ENVIRONMENTAL IMPACT STATEMENT EMC METALS PTY LTD Executive Summary Nyngan Scandium Project Report No. 773/05 Executive Summary

INTRODUCTION  A Processing Plant.  A Residue Storage Facility. This Environmental Impact Statement (EIS) has been prepared by R.W. Corkery & Co.  Ancillary infrastructure, including but Pty. Limited on behalf of EMC Metals not limited to, a site access road, Australia Pty Ltd (the Applicant) to support evaporation pond, levee bunds, water an application for development consent for and power supply infrastructure etc. the Nyngan Scandium Project (the Proposal), located approximately 20km The Proposal is classified as State west-southwest of Nyngan in Western NSW Significant Development in accordance (Figure A). with Paragraph 5 of Schedule 1 of State Environmental Planning Policy (State and Regional Development) 2011 (State and Regional Development SEPP) as it would Figure A have a capital investment value of more Locality Plan than $30 million. A6 / Colour Approval is required in accordance with Dated 29/03/16 Inserted 04/04/16 Division 4.1 of the Environmental Planning and Assessment Act 1979 (EP&A Act). The approval authority is the Minister for Planning and Environment or their delegate.

THE APPLICANT The Applicant, EMC Metals Australia Pty Ltd, is a subsidiary of the Canadian- incorporated Scandium International Mining Corp. (SCY). SCY is a specialty metals mining group with a worldwide exploration and development focus on scandium projects and market development, as well as opportunistic development of select specialty metals and rare earth elements that may accompany scandium resources. SCY’s primary operational focus is on its scandium project holdings, The Proposal would comprise construction specifically the Nyngan Scandium Project and use of the following. and the Honeybugle property in Australia  Two open cuts within a surrounding and the Tordal scandium property in borrow pit with extraction of up to Norway. 80 000t per annum (tpa) of high grade ore and up to 95 000tpa of low grade The Proposal is 100% owned and operated ore over a period of 21 years. by the Applicant.

ES-1

EMC METALS AUSTRALIA PTY LTD ENVIRONMENTAL IMPACT STATEMENT Nyngan Scandium Project Executive Summary Report No. 773/05 OBJECTIVES OF THE  Extraction of overburden and ore PROPOSAL material from two open cuts and a surrounding borrow pit using The Applicant’s objectives in constructing conventional free dig mining methods and operating the Proposal include the on a campaign basis. Annual ore following. production would be up to 80 000t of high grade ore, and up to 95 000t of  To mine the identified scandium low grade ore. Mining would be reserves in a safe and environmentally undertaken for a period of up to responsible manner. 21 years.

 To maximise the recovery of the  Use of extracted overburden for the identified scandium reserves through construction of site infrastructure, efficient mining and processing including the Residue Storage operations. Facility, levee bunds, haul roads and  To minimise the consumption of water management structures. water, power and chemical reagents.  Construction and use of a Processing  To operate the Proposal in a manner Plant, which would incorporate a run- that would minimise surface of-mine (ROM) Pad, feed preparation disturbance and impacts on circuit, high pressure acid leach plant surrounding residents and the local and associated infrastructure, environment. including boilers, reagent and  To develop and operate the Proposal consumable stores, as well as residue in compliance with all relevant management systems to produce up to statutory requirements. approximately 45t per year of scandium oxide. The scandium oxide  To create a final landform that is would be transported from the Project suitable for a post-mining land use Site in sealed containers with an that would include a mixture of indicative capacity of less than 100L. agriculture, nature conservation and Processing would be undertaken for water storage. the life of the mining operations,  To achieve the above objectives in a namely 21 years. cost-effective manner to ensure  Construction and use of a Residue security of employment and the Storage Facility. continued economic viability of the Applicant.  Construction and use of water management structures, including a Raw Water Pond, Event Pond, DESCRIPTION OF THE External Decant Pond, Evaporation PROPOSAL Pond and a number of Sediment Ponds. Overview  Construction and use of a transformer The Proposal would comprise the following and electrical distribution network. (Figure B).  Construction of soil stockpiles (for  Establishment of infrastructure use in rehabilitation works). required for the Proposal, including a  Establishment of a Biodiversity Offset Site Access Road, power and water Area. supply, levee bunds and administration area.

