SFG1801 V5 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Natural Gas Lines to The Egyptian Natural Gas Company Thermal Power Plant Mahmoudya Power Plant Pipeline (As part of North Savings)

Resettlement Action Plan

Public Disclosure Authorized Prepared By: December 2016

Final Report

Page 1 of 147 RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table of Contents

TABLE OF CONTENTS ______2 LIST OF TABLES ______5 LIST OF FIGURES ______6 LIST OF ACRONYMS AND ABBREVIATIONS ______7 1 EXECUTIVE SUMMARY ______8

INTRODUCTION ______8 RESETTLEMENT IMPACT ______10 POLICY, LEGAL AND INSTITUTIONAL FRAMEWORK ______12 VALUATION AND COMPENSATION ______13 PLANNING FOR LAND ACQUISITION ______13 INSTITUTIONAL ARRANGEMENT ______13 SOCIOECONOMIC SCOPE OF IMPACTS ______14 CONSULTATION, DISCLOSURE AND GRIEVANCES ______14 MONITORING ARRANGEMENT ______15 BUDGET AND TIME PLAN ______15 2 PROJECT DESCRIPTION ______17

2.1 PROJECT OVERVIEW ______17 2.2 DESCRIPTION OF PROJECT ACTIVITIES ______19 2.2.1 Valve Rooms ______19 2.2.1 Pressure Reduction Station (PRS) ______20 2.2.2 Activities of the Construction Phase ______20 2.3 DESCRIPTION OF THE PROJECT AREAS ______21 2.4 AVOIDANCE MECHANISM ______21 3 RESETTLEMENT IMPACTS ______23

3.1 IMPACTS DURING CONSTRUCTION ______23 3.1.1 Permanent land acquisition ______23 3.1.2 Temporary land acquisition______24 3.1.3 Temporary loss of assets ______25 3.2 IMPACTS DURING OPERATION ______26 3.3 VULNERABLE GROUPS ______26 4 SOCIO-ECONOMIC SURVEY ______30

4.1 FINDINGS OF THE CENSUS SURVEY ______30 4.1.1 Methodology of the Inventory of Affected Persons ______30 4.1.2 Findings of the census survey ______30 5 LEGISLATIVE AND REGULATORY FRAMEWORK______32

5.1 INTRODUCTION ______32 5.2 POLICY REFERENCES ______32 5.3 RELEVANT EGYPTIAN LEGISLATIONS FOR THE INVOLUNTARY RESETTLEMENT ______32 5.4 GAPS BETWEEN EGYPTIAN REGULATIONS AND WORLD BANK POLICIES ______33 6 VALUATION AND COMPENSATION ______34

6.1 ELIGIBILITY CRITERIA ______34

Page 2 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6.2 VALUATION OF CROPS/ASSETS ______34 6.2.1 Crop Valuation ______34 6.2.2 Temporary Loss of uncultivated land ______35 6.2.3 Temporary acquisition of land for storing construction material ______35 6.2.4 Asset Valuation ______35 6.3 ARRANGEMENT FOR DELIVERING OF COMPENSATIONS ______36 6.4 TRANSITIONAL SUPPORT ______37 6.5 ARRANGEMENTS FOR RECALCULATION OF COMPENSATION IN CASE OF PROLONGED DELAY IN DELIVERY OF COMPENSATION 37 7 INCOME AND LIVELIHOOD REHABILITATION MEASURES ______38

7.1 DISCUSSION OF MEASURES OF LIVELIHOOD AND INCOME REHABILITATION MEASURES ______38 8 INSTITUTIONAL ARRANGEMENTS ______39

8.1 INSTITUTIONAL RESPONSIBILITIES FOR THE RAP IMPLEMENTATION ______39 8.1.1 Organizational Setup ______39 8.2 INSTITUTIONAL ROLES IN GASCO COMPENSATION SYSTEM ______39 8.3 IMPLEMENTATION TIMETABLE ______41 8.3.1 Implementation Sequence______41 8.3.2 Time Schedule and the Cut-off Date ______42 9 BUDGET AND FUNDING ARRANGEMENTS ______44 9.1.1 Estimation of Total Temporarily Land Acquisition Cost ______44 9.1.2 Compensation amount ______44 9.1.3 Fund Flow and Payment Plan ______46 10 CONSULTATION, DISCLOSURE AND GRIEVANCE MECHANISM ______47

10.1 INTRODUCTION ______47 10.2 CONSULTATION ACTIVITIES ______47 10.2.1 Consultation Activities during Site Investigation ______48 10.2.2 Consultation Activities During preparation of the ESIA and RAP studies ______49 10.2.3 Consultation Activities during Preparation of the RAP ______52 10.2.4 Further Planned Consultation activities ______57 10.3 DISCLOSURE OF THE RAP ______58 10.3.1 Information Disclosure during Preparation Phase ______58 10.3.2 RAP Disclosure after Bank Clearance ______59 10.3.3 Information Disclosure during Implementation Phase______59 10.4 GRIEVANCE MECHANISM ______59 10.4.1 Institutional Responsibility for Grievances ______59 10.4.2 Grievance tiers ______60 10.4.3 Grievance channels ______61 10.4.4 Response to grievances ______61 10.4.5 Monitoring of grievances ______61 11 MONITORING ARRANGEMENTS ______63

11.1 GENERAL MONITORING BY GASCO ______63 11.2 INTERNAL MONITORING ______64 11.3 EXTERNAL MONITORING AND EVALUATION ______64 12 ENTITLEMENT MATRIX ______66 ANNEXES ______69

Page 3 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

ANNEX 1: NAMES OF PROJECT AFFECT PERSONS ______69 ANNEX 2: CROP PRICES LIST FROM BEHEIRA AGRICULTURAL DIRECTORATE ______108 ANNEX 3: LEGAL FRAMEWORK GOVERNING THE PROJECT ______109 ANNEX 4: GRIEVANCE FORM ______113 ANNEX 5: NAMES OF PARTICIPANTS IN THE CONSULTATION ACTIVITIES ______114 ANNEX 6: QUESTIONNAIRE SHEET ______145 ANNEX 7: DUE DILIGENCE REPORT OF THE LAND ACQUISITION OF THE ASSOCIATED FACILITIES ______147

Page 4 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

List of Tables Table 1-1 - Summary of needed budget for comepsnations ...... 15 Table 2-1 - Poverty and income description of surrounding villages (Income and Expenditure Survey, CAPMAS, 2013) ...... 21 Table 3-1 – Mahmoudya Power Plant Pipeline Summary of Resettlement Impacts – OP 4.12 ...... 28 Table 4-2 - Distribution of affected land by types of crops ...... 31 Table 6-1- Prices provided by the agricultural directorate in Beheira, 2015 ...... 35 Table 4-3 -Summary of the proposed price for the affected assets ...... 36 Table 8-1 - Institutional roles in the GASCO compensation system ...... 39 Table 9-2 - Total cost and budget in EGP ...... 45 Table 10-1 - Summary of the conducted consultation activities ...... 47 Table 10-2 - Participants in the scoping session ...... 49 Table 10-3 - Distribution of Participants in the Public Consultation ...... 50 Table 10-4 - Key comments and concerns raised during the scoping session ...... 50 Table 10-5 - Key comments and concerns raised during the public consultation session ...... 54 Table 10-6 - Summary of Proposed negotiation process with PAPs ...... 57 Table 11-1 - Examples of the Proposed Indicators Needed for Monitoring Activities ...... 65 Table 12-1 – Mahmoudya Power Plant pipeline project compensation entitlement matrix ...... 67

Page 5 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

List of Figures Figure 1-1 First pipeline location and route ...... 9 Figure 1-2 Location and route of the first pipeline (continued) and the second pipeline ...... 9 Figure 1-3 Location and route of the second pipeline (continued) and the third pipeline ...... 10 Figure 1-4 Location and route of the last part of the first pipeline ...... 10 Figure 2-1 First pipeline location and route ...... 18 Figure 2-2 Location and route of the first pipeline (continued) and the second pipeline ...... 18 Figure 2-3 Location and route of the second pipeline (continued) and the third pipeline ...... 19 Figure 2-4 Location and route of the last part of the first pipeline ...... 19 Figure 3-1 - Location of the Valve rooms ...... 24 Figure 10-1 - Photos during the field work ...... 53 Figure 10-2 - Grievance Form ...... 62

Page 6 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

LIST OF ACRONYMS AND ABBREVIATIONS CAPMAS Central Agency for Public Mobilization and Statistics CBOs Community-based Organizations CDA Community Development Association EA Environmental Assessment EDHS Egyptian Demographic and Health Survey EEAA Egyptian Environmental Affairs Agency EGAS EGP Egyptian Pound EIA Environmental Impact Assessment ESIA Environmental and Social Impact Assessment FGD Focus Group Discussion FHH Female Headed Household GASCO Egyptian Natural Gas Company GNPPP Giza North Power Plant Project IR Involuntary Resettlement Km Kilo Meter LDU Local Development Unit LGUs Local Governmental Units MALR Ministry of Agriculture and Land Reclamation NGO Non-Governmental Organization OP Operational Policy PAF Project Affected Family PAP Project Affected Persons PRS Pressure Reduction Station PC Public Consultation PL Poverty Line RAP Resettlement Action Plan ROW Right Of Way RPF Resettlement Policy Framework SRO Social and Resettlement Officer SDO Social Development Officer TOR Terms of Reference WB World Bank

Page 7 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

1 Executive Summary Introduction The proposed project is considered as part of ’s strategy to expand the use of natural gas as a clean source of energy as well as meet the needs of power generation projects. Giza North power project was implemented with assistance of the World Bank. Based on the savings made from this fund, the World Bank received formal request from the government of Egypt to utilize these savings to procure pipelines required for upgrading the natural gas network and supplying natural gas to new and existing power plants.

The aim of the proposed project is to construct and connect natural gas pipelines to Mahmoudya Power Plant1 and therefore the proposed additional scope is considered to be in line with the Giza North Power Plant Project objectives.

The power station is fed by 3 national network lines 42″, 30″, and 16″:

1st Pipeline (42″)

The path starts with a pipeline of 42″ diameter in Rashid Petroleum Company facility area, east to Edko City and nearly parallel to Edko/Damanhour Road, and extends to the south crossing the international coastal road, /Rashid Railway, and Bousily Drain. The pipeline then continues to the south passing through Villages no. 8, 6, and 1, then it crosses Edko Drain. Then, it extends crossing Edko eastern drain, Abu El-Einein drain, AlQamaheen canal, and the French drain till it reaches National Natural Gas Network Facility area, to the north of Bisintaway Village with a total length of 27 km.

2nd Pipeline (30″)

The path starts with 30″ diameter pipeline from a valve room on the 42″ pipeline to the north of Izbat Abdel Razeq and Hommosy. Then, it extends to the east in the agricultural lands parallel to Kom Al Gharaq Canal until it reaches Power Station with a total length of 17 km.

3rd Pipeline (16″)

The path starts from a valve room that will be constructed on Dairut Power Station pipeline, extending in the southern direction for a distance of 2.5 km parallel to high voltage power lines inside agricultural lands. The pipeline then continues its path in the southern east direction for a distance of 2 km also parallel to high voltage power towers, then turns to the east crossing Mahmodia Canal until it reaches the pressure reduction station inside the power station, with a total length of 7 km.

The figure sbelow show the pipeline location and route. In total, there are 48 main crossings. The 1st pipeline intersects with 9 roads, 1 railway, 8 canals, and 9 drains. The 2nd one intersects with 3 roads,

1 Hereinafter the power plant is considered the associated facility for the line, OP 4.12 has also been applied to the power plant and due diligence report is under preparation.

Page 8 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

4 canals, and 6 drains. While, the 3rd pipeline intersects with 3 roads, 2 canals, and 3 drains. Along the whole route, the pipeline will be located underground. The technical details of the pipeline, valve room and pressure reduction station will be presented in the following sub-sections.

Figure 1-1 First pipeline location and route

Figure 1-2 Location and route of the first pipeline (continued) and the second pipeline

Page 9 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Figure 1-3 Location and route of the second pipeline (continued) and the third pipeline

Figure 1-4 Location and route of the last part of the first pipeline

Resettlement Impact The RAP was prepared in compliance with the World Bank Policy OP 4.12 and relevant laws and regulations in Egypt based on detailed census survey, socioeconomic studies and consultations with PAPs.

During construction the project will result in temporary land acquisition. The lands are mainly cultivated with traditional crops. Impacts will also entail cutting the trees in affected areas during Page 10 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline construction. During Operation of the project, the RoW indicated in law number 4/1988. No impacts will occur as a result of the RoW, although some restrictions are normally applied on the land uses of the RoW (2*2 m in urban areas and 6*2 meters) in rural areas from the center of the pipeline), those limitations do not apply on this project .

Limited impact on assets was reported due to the avoidance mechanism adopted by the GASCO which aims at avoiding trees and constructions along the RoW as much as possible.

1. Temporary land acquisition impacts The project will require various types of lands both during the construction and during the operation phases. Following is a summary of the lands required by the project:

 Private owned cultivated areas: 1,133,825 m2

2. Permanent land acquisition impacts - 1st pipeline (42″) . Room 1: inside BP Co. . Room 2: inside Edko Co. and extensions are currently implemented . Room 3: 50 m x 50 m (to be purchased from farmers) . Room 4: inside Abu Hommos Valve Room - 2nd pipeline (30″) . Room 3: 50 m x 50 m (it is the same room 3 in the 42” pipeline) . Room 5: Inside Dairout Power Station - 3rd pipeline (16″) . Room 3: 50 m x 50 m (it is the same room 3 in the 42” pipeline) . A room inside Mahmodia Power Station  Needed areas for the rooms: (50 m x 50 m) = 2500 m2

Pressure Reduction Station will be constructed inside of Mahmoudya Power Station, no land is required.

3. RoW will not necessitate in land acquisition but will cause permanent restriction to the use of the land (2*2 m) in urban areas – (6*2 meters) in rural areas from the center of the pipeline above or near the line for construction or buildings (612,000 m2). The route will not pass across urban areas (no cities or villages) only cultivated areas, hence the restriction of use was considered 12 m along the 51 kms. No impacts related to the RoW will occur as a result of the following: 1. The route will pass across land which is only classified as agriculture land2 (no urban areas and no cities or villages). 2. GASCO consults with the survey department before determining the route to ensure that the land of the route is will not be included into the urban boundaries in the near future.

2 Construction on agriculture land is prohibited by law

Page 11 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3. There will be no restriction on use of the land of the route for this project since the PAP can continue cultivating all kinds of crops and trees3 they are currently cultivating. The only type of trees which is restricted above the gas lines were not observed in the area are the trees with deep roots (e.g. wood trees). 4. In the future, if the land where the pipelines are installed gets into urban boundaries, GASCO purchases the land from the owner. By law, once the land is within urban boundaries, the owner of the land is allowed to use the land for construction purposes. In such cases and in order for GASCO to secure the land where the pipelines are and prevent any activities that may damage the pipelines, GASCO buys the land from the owners at replacement value in line with market prices. This is stipulated under Article 6 and 7 of the Decree number 292 Year 1998 on the executive regulations of Law 4 year 1988. The 2 articles deal with the cases where damages occur to the owner of the land as a result of the implementation of Law 4. GASCO deals with the cases where the land gets into urban boundaries after the pipeline is installed as damage for the owner who should benefit from full market value for his land. In such cases, the affected person approaches GASCO, inform about the case and a new contract is signed for purchasing the land. This kind of arrangement is clearly known to the farmers and GASCO (through its compensation committee) always share this information during the early awareness raising and information sessions.

4. Number and types of trees affected

a. The affected trees inside the cultivated lands are limited due to the avoidance mechanism adopted by the GASCO. The trees found in the affected areas are: Mango - Guava – Citurs trees. The total number of affected trees is 8353 trees. b. The affected traditional crops cultivated during this season (ending in May) are mainly cotton – rice and corn.

Policy, legal and Institutional Framework The RAP study was prepared in accordance with the following Egyptian and International regulations:

1. Government of Egypt Relevant Legislation  Law No. 4 of year 1988 related to gas pipelines Article No. 2. This Law identifies the right of way and the limitation to use the lands above the pipeline. As well, define the groups who are entitled for compensation  Law No.10 of year 1990 on the expropriation of real estate for public interest and its amendments by law number 1 of year 2015.

3 It is normal for the trees cultivation tobe grown in rows with about 12 m distance left between the rows. The farmer will put into consideration the location of the pipeline and ensure it is in the middle of the 12m distance.

Page 12 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

 Law No. 217 of year 1980 related to Natural Gas which is the responsibility of Ministry of Petroleum to declare the expropriation decree. As well, the necessity to provide an appropriate compensation to the affected people. The safety of the constructions is assured according to this law (article 2).

2. World Bank Operational Policies  OP 4.12 – Involuntary Resettlement

In addition to the above mentioned regulations, the Agricultural Directorates as well as the agricultural Associations develop a list of prices for the crops located within their zones. They also participated in developing the entitlement list for compensation.

Valuation and Compensation GASCO Compensation Committee relies upon the price lists of compensation provided by the Agriculture Directorates that identify the prices of crops, trees, and irrigation systems according to the full compensation cost within .

Planning for Land Acquisition The temporary land acquisition and compensation will be applied as follows:

 The design department in GASCO has provided a detailed map of the routes in order to identify the land acquisition area.  Final assessment by GASCO compensation committee to evaluate the needed lands in cooperation with the Agricultural Association, the RAP consultant in order to develop the RAP document.  After receiving the approval from the WB of the RAP, the Compensation Committee will start their resettlement activities.  The PAPs will be informed and consulted with in order to provide them with the required information about their rights, valuation procedures and grievances and redress mechanism.  A list of owners/tenants and type of loss will be disclosed in the Local Governmental Units and the agriculture Associations Institutional Arrangement GASCO is the responsible entity for land acquisition. The following departments and committees work in resettlement within the GASCO - The Compensation Committee formed from GASCO headquarters representatives. This committee is supported by the Agriculture Associations and the governorate, - The Mediation Committee is responsible to solve the complaints received from the community on the central level - Social Development Officer who is responsible for monitoring, documenting and filing for the resettlement activities, particularly, the grievances.

The Ministry of Agriculture is responsible for, - Agricultural Directorates provides the prices for crops and trees Page 13 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

- Representatives of the Agriculture Associations are part of the composition of the compensation committee

GASCO will be in need to raise their capacity, particularly, regarding the documentation and reporting.

Socioeconomic scope of impacts It is expected that 848 crop holders will be affected due to the construction of the pipeline. The magnitude of impact can be measured by considering the impact on the livelihood of the whole family. Based on the findings of the field survey the average family size is 5.6 persons, thus it is expected that 4748 persons will have impacts on their livelihood during construction.

Perceptions about the project among the PAPs have been captured during field visits and data collection process. The majority of PAPs (crop holders) showed acceptance towards implementing the project on their land especially with some reluctance that the construction of the route will cause limitations on their future use of the land4. They were also worried about potential impacts on the new irrigation system that might be impacted during construction and the restoration of the land to its original productivity before excavation.

Further, the PAPs impression is that GASCO is benefitting and supporting the farmer through the following measures:

a. Providing full compensation for any damages caused during construction. b. Providing the farmer to harvest their crops and provide full compensation c. Providing the farmer to extract their own tree and replant.

Consultation, disclosure and grievances In accordance with the WB requirement of project appraisal, the RAP adopted a multi-level strategy that enables the PAPs to be appropriately consulted. Their concerns, worries and questions were responded to by the GASCO representatives. The consultation activities were applied in a form of individual meetings, public consultation and scoping meetings.

