CIVIC CENTRE, STOCKWELL CLOSE, BROMLEY BRI 3UH

TELEPHONE: 020 8464 3333 CONTACT: Keith Pringle [email protected] DIRECT LINE: 020 8313 4508 FAX: 020 8290 0608 DATE: 9 November 2012

To: Members of the ENVIRONMENT POLICY DEVELOPMENT AND SCRUTINY COMMITTEE

Councillor William Huntington-Thresher (Chairman) Councillor Ellie Harmer (Vice-Chairman) Councillors Reg Adams, Peter Fookes, Julian Grainger, Samaris Huntington- Thresher, David Jefferys, Nick Milner and Ian F. Payne

A meeting of the Environment Policy Development and Scrutiny Committee will be held at Bromley Civic Centre on TUESDAY 20 NOVEMBER 2012 AT 7.30 PM

MARK BOWEN Director of Resources

Copies of the documents referred to below can be obtained from www.bromley.gov.uk/meetings

A G E N D A

PART 1 AGENDA Note for Members: Members are reminded that Officer contact details are shown on each report and Members are welcome to raise questions in advance of the meeting.

STANDARD ITEMS

1 APOLOGIES FOR ABSENCE AND NOTIFICATION OF SUBSTITUTE MEMBERS

2 DECLARATIONS OF INTEREST

3 QUESTIONS FROM COUNCILLORS AND MEMBERS OF THE PUBLIC ATTENDING THE MEETING In accordance with the Council’s Constitution, questions to this Committee must be received in writing four working days before the date of the meeting. Therefore please ensure that questions are received by the Democratic Services Team by 5pm on Wednesday 14 th November 2012.

4 MINUTES OF THE ENVIRONMENT PDS COMMITTEE MEETING HELD ON 25TH SEPTEMBER 2012 (Pages 5 - 16)

HOLDING THE PORTFOLIO HOLDER TO ACCOUNT

5 QUESTIONS TO THE PORTFOLIO HOLDER FROM MEMBERS OF THE PUBLIC AND COUNCILLORS ATTENDING THE MEETING In accordance with the Council’s Constitution, questions to the Portfolio Holder must be received in writing four working days before the date of the meeting. Therefore please ensure that questions are received by the Democratic Services Team by 5pm on Wednesday 14 th November 2012.

6 ENVIRONMENT PORTFOLIO - PREVIOUS DECISIONS (Pages 17 - 26) To note decisions of the Portfolio Holder made since the previous meeting of the Committee.

7 PRE-DECISION SCRUTINY OF REPORTS TO THE ENVIRONMENT PORTFOLIO HOLDER The Environment Portfolio Holder to present scheduled reports for pre-decision scrutiny on matters where he is minded to make decisions.

a BUDGET MONITORING 2012/13 (Pages 27 - 36)

b CAPITAL PROGRAMME - 2ND QUARTER MONITORING 2012/13 (Pages 37 - 42)

c BRITTENDEN PARADE – PROPOSED MAKING UP (Pages 43 - 46)

d CONGESTION RELIEF SCHEME BLACKBROOK LANE/ PARK ROAD (Pages 47 - 54)

e ROAD SAFETY SCHEME SEVENOAKS WAY/ MAIN ROAD (Pages 55 - 62)

f 2013/14 PLANNED HIGHWAY MAINTENANCE PROGRAMME (Pages 63 - 88)

8 PRE-DECISION SCRUTINY OF REPORT TO THE EXECUTIVE

a PARKING SHARED SERVICE

As this report will also be considered by the General Purposes and Licensing Committee and Executive and Resources PDS Committee on 21 st November 2012 and the Executive on 28 th November 2012, the report is provided to Members under separate cover. Members are requested to bring their copy of the report with them to any of the meetings considering this item.

POLICY DEVELOPMENT AND OTHER ITEMS

9 ENVIRONMENT PORTFOLIO PLAN 2012/13; HALF-YEAR PROGRESS REPORT (Pages 89 - 104)

10 FORWARD WORK PROGRAMME, MATTERS ARISING FROM PREVIOUS MEETINGS AND CONTRACTS REGISTER (Pages 105 - 112)

PART 2 AGENDA

11 LOCAL GOVERNMENT ACT 1972 AS AMENDED BY THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) (VARIATION) ORDER 2006, AND THE FREEDOM OF INFORMATION ACT 2000 The Chairman to move that the Press and public be excluded during consideration of the items of business listed below as it is likely in view of the nature of the business to be transacted or the nature of the proceedings that if members of the Press and public were present there would be disclosure to them of exempt information.

12 PRE-DECISION SCRUTINY OF A PART 2 REPORT TO THE PORTFOLIO HOLDER The Environment Portfolio Holder to present a scheduled Part 2 report for pre-decision scrutiny on a matter where he is minded to make a decision.

a AWARD OF PARKING ICT CONTRACT Information relating to the (Pages 113 - 122) financial or business affairs of any particular person (including the authority holding that information)

13 PRE-DECISION SCRUTINY OF REPORTS TO THE EXECUTIVE

a AWARD OF STREET LIGHTING Information relating to the MAINTENANCE AND IMPROVEMENTS financial or business affairs CONTRACT AND STREET LIGHTING of any particular person INVEST TO SAVE INITIATIVE (including the authority holding that information) As this report will also be considered by the Executive and Resources PDS Committee on 21 st November 2012 (for any further pre- decision scrutiny) and the Executive on 28 th November 2012, the report is provided to Members under separate cover. Members are requested to bring their copy of the report with them to any of the meetings considering this item.

b STREET WORKS TENDER (NRSWA) Information relating to the financial or business affairs As this report will also be considered by the of any particular person Executive and Resources PDS Committee on (including the authority st 21 November 2012 (for any further pre- holding that information) decision scrutiny) and the Executive on 28 th November 2012, the report is provided to Members under separate cover. Members are requested to bring their copy of the report with them to any of the meetings considering this item.

DATES OF FUTURE ENVIRONMENT PDS COMMITTEE MEETINGS 15 th January 2013 5th March 2013

Agenda Item 4

ENVIRONMENT POLICY DEVELOPMENT AND SCRUTINY COMMITTEE

Minutes of the meeting held at 7.30 pm on 25 September 2012

Present

Councillor William Huntington-Thresher (Chairman) Councillor Ellie Harmer (Vice-Chairman)

Councillors Reg Adams, Peter Fookes, Julian Grainger, David Jefferys and Sarah Phillips

Also Present

Councillor Colin Smith and Councillor Peter Fortune

14 APOLOGIES FOR ABSENCE AND NOTIFICATION OF SUBSTITUTE MEMBERS

Apologies were received from Councillors Samaris Huntington-Thresher and Nick Milner. Councillor Sarah Phillips attended as substitute for Councillor Nick Milner.

15 DECLARATIONS OF INTEREST

There were no declarations.

16 QUESTIONS FROM COUNCILLORS AND MEMBERS OF THE PUBLIC ATTENDING THE MEETING

There were no questions to the Committee.

