Welcome to the Online Consultation Preliminary Construction & Traffic Planning Intro to Shop Local/Shop Eglinton Initiative Please review the presentation and complete the survey by July 11, 2012.

Preliminary Construction Planning

1 Update • The first Tunnel Contract (Keele St to Yonge St) will be awarded this summer • Detailed traffic plans will be developed after the contract is awarded • Additional public meetings in Fall 2012 to discuss detailed construction plans for the first tunnelling contract • The earliest utility work could begin on Eglinton in the vicinity of is late 2012 (west side of Allen southbound)

Preliminary Construction Planning

2 Tunnel Construction Principles • Package contracts to coordinate all work under same umbrella (utilities, city, transit) • Maintain a minimum of one lane eastbound and westbound on Eglinton in construction zones • Access to buildings from Eglinton remains open • Only propose road closures if required for safety reasons or to provide exceptional time savings and reduction to long term disruption

Preliminary Construction Planning

3 The Crosstown – 2012 *Final number and location of stations subject to Provincial review

• 60% faster than current bus routes • 15 minutes from Keele to Yonge

Preliminary Construction Planning

4 Eglinton Bus Ridership • Eglinton 32 & 34 buses carry 68,500 riders every weekday • Transfers required at Eglinton West and Eglinton Stations (Allen & Yonge) • Eglinton has amongst the highest ridership of all bus routes

Preliminary Construction Planning

5 Eglinton at Bathurst (looking west)

Preliminary Construction Planning

6

Preliminary Construction Planning

7 Looking east from Oakwood

Preliminary Construction Planning

8 Crosstown Construction Update • Tunnel preparation work at Black Creek and Eglinton in Keelesdale Park • Piling rigs are building concrete support walls for the future west tunnel launch shaft • The west launch shaft will enable tunnelling works in late 2012 towards Allen Road

Preliminary Construction Planning

9 West Launch Shaft Keelesdale Park near Launch Shaft Eglinton Ave • 60m Long • 20m wide • 16m deep

Preliminary Construction Planning

10 Tunnel Construction Overview • Relocate utilities at major intersections to maintain services (gas, water, cable) • Construct “headwalls” (support walls formed by a series of concrete columns) at east and west ends of each future station location – 4 - 5 months per station location – Process called “Jet Grouting” when soil conditions allow - 3 - 4 months • Concurrently, construct Tunnel launch and extraction shafts. These are large pits where tunnelling machines are first lowered for assembly and then extracted from the ground. • The tunnel machines are launched from Keelesdale Park (just west of ) and tunnel eastward through the station “headwalls”

Preliminary Construction Planning

11 Tunnel Construction Overview Continued • To ensure subway service is maintained throughout construction, tunnelling machines are removed from a pit at the west side of Allen Road on Eglinton and re-launched from a new pit on the east side of Allen Road on Eglinton • Tunnelling proceeds to , and a second extraction pit is built to remove and re-furbish the machines before they reach Eglinton Station • Following this tunnelling work, the Crosstown Stations between Keele and Yonge will be constructed. Stations will each take approximately 4 years to construct

Preliminary Construction Planning

12

Utilities - Bathurst

600mm BELL/ROGERS WATERMAIN CONDUITS (2) STACKED SANITARY 225mm SEWERS 1125mm STORM SANITARY SEWER SEWER

EGLINTON AVENUE WEST

TELUS/GT DUCT 300mm GASMAIN BELL/ROGERS BANK (18) (TO BE CONDUITS (20) ABANDONED) T.H.E.S. DUCT 150mm GASMAIN BANK (12) (ABANDONED) STACKED SANITARY SEWERS

300mm COMBINED EXISTING STORM SEWER

THURST STREET EXISTING SANITARY SEWER SEWER EXISTING WATERMAIN BA EXISTING COMBINED SEWER EXISTING GASMAIN PEVERIL HILL NORTH PEVERIL EXISTING BELL/ROGER CONDUIT EXISTING TELUS/GT CONDUIT EXISTING T.H.E.S./COGECO DUCT BANK

