July 15, 2011
Queens Quay Working Group: Issue and Comment Matrix
Items requiring follow-up:
Ground floor animation strategy for the north side of Queens Quay Curb management: layby locations, parking strategy, bus management plan report back Martin Goodman Trail, including possible interim extension east of Bay Street Wayfinding and signage strategy Integration with TTC repair works Mitigation strategies to address microclimate Additional landscaping along Queens Quay Alternative power generation Waiting areas for bus pick-up and drop-off Space for deliveries at the rear of Harbor Square Timing of the Bremner Boulevard extension July 15, 2011
Queens Quay Working Group: Issue/Comment Tracking Matrix
Topic: Accessibility Question/Comment Meeting Date Notes Follow Up Status Required 1 Concern that spacing and texture July 20, 2010 No Addressed at the Working of the granite pavers (re: Group meeting #2 proposed granite for the south sidewalk-promenade). 2 Waiting area for those that cannot July 20, 2010 There will be timed traffic lights No Addressed at the Working cross the street within the Group meeting #3 allocated time
3 Concern for how the TTC platform August 17, 2010 Final design will introduce several No Addressed at the Working and the Queens Quay TTC tracks materials to encourage people to Group meeting #3 will be separated. cross at the designated crosswalks. 4 Concern that not everyone will be September 21, Suggested to provide detailed No Addressed at the Working able to cross the street within the 2010 methodology and examples at two or Group meeting #5 allocated time available October 19, three intersections. 2010 Initially addressed at Working Group November 4, Meeting #4; follow up at Working 2010 Group Meeting #5.
Topic: Cycling Question/Comment Meeting Date Notes Follow Up Status Required 1 Can bicycle parking be located July 20, 2010 The detailed design show that this No Addressed at the Working along the transition zone? August 17, 2010 is an appropriate location for Group meeting #3 bicycle parking 2 Ensure sufficient transition areas July 20, 2010 Final design will be introducing No Addressed at the Working re: between Martin Goodman Trail several visual cues to differentiate Group meeting #3 (MGT) and the TTC platform and between the pathways.
1
between MGT and pedestrian pathway. 3 Concern how will cyclists make left July 20 2010 In cases where north-south cycling No Addressed at the Working and right hand turns at the August 17, 2010 lanes exist street markings Group meeting #3 intersection (chevrons or similar) will be included within the intersection to aid cyclists making turns to or from Queens Quay. A waiting area is proposed for cyclists at key intersections. The area is 6mX 2m in size. 4 Would it be possible to continue September 21, This is outside the scope of the No Addressed at the Working the Martin Goodman Trail past Yo 2010 project. However, when that Group meeting #4 Yo Ma? portion of Queens Quay is scheduled for rebuild we are designing that transition so that the extension west to Bathurst Street is feasible. 5 Explore opportunities to better November 4, No Addressed at the Working integrate cyclists into traffic, 2010 Group meeting #6 especially at busy intersections November 16, 2010
Topic: Tree Planting/Landscape Treatment Question/Comment Meeting Date Notes Follow Up Status Required 1 Are trees adequately spaced? July 20, 2010 Design team has consulted a No Addressed at Working landscape architect and urban Group Meeting #2. arborist to confirm that there will be adequate space to support healthy and mature trees. Trees will be spaced for optimal growth and will also have ideal planting soil volume.
2
2 What tree species are being July 20, 2010 A landscape architect and urban No Addressed at Working considered? October 19, arborist will help determine the Group Meeting #6. 2010 tree selection. Have determined that both Plane tree or American Elm tree are potential choices for southside promenade.
3 Why are trees located on either July 20, 2010 It is mostly to do with the spacing No Addressed at Working side of the MGT and not along the of the trees. Large trees occupy a Group Meeting #1 promenade? lot of space and would not fit as an allee on the southside sidewalk/promenade. 4 How will water get to the tree August 17, 2010 There will be slots by the tree No Addressed at Working roots? rings which will collect rain water. Group Meeting #6. In the interim a watering system will be introduced. 5 Please explore additional planting November 16, Yes Will be discussed with the along Queens Quay i.e. raised 2010 working group in the coming planters. This important to bring April 26, 2011 months. green in the winter months.
Topic: Materials Question/Comment Meeting Date Notes Follow Up Status Required 1 Is there an alternate ground cover July 20, 2010 Grass is no longer proposed along No Addressed at Working other than grass for the TTC the TTC Right-of-Way in order to Group Meeting #10 ROW? provide an emergency access route. The TTC ROW will be concrete but WT is considering an enhanced concrete finish. 2 Will the proposed paving July 20, 2010 Design team researched many No Addressed at Working treatment be impacted by snow August 17, 2010 materials and granite was Group Meetings #1 and 2 plows in the winter months? selected because it is more durable and sustainable.
