Environmental Safeguard Monitoring Report

Project No. 45148-005 Period Covering January to December 2016 May 2017

Sri Lanka: Greater Water and Wastewater Management Improvement Investment Program - Tranche 1

Prepared by the National Water Supply and Drainage Board for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area Environmental Management & Monitoring Report Annual Report - Year 2016

ADB ASSISTED GREATER COLOMBO WATER AND WASTEWATER MANAGEMENT IMPROVEMENT INVESTMENT PROGRAM

Environmental Management and Monitoring Report

Projects in Colombo city

For the period from January to December 2016

Prepared by Project Management Unit

On behalf of National Water Supply and Drainage Board Ministry of City Planning and Water Supply

Submitted to Resident Mission, Asian Development Bank, Colombo

Greater Colombo Water and Waste water Management Improvement Investment Programme Environmental Management & Monitoring Report Annual Report - Year 2016

Contents LIST OF FIGURES……………………………………………………………………………..…………….....ii

LIST OF TABLES………………………………………………………………………………………….…….ii

LIST OF ABBREVIATIONS……………………………………………………………….……………....……ii

1. Introduction of the Project ……………………………………………………………….….….…………1

1.1. The indicative scope of physical works for the Project 1 & 2…………………………...…….……2

1.2. Project Coverage Areas...... ……..…….…3

2. Construction activities during the period ...... 4

2.1 Key Activities of the project ...... 4

2.1.1 Project 1 ...... 4

2.1.2 Project 2 ...... 5

2.2 Descriptive Details of Physical progress……………………………………..……….………….…...7

2.2.1 Colombo North Area System Rehabilitation – Package I...... 7

2.2.2 Colombo East Area System Rehabilitation – PackageII ...... 11

2.2.3 Construction of office buildings for Area Engineer- Elli House………………………………13

2.2.4 Construction of booster pump stations in Colombo City (Eli house)……………….………14

2.2.5 Construction of existing office buildings for Area Engineer- …………………15

3.Environmental impacts, mitigation measures taken at site and monitoring ...... 16

4.Environmental Monitoring Measures – Base Line Survey……………………………………………...24

5.Status of environmental licenses and permits for rock blasting and plants………..……….…………24

5.Public complaints………………………………………..……………………..……….……………….…..29

6.Conclusion and further actions…………………….……………………………………………….…..….31

Greater Colombo Water and Waste water i Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

LIST OF FIGURES

Figure 1 DMA boundaries for each packages Figure 2 Safety Arrangement for transmission main

LIST OF TABLES Table 1.1. Status of the loan

Table 2.1 Civil contracts in Project I & Project II

Table 3.1. Activities carried out in each subproject, their impacts to environment, mitigation measures, effectiveness and any further action needed

Table 4.1 Baseline Survey – Ambient Air Quality Monitoring Results – Package I

Table 4.2 Baseline Survey – Noise Level Monitoring Results – Package I

Table 4.3 Baseline Survey – Water Quality Monitoring Results – Package I

Table 4.4 Baseline Survey – Ambient Air Quality Monitoring Results – Package II

Table 4.5 Baseline Survey – Noise Level Monitoring Results – Package II

LIST OF ABBREVIATIONS ADB Asian Development Bank

AFD Agence Francaise De Development

CMC Colombo Municipal Council

DMA District Meter Area EA Environmental Assessment EIA Environmental Impact Assessment EMoP Environmental Monitoring Plan EMP Environmental Management Plan EMS Environmental Method Statement EPL Environmental Protection License ES Environmental Specialist GIS Geographic Information System GOSL Government of Sri Lanka GRC Grievance Redress Committee

Greater Colombo Water and Waste water ii Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

IEE Initial Environmental Examination IEER Initial Environmental Examination Report NRW Non-Revenue Water NWSDB National Water Supply & Drainage Board NGO Non-Governmental Organization O&M Operation and Maintenance PCP Public Communications Policy PIU Project Implementation Unit PMU Project Management Unit PPE Personal Protection Equipment PPTA Project Preparatory Technical Assistance RP Resettlement Plan RSC Regional Support Centre SPS Safe Guard Policy Statement SLTB Sri Lanka Transport Board

Greater Colombo Water and Waste water iii Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Environmental Management and Monitoring Report – Projects in Colombo City

January to December 2016 Project Brief on ADB Assisted Greater Colombo Water and Wastewater Management Improvement Investment Program (GCWWMIIP) (Project 1&2)

Project 1: (i) Greater Colombo Water and Wastewater Management Improvement Investment Program (ADB)-Tranche 1

Project 2: (ii) Greater Colombo Water and Wastewater Management Improvement Investment Program (ADB)- Tranche 2 (iii) Ambathale Water Supply Systems Improvement & Energy Saving Project (AWSSIESP)-(AFD)

1. Introduction of the Project

The Government of Sri Lanka undertakes the Greater Colombo Water and Wastewater Management Improvement Investment Program (GCWWMIIP) with the recommendation of the National Water Supply and Drainage Board (NWSDB) and the financial assistance from the Asian Development Bank (ADB), Agence Francaise De Developpment (AFD) and the Government of Sri Lanka (GOSL).