ES-2

ENVIRONMENTAL IMPACT STATEMENT EMC METALS AUSTRALIA PTY LTD Executive Summary Nyngan Scandium Project Report No. 773/05

Figure B Project Site Layout

A4 / Colour

Dated 08/04/16 Inserted 11/04/16

ES-3

EMC METALS AUSTRALIA PTY LTD ENVIRONMENTAL IMPACT STATEMENT Nyngan Scandium Project Executive Summary Report No. 773/05 Processing Operations Site Preparation Ore material would be processed within the The following activities would be on-site Processing Plant, which would undertaken in preparation for mining include the following components. operations and the construction of the  A ROM Pad for stockpiling and Processing Plant and other infrastructure. blending of ore.  Survey, mark out and fencing of  A Feed Preparation Circuit for disturbance areas. physical preparation of ore material.  Construction of the Site Access Road,  A Leach Preparation Circuit for internal roads and intersection of the preheating and preparation of the ore Site Access Road and Gilgai Road. slurry.  Construction of the Processing Plant,  A High Pressure Acid Leach Circuit workshops, offices and associated where the contained scandium would infrastructure, including a high be transferred from the ore to the voltage electricity line and water leach solution. supply pipeline.  A Counter Current Decant Circuit  Removal of vegetation and stripping where the scandium-bearing leach of soil. solution would be removed from the ore slurry. Mining Operations  A Solvent Extraction Circuit where the leached scandium in solution Ore and overburden would be extracted would be transferred to an organic from two open cuts and a borrow pit as solvent. follows.  A Scandium Oxide Precipitation  Total area ...... 38.2ha. Circuit where the scandium would be  Depth precipitated from the organic solvent and converted to scandium oxide. – East Pit ...... 45mbgl.  A Residue Preparation Circuit where – West Pit ...... 50mbgl. the residue or tailings would be – Borrow Pit ...... 15mbgl. neutralised and thickened prior to being transferred to the Residue Following removal of vegetation and soil Storage Facility. material, mining operations would commence with the removal of overburden The anticipated annual production would be using a front-end loader and bulldozer. approximately 45t of scandium oxide per year. Open cut mining operations would then remove ore material in thin layers using a The Processing Plant would also include a front-end loader or excavator. Annual ore range of ancillary infrastructure, including production would be up to 80 000t of high the following grade ore and 95 000t of low grade ore for a  Reagent stores. period of 21 years.  An LPG-fired boiler. The Applicant does not anticipate that drill  A cooling tower. and blast extraction methods will be required.  A reverse osmosis plant.

ES-4

ENVIRONMENTAL IMPACT STATEMENT EMC METALS AUSTRALIA PTY LTD Executive Summary Nyngan Scandium Project Report No. 773/05

 Water management structure. Transportation Operations  Workshops. The Project Site would be accessed via the  Administration offices. and Gilgai Road, with the vast majority of vehicles accessing the Project Site from the east. Residue Management An assessment of the intersection between Residue would be pumped to the Residue the Barrier Highway and Gilgai Road Storage Facility, where the solid and liquid determined that the sight distance from the fractions would then be permitted to intersection along the Barrier Highway is separate. The liquid fraction would be 560m to the east and 200m to the west. pumped to the External Decant Pond for reuse within the Processing Plant. The Applicant would construct an intersection between Gilgai Road and the The Residue Storage Facility would be an Site Access Road in accordance with engineered, lined facility that would comply Austroads Guide to Road Design – Part 4A: with the design criteria of the Dams Safety Un-signalised and Signalised Intersections Committee of NSW and the Environment to the satisfaction of Council. Protection Authority’s Draft Environmental Guidelines: Solid Waste Landfills. Finally, the Applicant anticipates that the Proposal would result in up to 60 light vehicle movements (30 return trips) per day Water Management and 10 heavy vehicle movements (5 return The Applicant would source required trips) per day. operational water from the existing Nyngan to Pipeline. That water would be Hours of Operation subject of the relevant Water Access Licence and would be supplied under a The Applicant would undertake mining commercial arrangement with the Cobar operations on a campaign basis Water Board. approximately 3 times per year. Mining would typically be undertaken 7 days per Levee bunds would be constructed around week between 6:00am and 6:00pm, with a the proposed areas of disturbance, with the period before and after those times. crest of the bund approximately 1m high above the modelled height of a 0.1% (1 in Processing operations would be undertaken 1 000 year) Annual Exceedance Probability 24-hours per day, 7 days per week. storm event.