17 MINUTES OF THE ENVIRONMENT PDS COMMITTEE MEETING HELD ON 3RD JULY 2012

The minutes were agreed subject to concern about wording in the third paragraph of Minute 7C. (Democratic Services Note : subsequent to the 25 th September meeting this paragraph was removed from the 3 rd July minutes with the start of the fourth paragraph at Minute 7C of those minutes amended to read “Responding to enquiries/comment from Councillor Grainger, the Director indicated that proposals for ……..……..” ).

18 QUESTIONS TO THE PORTFOLIO HOLDER FROM MEMBERS OF THE PUBLIC AND COUNCILLORS ATTENDING THE MEETING

A question from Mrs Vikki Hughes for oral reply had been received and three questions from Mr Colin Willetts for written reply had also been received. Details of the questions and replies are at Appendix A .

20

Page 5 Environment Policy Development and Scrutiny Committee 25 September 2012

19 ENVIRONMENT PORTFOLIO - PREVIOUS DECISIONS

Decisions of the Portfolio Holder made since the previous meeting of the Committee were noted.

20 PRE-DECISION SCRUTINY OF REPORTS TO THE ENVIRONMENT PORTFOLIO HOLDER

A) BUDGET MONITORING 2012/13

Report ES12109

Based on expenditure and activity levels to 31st August 2012, the Environment Portfolio was projected to be balanced at year end.

Details were provided of the 2012/13 projected outturn with a forecast of projected spend for each division compared to the latest approved budget. Background to variations was also outlined.

Councillor Peter Fookes enquired about background to the shortfall in income for on and off street parking. He was advised of contributory factors which included languishing retail activity (impacted by poor summer weather), new parking increases not taking effect until 30 th April and performance expectations for parking income being set an optimistic level. The Chairman suggested that parking income may have also been affected by the impact of the Olympics.

Councillor Reg Adams was pleased that the net loss of custom for trade waste collections had been less than anticipated following the increase in prices from 1 st April 2012.

Noting that this position indicated a projected £140k surplus against a projected deficit of £150k for trade waste delivered to the depots (an apparent loss of £10k), the Chairman felt that it was necessary for the Waste Minimisation Working Group to look at the trade waste figures in more detail (before recommending price changes for the 2013/14 financial year).

RESOLVED that the Portfolio Holder be recommended to endorse the latest 2012/13 budget projection for the Environment Portfolio.

B) CAPITAL PROGRAMME - 1ST QUARTER MONITORING 2012/13 AND FINAL OUTTURN 2011/12

Report RES12151

At its meeting on 25th July 2012, the Executive agreed a revised Capital Programme for 2012/13 to 2015/16 and changes in respect of the Capital Programme for the Environment Portfolio were highlighted.

21

Page 6 Environment Policy Development and Scrutiny Committee 25 September 2012

Enquiring of progress with works to the road bridge, Councillor Fookes was advised that completion was due early November (on time).

RESOLVED that the Portfolio Holder be recommended to confirm the changes agreed by the Executive in July.

C) EXTENSION TO CONTRACT FOR PROVISION OF MOBILE PHONE PARKING

Report ES12111

Report ES12111 reviewed the first 2.5 years of the scheme for mobile phone parking payment, going forward into the third and final year of the contract. There was an option to extend the contract at the Council’s discretion for a further period not exceeding two years and Report ES12111 set out the reasons for recommending an extension.

Parking payment by mobile phone had proved to be a continuing success with an average 410 transactions per day. This was steadily increasing with a projected 150,000 transactions for 2012/13. Information was provided on the number of transactions, parking income received and a projection for the extension period.

The removal of 23 pay and display machines at specific on-street locations had also taken place throughout the Borough (enabling the machines to be recycled) with a further 18 machines ready to be removed. The Mobile Phone Parking Scheme was advertised at each location where a machine had been removed. Removal of the machines did not affect the public’s ability to pay by cash given the provision of at least one machine within the zone.

Mobile phone payment had contributed to the Council being able to reduce cash collection costs by £43k per annum. If mobile phone payment continued to increase, additional savings could be generated from cash collection costs. The expected growth would also enable more pay and display machines to be removed and recycled.

It was reported that Bromley Parking Services and Cobalt Technologies had worked well together in introducing new parking schemes or making adjustments to parking tariffs. There was scope within the current contact to provide other mobile phone parking solutions in future - Bromley Parking Services and Cobalt were keen to explore such ideas.

Officers had maintained a close interest in services provided by other mobile phone parking companies and were not aware of any different services that would warrant a tendering exercise. It was felt that there were clear advantages to continuing with the contract and the Portfolio Holder was recommended to grant a contract extension for a further two years.

In the first two financial years of operation income from Mobile Phone payment was £225k and receipt of an estimated £300k was expected for

22 Page 7 Environment Policy Development and Scrutiny Committee 25 September 2012

2012/13. With a further two year contract it was anticipated that income received could reach £600k per annum and this was likely to generate additional savings from reduced cash collections.

In discussion Councillor Grainger highlighted what he felt was an inconsistency whereby it was possible to “top up” parking payment by mobile phone but “feeding” a pay and display meter was technically a contravention which was subject to the issue of a Penalty Charge Notice (PCN) if undertaken regularly. He also enquired whether pay and display machines indicated certain charges associated with calls from mobile phones to the payment company.

Councillor Fookes suggested that consideration should perhaps be given to dispensing with cash payment for parking. The Head of Parking advised that mobile phone payment currently comprised some four to five percent of total parking transactions. Councillor David Jefferys felt that many residents such as the elderly would want to retain payment options.

The Chairman referred to trying to promote a modal shift on parking payment – if savings could be made it would help to prevent parking charges increasing. Councillor Grainger shared the concerns of Councillor Jefferys and felt that there would be a limit to the take up of mobile phone payment. Councillor Grainger was opposed to payment solely by mobile phone although he felt that further consideration should be given to parking payment by debit card.

RESOLVED that the Portfolio Holder be recommended to:

(1) grant the contract extension on mobile phone parking payment for a further two years; and

(2) continue the policy of reducing the number of pay and display machines where practical.

D) TFL FUNDED WORK PROGRAMME FOR 2013/14

Report ES12116

In relation to Bromley’s 2013/14 formula allocation from TfL (£2.771m), Portfolio Holder approval was sought for a recommended list of schemes to submit to TfL in early October 2012.

Ring-fenced TfL funding would also be available to support other programmes, including Local Transport Priorities, Principal Road Maintenance, Bridges/Structures and Bromley North Village. As such the Portfolio Holder was also asked to approve a bid for Bridges and Structures and a Programme of Principal Road Maintenance for submission to TfL.

