All About EVs Welcome and introduction Richard Hartshorn – EV Readiness Manager Safety Moment Purpose: To work with the Council, EV Express and Project EV and offer an information webinar for IOW stakeholders To present SSENs EV Strategy and sign-post our plans To highlight the EV process including application and design To present a high-level overview on our system planning process To present an overview of the network planning process system David Thornton (Ev Express) will introduce some core features around charge points Richard Pink (Project EV), will talk through the application, opportunities and considerations around EV charging To introduce John Lancaster - SW Energy Hub Project Manager - Energy Hub UK

Attendees: Isle of Wight based - tourism, hospitality, construction, manufacturing and service sectors as well as consultants, housing developers, the IoW Council and Chamber of Commerce

Purpose of the Day AGENDA – TIMINGS ARE A GUIDE ONLY TIME

Introduction, Safety and EV Strategy overview 10:05 – 10:15am Richard Hartshorn – EV Readiness Manager

David Thornton and Richard Pink 10:15 – 10:45am

Q&As 10:45am – 11am

EV application and design processes including Q&As – Ian Jessiman - Account Manager and James McNeish – Connections Design 11am – 11:15am Manager

Overview of System Planning – Yuan Gao – System Planner 11:15am – 11:20am

Overview of Network Planning – Rafael Rigoni – Network Planning 11:20 – 11:30am Engineer

Q&As 11:30 – 11:45am

Feedback and close 11:45am SSEN STAFF EMAIL

Sian Hughes – Lead Connections Engagement Manager [email protected] Debbie Watts – Connections Engagement Coordinator [email protected]

Alex Howison - Flexible Solutions Manager [email protected]

Richard Hartshorn - EV Readiness Manager [email protected]

Yuan Gao - System Planner [email protected]

Rafael Rigoni - Network Planning Engineer [email protected]

Paul Dawson-Plincke- Connections Designer [email protected]

Robert Arthur - Account Manager (SEPD) [email protected]

Abigail Furey – C&E Team Manager [email protected]

James McNeish – Connections Design Manager [email protected]

Ian Jessiman – Account Manager (SHEPD) [email protected]

Jasmin Myhill – Customer Relationship Manager (south east) [email protected]

Paul Towsey – Connections Delivery Manager [email protected] Go to Enter the Use the link code Audience provided in IOW20 Q&A function IM chat to ask a question or the Teams Chat facility

Online Interaction Tool EV Strategy SSEN today

Scottish and Southern Electricity Networks (SSEN) own and operate two distribution networks and one transmission network

Core purpose: To provide a safe, secure and reliable supply of electricity to nearly 3.8 million customers

Vision: To deliver a network that meets both Government ambitions and the aspirations of our customers in a smart, cost-effective and timely manner

45,000 40,000 20,000 EV chargers EVs registered installed HPs installed

9 EV Strategy 2020 Launched March 2020 Digital Strategy

Developed using stakeholder engagement, March DSO Strategy innovation and future vision

Builds on sister documents; Digital Strategy and DSO Strategy

Is focussed on our stakeholders’ experience Vision for Future Experiences What will stakeholders benefit from in coming years?

These are capabilities that have been requested

We are already working on delivering these experiences

11 Our strategic approach How we will facilitate EV uptake and make sure SSEN remains ‘EV ready’

12 Details of actions

For each principle we delve into actions needed to accomplish them

Provides visibility of what we are working on

Shows links with work in DSO and Digital strategies

Highlights areas stakeholders have specifically requested we focus on

13 Case studies

Highlights some of the key initiatives we’ve undertaken

A small part of our portfolio

More details can be found using the hyperlinks or contacting us

14 Consultation

Strategy needs to evolve

Chance to give anonymous feedback

Will help us refine our approach to helping you

Strategy available on our website www.ssen.co.uk/EV

15 Accelerating a Green Recovery

Investing in EV Key recommendations infrastructure and solutions to meet net Empower communities with LAEPs zero targets ssen.co.uk/EV End sale of ICE vehicles from 2030

202 0 Unlock private investment through area- wide tenders July

16 RIIO-ED2 CORE PRINCIPLES RIIO-ED2 is a five year ‘price control’ period from April 2023 to March 2028 VALUE FOR MONEY …focusing on efficiency and creating value for customers Each DNO must put forward a business plan and communities to the energy regulator, Ofgem, on the investment it requires for this period INNOVATION All proposals require strong justification of …embracing new ways of doing things for the benefit of engineering evidence, CBA and stakeholder customers and communities support TRANSPARENCY Our aim is to develop a business plan that is …being open and accessible in our activity and focused on, created with and trusted by our engagement customers and stakeholders

