EIS 1204 Vol 2
ABO1 9976
Environmental impact statement: flood plain soil extraction and
river bank stabilisat ion at Elderslie I 9976 NVIIRONMENTAL I 4PACT TATEMENT I I VOLUME 2 I I FLOOD PLAIN SOIL EXTRACTION AND I RWER BANK STABILISATION I AT ELDERSLIIE
I Prepared For: WOODGRAND PTY LTD I I I I : OF I AL RQURCES ir JUN 1S I I
By: I HARVEST SCIENTIFIC SERVICES I
I March 1996 I I
I NVIIRONMENTAL I 1PACT TATEMENT I I VOLUME 2 I
I FLOOD PLAIN SOIL EXTRACTION AND I RWER BANK STABILISATION AT ELDERSLIE I I Prepared For: WOODGRAN!) PTY LTD I I I I I I I By: I HARVEST SCIENTIFIC SERVICES I I March 1996 I I
I ENVIRONMENTAL IMPACT STATEMENT I I I VOLUME 2 I I I FLOOD PLAIN SOIL EXTRACTION I AND RIVER BANK STABILISATION AT ELDERSLIE WOODGRAND PTY LTD I I I I Prepared by:
Harvest Scientific Services I Geotechnical, Environmental and Resource Consultants P0 Box 204 I CAMD EN NSW 2570 Telephone: 046 558796 I Facsimil... 046 556417 I March 1996 I I VOLUME 2
ENVIRONMENTAL IMPACT STATEMENT
FLOOD PLAIN SOIL EXTRACTION AND RIVER BANK STABILISATION AT ELDERSLIE
APPENDICES
Energy Statement
Conespondence from the Department of Urban Affairs and Planning
Technical Reports Prepared for this Proposal
Excerpt from 'Environmental Guidelines for River Management'
Experts Qualifications
PLANS (Located in Jacket)
Plan 1 Project Site - Cunent Configuration showing Proposed Extraction Limits Plan 2 Project Site - Proposed Post-Extraction Landform showing Final Contours and Bank Regrade Plan 3 Project Site - Soil and Water Management Plan Plan 4 Project Site - Revegetation and Rehabilitation Measures I I
I I I I LI Ll APPENDIX 1 I ENERGY STATEMENT I I I I I I LI H F APPENDIX 1- ENERGY STATEMENT I
BACKGROUND INFORMATION
Woodgrand Pty Ltd proposes to extend its current an extractive operations on property owned by the Company at Elderslie. The operation will supply a wide range of screened soil products for use in local and regional building and construction projects. Excavation will be principally undertaken by heavy earth moving plant including bulldozers, hydraulic excavators and front- end-lo aders. The soil products will be screened by a mobile power screen. The excavation and processing plant will produce an average of between 60,000 and 100,000 cubic metres of soil each year. The operation is expected to last a minimum of 5 years at the anticipated annual rate of extraction.
OPERATIONAL ENERGY REQUIREMENTS.
2.1 Operational Establishment
During the initial stages of the operation - which would entail the stripping of the initial extractionsite and the commencement of a working face, the following fuel driven vehicles will be used on site:
One D-8 Bulldozer I One Front-end Loader
2.2 Extraction
During extraction, the following fuel driven plant will be used on site:
I One D-8 Bulldozer (intermittently) andlor hydraulic excavator One Front-end Loader
I 2.3 Processing
During the extraction and processing stage, fuel will be consumed by at least one Power Screen.
2.4 Transportation and Soil Haulage
The Company estimates that trucks hauling the soil to various local and regional projects will I travel up to 500,000 kilometres per year. The distance travelled by service and staff vehicles is considered to be a very small percentage of the truck haulage. I 11 2.5 Estimated Fuel Usage
The estimated yearly fuel usage is summarised below:
Plant Fuel Consumption Litres/Year
One Dozer 3000 One Front-end Loader 13000 One Hydraulic Excavator 4000 One Power Screen 960
Pumps 960 Vehicular Movements (11500 trucks movements/year) 144000 Site Vehicles 500
Total (approx.) 166420
3.0 JUSTIFICATION OF FuEL USAGE
3.1 Extraction
The proposed method of extraction is the only feasible, practical method to produce the soil feed for the power screen.
3.2 Transportation
The choice of highway trucks to transport the soil products is the only feasible means to convey the sand products from the extraction area to the anticipated local and regional consumers.