3
3 What is the maintenance cycle of August 17, 2010 Anticipate that some No Addressed at Working the promenade? maintenance required on an as Group Meeting # 2 needed basis. Repairs can be done locally reusing existing pavers. Granite pavers last 100 years. The materials were selected in part because they will are quite durable and will last a long time. 4 What is the maintenance cycle of August 17, 2010 asphalt path requiring standard No Addressed at Working the MGT? maintenance Group Meeting # 2
5 What is the honeycomb system August 17, 2010 Under the promenade there is No Addressed at Working and how will it help with the approximately 2 metres of soil Group Meeting # 2 longevity of the paving within milk crate looking objects treatment? called Silva Cells, which will support the growth of larger trees and will support minimal settlement over time. 6 Have you explored multi tasking September 21, Wayfinding/signage was initially Yes Will be discussed with the of poles in order to reduce clutter 2010 discussed at Working Group working group in the coming on the street? November 16, Meeting #6. months. 2010 7 Please provide more details November 4, 2010 Yes Will be discussed with the around the Martin Goodman Trail working group in the coming when available months.
8 Please explore including a ‘sharo’ November 4, 2010 No Addressed at Working concept for westbound bike path Group Meeting #6. at Spadina Avenue and the chevrons be located in the middle of the lane 9 Please explore the interim November 4, Waterfront Toronto will report Yes Will be discussed with the extension of the Martin Goodman 2010 back as information becomes working group in the coming Trail, east of Bay Street March 22, 2011 available months. Updated provided at Working Group Meeting #8
4
10 Has Waterfront Toronto explored November 16, 2010 Waterfront Toronto will share the No Addressed at Working strategies for preventing posters research that they conducted Group #7. being placed on the new light fixtures? 11 Please explore mitigation November 16, 2010 Yes Will be discussed with strategies to address microclimate the working group in the coming months. 12 Has Waterfront Toronto explored December 14, 2010 Teflon paint is not appropriate for No Documentation is teflon paint as a reduction use on wood poles. The coating available upon request. strategy for postering on light must be factory applied, then posts? heated to provide any hardness. In addition, it would not provide any protection from stapling. 13 Has Waterfront Toronto explored December 14, 2010 Yes Will be discussed with green power/alternative power the working group in the generation to light the trees along coming months. Queens Quay?
Topic: Intersection Design Question/Comment Meeting Date Notes Follow Up Status Required 1 Concern that cars could July 20, 2010 The third lane used for turning No Addressed at Working temporarily stop in the third lane. movements at intersections and Group Meeting # 2 will be clearly marked as such.
2 How can you promote a strong July 20, 2010 Need to accommodate trucks and No Addressed at Working pedestrian and cycling Email buses, so need large radii but not Group Meeting # 5 environment while correspondence at every intersection along accommodating wide curb radii Sept. 26, 2010 Queens Quay. for buses and large trucks? Need to still identify the key areas.
3 Where will storm drains be July 20, 2010 Locations still to be determined No Addressed at Working located? Storm drains should be but agree with rationale. Group Meeting # 5 located near pedestrian crossings
5
in order to reduce large puddles right at the intersection crossing. 4 Concern that layby will be used August 17, 2010 The laybys are intended to be No Addressed at Working for temporary stops used for loading and possibly Group Meeting # 3 short-term parking.
5 Concern that the mixed user August 17, 2010 Design team to explore No Addressed at Working group zones would not work strategies, including texture and Group Meeting # 3 effectively and would be signage, and report back to the confusing for the various users Working Group 6 Would like to receive more April 26, 2011 No Addressed on June 16, 2011 information about the Bay Street and Queens Quay intersection
Topic: Phasing Question/Comment Meeting Date Notes Follow Up Required Status
1 How will the Phase 1 project July 20, 2010 TTC confirmed that they No Addressed at Working be phased with TTC’s rebuild have a rebuild schedule Group Meeting # 2 of the tracks? and enough money to complete their scope of work. WT has planned to fund some of the design finishes. 2 If WT is unable to build the July 20, 2010 WT has committed to No area between Bay Street revitalizing the entire and Spadina Avenue, what length of Queens Quay will happen to the bike between Spadina and Bay lanes? Streets, which includes a continuous Martin Goodman Trail. A phased approach is no longer being considered
6
3 What is the proposed timing April 26, 2011 WT to confirm with City Yes Will be discussed with of the Bremner Boulevard the working group in extension? the coming months.
Topic: Wayfinding/Signage Question/Comment Meeting Date Notes Follow Up Required Status
1 It is very important that August 17, 2010 No Addressed at Working signs are introduced and Group Meeting #6. clearly visible in the mixed use zone 2 Where would signs for right August 17, 2010 Regulatory signage must No hand turns be located? be placed at prescribed locations in relation to the intersection. 3 Will the signs along Queens Email The number and location Yes Will be discussed with Quay be overly prescribed? correspondence of signs will be explored as the working group in September 26, 2010 part of the signage the coming months. November 16, 2010 strategy Initially discussed at Working Group Meeting #6 4 Future signage must be Email correspondence Yes Will be discussed with coordinated with other September 28, 2010 the working group in existing signage such as the November 16, 2010 the coming months. Waterfront Trail (bird, fish and leaf) markings
Topic: Streetscape Design Question/Comment Meeting Date Notes Follow Up Required Status
1 Would it be possible to September 21, 2010 To be explored by design No lower the sidewalk on the team northside of Peter Slip
7
bridge in order to mimic the wavedecks and animate space at Maple Leaf Quay?
