinity. or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered. 7. SOCIO-ECONOMIC ASPECTS 7.1 Will the proposal result in any Yes, Expected Population: 2340 Nos. changes to the demographic Will give rise to enhancement in economic structure structure of local population? of the area. Provide the details. 7.2 Give details of the existing Schools: social infrastructure around the Gurukul School:4.49 kms proposed project. St.Vincents High School:6.94 kms Hutchings High School & Junior College:6.76 kms Vidya Bhavan School:6.64 kms Colleges: Maharashtra Institute of Technology:4.91 kms Yashwantrao Mohite college of Arts & Science:4.25 kms Sir Parshurambhau college:4.43 kms Hospitals: Deenanath Mangeshwar Hospital:3.25 kms Poona Hospital & Research Centre:4.25 kms Sahyadri Hospital :4.39 kms Pune Adventist Hospital:5.37 kms 7.3 Will the project cause adverse No effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed? 8. BUILDING MATERIALS 8.1 May involve the use of No, building materials with high- Pozolona Cement with 15% ash shall be used. embodied energy. Are the Construction materials from nearest source are chosen construction materials to minimize energy consumption for transportation. produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency) 8.2 Transport and handling of  The construction material will be brought in materials during construction covered vehicles. may result in pollution, noise  All the contractors/Vendors will be instructed to & public nuisance. What use PUC certified vehicles. measures are taken to minimize  Security staff will supervise loading/ unloading of the impacts? material.  Construction material will be stored at identified area & temporary godowns.  Plot will be cordoned by 5 m tall tin sheets. Regular water sprinkling will be done on internal roads. 8.3 Are recycled materials used in Yes, Excavated earth and debris will be used as base roads and structures? State the for road. extent of savings achieved? 8.4 Give details of the methods of  Segregation of biodegradable and non collection, segregation & biodegradable shall be done at source by having disposal of the garbage two garbage bins with different color. generated during the operation  The non biodegradable garbage shall be handed phases of the project over to Authorized Agency for disposal.  Biodegradable garbage shall be treated in proposed composting machine. 9. ENERGY CONSERVATION 9.1 Give details of the power Power Requirement: Adequate power will be requirements, source of supply, supplied as per requirement backup source etc. What is the Following Energy conservation measures are energy consumption assumed proposed for Energy Saving : per square foot of built-up  Energy efficient light fittings like CFL, T5 Lamps area? How have you tried to & LED Lights. minimize energy consumption?  Water Level Controllers with Timers will be used for Water Pumps.  Auto Timer Switches will be provided for Street lights, Garden lights, Parking & staircase Lights & Other Common Area Lights, for saving electrical energy.  CFL & LED based lighting will be done in the common areas, landscape areas, signage’s, Entry gates and boundary compound walls etc.  Solar lights will be provided for common amenities like Street lighting & Garden lighting.  Solar Water Heating Systems Will Be Done For Bathrooms.  Annual Savings with energy efficient equipments is 2 to 4 % 9.2 What type of, and capacity of, DG Set of required capacity will be used. power back-up to you plan to provide? 9.3 What are the characteristics of Single glazed glass will be used. the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation? 9.4 What passive solar Maximize the use of natural lighting through design. architectural features are being Roof insulation. The recommended U-factor for roof used in the building? Illustrate shall be 0.409 W/m2 0C. the applications made in the proposed project. 9.5 Does the layout of streets & No buildings maximise the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details. 9.6 Is shading effectively used to Design is based on passive architectural reduce cooling/heating loads? considerations What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected? 9.7 Do the structures use energy- Yes. efficient space conditioning, Following Energy conservation measures are lighting and mechanical proposed for Energy Saving : systems? Provide technical  Energy efficient light fittings like CFL, T5 Lamps details. Provide details of the & LED Lights. transformers and motor  Water Level Controllers with Timers will be Used efficiencies, lighting intensity for Water Pumps. and air-conditioning load  Auto Timer Switches will be provided for Street assumptions? Are you using lights, Garden lights, Parking & staircase Lights & CFC and HCFC free chillers? Other Common Area Lights, for saving electrical Provide specifications. energy.  CFL & LED based lighting will be done in the common areas, landscape areas, signage’s, Entry gates and boundary compound walls etc.  Solar lights will be provided for common amenities like Street lighting & Garden lighting.  Solar Water Heating Systems Will Be Done For Bathrooms. 9.8 What are the likely effects of No impact anticipated on micro-climate. No inversion the building activity in altering or heat island effect expected. the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects? 9.9 What are the thermal  Roof insulation for all the spaces. 2 0 characteristics of the building  The U-factor for roof shall be 0.409W/m - C and envelope? (a) roof; (b) external 0.44 W/m2-OC for walls walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components. 9.10 What precautions & safety  Refuge area at 24th meter level. measures are proposed against  Fire staircase with fire doors. fire hazards? Furnish details of  Under Ground Water Tank of 1, 50,000 emergency plans Liter capacity reserved for Fire Fighting.  Overhead water tank of 20,000 liter reserved capacity over each building.  6” Dia. Down comer with hose reel drum and Hydrant valve at each floor level.  Booster Pump at terrace level for each building.  Fire service inlet with hydrant valve at parking level.  Public address system with talk back system at each floor.  Portable Fire extinguishers at required locations.  Court yard hydrant system with pumps.  Entire fire system is provided with DG back up. 9.11 If you are using glass as wall Glass shall be used only for windows. material provides details and specifications including emissivity and thermal characteristics. 