Concerning the disclosure of the RAP, once the Bank accepts this RAP, they make it available to the public through its InfoShop. The RAP will be publicly disclosed to all PAPs and other relevant stakeholders in a public meeting. GASCO will translate the RAP into Arabic and disclose it through the following channels:

1- GASCO website 2- Agriculture Association 3- Local governmental units

4 This will occur in case they will build illegally on their land. GASCO’s policy is to design the route in agricultural land that will not be turned to urban areas in the near future (10-15 years). In case the land will become urban, GASCO will buy the land at full market price for construction areas.

Page 14 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

After the Bank has approved the final Resettlement Action Plan, the Bank and the GASCO disclose it again in the same manner

Concerning grievances, GASCO managed to develop a multi level grievances mecahnism that enable the aggrieved person to be heard Adequately. The grievances tiers, responsibilities, response to the grievance and monitoring were presented in a leaflet that will be distributed to all PAPs.

Monitoring Arrangement Monitoring and evaluation are of significant importance to the project. Thus, the following monitoring activities were presented in the RAP

 Internal monitoring to be conducted by the GASCO. They will be responsible of monitoring all activities related to the resettlement activities, including, grievances, compensation payment, and consultation activities and document all of those activities. GASCO will develop a quarterly report and an annual report. Those reports will be sent to the WB for revision and clearance  An external monitoring should be implemented by an independent consultant twice along the life of the project. 6 months after the implementation of resettlement activities. This evaluation process will develop a mid-term review for the project activities. The final evaluation will be conducted by the end of resettlement activities. A final impact assessment report should be developed.

Budget and time plan Summary of needed budget:

Table 1-1 - Summary of needed budget for comepsnations Price Total Total crop price 2,527,164 Total trees price 8,061,230 Total price for trees and crops 10,588,394 1 barn 16m2 (1200LE/m2) 19,200 2 houses 240 m2 (2000 LE /m2) 960,000 2 houses 150 m2 (2000 LE / m2) 600,000 Total price for assets 1,579,200 Purchasing lands (valve rooms) 1,300,000 Monitoring 300,000 Total 13,767,594

Page 15 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Page 16 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

2 Project Description 2.1 Project overview The proposed project is considered as part of Egypt’s strategy to expand the use of natural gas as a clean source of energy as well as meet the needs of power generation projects. Giza North power project was implemented with assistance of the World Bank. Based on the savings made from this fund, the World Bank received formal request from the government of Egypt to utilize these savings to procure pipelines required for upgrading the natural gas network and supplying natural gas to new and existing power plants.

The aim of the proposed project is to construct and connect natural gas pipelines to Mahmoudya Power Plant5 and therefore the proposed additional scope is considered to be in line with the Giza North Power Plant Project objectives.

The power station is fed by 3 national network lines 42″, 30″, and 16″:

1st Pipeline (42″)

The path starts with a pipeline of 42″ diameter in Rashid Petroleum Company facility area, east to Edko City and nearly parallel to Edko/Damanhour Road, and extends to the south crossing the international coastal road, Alexandria/Rashid Railway, and Bousily Drain. The pipeline then continues to the south passing through Villages no. 8, 6, and 1, then it crosses Edko Drain. Then, it extends crossing Edko eastern drain, Abu El-Einein drain, AlQamaheen canal, and the French drain till it reaches National Natural Gas Network Facility area, to the north of Bisintaway Village with a total length of 27 km.

2nd Pipeline (30″)

The path starts with 30″ diameter pipeline from a valve room on the 42″ pipeline to the north of Izbat Abdel Razeq and Hommosy. Then, it extends to the east in the agricultural lands parallel to Kom Al Gharaq Canal until it reaches Dairut Power Station with a total length of 17 km.

3rd Pipeline (16″)

The path starts from a valve room that will be constructed on Dairut Power Station pipeline, extending in the southern direction for a distance of 2.5 km parallel to high voltage power lines inside agricultural lands. The pipeline then continues its path in the southern east direction for a distance of 2 km also parallel to high voltage power towers, then turns to the east crossing Mahmodia Canal until it reaches the pressure reduction station inside the power station, with a total length of 7 km.

The figuresbelow show the pipeline location and route. In total, there are 48 main crossings. The 1st pipeline intersects with 9 roads, 1 railway, 8 canals, and 9 drains. The 2nd one intersects with 3 roads,

5 Hereinafter the power plant is considered the associated facility for the line, OP 4.12 has also been applied to the power plant and due diligence report is under preparation.

Page 17 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

4 canals, and 6 drains. While, the 3rd pipeline intersects with 3 roads, 2 canals, and 3 drains. Along the whole route, the pipeline will be located underground. The technical details of the pipeline, valve room and pressure reduction station will be presented in the following sub-sections.

Figure 2-1 First pipeline location and route

Figure 2-2 Location and route of the first pipeline (continued) and the second pipeline

Page 18 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Figure 2-3 Location and route of the second pipeline (continued) and the third pipeline

Figure 2-4 Location and route of the last part of the first pipeline

2.2 Description of project Activities

2.2.1 Valve Rooms Valve rooms will be constructed so as to control the flow of the natural gas through the pipeline. Such control can be applied by changing the percentage opening of the valves, or by changing the

Page 19 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline path of the natural gas by operating the bypass valves. The main technical data of the valve rooms are:

 Number of Valve Rooms: 4 on the 1st pipeline, 2 on the 2nd pipeline, and 2 on the 3rd pipeline  Room Area: - 1st pipeline (42″) . Room 1: inside BP Co. . Room 2: inside Edko Co. and extensions are currently implemented . Room 3: 50 m x 50 m (to be purchased from farmers) . Room 4: inside Abu Hommos Valve Room - 2nd pipeline (30″) . Room 3: 50 m x 50 m (it is the same room 3 in the 42” pipeline) . Room 5: Inside Dairout Power Station - 3rd pipeline (16″) . Room 3: 50 m x 50 m (it is the same room 3 in the 42” pipeline) . A room inside Mahmodia Power Station

2.2.1 Pressure Reduction Station (PRS) The pressure reduction station at the Mahmoudya thermal power station aims to reduce the pressure of natural gas to the operational pressure of the power station. The total area needed for the PRS is 105m*105m. The land is secured inside of Mahmoudya Thermal Power station, No land is needed to be allocated by GASCO.

2.2.2 Activities of the Construction Phase Construction will be carried out by qualified and approved contractors under the supervisions and monitoring of GASCO. The work will broadly be split into the following phases:

• Right of Way activities. • Pipe transportation and storage. • Trenching. • Horizontal Directional Drilling (HDD) or boring for the road crossings • Welding and inspection. • Coating and inspection • Wrapping of joints. • Ditching. • Installation of valves. • Tie-ins • Laying fiber-optic cables

Page 20 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

• Backfilling. • Pigging. • Hydrostatic test. • Dewatering. • Purging & commissioning. • Manufacturing and fittings for valves rooms (including civil, mechanical, and electric components).

2.3 Description of the project areas

Socio-economic profile of surrounding villages

Table 2-1 - Poverty and income description of surrounding villages (Income and Expenditure Survey, CAPMAS, 2013) City Population Percentage of Per capita Poverty gap poor people consumption

El Mahmoudya 32730 18.41 6048.37 3.85 city city 112470 26.75 5380.99 6.22 Basantway 43809 48.46 4135.95 11.38 village

The route passes at agriculture areas, only very small hamlets exist close to the route pipeline. The main two cities close to the route are presented in the previous table (Table 2-1 - Poverty and income description of surrounding villages (Income and Expenditure Survey, CAPMAS, 2013). Agriculture represents the main source of livelihood for most of the areas where the route will pass.

2.4 Avoidance mechanism It is the policy of the GASCO to minimize the impacts on the individuals and assets whenever possible. The following procedures are usually adopted by Gasco to avoid the occurrence of resettlement and minimize its impacts if unavoidable. They were also specifically followed for this project:

 GASCO has planned the project to pass mainly through vacant state-owned and/or uncultivated desert lands whenever possible.  GASCO consults with the Survey department in the governorate to avoid land that will be considered urban land in the near future.

Page 21 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

 GASCO has planned the route to pass mainly along existing pipeline routes or roads.  Routing that would result in damage for fences, trees and any other fixed asset were avoided wherever possible.  GASCO tries to avoid damaging trees and constructions.  GASCO allows farmers to harvest their crops before land expropriation as long as the time plan for construction will not be affected.  GASCO allows farmers to move the trees by themselves in order to be able to benefit from the affected trees. However, compensations are paid to farmers even if they move the trees to other location.  GASCO aims to limit the duration of temporary land acquisition to minimize impacts on the livelihoods of land owners. Given the dominant small land shares in the areas and the fact that the total duration required for the construction of the route is not expected to exceed 8 months, the duration of the temporary land acquisition per each land owner during the pipeline installation is not expected to exceed one month.  Close monitoring of the project routes, so that whenever a new construction is started, the monitoring officer immediately reports to stop any encroachment on the lands.

Page 22 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3 Resettlement Impacts

This section will provide detailed information on the categories and amounts of significant adverse impacts related to resettlement activities and the project affected households and people. Additionally, the section will shed a light on groups that may be particularly vulnerable to hardship.

The project will result in various adverse impacts on the 1,986,422 m2 in agriculture area located in Beheira governorate. All of the areas that will be impacted by the construction of the route are located in cultivated areas. Farming is the main source of livelihood in the areas.

3.1 Impacts during construction

3.1.1 Permanent land acquisition Permanent land acquisition will be necessary for the establishment of valve rooms. Areas needed for establishment of the valve rooms are distributed as follows:

- 1st pipeline (42″) . Room 1: inside BP Co. . Room 2: inside Edko Co. and extensions are currently implemented . Room 3: 50 m x 50 m (to be purchased from farmers) . Room 4: inside Abu Hommos Valve Room - 2nd pipeline (30″) . Room 3: 50 m x 50 m (it is the same room 3 in the 42” pipeline) . Room 5: Inside Dairout Power Station - 3rd pipeline (16″) . Room 3: 50 m x 50 m (it is the same room 3 in the 42” pipeline) . A room inside Mahmodia Power Station  Needed areas for the rooms: (50 m x 50 m) = 2500 m2  Land needed for the establishment of the valve rooms will be secured as willing buyer – willing seller scheme.  Gasco follows the principles of the willing buyer willing seller by defining alternatives and always giving the opportunity to the land owner to refuse to sell his/her land. In case the land owners are not willing to sell their land, GASCO design team reroutes the line to pass through areas where land owners are willing to sell.  Based on field experience, the farmers were usually willing to sell their land to GASCO. usually purchases the land at a value that is equivalent to or above the market value. This ends with a value that is equivalent to the replacement value (here is equivalent to the market value in addition to any taxes or other fees associated with purchase/registration/title transfer of comparable replacement land)6. The RAP team was informed that even though

6 In determining the market price, the compensation committee of GASCO resort to recent land selling transactions that took place in the area for similar plots of land. The committee also has valuation experts and, in many cases, resort to local key informants from the area.

Page 23 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

the land is agriculture land, GASCO offers to buy it at a price equivalent to housing areas price which is significantly higher than the regular market price for agricultural land.

Table 3-1 - Types of ownership of the valve rooms Use ownership Number of Occupation Total property Valve room landowners of number landowners Inside the power Public None None None Rooms 1, 2 & 4 stations property (42”) Cultivated areas Private 2 landowners Farmers Part of the Room 3 (42”) Property tenancy

Inside Dairout Public None None None Room 5 (30”) power station property Inside Mahmoudya Public None None None Last room (16”) power station property

Figure 3-1 - Location of the Valve rooms

3.1.2 Temporary land acquisition Temporary land acquisition will be necessary for the construction of the pipeline. The impact duration will remain for one agricultural season (maximum 3 months). The crop holder will suffer from the loss of cultivated crops. Areas needed for the construction are distributed as follows: Page 24 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

 Private owned cultivated areas: 1,133,825 m2 

Various factors will determine the severity of the impacts. Fundamentally, the economic conditions of the PAP, having alternative source of income, the percentage of the affected lands from the total area that the PAP is cultivating are the main elements that identify the severity of impact. The time of land acquisition in relation to the farming seasons is also an important factor in determining the severity of impacts. Following are the potential severity of impacts according to the expropriation times:

 If the land is expropriated prior to the harvest season, unripe crops might be damaged completely as a result of the project causing the crop-holder losses in terms of financial investment and effort invested in the cultivation of those crops. This will be a complete loss of crops. In this case the crop holders will receive full compensation for the crops.  During harvest season, the crop holder is allowed to harvest the ripe crops allowing him to benefit from the crops. Moreover, s/he will receive their compensation. Consequently, s/he is partially affected as they will not lose their crops. In this case the crop holders will receive full compensation for the crops in addition to the harvested crops.  During the preparation of lands to be cultivated, the farmers will not lose their crops, and they will exert no effort to cultivate the land. This will be minor impact. In this case crop holders will receive a compensation equivalent to the rent of the land (uncultivated) identified by the agricultural directorate for uncultivated land.  The PIU will ensure that the contractor will return the land to its original status. The contractor will ensure that the top soil will be stored and reinstalled after completion of the excavation works, before it is retured to owners.

It is difficult to determine at this stage the exact number of PAPs under each category, because this will depend on the implementation plan and its relation to the harvest season.

3.1.3 Temporary loss of assets In addition to the previous impacts, there is potential loss of assets (irrigation network, constructed buildings…etc.) was ratified by the affected people. It was identified during the field work that limited number of assets will be affected. The impacts will not involve any physical relocation of individuals. These impacts can be classified as follows: a. 1 Barn – mud clay and straw baily (16 m2) b. 2 houses (240 m2) c. 2 houses (160 m2)

Page 25 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3.2 Impacts during operation

No impacts are anticipated after the pipeline is constructed and is under operation. Although some restrictions are normally applied on the land uses of the RoW (2*2 m in urban areas and 6*2 meters) in rural areas from the center of the pipeline), those limitations do not apply on this project for the following reasons:  The route will pass across land which is only classified as agriculture land7 (no urban areas and no cities or villages) or vacant state owned land.  GASCO consult with the survey department before determining the route to ensure that the land of the route is not getting into urban boundaries in the near future.  There will be no restriction of use of the land of the route of this project since the PAP can continue cultivating all the kind of crops and trees8 they are currently cultivating. The types of trees with deep roots (e.g. wood trees) which are restricted above the gas lines are not normally cultivated in this area.  In the future, if the land where the pipelines are installed gets into urban boundaries, GASCO purchases the land from the owner. By law, once the land is within urban boundaries, the owner of the land is allowed to use the land for construction purposes. In such cases and in order for GASCO to secure the land where the pipelines are and prevent any activities that may damage the pipelines, GASCO buys the land from the owners at replacement value in line with market prices. This is stipulated under Article 6 and 7 of the Decree number 292 Year 1998 on the executive regulations of Law 4 year 1988. The 2 articles deal with the cases where damages occur to the owner of the land as a result of the implementation of Law 4. GASCO deals with the cases where the land gets into urban boundaries after the pipeline is installed as damage for the owner who should benefit from full market value for his land. In such cases, the affected person approaches GASCO, inform about the case and a new contract is signed for purchasing the land. This kind of arrangement is clearly known to the farmers and GASCO (through its compensation committee) always share this information during the early awareness raising and information sessions.

3.3 Vulnerable groups The census survey did not identify any female headed families, elderly groups and ultra-poor people along the route. However, there is minor probability to find vulnerable groups in case of having any change in land tenancy status. Following is the proposed assistance that will be adopted by the GASCO:

1- Provide the PAPs with compensation in their premises 2- Sufficient and clear information to be provided to them

7 Construction on agriculture land is prohibited by law

8 It is normal for the trees cultivation tobe made in rows with about 12 m distance left between the rows. The farmer will put into consideration the location of the pipeline and ensure it is in the middle of the 12m distance.

Page 26 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3- Probability of hiring one of their unemployed children by the contractor as unskilled labour

In addition to the above mentioned procedures, it is crucial to pay attention to provide information to the illiterate groups. Thus, information will be attained by the provision of clear satisfactory information to the illiterate head of households using the appropriate communication approach.

Page 27 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table 3-2 – Mahmoudya Power Plant Pipeline Summary of temporary land acquisition on cultivated land – OP 4.12 Assets Trees Number of crop Total Affected area Name of Agricultural Association holders m2

Edku – Abu Homos pipeline (42’) 805800 El Marwaha Association 310 45325 El Atf Association 42 40600 Kafr Emliet Association 74 18025 Ezab el Kasr Association 18 116987.5 3780 citrus trees El Kasr el Mostagad Association 93 Dairout power station pipeline (30”) 7787.5 Basantway Association 43 8372.5 6 palm trees El Eshra Association 76 5037.5 Abu Hawash Association 24 Mahmoudya power station pipeline (16”) 1070 Guava New Edku/Edku Association 78 57312.5 3110 Mango 300 Citrus 1 barn (16m2) El Wafaa Association 14 2800 2 houses (240 m2) 2 houses(150 m2) 4025 El Kosour Association 14 21350 60 Guava El Barya 5 & 6 Association 52

Page 28 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

490 15 Guava El Sherka el zeraya Association 10 12 Mango 1133825 Total 848 5 assets 8353 trees

Page 29 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

4 Socio-economic Survey

This section will present a summary of the results and findings of the census survey.

4.1 Findings of the census survey

4.1.1 Methodology of the Inventory of Affected Persons Prior to the implementation of the project activities the following steps have been taken in order to prepare the RAP:

- The RoW was identified according to Gas pipeline Law 4 for year 1988 - The design of the route was finalized - Letters were sent to Beheira Governorate to inform about the project activities that will be implemented - Different meetings were conducted with the Compensation Committee and the Social Development Officer in GASCO to address the potential project impacts. Later on, preliminary site visits were paid to the PAPs. - The project affected persons census and compensation form were prepared in cooperation with GASCO team. - Based on the Egyptian regulations for crop compensation, the Agriculture Associations at the affected areas were contacted and interviewed. The Agricultural Associations developed a list of crops valuation and the other items that necessitate compensation i.e. modern types of irrigation that might be affected. - The affected areas were screened during the inventory. The PAPs were addressed according to their type of loss and the administrative governorate. The whole (51 Km) line was visited in order to identify the affected people there, in addition to highlighting their potential loss of assets, crops.

4.1.2 Findings of the census survey

The number of project affected people along the pipeline is 848 cultivated land owners/ persons, the magnitude of impact can be measured by considering the impact on the livelihood of the whole family. Based on the findings of the field survey the average family size is 5.6 persons, thus it is expected that 4748 persons will have impacts on their livelihood during construction.