A range of water management structures Life of the Proposal would be constructed within the bunded The Applicant proposes to undertake areas to ensure appropriate separation of mining operations for a period of 21 years, clean, dirty and contaminated water. No with a period prior to mining operations surface water would be discharged from the commencing for financing and construction Project Site. operations and following mining operations for rehabilitation and mine closure operations. As a result, development consent is sought for a period of 26 years.

ES-5

EMC METALS AUSTRALIA PTY LTD ENVIRONMENTAL IMPACT STATEMENT Nyngan Scandium Project Executive Summary Report No. 773/05 Employment and Economic The proposed final land uses for the Project Contribution Site would include agriculture, nature conservation and water storage. The Applicant anticipates that it would require the following full time equivalent (FTE) personnel to operate the Proposal. PLANNING CONTEXT  Construction – Approximately 60 FTE positions. Planning Instruments  Ongoing operations – Approximately The Project Site is situated within land 75 FTE positions zoned as RU1 – Primary Production under the Bogan Local Environmental Plan 2011 Additional employment would also be (Bogan LEP). Open-cut mining is identified generated for contract campaign mining as permissible with consent within this operations, contract truck drivers and zone. service providers. The Proposal would be developed and The Applicant anticipates that the Proposal operated in accordance with a number of would contribute approximately State planning instruments, namely: $12.4 million per year to the local and  SEPP (State and Regional regional economy, and approximately Development) 2011; $39.0 million per year to the State and national economies.  SEPP (Mining, Petroleum Production and Extractive Industries) 2007; Final Landform and Land Use  SEPP (Infrastructure) 2007; and The final landform would comprise the  SEPP 33 (Hazardous and Offensive following. Development).

 Two bunded and fenced open cuts The EIS addresses each of the above within a revegetated borrow pit with documents together with the Bogan LEP. side slopes of 1:3 (V:H) or less.  A free draining, covered and revegetated Residue Storage Facility. Approvals Required  A shaped, covered and revegetated In addition to development consent, the Low Grade Stockpile with slide Applicant anticipates the following slopes of 1:3 (V:H) or less approvals, licences and leases would be required.  A generally flat Processing Plant Area with all infrastructure not required for  An Environment Protection Licence the final land use, including the levee issued under the Protection of the bunds, removed. Environment Operations Act 1997.  Two water storage dams, namely the  A Mining Lease issued under the Event Pond and Sediment Pond, with Mining Act 1992. all other water storages removed.  Water Supply Works and Use Approval and Water Access Licence The Site Access Road would remain for the issued under the Water Management final land use. Infrastructure within the Act 2000. services corridor not required for the final land use would be removed.

ES-6

ENVIRONMENTAL IMPACT STATEMENT EMC METALS AUSTRALIA PTY LTD Executive Summary Nyngan Scandium Project Report No. 773/05

 A Section 138 Permit issued by the Ecology Bogan Shire Council under the Roads The Proposal would result in the Act 1993, for construction of the disturbance of approximately 9.3ha of intersection of the Site Access Road Poplar Box  Gum-barked Coolibah  and Gilgai Road. White Cypress Pine shrubby woodland  An approval from the NSW Dams mainly in the Cobar Peneplain Bioregion Safety Committee for the design and vegetation community. EnviroKey construction of the Residue Storage undertook an assessment of the impacts Facility. associated with the disturbance of this vegetation, and determined that the

 A high voltage connection agreement Proposal would not have a significant with Essential Energy under the impact upon this community, as it is well Electricity Supply Act 1995. represented in the immediate area.

