Environmental Monitoring Report

Project Number: 47100-004 March 2019

Period: January 2018 – June 2018

IND: Power Transmission and Distribution System Improvement Project

Submitted by Madhya Pradesh Power Transmission Company Ltd., Jabalpur

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Environmental Monitoring Report

Reporting Period: January 2018 to June 2018

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project

Loan no. 3066 IND Reporting Period: January 2018 to June 2018 Madhya Pradesh Power Transmission and Distribution System Improvement Project Madhya Pradesh,

TABLE OF CONTENTS 1.0 Introduction 1 2.0 Compliance to National/State/Local Statutory Environmental Requirements and 16 International Standards and Regulations 3.0 Compliance status with the environmental management and monitoring plans as 21 stipulated in the environmental documentation agreed with ADB 4.0 Monitoring of environmental receptors/attributes 57 5.0 Any other environmental aspects, impacts observed during implementation which were 59 not covered earlier 6.0 Details of Grievance Redress Committee and complaints received from public and 60 actions taken thereof to resolve 7.0 Public consultation during project implementation 61 8.0 Institutional set-up for EMP implementation 74 9.0 Follow-up actions and conclusions 76

LIST OF TABLES 1.0 Details of Transmission Lines and project status 3 1.1 Details of Substations and Feeder Bays and project status 12 2.0 Compliance Status with National/State/Local Statutory Environmental Requirements 16 and international standards 2.1 Labor License and Labor Insurance Details for all Contractors 18 3.0 Project Progress Status for environmental compliance (Transmission Lines) 21 3.1 Project Progress Status of Environmental Compliance (Substations and Feeder Bays) 33 3.2 Environment Management Plan and Status on Implementation 45 4.0 Environmental Monitoring Schedule 58 7.0 Public Consultation for Transmission Lines 61 7.1 Public Consultation for Substations, additional transformers and associated Feeder 70 Bays 8.0 Environmental and Safety Officer Details for all Contractors 74 LIST OF FIGURES Figure-1 Project Location 2 ANNEXURES Annexure 1: Photographs of site visit and Public Consultation 77 Annexure 2: Public Consultation details 78 Annexure 3: Forest Clearance Details 82 Annexure 4: Grievance Committee Details 95 Annexure 5: MPPTCL’s LOU 96 Annexure 6: Labour License Details of M/S Kalpataru 97 Annexure 7: Labour Insurance Details of M/S Kalpataru 101 Annexure 8: Labour License Details of M/S Punj Llyod 107 Annexure 9: Labour Insurance Details of M/S Punj Llyod 108 Annexure 10: Labour License Details of M/S Bajaj 110 Annexure 11: Labour Insurance Details of M/S Bajaj 121 Annexure 12: Labour License Details of M/S Larsen & Toubro 123 Annexure 13: Labour Insurance Details of M/S Larsen & Toubro 126

ABBREVIATIONS ADB – Asian Development Bank EA – Executing Agency EARF – Environmental Assessment and Review Framework EIA – Environmental Impact Assessment EMA – Environment Monitoring Agency EMP – Environmental Management Plan EMR – Environmental Monitoring Report ESMC – Environmental and Social Management Cell ESMU – Environmental and Social Management Unit ESO – Environmental Safety Officer GHG – Greenhouse Gas GoMP – Government of Madhya Pradesh GoI – Government of India GRC – Grievance Redressal Committee HSE – Health Safety Environment IA – Implementation Agency Ltd. – Limited NO2 – Nitrogen dioxide MPPCB – Madhya Pradesh Pollution Control Board PM10 – Particulate Matter (Size less than 10 µm) PM2.5 – Particulate Matter (Size less than 2.5 µm) PMU – Project Management Unit PPE – Personal Protective Equipment ROW – Right of Way S/S – Sub Station SEIA – Summary Environmental Impact Assessment SIEE – Summary Initial Environmental Examination SO2 – Sulphur dioxide T&D – Transmission and Distribution XIDAS – Xavier Institute of Development Action and Studies LILO – Line – in – Line – Out WEIGHTS AND MEASURES V – volt kV – kilovolt (1,000 volts) W – watt kW – kilowatt (1,000 watts) MW – Mega Watt (1000 kW) MWh – Megawatt hour VA – Volt Ampere MU – Million Units MVA – Million Volt Ampere

Environmental Monitoring Report

1.0 INTRODUCTION 1 To improve the quality and reliability of service in the power transmission and distribution system networks, the Government of Madhya Pradesh (GoMP) has taken initiatives to invest in the power sector with funding from development partners like the Asian Development Bank (ADB). The investment involves expansion, upgrading and reconfiguration of the existing power transmission networks. An IEE report for TRANSCOM was submitted for ADB’s approval in September, 2013. However, during the course of commencement of the works, there were route alignment changes in some transmission lines, further some new lines were also added to the same project and some were dropped as they were no longer necessary. In case of substations also, two substations were dropped from the original scope of work. In light of these changes, the IEE report was further updated and submitted for ADB’s approval. The updated IEE report of May, 2017 was approved and disclosed by ADB. Thereafter, an Environmental Monitoring Report (EMR) for the period July 2014 to December 2016 was submitted and approved by ADB. Second and third environmental monitoring for the period January 2017 to June 2017 and July 2017 to December 2017 were also accepted and disclosed by ADB respectively. The updated IEE report of May, 2017 was also updated to reflect addition of few lines and changes in route alignment and length of few lines. This updated IEE of August, 2017 was also accepted and disclosed by ADB. This monitoring report covers the period from January 2018 to June 2018. This project is classified by ADB as Category B.

2 Madhya Pradesh Power Transmission Company Limited (MPPTCL) is utilizing the finance availed for the construction of new and up gradation of existing power transmission network. The main features include power evacuation and transmission through 400 kV, 220 kV, and 132 kV transmission lines along with associated Substations and Feeder Bays. It is being implemented under ADB Loan no. 3066 which is implemented by MPPTCL, Jabalpur. Figure 1.0 shows project location in the state of Madhya Pradesh.

1

Figure 1.0: Project Location

3 The power sector investments are necessary to support continued investment in the state power sector, which is necessary for economic growth and poverty reduction. The loan availed will be utilized to finance the expansion and augmentation of the transmission and distribution (T&D) networks. The proposed investments are necessary to: (i) facilitate increased power transfers to accommodate increased demand and economic growth; (ii) improve supply-side energy efficiency by system de-bottlenecking and reducing technical losses; (iii) reduce the intensity of greenhouse gas (GHG) and other emissions via improved system efficiency; (iv) support expanded private sector participation in distribution system operations and other energy services; and (v) facilitate poverty reduction via improved electricity services and economic growth.

4 About 1,800 circuit-km of transmission line was proposed to be constructed under the original project as outlined in the approved IEE report of Sep, 2013. A total of 32 substations (or 12.5% of the existing substations) comprising two 400 kV, four 220 kV and twenty six 132 kV substations were proposed to be constructed. However, additions of new project components had resulted in a route length of 1880.285 kms and a total of 75 Transmission Lines and 56 substations (including additional transformers and associated feeder bays) as outlined in the updated and approved IEE report of May, 2017. Subsequently, 3 lines namely Dabra – Chinnaur DCSS Line, Morena (PGCIL) – Sabalgarh Line and Betul (PGCIL) – Betul Interconnecter were spilt into two (each line spilt into two) from system requirement point of view and there were changes in length and alignment of few lines. To incorporate these changes, the IEE report of May, 2017 was further updated and these changes were reflected in the IEE report of August, 2018 which was also accepted and disclosed by ADB.

2

At the time of finalization of IEE report of May, 2017, land allotment for three substations viz. Palohabada, Satna-II and Mada was not final. These were later finalized and the land status was duly updated and the changes were reflected in the updated IEE report of August, 2018.

There are changes in length and alignment during this reporting period and the report captures these changes along with the reason for such changes. For the subprojects where the length and alignment has changed by more than 500 metres, the reason for such changes has also been mentioned under remarks section. For length changes less than 500 metres, it is largely due to design elements requirements and does not result in any significant impact. The IEE report of august, 2018 will be further updated in order to reflect the changes in length and alignment captured during this reporting period.

The details of projects work viz. lines, substations and feeder bays along with project status during this monitoring period are given below in Table no. 1.0 and Table no. 1.1 respectively.

Table no. 1.0: Details of Transmission Lines and Project Status S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) Jabalpur 1 LILO of 400kv seoni to 3.375 3.375 No change Stub Setting: 8 Bhilai S/C line at completed of Balaghat/Kirnapur (D/C) 10 M/s BHEL Tower Erection: 3 completed of 10 Stringing: Not started yet 2 LILO of 132kV 4.7 4.7 No change Stub Setting: Balaghat- Seoni/ 18 completed Katangi line at of 18 Waraseoni 132kV S/s Tower Erection: (2XD/C) M/s Industrial 7 completed of House 18 Stringing: Not started yet 3 LILO of both circuit of 1.99 1.99 No change Completed 132kV Balaghat- Bhanegaon Line at Balaghat/Kirnapur 400kV S/s (2XD/C) M/s Industrial House 4 Second circuit of 32.218 32.218 No change Completed

3

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) Tikamgarh- Budhera 132kV DCSS Line M/s B.S. Ltd. 5 Narsinghpur 220- 24.43 24.43 No change Stub Setting: Devnagar 132kV DCSS 55 completed Line M/s Bajaj of 81 Tower Erection: 11 completed of 81 Stringing: Not started yet 6 Karakbel- Belkheda 24.445 24.522 Minor change in Stub Setting: 132kV DCSS line M/s length 84 completed KDBL of 88 Tower Erection: 29 completed of 88 Stringing: Not started yet 7 Narsinghpur 220KV 26.62 26.62 No change Stub Setting: Karakbel 132KV DCS 52 completed line M/s KDBL of 52 Tower Erection: 24 completed of 52 Stringing: Not started yet 8 Panagar 220-Patan 22.749 22.749 No change Stub Setting: 132kV DCSS line M/s 28 completed Bajaj of 74 Tower Erection: Not started yet Stringing: Not started yet 9 Chhindwara 220- Saori 31.468 31.600 Minor change in Stub Setting: 132kV DCSS line M/s length 110 completed Kalptaru of 110 Tower Erection: 110 completed of 110 Stringing: 1X26.620 10 Chichli 220- 21 25.606 Length and Stub Setting: Palohabada 132kV alignment 12 completed DCSS line M/s Kalptaru changed. of 88 Tapping point Tower Erection: has been Not started yet transferred to Stringing: Not Chichli and started yet hence length has increased due to a slightly longer

4

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) route. 11 132kv DCSS line from 38.748 38.942 Minor change in Stub Setting: Damoh 220kv to Patera length. 123 completed 132 kv substation M/s of 134 Kalptaru Tower Erection: 83 completed of 134 Stringing: 1 x 6.345 12 Second circuit of 132kV 36.17 36.17 No change Completed Tap Line from Balaghat- Katangi M/s B.S.Ltd. Satna 13 Second circuit 132kV of 34 34 No change Completed Chhatarpur-Khajuraho line M/s B.S.Ltd.

14 LILO of second ckt of 5.693 5.693 No change Completed Bansagar-Satna 220kV line at Kotar 220kV S/s M/s Vikran 15 LILO of Satna - Maihar 20 11.047 Length and Stub Setting: 5 132kV line at Satna-II alignment completed of 132kV S/s M/s Vikran changed. 36 The earlier length Tower Erection: of 20 kms was an Not started yet estimate during Stringing: Not route survey. The started yet actual length has been revised to 11.047 now. 16 LILO of second ckt of 5.684 5.684 No change Completed Birsinghpur - Amarkantak 220kV line at Shahdol 220kV s/s M/s Vikran 17 Birsinghpur 220- 44.821 44.821 No change Stub Setting: Shahdol 132kV DCDS 161 completed line M/s Vikran of 167 Tower Erection: 154 completed of 167 Stringing:2 x 30.579 18 LILO of 132 Tikamgarh- 1.675 1.14 The actual length Yet to start Bijawar line for Bada of the line is now Malehra M/s Bajaj 1.14 kms. The earlier figure of 1.675 kms was estimation during route survey

5

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) which has now been finalized.