Page 30 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table 4-1 - Distribution of affected land by types of crops

Crops in m2 Name of Agricultural Type of crops No of Trees Association Rice Corn Cotton Watermelon Uncultivated Potatoes

El Marwaha 805800 0 0 0 0 0 El Atf 33075 12250 0 0 0 0 Kafr Emliet 14787.5 25812.5 0 0 0 0 7350 Ezab el Kasr 9625 1050 0 0 0

El Kasr el Mostagad 62037.5 54950 0 0 0 0 3780 citrus trees Basantway 4725 875 1750 350 87.5 0 El Eshra 3937.5 575 3237.5 272.5 175 87.5 6 palm trees

Abu Hawash 2100 575 2275 0 87.5 0 1070 Guava New Edku /Edku 31325 12425 13562.5 0 0 0 3110 Mango 300 Citrus El Wafaa 350 1837.5 612.5 0 0 0

El Kosour 2450 0 1400 0 175 0 El Barya 5 & 6 Association 11287.5 4725 5337.5 0 0 0 60 Guava 15 Guava El Sherka el zeraya 440 0 50 0 0 0 12 Mango Total area by type of affected 979665 123650 29275 622.5 525 87.5 8353 trees crop

Page 31 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

5 Legislative and Regulatory Framework 5.1 Introduction

The RAP study was prepared in compliance with the national regulations and international guidelines about involuntary resettlement. For detailed discussion for the legislation, see Annex V. This chapter will cover the following:  Policy references  Egyptian Relevant Legislations  Gaps Between Egyptian Regulations and World Bank Policies  Summary of GASCO Compensation System for Affected Lands, Crops and Trees

5.2 Policy References OP. 4.12 has been considered the guiding principles for developing the current RAP study. The relevant principle policy objectives of OP 4.12 considered here are:

 Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs.

 Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits. Displaced persons should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs.

 Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher.

5.3 Relevant Egyptian Legislations for the Involuntary Resettlement This section presents a summary of all Egyptian Laws relevant to the RAP study, which are as follows

1- The Egyptian Constitution 2014 on protection of private property in articles 33 and 35 indicates that all types of private property are protected. Private property can be expropriated only for public benefit and in return of a fair compensation.

2- Law number 10 for the year 1990 and its amendments by law number 1 for the year 2015 on property expropriation for Public Benefit identifies natural projects as public benefit activities. It describes the acquisition procedures for private lands, assets and other affected materials. Article (20) of Law 10/1990 requires compensation to be determined on the basis of prevailing prices at the date of issuance of the expropriation decree.

3- Petroleum pipelines Law 4/1988 The petroleum pipelines law 4/1988 states that the owner of a property should allow the passing of pipelines transporting liquid or gaseous

Page 32 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

hydrocarbons beneath the ground surface in accordance with the procedure mentioned in the executive regulations (Decree 292/1988).

4- Ministerial Decree number 346 of the year 2007 that enables the governors to form a committee in order to identify the valuation of compensation for crops and assets within the jurisdiction of the governorate. In addition to the above-mentioned regulations, the Agricultural Directorates are allowed to set a list of prices for the crops located within their areas.

5.4 Gaps between Egyptian Regulations and World Bank Policies The gaps between Egyptian regulations and World Bank policies are summarized as follow:

1- The cut-off date: The WB identifies a cut-off date in order to prevent people influx to the project area. This measure is stipulated in order to protect the project owner and preventing wasting of resources. The Egyptian laws never set a cut-off date, particularly if the impacts are related to agricultural lands that might experience changes in crops and tenancy. 2- Monitoring and Evaluation: Monitoring or evaluation measures are not stipulated in Egyptian regulation. Lack of the necessary legal provision needed to put in place monitoring and evaluation measures can negatively impact the accountability and transparency programs and plans may not be able to benefit from corrective action in cases of mistakes nor receive rewards in cases of good performance.

3- Assistance during relocation: The Egyptian law does not pay attention to the assistance during replacement, while WB stipulates that affected people are to be offered support after displacement, for a transition period. It is worth mentioning that based on the World Bank requirements for applying an effective and accessible grievance mechanism, GASCO established a proactive grievance system. GASCO compensation committee usually conducts several meetings with the PAPs at the construction sites in addition to follow up activities throughout the compensation process. Any complaints arising during the construction activities will be submitted to the resident engineer.

Page 33 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 Valuation and Compensation

The valuation methodology of the crops and assets’ compensation is imperative for the RAP study in order to facilitate the compensation process. Following is a discussion of the valuation process adopted per each type of loss.

6.1 Eligibility Criteria There are various categories of PAPs who are entitled to compensation and socio-economic restoration according to the World Bank. The following are the identified groups of project-affected persons (PAPs) for this project that will be entitled to mitigation/compensation:

1. Temporary (complete or partial) loss of crops and trees in the construction area:

 Farmers / Individuals who have formal legal ownership rights to land  Farmers /Individuals who do not have formal legal ownership rights to land but have temporary or leasing rights  Farmers / Individuals who do not have any recognizable legal right or claim to the land: provide compensation for (complete or partial) loss of standing crops, trees, or plants

2. Permanent Loss of standing crops, trees, or plants or access to them

6.2 Valuation of Crops/Assets 6.2.1 Crop Valuation

In order to determine the prices of the crops, the study team relied upon the pricing lists provided for the crops. (Price list received from Agricultural Directorate is added as an annex II9).

The price lists are developed by the Agriculture Directorate, which is the affiliate Governorate level branch of the Ministry of Agriculture. Prior to developing such lists, the Agriculture Directorate has discussed with the Agriculture Associations within the jurisdiction of the governorate in order to identify the prevailing market price. Such dialogue is not documented by the Agriculture Directorate; however, it is reflected on the developed price list.

9GASCO makes sure to update the crop list from the agricultural directorate immediately before start of the compensation process to ensure it reflects the latest price updates. This lists are updated by the Agriculture Directorate based on the prevailing market price and are applicable to all agricultural associations, the list is updated every three years.

Page 34 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table 6-1- Prices provided by the agricultural directorate in Beheira, 2015 Crops Trees Crop Price Price Crop Price Per Price Trees Price Per per m2 feddan per m2 Per tree feddan (4200 m2) Rice 9450 2.25 Beetroot 11550 2.75 Guava 516 Corn 7350 1.75 Watermelon 17850 4.25 Mango 1150 Cotton 14700 3.5 Potatoes 17850 4.25 Citrus 950 ------Palms 685

Most of the crop holders that were consulted about the values of crops and trees, indicated that they are satisfied with the crops compensation. However, they reported that the best timing to give their land is by the end of the agricultural season after harvesting the crops. In addition to the tree prices GASCO pays compensation for the value of the harvest.

6.2.2 Temporary Loss of uncultivated land

Some plots are prepared for cultivation but have no standing crops at the moment as indicated in Table 4-1 - Distribution of affected land by types of crops. The amount of compensation will be calculated based on the rent price identified by the agricultural directorate.

The price included in the agricultural directorate is 2 LE/1 m2 of uncultivated land.

6.2.3 Temporary acquisition of land for storing construction material

Any land needed for temporary storage of construction material will be compensated at full rent price of uncultivated land determined by the agricultural directorate, and in case the land is cultivated the normal compensation mechanism of crops and tress compensation will be applied.

6.2.4 Asset Valuation

The Compensation Committee evaluates the affected assets. The assets that will be affected by the project are limited due to the fact that GASCO follows the avoidance mechanism aiming at reducing the impacts. Only small houses that are not inhabited were identified. They are mainly used for crop storage or for raising animals.

The valuation of this type of assets is mainly based on restoration price. GASCO will either restore the asset to its original status or will provide equivalent compensation for the restoration value.

Page 35 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

PAPs will be part of this process in cooperation with the compensation committee. The assets have been valuated according to the following determinants:

1. The construction material needed to rebuild the house 2. Needed cost to reconstruct the house (laborers- transfer of the construction materials- license…etc.) Based on the site visits to the affected areas, certain assets were reported, they are as follows:

 Barns  Houses built from brick

Table 6-2 -Summary of the proposed price for the affected assets Asset Price

A vacant house built in agriculture land 2000 EGP per square meter10 from brick Barn from mud brick and straw baily 1200 EGP per square meter

6.3 Arrangement for delivering of compensations The temporary land acquisition and compensation will be applied as follows:

. After receiving the approval from the WB on the RAP, the Compensation Committee11 will start the compensation procedures.

. A list of owners/tenants and type of loss will be disclosed in the Local Governmental Units and the agriculture Associations. . A formal agreement will be written with each PAP, upon which, the compensation is paid to him/ her and GASCO will receive the land from him/her to start the construction. . The value of compensation of the potential affected lands/crops/trees and assets will be defined and forwarded to the financial department in the GASCO. . The financial department will release the compensation amount. . Full compensation will be given to the PAP before the start of the construction activities.

10 GASCO offers the owner either to reconstruct the asset after construction or to provide the price of the building material. Both assets are built from the same material.

11 See the composition and role of the compensation committee in chapter 8

Page 36 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

. Complete legal procedures for land acquisition will be documented by the project manager and then sent to the Social Development Officer at GASCO headquarters (Eng. Ahmed Galal - 01211878678). 6.4 Transitional support Due to the nature of impacts which are mainly impacts on crops and trees, there will be limited transitional support activities. There will be no moving costs, temporary living allowance and payment of fees since there will be no physical resettlement of the PAPs. The four houses identified in the route are vacant. Moreover, it is constructed on agricultural land. Compensation for the barn will be either rebuilding them or offering equivalent price to the reconstruction. GASCO will pay the monetary compensation to the owners as a compensation for the structure that will be affected in order to enable him to build a new one prior to demolishing the affected structures. The PAP will receive their compensation, thereafter, it is up to them to reconstruct the structures or not. In both cases, the proposed compensation covers all reconstruction activities.

6.5 Arrangements for recalculation of compensation in case of prolonged delay in delivery of compensation In case of any prolonged delay related to the project implementation the following procedures will be applied:

1- GASCO will send a letter to the Agriculture Directorate in order to get the updated crops and trees price lists. This will be during the re-measuring process 2- The Compensation Committee will inform the PAPs about the change of the prices. They should sign a new agreement that reflects their approval on the new value of compensation re-calculation 3- The value of compensation of the potential affected lands/crops/trees and assets will be defined and forwarded to the financial department in the GASCO. 4- The financial department will release the compensation amount from the budget item allocated for compensation and requested early by the project manager. 5- The Compensation Committee will disburse the compensation value according to the previous conditions of payment reported in section 6.3 6- All updated lists, agreement and money disbursement will be documented by GASCO compensation committee

Page 37 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

7 Income and Livelihood Rehabilitation Measures

This section provides information about the arrangements for providing sufficient opportunities to those losing their land in addition to the compensation identified.

For this project, PAPs are only eligible for compensation for crops as identified in chapter 6. The project will not result in the type of livelihoods damage that will require livelihoods rehabilitation measures. No other impacts are anticipated that requires additional assistance or compensation.

7.1 Discussion of measures of Livelihood and Income Rehabilitation Measures The following types of compensation are considered:

- Arrangements (in addition to compensation) providing sufficient opportunity for those losing land to improve or at least restore incomes:

Not Applicable – Only compensation for crops for one agricultural season is considered.

- Arrangements, timing and availability for replacement housing, including site preparation and access to facilities and services as needed to improve, or at least restore, living standards:

Not Applicable

- Relocation or other arrangements necessary for shops and enterprises to resume profitable operation:

Not Applicable

- Arrangements (e.g. alternative employment, temporary wage support, other) necessary to maintain or restore incomes of workers in affected enterprises

Not Applicable

- Relocation Assistance to renters or leaseholders losing access to land or structures:

Not Applicable

- Special Assistance to be provided to vulnerable groups (e.g., the poor and the elderly and disabled):

Not Applicable

- Restoration or replacement of community infrastructure and services:

Not Applicable

Page 38 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

8 Institutional Arrangements

This section identifies organizations and/or agencies primarily responsible for resettlement implementation. It describes the capacity of these entities for effective implementation by reference to links to authority, prior experience with resettlement, and number and training of their personnel. This section also briefly describes the implementation timetable, establishing that key implementation measures precede adverse impacts.

8.1 Institutional Responsibilities for the RAP Implementation

8.1.1 Organizational Setup The organizational setup responsible for compensation activities under this project is the Compensation Committee in GASCO , formed of:

 Technical member (Agricultural Association)  GASCO represntative (Social Development Officer)  Represntative of the Contractor These are permanent staff members of GASCO. They work closely with the Agricultural Association and Agriculure Directorates12 in relevant governorates.

8.2 Institutional roles in GASCO compensation system

The following table presents the roles of different institutions in the compensation system at GASCO:

Table 8-1 - Institutional roles in the GASCO compensation system Stakeholder Institutional Role

Ministry of Petroleum According to law 10/1990, the Minister of Petroleum will issue the expropriation decree for the project

Ministry of Agriculture According to law 10/1990, the Minister of Agriculture approves the expropriation decree for cultivated lands

Agricultural Directorate Identifies concerned associations according to the project maps

12 The Agricultural Directorates are responsible for developing the crop prices list only

Page 39 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Provides the price list for the crops and trees at the governorate

Agricultural Associations Provide the names and tenures of the PAPs within their relevant areas

Participate in the census survey of the PAPs prior to starting of the expropriation activities as part of the compensation committee

Participate in the compensation committee to provide technical opinion about the crops (age of trees, fertility of land ... etc.)

GASCO Compensation Is responsible for the verifying the census survey of the PAPs prior to Committee implementation

Is responsible for implementation the compensation activities according to the standards and procedures stipulated in the RAP

Communicate with the governorate and the Agricultural Directorates for expropriation decree and valuation of crops

Pay the compensation amounts to the PAPs Petrojet (contractor) Participates during the implementation of the compensations process to confirm the final routes prior to construction, under full supervision from GASCO. Does not play a role in the actual compensation process in relationship with the PAPs.

GASCO Mediation Is responsible for handling the second tier of grievances Committee

GASCO Social A key player to ensure diligent implementation of the RAP and Development Officer ongoing consultation with the PAPs (SDO) Works in both compensation and mediation committees

Is responsible for handling the first tier of grievances along with the Site Project Manager as well as conducting awareness raising activities among PAPs to inform them about the grievance mechanism

Responsible for monitoring the progress of the RAP implementation and support the PIU in preparing monitoring reports and inform the Bank in case of sensing any possible deviation between the compensation plan implementation and what was stipulated in the RAP

Works with the GASCO team to ensure that land is restored to the same conditions as before the pipeline installation.

Conducting further consultations during the implementation and

Page 40 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

monitoring of the RAP (including affected persons of vulnerable groups such as women and poor people)

Ensures that the willing buyer-willing seller approach process was applied to meet the key principles and that the land owners and users had the right to refuse to sell their land and that involuntary land expropriation was not an option to resort to when the process is defined as “willing buyer willing seller”.

Site Project Manager Is responsible for supervising the construction activities

Is considered the first tier of grievances

GASCO Environment Will monitor the implementation of the RAP process during all its and Social Department phases.

Submit regular monitoring reports on the RAP implementation to the World Bank.

Keep record of the received grievance and the taken steps to resolve

8.3 Implementation timetable

8.3.1 Implementation Sequence The compensation process is governed by a clear detailed legal framework that enabled compensation committee to perform their work appropriately. In addition, the legal frame is in compliance with the regulations of the World Bank OP 4.12.

Temporary land acquisition and compensation will be completed in coordination with relevant organizations and as per the principles of the prepared RAP. The specific process is as follows:

. Prior to the RAP preparation, the project design department in GASCO provides a detailed map on land acquisition scope to identify the land acquisition scope and area. . Agricultural Directorate provides the prices for the different types of crops. . Compensation committee initially calculates the needed areas in cooperation with the Agricultural Associations, . Approval from the WB on the RAP . Prior to the implementation of the RAP, verifying the situation on the ground and checking if any changes (compared to the census survey baseline) happen, document the change, assess the implication and inform the Bank . Delivery of compensation amount to the PAPs. . Complete legal procedures for land acquisition

Page 41 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

8.3.2 Time Schedule and the Cut-off Date The potential date for the start of the construction is August 2016 which is considered the cutoff date13. Construction activities will start after completing the compensation activities. It is important to note that the project schedule will start with a cutoff date, after approval from the World Bank.

During this stage GASCO made a preliminary cost estimate for the project affected lands, the determinants of this estimate were:

 land size  type of crop or tree  the prices mentioned by the Agricultural Directorates

13 The cut-off date was communicated to PAPs during the consultation activities and field work.

Page 42 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Feb Mar April May June July Aug Sep Oct Nov Dec Jan Feb Mar April May Tasks and activities

During preparation phase

Consulting with the governorate Formation of the compensation committee Agricultural directorate develop crop price list Formation of the GRM committee

Consultation with the PAPs

Preparation of the PAP profiles

WB approval of the RAP

Verification of the RAP

During Resettlement Implementation

Consultation with the PAPs

Disbursing payment to PAPs Documentation of the compensation activities Documentation of the grivences and responses Documentation of operation and efficiency of the RAP During monitoring and evaluation

Quarterly reports to be developed

External Monitoring (Mid-term + Final)

Page 43 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

9 Budget and Funding Arrangements Construction is expected to start beginning of August 2016 until August 2017, since crops vary across, the implementation of the RAP should start two months before the construction of the project. Based on the WB requirements all compensation should be paid prior to the construction.

Thus the following are the consequent steps that will be applied after determining the time frame of the project:

1- The construction will begin only after the completion of the compensation process. The PAPs should be identified and documented.

2- Crop compensation is linked with implementation of project activities as no excavation should be conducted on site before the payment of a full cost of the compensation.

9.1.1 Estimation of Total Temporarily Land Acquisition Cost The total cost estimated was about 13,767,594 million EGP.

9.1.2 Compensation amount Compensation amounts refer to compensations to be paid directly to the affected persons, which include temporary land use compensation and compensation for sporadic trees. The census showed that the potential impacts will be as follow:

 The majority will be impacts on the crops and vegetation Depending on the legal status of the crop holder (owner or tenant), GASCO arranges to offer the compneation and the crop holders are aware of this division in the compensation value, as follows:

The land owner gets 2/3 of the compensation while tenant gets 1/3 of the compensation in the case of the trees planted by the land owner and the tenant rents only to collect the crops.

The tenants gets 2/3 of the compensation while land owner get 1/3 of the compensation in the case of the trees planted by the tenants.

The land owner gets 100% of the compensation in the case of the trees planted by him and the harvest is collected by him (no tenant).

 Temporary impact on the assets (houses)  Temporary impacts on empty lands  No impacts on permanent land Following are the estimated amount of money needed to compensate the affected people, along with other costs associated with RAP (site supervision, monitoring RAP implementation by client, etc.). Page 44 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

- Calculation of the compensation amount for crops

Type of Crop Total area in m2 Price per m2 Total price Rice 979665 2.25 2,204,246

Corn 123650 1.75 216,387.5 102,462.5 Cotton 29275 3.5 Watermelon 622.5 4.25 2645.625

Potatoes 87.5 4.25 371.875

Uncultivated land 525 2 1050 Total Price 2,527,164

- Calculation of the compensation amount for trees

Type of trees Number of trees Price per tree Total price Guava 1145 516 590,820 Mango 3122 1150 3,590,300 Citrus 4080 950 3,876,000 Palms 6 685 4,110

Total Price 8,061,230

- Calculation of the price for assets

Number of Type of asset assets Price per m2 Total price Houses 4 2000 1,560,000 Barns 1 1200 19,200 Total price 1,579,200

Table 9-1 - Total cost and budget in EGP Price Total Total crop price 2,527,164

Page 45 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Total trees price 8,061,230 Total price for trees and crops 10,588,394 1 barn 16m2 (1200LE/m2) 19,200 2 houses 240 m2 (2000 LE /m2) 960,000 2 houses 150 m2 (2000 LE / m2) 600,000 Total price for assets 1,579,200 Purchasing lands (valve rooms) 1,300,000 Monitoring 300,000 Total 13,767,594

* GASCO ensures that the compensation is paid to the crop holder (the tenant in case the land is rented). And GASCO has implemented this many times in previous projects.

