Monmouth County Mitigation Action Worksheets

Community Action Number: 31_03 Marlboro, Township of Describing the Action Action Name: Purchase and Install Generator at Tennent Rd. Water Treatment Plant and Pump Station Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Installation of a generator at the Tennent Road Water Treatment Plant and Pump Station.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 3, 7 Risk Reduction: Maintaining the operation of critical infrastructure during storm events is critical; however, some systems lack backup sources of power that would ensure their operability during a power outage (i.e., Tennent Road Water Treatment Plant and Pump Station). Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Administrative Capability: Project will need to be professionally designed and installed by a contractor. Local Champion: Public Works

Other Community Objectives: Will support overall capital improvement plan and maintain quality of life for the stakeholders. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $500,000.00 Priority: Medium Local Planning Mechanism: Capital Improvement Plan Responsible Party: Engineering Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; the Township still prioritizes this action and is researching funding opportunities. Monmouth County Mitigation Action Worksheets

Community Action Number: 31_04 Marlboro, Township of Describing the Action Action Name: Purchase and Install Generator at the Harbor Rd. Water Treatment Plant Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Installation of a stand-by generator for Water Utility wells 3 and 4 at the Harbor Road Water Treatment Plant.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 3, 7 Risk Reduction: Maintaining the operation of critical infrastructure during storm events is critical; however, some systems lack backup sources of power that would ensure their operability during a power outage (i.e., Water Utility wells 3 and 4 at Harbor Road Water Treatment Plant. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Administrative Capability: Project will need to be professionally designed and installed by a contractor. Local Champion: Public Works

Other Community Objectives: Will support overall capital improvement plan and maintain quality of life for the stakeholders. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $300,000.00 Priority: Local Planning Mechanism: Capital Improvement Plan Responsible Party: Engineering Likely Funding Source(s): Capital Funds; Grants; Loans Timeline: Action Status: Completed Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 31_05 Marlboro, Township of Describing the Action Action Name: Purchase and Install Generator at Recreation Center Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Installation of a generator at the Recreation Center which serves as a shelter.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 3, 7 Risk Reduction: Maintaining the operation of critical infrastructure during storm events is critical; however, some systems lack backup sources of power that would ensure their operability during a power outage. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Administrative Capability: Project will need to be professionally designed and installed by a contractor. Local Champion: Administration

Other Community Objectives: Will support overall capital improvement plan and maintain quality of life for the stakeholders. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $300,000.00 Priority: Local Planning Mechanism: Capital Improvement Plan Responsible Party: Engineering Likely Funding Source(s): Capital Funds; Grants; Loans Timeline: Action Status: Completed Notes: The Community Center/Warming and Comfort/Shelter received a $250,000 grant for a generator (HMGP) Monmouth County Mitigation Action Worksheets

Community Action Number: 31_06 Marlboro, Township of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Work with property owners on grants available to mitigate Repetitive Loss properties. There are seven RL properties that still need mitigation. Evaluating the Action Hazard(s) Addressed: Flood, Wave Action, Nor'easter, Hurricane and Tropical Storm, Storm Surge, Winter Storm Goals: 1, 2, 3, 5, 6 Risk Reduction: Several residential structures throughout the community are prone to flooding, with their main floor elevations below current BFEs. Sea level rise and will contribute to more frequent and severe flooding and surge events. Technical: Elevation and acquisition are both technically feasible project types. Political: Our political leadership supports this type of project. Legal: While the municipality does not own the structures in question, we fully support the homeowners in moving forward. Environmental: No environmental impacts are anticipated at this time; this would be confirmed as specific homeowners come forward and their property details are reviewed. It is likely that environmental impacts would be positive, as household hazardous wastes are no longer introduced into floodwaters. Social: No particular social group in our community is likely to be disproportionately impacted by this project; this would be re-evaluated as particular interested homeowners come forward. Administrative Capability: Our municipality has the administrative capabilities to manage an elevation, acquisition project. Local Champion: Affected homeowners, elected officials.

Other Community Objectives: Improve and protect lifestyles of residents; reduction of costly property damage; resiliency; floodplain management; capital improvements. STAPLEE Evaluation: 11

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Homeowners; Mayor; Council; Administrator; Engineer; local ordinance; Hazard Mitigation Plan Responsible Party: Construction Official Likely Funding Source(s): FEMA HMA Timeline: 5 + years Action Status: Ongoing Notes: Ongoing action; the Township deems this action necessary and is searching for potential funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 31_07 Marlboro, Township of Describing the Action Action Name: Desnag and Clean Stream Corridors within the Township Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Desnagging and cleaning four streams the Township.

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm Goals: 6 Risk Reduction: The Township streams are causing localized flooding. Removal of debris will improve the natural infiltration of stormwater and prevent flooding. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: Coordination with NJDEP and the County will be required. Environmental: Positive environmental benefits from stream stabilization. Social: No adverse environmental effects. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: New Notes: The Township was awarded HMGP funding of $420,236 for stream bank stabilization to protect Pleasant Valley Road. Monmouth County Mitigation Action Worksheets

Community Action Number: 31_08 Marlboro, Township of Describing the Action Action Name: Construct Flood Measure (e.g. floodwalls or small berms) along Deep Run Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Use minor structural projects that are smaller and more localized (e.g., floodwalls or small berms) along Deep Run.

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm Goals: 2, 3 Risk Reduction: Deep Run transects the Township (severe residential properties) and is a Regulatory Floodway. Technical: Technically feasible. Political: No adverse political implications. Legal: No legal impediments. Environmental: Minor affects to the envioronment. Social: Does not adversely affect any particular social group. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: 9

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Engineering Likely Funding Source(s): FEMA HMA Timeline: 3 years Action Status: New Notes: CAPABILITY ASSESSMENT WORKSHEET

Name: Bruce Hall Title: Chief of Police/OEM Coordinator

Jurisdiction: Marlboro Township Organization:

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? Yes Comprehensive/Master Plan

Yes Capital Improvements Plan

No Economic Development Plan

Yes Revised 7-21-19 All Hazards Plan. Projects included in mitigation Local Emergency Operations Plan plan. Can be used in mitigation actions.

Continuity of Operations Plan

Yes Post-Disaster Recovery Plan

no Transportation Plan

Yes 2008 Stormwater Pollution Plan with annual updates Stormwater Management Plan

No Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other special plans (e.g., brownfields redevelopment, disaster recovery, coastal zone management, climate change adaptation) Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code yes 2018 IBC and 2018 IRC

Building Code Effectiveness Score: No Grading Schedule (BCEGS) Score

Rating: ISO 4/4B Fire Department ISO rating yes

Site Plan Review Requirements Yes Reviews are extensive

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning Ordinance Yes on effective measures and yes on enforcement. Yes Yes on effective measures and yes on enforcement. Subdivision Ordinance

Floodplain Ordinance no

Natural hazard ordinance (stormwater, steep slope, yes wildfire)

Flood Insurance Rate Maps no

Acquisition of Land for Open yes Permanent Open Space tax. Space and Public Recreation Uses

Post-Disaster Recovery Yes Ordinance

Real Estate Disclose Ordinance Yes

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other (ie. Special Purposes Yes Special Purposes Ordinance and Growth Management Ordinance Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective? Yes Planning Commission

Yes Local Hazard Committee Mitigation Planning Committee

Maintenance Programs to Brush and leaf collection in place; temporary management plan in Reduce Risk (e.g., tree trimming, Yes place. clearing drainage systems) JCP&L partnered with the Township on trees that create hazards

Emergency Management and Law Enforcement executed at the Mutual Aid Agreements yes County level and approved by Municipal Council

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective? Yes F/T Full time staff. Adequate for normal operations. Staff is trained on Chief Building Official Hazard and mitigation strategies. Coordination is effective..

Yes Floodplain Administrator

Emergency Manager Yes P/T staff.

Community Planner Yes

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Civil Engineer Yes

Surveyor Yes

GIS Coordinator Yes

Scientists familiar with the No hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past? Reverse 911 Warning Systems/Services (Reverse 911, outdoor warning signals)

Twitter, email, semi-annual e-mail blasts on hazards Hazard Data and Information

Grant Writing Yes

Hazus Analysis Yes

Other

How can the above capabilities be expanded and improved to reduce risk? The past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

Yes Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or yes Water service only. Electric Services

Impact Fees for New Tree Trust Fund on development applications to mitigate falling Yes Development trees.

Stormwater Utility Fee yes Stormwater impact fee.

Incur Debt Through Private Yes Activities

Community Development Block Yes Grant

Other Federal Funding Programs Yes

State Funding Programs

Yes Withhold spending in hazard-prone areas, Incur Debt through Other (e.g., withhold spending in General Obligation Funds and Incur Debt through Special Tax and hazard-prone areas) Revenue Bonds How can these capabilities be expanded and improved to reduce risk?

5 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection,

Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or Information Programs (e.g., responsible water use, fire safety, household preparedness, environmental education)

Natural Disaster or Safety

Related School Programs

StormReady Certification

Firewise Communities

Certification

Public-Private Partnership Initiatives Addressing Disaster Related Issues

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Monmouth County Parcel Classification 0 2,250 4,500 MARLBORO TOWNSHIP Feet Marlboro Industrial Commercial Apartment Residential (four families or less) ± FLOOD VULNERABILITY Township Source: © 2014 Esri; Monmouth County; MONMOUTH COUNTY HAZARD MITIGATION PLAN Farm Vacant Civic/Public (Tax Exempt) Unclassified Open Space NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

Matawan Borough Middletown Aberdeen Township

Holmdel Township

Middlesex Middletown County Township

#18 " #"34 #"9 #"79 LK3 LK520

Wesley Lake FEMA FLOOD HAZARD AREAS 1% Annual Chance Flood (SFHA) Regulatory Floodway Manalapan Zone A, AE, AO, AH Township Zone VE Colts 46 0.2% Annual Chance Flood LK Neck Englishtown Township Zone X Borough Undetermined Zone D A t l a n t i c Evacuation Route Flood Hazard Areas are a composite of EffectiveO cFIRMs e a(06/20/2018) n and Preliminary FIRMs (01/30/2015)

Freehold Township

This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. Monmouth County ParcelClassific ation 0 2,250 4,500 MARLBORO TOWNSHIP Feet Marlboro Ind ustrial Com m ercial Apartment Resid ential(fourfamilies or less) ± FLOOD VULNERABILITY Township Source: © 2014 Esri; Monmouth County; MONMOUTHCOUNTY HAZARD MITIGATION PLAN Farm Vacant Civic /PublicExempt)(Tax Unc lassified OpenSpace NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

Matawan Borough Middletown Aberdeen Township

Holmdel Township

Mid d lesex Middletown County Township

#18 " #"34 #"9 #"79 LK3 LK520

Wesley Lake POTENTIAL SEA LEVEL RISE INUNDATION AREAS 1 Foot1 SeaLevelRise (2050) Manalapan Township Foot3 SeaLevelRise (2100) EvacuationRoute Colts LK46 SpatialResolution and Acc uracy:Th ismap depic inland ts extent Neck andrelativedepth inundof SLR ofusing and 3ft. NOAA ation for1ft. Englishtown Township SLRwithdatavertic a datum al Meanof Hig hHig er hWater (MHHW). T h ese inund ation rang es are consistent w ith the Rutgers Borough University’sNew Jersey Clim Adaptation ate Allianc Scienc e and e T ech nicAdvisory al Panel Report (STAP Report).Th STAP e Report estimNew ates Jerseywill experienc SLR e betweenandfeet 1.0 1.8 priorregardless2050, to futureofgreenh ousegasemissions. Th e d ata displayedd ata on mapthis represents current cond itionsand does A t l a n t i c notconsid ernatural proc suc esses erosion has or marsh mig ration that will futurethat bylevel seaaffectedDue berise. coarseto spatial resolution,the user should not interpret the layers as precise O c e a n inund ationextents.

Freehold Township

T hmap is was developed using statew id10-04-18the com e positeparcelof publisheddata NJOIT-OGIS.theby NewThof JerseyState makes e providto great effort secure, e acc and urate, com pletedataand metadata.How portions ever, anddatathe of metadata mayinc be orrector notcurrent. Any errors or om issionsshould reportedbe forinvestig ationOGIS.to

MEETING NOTES

Topic: Marlboro- Monmouth County HMP Meeting

Date: June 6, 2019

Time: 10:00 AM- 11:00 AM

Location: 1979 Township Dr, Marlboro Township, NJ 07746

Attendees: Johnahan Capp, Administrator

Bruce Hall, Police Chief/OEM Coordinator

Kevin Kane, Director of Community Development

Robert Miller, Superintendent of Public Works

Laura Neumann, Engineer

Peter Pezzullo, OEM Coordinator

Brittany Ashman, MB Planner

Paige Kaspar, MB Planner

Drafted by: Paige Kaspar ______

Introductions

• What is Hazard Mitigation • Funding SRL & RL Properties

• What happens if a RL property has been declared a substantially damaged property • Don’t have a good underlining soil condition and homes were built near streams Critical Facilities

• Will follow up and add water facility as a critical facility

2015 Mitigation Actions:

• Mitigation action 1 and 2: ongoing capability, oem coordination meetings, reverse 911, don’t park on the streets during snow storms, email blasts,  capability assessment • Mitigation 3: Pending/ ongoing. Generator for both buildings • Mitigation 4: Completed • Mitigation 5: Completed • Mitigation 6: Ongoing • Pleasant Valley Project: 2020 Mitigation Actions (NEW):

• Stream bank stabilization project: o Snagging of streams for 4 streams o Why are there ongoing mitigation actions missing that were originally from the 2008 plan but never transferred over to 2015 that we want to be on this 2020 plan o Taylor rd 1 & 2 • Potential for 10-15 acre property wildfire. No ordinance in plan. More of public awareness Successes:

• Got funding for Rec center generator Capability Assessment

• Reverse 911 • Email blast • OEM Coordination Meetings • Capital Improvement Plan • Local Power company trim around transmissions. When they do their forestry review that they tell Marlboro about issues. Tree trust fund that is available for planting and trimming trees.  power outages are a major issue… effects water plants. • Stormwater Management Plan  2008 • Pollution Prevention Plan • Master Plan • Debris Management Sites (3) • Temporary Debris Management Program

Appendix Vol I.32 Matawan Borough

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Matawan Borough CRS Class 0

NFIP Statistics 7%

16 Polices In-force

23 Total Losses

$182,548 Total Payments 999 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 999 RL Properties

0 RL - Total Losses 9 Total Mitigation $0 RL - Total Paid Actions

0 Number of SRL Properties 0

Number Mitigated SRL 0 Properties Education and Awareness Programs

0 SRL - Total Losses 7

$0 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 0

15 Critical Facilities Local Plans and Regulations

1 Critical Infrastructure 2

66 Historic & Cultural Resources Natural Systems Protection

0 SV Population At Risk (2017) 652 Population at Risk (2017) Matawan, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

32_01 Replace Lake Lefferts Dam Replace existing Lake Lefferts dam to include realigning of Structure and Dam Failure, Flood, Borough and County State, County and $8,000,000.00 Completed Ravine Dr. to comply with current DOT standards. Infrastructure Coastal Erosion, Engineers Federal Grants, Project Nor'easter, Hurricane and Bonded funds Tropical Storm

32_02 Replace Lake Matawan Dam Coordinate with NJDEP to replace existing Lake Matawan Mitigation - Risk Structure and Dam Failure, Flood, High Borough and County Lake Matawan Dam is $8,000,000.00 5 + years Ongoing dam to include replacement of the Main Street Lake Reduction Infrastructure Nor'easter, Hurricane and Engineers eligible for FEMA's Matawan/Matawan Creek Bridge and adjoining roadway. Project Tropical Storm High-Hazard Potential Dam Grant Program.

32_03 Elevate Aberdeen Road Elevate Aberdeen Road above the Matawan Creek and Mitigation - Structure and Flood, Nor'easter, High Matawan Borough & FEMA HMA, DOT $7,100,000.00 1 year Ongoing BFE. Continuity of Infrastructure Hurricane and Tropical Monmouth County Functional Use Project Storm, Storm Surge Engineers in conjunction with

32_04 Provide Auxiliary Power to the Provide auxiliary power to the Matawan Municipal Structure and Extreme Temperatures, Borough Engineer, Bonded funding, $150,000.00 Completed Matawan Municipal Community Center-Borough Hall (201 Broad Street), to Infrastructure Flood, Extreme Wind, Office of Emergency State, County, federal Community Center/Borough allow for continuity of government operations and public Project Lightening, Nor'easter, Management grant Hall access to the Municipal Complex during a sustained loss Hurricane and Tropical of power. Having auxiliary power would also facilitate the Storm, Storm Surge use of the complex as a temporary shelter or warming/charging station during a declared state of emergency.

32_05 Purchase a Jet Vac Ravine Clean outfall pipes and ravines that are clogged (need list Maintenance/Resp Natural Systems Flood, Nor'easter, High Borough DPW Municipal budget $1,000,000.00 1 year New Cleaning and Clean Outfall from engineer on which outfalls and revaines need onse/Recovery Protection Hurricane and Tropical Pipes cleaning). Additionally, purchase a jet vac (est. $700,000) Storm for DPW to clean the pipes and ravines from debris.

32_06 Upgrade Generators at Critical Upgrade generators at Police HQ, Somerset Place Sewer Maintenance/Resp Structure and All Hazards Low Borough FEMA HMA $150,000.00 1 year New Facilities Life Station, Victoria Court Sewer Pump Station, and DPW onse/Recovery Infrastructure Administration building. Project

32_07 Target Harden Critical The Water Treatment Plan needs more security in the Maintenance/Resp Structure and Terrorism Medium Borough Homeland Security 1 year New Facilities by Installing form of an upgraded camera system and concrete onse/Recovery Infrastructure Administration, DPW grants Surveillance Cameras, an barriers. Borough Hall could be more secure with Project Access Control System, and/or bulletproof glass, an access card system, and an Bulletproof Glass enhanced camera system.

32_08 Develop a Tree Trimming Create a shared service agreement for tree trimming Maintenance/Resp Natural Systems Flood, Nor'easter, Medium DPW Municipal budget 2 years New Program program with the county or a consultant. onse/Recovery Protection Hurricane and Tropical Storm, Winter Storm

Wednesday, March 4, 2020 Page 1 Matawan, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 32_09 Acquire, elevate, or relocate There are currently no RL or SRL properties in the Mitigation - Risk Structure and Flood, Nor'easter, High Borough and FEMA HMA 5 + years New buildings and infrastructure in Borough; however, the Borough realizes the floodplain Reduction Infrastructure Hurricane and Tropical Property Owners flood prone areas, with a changes over time and the risk is always present. If in the Project Storm focus on Repetitive Loss (RL) next five years properties become RL/SRL, the Borough and Severe Repetitive Loss will coordinate with residents to mitigate properties (SRL) properties through structure elevation, demolition to open space, or another type of mitigation.

Wednesday, March 4, 2020 Page 2 Monmouth County Mitigation Action Worksheets

Community Action Number: 32_01 Matawan, Borough of Describing the Action Action Name: Replace Lake Lefferts Dam Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Replace existing Lake Lefferts dam to include realigning of Ravine Dr. to comply with current DOT standards.

Evaluating the Action Hazard(s) Addressed: Dam Failure, Flood, Coastal Erosion, Nor'easter, Hurricane and Tropical Storm Goals: 1, 2, 3, 5, 7 Risk Reduction: The Lake Lefferts Dam is a high hazard dams noted by the municipality as in need of replacement. There is potential for extensive damage downstream from Lake Lefferts to include the NJ Transit North Jersey Coast Railroad bridge over Matawan Creek. Slope failure and erosion to numerous lakefront homes. Environmental and wildlife issues associated with the draining of the lake. Flooding occurs due to severe storms such as nor'easters and/or hurricanes. Climate change will contribute to more frequent and severe weather events. Technical: This mitigation action is technically feasible. Any threat of dam failure and the associated losses will be solved. Political: This project is being strongly advised by the Department of Environmental Protection. Some political issues may arise over ownership and responsibility of funding between the Borough of Matawan and the County of Monmouth. Legal: No apparent legal issues. Environmental: Project would require permitting by the DEP. Social: Project does not negatively impact any particular group as currently proposed. Project could negatively impact motorist if the roadway is impassable for any considerable duration. Administrative Capability: Borough Administrator, Borough and County Engineers would be responsible for administration of project. Local Champion: NJ DEP, Monmouth County Department of Public Works & Engineering, Matawan Borough Council

Other Community Objectives: Project would support the adjacent Lake Lefferts recreation facility (Green Acres park and recreation area). STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $8,000,000.00 Priority: Local Planning Mechanism: Borough & County Engineering, Planning and Bond Ordinances Responsible Party: Borough and County Engineers Likely Funding Source(s): State, County and Federal Grants, Bonded funds Timeline: Action Status: Completed Notes: This is a high hazard dam. Monmouth County Mitigation Action Worksheets

Community Action Number: 32_02 Matawan, Borough of Describing the Action Action Name: Replace Lake Matawan Dam Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Coordinate with NJDEP to replace existing Lake Matawan dam to include replacement of the Main Street Lake Matawan/Matawan Creek Bridge and adjoining roadway. Evaluating the Action Hazard(s) Addressed: Dam Failure, Flood, Nor'easter, Hurricane and Tropical Storm Goals: 1, 2, 3, 5, 7 Risk Reduction: The Lake Matawan Dom is a high hazard dams noted by the municipality as in need of replacement. Potential for extensive damage to the surrounding properties of Lake Matawan to include Main Street (County Route 516). Slope failure and erosion to numerous lakefront homes. Environmental and wildlife issues associated with the draining of the Jake. Flooding occurs due to severe storms such as nor'easters and/or hurricanes. Climate change will contribute to more frequent and severe weather events. Technical: This mitigation action is technically feasible. Any threat of dam failure and the associated losses will be solved. Political: This project is being strongly advised by the Department of Environmental Protection. Some political issues may arise over ownership and responsibility of funding between the Borough of Matawan and the County of Monmouth. Legal: No apparent legal issues. Environmental: Project would require permitting by the DEP. Social: Project does not negatively impact any particular group as currently proposed. Project could negatively impact motorist if the roadway is impassable for any considerable duration. Main Street is a direct thoroughfare to the Aberdeen-Matawan Train Station an NJ Transit's North Jersey Coast RR line. Administrative Capability: Borough Administrator, Borough and County Engineers would be responsible for administration of project. Local Champion: NJ DEP, Monmouth County Department of Public Works & Engineering, Matawan Borough Council

Other Community Objectives: Project would support the near-by Aberdeen-Matawan Train Station (and the proposed redevelopment of the area) and the Main Street Business District. STAPLEE Evaluation: 9

Implementing the Action Cost Estimate: $8,000,000.00 Priority: High Local Planning Mechanism: Borough & County Engineering, Planning and Bond Ordinances Responsible Party: Borough and County Engineers Likely Funding Source(s): Lake Matawan Dam is eligible for FEMA's High-Hazard Potential Dam Grant Program. Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; this is a high hazard dam. Monmouth County Mitigation Action Worksheets

Community Action Number: 32_03 Matawan, Borough of Describing the Action Action Name: Elevate Aberdeen Road Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevate Aberdeen Road above the Matawan Creek and BFE.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 7 Risk Reduction: Aberdeen Road (downstream from Lake Lefferts) is subject to recurrent flooding. Aberdeen Road becomes impassable due to tidal flooding at virtually every high tide creating a delay in emergency response for both Matawan and Aberdeen Emergency Services. Technical: Technically feasible. Flooding of roadway salved for the long term; Community's problem of interrupted transportation and emergency response solved. Adequate detour route for Ravine Dr. during Lake Lefferts dam project. Political: No apparent political issues. Legal: Project would need County approval/contribution is Matawan Creek Bridge on Aberdeen Rd. is county owned and maintained. No other foreseen legal issues. Environmental: Due to the proximity to Matawan Creek. DEP permits would be needed. No other environmental issues are foreseen. Social: The proposed project will provide uninterrupted transportation at high tides for those residing in the northwestern portion of the Borough and those travelling to neighboring Aberdeen and Old Bridge Townships to access State Highway 35 and the Garden State Parkway. Administrative Capability: Administrative function will be handled by the Borough Administrator and Engineer Local Champion: Borough Department of Public Works, Emergency Services, OEM

Other Community Objectives: This project would further the Borough's proposed NJ Transit Village Redevelopment Plan as Aberdeen Rd./High St. intersect with Main Street in the proposed redevelopment zone. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $7,100,000.00 Priority: High Local Planning Mechanism: State DOT, Local Ordinances governing traffic and roadway construction. Responsible Party: Matawan Borough & Monmouth County Engineers in conjunction with DPW and OEM Likely Funding Source(s): FEMA HMA, DOT Timeline: 1 year Action Status: Ongoing Notes: Cost share agreement signed with County & Borough; in planning stages. Monmouth County Mitigation Action Worksheets

Community Action Number: 32_04 Matawan, Borough of Describing the Action Action Name: Provide Auxiliary Power to the Matawan Municipal Community Center/Borough Hall Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Provide auxiliary power to the Matawan Municipal Community Center-Borough Hall (201 Broad Street), to allow for continuity of government operations and public access to the Municipal Complex during a sustained loss of power. Having auxiliary power would also facilitate the use of the complex as a temporary shelter or warming/charging station during a declared state of emergency. Evaluating the Action Hazard(s) Addressed: Extreme Temperatures, Flood, Extreme Wind, Lightening, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 3, 7 Risk Reduction: A need has been identified for auxiliary power to the Matawan Municipal Community Center/Borough Hall Complex as a result of Superstorm Sandy. Loss of power, continuity of government, community access to government and municipal complex during power loss. Technical: Technically feasible. Power loss at the Matawan Municipal Community Center (Borough Hall} would be solved upon completion of this project. Political: This project is supported by the Matawan Borough Mayor and Council and both the Monmouth County and Matawan Offices of Emergency Management. Legal: No apparent legal issues. Environmental: No apparent environmental issues. Social: Project would not negatively impact any particular social group but would positively impact all residents of the Borough. Administrative Capability: The Borough Administrator, Borough Engineer and OEM Coordinator would administer this project collectively. Local Champion: Monmouth County and Matawan Offices of Emergency Management

Other Community Objectives: Provide a higher level of uninterrupted government services to the residents of Matawan during a large scale, long term power outage. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $150,000.00 Priority: Local Planning Mechanism: Ordinances and Codes governing electrical improvements Responsible Party: Borough Engineer, Office of Emergency Management Likely Funding Source(s): Bonded funding, State, County, federal grant Timeline: Action Status: Completed Notes: HMGP grant of $75,000 post-Sandy for Generator for Municipal Building/Warming Center/Shelter. Monmouth County Mitigation Action Worksheets

Community Action Number: 32_05 Matawan, Borough of Describing the Action Action Name: Purchase a Jet Vac Ravine Cleaning and Clean Outfall Pipes Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Clean outfall pipes and ravines that are clogged (need list from engineer on which outfalls and revaines need cleaning). Additionally, purchase a jet vac (est. $700,000) for DPW to clean the pipes and ravines from debris. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 2, 3, 5, 6 Risk Reduction: When the outfall pipes and ravines are clogged with debris, this leads to localized flooding problems. The Matawan Ave pipe clos even when clear there is nowhere for water to flow from tidal events Technical: Political: No political obstacles anticipated. Legal: May need DOT permitting if within right-of-way and will need to coordinate with County on Matawan Ave, since it is a county bridge. Environmental: No adverse environmental effects anticipated. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial as clean outfalls and ravines will help to reduce the impact of flooding on residents. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: DPW, OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,000,000.00 Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough DPW Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 32_06 Matawan, Borough of Describing the Action Action Name: Upgrade Generators at Critical Facilities Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Upgrade generators at Police HQ, Somerset Place Sewer Life Station, Victoria Court Sewer Pump Station, and DPW building. Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 2, 3, 7 Risk Reduction: Critical facilities in Matawan can lose power during storm events. Technical: Technically feasible. Political: No adverse political ramifications are expected Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because the generators will help keep critical local services operational during emergencies. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Public Works

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $150,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 32_07 Matawan, Borough of Describing the Action Action Name: Target Harden Critical Facilities by Installing Surveillance Cameras, an Access Control System, and/or Bulletproof Glass Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other Action Description: The Water Treatment Plan needs more security in the form of an upgraded camera system and concrete barriers. Borough Hall could be more secure with bulletproof glass, an access card system, and an enhanced camera system. Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1, 2, 3, 7 Risk Reduction: These critical facilities are vulnerable to a terrorist attack or smaller crimes, such as vandalism. These areas need to be monitored and more secure. Technical: Technically feasible. Political: Politically acceptable and encouraged. Legal: No legal issues anticipated. Environmental: Does not adversely affect the environment. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it reduces risk for residents. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: Police, OEM, Administrator

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration, DPW Likely Funding Source(s): Homeland Security grants Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 32_08 Matawan, Borough of Describing the Action Action Name: Develop a Tree Trimming Program Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Create a shared service agreement for tree trimming program with the county or a consultant.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Winter Storm Goals: 1, 2, 3, 5, 6 Risk Reduction: Aberdeen Ave has very low along the right-of-way and are in danger of falling on pedestrians or automobiles. Technical: Technically feasible. Political: Politically acceptable and encouraged. Legal: No legal issues anticipated. Environmental: Does not adversely affect the environment. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it reduces risk for residents. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: DPW Likely Funding Source(s): Municipal budget Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 32_09 Matawan, Borough of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: There are currently no RL or SRL properties in the Borough; however, the Borough realizes the floodplain changes over time and the risk is always present. If in the next five years properties become RL/SRL, the Borough will coordinate with residents to mitigate properties through structure elevation, demolition to open space, or another type of mitigation. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 1, 2, 3, 6 Risk Reduction: Risk of future destruction and property loss in repetitive flooded areas. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: If structures are elevated, they must be built in compliance with the FEMA flood maps. Environmental: Positively impacts the environment by increasing the permeable surface for each homeowner property. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because of repetitive nature of flooding in the project area. Administrative Capability: There is sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: 10

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough and Property Owners Likely Funding Source(s): FEMA HMA Timeline: 5 + years Action Status: New Notes: CAPABILITY ASSESSMENT WORKSHEET

Name: Thomas J. Falco Jr. Title: Chief of Police

Jurisdiction: Matawan Borough Organization:

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? Yes 1. 2015 Comprehensive/Master Plan

Yes Capital Improvements Plan

Yes Economic Development Plan

Yes Local Emergency Operations Plan

Continuity of Operations Plan

No Post-Disaster Recovery Plan

No Transportation Plan

Yes 1. 2018 Stormwater Management Plan

No Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other special plans (e.g., brownfields redevelopment, disaster recovery, coastal zone management, climate change adaptation) Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code No

Building Code Effectiveness Score: Grading Schedule (BCEGS) Score

Rating: Fire Department ISO rating

Site Plan Review Requirements Yes

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning Ordinance

Yes Subdivision Ordinance

Floodplain Ordinance Yes Flood Damage Prevention Ordinance

Natural hazard ordinance (stormwater, steep slope, Yes Stormwater Ordinance wildfire)

Flood Insurance Rate Maps

Acquisition of Land for Open Space and Public Recreation Uses

Post-Disaster Recovery No Ordinance

Real Estate Disclose Ordinance No

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other (ie. Special Purposes Yes Special Purposes Ordinance and Growth Management Ordinance Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective? Yes Planning Commission

Mitigation Planning Committee

Maintenance Programs to Reduce Risk (e.g., tree trimming, Yes clearing drainage systems)

Cost share agreement w/ county Mutual Aid Agreements Yes County to inspect catch basin  county helps clear

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective?

