BALFOUR BEATTY GROUND ENGINEERING Market leading ground engineering SUCCESSFUL SUSTAINABLE SKILLED

Balfour Beatty Ground Engineering offers a wide range of geotechnical services across the construction sector, from piled foundations to ground improvement, testing and analysis. We have established our reputation through our integrated design approach to every project, from the small to the very large. We best demonstrate our capabilities when we’re consulted early on, sharing our expertise and experience to get your project off to a sure start.

CREATING THE INFRASTRUCTURE FOR EXCELLENCE

We make our processes as sustainable as Our ground engineering skills, equipment possible, and are proud to have been the and experience provide a solid fi rst ground engineering company able for every project. We work across all to evaluate our solutions for embedded construction sectors, helping our carbon. Through collaboration with customers achieve cost savings by academic institutions, we make sure fully value-engineering projects using our techniques are at the forefront of the latest design technology. innovation, so that we can offer the Balfour Beatty Ground Engineering. most effective all-round solutions for Success built on strong foundations. our customer’s challenges. FOCUS ON PILING AND FOUNDATIONS

Balfour Beatty Ground Engineering offer a comprehensive range of piling systems in the UK and Ireland.

Rotary large diameter piles

Continuous Flight Auger (CFA) piles

Driven piles

Mini piles

VAUXHALL SKY GARDENS, NINE ELMS, LONDON ROTARY LARGE DIAMETER PILING

Primarily used for large public, commercial and industrial ROTARY BORED PILING TECHNIQUE developments as as transport infrastructure projects, we are one of the largest contractors in this fi eld. We have particular expertise in delivering large, complex and technically challenging projects.

AUGER EXCAVATES AS STEEL CASING SUPPORTS THE HOLE

AFTER INSERTION AT THE DESIGN DEPTH, OF REINFORCEMENT STEEL CASING IS ROTARY BORED PILING RIG A CLEANING BUCKET CONCRETE IS REMOVED LEAVING ENSURES THE BASE OF TREMMIED IN FROM COMPLETED PILE THE PILE IS SOUND THE BASE

To speed up construction of multi-storey Other developments include under THE TECHNIQUE ROTARY BORED PILING TECHNICAL CAPABILITIES projects with deep basements top down reams for very high loads and drilling An auger is used to excavate the , construction is used. This uses plunge fl uids such as bentonite and vinyl DIMENSION FROM TO whilst a steel casing is inserted to columns within piles which enables polymer, where the bore requires PRACTICAL DEPTH n/a 70m maintain the bore through the top layers the construction of the building above support during excavation. DIAMETER 0.45m 3.0m of unstable ground. A steel cage or ground level to commence at the LOAD CAPABILITY 1,000kN 30,000kN (typical range) To save on the construction of pile pattern of reinforcing bars is introduced same time as excavation for the MINIMUM WORKING HEIGHT 12.5m Varies caps they can sometimes be removed into the bore before the concrete is poured. basement, saving months off the TYPICAL RIG WEIGHT 37t 120t altogether by embedding the steel The steel casing is later withdrawn. Where construction period. NOISE PROFILE AT 10m 85db 90db structure directly into the top of large collapsible conditions are expected at UNDER-REAMS Typically 3 x shaft diameter n/a diameter piles. These are known as depth, vinyl polymer or bentonite support DRILLING FLUIDS Bentonite, vinyl polymer n/a monopiles. fl uids can be used. MONOPILES From 0.75m To 3.0m This technique is suitable for all soil types and is ideal for retaining walls. The ability to deal with obstructions and the minimal disturbance created by the method are key strengths. CASE STUDY: THE SHARD, LONDON

THE SHARD IS AN 87-STOREY SKYSCRAPER IN LONDON THAT FORMS PART OF THE Standing at over 300m tall the tallest building in western Europe is LONDON BRIDGE QUARTER DEVELOPMENT supported on Balfour Beatty Ground Engineering Rotary Bored piles, Photography courtesy of www.vincewinterphotography.co.uk up to 1.8m diameter and extending up to 60m in depth.