9.1.3 Fund Flow and Payment Plan GASCO team are keen to allocate the necessary funds before the implementation of any compensation activities in order to: 1) have the money paid on the spot; 2) facilitate work through avoiding tiring red tap. Paying the money to the farmers increasessatisfaction and enhances their willingness to give their lands for the project. Based on meetings conducted with the Compensation Committee it was reported that the estimated funds needed for compensation will be put in a new account under GASCO. The main objective of having the full amount of compensation allocated before the construction is facilitating the compensation process, in addition to facilitate the auditing required by Law.

GASCO is the sole entity to provide the financial compensation. In case of having awareness raising acitivities or orientation sessions, that will be in cooperation with the relevant Ministries (Ministry of Agriculture).during the compensation payment

Page 46 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

10 Consultation, Disclosure and Grievance Mechanism

10.1 Introduction This chapter aims to highlight the key consultation and community engagement activities and their outcomes that were conducted in relation to the land acquisition and mitigation of resettlement impacts, in addition to outlining the key aspects that were addressed when holding the consultation activities.

Consultation activities (census survey, scoping, interviews, focus group discussions, public hearings/consultations) with various stakeholders and community people in the host communities including the affected persons were held for the proposed NG pipeline connections project in compliance with relevant WB and Egyptian legislations.

10.2 Consultation Activities

Consultation has been carried out in the form of a continious process that started before the start of preparation of RAP and ESIA and has continued during preparation of the RAP study. GASCO has applied multi-levels of consultation with the stakeholder and the PAPs during preparation of the RAP. The consultation process is expected to be continued by Gasco during varous stages. Following are the main objectives of the consultation activities held:

 Informing the PAPs of the RAP preparation process and the scope of the ESIA and RAP  Collecting information related to the socio-economic profile of the PAPs  Sharing information about the compensation approach including compensation values and the calculation methods with the PAPs  Consulting the PAPs about the draft findings of the ESIA and RAP studies

The following table (Error! Reference source not found.) shows the detailed consultation activities held during preparation of the RAP:

Table 10-1 - Summary of the conducted consultation activities Consultation Data Number of Time and Number of Main topics covered approaches collection consultatio location people tools ns consulted (Table/male and female) Census Survey Census December 848 crop Census of the affected during the survey sheet 2015 – holders persons and the scope RAP January 2016 of land acquisition preparation conducted by GASCO

Interviews Questionnai 39 interviews April-May, 39 persons Identification of impacts of land Page 47 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

with PAPs re sheet 2016 acquisition. Collecting information related to the Socio-economic profile of the affected persons. Discuss the impacts of land acquisition and compensation methodology.

FDGs FGD 16 sessions April-May, 70 persons Discussion of project guideline 2016 (community impacts including members + 24 socio-economic and PAPs) resettlement impacts

Stakeholders Interview 14 interviews April-May, 14 persons Discussing the roles semi guideline 2016 of stakeholders in the structured RAP process interviews Including interviews with agricultural associations and the agricultural directorate to discuss the compensation approach and valuation methodology

Scoping - 1 session Damanhour, 134 persons, Inform the local session for the 12 April, 82.08% males community including ESIA and 2016 and 17.9% PAPs of RAP Methodology for data preparation females collection for both the ESIA and the RAP studies And present ToR for ESIA and RAP

Public - 1 session Damanhour, 86 persons, Present findings of the Consultation 11 May, 2016 80.2 %males field work of both the session for and 19.7% ESIA and RAP presenting the studies including ESIA and females. resettlement and RAP findings socio-economic impacts

10.2.1 Consultation Activities during Site Investigation

Prior to the planning phase, GASCO teams paid several visits to the project site in order to consult with the local community. The main objective of these visits was to introduce the project to the governmental entities and community people. During these visits, all the concerns and comments received from the governorates and the directorates (health,

Page 48 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

environment, etc...) are considered during the planning of the project. Those visits also helped in determining the route of the pipelines.

10.2.2 Consultation Activities During preparation of the ESIA and RAP studies

 During the preparation of the ESIA, community groups were consulted through the focus group discussions (FGDs), stakeholder interviews and scoping meetings conducted along the route. In addition, individual interviews were conducted with the potential affected persons in their fields. The farmers interviewed noted that they have witnessed other Gas pipeline projects. Concerns were raised about the possibility of building on the land after construction of the pipeline. This is an important issue given the huge illegal expansion of construction over agricultural land14.

 During the preparation of the ESIA and the RAP, two public consultations (PCs) were held with the stakeholders and community people in the project areas (scoping session and Public Consultation). PCs results were included as part of the ESIA study. Comments raised by participants were considered. Temporary land acquisition was raised as an important theme including questions about the compensation value. Number of the PAPs participated in those sessions.

Scoping session held in Damanhour, Beheira on April 12, 2016

The event was conducted on the 12 April 2016. 134 persons attended the consultation event. They are segregated into 82.08% males and 17.9% females.

Table 10-2 - Participants in the scoping session Distribution of participants according to Profession Number Percentage

Administrative officials governorate level 8 5.9

Gas Companies 12 8.9 NGO’s 6 4.4 Community members 108 80.5 Total 134 100

14 GASCO ensures that the selected land is agricultural and will not be turned to urban within the coming 10-15 years. Farmers in this issue are aiming to illegally build on the land as a status quo, while this land is officially declared agricultural land with no near future plans to be urbanized.

Page 49 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Public Consultation in Damanhour, Beheira on May 11, 2016

In order to review the findings of the draft ESIA and RAP studies, a public consultation event was held to allow various groups of stakeholders to come together and raise any comments on the drafted ESIA. EcoConServ consulting carried out several steps to announce for the event and invite stakeholders. The event was conducted on the 11thof May 2016. 86 persons attended the consultation event. They are distributed into 80.2 %males and 19.7% females.

Table 10-3 - Distribution of Participants in the Public Consultation Distribution of participants according to Profession Numbers Percentage Administrative officials governorate level 5 5.8

Gas Companies 13 15.1 NGO’s 5 5.8 Community members 63 73.2 Total 86 100

The main comments raised during the consultation with regards the land acquisitions were as follows (For detailed information about the participants of the consultation sessions, see Annex 5):

Table 10-4 - Key comments and concerns raised during the scoping session Issue Questions and comments Responses Route What is the depth of the pipeline? Usually the lines are installed at about Alternatives 1 meter depth from the surface.

As explained the route will pass The route passes through four or five through surface water, that are water canals as presented. And since sources of drinking. Are there any these are important water ways we impacts on drinking water? will perform the excavation What are the maintenance underneath them. We follow the procedures for the pipelines? Are requirements of the Ministry of they taken into consideration? Irrigation in their approvals. We will be excavating at a depth of about 5 or 6 meters. Hence no impacts are expected on the waterways. Does the line pass through any Concerning Edku/Abo Homos historic areas at Beheira including pipeline it passes close to the military Damanhour, Mahmoudia or Abu station but far from the historic sites. Homos? We send requesting approvals from all concerned stakeholders including Ministry of Antiquities.

Page 50 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Issue Questions and comments Responses Some cultivated areas have sand soil, Most of the land needed for the do they require deeper excavation project is agricultural land. Technical than one meter? persons determine the depth of the construction of the line according to soil type. A depth of one meter is not enough The technical team are the ones who to avoid any damages caused by decide on the depth of the lines activities on the surface? How can we detect any hazards early enough?

It is important to consider Excavation will be conducted using excavation under waterways to avoid HDD technology to avoid any any disturbance impacts Impacts on Are there certain types of crops that There are no impacts on cultivation land use and will not be able to grow after activities afterwards. We only damage compensations construction of the line? existing crops then the owner can use the land normally afterwards.

There are some restrictions to plant some trees with deep roots15.

How will the farmers receive their Directly from GASCO and before compensations? any excavation starts

Community What benefit will the surrounding Natgas is the company responsible participation area get from the pipeline? for household connections at Beheira and CSR governorate. They are the ones who initiatives have the plans for the households that will be connected to the network according to their technical specifications.

What is the role of the NGOs to Raise awareness among community participate in this project? members about the project.

Agricultural engineers at GASCO officially requests the Horticulture department in the agricultural directorate at Beheira Agricultural directorate should governorate to participate in the participate in calculating process of compensations. compensation values for trees. It is important to have an agricultural engineer to coordinate between GASCO and the farmers. And also to monitor the line after operation

15 As confirmed by GASCO only restriction is on building wood trees. Also farmers can maneuver to build trees only avoiding the actual top of the pipeline. Hence this impact is considered very limited on farming activities.

Page 51 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Issue Questions and comments Responses Environmental What is meant by form C projects – Form C projects are considered impacts or black list projects? according to the size of the project and the expected impacts. It is also considered based on the severity of the impacts, the type of waste and emissions.

What happens if any chance finds We have specific procedures for were found during excavation? change finds.

What are the security measures GASCO takes maximum security around the route? measures. Now lines are covered to avoid any sabotage work. Regular patrolling to the line. It is important to handle welding All types of waste are handled waste carefully. And to add clear according to the legal requirements signage at the construction site. It is important to develop a GASCO has a clear emergency maintenance strategy for the pipeline response plan to respond to any of and procedures for handling cases of these cases natural disasters or emergencies. Kindly take into consideration that No impacts are expected on there will be no impacts on the infrastructure. In cases of any drinking water network and also on damages the contractor is obliged to the main roads restore it to its original status It is important to develop awareness Yes and collaboration with the local strategies to avoid negative impacts civil society institutions is very during construction in collaboration important with civil society organizations.

10.2.3 Consultation Activities during Preparation of the RAP

 The RAP team accompanied with GASCO team conducted different consultation activities at the local target areas. Consultations events were mainly held through the agricultural Association.  Preparation of the RAP for this line mainly involved engaging with the area where agricultural activities occur (about 51 kms).  The study team prepared a community based consultation strategy in order to cover the all of the cultivated areas. It was relatively multi-level process which was implemented by applying consultation activities as Focus Group Discussions and Individual Interviews.

Page 52 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Figure 10-1 - Photos during the field work

 The project team ensured to disseminate the following information to the participants during the meetings: 1- The project objectives and justification 2- Potential impacts 3- Compensation strategy and mitigation measures 4- Entitlement categories 5- Grievances mechanism

Page 53 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table 10-5 - Key comments and concerns raised during the public consultation session Issue Questions and comments Responses Environmental The water company was not GASCO holds coordination impacts consulted although it plays a major meetings with the governorate prior role since the line passes beside to construction to arrange for all several waterways important for these issues. irrigation. How will liquid effluents be stored Oils and these kinds of liquid and disposed of? effluents are collected and handled properly according to the regulations of EEAA. There is a system also to monitor and document the amount of used oils in the environmental records.

Are there negative impacts during The project is like any other project, operation? it involves some negative impacts. We cannot claim that there are no negative impacts at all. But after applying safety measures and the proposed mitigation measures, we lower risks to the minimum.

What are the measures for handling Wastes generated during the waste during construction and construction phase are classified. during operation? Where are these Contractor is obliges to dispose of waste disposed of? hazardous waste in certified landfills, according to the regulations of EEAA. GASCO monitors this process. No waste is left unhandled on site. In case the contractor does not handle waste properly he is subject to penalties by GASCO.

It is also important to note that the governorate monitors the waste handling process. There are some wastes that are considered within the while other رد الشئ ألصله restoration waste is considered hazardous waste is sent to Nassreya landfill. Beheira is one of the strict governorates in this issue.

Page 54 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Issue Questions and comments Responses What is the impact of the pipelines Impacts on infrastructure networks on the drinking water network? may occur. We can accidently cut the Does it contribute to polluting drinking water pipelines. We drinking water? communicate with the governorate and local directorates in order to coordinate for securing the infrastructure. They have information system and maps. We try to avoid any impacts on the infrastructure.

There is also an emergency plan, in case of any disruption of infrastructure.

Social impacts Who pays the compensations? Yes all compensations will be paid by and GASCO or the contractor GASCO – compensation committee- compensations directly to the affected farmers. GASCO is also monitored by the Holding company in this process.

How to avoid negative impacts on The value of the compensation is the crops and to ensure fair determined by GASCO compensations to the farmers? compensation committee on the ground and before construction. The persons who will be actually impacted will all be compensated. The agricultural directorate will determine the fair price of the crops. They will ensure that farmers are paid fair prices.

What is the role of the social officer We have met many stakeholders as a at the environmental department at sample of the study. And we the local government units in welcome any form of participation. facilitating the project? Social We can meet further with the civil departments and local NGOs can society organizations to contribute to facilitate the objectives of the study. the study.

Have any decrees been issued for There is no such a thing as political expropriation of the land without decrees. We will pay full fair compensation? compensations to the farmers. We are not going to damage crops and leave them without compensations.

Page 55 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Issue Questions and comments Responses What is your community GASCO has conducted a preliminary engagement strategy and community survey of the farmers who will be participation measures? impacted by land acquisition. The Who are the participating actual will be determined on site stakeholders from local and civil before construction. Agricultural society organizations in the land associations participants in acquisition? Where the committees determining the final names of the only from GASCO or from the farmers and the actual community and other stakeholders compensations. as well? Safety What are the safety measures for the We have an automated smart system measures pipelines? to detect any leakage. In this case the automated system cuts the gas supply.

It is not likely that fires occur from the pipelines after applying the safety measures.

What are the safety measures applied We apply the electronic scanning by GASCO to avoid any safety system to ensure no leakages occur. problems at the surrounding In addition to regular patrolling of villages? the line. We coordinate with infrastructure networks. GASCO is very keen to protect its lines.

What are the maintenance We apply maintenance procedures procedures of the pipeline during because we are keen on protecting operation? the pipelines and the surrounding neighours. The pipelines are an investment for GASCO that we have to protect.

It is important to add signs along the GASCO adds signs along the route route in order to avoid any to mark its pipeline in addition to the encroachments on the line during regular patrolling of the line. operation. Signs are very important especially at housing areas.

Land use Construction of the pipeline will This land is considered agricultural restrict our right to build on the land land. We compensate for crops. later? Is there any compensation for Laws restrict building on agricultural this right? land.

In case the land turns into urban area, the restriction is for the RoW – 2 meters from each side.

Page 56 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

10.2.4 Further Planned Consultation activities

 Prior to construction, GASCO Compensation committee team has sent letters to the governorates to inform them about the procedures of the compensation and the establishment of the compensation committees.  After sending the letters, different meetings were conducted with the governorate and the Agriculture Directorate. The Agricultural Directorate coordinates with GASCO compensation committee team the valuation of the compensation according to the market prices and after consulting farmers from the area.  Consultation activities already started with the PAPs accordingly in order to inform them about the compensation values and procedures.  Specific and differentiated efforts will be made to reach out to women in particular during the upcoming consultations on the RAP (which will be documented by the SDO).  GASCO’s general practice is usually to conduct several meetings with the PAPs at the project affected areas in order to inform the PAPs of the compensation procedures and avoid any problems. The negotiation process can be summarized as follows:

Table 10-6 - Summary of Proposed negotiation process with PAPs

Five consultation activities will be conducted with the PAPs, based on GASCO’s CSR policy.

The First activity: Discussion with the PAPs during the inventory survey, with the compensation committee and the representatives of the agricultural association. All PAPs/farmer were included in this activity. The inventory will take place prior to the construction; all information will be reported to the PAPs/farmers as follows: 1 - Information about the construction works and excavation 2 - The compensation mechanism followed by GASCO to ensure the rights of the farmers. 3 - Highlight the importance of GASCO to restore the cultivated areas to its original condition.

The Second activity: After the census survey process, GASCO will hold meetings at the agricultural Association. All listed land owners in the census survey are invited. They will be informed about the following:  Information about the gas pipeline  GASCO compensation procedures to ensure fair compensations. Procedures of crop valuation based on the prices provided by the agricultural Directorate.  Respond to any questions raised by the PAPS.  Clarify the grievance mechanisms to submit any complaints from the PAPs  Ensure that farmers that the land will be restored to its original status after construction  Provide information about the Ministry of Petroleum is the entity responsible for the line  Provide information about the safety measures during operation of gas pipeline  Provide means of contacts during and after the implementation of the line with GASCO

The Third activity : Will be conducted after the general meeting at the Agricultural Associations. Individual meetings will be held with each farmer. During the meeting the following procedures will happen:  To clarify the information previously provided. Conduct site visits if necessary, explain methods of compensation valuation. The Compensation Committee and a representative of the Agriculture Association will participate.  The full amount of compensation will be paid and each PAP will sign a receipt. PAPs are entitled to submit grievances in case they are not satisfied with the compensation. Page 57 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

The Fourth activity : The activity will be arranged at the beginning of the construction works, to coordinate between the farmer and the implementing company (Petrojet) to ensure the maximum benefits for the famer, completed through the following:  Farmers are allowed to move the trees to another area and still receive full compensations  In case that the crop is about to be harvested, the company waits until after harvesting the crops as long as that does not to affect the project time plan. However, the compensation will be paid in full amount.  The farmer is allowed to use the affected crops (he/she might use the unripe crop as fodder for the cattle)

The Fifth activity : During the implementation process, a communication channel will be established between the farmer and the project manager during the construction. Only after removing all the excavation equipment and restoring the land to its original status the compensation process is considered finalized. The main objective is to ensure continuous coordination between the farmers and the project manager.

10.3 Disclosure of the RAP

10.3.1 Information Disclosure during Preparation Phase The project, in compliance with the requirements of Law 10/1990, paid more attention to the disclosure of all information related to the project activities and potential impacts:

 During the ESIA and RAP preparation all information related to the project including compensation and resettlement, was presented in the website of the following entities: o GASCO website o EcoConServ website16 o The non-technical summary and the Final ESIA and RAP reports, were uploaded to the websites  Meetings were conducted in the locations of land that will be expropriated. GASCO team disclosed all needed information to relevant stakeholders. They provided the needed information transparently and sufficiently. The team was open to receive questions and responded to it during conducted meeting, as well as, after the sessions  During the RAP data collection process, the Social Development Officer from GASCO and the agriculture Association representatives as well as the consultant disclosed all needed information to the farmers and the PAPs. Information provided covered the following topics: o Land requirements for temporary expropriation o Potential impacts on the lands and assets o The valuation strategy o Grievance channels o Project time schedule

16 The Study is added to EcoConServ website only for the purpose of disclosure during the public consultation process. This allows the consultant to collect any relevant feedback. But official disclosure of the study is the full responsibility of GASCO

Page 58 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

10.3.2 RAP Disclosure after Bank Clearance

Upon the Bank clearance for the RAP, the document should be translated into Arabic. Gasco should disclose the Arabic and the English RAP on Gasco website as well as other locally appropriate locations (e.g.at local NGOs, at the agriculture directorates…etc.). Upon the finalization of the local disclosure by Gasco, they send a letter to the Bank authorizing the disclosure on the Bank InfoShop.

10.3.3 Information Disclosure during Implementation Phase  Land owners will be informed about the implementation schedule. They will be notified by the Agriculture Association and GASCO compensation Committee. The notification memo should be provided to them in a written form (in addition to a verbal form) as the majority of head of households are illiterate. All process should be documented and reported to the Bank in order to verify the implementation.  Disclosure of information in the religious places (church/ mosque) might be useful to the project. Based on different studies implemented in the rural areas, advertising through religious places is one of the most practical strategies to disclose information.  Disclosure of information in the local governmental units and the Agricultural Association (the Arabic RAP should be available at those local locations). In addition to the above-mentioned strategies, all information about the PAPs and how they will be affected is already included during the individual meetings conducted during the census.

10.4 Grievance Mechanism

Grievance system is also important to ensure that complaints are properly handled without delay that may negatively affect the project. Moreover, to ensure that information is shared transparently and that they are accountable to the hosting communities. A functioning GRM is considered to be a good feedback mechanism from the project affected persons and one tool of the citizen engagement.