Chief Building Official

No Floodplain Administrator

Emergency Manager Yes

Community Planner Yes

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Civil Engineer Yes

Surveyor No

GIS Coordinator No

Scientists familiar with the No hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past? Yes Reverse 911/Nexel Warning Systems/Services (Reverse 911, outdoor warning signals)

Yes Public information officer to increase hazard data Hazard Data and Information

Grant Writing Yes TRIAD Assocciates

Hazus Analysis No

Other Message boards w/ community center, Police HQ

How can the above capabilities be expanded and improved to reduce risk? the past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

Yes Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or Yes Electric Services

Impact Fees for New Yes Development

Stormwater Utility Fee

Incur Debt Through Private Yes Activities

Community Development Block Yes Grant

Other Federal Funding Programs No

State Funding Programs

Yes Withhold spending in hazard-prone areas, Incur Debt through Other (e.g., withhold spending in General Obligation Funds and Incur Debt through Special Tax and hazard-prone areas) Revenue Bonds How can these capabilities be expanded and improved to reduce risk?

5 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection, No Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or The Matawan Borough Fire Department and Matawan Information Programs (e.g., Yes Fire Prevention Bureau educates the community responsible water use, fire safety, throughout year on fire prevention programs and household preparedness, home safety. environmental education)

Natural Disaster or Safety

Related School Programs No

StormReady Certification No

The Matawan Fire Prvention Bureau and the Matawan Firewise Communities Yes Borough Fire Department Educates children and the Certification community during the NFPA Fire Prevention week every October. Public-Private Partnership Initiatives Addressing Disaster Related Issues No

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Matawan Borough

Monmouth County Parcel Classification 0 800 1,600 MATAWAN BOROUGH Feet Industrial Commercial Apartment Residential (four families or less) ± FLOOD VULNERABILITY Source: © 2014 Esri; Monmouth County; Farm Vacant Civic/Public (Tax Exempt) Unclassified Open Space MONMOUTH COUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

Keyport Borough

#"36

#"35

Aberdeen-Matawan Hazlet LK6A Township

Hazlet

s #"34 rt ffe Middlesex Le ke County La

516 LK Aberdeen Township Wesley Lake

FEMA FLOOD HAZARD AREAS 1% Annual Chance Flood (SFHA) Aberdeen Holmdel Township Regulatory Floodway #79 " Zone A, AE, AO, AH Township Zone VE

0.2% Annual Chance Flood Zone X Undetermined A t l a n t i c Zone D O c e a n Evacuation Route Flood Hazard Areas are a composite of Effective FIRMs (06/20/2018) and Marlboro Preliminary FIRMs (01/30/2015) Township

This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. Matawan Borough

Monmouth County ParcelClassific ation 0 800 1,600 MATAWAN BOROUGH Feet Industrial Com m ercial Apartment Residential(four families or less) ± FLOOD VULNERABILITY Source: © 2014 Esri; Monmouth County; Farm Vacant Civ ic /PublicExempt) (Tax Unc lassified OpenSpace MONMOUTHCOUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

Keyport Borough

#"36

#"35

Aberdeen-Matawan Hazlet LK6A Township

Hazlet

s #"34 rt ffe Middlesex Le ke County La

516 LK Aberdeen Township Wesley Lake

POTENTIAL SEA LEVEL RISE Aberdeen INUNDATION AREAS Holmdel Township #"79 Foot1 SeaLevel Rise(2050) Township 3 Foot3 SeaLevel Rise(2100) EvacuationRoute

S patialResolution and Acc uracy:This map depic tsinland extent andrelativ depth e of inundation for and1ft.of3ft. SLR using NOAA S LRdatawith vertica datum al ofMean Hig hHig er hWater (MHHW). These inundation rang es are consistent with the Rutgers Univ ersity’sNew Jersey Clim ateAdaptation Allianc Sc e iencand e Tech nicAdvisory al Panel Report (STAP Report). The STAP Report A t l a n t i c estim atesNew Jerseywill experienc SLR e between feetand 1.8 1.0 priortoregardless 2050, of future greenh ousegasemissions. The datadisplayed on this map represents current conditions and does O c e a n notconsider natural proc such esses erosionas or marsh mig ration thatwill be affected byfuture levelsea Duerise. to coarse spatial resolution,the user should not interpret the layers as precise Marlboro inundationextents. Township

Thismap wasdeveloped using thestatewide 10-04-18 com positeof parcel datapublished bythe NJOIT-OGIS. The State of New Jerseymakes great effort to prov idesecure,acc urate,andcom pletedataand metadata. However, portions of th dataand e metadata may beinc orrector not current. Any errors or om issionsshould bereported for inv estig ationto OGIS.

MEETING NOTES

Topic: Matawan- Monmouth County HMP Meeting

Date: July 2, 2019

Time: 10:00 AM- 11:00 AM

Location: Borough Hall, 201 Broad Street, Matawan, NJ 07747

Attendees: John Applegate, DPW Director

Louis Ferrara, Administrator

Brittany Ashman, MB Planner

Drafted by: Paige Kaspar

______

Introductions (Brittany):

• What is Hazard Mitigation? • Matching actions with Goals • New Hazards • HMP Pamphlet • Funding Mitigation Actions:

• Community Action 32_01 – Replace Lake Lefferts Dam – Completed o High hazard dam o County looking to update trail • Community Action 32_02 – Replace Lake Matawan Dam – Ongoing o High hazard dam – State DEP • Community Action 32_03 – Roadway elevation above Matawan Creek – Completed o Municipal and County o Cost share agreement signed with County & Borough  Actions 1 to 3 have a combined cost of $14.2 million

• Community Action 32_04 – Provide auxiliary power to the Matawan Municipal Community Center- Borough Hall – Completed 2020 Mitigation Actions (NEW):

o #5 – Outfall pipes & ravine cleaning – engineer to send list . Matawan Ave pipe clogged  even when clear there is nowhere for water to flow from tidal events • Coordinate w. County as pipe is County owned

. Vac truck tank to clean catch basins, pump stations and remove debris • Cost estimate = $700,000 o #6 – Upgrade generators at Police HQ, Somerset Place sewer life station, and Victoria court sewer pump station, DPW o #7 – Water treatment plant security – cameras and possible concrete barriers . Upgrade & add camera, access cards, bullet proof glass at Borough Hall and Community Center o #8 – Tree trimming program shared service w/ county or consultant for Aberdeen Ave, trees very low

Capabilities: • Sanitary Lift Stations

Appendix Vol I.33 Middletown Township

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Middletown Township CRS Class 6

NFIP Statistics 11%

2,648 Polices In-force

1,693 Total Losses

$59,437,930 Total Payments 163 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 42 RL Properties

398 RL - Total Losses 13 Total Mitigation $13,996,103 RL - Total Paid Actions

5 Number of SRL Properties 1

Number Mitigated SRL 0 Properties Education and Awareness Programs

22 SRL - Total Losses 6

$712,270 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 5

106 Critical Facilities Local Plans and Regulations

1 Critical Infrastructure 1

59 Historic & Cultural Resources Natural Systems Protection

1 SV Population At Risk (2017) 7,459 Population at Risk (2017) Middletown, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

33_01 Acquire, elevate, or relocate Elevate 248 structures determined to be substantially Mitigation - Risk Structure and Flood, Wave Action, High State of New Jersey, FEMA HMA $13,500,000.00 5 + years Ongoing buildings and infrastructure in damaged and mitigate (elevate or acquire for open Reduction Infrastructure Nor'easter, Hurricane and Monmouth County, flood prone areas, with a space) RL and SRL properties. Project Tropical Storm, Storm Township of focus on Substantially Surge Middletown, HMA Damaged, Repetitive Loss (RL), and Severe Repetitive Loss (SRL) properties

33_02 De-snag and Desilt Streams Management of riparian buffers along rivers and streams, Maintenance/Resp Natural Systems Flood, Nor'easter, High Middletown Municipal budget, $3,294,900.00 5 + years Ongoing and Provide channel desnagging to preserve the function of natural onse/Recovery Protection Hurricane and Tropical Township (in EPA, National Maintenance drainage channels and floodplains, wetlands Storm, Wildfire conjunction with and Wildlife maintenance and removal of invasive plant species, Monmouth County Foundation (NFWF), desilting and of streams and ditches of the following: Waackaack Creek/L.F. 12,500; Pew's Creek/L.F. 10,500; Compton's Creek/L.F. 39,300; Ware Creek/L.F. 10,800; Wagner's Creek/L.F. 12,000; Claypit Creek/L.F. 14,400; McClees Creek L.F. 19,200. The total stream cleaning is 118,700 LF and assumed removal rate 0.75 cu.

33_03 Construct and Install an Construct and install an additional automatic tide- Mitigation - Risk Structure and Flood, Nor'easter, Mayor and Township FEMA HMA $170,000.00 Completed Automatic Slide Gate at activated electrically-actuated slide gate device at Wilson Reduction Infrastructure Hurricane and Tropical Committee Wilson Avenue at Pews Creek Avenue at Pews Creek. Project Storm, Storm Surge

33_04 Purchase Temporary/Portable Installing temporary/portable pumps in certain areas will Maintenance/Resp Structure and Flood, Nor'easter, High Middletown Municipal budget $110,000.00 5 + years Ongoing Pumps to Remove Stormwater allow stormwater from major nuisance flooding events in onse/Recovery Infrastructure Hurricane and Tropical Township Leonardo and Belford sections. The goal is to pump Project Storm stormwater from the system, discharging into Pew's Creek. Once the water level in the system reaches a certain elevation below existing street elevations, pumps would be activated, and system water would be discharged into the creek. Slide gates would be closed during the pumping to prevent stormwater from re- entering the drainage systems.

33_05 Purchase and Install Generators for three fire houses (River Plaza, Port Structure and All Hazards HMPG Energy $800,000.00 Completed Generators for Critical Monmouth, Belford), transfer station (Fire House, Tanya Infrastructure Allocation - no Keller, Crossroads), community Center for shelter, pump Project match required. station (N. Middletown storm sewer - new generator & new pumps), and five communication towers need generators and have backup batteries.

33_06 Provide for Continuity of Elevate generators and switches at all fire stations Mitigation - Structure and Flood, Wave Action, Low Each Fire Company, FEMA HMA $300,000.00 1 year Ongoing Operations by Elevating located in the flood hazard area. Continuity of Infrastructure Nor'easter, Hurricane and Township Generators and Switches at Functional Use Project Tropical Storm, Storm Fire Stations Surge

Wednesday, March 4, 2020 Page 1 Middletown, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 33_07 Develop a Microgrid In August 2017, Middletown Township was awarded a Administrative Local Plans and All Hazards Low Township Municipal budget 2 years New Feasibility Study (2017) $150,000 grant from the New Jersey Board of Public Regulations Utilities to hire experts to conduct an initial study to determine a cost-effective configuration that will allow the Township to use local resources to power critical facilities, especially during times of emergency.

33_08 Enhance Security at Township Increase surveillance systems in Township critical Maintenance/Resp Structure and Terrorism Low Middletown Homeland Security 2 years New Facilities facilities. onse/Recovery Infrastructure Township grants, Municipal Project budget

33_09 Increase the Number of More drones and drone training for police officers. Two Maintenance/Resp Education and All Hazards Medium Township Police Homeland Security 1 year New Drones and Provide Drone officers have completed the training already. onse/Recovery Awareness grants, Municipal Training Programs budget

33_10 Conduct Compton Creek The proposed project is primarily north of Broadway Mitigation - Natural Systems Nor'easter, Hurricane and High Township, County New Jersey 2 years New Marsh Restoration and Build a where Compton Creek enters a 2,000-foot wide Salt Hay Continuity of Protection Tropical Storm, Storm Corporate Wetlands Maritime Forest; Repair Grass-dominated floodplain characterized by historic Functional Use Surge Restoration Bulkhead at Belford Harbor drainage and mosquito ditches. Current mitigation Partnership strategies include an existing bulkhead, a rock groin breakwater, and possible future maintenance dredging by the USACE. However this area needs marsh restoration, an upland berm maritime forest along Church Road, and repairs to the existing bulkhead along Belford Harbor.

33_11 Conduct Ware Creek Marsh This action includes marsh restoration and an upland Mitigation - Natural Systems Nor'easter, Hurricane and High Township, County New Jersey 2 years New Restoration and Build a maritime forest berm along Ware Creek. Continuity of Protection Tropical Storm, Storm Corporate Wetlands Upland Berm Maritime Forest Functional Use Surge Restoration Partnership

33_12 Coordinate with NWS Earle on The project proposes restoring marshlands to enhance Mitigation - Risk Natural Systems High Township, County New Jersey 2 years New Protecting the Navy Base and their ability to act as natural buffers to reduce impacts of Reduction Protection Corporate Wetlands the Belford Neighborhood storm-induced surge and waves, as well as upland Restoration through Resiliency and Risk restoration to provide a buffer to Normandy Road. Partnership Reduction Projects Upland dune restoration landward of the replenished beach and expansion of the wave-attenuating oyster reef, currently within the NWS Earle Security Zone, could serve as nature-based solutions to mitigate flooding, erosion, and storm surge.

Wednesday, March 4, 2020 Page 2 Middletown, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 33_13 Build Upland Dune This action proposes marsh restoration bordered to the Mitigation - Natural Systems Nor'easter, Hurricane and High Township, County New Jersey 3 years New Restoration Install Wave- west by a maritime forest berm to provide a buffer to Continuity of Protection Tropical Storm, Storm Corporate Wetlands attenuating Oyster Reefs to Normandy Road and neighboring properties. Upland Functional Use Surge Restoration Protect the Leonardo dune restoration landward of the replenished beach, Partnership Neighborhood from Flooding along with the expansion of the wave-attenuating oyster reefs within the NWS Earle Security Zone could serve as nature-based solutions to mitigate flooding and storm surge.

Wednesday, March 4, 2020 Page 3 Monmouth County Mitigation Action Worksheets

Community Action Number: 33_01 Middletown, Township of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Substantially Damaged, Repetitive Loss (RL), and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevate 248 structures determined to be substantially damaged and mitigate (elevate or acquire for open space) RL and SRL properties. Evaluating the Action Hazard(s) Addressed: Flood, Wave Action, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 1, 2, 3, 6 Risk Reduction: Several residential structures throughout the community are prone to flooding, with their main floor elevations below current BFEs. A substantial portion of Middletown lies within mapped storm surge hazard areas, including locations well inland of the Sandy Hook Bay shore, as well as areas along the Navesink River and its tributaries. During Superstorm Sandy, Middletown's Sandy Hook Bay communities of Port Monmouth, Belford, and Leonardo experienced storm surge flooding over a very large area generally north of Route 36 (though tidal flooding along Pews Creek and Compton Creek did extend south of Route 36). Communities in these areas were severely impacted. Along the Navesink and its tributaries, flooding tended to be more constrained to undeveloped floodplains and marina areas; however, along the meandering Swimming River, overbank flooding did affect some homes and businesses. Sea level rise and climate change will contribute to more frequent and severe flooding and surge events. Technical: Elevation is technically feasible. Political: Our political leadership supports this type of project. Legal: While the municipality does not own the structures in question, we fully support the homeowners in moving forward. Environmental: No environmental impacts are anticipated as a result of elevating the homes. Social: No particular social group in our community is likely to be disproportionately impacted by this project. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Affected homeowners and businesses.

Other Community Objectives: Elevating homes in flood hazard areas will represent a benefit to the community as a whole by reducing the emergency response, cleanup, and social costs inflicted by future flood events. STAPLEE Evaluation: 11

Implementing the Action Cost Estimate: $13,500,000.00 Priority: High Local Planning Mechanism: Funding. LOIs for HMPG programs have been submitted. The Township has not received funding to date. Elevation co Responsible Party: State of New Jersey, Monmouth County, Township of Middletown, HMA Likely Funding Source(s): FEMA HMA Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; new flood prevention ordinance has language on substantially damaged properties. Monmouth County Mitigation Action Worksheets

Community Action Number: 33_02 Middletown, Township of Describing the Action Action Name: De-snag and Desilt Streams and Provide Wetlands Maintenance Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other Action Description: Management of riparian buffers along rivers and streams, channel desnagging to preserve the function of natural drainage channels and floodplains, wetlands maintenance and removal of invasive plant species, desilting and dredging of streams and ditches of the following: Waackaack Creek/L.F. 12,500; Pew's Creek/L.F. 10,500; Compton's Creek/L.F. 39,300; Ware Creek/L.F. 10,800; Wagner's Creek/L.F. 12,000; Claypit Creek/L.F. 14,400; McClees Creek L.F. 19,200. The total stream cleaning is 118,700 LF and assumed silt removal rate 0.75 cu. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Wildfire Goals: 2, 3, 5, 6 Risk Reduction: Streams and ditches in Special Flood Hazard Areas do not convey storm flows as efficiently as they should, which results in flooding in several areas. In addition to a flood hazard, accumulated dead vegetation poses a fire hazard. Invasive plant species are becoming prominent in areas, thus decreasing storage capacities. Technical: Excavation is technically feasible. Political: Our political leadership supports this type of project. Legal: This proposal is consistent FEMA program eligibility guidance, and local mitigation plans. Environmental: Permit required for dredging. Social: No particular social group in our community is likely to be disproportionately impacted by this project. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Residents in affected areas in Middletown support the township in moving forward.

Other Community Objectives: To prevent blockages in our waterways and mosquito control. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $3,294,900.00 Priority: High Local Planning Mechanism: In the post Sandy environment more than stream and ditch maintenance. We need a high priority with other agencie Responsible Party: Middletown Township (in conjunction with Monmouth County and Army Corp) Likely Funding Source(s): Municipal budget, EPA, National Fish and Wildlife Foundation (NFWF), NOAA, New Jersey Corporate Wetlands Restor Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; FEMA, post-Sandy grant denied. The Township will continue to search for funding for wetlands maintenance and management. Monmouth County Mitigation Action Worksheets

Community Action Number: 33_03 Middletown, Township of Describing the Action Action Name: Construct and Install an Automatic Slide Gate at Wilson Avenue at Pews Creek Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Construct and install an additional automatic tide-activated electrically-actuated slide gate device at Wilson Avenue at Pews Creek. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5 Risk Reduction: During extreme lunar tides, the flood protection provided by the newly constructed Wilson Ave. slide gate is compromised and there is a tidal flow of water from Compton's Creek across Main Street into the residential properties between Main St. and Brainard Ave. The drainage system is then quickly inundated, and the streets become flooded, negating the intended positive effects of the Wilson Ave flood gate. Technical: Construction is technically feasible. Political: Our political leadership supports this type of project. Legal: No apparent legal issues. Environmental: No environmental impacts are anticipated as a result of construction and installation. Social: No particular social group in our community is likely to be disproportionately impacted by this project. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Affected homeowners, and businesses support the construction and installation of the gate.

Other Community Objectives: We are continuing to review shoreline protection in the post Sandy environment regarding maintenance and upgrades. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $170,000.00 Priority: Local Planning Mechanism: We continue to monitor and maintain flood gates during normal tidal conditions. Responsible Party: Mayor and Township Committee Likely Funding Source(s): FEMA HMA Timeline: Action Status: Completed Notes: Awarded FEMA funds. When the Pews Creek slide gate is closed and the tide is very high, water from Comptons Creek floods the underground drainage system in the streets and the roads stay flooded until the gate opens again near low tide. Monmouth County Mitigation Action Worksheets

Community Action Number: 33_04 Middletown, Township of Describing the Action Action Name: Purchase Temporary/Portable Pumps to Remove Stormwater Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Installing temporary/portable pumps in certain areas will allow stormwater from major nuisance flooding events in Leonardo and Belford sections. The goal is to pump stormwater from the system, discharging into Pew's Creek. Once the water level in the system reaches a certain elevation below existing street elevations, pumps would be activated, and system water would be discharged into the creek. Slide gates would be closed during the pumping to prevent stormwater from re-entering the drainage systems. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 2, 3, 5, 6 Risk Reduction: Stormwater management infrastructure does not convey storm flows as efficiently as it should in Leonardo and Belford. Technical: The project is technically feasible with existing staff and vehicles capable of moving the pumps. The goal is to pump stormwater from the system, discharging into Pew's Creek. Once the water level in the system reaches a certain elevation below existing street elevations, pumps would be activated and system water would be discharged into the creek. Slide gates would be closed during the pumping to prevent stormwater from reentering the drainage systems. Political: Our political leadership supports this type of project. Legal: No apparent legal issues. Environmental: No environment al impacts are anticipated as a result of temporary usage and installation. Social: No particular social group in our community is likely to be disproportionately impacted by this project. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Affected homeowners and businesses

Other Community Objectives: Protecting lives and property from flooding. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $110,000.00 Priority: High Local Planning Mechanism: To eliminate tidal and nuisance flooding. Responsible Party: Middletown Township Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; removing Port Monmouth from this action since the Army Corp project will mitigate the issue there. Township is still interested in finding funding for the Leonardo and Belford sections. The Emory Drive Pump Station was awarded $531,000 of HMGP funding to elevate the station. The Township was also awarded HMGP funding of $153,000 for Port Monmouth Drainage II. Monmouth County Mitigation Action Worksheets

Community Action Number: 33_05 Middletown, Township of Describing the Action Action Name: Purchase and Install Generators for Critical Facilities Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Generators for three fire houses (River Plaza, Port Monmouth, Belford), transfer station (Fire House, Tanya Keller, Crossroads), community Center for shelter, pump station (N. Middletown storm sewer - new generator & new pumps), and five communication towers need generators and have backup batteries. Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 5, 7 Risk Reduction: Reduce or eliminate loss of service at 3 critical facilities. Installation of standby generators will improve response time to service calls during emergencies and improve safety conditions for the responders utilizing the buildings (for example, crucial time was often lost while responders were working in the dark manually opening bay doors). Technical: Technically feasible. Political: Our political leadership supports this type of project. Legal: No legal issues anticipated. Environmental: No environmental impacts are anticipated. Social: No particular social group in our community is likely to be disproportionately impacted by this project. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: affected homeowners and businesses.

Other Community Objectives: Fire Stations & First Aid Squads that remain fully operational during emergencies can also be of greater assistance to the community by serving as short-term shelters, warming and charging stations, and points of distribution for emergency supplies. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $800,000.00 Priority: Local Planning Mechanism: The project is designed to provide the labor and materials necessary for the upgrade of the delivery of emergency po Responsible Party: HMPG Energy Allocation - no match required. Likely Funding Source(s): Timeline: Action Status: Completed Notes: The following HMGP grants were awarded to the Township: Port Monmouth Fire Company Generator: $93,220.00 Belford Independent Fire Company Generator: $52,840.00 River Plaza Fire Company Generator: $55,383.00 Crossroad Shelter: $15,500.00 Croydon Hall - Field House: $14,900.00 Plant: $593,079.64 Tonya Keller Community Center: $14,400.00 Monmouth County Mitigation Action Worksheets

Community Action Number: 33_06 Middletown, Township of Describing the Action Action Name: Provide for Continuity of Operations by Elevating Generators and Switches at Fire Stations Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevate generators and switches at all fire stations located in the flood hazard area.

Evaluating the Action Hazard(s) Addressed: Flood, Wave Action, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 7 Risk Reduction: All the fire companies are located in flood hazard areas and are prone to flooding and power outages. Technical: Technically feasible. Suitable land would be to be acquired. Political: Fire Company membership and community could be oppose relocation of Fire House. Reduction of the total number of fire houses within the township would be considered further. Several stations in this area are fairly close to each other. Adjusting response area of remaining nine firehouses would be considered. Legal: No apparent legal issues. Environmental: No apparent environmental issues. Social: No apparent effect on any social group. Administrative Capability: It is unlikely the Fire Companies have sufficient in-house administrative capabilities. Assistance from contracted services. Local Champion: Possibly the Fire Department

Other Community Objectives: Fire stations that remain fully functional can also be of greater assistance to the community by serving as short-term shelters, warming and charging stations and points of distribution for emergency supplies. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $300,000.00 Priority: Low Local Planning Mechanism: Emergency Planning Responsible Party: Each Fire Company, Township Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action was "Relocate Critical Facilities out of Flood Zones" which is not realistic as all are in a flood zone. Changed to elevate generators and switches. Monmouth County Mitigation Action Worksheets

Community Action Number: 33_07 Middletown, Township of Describing the Action Action Name: Develop a Microgrid Feasibility Study (2017) Action Category: Administrative Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other/NA Action Description: In August 2017, Middletown Township was awarded a $150,000 grant from the New Jersey Board of Public Utilities to hire experts to conduct an initial study to determine a cost-effective configuration that will allow the Township to use local resources to power critical facilities, especially during times of emergency. Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 7 Risk Reduction: The Distributed Energy Resource (DER) microgrid would reinforce the Township’s power supply. The microgrid would prevent prolonged power outages such as the one we experienced during Superstorm Sandy, and also help insulate Naval Weapons Station Earle, multiple fire departments, schools, and other critical facilities. A microgrid can remain connected to the wider electric grid but can also function independently during an emergency situation. Technical: Technically feasible. The study is already complete. Political: Supported by administration. Legal: No legal issues are anticipated Environmental: No adverse environmental effects. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it keeps critical facilities operational during storms. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: OEM, Fire, Police, Mayor

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Low Local Planning Mechanism: Microgrid Feasibility Study, Hazard Mitigation Plan Responsible Party: Township Likely Funding Source(s): Municipal budget Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 33_08 Middletown, Township of Describing the Action Action Name: Enhance Security at Township Facilities Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other Action Description: Increase surveillance systems in Township critical facilities.

Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1, 2, 6 Risk Reduction: Township critical facilities are vulnerable to terrorism or vandalism. Increased security will lower the risk of such hazards. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated Social: Does not adversely affect any particular social group. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Township staff

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Middletown Township Likely Funding Source(s): Homeland Security grants, Municipal budget Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 33_09 Middletown, Township of Describing the Action Action Name: Increase the Number of Drones and Provide Drone Training Action Category: Maintenance/Response/Recovery Action Type: Education and Awareness Programs HMA Eligible Activity: Green Infrastructure Action Description: More drones and drone training for police officers. Two officers have completed the training already.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 5, 7 Risk Reduction: Drones can assist with any hazard, such as a fire or terrorist attack. The drones can give eyes to the first responders. Technical: Technically feasible; Township already bought two drones and had two officers complete the training. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it supports local services during emergencies. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Police, Fire, Mayor, OEM, Mayor

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Police Likely Funding Source(s): Homeland Security grants, Municipal budget Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 33_10 Middletown, Township of Describing the Action Action Name: Conduct Compton Creek Marsh Restoration and Build a Maritime Forest; Repair Bulkhead at Belford Harbor Action Category: Mitigation - Continuity of Functional Use Action Type: Natural Systems Protection HMA Eligible Activity: Floodplain and Stream Restoration Action Description: The proposed project is primarily north of Broadway where Compton Creek enters a 2,000-foot wide Salt Hay Grass- dominated floodplain characterized by historic drainage and mosquito ditches. Current mitigation strategies include an existing bulkhead, a rock groin breakwater, and possible future maintenance dredging by the USACE. However this area needs marsh restoration, an upland berm maritime forest along Church Road, and repairs to the existing bulkhead along Belford Harbor. Evaluating the Action Hazard(s) Addressed: Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 5, 6, 7 Risk Reduction: Belford and Port Monmouth (Middletown Township) are at risk of coastal flooding due to their low-lying locations containing Compton Creek. Technical: Technically feasible. Political: The County and NWS Earle support this action. Legal: Project will be completed on public lands owned by the County or Township; NJDEP permits and and Control approvals may be required. Environmental: This action will improve the natural environment. Social: Does not adversely affect any particular social group. Administrative Capability: Township has the capability to oversee this action, and the County is willing to help implement the Raritan/Sandy Hook Bay Coastal Resilience Planning Study projects. Local Champion: This project is one of 11 projects listed in the 2019 Raritan/Sandy Hook Bay Coastal Resilience Planning Study (by Monmouth County) and is supported by the County, the Township, NWS Earle, and the Planning Study Technical Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Raritan/Sandy Hook Bay Coastal Resilience Planning Study, NWS Earle Joint Land Use Study, Monmouth County Mast Responsible Party: Township, County Likely Funding Source(s): New Jersey Corporate Wetlands Restoration Partnership (NJCWRP), FEMA HMA, National Fish and Wildlife Foundatio Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 33_11 Middletown, Township of Describing the Action Action Name: Conduct Ware Creek Marsh Restoration and Build a Upland Berm Maritime Forest Action Category: Mitigation - Continuity of Functional Use Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other Action Description: This action includes marsh restoration and an upland maritime forest berm along Ware Creek.

Evaluating the Action Hazard(s) Addressed: Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 5, 6, 7 Risk Reduction: Belford (Middletown Township) experiences coastal flooding in the low-lying locations between the tidal waterways of Compton Creek and Ware Creek. This location includes the Belford Ferry Terminal and other utility facilities that serve NWS Earle. Technical: Technically feasible. Political: The County and NWS Earle support this action. Legal: Project will be completed on public lands owned by the County or Township; NJDEP permits and Soil Erosion and Sediment Control approvals may be required. Environmental: This action will improve the natural environment. Social: Does not adversely affect any particular social group. Administrative Capability: Township has the capability to oversee this action, and the County is willing to help implement the Raritan/Sandy Hook Bay Coastal Resilience Planning Study projects. Local Champion: This project is one of 11 projects listed in the 2019 Raritan/Sandy Hook Bay Coastal Resilience Planning Study (by Monmouth County) and is supported by the County, the Township, NWS Earle, and the Planning Study Technical Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Raritan/Sandy Hook Bay Coastal Resilience Planning Study, NWS Earle Joint Land Use Study, Monmouth County Mast Responsible Party: Township, County Likely Funding Source(s): New Jersey Corporate Wetlands Restoration Partnership (NJCWRP), FEMA HMA, National Fish and Wildlife Foundatio Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 33_12 Middletown, Township of Describing the Action Action Name: Coordinate with NWS Earle on Protecting the Navy Base and the Belford Neighborhood through Resiliency and Risk Reduction Projects Action Category: Mitigation - Risk Reduction Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other Action Description: The project proposes restoring marshlands to enhance their ability to act as natural buffers to reduce impacts of storm-induced surge and waves, as well as upland restoration to provide a buffer to Normandy Road. Upland dune restoration landward of the replenished beach and expansion of the wave-attenuating oyster reef, currently within the NWS Earle Security Zone, could serve as nature-based solutions to mitigate flooding, erosion, and storm surge. Evaluating the Action Hazard(s) Addressed:

Goals: 5, 6, 7 Risk Reduction: The NWS Earle Pier and Normandy Road (transportation route for the Navy) is at risk of flooding due to Sea Level Rise. The neighborhood of Belford is also at risk to Sea Level Rise as it is located at a very low elevation. Technical: Technically feasible. Political: The County and NWS Earle support this action. Legal: Project will be completed on public lands owned by the County or Township; NJDEP permits and Soil Erosion and Sediment Control approvals may be required. Environmental: This action will improve the natural environment. Social: Does not adversely affect any particular social group. Administrative Capability: Township has the capability to oversee this action, and the County is willing to help implement the Raritan/Sandy Hook Bay Coastal Resilience Planning Study projects. Local Champion: This project is one of 11 projects listed in the 2019 Raritan/Sandy Hook Bay Coastal Resilience Planning Study (by Monmouth County) and is supported by the County, the Township, NWS Earle, and the Planning Study Technical Other Community Objectives: STAPLEE Evaluation: 10

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Raritan/Sandy Hook Bay Coastal Resilience Planning Study, NWS Earle Joint Land Use Study, Monmouth County Mast Responsible Party: Township, County Likely Funding Source(s): New Jersey Corporate Wetlands Restoration Partnership (NJCWRP), FEMA HMA, National Fish and Wildlife Foundatio Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 33_13 Middletown, Township of Describing the Action Action Name: Build Upland Dune Restoration Install Wave-attenuating Oyster Reefs to Protect the Leonardo Neighborhood from Flooding Action Category: Mitigation - Continuity of Functional Use Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other Action Description: This action proposes marsh restoration bordered to the west by a maritime forest berm to provide a buffer to Normandy Road and neighboring properties. Upland dune restoration landward of the replenished beach, along with the expansion of the wave-attenuating oyster reefs within the NWS Earle Security Zone could serve as nature-based solutions to mitigate flooding and storm surge. Evaluating the Action Hazard(s) Addressed: Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 5, 6, 7 Risk Reduction: Adjacent to Sandy Hook Bay in Leonardo (Middletown Township) is a small depressed area surrounding an unnamed tidal creek. Located between the NWS Earle Pier Complex and Leonardo State Marina, the site contains a sandy beach, low and high marsh areas grading up into upland wooded habitat surrounded by residential lots. Stormwater collects in this ‘bowl’ particularly during high tides and contributes to nuisance flooding. Technical: Technically feasible. Political: The County and NWS Earle support this action. Legal: Project will be completed on public lands owned by the County or Township; NJDEP permits and Soil Erosion and Sediment Control approvals may be required. Environmental: This action will improve the natural environment. Social: Does not adversely affect any particular social group. Administrative Capability: Township has the capability to oversee this action, and the County is willing to help implement the Raritan/Sandy Hook Bay Coastal Resilience Planning Study projects. Local Champion: This project is one of 11 projects listed in the 2019 Raritan/Sandy Hook Bay Coastal Resilience Planning Study (by Monmouth County) and is supported by the County, the Township, NWS Earle, and the Planning Study Technical Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Raritan/Sandy Hook Bay Coastal Resilience Planning Study, NWS Earle Joint Land Use Study, Monmouth County Mast Responsible Party: Township, County Likely Funding Source(s): New Jersey Corporate Wetlands Restoration Partnership (NJCWRP), FEMA HMA, National Fish and Wildlife Foundatio Timeline: 3 years Action Status: New Notes: CAPABILITY ASSESSMENT WORKSHEET

Name: Charles Rogers Title: OEM Coordinator

Jurisdiction: Middletown Township Organization:

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? No Comprehensive/Master Plan

Yes Capital Improvements Plan

Yes Economic Development Plan

Yes Local Emergency Operations Plan

Continuity of Operations Plan

Yes Post-Disaster Recovery Plan

Transportation Plan

Stormwater Management Plan

Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other special plans (e.g., Yes • Town Center Middletown Micro Grid Study brownfields redevelopment, • Monmouth County Joint Land Use Study (2017) disaster recovery, coastal zone • Getting to Resilience (2017) management, climate change • NJ FRAMES adaptation) • Raritan/Sandy Hook Bay Coastal Resilience Planning Study Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code Yes

Building Code Effectiveness Score: Grading Schedule (BCEGS) Score

Rating: Fire Department ISO rating

Site Plan Review Requirements Yes

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning Ordinance

Yes Subdivision Ordinance

Floodplain Ordinance

Natural hazard ordinance (stormwater, steep slope, wildfire)

Flood Insurance Rate Maps

Acquisition of Land for Open Space and Public Recreation Uses

Post-Disaster Recovery Yes Ordinance

Real Estate Disclose Ordinance Yes

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other (ie. Special Purposes Yes Special Purposes Ordinance Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective?

Planning Commission Yes

Mitigation Planning Committee Yes Local Emergency Planning Committee

Maintenance Programs to Reduce Risk (e.g., tree trimming, Yes Regular maintenance on beach, trees, storm sewers, and pumps clearing drainage systems) As part of the County Mutual Agreement and appointed/distrubted by the county: Fire/EMS: All towns nearby, at their request Yes Police: Sandy Hook , as needed nearby Mutual Aid Agreements Police Dogs: As requested RDF: Large scale event

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective?

Chief Building Official

Yes Floodplain Administrator

Emergency Manager Yes

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Community Planner Yes

Civil Engineer Yes

Surveyor Yes

GIS Coordinator Yes

Scientists familiar with the Yes hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past?

Warning Systems/Services (Reverse 911, outdoor warning Yes signals)

Hazard Data and Information

Grant Writing Yes

Hazus Analysis Yes

Other 5 or 6 communication towers have battery backup

How can the above capabilities be expanded and improved to reduce risk? the past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

No Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or No Electric Services

Impact Fees for New No Development

Stormwater Utility Fee

Incur Debt Through Private Yes Activities

Community Development Block No Grant

Other Federal Funding Programs No

State Funding Programs

Yes Incur Debt through General Obligation Funds and Incur Debt Other (e.g., withhold spending in through Special Tax and Revenue Bonds hazard-prone areas)

How can these capabilities be expanded and improved to reduce risk?

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection, Yes Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or Information Programs (e.g., responsible water use, fire safety, household preparedness, environmental education)

Natural Disaster or Safety Related School Programs

StormReady Certification

Firewise Communities Certification

Public-Private Partnership Initiatives Addressing Disaster Related Issues

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

7 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Monmouth County Parcel Classification 0 3,250 6,500 MIDDLETOWN TOWNSHIP Feet Middletown Industrial Commercial Apartment Residential (four families or less) Township ± FLOOD VULNERABILITY Source: © 2014 Esri; Monmouth County; Farm Vacant Civic/Public (Tax Exempt) Unclassified Open Space MONMOUTH COUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

R a r i tan B a y A t l a ntic O c e an

Keansburg Middlesex Borough County Union Beach Borough

Aberdeen Township Keyport Borough 7 Hazlet LK Township

Aberdeen-Matawan

Matawan Hazlet Borough Atlantic Highlands Borough

Naval Weapons Highlands Station Earle Borough LK8B #"36

#"35 Middletown

LK8A r 52 ive Holmdel LK k R Marlboro sin Township ve Township LK12A Na Sea Bright Borough Fair Haven 50 Rumson LK Borough Borough LK12 FEMA FLOOD HAZARD AREAS 1% Annual Chance Flood (SFHA) Regulatory Floodway

Red Bank iver Zone A, AE, AO, AH Borough Red Bank Zone VE sbury R 0.2% Annual Chance Flood Little Shrew NAVAL WEAPONS STATION Silver Monmouth Zone X Borough Beach (NWS) EARLE Borough Undetermined LK520 NWS Earle Restricted Area Zone D Shrewsbury Little Silver NWS Earle Boundary Colts Neck Borough Evacuation Route Tinton Township 54 Oceanport Flood Hazard Areas are a composite of Effective FIRMs (06/20/2018) and NWS Earle Military Influence Area LK Falls Preliminary FIRMs (01/30/2015) Borough Borough Long Branch

This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. Monmouth County P a rcelClas s ification 0 3,250 6,500 MIDDLETOWN TOWNSHIP Fee t Middletown Ind ustrial Comm e rcial Apa rtme nt Res ide ntialfa (four m iliesles or s ) Township ± FLOOD VULNERABILITY Source: © 2014 Esri; Monmouth County; Farm Vacant Civic/PublicExem(Tax pt) Unclas s ified Ope nSpa ce MONMOUTHCOUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

R a r i tan B a y A t l a ntic O c e an

Keansburg Midd les e x Borough County Union Beach Borough

Aberdeen Township Keyport Borough 7 Hazlet LK Township

Aberdeen-Matawan

Matawan Hazlet Borough Atlantic Highlands Borough

NavalWe a pons Highlands StationEarle Borough LK8B #"36

#"35 Middletown

LK8A r 52 ive Holmdel LK k R Marlboro s in POTENTIAL SEA LEVEL RISE (SLR) Township ve Township LK12A Na Sea INUNDATION AREAS Bright Borough AreaInund aSLR tedFootabby1 oveMHHW* Fair Haven 50 Rumson LK Borough Borough AreaInund aSLR tedFootabby3 oveMHHW* LK12 *Me a nHighe High r Wa ter EvacuationRoute Source: NOAASource: SLR Estima tes This : ma p d e pictsinland extentand relativede pthofinund andSLRof ausing 1ft. tionfor3ft. Red Bank NOAASRL da with ta a vertical da tumMeaof nHighe r iver High Wa (MHHW). ter The s e inund a tionrang eare s Borough cons istent with the Rutge rs University’sNew Jerse y Red Bank s b uryR Clima te Ada ptation AllianceScience and Technical AdvisoryPa neReport (STAP l TheReport). STAP Report Little Shrew e s tima tesNew Jerse will y expe rienceSLRbe twee n1.0 NAVAL WEAPONS STATION Silver Monmouth a nd fe1.8 e prior t 2050, regto a rdles sfutureof Borough Beach g ree nhousega sem iss ions . (NWS) EARLE Borough P rojection:NJStatePlane Fee(NAD83) t LK520 Spa tialRes olutionand TheAccuracy: da displayed ta NWSEarle Res Area tricted onthisma prepres econd ntscurrent itionsand does not Shrewsbury Little Silver cons idena r proces tural s e ssuch as erosion ma or rsh NWSEarle Bound a ry Colts Neck Borough m igrationtha twillbe affe ctedsebyfuture alevel rise . Township Tinton Oceanport coarseDue to spa tialres olution,theuse should r not NWSEarle Military Influence Area LK54 Falls Borough interpretthelayers as precise inund a tionextents. Borough Long Branch

Thisma pwas de velope dusing thestatewide10-04-18 composite paof rcelda publishe ta dbythe NJOIT-OGIS. The StateNewof Jerse ma y ke sprovidegrea effortto se t accurate,and cure, complete da and ta me tadHowever, a portions ta. theof da and ta me tadomiss aAnyor maerrors ta current. notbe y ionsor incorrect should be reported invesfor tigaOGIS. to tion

MEETING NOTES

Topic: Middletown Township HMP Meeting

Date: June 13, 2019

Time: 10:00 AM

Location: Middletown Township Arts Center - 36 Church Street, Middletown 07748 - in the Gallery

Drafted by: Paige Kaspar

______

Introductions (Brittany):

• What is Hazard Mitigation? • Matching actions with Goals • New Hazards • HMP Pamphlet • Funding Mitigation Actions:

• Community Action 33_01 – Elevate Substantially Damaged Structures – ongoing o Elevate 248 structures determined to be substantially damaged o Flood prevention ordinance has language on substantially damaged o If built to 1% flood event then would reduce funding, but must be shown on FIRMS o Homeowners can challenge FRIMS if they feel so o Can Army Corp project can mitigate RL, as it reduces risk, broadly speaking? o properties are not elevated or moved by deadline then the town can serve notification of non-compliance and as a last resort write to FEMA that people are living there. The town is not able to evict and only if/when owners abandon the property will it become the towns problem?

• Community Action 33_02 – Wetlands Maintenance and Management - ongoing o FEMA, post-Sandy grant denied o Army Corp project will mitigate, can designate neighborhood o • Community Action 33_03 – Automatic Slide Gate at outfall to Compton’s Creek - ongoing • Community Action 33_04 – Temporary/portable pumps to remove stormwater – ongoing o Port Monmouth out since Army Corp o Leonardo and Belford remain • Community Action 33_05 – Generators for Critical Facilities – completed

o 3 Fire houses (River Plaza, Port Monmouth, Belford Independent) o Transfer stations (Field House, Tanya Keller, Crossroads) o Community Center for shelter o Pump station (N. Middle storm sewer - new generator & new pumps) o 5 communication towers need generators and have backup batteries. • Community Action 33_06 – Relocate Critical Facilities out of Flood Zones – withdrawn? o Not realistic as all in a flood zone – generators and switches

2020 Mitigation Actions (NEW):

• 07 – Implement Micro Grid Study • 08 – New Emergency Operation Center Funded o Need to generator • 09 – Enhanced Security Building • 10 – More drones and drone training for police officers o 2 officers are trained already

Appendix Vol I.34 Millstone Township

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Millstone Township CRS Class 0

NFIP Statistics 5%

21 Polices In-force

8 Total Losses

$46,633 Total Payments 999 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 999 RL Properties

0 RL - Total Losses 7 Total Mitigation $0 RL - Total Paid Actions

0 Number of SRL Properties 0

Number Mitigated SRL 0 Properties Education and Awareness Programs

0 SRL - Total Losses 5

$0 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 1

11 Critical Facilities Local Plans and Regulations

0 Critical Infrastructure 1

210 Historic & Cultural Resources Natural Systems Protection

0 SV Population At Risk (2017) 475 Population at Risk (2017) Millstone, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

34_01 Improve Stormwater Develop mitigation steps to reduce damage and losses Maintenance/Resp Structure and Flood, Nor'easter, Low Township Engineer Municipal budget $200,000.00 2 years Ongoing Management through Larger due to flooding through stormwater runoff control and onse/Recovery Infrastructure Hurricane and Tropical Piping and Maintenance of more efficient drainage and to the five major Project Storm Drains and Basins streams. Provide larger piping capacity and reduce sediment and debris from entering the watershed. Maintain storm drain and detention basins.

34_02 Remove Dead and Hazardous Removal of dead and hazardous trees along Township Maintenance/Resp Natural Systems All Hazards Low Township Engineer Municipal budget $5,000.00 1 year Ongoing Trees along Township's ROWs roads’ rights-of-way onse/Recovery Protection

34_03 Mitigate Flooding Behind Mitigate the flooding issue behind the Fire House and Mitigation - Structure and Flood, Nor'easter, Medium Millstone Township Municipal budget, 2 years New Township Fire House coordinate with Monmouth County on the flooding that Continuity of Infrastructure Hurricane and Tropical and Monmouth County budget, FEMA occurs at the Red Valley Rd. bridge. Functional Use Project Storm County HMA

34_04 Improve Security at Parks and Add security cameras to township parks and historic Maintenance/Resp Local Plans and Terrorism Medium Township Homeland Security 1 year New Historic Buildings buildings. onse/Recovery Regulations Administration grants

34_05 Improve Security by Upgrade the generator at Department of Public Works Maintenance/Resp Structure and All Hazards Low Township FEMA HMA 1 year New Purchasing and Installing and purchase and install a new generator at Wagner Park onse/Recovery Infrastructure Administration Generators at Parks and Farm. Project Historic Buildings

34_06 Acquire, elevate, or relocate There are currently no RL or SRL properties in the Mitigation - Risk Structure and Flood, Nor'easter, High Borough and FEMA HMA 5 + years New buildings and infrastructure in Township; however, the Township realizes the floodplain Reduction Infrastructure Hurricane and Tropical Property Owners flood prone areas, with a changes over time and the risk is always present. If in the Project Storm focus on Repetitive Loss (RL) next five years properties become RL/SRL, the Township and Severe Repetitive Loss will coordinate with residents to mitigate properties (SRL) properties through structure elevation, demolition to open space, or another type of mitigation.

34_07 Repair, Remove, or Repair, remove, or rehabilitate the Assunpink #18 Dam, a Mitigation - Risk Structure and Dam Failure High Ownership not Municipal budget, $0.00 3 years New Rehabilitate the Assunpink High-Hazard Potential Dam, located on the Assunpink Reduction Infrastructure known. NJDEP Bureau of Dam #18 Dam Creek. Project Safety and Flood Control

Wednesday, March 4, 2020 Page 1 Monmouth County Mitigation Action Worksheets

Community Action Number: 34_01 Millstone, Township of Describing the Action Action Name: Improve Stormwater Management through Larger Piping and Maintenance of Drains and Basins Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Develop mitigation steps to reduce damage and losses due to flooding through stormwater runoff control and more efficient drainage and discharge to the five major streams. Provide larger piping capacity and reduce sediment and debris from entering the watershed. Maintain storm drain and detention basins. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 2, 3, 5, 6 Risk Reduction: Current streams, ditches, and stormwater management infrastructure do not convey stormwater runoff as efficiently as they should; this results in flooding in several areas. Technical: Technically feasible. Will help remove stormwater runoff more effectively and Eco grates will eliminate debris from enter into the watershed. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental effects. Will help improve flood control and debris within watershed. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing due to the reduction in flood risk Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Millstone, Township Environmental Commission

Other Community Objectives: Municipal Stormwater Management Regulation Program STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $200,000.00 Priority: Low Local Planning Mechanism: Municipal Stormwater Management Regulation Program Responsible Party: Township Engineer Likely Funding Source(s): Municipal budget Timeline: 2 years Action Status: Ongoing Notes: Ongoing 2015 action; the Township improves their stormwater system every year with their yearly roadway program ($100,000 per annual plan). Monmouth County Mitigation Action Worksheets

Community Action Number: 34_02 Millstone, Township of Describing the Action Action Name: Remove Dead and Hazardous Trees along Township's ROWs Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Removal of dead and hazardous trees along Township roads’ rights-of-way

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 2, 3, 4, 5, 6 Risk Reduction: Much of Millstone Township is located in mapped moderate to extreme wildfire risk areas. Dead and hazardous trees exist at various locations throughout the town presenting fuel sources for wildfire. In addition to the inherent risks associated with dead and hazardous trees in moderate and extreme wildfire risk areas, dead and hazardous trees are more likely to fall as a result of wind during various types of storms. Downed trees block roadways and take down powerlines as they fall. Blocked roadways hamper transportation of all types; most importantly, emergency services. Power outages hamper communications {particularly emergency services type); and, because the Township still operates on private wells and septic systems, it is totally dependent on electric power for running water and other basic toileting and bathing needs. Finding workable solutions to these problems continue to be Millstone's biggest challenges. Technical: Technically feasible. Will help remove dead trees from the roadway, additionally providing a safe roadway access for emergency vehicles. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental effects. Will help improve right-of-way access without any environmental impact. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing due to the reduction in wildfire risk. Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Millstone, Millstone Shade Tree & Fire Commissions

Other Community Objectives: Shade Tree Commission safety program STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $5,000.00 Priority: Low Local Planning Mechanism: Shade Tree Commission Safety Program Responsible Party: Township Engineer Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; JCP&L trims and removes trees as needed but there is no formal program. Township has a Hazardous Trees Assessment Plan that they can use as a guide for the removal of hazardous trees. Monmouth County Mitigation Action Worksheets

Community Action Number: 34_03 Millstone, Township of Describing the Action Action Name: Mitigate Flooding Behind Township Fire House Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Mitigate the flooding issue behind the Fire House and coordinate with Monmouth County on the flooding that occurs at the Red Valley Rd. bridge. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 2, 3, 5, 6 Risk Reduction: The fire houses’ emergency exit can flood up to 20 feet, which can impede emergency response time from the fire department. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated however may need to coordinate with County on any bridge mitigation. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it will better protect the fire station. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: OEM, Council, Mayor

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Millstone Township and Monmouth County Likely Funding Source(s): Municipal budget, County budget, FEMA HMA Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 34_04 Millstone, Township of Describing the Action Action Name: Improve Security at Parks and Historic Buildings Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other Action Description: Add security cameras to township parks and historic buildings.

Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1, 2, 3, 7 Risk Reduction: Parks and historic buildings, which attract visitors, are vulnerable to terrorism or vandalism. Increased security will lower the risk of such hazards. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal issues anticipated. Environmental: Does not adversely affect the environment. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it reduces risk for residents. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: OEM, Council, Mayor, Police

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Administration Likely Funding Source(s): Homeland Security grants Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 34_05 Millstone, Township of Describing the Action Action Name: Improve Security by Purchasing and Installing Generators at Parks and Historic Buildings Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Upgrade the generator at Department of Public Works and purchase and install a new generator at Wagner Park Farm. Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 3, 7 Risk Reduction: Critical facilities in Millstone Township can lose power during storm events. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because the generators will help keep critical local services operational during emergencies. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: OEM, Council, Mayor, Police

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Administration Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 34_06 Millstone, Township of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: There are currently no RL or SRL properties in the Township; however, the Township realizes the floodplain changes over time and the risk is always present. If in the next five years properties become RL/SRL, the Township will coordinate with residents to mitigate properties through structure elevation, demolition to open space, or another type of mitigation. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 1, 2, 3, 6 Risk Reduction: Risk of future destruction and property loss in repetitive flooded areas. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: If structures are elevated, they must be built in compliance with the FEMA flood maps. Environmental: Positively impacts the environment by increasing the permeable surface for each homeowner property. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because of repetitive nature of flooding in the project area. Administrative Capability: There is sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: 10

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough and Property Owners Likely Funding Source(s): FEMA HMA Timeline: 5 + years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 34_07 Millstone, Township of Describing the Action Action Name: Repair, Remove, or Rehabilitate the Assunpink #18 Dam Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Repair, remove, or rehabilitate the Assunpink #18 Dam, a High-Hazard Potential Dam, located on the Assunpink Creek. Evaluating the Action Hazard(s) Addressed: Dam Failure Goals: 1, 2, 3 Risk Reduction: NJDEP classifies Assunpink #18 Dam to be a High-Hazard Potential, meaning failure of the dam may result in probable loss of life and/or extensive property damage. Technical: Technically feasible. Political: There are no anticipated political implications. Legal: May require coordination with NJDEP. Environmental: Minor environmental impacts expected. Social: No adverse social impact anticipated. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: 10

Implementing the Action Cost Estimate: $0.00 Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Ownership not known. Likely Funding Source(s): Municipal budget, NJDEP Bureau of Dam Safety and Flood Control Timeline: 3 years Action Status: New Notes: FEMA has a National Dam Safety Program with funding available to High-Hazard Potential Dams, however, the Assunpink #18 Dam does not qualify for funding at the time of this plan update. CAPABILITY ASSESSMENT WORKSHEET

Name: Roger K. Staib Title: Business Administrator

Jurisdiction: Millstone Township Organization: ______

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? Yes 1. 2017 Comprehensive/Master Plan

Yes Capital Improvements Plan

Yes Economic Development Plan

Yes Local Emergency Operations Plan

Continuity of Operations Plan

Yes Post-Disaster Recovery Plan

Yes 1. As an element of the Master Plan Transportation Plan

Yes 1. 2008 Stormwater Management Plan

Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other special plans (e.g., • Hazardous Tree Assessment Plan (2009) brownfields redevelopment, • Stormwater Pollution Prevention Plan (2009) Yes disaster recovery, coastal zone management, climate change adaptation) Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code No

Building Code Effectiveness Score: Grading Schedule (BCEGS) Score

Rating: Fire Department ISO rating

Site Plan Review Requirements Yes

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning Ordinance

Yes Subdivision Ordinance

Floodplain Ordinance Yes Flood Damage Prevention Ordinance

Natural hazard ordinance (stormwater, steep slope, wildfire)

Flood Insurance Rate Maps

Acquisition of Land for Open Space and Public Recreation Uses

Post-Disaster Recovery Yes Ordinance

Real Estate Disclose Ordinance Yes

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

• Special Purposes Ordinance Other (ie. Special Purposes Yes Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

List of detention basins and storm drains that are regularly maintained by Public Worked

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective?