PLUNGE COLUMNS AT THE SHARD

Of the 166 load bearing piles, 67 had Each of the plunged column piles are Coring of existing underreamed piles plunge columns installed, each inserted designed to carry a working load of up to and foundations also presented to an average vertical tolerance of 1 in 24,000kN and are employed to facilitate challenges that were overcome using 800 which has set new standards in top-down construction which saved bespoke coring equipment. the industry. over six months on the construction programme. The three level basement was retained using 388 no. 900mm diameter hard/fi rm secant piles, and these also supported the fi nal structure. CONTINUOUS FLIGHT AUGER (CFA) PILES

This solution is ideal for noise and environmentally sensitive sites for CONTINUOUS FLIGHT AUGER (CFA) PILING TECHNIQUE both load bearing piles and excavation support. Suitable for all soil types and fast to install, it is ideal for retaining walls as it causes minimal disturbance so posing limited risk to adjacent structures.

DRILLING IN PROGRESS

CFA PILING RIG DRILLING COMPLETED CONCRETE PUMPED THROUGH REINFORCEMENT CAGE ADDED, TO REQUIRED LENGTH HOLLOW STEM AS AUGER EXTRACTED TO COMPLETE THE PILE

Our integrated rig instrumentation system THE TECHNIQUE CONTINUOUS FLIGHT AUGER (CFA) PILING TECHNICAL CAPABILITIES allows us to monitor installation and A hollow stemmed continuous fl ight Two signifi cant factors can infl uence the measure data such as depth, concrete DIMENSION FROM TO auger is rotated into the ground to load of CFA piles – the pressure, volume and productivity. PRACTICAL DEPTH n/a Max 33m the required depth. As the auger is sophistication of the equipment used We use this data to produce graphical DIAMETER 0.35m 1.2m withdrawn, concrete is pumped down and the experience of the operators on representations of pile conformity as LOAD CAPABILITY Dependent on depth and ground conditions the hollow stem under balancing pressure the ground. Our depth of experience a historical reference. MINIMUM WORKING HEIGHT 10m 33m forming a shaft of liquid concrete to and investment in R&D are both key TYPICAL RIG WEIGHT 38,000kg 87,000kg CFA piling ground level. A reinforcing cage is then strengths in this area. NOISE PROFILE AT 10m 85db 90db Auger displacement piling inserted by hand or vibrator. CASE STUDY: READING VIADUCT The new £40 million Reading Viaduct was part of a redevelopment of the whole of Reading Station. Constructed by Balfour Beatty, it will ease congestion by taking fast mainline trains over freight and relief lines.

“Over 20,000 linear metres of piling has been completed by the Balfour Beatty Ground Engineering piling crews. The fact that all of it has been successfully completed within 15m of the operational railway, without any impact on train operations or driver concerns is a major contribution to the satisfaction of passengers on this key route.” Jim Weeden, Reading Station and Area Redevelopment Project Director, Network Rail

The £3.8 million foundations package The ground improvement phase required The VCCs were up to 8m deep, toed Working alongside the live railway, safety “Careful planning was essential to this included the installation of 980 the installation of 1685 vibro concrete into the and required a and logistics have been key to planning project, and our use of lean visual continuous fl ight auger piles up to columns (VCCs), to support the ramps 600mm diameter enlarged head to the project. One of the most critical management has enabled us to closely 1,050mm diameter and 24m deep at the Eastern and Western ends. support a geogrid load transfer platform stages was the installation of piles monitor and control activities as well as through to the chalk , all required which helped support the overlying neighbouring the trackline on the main provide instant updates to Network Rail.” to support the viaduct structure. . London to Swansea line and Reading Rob Cannon, Project Manager, commuter routes. These created a pinch Balfour Beatty Ground Engineering point which required careful planning to accommodate rigs and handling cranes in such a restricted area. DRIVEN PILES

Due to their versatility, driven piles are widely used and are suited PRECAST DRIVEN PILING TECHNIQUE to most ground conditions. They are particularly suited where the founding strata is overlain by soft alluvial deposits or made ground. Driven piles are unaffected by ground water and don’t generate spoil on site.