The project comprises of (i) establishing Greater Colombo NRW reduction mechanism; (ii) rehabilitating the water distribution network; (iii) strengthening institutional, operational and maintenance capacity of NWSDB; and (iv) Increasing public awareness on NRW (v) Ambatale Water Supply Systems Improvement and energy saving aspects in water transmission.

The major objectives of the project are:

(i) to increase of water supply availability and efficiency in Colombo city; (ii) enhance the distribution system and reduce NRW from 49% to 18% by the year 2020; (iii) to establish a long-term mechanism to reduce NRW; (iv) to enhance the institutional, operational and project management capacity of NWSDB.

Table 1.1. Status of the loan

Project Number: 45148 Loan Number Project Name Status L2947 / 2948-SRI Project 1- Colombo Water Supply Loan signed on 28th June Service improvement Project (ADB) 2013.

L 3029 / 3030 - Project 2- Colombo Water Supply Loan signed on 03rd June SRI Service Improvement Project (ADB)) 2014.

L 3348 -SRI Project 3 - Colombo Water Supply Loan Signed on 11th August Service Improvement Project (ADB) 2016.

1 Greater Colombo Water and Waste water Management Improvement Investment Programme Environmental Management & Monitoring Report Annual Report - Year 2016

1.1 The indicative scope of physical works for the Project 1 & 2

1) Replacement of System Input Volume (SIV) meters with electromagnetic meters for remote reading; 2) Rehabilitation of Colombo city water distribution network by replacing Cast Iron (CI) pipes with HDPE, PVC & DI pipes as per DMA concept and de-scaling & relining larger diameter pipes, introducing reinforcing pipes, establishment of DMA’s with electromagnetic meters for remote reading; (refer the Annex 1 for the Project Area map) a. Area covered under the project 1 Package 1 & 2: , , , , Bloemendal, Welikada, Boralla, , , approximate pipe length; 194 km, b. Area covered under the project 2 Package 3 & 4: , , Part of , Area, Narahenpitiya, Cinnamon garden, Thimprigasaya, Bampalapitiya, , Wellawatta, Kirulapone approximate pipe length; 350 km,

3) Replacement of identified large customer meters with electromagnetic meters for remote reading; 4) Replacement of defective water meters; 5) Calibration and updating of the GIS network; 6) Replacement of spaghetti pipes with larger diameter pipes; 7) Construction of a NRW building & Area Engineers offices. 8) Implementation of Active Leakage Control policies, speed and quality repairs; 9) Pressure management in District Meter Areas (DMA) and establish customer service Management on GIS based model; 10) Implementation of effective public awareness campaign with effective participation of women and NGOs. 11) Establishing GIS based asset registry for Regional Support Center for Western Central RSC – (WC): 12) Rehabilitation of plumbing system in government apartments.

Greater Colombo Water and Waste water 2 Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

1.2 Project Coverage Areas

Under the ADB project CMC Area of Colombo City will be covered for pipe replacement / rehabilitation works. Colombo city will be divided in to 69 DMAs for easy operation & maintenance. DMAs were divided as sub DMA.

Figure 1- DMA boundaries for each packages

Greater Colombo Water and Waste water 3 Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

2. Construction activities during the period

2.1 Key Activities of the project

Table 2.1. Civil contracts in Project I & Project II

2.1.1 Project 1

Contracts Contract No. Current Status

• Civil Works 1. Colombo CWSSIP/ADB/CIVI • Contract awarded to TODA-Sierra Joint venture on 30th North Area L/ICB/01 October 2014 & commencement on 05 January 2015. System • Trail pit excavation work was completed. Rehabilitatio • On-going works: n – Package I . Pipe laying work in progress – DMA: 2A, 2B, 4A, 5A, 11B and 9A.

. NRW Management work is progressing at DMA 3 & 01. . Transmission main and feeder main laying work is in progress.

2. Colombo CWSSIP/ADB/CIVI • Contract was awarded to Kolon Global Corporation on East Area L/ICB/02 12th March 2015 & commencement on 13th July 2015. System • On-going works: Rehabilitatio . House to house survey completed and final n - Package report preparation is in progress II . Trial trench works is in progress. . Pipe laying work in progress- DMA 25, 30B, 30A, 27B & 18.

• Buildings 3. Elie house GCWWMIIP/ADB/ • Contract awarded to M/s Darinton Construction on Area BUILD/ELLI/NCB/ 11/06/2016 & commencement on 20th July 2016. Engineer’s 02/R • On-going works: Office . Site clearing & rock blasting work completed . Preconstruction works and Raft foundation work is completed. . Column construction up to 1st floor level in progress.

4. NRW GCWWMIIP/ADB/ • Architectural Design of the building was completed and building at BUILD/ Superstructure and sub structure design completed. Maligakanda. NRW/NCB/03 . Bid document preparation and evaluation for civil works completed. . Tender called on 20th October 2016 and closed th on 16 December 2016. . It is under the evaluation stage.