17 Go to Enter the Use the link code Audience provided in IOW20 Q&A function IM chat to ask a question or the Teams Chat facility

Q&A David Thornton – EV Express EV charging opportunities

Presentation supported by: Presentation format

• 2 parts • Introductory info (EV Express) • Applications, opportunities and considerations in various settings (Project EV) Growth of EV new car regs Charge points – essential info

• Premium pay for Fast chargers: quicker charge time • 7kW (single phase) to 22kW (3 phase) experience • 100% charge times (e.g. Renault Zoe): 9-12 hours to 3-4 hours • Range (e.g. Renault Zoe = 245 miles). 1 hour charge = approx. 27 miles on 7kW unit

Rapid chargers: • 40kW to 100kW+ (spec rising to 150kW) • 100% charge times (e.g. Renault Zoe): 30 mins to 2 hours, depending upon output and AC or DC options Fast chargers

• Residential & commercial settings • Smart charging – use phone app to charge at appointed time, e.g. optimum off peak time • Destination charging: coming for another purpose other than charging • Good ROI models Rapid chargers

• Need for speed • Strong ROI models – much greater set up cost, but will attract users to travel to it • Clear evidence of users prepared to pay premium for convenience of quicker charge time • Creates secondary spend – e.g. food outlets around charge point Charging options for residential accommodation Charging options for individual businesses Accessing grants

• OLEV approved lists for grant funding – commercial & domestic • Some units fit both lists • Workplace Charging Scheme (£350 x 40 chargers= £14000) • Home charge grant (£350) • Grant paid to OLEV approved installer • Grants not available where commercial gain / advantage and owner controls tariff Applications, opportunities & considerations in various settings

Presented by: Richard Pink Richard Pink – Project EV

(EVA-07S-SE) No additional components required Compliant out the box projec EV can save customers 66% on their charging using Oct go. Like the slide im just looking for the information and feels like we have made it in a rush, have another go, I like what you have done with the titles USP’s maybe bigger

You can also charge through solar power online with Solar…

Fast charging mode incorporates any solar export and tops up any remaining power from the grid to the full capacity of the charger, standard operation.

Solar Eco mode charges incorporating any solar export and tops up any remaining power from the grid, but with a limit on the amount of power it takes from the grid up to a maximum power of 3.6KW.

Solar Eco+ charges exclusively with solar exported power and will start charging at 1.4kw, which is the regulatory minimum charging requirement. Increasing Location Capacity with Battery Storage • IP55 Protection, outdoor applications • Flexible combination, suitable for industrial and commercial energy storage • Standard all-in-one ESS container applications • Shipped 300MVA/350MWh+ • Integrated Design, easy on-site

• Short installation cycle, easy maintenance installation and maintenance • Air cooling • Air cooling

• Cube Energy Storage Container System(10 or 12 string)

• Flexible and modular stacking • High-density energy storage systems are arrangement now viable • Large energy density, flexible • Maximum capacity up to 5.6MWh cell layout mode energy,4.88MWh@AC400V • Air cooling • High energy density, it is recommended to connect the outdoor 800kVAPCS

• Liquid cooling

Phones in the middle and title upper left Project EV Pro CRM on the go

Driving together with Project EV towards a cheaper, cleaner, smarter future. Driving together with Project EV towards a cheaper, cleaner, smarter future.

Go to Enter the Use the link code Audience provided in IOW20 Q&A function IM chat to ask a question or the Teams Chat facility

Q&A EV Application Processes Ian Jessiman EV Account Manager SHEPD/North EV Connections Early engagement

Early engagement Application and Design

Applying for and designing your connection Connections

Delivering your connection Getting you connected

Customer service/ Feedback feedback Early Engagement

Come and speak with us as soon as possible as we will be happy to help you firm up your requirements prior to you submitting your connection application.