GASCO operates a comprehensive GRM procedure: Leaflets, posters and brochures are prepared and distributed to the beneficiaries, NGOs, local governmental units, mosques and churches. Thus, sufficient and appropriate information about the GRM will be shared with the communities prior to the construction phase

The following procedures will be applied in order to have a clear grievance’s activities:

10.4.1 Institutional Responsibility for Grievances GASCO Compensation Committee and Social Development Officer (SDO) in cooperation with the agriculture Association, and the project manager will address all grievances raised by community people, particularly the ones related to resettlement activities.

Page 59 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

The main tasks of the Social Development Officer are:

1- Raise awareness about the grievances mechanisms among the PAPs 2- Collect the grievances received from different channel 3- Document received grievances 4- Direct the grievance to the responsible department to address the grievance 5- Follow up on the resolution 6- Document, report and disseminate outcomes of the grievances 7- Monitoring of grievances activities

10.4.2 Grievance tiers

The proposed mechanism is built on two tiers of grievances: First tier of Grievances: Project Manager (on Site) Eng. Abu el Kassem Foda (Edku / Abu Homos pipeline) - (01065511433) Project Manager (on Site) Eng. Tarek Mamdouh (Dairout power plant) (01008025500) - Project Manager (on Site) Eng. Abdel Fattah Abu Aly (Mahmoudya power plant) (01224954223) / Social Development Officer – Eng. Ahmed Galal (01211878678)

The Project Manager for each site / SDO is responsible to ensure that the GRM system is widely advertised and well explained on the local level. Moreover, s/he will follow up on the complaint until a resolution is reached. The turnaround time for the response/resolution should be 10 days and The SDO should inform the complainant of the outcome of the grievance.

It is worth noting that most of the previous experience of GASCO is suggesting that complaints are usually handled efficiently and resolved on the local level. In case the PAP is not satisfied with the resolution, the complainant shall submit the grievance to the second level of grievance.

Second tier of Grievances: On the level of GASCO headquarter (Mediation Committee)

If the aggrieved person is not satisfied with the decision of the first tier, he can raise the complaint to the Mediation Committee at GASCO headquarter. The Mediation committee should ensure a resolution is made within 15 days.

The above mentioned tiers are consistent with the World Bank’s policy OP 4.12. Providing multi-levels of tiers will result in amicable implementation of the project .It is a function of the project, to provide aggrieved people with an avenue for amicable settlement without necessarily pursuing a court case. The absence of first tier mechanism denies project affected groups the direct channel for grievance and delays resolution of disputes against the interest of both the PAP and the project.

Page 60 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

10.4.3 Grievance channels Due to the diversity of the context in different Governorates and the socioeconomic characteristics of the beneficiaries, the communication channels to receive grievances were locally tailored to address all petitioners concerns and complaints. The following are the main channels through which grievances will be received: 1. Project Manager (on Site) acts as the main channel for receiving complaints. He is available on the location. Most of the complaints raised to him/her are raised verbal. He should document all received grievances in written form, giving each grievance a serial number. 2. Hotline: 149 is the hotline in GASCO 3. GASCO Website for literate persons who have access to the internet 4. GASCO Compensation Committee and Mediation Committee

It is also important to note that local community leaders and NGOs/CDAs can be used to raise awareness among the local community to refer any complaints to the Project Manager or the Social Development Officer. Regular meetings with community members including influential stakeholders can also raise awareness about the grievance channels.

10.4.4 Response to grievances Response to grievance will be through the following channels 1. The same channel the complaint was submitted. 2. Response to grievances should be handled in timely manner (according the duration indicated for each tier), thereby conveying a genuine interest in and understanding of the worries put forward by the community. 3. GASCO should keep a record of complaints and results.

10.4.5 Monitoring of grievances All grievance activities should be monitored in order to verify the process. The following indicators should guide the monitoring process:

1. Number of received grievances per month (Channel, gender, age, basic economic status of the complainants should be included) 2. Type of grievance received (according to the topic of the complaint) 3. Number of grievances solved 4. Level of satisfaction with grievance resolutions 5. Documentation efficiency 6. Dissemination activities done 7. Efficiency of response to grievance provided ( efficiency in time and action taken)

A Grievance Monitoring Report should be developed on a quarterly basis in order to keep track of all grievances developed. The report should be developed by the SDO in the GASCO headquarter

Page 61 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

All grievances received shall be documented in a grievance register. The following table represents the main contents of such form:

Box 1: Grievance form Serial Number: Markaz Date: Gender of the aggrieved person Age of the aggrieved person Education of the person reporting a grievance Topic of grievance Actions to be taken (short term- long term) The referral of grievance Monitoring for grievance Figure 10-2 - Grievance Form

Page 62 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

11 Monitoring Arrangements

11.1 General monitoring by GASCO

Monitoring and Evaluation (M&E) are key elements to ensure the RAP is appropriately implemented. Main objective of monitoring and evaluation are:  Monitoring of specific situations or difficulties arising from the implementation, and the compliance of the implementation with objectives and methods as set out in the RAP.

Monitoring aims at tracking project implementation procedures. It will address the following aspects:

1- Monitoring the activities recommended in the RAP (valuation, awareness raising events, disclosure, dissemination activities). The following indicators should be covered: a. The valuation documents b. Awareness raising activities conducted c. Disclosure activities (number of participants, gender, age) d. Consultation activities (who were consulted, how many, age, gender, education) 2- Monitoring the status of the project affected persons. This will be applied through the following indicators: a. The type of impacts affected the PAP b. Compensation procedures c. Satisfaction with compensation and all related activities (valuation, compensation, grievances …etc) 3- Monitoring the process of grievances in order to identify the efficiency of livelihood restoration for agriculture loss. The proposed indicators are: a. No. of grievances received per each channel b. How they were handled c. Resolving the complaints d. Obstacles and barriers 4- Provision of all data needed to apply the mid-term evaluation and final assessment. The data will be prepared to an independent consultant.

Evaluation aims at ensuring that policies have been complied with and should provide feedback needed for adjusting strategic directions. The evaluation has the following specific objectives:

 General assessment of the compliance of the implementation of resettlement activities with objectives and methods as set out in this RAP,

Page 63 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

 Assessment of the compliance of the implementation of resettlement activities with laws, regulations and safeguard policies as stated above,  Identification of actions to take as part of the on-going monitoring to improve the positive impacts of the program and mitigate its possible negative impacts, if any.

11.2 Internal monitoring While Egyptian regulations do not indicate any monitoring or evaluation measures, the Bank’s OP 4.12 does. It embraces monitoring and evaluating the social and economic impact on the affected groups. It requires monitoring of the amounts of compensation paid, time taken to receive the compensation amount, number of grievances submitted and addressed and objective feedback on the overall impact of the RAP on the affected group. The OP 4.12 explains procedures for a monitoring and evaluation process that should be incorporated into the Egyptian law.

GASCO Environment and Social Department will monitor the implementation of the RAP process during all its phases. They will be responsible for ensuring efficient consultation with all land owners, their representatives, fairness of agreement, proper implementation of the compensation process and its effects on the PAPs socioeconomic status (that might be affected due to the project implementation). This will not be reflected on the financial cost as it is part of GASCO activities.

11.3 External monitoring and evaluation

Independent Consultant

GASCO develops in cooperation with the RAP consultant a detailed list of indicators as the RAP will be the baseline study for the project affected people. During the implementation of the RAP, an independent consulting firm should be contracted by GASCO in order to apply a rapid assessment for the activities done under the RAP, as well as, the impact of involuntary resettlement on the livelihood of community people.

This assessment aims at providing the guidance for GASCO in case of any obstacles that might affect the implementation of the RAP. The assessment should be implemented by an independent consultant twice along the life of the project. 6 months after the implementation of resettlement activities. This evaluation process will develop a mid- term review for the project activities. The final evaluation will be conducted by the end of resettlement activities. A final impact assessment report should be developed.

The assessment will also provide a full assessment for the activities done, including documentation, grievances mechanism, valuation, entitlement and the lessons learned. The independent consulting firm should be responsible for developing a final evaluation report by the end of construction. A full final evaluation report for all activities should be developed.

The following table presents some indicators to be measured during the external monitoring and evaluation process: Page 64 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table 11-1 - Examples of the Proposed Indicators Needed for Monitoring Activities Proposed indicators during RAP implementation

PAPS 1. Number of affected persons censed 2. Number of persons compensated for a) land b) crops c) trees, etc. 3. Number of persons not yet compensated ( by types of losses) 4. Number of consultations held 5. Number of grievances outstanding etc. 6. Level of satisfaction of affected people with the compensation 7. Number of awareness activities held Consultation 8. Number of participants (According to the communication channel) 9. Gender of participants 10. Age of participants 11. Occupation of participants 12. Their comments Grievances 13. Number of complaints received ( by types) 14. Number of grievances resolved 15. Number of complainants 16. Gender of complainants 17. Main complains raised 18. Number of solved complains 19. Number of complains left unsolved (reasons should be reported) Proposed indicators during the final evaluation and assessment 1. Total Number of persons compensated for a) land b) crops c) trees, etc. versus the baseline information provided in the RAP 2. Number of persons left with no compensation ( by types of losses) and reasons 3. Number of consultations held ( A full assessment about their characteristics of participants, reason for holding consultation, comments, where they held different consultation 4. Number of complaints received ( by types) (How they were dealt with 5. Number of grievances resolved 6. Number of grievances outstanding etc

Page 65 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

12 Entitlement Matrix

The project entitlement matrix (Table 12-1 – Mahmoudya Power Plant pipeline project compensation entitlement matrix) was developed based on the WB requirements. It is important to note that the compensation value developed by the Agriculture Directorate is based on the full market price prevailing in the governorate.

Page 66 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Table 12-1 – Mahmoudya Power Plant pipeline project compensation entitlement matrix No Type of Losses Level of Entitled Compensation Policy & Standards Type of Responsible Impact Person(s) compensation entity to be applied A. Loss of standing crops and trees 1 Loss of crops or Temporary Farmers /  Provide cash compensation for loss of crops or Full cash GASCO plants (complete or Individuals who trees at replacement cost provided by the compensation partial) loss of have formal agricultural directorate 17 provided prior to standing legal construction crops or plants ownership rights to land (Tenants or owners)

2 Loss of crops or Temporary Farmers /  Provide cash compensation for loss of crops or Full cash GASCO plants or access (complete or Individuals who trees at replacement cost provided by the compensation to them partial) loss of do not have agricultural directorate provided prior to all or part of formal legal construction arable and ownership grazing land rights to land located in the but have sub-project site temporary or leasing rights

3 Loss of standing Permanent Farmers or  Provide cash compensation for loss of crops or Full cash GASCO trees (complete or individuals who trees at replacement cost provided by the compensation partial) loss of have formal agricultural directorate provided prior to

17 GASCO ensures receiving the most updated list from the agricultural directorate at the start of the compensation process. From previous GASCO experience PAPs were satisfied by the prices of the directorate, no complaints have been received in this sense. It was also noted during the field work and the public consultations that PAPs indicated they are satisfied with the crop prices that the agricultural directorate will provide.

The agricultural directorate indicated that the prices are determined by a special committee that investigates the prevalent market prices and calculates the average of these prices that are satisfactory to the farmers. Finally the prices are approved by the governor and are updated every three years.

Page 67 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

standing trees legal construction ownership of the trees

4 Loss of standing Permanent Farmers or  Provide cash compensation for loss of crops or Full cash GASCO trees (complete or individuals who trees at replacement cost provided by the compensation partial) loss of don’t have agricultural directorate provided prior to standing trees formal legal construction tenancy of the trees

B. Loss of Structures or Buildings (Commercial, Business, Industrial, or Residential) 1 Those who Temporary The owner of  Provide cash compensation for loss of Cash GASCO possess impact during the unit who has constructions or rebuild the asset compensation buildings/ construction legal rights rooms on the route C. Loss of construction land 1 Those who Permanent The owner of  Provide cash compensation for loss of lands. Cash GASCO possess lands impact during the lands who Regardless to the legality status. The owners of the compensation used for the construction have legal/illegal lands should be compensated construction of and operation rights the valve rooms

Page 68 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Annexes Annex 1: Names of Project Affect Persons

Page 69 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Area Afficted No. Of Agriculture Name Fadan Kirat Sahm Type Of Crops Trees Governorate Association 28 Rice 0 El-Behira El-Marwha 28 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 10 Rice 0 El-Behira El-Marwha 36 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 10 Rice 0 El-Behira El-Marwha 10 Rice 0 El-Behira El-Marwha 9 Rice 0 El-Behira El-Marwha 10 Rice 0 El-Behira El-Marwha 28 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha Page 70 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

16 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 48 Rice 0 El-Behira El-Marwha 48 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 36 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 48 Rice 0 El-Behira El-Marwha 18 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 48 Rice 0 El-Behira El-Marwha

Page 71 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 18 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 2 12 Rice 0 El-Behira El-Marwha 18 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha

Page 72 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

22 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 2 12 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 18 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha

Page 73 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 Rice 0 El-Behira El-Marwha 10 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 2 12 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 1 12 Rice 0 El-Behira El-Marwha 1 12 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 3 12 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha

Page 74 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

2 Rice 0 El-Behira El-Marwha 9 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 11 Rice 0 El-Behira El-Marwha 9 Rice 0 El-Behira El-Marwha 9 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 1 12 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 2 12 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha

Page 75 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

16 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 2 12 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 36 Rice 0 El-Behira El-Marwha 36 Rice 0 El-Behira El-Marwha 36 Rice 0 El-Behira El-Marwha

Page 76 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

24 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 36 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha

Page 77 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

1 14 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 2 12 Rice 0 El-Behira El-Marwha 20 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 11 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha

Page 78 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 16 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 1 Rice 0 El-Behira El-Marwha 30 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 33 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha

Page 79 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 Rice 0 El-Behira El-Marwha 17 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 18 Rice 0 El-Behira El-Marwha 18 Rice 0 El-Behira El-Marwha 44 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 24 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 10 Rice 0 El-Behira El-Marwha 3 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 2 Rice 0 El-Behira El-Marwha 15 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 12 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha

Page 80 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 6 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 22 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 7 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 14 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 8 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 5 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha 4 Rice 0 El-Behira El-Marwha

Page 81 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

20 Rice 0 El-Behira El-Atf 10 Rice 0 El-Behira El-Atf 4 Corn 0 El-Behira El-Atf 4 Corn 0 El-Behira El-Atf 4 Rice 0 El-Behira El-Atf 6 Rice 0 El-Behira El-Atf 1 Rice 0 El-Behira El-Atf 4 Corn 0 El-Behira El-Atf 1.5 Rice 0 El-Behira El-Atf 1.5 Rice 0 El-Behira El-Atf 1 Rice 0 El-Behira El-Atf 6 Rice 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 16 Corn 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 10 Rice 0 El-Behira El-Atf 2 Rice 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 2 Rice 0 El-Behira El-Atf 8 Corn 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 3 Rice 0 El-Behira El-Atf 10 Rice 0 El-Behira El-Atf 10 Rice 0 El-Behira El-Atf

Page 82 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 Rice 0 El-Behira El-Atf 2 Rice 0 El-Behira El-Atf 5 Corn 0 El-Behira El-Atf 4 Corn 0 El-Behira El-Atf 12 Rice 0 El-Behira El-Atf 16 Rice 0 El-Behira El-Atf 10 Corn 0 El-Behira El-Atf 5 Corn 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 5 Rice 0 El-Behira El-Atf 8 Rice 0 El-Behira El-Atf 10 Corn 0 El-Behira El-Atf 0.5 Rice 0 El-Behira El-Atf 0.5 Rice 0 El-Behira El-Atf 6 Rice 0 El-Behira El-Atf 10 Rice 0 El-Behira El-Atf 4 Rice 0 El-Behira Kafr Amlet 4 Rice 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet

Page 83 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

1 Corn 0 El-Behira Kafr Amlet 1.5 Corn 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 2 Corn 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 0.5 Corn 0 El-Behira Kafr Amlet 0.5 Corn 0 El-Behira Kafr Amlet 0.5 Corn 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 12 Corn 0 El-Behira Kafr Amlet 6 Rice 0 El-Behira Kafr Amlet 5 Corn 0 El-Behira Kafr Amlet 4 Corn 0 El-Behira Kafr Amlet 2 Corn 0 El-Behira Kafr Amlet 6 Corn 0 El-Behira Kafr Amlet 10 Corn 0 El-Behira Kafr Amlet 6 Corn 0 El-Behira Kafr Amlet 18 Corn 0 El-Behira Kafr Amlet 10 Rice 0 El-Behira Kafr Amlet Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd

Page 84 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 8 Corn 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd 3 Corn 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 6 Corn 0 El-Behira Kafr Amlet 2 Corn 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 0.5 Rice 0 El-Behira Kafr Amlet 10 Rice 0 El-Behira Kafr Amlet 8 Corn 0 El-Behira Kafr Amlet 14 Corn 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 16 Corn 0 El-Behira Kafr Amlet 0.5 Corn 0 El-Behira Kafr Amlet 12 Rice 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet 12 Corn 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet

Page 85 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 Rice 0 El-Behira Kafr Amlet 9 Corn 0 El-Behira Kafr Amlet 1 Corn 0 El-Behira Kafr Amlet Corn 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 2 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet 1 Rice 0 El-Behira Kafr Amlet Al-Qasr Al- 0.5 Rice 0 El-Behira Mostagd Al-Qasr Al- 6 Corn 0 El-Behira Mostagd Al-Qasr Al- 5 Corn 0 El-Behira Mostagd Al-Qasr Al- 10 Corn 0 El-Behira Mostagd 6 Rice 0 El-Behira Eezb El-Qasr 6 Rice 0 El-Behira Eezb El-Qasr 1 Corn 0 El-Behira Eezb El-Qasr 6 Corn 0 El-Behira Eezb El-Qasr 6 Corn 0 El-Behira Eezb El-Qasr 6 Rice 0 El-Behira Eezb El-Qasr 6 Corn 0 El-Behira Eezb El-Qasr 6 Corn 0 El-Behira Eezb El-Qasr 10 Corn 0 El-Behira Eezb El-Qasr 6 Rice 0 El-Behira Eezb El-Qasr Page 86 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 Cotton 0 El-Behira Eezb El-Qasr 6 Rice 0 El-Behira Eezb El-Qasr 2 Rice 0 El-Behira Eezb El-Qasr 2 Rice 0 El-Behira Eezb El-Qasr 2 Rice 0 El-Behira Eezb El-Qasr 10 Rice \ Corn 0 El-Behira Eezb El-Qasr 10 Rice \ Corn 0 El-Behira Eezb El-Qasr 6 Rice 0 El-Behira Eezb El-Qasr Al-Qasr Al- 10 Rice 0 El-Behira Mostagd Al-Qasr Al- 3 Rice 0 El-Behira Mostagd Al-Qasr Al- 15 Rice\Corn 0 El-Behira Mostagd Al-Qasr Al- 4 Rice 0 El-Behira Mostagd Al-Qasr Al- 12 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 20 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 18 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 8 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd

Page 87 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 15 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 15 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd

Page 88 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 16 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 20 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 20 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 18 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 16 Rice \ Corn 0 El-Behira Mostagd

Page 89 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 3 Rice 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd Al-Qasr Al- 18 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 6 Rice 0 El-Behira Mostagd