LI 1 I I I I I I I I I
U APPENDIX 2 CORRESPONDENCE FROM THE DEPARTMENT OF URBAN I AFFAIRS AND PLANNING I I I I I I I I New South Wales Government Department of Urban Affairs and Planning
Mr Mart Rampe Gordon Kirkby Harvest Scientific Services Contact: P0 Box 204 W91/01 150/001 CAMDEN NSW 2570 Our Reference:
Your Reference: b
Dear Mr Rampe,
Proposed Soil Extraction, Lot 2 DP 228039, Springs Farm, Camden LGA.
Thank you for your letter of 24 November 1995 indicating that you are consulting with the Director General with regard to the preparation of an environmental impact statement (EIS) for the above development.
If development consent is required for the proposal and it is a designated development within the meaning of Schedule 3 of the Environmental Planning and Assessment Regulation, 1994, an EIS must accompany the development application to Camden Council. The EIS shall be prepared in accordance with clause 51 of the Regulation (see Attachment No. 1) and shall bear a certificate required by clause 50 of the Regulation.
Attachment No.2 is a guide to the type of information most likely to be relevant to the development you propose and should be used as a basis for preparing the EIS. Not all of the matters raised therein may be appropriate for consideration in the EIS for your proposal; equally, the guide is not exhaustive.
In addition, pursuant to clause 52 of the Regulation, the Director General requires that the following key issues be specifically addressed in the EIS:
the provisions of Sydney Regional Environmental plan No. 20 - Hawkesbury - Nepean River; the provisions of Sydney Regional Environmental Plan No. 9 - Extractive Industries; Macarthur Regional Environmental Study; Elderslie Sand and Soil Deposits Land Management Study;
Governor Macquarie Tower 1 Farrer Place, Sydney 2000 Box 3927 GPO, Sydney 2001
Telephone: 1021 391 2000 Facsimile: (02) 391 2111 V.
n Page 2
. the relationship of the existing development and the proposed extension to the operation, I including a review of the environmental performance of the existing extraction operations; . an assessment of the impact of the development on the local flood regime, any proposed I mitigation measures, and their potential impact on floodwater distribution; assessment of thepotential long term geomorphological impacts to the Nepean River and Springs Creek, including channel changes, alteration to flow and flooding; potential impacts to surface and groundwater quality and mitigation measures; an assessment of potential impacts to riparian vegetation and habitat values; results of consultations with: - Department of Land and Water Conservation - Environment Protection Authority - Hawkesbury Nepean Catchment Management Trust - Mine Subsidence Board - Department of Mineral Resources - National Parks and Wildlife Service
In preparing the EIS you should approach Camden Council and take into account any comments Council considers may apply to its determination of the proposal.
Should you require any further information regarding this matter please do not hesitate to contact us again.
Yours sincerely,
. Stephen Brown i Acting Manager Major Assessments and Hazards Branch As Delegate for the Director General I Department of Urban Affairs and Planning I ATTACHMENT NO 1 I STATUTORY REQUIREMENTS FOR ENVIRONMENTAL IMPACT STATEMENTS Pursuant to clauses 51 and 84 of the Environmental Planning and Assessment Regulation, 1994, I the contents of an EIS must include: SCHEDULE 2
I 1 . A summary of the environmental impact statement. 2. A statement of the objectives of the development or activity. 3. An analysis of any feasible alternatives to the carrying out of the development or activity, having regard to its objectives, including: (a) the consequences of not carrying out the development or activity; and (b) the reasons justifying the carrying out of the development or activity. I 4. An analysis of the development or activity, including: (a) a full description of the development or activity; and a general description of the environment likely to be affected by the development or I activity, together with a detailed description of those aspects of the environment that are likely to be significantly affected; and I the likely impact on the environment of the development or activity, having regard to: (i) the nature and extent of the development or activity; and (ii) the nature and extent of any building or work associated with the development or I activity; and the way in which any such building or work is to be designed, constructed and operated; and I any rehabilitation measures to be undertaken in connection with the development or activity; and (d) a full description of the measures proposed to mitigate any adverse effects of the I development or activity on the environment. 5. The reasons justifying the carrying out of the development or activity in the manner proposed, having regard to biophysical, economic and social considerations and the principles of I ecologically sustainable development or activity in the manner proposed, having regard to biophysical, economic and social considerations and the principles of ecologically sustainable development. I 6. Compilation, (in a single section of the environmental impact statement) of the measures referred to in item 4 (d). 