Indore 19 LILO of one circuit of 32.782 32.782 No change Stub Setting: Ashta 400-Dewas 220 18 completed kv D/C line at Chapda of 104 220kv S/s (D/C) M/s Tower Erection: Bajaj Not started yet Stringing: Not started yet 20 Pithampur 400 - 35.583 37.583 Length and Stub Setting: Depalpur 220kv DCSS alignment 120 completed line M/s Bajaj changed. of 120 There were some Tower Erection: temporary 63 completed housing of 120 structures in Stringing: Not RoW and route started yet had to be diverted in order to avoid these housing units. 21 Dewas 220- Agrod 19.374 19.374 No change Completed 132kv DCSS line M/s Swastik Mechnical

22 Dhar 220 - Teesgaon 15.35 15.35 No change Stub Setting: 132kv DCSS line M/s 42 completed Bajaj of 53 Tower Erection: Not started yet Stringing: Not started yet 23 LILO of both Circuit of 8.163 8.163 No change Stub Setting: 400 kv Nagda-Rajgarh 21 completed line at Badnawar (2 x of 22 D/C) M/s BHEL Tower Erection: 14 completed of 22 Stringing: 4 x 1.3 24 Second Circuit of 35.65 35.65 No change Completed Kukshi Alirajpur 132kv line M/s B.S.Ltd. Barwaha 25 LILO of 132 Khargone 18.997 18.997 No change Yet to start Bikayan line at 132 Kv sub-station Bistan M/s Bajaj

6

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) 26 LILO of 132kv Chegaon 1.895 1.895 No change Completed Nepanagar line at Pandhana M/s B.S.Ltd. 27 LILO Manawar - Kukshi 3.1 3.1 No change Completed DCSS line at Singhana (D/C) M/s B.S.Ltd. 28 LILO of 132Kv 1.9 1.9 No change Completed Khargone -Julwaniya line at 132Kv S/S Talakpura M/s B.S.Ltd. 29 Julwaniya 400- Kukshi 62.9 62.9 No change Stub Setting: 220kv line (D/C) M/s 108 completed Bajaj of 190 Tower Erection: 34 completed of 190 Stringing: Not started yet

30 220kV DCDS Khandwa 39.322 39.322 No change Stub Setting: (400 PGCIL) to 120 completed Chhanera line M/S out of 120 Kalptaru Tower Erection: 108 completed of 120 Stringing:2 x 29.438 31 Chhegaon 220- Singot 57.76 57.76 No change Completed 132kV DCSS Line M/s Kalptaru 32 Chhanera 220- Khirkiya 30.179 30.179 No change Completed 132kV DCDS Line M/s Kalptaru 33 Bairagarh 220 - Intkhedi 9.049 9.049 No change Completed 132kv DCDS line M/s P. S. Associated 34 Second circuit of 21.44 21.44 No change Completed Bairagarh – Shyampur M/s P. S. Associated 35 Second circuit of 48.27 Completed Gairatganj - 220 132kv line M/s Punj Lyod 36 Shujalpur- 44.575 52 Length and Stub Setting: Narsinghgarh 220kv alignment 84 completed DCSS line (Initially changed. of 144 charged on 132kv) M/s The entire route Tower Erection: Bajaj survey was 24 completed pending at of 144

7

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) approach end Stringing: Not and therefore started yet earlier length of 44.575 was an estimate which has now been finalized to 52 kms. 37 LILO of one circuit of 2.868 2.868 No change Yet to start Bhopal - Hosangabad 220kv D/C line at Adampur 220kv S/s (D/C) M/s Bajaj 38 -Silvani 132kv 28.068 28.068 No change Stub Setting: DCSS line M/s Bajaj 77 completed of 77 Tower Erection: 42 completed of 77 Stringing: Not started yet 39 LILO of Vidisha- 0.162 0.162 No change Completed Bairasiya Line at Salamatpur 132 KV S/s M/s Punj Llyod 40 Mugaliyachhaap 220- 17.2 17.2 No change Completed Bikisganj 132kV DCDS line M/s Punj Lyod 41 132kv Rajgarh () – 27.956 27.956 No change Stub Setting: / Sindaota Line 87 completed M/s Punj Lyod of 87 Tower Erection: 83 completed of 87 Stringing:2 x 12.52 42 LILO of one ckt of 18.221 18.221 No change Completed Vidisha Gairatganj at 132kV S/s M/s Punj Lyod Itarsi 43 Second circuit of Betul 57 57 No change Completed 220 Gudgaon 132kv line M/s Punj Lyod 44 Chichli 220- Udaipura 47.56 47.56 No change Completed 132kv DCDS line (220kv line charged at 132kv) M/s B.S. Ltd. 45 Betul400 (PGCIL)- 1.88 1.88 No change Completed Betul 220kV DCDS line M/s Punj Lyod

8

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) 46 LILO of 220kV Sarni- 38.864 38.864 No change Stub Setting: Pandhurna at 400kV 129 completed (PGCIL) Substation of 135 Betul M/s Punj Lyod Tower Erection: 35 completed of 135 Stringing: Not started yet 47 Betul 220- 35.245 35.245 No change Stub Setting: Bisnoor/Masod 132kV 112 completed DCSS line M/s Punj of 114 Lyod Tower Erection: 78 completed of 114 Stringing: 1.00 Ujjain 48 Badnagar 220- 28.26 28.26 No change Stub Setting: Chhayan 132kv DCSS 95 completed line M/s Swastik of 95 Mechnical Tower Erection: 67 completed of 95 Stringing: Not started yet 49 LILO of both circuits of 6.6 6.6 No change Stub Setting: 6 220kV Badnagar- completed of 6 Ratlam DC line at Tower Erection: 400kV S/s Badnawar Not started yet M/s NKR Stringing: Not started yet 50 LILO of both ckt of 14.5 14.5 No change Stub Setting: Gandhisagar-Suwasra 60 completed /Garoth 132kV line at of 60 Bhanpura 220kV S/s M/s Tower Erection: Kalptaru 47 completed out of 60 Stringing: Not started yet Ratlam 51 LILO of 132kv Badod - 3 3 No change Yet to start Garoth line at Shyamgarh (D/C) M/s Bajaj 52 LILO of Ratlam- 7.4 9 Length and Stub Setting: 8 Meghnagar 132kv S/c alignment completed of line at Petlawad DCDS changed. 28 (D/C) M/s Bajaj The earlier length Tower Erection: of 7.4 was an Not started yet estimate which Stringing: Not has now been started yet finalized to 9

9

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) kms.

53 LILO of second ckt of .5 .5 No change Completed Badod - Kota/Madok 220kV line at Bhanpura 220kV S/s M/s Kalptaru 54 LILO of second ckt of 12.2 12.2 No change Stub Setting: Nagda- Neemuch 29 completed 220kV line at Daloda of 31 220kV S/s M/s Kalptaru Tower Erection: 21 completed of 31 Stringing: 2 x 1.987 55 LILO of Nagda 220- 1.244 1.244 No change Completed Ratadiya 132kV line at Unhel M/s Kalptaru Gwalior 56 LILO of 132 KV 13.68 13.68 No change Completed Gwalior- Karera– Pichhore Line at Chinaur M/s Bajaj 57 LILO of 132 KV 0.108 0.108 No change Stub Setting: 2 Gwalior- Dabra – Datia completed of 2 –Pichhore Line at Tower Erection: Dabra M/s Bajaj 2 completed of 2 Stringing: Not started yet 58 Datiya 220- Bhander 34.038 34.038 No change Completed 132kV DCSS Line M/s Bajaj 59 Mehgaon 220- 29.74 29.74 No change Completed Pratappura 132kV DCSS line M/s Bajaj 60 Sabalgarh 220- Kelaras 19.655 19.655 No change Completed 132kV DCSS Line M/s Bajaj 61 Malanpur 220- Gohad 14.5 14.5 No change Completed 132kV DCDS Line M/s. Bajaj 62 220 KV DCDS Morena 94.42 94.512 Minor change in Stub Setting: 400 KV (CWRTL Adani) length 288 completed –Sabalgarh DCDS Line of 290 M/s L&T Tower Erection: 273 completed of 290 Stringing: 2 x 81.71 63 220kv (Jarerua) DCDS 0.5 0.5 No change Completed LILO of Morena 400kV

10

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) S/s (Adani)-Sabalgarh at Morena 220kV substation M/s L&T 64 Bhonra-Kapasi 132 kv 22.569 22.569 No change Completed DCSS line M/s L&T 65 Kolaras-Mada 132kV 20.293 20.293 No change Completed DCSS line M/s L&T 66 132kv DCDS Guna 21.394 25.374 Length and Stub Setting: 220-Bhonra line M/s alignment 73 completed L&T changed. of 78 The route length Tower Erection: has been revised 57 completed due to a pond of 78 and national Stringing:2 x highway 9.80 crossing. 67 LILO of one circuit of 7.396 7.396 No change Completed Malanpur- Mehgaon line at 400 KV S/s (CWRTL Adani) Morena M/s L&T 68 2nd circuit of Shivpuri 34.686 34.686 No change Completed 220- Kolaras 132kV DCSS line M/s L&T 69 2nd ckt of Malanpur- 28.708 28.708 No change Completed Morar 132kV line M/s L&T Sagar 70 Khurai- Khimlasa 132kV 20.937 20.937 No change Stub Setting: DCSS line 71 completed M/s Bajaj of 71 Tower Erection: 2 completed of 71 Stringing: Not started yet 71 LILO of Mungaoli 8.32 8.32 No change Completed Traction Feeder to Mungaoli (D/C) M/s Bajaj 72 Ashoknagar 220- 30 30 No change Completed Kothiya 132kV DCSS Line M/s Bajaj 73 Sagar220- Rehli 132kV 38.458 38.458 No change Stub Setting: DCSS line 109 completed M/s Kalptaru of 127 Tower Erection: 36 completed of 127 Stringing: Not

11

S. Name of Line Works Total Total Route Remarks Project Status N Route Length in o Length in Km. (As per Km. (As EMR Jan to per EMR June 2018, July to present Dec reporting 2017) period) started yet 74 2nd ckt of Sagar 220- 8.77 8.77 No change Completed Sagar 132kV (I/C) M/s Kalptaru 75 Stringing of 3rd 31.3 31.3 No change Completed conductor from Bina220 to Mungaoli M/s Kalptaru Mandsaur 76 LILO of both ckt of 4.382 4.382 No change Completed Badod- Kota/Modak 220kV line at Suwasra 220kV S/s (2XD/C M/s Kalptaru 77 LILO of one ckt of 22.077 22.077 No change Stub Setting: Neemuch 220- 70 completed Mandsaur 132kV line at of 70 Budha 132kvS/s M/s Tower Erection: Kalptaru 70 completed of 70 Stringing:2 x 21.463 78 LILO of both circuit of 1.423 1.423 No change Completed 132kV Gandhisagar- Suwasara/Garoth line at Suwasara 220kV Sub- station M/S Kalptaru

Table no. 1.1: Details of Substations and Feeder Bays and project status S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) Jabalpur 1 Balaghat/Kirnapur 400/132kv (2 x 100+40MVA) +400kv C:100% FB(2) +132kv FB(4) S:100% E:99% 2 Waraseoni 132kV 40MVA+132kV FB(2) C:98% S: 90% E: 65% 3 BadaMalehra 132/33kV 40 MVA+132kV FB(1) Layout issued. 4 Deonagar 132/33kV 40 MVA+132kV FB(1) C:98% S:82% E:Not started yet 5 Belkheda 132/33kV 40MVA+132kV FB(1) C:88% S: Not started yet

12

S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) E: Not started yet 6 Karakbel 132/33kV 40MVA+132kV FB(2) C:88% S: Not started yet E: Not started yet 7 Saori 132/33kV S/s (1X50) MVA; 132kV FB(1) C:100% 8 Palohabada 132/33kV S/s (1X50) MVA; 132kV FB(1) Yet to start 9 Patera 132/33kV S/s (1X50) MVA; 132kV FB(1) C:100% S:99% E:97% Satna 10 Additional Transformer at Sidhi 220 (2nd) +160 MVA Completed 11 Additional Transformer at Kotar 220 (2nd) +160 MVA Completed 12 Additional Transformer at Chhatarpur (2nd) +160 MVA Completed 13 Satna-II 132/33kV S/s (2X50) MVA; 132kV FB(2) C:100% S: 96% E:82% 14 Shahdol 220/132kV S/s (Upgradation) (1X60) MVA; 220kV Completed FB(2)+132kV FB(1) Indore 15 Badnawar 400/220kv (2x315MVA) + 400kv FB Completed (4) + 220kv FB (4) +125MVAR bus Reactor 16 Upgradation of Chapda 132kv S/S to 220kv (1x160MVA) + 220kv C:12% FB(2) S: Not started yet E:Not started yet 17 Upgradation of Depalpur 132kv S/s to 220kv (1x160MVA) + 220kv FB C:46% (1) S:Not started yet E:Not started yet 18 Agrod 132/33kV 40MVA+132kV FB(1) C:100% S:100% E:80% Barwaha 19 400/220kv additional transformer at 1x315 MVA Completed Chhegaon 400kv S/S 20 Teesgaon 132/33kV 40MVA+132kV FB(1) C:35% S:19% E:1% 21 Bistan 132/33 kV 40 MVA+ 132kV FB(1) C:57% S:Not started yet E:Not started yet 22 Pandhana 132/33kV 40MVA+132kV FB(2) Completed 23 Singhana 132/33kV 40MVA+132kV FB(2) Completed 24 Talakpura 132/33kV 40MVA+132kV FB(1) Completed 25 Kukshi 220/132kv 160 MVA + 220kv FB(2) C:56% +132kv FB(1) S:Not started yet E:Not started yet 26 Chhanera 220/132kV S/s (2X160+1X50) MVA C:99% 220kV FB(2)+132kV FB(3) S:93% E:84% 27 Singot 132/33kV S/s (1X50)MVA; 132kV FB(1) Completed