Page 90 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 6 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 6 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 6 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 2 Corn 0 El-Behira Mostagd Al-Qasr Al- 5 Corn 0 El-Behira Mostagd Al-Qasr Al- 5 Rice 0 El-Behira Mostagd Al-Qasr Al- 5 Rice 0 El-Behira Mostagd Al-Qasr Al- 20 Corn 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 1 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 26 Rice \ Corn 0 El-Behira Mostagd Al-Qasr Al- 12 Rice 0 El-Behira Mostagd Al-Qasr Al- 22 Rice 0 El-Behira Mostagd

Page 91 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 16 Gardens 0 El-Behira Mostagd Al-Qasr Al- 20 Gardens 0 El-Behira Mostagd Al-Qasr Al- 28 Gardens 0 El-Behira Mostagd Al-Qasr Al- 12 Gardens 0 El-Behira Mostagd Al-Qasr Al- 12 Gardens 0 El-Behira Mostagd Al-Qasr Al- 8 Gardens 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 7 Corn 0 El-Behira Mostagd Al-Qasr Al- 4 Rice 0 El-Behira Mostagd Al-Qasr Al- 3 Rice 0 El-Behira Mostagd Al-Qasr Al- 8 Rice 0 El-Behira Mostagd Al-Qasr Al- 4 Rice 0 El-Behira Mostagd Al-Qasr Al- 2 Rice 0 El-Behira Mostagd Al-Qasr Al- 3 Rice 0 El-Behira Mostagd Al-Qasr Al- 7 Rice 0 El-Behira Mostagd Al-Qasr Al- 10 Gardens 0 El-Behira Mostagd

Page 92 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Al-Qasr Al- 10 Gardens 0 El-Behira Mostagd Al-Qasr Al- 10 Gardens 0 El-Behira Mostagd

Page 93 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Area Afficted Agriculture Name kirat Type Of Crops Governorate Association Assets 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 0.5 Corn El-Behira Abo Hems - Basntway 0.5 Corn El-Behira Abo Hems - Basntway Tarek Mahgoub El-Mashad, Mohammed Shehata El- 1.5 Cotton El-Behira Abo Hems - Basntway Mashad Ahmed Mahgoub El-Mashad, 7.5 Rice El-Behira Abo Hems - Basntway Abd El-Fatah Kamel Megahed 1 Cotton El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 0.5 Rice El-Behira Abo Hems - Basntway 0.5 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Watermelon El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 0.5 Cotton El-Behira Abo Hems - Basntway 0.5 Watermelon El-Behira Abo Hems - Basntway 0.5 Watermelon El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway Page 94 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

1 Rice El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 2 Corn \ Cotton El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 1 Corn El-Behira Abo Hems - Basntway 1 Corn El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 0.5 Rice El-Behira Abo Hems - Basntway 1 Cotton El-Behira Abo Hems - Basntway 0.5 Rice El-Behira Abo Hems - Basntway 1.5 Rice El-Behira Abo Hems - Basntway Six Palms Fruitful 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 1 Rice El-Behira Abo Hems - Basntway 0.5 Uncultivated El-Behira Abo Hems - Basntway 1.5 Cotton El-Behira Abo Hems - El-Eshra 1 Cotton El-Behira Abo Hems - El-Eshra 1 Corn El-Behira Abo Hems - El-Eshra 1.5 Rice El-Behira Abo Hems - El-Eshra 1.5 Rice El-Behira Abo Hems - El-Eshra 1.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra

Page 95 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Uncultivated El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Corn El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 4 Palms Fruitful Trees & 0.5 Uncultivated El-Behira Abo Hems - El-Eshra Kazina & Tree Decorations 1 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton \ Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Watermelon El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra

Page 96 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

0.5 Watermelon El-Behira Abo Hems - El-Eshra 0.5 Watermelon El-Behira Abo Hems - El-Eshra 0.5 Rice \ Corn El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Corn El-Behira Abo Hems - El-Eshra 0.5 Cotton \ Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Corn El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 2 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra Mata Sub Canal & Mata Canal 0.5 Cotton El-Behira Abo Hems - El-Eshra Walker 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra

Page 97 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Cotton El-Behira Abo Hems - El-Eshra 0.5 Potatos El-Behira Abo Hems - El-Eshra 2 Cotton \ Rice El-Behira Abo Hems - El-Eshra 0.5 Corn El-Behira Abo Hems - El-Eshra 2 Palm Fruitful 1.5 Rice El-Behira Abo Hems - El-Eshra 0.5 Fish Farm El-Behira Abo Hems - El-Eshra Abo Hems - Abo 1.5 Rice El-Behira Hawash Repair Abo Hems - Abo 0.5 Cotton El-Behira Hawash Repair Abo Hems - Abo 1 Corn El-Behira Hawash Repair Abo Hems - Abo 1 Rice El-Behira Hawash Abo Hems - Abo 2 Rice El-Behira Hawash Five Trees Guava Fruitful Abo Hems - Abo 1 Cotton El-Behira Hawash Reclamation 1 Rice El-Behira Abo Hems - Abo Reclamation Page 98 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Hawash Abo Hems - Abo 1 Cotton El-Behira Hawash Reclamation Abo Hems - Abo 3 Cotton \ Rice El-Behira Hawash Reclamation Abo Hems - Abo 1 Cotton El-Behira Hawash Abo Hems - Abo 1 Rice El-Behira Hawash Abo Hems - Abo 1 Cotton El-Behira Hawash Abo Hems - Abo 1.5 Cotton El-Behira Hawash Reclamation Abo Hems - Abo Reclamation 1 Cotton El-Behira Hawash Abo Hems - Abo Reclamation 1.5 Rice \ Corn El-Behira Hawash Abo Hems - Abo Reclamation 1 Cotton \ Rice El-Behira Hawash Abo Hems - Abo Reclamation 1 Rice El-Behira Hawash Abo Hems - Abo Reclamation 1 Cotton El-Behira Hawash Abo Hems - Abo 1.5 Rice El-Behira Hawash Abo Hems - Abo 1 Cotton El-Behira Hawash Abo Hems - Abo 1.5 Corn \Rice El-Behira Hawash Abo Hems - Abo 0.5 Uncultivated El-Behira Hawash 1 Cotton \ Corn El-Behira Abo Hems - Abo

Page 99 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Hawash Abo Hems - Abo 1 Cotton \ Corn El-Behira Hawash

Page 100 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

No of trees Existing crop Assets guava mango Citrus cotton rice corn Agriculture Name trees trees trees S F K S F K S F K association 70 30 New Edku 70 30 New Edku 35 15 New Edku 50 New Edku 15 45 New Edku 15 65 New Edku 70 New Edku 80 New Edku 80 New Edku 80 New Edku 70 30 New Edku 20 New Edku 50 New Edku 20 50 New Edku 80 New Edku 50 30 New Edku 30 New Edku 15 35 New Edku 50 New Edku 100 New Edku 250 New Edku 250 New Edku 100 New Edku

Page 101 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

100 New Edku 100 New Edku 850 New Edku 100 New Edku 100 New Edku 100 New Edku 0.5 New Edku 450 New Edku 150 New Edku 30 New Edku 0.5 New Edku 0.5 New Edku 450 New Edku 70 New Edku 5 5 New Edku 2 1 New Edku 6 New Edku 7 New Edku 3 New Edku 6 New Edku 8 New Edku 5 5 New Edku 5 5 New Edku 10 New Edku 10 New Edku 10 New Edku

Page 102 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

10 New Edku 10 New Edku 10 New Edku 10 New Edku 0.5 0.5 New Edku 4 4 New Edku 5 5 New Edku 10 New Edku 3 3 New Edku 3 2 New Edku 4 4 4 New Edku 4 4 4 New Edku 4 4 4 New Edku 2 New Edku 6 New Edku 12 New Edku 12 New Edku 12 New Edku 12 New Edku 12 New Edku 4 New Edku 4 New Edku 4 New Edku 10 New Edku 5 5 New Edku 10 New Edku

Page 103 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3 3 New Edku 0.5 0.5 New Edku 1 1 1 Al-wafaa house and Animal farming Al-wafaa barn 240m2 0.5 0.5 1 Al-wafaa 2 Al-wafaa 2 Al-wafaa 1 Al-wafaa Al-wafaa house 240 m2 1 Al-wafaa 1 Al-wafaa 1 Al-wafaa 1 Al-wafaa 2 Al-wafaa Al-wafaa house 150m2 Al-wafaa house 150m2 2 El-qosour 1.5 El-qosour 0.5 El-qosour 3.5 El-qosour 3 El-qosour 1 El-qosour 1 El-qosour 1 El-qosour 1 El-qosour

Page 104 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

3 El-qosour 3 El-qosour 0.5 El-qosour 1 El-qosour El-qosour 2 El-Baria 5,6 6 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 1 1 El-Baria 5,6 1 El-Baria 5,6 1 El-Baria 5,6 2 El-Baria 5,6 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 2.5 El-Baria 5,6 2.5 El-Baria 5,6 2.5 El-Baria 5,6 3 El-Baria 5,6

Page 105 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

1.5 1.5 El-Baria 5,6 9 El-Baria 5,6 1.5 1.5 El-Baria 5,6 1.5 1.5 El-Baria 5,6 2 El-Baria 5,6 2 kirat El-Baria 5,6 fadan guava 2.5 El-Baria 5,6 1.5 El-Baria 5,6 1.5 El-Baria 5,6 1.5 El-Baria 5,6 2 El-Baria 5,6 1.5 El-Baria 5,6 1.5 El-Baria 5,6 1.5 El-Baria 5,6 1.5 El-Baria 5,6 2 El-Baria 5,6 2 El-Baria 5,6 1.5 1.5 El-Baria 5,6 1.5 1.5 El-Baria 5,6 1.5 El-Baria 5,6 1.5 El-Baria 5,6 1.5 1.5 El-Baria 5,6 3 El-Baria 5,6 3 El-Baria 5,6 1.5 1.5 El-Baria 5,6 3 El-Baria 5,6

Page 106 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

6 El-Baria 5,6 2 El-Baria 5,6 1.5 El-Baria 5,6 1 1 El-Baria 5,6 1.5 1.5 El-Baria 5,6 El Sherka el 50 Zeraya El Sherka el 50 Zeraya El Sherka el 50 Zeraya El Sherka el 50 Zeraya El Sherka el 30 m Zeraya El Sherka el 50 m Zeraya El Sherka el 70 Zeraya El Sherka el 100 Zeraya El Sherka el 70 Zeraya El Sherka el 50 Zeraya El Sherka el 50 m Zeraya

Page 107 of 147

ESIA study for EG-GIZA North Power Project – El Wasta – Beni Suef Pipeline

Annex 2: Crop Prices list from Beheira Agricultural Directorate

Page 108 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Annex 3: Legal Framework governing the project

This project is governed by three main legislative frameworks, namely Egyptian generic and the WB OP 4.12, in addition the compensation system applied in GASCO which is closer to WB rules and regulations as GASCO applies some procedures that is more compatible with the WB regulations, especially, compensation for squatters and the crop owners (not necessary land owners), grievances and consultation procedures

- Egyptian Legislations Relevant to Resettlement and Compensation

The main legislations and guidelines that will be discussed under this section are as follows:

5- The Egyptian Constitution 2014 on protection of private property in articles 33 and 35 indicates that all types of private property are protected. Private property can be expropriated only for public benefit and in return of a fair compensation.

6- Law number 10 for the year 1990 and its amendments by law number 1 for the year 2015 on property expropriation for Public Benefit identifies natural projects as public benefit activities. It describes the acquisition procedures for private lands, assets and other affected materials. Article (20) of Law 10/1990 requires compensation to be determined on the basis of prevailing prices at the date of issuance of the expropriation decree. Provisions guiding the expropriation of private property (according to Law 577/54, Law No. 27 of 1956, Law No. 252 of the year 1960, and Law 577/54) indicate the following:

 Property expropriation is only applicable to tangible real estate property, there shall be no expropriation of movable possessions.  Expropriation is only to property privately, thus, public property is excluded from the procedures.  The expropriation is applicable to both land and structures.

The law describes the procedures for transfer of ownership as well as the grievance procedures.

According to the Law 10, 1990 the expropriation procedures involves (i) declaration of public benefit of the property by a Presidential Decree accompanied with a memorandum on the required project and a complete plan for the project and its buildings (Law 59/1979 and Law 3/1982 provide that the Prime Minister issues the decree) and, (ii) the decree and the accompanying memorandum must be published in the Official Newspaper. A copy for the public is placed in the main offices of the concerned local government unit.

Page 109 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

The grievance procedures indicated in the latest amendments by law 1/2015 indicate that after preparation of the census survey, the lists of affected persons should be announced at the relevant administrative units. The affected persons have the right to object to the included data within 15 days. The law also gave them 30 days after objecting to submit supporting documents for their claims. Otherwise the objection is denied. The Egyptian constitution allows any aggrieved person the right of access to Court of law as described by Law 10/1990. Law 10/1990 sets the requirements for disclosure of the names of the affected persons.

7- Petroleum pipelines Law 4/1988 The petroleum pipelines law 4/1988 states that the owner of a property should allow the passing of pipelines transporting liquid or gaseous hydrocarbons beneath the ground surface in accordance with the procedure mentioned in the executive regulations (Decree 292/1988). Article 2 of the law specifies that no buildings or trees, other than agricultural land trees, should be constructed or planted at a distance less than 2 m on each side of the pipeline inside urban and 6 m on each side of the pipeline outside the urban areas. If it is necessary to place the pipelines at a closer distance than what is specified in the law, it is allowed through a decision from the chairman of Egyptian General Petroleum Corporation (EGPC); taking into consideration the necessary safety precautions.

The law also specifies that if the activities done in accordance to the law will result in damage to the property, the owner has the right to a fair compensation to be decided by a committee formed by a decision from the Minister of Petroleum, and the executive regulations include the guidelines for compensation estimation.

8- Ministerial Decree number 346 of the year 2007 that enables the governors to form a committee in order to identify the valuation of compensation for crops and assets within the jurisdiction of the governorate.

- World Bank Involuntary Resettlement OP 4.12

The relevant principle policy objectives of OP 4.12 are:

 Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs.  Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits. Displaced persons should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs.

Page 110 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

 Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher.

Involuntary resettlement resulting from development projects, if unmitigated, will give rise to difficult economic, social, and environmental risks which may lead to: i) dismantling production systems, ii) impoverishing people when their productive assets or income sources are lost, iii) relocating people to environments where their productive skills may be less applicable and the competition for resources is greater, iv) resettling people into community institutions and social networks are weakened, v) dispersing kin groups and, vi) diminishing or losing cultural identity, traditional authority, and the potential for mutual help.

Eligibility Criteria: A project triggering OP 4.12 is required to develop a procedure, satisfactory to the Bank, for establishing the criteria by which PAPs will be deemed eligible for compensation and other resettlement assistance. The procedure includes provisions for meaningful consultations with: (i) Project affected persons and communities, (ii) Local authorities, and, as appropriate, (iii) Nongovernmental organizations (NGOs), and (iv) Grievance mechanisms.

The aim of including the eligibility criteria in the RAP is to ensure that PAPs who suffer a complete or partial loss of assets or access to assets shall be clearly defined and recognized as eligible for some kind of assistance, according to their legal rights to the land, if it can be established that they occupied the land before the claim cut-off date. The Bank OP4.12 specifically proposes general categories for eligibility, as follows:

1) Category One: Individuals who have formal legal rights to land are the owners of lands within the 28 km located in the agriculture area. 2) Category Two: Individuals, who do not have formal legal rights to land, but have a claim to such land or assets18 . They are mainly the tenants who have no documents that declare the tenancy relation with the owners

Valuation of Assets: In compliance with paragraph 6 of the OP 4.12, a Resettlement Action Plan (RAP) or a resettlement policy framework should apply to impacts covered under paragraph 3 (a) of Bank’s resettlement policy. Hence, the project covers the following measure:

(a) Measures to ensure that the PAPs are:

 Informed about their options and rights pertaining to resettlement,  Consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives,  Provided prompt and effective compensation at full replacement cost19 for losses of assets attributable directly to the project.

18 provided that such claims are recognized under Egyptian laws or become recognized through a process identified in the involuntary resettlement plan

Page 111 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

(b) If the impacts include physical relocation, the project includes measures to ensure that the PAPs are:

 Provided assistance (such as moving allowances) during relocation,  Provided with residential housing, or housing sites, or, as required, agricultural sites for which a combination of productive potential, locational advantages, and other factors are at least equivalent to the advantages of the old site.

(c) Where necessary to achieve the objectives of this policy, the RAP or RPF also includes measures to ensure that PAPs are:

 Offered support after displacement, for a transition period, based on a reasonable estimate of the time likely to be needed to restore their livelihood and standards of living,  Provided with development assistance in addition to compensation measures described in paragraph 6(a) of the OP4.12,  Provided with land preparation, credit facilities, training, or job opportunities.

According to paragraph 11 of the OP 4.12, preference should be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based.

19 "Replacement cost" is the method of valuation of assets that helps determine the amount sufficient to replace lost assets and cover transaction costs. In applying this method of valuation, depreciation of structures and assets should not be taken into account. For losses that cannot easily be valued or compensated for in monetary terms (e.g., access to public services, customers, and suppliers; or to fishing, grazing, or forest areas), attempts are made to establish access to equivalent and culturally acceptable resources and earning opportunities. Where domestic law does not meet the standard of compensation at full replacement cost, compensation under domestic law is supplemented by additional measures necessary to meet the replacement cost standard. Such additional assistance is distinct from resettlement assistance to be provided under other clauses of para. 6. If the residual of the asset being taken is not economically viable, compensation and other resettlement assistance are provided as if the entire asset had been taken. The alternative assets are provided with adequate tenure arrangements. The cost of alternative residential housing, housing sites, business premises, and agricultural sites to be provided can be set off against all or part of the compensation payable for the corresponding asset lost.