Greater Colombo Water and Waste water 4 Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

2.1.2 Project 2

Contracts Contract No. Current Status Civil Works 5. Colombo West Area CWSSIP/AD • Bid was advertised on 01 Dec 2014 & closed with System Rehabilitation. - B/CIVIL/ICB extension on 20th Mar 2015. Package III /03 • Financial bid evaluation completed. SCAPC and ADB concurrence received. • Cabinet approval received to award the contract. • Contract awarded to China Harbour Engineering Company Limited and China Geo Engineering Corporation JV on 20th October 2016. • Advance payment was paid (ADB part only and GOSL part to be paid) 1. Colombo South Area (CWSSIP/AD • Tendering was closed on 29th August 2014. system Rehabilitation - B/CIVIL/ICB • ADB approval was received for the technical evaluation Package IV /04 on 28/05/2015. • Financial bid evaluation report was approved on 11/02/2016 to award the contract to M/S Sinohydro. The same decision has been forwarded to SCAPC on 15/02/2016. • Cabinet paper has been sent for cabinet approval as per the ADB decision on 23/03/2016 and approval received on 27/05/2016. • Negotiation meeting was held and cabinet approval to be obtained for negotiation report. • Negotiation meeting was held and cabinet approval obtained for negotiation report. • During the appeal period one appeal received and it was withdrawn. • Contract to be awarded to Sinohydro.

Buildings 2. Renovation of central • Soil investigation was completed in LS Yard (the Training center, proposed land for construction). Construction of • Architectural & Structural Consultancy contract was accommodation facilities, awarded to M/s Russell Dandeniya Chartered Architects NRW simulation yard, on 29/09/2015. pipe fitters (plumber) • Structural design and document preparation completed. training workshop, • Bid document preparation completed and it is under the renovation of meter evaluation. testing facility. 3. Construction of existing GCWWMIIP/ • Works completed and building was handed over. office buildings for Area ADB/BUILD/ Engineer- Maharagama MAHA/NCB ( 2nd & 3rd floor ) /01

Greater Colombo Water and Waste water 5 Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Contracts Contract No. Current Status

4. Construction of office GCWWMIIP • Land has been found and advance payment was made to buildings for Area /ADB/BUIL UDA. Engineer- D/PAMAN/ Architectural & structural consultancy bid was called on NCB/04 • 13/07/2016 and was closed on 24/08/2016.

• Bid evaluation completed and awarded to be Archie Triad.

Others 5. Rehabilitation of GCWWMIIP/ • Bid document was advertised on 17/09/2014 & Closed Plumbing Systems in ADB/BUILD with extension on 07/11/2014. However, during the bid Government Apartments /CONDO/N evaluation it was decided to recall the bids. CB/04 • Presently, total contracts divided into 4 packages.

. Package 01: Decided to recall the again (2nd time). Currently, under the document evaluation stage. . Package 02- Tender to be published. . Balance packages under the document preparation stage.

6. (1) Construction of booster GCWWMIIP/ • Document preparation works completed & PPC and pump stations in ADB/PH/NC ADB approved. Bid document was published on Colombo City (Eli house) B/05 14/12/2015 and will be closed with extension on 16/02/2016.

• Bid evaluation completed. PPC approval and ADB approval received • Contract awarded to M/s Drinton construction (Pvt) LTD on 3rd August 2016. • Agreement signed on 22nd September 2016. • Commencement date of contact is 1st December 2016 6. (11) Elli house pump GCWWMIIP/ • Procurement Stage - Tender called on 05th December house mechanical & ADB/PH/M 2016 and will be closed on 30th January 2017 electrical &E/NCB/06

Consultancy 7. Capacity building of GCWWMIIP/ • Contract awarded to M/s Sevanatha Urban Resource communities (NGO) ADB/NGO/ center on 06th June 2016 and agreement was signed. th QBS/04 • Kick off meeting held on 10 August 2016. • Consultancy contract commenced on 1st November 2016.

Greater Colombo Water and Waste water 6 Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016 2.2 Descriptive Details of Physical Progress Critical construction activities that were carried out in each project during the reporting period are listed below

2.2.1 Colombo North Area System Rehabilitation – Package I

(a) Civil work (i) Trial pits, Trial trenches Trial trenches excavations required for verification of the model as well as for the 1200mm. transmission line have been completed for all DMAs. Altogether, 270 locations were excavated. Almost all such locations are permanently reinstated now.

Trail pits and trial trenches excavation works are carried out during the less in day time and mostly done at night time to minimize the public disturbances. Contractor has properly used traffic signs –(Road works ahead & Mandatory signs) and safety equipment ( warning and safety sign boards, safety jackets, safety helmets, safety gloves ,gum boots barricade tapes, traffic cones & blinking lights) have been provided.

(ii) Distribution Line Pipe laying work commenced on 24th July 2015 with the final approval of the detail design of DMA 1 & 3. Work in DMAs 2A, 2B, 5A, 11B and 9A are in progress. The CMC was granted principle approval to groups of roads in each DMA when the application, along with details such as trench width, pipe diameter and details of the roads, is made. Further, CMC was granted approval for pipe laying in 17 roads in DMAs 2A & 2B. The total length of pipe laying done is 35,684.47 m. with pressure testing done in 24, 241.13 m successfully. The contractor is equipped with all the safety gear for workmen, equipment necessary for road safety during the night work with lighting, excavation and road reinstatement, GPS equipment used for recording locations of pipe and other utilities. House to house survey was carried out before commencement of the work.