13

S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) Bhopal 28 Salamatpur 132kv/33kv 40 MVA +132kv FB(1) Completed 29 Intkhedi 132kv /33kv 63 MVA +132kv FB(2) Completed 30 400/220kv additional transformer at Bhopal 1x315 MVA Completed 400 kv S/S 31 Additional Transformer at 220 +160 MVA Completed (2nd) 32 Narsinghgarh 132/33kv 40MVA +132kv FB(1) C: 37% S:Not started yet E:Not started yet 33 Adampur 220/33kv 2x50MVA + 220kv FB(2) C:43% S:Not started yet E:Not started yet 34 Bilkisganj 132/33kV S/s (1X50) MVA; 132kV FB(1) C:100% S: 99% E: 88% 35 Khujner/sindaota132/33kV (1X50) MVA; 132kV FB(1) C:100% S: 99% E: 98% 36 Bisnoor/Masod 132/33kV (1X50) MVA; 132kV FB(1) C:100% S: 95% E: 56% Itarsi 37 Additional Transformer at Betul 220 (2nd) +160 MVA Completed 38 Silvani 132kv /33kv 40 MVA +132kv FB(1) C:26% S:38% E:Not started yet 39 Udaipura 132/33kv 40MVA + 132kv FB(2) C:100% S:98% E:98% Ujjain 40 Chhayan 132/33kV 40MVA+132kV FB(1) C:97% S:100% E:100% 41 400kv Bus Reactor at Nagda 400kv S/S 1X125 MVAR Completed 42 Shyamgarh 132/33kV 40MVA+132kV FB(2) Layout issued. 43 Suwasra 220/132kV S/s (2X160+1X50) MVA Completed 220kV FB(4)+132kV FB(4) 44 Unhel 132/33kV S/s (1X50) MVA; 132kV FB(2) Completed 45 Budha 132/33kV S/s (1X50) MVA; 132kV FB(2) Completed Gwalior 46 Chinaur 132/33kV 40MVA+132kV FB(1) Completed 47 Bhander 132/33kV 63MVA+132kV FB(2) Completed 48 Pratappura 132/33kV 40MVA+132kV FB(1) Completed 49 Kelaras 132/33kV 63MVA+132kV FB(1) Completed 50 Gohad 132/33kV 63MVA+132kV FB(2) Completed 51 Kapasi/ Paranth 132/33kv (1X50) MVA; 132kV FB(1) Completed 52 Mada 132/33kV S/s (1X50) MVA; 132kV FB(1) Completed Sagar

14

S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) 53 Khimlasa 132/33kV 40MVA+132kV FB(1) C:14% S: Not started yet E: Not started yet 54 Mungaoli 132/33kV 63MVA+132kV FB(2) Completed 55 Kothiya 132/33kV 40MVA+132kV FB(1) Completed 56 Rehli 132/33kV S/s (1X50) MVA; 132kV FB(1) C:100% S:96% E:95%

2.0 Compliance to National/State/Local Statutory Environmental Requirements and International Standards and Regulations

15

5. Compliance Status with National/State/Local Statutory Environmental Requirements and international standards to the project are given in Table No. 2.0 below.

Table No. 2.0: Compliance Status with National/State/Local Statutory Environmental Requirements and international standards S No Legal Requirements/ Acts/Rules/ Applicable Attributes MPPTCL’s Guidelines Compliance Status 1 The Water (Prevention and Control of Water Pollution No siltation of water Pollution) Act, 1974 bodies due to the project will take place. No release of chemicals to the water bodies will occur. The Air (Prevention and Control Air Pollution Dust emissions 2 of Pollution) Act, 1981 limited to construction period. The Environment (Protection) Construction Practices Complied 3 Act, 1986 4 The Environment Impact EMP monitoring EIA is not required Assessment Notification, 2006 for transmission projects. An IEE report has been submitted to ADB. The report was accepted and disclosed by ADB. Complied. 5 The Hazardous Wastes Transformer Oil As per the practice (Management and Handling) Rules, adopted by 1989 as amended 2002 MPPTCL, detailed tender specifications deal with oil usage. Tender specifications ensure that oil used is free from PCB’s. Complied 6 The Ozone Depleting Cleaning of electrical As per the practice Substances (Regulation and contacts using HFCs etc. adopted by Control) Rules, 2000 MPPTCL, detailed tender specifications deal with avoidance of ozone depleting substances. Complied. 7 The Batteries (Management and Batteries MPPTCL ensures Handling) Rules, 2001 as that batteries after amended use are disposed through auction to registered dealers/recyclers to avoid pollution from waste batteries. Complied The Indian Forest Act, 1927 Reserve Forest areas, Six lines pass 8 Right of Way through forest land,

16

S No Legal Requirements/ Acts/Rules/ Applicable Attributes MPPTCL’s Guidelines Compliance Status prior forest clearance is obtained in such cases. See annexure 3 for forest clearance details. 1 Complied. The Wild Life (Protection) Act, Critical habitats None of the lines 9 1972 as amended 2006 pass through critical wildlife habitats. Where lines pass through forest, forest clearance is taken as per existing law. See annexure 3 for forest clearance details.2 Complied The Biological Diversity Act, Wetland Not applicable 10 2002 The Forest (Conservation) Act, Construction work in forest Construction activity 11 1980 as amended Areas in forest areas is only started after gaining relevant permission as per existing laws. Forest clearance is obtained whenever lines pass through forest areas. See annexure 3 for forest clearance details. 3 Complied The National Environmental Construction Practices As per terms of the 12 Policy, 2006 of GoI contract, all contractors are required to undertake good construction practices as per prevailing law. Complied. 13 Other State Level Acts Compensation Farmers are paid compensation for loss of crop due to construction activities. Complied Other International levels Biodiversity, GHG None of the 14 conventions and treaties emissions construction activities will result in GHG emissions or cause harm to biodiversity

1 Six lines with forest involvement are: 132kV DCDS line from 220kV Guna to Bhonra (A combined forest clearance has been provided for both lines viz. Guna-Bhonra and Bhonra-Kapasi and the total area has been revised to 9.1341 ha by forest department); 132kV DCSS Bhonra to Kapasi line (A combined forest clearance has been provided for both lines viz. Guna-Bhonra and Bhonra-Kapasi and the total area has been revised to 9.1341 ha by forest department); 132kV DCSS Sagar-Rehli line (Forest clearance has been applied for. Case forwarded to APCCF Bhopal); 132kV DCSS Birsinghpur-Shahdol line (First Stage approval received. Working permission received); Second circuit of Gairatganj-Vidisha 220 132Kv line (Forest Clearance has been obtained); 220kV DCDS Khandwa (400PGCIL) to Channera Line (forest Clearance has been obtained). 2 Ibid 1 3 Ibid 2

17

S No Legal Requirements/ Acts/Rules/ Applicable Attributes MPPTCL’s Guidelines Compliance Status rich areas. Complied The Noise Pollution (Regulation and Noise Pollution Noise limited to 15 Control Rules, 2000) and Amendment construction period. 2006 The Ancient Monuments and Historical Monuments Not applicable 16 Archaeological sites and Remain Act 1958 17 Employing Labour/workers The Building and Other As per terms of the Construction Workers contract, all (Regulation of Employment contractors are and Conditions of Service) required to take Act, 1996 labour insurance and also license if they engage contract labourers as per prevailing law. This is being followed strictly in all contracts. Complied. Details of labour license and insurance details are provided in table 2.1 below.

Table No.2.1: Labour License and Labour Insurance Details for all Contractors*

* Transmission Lines have been denoted as TL and Substations have been denoted as SS. The transmission lines and substations are numbered in same sequence as provided in table 1.0 and 1.1. For example, TL1 denotes Transmission Line 1 or LILO of 400kv Seoni to Bhilai S/C line at Balaghat/Kirnapur (D/C) as evident from Table 1.0.

S Contractor Labour License Labour Insurance Annexure No applicable for applicable for following following Transmission Transmission Lines and Lines and substations substations 1 M/s BHEL TL1, TL23 TL1, TL23 Please see annexure no. 5 for LoU SS1. SS15, SS30, SS1. SS15, SS30, from MPPTCL. M/S BHEL has SS41 SS41 subcontracted the works and MPPTCL’s reply regarding same is also given in Annexure no. 5. 2 M/s Vikran TL14,TL15,TL16,T TL14,TL15,TL16,T Please see annexure no. 5 for LoU L17 L17 from MPPTCL. M/S Vikran has SS13,SS14 SS13,SS14 subcontracted the works and MPPTCL’s reply regarding same is also given in Annexure no. 5. 3 M/s Kalptaru TL9, TL10, TL11, TL9, TL10, TL11, Please see annexure no. 6 for TL30,TL31,TL32, TL30,TL31,TL32,T relevant supporting documents of TL53,TL54,TL55,T L51,TL54,TL55,TL7 Labour License and annexure no. 7 L73,TL74,TL75,TL 3,TL74,TL75,TL76, for Labour insurance details. 76,TL77,TL78,TL5 TL77,TL78,TL50 0 SS7,SS8,SS9,SS2 SS7,SS8,SS9,SS 6,SS27,SS53,SS54 26,SS27,SS53,SS ,SS55,SS56 54,SS55,SS56

18

4 M/s Punj TL35,TL39,TL40,T TL35,TL40,TL41,T Please see annexure no. 8 for Lyod L41,TL42,TL43,TL L42,TL43,TL45,TL4 relevant supporting documents of 45,TL46,TL47 6,TL47 Labour License and annexure no. 9 SS34,SS35,SS36, SS34,SS35,SS36, for Labour insurance details. SS39 SS39 5 M/s Bajaj TL5,TL8,TL18,TL1 TL56,TL57,TL58,T Please see annexure no. 10 for 9,TL20,TL22,TL25 L59,TL60,TL61,TL7 relevant supporting documents of ,TL29,TL36,TL37, 2 Labour License and annexure no. TL38,TL51,TL52,T SS43,SS44,SS45, 11 for Labour insurance details. L56,TL57,TL58,TL SS46,SS47,SS51, 59,TL60,TL61, SS52 TL70, TL71,TL72 SS43,SS44,SS45, SS46,SS47,SS51, SS52 6 M/s L&T TL62,TL63,TL64,T TL62,TL63,TL64,T Please see annexure no. 12 for L65,TL66,TL67,TL L65,TL66,TL67,TL6 relevant supporting documents of 68,TL69 8,TL69,TL70 Labour License and annexure no. SS48,SS49 SS48,SS49 13 for Labour insurance details. 7 M/s BS TL4,TL6, TL7, TL4,TL5,TL6, NA LTD** TL12,TL13,TL24, TL7,TL8, TL26,TL27,TL28, TL12,TL13,TL18,T TL44 L19,TL20, SS2,SS3,SS4,SS TL22,TL24,TL25,T 5,SS6,SS10,SS11 L26,TL27,TL28,TL2 ,SS12,SS16,SS17 9,TL36,TL37,TL38, ,SS18,SS19,SS20 TL44,TL52,TL53,T ,SS21,SS22,SS23 L71 ,SS24,SS25,SS28 SS2,SS3,SS4,SS5, ,SS29,SS31,SS32 SS6,SS7,SS8,SS9, ,SS33,SS37,SS38 SS10,SS11,SS12, ,SS40,SS42,SS50 SS16,SS17,SS18, SS19,SS20,SS21, SS22,SS23,SS24, SS25,SS28,SS29, SS31,SS32,SS33, SS37,SS38,SS40, SS42,SS50 8 M/S TL2, TL3 TL2, TL3 MPPTCL has awarded work to petty Industrial contractors for fulfilling parts of House4 subprojects or works left unfinished by previous contractor. 9 M/S Swastik TL21,TL48 TL21,TL48 MPPTCL has awarded work to petty Mechanical5 contractors for fulfilling parts of subprojects or works unfinished by previous contractor. 10 M/S PS TL33, TL34 TL33, TL34,TL39 MPPTCL has awarded work to petty Associated6 contractors for fulfilling parts of subprojects or works unfinished by previous contractor. 11 M/S NKR7 TL49 TL49 MPPTCL has awarded work to petty

4 This is a sub-contractor/petty contractor under Bajaj. Labour License and Labour insurance for Bajaj are given in Annexure 10. 5 This is a sub-contractor/petty contractor under Bajaj. Labour License and Labour insurance for Bajaj are given in Annexure 10. 6 This is a sub-contractor/petty contractor under Bajaj. Labour License and Labour insurance for Bajaj are given in Annexure 10. 7 This is a sub-contractor/petty contractor under Bajaj. Labour License and Labour insurance for Bajaj are given in Annexure 10.

19

contractors for fulfilling parts of subprojects or works unfinished by previous contractor. 12 M/S KDBL8 TL6, TL7 TL6, TL7 MPPTCL has awarded work to petty contractors for fulfilling parts of subprojects or works unfinished by previous contractor. **Contracts for BS Ltd have been cancelled. The contract is presently being re-awarded. The details will be captured and provided in subsequent environmental monitoring reports when the tenders are re-awarded.

8 This is a sub-contractor/petty contractor under Bajaj. Labour License and Labour insurance for Bajaj are given in Annexure 10.

20

3.0 Compliance status with the environmental management and monitoring

plans as stipulated in the environmental documentation agreed with ADB

6. The updated status of environmental activities for the subprojects is given below in Table 3.0 and Table 3.1 respectively.