Page 112 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Annex 4: Grievance Form

Page 113 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Annex 5: Names of Participants in the Consultation Activities

Names of PAPs consulted during the census survey

ELMARWAHA

Ali Metwaly Shahawy Badr Mohammed Metwaly Shahawy Badr

Nadia Metwaly shahawy Badr Hanan Metwaly Shahawy Badr

Mahmoud Metwaly Shahawy Badr Abd El-Hakim Metwaly Shahawy Badr

Nahid Metwaly Shahawy Badr Youssef Metwaly Shahawy Badr

Hamada Metwaly Shahawy Badr Manal Metwaly Shahawy Badr

Youssef Abd El-Ghany Shahawy Badr Younis Abd El-Ghany Shahawy Badr

Maher Abd El-Ghany Shahawy Badr Montaser Abd El-Ghany Shahawy Badr

Sobhy Abd El-Ghany Shahawy Badr Metwaly Abd El-Ghany Shahawy Badr

Atef Abd El-Ghany Shahawy Badr Abdullah Abd El-Ghany Shahawy Badr

Ahmed Abd El-Ghany Shahawy Badr Abd El-Aal Abd El-Ghany Shahawy Badr

Sami abd el-ghany shahawy badr Samir mousa shahawy badr

Adel mousa shahawy badr Eid Mousa Shahawy badr

Noha Nabil Ibrahim Shahawy Badr Reda Shahawy Shahawy Badr

Page 114 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Mansoura Shahawy Shahawy Badr Amira Shahawy Shahawy Badr

Essam Shahawy Shahawy Setwaly Badr Amira Shahawy Shahawy Badr sherifa shahawy shahawy badr ossama shahawy shahawy badr nassra shahawy shahawy badr nagfa shahawy shahawy badr wageh ragab shahawy badr fady ragab shahawy badr khaled fathallah souliman el-kefl fathy fathallah souliman el-kefl mohammed fathallah souliman el-kefl salem fathallah souliman el-kefl tamam mohammed abd el-ghany el-senhory mohammed ismael moustafa el-mahr moharm ismael moustafa el-mahr gaber ismael moustafa el-mahr amal ismael moustafa el-mahr mohammed fathallah ali mohammed el-marakby ali fathallah ali mohammed el-marakby mohammed ali mohammed shehata masoud abd el-gelil el-tahawy wahida mansour abd el-gelil el-tahawy wahida mabrouka abd el-gelil el-tahawy wahida mahmoud mohammed khamis el-tahawy om el-saad mohammed khamis el-tahawy gomaa mohammed khamis el-tahawy azema fathallah souliman el-gefl mohammed mansour khamis el-tahawy saad mosbah abd el-razeq wahida awad abd el-razeq farag wahida hassan othman ahmed shaldam abd el-razeq farag wahida

Page 115 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline mohammed abd el-latif abd el-kareem wahida saad taher abd el-kareem wahida hania abd el-wakel qahida seria abd el-latif abd el-kareem wahida abd el-wahed abd el-latifa abd el-kareem wahida abd el-hamid abd el-latif abd el-kareem wahida abdullah abd el-razeq farag wahida saieda mansour abd el-kareem wahida el-safy abd el-aziz abd el-kareem wahida mohammed abd el-aziz ahmed okasha ahmed mohammed hessien ismael omara el-sayed ahmed mohammed omara el-shahat mahmoud hessien omara mahmoud el-shahat mahmoud omara gomaa el-shahat mahmoud omara mohammed saad mohammed omara ansaf saad mohammed omara darin saad mohammed omara ahmed saad mohammed omara tafida saad mohammed omara mabrouka saad mohammed omara el-safy mohammed hawary badr abd el-moniem mohammed hawary badr nabil abd el-hamid hawary badr badria abd el-hamid hawary badr abd el-hamid abd el-hamid hawary badr saieda abd el-hamid hawary badr baher abd el-hamid hawary badr saied mohammed hawarry badr fawzia abd el-moniem gaballah khatab mohammed omar gamal ragab ahmed mohammed darballah saieda ibrahim darbak El-Behira Joint Stock Company

Page 116 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline khalid khamis ibrahim el-akazy salem abd el-gawad awad saber saieda gomaa ibrahim saber hamdia abd el-gawad awad saber aziza abd el-gawad awad saber neama abd el-gawad awad saber mabrouka gomaa ibrahim saber khalid ibrahim gomaa saber saied ibrahim gomaa ibrahim saber mohammed ibrahim gomaa saber abd el-salam abd el-gawad awad saber madiha mohammed youssef sharaf el-dien ali saied ali el-wadeny etmad saied ali el-wadeny sanaa saied ali el-wadeny howida saied ali el-wadeny mohammed othman ahmed shaldam ragab othman ahmed shaldam diab othman ahmed shaldam ali othman ahmed shaldam gamal othman ahmed shaldam hayah othman ahmed shaldam hoda othman ahmed shaldam badr mahmoud younis badr asmahan ismael eissa soaad mohammed younis badr younis mohammed younis badr mohammed mohammed younis badr soaad mohammed younis badr saad mohammed younis badr safia mohammed younis badr sami mohammed younis badr ahmed mohammed younis badr mahmoud ibrahim el-sayed badr

Page 117 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline hessien ibrahim el-sayed badr mahasen mabrouk el-sayed badr reda ahmed el-sayed badr soaad ibrahim el-sayed badr khairya ibrahim el-sayed badr khamis ibrahim el-sayed badr youssef ibrahim el-sayed badr gomaa ibrahim el-sayed badr youssef ibrahim el-sayed badr ali ibrahim el-sayed badr omar ibrahim el-sayed badr ali ramdan ali badr hamada ramdan ali badr hassan ramdan ali badr nasr ramdan ali badr mamdouh ramdan ali badr moukhtar mansour ali badr aziza moukhtar hamada hamada el-tanekhy el-shahat ali mohammed el-khaiary maher mahmoud el-sabah el-khaiary fathy mahmoud el-sabah el-khaiary adel mahmoud el-sabah el-khaiary ashraf saied el-sayed el-khaiary saied el-sayed mohammed el-khaiary zinab saied abd el-rahman el-khaiary mohammed ibrahim mohammed anani anani ibrahim mohammed anani saada ibrahim mohammed anani taha ibrahim mohammed anani saleh ibrahim mohammed anani nora ibrahim mohammed anani el-sayda mohammed rezq shobat saied mohammed saad motawe moustafa ali mohsen moustafa

Page 118 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline mohsen ali moustafa Mohsen el-saied ali moustafa mohsen saad ali moustafa Mohsen ahmed abd el-salam moustafa mohsen shaaban abd el-hakim mohammed ibrahim abd el-hakim mohammed ibrahim abdullah abd el-hakim mohammed ibrahim mabrouk abd el-hakim mohammed ibrahim abo zaid mohammed hemida hamad owon mohammed hemida hamad mouza abd el-rahman youssef basal hamdia abd el-rahman youssef basal sherif abd el-rahman basal laila abd el-rahman youssef basal wafaa abd el-rahman youssef basal fawzia mousa abd el-atie basal faiza youssef ali basal hanan basiouny abd el-wahed zaghloul hanaa basiouny abd el-wahed zaghloul yasser rashad mousa el-ganainy moufida rashad mousa el-ganainy hanafy rashad mousa el-ganainy nour rashad mousa el-ganainy gomaa rashad mousa el-ganainy taha el-saied mousa el-ganainy el-sharnouby el-saied mousa el-ganainy fathia moustafa el-shamaa mosaad el-saied mousa el-ganainy atef el-sayed mousa el-ganainy ibrahim abd el-hamid ibrahim el-qady ahmed ibrahim abd el-hamid ibrahim el-qady mohammed abd el-maqsoud abd el-mawla sakran

Page 119 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline abd el-mawla abd el-fatah abd el-maqsoud abd samir abd el-satar abd el-maqsoud abd elmawla el-mawla rabha ahmed abd el-latif zalouk om el-saad ibrahimabdo zalouk gamal zahran fathallah amer gomaa hassan zahran amer fatma mohammed nasr el-sayed soaad hassan zahran amer mahmoud hassan zahran amer mohammed hassan zahran amer saad hassan zahran amer ahmed hassan zahran amer hanan hassan zahran amer mohammed hassan youssef attia khedra hassan youssef attia rabie abd el-rahman hassan farag el-gaml fatma mohammed khedr mohammed mohammed bayoumy khafagy hassan mohammed bayoumy khafagy fathia mohammed bayoumy khafagy karima mohammed bayoumy khafagy samia mohammed bayoumy khafagy zakia mohammed bayoumy khafagy khedra mohammed bayoumy khafagy om el-sayed hassan mousa hanem ibrahim razdaq ibrahim mohammed ali razdaq ragab mohammed ali razdaq hani mohammed ali razdaq nagia ibrahim abd el-aal magdy mohammed mohammed el-hanon saied hasafy mohammed ali

Page 120 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline hassan ahmed el-wadeny zinab saad el-khaiary mahmoud mesbah el-khaiary shawky mohammed hamid hamad sabry fathallah ali el-marakby badria mabrouk el-akhdar abd el-salam moustafa Mohsen mahmoud mohammed hassan el-sanhory abd el-hakim mohammed Ibrahim mousa ali badr ibrahim ramdan ali badr abd el-latif mohammed masoud el-tahawy nasrallah mohammed masoud el-tahawy mohammed masoud el-tahawy abd el-fatah youssef attia mohammed ali zidan bayoumy mohammed bayoumy khafagy mohammed mohammed hawary badr saad abd el-wahed zaghloul ali mohammed el-khaiary faiza gomaa Yasser ibrahim gomaa saber shehata youssef badr fakiha youssef badr baraka hamed anani attiat attia mohammed negm ramadan abd el-rahman hassan farag el-gaml mohammed moustafa el-sayed hadeer abd el-latif abd el-kareem waheda samir metwaly mohammed hamid hamid metwaly mohammed hamid mansour mesbah abd el-razeq waheda awad mohammed masoud el-tahawy mohammed masoud mohammed el-tahawy

Page 121 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline ibrahim mousbah abd el-razeq waheda awad defallah mousbah abd el-razeq waheda samir defallah mousbah waheda samah defallah mousbah waheda saieda defallah mousbah waheda om el-saad mousbah abd el-razeq waheda mabrouka mousbah abd el-razeq waheda afaf mousbah abd el-razeq waheda aziza mousbah abd el-razeq waheda ghalia mousbah abd el-razeq waheda khamis mohammed khamis el-tahawy alia mohammed khamis el-tahawy abd el-wanees mohammed khamis el-tahawy mansour mohammed khamis el-tahawy fatma mohammed khamis el-tahawy mohammed abd el-gawad awad saber essam abd el-gawad awad saber sabah abd el-gawad awad saber ahmed hassan ali shehata mohammed saad abd el-kareem waheda saied mohammed saad abdo hemdan mohammed saad abdo abaas mohammed zahran amer sabry mohammed zahran amer ragaa fathallah ali el-marakby noha mohammed zahran amer zakia mohammed zahran amer naiema mohammed zahran amer

ABO HEMS (BASNTWAY)

Mohammed Mohammed Ibrahim Basiouny Ragab el-Mashad

Salah Mahmoud El-Tabakh Ali Mahmoud El-tabakh

Page 122 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Rafiea Ahmed Hassan Fathy Abd El-Aziz Baqoush

Abd El-Qawy Abd El-Aziz Baqoush Sherifa Bahgat Mohammed

Mohammed Abd El-Maqsoud Abd Rabu Ayman Mohammed Farag Kola Ibrahim

Mohammed Fathallah Abo Tahon Gomaa Bakr Abo Tahon

Sami Gomaa El-Tabakh Hasafy Abd El-Hamid El-Tabakh

Salah Gomaa El-Tabakh Fathy Abd El-Maqsoud Abd Rabu

Saad Mohammed Baqoush Abd El-Satar Ahmed Baqoush

Nassra Abd El-Aziz El-Tabakh Ramadan Sayed Khalil Shahiwa

Youssef Abd El-Hamid Youssef Adila Abd El-Hamid Shehata

Mosbah Abd El-Salam Saad Abd El-Malek Mohammed Metrawy Karam

Karima Abd El-Salam Saad Abd El-Malek Mohammed Matrawy Karam El-Soghier

Mahmoud Matrawy Karam Mamdouh Matrawy Karam

Refaat Mamdouh Matrawy Fahmy Matrawy Karam

Ayman Matrawy Karam Mohammed Matrawy Karam

Fisal Matrawy Karam Mina Fawzy Souliman

Vilvia Fawzy Souliman Fawzy Souliman Yakoub

Page 123 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Mohammed Abd El-Fatah Ali Mohammed Mohammed Awad

Bakr Ibrahim Awad Moustafa Mohammed Mohammed Awad

Youssef Moustafa El-Hamamy Farag Mohammed Metwaly

Ahmed Ramadan Neamatalah Fathy Mohammed El-Zohery

Naema Mansour El-Sheikh Ismael Mohammed El-Zohery

Salah Hassan Abo Salem Fatma Mohammed El-Zohery

Adel Ismael el-Zohery Nabil Mohammed el-Zohery

Atef Mohammed El-Zohery El-Sayed Mohammed El-Zohery

Saied Mohammed El-Zohery Afaf Mohammed El-Zohery

Sami Mohammed El-Zohery Khedr Mohammed Ismael El-Zohery

Hamdia Mohammed Ismael El-Zohery Mohammed Mohammed Saad Ghanem

Zakia Abd El-Fatah Karsham Rezq Abd El-Salam Abu Zaid

Awad Abd El-Rehim El-Kholi Mohammed Ismael Gabalah

Ragab Abd El-Rehim El-Kholi Shama Ali Derbalah

Mohammed Ibrahim Salem Gomaa Ibrahim Salem

Ibrahim Salah Salem Wael Salah Salem

Yassin Ibrahim Salem Wesal Eid Mohammed Eid

Page 124 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Mohammed Mohammed Ali Mokadem Souliman Mohammed Ali Mokadem

Khalid Mohammed Ali Mokadem Ahmed Azoz Mokadem

Ali Azoz Mokadem Hamed Mohammed Ali Mokadem

Mohammed Abd El-Attie Ashiba Ismael Ahmed Behiry

Mohammed Ahmed Behiry Ahmed Mohammed Kamel

Ahmed Saied Salem Sabry Shahat Moursy

Boushra Shahat Moursy Sayed Ahmed Mansour Mokadem

Maher Mohammed El-Safy Saad El-Safy Abo Warda

Aziza Ali El-Sayed Khalil El-Saqa Khalil El-Sayed Farag

Refaat Mahmoud Tayel Ahmed Mahmoud Tayel

Salah Ahmed El-Saqa Ahmed Hassan Salem

Ibrahim Mahgoub Mohsen Mabrouk Awad El-Sisi

Ahmed Abd El-Bary Hamed Abo Donia Mohammed Basiouny Abd El-Latif Abu Donia

Abd El-Latif Abu Zaid Abd El-Latif Abu Donia Ragab Basiouny Abd El-Latif

Kawthar Abd El-Aziz Mohammed Saleh Saied Abd El-Aziz Saleh

Abd El-Satar Mohammed Abd El-Attie Abd El-Wareth Abd El-Aziz Mohsen

Abd El-Halim Mosbah Shehata Mansour Shehata Ismael

Page 125 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Awad Ahmed Mokadem Khalid Sayed Ibrahim Abd El-Mohsen

Abd El-Mohsen Saad Mohsen Mabrouka Abd El-Latif Abu Donia

Sheta Abd El-Latif Abu Donia Abd El-Latif Radwan Abu Donia

Moustafa Omar El-Hasawy Rezq Ali Oukasha

Mohammed Ibrahim Abu Zaid Fathy Mohammed Saad El-Gendy

Mahmoud Ahmed El-Saqa Mohammed Abdullah El-Tahan

Abd El-Kerim Abd El-Fatah Ghorab Ali Mohammed Abd El-Hamid

Ibrahim Mohammed Abd El-Hamid Abd El-Hamid Mohammed Abd El-Hamid

Mohammed Abd El-Fatah Ghorab Abd El-Kerim Abd El-Fatah Ghorab

El-Saied Ali El-Mezain Mohammed Mahmoud Sharaf

Abd El-Ghafar abd El-Fatah Ghorab Abd El-Attie Mohammed Dawood

Mohammed Mohammed El-Sayed Fahima Mohammed Ismael El-Zaiety

Fahima Mohammed Ismael Abo El-Souod Hala Fathy Marzouq

Ayman Abd El-Kader saied Bahia Ghanem Badr

EDKU (ELSHERKA)

Ahmed Ibrahim el-Gamal Younis Ibrahim El-Gamal

Gamil Ibrahim El-Gamal Khalid Ibrahim el-Gamal

Page 126 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Mohammed Saad Salem el-Labani Fatma Hamza Shawr

Mohammed Mohammed Selim El-Sayed Farag Galal

EDKU (NEW EDKU)

Sami Mohammed Henidi Mohammed Abdullah Berish

Abu El-Nasr Abu Abdullah Mohammed Menshawy

Hamada Mohammed Mansour Abd El-Nabi Hamed Ibrahim Tamam

Hamada Moursy Zaitoun Hassan Ibrahim Mahdy

Ahmed Helmy Toto Mohammed El-Sawy Zantakh

Mansour Henedi Saied Mashallah Hasson

Mohammed Ahmed Ramadan Abd El-Latif El-Sayed Henedi

Mohammed Ahmed Badr Mahmoud El-Sayed Yehia

Mohammed Masoud Kharaba Abd El-Samie Hassan Zaitoun

Gomaa Mdarah El-Sayed Mohammed Ismael Belal

Mohammed Ahmed Ismael Zaitoun Ahmed Ahmed Ismael Zaitoun

Ahmed Hassan Barmo Moustafa Abd El-Hamid Mady

Ahmed Abd El-Hamid Mady Mohammed El-Sayed Mohammed

Gomaa Ibrahim Mohammed Youssef Souliman Zaki Ebid

Page 127 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Mohammed Zaki Ebid Gomaa Zaki Ebid

Ahmed Zaki Ebid Fakih Mohammed Konah

Shehata Mohammed Souliman Galal Mohammed Ahmed Abu el-Hassan

Shaker Sedek Rabiee Fahim Ahmed Abu Hessien

Ramadan Fahim Ahmed Aziz Abd El-Aziz El-Moqamer

Awad Fawzy Saad Awad Abd El-Shafy Hassan Youssef

Hamadallah Basiouny Abu Saada Saad Mohammed Hassan

Sobhia Ahmed Awad El-Feqi Fatma Mohammed Bakr

Fathia Moustafa El-Garf Zahran Abd El-Wahed Zahran

Ibrahim Atta Ibrahim Ramadan Mohammed Basiouny

Saied Mashout Ibrahim Sobhia Ahmed Awad El-Feqi

Mohammed Saad Awad Abd El-Gawad Fawzy Saad Awad Abd El-Gawad

El-Sayed Mohammed Ali Hamad Ali Mohammed Abd El-Aal

Mohammed Abd El-Latif Sadek Shaaban Ahmed Abd EL-Gayed

Ahmed Hassan Tarbia Awad Abd El-Azim Farag

Amer Saied Amer Mahroush Amin Metwaly Ahmed Qassem

Ahmed Abd El-Rasoul Moursy Ibrahim Abd El-Razeq Abu El-Noor

Page 128 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Halawa Mosaad Mohammed Abd El-Fatah Mahmoud Abu Salam

Madeh Mahmoud Abo Salam Omar Mohammed Omar Abd El-Kader

Kamal Saied el-Bardany El-Sayed Abd El-Wahab Doma Hassan

Ibrahim Abd El-Wahab Doma Hassan

EDKU (ELWAFAA)

Mohammed Ahmed El-Qarnshawy Ali Mohammed Motawee

Beheri Ahmed Emara Mohammed Hamed Orabi

Abd El-Gayed Amer Abo Warda Nagha Saied Reyad El-Khashab

Khalid Ibrahim El-Akazy Ramzy Mohammed Attia Noufal

Gomaa Ibrahim El-Shami Matrawy saber Abd El-Samie

Gaber Matrawy Abd El-Samie Abd El-Salam Matrawy Saber

EDKU (ELQOSOUR)

Saad Ali Ismael El-Sayed Saad Nawar Mohammed Nawar El-Sakran

Khamis Mohammed Hassan Saad Mohammed Kanan

Mohammed Abd El-Maqsoud Nouir Mohammed Shaaban Slama

Abd El-Rahman Maragy Abd El-Hady Abd El-Hamid Abd El-Wahab Aboud

Mohammed Hamed Youssef Ashri Hassan Ali

Page 129 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Mohammed Mohammed El-Bably Rezq Ragheb Mousa

Fawzy Mohammed Zaid Ashour Abd El-Moniem Mohammed

EDKU (ELBARIA 5,6)