UNDER PILE MIDDLE PILE OVER PILE

HYDRAULIC HAMMER DRIVES PRECAST PRECAST CONCRETE CONCRETE PILES PILES ARE JOINED BY TO DESIGN LENGTH EITHER UNIJOINT OR OR SET STRUCTURAL MULTIJOINT

DRIVEN PRECAST CONCRETE PILING

Adaptions that can be made to deal with THE TECHNIQUE PRECAST DRIVEN PILING TECHNICAL CAPABILITIES contaminated land include a tapered shoe Precast concrete piles are manufactured Enlarged heads are an add-on to precast at the end of the precast pile to minimise DIMENSION FROM TO by BBGE off site in standard lengths up piles that help spread the load of a risk of aquifer contamination in line with PRACTICAL DEPTH Min 2.5m Unlimited (72m longest to date) to 15m, and driven into the ground using building or embankment over a greater 2 2 2 2 2 Environment Agency guidelines. In areas STANDARD PILE SIZES 190mm 235mm 275mm 350mm 400mm a hydraulic hammer until the required area and ensures that increased loads where environmental disturbance needs LOAD CAPABILITY (typically) 300kN 500kN 800kN 1,200kN 1,500kN depth/resistance is reached. Where a can be placed on the piles without the to be kept to a minimum we offer the (in the right conditions, piles would be capable of carrying greater depth is required, the lengths are risk of the pile puncturing the slab or loads 25% higher than the above indicated fi gures) most up-to-date enclosed hydraulic jointed together using the Multijoint or a geo-membrane. Signifi cant savings in PILE SEGMENT LENGTH Normally between 3m and 15m in one metre increments hammers which signifi cantly reduce noise. pinned UNIjoint. In this way, piles can be slab reinforcement and thickness can MINIMUM WORKING HEIGHT 12m 23m Steel tube and H-piles can be used as as long as required to meet the load be realised when using enlarged heads TYPICAL RIG WEIGHT 36,000kg 67,000kg well, to deal with obstructive ground or bearing specifi cations. Driven piles can on piles. NOISE PROFILE AT 10m 77-82db at rear of rig 85-90db at front of rig where high shear loads need to be taken. also be raked up to 1:3 depending on hammer weight and pile size. Precast concrete piles Steel tube piles Steel H-piles BALFOUR BEATTY HOUSE FOUNDATIONS

This workstream focuses on full design and build foundation packages for housing, as well as for schools, community amenities and light commercial buildings.

DESIGNING PILE AND GROUND BEAM PACKAGES FROM ARCHITECTURAL DRAWINGS

GROUND BEAMS AT BUSHBY, LEICESTERSHIRE FOR GATEWAY HOMES We offer bespoke design packages from Utilising the architectural drawings with pile only schemes to full pile, ground wall line loads, our team of experienced beam and block fl oor solutions. For engineers can design the optimum housebuilders, using a single point of confi guration of piles and precast concrete service for all the foundation work saves ground beams to suit each scheme. Using time and money and ensures that quality assured factory components projects can be managed effectively which are produced and installed to and safely on site. ISO5000 standards, our customers are assured that the system is compliant with all NHBC and LABC standards. MINI PILES

BBGE offer a wide range of high capacity, small diameter piles BOTTOM DRIVEN MINI PILING TECHNIQUE which can be formed in almost any type of ground. Typically used where access or working space is restricted these rigs require minimal site preparation.

ADDITIONAL INTERNAL CASING ADDED DROP AS REQUIRED HAMMER

FULLY WELDED PLUG OF DRY JOINT CONCRETE THIN WALL STEEL TUBE

ON COMPLETION OF DRIVING CASING IS FILLED WITH CONCRETE AND REINFORCED

BOTTOM DRIVEN MINI PILING

We offer the largest fl eet of modern THE TECHNIQUE BOTTOM DRIVEN MINI PILING TECHNICAL CAPABILITIES mini piling rigs in the UK: A thin walled steel tube, closed ended, Once the required depth is reached the DIMENSION FROM TO Bottom driven mini piles is driven in lengths of 1.5m to 6m using tube is fi lled with high slump concrete DIAMETER 150mm 450mm Augered mini piles an internal drop hammer on to a dry or grout. A single steel reinforcing bar, PILE LOADS n/a up to 1,500kN Drilled mini piles concrete plug. The tubes are joined by cage or CHS (Circular Hollow Section) HEIGHT OF RIG 2.2m 8.0m a full fi llet weld as the installation is then inserted. Self-drilled micro-piles LENGTH OF RIG 1.8m 3.3m proceeds. The depth of the piles are Soil nails WIDTH OF RIG 0.7m 1.6m designed using a predetermined set OPERATING DISTANCE FROM FACE OF WALL TO CENTRE LINE OF PILE 350mm 500mm Ground anchors or length criteria. CASE STUDY: BEAULY-DENNY OVERHEAD LINE TOWER BASES, SCOTTISH HIGHLANDS

When complete, the Beauly-Denny Replacement Transmission Line project will have upgraded more than 220km of overhead power lines.