Table No. 3.0: Project Progress Status for environmental compliance (Transmission Lines) S. Name of Line Works Current Status of Environmental Compliance No Jabalpur 1 LILO of 400kv seoni to Bhilai S/C line The line does not pass through critical environmental at Balaghat/Kirnapur (D/C) M/s BHEL areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 30 2 LILO of 132kV Balaghat- Seoni/ The line does not pass through critical environmental Katangi line at Waraseoni 132kV S/s areas such as wildlife sanctuaries. No construction is (2XD/C) M/s Industrial House being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 170 3 LILO of both circuit of 132kV Balaghat- The line does not pass through critical environmental Bhanegaon Line at Blaghat/Kirnapur areas such as wildlife sanctuaries. No construction is 400kV S/s (2XD/C) M/s Industrial being undertaken in such environmentally sensitive House regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 38 4 Second circuit of Tikamgarh- Budhera The line does not pass through critical environmental 132kV DCSS Line M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due

21

S. Name of Line Works Current Status of Environmental Compliance No to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 1452 5 Narsinghpur 220- Devnagar 132kV The line does not pass through critical environmental DCSS Line M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 6 Karakbel- Belkheda 132kV DCSS line The line does not pass through critical environmental M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 7 Narsinghpur 220KV Karakbel 132KV The line does not pass through critical environmental DCS line M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 8 Panagar 220-Patan 132kV DCSS line The line does not pass through critical environmental M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 9 Chhindwara 220- Saori 132kV DCSS The line does not pass through critical environmental line M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 205 10 Chichli 220- Palohabada 132kV DCSS The line does not pass through critical environmental line M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 11 132kv DCSS line from Damoh 220kv The line does not pass through critical environmental to Patera 132 kv substation M/s areas such as wildlife sanctuaries. No construction is

22

S. Name of Line Works Current Status of Environmental Compliance No Kalptaru being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 18 12 Second circuit of 132kV Tap Line from The line does not pass through critical environmental Balaghat-Katangi M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 532 Satna 13 Second circuit 132kV of Chhatarpur- The line does not pass through critical environmental Khajuraho line M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 1822 14 LILO of second ckt of Bansagar-Satna The line does not pass through critical environmental 220kV line at Kotar 220kV S/s areas such as wildlife sanctuaries. No construction is M/s Vikran being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 175 15 LILO of Satna – Maihar 132kV line at The line does not pass through critical environmental Satna-II 132kV S/s M/s Vikran areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice

23

S. Name of Line Works Current Status of Environmental Compliance No involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: NIL 16 LILO of second ckt of Birsinghpur – The line does not pass through critical environmental Amarkantak 220kV line at Shahdol areas such as wildlife sanctuaries. No construction is 220kV s/s M/s Vikran being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 520 17 Birsinghpur 220-shahdol 132kV DCSS The line passes through forest land and forest line M/s Vikran clearance has been obtained. See annexure 3. 9 Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 1050 18 LILO of 132kV Tikamgarh-Bijawar line The line does not pass through critical environmental for Bada Malehra M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 100 Indore 19 LILO of one circuit of Ashta 400- The line does not pass through critical environmental Dewas 220 kV D/C line at Chapda areas such as wildlife sanctuaries. No construction is 220kv S/s (D/C) M/s B. S. Ltd being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided

9 Ibid 3

24

S. Name of Line Works Current Status of Environmental Compliance No solely by EA or contractor. Number of trees to be cut: 1 20 Pithampur 400 – Depalpur 220kv The line does not pass through critical environmental DCSS line M/s B. S. Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 14 21 Dewas 220- Agrod 132kv DCSS line The line does not pass through critical environmental M/s Swastik Mechanical areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: 3 22 Dhar 220 – Teesgaon 132kv DCSS The line does not pass through critical environmental line M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 23 LILO of both Circuit of 400 kv Nagda- The line does not pass through critical environmental Rajgarh line at Badnawar (2 x D/C) areas such as wildlife sanctuaries. No construction is M/s BHEL being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 24 Second Circuit of Kukshi Alirajpur The line does not pass through critical environmental 132kv line M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 492 Barwaha 25 LILO of 132 Khargone Bikayan line at The line does not pass through critical environmental 132 Kv sub-station Bistan M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL

25

S. Name of Line Works Current Status of Environmental Compliance No 26 LILO of 132kv Chegaon Nepanagar The line does not pass through critical environmental line at Pandhana M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 27 LILO Manawar – Kukshi DCSS line at The line does not pass through critical environmental Singhana (D/C) M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 28 LILO of 132Kv Khargone –Julwaniya The line does not pass through critical environmental line at 132Kv S/S Talakpura areas such as wildlife sanctuaries. No construction is M/s BS Ltd being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 29 Julwaniya 400- Kukshi 220kv line The line does not pass through critical environmental (D/C) M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 30 220kV DCDS Khandwa (400 PGCIL) The line passes through forest land and forest to Channera Line (Earlier Malwa TPS- clearance has been obtained. See annexure 310. Chhanera 220kV DCDS Line) M/s Farmers will be compensated for loss of income due Kalptaru to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 44 31 Chhegaon 220- Singot 132kV DCDS The line does not pass through critical environmental Line M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 32 Chhanera 220- Khirkiya 132kV DCDS The line does not pass through critical environmental Line M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL Bhopal 33 Bairagarh 220 – Intkhedi 132kv DCDS The line does not pass through critical environmental

10 Ibid 8

26

S. Name of Line Works Current Status of Environmental Compliance No line M/s PS Associated areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 34 Second circuit of Bairagarh – The line does not pass through critical environmental Shyampur M/s PS Associated areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 35 Second circuit of Gairatganj – Vidisha The line passes through forest land and forest 220 132kv line M/s Punj Lyod cleanrance has been obtained. See Annexure 3. 11 Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 36 Shujalpur- Narsinghgarh 220kv DCSS The line does not pass through critical environmental line (Initially charged on 132kv) M/s BS areas such as wildlife sanctuaries. No construction is Ltd being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 37 LILO of one circuit of Bhopal – The line does not pass through critical environmental Hosangabad 220kv D/C line at areas such as wildlife sanctuaries. No construction is Adampur 220kv S/s (D/C) being undertaken in such environmentally sensitive M/s BS Ltd regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 38 Udaipura –Silvani 132kv DCSS line The line does not pass through critical environmental M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 39 LILO of Vidisha- Bairasiya Line at The line does not pass through critical environmental Salamatpur 132 KV S/s M/s PS areas such as wildlife sanctuaries. No construction is Associated being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 40 Mugaliyachhaap 220- Bikisganj 132kV The line does not pass through critical environmental DCDS line M/s Punj Lyod areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 41 132kv Rajgarh (Biaora) –Khujner/ The line does not pass through critical environmental Sindaota Line M/s Punj Lyod areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive

11 Ibid 9

27

S. Name of Line Works Current Status of Environmental Compliance No regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 42 LILO of one ckt of Vidisha Gairatganj The line does not pass through critical environmental at Raisen 132kV S/s M/s Punj Lyod areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL Itarsi 43 Second circuit of Betul 220 Gudgaon The line does not pass through critical environmental 132kv line M/s Punj Lyod areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 44 Chichli 220- Udaipura 132kv DCDS The line does not pass through critical environmental line (220kv line charged at 132kv) areas such as wildlife sanctuaries. No construction is M/s BS Ltd being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 47 45 Betul400 (PGCIL)- Betul 220kV DCDS The line does not pass through critical environmental line M/s Punj Loyd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 46 LILO of 220kV Sarni-Pandhurna at The line does not pass through critical environmental 400kV (PGCIL) substation Betul areas such as wildlife sanctuaries. No construction is M/S Punj Llyod being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 47 Betul 220- Bisnoor/Masod 132kV The line does not pass through critical environmental DCSS line areas such as wildlife sanctuaries. No construction is (Punj Loyd Ltd.) being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL Ujjain 48 Badnagar 220- Chhayan 132kv DCSS The line does not pass through critical environmental line M/s Swastik Mechanical areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive

28

S. Name of Line Works Current Status of Environmental Compliance No regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 49 LILO of Badnagar –Ratlam 220kv D/C The line does not pass through critical environmental line at Badnagar 400kv S/s (2xD/C) areas such as wildlife sanctuaries. No construction is M/s NKR being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 50 LILO of both ckt of Gandhisagar – The line does not pass through critical environmental Suwasra/Garoth 132kV line at areas such as wildlife sanctuaries. No construction is Bhanpura 220kV S/s M/s Kalptaru being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL Ratlam 51 LILO of 132kv Badod – Garoth line at The line does not pass through critical environmental Shyamgarh (D/C) M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 3 52 LILO of Ratlam - Meghnagar 132kv The line does not pass through critical environmental S/c line at Petlawad DCDS (D/C) areas such as wildlife sanctuaries. No construction is M/s BS Ltd being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 53 LILO of second ckt of Badod – The line does not pass through critical environmental Kota/Madok 220kV line at Bhanpura areas such as wildlife sanctuaries. No construction is 220kV S/s M/s BS Ltd being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 54 LILO of second ckt of Nagda- The line does not pass through critical environmental Neemuch 220kV line at Daloda 220kV areas such as wildlife sanctuaries. No construction is S/s M/s Kalptaru being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor.

29

S. Name of Line Works Current Status of Environmental Compliance No Number of trees to be cut: 33 55 LILO of Nagda 220-Ratadiya 132kV The line does not pass through critical environmental line at Unhel M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL Gwalior 56 LILO of 132 KV Gwalior-Karera- The line does not pass through critical environmental Pichhore Line at Chinaur M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 57 LILO of 132kV Gwalior-Dabra-Datia- The line does not pass through critical environmental Pichore line at Dabra M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 2 58 Datiya220- Bhander 132kV DCSS Line The line does not pass through critical environmental M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 59 Mehgaon 220-Pratappura 132kV The line does not pass through critical environmental DCSS line M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 60 Sabalgarh 220- Kelaras 132kV DCSS The line does not pass through critical environmental Line M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 61 Malanpur 220- Gohad 132kV DCDS The line does not pass through critical environmental Line M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL

30

S. Name of Line Works Current Status of Environmental Compliance No 62 220 KV DCDS Morena 400 KV The line does not pass through critical environmental (CWRTL Adani) – Sabalgarh DCDS areas such as wildlife sanctuaries. No construction is Line M/s L&T being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 63 220kv (Jarerua) DCDS LILO of Morena The line does not pass through critical environmental 400kV S/s (Adani)-Sabalgarh at areas such as wildlife sanctuaries. No construction is Morena 220kV substation M/s L&T being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 64 Bhonra-Kapasi 132 kv DCSS line The line passes through forest land and a combined M/s L&T forest clearance has been provided for both lines viz. Guna-Bhonra and Bhonra-Kapasi and the total area has been revised to 9.1341 ha by forest department. See annexure 3. Farmers will be compensated for loss of income due to construction activities. Works shall only be commenced in forest sections of the sub-project after obtaining the requisite forest permissions. Number of trees to be cut: NIL 65 Kolaras-Mada 132kV DCSS line The line does not pass through critical environmental M/s L&T areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 66 132kv DCDS Guna 220-Bhonra line The line passes through forest land and A combined M/s L&T forest clearance has been provided for both lines viz. Guna-Bhonra and Bhonra-Kapasi and the total area has been revised to 9.1341 ha by forest department. See annexure 3. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 67 LILO of one circuit of Malanpur- The line does not pass through critical environmental Mehgaon line at 400 KV S/s (CWRTL areas such as wildlife sanctuaries. No construction is Adani) Morena M/s L&T being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 68 2nd circuit of Shivpuri 220- Kolaras The line does not pass through critical environmental 132kV DCSS line M/s L&T areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 69 2nd ckt of Malanpur- Morar 132kV line The line does not pass through critical environmental M/s L&T areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due

31

S. Name of Line Works Current Status of Environmental Compliance No to construction activities. Number of trees to be cut: NIL Sagar 70 Khurai- Khimlasa 132kV DCSS line The line does not pass through critical environmental M/s L&T areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 71 LILO of Mungaoli Traction Feeder to The line does not pass through critical environmental Mungaoli (D/C) M/s BS Ltd areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 72 Ashoknagar 220-Kothiya 132kV DCSS The line does not pass through critical environmental Line M/s Bajaj areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 73 Sagar220- Rehli 132kV DCSS line M/s The line passes through forest land and forest Kalptaru cleanrance has been applied for. Works shall only be commenced in forest sections of the sub-project after ontaining the requisite forest permissions. See annexure 3. 12 Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 74 2nd ckt of Sagar 220-Sagar 132kV (I/C) The line does not pass through critical environmental M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL 75 Stringing of 3rd conductor from The line does not pass through critical environmental Bina220 to Mungaoli M/s Kalptaru areas such as wildlife sanctuaries. No construction is being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Number of trees to be cut: NIL Mandsaur 76 LILO of both ckt of Badod- Kota/Modak The line does not pass through critical environmental 220kV line at Suwasra 220kV S/s areas such as wildlife sanctuaries. No construction is (2XD/C) M/s Kalptaru being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the

12 Ibid 10

32

S. Name of Line Works Current Status of Environmental Compliance No revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut:17 77 LILO of one ckt of Neemuch 220- The line does not pass through critical environmental Mandsaur 132kV line at Budha areas such as wildlife sanctuaries. No construction is 132kvS/s M/s Kalptaru being undertaken in such environmentally sensitive regions. Farmers will be compensated for loss of income due to construction activities. Separate and individual tree cutting permission is not required. Present practice involves calculation of monetary value of trees by the revenue department which is then paid as compensation to the farmers. This ensures that the compensation is fair, unarbitrary and not decided solely by EA or contractor. Number of trees to be cut: 88 78 LILO of both circuit of 132kV The line does not pass through critical environmental Gandhisagar-Suwasra/Garoth line at areas such as wildlife sanctuaries. No construction is Suwasra 220kV Substation* being undertaken in such environmentally sensitive *Earlier LILO of both ckt of Badod- regions. Suwasra / Garoth 132kV line at Farmers will be compensated for loss of income due Suwasra 220kV S/s M/s Kalptaru to construction activities. Number of trees to be cut: NIL

Table No. 3.1: Project Progress Status of Environmental Compliance (Substations and Feeder Bays) S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays Jabalpur 1 Balaghat/ (2 x 100+40MVA) • No major adverse environmental issues identified. Kirnapur +400kv FB(2) No private land acquisition. The substation is built on 400/132kv +132kv FB(4) government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 2 Waraseoni 40MVA+132kV • No major adverse environmental issues identified. 132kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period.