Highlighting the A224 congestion relief scheme (northern section), Councillor Grainger considered the Leesons Hill/Sevenoaks Way junction to be more

23

Page 8 Environment Policy Development and Scrutiny Committee 25 September 2012 significant in contributing to congestion than the Nugent Centre entrance/exit. In response it was indicated that the project was looking to link signals and their junctions along Sevenoaks Way. Studies had shown that the Nugent Centre would be the main traffic blockage. With signals installed at the Nugent Centre junction all signals would then be linked along the by pass northern section. Improving the Nugent Centre exit would be the major part of the sc heme’s cost.

Councillor Grainger also referred to opening the north east corner of High Street for one-way traffic (which would involve opening the rear of the Nugent Centre to the High Street). Members were advised that this had been looked at but rejected for the present time - it would encourage too much traffic on to the minor road.

In connection with Bromley’s status as a “Biking Borough” , Councillor Jefferys was informed that there were a couple of options for proposed junction improvements at Westmoreland Road/High Street. Details would be brought to the Committee for consideration; the outcome of the planning process was also awaited in respect of Site L.

Concerning pedestrian crossings in the context of cycling and walking schemes, Councillor Grainger expressed a preference for refuges. An explanation was also provided on the proposed scheme for Shire Lane involving access to the bus stop by . Councillor Grainger also highlighted school travel plan monitoring and review; the Head of Traffic and Road Safety indicated that monitoring would continue and that current monitoring approaches provided information. Most of funding was spent on developing plans; much less time was spent reviewing and there was an emphasis on what would change travel behaviours.

For Congestion Relief, Councillor Reg Adams noted that there were no schemes included for the /Crystal Palace area and he enquired how the congestion relief funding was allocated. In reply, reference was made to outcomes from the former Congestion Working Party and pinch points highlighted in the review. To make a significant impact on congestion officers had looked at key pinch points such as the A224 Orpington by pass. The Penge/Crystal Palace area would be looked at for the future; however, schemes providing maximum benefit would be taken forward. Councillor Fookes suggested that it be would useful to see schemes not included and Councillor Grainger suggested a list identifying pinch points from the Congestion review where work had completed. The Chairman asked the Head of Traffic and Road Safety to circulate the list considered by the Congestion Working Party.

Concerning Road Safety Education, it was explained that “Smarter Driving” was aimed mainly at Year 12 students providing them with pre-driver training. It also covered safer driving for adults through the Advance Driving Course. Moped training was also provided for senior school students. Councillor Adams was advised that all types of secondary school could receive relevant training including Academy and Independent Sector schools.

24 Page 9 Environment Policy Development and Scrutiny Committee 25 September 2012

It was also explained that the “Car Seats Project” related to the Car Seat Fitting Centre facilitated by the Bromley Adult Education College at Nightingale Lane. The Project enabled parents to try a brand of child seat before buying and it was advertised at venues such as neo-natal clinics and schools. It also offered a training programme to local retail staff involved in child seat sales, providing advice on the proper fitting of car seats for new born babies.

Under “Cycling and Walking Schemes” , the Chairman noted a proposed scheme entitled “ Upgrade Bridleway, 192 Court Road ”. Members were advised that the footpath was not in good condition from Ramsden Road; the Chairman felt that it was necessary to clarify what was meant by 192 .

Members were advised that the list of schemes at Enclosure 1 to Report ES12116 was a suggested programme (even though the list might be submitted to TfL). The report indicated that there would be little difficulty in changing the list of schemes following submission or during 2013/14 itself. On proposals for the 2013/14 Principal Road Maintenance Programme, the Head of Traffic and Road Safety indicated that there would be opportunity for the Committee to consider a final Programme later in the year and that the Programme at Enclosure 2B to the report was not therefore final.

RESOLVED that the Portfolio Holder be recommended to agree that:

(1) the programme of formula funded schemes for 2013/14 at Enclosure 1 be approved for submission to Transport for ;

(2) the bid for Bridges and Structures at Enclosure 2A be approved for submission to Transport for London;

(3) the programme for Principal Road Maintenance at Enclosure 2B be approved for submission to Transport for London; and

(4) the Director of Environmental Services, in consultation with the Environment Portfolio Holder, be authorised to make post-submission changes to the programme to reflect any necessary changes to priority, potential delays to implementation following detailed design and consultation, or other unforeseen events.

E) GREEN STREET GREEN PARKING REVIEW

Report ES12121

Portfolio Holder approval was sought for the introduction of a parking scheme in the Green Street Green area.

There is a high demand from shoppers, workers and residents to park on street given a number of small business units in the High Street at Green Street Green. Additionally a number of properties close to the High Street

25

Page 10 Environment Policy Development and Scrutiny Committee 25 September 2012 have limited off street parking facilities and residents can find it difficult to find a suitable parking place.

Following informal consultation with Ward Members, traders and resident groups, a formal consultation was undertaken in August 2012 to assess support for introducing a parking scheme.

Proposals for the scheme as originally drafted were outlined in Report ES12121. At the meeting additional drawings were tabled showing:

 a revised drawing (Drawing Number 11033-05 Revision A) for the Green Street Green Parking Scheme to replace the drawing appended to Report ES12121;  a proposed parking scheme for “Old” Shire Lane (Drawing Number 11160-01); and  proposed parking restrictions around the Beechwood Estate (Drawing Number 11033-01-10 Revision C).

Certain details in the text of Report ES12121 were amended by virtue of Drawing Number 11033-05 Revision A. This drawing took account of the outcomes from consultation - which were not available when the report was drafted - along with outcomes of a meeting on 21 st September 2012 between Councillor Grainger, the Head of Traffic and Road Safety and the Contact Officer for the report.

The Head of Traffic and Road Safety explained that some of the Green Street Green parking was associated with Metrobus staff based at the nearby Metrobus garage. It had been suggested by Councillor Samaris Huntington- Thresher that officers also look at using “Old” Shire Lane for parking. The proposal for consideration was that free parking spaces be allocated at places along “Old” Shire Lane subject to continued access to the salt depot at the end of the Lane. Concerning proposed parking restrictions for the Beechwood Estate, the Head of Traffic and Road Safety indicated that consultation would be undertaken on the proposals.

Councillor Grainger supported views conveyed prior to the meeting from Councillor Samaris Huntington-Thresher. It would be helpful to have the additional parking in “Old” Shire Lane and the additional parking indicated on Drawing 11033-05 Revision A. Reference was also made to drawing away Metrobus and Waitrose staff from parking in Laxey and Lezayre Roads.

To prevent any problems for snow clearance vehicles exiting the salt depot along “Old” Shire Lane, the Chairman suggested a restriction preventing overnight parking along the Lane. Councillor Adams suggested that any restriction apply to a period when snow clearance vehicles might be likely to operate and it was confirmed that seasonal restrictions could be looked into.