Planning Commission

Mitigation Planning Committee

Maintenance Programs to Reduce Risk (e.g., tree trimming, Yes Road Program clearing drainage systems)

Mutual Aid Agreements

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective?

Chief Building Official

Yes Floodplain Administrator

Emergency Manager Yes

Community Planner Yes

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Civil Engineer Yes

Surveyor Yes

GIS Coordinator Yes

Scientists familiar with the No hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past?

Warning Systems/Services (Reverse 911, outdoor warning signals)

Hazard Data and Information

Grant Writing Yes

Hazus Analysis Yes

Phase 1: Security cameras for twp buildings, DPW, municipal Other building, community center, parks Barret Homestead: fire and burglary alarms How can the above capabilities be expanded and improved to reduce risk? the past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

Yes Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or No Electric Services

Impact Fees for New Yes Development

Stormwater Utility Fee

Incur Debt Through Private No Activities

Community Development Block Yes Grant

Other Federal Funding Programs No

State Funding Programs

Yes Incur Debt through General Obligation Other (e.g., withhold spending in hazard-prone areas)

How can these capabilities be expanded and improved to reduce risk?

5 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection,

Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or Information Programs (e.g., responsible water use, fire safety, household preparedness, environmental education)

Natural Disaster or Safety

Related School Programs

StormReady Certification

Firewise Communities

Certification

Public-Private Partnership Initiatives Addressing Disaster Related Issues

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Monmouth County Parcel Classification 0 2,750 5,500 MILLSTONE TOWNSHIP Feet Industrial Commercial Apartment Residential (four families or less) FLOOD VULNERABILITY Millstone ± Township Farm Vacant Civic/Public (Tax Exempt) Unclassified Open Space Source: © 2014 Esri; Monmouth County; MONMOUTH COUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

Middlesex Manalapan County #"33 Township Freehold Borough 527ALK

Mercer County

LK571

LK1 Roosevelt A ssunpink Lake Borough LK527 Freehold Township

LK524

Allentown Wesley Lake Borough 195 §¨¦ LK526 FEMA FLOOD HAZARD AREAS 537 LK 1% Annual Chance Flood (SFHA) Upper Regulatory Floodway Freehold Zone A, AE, AO, AH Township Zone VE

0.2% Annual Chance Flood Zone X Undetermined A t l a n t i c Zone D O c e a n Ocean County Evacuation Route Flood Hazard Areas are a composite of Effective FIRMs (06/20/2018) and Preliminary FIRMs (01/30/2015)

This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. Monmouth County ParcelClassific ation 0 2,750 5,500 MILLSTONE TOWNSHIP Feet Industrial Com m ercial Apartment Residentialfamilies(four less)or FLOOD VULNERABILITY Millstone ± Township Farm Vacant Civ ic /PublicExempt) (Tax Unc lassified OpenSpace Source: © 2014 Esri; Monmouth County; MONMOUTHCOUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

Middlesex Manalapan County #"33 Township Freehold Borough 527ALK

MercerCounty

LK571

LK1 Roosevelt A ssunpink Lake Borough LK527 Freehold Township

LK524

Allentown Wesley Lake Borough 195 §¨¦ LK526 POTENTIAL SEA LEVEL RISE LK537 INUNDATION AREAS 1 Foot1 SeaLevel Rise (2050) Upper Freehold Foot3 SeaLevel Rise (2100) Township EvacuationRoute

S patialResolution and Acc This uracy: map depic tsinland extent andrelativ depth e of inundation andfor1ft.of3ft. SLR using NOAA S LRdatawith vertica datum al ofMean Hig Hig h er hWater (MHHW). These inundation rang es are consistent with the Rutgers Univ ersity’sNew JerseyClim ateAdaptation Allianc Sc e iencand e Tech nicAdvisory al Panel Report (STAP Report).The STAP Report estim atesNew willJersey experienc SLR e between feetand 1.8 1.0 A t l a n t i c priortoregardless 2050, of futuregreenh ousegas emissions. The datadisplayed on this map represents current conditions and does notconsider natural proc essessuch aserosion marshor mig ration O c e a n OceanCounty thatwill be affected byfuture sea level Duerise. to coarse spatial resolution,the user sh ouldnot interpret the layers as precise inundationextents.

Thismap was developed using thestatewide 10-04-18 com positeof parcel datapublish by edthe NJOIT-OGIS. The State of New Jerseymakes greateffort to prov idesecure,acc andcom urate, pletedataand metadata. However, portions of th dataand e metadata may beinc orrectnotor current.Anyom or errors issionssh ouldbereported forinv estig ationto OGIS.

MEETING NOTES

Topic: Millstone- Monmouth County HMP Meeting

Date: June 19, 2019

Time: 7:00 PM- 8:00 PM

Location: Municipal Building; 470 Stage Coach Rd. Millstone, NJ

Attendees: Kathleen Hart, Deputy Municipal Clerk

Michael Kuczinski, Committee / OEM Coordinator

Fiore Masci, Mayor

Matt Shafai, Township Engineer

Daniel Specht, Public Works Coordinator

Roger Staib, Business Administrator

Brittany Ashman, MB Planner

Drafted by: Paige Kaspar

______

Introductions (Brittany):

• What is Hazard Mitigation? • Matching actions with Goals • New Hazards • HMP Pamphlet • Funding 2015 Mitigation Actions:

• Community Action 34_01 – Drainage Improvements – Ongoing o $100,000 per year for road program o Maintain storm drains & detention basins o Ongoing pipe issues • Community Action 34_02 – Fuel Management (right-of-way clearing) -Ongoing o JCP&L trim and removes trees as needed but there is no formal program o Town has a Hazardous Trees Assessment Plan

2020 Mitigation Actions (NEW):

• #3 – Red Valley Rd. Bridge flood (County Bridge), this is behind the Fire House and flood emergency exit, 20ft • #4 – Add security cameras to park and historic buildings • #5 – Improve the safety of intersections still house, coordinate w/ County (not really mitigation scope) • #6 – Upgrade generator at Public Works, new generator at Wagner Park Farm, residents to apply for grants information

Other Issues

• Soil stabilization is an issue because there are no curbs • Water tables are high • Well & septic power loss Successes

• HMA added generators to township court house, community center, and town hall

Appendix Vol I.35 Monmouth Beach Borough

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Monmouth Beach Borough CRS Class 8

NFIP Statistics 45% 1,751 Polices In-force

1,743 Total Losses

$109,860,448 Total Payments 148 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 16 RL Properties

487 RL - Total Losses 19 Total Mitigation $26,797,162 RL - Total Paid Actions

20 Number of SRL Properties 3

Number Mitigated SRL 0 Properties Education and Awareness Programs

104 SRL - Total Losses 11

$7,428,110 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 5

5 Critical Facilities Local Plans and Regulations

0 Critical Infrastructure 0

25 Historic & Cultural Resources Natural Systems Protection

0 SV Population At Risk (2017) 1,457 Population at Risk (2017) Monmouth Beach, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

35_01 Elevate Existing Retaining Wall The existing sunken retaining wall needs to be elevated Mitigation - Risk Structure and Flood, Extreme Wind, High Borough FEMA HMA $1,400,000.00 1 year Ongoing & Floodproof Pump Station at to a height of 15 feet to protect the park and its existing Reduction Infrastructure Nor'easter, Hurricane and Administrator Shorelands Park amenities from flood-related damage. Project Tropical Storm, Storm Surge

35_02 Floodproofing Pump Station Drainage improvements to mitigate storm-related Mitigation - Risk Structure and Flood, Extreme Wind, Borough FEMA Hazard $75,000.00 Withdrawn flooding. Reduction Infrastructure Nor'easter, Hurricane and Administrator Mitigation Grant, Project Tropical Storm, Storm Borough funding Surge

35_03 Conduct Improvements to Drainage Improvements to mitigate storm-related Mitigation - Structure and Flood, Extreme Wind, Low Borough Municipal budget $15,000,000.00 3 years Ongoing Drainage Infrastructure at flooding. Continuity of Infrastructure Nor'easter, Hurricane and Administrator, OEM, Shorelands Park Functional Use Project Tropical Storm, Storm Borough Engineer, Surge DPW

35_04 Acquire, elevate, or relocate Elevate or acquire approximately 1,891 residential Mitigation - Risk Structure and Flood, Extreme Wind, High Homeowners and/or FEMA HMA $1,500,000.00 3 years Ongoing buildings and infrastructure in structures to new FEMA FIRM maps, specifically RL/SRL Reduction Infrastructure Nor'easter, Hurricane and Borough flood prone areas, with a properties. Project Tropical Storm, Storm Administrator focus on Repetitive Loss (RL) Surge and Severe Repetitive Loss (SRL) properties

35_05 Elevate Four Municipal Elevate the Police Station, Cultural Center, First Aid, and Mitigation - Risk Structure and Flood, Extreme Wind, High Borough FEMA Hazard $1,500,000.00 2 years Ongoing Structures Fire House to new FEMA FIRM maps. Reduction Infrastructure Nor'easter, Hurricane and Administrator Mitigation Grant, Project Tropical Storm, Storm Borough funding, Surge Army Core of

35_06 Install Stormwater Install stormwater improvements such as inlets, Mitigation - Structure and Flood, Extreme Wind, High Borough Municipal budget $2,000,000.00 1 year Ongoing Improvements in Low-laying manholes, and piping for low lying areas such as Johnson Continuity of Infrastructure Nor'easter, Hurricane and Administrator Areas St., Anderson St., Drew Ct., and Valentine St. Functional Use Project Tropical Storm, Storm Surge

35_07 Expand the Existing Seawall Expand the existing seawall to fill in the approx. 675 LF Structure and Flood, Extreme Wind, Borough FEMA Hazard $10,000,000.00 Completed gap between Valentine St. and the south end of the Infrastructure Nor'easter, Hurricane and Administrator Mitigation Grant, Bathing Pavilion. Project Tropical Storm, Storm Borough funding, Surge Army Core of

35_08 Elevate Evacuation Roadways Elevate the following roadways (listed in order of Mitigation - Structure and Flood, Nor'easter, High Borough Engineering FEMA HMA, $40,000,000.00 2 years New importance): (1) Patton Ave, (2) Riverdale, (3) Meadow Continuity of Infrastructure Hurricane and Tropical Municipal budget Ave, and (4) North Rd. Functional Use Project Storm, Storm Surge

Wednesday, March 4, 2020 Page 1 Monmouth Beach, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 35_09 Elevate DPW Generator Elevate generator at DPW at least 10ft. Maintenance/Resp Structure and All Hazards Low Borough DPW FEMA HMA $50,000.00 1 year New onse/Recovery Infrastructure Project

35_10 Purchase and Install Permanent roof for the Borough's salt shed, which stores Maintenance/Resp Structure and Extreme Wind, Low DPW Municipal budget $100,000.00 1 year New Permanent Roof for Salt Shed the salt for DPW's salt trucks. onse/Recovery Infrastructure Nor'easter, Hurricane and Project Tropical Storm

35_11 Purchase Drones for Research Drones and drone training. The Police Department have Maintenance/Resp Education and All Hazards Low OEM Homeland Security $5,000.00 2 years New & Recovery Attempts completed the training already. onse/Recovery Awareness grants Programs

35_12 Install Surveillance Cameras at Install security cameras at Griffin Park, Shorelands Park, Maintenance/Resp Structure and All Hazards Low Borough Homeland Security $10,000.00 1 year New Critical Facilities Bathing Room, and Recycling Center for surveillance of onse/Recovery Infrastructure Administration grants human-based hazards (terrorism, vandalism) and natural Project hazards (flood, water levels).

35_13 Develop a Winter Storm Improve capability to respond to winter storm events by Maintenance/Resp Local Plans and Winter Storm Low Borough Borough funding $350,000.00 1 year New Response Plan purchasing a new salt spreader truck and new inflatable onse/Recovery Regulations Administrator boat.

35_14 Develop a Civil Unrest Improve ability to respond to a civil unrest event by Maintenance/Resp Education and Terrorism Low Borough Homeland Security $70,000.00 1 year New Response Plan and Preparation purchasing shields, helmets and riot gear. onse/Recovery Awareness Administrator, OEM Grants, Borough Programs Funding

35_15 Develop a Cyber Attack Update emergency response plans to address, mitigate, Maintenance/Resp Education and Terrorism Low Borough Homeland Security $1,000,000.00 1 year New Response and recover from a potential cyber attack affecting the onse/Recovery Awareness Administration Grants, Borough operation of borough activities. Programs Funding

35_16 Develop an Action Plan to Plan, develop, and maintain a borough-wide action plan Maintenance/Resp Local Plans and All Hazards Low Borough Homeland Security $70,000.00 1 year New Address Economic Collapse to address the public safety response in the event of an onse/Recovery Regulations Administration Grants, Borough economic collapse. The plan should be all inclusive to Funding safeguard and protect all critical facilities.

35_17 Develop an Action plan to Emergency Response to address pandemic event. Maintenance/Resp Local Plans and All Hazards Low Borough Homeland Security $70,000.00 1 year New Address Pandemic Event onse/Recovery Regulations Administration Grants, Borough Action Funding

Wednesday, March 4, 2020 Page 2 Monmouth Beach, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 35_18 Develop an Action plan to Action plan to address and respond to power failure Maintenance/Resp Local Plans and All Hazards Low Borough Homeland Security $300,000.00 1 year New Address Power Failure events and install a generator at Monmouth Beach onse/Recovery Regulations Administration, Grants, Borough Elementary School OEM, Borough Funding Engineer, DPW

35_19 Develop a Terrorism Response Emergency Response to Terroristic Threat Maintenance/Resp Local Plans and Terrorism Low Borough Homeland Security 1 year New Plan onse/Recovery Regulations Administration, Grants, Borough OEM, Police, Fire, Funding EMS, DPW

Wednesday, March 4, 2020 Page 3 Monmouth County Mitigation Action Worksheets

Community Action Number: 35_01 Monmouth Beach, Borough of Describing the Action Action Name: Elevate Existing Retaining Wall & Floodproof Pump Station at Shorelands Park Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: The existing sunken retaining wall needs to be elevated to a height of 15 feet to protect the park and its existing amenities from flood-related damage. Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6, 7 Risk Reduction: The elevation of the existing retaining wall at Shorelands Park is not high enough and when it is breached, residential structures and the pump station at the northern terminus of Monmouth Parkway incur significant flooding damage. Floodwaters also erode, litter, and change the topography of the park. Monmouth Beach is located on a narrow strip of land just south of Sea Bright. All of Monmouth Beach is in an area mapped as potentially susceptible to storm surge. Most of Monmouth Beach was inundated during Superstorm Sandy; a great deal of this was back bay flooding which this retaining wall protects. Technical: This mitigation project is technically feasible. Political: This project was advised by commissioners and the Mayor. Legal: The community does have the legal authority to implement this project. Environmental: There are no negative environmental impacts caused by this project and it will comply with all federal, state, and local regulations. Social: There are no social impacts from this project on the community. Administrative Capability: The community does have the personnel and administrative capability implement this action as well as maintain it. Borough would have to bid the project and construction Local Champion: Commissioners and the Mayor

Other Community Objectives: Capital improvements STAPLEE Evaluation: 12

Implementing the Action Cost Estimate: $1,400,000.00 Priority: High Local Planning Mechanism: Mitigation activities will be implemented according to all governing regulatory documents. Responsible Party: Borough Administrator Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; combining with Community Action 35_02. Rewarded $150K, but need grant extensions, partial grant HMPG, waiting for more grant money. Monmouth County Mitigation Action Worksheets

Community Action Number: 35_02 Monmouth Beach, Borough of Describing the Action Action Name: Floodproofing Pump Station Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Mitigation Reconstruction Action Description: Drainage improvements to mitigate storm-related flooding.

Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6, 7 Risk Reduction: Flooding occurs in the residential area around the pump station at the northern terminus of Monmouth Parkway. Technical: This mitigation is technically feasible. Political: This project was advised by commissioners and the Mayor. Legal: The community does have the legal authority to implement this project. Environmental: There are no negative environmental impacts caused by this project and it will comply with all federal, state, and local regulations. Social: There are no social impacts from this project on the community. Administrative Capability: The community does have the personnel and administrative capability implement this action. Borough would have to bid the project and construction. Local Champion: Commissioners and the Mayor

Other Community Objectives: Capital improvements STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $75,000.00 Priority: Local Planning Mechanism: Mitigation activities will be implemented according to all governing regulatory documents Responsible Party: Borough Administrator Likely Funding Source(s): FEMA Hazard Mitigation Grant, Borough funding Timeline: Action Status: Withdrawn Notes: Combined with Community Action #35_01. Monmouth County Mitigation Action Worksheets

Community Action Number: 35_03 Monmouth Beach, Borough of Describing the Action Action Name: Conduct Improvements to Drainage Infrastructure at Shorelands Park Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Drainage Improvements to mitigate storm-related flooding.

Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5,6,7 Risk Reduction: Shorelands Park is prone to flooding. Technical: This mitigation project is technically feasible. Political: No political obstacles anticipated Legal: Homes must be elevated in compliance with the new FEMA flood maps once they are finalized. Environmental: No adverse environmental impacts Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: Borough Administrator

Other Community Objectives: Capital improvements STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $15,000,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administrator, OEM, Borough Engineer, DPW Likely Funding Source(s): Municipal budget Timeline: 3 years Action Status: Ongoing Notes: HMGP pending obligation as of 2020: Shorelands Park Drainage Improvement project Monmouth County Mitigation Action Worksheets

Community Action Number: 35_04 Monmouth Beach, Borough of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevate or acquire approximately 1,891 residential structures to new FEMA FIRM maps, specifically RL/SRL properties.

Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5 Risk Reduction: Monmouth Beach is located on a narrow strip of land just south of Sea Bright. All of Monmouth Beach is in an areas mapped as potentially susceptible to storm surge. Most of Monmouth Beach was inundated during Superstorm Sandy; a great deal of damage was back bay flooding. Sea level rise and climate change will contribute to more frequent and severe flooding and surge events over a larger area. Technical: This mitigation project is technically feasible. Political: This project was advised by commissioners and the Mayor. Legal: Homes must be elevated in compliance with the new FEMA flood maps once they are finalized Environmental: Positively impacts the environment by increasing the permeable surface for each homeowner property Social: Municipality workers may need to relocate while the structural elevation is implemented. Administrative Capability: The community does have the personnel and homeowners will maintain projects. bid the project and construction Local Champion: Commissioners and the Mayor

Other Community Objectives: Capital improvements STAPLEE Evaluation: 10

Implementing the Action Cost Estimate: $1,500,000.00 Priority: High Local Planning Mechanism: Mitigation activities will be implemented according to all governing regulatory documents, additionally current code r Responsible Party: Homeowners and/or Borough Administrator Likely Funding Source(s): FEMA HMA Timeline: 3 years Action Status: Ongoing Notes: Ongoing 2015 action; 100 structures have been elevated already. Monmouth County Mitigation Action Worksheets

Community Action Number: 35_05 Monmouth Beach, Borough of Describing the Action Action Name: Elevate Four Municipal Structures Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Mitigation Reconstruction Action Description: Elevate the Police Station, Cultural Center, First Aid, and Fire House to new FEMA FIRM maps.

Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 7 Risk Reduction: The critical facilities are located in the SFHA and need to be elevated Technical: This mitigation project is technically feasible Political: This project was advised by commissioners and the Mayor. Legal: The community does have the legal authority to implement this project Environmental: There are no negative environmental impacts caused by this project and it will comply with all federal, state, and local regulations. Social: There are no social impacts from this project on the community. Administrative Capability: The community does have the personnel and administrative capability implement this action as well as maintain it. Borough would have to bid the project and construction. Local Champion: Commissioners and the Mayor

Other Community Objectives: Capital improvements STAPLEE Evaluation: 12

Implementing the Action Cost Estimate: $1,500,000.00 Priority: High Local Planning Mechanism: Mitigation activities will be implemented according to oil governing regulatory documents Responsible Party: Borough Administrator Likely Funding Source(s): FEMA Hazard Mitigation Grant, Borough funding, Army Core of Engineers Timeline: 2 years Action Status: Ongoing Notes: Ongoing 2015 action; Borough Hall and the Library are elevated, DPW added concrete walls and elevated, still need to elevate Police Station, Cultural Center, First Aid, and Fire House. The Borough was awarded FEMA Funding 406 Public Assistance for damages to the Cultural Center ($10k), Borough Hall ($45k), the First Aid Building ($50k), and the Fire House (1.9M) after Sandy. Monmouth County Mitigation Action Worksheets

Community Action Number: 35_06 Monmouth Beach, Borough of Describing the Action Action Name: Install Stormwater Improvements in Low-laying Areas Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Install stormwater improvements such as inlets, manholes, and piping for low lying areas such as Johnson St., Anderson St., Drew Ct., and Valentine St. Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5 Risk Reduction: The Borough's drainage system does not currently accommodate typical periods of high runoff; this causes flooding in locations such as Johnson St., Anderson St., Drew Ct., and Valentine St. Technical: This project is technically feasible. Political: This project was advised by commissioners and the Mayor. Legal: The community does have the legal authority to implement this project. Environmental: There are no negative environmental impacts caused by this project and it will comply with all federal, state, and local regulations. DEP permits may be required. Social: There are no social impacts from implementing this action. Administrative Capability: The community does have the personnel and administrative capability implement this action as well as maintain it. Borough would have to bid the project and construction. Borough may need to get easements. Local Champion: Commissioners and the Mayor

Other Community Objectives: Capital improvements STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $2,000,000.00 Priority: High Local Planning Mechanism: Mitigation activities will be implemented according to all governing regulatory documents, additionally current code r Responsible Party: Borough Administrator Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; new flap values on outfalls located at Valentine St., Monmouth Parkway, Drew, Navesink Dr, Central Dr. Monmouth County Mitigation Action Worksheets

Community Action Number: 35_07 Monmouth Beach, Borough of Describing the Action Action Name: Expand the Existing Seawall Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Mitigation Reconstruction Action Description: Expand the existing seawall to fill in the approx. 675 LF gap between Valentine St. and the south end of the Bathing Pavilion. Evaluating the Action Hazard(s) Addressed: Flood, Extreme Wind, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 7 Risk Reduction: The massive storm surges from Superstorm Sandy breached the existing sea wall and carried water over the wall, causing severe flooding and significant damages to both private residences and commercial business throughout the Borough. Technical: This mitigation is technically feasible. Political: This project was advised by commissioners and the Mayor. Legal: The community does have the legal authority to implement this project. Environmental: Environmental concerns such as disrupting the natural shoreline processes will be considered in the design and all federal, state, and local regulations will be followed. Social: There are no social impacts from this project on the community. Administrative Capability: The community does have the personnel and administrative capability implement this action as well as maintain it. Borough would have to bid the project and construction. Local Champion: Commissioners and the Mayor as well as residents located on the west side of Ocean Ave.

Other Community Objectives: Capital improvements STAPLEE Evaluation: 12

Implementing the Action Cost Estimate: $10,000,000.00 Priority: Local Planning Mechanism: Mitigation activities will be implemented according to all governing regulatory documents Responsible Party: Borough Administrator Likely Funding Source(s): FEMA Hazard Mitigation Grant, Borough funding, Army Core of Engineers Timeline: Action Status: Completed Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_08 Monmouth Beach, Borough of Describing the Action Action Name: Elevate Evacuation Roadways Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevate the following roadways (listed in order of importance): (1) Patton Ave, (2) Riverdale, (3) Meadow Ave, and (4) North Rd. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 3, 7 Risk Reduction: These roadways are critical to the evacuation of the town and cannot be flooded. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal issues anticipated. Environmental: Elevation of roadways would involve significant reconstruction of roadways which will have some impacts on the surrounding environment. Social: Could adversely impact property owners living adjacent to roadways. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: Mayor, Administrator, OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $40,000,000.00 Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Engineering Likely Funding Source(s): FEMA HMA, Municipal budget Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_09 Monmouth Beach, Borough of Describing the Action Action Name: Elevate DPW Generator Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Elevate generator at DPW at least 10ft.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 3, 7 Risk Reduction: The generator is not above the BFE and is susceptible to flooding and power loss during storm events. Technical: Technically feasible. Political: No political obstacles anticipated. Legal: No legal issues expected. Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it supports local services during emergencies. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Public Works

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $50,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough DPW Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_10 Monmouth Beach, Borough of Describing the Action Action Name: Purchase and Install Permanent Roof for Salt Shed Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Permanent roof for the Borough's salt shed, which stores the salt for DPW's salt trucks.

Evaluating the Action Hazard(s) Addressed: Extreme Wind, Nor'easter, Hurricane and Tropical Storm Goals: 3, 7 Risk Reduction: The existing shed has a roof that is easily ripped by the wind; needs a permanent roof to prevent wind from taking the salt. Technical: Technically feasible. Political: No political obstacles anticipated. Legal: No legal issues expected; the salt shed and is located on Borough property behind Borough Hall. Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it supports local services during emergencies. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: DPW

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $100,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: DPW Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: New Notes: Post- Sandy, the Borough was awarded $607 to manufacture and install the new canopy and side drops (FEMA 406 Public Assistance Grant) Monmouth County Mitigation Action Worksheets

Community Action Number: 35_11 Monmouth Beach, Borough of Describing the Action Action Name: Purchase Drones for Research & Recovery Attempts Action Category: Maintenance/Response/Recovery Action Type: Education and Awareness Programs HMA Eligible Activity: Miscellaneous/Other Action Description: Drones and drone training. The Police Department have completed the training already.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 2, 3, 5, 7 Risk Reduction: Drones can assist with any hazard, such as a fire or terrorist attack. The drones can give extra eyes for first responders; in addition they can assist with hazard mitigation research by flying over areas that are not physically accessible. Technical: Technically feasible. Political: No political obstacles anticipated. Legal: No legal issues expected. Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it supports local services during emergencies. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: Police, OEM, Mayor

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $5,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: OEM Likely Funding Source(s): Homeland Security grants Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_12 Monmouth Beach, Borough of Describing the Action Action Name: Install Surveillance Cameras at Critical Facilities Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Install security cameras at Griffin Park, Shorelands Park, Bathing Room, and Recycling Center for surveillance of human-based hazards (terrorism, vandalism) and natural hazards (flood, water levels). Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 2, 3, 5, 7 Risk Reduction: These critical facilities are vulnerable to a terrorist attack or smaller crimes, such as vandalism in addition to flooding from the back bay; these areas need to be monitored. Technical: Technically feasible Political: No political obstacles anticipated. Legal: No legal issues expected. Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $10,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration Likely Funding Source(s): Homeland Security grants Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_13 Monmouth Beach, Borough of Describing the Action Action Name: Develop a Winter Storm Response Plan Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Advance Assistance Action Description: Improve capability to respond to winter storm events by purchasing a new salt spreader truck and new inflatable boat. Evaluating the Action Hazard(s) Addressed: Winter Storm Goals: 1,2,3,4,5,6,7 Risk Reduction: Reduction in damages and losses due to winter storm residual affects; including potential power loss due to downed Power lines, increased response times of emergency personnel due to poor road conditions and possible health Hazards due to potential loss of heat and other utilities. Technical: Technically feasible. Political: No political obstacles anticipated Legal: No legal issues expected. Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $350,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administrator Likely Funding Source(s): Borough funding Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_14 Monmouth Beach, Borough of Describing the Action Action Name: Develop a Civil Unrest Response Plan and Preparation Action Category: Maintenance/Response/Recovery Action Type: Education and Awareness Programs HMA Eligible Activity: Advance Assistance Action Description: Improve ability to respond to a civil unrest event by purchasing shields, helmets and riot gear.

Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1,2,5,7 Risk Reduction: To reduce the potential loss of life and property damage in the event of a civil uprising event. In preparation, Police vehicles and equipment in addition to other public safety apparatus will be dispatched accordingly at strategic locations throughout the borough. Technical: Technically feasible. Political: No political obstacles anticipated. Legal: No legal issues expected. Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $70,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administrator, OEM Likely Funding Source(s): Homeland Security Grants, Borough Funding Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_15 Monmouth Beach, Borough of Describing the Action Action Name: Develop a Cyber Attack Response Action Category: Maintenance/Response/Recovery Action Type: Education and Awareness Programs HMA Eligible Activity: Advance Assistance Action Description: Update emergency response plans to address, mitigate, and recover from a potential cyber attack affecting the operation of borough activities. Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1,2,5,7 Risk Reduction: Due to the increasing number of frequent occurrences involving cyber attacks and threats, the borough should be Prepared to prevent or avoid any potential hackers from gaining unauthorized access to their computer systems. In addition, by maintaining the integrity of the borough’s networks and systems, this reduces the chances of Compromise and an imminent threat to life, health and public safety. Technical: Technically feasible Political: No political obstacles anticipated Legal: No legal issues expected Environmental: No adverse environmental impacts Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,000,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration Likely Funding Source(s): Homeland Security Grants, Borough Funding Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_16 Monmouth Beach, Borough of Describing the Action Action Name: Develop an Action Plan to Address Economic Collapse Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other Action Description: Plan, develop, and maintain a borough-wide action plan to address the public safety response in the event of an economic collapse. The plan should be all inclusive to safeguard and protect all critical facilities. Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 2 Risk Reduction: To reduce, minimize and prevent any loss of public/private property in the event of an economic collapse or downturn. Technical: Technically Feasible Political: No political obstacles anticipated Legal: No legal issues expected Environmental: No adverse environmental impacts Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Borough Administration

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $70,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration Likely Funding Source(s): Homeland Security Grants, Borough Funding Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_17 Monmouth Beach, Borough of Describing the Action Action Name: Develop an Action plan to Address Pandemic Event Action Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other Action Description: Emergency Response to address pandemic event.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1,3,5,6,7 Risk Reduction: To reduce and/or prevent the loss of life and spread of potential communicable diseases or contamination by harmful substances. Technical: Technically Feasible Political: No political obstacles anticipated Legal: No legal issues expected Environmental: No adverse environmental impacts Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Borough Administration

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $70,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration Likely Funding Source(s): Homeland Security Grants, Borough Funding Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_18 Monmouth Beach, Borough of Describing the Action Action Name: Develop an Action plan to Address Power Failure Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other Action Description: Action plan to address and respond to power failure events and install a generator at Monmouth Beach Elementary School Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1,2,6,7 Risk Reduction: To reduce and/or prevent the loss of life and destruction of public and private property as a result of power failure. Technical: Technically Feasible Political: No political obstacles anticipated Legal: No legal issues expected Environmental: No adverse environmental impacts Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Borough Administration

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $300,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration, OEM, Borough Engineer, DPW Likely Funding Source(s): Homeland Security Grants, Borough Funding Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 35_19 Monmouth Beach, Borough of Describing the Action Action Name: Develop a Terrorism Response Plan Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other Action Description: Emergency Response to Terroristic Threat

Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1,2,5,7 Risk Reduction: To reduce and/or prevent the loss of life and/or destruction of public and private property as a result of a terroristic event. Technical: Technically Feasible Political: No political obstacles anticipated Legal: No legal issues expected Environmental: No adverse environmental impacts. Social: Does not adversely affect any particular social group. Perceived by the public to be beneficial because it keeps the community safe. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Borough Administration

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Administration, OEM, Police, Fire, EMS, DPW Likely Funding Source(s): Homeland Security Grants, Borough Funding Timeline: 1 year Action Status: New Notes: CAPABILITY ASSESSMENT WORKSHEET

Name: Gerald Paige Title: Grants Manager

Jurisdiction: Monmouth Beach Borough Organization: T&M Associates

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? Yes Comprehensive/Master Plan

Yes Capital Improvements Plan

No Economic Development Plan

Yes Local Emergency Operations Plan

Yes Succession Plan Continuity of Operations Plan

Yes Post-Disaster Recovery Plan

No Under Development Transportation Plan

Yes Stormwater Management Plan

No Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Yes • Getting to Resilience (2017) • Floodplain Management Plan (2017) Other special plans (e.g., • Monmouth Beach Lot Coverage Study (2018) brownfields redevelopment, • Debris Management Plan disaster recovery, coastal zone • management, climate change Borough Hazard Mitigation Plan (2017) • adaptation) NJFRAMES • Strategic Recovery Planning Report

Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code Yes

Building Code Effectiveness Score: No Grading Schedule (BCEGS) Score

Rating: 4 Fire Department ISO rating Yes

Site Plan Review Requirements Yes

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning to allow for resiliency Zoning Ordinance

Yes Subdivision Ordinance

Floodplain Ordinance Yes

Natural hazard ordinance (stormwater, steep slope, Yes Stormwater Control Ordinance wildfire)

Flood Insurance Rate Maps Yes Currently being updated by FEMA

Acquisition of Land for Open No Space and Public Recreation Uses

Post-Disaster Recovery No Ordinance

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Real Estate Disclose Ordinance No

Other (ie. Special Purposes Yes Special Purposes Ordinance Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective? Yes Planning Commission

Yes Mitigation Planning Committee

Maintenance Programs to Reduce Risk (e.g., tree trimming, Yes clearing drainage systems)

Mutual Aid Agreements Yes

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective? Yes PT Chief Building Official

Yes FT Floodplain Administrator

Emergency Manager Yes FT

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Community Planner Yes

Civil Engineer Yes PT Consultant, T&M Associates

Surveyor Yes PT Consultant, T&M Associates

GIS Coordinator Yes PT Consultant, T&M Associates

Scientists familiar with the No PT Consultant, T&M Associates hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past? Yes Warning Systems/Services (Reverse 911, outdoor warning signals)

No Hazard Data and Information

Grant Writing Yes PT Consultant, T&M Associates

Hazus Analysis Yes PT Consultant, T&M Associates

Other

How can the above capabilities be expanded and improved to reduce risk? the past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

Yes Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or No Electric Services

Impact Fees for New No Development

Stormwater Utility Fee No

Incur Debt Through Private No Activities

Community Development Block Yes Grant

Other Federal Funding Programs No

Yes State Funding Programs

Yes Incur Debt through General Obligation Other (e.g., withhold spending in hazard-prone areas)

How can these capabilities be expanded and improved to reduce risk? The Borough will seek additional grant funding to supplement fiscal gaps. The Borough is financially capable of bonding to contribute to mitigation projects. They will seek alternative measures through ordinances or fundraising (including fees/taxes to levy on developers that will be dedicated specifically to mitigation projects). The Borough has a demonstrated track record of cooperating and providing technical and legal support to large projects for the protection of its shore and, specifically, easements required for seawall and beach replenishment projects.

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection, No Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or Information Programs (e.g., responsible water use, fire safety, Yes household preparedness, environmental education)

Natural Disaster or Safety Yes Related School Programs

StormReady Certification No

Firewise Communities No Certification

Public-Private Partnership Initiatives Addressing Disaster Yes Related Issues

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

7 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Building Classification Industrial Commercial Apartment Residential (four families or less) Monmouth Monmouth 0 500 1,000 MONMOUTH BEACH BOROUGH County Farm Vacant Civic/Public (Tax Exempt) Unclassified Beach Feet FLOOD VULNERABILITY Borough Parcel Classification ± Industrial Commercial Apartment Residential (four families or less) Source: © 2014 Esri; Monmouth County; MONMOUTH COUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Farm Vacant Civic/Public (Tax Exempt) Unclassified Open Space Projection: New Jersey State Plane, NAD 1983

Sea Bright Borough

RIVERVIEW RD

SUNSET LN Rumson MARAVISTA DR Borough r e A t l a n t i c iv

ry R O c e a n u b SEEAC s REST R D w re h S

SEAVIEW AVE

RD SE HOU

E

C I PARK RD

Little Silver MONMOUTHPRKWY Borough

CENTRAL RD

E V A GERTRUDE PL W O D EA M CHANNEL DR SAILO SOUTHRD RS HIGHLAND AVE WAY

COLUMBUSDR

H

A

L A S CENTER RD COTTAGE RD CO MEADOW AVE T T N TAGE RD

I

N D

GP

MONMOUTHPRKWY NB

BAYONNEAVE E G N R

I S S D S P WEST ST Oceanport P O L A L A B N L #36 P O D " S S R I T Borough N D G E N UB RD GULLPOINT RD P CL S L

T SEAVIEWAV

D

R

SOUTH RD B U L

C I RD R O L J TOCCIAVE NB PATTEN AVE AC K S D O LO R RI N C

T WILLOW RD

E LL GAIL RD IS CT AVETOCCI SEAWANEKA AV HARBOUR WAY LORI RD Wesley Lake TICONDEROGA AV GRIFFIN ST MANNCT WOOLLEY ST ONEIDA AV ROBBIN ST M FEMA FLOOD HAZARD AREAS A MARGARET PL GENESSE AV N N SU RF CT R 1% Annual Chance Flood (SFHA) JOHNSON ST D PL K

C ITHICA AV I Regulatory Floodway CAYUGA AV W RIVERDALE AV L N

P E ANDERSON ST

R

K D Zone A, AE, AO, AH C R RENWI RENWICK PL EW CT COMANCHEDR Zone VE MOHICAN AV RIDDLE AVE VALENTINE ST 0.2% Annual Chance Flood SYDNEYST SERAND AV PORT AU PECK AV VISTA CT WINHAR PL Zone X Long MANAHASSETT AV HORICON AV Branch JESSICA ST Undetermined RIVERGATE WAY A t l a n t i c

COOK ST POCAHONTAS AV E City

LONG BRANCH AV V Zone D

A BEACH AV WILLOWL N N SO N MOHAWK AV L P O c e a n HO E IC L N COOKMAN AV N T WYANDOTTE AV T Evacuation Route

A CHURCHST WESTST COLUMBIA AV P # ALGONQUIN AV "36 Flood Hazard Areas are a composite of Effective FIRMs (06/20/2018) and Preliminary FIRMs (01/30/2015) HIAWATHA AV

BAYVIEW PL NICHOLSON PL MANAHASSETT WAY S COOKMAN AV NARRAGANSETT CATHERINE ST OCEAN AV N WHITE ST NEPTUNE AV NABERAL AV This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. BuildingClassific ation Industrial Com m ercial Apartment Residentialfamilies(four less)or Monmouth Monmouth 0 500 1,000 MONMOUTH BEACH BOROUGH County Farm Vacant Civ ic /PublicExempt) (Tax Unc lassified Beach Feet FLOOD VULNERABILITY Borough ParcelClassific ation ± Industrial Com m ercial Apartment Residentialfamilies(four less)or Source: © 2014 Esri; Monmouth County; MONMOUTHCOUNTY HAZARD MITIGATION PLAN NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Farm Vacant Civ ic /PublicExempt) (Tax Unc lassified OpenSpace Projection: New Jersey State Plane, NAD 1983

Sea Bright Borough

RIVERVIEW RD

SUNSET LN Rumson MARAVISTA DR Borough r e A t l a n t i c iv

ryR O c e a n u b SEEAC s REST R D w re h S

SEAVIEW AVE

RD SE HOU

E

C I PARK RD

Little Silver MONMOUTHPRKWY Borough

CENTRAL RD

E V A GERTRUDE PL W O D EA M CHANNEL DR SAILO SOUTHRD RS HIGHLAND AVE WAY

COLUMBUSDR

H

A

L A S CENTER RD COTTAGE RD CO MEADOW AVE T T N TAGE RD

I

N D

GP

MONMOUTHPRKWY NB

BAYONNEAVE E G N R

I S S D S P WEST ST Oceanport P O L A L A B N L #36 P O D " S S R I T Borough N D G E N UB RD GULLPOINT RD P CL S L

T SEAVIEWAV

D

R

SOUTH RD B U L

C I RD R O L J TOCCIAVE NB PATTEN AVE AC K S D O LO R RI N C

T WILLOW RD

E LL GAIL RD IS CT AVETOCCI SEAWANEKA AV HARBOUR WAY LORI RD Wesley Lake TICONDEROGA AV GRIFFIN ST MANNCT WOOLLEY ST ONEIDA AV ROBBIN ST M POTENTIAL SEA LEVEL RISE A MARGARET PL GENESSE AV N N SU RF CT R INUNDATION AREAS JOHNSON ST D PL K

C ITHICA AV I Foot1 SeaLevel Rise(2050) CAYUGA AV W RIVERDALE AV L N

P E ANDERSON ST

R

K D

C R Foot3 SeaLevel Rise(2100) RENWI RENWICK PL EW CT COMANCHEDR EvacuationRoute MOHICAN AV RIDDLE AVE VALENTINE ST S patialResolution and Acc This uracy: map depic tsinland extent SYDNEYST andrelativ depth e of inundation andfor1ft.of3ft. SLR using NOAA SERAND AV PORT AU PECK AV S LRdatawith vertica datum al ofMean Hig Hig h er hWater (MHHW). VISTA CT Long WINHAR PL These inundation rang es are consistent with the Rutgers MANAHASSETT AV UnivNew Clim ersity’s Jersey ateAdaptation Allianc Sc e iencand e HORICON AV Branch JESSICA ST Tech nicAdvisory al Panel Report (STAP Report).The STAP Report RIVERGATE WAY A t l a n t i c

COOK ST estim atesNewwill Jersey experienc SLR e between feetand 1.8 1.0

POCAHONTAS AV E City

LONG BRANCH AV priortoregardlessof 2050, future greenh ousegasemissions. The V

A BEACH AV WILLOWL N N datadisplayed on this map represents current conditions and does SO N MOHAWK AV L P O c e a n HO E IC L N COOKMAN AV notconsider natural proc such esses erosionas marshor mig ration N T

WYANDOTTE AV T

A CHURCHST WESTST COLUMBIA AV thatwill be affected byfuture levelseaDue to rise. coarse spatial P # ALGONQUIN AV "36 resolution,the should user not interpret the layers asprecise HIAWATHA AV inundationextents.

BAYVIEW PL NICHOLSON PL MANAHASSETT WAY S COOKMAN AV NARRAGANSETT CATHERINE ST OCEAN AV N WHITE ST NEPTUNE AV NABERAL AV Thismap wasdeveloped using thestatewide 10-04-18 com positeof parcel datapublished bythe NJOIT-OGIS. The State of Newmakes Jersey greateffort to prov acc idesecure, and com urate, pletedataand metadata. However, portions of th dataand e metadata may beinc orrectnotor omorcurrent.Any errors issionsshould bereported forinv estig ationto OGIS.

MEETING NOTES

Topic: Matawan- Monmouth County HMP Meeting

Date: July 2, 2019

Time: 10:00 AM- 11:00 AM

Location: Borough Hall, 201 Broad Street, Matawan, NJ 07747

Attendees: Joe Chirichello, Monmouth Beach Public Works

Don Clare, Construction Official

Bonnie Heard, Borough Engineer/ Engineer Zoning Officer

Sue Howard, Mayor

Edward Junquet, OEM Deputy Coordinator

Aaron Rock, OEM Deputy Coordinator

Emily Trethewey, Borough Engineers Office Staff Design

Dana Webb, Engineering Support Tech

Judy Wilson, Borough Administrator

Brittany Ashman, MB Planner

Drafted by: Paige Kaspar

______

Introductions (Brittany):

• What is Hazard Mitigation? • Matching actions with Goals • New Hazards • HMP Pamphlet • Funding 2015 Mitigation Actions:

• Community Action 35_01/35_02 – Elevate existing sunken retaining wall/Floodproofing pump station – Ongoing o Combining actions #1 & #2 o Cost estimate = $1.4 million

o Funding issues: rewarded $150K, but need grant extensions, partial grant HMPG, waiting for more grant money o Shorelands Park • Community Action 35_03 – Elevate approximately 1,991 residential structures – Ongoing o 100 structures have been elevated already • Community Action 35_04 – Elevating six municipal structures – Ongoing o Borough Hall and Library have been elevated o DPW added concrete walls and was elevated o Still need to elevate Police building, Cultural Center, First Aid, and Fire House • Community Action 35_05 – Raising and re-grouting of seawall – Completed o Re-grouted areas that had been damages o Did not raise sea wall o Also see Action #7 • Community Action 35_06 – Installation of stormwater systems – Ongoing o Flap valves on Valentine St., Monmouth Parkway, Drew, Navensivk Dr, Central Dr. o New flap valves on outfalls • Community Action 35_07 – Expand existing seawall - Completed o Completed as of May 2019 2020 Mitigation Actions (NEW):

• #8 – (1) Elevate Patton Ave, (2) Riverdale, (3) Meadow Ave, and (4) North Rd which are critical to the evacuation of the town (listed in order of importance) • #9 – Elevate 2nd floor generator at DPW at least 10ft • #10 – permanent roof for salt shed • #11 – Drones for Research & Recovery attempts  police have drones • #12 – Surveillance & watch flood water at Griffin Park, Shorelands Park, Bathing Room, Recycling Center

Successes

• Seaview Ave + C: floodproofed JCP&L substation two years ago • Schools: flood gates at elementary school, security cameras, locked doors, resource officer w/ gun

Appendix Vol I.36 Neptune City Borough

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Neptune City Borough CRS Class 0 NFIP Statistics 15%

166 Polices In-force

50 Total Losses

$2,893,365 Total Payments 4 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 0 RL Properties

8 RL - Total Losses 8 Total Mitigation $808,862 RL - Total Paid Actions

0 Number of SRL Properties 0

Number Mitigated SRL 0 Properties Education and Awareness Programs

0 SRL - Total Losses 7

$0 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 1

10 Critical Facilities Local Plans and Regulations

0 Critical Infrastructure 0

1 Historic & Cultural Resources Natural Systems Protection

4,167 SV Population At Risk (2017) 4,284 Population at Risk (2017) Neptune City, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

36_01 Increase Piping Capacity and The Borough improves their stormwater system every Structure and Flood, Nor'easter, Borough Engineer $80,000.00 Completed Reduce Sediment/Debris year with their yearly roadway program. Develop Infrastructure Hurricane and Tropical within Watershed mitigation steps to reduce damage and losses due to Project Storm, Storm Surge flooding through control of stormwater runoff and more efficient drainage and discharge to Shark River. Provide larger piping capacity and reduces sediment/ debris within watershed providing better overall volume/flow throughout the system. The City has identified the following key areas: Evergreen, East End Ave, Boston Rd, Rt 35/3rd Ave and Windsor Ct.

36_02 Purchase and Install To maintain police, fire, and medical service throughout Maintenance/Resp Structure and Flood, Nor'easter, Low OEM Director FEMA HMA, 1 year Ongoing Generators at Borough Hall, the municipality, the Borough seeks to provide temporary onse/Recovery Infrastructure Hurricane and Tropical Municipal budget the Fire Station, and the power for Borough Hall, the Fire Station, and the School. Project Storm, Storm Surge School The Office of Emergency Management and a Central Command is within Borough Hall. Likewise, the Fire House is utilized by the EMS employees, whereas the school is utility as an evacuation center for residents in need of safety.

36_03 Elevate and Waterproof Sewer Elevate the sewer pumps within the building and to Mitigation - Structure and Flood, Nor'easter, Medium Borough Engineer FEMA HMA, $47,000.00 1 year Ongoing Pump Station waterproof the building to mitigate any future damage. Continuity of Infrastructure Hurricane and Tropical Municipal budget Functional Use Project Storm, Storm Surge

36_04 Create a Safe House for OEM To maintain police, fire, and medical EMS services Maintenance/Resp Structure and Flood, Nor'easter, Medium Borough Engineer Municipal budget 1 year Ongoing Equipment throughout the municipality, the Borough seeks to onse/Recovery Infrastructure Hurricane and Tropical and OEM Director provide a centralized building "AKA Safe House" for Project Storm, Storm Surge critical OEM equipment. Currently this equipment is stored outside and subject to the daily elements which damages the effectiveness of the equipment in emergency events.

36_05 Implement Improvements to Neptune City seeks to provide key sleeping and shower Maintenance/Resp Structure and Flood, Lightening, Low Borough Engineer Municipal budget $14,000.00 1 year Ongoing Designated Shelters facilities to emergency personnel and evacuated onse/Recovery Infrastructure Nor'easter, Hurricane and and OEM Director residents during a storm event. Three key buildings Project Tropical Storm within the Borough have been identified within the action plan: Borough Hall, Fire Station and the Elementary School. Equipment and building upgrades are needed to ensure these facilities can meet emergency needs.

36_06 Develop a Comprehensive The Borough would like to develop a comprehensive Maintenance/Resp Local Plans and Flood, Nor'easter, Medium Borough Engineer Municipal budget $1,500,000.00 1 year Ongoing Drainage Study to Mitigate mitigation study to reduce damage and losses due to onse/Recovery Regulations Hurricane and Tropical Borough Flooding flooding. The study will provide the necessary data to Storm, Storm Surge determine the larger piping needed to provide a better overall volume/ flow throughout the system. The Borough flood hazard areas have not been studied or updated since 1976.

Wednesday, March 4, 2020 Page 1 Neptune City, Borough of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 36_07 Acquire, elevate, or relocate Elevation and/or acquisition of Flood-prone residential Mitigation - Risk Structure and Flood, Wave Action, High Mayor and Council FEMA HMA 1 year Ongoing buildings and infrastructure in structures, with particular focus on those in our Reduction Infrastructure Nor'easter, Hurricane and flood prone areas, with a community that are on FEMA's Repetitive Loss List and Project Tropical Storm, Storm focus on Repetitive Loss (RL) Severe Repetitive Loss list. New Jersey is committed to Surge, Winter Storm and Severe Repetitive Loss continuing the reduction of RL and SRL properties in the (SRL) properties State; in turn, they have assigned a high priority to mitigating SRL and RL properties in the State Hazard Mitigation Plan. We are committed to supporting these projects as interested homeowners come forward and will support such homeowners, despite the loss in tax revenue, because we recognize the importance of making our community more disaster-resistant and reducing the financial burden of repetitive flooding in our community.

36_08 Target Harden Critical Improve alarm, access control and camera systems Maintenance/Resp Structure and Terrorism Low Borough Homeland Security $300,000.00 2 years New Facilities by Installing located at all Borough Facilities, Specifically DPW, onse/Recovery Infrastructure grants Surveillance Cameras, an Borough Hall, Fire Station, First Aid Squad, Community Project Access Control System, and/or Center and Three sewer Pumping Stations. an Alarm System

Wednesday, March 4, 2020 Page 2 Monmouth County Mitigation Action Worksheets

Community Action Number: 36_01 Neptune City, Borough of Describing the Action Action Name: Increase Piping Capacity and Reduce Sediment/Debris within Watershed Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: The Borough improves their stormwater system every year with their yearly roadway program. Develop mitigation steps to reduce damage and losses due to flooding through control of stormwater runoff and more efficient drainage and discharge to Shark River. Provide larger piping capacity and reduces sediment/ debris within watershed providing better overall volume/flow throughout the system. The City has identified the following key areas: Evergreen, East End Ave, Boston Rd, Rt 35/3rd Ave and Windsor Ct. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: Piped streams and stormwater management infrastructure do not convey stormwater runoff as efficiently as they should resulting in flooding. Most of the City is in areas mapped as potentially susceptible to storm surge. During Superstorm Sandy, the inundation area was limited fairly close to the Shark River including East End Ave., Windsor Ct., Route 35, and Steiner Ave. between Route 35 and 3rd Ave. Drainage system does not efficiently convey storm water runoff; this results in flooding in several areas. Sea Level Rise and climate change will contribute to more frequent and severe flooding and surge events over a larger area. Technical: Technically feasible. Will help remove stormwater runoff more effectively and eliminate debris from entering the watershed. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental impacts. Will help improve flood control and debris within watershed. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because of repetitive nature of flooding in the project area. Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Neptune City, Shark River Environmental Commission

Other Community Objectives: Municipal Stormwater Management Regulation Program STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $80,000.00 Priority: Local Planning Mechanism: Municipal Stormwater Management Regulation Program Responsible Party: Borough Engineer Likely Funding Source(s): Timeline: Action Status: Completed Notes: Added additional drainage pipes on Windsor St. Route 35/3rd Ave – critical drainage issues, but too extensive. DOT looked at the intersection in the 1980s, but the amount of infrastructure that would need to be moved made the cost prohibitive. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_02 Neptune City, Borough of Describing the Action Action Name: Purchase and Install Generators at Borough Hall, the Fire Station, and the School Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: To maintain police, fire, and medical service throughout the municipality, the Borough seeks to provide temporary power for Borough Hall, the Fire Station, and the School. The Office of Emergency Management and a Central Command is within Borough Hall. Likewise, the Fire House is utilized by the EMS employees, whereas the school is utility as an evacuation center for residents in need of safety. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 7 Risk Reduction: Power outages have been frequent occurrences in the Borough. During severe storms, this impacts public buildings and disrupts local government operations and does not allow the Borough to shelter its emergency personnel. During storm events it is critical to maintain emergency services throughout the Borough. To maintain these services emergency power is needed until primary power source is restored Technical: Technically feasible. Will provide critical power until primary power is restored. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental impacts. Social: Borough of Neptune City residents. Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Neptune City

Other Community Objectives: Will provide services in accordance with the Office of Emergency Management duties. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Low Local Planning Mechanism: Office of Emergency Management Program Responsible Party: OEM Director Likely Funding Source(s): FEMA HMA, Municipal budget Timeline: 1 year Action Status: Ongoing Notes: The City was awarded HMGP funding of $90,300 for Generators for critical facilities post-Sandy. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_03 Neptune City, Borough of Describing the Action Action Name: Elevate and Waterproof Sewer Pump Station Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Mitigation Reconstruction Action Description: Elevate the sewer pumps within the building and to waterproof the building to mitigate any future damage.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 1, 3, 6, 7 Risk Reduction: During storm events it is critical to maintain sanitary services throughout the Borough. The pump stations continuous operation during storm events is paramount to the communities, health, and welfare. While no one has been killed or become deathly ill from the sanitary pump station being offline, the fact remains that non-sanitary conditions pose a direct health concern for the immediate municipality and surrounding hospitals/residents within the adjoining area. The ability to provide continuous sanitation service during a storm event is critical to maintaining the communities, health, and limiting the potential viral outbreaks associated with poor sanitation conditions. Technical: Technically feasible. Will provide critical services during storm events. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental effects. Social: Borough of Neptune City residents. Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Neptune City

Other Community Objectives: Will provide services in accordance with the Office of Emergency Management duties. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $47,000.00 Priority: Medium Local Planning Mechanism: Office of Emergency Management Program Responsible Party: Borough Engineer Likely Funding Source(s): FEMA HMA, Municipal budget Timeline: 1 year Action Status: Ongoing Notes: The Borough was awarded $22k of FEMA Funding 406 Public Assistance for East End Avenue - Sewer Lift Station. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_04 Neptune City, Borough of Describing the Action Action Name: Create a Safe House for OEM Equipment Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: To maintain police, fire, and medical EMS services throughout the municipality, the Borough seeks to provide a centralized building "AKA Safe House" for critical OEM equipment. Currently this equipment is stored outside and subject to the daily elements which damages the effectiveness of the equipment in emergency events. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 3, 7 Risk Reduction: During storm events it is critical to maintain emergency equipment throughout the Borough. OEM operations during storm events is paramount to the communities' health and welfare. The ability to provide emergency services during a storm event is critical to maintaining the community's health and safety. Technical: Technically feasible. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental effects. Social: Borough of Neptune City residents. Administrative Capability: Borough of Neptune City residents. Administrative capability needs at least three people to administer (after technical assistance from the State) Local Champion: Residents of Neptune City