(iii) Transmission main Laying and Connecting of DI Pipes Supply and installation of Ductile Iron transmission main from bridge at Sedawatta to existing Ellie House reservoir. The total length - 2,081 m. Inspection was done in existing Sewerage, Telephone, Electricity, Water and any other utility lines. Excavated trial pits in every 25m interval to identify the rock areas and Utility lines. Shoring arrangement was done wherever necessary. Carried out trial excavation for 1 m length in 100m interval to determine the shoring requirements and soil test (depth of 2.5 m and width 2.0 m). Backfilled the trial pits with suitable soil after 8hrs inspection. Pipe installation done day & night, traffic diversion, utility diversion (if any) etc. If the excavated soil was unsuitable, quarry dust used for backfilling. Back filling and compaction was done layer by layer.

Greater Colombo Water and Waste water Management 7 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016 Permanent Reinstatements Permanent Reinstatements was carried out after completion of backfilling and compaction according to the specification. Scarified and trimmed the broken edges a base of ABC was laid and compacted by means of roller. Compacted ABC layer was 225 mm thickness of (to attain minimum 98% MDD as per specification).Applied a prime coat of emulsion bitumen (CSS 1) - at the rate of 0.5 litter per square meter. Overlaying of bituminous coat with the application of 50 mm thick asphalt concrete was done.

Safety Arrangement Safety cones, Information boards, barricades, warning signs was place along the excavation area. Deployed two traffic controllers beside the construction area to control the traffic. Strong metal plate was placed crossing over the trench, if the excavated trench crosses the footpath. In the event of road closure, prior approval was taken from relevant authority. Blinking lights was provided for open excavated areas at night time barricade tapes was provided for open excavations. Note: Constantly one side of the road was allowed access for people and vehicles, to minimize the disruption of the entering and exiting. Other side of road closure for construction work.

Sedawatta Bridge Ellie House

75m - 100m Trench 75m - 100m IB IB SC SC B B FM FM B B SC SC SC

Road Center

Carriage way

Legend; IB Information Board SC Safety Cones B Barricade Board FM Flagmen ------Barricade Tape Figure 2 - Safety ArrangementFigure 01 for transmission main

Greater Colombo Water and Waste water Management 8 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

HDPE Pipe laying Transmission Main Pipe laying

Trial trench works

Pipe laying works

Greater Colombo Water and Waste water Management 9 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016 (b) Public Awareness Programme

Shifting of Water Meter to accessible location In accordance with the requirement of water meter location changing in the Crow Island area (DMA 03), a comprehensive House to House awareness programme conducted successfully with the participation of the PMU Sociologist, PIU officers & TODA-Sierra officers. This programme were carried out under the supervision of project manager of package 01.

Project awareness leaflets in all three languages (Sinhala, Tamil & English) was distributed to the consumers in DMA 03 area (Crow Island),

This leaflets highlighted main 04 reasons concerning the important for dislocation of water meter in both parties,

House to house surveying

Greater Colombo Water and Waste water Management 10 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016 2.2.2 Colombo East Area System Rehabilitation - Package II

(a) Civil work Trail pit excavation and pipe laying Public awareness was done by contractor before commencing trial trench and pipe laying. Awareness notices were distributed to public to make them aware of the on-going project activities. The Contractor coordinate with relevant authorities and other parties through the Employer and obtains permission for the excavation and pipe laying. SLTB and private bus companies were informed at least one week before, if any traffic re-routing happens due to the excavation and pipe laying work. In such case, alternative routes was provided and at the both ends of the closed roads signs was be placed. During excavation, half of the road was closed to minimize the disturbance. Traffic control and the road safety program proposed during the day and night. Traffic controllers were provided with illumination (Duel Color) traffic controlling battens to manage the traffic. Further, hazard warning flash lights were installed to warn the motorists in night. Traffic signs and safety equipment’s ( warning and safety sign boards, safety jackets, safety helmets, safety gloves, gum boots, barricade tapes, traffic cones & blinking lights were provided during excavation. The Contractor was take reasonable measures to control air pollution due to dust from their construction activities. Earth surface causing emission of dust was kept moist with water. Dusty material in piles or in transit was covered as practical as possible to prevent blowing in the wind. Sufficient number of water bowsers was used to above purpose. Machinery and equipment was operated under normal conditions to avoid noise. The Contractor was maintain the roads to be reinstated until they are permanently reinstated after completing pipe laying work including pressure testing of pipelines and testing of the backfill of the trenches.

Pipe laying

Greater Colombo Water and Waste water Management 11 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Safety meeting

Toolbox meeting

Safety arrangement at site

Greater Colombo Water and Waste water Management 12 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016 (b) Public Awareness Programme House to house surveying In consultation with the PMU of the NWSDB, a project awareness leaflet in two languages (Sinhala & Tamil) was distributed to the consumers before commencing trial trench work. Public was educated about the area that the civil work is to be done and about the inconveniences that they can undergo.

House to house surveying

2.2.3 Construction of Ellie house Area Engineer’s office The proposed building is designed as five story building and it is planned to construct first three stories under this contract. The work comprises of Construction of first three stories in the building with a total floor area of approximately 1,376.00 m2. Site clearing & rock blasting work completed. Chemical blasting approved due to dust emission and noise. Column construction up to 1st floor level in progress. Safety precautions following at the construction site.