Preliminary Construction Planning

13 Challenge of Underground Utilities

Preliminary Construction Planning

14 Tunnel Drive Sequence

1 2 3 Launch Shaft Leading Tunnel

Trailing Tunnel

Extraction Shaft

Station 4 Mine-Through 5 6 Headwalls Headwalls

Excavate Station and Remove Tunnel Liners

Preliminary Construction Planning

15 Extraction Shaft Example Spadina Subway Extension - Keele and Finch

KEELE STREET

Preliminary Construction Planning

16 Extraction Shaft Example Spadina Subway Extension - Keele and Finch

KEELE STREET

FINCH AVE

Preliminary Construction Planning

17 Extraction Shaft Example Spadina Subway Extension - Keele south of Finch

KEELE STREET

Preliminary Construction Planning

18 Eglinton and Allen - Existing

Preliminary Construction Planning

19 Utility Relocation Work Exact Lane Setup TBD

Preliminary Construction Planning

20 Utility Relocation Work Exact Lane Setup TBD

Preliminary Construction Planning

21 Utility Relocation Work Exact Lane Setup TBD

Preliminary Construction Planning

22 Extract TBM & Re-Launch

Preliminary Construction Planning

23 Soil removal for Tunnelling • 1 165 000 cubic metres of soil to be removed during tunnelling

• Enough to fill the ACC rink higher than the CN Tower

Preliminary Construction Planning

24 West Tunnelling – Keele Street to Yonge Street Traffic Management Overview

Preliminary Construction Planning

25 Existing Conditions on Eglinton • Rush Hours : 7am to 9am & 4pm to 6pm • Most sections of Eglinton between Keele and Allen have one lane in each direction for general traffic inrush hours • Between Allen and Yonge, most sections have two lanes in each direction available for general traffic inrush hours • In most sections during rush hours, the curb lane is for buses only • Outside of rush hours, the curb lanes are used for on-street parking, generally leaving one lane per direction for moving traffic

Preliminary Construction Planning

26 Existing Conditions Dufferin to Chaplin • External traffic represents45% of the auto trips (AM peak) • 45% of traffic has an origin and destination outside the area & use Eglinton as a traffic corridor • PM peak period is similar, 42% external, 58% local

Preliminary Construction Planning

27 During Tunnel Construction • One lane of traffic available on Eglinton both EB and WB all-day in active construction zones. Buses and general traffic will share this lane. • Advance warning signs will be placed in the vicinity of the corridor. Changeable Message Signs and Static Signs.

Preliminary Construction Planning

28 Transit Services during Tunnel Construction • Pedestrian and bus access to Eglinton West and Eglinton Stations will remain open • No major change to existing bus routes • Local bus route detours may be required for key construction activities for tunneling • TTC buses along Eglinton will be monitored and additional vehicles added as needed to respond to changes in traffic conditions

Preliminary Construction Planning

29 Parking • Currently, 3 hour paid parking is available on Eglinton Avenue West outside of weekday rush hours. • In order to provide space for construction work, some of these spaces will be unavailable • One-hour parking on some local roads will be extended to 3 hours, only while construction is impacting parking availability on Eglinton Avenue • Parking on local roads will be enforced to discourage long-term parking and will be closely monitored by Police Services Parking Enforcement

Preliminary Construction Planning

30 Pedestrians/Cyclists • Front door access to Eglinton Avenue buildings maintained • Minimum 1.5 metre sidewalk widths • Some temporary closures of sections of sidewalk required. Where necessary, crossings will be available at traffic signals. One side open at all times. • Bike lanes not currently provided on Eglinton • During construction, cyclists will continue to share general traffic lanes • Where space is available, wider lanes provided to accommodate all users

Preliminary Construction Planning

31 Jet Grouting

Typical Rig

2–3m Diameter Jet Grout Formed Soilcrete Columns Jet Grouting Process

Preliminary Construction Planning

33 Allen Road Area • Tunnelling under Eglinton West Station carries risk to subway operations • Detailed Traffic management plans to be developed upon award of tunnel contract and presented at Fall 2012 follow-up meeting • 2013 – Potential for occasional, off peak (overnight) Southbound Right Turn prohibitions from Allen to Eglinton for utility relocations at Extraction Shaft • Potential short duration Eastbound to Northbound left turn prohibitions from Eglinton onto Allen Road for decking installation at ramp

Preliminary Construction Planning

34 Allen Road Proposed One Year Closure in 2014 to Northbound Access at Eglinton • Potential closure of northbound access to Allen Road at Eglinton to expedite tunnelling • Closure projected to reduce construction by approximately one year • Northbound Allen would remain open north of Eglinton • Closure would give contractor enough space for construction staging and movement of 150 trucks per day directly onto Allen Road - All prohibitions at Allen Road require City Council approval - Anticipated report timing is FALL 2012 Public Works Committee/City Council

Preliminary Construction Planning

35 Tunnel Launch Shaft – Sheppard Subway

Preliminary Construction Planning

36 13 Division – Working with Police Temporary Property Requirements • 5 metre area between sidewalk and 13 Division building • Utility construction area • Temporary sidewalk • Tree removals are unavoidable • Sign removal/ relocation • Tiebacks

Preliminary Construction Planning

37 Cross Passages – 2014 • Cross passages are used for emergency evacuation of the tunnels and for access between the tunnels for maintenance • Constructed by hand mining between the two tunnels • Area needed on road for pumping equipment to dewater the area where the mining is conducted • Impact = 2 - 3 months per location • 1 lane per direction