We offer support and advice through our: • Dedicated teams of Account Managers (contact info for SHEPD and SEPD) • Pre-application meetings and local connection surgeries (request meetings via [email protected] or register via our online event calendar) • Website and EV guide ENA Process ENA has a standard process for connection of EVs to DNO networks:

• A new EV and Heat Pump notification and connection process was released by Energy Networks Association (ENA) in 2019 • Helps installers identify when an installation is ‘Connect & Notify’ vs ‘Apply to Connect’ • Heat Pumps will have an online database associated with the process; ENA intend to do the same thing for EV Charge Points (particularly DC units) • Now includes commercial properties and DC charge points • Typically (but not always) slow chargers can ‘Connect & Notify’ and fast chargers need to ‘Apply to Connect’

We encourage all installers to talk to us and use the notification/application process

ENA application form http://www.energynetworks.org/electricity/futures/electric- vehicles-and-heat-pumps.html Connect & Notify Only possible if • The Maximum Demand (MD) is not greater than 60A per phase (13.8kVA single phase) • The MD exceeds 13.8kVA and the connection is CT metered, but the aggregate Maximum AC output of the EV charging points are equal or less than 30% of the Maximum Import Capacity of the supply

Your installer will, however, need to contact us prior to installation if:

• The MD is greater than the supply capacity • There are safety concerns with the cut out • There is uncertainty over the supply capacity • The connection is a looped supply or if this is unknown • The survey indicates that the connection needs upgrading

We can then arrange a load check and advise your installer but if your connection or the adjacent network needs upgrading then we will need to prepare a quote for you to consider.

Once you have accepted our quote we will then progress the works and, on completion, will advise your installer that they can connect your charger. Applying for your Connection

Information we need to design your connection ENA application form • Name of applicant http://www.energynetworks.org/electricity/ • Address of applicant futures/electric-vehicles-and-heat- pumps.html • Name of site contact (if different from applicant) • Address and plans of connection site (location and site plans) • Location of supply point (meter) marked on site plan • Number, location and loading of EV chargers • Total load requirements (kVA) • Any generation on site (energy storage, PV etc…) • Letter of authority (if you are not the landowner)

How to apply • Online • Email ENA EV Connections Forms

• There are two types of forms; one for a single connection and a spreadsheet for multiple EV connections • The spreadsheet can be used for multiple addresses as well as multiple EV/HP Units on the same MPAN • The word document is only for one unit being installed on one MPAN • Captures details such as owner, location, MPAN, max demand, capacity, connection type, etc EV Webpage Review our online Contact guides webpage & guides to help you when EV guide considering type of charger, power rating, charging time Get in touch Pre-application support is and locations available through Account Managers, meetings, online meetings and surgeries

Apply early Design to final connection can take up to 10 months Summary depending on the size and complexity of connection requested. Applying as early as possible will help us meet your delivery timescales EV Design Processes James McNeish Connections Design Manager Designing the Network

• Recently overhauled how we do LV studies • Revised connection design for LV connections below 69 kVA • Now take Diversity into account even for EV chargers on LV studies • Load profiles used as power is used at different times during the day and night • Will allow more connections to the network than previous Designing the Network

What does this mean for EV connections? • Some connections can be completed and no network studies required • SSEN accept the risk if there are any issues with this • Where network studies are done, these consider Diversity • LV models completed using Windebut software

• Domestic EV profile • Commercial EV profile Designing the Network What is Diversity and how does it benefit EV?

If we take the example of fifteen 50kW EV chargers connecting to the network on separate connections to the same transformer

Previously Total Load would have been 750kVA

This would require a 800kVA transformer

Large LV cable, several feeders

Large costs, 3 feeders on 300mm cable required Designing the Network What is Diversity and how does it benefit EV?

Diversity reduces the amount per customer

Assumes that the use is not the same for every customer at the same time

Reduction is exponential

Single customer there will be no diversity. 10 customers, it will be reduced

Only takes into account single customer type Designing the Network What is Diversity and how does it benefit EV?

Taking the previous example into the new method, fifteen 50kW chargers connecting to a new transformer

Total demand would now be 473kVA

This would mean smaller transformer and smaller cables could be used. Only two feeders of 185mm cable

Saving money for the connection and allowing connections for less cost

Network still remains within limits and capacity is still available What do we need from you?

• Only apply for the size that you need • Designs and costings will be based on the requested capacity • If you request 69kVA but only require 50kVA, you may pay for unnecessary upgrade works to the network • If you are unsure, get in touch. We are more than happy to discuss connections prior to application • Engage with us Go to Enter the Use the link code Audience provided in IOW20 Q&A function IM chat to ask a question or the Teams Chat facility

Q&A Yuan Gao – System Planning Overview Overview of electricity transmission • Electricity is transmitted down from National Grid transmission system to SSEN distribution system and eventually to end users.

• The higher the voltage, the bigger capacity rating. EHV/132kV HV networks LV networks networks • EV charging facilities are normally connected at HV or LV networks.