Rock blasting by using chemical Site clearing & levelling

Greater Colombo Water and Waste water Management 13 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Preparation for Column concerting

2.2.4 Construction of booster pump stations in Colombo City (Eli house) Construction of proposed pump house at Ellie House, and caretaker quarters. The proposed pump station is having eleven pumps and total floor area is around 500 m2. Commencement date of contact is 1st of December 2016, mobilization work and site clearing in progress

Site clearing & levelling

Construction area cover by Fence and safety mesh

Greater Colombo Water and Waste water Management 14 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016 2.2.5 Construction of existing office buildings for Area Engineer- Maharagama

(a) Civil Work

Works completed and building was handed over

External view of office building

Internal partition of office building

Greater Colombo Water and Waste water Management 15 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

3 Environmental impacts, mitigation measures taken at site and monitoring Key activities discussed under section 2 have been carried out in each subproject during the reporting period. These activities in general have impacts on physical, ecological and social environments for which mitigation measures have been taken by the contractor under the supervision of PIU and PMU. The effectiveness of mitigation measures have been monitored and recorded by the contractor and PMU. In cases where further actions were needed, the PMU has advised the contractor. Table 3.1 below summarizes the activities carried out in each subproject, their impacts to the environment, mitigation measures taken to avoid/ minimize the adverse impacts, effectiveness of the mitigation measure adopted and any further action needed.

Table 3.1. Activities carried out in each subproject, their impacts to environment, mitigation measures, effectiveness and any further action needed

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Subprojects in Project I - Package I - Colombo North Area Pipe laying work – Distribution Main and Transmission Main Excavation of • Income losses to  Ensure careful planning and scheduling of No. of Prior to  Plan and Schedule for Road Closures trenches shop owners the activities public start the of  Contractor has provided one way - Work • Difficulty faced to  Prepare a traffic management plan and complaints civil work access without disturbing the public/ Schedule and pedestrians road safety plan related to vehicle movement. Closure of • Create traffic road closure  No accident was recorded during the Areas congestion in such reporting period. area.

- Barricades • Risk of accidents to  Placing of barricades and warning signs No. of Once a  No accident was recorded during the and Warning public, workers and such as those made of high reflector plastic accidents month reporting period due to open trenches. Signs animals. materials. recorded  Also use aluminized rolled warning signs due to open to warn the public. trenches.

16 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Excavation of • Develop health  Access and other cleared surfaces including No. of Weekly  No public complaints were received trenches problems from long backfilled trenches was dampened public during the reporting period. - Dust term exposure to whenever possible and especially in dry complaints  Contractor has carried out spraying of emission and high levels of dust. and windy conditions regarding water around the construction site air pollution  Spraying of water along the access road and dust. within the site - Generation

of noise • Harm the activity or  Machinery and vehicles were kept in good Public Weekly  No complaints on noise were received balance of human or working condition complaints during the reporting period. animal life.  Notices of particularly noisy activities were on noise  Contractor used noise control such as

• Can cause given to residents / businesses adjacent to using low-noise excavators, hypertension, high the construction site. jackhammers, drills, and power stress levels, tinnitus,  Noisy activities were restricted to the times generators. hearing loss, sleep given in the Project. disturbances, and other harmful effects

- Temporary • Difficulty faced to  Provide temporary cover slabs over No. of Monthly  The Contractor has provided stock steel loss of access pedestrians tranches. public plates and wooden planks which were to public • Risk of accidents and  Back fill the trenches as soon as the pipe complaints deployed on top of trench excavation to health hazards to laying is completed. related to provide temporary access to buildings workers  Expedite works in front of businesses with loss of and other areas where these were increased manpower to limit time of access. necessary. disruption  Advance road signage indicating the road detour and alternative routes.  Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/ complaints.

17 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Excavation of • Risk of accidents and  Display of safety and warning sign boards Number of Monthly  minor accident and work-related trenches & health hazards to at site. Accidents injuries pipe laying workers  Employ workers with adequate experience, and Work-  Less complaints from community and - Occupational training and conduct Tool box meeting Related workers Health and before commencing construction work Injuries  Further improvement of safety and Safety  Use safety precautions to minimize risk warning sign boards at site during construction i.e. safety helmets,

safety shoes, dust masks, gloves and reflective jackets No. of Monthly  Monthly awareness trainings are

 Contractor follow awareness of the general trainings conducted by the contractor’s staff. given to rules:  Contractor has carried out at least tool - no alcohol/drugs on site; workers on box training daily and safety meeting in

- prevent excessive noise; health and monthly. - safety construction staff are to make use of the facilities - other than pre-approved security staff, and - no worker was forced to do work that is potentially dangerous or that he/she is not trained to do.