7. A list of any approvals that must be obtained under any other Act or law before the I development or activity may lawfully be carried out. 8. For the purposes of this Schedule, "the principles of ecologically sustainable development" are as follows: I The precautionary principle - namely, that if there are threats of serious or irreversible environmental damage, lack of full scientific certainty should not be used as a reason for postponing measures to prevent environmental degradation. I Inter-generational equity - namely, that the present generation should ensure that the health, diversity and productivity of the environment is maintained or enhanced for the I benefit of future generations. Conservation of biological diversity and ecological integrity. I (d) Improved valuation and pricing of environmental resources. -2-
I Note: The matters to be included in item (4) (c) might include such of the following as are relevant to the development or activity:
I the likelihood of soil contamination arising from the development or activity; the impact of the development or activity on flora and fauna; the likelihood of air, noise or water pollution arising from the development or activity; I the impact of the development or activity on the health of people in the neighbourhood of the development or activity; I any hazards arising from the development or activity; the impact of the development or activity on traffic in the neighbourhood of the development or activity; I the effect of the development or activity on local climate; the social and economic impact of the development or activity; the visual impact of the development or activity on the scenic quality of land in the I neighbourhood of the development or activity; the effect of the development or activity on soil erosion and the silting up of rivers or lakes; I the effect of the development or activity on the cultural and heritage significance of the land. I I I I I I I I I I I I I I I I I I I APPENDIX 3 I TECHNICAL REPORTS PREPARED FOR THIS PROPOSAL
Li Hranisavljevic D, Nittim, R, and Cox, RJ:( 1996). Proposed Floodplain Soil Extraction - Option 5. Technical Report. February, 1996. Unpublished Report from the University of NSW I Water Research Laboratory for Harvest Scientific Services. Mucci, A (1996). Correspondence from Wirrimbirra Sanctuary
I Rampe, M (1995b): Report on Drilling, Thurn's Weir. Unpublished Report by Harvest Scientific Services for Woodgrand Pty Ltd.
I Thorns, M (1996): Geomorphological Assessment of Nepaen River and Adjacent River Bank - near Thurn's Weir. Unpublished Report for Harvest Scientific Services.
I Evans, N (1996): Elderslie Soil Extraction Project. Unpublished Report from Snowy I Mountains Engineering Corporation. I I I I I I I 1 I THE UNIVERSITY OF NEW SOUTH WALES WATER RESEARCH LABORATORY I I I I I I I WOODGRAND Pty Ltd PROPOSED FLOOD PLAIN SOIL EXTRACTION - OPTION 5 I I I by I I D Hranisavljevic, R Nittim and R J Cox I I Technical Report No. 96/03 I February 1996 I I I I I PREFACE I The work reported herein was carried out and is published under the direction of the I Director of the Water Research Laboratory, acting on behalf of the client, Harvest Scientific I Services. Information published in technical reports is available for general release only by permission I of the client and the Director. I I I I I I I I I I I I I I I I
I TABLE OF CONTENTS 1 PREFACE 1 I INTRODUCTION 1 PROPOSED SITE TREATMENT - OPTION 5 1 I NUMERICAL MODELLING 1 3. 1. Presentation of numerical modelling results 2 I 3. 1.1. Vector diagrams 3 3.1.2. Flow Distributions 3 I 3.2. Proposed site treatment - Option 5 3 UPPER NEPEAN FLOOD STUDY (1996) 4 1 BANK PROTECTION 5 CUMULATIVE EFFECTS OF BANK MINING S
I FREQUENCY OF FLOODING 6 I CONCLUSION 6 REFERENCES 8 I
I LIST OF TABLES
I Floods modelled Flow division between river channel and flood plain I Comparison of DLAWC and WRL models I I I I I I I I
I LIST OF FIGURES
1 Finite element model of Site Flood flow distribution in Thums weir reach I Velocity vectors - existing condition, 1 in 2 year flood Velocity vectors - Option 5, 1 in 2 year flood Velocity vectors - existing condition, 1 in 5 year flood I Velocity vectors - Option 5,1 in 5 year flood Velocity vectors - existing condition, 1 in 100 year flood I Velocity vectors - Option 5, 11 in 100 year flood Existing condition - flow distribution, 1 in 2 year flood I Option 5 - flow distribution, 1 in 2 year flood Existing condition - flow distribution, 1 in 5 year flood I Option 5 - flow distribution, 1 in 5 year flood Existing condition - flow distribution, 1 in 100 year flood I Option 5 - flow distribution, 1 in 100 year flood I I I I I I I I I I I I -1- 1 i. INTRODUCTION I This report was commissioned by Harvest Scientific Services on behalf of Woodgrand Pty Ltd as a continuation of the work described in Water Research Laboratory (WRL) Technical I Report No.95/05 "Woodgrand Pty Ltd, Bank Soil Extraction at Elderslie' (Nittim & Hranisavljevic 1995). The present report describes the results of numerical modelling of a I further development option, Option 5, which preserves more of the riparian vegetation.