26 Page 11 Environment Policy Development and Scrutiny Committee 25 September 2012

RESOLVED that the Portfolio Holder be recommended to:

(1) implement parking changes shown on Drawing Number 11033-05 Revision A along with the additional parking and changes for “Old” Shire Lane as shown on Drawing Number 11160-01;

(2) undertake a consultation on the proposed parking restrictions around the Beechwood Estate (Drawing Number 11033-01-10 Revision C);

(3) delegate the decision on final design of the schemes at (1) and (2) above to the Director of Environmental Services, in consultation with the Environment Portfolio Holder and Ward Members; and

(4) agree that the Green Street Green and Old Shire Lane schemes be reviewed after six months to determine if they have met their objectives and to discover if parking issues need to be addressed in any roads currently outside of the affected area, and that if a scheme is installed in the Beechwood Estate that this scheme is also reviewed at the same time as the Green Street Green and “Old” Shire Lane schemes.

F) BRITTENDEN PARADE, GREEN STREET GREEN - PROPOSED MAKING UP

Report ES12128

Details were provided of the referendum results into the making up of Brittenden Parade.

RESOLVED that the Portfolio Holder be recommended to:

(1) Approve the layout for Brittenden Parade as shown on drawing no. ESD-10542-3

(2) Make a First Resolution under s.205(1) of the Highways Act 1980 in respect of Brittenden Parade as follows:

The Council do hereby declare that Brittenden Parade, Green Street Green is not sewered, levelled, paved, metalled, flagged, channelled, made good and lighted to its satisfaction and therefore resolve to execute street works therein, under the provisions of the Private Street Works Code as set out in the Highways Act 1980.

Schedule of Works From the junction with Glentrammon Road to the north to a point some 45.0m south where the street terminates outside no. 5 Brittenden Parade, as more particularly shown on drawing no. ESD- 10542-3

27

Page 12 Environment Policy Development and Scrutiny Committee 25 September 2012

21 FORWARD WORK PROGRAMME AND MATTERS ARISING

Report ES12108

In considering the Work Programme, the Chairman was keen for the Committee’s Working Groups to take forward outstanding matters.

In particular, the Chairman was looking to see the Transport Priorities Working Group begin its review on tram and DLR links into the borough. He indicated that the Working Group should begin this aspect of its work ahead of considering a Borough Transport Policy which could start next year - this would be in advance of the next Local Implementation Plan (LIP) process.

APPENDIX A

QUESTION TO THE PORTFOLIO HOLDER FROM MRS VIKKI HUGHES, WICKHAM COMMON RESIDENTS ASSOCIATION ( WCRA) FOR ORAL REPLY

1. Following an accident the WCRA is re -igniting the appeal for a pedestrian crossing on the A232 Croydon Road, close to Hartfield Crescent. This location is used extensively by school children at peak rush hour, from an estate effectively cut off from Hayes. What, after over 10 years, is the best way to ensure a successful outcome?”

Reply

Mindful of the history of this site, likewise of the numerous q uestions and enquiries posed and considered over time, I am by no means clear that there is either a ‘best’ or indeed any way at all to obtain the outcome you would prefer.

That said, I am also extremely conscious of the tremendous efforts which have been expended by Ward Councillors and Council Officers alike over time to achieve an accommodation with TfL, and were TfL’s position on related matters to change, I know that they can be relied upon to update and inform you immediately.

Supplementary Question

In her supplementary question, Mrs Hughes sought further advice on how to effectively take forward the Residents Association’s appeal for a crossing and whether there was any further way to move forward.

Reply

The Portfolio Holder referred to three particular considerations; (i) the need for TfL agreement to a pedestrian crossing as the A232 is a Principal Road maintained by TfL funding; (ii) land either side of the road being City of

28 Page 13 Environment Policy Development and Scrutiny Committee 25 September 2012

London Common Land and (iii) a need for clarity amongst local residents on measure(s) that are wanted.

The Portfolio Holder was keen to help but indicated that it might be necessary to accept that TfL might not be prepared to change their view. TfL focussed analytically with limited funds and there was a rationale and priority for TfL spending on schemes. The local London Assembly Member and Member of Parliament could also be approached.

------

QUESTIONS TO THE PORTFOLIO HOLDER FROM MR COLIN WILLETTS FOR WRITTEN REPLY

1. With regard to Cotmandene Crescent Car Park, could the Portfolio Holder tell us the cost on each occasion for removal of i) the dumped bagged arisings (and associated rubbish) at the far end of the car park adjacent to the petrol garage via grab lorry? and ii) the cost on each occasio n for the removal of dumped bagged rubbish (and associated bric a brac) in front of the recycling banks?

Reply i) Where a fly-tip is of sufficient quantity for Veolia to be required to attend with the ‘grab lorry’, a set price per visit of £47.16 is charged. This covers all material to a maximum volume of 10 cubic metres. ii) For small quantities of general waste and bric-a-brac, this is cleared by Kier as part of the daily clean of the Bring Sites incorporated in the Street Cleansing Contract, and there is no specific additional cost involved other than possible additional landfill tax.

------

2. Could the Portfolio Holder tell us how many offenders the Council has taken action against/or prosecuted for illegally fly tipping/dumping rubbish in Cotmandene Crescent car park over the previous six months up until the 25/9/12?

Reply

I will provide you with a full answer to this question at the earliest appropriate opportunity.

------

3. Following my complaints to the local authority regarding illegal flytipping, can the Portfolio Holder confirm that he will be 'giving the go ahead ' for the installation of CCTV (covert or otherwise) to catch & penalise those perpetrators committing this environmental nuisance in Cotmandene Crescent

29

Page 14 Environment Policy Development and Scrutiny Committee 25 September 2012 car park?

Reply

I will provide you with a full answer to this question at the earliest appropriate opportunity.

------

The Meeting ended at 8.46 pm

Chairman

30 Page 15 This page is left intentionally blank

Page 16 Agenda Item 6

LONDON BOROUGH OF BROMLEY

STATEMENT OF EXECUTIVE DECISION

The Portfolio Holder for the Environment, Councillor Colin Smith, has made the following executive decision:

BUDGET MONITORING 20 12/13

Reference Report (ES12109) :

Env Budget Monitoring 2012/13

Enc. 1 for Env Budget Monitoring 2012/13

Decision:

The latest 2012/13 budget projection for the Environment Portfolio be endorsed.

Reasons:

Based on expenditure and activity levels to 31st August 2012, the 2012/13 budget for the Environment Portfolio is projected to balance at year end.

The proposed decision was scrutinised by the Environment PDS Committee on 25th September 2012 and the Committee supported the proposal.

.. Councillor Colin Smith Environment Portfolio Holder

Mark Bowen Director of Resources Bromley Civic Centre Stockwell Close Bromley BR1 3UH

Date of Decision: 5 Oct 2012 Implementation Date (subject to call-in): 12 Oct 2012 Decision Reference: ENV12008

Page 17

LONDON BOROUGH OF BROMLEY

STATEMENT OF EXECUTIVE DECISION

The Portfolio Holder for the Environment, Councillor Colin Smith, has made the following executive decision:

CAPITAL PROGRAMME – FIRST QUARTER MONITO RING 2012/13 AND FIN AL OUTTURN 2011/12

Reference Report (RES12151):

ENV PDS 250912 Capital Programme - 1st Quarter Monitoring 2012-13 and Final Outturn 2011-12

ENV PDS 250912 Appendix A to Capital Programme Report

Decision:

The changes agreed by the Executive in July be confirmed.

