Ongoing Projects - Civil

Contract Sl. L.O.A/W.O./C.A No. Name of Work Value (In Remarks No. & Date Rs.)

1 Submission of Tender for “Supply, ECL//W 18.75 Work Erection , Modification, Testing & O/CIVIL/18 completed of commissioning and preparation of Dated 16.09.2017 Crores. Rs.10 Crores. approved as built drawings of OHE, Signaling & Telecommunication of Total Work New proposed Private Railway Completed siding for EMAMI CEMENT LTD. within from existing Matrix Fertilizer & Chemical Limited siding at February,2018. Panagarh station in Division of Eastern Railway.

2 “Earthwork in formation, NOCCI/Railway 13 Work Construction of Bridges, High level Siding (Civil)/2015- Crores completed of Platform, Service Building, Supply of 16/1320 Rs.8 Crores. Ballast, Permanent Way Materials and Linking of Track in connection Dated:29.09.2015 with provision of new siding taking off from New Block Station on Nilgiri siding, Balasore under Kharagpur Division of South Eastern Railway.”

3 New Loop Line 7 intersection PSE/ADD-LOOP/17 1.20 Work in between Railway lines at in Crores progress. plant Railway siding at Sonar Dated:15.09.2017 Bangla Cement Plant at Vill: Dhola , P.O.- Gankar, Block- Raghunath Gunj-1, Dist: Murshidabad, ().

Ongoing Projects - Civil

Contract Sl. L.O.A/W.O./C.A No. Name of Work Value (In Remarks No. & Date Rs.)

4 Work for CIVIL, Engineering W.O. NO. 15.46 Work & OHE work turnkey basis GEN/RLY- Crores completed including drawing & Siding/90002 dt. designing as per Railway 08.08.2008 System at Gokulpur-Nimpura with Central Panel Interlocking of Kharagpur Div. S.E. Rly.

5 Turnkey basis of CIVIL work PSE/STCPL/004/2 10 Work including the work of 014-15 dated Corers completed Earthing in Formation 30.04.2014 ,Service Building , Supply of Ballast, Permanent way materials and linking of Tracks in connection with private railway siding at Ranital , Bhadrak.

Ongoing Projects - Signal & Telecom

Contract Sl. L.O.A/W.O./C.A No. Name of Work Value (In Remarks No. & Date Rs.)

1 Supply & Execution of materials for i)DC/CMV/9021000 12.75 Work in S&T work for infrastructure 127 dtd. 16.03.2016 Crores Progress development of Janai Road Railway (Supply) & station in connection for UTCL Revised siding. ii)DC/CMC/807800 0786 dtd. 16.13 16.03.2016 Crores (Execution)

2 Supply & Installation of JSWCL/Salboni/35 4.66 Work in Signal with Telecom work for Dated 01.03.2017 Corers Progress Railway siding pertaining to 2 x 1.2 MTPA Grinding unit at Revised JSW Cement Ltd., Salboni. 8.52 Crores

3 Supply, Installation, Testing and W.O No.: 5.11 Work in commissioning of S&T work for HEL:WO:3230C Crores Progress DOUBLING BETWEEN BASULIYA SUTAHATA STATION to BYSA JN. Dt. 27.02.2016 CABIN Till LC Gate at KM No.:56.662 from PKU including 5th Loop line at BYSA Stn. With DI alteration at BYSA Stn. And Panel Modification at BYSA Jn. & DZK Stn. 4 Supply, Installation, Wiring, Testing C.A. No.- 2.85 Work in & Commissioning work- of S&T RITES/RPO- Crores Progress Equipments for modification of In- KOL/WBPDCL- Plant Yard to provide Additional Sg.TPP/Phase- Track Hopper and Wagon Tippler for 2x500 MW expansion of Sagardighi II/S&T/ 2015/467 Thermal Power Plant (Phase-II) near Dt. 20.02.2017 Manigram Station of Malda Division in Eastern Railway, Dist. Murshidabad, West Bengal

Ongoing Projects - Signal & Telecom

Contract Sl. L.O.A/W.O./C.A No. Name of Work Value (In Remarks No. & Date Rs.)

5 “Supply, installation, testing & C.A. No. 2.26 Sitarampur to commissioning of STM, Muxs and CORE/S&T/TELE/ Crores OFC Link & Supply, Installation, 9041/PKR-MLDT & Stations Testing & commissioning of Way UDL-STN Dated Commissioned station equipments, Head quarter control equipments with power 10.08.2015 Barabania to supplies, Emergency sockets etc in Tapshia

SP/SSP/TSS including Trenching, Commissioned Laying, Jointing of 6-Quad/PIJF cable for SP/SSP/TSS etc in PAKUR-MALDA & ANDAL- SITARAMPUR VIA -IKRA & SRIPUR Section of Eastern Railway. 6 Design and Construction of i) LOI No. : 1.73 Work in Civil, Structures and Track GIL/DFCC/201/C& Corers Progress Works for Double Line C/2016-17/2752 Railway involving Formation Dated 06.03.2017 in Embankments/Cutting, Ballast on Formation, Track ii) LOI No. : Works, Bridges, Structures, GIL/DFCC/201/C& Buildings, Yard, Integration with IR Existing Railway C/2016-17/2753 System and Testing & Dated 06.03.2017 Commissioning on Design- Build Lump Sum Basis for Mughal Sarai to New Karchana Station (Including) of Eastern Dedicated Freight Corridor (Contract Package 201) "Project" - Supply of material Outdoor S&T Works for Track works in DFCC CP 201 - LOI ("LOI")

Ongoing Projects - Signal & Telecom

Contract Sl. L.O.A/W.O./C.A No. Name of Work Value (In Remarks No. & Date Rs.)

7 Design and Construction of i) LOI. No. : 48 Lakhs Work in Civil, Structures and Track GIL/DFCC/202/C& Progress Works for Double Line C/2016-17/2754 Railway involving Formation Dated 06.03.2017 in Embankments/Cutting, Ballast on Formation, Track ii) P.O. No. : Works, Bridges, Structures, GIL/DFCC/202/C& Buildings, Yard, Integration with IR Existing Railway C/2016-17/2755 System and Testing & Dated 06.03.2017 Commissioning on Design- Build Lump Sum Basis for New Karchana Station (Excluding) to New Bhaupur (Excluding) of Eastern Dedicated Freight Corridor (Contract Package 202) "Project" - Supply of material Outdoor S&T Works for Track works at Ramwa Depot in DFCC CP 202 - Purchase Order ("PO") 8 Supply, Erection, Modification, LOA under process 6.42 Work in Testing & Commissioning Corers Progress and preparation of approved as built drawings of Signaling & Telecommunication work at new railway siding taking off from New Block Station on Nilgiri Ballast Siding, B a las o re u n d e r Kharagpur Division of South Eastern Railways.