Preliminary Construction Planning

38 Temporary Local Road Closures at Eglinton Avenue

Temporary closures at Eglinton intersections with some local streets will unfortunately be required during different phases of tunnel construction to safely complete work (access always maintained from one direction) • Yarrow Road (2012-2013 - 7 weeks) • Kane Avenue (2013 - 5 weeks) • Little Boulevard (2013 – 4 days) • Strathearn Road (2013 - 11 Weeks) • Flanders Road (2013 - 11 Weeks) • Peveril Hill North Road (2013 - 9 Weeks) • Chaplin Crescent Southbound Thru & Left (2013 - 9 Weeks) • Latimer Avenue (2013 - 9 Weeks) • Highbourne Road (2014 - 9 Weeks) • Maxwell Avenue (2015 - 17 Weeks)

Preliminary Construction Planning

39 Ministry of Transportation (MTO) Highway 401/Allen Road Ramp Improvements • MTO is rehabilitating 8 structures in the Highway 401 and Allen Road • Bridge improvements have been broken into 2 contracts • Contract 1 (Bridges 4 and 24) Contract 2 (Bridges 5, 6, 12, 16 19 22) • Construction for Contract 1 commenced in Spring 2012 • Completion for Contract 1: late Fall 2012 • Construction schedule for Contract 2 TBD

Preliminary Construction Planning

40 Ministry of Transportation (MTO) Highway 401/Allen Road Ramp Improvements

Preliminary Construction Planning

41 MTO – Highway 401 /Allen Road Ramp Construction Details • Lane reductions on the 401 to Allen Road ramps and bridges • Periodic overnight ramp/bridge closures • Advance traffic warning signs will be posted in the area to advise the public of traffic restriction and lane closures • Construction is planned to take place during daytime hours from Monday to Friday • Extended working hours (periodic night time work) & weekend work required to complete construction on schedule. Project information: Mr. Sam Molai, P.Eng., Senior Structural Engineer Mr. Larry NG, Project Manager, Design Ministry of Transportation, Central Region SNC Lavalin tel: 416-235-5506 tel: 416-252-5315 Ext 2711 e-mail: [email protected]

Preliminary Construction Planning

42 City of Toronto – Long Term Planning Construction Details • The City of Toronto is studying ways to improve Allen Road • The study will follow a provincially mandated Environmental Assessment process. • Study investigating current challenges and opportunities in the Allen Road corridor from Eglinton to just south of Transit Road • Currently, a Terms of Reference (Study Framework/Work Plan) is being developed to guide future work

Preliminary Construction Planning

43 Allen Road Environmental Assessment For more information, please contact: Jason Diceman Tel: 416-392-3787 E-mail: [email protected] Web Site: www.toronto.ca/involved/ projects/allenrdstudy

Preliminary Construction Planning

44 Station Construction Overview Projected Start – 2015

• After tunneling is completed, station construction begins

Preliminary Construction Planning

45 Eglinton Pre-Construction - Existing Right of Way Use

Watermain

Preliminary Construction Planning

46 Station Construction Stage 1A Piling - Divert Traffic & Construct Support of Excavation

Watermain

(Exact Construction Set-Up TBD by Location for all stages)

Preliminary Construction Planning

47 Station Construction Stage 1B – Construct Centre Piles

Watermain

Preliminary Construction Planning

48 Station Construction Stage 2A – Construct Roadway Decking on one Side

Watermain

Preliminary Construction Planning

49 Station Construction Stage 2B – Construct opposite side Decking & Support of Excavation

Watermain

Preliminary Construction Planning

50 Station Construction Stage 3 – Construct Station Box under the Roadway Decking

Watermain

Preliminary Construction Planning

51 Station Construction Station Complete – Restore Roadway, Utilities & Traffic

Watermain

Preliminary Construction Planning

52 Next Steps a) Meetings in advance of construction (Review and input on traffic and construction staging plans) b) Construction Liaison Groups Smaller groups (10 local representatives per station with local councillor) give input, questions & concerns directly to construction team c) Contact Community Liaisons with specific local issues & recommendations for investigation

Preliminary Construction Planning

53 The Crosstown Team Please get in touch with us

Devin Horne, Franca Di Community Office Hours — 2012 Giovanni, Denise Jayawardene Monday, Wednesday, Friday: E-mail: [email protected] 9:00 a.m. – 5:00 p.m. Online: www.thecrosstown.ca Tuesday & Thursday: by appointment Tel: 416-338-6310 Fax: 416-397-8193 TTY: 416-481-2523 Visit our West Community Office at 1848 Eglinton Avenue West (at Dufferin)

Preliminary Construction Planning

54 Thank You!

Preliminary Construction Planning

55