2 Concern that the lay-bys are September 21, 2010 To be explored by design Yes Will be discussed with the not located in the October 19, 2010 team working group in the appropriate locations and/or November 4, 2010 Initially reviewed at coming months. that there are not enough March 22, 2011 Working Group Meeting along Queens Quay #8 3 What is planned west of September 21, 2010 Discussed by design team No Addressed at Working Bathurst Street; specifically at Working Group Meeting Group Meeting #4. the intersection of Spadina #4. Specifically, discussion Avenue and Queens Quay focused on intersection crossing for pedestrians and cyclists. 4 It is integral to maintain September 21, 2010 In consultation with key No vehicle access (servicing and Email stakeholders, the design drop-off) to York slip/pier correspondence team confirmed that the for the variety of marine September 23, 2010 existing informal access to user groups, including October 19, 2010 York Slip and the ferry businesses on the island, terminal will not be users of yacht club, pleasure precluded by the and charter boats. reconfigured street. Access to York Quay will be improved by the relocation of the kiosk and transformer at York Street. 5 Can we explore Pier 27 as a Email The relocation of the ferry No potential alternative to York correspondence terminal is not within the Quay for drop-offs for October 23, 2010 scope of this project. pleasure boats and yacht Improved access to the club users? water will continue to be explored through future endeavors. 6 Will the taxi stand in front of September 21, 2010 There will no longer be a No Queens Quay Terminal taxi stand in front of remain? Queens Quay Terminal.
8
The locations of taxi stands will be confirmed during the bus/curbside management plan. 7 What is the ground floor October 19, 2010 Under the Zoning Bylaw, Yes Will be discussed with animation strategy for the there is a requirement for the working group in north side sidewalk? Are 5 metre deep colonnade the coming months. there incentives in place to to support spill out and support spill-out onto the animation along the street? street. 8 Is it possible to introduce October 19, Initially discussed at the Yes Yes, this will be wider pedestrian crosswalk 2010 November 4th working integrated into the areas at busy intersections November 4, group meeting. design. Exact such as Bay Street? 2010 dimensions to be determined. 9 How is the Queens Quay October 19, 2010 Yes Waterfront Toronto streetscape design process Email will continue to being integrated with the correspondence provide updates to the TTC’s scope of work? December 04, 2010 Working Group. December 14, 2010 April 26, 2011 10 Is it possible to connect the October 19, 2010 Yes Will be discussed with Parliament Street bus with the working group in the future LRT line re: ability the coming months. to transform the area into a transit hub? 11 Coordination with BIXI bike October 19, 2010 Initially discussed at the No Addressed at Working program. Information Email November 16th working Group Meeting #10 session on how the program correspondence group meeting. works. November 19, 2010 12 Explore limiting the amount Email correspondence No Addressed at Working of laybys along Queens Quay October 23, 2010 Group Meeting #8 and promote other modes of transportation (other than cars), such as walking, cycling and public transit
9
13 Would it be possible to map Email correspondence Yes Will be discussed with out all the underground and October 23, 2010 the working group in other public parking facilities the coming months. along or near Queens Quay 14 Explore idea of dedicated October 19, 2010 Waterfront Toronto to No layby for the ferry terminal explore to accommodate drop-offs 15 Would Harbour Square be October 19, 2010 The removal of a turning No willing to remove one December 14, 2010 lane would require an turning movement amendment to the EA, eastbound at Bay Street which would delay the (shared right northbound or construction of the removal of eastbound left project. This option is no turn)? longer being considered. 16 Please include Robertson November 4, 2010 No This is not currently is Crescent on the schematic the scope of the design for Queens Quay project. 17 Please provide details on the November 4, 2010 Waterfront Toronto to No Addressed at Working outcome of the Yonge consult with City Group Meeting #8. Street, York Street and Bay Street ramp EA
18 Please discuss the parking November 16, 2010 Yes Will be discussed with strategy being proposed the working group in the coming months. 19 Please provide sufficient February 17, 2011 No Addressed at Working waiting areas for bus pick-up Group Meeting #8 and drop-off 20 While the transit portal is April 26, 2011 An interim bus service will No being constructed, could be provided during the there be an interim bus construction period. route provided?
21 Is there enough space for April 26, 2011 • WT to confirm Yes Will be discussed with deliveries at the rear of the working group in Harbor Square the coming months.
10