18 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Excavation of • Risk of accidents and  Provide walkways and metal sheets where No. of Monthly  No public complaints were received trenches & health hazards to required to maintain access for people and public during the reporting period. pipe laying workers vehicles. complaints - Community  inform neighbors in writing of disruptive related to Health and activities at least 24 hours beforehand loss of Safety  Provide sign boards for pedestrians to access inform nature and duration of construction works and contact numbers for No. of Monthly  Further Safety arrangement and concerns/complaints. minor warning signboards needed.  Ensure that any damage to properties and accidents at  No fatal accidents were recorded utilities will be restored or compensated to site. during the reporting period. pre-work conditions.  The site must be kept clean to minimize  Lighting on the construction site pointed the visual impact of the site downwards  Machinery and vehicles kept in good working order for the duration of the project

19 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Subprojects in Project I - Package II – Colombo East Area Trail Trenches & Pipe laying work Excavation of • Difficulty faced to  Ensured careful planning and scheduling of No. of Daily  Proper Plan and Schedule for Road trenches pedestrians the activities public Closures - Work • Create a traffic flow  Prepared a traffic management plan and complaints  Contractor has provided one way Schedule and in such area. road safety plan related to access without disturbing the public/ Closure of loss of road vehicle movement. Areas closure  Complains and accidents were not recorded during the reporting period. Excavation of • Risk of accidents to  Placed of barricades and warning signs No. of Daily  No accident was recorded during the trenches public, workers and such as those made of high reflector plastic accidents reporting period. - Barricades animals. materials. recorded and Warning  Also use aluminized rolled warning signs due to open Signs to warn the public trenches. - Dust and air • Develop of health  Access and other cleared surfaces including No. of Daily  Less public complaints were received pollution problems from long backfilled trenches were dampened public during the reporting period. term exposure to whenever possible and especially in dry complaints  Constantly contractor has to provide high levels of dust. and windy conditions regarding spraying of water during construction dust.

- Generation • Harm the activity or  Machinery and vehicles are kept in good Public Daily  Few complaints were received about of noise balance of human or working condition complaints noise issue during the reporting period. animal life.  Notice of particularly noisy activities was on noise  Contractor has to control noise • Can be cause given to residents / businesses adjacent to especially in night time. hypertension, high the construction site. stress levels, tinnitus, hearing loss, sleep disturbances, and other harmful effects

20 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Excavation of • Risk of accidents and  Display of safety and warning sign boards Number of Monthly  Zero accident and work-related injuries trenches health hazards to at site. Accidents  less complaints from community and - Occupational workers  Employ workers with adequate experience, and Work- workers Health and training and conduct Tool box meeting Related  Further improvement of safety and Safety before commencing construction work Injuries warning sign boards at site  Use safety precaution to minimize risk during construction i.e. safety helmets, No. of Monthly  Monthly awareness trainings are safety shoes, dust mask , gloves and trainings conducted by the contractor’s staff. reflective jackets given to  Contractor has carried out at least one  Contractor follow awareness of the general workers on tool box training per weekly. rules: health and - no alcohol/drugs on site; safety - prevent excessive noise; - construction staff are to make use of the facilities

- Community • Risk of accidents and  informed neighbors in writing of disruptive No. of Monthly  No public complaints were received Health and health hazards to activities at least 24 hours beforehand public during the reporting period. Safety workers  Provide sign boards for pedestrians to complaints inform nature and duration of construction related to works and contact numbers for loss of concerns/complaints. access  Ensure that any damage to properties and utilities will be restored or compensated to No. of Monthly  Safety and warning signboards have pre-work conditions. accidents at been displayed at site. No fatal  Lighting on the construction site pointed site. accidents were recorded during the downwards reporting period  Machinery and vehicles kept in good  The site must be kept clean to minimize working order for the duration of the the visual impact of the site project

21 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Subprojects in Project 2 - Elie house Area Engineer’s Office Construction of office buildings Site clearing • Induced hearing loss • For rock breaking, use non-explosive Public Daily  No complaints were received during and Rock is irreversible blasting chemicals, silent rock cracking complaints during the reporting period blasting damage to the ears chemicals. on dust period  Regularly spraying of water within - Generation caused by exposure the site area to control dust of noise to high levels of noise. • Regularly breathing • Blasting area were dampened whenever - Emission of can cause diseases possible and especially in dry and windy Dust like lung cancer, conditions asthma, Chronic • Construction area covered metal sheets Obstructive fenced and safety net Pulmonary Disease and silicosis. Preconstruction • Can be cause • Construction works that create noise Public Monthly  No complaints on noise were received works, Raft hypertension, high nuisance are stopped during day time. complaints during the reporting period. foundation and stress levels, tinnitus, • Control excessive sounds and vibration on noise & Column hearing loss, sleep • Control dust by spraying water in site dust construction disturbances, and • Display of safety and warning sign boards - Generation other harmful effects at site of noise • Develop of health • Laying the safety net around the building

- Construction problems from long • Provide Safety Barriers in open pits No. of Monthly • No accident was recorded during the Dust term exposure to • Use safety helmets, gloves, eye protection, minor reporting period high-visibility clothing, safety footwear accidents at All machinery and equipment has to - Safety high levels of dust • and safety harnesses site kept in good working order for the • Risk of accidents to • Display of safety and warning sign duration of the project period to public and workers boards at site minimize noise nuisance