Other Community Objectives: Will provide services in accordance with the Office of Emergency Management duties. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Office of Emergency Management Program Responsible Party: Borough Engineer and OEM Director Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; the City prioritizes this project and is researching potential funding sources. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_05 Neptune City, Borough of Describing the Action Action Name: Implement Improvements to Designated Shelters Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Neptune City seeks to provide key sleeping and shower facilities to emergency personnel and evacuated residents during a storm event. Three key buildings within the Borough have been identified within the action plan: Borough Hall, Fire Station and the Elementary School. Equipment and building upgrades are needed to ensure these facilities can meet emergency needs. Evaluating the Action Hazard(s) Addressed: Flood, Lightening, Nor'easter, Hurricane and Tropical Storm Goals: 3, 7 Risk Reduction: The OEM operation during storm events is paramount to the community's health and welfare. The ability to provide emergency services during a storm event is critical to maintaining the communities, health, and safety. Technical: Technically feasible. Will provide critical services during storm events. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental effects. Social: Borough of Neptune City residents Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Neptune City

Other Community Objectives: Will provide services in accordance with the Office of Emergency Management duties STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $14,000.00 Priority: Low Local Planning Mechanism: Office of Emergency Management Program Responsible Party: Borough Engineer and OEM Director Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; Neptune City still needs building improvements to their shelters and is searching for potential funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_06 Neptune City, Borough of Describing the Action Action Name: Develop a Comprehensive Drainage Study to Mitigate Borough Flooding Action Category: Maintenance/Response/Recovery Action Type: Local Plans and Regulations HMA Eligible Activity: Miscellaneous/Other/NA Action Description: The Borough would like to develop a comprehensive mitigation study to reduce damage and losses due to flooding. The study will provide the necessary data to determine the larger piping needed to provide a better overall volume/ flow throughout the system. The Borough flood hazard areas have not been studied or updated since 1976. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 3, 4, 5 Risk Reduction: The current drainage system does not efficiently convey stormwater runoff; this results in flooding in several areas. Sea Level Rise and climate change will contribute to more frequent and severe flooding and surge events over a larger area. Technical: Technically feasible. Political: No apparent political issues. Legal: No apparent legal issues. Environmental: No adverse environmental effects. Will help improve flood control and debris within watershed. Social: Borough of Neptune City residents. Administrative Capability: Need at least three people to administer (after technical assistance from the State) Local Champion: Residents of Neptune City, Shark River Environmental Commission

Other Community Objectives: Municipal Stormwater Management Regulation Program STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,500,000.00 Priority: Medium Local Planning Mechanism: Municipal Stormwater Management Regulation Program Responsible Party: Borough Engineer Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; Route 35 needs the study and the Borough is researching potential funding opportunities. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_07 Neptune City, Borough of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevation and/or acquisition of Flood-prone residential structures, with particular focus on those in our community that are on FEMA's Repetitive Loss List and Severe Repetitive Loss list. New Jersey is committed to continuing the reduction of RL and SRL properties in the State; in turn, they have assigned a high priority to mitigating SRL and RL properties in the State Hazard Mitigation Plan. We are committed to supporting these projects as interested homeowners come forward and will support such homeowners, despite the loss in tax revenue, because we recognize the importance of making our community more disaster-resistant and reducing the financial burden of repetitive flooding in our community. Evaluating the Action Hazard(s) Addressed: Flood, Wave Action, Nor'easter, Hurricane and Tropical Storm, Storm Surge, Winter Storm Goals: 2, 3, 5, 6 Risk Reduction: Several residential structures throughout the community are prone to flooding, with their main floor elevations below current BFEs. Sea Level Rise and climate change will contribute to more frequent and severe flooding and surge events. Technical: Elevation and acquisition are both technically feasible project types. Political: Our political leadership supports this type of project. Legal: While the municipality does not own the structures in question, we fully support the homeowners in moving forward. Environmental: No environmental impacts are anticipated at this time; this would be confirmed as specific homeowners come forward and their property details are reviewed. It is likely that environmental impacts would be positive, as household hazardous wastes are no longer introduced into floodwaters. Social: No particular social group in our community is likely to be disproportionately impacted by this project; this would be re-evaluated as particular interested homeowners come forward Administrative Capability: Our municipality has the administrative capabilities to manage an elevation and/or acquisition project. Local Champion: Affected homeowners, elected officials

Other Community Objectives: Improve and protect lifestyles of residents; reduction of costly property damage; resiliency; floodplain management; capital improvements. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: High Local Planning Mechanism: Homeowners; Mayor; Council; Administrator; Engineer; local ordinance; Hazard Mitigation Plan Responsible Party: Mayor and Council Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Ongoing Notes: Ongoing action; the Borough deems this action necessary and is searching for potential funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 36_08 Neptune City, Borough of Describing the Action Action Name: Target Harden Critical Facilities by Installing Surveillance Cameras, an Access Control System, and/or an Alarm System Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other Action Description: Improve alarm, access control and camera systems located at all Borough Facilities, Specifically DPW, Borough Hall, Fire Station, First Aid Squad, Community Center and Three sewer Pumping Stations. Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1, 2, 3, 7 Risk Reduction: Increasing surveillance to reduce the risk of terrorism or crime. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it supports local services during emergencies. Administrative Capability: Borough has sufficient capacity and experience to administer this action. Local Champion: OEM, Police

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $300,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Borough Likely Funding Source(s): Homeland Security grants Timeline: 2 years Action Status: New Notes: CAPABILITY ASSESSMENT WORKSHEET

Name:Keith Mitchell Title: Captain / Deputy OEM Coordinator

Jurisdiction: Neptune City Borough Organization: ______

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? Yes Comprehensive/Master Plan

Yes Capital Improvements Plan

No Economic Development Plan

Yes Local Emergency Operations Plan

Yes Continuity of Operations Plan

No Post-Disaster Recovery Plan

No Transportation Plan

Yes Stormwater Management Plan

No Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other special plans (e.g., brownfields redevelopment, disaster recovery, coastal zone management, climate change adaptation) Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code Yes

Building Code Effectiveness Score: Grading Schedule (BCEGS) Score

Rating: Fire Department ISO rating

Site Plan Review Requirements Yes

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning Ordinance

Yes Subdivision Ordinance

Floodplain Ordinance No

Natural hazard ordinance (stormwater, steep slope, No wildfire)

Flood Insurance Rate Maps No

Acquisition of Land for Open No Space and Public Recreation Uses

Post-Disaster Recovery No Ordinance

Real Estate Disclose Ordinance No

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other (ie. Special Purposes Yes Special Purposes Ordinance Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

The city council could in act an ordinance for post-disaster recovery in addition to establishing a post disaster

recovery plan in conjunction with the ordinance. We could also establish an Economic Development Plan.

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective? LEPC Planning Commission Yes

LEPC Mitigation Planning Committee Yes

Maintenance Programs to Reduce Risk (e.g., tree trimming, Yes Locally performed by DPW clearing drainage systems)

Mutual Aid Agreements Yes Neptune Township, Monmouth County

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective? Yes Part Time Chief Building Official

Yes Part Time Floodplain Administrator

Part Time OEM Coordinator Emergency Manager Yes Deputy is Full Time Police Captain

Community Planner Yes Part Time

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Civil Engineer Yes Part Time

Surveyor No Part Time

GIS Coordinator Yes Monmouth County

Scientists familiar with the No hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past?

Warning Systems/Services Outside Warning Siren (Reverse 911, outdoor warning Yes Nixle (reverse 911) New System signals)

Yes Hazard Data and Information

Grant Writing Yes

Hazardous Analysis Yes

Other

How can the above capabilities be expanded and improved to reduce risk? the past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

Yes Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or Yes Electric Services

Impact Fees for New Yes Development

Stormwater Utility Fee

Incur Debt Through Private No Activities

Community Development Block Yes Grant

Other Federal Funding Programs No

State Funding Programs

No Other (e.g., withhold spending in hazard-prone areas)

How can these capabilities be expanded and improved to reduce risk? To help us with our fiscal capability, we need to pursue more grants and also possibly look into bonds.

5 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection, No Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or Information Programs (e.g., responsible water use, fire safety, Yes Fire Safety, Emergency Preparedness household preparedness, environmental education)

Natural Disaster or Safety No Related School Programs

Storm Ready Certification No

Firewise Communities No Certification

Public-Private Partnership Currently starting to partner with local businesses for future Initiatives Addressing Disaster No storms Related Issues

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

Currently we are looking to partner with our businesses to make them part of the LEPC as stakeholders. We are exploring the Storm Ready Certification.

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Building Classification Industrial Commercial Apartment Residential (four families or less) Monmouth 0 350 700 County Farm Vacant Civic/Public (Tax Exempt) Unclassified NEPTUNE CITY Feet FLOOD VULNERABILITY Parcel Classification ± Neptune Industrial Commercial Apartment Residential (four families or less) Source: © 2014 Esri; Monmouth County; MONMOUTH COUNTY HAZARD MITIGATION PLAN City NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Farm Vacant Civic/Public (Tax Exempt) Unclassified Open Space Projection: New Jersey State Plane, NAD 1983

W

WAYSIDE RD A DAVIS AVE K OXFORD WAY E F TENTH AV I E NEW GATE LN L W D A ALBERTA AV L R N D U T 9TH AV

A HAMILTON AV V FORTUNATO PL

STANLEY AV

LAKEVIEW AV TAYLOR AV TAYLOR #"33 EIGHTH AV

O OXFORD DR AK DR

EMERSON PLEMERSON LAREINE AVE 2 V LK A N NEPTUNE AV HTO BRIG FILLMORE AV

Bradley PL FIFTH AV D

O Beach

O PROSPECT ST

W HAWTHORNE AVE

N

E

E

R G GROVE PL OLIVER DR LAWRENCE DR ROLAND PL WESTWOOD PL 17 LK LOCUST AV

MORRIS AVE

SHARK PL

RIVERDALE AV BENNETT AV

WICKAPECKO DR

TFH WAY ROBBINS RD FOURTH AVE THIRD AVE

RIVERVIEW AV 5 SMOCK AVE LK DURAND RD PARK AVE HILLSIDE AVE

E

V AVONDALE AVE A

K WILSON RD SUMMIT AVE SECOND AVE

C

BRIGHTON AVE O MAY PL

H C Bradley S E VERGR NEPTUNE AVE EEN AVE # LAUREL AVE "18 WOODLAND AVE RIDGE PL Beach

R # Borough D "35 E BENNET RD POPLAR PL ID 40A S TUCKER DR R K L L IL H D RIDGE TERR E

D

PITTENGER PL SI

R

MCDERMOTT RD E FOREST AVE

V I MONMOUTH AVE

R

CARTON AVE

S ELY RD IV MIDWOOD ST # ANS RD "71 E V A WEST WALL PL N A PACIFIC AVE MERRIT PL M BURLINGTON AVE WALKER RD PI L

MORRISEY RD HILLSIDE RD S WALL ST

ELIZABETH TERR H

O

L

L BRADLEY BLVD Y MCLELLAND PL O S V AUDREY T FIELD ST LAKESIDE AVE E PL R R L D MOORE RD O BRADLEY ST K WINDSOR AVE O R K A Wesley Lake D P WINDSOR TERR R Neptune WEST END AVE

FEMA FLOOD HAZARD AREAS WILSON AVE LAIRD AVE Township VICTOR PL HOME ST 1% Annual Chance Flood (SFHA) HELEN TERR MYRON AVE S NORWOOD AVE ha Regulatory Floodway ELMWOOD DR RIVERVIEW CT r COUSE RD k GREEN ST SMOCK ST V BEVERLY WAY A R

CLAYTON AVE S L NORWOOD LN

Zone A, AE, AO, AH U L i

E v RI M V Y e E R BELL PL R V M r I D EW I Zone VE T AV R E D FAIRVIEW PL STANTON ST LAKEWOOD AVE

0.2% Annual Chance Flood LORRAINE DR NNP STEINER AVE WOODLAND LN R D HILLCREST AVE T Zone X S E

R

O F OAK TERR Undetermined WOODMERE AVE HIGHLAND AVE Zone D MELROSE AVE BOSTON RD FIFTHAVE SYLVANIA LN OAKDALE DR A t l a n t i c Evacuation Route PROSPECT AVE GARFIELD AVE GLENMERE AVE FAIRFIELD WAY R ALBANY RD Flood Hazard Areas are a composite of Effective FIRMs (06/20/2018) and D

C COTTAGE PL Avon-by-the-Sea D Preliminary FIRMs (01/30/2015) E BERRY AVE O c e a n D O O A W L R F IF P Borough GARFIELD LN

P L C RILEY RD L N HAGERMAN WAY O SOUTH CONCOURSE WATERVIEW CT P T IN FUL LINCOLN AVE E R W D BA O CHELOR Wall N PL MARINE PL O LS A IL ID D HAMPTON CT V TREYMONT DR E CLIFWOOD PL H L SOUTH STATION AVE D EACH R Y Township RD R B D S LINCOLN LN

This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. BuildingClassification Industrial Com m e rcial Apartme nt R e sidential(fou fa r m iliesor less) Monmouth 0 350 700 County Farm Vacant Civic/PubExem lic(Tax pt) Unclassified NEPTUNE CITY Fee t FLOOD VULNERABILITY ParcelClassification ± Neptune Industrial Com m e rcial Apartme nt R e sidential(fou fa r m iliesor less) Source: © 2014 Esri; Monmouth County; MONMOUTHCOUNTY HAZAR MITIGATION D PLAN City NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Farm Vacant Civic/PubExem lic(Tax pt) Unclassified OpenSpace Projection: New Jersey State Plane, NAD 1983

W

WAYSIDE RD A DAVIS AVE K OXFORD WAY E F TENTH AV I E NEW GATE LN L W D A ALBERTA AV L R N D U T 9TH AV

A HAMILTON AV V FORTUNATO PL

STANLEY AV

LAKEVIEW AV TAYLOR AV TAYLOR #"33 EIGHTH AV

O OXFORD DR AK DR

EMERSON PLEMERSON LAREINE AVE 2 V LK A N NEPTUNE AV HTO BRIG FILLMORE AV

Bradley PL FIFTH AV D

O Beach

O PROSPECT ST

W HAWTHORNE AVE

N

E

E

R G GROVE PL OLIVER DR LAWRENCE DR ROLAND PL WESTWOOD PL 17 LK LOCUST AV

MORRIS AVE

SHARK PL

RIVERDALE AV BENNETT AV

WICKAPECKO DR

TFH WAY ROBBINS RD FOURTH AVE THIRD AVE

RIVERVIEW AV 5 SMOCK AVE LK DURAND RD PARK AVE HILLSIDE AVE

E

V AVONDALE AVE A

K WILSON RD SUMMIT AVE SECOND AVE

C

BRIGHTON AVE O MAY PL

H C Bradley S E VERGR NEPTUNE AVE EEN AVE # LAUREL AVE "18 WOODLAND AVE RIDGE PL Beach

R # Borough D "35 E BENNET RD POPLAR PL ID 40A S TUCKER DR R K L L IL H D RIDGE TERR E

D

PITTENGER PL SI

R

MCDERMOTT RD E FOREST AVE

V I MONMOUTH AVE

R

CARTON AVE

S ELY RD IV MIDWOOD ST # ANS RD "71 E V A WEST WALL PL N A PACIFIC AVE MERRIT PL M BURLINGTON AVE WALKER RD PI L

MORRISEY RD HILLSIDE RD S WALL ST

ELIZABETH TERR H

O

L

L BRADLEY BLVD Y MCLELLAND PL O S V AUDREY T FIELD ST LAKESIDE AVE E PL R R L D MOORE RD O BRADLEY ST K WINDSOR AVE O POTENTIAL SEA LEVEL RISE R K A Wesley Lake D P WINDSOR TERR R Neptune WEST END AVE

INUNDATION AREAS WILSON AVE LAIRD AVE Township VICTOR PL HOME ST 1 Foot1 Sea Level Rise (2050) HELEN TERR MYRON AVE S NORWOOD AVE h a 3 Foot3 Sea Level Rise (2100) ELMWOOD DR RIVERVIEW CT r COUSE RD k GREEN ST SMOCK ST V BEVERLY WAY A R

CLAYTON AVE S L NORWOOD LN

Evacua tionRou te U L i

E v RI M V Y e E R BELL PL R V M r I D EW SpatialRe solutionand Accuracy: This ma depicts p inland extent I T AV R E a ndrelative depth of inu ndationofandfor SLR 3ft. 1ft. using NOAA D SLRdatawith avertical datum ofMe a nHigh eHigh r Wa (MHHW). ter FAIRVIEW PL STANTON ST LAKEWOOD AVE The se inu ndation rang e s are consistent with the R u tge rs LORRAINE DR NNP STEINER AVE WOODLAND LN University’sNew Jerse Clima y Adaptation te Alliance Science and R D HILLCREST AVE TechnicalAdvisory Pane Re l port(STAPRe The port). STAP Re port T S

E e stima tesNew Jerse will y experience SLR be tweeandfe n 1.0 1.8 e t R

O priorreg2050, to a rdlessof fu turegre e nh ou sega sem issions.The F OAK TERR datadisplayed on this ma represe p ntscurrent conditions and doe s WOODMERE AVE notconsider na turalprocesse ssu chas erosion or ma rshmigration HIGHLAND AVE MELROSE AVE BOSTON RD FIFTHAVE SYLVANIA LN tha t willtha t be affe by ctedfu turese alevel rise Due . coato rsespatial OAKDALE DR resolution,the use rsh ou ldnot interpret the layers as precise A t l a n t i c inu ndationextents. PROSPECT AVE GARFIELD AVE GLENMERE AVE FAIRFIELD WAY R ALBANY RD D

C COTTAGE PL Avon-by-the-Sea D E BERRY AVE O c e a n D O O A W L R F IF P Borough GARFIELD LN

P L C RILEY RD L N HAGERMAN WAY O SOUTH CONCOURSE WATERVIEW CT P T IN FUL LINCOLN AVE E R W D BA O CHELOR Wall N PL MARINE PL O LS A IL ID D HAMPTON CT V TREYMONT DR E CLIFWOOD PL H L SOUTH STATION AVE D EACH R Y Township RD R B D S LINCOLN LN

Thisma was p developed using thestatewide10-04-18 com positeof parcel datapub lish ebythe d NJOIT-OGIS. The Stateof New Jerse ma y ke sgre effort a t provideto se cureaccurate, , and com pletedata and me tadata.However, portions of thedata and me tadatama be y incorre or notcurre ct Any errors nt. or om issionssh oube ld re portedfor investiga tionOGIS.to MEETING NOTES

Topic: Neptune City- Monmouth County HMP Meeting

Date: May 6, 2019

Time: 1:00 PM- 2:00 PM

Location: Neptune City Borough Hall 106 W Sylvania Ave.

Attendees: Keith Mitchell, Police Captain / OEM Deputy Coordinator

Bryan Russell, Borough Administrator

Matt Shafai, Engineer

Brittany Ashman, MB Planner

Drafted by: Paige Kaspar

______

Introductions (Brittany):

• What is Hazard Mitigation? • Matching actions with Goals • New Hazards • HMP Pamphlet • Funding

2015 Mitigation Actions:

• Community Action 36_01 - Drainage Improvements – Completed o Added additional drainage pipes on Windsor Ct. rd o Route 35/3 Ave – critical drainage issues, but too expensive . DOT looked at the intersection in the 80s, but the amount of infrastructure that would need to be moved made the cost prohibitive . New action? • Community Action 36_02 - Emergency Generators to Borough Hall, the Fire Station, and the School – Completed o Town Hall, Police, East End Pumping Station o Need school • Community Action 36_03 - Storm Surge Mitigation/Floodproofing – Ongoing • Community Action 36_04 - Building Structure for OEM Equipment – Ongoing • Community Action 36_05 - Building Improvements to Key Critical Buildings – Ongoing o Men’s locker room facility only has one shower o Handicap accessibility o School generators • Community Action 36_06 - Drainage Study – Ongoing o Route 35 Needs study • Community Action 36_07 - Elevation and/or Acquisition of Flood-prone Residential Structures –Ongoing

2020 Mitigation Actions (NEW):

• Target Hardening o Surveillance  DPW o Borough Hall o Fire Station o Lard Ave Pumping Station o Alarm systems o Camera systems • Shower facilities o Female/Male • Elevating pumps/pump stations

Successes

• Shared service agreement with Neptune Twp. for debris removal (capability)

Appendix Vol I.37 Neptune Township

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Neptune Township CRS Class 6

NFIP Statistics 7%

761 Polices In-force

396 Total Losses

$22,901,625 Total Payments 19 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 2 RL Properties

46 RL - Total Losses 22 Total Mitigation $2,242,882 RL - Total Paid Actions

0 Number of SRL Properties 2

Number Mitigated SRL 0 Properties Education and Awareness Programs

0 SRL - Total Losses 12

$0 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 0

50 Critical Facilities Local Plans and Regulations

1 Critical Infrastructure 8

1,836 Historic & Cultural Resources Natural Systems Protection

23 SV Population At Risk (2017) 341 Population at Risk (2017) Neptune, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

37_01 Purchase and Install a Create elevated platform for new emergency generator Structure and Flood, Nor'easter, Neptune Township $18,500.00 Completed Generator at North Island to service pump station. Infrastructure Hurricane and Tropical Engineering Pump Station Project Storm, Storm Surge Department/Neptun e Sewer Department

37_02 De-snag and Desilt Wesley Remove/desilt the lake. Maintenance/Resp Natural Systems Flood, Hurricane and Medium Township Municipal budget $1,500,000.00 5 + years New Lake onse/Recovery Protection Tropical Storm, Storm Engineering Surge

37_03 Construct an Elevated Construct or elevate a structural or earth berm bulkhead Mitigation - Risk Natural Systems Flood, Hurricane and High Neptune Township FEMA HMA, The $2,500,000.00 2 years New Bulkhead and a Living around the lake along with a living shoreline. Reduction Protection Tropical Storm, Storm Engineering Nature Conservancy Shoreline Around Wesley Lake Surge Department; (TNC) Neptune Township

37_04 Construct a Living Shoreline Construct a living shoreline along the Shark River, located Mitigation - Natural Systems Flood, Nor'easter, Medium Neptune Township FEMA HMA, The $6,000,000.00 1 year Ongoing along Shark River in the Shark River Hills neighborhood of the Township, Continuity of Protection Hurricane and Tropical Engineering Nature Conservancy connecting into the bordering town of Neptune City. Functional Use Storm, Storm Surge Department (TNC)

37_05 De-snag and Desilt Fletcher Remove/desilt the lake. Maintenance/Resp Natural Systems Flood, Nor'easter, Medium Township Municipal budget $1,500,000.00 5 + years New Lake onse/Recovery Protection Hurricane and Tropical Engineering Storm

37_06 Construct an Elevated Construct or elevate a structural or earth berm bulkhead Mitigation - Risk Natural Systems Flood, Nor'easter, High Neptune Township FEMA HMA, The $2,500,000.00 2 years New Bulkhead and a Living around the lake along with a living shoreline. Reduction Protection Hurricane and Tropical Engineering Nature Conservancy Shoreline Around Fletcher Lake Storm, Storm Surge Department; (TNC) Neptune Township

37_07 Establish and Install Warning Install flood gauges with warning lights in rivers and lakes Maintenance/Resp Structure and Flood, Hurricane and Low Engineering and Municipal budget $700,000.00 3 years Ongoing System and Flood Gauges in or near flood-prone areas, specifically along Shark onse/Recovery Infrastructure Tropical Storm, Storm Planning/OEM River, Alberta Lake, and Fletcher Lake. Connect the flood Project Surge gauges to automatically communicate warnings.

37_08 Acquire and Demolish or Identify and target properties of willing sellers in Special Mitigation - Risk Structure and Flood, Nor'easter, High Neptune Township FEMA HMA $1,200,000.00 3 years Ongoing Relocate Buildings and Flood Hazard Areas or flood-prone areas, especially Reduction Infrastructure Hurricane and Tropical Administration Infrastructure in flood-prone Repetitive Loss and Severe Repetitive Loss properties, Project Storm, Storm Surge areas, with a focus on and obtain appraisals and funding for acquisition. Upon Repetitive Loss (RL) and acquisition, maintain as dedicated open space. Severe Repetitive Loss (SRL) properties

Wednesday, March 4, 2020 Page 1 Neptune, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 37_09 De-snag and Desilt Hollow Removal of dense overgrown vegetation, dead fallen Maintenance/Resp Natural Systems Flood, Nor'easter, Low Township Municipal budget $4,000,000.00 5 + years New Brook trees, silt, and sediment from Hallow Brook onse/Recovery Protection Hurricane and Tropical Engineering, DPW Storm

37_10 Target Harden Critical Install and improve surveillance equipment and CCTV, Maintenance/Resp Structure and Terrorism Medium Township Homeland Security 1 year New Facilities by Installing barriers, bulletproof glass, access control, window film on onse/Recovery Infrastructure grants Surveillance Cameras, entrance-facing access points, and surveillance footprints Project Barriers, Window Film, an on the ground for Township schools and municipal Access Control System, and/or buildings. Bulletproof Glass

37_11 Elevate 23 Flood-prone Elevate 23 flood-prone residential properties, especially Mitigation - Risk Structure and Flood, Hurricane and High Homeowners, FEMA HMA $57,500.00 1 year Ongoing Properties, with a focus on Repetitive Loss and Severe Repetitive Loss properties. Reduction Infrastructure Tropical Storm, Storm Neptune Township Repetitive Loss and Severe Project Surge Engineering Repetitive Loss Properties Department,

37_12 Construct a Living Shoreline Construct a living shoreline along the Seaview Island. Mitigation - Natural Systems Wave Action, Nor'easter, Medium Township FEMA HMA, The $3,000,000.00 5 + years New along Seaview Island Continuity of Protection Hurricane and Tropical Engineering, DPW Nature Conservancy Functional Use Storm, Storm Surge (TNC)

37_13 Purchase and Install Generators for stormwater pumps and at the Township Maintenance/Resp Structure and All Hazards Low Township FEMA HMA $100,000.00 2 years New Generators for Critical EOC center. onse/Recovery Infrastructure Infrastructure Project

37_14 De-snag and Desilt Alberta Remove/desilt the lake. Maintenance/Resp Structure and Flood, Nor'easter, Medium Neptune Township Municipal budget $1,500,000.00 5 + years Ongoing Lake onse/Recovery Infrastructure Hurricane and Tropical Engineering Project Storm, Storm Surge Department; Neptune Township

37_15 Reconstruct Deteriorating Reconstruct deteriorating bulkheads, extend drainage Mitigation - Structure and Flood, Nor'easter, Medium Neptune Township FEMA HMA $2,500,000.00 5 + years Ongoing Bulkheads on S. Riverside pipes, and retrofit storm drains with Tideflex valves. Continuity of Infrastructure Hurricane and Tropical Engineering Drive and Retrofit Stormwater Functional Use Project Storm, Storm Surge Department, Infrastructure Neptune Township

37_16 Retrofit Pump stations with Retrofit existing pump stations in flood zones with Mitigation - Risk Structure and Flood, Nor'easter, Medium Neptune Township FEMA HMA $100,000.00 2 years Ongoing Watertight Doors and/or watertight doors and/or windows. Reduction Infrastructure Hurricane and Tropical Engineering Windows Project Storm, Storm Surge Department/Neptun e Sewer Department

Wednesday, March 4, 2020 Page 2 Neptune, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 37_17 De-snag and Desilt the Shark Removal of dense overgrown vegetation, dead fallen Maintenance/Resp Natural Systems Flood, Hurricane and Low Neptune Township, Municipal budget $4,000,000.00 5 + years Ongoing River Tributary, Jumping trees, silt, and sediment from the Shark River Tributary, onse/Recovery Protection Tropical Storm, Storm Neptune City, Wall, Brook, and Musquash Brook Jumping Brook, and Musquash Brook. Surge Belmar, and NJDEP

37_18 Create a Permanent Confined Identify and target properties that have the Maintenance/Resp Structure and Flood, Hurricane and Low Engineering and Municipal budget $350,000.00 2 years Ongoing Disposal Facilities (CDF) and characteristics that can be used for a Confined Disposal onse/Recovery Infrastructure Tropical Storm, Storm Planning Structural Earthen Berm Facility (CDF) and construct an Earthen Berms out of Project Surge materials and form a stable slope. Berm to be stabilized with seed.