Abd El-Ghafar El-Sayed El-Kharoun Kamal Youssef bolah

Fathia Mohammed Fadl Ahmed Desouqy Mady

Tawfik Fahim Mohammed Selim Moustafa Abu El-Adala

Slama Ismael Slama Rabiee Ramadan El-Aiouty

Ramadan Abd El-Aziz El-Aiouty Baioumy Hassan El-Shamas

El-Sayed Ibrahim Mahmoud Souliman Mohammed Bardana

Saied Ali Ebish Mohammed Abd El-Gawad waslet

Gamil Mohammed Abu Roqia Dief Ismael Slama

Mohammed Hessien El-Feqi Fathy Mohammed Salit

Ahmed Mansour Salem Abd El-Qawi Mohammed Bardana

El-Sayed Omar Kabeel Shehata Sherif El-Azazi

Omar Abd El-Aziz Eida Abd El-Salam El-Refaey

Ibrahim Abd El-Rasoul Ahmed Abd El-Azim Mousa

Hamdi Mohammed Slama Abd El-Halim Abd El-Raouf El-Behiry

Page 130 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Abd El-Hay Abd El-Raouf El-Behiry Ahmed Mansour Hamed Youssef El-Shamy

El-Shamy Mansour Youssef El-Shamy Hamdy Mohammed Khalil Ibrahim

El-Sayed Hessien Abd El-Aziz Hassan Abd El-Salam

Ahmed Mohammed Abu El-Kheer Omar Abd El-Aziz Abu El-Kheer

Hamdi Khamis Maatoka El-Nahas Hamdi Ali Abd El-Kerim

Nasr Hassan Abd El-Kerim Mokhtar Abu Ali

Abd El-Baset Abd El-Salam Mohammed Hassan Abd El-Salam Mohsen

Mark Saied El-Shesh Qassem Awad Eqab

Saber Abd El-Aziz Zaitoun Ali Abd El-Aziz Abdullah

Mahmoud Ali El-Salamouny Abd El-Wahed Abd El-Rahman Abd El-Salam

Awad Abd El-Halim Mansour Attia Awad Eqab

Awan Abd El-Mawla El-Bardesy Mahmoud Taher Kheerallah

ELMARWAHA

Ali Metwaly Shahawy Badr Mohammed Metwaly Shahawy Badr

Nadia Metwaly Shahawy Badr Hanan Metwaly Shahawy Badr

Mahmoud Metwaly Shahawy Badr Abd El-Hakim Metwaly Shahawy Badr

Page 131 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Nahid Metwaly Shaahwy Badr Youssef Metwaly Shahawy Badr

Hamada Metwaly Shahawy Badr Manal Metwaly Shahawy Badr

Youssef Abd El-Ghani Shahawy Badr Younis Abd El-Ghani Shahawy Badr

Maher Abd El-Ghani Shahawy Badr Montaser Abd El-Ghani Shahawy Badr

Sobhy Abd El-Ghani Shahawy Badr Metwaly Abd El-Ghani Shahawy Badr

Atef Abd El-Ghani Shahawy Badr Abdullah Abd El-Ghany Shahawy Badr

Adel Mousa Shahawy Badr Noha Nabil Ibrahim shahawy Badr

Reda Shahawy Shahawy Badr Mansoura Shahawy Shahawy Badr

Amira Shahawy Shahawy Badr Essam Shahawy Shahawy Metwaly Badr

Ossama Shahawy Shahawy Badr Nassra Shahawy Shahawy Badr

Nagafa Shahawy Shahawy Badr Wageh Ragab Shahawy Badr

Fady Ragab Shahawy Badr Khalid Fathallah Souliman El-Kefl

Fathy Fathallah Souliman El-Kefl Mohammed Fathallah Souliman El-Kefl

Salem Fathallah Souliman El-Kefl Gaber Ismael Moustafa El-Mahr

Mohammed Ismael Souliman El-Kefl Mohammed Fathallah ali Mohammed El- Marakby

EL-ATF

Page 132 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Abd El-Qawy Mohammed Khamis Amin Ali El-Kafrawy

Soaad Abd El-Hamid El-Rakaby El-Sayed Ali El-Kafrawy

Attia Shehata El-Kafrawy Soaad Abd El-Hamid El-Rakaby

Rasmia Moghazy El-Rakaby Abd El-Hamid Abd El-Salam El-Rakaby

Dalal Abd El-Azim El-Kafrawy Ebtisam Abd El-Azim El-Kafrawy

Amany Abd El-Azim El-Kafrawy Mohammed Ezz El-Dien El-Kafrawy

Fahmy Abd El-Azim El-Kafrawy Bakr El-Sayed El-Kafrawy

Hekmat Ahmed Khater Shawkia El-Sayed El-Kafrawy

Nashwa Abd El-Azim El-Kafrawy Mohammed Ezz El-Dien El-Kafrawy

Sonia Abd El-Azim El-Kafrawy Mohammed Gamal El-Rakaby

Mohammed Mohammed Ali Naem Ramadan Ali Naem

Mahmoud Hassan Naem Sayed Ahmed Ouf Hasoub

Abd El-Aziz Abd El-Aziz Naem Ali Mohammed Naem

Shawkia El-Sayed el-Kafrawy El-Sayed Saad El-Manzlawy

Mohammed El-Sayed El-Manzlawy Abd El-Salam rouhi El-Rakaby

Khalid El-Sayed Taalab Zakia Mohammed El-Gweeny

KAFR AMLET

Page 133 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Sherif El-Sayed Ghanem Hanem Ahmed Abu Ibrahim

Ahmed Ibrahim Abu Ibrahim Mohammed Ibrahim Abu Ibrahim

Mahmoud Ibrahim Abu Ibrahim Shafika Saad Abu Ibrahim

Gomaa Saad Abu Ibrahim Zainab Saad Abu Ibrahim

Ghareb Mohammed Basher Sabry Mohammed Basher

Ali Gomaa El-Balahy Abdullah El-Sayed Abu Ibrahim

Abdo Gomaa Melegy Hala Ahmed Abu Ibrahim

Labiba Ahmed Abu Ibrahim Hedaya Ahmed Abu Ibrahim

Gad El-Sayed Abu Ibrahim Amin Mohammed Amin

Hoiam Gomaa Melegy Magda Gomaa Melegy

Hamed Abd El-Aziz El-Rashedy Mamdouh Khalil el-Safty

Samy Khalil El-Safty Mohammed Abd El-Aziz Fayed

Younis Rashed Moursy Salma Mohammed El-Sawy

Taha Tolba El-Balahy Saad Abdo El-Balahy

Abd El-Hady El-Sayed El-Sobky Moheb Abd El-Hamid El-Sobky

Mohammed Mahmoud Mowafy Shoukry Ahmed El-Sawy

Ragaa Mohammed El-Yamany Hekmat Mohammed Youssef

Page 134 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Farag Mohammed El-Meslmany

EZBET ELKASR

Mohammed Abd El-Aal Abd El-Aal Mohammed Mahmoud Ismael Wahban

Moushira labib Shawr Esmaat Labib Shawr

Eman Labib Shawr Hala Saber Eisa

Ahmed Nabil El-Daks Mohammed El-Sayed Sarhan

Abd El-Hafiz Abd El-Hakim El-Soubky Mohammed Abd El-Hakim el-Soubky

Farag Ahmed Khamis

EL-QASR EMOSTAGAD

Mohammed Mohammed El-Sharqawy Yassin Abd El-Hafiz Younis

Gimaa Abd El-Hafiz Younis Awad Mohammed Taha

El-Sayed Abd El-Hafiz Younis Ramadan Abd El-Hafiz Younis

Amer Ahmed Awad Kamel Tolba Teraz

Nwara Ali Abdo Attia Mohammed El-Qarshawy

Khalil Mohammed Teraz Adham Ahmed Mahmoud

Ramadan Abd El-Nabi El-Aarag Hassan Ahmed Abu Hossa

Ahmed Ali Shaheen Tarek Tolba Deraz

Page 135 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Makhlouf Mohammed Shaheen Othman Abd El-Latif

Ali Mohammed El-Mazien Kawkab Ahmed El-Aarag

Names of PAPs consulted during the field work (Interviews and FGDs)

Name of PAP Name of PAP 1. Maher Abd El-Ghany Shahawy Badr 2. Eid Mousa Shahawy Badr 3. Ossama Shahawy Shahawy Badr 4. Wageh Ragab Shahawy Badr 5. Saad Taher Abd El-Kerim 6. Hassan Othman Ahmed 7. El-Sayed Ahmed Mohammed 8. Salem Abd El-Gawad Awad 9. Khalid Khamis Ibrahim 10. Khalid Ibrahim Gomaa 11. Ragab Othman Ahmed 12. Badr Mahmoud younis 13. Abd El-Salam Abd El-Gawad 14. Omar Ibrahim El-Sayed 15. Reda Ahmed El-Sayed 16. Ali Ramadan Ali 17. Maher Mamdouh El-Sabah 18. Noura Ibrahim Mohammed 19. Abo Zaid Mohammed Hemida 20. Sherif Abd El-Rahman 21. Mabrouk Abd El-Hakim 22. Gamal Zahran Abdullah 23. Mohammed Hassan Youssef 24. Fatma Mohammed Khedr 25. Mohammed Mohammed Baioumy 26. Saad Hassan Zahran 27. Hany Mohammed Ali 28. Shawky Mohammed Hamid 29. Samir Metwaly Mohammed 30. Mohammed Ali Zidan

Page 136 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

31. Khamis Mohammed Khamis 32. Fatma Mohammed Khamis 33. Younis Ibrahim El-Gamal 34. Fatma Hamza Shawr 35. Mohammed Ahmed Badr 36. Gomaa Zaki Ebid 37. Awad Fathy Saad 38. Mohammed Hamed Orabi 39. Gaber Ismael Moustafa 40. Gomaa Rashad Mousa El-Ganainy 41. Mohammed Hassan Zahran Amer 42. Saied Mohammed Hawarry Badr 43. Saad Taher Abd El-Kareem Wahida 44. Samir Abdullah El-Safty 45. El-Soghair Mohammed Deraz 46. Mohammed Ibrahim Mohammed Anani 47. Gomaa Mohammed Khamis El-Tahawy 48. Masoud Abd El-Halim Abd El-Aal 49. Adham Ahmed Mahmoud Youssif 50. Montaser Abd El-Ghany Shahawy Badr 51. Khaled Fathallah Souliman El-Kefl 52. Mahmoud Hassan Zahran Amer 53. Mohammed Ibrahim Gomaa Saber 54. Taha El-Saied Mousa El-Ganainy 55. Amin Mohammed Amin 56. Bakr El-Sayed El-Kafrawy 57. Youssef Ibrahim El-Sayed Badr 58. Hassan Mohammed Bayoumy Khafagy 59. Abd El-Fatah Youssef Attia 60. Gamal Othman Ahmed Shaldam 61. Saied El-Sayed Mohammed El-Khaiary 62. Sobhy Abd El-Ghany Shahawy Badr 63. Mohammed Fakhry Hasoub

Page 137 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Names of participants in the Scoping Session for the ESIA and RAP

Names of Participants of the Public Consultation session for the ESIA and RAP

No. Name job Telephone

1. Mohammed Azzab Ramdan Rashid City Council - Environmental Affairs 01127708915

2. Abd El-Fatah Ahmed Hessien Chairman of Community Development 01000997860 Association in Kafr Awan

3. Ahmed Moustafa El-Beshbeshy Environmental Affairs Department 01005045374

4. Abdo Al-Sakndry Environmental Affairs Department 01212864417

5. Mohammed Sabry Hanafy Mahmoud GASCO 01006072559

6. Magdy Mohammed Amin Senior Research Department of Agriculture 01066484739

7. Abd El-Fatah Salem Agricultural engineer 01001826551

8. Ali Abd El-Baqi Head of the Department of orchards – Kafr El- 01228032814 Dawar

9. Ahmed Moustafa El-qazaz Director of Environment Department El- 01003575020 Behira water company

Page 138 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

10. Hessien Abd El-Aziz Hamed Director general - GASCO 01001663863

11. Ramy Shaaban Engineer -

12. Abd El-Samad Abd El-Moneam Ziada Public Environmental Health Monitor 01222858656

13. Fathy Fathy Galal Technician Environmental Affairs 01009027764

14. Shawky Mohammed El-Sayed Head of Department of Environment- EDKU 01280908525

15. Ahmed Abd El-Hamid Ibrahim Department of Environment - EDKU 01211909025

16. El-Sayed Hamad Khalil Administration official building and village 01284319235 development – El-Behira governorate

17. Hassan Abo El-Maatie Gomaa Agricultural Management 04529210061

18. Somaia Meselhy Damanhour Agricultural Management 01093092064

19. Ibrahim Mahmoud Ahmed El-Sayed General Manager of Safety - GASCO 01006072291

20. Abd El-Aziz Saied El-Meniawy Development Committee Mahmudiyah city 01225744923 administration

21. Amal Mahmoud Fouda Director of the Environmental Health 01266560297 Department of Health Management

22. Marwa Mahmoud Samy EEAA 01012267765

23. Yasser Mokhtar Ghazy EEAA 01001480306

24. Maher Shawky Masoaed EEAA 01008320707

Page 139 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

25. Mohammed Essam Ashour The Holding Company for Natural Gas 01008993058

26. Ahmed Souliman Ibrahim GASCO 01001777660

27. Mohammed Hamed GASCO 01129494811

28. Fathy Magdy El-Adwi State property – El-Behira Governorate 01022908817

29. Alaa Ahmed Seyam Urban Planning Engineer 01061213424

30. Emad Saad Mesharf Director of field work management 01094203842

31. Tawfik Abdullah Head of Projects Department 01064405824

32. Salah Mahmoud Ahmed El-Tabakh Farmer \ Head of the Agricultural Society of 01281651839 Homs Center

33. Mona Mohammed Ossama Shehab Inspector environmental management 01010388783 Environmental Affairs

34. Saied Abd El-hafiz El-Tony Farmer 01143741521

35. Dr. Magda Mohammed Amin Director General of the Environment 01223420095

36. Tahany Mohammed Director General of the orchards – El-Behira 01091296392

37. Ahmed Khalifa GASCO 01226099995

38. Amira Abdo El-Shaarany Rasheed Sons Association 01019711091

39. Hasan Fathy Ewis Care orchards engineer – Kafr El-Dawar 01225601940

Page 140 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

40. Khalifa Shehata Mahmoud Environmental Affairs – Kafr El-Dawar 01003912351

41. Ahmed Hessien Abd El-Fatah Ramdan Environmental Affairs – Kafr El-Dawar 01270917789

42. Sara Fathy Mohammed Ali Specialist Environmental Affairs 01091695217

43. Alaa Abdullah Abd El-Aziz Specialist -

44. Hassan Meshref Director General of the orchards -

45. Eisa Saleh Director of Environmental Affairs department -

46. Hieth Mohammed Helal Director of Environmental Affairs department -

47. Slama Zaki El-Eisawy Director of Environmental Affairs department 01274182035 – Abo Homs

48. Abeer Abd El-Maged El-Kholy Environment official Abu Homs -

49. Samir Ibrahim Shraby Investors Service Office 01062950628

50. Saied Mady El-Khiainy Director General of Social Solidarity 01006586044

51. Dalal Ibrahim Attia Engineer 01017411487

52. Sameh Mansour Projects and Planning Engineer - EGAS 01003435411

53. Manar Mohammed Abd El-Rehim Civil Engineer in The Technical Office of the 01002045332 General Department for irrigation

54. Rania Fawzy Abd El-Aziz Desouki Civil Engineer in The Technical Office of the 01060153939 General Department for irrigation

Page 141 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

55. Lamiaa Mohammed Ali Shaheen Director of the General Directorate of Water 01002660801 Resources and Irrigation

56. Mohammed Abd El-Ghany Mohammed Director General of the province of Great 01100839348 Ibrahim - GASCO

57. Mona Ahmed Ahmed El-Sayed Director of Development and Social Affairs 01007965556 Department

58. Saad Magdy Shubra Association 01009819081

59. Zainab Ahmed Ismail Amin Community Development Association - Kafr 01064870777 Awana

60. Dr. Mohammed GASCO 01110103154

61. Maged Abdullah Hassan Baioumy Director general - Safety Assistant 01011246934

62. Ramdan Gomaa Ibrahim Engineer Department of Agriculture 01228298100

63. Essam Saad Abd El-Aal Member of Governing Council of the Charity 01221915048 Association – Abo Homs

64. Mohammed Nassif Zaytoun Agricultural Management (orchards) 01112434282

65. Zainab Ahmed Zaytoun Secretary of El-Maadia village - EDKU 01287211385

66. Marwa Samir First Specialty environmental 01007909789

67. Basma Soubhy Khalil Specialty environmental 01227215791

68. Shaaban Mohammed El-Falah Head of the Department of orchards - Shubra 01272479489

Page 142 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

69. Hassan Hafez Head of the Department of orchards - 01225427171 Mahmudiyah

70. El-Saied El-Sayed Fadlallah Agronomist In agricultural management - 01226239842 Mahmudiyah

71. Abdullah Fathy Supervisor development - Derot 01221858300

72. Abdo Youssef Director of Environmental Affairs - Derot 01004849538

73. Sayed Mahmoud El-Sayed Director of Environmental Affairs 01003842201 Administration

74. Alaa El-Dien Ali Alaam Rashid Local Unit secretary 01003968143

75. Mohammed Ali El-Nada Environmental Management - Rashid 01066125045

76. Mohammed Sayed EEAA 01225622139

77. Reda Hassan Rahil EEAA 01023815098

78. Khamis Ahmed Nassif EEAA 01008502314

79. Hessien El-Saied El-Behira Health Directorate 01004000686

80. Sagi Samieh Ramdan Director General of the east of Alexandria 01005459658 district - GASCO

81. Marwa Abd El-Monaem Shaaban Engineer in state property 01117662399

82. Asmaa Khamis Nasser Engineer 01007011988

Page 143 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

83. Ahmed Mohammed Saleh Utility grids Information Center 01013788808

84. Mohab Mousa Vice President Abo Homs Center 01221909575

85. Samir Hamood Hassan Egyptian Company coordinator 01011270078

86. Qoutb Mahmoud Moustafa - 01111117376

Page 144 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Annex 6: Questionnaire Sheet

Affected people compensation Questionnaire RESETLLEMENT ACTION PLAN Natural Gas Lines to Additional Power Plants in Egypt Mahmoudya Power Plant Pipeline

Data is highly confidential and will not be used for purposes other than compensation

1. Governorate : Questionnaire code ......

2. District: ...... 3. Local Unit: ......

4. Village: ...... 5. Ezbit: ......

6. Agricultural Association Representative 7. Name of Agricultural Association ......

...

9. GASCO Representative 8. Date:----/----/------...... For data collector: the shaded part should be filled by GASCO 10. Total affected area in Qirate: ……………………………………………….. 11. Information about affected crops:------12. Type of impact:------13. Total compensation : 14. Date of compensation to be received ......

15. Signature of the technical person responsible for the census

Page 145 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

16. Information about the affected person

a. Crop owner ------b. Gender Male------1 Female------2 c. Age ]______[ d. Educational

status ]______[ ------e. Main occupation

]______[ ------f. Secondary

Occupation ]______[ ------g. Contact Data Address:------Mobile------Telephone:------

Legal ownership 1 17. Legal possession of Illegal owe\nership 2 Legal land tenant 3 land: Illegal land tenant 4 Other (specify------) 5 18. In case of legal possession, Does the affected person have all documents (Ask the agriculture association : ]______[ Yes all………….1 Yes some………………..2 No……………...3 Other Specify……………4 19. What are the documents available? Please enclose a copy of them (if possible) ...... ]______[ ......

Page 146 of 147

RAP study for EG-GIZA North Power Project – Mahmoudya Power Plant Pipeline

Annex 7: Due Diligence Report of the Land Acquisition of the Associated Facilities

Page 147 of 147