MINI PILING BEAULY-DENNY

The project stretches from Beauly near The is varied and the rocks are The reduction in diameter also improved Inverness, to Denny, near Falkirk in extremely strong. Initial progress was the quality of positional tolerance often challenging and includes slow, despite using four rigs. The cage control. The overall result of our changes the installation of approximately 532 required for the horizontal loads dictated has resulted in a 50% increase in pile new towers. Using eight of our mini piling a 300mm diameter pile in the rock. production on the project. Where access fl eet, Balfour Beatty Ground Engineering By revisiting the entire design philosophy, and ground conditions permit the more is installing a combination of drilled we were able to reduce this diameter cost-effective driven steel tube and mini piles, top-driven steel tubes and by utilising a heavy Ischebeck bar instead precast concrete piling solutions have precast concrete piles to support the of the cage, at the same time as reducing been used. foundations for over 160 of the new towers. pile numbers and overall drilling depth at each tower leg. FOCUS ON RETAINING WALLS

Balfour Beatty Ground Engineering is able to combine a variety of piling and grab techniques for excavation support projects.

Bored pile retaining walls: – Contiguous – Secant

Diaphragm walls

King post retaining walls

WEMBLEY STADIUM, LONDON – CONTIGUOUS PILE WALL BORED PILE RETAINING WALLS

CONTIGUOUS PILE WALLS Used in locations where water retention is not a consideration and soils are stable, contiguous bored walls dispense with interlocking piles completely. Typically a gap of 150mm to 300mm is left between the piles. GAP BETWEEN THE PILES CAN VARY DEPENDING ON SOILS

SECANT PILE WALLS (HARD / HARD AND HARD / FIRM) FEMALE PILE Secant walls are particularly suitable where high water retention is a consideration as they have a positive interlock between adjacent concrete piles. Both male and female piles can be reinforced enabling high lateral loads to be supported. MALE PILE FEMALE PILES CAN BE REINFORCED

SECANT PILE WALLS (HARD / SOFT) FEMALE PILE This wall is used where considerations of height and lateral defl ection are less critical. Female piles use self hardening slurry or unreinforced concrete to provide the seal between the reinforced concrete male piles.

MALE PILE CEMENT / BENTONITE SLURRY PILES SECANT PILE WALL, NARBOROUGH, LEICESTERSHIRE

KING POST WALLS DIAPHRAGM WALLS

Used most frequently for building Either open bored or continuous fl ight Largely used as temporary retaining Diaphragm walls are underground Our experience in diaphragm walling is basements, we can combine this auger techniques can be used to create walls, this system uses a king post structural elements commonly used extensive with projects ranging in size technique with the installation of plunge retaining structures to cater for all (open bore fi lled with concrete to form as retention systems and permanent from 2,000 to 50,000m2 and from a few piles to enable top down construction ground and water conditions. There are a base for steel H-pile). Panels of timber foundation walls. They can also be used metres to over 50m deep. We are and thereby reduce the programme. three broad types of wall. Essentially sleepers, precast concrete or steel sheets as groundwater barriers. A reduced experienced in carrying out complex primary piles are installed at suitable can then be slotted into the H-piles number of joints means that diaphragm operations on restricted urban sites spacing to allow secondary piles to be to form the . walls have improved water tightness and have installed diaphragm walls installed between. compared to secant walls. Diaphragm at Heathrow Terminal 2B, Royal Arsenal Where ground and environmental walls tend to be used for retaining deep Woolwich and in low headroom in the conditions permit the steel H-pile excavations as they can be designed to redevelopment of Westminster Station. (king post) may be installed using take high structural loads. driven techniques. CASE STUDY: HEATHROW TERMINAL 2B This huge project required construction of a 2km diaphragm wall, over 700 piles and over 160 plunge columns for the new terminal building.

Over 43,000m3 of concrete and 7,800 tonnes of prefabricated steel cages were used to construct the piles. There were over 1,100 deliveries to the site for the cages alone!