2. PROPOSED SITE TREATMENT - OPTION 5
The site treatment proposed now (Option 5) preserves more of the riparian vegetation. The I bank between Ch 3,800 and 4,000 is regraded to a flatter 1 in 3 slope and revegetated, the crest being adjusted from the existing level of RL 69.0 to RL67.0 AHD. This regrading was I referred to as a "diversion bank" in Options 3 and 4 in the previous report.
1 3. NUMERICAL MODELLING The RMA-2 numerical model used in this study was described in the previous report (Nittim I & Hranisavljevic 1995). The model parameters were given in Section 3.1 of that report and have not been altered for this report.
The model schematisation is shown in Figure 1 (Figure 4 in Nittim & Hranisavljevic 1995). I As can he seen in the figure, only a small part of the flood plain on the southern bank was included in the model. The reasoning behind excluding most of the southern flood plain is that the area is essentially a backwater area with the flow pattern governed by the 90° bend I about 1 km upstream at Menangle Park. Figure 2 shows the expected flow pattern between the upstream and downstream bends. In the upstream bend the flow follows the high ground I on the outside of the bend (right bank) driving a slow moving circulation cell on the flood plain on the left bank. At the downstream end of the circulation cell the flow spreads out I onto the flood plain.. On the northern flood plain the main flow is at the toe of Springs Dam and on the southern flood plain the flow spreads over part of the flood plain driving another I circulation cell in Navigation Creek valley. The actual southern flood plain flow may extend somewhat further south than modelled but the effect of the reduced flood plain width in the model is expected to he negligible, especially as the evaluation of the modelling is based on I comparing the development option with the existing situation both of which are modelled with the same flood plain width. This analysis of the the flow pattern is based on past I experience with similar major river bends including observations on the Hunter and
I P -2-
Hawkeshury Rivers and on numerical modelling with RMA-2 of the bend at Paradise Point on the Lower Hawkesbury River.
The results from the previous modelling showed some anomalous velocity vectors near the downstream boundary for the 1 in 100 year average recurrence interval (ART) flood, existing condition (Figure 7, Nittim & Hranisavljevic 1995). The flow as it left the high ground at Ch 3,350 accelerated in the deeper water as shown by the vector plot, instead of slowing I down. Similarly there was a decrease in velocity downstream of Thurns Weir in the river channel. These anomalies have been traced to a problem with the computer plotting routine I - once the plotting routine was correctly adjusted these errors were eliminated. Figure 7 in this report showing the 1 in 100 year ART flood flow on existing topography now records a I reduction in velocity as the flow leaves the high ground on the flood plain at Ch 3,350 and also the velocity vectors downstream of Thurns Weir in the river channel stay at the same I magnitude instead of decreasing. This figure (Figure 7 in this report) should replace the incorrectly plotted Figure 7 in Nittim & Hranisavljevic (1995).
The existing topography which was previously modelled only for the 1 in 100 year flood, is now also modelled with the 1 in 2 and 5 year ART floods. The new design topography, I Option 5, is modelled with the 1 in 2, 5 and 100 year ARI floods. The characteristics of the floods modelled are described in Table 1 below.
Table 1 I Floods modelled
Hood Down stream I frequency Peak discharge flood level years m3/s in AHD I 1 in 2 620 66.0 1 in 5 2200 69.2 7200 72.7 I 1 in 100 1 1 3.1. Presentation of numerical modelling results The results of numerical modelling are presented as vector diagrams in Figures 3 to 8 and 1 the flow disinhutions between river channel and flood plain are summarised in Table 2 and plotted in Figures 9 to 14. I I I -3-
1 3.1.1. Vector diagrams The vector diagrams are plotted as pictorial representations of the flow patterns. They are I not an accurate record of point velocities and care is needed when comparing point velocities between different conditions. Because of the fmeness of the model mesh it is not I possible to plot a vector at every mesh node. The plotting program therefore plots the arrows a minimum distance apart and as the meshes for the existing conditions may he I different from the meshes for the Options, the arrows will not necessarily he plotted at the same locations. Groups of several vectors can, however, be safely compared.
3.1.2. Flow Distributions
Flow distributions were derived as before along a cross section line near chainage (Ch) I 3,700E by transferring node velocities from RMA-2 to a Lotus spreadsheet set up to calculate discharges heween nodes along the cross section line. The flow distributions are I summarised in Table 2 below and plotted in Figures 9 to 14.