33

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 3 Bada Malehra 40 MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 4 Deonagar 40 MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 5 Belkheda 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 6 Karakbel 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 7 Saori (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 8 Palohabada (1X50) MVA; 132kV • No major adverse environmental issues identified.

34

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 132/33kV S/s FB(1) Private land has been acquired through mutual consent. Compensation has been paid to the land owner. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 9 Patera (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Satna 10 Sidhi 220 (2nd) +160 MVA • No major adverse environmental issues identified. No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 11 Kotar 220 (2nd) +160 MVA • No major adverse environmental issues identified. No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 12 Chhatarpur +160 MVA • No major adverse environmental issues identified. (2nd) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period.

35

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 13 Satna-II (2X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 14 Shahdol (1X60) MVA; 220kV • No major adverse environmental issues identified. 220/132kV S/s FB(2)+132kV FB(1) No private land acquisition. The substation is built on (Upgradation) government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Indore 15 Badnawar (2x315MVA) + • No major adverse environmental issues identified. 400/220kv 400kv FB (4) + No private land acquisition. The substation is built on 220kv FB (4) government wasteland. +125MVAR bus • No trees felling in substation land Reactor • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 16 Upgradation of (1x160MVA) + • No major adverse environmental issues identified. Chapda 132kv 220kv FB(2) No private land acquisition. The substation is built on S/S to 220kv government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 17 Upgradation of (1x160MVA) + • No major adverse environmental issues identified. Depalpur 220kv FB (1) No private land acquisition. The substation is built on 132kv S/s to government wasteland. 220kv • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period.

36

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 18 Agrod 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Barwaha 19 400/220kv 1x315 MVA • No major adverse environmental issues identified. additional No private land acquisition. The substation is built on transformer at government wasteland. Chhegaon • No trees felling in substation land 400kv S/S • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 20 Teesgaon 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 21 Bistan 132/33 40 MVA+ 132kV • No major adverse environmental issues identified. kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 22 Pandhana 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period.

37

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 23 Singhana 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 24 Talakpura 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 25 Kukshi 160 MVA + 220kv • No major adverse environmental issues identified. 220/132kv FB(2) +132kv FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 26 Chhanera (2X160+1X50) MVA • No major adverse environmental issues identified. 220/132kV S/s 220kV FB(2)+132kV No private land acquisition. The substation is built on FB(3) government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 27 Singot (1X50)MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Bhopal

38

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 28 Salamatpur 40 MVA +132kv • No major adverse environmental issues identified. 132kv/33kv FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 29 Intkhedi 132kv 63 MVA +132kv • No major adverse environmental issues identified. /33kv FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 30 400/220kv 1x315 MVA • No major adverse environmental issues identified. additional No private land acquisition. The substation is built on transformer at government wasteland. Bhopal 400kv • No trees felling in substation land S/S • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 31 Mandideep +160 MVA • No major adverse environmental issues identified. 220 (2nd) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 32 Narsinghgarh 40MVA +132kv • No major adverse environmental issues identified. 132/33kv FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 33 Adampur 2x50MVA + 220kv • No major adverse environmental issues identified.

39

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 220/33kv FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 34 Bilkisganj (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 35 Khujner/sindao (1X50) MVA; 132kV • No major adverse environmental issues identified. ta132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 36 Bisnoor/Masod (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Itarsi 37 Betul 220 (2nd) +160 MVA • No major adverse environmental issues identified. No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 38 Silvani 132kv 40 MVA +132kv • No major adverse environmental issues identified.

40

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays /33kv FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 39 Udaipura 40MVA + 132kv • No major adverse environmental issues identified. 132/33kv FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Ujjain 40 Chhayan 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 41 400kv Bus 1X125 MVAR • No major adverse environmental issues identified. Reactor at No private land acquisition. The substation is built on Nagda 400kv government wasteland. S/S • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 42 Shyamgarh 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 43 Suwasra (2X160+1X50) MVA • No major adverse environmental issues identified.

41

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 220/132kV S/s 220kV FB(4)+132kV No private land acquisition. The substation is built on FB(4) government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 44 Unhel (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 45 Budha (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Gwalior 46 Chinaur 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 47 Bhander 63MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 48 Pratappura 40MVA+132kV • No major adverse environmental issues identified.

42

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 49 Kelaras 63MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 50 Gohad 63MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 51 Kapasi/ (1X50) MVA; 132kV • No major adverse environmental issues identified. Paranth FB(1) No private land acquisition. The substation is built on 132/33kv government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 52 Mada (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. Sagar 53 Khimlasa 40MVA+132kV • No major adverse environmental issues identified.

43

S. Substation Capacity and Status of Environmental Compliance No Name associated Feeder Bays 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 54 Mungaoli 63MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(2) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 55 Kothiya 40MVA+132kV • No major adverse environmental issues identified. 132/33kV FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 56 Rehli (1X50) MVA; 132kV • No major adverse environmental issues identified. 132/33kV S/s FB(1) No private land acquisition. The substation is built on government wasteland. • No trees felling in substation land • No Forest Land acquisition for Sub Station. • No Wild life sanctuary involved in Substation land. • Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period.

7. Based on the Environmental Management Plan, the Compliance Status on Environmental Issues and various environmental parameters has been prepared and presented in Table No. 3.2.

44

Table No. 3.2: Environment Management Plan and Status on Implementation Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period  Preparation  Land and  Loss of  Use of 25  MP  Complied NA of feasibility vegetation agricultural criteria for site Transc study and land and selection which o, detailed crops include District project report  Loss of environmental Commi (DPR) habitat and factors to ssioner  Location of vegetation minimize Office substation, clearing potential transmission  Land impacts and acquisition  Checklist/questi distribution  Increase in onnaire in lines soil erosion evaluating  Choice of and impact substation sites equipment to soil which aim at and productivity avoidance of technology  People  Physical land acquisition  Some  As displacem and contract some ent of environmental s were projects people impacts cancelle are and  Substations are d and complet structures all on had to ed and  Economic government land be few loss to (56 sites reaward projects people for MP Transco) ed, are due  Disturbance  No land hence, for and acquisition environ complet nconvenienc required but mental ion, e to people transfers of testing is testing due to ownership delayed. of traffic, from the Testing environ increased government to of mental noise MP Transco. environ parame and dust  Use of mineral oil mental ters levels, such as paramet needs vibration Duralife ers will to be  Interference Transformer Oil be carried to existing for transformers carried out on utilities  Use of air out and priority insulated submitte basis. substations to d during avoid fugitive next emissions of SF6 monitori (a potent ng GHG gas) period.  Water  Interference • MP  The sub- NA to local Transco, project drainage EPC activities  Water Contract do not quality or interfere impacts due with to erosion drainage and/or patterns or sedimentatio impact

45

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period n water quality in any manner. Complied  Air  Increased  MP  Some  As some dust and Transco, contracts projects noise levels, EPC were are and Contract cancelled complete vibration. or and had to d and few be projects  Emissions reawarded are due from heavy , hence, for equipment environme completio machinery ntal testing n, testing and is delayed. of constructio Testing of environm n vehicles. environme ental Baseline ntal paramete data will be parameter rs needs generated s will be to be before carried out carried commence and out on ment of civil submitted priority works. during basis. Twice a next year monitoring monitoring period. will be done.

      Orientation People Awareness Conduct briefing EPC Tender NA for of workers of EPC Contrac specificati contractor on the Contractor(s) on tor(s), ons for and workers environmen EMP, records PMUs contracto tal management, of MP rs include requiremen and reporting Transc guidleine ts and their o, s for  responsibilit Identify critical Environ ensuring y areas to be mental best monitored and staff/co condition  Understand the required nsultant s and ing of EPC mitigation in PMU awarenes Contractor( measures s  s) of their Create programs responsibilit awareness of for y in sexually- workers. implementi transmitted Complied ng theEMP diseases such as HIV/AIDs  Prepare  People  Avoid  Temporary  EPC  Complied  NA construction effects of pedestrian and Contrac managemen EPC traffic tor(s), t Contractor( management PMUs work plan s) plan of MP

46

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period Transc   unplanned Community and o,Envir activities safety plan onment

 Smooth al work staff/co implementa nsultant tion in PMU  Land  Spoils disposal  Some  As some plan contracts projects were are   Air Noise and dust cancelled complet control plan and had ed and  Water  Drainage and to be few storm water reawarde projects management d, hence, are due plan environm for ental completi  Waste  Materials testing is on, management delayed. testing plan Testing of of environm environ  Construction ental mental waste paramete paramet management rs will be ers plan. Baseline carried needs to data will be out and be generated submitted carried before during out on commencement next priority of civil wroks. monitorin basis. Twice a year g period. monitoring will be done.

     Hiring of People Conflict due EPC EPC Complied NA project staff to potential Contractor(s) will Contrac and workers workers be required to tor(s), migration use local labour PMUs for manual work of MP  Lack of and eligible local Transc local workforce for o, support to clerical and Environ the project office jobs mental  Dispute staff/co over nsultant transparenc in PMU y of hiring

    - Presence of People Increase in None required Complied NA workers at demand for construction services sites such as food, temporary

47

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period housing, etc.  Create opportunitie s for small- scale business to provide services such as food, temporary housing, etc.

     Site People Dismantling Construction EPC Complied NA preparation, of management Contrac vegetation structure(s) plan will be tor(s), and land and strictlyimplement PMUs clearing for equipment ed of MP substations from Transc  and existing Use of proper o, transmission substations safety Environ line right-of- clothes/equipme mental way(ROW) nt in dismantling staff/co structure(s) nsultant  Construction andequipment in PMU of  substations, Debris/dismantle installation d of required structures/equip equipment ment will be at disposed of in substations, designatedlandfil erection of l and/or transmission controlled towers and dumpsites stringing of  Usable scrap conductors materials from dismantling will be stored in warehouses of MP Transco in Jabalpur. Complied NA  Potential  Provide fence or safety risks barricade to (as appropriate), community sufficient lights, clear warning signs and danger signals, and take all precautions

48

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period identified in the community and safety plan  Assign security personnel to prevent accidents, trespassing, and pilferage  EPC Contractor(s) to direct drivers to strictly follow road regulations

  MP Interferenc Danger and Complied NA e with road clearly visible Transc crossings warning signs o, EPC will be posted at contrac designated sites tor  Scaffoldings will be placed over road crossing points  Construction vehicles to strictly follow road regulations  Implement temporary pedestrian and trafficmanageme nt plan Complied NA  Potential  Provide sanitary health and facilities and safety risks wash areas to workers  Provide safe drinking water and garbage bins  Enforce good housekeeping at all times  Provide workers with hard hat, safety shoes and belts  Coordinate with nearest hospital for

49

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period arrangements in case of accidents  Assign nurse or medical staff to make weekly rounds at substation sites  Set up first aid treatment within construction sites and field office  Observance and compliance with relevant safety measures required by law and best engineering practices  Provide communication devices to designated workers

   MP Land and Erosion Compensation Compensat NA Transc vegetation and for temporary ion is paid o, EPC localized damages to for crop Contrac flooding crops/plants and tree along the ROW tor  damages. Loss of and substations habitat and The sub- some  Cut trees owned projects do mature by the not result in trees of government will any major economic be sold erosion but value such andrevenue best as teak turned over to practices Revenue ensure that Authority soil is  Landscaping/rep replaced lanting of trees once at subs-stations excavation will bedone after is carried completion of out. construction Complied works  Erosion-control measures will be provided (as needed)

50

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period  Implement spoils disposal plan and construction waste management plan

   MP Water Generation Avoidance of Complied NA of sewage waterways in Transc from site selection o, EPC constructio Contrac  n workers Provide sanitary tor facilities to  Localized workers and flooding safe drinking water  Increase turbidity in  Construction surface works will done water near during summer constructio in areas n sites potential for erosion and localized flooding  Implement drainage and storm water management plan  Waterways were avoided in selecting subproject sites

   MP Air Heavy Construction Complied NA equipment vehicles will be Transc and maintained to o, EPC constructio minimize Contrac n vehicles vehicular tor may emissions increase  vehicular Enclose emissions construction sites temporarily  Transport to contain dust of dispersion constructio  n materials Warehouse for to construction constructio materials onsite ns sites will be provided may to reduce trips of increase material delivery dust level  EPC Contractor(s) will

51

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period be required to  Earthmovin maintain g works, construction excavations vehicles and , and heavy opened equipment land areas machineries for regularly to substations reduce and towers emissions may increase  Opened land dust levels areas or sources of dust will be  Increase in sprayed with noise level water (as and needed) vibration from  Transport of excavation dust-generating and heavy materials will be equipment covered and  constructio Observance of n vehicles low speed by vehicles to reduce noise  Noise- generating works will be done between 7AM and 7PM done at daytime as required by MPPCB (February 2013)  Construction sites will be covered with acoustic screens and machineries will be temporarily enclosed to control noise (MPPCB guidelines, February 2013)  Require EPC Contractor(s) to maintain and tune-up construction vehicles to reduce noise