Reasons:

At its meeting on 25th July 2012, the Executive agreed a revised Capital Programme for 2012/13 to 2015/16 and changes in respect of the Capital Programme for the Environment Portfolio are highlighted in Report RES12151.

The proposed decision was scrutinised by the Environment PDS Committee on 25th September 2012 and the Committee supported the proposal.

.. Councillor Colin Smith Environment Portfolio Holder

Mark Bowen Director of Resources Bromley Civic Centre Stockwell Close Bromley BR1 3UH

Date of Decision: 5 Oct 2012 Implementation Date (subject to call-in): 12 Oct 2012 Decision Reference: ENV12009

Page 18

LONDON BOROUGH OF BROMLEY

STATEMENT OF EXECUTIVE DECISION

The Portfolio Holder for the Environment, Councillor Colin Smith, has made the following executive decision:

EXTENSION TO CONTRAC T FOR PROVISION OF M OBILE PHONE PARKING

Reference Report (ES12111) :

Extension to Contract for Provision of Mobile Phone Parking

Decision:

(1) The contract for mobile phone parking payment be extended for a further two years.

(2) The policy of reducing the number of pay and display machines be continued where practical.

Reasons:

Report ES12111 reviews the first 2.5 years of the scheme for mobile phone parking payment, going forward into the third and final year of the contract. There is an option to extend the contract at the Council’s discretion for a further period not exceeding two years and the report sets out the reasons for recommending an extension.

Parking payment by mobile phone has proved to be a continuing success with an average 410 transactions per day. This is steadily increasing with a projected 150,000 transactions for 2012/13.

The removal of 23 pay and display machines at specific on-street locations has also taken place throughout the Borough (enabling the machines to be recycled) with a further 18 machines ready to be removed. The Mobile Phone Parking Scheme is advertised at each location where a machine has been removed. Removal of the machines does not affect the public’s ability to pay by cash given the provision of at least one machine within the zone.

Mobile phone payment has contributed to the Council being able to reduce cash collection costs by £43k per annum. If mobile phone payment continues to increase, additional savings could be generated from cash collection costs. The expected growth would also enable more pay and display machines to be removed and recycled.

Bromley Parking Services and Cobalt Technologies have worked well together in introducing new parking schemes or making adjustments to parking tariffs. There is scope within the current contact to provide other mobile phone parking solutions in future and Bromley Parking Services and Cobalt are keen to explore such ideas.

Officers have maintained a close interest in services provided by other mobile phone parking companies and are not aware of any different services that would warrant a tendering exercise. It is felt that there are clear advantages to continuing with the contract and this decision gives approval to extend the contract for a further two years. Page 19

The proposed decision was scrutinised by the Environment PDS Committee on 25th September 2012 and the Committee supported the proposal.

.. Councillor Colin Smith Environment Portfolio Holder

Mark Bowen Director of Resources Bromley Civic Centre Stockwell Close Bromley BR1 3UH

Date of Decis ion: 5 Oct 2012 Implementation Date (subject to call-in): 12 Oct 2012 Decision Reference: ENV12010

Page 20

LONDON BOROUGH OF BROMLEY

STATEMENT OF EXECUTIVE DECISION

The Portfolio Holder for the Environment, Councillor Colin Smith, has made the following executive decision:

TFL FUNDED WORK PROG RAMME FOR 2013/14

Reference Report (ES12116):

TFL FUNDED WORK PROGRAMME FOR 2013/14

Enc. 1 for LIP Programme Update

Enc. 2 for LIP Programme Update

Decision:

(1) The programme of formula funded schemes for 2013/14 at Enclosure 1 to Report ES12116 be approved for submission to Transport for London.

(2) The bid for Bridges and Structures at Enclosure 2A to Report ES12116 be approved for submission to Transport for London.

(3) The programme for Principal Road Maintenance at Enclosure 2B to Report ES12116 be approved for submission to Transport for London.

(4) The Director of Environmental Services, in consultation with the Environment Portfolio Holder, be authorised to make post-submission changes to the programme to reflect any necessary changes to priority, potential delays to implementation following detailed design and consultation, or other unforeseen events.

Reasons:

In relation to Bromley’s 2013/14 formula allocation from TfL (£2.771m), this decision provides approval for a recommended list of schemes to be submitted to TfL in early October 2012.

Ring-fenced TfL funding will also be available to support other programmes, including Local Transport Priorities, Principal Road Maintenance, Bridges/Structures and Bromley North Village. As such the above decision also approves the submission of bids to TfL for Bridges and Structures and a Programme of Principal Road Maintenance.

The proposed decision was scrutinised by the Environment PDS Committee on 25th September 2012 and the Committee supported the proposal.

.. Councillor Colin Smith Environment Portfolio Holder

Page 21

Mark Bowen Director of Resources Bromley Civic Centre Stockwell Close Bromley BR1 3UH

Date of Decision: 5 Oct 2012 Implementation Date (subject to call-in): 12 Oct 2012 Decision Reference: ENV12011

Page 22

LONDON BOROUGH OF BROMLEY

STATEMENT OF EXECUTIVE DECISION

The Portfolio Holder for the Environment, Councillor Colin Smith, has made the following executive decision:

GREEN STREET GREEN PARKING REVIEW

Reference Report (ES12121):

Green Street Green Parking Review

Enc. 1 for Green Street Green Parking Review

Enc. 2 for Green Street Green Parking Review

Decision:

(1) Parking changes shown on Drawing Number 11033-05 Revision A along with the additional parking and changes for “Old” Shire Lane as shown on Drawing Number 11160-01 be implemented.

(2) A consultation on the proposed parking restrictions around the Beechwood Estate (Drawing Number 11033-01-10 Revision C) be undertaken.

(3) The decision on final design of the schemes at (1) and (2) above be delegated to the Director of Environmental Services, in consultation with the Environment Portfolio Holder and Ward Members.

(4) The Green Street Green and “Old” Shire Lane schemes be reviewed after six months to determine if they have met their objectives and to discover if parking issues need to be addressed in any roads currently outside of the affected area, and that if a scheme is installed in the Beechwood Estate that this scheme is also reviewed at the same time as the Green Street Green and “Old” Shire Lane schemes.

Reasons:

This decision gives approval for the introduction of a parking scheme in the Green Street Green area.

There is a high demand from shoppers, workers and residents to park on street given a number of small business units in the High Street at Green Street Green. Additionally a number of properties close to the High Street have limited off street parking facilities and residents can find it difficult to find a suitable parking place.

Following informal consultation with Ward Members, traders and resident groups, a formal consultation was undertaken in August 2012 to assess support for introducing a parking scheme.