I Table 2 Flow division between river channel and flood plain LT Flood Flow distribution % frequency River channel Flood Plain I years existing Option 4 Option 5 existing Option 4 Option 5 100 25 24 27 75 76 73 I 5 58 45 47 42 55 53 I 2 89 82 85 11 18 15 3.2. Proposed site treatment - Option 5
I Comparison of vector plots of the existing condition and Option 5 shows that for the 1 in 2 year ARI flood there is very little difference (Figures 3 and 4). Springs Creek is flooded by I backwater from the river and no flood water flows along the base of Springs Dam. More of the flood plain upstream of Ch 4000E is flooded under Option 5 but the flood plain I velocities are quite similar. At the comparison cross section line (Ch 3700E) the flow is mostly confined to the river channel and the area excavated in Option 5 is a backwater with no flow through it. As shown in Table 2 there is a reduction in river channel flow of 4% LI from the existing condition and a corresponding increase in flood plain flow. This increase is I considered to he insignificant. I I -4-
For the 1 in 5 year ART flood there is a concentration of flow at the toe of Springs Dam in the existing condition whereas in Option 5 there is a more even spread of flow over the flood I plain (Figures 5 and 6). This is due to the even cover of vegetation on the flood plain in Option 5 compared with the minimal tree cover in the existing state. Flow distribution at the comparison line shows an increase in flood plain flow from 42% of the total to 53%, an I increase of 11%. This increase in flood plain flow is, however, accompanied by a reduction in flood plain velocity and it is expected that there will be no adverse effects on the flood plain.
For the 1 in 100 ART flood the velocities are significantly reduced at the base of Springs Dam by Option 5 (figures 7 and 8). Elsewhere on the floodplain the velocities are slightly I lower for Option 5. This is because the increased roughness of the fully vegetated flood plain reduces the velocity but the greater depth of flow maintains the total flow on the floodplain. At the comparison cross section line the proportion of flow on the flood plain is I practically the same as for the existing condition (less than 2% change).
Floods higher than 1 in 100 year ART have not been modelled, fistly because no data had been published when the original study was carried out and secondly the impact of the I development decreases as the flood level increases, the excavation depth on the flood plain becoming a smaller proportion of the flood flow depth. Also, it must he remembered that I floods of say 50 years and higher recurrence interval are regarded as natural disasters and some damage of the river banks or flood plain through scour, debris or deposition must he expected. For instance the minor flood of July 1975 (1 in 6.5 year ART, WRC 1986) washed I away the Cowpastures Bridge, showing that damage, especially from debris must he I expected in any flood. 4. UPPER NEPEAN FLOOD STUDY (1996)
The report of this study by the Department of Land & Water Conservation (DLAWC) was released on 12 February 1996. The Executive Summary and results of numerical modelling I near Thurns weir were supplied to WRL by Harvest Scientific Services. The numerical modelling in that study was carried out using the one dimensional MIKE 1 1 model. The I comparison cross section line for RMA-2 modelling (Figure 1) is about 400 metres upstream of cross-section B9 of the MIKE 1 1 model. This is sufficiently close for comparing the two I models. Comparisons are made for the 1 in 100 year flood in Table 3 below. I I -5-
Table 3 Comparison of DLAWC and WRL models
MIKE11 (DLAWC) RMA-2 (WRL) flood level 72.7 in AHD at CS B9 72.6 rn AHD at CS 139 left hand flood plain velocity 1.5 rn/sec no flow assumed river channel velocity 1.9 rn/sec 1.8 rn/sec Fight hand flood plain velocity 1 1.0 rn/sec 2.4 rn/sec
As can he seen the flood levels are practically equal, WRLs flood level being adopted from the Camden Flood Plain Study (WRC 1986). WRL assumed no flow on the left hand flood (L/H) plain as explained in Section 3. The river channel velocities are practically equal for the two models but the right hand flood plain velocity derived by WRL is higher than that obtained by DLAWC. This is the consequence of assuming no flow on the left flood plain as explained in Section 3. As shown in Figure 2 some flow probably does take place on the L/H flood plain and the WRL estimate of RJH flood plain velocity is probably too high while the DLAWC estimate is probably too low. For the purposes of this report, which is to compare Option 5 with the existing condition, this is of no consequence since we are comparing like with like.
BANK PROTECTION
In the previous report WRL argued against using toe protection (Nittirn & Hranisavljevic 1995, Section 3.4.2) on the basis that it may initiate erosion downstream on the opposite hank. This was based on experience with rock bank protection; the softer approach of using "brushing" to protect the toe as suggested by Dr Thorns is less likely to cause downstream erosion. The Water Research Laboratory has no experience with this type of toe protection.