EnviroKey further identified that: ENVIRONMENTAL FEATURES SAFEGUARDS AND IMPACTS  five species listed under the Threatened Species Conservation Act The components and features of the existing 1995 have the potential to occur environment within and surrounding the within the Project Site; and Project Site have been studied in detail and  one protected species listed under the the Proposal has been designed to avoid or Environment Protection and minimise impacts on that environment. A Biodiversity Conservation Act 1999 brief overview of the main components of has the potential to occur within the the surrounding environment, the proposed Project Site. safeguards and the assessed level of impact are set out in the following sections. EnviroKey undertook significance assessments for each of the observed Air Quality species or those with potential to occur and determined that, with the implementation of Ramboll Environ determined that the management and mitigation measures, the Proposal would not result in an exceedance Proposal would be unlikely to have a of the relevant deposited or suspended significant impact on any identified species. particulate matter assessment criteria at any surrounding residences as a result of the The Applicant would implement a Proposal. In addition, the Proposal would Biodiversity Offset Strategy to offset not result in significant greenhouse gas vegetation clearing impacts, including a impacts. Furthermore, taking into proposed 64ha Biodiversity Offset Area consideration the Applicant’s commitment (Figure B). EnviroKey concluded that the to install a range of emission control proposed Biodiversity Offset Strategy devices to ensure compliance with the would be consistent with the Office of Clean Air Regulation, Ramboll Environ Environment and Heritage’s offsetting determined that the Proposal would not principles. result in adverse air quality impacts associated with the proposed processing operations. Surface Water Knight Piésold undertook an assessment of the hydrology of the Project Site and surrounds. In particular, the assessment focused on the potential for flooding

ES-7

EMC METALS AUSTRALIA PTY LTD ENVIRONMENTAL IMPACT STATEMENT Nyngan Scandium Project Executive Summary Report No. 773/05 associated with Whitbarrow Creek, located Traffic and Transportation to the south of the Project Site. The The Site Access Road, the intersection of assessment considered both a 1% (1 in the Site Access Road and Gilgai Road, and 100 year) and 0.1% (1 in 1 000 year) the intersection of Gilgai Road and the Annual Exceedance Probability (AEP) Barrier Highway would be upgraded to Storm. accommodate Project-related heavy vehicle Knight Piésold determined that the movements. As a result, the Proposal would maximum flood height for a 0.1% AEP not result in additional adverse traffic- event in the vicinity of the Processing related impacts. Plant/Residue Storage Facility Area and the open cuts would be approximately Aboriginal and Historic Heritage 185.2m AHD and 184.5m AHD No sites of Aboriginal heritage significance respectively. As a result; the Applicant were identified within the Project Site. One proposes to construct levee bunds around site of potential historic heritage the Processing Plant/Residue Storage significance was identified but would not be Facility Area and open cuts of 186.6m AHD disturbed by the Proposal. and 185.6m AHD respectively, or more than 1m higher than the anticipated 0.1% AEP flood level. Visual Amenity Based on the relative isolation of the Project The levee bunds would exclude all surface Site and the proposed landscape and visual water from the proposed disturbance areas amenity related controls, the Proposal and retain all potentially dirty or would not impact significantly on local contaminated water within the bunded area. visual amenity. As a result, no adverse surface water impacts are anticipated. Soils and Land Capability

Groundwater Given the establishment of soil management procedures and safeguards, the Ground Doctor determined that the Proposal would not result in significant soil groundwater within the Project Site would and land capability impacts. not be suitable for any common beneficial use without prior treatment due to high salinity. Impax also determined that the PROPOSAL EVALUATION AND Proposal is not anticipated to result in groundwater drawdown at any surrounding JUSTIFICATION groundwater bores or drainage lines. The Nyngan Scandium Project has been evaluated and justified principally through Noise consideration of its potential impacts on the Operational and transport noise generated environment and potential benefits to the by the Proposal would, assuming the local and wider community. implementation of the nominated safeguards and controls, not exceed the An evaluation of the Proposal has been relevant criteria at any privately-owned undertaken by firstly re-assessing the risks residence. posed to the local environment by Proposal- related activities following the implementation of all operational controls, safeguards and/or mitigation measures, and

ES-8

ENVIRONMENTAL IMPACT STATEMENT EMC METALS AUSTRALIA PTY LTD Executive Summary Nyngan Scandium Project Report No. 773/05 secondly through consideration of the CONCLUSION principles of ecologically sustainable development. The Proposal has, to the extent feasible, been designed to address all issues raised by This evaluation has found that, with the the local community and all levels of implementation of the proposed operational government, as well as the principles of controls, safeguards and/or mitigation ecologically sustainable development. The measures, the residual risk posed by each Proposal provides for the extraction of a potential environmental impact has been valuable State-owned resource that would reduced to either moderate, low, or as low facilitate the development of new and as reasonably practicable, and therefore innovative products, including wider use of acceptable. aluminium – scandium alloys and fuel cells.