The diaphragm wall was split into 320 The diaphragm wall was excavated using The piles were all constructed from the We installed 163 plunge columns during Columns were installed using two plunge panels with the length ranging from a hydraulic grab, mounted on the end of existing ground level with the pile -off the Heathrow Terminal 2B project, the frames during both day and night shift 3.1m to over 7m. All the panels were a Telescopic Kelly Bar, carried on a heavy level being between 10 and 15m below largest number ever installed on a project leading to the completion of the plunge 1m wide and constructed to a maximum duty base unit. Bentonite fl uid was used this ground level. in the UK. The columns were plunged columns two weeks ahead of schedule. depth of 25m. In total over 39,00m3 of to provide support to the sides of the into large diameter piles that were Over 43,000m3 of concrete and 7,800 concrete was poured and 6,795 tonnes excavation to prevent it from collapsing. 1,800mm in diameter. Each column tonnes of prefabricated steel cages were of steel, made up of 615 prefabricated weighed approximately 15 tonnes and A total of 705 large diameter piles were used to construct the piles. There were reinforcement cages were installed. was up to 17m in length. The columns installed over a period of seven months, over 1,100 deliveries to the site for the The cages included casting ducts for had to be installed to a strict vertical this equates to around 35km of total cages alone! the anchor construction and couplers tolerance of 1 in 400 and with just a bored length (roughly the distance from for up to three slab connections. The +/-10mm level tolerance. Dover to Calais!). The piles were 1,200mm, slab connection couplers were installed 1,500mm and 1,800mm in diameter to a tight tolerance of +/-50mm. with the average depth being 50m. FOCUS ON GROUND IMPROVEMENT

Balfour Beatty Ground Engineering provide a comprehensive range of ground improvement solutions using state-of-the-state equipment ideal for engineering brownfi eld sites and areas of weak compressible soil.

Vibro stone columns

Vibro compaction

Vibro concrete columns

Dynamic deep compaction

Pencol™

Marine ground improvement

MARINE VIBRO COMPACTION – VANCOUVER DELTAPORT VIBRO STONE COLUMNS

The Vibro stone column system is the most common ground VIBRO STONE COLUMNS BOTTOM FEED TECHNIQUE improvement technique in the UK. Fast and effi cient it can treat a wide range of weak soils and offers signifi cant savings over piling.

VIBRO POKER DISPLACES SOIL

STONE IS ADDED AND COMPACTED IN LAYERS

TIGHTLY COMPACTED STONE COLUMN IS CONFINED BY SURROUNDING SOIL

VIBRO STONE COLUMNS – TOP FEED

THE TECHNIQUE VIBRO STONE COLUMNS TECHNICAL CAPABILITIES

A vibrating poker attached to a purpose- Our ground improvement solutions offer Treatment of a wide range of soil types DIMENSION FROM TO built vibropiling rig is inserted into the the following benefi ts: Specifi cally developed equipment for PRACTICAL DEPTH 1.5m 15m – rig mounted) / 30m – crane mounted ground using a combination of its own Simplifi ed sub structure design and restricted access and limited headroom DIAMETER 0.3m 1.3m mass and the pull-down facility of the rig. 2 construction situations GROUND BEARING CAPACITY Typically up to 200kN/m (higher in granular soils) Once refusal or design depth is achieved MINIMUM WORKING HEIGHT 7m Varies the vibrofl ot is removed and a charge of Little or no spoil generated – avoiding TYPICAL RIG WEIGHT 22,000kg 58,000kg graded stone is tipped into the hole. The the need for expensive disposal costs vibrating poker then re-enters the hole Reduced project time through fast to compact the stone into the soil. The design and implementation process is repeated until a very tightly compacted stone column is formed. Around 30% of the aggregates we Where collapsible soils are present, such use come from recycled sources, as soft and with a high water contributing to the sustainability table, then the bottom feed system is requirements of projects used to form the stone column. CASE STUDY: NATIONAL INDOOR SPORTS ARENA AND VELODROME, GLASGOW

The National Indoor Sports Arena and Velodrome was the main indoor sports facility at the 2014 Commonwealth Games, providing competition venues for track cycling and badminton.

GLASGOW VELODROME

ONE STOP SHOP The £116m project was built in the One advantage to the client was that all of For the curved design of the Sir Chris Hoy east end of Glasgow, close to Celtic’s the required techniques could be provided Velodrome cycling track 1,287 vibro Parkhead ground. by BBGE. This meant the programming, stone columns were installed using communication and coordination required both top and bottom feed methods. BBGE were awarded the work by main was much simpler when compared to contractor Sir Robert McAlpine after The structure was supported by a the alternative of appointing different a value engineered solution was combination of Rotary Bored Piles subcontractors for each technique. proposed utilising: (bores supported using Vinyl Polymer The ground improvement works fl uid), and driven precast concrete piles. Dynamic compaction commenced fi rst with dynamic Vibro stone columns compaction undertaken for the fl oor Large diameter rotary bored piles slab. The slab is lightly loaded and the CFA piles granular ground conditions meant the Driven precast concrete piles dynamic compaction technique was suitable to achieve a bearing capacity of 15kN/m² in this area. FOCUS ON SUSTAINABLE ALTERNATIVES

Balfour Beatty Ground Engineering offer a wide range of sustainable solutions and aim to ensure that the products and services we deliver help to contribute towards our customers’ sustainable targets.