CUMULATIVE EFFECTS OF BANK MINING
As was described in the previous report (Nittim & Hranisavljevic 1995, Section 4.3) about I 7.4 km of river hank mining including some 4 km of river bed mining has taken place or is under way between Cohhity and Menangle under the present mining policy. At the I Woodgrand site 980 metres of hank have been mined under previous permits. The present proposal, Option 5, involves no further hank mining, the mining taking place on the flood I plain away from the river hank. The proposed development thus does not create any sediment sink.s and does not afièct the sediment budget of the river and therefore does not [I I -6-
I contribute to any effects that the past and present bank mining may have had or will have in I the future. FREQUENCY OF FLOODING
I The frequency of flooding on the flood plain is controlled by the level of the river hank while the extent of the flooding is controlled by the level of the flood plain. For a particular point I on the flood plain, if its level is lowered by mining then it may he flooded more frequently if there is a section of river hank low enough to let the flood waters onto the flood plain. The I areas mined under Option 5 drain to Springs Creek, which is open to the river. As can he seen in Figures 9 to 11 some of the land that was just flooded by the 1 in 5 year flood (Figure 11) is now flooded by the 1 in 2 year flood. On the other hand the 1 in 10 year, which reaches a height of 71.6 m AHD will not flood a larger area as no land above RL70.0 m AHD will he excavated. The increase in the extent of flooding will he confined to floods Li in the range of 1 in 2 years to 1 in 10 years.
L CONCLUSION
A new development option for the Woodgrand site, Option 5, is proposed by Harvest Li Scientific Services. This Option, which preserves more of the riparian vegetation has been compared with the existing condition for 1 in 2, 5 and 100 year floods by two dimensional numerical modelling. The numerical modelling indicated that the magnitude of the velocities on the flood plain was significantly reduced by the proposed Option 5 while in the river P channel the velocities remain constant or are slightly reduced.
The modelling showed no change in the distribution of flow between the river channel and I the flood plain for the 1 in 2 and 1 in 100 year floods. Although an increase in flood plain 1 flow was deduced for the 1 in 5 year flood there is a decrease in flood plain velocity due to L.J the higher flood plain roughness. For the 1 in 10 and 20 year floods the increases in flood plain flow will he smaller as the depth of flooding increases and the depth of excavation I becomes a smaller proportion of the flood depth. It is considered that the changes in flow distribution are small enough for successful rehabilitation of the site to he carried out.
An important benefit of the revegetation and reshaping of the ground under Option 5 is that rl the high velocities that at present exist at the toe of Springs Dam will he significantly reduced thus substantially reducing the risk of scour that exists at present. I As no hank mining will he undertaken in Option 5, no new sediment sinks will he created and the sediment budget of the river will not he changed. Consequently there will he no I -7- addition to the effects of present and past bank mining that may have been cumulating over time.