37_19 Desilt and Dredge Shark River Dredge or pump siltation from entire Shark River Basin to Maintenance/Resp Structure and Flood, Hurricane and Medium Neptune Township, Municipal budget $10,000,000.00 1 year Ongoing Confined Disposal Facility (CDF). onse/Recovery Infrastructure Tropical Storm, Storm Neptune City, Project Surge NJDEP, Wall, Belmar, NJDOT

37_20 Create Hazard Overlay Zones Work with GIS Consultant and in-house staff to overlay Administrative Education and Flood, Nor'easter, Low Neptune Township Municipal budget $12,000.00 1 year Ongoing and Update ArcGIS Online Special Flood Hazard Zones on Township Maps. Awareness Hurricane and Tropical Engineering Distribute as handouts to residents at Neptune Day, at Programs Storm, Storm Surge Department/GIS Township counters, and to Homeowners Associations in Consultant Special Flood Hazard Zones. Update ArcGIS online and publish on Township website to increase hazard awareness and evacuation routes.

37_21 Update ArcGIS Online Update ArcGIS online and publish on Township website Administrative Education and Flood, Hurricane and High Neptune Township FEMA HMA $2,000.00 1 year Withdrawn to increase hazard awareness and evacuation routes. Awareness Tropical Storm, Storm Engineering Programs Surge Department

37_22 Purchase Stormwater Pumps Purchase stormwater pumps and appurtenances to Maintenance/Resp Structure and Flood, Nor'easter, Low Neptune Township Municipal budget $100,000.00 1 year New and Appurtenances reduce flood risk in the special flood hazard area. onse/Recovery Infrastructure Hurricane and Tropical Engineering Project Storm, Storm Surge Department, DPW

Wednesday, March 4, 2020 Page 3 Monmouth County Mitigation Action Worksheets

Community Action Number: 37_01 Neptune, Township of Describing the Action Action Name: Purchase and Install a Generator at North Island Pump Station Action Category: Action Type: Structure and Infrastructure Project HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Create elevated platform for new emergency generator to service pump station.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 3, 7 Risk Reduction: Superstorm Sandy highlighted pump stations that are in need of power back up at an elevation that will not avoid flooding. The existing at-grade emergency generator was flooded beyond repair as a result of storm surge during Sandy. Technical: Technically feasible. Need planning and local building permit. Political: Neptune Township Sewer Department and Township Committee in support of project. Legal: No apparent legal issues; Township owns property. Environmental: No NJDEP permitting required. Social: This action does not adversely affect any particular neighborhood, social group or organization. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer action. Local Champion: Neptune Township, Neptune Township Sewer Department

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviating failure and sewer back- ups due to flooding. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $18,500.00 Priority: Local Planning Mechanism: Local Building code Responsible Party: Neptune Township Engineering Department/Neptune Sewer Department Likely Funding Source(s): Timeline: Action Status: Completed Notes: HMGP grant of $85k for Generator Improvements. Additionally, the Township was awarded FEMA 406 Public Assistance funding for repairs to the North Island Pump Station post-Sandy. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_02 Neptune, Township of Describing the Action Action Name: De-snag and Desilt Wesley Lake Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Remove/desilt the lake.

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near Wesley Lake. Both private homes and public infrastructure were impacted. The removal of silt and sediment will enable the lake to hold more water. Technical: Technically feasible. Need planning and permitting. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: Neptune Township, Wesley Lake Commission, Asbury Park

Other Community Objectives: Adds capacity, reduces flooding, and increases water quality. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,500,000.00 Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Engineering Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: New Notes: Township's top priority; ranked in order from highest priority (this action) to lowest priority. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_03 Neptune, Township of Describing the Action Action Name: Construct an Elevated Bulkhead and a Living Shoreline Around Wesley Lake Action Category: Mitigation - Risk Reduction Action Type: Natural Systems Protection HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Construct or elevate a structural or earth berm bulkhead around the lake along with a living shoreline.

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near Wesley Lake. Both private homes and public infrastructure were impacted. Superstorm Sandy highlighted gaps in the existing bulkhead system and its associated flood impacts. The areas that need bulkheading reconstruction are areas where there are no existing bulkheads, or the elevations are too low. Backflow of tidewaters into the drainage system at the outfalls creates flooding when the system is full of tidewater instead of runoff. Technical: Technically feasible. Political: No adverse issues anticipated Legal: No apparent legal issue. Environmental: NJDEP permitting required. Social: This action would serve to protect a neighborhood that was severely damaged by Sandy. It would not adversely affect them, it would further protect them. Administrative Capability: Township can administer action but will need consultants for permitting and plans. Local Champion: Neptune Township, Neptune Township Sewer Department, Wesley Lake Commission, Asbury Park, homeowners

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviate flooding and evacuations. STAPLEE Evaluation: 12

Implementing the Action Cost Estimate: $2,500,000.00 Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Neptune Township Engineering Department; Neptune Township Committee Likely Funding Source(s): FEMA HMA, The Nature Conservancy (TNC) Timeline: 2 years Action Status: New Notes: The Township was awarded HMGP funding of $430,176 for outfall valve and bulkhead installation project. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_04 Neptune, Township of Describing the Action Action Name: Construct a Living Shoreline along Shark River Action Category: Mitigation - Continuity of Functional Use Action Type: Natural Systems Protection HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Construct a living shoreline along the Shark River, located in the Shark River Hills neighborhood of the Township, connecting into the bordering town of Neptune City. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: Neptune Township is a coastal community with a substantial amount of land within the mapped flood and storm surge hazard areas. During Superstorm Sandy, significant storm surge flooded areas near the Shark River, Fletcher Lake, Wesley Lake, and Atlantic Ocean. Both private homes and public infrastructure were impacted. Sea Level Rise and climate change will contribute to more frequent and severe flooding and surge events over a larger area. Climate change will contribute to more frequent and severe weather events. Technical: Technically feasible. Conceptual plan completed for grants, properties owned by the Township and bordering municipalities. Political: Neptune Township, Neptune City, and Belmar support the living shorelines along portions of their boundaries. Legal: Proposed properties for the living shoreline are owned by the Township. Environmental: May require NJDEP permitting Social: This action does not adversely affect any particular neighborhood, social group or organization. The project would be completely on publicly-owned property. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer action with help from consultants. Local Champion: Planning, Emergency Management, Harbor Commission, Governing Bodies, neighborhood groups in favor of project

Other Community Objectives: This action furthers environmental quality, furthers the use of open space preservation, helps support fish habitat. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $6,000,000.00 Priority: Medium Local Planning Mechanism: Plans and Specifications Responsible Party: Neptune Township Engineering Department Likely Funding Source(s): FEMA HMA, The Nature Conservancy (TNC) Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action: first phase (design) is complete. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_05 Neptune, Township of Describing the Action Action Name: De-snag and Desilt Fletcher Lake Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Remove/desilt the lake.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 2, 3, 5, 6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near Fletcher Lake. Both private homes and public infrastructure were impacted. The removal of silt and sediment will enable the lake to hold more water. Technical: Technically feasible. Need planning and permitting. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated. Social: Does not adversely affect any particular social group. Administrative Capability: Borough has sufficient capacity and experience to administer this action Local Champion: Fletcher Lake Commission, HOA, Bradley Beach

Other Community Objectives: Adds capacity, reduces flooding, and increases water quality. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,500,000.00 Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Engineering Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 37_06 Neptune, Township of Describing the Action Action Name: Construct an Elevated Bulkhead and a Living Shoreline Around Fletcher Lake Action Category: Mitigation - Risk Reduction Action Type: Natural Systems Protection HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Construct or elevate a structural or earth berm bulkhead around the lake along with a living shoreline.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near Fletcher Lake. Both private homes and public infrastructure were impacted. Superstorm Sandy highlighted gaps in the existing bulkhead system and its associated flood impacts. The areas that need bulkheading reconstruction are areas where there are no existing bulkheads, or the elevations are too low. Backflow of tidewaters into the drainage system at the outfalls creates flooding when the system is full of tidewater instead of runoff. Technical: Technically feasible. Political: Neptune Township Committee, TNHA, OEM, Ocean Grove Homeowners Association. Legal: No apparent legal issue. Environmental: NJDEP permitting required. Social: This action would serve to protect a neighborhood that was severely damaged by Sandy. It would not adversely affect them, it would further protect them. Administrative Capability: Township can administer action but will need consultants for permitting and plans. Local Champion: Neptune Township, Neptune Township Sewer Department, HOA, Fletcher Lake Commission, Bradley Beach

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviate flooding and evacuations. STAPLEE Evaluation: 12

Implementing the Action Cost Estimate: $2,500,000.00 Priority: High Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Neptune Township Engineering Department; Neptune Township Committee Likely Funding Source(s): FEMA HMA, The Nature Conservancy (TNC) Timeline: 2 years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 37_07 Neptune, Township of Describing the Action Action Name: Establish and Install Warning System and Flood Gauges Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Install flood gauges with warning lights in rivers and lakes in or near flood-prone areas, specifically along Shark River, Alberta Lake, and Fletcher Lake. Connect the flood gauges to automatically communicate warnings. Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 1, 2, 3, 4, 7, 8 Risk Reduction: Residents living and working in flood hazard areas do not always have enough time to prepare and evacuate flood- prone areas. This warning system would increase public preparedness. Technical: Technically feasible. Township would have to locate lake or tide gauges on Township-owned property. Political: Neptune Township Committee Adjacent property owners Legal: All work would have to be located on Township owned property. AM station would have to be obtained. Environmental: Local permitting required for post with warning light. Social: Proposed action will help to warn certain flood prone neighborhoods. These would be strategically be located in 4 separate sectors of the Township. Administrative Capability: Township can administer would have to prepare bids and specs for radio station and proposed gauges with lights and warning system tied to radio station. Local Champion: Neptune Township, Homeowners Associations, TNHA, OEM

Other Community Objectives: Provides advanced warning for people and business to prepare or evacuate to higher ground prior to an event. Minimizes use of Police and OEM personal for detours and evacuations. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $700,000.00 Priority: Low Local Planning Mechanism: Plans, specifications, technology and infrastructure Responsible Party: Engineering and Planning/OEM Likely Funding Source(s): Municipal budget Timeline: 3 years Action Status: Ongoing Notes: Ongoing 2015 action; the Township is searching for funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_08 Neptune, Township of Describing the Action Action Name: Acquire and Demolish or Relocate Buildings and Infrastructure in flood-prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Property Acquisition and Structure Demolition Action Description: Identify and target properties of willing sellers in Special Flood Hazard Areas or flood-prone areas, especially Repetitive Loss and Severe Repetitive Loss properties, and obtain appraisals and funding for acquisition. Upon acquisition, maintain as dedicated open space. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near the Shark River, Fletcher Lake, Wesley Lake, Lake Alberta, and Atlantic Ocean. Bath private homes and public infrastructure were impacted. Some structures need to be elevated; others in more low-lying areas would seem to be good candidates for acquisition (particularly: Shark River Hills, South Riverside Drive, and Shark River Memorial Park). Sea level rise and climate change will contribute to more frequent and severe flooding and surge events over a larger area. Climate change will contribute to more frequent and severe weather events. Technical: Technically feasible. Need appraisals and funding. Political: Neptune Township Committee, willing property owners. Legal: Appraisals have to be obtained and negotiations are needed with property owners. Environmental: Depending on prior use, may have some environmental issues to remediate. Social: This action would serve to protect a neighborhood that was severely damaged by Sandy. It would serve to have properties preserved and not be developed in the future as some parcels have approved subdivisions on them. Administrative Capability: Township can administer action but will need appraisals for properties Local Champion: Neptune Township, Willing Property Owners

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviate flooding and evacuations. STAPLEE Evaluation: 10

Implementing the Action Cost Estimate: $1,200,000.00 Priority: High Local Planning Mechanism: Appraisals and Attorneys Responsible Party: Neptune Township Administration Likely Funding Source(s): FEMA HMA Timeline: 3 years Action Status: Ongoing Notes: Ongoing 2015 action; Green Acres for funding and Monmouth County Funding: closed by end of May 2019. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_09 Neptune, Township of Describing the Action Action Name: De-snag and Desilt Hollow Brook Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Removal of dense overgrown vegetation, dead fallen trees, silt, and sediment from Hallow Brook

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm Goals: 2, 3,5,6 Risk Reduction: Debris and siltation in Hallow Brook obstruct flood flows. Limited capacity causes evacuations, road closures, property damage. During Superstorm Sandy, areas near the Hallow Brook were flooded. Both private homes and public infrastructure were severely impacted. Technical: Technically Feasible. Political: No adverse political ramifications are expected Legal: No legal impediments anticipated. Environmental: NJDEP, Army Corp of Engineers, and Freehold Soil Conservation District may require permits. Social: Does not adversely affect any particular social group. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Neptune Township and HOA

Other Community Objectives: Adds capacity, reduces flooding, and increases water quality. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $4,000,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Engineering, DPW Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 37_10 Neptune, Township of Describing the Action Action Name: Target Harden Critical Facilities by Installing Surveillance Cameras, Barriers, Window Film, an Access Control System, and/or Bulletproof Glass Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other Action Description: Install and improve surveillance equipment and CCTV, barriers, bulletproof glass, access control, window film on entrance-facing access points, and surveillance footprints on the ground for Township schools and municipal buildings. Evaluating the Action Hazard(s) Addressed: Terrorism Goals: 1, 2, 3, 4, 5, 7 Risk Reduction: Schools are the most vulnerable for a terrorist attack. Technical: Technically feasible. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated; schools are owned by the Township. Environmental: No adverse environmental impact anticipated Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it supports local services during emergencies. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: Police, OEM, Schools

Other Community Objectives: STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Likely Funding Source(s): Homeland Security grants Timeline: 1 year Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 37_11 Neptune, Township of Describing the Action Action Name: Elevate 23 Flood-prone Properties, with a focus on Repetitive Loss and Severe Repetitive Loss Properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Structure Elevation Action Description: Elevate 23 flood-prone residential properties, especially Repetitive Loss and Severe Repetitive Loss properties.

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 6 Risk Reduction: Several residential structures throughout the community are prone to flooding, with their main floor elevations below current BFEs. Sea Level Rise and climate change will contribute to more frequent and severe flooding and surge events. Technical: Technically feasible. Need planning and permitting. Political: Neptune Township Committee, Shark River Hills Homeowners Association, OEM Legal: While the municipality does not own the structures in questions, we fully support the homeowners in moving forward. Environmental: No environmental impacts are anticipated as a result of elevating the home. Social: No particular social group in our community is likely to be disproportionately impacted by this project. This action would serve to protect a neighborhood that was severely damaged by Sandy. It would not adversely affect them, it would further protect them. Administrative Capability: Township can administer action but will need cooperation from affected homeowners. Local Champion: Affected homeowners and Neptune Township

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviate failure and sewer back ups. STAPLEE Evaluation: 12

Implementing the Action Cost Estimate: $57,500.00 Priority: High Local Planning Mechanism: Local building code and permits Responsible Party: Homeowners, Neptune Township Engineering Department, Neptune Township Administration Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Ongoing Notes: Ongoing action; the Township deems this action necessary and is searching for potential funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_12 Neptune, Township of Describing the Action Action Name: Construct a Living Shoreline along Seaview Island Action Category: Mitigation - Continuity of Functional Use Action Type: Natural Systems Protection HMA Eligible Activity: Localized Flood Risk Reduction Projects Action Description: Construct a living shoreline along the Seaview Island.

Evaluating the Action Hazard(s) Addressed: Wave Action, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: Neptune Township is a coastal community with a substantial amount of land within the mapped flood and storm surge hazard areas. Sea Level Rise and climate change will contribute to more frequent and severe flooding and surge events over a larger area. Climate change will contribute to more frequent and severe weather events. Seaview Island is surrounded completely by Shark River; a living shoreline will help absorb rising waters and provide a natural buffer for the island. Technical: Technically Feasible. Conceptual plan completed for grants Political: Neptune Township, Neptune City, and Belmar support the living shorelines along portions of their boundaries. Legal: Proposed properties for the living shoreline are owned by the Township. Environmental: May require NJDEP permitting. ACOE permitting Social: This action does not adversely affect any particular neighborhood, social group or organization. The project would be completely on publicly-owned property. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer this action with the help from consultants. Local Champion: Planning, Emergency Management, Homeowners Association, Governing Bodies, neighborhood groups in favor of project. Other Community Objectives: This action furthers environmental quality, furthers the use of open space preservation, and helps support fish habitat. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $3,000,000.00 Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Engineering, DPW Likely Funding Source(s): FEMA HMA, The Nature Conservancy (TNC) Timeline: 5 + years Action Status: New Notes: Monmouth County Mitigation Action Worksheets

Community Action Number: 37_13 Neptune, Township of Describing the Action Action Name: Purchase and Install Generators for Critical Infrastructure Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Generators Action Description: Generators for stormwater pumps and at the Township EOC center.

Evaluating the Action Hazard(s) Addressed: All Hazards Goals: 1, 2, 3, 7 Risk Reduction: Stormwater pumps and the EOC center need generators in order to keep functioning during a severe storm. If either fail, human life and property will be at risk. Technical: Technically feasible, area around building exists. Political: No adverse political ramifications are expected. Legal: No legal impediments anticipated. Environmental: No adverse environmental impact anticipated, but may require construction permits. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it supports local services during emergencies. Administrative Capability: Township has sufficient capacity and experience to administer this action. Local Champion: EOC, OEM, Public Works

Other Community Objectives: Keeps Township critical facilities operational during an event. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $100,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Township Likely Funding Source(s): FEMA HMA Timeline: 2 years Action Status: New Notes: Shark River Municipal Marina Building was awarded a HMGP grant of $83,113.00 for Generator Improvements Monmouth County Mitigation Action Worksheets

Community Action Number: 37_14 Neptune, Township of Describing the Action Action Name: De-snag and Desilt Alberta Lake Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Remove/desilt the lake.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near Alberta Lake. Both private homes and public infrastructure were impacted. The removal of silt and sediment will enable the lake to hold more water. Technical: Technically feasible. Need planning and permitting. Political: Neptune Township Committee, OEM Legal: No apparent legal issues; Township owns property. Environmental: NJDEP and possibly Freehold Soil Conservation District may require permits. Social: This action would serve to protect a neighborhood that is evacuated during large storm events. It would further protect them and reduce evacuation costs and the displacement of residents. Administrative Capability: Township can administer action but will need consultants for permitting and plans. Local Champion: Neptune Township, Neptune Township Sewer Department, TNHA

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviate flooding and evacuations. It also improves the ecosystem. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,500,000.00 Priority: Medium Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Neptune Township Engineering Department; Neptune Township Committee Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; the Township is still interested in this action and once funds are available, will implement. The Alberta Basin was awarded HMGP funding ($683,055) Monmouth County Mitigation Action Worksheets

Community Action Number: 37_15 Neptune, Township of Describing the Action Action Name: Reconstruct Deteriorating Bulkheads on S. Riverside Drive and Retrofit Stormwater Infrastructure Action Category: Mitigation - Continuity of Functional Use Action Type: Structure and Infrastructure Project HMA Eligible Activity: Infrastructure Retrofit Action Description: Reconstruct deteriorating bulkheads, extend drainage pipes, and retrofit storm drains with Tideflex valves.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 2,3,5,6 Risk Reduction: During Superstorm Sandy significant storm surge flooded areas near the Shark River. Superstorm Sandy highlighted gaps in the existing bulkhead system and its associated flood impacts. The areas that need bulkheading reconstruction are areas where there are no existing bulkheads, or the elevations are too low. Backflow of tidewaters into the drainage system at the outfalls creates flooding when the system is full of tidewater instead of runoff. Technical: Technically feasible. Need planning and permitting. Political: Neptune Township Committee, Shark River Hills Homeowners Association, OEM. Legal: No apparent legal issues; Township owns property. Environmental: NJDEP, Army Corp of Engineers, and possibility the Freehold Soil Conservation District may require permits. Social: This action would serve to protect a neighborhood that was severely damaged by Sandy. It would not adversely affect them it would further protect them. Administrative Capability: Township can administer action. Local Champion: Neptune Township, Neptune Township DPW, HOA

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $2,500,000.00 Priority: Medium Local Planning Mechanism: Plans and specification for bid required Responsible Party: Neptune Township Engineering Department, Neptune Township Committee Likely Funding Source(s): FEMA HMA Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; the Township is still interested in bulkhead reconstruction and will research potential funding opportunities. 25 Neptune Blvd was awarded HMGP funding for Outfall Valve and Bulkhead Installation. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_16 Neptune, Township of Describing the Action Action Name: Retrofit Pump stations with Watertight Doors and/or Windows Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Non-structural Retrofitting of Existing Buildings and Facilities Action Description: Retrofit existing pump stations in flood zones with watertight doors and/or windows.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 3, 7 Risk Reduction: Superstorm Sandy highlighted pump stations that are in need of water-tight doors. When water enters the pump station, the controls and the pumps themselves get damaged or destroyed and service is interrupted. Technical: Technically feasible. Need plans and local building permit. Political: Neptune Township Sewer Department and Township Committee in support of project. Legal: Properties where pump stations are located are owned by the Township of Neptune, no legal issue. Environmental: No NJDEP permitting required. Social: This action does not adversely affect any particular neighborhood, social group or organization. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer action. Local Champion: Neptune Township, Neptune Township Sewer Department

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by alleviate failure and sewer backups. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $100,000.00 Priority: Medium Local Planning Mechanism: Local Building Code Responsible Party: Neptune Township Engineering Department/Neptune Sewer Department Likely Funding Source(s): FEMA HMA Timeline: 2 years Action Status: Ongoing Notes: Ongoing 2015 action; designed with dry pit submergible pumps so that even if the building floods, the pump system will still work. Electronics are elevated above the BFE and the building has been mitigated. This project is expensive. Additionally, the Township was awarded $450k of FEMA Funding 406 Public Assistance funding for repairs to the North Riverside Pump Station, North Island Pump Station, and the South Island Pump Station post-Sandy. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_17 Neptune, Township of Describing the Action Action Name: De-snag and Desilt the Shark River Tributary, Jumping Brook, and Musquash Brook Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Floodplain and Stream Restoration Action Description: Removal of dense overgrown vegetation, dead fallen trees, silt, and sediment from the Shark River Tributary, Jumping Brook, and Musquash Brook. Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: Debris and siltation in Shark River Tributary, Jumping Brook, and Musquash Brook obstructs flood flows. Limited capacity causes evacuations, rood closures, property damage. During Superstorm Sandy areas near the Shark River were flooded. Both private homes and public infrastructure were severely impacted. Technical: Technically feasible. Cooperation needed from NJDEP, adjacent property owners and adjoining municipalities. Political: Neptune Township Committee would have to jointly work on this project with Neptune City, Wall, Belmar and NJDEP. Legal: Legal issue is the ownership of the sections of the Shark River tributaries Environmental: No adverse environmental effects because project involves no structural changes and should clean and repair the watershed Social: Proposed action will help to protect flood prone neighborhoods in Neptune Township, Neptune City, Wall, & Belmar Administrative Capability: Township can administer with an outside consulting preparing plans and specifications for public bid of the improvements by a contractor. Local Champion: Neptune Township, Neptune City, Wall, Belmar, Friends of Belmar Harbor, Shark River Yacht Club, Homeowners Associations Other Community Objectives:

Provides not only additional capacity and flood protection but helps to reestablish the existing waterways, their natural habitat and its wildlife. Provide better cleansing of the river and improved stormwater management. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $4,000,000.00 Priority: Low Local Planning Mechanism: Plans and specifications Responsible Party: Neptune Township, Neptune City, Wall, Belmar, and NJDEP Likely Funding Source(s): Municipal budget Timeline: 5 + years Action Status: Ongoing Notes: Ongoing 2015 action; the Township is searching for funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_18 Neptune, Township of Describing the Action Action Name: Create a Permanent Confined Disposal Facilities (CDF) and Structural Earthen Berm Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Identify and target properties that have the characteristics that can be used for a Confined Disposal Facility (CDF) and construct an Earthen Berms out of materials and form a stable slope. Berm to be stabilized with seed. Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 2, 3, 5, 6 Risk Reduction: Debris and siltation in Shark River obstruct flood flows. Limited capacity causes evacuations, road closures, property damage. During Superstorm Sandy, areas near the Shark River were flooded. Both private homes and public infrastructure were severely impacted. Technical: Technically feasible. Township has property that could be utilized needs prelim. design. Political: Neptune Township Committee, adjacent homeowners' associations. Legal: Township owned property, CDF can be built. Environmental: NJDEP permitting will be required. Social: This action does not adversely affect any particular social group. Administrative Capability: Township can administer and prepare CDF plan with consultant permitting help. Local Champion: Neptune Township, Homeowners Association

Other Community Objectives: This project provides a permanent facility for dredging water bodies so continued maintenance dredging can take place. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $350,000.00 Priority: Low Local Planning Mechanism: Plans and specification Responsible Party: Engineering and Planning Likely Funding Source(s): Municipal budget Timeline: 2 years Action Status: Ongoing Notes: Ongoing 2015 action; the Township still prioritizes this project and is searching for funding. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_19 Neptune, Township of Describing the Action Action Name: Desilt and Dredge Shark River Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Dredge or pump siltation from entire Shark River Basin to Confined Disposal Facility (CDF).

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 3, 5, 6 Risk Reduction: Debris and siltation in Shark River obstruct flood flows. Limited capacity causes evacuations, road closures, property damage. During Superstorm Sandy, areas near the Shark River were flooded. Both private homes and public infrastructure were severely impacted. Technical: Technically feasible. Cooperation needed from NJDEP, ACOE and adjoining municipalities. Political: Neptune Township Committee would have to jointly work on this project with Neptune City, Belmar and NJDEP and NJDOT. Legal: Legal issue is the ownership of the Shark River Basin. Environmental: NJDEP, ACOE permitting required. Social: Proposed action will help to protect flood prone neighborhoods. Administrative Capability: State would have to administer in conjunction with Township. Would have to be a joint effort between Neptune, Neptune City, Belmar, Wall, NJDEP and NJDOT. Local Champion: Neptune Township, Neptune City, NJDOT, Belmar, Friends of Belmar Harbor, Shark River Yacht Club, Homeowners Associations. Other Community Objectives: Provides not only additional capacity and flood protection but helps to reestablish the marine environment through better cleansing of the river and improved Tidal flow. Also alleviates safety issues associated with the siltation of the river with regards to the booting and recreational communities (i.e. paddle boarders, jet skiers, etc.) who are at risk with no water and siltation of the river). STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $10,000,000.00 Priority: Medium Local Planning Mechanism: Plans and specifications Responsible Party: Neptune Township, Neptune City, NJDEP, Wall, Belmar, NJDOT Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: The Township was awarded $1,137,038.28 of FEMA Funding 406 Public Assistance to restore the Shark River Municipal Piers & Docks back to their pre-disaster design, function, and capacity. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_20 Neptune, Township of Describing the Action Action Name: Create Hazard Overlay Zones and Update ArcGIS Online Action Category: Administrative Action Type: Education and Awareness Programs HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Work with GIS Consultant and in-house staff to overlay Special Flood Hazard Zones on Township Maps. Distribute as handouts to residents at Neptune Day, at Township counters, and to Homeowners Associations in Special Flood Hazard Zones. Update ArcGIS online and publish on Township website to increase hazard awareness and evacuation routes. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 1, 2, 3, 4 Risk Reduction: Property owners and residents are not always aware of the zones that they live in, how they will be impacted by storms, or where their evacuation route is located. A lack of understanding the risks from hazards and what to do in an emergency can lead to a loss of life or property. Technical: Technically feasible with in house engineering department. Need coordination with in house staff and GIS consultant. Political: The project should have the support of the Governing body as its implementation would serve to aid the residents. Legal: No apparent legal issue. Environmental: No NJDEP permitting required. Social: This action does not adversely affect any particular neighborhood, social group or organization. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer action. Local Champion: Neptune Township Committee; Neptune Township OEM; Neighborhood Groups, Engineering Department, and DPW

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by furthering public education. Project also serves to help us satisfy some of our annual NJDEP Stormwater Permitting requirement. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $12,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Neptune Township Engineering Department/GIS Consultant Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Partially complete; haven't published information on the Township's website yet. Monmouth County Mitigation Action Worksheets

Community Action Number: 37_21 Neptune, Township of Describing the Action Action Name: Update ArcGIS Online Action Category: Administrative Action Type: Education and Awareness Programs HMA Eligible Activity: Miscellaneous/Other Action Description: Update ArcGIS online and publish on Township website to increase hazard awareness and evacuation routes.