52

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period and no blowing of horns  Observe/comply with traffic management plan

     Use of Land Accidental Provision of oil- MP Complied NA mineral oil spillage water separator Transc  for Water that would Provide for oil o transformers contaminat containment e land and structure. water  Baseline data will be generated before commencement of civil wroks. Twice a year monitoring will be done.  People  Occupation  Acceptance of Complied NA al health mineral oil risks to should be workers accompanied due to with Material exposure Data Safety Sheets and/or be certified that it is PCB-free  Fire extinguishers readily available in storage areas for mineral oil

 Presence of  Land  Depreciatio  Availability of Complied NA substations, n of land stable and power property reliable power transmission values will trigger and adjacent to economic distribution substations development in lines and power the area transmissio n towers  People  Hazards  Provide security MP All sub- NA such as and inspection Transc projects electrocutio personnel to o, EPC ensure n, lightning avoid pilferage Contrac that strike, etc. and vandalism tor danger due to of equipment signs and accidental and lines. awarenes

53

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period failure of s posters  power Appropriate are transmissio grounding and displayed n and deactivation of to distribution live power lines educate lines during and maintenance inform work members  Designed with of the protection public. system that Complied shuts off during power overload or similar emergencies  Maintain and comply with electrical standards  Distribution lines entering and leaving the substations are insulated (or covered) to minimize impacts  Regular monitoring and maintenance to ensure safety and integrity of power lines and substations  Conduct information and education campaign to local people to enhance awareness on safety practices of living near substations

54

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period

  Accident Implement MP Complied NA working in safety plan to Transco elevated reduce risks position  Provision of safety belts and other working gears for protection

 Potential All sub- NA  EMF levels MP exposure to projects expected to be Transco electric and ensure way below the magnetic that limits set by fields danger International (EMF) signs and Commission awarenes on Non-Ionizing s posters Radiation are Protection(ICNR displayed P) which is to 4.17 kV/m for educate electric field and and 833 mG for inform magnetic field members  Spot of the measurements public. of EMF Complied  Substations will be fenced and security staff assigned to prevent unauthorized public access  Information and education campaign will be conducted to local people to create awareness on safety practices

 Generation  More than 200 MP Complied NA of positions will be Transco employmen created during t the operation MP Some As some    Noise Disturbanc Periodic Transco contracts projects e to maintenance of were are settlements equipment such cancelled completed

55

Project Environme Description Mitigation/Enhan Respons Complianc Correctiv Activity ntal of Potential cement ible Unit e status e Component Environment Measures during the Actions Likely to be al Impact reporting Required Affected period near the as transformers and had to and few substations and capacitors be projects to minimize reawarded, are due noise hence, for generation. environme completio ntal testing n, testing  Provide is delayed. of enclosure of Testing of environme noise- environme ntal generating ntal parameter equipment parameters s needs to  Monitor ambient will be be carried noise levels. carried out out on Baseline data and priority will be submitted basis. generated during next before monitoring commencement period. of civil works. Twice a year monitoring will be done.

56

4.0 Monitoring of environmental receptors/attributes

8. In order to comply with requirements of Environmental monitoring, the contractor carries out regular testing at specified intervals with regards to air quality, water quality and noise levels during preconstruction, construction and post construction stage as mentioned in the environmental monitoring plan. The implementation is monitored through MPPTCL. The primary responsibility of the environmental monitoring agency are for ensuring that testing, monitoring and reporting impact of transmission lines & substation projects on air, ground & surface water and noise levels is carried out as per schedule.

9. During the construction and operation phase of this project, the monitoring of the environmental aspects is done at the transmission line by the safeguard specialist of the PMU. The mitigation measures suggested in the IEE require monitoring of environmental parameters during construction and operational phases of the project. During the construction phase, the Contractor ensures that activities like handling of earth works clearing work, access road construction, putting proper traffic signals is done properly to have minimum impact. This in turn is monitored by the Project Engineer of the individual transmission line/substation project.

10. The ESU and site support team ensures that EPC contractors will adhere and comply with all measures and procedures identified in the EMP. The plans, endorsed by the EA and GoMP, will be monitored in accordance to ADB Safeguard Policy 2009 requirements. Mitigation measures related to construction as specified in the EMP will be incorporated into civil works contracts, and their implementation will be primarily the responsibility of the contractors. Monitoring of the quality of water, soil, air and noise during the construction stage is the responsibility of the contractor by the approved government agency. Other environmental good practices to be followed include sanitary waste management, noise abatement, maintaining hygienic conditions, maintenance of fire and safety equipment. Monitoring report will be prepared once in six months with the corrective action plan for the problem areas. PMU’s monitoring report will be provided to ADB on a bi-annual basis and will demonstrate that sound environmental management practices are applied during construction and operation, and the set environmental mitigation targets are achieved.

11. Since the civil construction works under the project are very minor, hence, the environmental monitoring for ambient air quality, water quality, soil and noise levels during various stages – pre construction, construction and post construction will be monitored as per below schedule given in Table 4.0.

57

Table 4.0: Environmental Monitoring Schedule

Environmental Environmenta Parameters Sampling Monitoring Implementation Supervision Component l to be Location Frequency Component monitored 1.Air Quality A. Pre PM10, PM2.5, Boundary of One time Contractor by Contractor/

construction SO2& NOX as substation CPCB approved MPPTCL Field staff stage per NAAQS, laboratory (Baseline 2009 development)

B. Construction PM10, PM2.5, Boundary of For each sub- Contractor by Contractor/ Stage SO2& NOX as substation station CPCB approved MPPTCL Field staff per NAAQS, location, twice laboratory 2009 a year monitoring will be done. C. Post PM10, PM2.5, Boundary of One time Contractor by Contractor/ construction SO2& NOX as substation CPCB approved MPPTCL Field staff Stage per NAAQS, laboratory 2009 2.Noise A. Pre Noise level Boundary of One time Contractor by Contractor/

construction Leq (Day), Leq substation CPCB approved MPPTCL Field staff stage (Baseline (Night), laboratory development) Maximum Noise level. B. Construction Noise level Boundary of For each sub- Contractor by Contractor/ Stage Leq (Day), Leq substation station CPCB approved MPPTCL Field staff (Night), location, twice laboratory Maximum a year Noise level. monitoring will be done. C. Operation Noise level Boundary of One time Contractor by Contractor/ Stage Leq (Day), Leq substation CPCB approved MPPTCL Field staff (Night), laboratory Maximum Noise level. 3. Soil A. Pre Visible spills 1 location One time Contractor by Contractor/

construction and/or soil inside CPCB approved MPPTCL Field staff stage staining, Oil & substation laboratory (Baseline grease development) B. Construction Visible spills 1 location For each sub- Contractor by Contractor/ Stage and/or soil inside station CPCB approved MPPTCL Field staff staining, Oil & substation location, twice laboratory grease a year monitoring will be done. C. Operation Visible spills 1 location One time Contractor by Contractor/ Stage and/or soil inside CPCB approved MPPTCL Field staff staining, Oil & substation laboratory grease

12. The environmental monitoring of ambient air, ambient noise and soil quality was planned to be carried out during this monitoring period of January 2018 to June 2018. Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period.

58

5.0 Any Other environmental aspects, impacts observed during implementation which were not covered earlier

13. The project does not have any unanticipated impacts during this reporting period.

59

6.0 Details of Grievance Redress Committee and Complaints Received from public and actions taken thereof to resolve

14. The Grievance rederess committee is set up by MP Transco-PMU and consists of representatives from the local Panchayat Head, a District Revenue Commissioner, representative from the EPC Contractor(s) only during construction phase, designated staff of MP Transco-PMU on safeguards, Manager/Director of MP Transco-PMU, and a witness of the complainant/affected person. See annexure 4 for details.

15. Responsibilities: The GRC is expected to: (i) resolve issues on land acquisition (if any), compensation to temporary damages to crops and plants, and other use of land such as borrow areas for transmission towers and substations; (ii) convene twice a month to review complaints lodged (if any), (iii) record the grievances and resolve the issues within a month (30 days) from the date the grievance was filed, (iv) report to the complainant(s) the status of grievance resolution and the decisions made.

16. Procedures: Minor grievances on compensation or environmental issue during construction will be resolved onsite through the EPC Contractor(s) Project Site Engineer. As a formal process of grievance resolution, the procedure is described below. (i) Affected persons (Aps) are informed in writing by MP Transco-PMU (or designated representative) of the damages and entitlements for compensation. If the Aps are satisfied, compensation can be claimed from MP Transco-PMU through the EPC Contractor(s). If the Aps are not satisfied, they can request for clarification from MP Transco-PMU. If the Aps are not convinced with the outcome, they can file the grievance to the GRC with the help of MP Transco-PMU who will provide the written documentation. (ii) The GRC conducts a hearing of the grievance in the presence of the Aps and will provide a decision within 15 days from the receipt of the complaint. Minutes of the meeting are approved by MP Transco-PMU and provided to the Aps including the decision made by the GRC. If the Aps are satisfied with the GRC decision, they can claim the compensation from MP Transco-PMU and/or EPC Contractor(s). (iii) No grievances have been received in any of the subprojects during this monitoring period.

60

7.0 Public Consultation During Project Implementation

17. During field visits, public consultations with affected persons were carried out. The site visit was accompanied by Contractor representative and meeting with MPPTCL officials at divisional offices was held to understand the overall physical progress, issues impediment to project completion and observation requiring attention of PMU.

18. Substations are built on government wasteland except for Palohabada (where a part of substation land has been acquired through mutual consent). In case of transmission lines, compensation is paid to farmers for crop loss and trees. The ROW is selected in a manner such that it avoids ecological sensitive areas. No major complaints were received with regards to compensation amount. In some lines, payments are pending at relevant tehsil or revenue office and contractor and MPPTCL officials assured that they will be cleared soon. The contractor provides amenities and safety equipments to workers. The photographs of site visits and lists of affected persons who participated in public consultations are provided in Annexure 1 and Annexure 2 respectively. Table 7.0 and 7.1 summarises public consultations findings for transmission lines and substations, additional transformers and associated Feeder Bays respectively.

Table 7.0: Public Consultation for Transmission Lines

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion Jabalpur 1 LILO of 400kv seoni Waratola, Wara, June 2018 People Compensation to Bhilai S/C line at Kaneri, Sompuri, enquired about process and Balaghat/Kirnapur Hirapur the project schedule (D/C) schedule and explained. compensation time frame. 2 LILO of 132kV Kholtola, Sarandi, June 2018 People wanted Assured that no Balaghat- Seoni/ Chandanpur, to know if the damage to Katangi line at Kasartola project will existing resources Waraseoni 132kV impact drinking of water will be S/s (2XD/C) water done as a result resources. of project activity. 3 LILO of both circuit Hirapur, Kumeri, NA NA Subproject NA Subproject of 132kV Balaghat- Waratolo, Nara completed completed Bhanegaon Line at Blaghat/Kirnapur 400kV S/s (2XD/C) 4 Second circuit of Nayakhera, NA NA Subproject NA Subproject Tikamgarh- Budhera Lachamanpura, completed completed 132kV DCSS Line Nonhitehri, Ganesgnagar, Barmarai,

61

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion 5 Narsinghpur 220- Magardha, June 2018 People Explained about Devnagar 132kV Samnapur, enquired about time frame and DCSS Line Bhelpani, rohhata the project complaint schedule and mechanism. complaint mechanism. 6 Karakbel- Belkheda Belkhera, Kunra, June 2018 People Explained that the 132kV DCSS line Jamuniya, Rakhi enquired revenue authority about calculates the compensation amount payable amount and by MPPTCL. calculation process. 7 Narsinghpur 220KV Bichua, Pindarai, June 2018 People Explained about Karakbel 132KV Mekh, dokarghat enquired about time frame and DCS line the project complaint schedule and mechanism. complaint mechanism. 8 Panagar 220-Patan Rampura, Patan, June 2018 People Grievance 132kV DCSS line Jogiya, enquired about mechanism Kukarbhuka, the complaint explained. Kamond, mechanism. Didhaura 9 Chhindwara 220- Ghoghra, June 2018 People Explained about Saori 132kV DCSS Kukrachiman, enquired about time frame and line Malhanwara, the project complaint Paunari schedule and mechanism. complaint mechanism. 10 Chichli 220- Sukri, Chiraha, June 2018 People Explained that no Palohabada 132kV Motiyadau, enquired about land will be DCSS line Siddhi, Tanchana land acquisition acquired in the process. subproject activity. 11 132kv DCSS line Khamkhera, June 2018 People Grievance from Damoh 220kv Pathariya, Mara, enquired about mechanism to Patera 132 kv Chaupa Khurd the complaint explained. substation mechanism. 12 Second circuit of Kateratola, NA NA Subproject NA Subproject 132kV Tap Line Kosmi, Sirpurtola, completed completed from Balaghat- Nandgaon Katangi Satna

62

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion 13 Second circuit NA NA Subproject NA Subproject 132kV of completed completed chhatarpur- Khajuraho line