The frequency of over bank flooding will not be increased by Option 5 although hack water flooding up Spring Creek will inundate a larger the area for floods smaller than 1 in 10 years. This is considered not to he detrimental to the successful rehabilitation of the mined area.
9. REFERENCES
Dept of Land and Water Conservation (1996), Upper Nepean flood study'
Nittim R & Hranisavljevic D (1995), 'Woodgrand Pty Ltd, Bank soil extraction at Elderslie", WRL Technical Report 95/05
Water Resources Commission, NSW (1986), "Camden flood study report" ------
1100
1000
900
800
C-,
z0 700z
600
000 273900 274000 274100 Z74ZOO .'4iUU i/44UU e (4CUU C (4DUU 273100 273200 273300 273400 273500 213600 273700 273800 IASflNG 41
Menange Pa
QT
CALM 1975 AIR PHOTO
LEGEND
I 1 I I 1 1 HIGH GROUND
0 500 l000m I - FLOW DIREGTON SCALE I
I FLOOD FLOW DISTRIBUTION IN THURNS WEIR REACH FIGURE 2 I ------
.75o
1100
000 CROSS SECON ONE
Sprin trn 900 70 68 66 --- / - 66
64
CHANNEL '/ lIe; 66 64
600 / .-NEPAN Thurns/ Weir - -
500 274000 274100 2 74200 274300 274400 274500 2746uu 27 1 00 273200 27330C 273400 Z73e0U Z I.SuLlu 4fitm, 273800 273900 0 100 200m -1 EXISTCON 2 AR! N=0 030, 0025, 0090 SCALE
ii
VELOCITY VECTORS - EXISTING CONDITION m 1 IN 2 YEAR FLOOD ------
-3 750 1100
1000 GROSS SECTION LINE
Sp ong S Dam 900
L -64 65 6 - \ 64- -62 800
-6/ 66
64 60
6; 61 700 64 CHANNEL 67 - -
T 600 - .- T hums Woo
500 .------_-- 273101 27320C 277300 273100 273500 273800 273700 273800 273900 274000 274100 274200 274300 274400 274500 274600 FST1NC
0 100 200m NEWDESIGN 2 AR! N=0 030. 0025. 0090
SCALE
-Ti C) C VELOCITY VECTORS - OPTION 5 1 IN 2 YEAR FLOOD ------
4 000
1100 - TPlijIIP iI)IIII T1 11TI )IIIIITIIIIJIIIIIIIIIIIII)ITTIIIIIIIIIIIIJIIT
CROSS SECTION LINE 1000 -
800 - - - 111 4-
800
7)0 66
45
Thurns Weir
500 273100 273200 273300 273-400 273500 273800 2(3700 4J 1.1000 Id t.JVUU 2(4U)II) 2)400 074000 274300 274400 274500 274600 E'T0)0 0 100 200m I. EXISTCON 5 ARI N =0.030, 0 025, 0.090 SCALE
11
c VELOCITY VECTORS — EXISTING CONDITION 1 IN 5 YEAR FLOOD a' ------
1100
I 000 GROSS SECTION LINE
Springs . Dam 800
70
64
800 61 464
700 CHAYNEL -67 -
54
600 NEFFAN
Thurns Weir -
500 273103 272200 272300 273400 27300 273630 22702 573800 570800 014000 014100 014504' 274300 274400 274500 274600 NC 0 100 200ii N}:WDE3i 5 API N=0 030. 0 025. 0090 SCALE
m VELOCITY VECTORS - OPTION 5 1 IN 5 YEAR FLOOD ------
4000
100 =
4— 4- CROSS SECTION LINE 4-- 4 HE - HIGH VELOCITIES AT BASE 4- OF SPRINGS DAM 4- 4— -- 8 - Sprin s 00 -66
. 68
800
tiNEL 70'
64 4-
44 601 ( - * Thurns Weir - - -
I -- -- -i-- 300 ,00 273100 277200 073:00 4Ii4U -- _ 0 100 200.
EXISTCON 100 AR! N'- O 030, 0025. 0090 *CALE
11 0 C VELOCITY VECTORS - EXISTING CONDITION m 1 IN 100 YEAR FLOOD ------
4 000
1100
4- 4- 4- 4--
1000 4- 4-- - •-- - CROSS SECTION LINE -
4- 4- 4- 4--- * REDUCED VELOCITIES AT BASE OF SPR GS DAM 4 SprIngs - Dam - Poo 4 4- 4- 4- 68 4- 4,- 4-- 4---4- ---- - 4- 4- - '- - 4-- - 4- 4- -- 4 4- 4- - = 4- - - 4- 4 - • 4- 4- 4- - J-_ - 66, 64 4-. 4- 4__ 4- .- 4- 4- - 4- 4- 4- 4- -4 •_ _- 4- 4-.4-- 4- 4-- i- 4- 4- 4-- •- 44 - 4- - 4- 00 4-61 4- 4- 4-4 700 --- - - - 4- 4- - - -. - 4- 4- 4-4-i - - 4 . • • - 4 4- - - 4- 4- - - - - 4- 4- 4- 4- 4- 4- 4- 4- 4- 4-4- 4- 4- 600 - 4- 4-4-4- - Thursir •-.4- - - - -