Proposals for the scheme as originally drafted are outlined in Report ES12121. However the Environment PDS Committee at their meeting on 25 th September 2012 supported proposals for revising and adding to those contained in Report ES12121. These proposals are outlined in additional drawings which were tabled at the Page 23

Committee meeting and show:

• a revised drawing (Drawing Number 11033-05 Revision A) for the Green Street Green Parking Scheme to replace the drawing appended to Report ES12121; • a proposed parking scheme for “Old” Shire Lane (Drawing Number 11160-01); and • proposed parking restrictions around the Beechwood Estate (Drawing Number 11033-01-10 Revision C).

Certain details in the text of Report ES12121 are amended by virtue of Drawing Number 11033-05 Revision A. This drawing takes account of the outcomes from consultation - which were not available when the report was drafted - along with outcomes of a meeting on 21 st September 2012 between a Ward Councillor, the Head of Traffic and Road Safety and the Contact Officer for Report ES12121. It was at the recommendation of Ward Councillors that proposals have been developed for the use of “Old” Shire Lane in the context of overall parking proposals for the Green Street Green area.

The proposed decision was scrutinised by the Environment PDS Committee on 25th September 2012 (see text above).

.. Councillor Colin Smith Environment Portfolio Holder

Mark Bowen Director of Resources Bromley Civic Centre Stockwell Close Bromley BR1 3UH

Date of Decision: 5 Oct 2012 Implementation Date (subject to call-in): 12 Oct 2012 Decision Reference: ENV12012

Page 24

LONDON BOROUGH OF BROMLEY

STATEMENT OF EXECUTIVE DECISION

The Portfolio Holder for the Environment, Councillor Colin Smith, has made the following executive decision:

BRITTENDEN PARADE GR EEN STREET GREEN - PROPOSED MAKING UP

Reference Report (ES12128):

Brittenden Parade, Green Street Green - Proposed Making Up

Enc. 1 for Brittenden Parade, Green Street Green - Proposed Making UP

Deci sion:

(1) The layout for Brittenden Parade as shown on drawing no. ESD-10542-3 be approved.

(2) A First Resolution under s.205(1) of the Highways Act 1980 be made in respect of Brittenden Parade as follows:

The Council do hereby declare that Brittenden Parade, Green Street Green is not sewered, levelled, paved, metalled, flagged, channelled, made good and lighted to its satisfaction and therefore resolve to execute street works therein, under the provisions of the Private Street Works Code as set out in the Highways Act 1980.

Schedule of Works From the junction with Glentrammon Road to the north to a point some 45.0m south where the street terminates outside no. 5 Brittenden Parade, as more particularly shown on drawing no. ESD-10542-3

Reasons:

Report ES12128 provides details of the referendum results into the making up of Brittenden Parade, Green Street Green.

The proposed decision was scrutinised by the Environment PDS Committee on 25th September 2012 and the Committee supported the proposal.

.. Councillor Colin Smith Environment Portfolio Holder

Mark Bowen Director of Resources Bromley Civic Centre Stockwell Close Bromley BR1 3UH Date of Decision: 5 Oct 2012 Implementation Date (subject to call-in): 12 Oct 2012 Decision Reference: ENV12013 Page 25 This page is left intentionally blank

Page 26 Agenda Item 7a

Report No. London Borough of Bromley ES12138 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For pre-decision scrutiny by the Environment PDS Committee on Date: 20 November 2012 Decision Type: Non-Urgent Executive Non-Key

Title : BUDGET MONITORING 2012/13

Contact Officer: Claire Martin, Head of Finance Tel: 020 8313 4286 E-mail: [email protected]

Chief Officer: Nigel Davies, Director of Environmental Services

Ward: Borough-wide

1. Reason for report

This report provides an update of the latest budget monitoring position for 2012/13 for the Environment Portfolio, based on expenditure and activity levels up to 30th September 2012. This shows a projected underspend of £255k for 2012/13.

It also reports the level of expenditure and progress with the implementation of the selected projects within the Member Priority Initiatives.

______

2. RECOMMENDATIONS

2.1 The Portfolio Holder is recommended to endorse the latest 2012/13 budget projection for the Environment Portfolio.

2.2 The Portfolio Holder is recommended to note the progress of the implementation of the Environment projects within the Member Priority Initiatives programme.

1 Page 27 Corporate Policy

1. Policy Status: Existing Policy Sound financial management.

2. BBB Priority: Excellent Council; Quality Environment ______

Financial

1. Cost of proposal: Not Applicable

2. Ongoing costs: Recurring Cost

3. Budget head/performance centre: All Environment Portfolio Budgets and Earmarked Reserve for Member Priority Initiaitives

4. Total current budget for this head: £41.0m and £1.15m

5. Source of funding: Existing revenue budgets 2012/13 and Earmarked Reserve for Member Priority Initiaitives ______

Staff

1. Number of staff (current and additional): 206ftes

2. If from existing staff resources, number of staff hours: N/A ______

Legal

1. Legal Requirement: Statutory Requirement: The statutory duties relating to financial reporting are covered within the Local Government Act 1972; the Local Government Finance Act 1998; the Accounts and Audit Regulations 1996; the Local Government Act 2000 and the Local Government Act 2002

2. Call-in: Applicable ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): The services covered in this report affect all Council Taxpayers, Business Ratepayers, those who owe general income to the Council, all staff, Members and Pensioners. ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? Not Applicable

2. Summary of Ward Councillors comments:

2 Page 28 3. COMMENTARY

3.1 The 2012/13 projected outturn is detailed in Appendix 1. This forecasts the projected spend for each division compared to the latest approved budget, and identifies in full the reason for any variances.

3.2 Costs attributable to individual services have been classified as “controllable” and “non- controllable” in Appendix 1. Budget holders have full responsibility for those budgets classified as “controllable” as any variations relate to those factors over which the budget holder has, in general, direct control. “Non-controllable” budgets are those which are managed outside of individual budget holder’s service and, as such, cannot be directly influenced by the budget holder in the shorter term. These include, for example, building maintenance costs and property rents which are managed by the Property Division but are allocated within individual departmental/portfolio budgets to reflect the full cost of the service. As such, any variations arising are shown as “non-controllable” within services but “controllable” within the Resources Portfolio. Other examples include cross departmental recharges and capital financing costs. This approach, which is reflected in financial monitoring reports to budget holders, should ensure clearer accountability by identifying variations within the service that controls financial performance. Members should specifically refer to the “controllable” budget variations relating to portfolios in considering financial performance. These variations will include the costs related to the recession.

3.3 Council on 26 th March 2012 approved the setting aside of £2.26m in an earmarked reserve for Member priority initiatives. The Environment Portfolio is responsible for the delivery of three of these initiatives as detailed below:-

Member Priority Initiatives £'000

General Improvements to footways and highways 750 Support to Friends Groups 250 Renew/replace the Council's community recycling sites 150 1,150

3.4 Appendix 2 has the details of the progress of each of the schemes.

4. POLICY IMPLICATIONS

4.1 The Resources Portfolio Plan includes the aim of effective monitoring and control of expenditure within budget and includes the target that each service department will spend within its own budget.