Further, the design of the Proposal has The Proposal would also result in the addressed each of the sustainable creation of local employment and development principles, and on balance, it expenditure within the regional economy. is concluded that the Proposal achieves a The socio-economic impacts of the sustainable outcome for the local and wider Proposal are considered to be positive. environment. Finally, the post-mining landform would The Proposal and associated activities have result in the continuation of the existing been assessed in terms of a wide range of land use, namely agriculture, as well as biophysical, social and economic issues. providing areas for nature conservation and Potential residual impacts can be justified in water storage. terms of the positive economic and social benefits to the local surrounding towns, In light of the conclusions included villages and regional centres and the Bogan throughout this Environmental Impact and surrounding Local Government Areas. Statement, it is assessed that the Proposal could be constructed and operated in a manner that would satisfy all relevant statutory goals and criteria, environmental objectives and reasonable community expectations.

ES-9

EMC METALS AUSTRALIA PTY LTD ENVIRONMENTAL IMPACT STATEMENT Nyngan Scandium Project Executive Summary Report No. 773/05 Project Summary

Page 1 of 2 Project Component Summary of the Proposal Mining Method Open cut mining using free dig techniques within two open cuts and a borrow pit with a combined area of 38.2ha and a maximum depth of approximately 50mbgl. Mining would be undertaken on a campaign basis approximately three times per year. Resource Measures and indicated – 12Mt at 261ppm scandium. Disturbance Area Approximately 145ha, comprising:  9.3ha of Benson ID 103 – Poplar Box – Gum Coolabah and White Cypress Pine Shrubby Woodland mainly in the Cobar Peneplain Bioregion; and  135.7ha of exotic vegetation. Annual Ore Production Up to approximately 80 000tpa of high grade ore and 95 000tpa of low grade ore. Mine Life Approximately 21 years for mining operations, with an additional 2 years for financing and construction and 2 to 3 years for rehabilitation for a total Proposal life of 26 years. Total Resource Approximately 1.5Mt. Recovered Processing Scandium would be extracted using high pressure acid leach and solvent extraction to produce up to 45t of scandium oxide per year. Management of Overburden would be used to construct site infrastructure, including the Overburden Residue Storage Facility, levee bunds and water storages. General Infrastructure General infrastructure would include the following. (see Figure B)  Site Access Road and intersection with Gilgai Road.  Two open cuts and a borrow pit.  A Processing Plant Area incorporating the proposed Processing Plant, reagent storage areas, water storages and hardstand areas.  A Residue Storage Facility.  Internal roads, including an elevated haul road.  Electricity supply and distribution network.  Ancillary infrastructure, including offices, workshops, hydrocarbon stores, ablution and waste water treatment facilities and hardstand areas. Product Transport Scandium oxide would be transported from the Project Site in small containers with an indicative capacity of less than 100L. Water Management Operational water – sourced from the Nyngan – Cobar Pipeline under licence. Potentially contaminated and sediment-laden water – retained on-site. External flood water – excluded by levee bund with a crest approximately 1m higher than the modelled 0.1% (1 in 1 000 years) storm event. Workforce Approximately 60 personnel during construction and 75 during operation.

ES-10

ENVIRONMENTAL IMPACT STATEMENT EMC METALS AUSTRALIA PTY LTD Executive Summary Nyngan Scandium Project Report No. 773/05

Project Summary ( C o n t ’ d )

Page 2 of 2 Project Component Summary of the Proposal Hours of Operation Land preparation and rehabilitation – daylight hours, 7 days per week. Mining – 6:00am to 6:00pm, 7 days per week. All other activities – 24-hours per day, 7 days per week. Capital Investment Approximately A$124.4 million. Value Final landform / land Open cuts – final void / water storage. use Borrow Pit and Low Grade Stockpile – nature conservation (woodland). Residue Storage Facility – free draining landform / nature conservation (grassland). Event and Sedimentation Ponds – water storage. Remaining disturbed areas – consistent with current landform / agriculture.

ES-11

EMC METALS AUSTRALIA PTY LTD ENVIRONMENTAL IMPACT STATEMENT Nyngan Scandium Project Executive Summary Report No. 773/05

This page has intentionally been left blank

ES-12