jJ______274000 274100 273100 270700 273300 270406 270500 273400 270770 273800 273800 274200 274300 274400 274500 2741500 E*271*G
100 200m NEEsoP 100 APi N-0 030. 0.025, 0,000 SCALE ii C - VELOCITY VECTORS - OPTION 5 1 IN 100 YEAR FLOOD co I I WOODGRO5.WK4 01/30/96 Nepean River comparison section existing topography I 1:2 year flood flood level 66.1 02 = 620 node velocity average node no. X Y Z delta Y chainage depth area Vx Vy V-node delta 0 adjust 0 %0 vdocity I 505 3696.2 942.3 70.00 34.1 391.9 0.00 0.0 0.00 0.00 0 0 1468 3699.1 908.2 69.00 25.0 357.8 0.00 0.0 0.00 0.00 0 0 388 3700.5 883.2 68.00 46.3 332.8 0.00 0.0 0.00 0.00 0 0 389 3686.8 836.9 66.17 42.3 286.6 0.00 0.0 0.00 0.00 0 0 I 391 3679.7 794.6 67.11 23.7 244.2 0.00 60.0 0.00 0.00 0 0 456 3691.3 770.8 61.00 27.0 220.5 5.06 83.1 0.00 0.00 0 0 383 3696.9 743.8 64.97 27.5 193.5 1.09 15.0 0.00 0.00 0 0 381 3704.3 716.3 67.73 15.3 166.0 0.00 0.0 0.00 0.00 0 0 376 3704.3 701.0 68.99 44.3 150.7 0.00 0.0 0.00 0.09 0 0 I 375 3706.6 656.7 68.25 28.3 106.4 0.00 32.6 0.18 0.01 0.18 0.32 10 12 366 3702.9 628.5 63.75 15.9 78.1 2.31 66.7 0.45 0.00 0.45 0.74 49 57 11 45 3707.2 612.5 60.00 4.4 62.2 6.06 42.0 1.02 0.17 1.03 1.10 46 53 61 3708.3 608.1 53.00 27.2 57.8 13.06 355.5 1.14 0.22 1.16 1.06 377 432 62 3713.7 580.9 53.00 4.8 30.6 13.06 46.1 0.95 0.13 0.96 0.86 40 45 I 0.75 0.54 18 46 3714.0 576.1 60.00 11.1 25.8 6.06 34.1 0.13 0.76 21 155 37169 565.0 66.00 14.6 14.6 0.06 0.4 0.31 0.05 0.31 0.16 0 0 156 3721.7 550.3 70.00 0.0 0.00 0.0 0.00 0.00 0.00 0.00 0 0 89 I total 0 541 620 100 I I I I I I I I I I I
EXISTING CONDITION - FLOW DISTRIBUTION I 2 year flood FIGURE 9 I I I WOODGRO5.WK4 01/30/96 Nepean River comparison section Option 5 I 1:2 year flood flood level 66.0 05 = 620 node velocity node no. X Y Z delta Y chainage depth area Vx Vy V-node delta 0 adjust 0 %Q velocity 1 505 3696.2 942.3 70.00 34.1 391.9 0.00 0.0 0.00 0.00 0 0 1468 3699.1 908.2 69.00 25.0 357.8 0.00 0.0 0.00 0.00 0 0 388 3700.5 883.2 67.50 46.3 332.8 0.00 23.1 0.00 0.00 0 0 389 3686.8 836.9 65.00 42.3 286.6 1.00 21.2 0.00 0.00 0 0 391 3679.7 794.6 67.00 23.7 244.2 0.00 71.1 0.00 0.00 0.00 0.00 0 0 I 456 3691.3 770.8 60.00 27.0 220.5 6.00 121.7 0.00 0.00 0.00 0.00 0 0 383 3696.9 743.8 63.00 27.5 193.5 3.00 116.9 0.00 0.00 0.00 0.00 0 0 381 3704.3 716.3 60.50 15.3 166.0 5.50 87.8 0.00 0.00 0.00 0.00 0 0 376 3704.3 701.0 60.00 44.3 150.7 6.00 132.9 0.00 0.00 0.00 0.22 30 31 I 375 3706.6 656.7 67.00 28.3 106.4 0.00 28.3 0.44 0.07 0.45 0.47 13 14 366 3702.9 628.5 64.00 15.9 78.1 2.00 63.7 0.50 0.03 0.50 0.76 48 51 15 45 3707.2 612.5 60.00 4.4 62.2 6.00 41.7 1.00 0.14 1.01 1.08 45 47 61 3708.3 608.1 53.00 27.2 57.8 13.00 353.8 1.13 0.18 1.14 1.10 388 409 62 3713.7 580.9 53.00 4.8 30.6 13.00 45.8 1.04 0.14 1.05 0.94 43 46 I 46 3714.0 576.1 60.00 11.1 25.8 6.00 33.4 0.83 0.13 0.84 0.63 21 22 155 3716.9 565.0 66.00 14.6 14.6 0.00 0.0 0.41 0.07 0.42 0.21 0 0 156 3721.7 550.3 70.00 0.0 0.00 0.0 0.00 0.00 0 0 85 1 totalO 588 620 100 I I I I I I I I I I I
OPTION 5 - FLOW DISTRIBUTION I 2 year flood FIGURE 10 I LL 38flOkJ POOU leolc 9 NOi1fl8IU1SG M01J - NOI1INO3 ONI1SIX I I I I j oo.]
w a6euieqO I 000 000 00 0 0
OL I 00 I 0) Oc 000 0) C) I
3 > 09 I
09 0000 I OL