Evaluating the Action Hazard(s) Addressed: Flood, Hurricane and Tropical Storm, Storm Surge Goals: 1, 2, 3, 4 Risk Reduction: Property owners and residents are not always aware of the zones that they live in, how they will be impacted by storms, or where their evacuation route is located. A lack of understanding the risks from hazards and what to do in an emergency can lead to a loss of life or property. Technical: Technically feasible. Need coordination with in house staff and GIS consultant. Political: Neptune Township Committee Legal: No apparent legal issues. Environmental: No NJDEP permitting required. Social: This action does not adversely affect any particular neighborhood, social group or organization. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer action Local Champion: Neptune Township Committee, Neptune Township OEM, Neptune Township Department of Engineering

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by furthering public education. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $2,000.00 Priority: High Local Planning Mechanism: Neptune Township Committee, Neptune Township Engineering Department Responsible Party: Neptune Township Engineering Department Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Withdrawn Notes: Combine with Action 37_20 Monmouth County Mitigation Action Worksheets

Community Action Number: 37_22 Neptune, Township of Describing the Action Action Name: Purchase Stormwater Pumps and Appurtenances Action Category: Maintenance/Response/Recovery Action Type: Structure and Infrastructure Project HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Purchase stormwater pumps and appurtenances to reduce flood risk in the special flood hazard area.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge Goals: 1,2,4,5,6 Risk Reduction:

Technical: Technically feasible with in house engineering department and DPW. Need quotes for pumps, hoses, and deployment materials. Political: The project should have the support of the Governing body as its implementation would serve to aid the residents. Legal: No apparent legal issues Environmental: No NJDEP permitting required Social: This action does not adversely affect any particular neighborhood, social group or organization. It would serve to further protect property and infrastructure. Administrative Capability: Township can administer action Local Champion: Neptune Township Committee; OEM, Neighborhood Groups, Engineering Department, and DPW

Other Community Objectives: Project furthers the protection of critical infrastructure and local neighborhood by mitigating flooding. Keeps roads open and minimizes debris. STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $100,000.00 Priority: Low Local Planning Mechanism: Hazard Mitigation Plan Responsible Party: Neptune Township Engineering Department, DPW Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: New Notes: CAPABILITY ASSESSMENT WORKSHEET

Name: Leanne R. Hoffmann Title: Director of Engineering & Planning

Jurisdiction: Neptune Township Organization:

Local Mitigation Capabilities are existing authorities, policies, programs, and resources that reduce hazard impacts or that could be used to implement hazard mitigation activities. Please complete the tables and questions in the worksheet as completely as possible.

Planning & Regulatory Planning and Regulatory Capabilities are the plans, policies, codes, and ordinances that prevent and reduce the impacts of hazards. Please indicate which of the following your jurisdiction currently has in place. 1. What is the date/year of the plan? 2. Does the plan address hazards? Yes/No Plan 3. Does the plan identify projects to include in the mitigation strategy? 4. Can the plan be used to implement mitigation actions? Yes 1. 2011 Comprehensive/Master Plan

Yes Capital Improvements Plan

Yes 1. An element of the 2011 Master Plan Economic Development Plan

Yes Local Emergency Operations Plan

Continuity of Operations Plan

No Post-Disaster Recovery Plan

Yes 1. An element of the 2011 Master Plan Transportation Plan

Yes 1. 2009 Stormwater Management Plan

No Community Wildfire Protection Plan

1 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other special plans (e.g., Yes • Getting to Resilience (2016) brownfields redevelopment, • Strategic Recovery Planning Report (2014) disaster recovery, coastal zone management, climate change adaptation) Building Code, Permitting, and Yes/No Are codes adequately enforced? Inspections

Version/Year: Building Code Yes

Building Code Effectiveness Score: Grading Schedule (BCEGS) Score

Rating: Fire Department ISO rating

Site Plan Review Requirements Yes 1. 2013

Is the ordinance an effective measure for reducing hazard Land Use Planning and Yes/No impacts? Ordinances Is the ordinance adequately administered and enforced? Yes Zoning Ordinance

Yes Subdivision Ordinance

Floodplain Ordinance Yes

Natural hazard ordinance (stormwater, steep slope, Yes Steep slope ordinance wildfire)

Flood Insurance Rate Maps

Acquisition of Land for Open Space and Public Recreation Uses

Post-Disaster Recovery No Ordinance

Real Estate Disclose Ordinance No

2 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Other (ie. Special Purposes Yes Special Purposes Ordinance and Growth Management Ordinance Ordinance)

How can the above capabilities be expanded and improved to reduce risk?

Administrative & Technical Identify whether your community has the following administrative and technical capabilities. These include staff and their skills and tools that can be used for mitigation planning and to implement specific mitigation actions. For smaller jurisdictions without local staff resources, if there are public resources at the next higher-level government that can provide technical assistance, indicate so in your comments. Describe capability Administration Yes/No Is coordination effective?

Planning Commission

Mitigation Planning Committee

Maintenance Programs to Reduce Risk (e.g., tree trimming, Yes Shade Tree Commission clearing drainage systems)

Mutual Aid Agreements

Is the staff full time or part time? Yes/No Is staffing adequate to enforce regulations? Staff FT/PT Is the staff trained on hazards and mitigation? Is coordination between agencies and staff effective?

Chief Building Official

Yes Floodplain Administrator

Emergency Manager Yes

Community Planner Yes

3 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Civil Engineer Yes

Surveyor Yes

GIS Coordinator Yes

Scientists familiar with the Yes hazards of the community

Other

Describe capability Technical Yes/No Has capability been used to access/mitigate risk in the past?

Warning Systems/Services (Reverse 911, outdoor warning signals)

Hazard Data and Information

Grant Writing Yes

Hazus Analysis Yes

Other

How can the above capabilities be expanded and improved to reduce risk? the past?

4 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Financial Identify whether your jurisdiction has access to or is eligible to use the following funding resources for hazard mitigation.

Access / Has the funding resource been used in the past and for what type Funding Resource Eligibility of activities? (Yes/No) Could the resource be used to fund future mitigation actions?

Yes Capital Improvements Project Funding

Yes Authority to Levy Taxes for Specific Purposes

Fees for Water, Sewer, Gas, or Yes Electric Services

Impact Fees for New Yes Development

Stormwater Utility Fee

Incur Debt Through Private Yes Activities

Community Development Block Yes Grant

Other Federal Funding Programs No

State Funding Programs

No Incur Debt through General Obligation and Incur Debt through Other (e.g., withhold spending in Special Tax and Revenue Bonds hazard-prone areas)

How can these capabilities be expanded and improved to reduce risk?

5 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN CAPABILITY ASSESSMENT WORKSHEET

Education and Outreach Identify education and outreach programs and methods already in place that could be used to implement mitigation activities and communicate hazard-related information. Describe program/organization and how it relates to disaster resilience and mitigation. Program/Organization Yes/No Could the program/organization help implement future mitigation activities? Local Citizen Groups or Non- Profit Organizations Focused on Environmental Protection,

Emergency Preparedness, Access and Functional Needs Populations, etc. Ongoing Public Education or Information Programs (e.g., responsible water use, fire safety, household preparedness, environmental education)

Natural Disaster or Safety

Related School Programs

StormReady Certification

Firewise Communities

Certification

Public-Private Partnership Initiatives Addressing Disaster Related Issues

Other

How can these capabilities be expanded and improved to reduce risk? these capabilities be expanded and improved to reduce risk?

Working towards a new classification in the CRS Program

6 MONMOUTH COUNTY MULTI-JURISDICTIONAL HAZARD MITIGATION PLAN Monmouth Parcel Classification 0 1,000 2,000 NEPTUNE TOWNSHIP County Industrial Commercial Apartment Residential (four families or less) Feet ± Farm Vacant Unclassified FLOOD VULNERABILITY Neptune Civic/Public (Tax Exempt) Open Space Source: © 2014 Esri; Monmouth County; MONMOUTH COUNTY HAZARD MITIGATION PLAN Township NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

#18 K40 Loch " L Interlaken 15 LK Arbour Borough Ocean Village Township Tinton ke La Falls Borough al De #"66

16 LK Asbury Park

LK17

Asbury Park

#"35 #"71 #"33 LK40A A t l a n t i c

Bradley O c e a n LK2 Beach

LK5 Neptune Bradley City Beach Borough Wesley Lake Borough Wall Township FEMA FLOOD HAZARD AREAS 1% Annual Chance Flood (SFHA) Regulatory Floodway Zone A, AE, AO, AH Zone VE

0.2% Annual Chance Flood Avon-by-the-Sea Zone X Borough Undetermined

Zone D r A t l a n t i c e iv Evacuation Route R O c e a n k Flood Hazard Areas are a composite of Effective FIRMs (06/20/2018) and r Preliminary FIRMs (01/30/2015) a Belmar h S Borough

This map was developed using the 10-04-18 statewide composite of parcel data published by the NJOIT-OGIS. The State of New Jersey makes great effort to provide secure, accurate, and complete data and metadata. However, portions of the data and metadata may be incorrect or not current. Any errors or omissions should be reported for investigation to OGIS. Monmouth ParcelClassific ation 0 1,000 2,000 NEPTUNE TOWNSHIP County Ind ustrial Com m ercial Apartment Resid ential(fourfamilies or less) Feet ± Farm Vacant Unc lassified FLOOD VULNERABILITY Neptune Civic /PublicExempt)(Tax OpenSpace Source: © 2014 Esri; Monmouth County; MONMOUTHCOUNTY HAZARD MITIGATION PLAN Township NJOIT-OGIS; NJGIN MODIV Parcel, FEMA Projection: New Jersey State Plane, NAD 1983

#18 K40 Loch " L Interlaken 15 LK Arbour Borough Ocean Village Township Tinton k e La Falls Borough al De #"66

16 LK Asbury Park

LK17

Asbury Park

#"35 #"71 #"33 LK40A A t l a n t i c

Bradley O c e a n LK2 Beach

LK5 Neptune Bradley City Beach Borough Wesley Lake Borough POTENTIAL SEA LEVELWall RISETownship INUNDATION AREAS 1 Foot1 SeaLevelRise (2050)

3 Foot3 SeaLevelRise (2100) EvacuationRoute

SpatialResolution and Acc uracy:Th ismap depic inland ts extent andrelativedepth inundof SLR ofusing and 3ft. NOAA ation for1ft. SLRwithdatavertic a datum al Meanof Hig hHig er hWater (MHHW). T h ese inund ation rang es are consistent w ith the Rutgers Avon-by-the-Sea University’sNew Jersey Clim Adaptation ate Allianc Scienc e and e T ech nicAdvisory al Panel Report (STAP Report).Th STAP e Report Borough estimNew ates Jerseywill experienc SLR e betweenandfeet 1.0 1.8 priorregardless2050, to futureofgreenh ousegasemissions. Th e d ata displayedd ata on mapthis represents current cond itionsand does notconsid ernatural proc suc esses erosion has or marsh mig ration r A t l a n t i c that will futurethat bylevel seaaffectedDue berise. coarseto spatial e v resolution,the user should not interpret the layers as precise i inund ationextents. R O c e a n k r a Belmar h S Borough

T hmap is was developed using statew id10-04-18the com e positeparcelof publisheddata NJOIT-OGIS.theby NewThof JerseyState makes e providto great effort secure, e acc and urate, com pletedataand metadata.How portions ever, anddatathe of metadata mayinc be orrector notcurrent. Any errors or om issionsshould reportedbe forinvestig ationOGIS.to

MEETING NOTES

Topic: Neptune City- Monmouth County HMP Meeting

Date: May 6, 2019

Time: 1:00 PM- 2:00 PM

Location: Neptune City Borough Hall 106 W Sylvania Ave.

Attendees:

Mark Balzarano DPW Director Joe Barris Assistant Director, Planning Michael Bascom OEM Coordinator Kyle Bascom PIO Randy Bishop Director John Bleck Assistant Super Steve Colombo Operations Director Michael DiLeo Deputy Coordinator Bill Doolittle Construction Official Ed Finley Harbor Master Vito Gadaleta BA/Cert. Coordinator Leanne Hoffman Director of Engineering & Planning Joseph Maro Director of Operations Michael McGhee Captain of Police Michael Oppegaard Coordinator Steph Oppegaard Human Resources Sharon Rowe OEM Security Douglas Rowen Fire Official Stephen Vetrand Medical Director Mike Zagory Security/Safety Brittany Ashman MB Planner Michael Yaffe MB Planner Craig Wenger MB Project Manager

Drafted by: Paige Kaspar

______

Introductions (Michael):

• What is Hazard Mitigation? • Matching actions with Goals • New Hazards • HMP Pamphlet • Funding

2015 Mitigation Actions:

• Community Action 37_01 - Living Shoreline – Ongoing st o 1 phase is complete  the design phase is complete • Community Action 37_02 - Floodproofing Pump Station Doors – Ongoing o Designed with dry pit submergible pumps  even if the building floods the pump system will still work o Electronics elevated above the floodplain o Flood of the building has been mitigated o Expensive • Community Action 37_03 - Bulkheading of S. Riverside Drive – Ongoing o Would rather do a Living Shoreline in marine area • Community Action 37_04 - Bulkheading Berm around local Lake Alberta, Fletcher Lake, and Wesley Lake – Ongoing o Separate out the lakes J o Structural lakes o Living shorelines o Will be three separate priorities • Community Action 37_05 - Acquisition of Flood Prone Properties – Ongoing o Green Acres for funding and Monmouth County Funding  closed by end of May 2019 • Community Action 37_06 - Creation of a Permanent Confined Disposal Facilities (CDF) - Structural Earthen Berm – Ongoing • Community Action 37_07 - Establish AM Radio station install warning system and flood gauges – Ongoing • Community Action 37_08 - Removal of silt and sediment from the Shark River Basin – Ongoing o Medium priority • Community Action 37_09 - Desnagging/Desilting of Shark River Tributary, Jumping Brook, and Musquosh Brook – Ongoing • Community Action 37_10 - Elevation of Floodprone Properties – Ongoing o Allow funds to go back to property owners o Rescind access o Property owners to select contractor o Acquisitions • Community Action 37_10 - Generator at North Island Pump Station - Complete • Community Action 37_11 - Preparation of Hazard Overlay Zones – Partially complete o Not rolled out on public website • Community Action 37_12 - Updating online GIS on Township's website – Ongoing

o Hazard overlay 2020 Mitigation Actions (NEW):

• Living Shoreline along Seaview • Generators for Emergency OEM • Generators for stormwater pumps • Microgrid BPU – supports critical facilities • Largest hospital in County is in Neptune Twp o Points of distribution • Stormwater into sewer service – park flows • Target hardening o Schools o Municipal buildings o Surveillance equipment o Barriers o Bullet proof glass o Access control o Facilities for school  access controls/visitor management o CCTV o Ballard’s where there are high volumes of people  events o Window film on entrance o Surveillance footprints on the ground o Parking lot o Schools identified as being the most vulnerable . Special needs and low functioning students . Socially vulnerable Repetitive Loss Properties:

• There are struggles in the Ocean Grove historic district o Small lots, 30x60 ft o Close proximity to other homes o Negates the historic value • Rules elevating home before or after ICC money • Spike in fraud insurance • Paid by insurance is the biggest battle

Appendix Vol I.38 Ocean Township

Please find below the following documents specific to this jurisdiction that have been included as part of the plan update process.

• Summary Sheet

• Mitigation Action Table

• Mitigation Action Worksheets

• Capability Assessment

• Flood Zone Map

• Sea Level Rise Vulnerability Map

• Meeting Material Ocean Township CRS Class 6

NFIP Statistics 7%

285 Polices In-force

282 Total Losses

$6,600,281 Total Payments 35 Number of RL Properties Number Mitigated Percent Land Area Within SFHA 14 RL Properties

108 RL - Total Losses 17 Total Mitigation $3,692,182 RL - Total Paid Actions

3 Number of SRL Properties 0

Number Mitigated SRL 0 Properties Education and Awareness Programs

18 SRL - Total Losses 10

$404,224 SRL - Total Paid Structure and Infrastructure Projects Critical Facilities 0

36 Critical Facilities Local Plans and Regulations

0 Critical Infrastructure 7

35 Historic & Cultural Resources Natural Systems Protection

489 SV Population At Risk (2017) 1,905 Population at Risk (2017) Ocean, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources

38_01 Acquire, elevate, or relocate Acquire 28 Repetitive Loss Properties to purchase, Mitigation - Risk Structure and Flood, Nor'easter, High Township Manager, FEMA HMA $12,600,000.00 1 year Ongoing buildings and infrastructure in demolition, and maintain as open space or elevate the Reduction Infrastructure Hurricane and Tropical Police, DPW, Green flood prone areas, with a structure. Project Storm, Storm Surge, Acres, County Open focus on Repetitive Loss (RL) Winter Storm Space office and and Severe Repetitive Loss (SRL) properties

38_02 Clean and Desilt Poplar Brook Dredge the length of both Poplar Brook and Whalepond Maintenance/Resp Natural Systems Flood, Nor'easter, Medium Township Manager, Municipal budget $1,000,000.00 1 year Ongoing and Whalepond Brook Brook to remove all obstructions. Remove snagging and onse/Recovery Protection Hurricane and Tropical DPW, County debris from floodway and dredging up to two feet of silt. Storm, Storm Surge, Mosquito Winter Storm Commission and

38_03 Reconstruct Roseld Avenue Rehabilitation of dam adjacent to Roseld Avenue to Mitigation - Natural Systems Nor'easter, Hurricane and Township Manager, $1,000,000.00 Withdrawn Dam alleviate flooding and prevent erosion of roadway. The Continuity of Protection Tropical Storm, Storm DPW, NJDEP, Deal Roseld Avenue project will provide a water quality Functional Use Surge, Winter Storm Lake Commission structure to remove sediment from water prior to and Engineer entering Deal Lake.

38_04 Purchase and Install Upgrade the current and outdated generator at the Town Structure and Flood, Nor'easter, Township Manager, Federal, state, county $500,000.00 Completed Generators for Town Hall Hall which houses the Emergency Operations Center for Infrastructure Hurricane and Tropical Police, DPW and grants with some OEM, Police Dept, and Public Works offices which is also Project Storm, Storm Surge, Engineer local funds used as a reception center for shelters. Winter Storm

38_05 Create a Detention for An area needs to be created that is large enough to hold Maintenance/Resp Structure and Flood, Nor'easter, High Monmouth County Municipal budget $3,000,000.00 1 year Ongoing Whalepond Brook stormwater after a heavy storm and slowly release back onse/Recovery Infrastructure Hurricane and Tropical officials, OT into the proper detention system. Project Storm, Storm Surge, Township Manager, Winter Storm DPW, and Engineer

38_06 Purchase and Install Acquisition of emergency generators for critical facilities, Maintenance/Resp Structure and Nor'easter, Hurricane and Low Township Manager, FEMA HMA $150,000.00 1 year Ongoing Generators for Other Critical including the gym, high school, recreation center, and onse/Recovery Infrastructure Tropical Storm, Storm School Facilities elementary school. Project Surge, Winter Storm administration, DPW, and Engineer

38_07 Remove Sediment and Tree Remove sediment and tree debris to create a clear Maintenance/Resp Natural Systems Flood, Nor'easter, Low Township Manager, Municipal budget $5,000,000.00 1 year Ongoing Debris Along the Arm of Deal channel for stormwater entering Deal Lake. onse/Recovery Protection Hurricane and Tropical DPW, NJDEP, Deal Lake Storm, Storm Surge, Lake Commission Winter Storm and Engineer

38_08 Redesign the Existing Weir to Redesign existing weir to increase storm attenuation Mitigation - Natural Systems Flood, Nor'easter, Township Manager, NFWF grant $220,000.00 Withdrawn Increase Storm Attenuation capacity of the Colonial Terrace Arm of Deal Lake (west of Continuity of Protection Hurricane and Tropical DPW, NJDEP, Deal application for Capacity at the Colonial Wickapecko Ave). Functional Use Storm, Storm Surge, Lake Commission planning/design Terrace Arm of Deal Lake Winter Storm and Engineer submitted by DLC,

Wednesday, March 4, 2020 Page 1 Ocean, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 38_09 Reconstruct Wetlands and Multi-phase project involving the construction of a Mitigation - Natural Systems Dam Failure, Flood, Medium Township Manager, NJDEP Bureau of Dam $2,250,000.00 1 year Ongoing Flood Attenuation Basins regional wetland, flood attenuation basins, stabilization Continuity of Protection Nor'easter, Hurricane and DPW, NJDEP, Deal Safety and Flood around Harvey Brook; of stream bank, and coordinate with private property Functional Use Tropical Storm, Storm Lake Commission Control, EPA, Stabilize Stream Banks owner replacement of dam (new to this action). Surge, Winter Storm and Engineer, National Fish and

38_10 Redesign the Existing Weir to Retrofit of existing weir so pond can function as a Mitigation - Natural Systems Nor'easter, Hurricane and High Township Manager, NFWF, FEMA HMA $400,000.00 1 year Ongoing Increase Storm Attenuation regional flood attenuation basin. Install MTD in road to Continuity of Protection Tropical Storm, Storm DPW, NJDEP, Deal Capacity at Fireman Pond control pollutant loading to lake. Functional Use Surge, Winter Storm Lake Commission and Engineer

38_11 Replace Existing Weir and Replace existing weir, dredge, and reconfigure existing Maintenance/Resp Structure and Flood, Nor'easter, High Township Manager, NFWF grant $1,000,000.00 1 year Ongoing Dredge and Reconfigure impoundment west of Chestnut Ave construct regional onse/Recovery Infrastructure Hurricane and Tropical DPW, NJDEP, Deal application for Existing Impoundment at created wetland flood attenuation basin. Project Storm, Storm Surge, Lake Commission planning/design Lollipop Pond Winter Storm and Engineer submitted by DLC,

38_12 Enlarge Culverts under An area needs to be created large enough to hold Mitigation - Structure and Flood, Nor'easter, Low Township Manager, Municipal budget, $4,000,000.00 3 years Ongoing Roadway and Railroad stormwater runoff during and after a severe storm and Continuity of Infrastructure Hurricane and Tropical DPW, County FEMA HMA (Intersection of New Jersey then the stormwater be released at a slower pace not to Functional Use Project Storm, Winter Storm Roads/Bridge Depts. Transit and Poplar Brook) cause any flooding. and Engineer

38_13 Create a Detention Pond near An area needs to be created large enough to hold Mitigation - Structure and Flood, Nor'easter, Low Township Manager, Municipal budget $5,000,000.00 3 years Ongoing Joe Palaia Park stormwater runoff during and after a severe storm and Continuity of Infrastructure Hurricane and Tropical DPW and Engineer then the stormwater be released at a slower pace not to Functional Use Project Storm, Storm Surge, cause any flooding. Winter Storm

38_14 Construct a Flood Wall along Build a flood wall along the rear properties of the houses Mitigation - Risk Structure and Flood, Nor'easter, High Township Manager, FEMA HMA $1,882,772.00 2 years Ongoing Poplar Brook on Brookside Ave. along the banks of the Poplar Brook. Reduction Infrastructure Hurricane and Tropical Police, DPW, Green Project Storm, Storm Surge, Acres, County Open Winter Storm Space office and

38_15 Enlarge Culverts under An area needs to be created large enough to hold Mitigation - Structure and Flood, Nor'easter, Low Township Manager, Municipal budget $4,000,000.00 3 years Ongoing Roadway and Railroad stormwater runoff during and after a severe storm and Continuity of Infrastructure Hurricane and Tropical DPW, County (Whalepond Brook) then the stormwater be released at a slower pace not to Functional Use Project Storm, Storm Surge, Roads/Bridge Depts. cause any flooding. Winter Storm and Engineer

38_16 Purchase Joanna Ct. Property Acquire Repetitive Loss Property, demolish the property, Mitigation - Risk Natural Systems Flood, Nor'easter, High Township FEMA HMA $700,000.00 2 years New for Detention Pond and create detention pond to alleviate flooding along Reduction Protection Hurricane and Tropical Poplar Brook. Storm

Wednesday, March 4, 2020 Page 2 Ocean, Township of Monmouth County HMP Mitigation Action Summary

Community Action Name Action Description Action Category Action Type Hazard(s) Addressed Priority Responsible Party Potential Funding Cost Estimate Timeline Action Status Action # Sources 38_17 Target Harden Municipal The Municipal Complex and Township schools should be Maintenance/Resp Structure and Terrorism Low Township Council Homeland Security 2 years New Complex and Schools by more secure from the public. The Municipal Complex onse/Recovery Infrastructure grants Installing Surveillance could use panic buttons, bulletproof glass for staff that Project Cameras, Panic Buttons, Metal interact with the public daily, a new secure office layout, Detectors, and/or Bulletproof and metal detectors. The school could benefit from a Glass surveillance system.

Wednesday, March 4, 2020 Page 3 Monmouth County Mitigation Action Worksheets

Community Action Number: 38_01 Ocean, Township of Describing the Action Action Name: Acquire, elevate, or relocate buildings and infrastructure in flood prone areas, with a focus on Repetitive Loss (RL) and Severe Repetitive Loss (SRL) properties Action Category: Mitigation - Risk Reduction Action Type: Structure and Infrastructure Project HMA Eligible Activity: Property Acquisition and Structure Demolition Action Description: Acquire 28 Repetitive Loss Properties to purchase, demolition, and maintain as open space or elevate the structure.

Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge, Winter Storm Goals: 3, 6 Risk Reduction: Flooding damage to buildings and properties during hurricane, tropical storm, nor'easter, winter storm, flood, and storm surge. Dozens of homes in the 10-year flood zone on Brookside Avenue are susceptible to flooding during severe storms. Technical: Technically feasible. Political: Political actions present in support of effort. Legal: No legal issues. Environmental: Positively impacts the environment by increasing the permeable surface for each homeowner property. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because of repetitive nature of flooding in the project area. Administrative Capability: Township has sufficient capacity and experience to administer this action Local Champion: Township Manager, OEM, DPW, Police, elected officials

Other Community Objectives: STAPLEE Evaluation: 11

Implementing the Action Cost Estimate: $12,600,000.00 Priority: High Local Planning Mechanism: Township Manager, DPW, Engineer and OEM Responsible Party: Township Manager, Police, DPW, Green Acres, County Open Space office and Engineer Likely Funding Source(s): FEMA HMA Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; 20 of the 33 RL properties are mitigated; 2 of the 3 SRL properties are mitigated. $2,207,820 was awarded through the HMGP grant to Poplar Village and $2,046,126 for Phase II Poplar Village. Monmouth County Mitigation Action Worksheets

Community Action Number: 38_02 Ocean, Township of Describing the Action Action Name: Clean and Desilt Poplar Brook and Whalepond Brook Action Category: Maintenance/Response/Recovery Action Type: Natural Systems Protection HMA Eligible Activity: Miscellaneous/Other/NA Action Description: Dredge the length of both Poplar Brook and Whalepond Brook to remove all obstructions. Remove snagging and debris from floodway and dredging up to two feet of silt. Evaluating the Action Hazard(s) Addressed: Flood, Nor'easter, Hurricane and Tropical Storm, Storm Surge, Winter Storm Goals: 2, 3, 5, 6 Risk Reduction: Obstructions along the length of Poplar Brook and Whalepond Brook (silt, snags, debris) cause flooding of properties and roadways. Technical: Technically feasible. Political: Political actions present in support of effort. Legal: Since stream is a natural border with adjoining town, might have to discuss impacts with adjacent municipalities; may need NJDEP permits. Environmental: There are areas that will needed to be examined along the stream, but no major issues to be dealt with known at this time. Social: Does not adversely affect any particular social group. Perceived by the public to be a good thing because it reduces risk for individual homeowners. Administrative Capability: Township agencies can oversee the removal and maintenance. Local Champion: Township Manager, Engineer, OEM and DPW

Other Community Objectives: storm drain improvements STAPLEE Evaluation: N/A

Implementing the Action Cost Estimate: $1,000,000.00 Priority: Medium Local Planning Mechanism: Local officials and County agencies; adjoining town on border with stream and where the outfall is located. Responsible Party: Township Manager, DPW, County Mosquito Commission and Engineer Likely Funding Source(s): Municipal budget Timeline: 1 year Action Status: Ongoing Notes: Ongoing 2015 action; permit issue was resolved, and the project is back on track.