4.2 The four year financial forecast report highlights the financial pressures facing the Council. It remains imperative that strict budgetary control continues to be exercised in 2012/13 to minimise the risk of compounding financial pressures in future years.

4.3 Chief Officers and Departmental Heads of Finance are continuing to place emphasis on the need for strict compliance with the Council’s budgetary control and monitoring arrangements.

5. FINANCIAL IMPLICATIONS

5.1 The 2012/13 controllable budget for the Environment Portfolio is projected to be £250k underspent at the year end based on financial information available to 30th September 2012. Within this projection there are major variations which are detailed in Appendix 1 and summarised below.

3 Page 29 5.2 A shortfall in income totalling £560k is projected for on- and off-street parking, partly due to the price increases not taking effect until 30 th April and partly due to a reduction in usage. This deficit is currently being offset by management action to reduce parking running costs (Cr £104k), extra income from parking and bus lane contraventions (Cr £166k), and a reduction in waste disposal tonnage (Cr £213k).

5.3 Customer drop out for trade waste collections has not been as high as previous years despite the recent price increase. Based on current information, there could be a surplus of £150k. This is offsetting a reduction in income (£150k) from trade waste delivered to the depots due to a decrease in customers. It should be noted that part of the reduction in waste disposal tonnages is directly related to decrease in customers (Cr £77k). The situation will be closely monitored.

5.4 A reduction in unit rates of electricity in April has resulted in an underspend being projected for the street lighting electricity budget of £170k. In addition to this, rebates and credits have been received totalling £80k.

5.5 Appendix 2 shows that nothing has been spent or committed as at 30 th September 2012 out of the £1.15m set aside for the three projects within the Member priority initiatives. It also includes comments on the progress of each of the schemes.

Non -Applicable Sections: Legal, Personnel Background Documents: 2012/13 budget monitoring files within ES finance section (Access via Contact Officer)

4 Page 30 Appendix 1a Environmental Services Portfolio Budget Monitoring Summary

2011/12 Division 2012/13 2012/13 2012/13 Variation Notes Variation Full Year Actuals Service Areas Original Latest Projection Last Effect Budget Approved Reported £'000 £'000 £'000 £'000 £'000 £'000 £'000

Customer & Support Services (5,610) Parking (6,697) (6,722) (6,432) 290 1 - 4 300 400 1,932 Support Services 1,402 1,342 1,342 0 0 0

(3,678) (5,295) (5,380) (5,090) 290 300 400

Public Protection - ES 101 Emergency Planning 113 113 113 0 0 0

101 113 113 113 0 0 0

Street Scene & Green Space 5,904 Area Management/Street Cleansing 4,535 4,465 4,465 0 5 0 0 2,454 Highways 2,385 2,385 2,385 0 0 0 (18) Markets (29) (29) (29) 0 0 0 6,057 Parks and Green Space 6,042 6,129 6,129 0 0 0 567 Street Regulation 628 570 570 0 0 0 16,549 Waste Services 16,254 16,453 16,163 (290) 6 (300) (300)

31,513 29,815 29,973 29,683 (290) (300) (300)

Transport & Highways 6,613 Highways incl London Permit Scheme 6,188 6,469 6,219 (250) 7 0 (200) 161 Highways Planning 142 167 167 0 0 0 866 Traffic & Road Safety 346 310 310 0 0 0

7,640 6,676 6,946 6,696 (250) 0 (200)

35,576 TOTAL CONTROLLABLE 31,309 31,652 31,402 (250) 0 (100)

7,652 TOTAL NON-CONTROLLABLE 6,937 7,160 7,155 (5) 8 0 0

2,614 TOTAL EXCLUDED RECHARGES 2,103 2,228 2,228 0 0 0

45,842 PORTFOLIO TOTAL 40,349 41,040 40,785 (255) 0 (100)

Reconciliation of latest approved budget £'000

Original budget 2012/13 40,349 Repairs and Maintenance 167 Supplementary estimate for implementation of Flooding and Water Act 220 Carry forward re Garden Waste Trial 161 Carry forward re Parks & Green Space - Ponds 20 Carry forward re Parks & Green Space - Playground works 67 Rental Income - Budget Adjustments (already actioned by KT) 60 Property Services Rental Income (4) Latest Approved Budget for 2012/13 41,040

Page 31 Appendix 1b

Environmental Services Department - Budget Monitoring Notes - 30 September 2012

1. Income from bus lane contraventions Cr £109k

An increase in bus lane contraventions has meant that income is above estimated levels by £115k, offset by £6k less income received for tickets issued in 2011/12 than expected. The net effect is a surplus of £109k.

2. Off Street Car Parking Dr £217k

The parking charges income budget assumed that the new charges would be in place for the full financial year 2012-13 but these came into effect in late April 2012, as advised in the increase in charges report. The impact of this slight delay is Dr £20k.

Using the data available from the first five months following the increase, off-street car parking income is projected to be £280k below budget expectation - although this could be as high as £300k. Within this variation, around £100k relates to the four multi-storey car parks and £160k other surface car parks. The income will be closely monitored during the next few months and any major variances reported to Members.

The projected income deficit is partly being offset by savings from management action of £63k; through reducing running expenses including contract costs.

3. On Street Car Parking Dr £210k

Income shortfall in April was £40k as the fees were introduced at the end of the month. After analysing the data to 30th September 2012, it is clear that income is well below expected levels in Bromley town centre, and Orpington. Overall a shortfall in income of £280k is projected, although this could be as high as £300k.

Management action has been taken to freeze the equipment replacement budget of £70k, on the assumption that - following the introduction of mobile phone parking - the policy of recycling surplus pay and display machines is continued.

The full year effect of the deficit currently projected for parking will be balanced primarily through additional income generated from the extra parking capacity being provided within Bromley town centre to address the planned closure of Westmoreland Road Car Park. The remainder will be funded from the underspend within waste management.

4. Car Parking Enforcement Cr £28k

There is a projected net surplus of £127k from PCNs issued by Vinci due to an increase in contraventions. As a result of a range of contract performance requirements being met, there is a performance payment due to the contractor of around £40k.

There is a projected deficit of £30k for mobile and static cameras due to reduced contraventions. However contraventions have begun to increase over the last couple of months which could reduce the projected deficit if the trend continues.

There is a projected overspend within staffing budgets of £29k.

Page 32 Appendix 1b

Summary of variations within Parking: £'000

Bus Routes Enforcement (109) Off Street Car Parking 280 On Street Car Parking 280 Deficit in income from CCTV parking contraventions 30 Net additional income from other parking contraventions (87) Savings resulting from management action (133) Overspend within Enforcement staffing costs 29 Total variation for parking 290

5. Area Management & Street Cleansing £0k

There is a projected overspend within employee costs of £13k. This is a result of delays in implementing the Street Scene & Green Space review of back-office functions.