BBGE PRECAST PILE FACTORY – ZERO WASTE TO LANDFILL SUSTAINABLE SOLUTIONS

OUR FACTORIES Our two factories in Scotland and Nottinghamshire manufacture all our precast piles. This means that as well as having full quality control we are also able to ensure they are sustainable. This includes the use of 100% harvested rainwater, 99% recycled steel reinforcement and a minimum of 25% cement replacement in the production of all our precast piles. Having our own factories also means that we are able to produce non standard pile sizes and reinforcement to meet specifi c needs, as well as setting up modular pile production units as required. GEOTHERMAL LOOPS WITHIN CFA PILES GEOTHERMAL PILES Providing Geothermal Piles for use in ground storage systems is one way that we can help with the provision of renewable energy and reduce carbon emissions. Leading by example BBGE developed the fi rst use of Geothermal precast concrete driven piles in the UK which are being used to provide energy for the BBGE offi ce in Scotland.

USING ENVIRONMENTALLY FRIENDLY POLYMER SUPPORT FLUID ZERO WASTE PILING RE-USE OF EXISTING PILES PENCOL™ We launched the UK’s fi rst precast In many city centre developments the Pencol™ offers a highly economical and concrete pile cutting system which has sites have been previously built upon. sustainable alternative to piling. It is a the potential to reduce waste to zero. When redeveloping these urban areas new and effective ground improvement we often encounter old foundations and technique developed to provide enhanced The patent pending system works by existing piles, which cause obstruction bearing capacity and settlement control diamond-tipped twin blades neatly and are problematic. in very weak soils. It works in conjunction cutting precast concrete piles to within with a load transfer mattress which 100mm of ground level. If used in every Using a combination of rigorous integrity, shares the load between the columns BBGE project to the optimum it could materials and can lead to and soil. save up to 2,000 tonnes of harmful C02 existing piles being deemed suitable for emissions per year. re-use, with appropriate warranties given. FOCUS ON TESTING AND ANALYSIS

We are established providers of specialist technical services to the construction industry. PROVIDING SURETY OF DELIVERY

PILE TESTING NOISE AND VIBRATION MONITORING SOUND INSULATION TESTING Through our UKAS accredited team who Our comprehensive range of noise and We are UKAS accredited for sound have a proven track record built from vibration monitoring capabilities includes insulation testing for residential and over 30 years’ experience, we offer: prediction, measurement and the control commercial buildings. Testing is carried of both environmental and personal out in accordance with the Building exposures to noise and vibration. Regulations Schedule E. We also offer Dynamic load testing an acoustic design and testing service DIAGNOSTIC TESTING Integrity testing for UK schools in accordance with Sonic logging We undertake structural, diagnostic and Building Bulletin 93 through our geotechnical monitoring on buildings, partnership with Parsons Brinckerhoff. bridges, car parks and industrial premises. We survey structures to assess the nature and extent of any defects, their probable cause and to allow development of repair strategies.

VIBRATION MONITORING WORKING PLATFORM ASSESSMENT STRUCTURAL AND ENVIRONMENTAL THERMAL RESPONSE TESTING MONITORING As part of the Balfour Beatty Zero Harm BBGE can test the thermal conductivity initiative BBGE have developed a suite of We offer a full structural monitoring of the ground to provide the information tests to assess working platforms and service covering a wide range of necessary to design Geothermal piles, piling platforms constructed with structures including retaining walls, Geothermal and Ground unbound material. Tests include: modern and historic buildings, Source Heat Pumps (GSHP). monuments, bridges, , jetties, Plate Load dams, pavements, pipelines, railways, Clegg Hammer industrial utility plants, earthworks and Light Weight Defl ectometer (LWD) embankments. Ground Penetrating Radar (GPR) Our range of environmental monitoring services include Legionella testing, air quality monitoring and gas monitoring. Balfour Beatty is a global integrated infrastructure services group, WE ARE with operations in over 80 countries. BALFOUR BEATTY

