Begin ROW/Easement Acquisition: October 2020 The Hungary Road Sidewalk project will infill Pedestrian signals and crosswalks will be Total Cost: $ 1,854,000 Advertisement: September 2022 sidewalk to provide pedestrian connectivity incorporated into the existing traffic signalization Preliminary Engineering: $ 414,000 along this urban minor arterial roadway at the intersections with Staples Mill Road and Right of Way/Utilities: $ 100,000 Begin Construction: January 2023 improving safety, convenience, and accessibility Hungary Spring Road. Construction: $ 1,340,000 Project Completion: January 2024 for pedestrians .
A total of approximately 390 feet of 4-foot and These estimated costs are subject to change.
5-foot sidewalk with ADA ramps will be * Final lane configuration subject to change constructed on the north side of Hungary Road This project will be funded with State Revenue Representatives from the County are present between Hastings Way Drive and Big Tree Lane Sharing funds and Local Funds. to discuss the project and answer your and approximately 3,400 feet of 4-foot and 5- questions. It is the responsibility of the foot sidewalk with ADA ramps will be County to ensure that all members of the
community are afforded the opportunity to constructed from Mountain Cove Court to provide comments and participate in public Hungary Spring Road. decisions on transportation projects affecting The County has hired AMT Engineering to review them. The County ensures nondiscrimination the social, economic and environmental impacts in all programs and activities in accordance of the project on the local community and the with Title VI of the Civil Rights Act of 1964. surrounding area. The project is being
HUNGARY ROAD SIDEWALK IMPROVEMENTS coordinated with the appropriate federal, state, and local agencies. As a result of this review, a determination will be made concerning the construction impacts of the project. We anticipate this will result in a finding of no Displays at this meeting show the extent of right- significant impact. of-way that may be needed as the project is
currently proposed. As the design is further
New Sidewalk During construction, all reasonable efforts will be developed, additional easements and right-of-
made to protect the environment with respect to way may be required beyond what is shown on the preliminary plans. Property owners will be dust control, siltation and erosion. Construction informed of the exact location of any needed will conform to Henrico County specifications easements and/or right-of-way during the and special provisions and the Virginia Department of Soil and Water Conservation acquisition process and prior to construction. regulations.
Existing Sidewalk
New Sidewalk
The public comment period will close on Project information shared here will be available Citizen Information Meeting September 4, 2020, following this citizen for review after the citizen information meeting Henrico County Hungary Road Sidewalk information meeting. County representatives at https://henrico.us/project/hungary-sw/ Wednesday, August 19, 2020, 5:00 p.m. - 6:00 p.m. will review and evaluate any information online. Glen Allen Library received as a result of the citizen information 10501 Staples Mill Road Glen Allen, VA 23060 meeting. Comments can also be submitted in writing
through e-mail to Steve Bandura Right-of-way and easement acquisition is ([email protected]); online survey link at expected to begin in late 2020 and https://henrico.us/projects/hungary-sw/ or construction is anticipated to begin in early USPS mail to the contact address below. 2023. Information must be postmarked, emailed, or Welcome to the County of Henrico Department A comment sheet is included in the handout for this delivered to the County of Henrico by September of Public Works citizen information meeting for meeting and your input is encouraged. All
4, 2020 in order to be included in the Citizen the Hungary Road Sidewalk project. comments received on this project will be reviewed
Information Meeting record. and responded to in writing.
This meeting is being held to give citizens and
organizations an opportunity to comment on the Primary Contact: proposed project. The County strives to ensure Henrico County DPW Capital Projects Steve Bandura, P.E. P. O. Box 90775 (804) 501-5985 that all members of the community have the Manager County of Henrico Henrico, VA 23273-0775 opportunity to provide feedback and participate in public decisions on transportation projects Henrico County DPW affecting them. Sharon Smidler, P.E. Transportation P.O. Box 90775 (804) 501-4393 County of Henrico Division Director Henrico, VA 23273-0775
Anticipated Cost: Approximately $1,800,000
Purpose: – To provide improved pedestrian access From: Hardings Way Drive To: Hungary Spring Road Total length of sidewalk: 0.72 miles Improvements: Incorporate new sidewalk and ADA compliant curb ramps on the north side of Hungary Road and pedestrian signal improvements at the intersections
Existing Hungary Road future sidewalk location. with Staples Mill Road and Hungary Spring Road.