14 LILO of second ckt Lakhanwa, NA NA Subproject NA Subproject of Bansagar-Satna Karahi Khurd, completed completed 220kV line at Kotar Ahmadpur, 220kV S/s Dhenrhi 15 LILO of Satna – June 2018 People Explained that it Maihar 132kV line at enquired if is transmission Satna-II 132kV S/s electricity network and supply will be electricity supply affected during will not be project activity. affected. 16 LILO of second ckt Gortara, Jamur, NA NA Subproject NA Subproject of Birsinghpur – Jamua, Raipur completed completed Amarkantak 220kV line at Shahdol 220kV s/s 17 Birsinghpur 220- Senduri, June 2018 People Explained that no shahdol 132kV Chhotakhamaria, enquired about land will be DCSS line Shahpur, land acquisition acquired in the Raugarh process. subproject activity. 18 LILO of 132 Mungwari, June 2018 People were NA Tikamgarh-Bijawar Bandha, supportive of line for Bada Gharauli, Goura the project. No Malehra (Satna Div.) major queries. Indore 19 LILO of one circuit Manasa, Gunai, June 2018 People were NA of Ashta 400-Dewas Budangaon, supportive of 220 kv D/C line at Nanasa, the project. No Chapda 220kv S/s Khonpirpipaliya major queries. (D/C) 20 Pithampur 400 – Sejwani, June 2018 People Explained that Depalpur 220kv Kumarkaradya, enquired about revenue authority DCSS line Sulawar, Umariya calculation of is responsible for compensation calculation of amount. project amount payable by MPPTCL. 21 Dewas 220- Agrod Jaitpura, NA NA Subproject NA Subproject 132kv DCSS line Kamarkhedi, completed completed Kalukhedi, Karnakhedi 22 Dhar 220 – Pinjrao, Pipaliya, June 2018 People Explained that Teesgaon 132kv Kherod, Antaray enquired if top best practices

63

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion DCSS line soil fertility will ensure that be affected as a fertility will not be result of the affected and project’s normal activity. agricultural activities can resume after construction works. 23 LILO of both Circuit Dokliyapara, June 2018 People Explained that no of 400 kv Nagda- Piplipara, enquired about land is acquired in Rajgarh line at Imlipara, land acquisition the project activity Badnawar (2 x D/C) Satrunda and and compensation compensation is amount. paid for crop damages. 24 Second Circuit of Mohnipura, NA NA Subproject NA Subproject Kukshi Alirajpur Chaundiyapura, completed completed 132kv line Talanpur, Julwaniya Barwaha 25 LILO of 132 Magariya, June 2018 People Compensation Khargone Bikayan Bargaon, enquired about process line at 132 Kv sub- Moghan, compensation explained. station Bistan Chandabad process. 26 LILO of 132kv Dulhar, Teela NA NA Subproject NA Subproject Chegaon completed completed Nepanagar line at Pandhana 27 LILO Manawar – Singhana, NA NA Subproject NA Subproject Kukshi DCSS line at Anjaniya, completed completed Singhana (D/C) Bhesawad 28 LILO of 132Kv Birla NA NA Subproject NA Subproject Khargone – completed completed Julwaniya line at 132Kv S/S Talakpura 29 Julwaniya 400- Lingwa, Kusmari, June 2018 People Explained that no Kukshi 220kv line Jalgone, Morgun enquired about land is acquired in (D/C) land acquisition the project activity and and compensation compensation is amount. paid for crop damages. 30 220kV DCDS Manjadhar, June 2018 People Explained that no Khandwa(400 Sakkapur, enquired about land will be PGCIL) to Chhanera Surwanya land acquisition. acquired for the line project. 31 Chhegaon 220- Sahejla, NA NA Subproject NA Subproject Singot 132kV DCDS Bikankheri, completed completed Line lakhmenkhri,

64

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion Sombulai 32 Chhanera 220- Sadiyapani, NA NA Subproject NA Subproject Khirkiya 132kV Manjhad, completed completed DCDS Line Bediyakhal, Nishaniya Bhopal 33 Bairagarh 220 – Intkhedi, NA NA Subproject NA Subproject Intkhedi 132kv Hazzampura, completed completed DCDS line Hazarpura, Chandanpura 34 Second circuit of Bagoniya, NA NA Subproject NA Subproject Bairagarh – Purachindwada, completed completed Shyampur Tarasewaniya 35 Second circuit of Sherpura, Dabar, NA NA Subproject NA Subproject Gairatganj – Vidisha Berkheri, completed completed 220 132kv line Berkheda, Ahmadpur 36 Shujalpur- Bamora kheda, June 2018 People Compensation Narsinghgarh 220kv Gokalpur, enquired about process DCSS line (Initially Buchakhedi, compensation explained. charged on 132kv) Kansrod process. 37 LILO of one circuit Hathaikera June 2018 People Explained with of Bhopal – enquired about help of site Hosangabad 220kv delay in project engineer that D/C line at Adampur activity. project activity will 220kv S/s (D/C) be resumed shortly. 38 Udaipura –Silvani Nigri, Saikheda, June 2018 People Compensation 132kv DCSS line Chunnehitya, enquired about process Nurpura compensation explained. process. 39 LILO of Vidisha- , NA NA Subproject NA Subproject Bairasiya Line at Chirohlikhurd completed completed Salamatpur 132 KV S/s 40 Mugaliyachhaap Aamkheda, Bilori, NA NA Subproject NA Subproject 220- Bikisganj Choona, Nagori completed completed 132kV DCDS line 41 132kv Rajgarh Nagori June 2018 People Explained with (Biaora) –Khujner/ enquired about help of site Sindaota Line delay in project engineer that activity. project activity will be resumed shortly. 42 LILO of one ckt of Hansuwa, NA NA Subproject NA Subproject Vidisha Gairatganj Parasikunda, completed completed at Raisen 132kV S/s Dhanorahaveli, Murelkhurd Itarsi 43 Second circuit of Amdar, Thawdi, NA NA Subproject NA Subproject Betul 220 Gudgaon Junawani, Chata, completed completed

65

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion 132kv line Gawdigaula 44 Chichli 220- Injri, Satehri, NA NA Subproject NA Subproject Udaipura 132kv Kirgikala, completed completed DCDS line (220kv Kathalikhurd, line charged at Ghanatunda 132kv) 45 Betul400 (PGCIL)- Khadla NA NA Subproject NA Subproject Betul 220kV DCDS completed completed line 46 LILO of 220kV June 2018 People wanted Explained that Sarni-Pandhurna at to know if fertile best practices 400kV (PGCIL) land will be ensure that Substation Betul damaged during fertility is not the project affected in any activity. manner. 47 Betul 220- Khadla, June 2018 No major NA Bisnoor/Masod Karajgaon, issues. People 132kV DCSS line Sehra, Gorakhar, are supportive Sarandai of the project. Ujjain 48 Badnagar 220- Badnawar, June 2018 No major NA Chhayan 132kv Silodiya, Karoda, issues. People DCSS line Dhulana, are supportive Palibaroda of the project. 49 LILO of Badnagar – Dhamna, June 2018 People Explained with Ratlam 220kv D/C Bhuwankheda, enquired about help of site line at Badnagar Kherwas delay in project engineer that 400kv S/s (2xD/C) activity. project activity will be resumed shortly. 50 LILO of both ckt of Govindkhera, June 2018 People Compensation Gandhisagar – Dhanakpura, enquired about process Suwasra/Garoth Borobiya the explained. 132kV line at compensation Bhanpura 220kV S/s process. Ratlam 51 LILO of 132kv Banskhedi, June 2018 People Explained that no Badod – Garoth line Barkhera, enquired land acquisition at Shyamgarh (D/C) Dhamniyadiwan whether the would result from project will the project result in land activity. acquisition. 52 LILO of Ratlam - Khariya, Khoriya, June 2018 No major NA Meghnagar 132kv Nabarpura, issues. People S/c line at Petlawad Mawaripara are supportive DCDS (D/C) of the project. 53 LILO of second ckt Govindkhera, NA NA Subproject NA Subproject of Badod – Dhanakpura, completed completed Kota/Madok 220kV Borobiya line at Bhanpura 220kV S/s

66

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion 54 LILO of second ckt Lalakhera, June 2018 People Assured that no of Nagda- Neemuch Daloda, Sagra, enquired if such disturbances 220kV line at Sersob, drinking water will be caused Daloda 220kV S/s Kalhmankheri supply will be due to the project affected due to activity. the project. 55 LILO of Nagda 220- Nawada, Gurla NA NA Subproject NA Subproject Ratadiya 132kV line completed completed at Unhel Gwalior 56 LILO of 132 KV Bhagrathpura, NA NA Subproject NA Subproject Gwalior- Karera- Chakrakra, completed completed Pichhore Line at Chakkhurdpur, Chinaur Khudpur 57 LILO of 132kV June 2018 People wanted Explained that Gwalior-Dabra- to know if the only tower Datia-Pichhore line project will locations base is at Dabra cause problems built and no major with soil fertility. excavation is carried out. 58 Datiya220- Bhander Dudhra, Kumehri, NA NA Subproject NA Subproject 132kV DCSS Line Sirol, Chirauli, completed completed Sindhwari 59 Mehgaon 220- Kheriya, Devri, NA NA Subproject NA Subproject Pratappura 132kV Maroli, completed completed DCSS line Meghpura, Pali, Pawai 60 Sabalgarh 220- Khumankapura, NA NA Subproject NA Subproject Kelaras 132kV Surapura, completed completed DCSS Line Lilarkupra, Semai 61 Malanpur 220- Tukera, Ikehra, NA NA Subproject NA Subproject Gohad 132kV Jhawanpura, completed completed DCDS Line Ramanpur 62 220 KV DCDS Basahri, June 2018 People Explained about Morena 400 KV Lolakpur, Barera, enquired about compensation (CWRTL Adani) – Churela, Jafra, compensation process and Sabalgarh DCDS Khanela process and complaint Line complaint mechanism. mechanism. 63 220kv (Jarerua) NA NA Subproject NA Subproject DCDS LILO of completed completed Morena 400kV S/s (Adani)-Sabalgarh at Morena 220kV substation M/s L&T 64 Bhonra-Kapasi 132 Mangrora, NA NA Subproject NA Subproject kv DCSS line Lakhmanpura, completed completed Dhanaria, Pachria

67

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion 65 Kolaras-Mada Manipura, NA NA Subproject NA Subproject 132kV DCSS line Mohral, Khairdi, completed completed Kharee 66 132kv DCDS Guna Bhurakheri, June 2018 People Explained that the 220-Bhonra line Dhaneria, wanted to project does not Khadakpurchak know if land have any land will be acquisition. acquired for the project. 67 LILO of one circuit Rithora, NA NA Subproject NA Subproject of Malanpur- Malanpur, completed completed Mehgaon line at 400 Naugaon, Gurkha KV S/s (CWRTL Adani) Morena 68 2nd circuit of Shivpuri Binega, NA NA Subproject NA Subproject 220- Kolaras 132kV Piparsama, completed completed DCSS line Malakhera, Marikhera 69 2nd ckt of Malanpur- Barwari, NA NA Subproject NA Subproject Morar 132kV line Sanichara, Paroli, completed completed Nayagaon Sagar 70 Khurai- Khimlasa Gamariyakhurd, June 2018 No major NA 132kV DCSS line Naukheda, queries. Jagdishpura, Khejra Ijjat 71 LILO of Mungaoli Semerkhedi, NA NA Subproject NA Subproject Traction Feeder to Belai, Nidar, completed completed Mungaoli (D/C) Hureri, Niboda 72 Ashoknagar 220- Bhorakachi, NA NA Subproject NA Subproject Kothiya 132kV Takneri, Mohrirai, completed completed DCSS Line Silawan, Seji 73 Sagar220- Rehli Pandarpur, Patna June 2018 People Assured that no 132kV DCSS line Kakri, Khamariya, enquired if such disturbances Jamghat, Patna drinking water will be caused supply will be due to the project affected due to activity. the project. 74 2nd ckt of Sagar 220- Makroniya, NA NA Subproject NA Subproject Sagar 132kV (I/C) Bartuma, completed completed Sainkhera 75 Stringing of 3rd Mungaoli, Kasba NA NA Subproject NA Subproject conductor from range, Kasba completed completed Bina220 to Mungaoli Kachi Mandsaur 76 LILO of both ckt of NA NA Subproject NA Subproject Badod- Kota/Modak completed completed 220kV line at Suwasra 220kV S/s (2XD/C) 77 LILO of one ckt of June 2018 People Explained that no

68

S. Subproject Location of Date Issues Outcomes of the No Public Discussed Public consultation Discussion Neemuch 220- enquired about acquisition will Mandsaur 132kV land acquisition take place in the line at Budha and project activity 132kvS/s compensation and explained the process. compensation process. 78 LILO of both circuit NA NA Subproject NA Subproject of 132kV completed completed Gandhisagar- Suwasara/Garoth line at Suwasara 220kV Sub-station* *Earlier LILO of both ckt of Badod- Suwasra / Garoth 132kV line at Suwasra 220kV S/s