22 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Construction Environmental Impact Mitigation Measure/s Adopted Monitoring Monitoring Effectiveness & further actions needed activity indicator frequency Establishment • Risk of accidents • Camp and working areas are kept clean Open waste Weekly  Wastes have to be placed in the and and health hazards and tidy at all times. dumps at designated skips / bins which are maintenance to workers. • Properly dispose construction debris and site. regularly emptied. These are remain of site office, • Accumulation and dewatering (eradicate mosquito breeding) within demarcated areas and are yard and disposal of solid and • Bins and/or skips are emptied regularly No. of Monthly designed to prevent wastes from being labour camp. kitchen waste and waste are disposed of at the pre- trainings blown out by wind. - Occupational approved site. given to • Waste bins have to be located in labour Health and • These are remain within demarcated workers on camp and site office. Workers have been Safety areas and designed to prevent wastes health and instructed to dump waste only to the from being blown out by wind. safety bins. Collected waste material has to be • Workers are provided with proper disposed only at approved locations. accommodation with sanitary facilities and No. of Monthly Good housekeeping was observed at Personal Protection Equipment (PPE) accidents at site. site • The Contractor ensure that all litter is collected from the work and camp areas daily. • The Contractor ensure that his camp and working areas are kept clean and tidy at all times • The Contractor has fenced off safety mesh over the building. • All workers have to be supplied with mosquito nets and proper water service. • Monthly safety meeting has to be conducted by the contractor’s staff • Monthly awareness trainings has to be conducted by the contractor’s staff.

23 Greater Colombo Water and Waste water Management Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

4. Environmental monitoring measures - Base Line Survey The term “baseline” refers to conditions existing before development against which subsequent changes can be referenced. An Environmental Baseline Survey helps to understand existing environmental conditions thus defining the focus of the environmental impact analysis and resources that need protection through appropriate and viable mitigation measures. Based on the approved EMoPs, the Package I &II, contractors have to carry out the monitoring of selected environmental parameters such as ambient air quality, noise levels and the water quality periodically. The contractor should monitor the above parameters during the pre-constructing (baseline) and construction period of project.

Colombo East Area System Rehabilitation – Package II Monitoring of ambient Air quality Water and Noise had been monitored at the pre - construction stage by the contractor in the month of Mach 2016 and a June 2016. The observer of the event of Air quality and Noise is National Building Research Organization (NBRO) and the event of Water is National Water Supply & Drainage board (NWS&DB). The final observations should be done during construction stage.

Table 4.1 Baseline Survey – Ambient Air Quality Monitoring Results- Package I Standard Time Base Line Data Concentration Average ( µg/m3 ) Colombo 10 - Colobmo 08 - Colobmo 05 – Bodiraja Mawatha Noris channel Gajaba road

CO 10,000 8 hrs 4000 4000 3000

SO2 80 24 hrs 25 19 20

NO2 100 24 hrs 41 28 29

PM10 100 24 hrs 72 54 41

PM 2.5 50 24 hrs 40 29 22

Greater Colombo Water and Waste water Management 24 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Table 4.2 Baseline Survey – Noise Level Monitoring Results- Package I The Maximum Permissible Noise Level Day Time 75 dB Leq (A) for the construction Activity Night Time 50 dB Leq (A) Location Time Run time Measured Residual (min) Noise Level Leq (dB) Colombo 10 - Bodiraja Morning 15 76 Mawatha Day 15 76 Evening 15 75 Night 05 71 Colobmo 08 - Noris Morning 15 70 channel Day 15 70 Evening 15 67 Night 05 61 Colobmo 05 – Gajaba Morning 15 58 road Day 15 55 Evening 15 64 Night 05 56

Table 4.3 Baseline Survey – Water Quality Monitoring Results –Package I Requirement Well at Well at Well at Canal at Canal at Roney Heen Ela (SLS 614:14 Vidyodaya Wanathamulla Ketharamaya Street Canal at Part 01) Pirevene - Narahenpita Maximum Maligakanda

Physical and Chemical Physical Quality Colour (PtCo) 15 Less than 1 1 4 189 212 245 Turbidity (N.T.U.) 2 0.2 0.5 1.5 10.1 9.2 27.1 Chemical Quality PH 6.6 6 6.6 6.9 7.1 6.8 Electrical Conduciivity 750 µs/cm 238 176 345 419 391 351 Result in mg/l Chloride ( as Cl ) 250 25 27 27 53 53 40

Total Alkalinity ( as CaCO3) 200 47 36 90 162 122 135

Free Amonia ( as NH3) 0.06 Less than 0.01 0.05 1.6 15.4 11.9 13.25

Nitrate (as NO3) 50 9.1 4.9 4.3 0.3 0.5 Less than 1

Nitrite (as NO2) 3 0.115 0.003 0.093 0.131 0.095 0.034 Fluoride (as F) 1 0.08 0.16 0.06 Less than 0.01 Less than 0.01 Less than 0.01

Total Phosphates(as PO4) 2 0.09 0.1 0.2 3.89 1.68 2.22 Total Residue 500 159 117 230 279 261 234

Total Hardness ( as CaCO3) 250 84 80 150 90 100 100 Total Iron (as Fe) 0.3 0.01 0.02 0.11 0.38 0.51 0.42

Sulphate (as SO3) 250 59 64 87 53 29 2 Bacteriological Examination of water Temperature 27.10C 27.10C 27.10C 27.10C 27.10C 27.10C Total number of all types of Less 10 19 57 89 TNC TNC 58 NumberColoform of bacteria E.Coli inpresent 100 ml in of none 49 33 53 TNC TNC 41 Remarkssample at 440C Unsatisfactory. Unsatisfactory. Unsatisfactory. Unsatisfactory. Unsatisfactory. Unsatisfactory. There is an There is an There is an There is an There is an There is an *TNC - Too Numerous to evidence of evidence of evidence of evidence of evidence of evidence of Count recent faecal recent faecal recent faecal recent faecal recent faecal recent faecal pollution. pollution. pollution. pollution. pollution. pollution.