OUR STRATEGIC PRIORITIES

ZERO HARM BECOMING MORE SUSTAINABLE GREAT CUSTOMER RELATIONSHIPS Zero Harm is our commitment to We want and need to be a truly We want Balfour Beatty to be recognised eliminating any injuries or deaths as a sustainable business. Our strategy to in all its market sectors for customer result of our activities and aiming for deliver this is called the Blueprint and focus and collaborative working. We look an Accident Frequency Rate of zero. is based on three central pillars: to build mutual trust through listening and acting on what we are told. We use Zero Harm means eliminating Profi table Markets our customer experience (MAP) reporting hazards, maintaining Zero Harm Through close collaboration with tool to do this. day-to-day, keeping the public safe, our supply chain and the creation keeping our people healthy, working of unique industry partnerships, we Every quarter, from the start of a project with our customers and supply chain. are helping our customers to choose through to its completion, we invite our more sustainable solutions. customers to provide feedback on how We have launched a set of ten Global project delivery is shaping up and how it’s Safety Principles, which apply to all Healthy Communities meeting their expectations in order to help employees of Balfour Beatty and Our activities must improve the quality shape improvements as work progresses. under no circumstances will any of of people’s lives while supporting the our employees carry out a task unless needs of future generations. Our Perfect Landings process helps us they comply with them. They cover: work with our customers and stakeholders Environmental Limits to make sure they get the best out of their Working at height Sustainable development means newly built assets. Restricted areas using less natural resources, as well as managing our environmental risk At its core is a progressive, collaborative Unsupported ground and biodiversity. approach that provides gateway reviews Mobile equipment throughout the project lifecycle. There are clear deliverables that allow all those Energy sources involved to understand the actions required Equipment limits in order to make the project a success. Work over water This all builds towards managing a smooth transition from construction through to Driving handover, operations and after care. Protective arrangements Lone work

2012 OLYMPICS AQUATICS CENTRE – SUPPORTED ON BBGE CFA PILES OPERATIONAL EXCELLENCE PEOPLE AND PERFORMANCE Jobs that deliver what we promised to Our people are accountable and the customer. Our customers get a professional, coming together to make smooth, professional service that involves high performing teams that deliver for good communication and regular reviews our customers. We help them grow where we can see exactly how we are their careers with Balfour Beatty. doing, providing additional support when We have created Communities of Practice it is needed to ensure that our projects where people involved in the core skills succeed physically and commercially. of construction get together, share ideas Every team should fi nish a job stronger: and best practice and help the business developing their capabilities, understanding to understand where it can provide and experience, enabling them to grow further support to improve performance. their careers and helping Balfour Beatty offer an even better service. REGIONAL OFFICES

GLASGOW Balmore, Torrance, Glasgow, G64 4AB t: +44 (0)1360 622000 e: [email protected]

NORTHERN IRELAND The Gasworks, 5 Cromac Avenue, Belfast, BT7 2JA t: +44 (0)28 9044 7608 e: [email protected]

IRELAND City Junction Business Park, SCOTLAND Northern Cross, Malahide , Dublin 17 t: +353 (0)1 867 3722 Glasgow e: [email protected]

BRISTOL NORTHERN IRELAND Stratton House, Cater Road, Belfast Bishopsworth, Bristol, BS13 7UH t: +44 (0)117 983 2000 e: [email protected] Dublin Worsley REPUBLIC WORSLEY OF IRELAND Somercotes Chaddock Lane, Worsley, Manchester, M28 1XW t: +44 (0)1942 898550 e: [email protected]

SOMERCOTES Bristol Birchwood Way, Cotes Park West, Basingstoke Somercotes, Derbyshire, DE55 4QQ t: +44 (0)1773 526300 e: [email protected]

BASINGSTOKE (HEAD OFFICE) Pavilion B, Ashwood Park, Ashwood Way, Basingstoke, Hampshire, RG23 8BG t: +44 (0)1256 400400 e: [email protected] www.bbge.com

Printed on Revive Pure White 100 Silk. Made from 100% recovered fi bre, certifi ed in accordance with the FSC (Forest Stewardship Council). Revive Pure White 100 Silk is a Carbon Balanced Paper – where the carbon intensity has been measured through the production process and an equivalent carbon credit (offset) has been purchased. Laminated using fully biodegradable, cellulose based laminate.