9.12 What is the rate of air Design is based on Passive Architectural infiltration into the building? Considerations and Features. Provide details of how you are mitigating the effects of infiltration 9.13 To what extent the non- Provision of Solar for Garden area lighting will conventional energy reduce for 20% of Energy Consumption. technologies are utilised in the overall energy consumption? Provide details of the renewable energy technologies used. 10. ENVIRONMENT EMP would consist of mitigation measures for MANAGEMENT PLAN environmental attributes viz, air, water, noise, etc The Environment Management to minimize the anticipated impacts during the Plan would consist of all construction and operation phase of the project. mitigation measures for each It would also delineate the monitoring program to item wise activity to be comply with environmental regulations. This will undertaken during the also include the action to be taken in case of construction, operation and the emergency such as accidents at the site including fire. entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire . ENVIRONMENTAL IMPACTS AND MANAGEMENT PLAN EMP for Construction Phase Attribute Construction Phase 1. Water Regime  Install water meters, take readings routinely, record in the register and check to avoid water wastage. If wastage is more report to the management for caution & correct  To provide septic tanks to the construction workers and staff on site and to look after its operational & maintenance, take periodical sample to asses the quality, record & report for any abnormality & rectification.  Potable water will be provided for workers and staff.  Keep a daily watch to avoid sanitation / drains, & good housekeeping.  Sedimentation of outside drains avoided by using screens and silt traps.  To examine proper management of channelization of water to avoid water logging at site. 2. Air  Ensure water sprinkling for dust suppression will be used during excavation and the record for the same will be keep and report will be  submitted to management.  Ensure the use of covering sheets, on the material being transported incoming or outgoing or stored. Make adequate arrangement for such sheets by anticipations.  Arrange use of ready mix concrete (RMC) through concrete batching at a place secluded, barricaded by trees and precautions taken of dust suppression by sprinkling. Logbooks to be maintain for journey of the RMC trucks. When the trucks are washed, ensure that the waste water send for reuse or treatment.  For use as backup power DG sets to be procured from renowned suppliers with acoustic enclosures and foundation is to be laid as per suppliers specification as per CPCB norms for its stack height.  Adequacy of parking provision will be provide near project site and proper traffic arrangement for the construction vehicles including instance of their PUC.  Labour camp will be arrange away from project site and to be instructed that open burning of solid waste will be prohibited.  Prepare in consultation with sub contractors, a list for regular weekly checkup of the workers and keep its record including any remediation steps if necessary.  Use of the standard personal protective equipments like -mask and other personnel gazettes like goggles, gum boots & helmets for workers. 3. Solid Waste  Segregated garbage will be handed over to Authorized contractor. Of PMC  Proper covering for to prevent damages due to water seepages at godowns especially Cement, Plywood etc  The contractors should collect the empty drums of paints, pesticides & tubes at one place & send to authorized CHWTSDF site. Include this condition in the agreement to be signed as it is his responsibility. 4. Noise  Location for Noise level monitoring will be done as per MPCB norms  Noise level monitoring will be done daily.  To make provision of ear plugs for construction labour and staff & insist its use.  There shall be no noisy work in night shift.  To ensure Provision of barricades along the periphery of the site  To obtain guidance from the suppliers & maintain acoustic enclosure for DG sets. 5. Soil & Greening  Anticipate where the excavation is going to commence and in advance take a laboratory test of its top soil to ensure whether it is capable to support tree plantation.  The excavated material will kept at project by covering polyethylene sheets.  Avoid excavation during high winds and heavy monsoon day.  Make proper calculation as to where this excess excavation should be used either within the premises or off site or as disposal. This to be quantified in consultation with subcontractor in advance.  Anticipate the rains and see that no water logging takes place as also a need to keep traps on storm water drain.  Sapling will be purchase from nursery and planted along project site boundary. Regular watering will be done. 6. Socio  During Initial Phase of the project ,information Economics regarding the proposed development plan should be communicated to the local community in the form of booklets and posters on road at various location of Pune city  Provision of adequate drinking water, toilet and bathing facilities should be made available on project site for construction labours.  Water shall be sprinkle/spread to suppress dust during construction phase to control air pollution and thereby avoid adverse health impact  Proper living condition with appropriate facilities for residential labours should be provided  Proper Training and awareness programme should be carried out so that the workers understand the importance of wearing the personal protective equipments.  First aid and medical facilities  Arrangement of Day care facility/crèche  Proper precaution to prevent any accident.  Provision of mask to workers that can prevent inhalation of dust.

Note: Environmental monitoring plan will be prepared based on Environmental Management Plan. All environmental parameters will be studied as and when required and based on analysis result mitigation measures will be implemented.

Environmental Management Plan for Hazardous Waste Generation Construction Phase: Sr. Source of Hazardous Mitigation Measures No. Waste Generation 1 Leakages and spillage oil or Contaminated soil if any shall be disposed off to fuel Authorized Disposal Site. * Bituminous materials /any other chemicals shall not be allowed to leach into the soil. Operational Phase: 1 Residual Paints/Solvents --do-- 2 Waste Oil from D.G Sets Waste oil will be handed over to authorized recyclers. Other hazardous wastes, if any, shall also be handled in the similar way through authorized dealers only.

G+3

G+3 HOTEL BRAMHA PURE-VEJ

G+3

OMKAR APARTMENT G+3

S.NO.391

SURVEYORS AND ENGINEERING CONSULTANTS Pvt. Ltd.

DATE : 10/02/2012 PATH : G\JOB2011\DWG\913 .Dwg

DWG. NO : 1 REV.NO. - R0 CHECKED BY : Ms..PRADNYA