Greater Colombo Water and Waste water Management 25 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Monitoring of ambient Air quality

Monitoring of Noise level

Samples collection for monitoring Water quality

Greater Colombo Water and Waste water Management 26 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Colombo North Area System Rehabilitation – Package I Monitoring of ambient Air quality and Noise had been monitored at the pre - construction stage by the contractor in the month of August 2016. The observer of the event of Air quality and Noise is National Building Research Organization (NBRO). The final observations should be done during construction stage The observed results are given in Tables

Table 4.4 Baseline Survey – Ambient Air Quality Monitoring Results – Package II

Standard Time Base Line Data Concentration Average ( µg/m3 ) Mattakkuliya , Sri Colobmo 15 – Colobmo 14 – Wickrama Mawatha Modera, Blumendhal Road ( Church Road) Mutuwella Road - Price of Wales

CO 10,000 8 hrs 2500 3000 2000

SO2 80 24 hrs 23 18 22

NO2 100 24 hrs 40 28 35

PM10 100 24 hrs 91 74 69

PM 2.5 50 24 hrs 53 40 31

Table 4.5 Baseline Survey – Noise Level Monitoring Results – Package II The Maximum Permissible Noise Level Day Time 75 dB Leq (A) for the construction Activity Night Time 50 dB Leq (A) Location Time Run time Measured Residual (min) Noise Level Leq (dB) Colombo 10 - Bodiraja Morning 15 80 Mawatha Day 15 77 Evening 15 75 Night 05 58 Colobmo 08 - Noris Morning 15 78 channel Day 15 79 Evening 15 78 Night 05 71 Colobmo 05 – Gajaba Morning 15 76 road Day 15 77 Evening 15 81 Night 05 71

Greater Colombo Water and Waste water Management 27 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Monitoring of ambient Air quality

Monitoring of Noise Level

5. Status of environmental licenses and permits for trial trench and pipe laying work All contractors were instructed to obtain all necessary approvals and licenses such as Environmental Protection License (EPL). Permits were obtained from following organizations by Package I & Package II for construction activities  Geological Survey & Mines Bureau  Road Development Authority  Colombo Municipal Council  Sri Lanka Land Reclamation and Development Corporation(SLLRDC)  Sri Lanka Police  Sri Lanka Telecom  Ceylon Electricity Board

Greater Colombo Water and Waste water Management 28 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

6. Public complaints Grievance Redress Mechanism (GRM) was established on 3rd February 2016 and 10th February 2016 for package II to receive, evaluate and facilitate the resolution of AP’s concerns, complaints and grievances about the social and environmental performance at the level of the project.

The Grievance Redress Committee (GRC) will have the following as members: Divisional Secretary as Chairperson, GCWWMIIP Project Director, PMU Social Development/Safeguards Officer as the Convener, Project Public Relations Officer, Director of the project NGO, the Area Engineer, Maigawatta (NWSDB), representatives of APs, Community Based Organizations (CBOs), and eminent citizens.

Grievance redress/ suggestion forms, complaints / suggestion boxes and complain register was placed at following four locations.

1. Divisional Secretary office –Colombo & Thimbirigasya 2. Project Management Unit -Wellawatta 3. NWSDB, Area Engineer’s Office –Maligawatta 4. Contractor’s office –Colombo 08 .

GRM establishment meeting – DS Thimbirigasyaya - Package II

GRM establishment meeting – DS Colombo - Package II

Greater Colombo Water and Waste water Management 29 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

Contractor is maintaining a public complaint register. However no written public complaint has been received during the reporting period although minor complains were received due to dust emissions, damages of road & fence and reinstatement of road, constructor was rectified such damages and control the duct emission.

Complain box placed at Contractor’s office Complain box placed at Area Engineer’s Office

Complain box placed at Divisional Secretary office –Thimbirigasya Complain box placed at Project Management unit

Complain box placed at Divisional Secretary office –Colombo

Greater Colombo Water and Waste water Management 30 Improvement Investment Programme

Environmental Management & Monitoring Report Annual Report - Year 2016

7. Conclusion and further actions The project will benefit the general public by contributing to the long-term improvement of water supply system and community livability in Colombo City. The potential adverse environmental impacts are mainly related to the construction period, which can be minimized by the mitigating measures and environmentally sound engineering and construction practices.

The ongoing works of sub projects did not make vital impacts to the surrounding environment. However, observations revealed that there were some impacts due to dust emission. It was exposed that construction safety and the occupational safety activities which are very poor at Package I. The contractors of Package I should further improve their safety culture/occupational safety and construction safety.

The ongoing construction works may have caused traffic congestion due to high volume of traffic and narrow condition of existing roads, Therefore a good traffic control plan must be implemented throughout the working period.

The project’s Grievance Redressal Mechanism was established. No significant issues were observed during the reporting period. The contractors should give attention to reduce public nuisances caused by the construction works, especially they involved for rectification activities on utilities and house damages.