• Assets overloading, typically on circuits and transformers, is a potential concern when connecting EV charging facilities.

73 Overview of EHV/132kV networks in IoW • IoW networks are fed by Fawley GSP (Grid Supply Point 400/132kV), and Wootton Common BSP (Bulk Supply Point 132/33kV) and 9 local primary substations (33/11kV).

• Capacity required for EV charging facilities at LV/HV networks will be subject to capacity availability at EHV/132kV networks.

• Network reinforcement will be required if there is no sufficient EHV (33kV) networks capacity. 132kV networks

74 Capacity availability at primary substations

How many EV chargers can be supplied** • Capacity is generally available at Capacity Primary Substation 132kV networks feeding IoW. availability* Tesla super charger Domestic EV charger (120kW) (7kW) Cowes 9MVA 75 1286 • , Freshwater and have limited capacities. Newport 9MVA 75 1286 Large scale of EV charging Shalfleet 5MVA 42 714 infrastructure should be well Freshwater 5MVA 42 714 planned in advance in these areas. 7MVA 58 986 10MVA 83 1411 • Comparing to EHV/132kV Sandown 3MVA 25 425 networks, HV and LV networks 10MVA 83 1411 are more of concern due to their smaller capacity ratings and 10MVA 83 1411 generally bigger utilisation. * This capacity availability is only indicative. The network capacity availability can only be confirmed with a network assessment on the time that the inquiry is made. ** The number is only an indicative number to demonstrate the relationship between capacity availability and number of EV chargers can be supplied. Practically, more chargers would be supplied when considering other factors such as diversity etc. 75 Electric Vehicles Uptake in the Distribution Networks Isle of Wight

Rafael Rigoni Network Planning Engineer Distribution Networks Configuration

Electric Vehicles Uptake and Networks Impacts

Challenge

Future Scenario

77 Distribution Networks

Primary Substation

Secondary Substation

End-user

HIGH VOLTAGE LOW VOLTAGE

78 Isle of Wight Distribution Networks - Overview

Cowes

Ryde

Newport Shalfleet

Freshwater Sandown

Shanklin Primary Substation

79 Ventnor Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

80 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

81 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

82 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

83 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

84 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

85 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

86 Distribution Networks Schematic

Cross Lane

Hunny Hill Newport Barton

HV Shide LV

87 88 89 90 91 Challenge

92 93 Future Scenario

• Societal Change • Motorist Behaviour • Shared Vehicle Access

• Demand Side Flexibility www.project-leo.co.uk • Smart Charging • V2G (vehicle-to-grid)

94 Demand Side Flexibility - Concept

Charging Time: 6am – 10am 10am – 2pm Grid 2pm – 6pm 10pm – 2am 2am – 6am

Discharging Time: 6pm – 10pm

95 The electric revolution has begun!

Resilience is necessary

Thank you

Rafael Rigoni Network Planning Engineer Go to Enter the Use the link code Audience provided in IOW20 Q&A function IM chat to ask a question or the Teams Chat facility

Q&A & Survey Links to information provision Project EV: www.projectev.co.uk Richard Pink (Project EV): [email protected] EV Express: www.evexpress.co.uk David Thornton (EV Express): [email protected]

Government’s Draft Technical Guidance on EV Charger requirements for new developments https://www.gov.uk/government/consultations/electric-vehicle-chargepoints- in-residential-and-non-residential-buildings Links to information provision South West Energy Hub

E: [email protected] W: swenergyhub.org.uk/

We are BEIS funded, we help public sector and not-for-profit organisations get green energy and low carbon vehicle projects up and running. Our aim is to increase the number, scale and quality of low carbon energy projects across the South West, reducing the region’s carbon footprint. Links to information provision

> Contact & Escalation guide (SEPD) https://www.ssen.co.uk/ConnectionsInformation/Contact/ > Contact & Escalation guide (ICP/IDNO) https://www.ssen.co.uk/ConnectionsInformation/Contact/, https://www.ssen.co.uk/ConnectionsInformation/CompetitionInConnections/ > Variations & Requotes guide https://www.ssen.co.uk/ConnectionServices/ChangingOrMovingYourSupply/UpdateYourA pplication/ ➢ Service Alteration guide https://www.ssen.co.uk/ConnectionServices/ChangingOrMovingYourSupply/MovingYo urMeter/ Thank you for attending

Engage with us online

Search ‘SSEN Connections Engagement’

twitter.com/ssencommunity

facebook.com/ssencommunity

instagram.com/ssencommunity/

www.ssen.co.uk/Connections/