69

Table 7.1: Public Consultation for Substations, additional transformers and associated Feeder Bays S. Subproject Capacity and Date Issues Outcomes of the No associated Discussed Public Feeder Bays Discussion 1 Balaghat/Kirnapur (2 x June 2018 People wanted Assured that no 400/132kv 100+40MVA) to know about land acquisition +400kv FB(2) land acquisition would result +132kv FB(4) for the project. because of the project activity. 2 Waraseoni 132kV 40MVA+132kV June 2018 People enquired Assured that FB(2) about disruption project is entirely of crop on government cultivation due land and would to the project. not encroach upon farmlands in any manner. 3 Bada Malehra 40 MVA+132kV June 2018 No major NA 132/33kV FB(1) concerns reported. 4 Deonagar 40 MVA+132kV June 2018 People enquired Assured that 132/33kV FB(1) about disruption project is entirely of crop on government cultivation due land and would to the project. not encroach upon farmlands in any manner. 5 Belkheda 40MVA+132kV June 2018 People wanted Explained that the 132/33kV FB(1) to know if project activity project activity aims at improved would result in power electricity supply transmission in improvement. the state. 6 Karakbel 132/33kV 40MVA+132kV June 2018 People wanted Assured that no FB(2) to know about land acquisition land acquisition would result for the project. because of the project activity. 7 Saori 132/33kV (1X50) MVA; June 2018 No major NA S/s 132kV FB(1) concerns reported. 8 Palohabada (1X50) MVA; June 2018 No major NA 132/33kV S/s 132kV FB(1) concerns reported. 9 Patera 132/33kV (1X50) MVA; June 2018 People enquired Assured that S/s 132kV FB(1) about disruption project is entirely of crop on government cultivation due land and would to the project. not encroach upon farmlands in any manner. 10 Additional +160 MVA NA NA Subproject Transformer at Completed Sidhi 220 (2nd) 11 Additional +160 MVA NA NA Subproject Transformer at Completed Kotar 220 (2nd) 12 Additional +160 MVA NA NA Subproject Transformer at Completed

70

S. Subproject Capacity and Date Issues Outcomes of the No associated Discussed Public Feeder Bays Discussion Chhatarpur (2nd) 13 Satna-II 132/33kV (2X50) MVA; June 2018 No major NA S/s 132kV FB(2) queries. 14 Shahdol (1X60) MVA; NA NA Subproject 220/132kV S/s 220kV Completed (Upgradation) FB(2)+132kV FB(1) 15 Badnawar (2x315MVA) + NA NA Subproject 400/220kv 400kv FB (4) + Completed 220kv FB (4) +125MVAR bus Reactor 16 Upgradation of (1x160MVA) + June 2018 People wanted Assured that no Chapda 132kv 220kv FB(2) to know about land acquisition S/S to 220kv land acquisition would result for the project. because of the project activity. 17 Upgradation of (1x160MVA) + June 2018 People enquired Assured that Depalpur 132kv 220kv FB (1) about disruption project is entirely S/s to 220kv of crop on government cultivation due land and would to the project. not encroach upon farmlands in any manner. 18 Agrod 132/33kV 40MVA+132kV June 2018 People wanted Explained that FB(1) to know if crop sub project will be damaged activity is entirely due to project on government activity. land. 19 400/220kv 1x315 MVA NA NA Subproject additional Completed transformer at Chhegaon 400kv S/S 20 Teesgaon 40MVA+132kV June 2018 No major NA 132/33kV FB(1) concerns reported. 21 Bistan 132/33 kV 40 MVA+ 132kV June 2018 People wanted Explained that FB(1) to know if crop sub project will be damaged activity is entirely due to project on government activity. land. 22 Pandhana 40MVA+132kV NA NA Subproject 132/33kV FB(2) Completed 23 Singhana 40MVA+132kV NA NA Subproject 132/33kV FB(2) Completed 24 Talakpura 40MVA+132kV NA NA Subproject 132/33kV FB(1) Completed 25 Kukshi 220/132kv 160 MVA + June 2018 People wanted Explained that 220kv FB(2) to know if crop sub project +132kv FB(1) will be damaged activity is entirely due to project on government activity. land. 26 Chhanera (2X160+1X50) June 2018 People wanted Explained that the 220/132kV S/s MVA 220kV to know if project activity FB(2)+132kV project activity aims at improved

71

S. Subproject Capacity and Date Issues Outcomes of the No associated Discussed Public Feeder Bays Discussion FB(3) would result in power electricity supply transmission in improvement. the state. 27 Singot 132/33kV (1X50)MVA; NA NA Subproject S/s 132kV FB(1) Completed 28 Salamatpur 40 MVA +132kv NA NA Subproject 132kv/33kv FB(1) Completed 29 Intkhedi 132kv 63 MVA +132kv NA NA Subproject /33kv FB(2) Completed 30 400/220kv 1x315 MVA NA NA Subproject additional Completed transformer at Bhopal 400kv S/S 31 Additional +160 MVA NA NA Subproject Transformer at Completed Mandideep 220 (2nd) 32 Narsinghgarh 40MVA +132kv June 2018 People wanted Explained that 132/33kv FB(1) to know if crop sub project will be damaged activity is entirely due to project on government activity. land. 33 Adampur 220/33kv 2x50MVA + June 2018 No major NA 220kv FB(2) concerns reported. 34 Bilkisganj (1X50) MVA; June 2018 People wanted Assured that no 132/33kV S/s 132kV FB(1) to know about land acquisition land acquisition would result for the project. because of the project activity. 35 Khujner/sindaota1 (1X50) MVA; June 2018 People wanted Explained that 32/33kV 132kV FB(1) to know if crop sub project will be damaged activity is entirely due to project on government activity. land. 36 Additional +160 MVA NA NA Subproject Transformer at Completed Betul 220 (2nd) 37 Silvani 132kv 40 MVA +132kv June 2018 People wanted Assured that no /33kv FB(1) to know if water such disruptions table will be would occur due disrupted due to to the project. project activity. 38 Udaipura 132/33kv 40MVA + 132kv June 2018 People wanted Explained that the FB(2) to know if project activity project activity aims at improved would result in power electricity supply transmission in improvement. the state. 39 Bisnoor/Masod (1X50) MVA; June 2018 People wanted Explained that 132/33kV 132kV FB(1) to know if crop sub project will be damaged activity is entirely due to project on government activity. land. 40 Chhayan 132/33kV 40MVA+132kV June 2018 People wanted Explained that the FB(1) to know if project activity

72

S. Subproject Capacity and Date Issues Outcomes of the No associated Discussed Public Feeder Bays Discussion project activity aims at improved would result in power electricity supply transmission in improvement. the state. 41 400kv Bus Reactor 1X125 MVAR NA NA Subproject at Nagda 400kv Completed S/S 42 Shyamgarh 40MVA+132kV June 2018 People wanted Explained that the 132/33kV FB(2) to know if project activity project activity aims at improved would result in power electricity supply transmission in improvement. the state. 43 Chinaur 132/33kV 40MVA+132kV NA NA Subproject FB(1) Completed 44 Bhander 132/33kV 63MVA+132kV NA NA Subproject FB(2) Completed 45 Pratappura 40MVA+132kV NA NA Subproject 132/33kV FB(1) Completed 46 Kelaras 132/33kV 63MVA+132kV NA NA Subproject FB(1) Completed 47 Gohad 132/33kV 63MVA+132kV NA NA Subproject FB(2) Completed 48 Kapasi/ Paranth (1X50) MVA; NA NA Subproject 132/33kv 132kV FB(1) Completed 49 Mada 132/33kV (1X50) MVA; NA NA Subproject S/s 132kV FB(1) Completed 50 Khimlasa 40MVA+132kV June 2018 People wanted Explained that 132/33kV FB(1) to know if crop sub project will be damaged activity is entirely due to project on government activity. land. 51 Mungaoli 63MVA+132kV NA NA Subproject 132/33kV FB(2) Completed 52 Kothiya 132/33kV 40MVA+132kV NA NA Subproject FB(1) Completed 53 Rehli 132/33kV S/s (1X50) MVA; June 2018 People wanted Assured that no 132kV FB(1) to know about land acquisition land acquisition would result for the project. because of the project activity. 54 Suwasra (2X160+1X50) NA NA Subproject 220/132kV S/s MVA 220kV Completed FB(4)+132kV FB(4) 55 Unhel 132/33kV (1X50) MVA; NA NA Subproject S/s 132kV FB(2) Completed 56 Budha 132/33kV (1X50) MVA; NA NA Subproject S/s 132kV FB(2) Completed

73

8.0 Institutional set-up for EMP Implementation

19. Currently, The Madhya Pradesh Power transmission Company (MP Transco serves as the executing agencies (EAs) and implementing agencies (IAs) for the project. MP Transco has established project management units (PMUs) to implement the ADB loans in Madhya Pradesh Power Sector Program. They function as PMUs of the proposed project. Field level staff/engineer is deputed at divisional level who assumes primary responsibility for the environmental and social assessment as well as implementation of RPs for their respective components. Overall implementation of the EMP is carried out under the supervision of the Head, MP Transco-PMU. The PMUs are also responsible for managing the site activities related to safeguards and work closely with the field level staff. MP Transco has also established Project Implementation Units (PIUs) for the project. The PIU is headed by the Project Head who is overall in charge of project implementation. The PIU also consists of officers deputed to look after various aspects such as design, procurement, environmental and social aspects of the project. A field level staff/engineer is also deputed who assumes primary responsibility for the environmental and social assessment as well as implementation of RPs for their respective components.

20. All contractors currently working in various subprojects have appointed designated officers for ensuring environmental and safety requirements. Details are given below in table 8.0.

Table 8.0: Environmental and Safety Officer Details for all Contractors

S No Contractor Environmental Officer Safety Officer 1 M/s BHEL Mr. Arun Pratap Moriya, Mr. Mr. Arun Pratap Moriya, Mr. Umesh Kumar, Mr. B.C. Umesh Kumar, Mr. B.C. Singh, Singh, Mr. Lakhan Singh Mr. Lakhan Singh Meena Meena 2 M/s Vikran Mr. Sanjeev Acharya Mr. Shailendra Umale 3 M/s Kalptaru Mr. Anil Kumar Singh, Mr. Mr. Anil Kumar Singh, Mr. Chandra Shekhar Shastri, Chandra Shekhar Shastri, Mr. Mr. Rajeev Ranjan, Mr. Rajeev Ranjan, Mr. Azazul Haq, Azazul Haq, Mr. Vikash Mr. Vikash Oram and Mr. Arun Oram and Mr. Arun Kumar Kumar Panda Panda 4 M/s Punj Lyod Mr. Mahesh Kumar Mr. Shyam Kumar Singh 5 M/s Bajaj Mr. Anirudh Mishra Mr. Anirudh Mishra 6 M/s L&T Mr. Priyadarshan Prasad Mr. Manoj Kumar

74

7 M/s BS LTD Contracts for BS Ltd have Contracts for BS Ltd have been been cancelled. The cancelled. The contract is contract is presently being presently being re-awarded. The re-awarded. The details will details will be captured and be captured and provided in provided in subsequent subsequent environmental environmental monitoring reports monitoring reports when the when the tenders are re- tenders are re-awarded. awarded.

21. M/s XIDAS (XIDAS or the Xavier Institute of Development Action and Studies (XIDAS), Jabalpur) has been appointed as an environmental consultant by MPPTCL for preparing the environmental monitoring report. For this purpose, XIDAS personnel have carried out field surveys for ground truthing and for collecting data. The EMR has been prepared by XIDAS for MPPTCL.

75

9.0 Follow-up actions and conclusions

25. In order to have sustainable development in the project, emphasis on the implementation of EMP has been given top most priority. Compliances to regulations as contained in ADB Loan Agreement are being met. MPPTCL is monitoring the implementation of environmental safeguards measures being undertaken by the contractor on regular basis. A grievance redressal committee has been constituted. Complaints, if any, received will be resolved at the earliest. The contractor will implement the decision taken by the committee. 26. Forest clearance is awaited for one subproject and construction activities will only begin once clearance is obtained. Some contracts were cancelled and had to be reawarded, hence, environmental testing is delayed. Testing of environmental parameters will be carried out and submitted during next monitoring period. 27. There are line alignment changes and minor changes in length in case of some subprojects and the reasons have been outlined in this EMR. The changes are not likely to cause any negative residual impacts. The IEE report of august, 2018 will be further updated in order to reflect the changes in length and alignment captured during this reporting period.

76

Annexure 1: Photographs of site visit and Consultation

LILO of Satna-Maihar 132kV line Sagar220-Rehli 132kv DCSS line

LILO of one circuit of Neemuch 220- Dhar 220-Teesgaon 132kV DCSS line Mandsaur 132kv line

77

Annexure 2: Public Consultation List

78

79

80

81

Annexure 3: Forest Cleranace Details- Second circuit of Gairatganj - Vidisha 220 132kv line

82

83

84

85

86

87

Forest Clearance Details: Birsinghpur 220-shahdol 132kV DCSS line

88

89

90

Forest Clearance Details: 220kV DCDS Khandwa (400 PGCIL) to Chhanera Line

91

92

Forest Clearance Details: Guna Bhonra and Bhonra Kapasi Line

93

94

Annexure 4: Grievance Committee Details

95

Annexure 5: MPPTCL’s LOU

96

Annexure 6: Labour License Details of M/S Kalpataru

97

98

99

100

Annexure 7: Labour Insurance Details of M/S Kalpataru

101

102

103

104

105

106

Annexure 8: Labour License Details of M/S Punj Llyod

107

Annexure 9: Labour Insurance Details of M/S Punj Llyod

108

109

Annexure 10: Labour License Details of M/SBajaj

110

111

112

113

114

115

116

117

118

119

120

Annexure 11: Labour Insurance Details of M/SBajaj

121

122

Annexure 12: Labour License Details of M/S Larsen & Toubro

123

124

125

Annexure 13: Labour Insurance Details of M/S Larsen & Toubro

126

127