There is also a projected net overspend within premises costs of £13k, and toilet cleaning contract payments of £12k, as a result of delays in the planned closure of public conveniences. These overspends are being met by underspends within graffiti removal of £38k.

6. Waste Management Cr £290k

There is currently a total projected underspend within waste disposal tonnages of £290k. £165k has arisen from 2,150 lower tonnes disposed than budgeted for between April and September, with a further projected underspend of £125k relating to a variation of 1,630 tonnes projected for the rest of 2012-13.

Within the total projected variation of 3,780 tonnes, approximately 1,000 tonnes relates to decreased activity from builders and other tradesmen bringing waste to the depots. (500 tonnes lower of waste disposal at the depots in the period April to September 2012 compared to the equivalent period in 2011). This has resulted in a projected underspend of £77k, which partly offsets the income shortfall described below.

A deficit of £150k is being projected for trade waste delivered income due to reduced activity as described above. The bad weather in this period, especially during April and May, may have had an impact and it has been hoped that this activity would pick up later in the year. So far, this appears not to have happened, hence the deficit continues to be projected. The projected net deficit relating to this service is thefefore £73k.

Within trade waste collection income, there is a projected surplus of £150k. Prices were increased by 17% from 1st April 2012 and expectation was built into the 2012-13 for a dropout of 11% of customers. However, it would appear that the actual net loss of total customers has only been around 3.5%, resulting in the projected surplus income.

As a result of a reduced dropout of customers than budgeted, there are increased costs within the collection contract of approximately £25k. These are offset by various underspends across other aspects of the collection contract.

Summary of variations within Waste Management £'000

Decrease in waste disposal tonnage (213) Reduction in disposal tonnage as a direct result of a decrease in trade waste delivered customers (77) Shortfall of income due to drop in customers delivering trade waste to depots 150 Additional income from trade waste collections (150) (290)

Page 33 Appendix 1b

7. Highways including London Permit Scheme Cr £250k

There is a projected underspend within the Street lighting electricity budget of £250k. This is largely the result of an unanticipated reduction in unit rates of over 25% between March and April 2012. Additionally, rebates and credits of £80k have been received.

Within NR&SWA income, there is a projected net deficit of £30k. It is expected that this will be covered from management action to reduce running expenses.

8. Non-controllable budgets Dr £5k

For information - here, the variations relate to a net shortfall within property rental income budgets across the division. Property Division are accountable for these variations.

Page 34 Appendix 2

Analysis of Members' Initiatives - Earmarked Reserves @ 30.09.2012

Total Spend & Balance Responsible Allocation Spend To Commitments Item Divison / Service Area Commitments Available Comments on Progress of Scheme Officer £'000 Date £'000 £'000 £'000 £'000 Footways, Highways & T&H - Highways Garry Warner 750 0 0 0 750 Orders to be placed imminently General Improvements

SS&GS - Parks & Green Plans already underway, but no orders Support for Friends Groups Louise Simpson 250 0 0 0 250 Space placed yet.

Renewal / Replacement of Plans already underway, but no orders SS&GS - Waste John Woodruff 150 0 0 0 150 Community Recycling Sites placed yet.

TOTAL 1,150 0 0 0 1,150 Page 35 This page is left intentionally blank

Page 36 Agenda Item 7b

Report No. London Borough of Bromley RES12179 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For Pre-Decision Scrutiny by the Environment PDS Committee on

Date: 20 November 2012 Decision Type: Non-Urgent Executive Non-Key

Title : CAPITAL PROGRAMME - 2ND QUARTER MONITORING 2012/13

Contact Officer: Martin Reeves, Principal Accountant Tel: 020 8313 4291 E-mail: [email protected]

Chief Officer: Director of Resources

Ward: (All Wards);

1. Reason for report

On 24th October 2012, the Executive received the 2nd quarterly capital monitoring report for 2012/13 and agreed a revised Capital Programme for the four year period 2012/13 to 2015/16. This report highlights in paragraphs 3.1 to 3.2 changes agreed by the Executive in respect of the Capital Programme for the Environment Portfolio and highlights in Appendix B progress on schemes in the 2012/13 programme. The revised programme for this portfolio is set out in Appendix A.

______

2. RECOMMENDATION

The Portfolio Holder is asked to confirm the changes agreed by the Executive in October.

1 Page 37 Corporate Policy

1. Policy Status: Existing Policy: Capital Programme monitoring and review is part of the planning and review process for all services.

2. BBB Priority: Excellent Council: ______

Financial

1. Cost of proposal: Not Applicable:

2. Ongoing costs: Not Applicable:

3. Budget head/performance centre: N/A (Capital Programme)

4. Total current budget for this head: £19.0m for the Environment Portfolio over four years 2012/13 to 2015/16

5. Source of funding: Capital grants, capital receipts and earmarked revenue contributions ______

Staff

1. Number of staff (current and additional): 0.25 FTE

2. If from existing staff resources, number of staff hours: 9 hours per week ______

Legal

1. Legal Requirement: Non-Statutory - Government Guidance:

2. Call-in: Applicable ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): N/A ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? No

2. Summary of Ward Councillors comments: N/A

2 Page 38 3. COMMENTARY

Capital Monitoring – variations agreed by the Executive on 24 th October 2012

3.1 A revised Capital Programme was approved by the Executive in October, following a detailed monitoring exercise carried out after the 2nd quarter of 2012/13. The base position was the revised programme approved by the Executive on 25 th July 2012, as amended by variations approved at subsequent Executive meetings. Only one change to the Environment Portfolio Programme was approved by the Executive in October and this is shown in the table below and further details are included in paragraph 3.2. The revised Programme for the Environment Portfolio is attached as Appendix A and detailed comments on individual schemes are included at Appendix B.

Capital Expenditure 2012/13 2013/14 2014/15 2015/16 TOTAL £000 £000 £000 £000 £000 Approved Capital Programme (25/07/12) 6,416 3,220 4,050 4,050 17,736

Variations agreed by Executive 24/10/12 Transport for London – revised grant allocations for 1,267 - - - 1,267 various highways schemes Scheme rephasing from 2012/13 into 2013/14 - Chislehurst Road Bridge (retention) -59 59 - - - - Bromley Town Centre – extra parking capacity -10 10 - - -

Revised Environment Programme 7,614 3,289 4,050 4,050 19,003

3.2 Transport for London – revised support for highway schemes (addition of £1,267k in 2012/13)

Provision for transport schemes to be 100% funded by TfL was originally included in the Capital Programme 2012/13 to 2015/16 on the basis of the bid in our Borough Spending Plan (BSP). Notification of an overall increase of £1,267k in 2012/13 was recently received from TfL and has now been included in the Programme. Grant allocations from TfL change frequently and any further variations will be reported in subsequent capital monitoring reports.

3.3 Scheme Rephasing

In reports to both the June and July meetings, the Executive was informed of the final outturn for capital expenditure in 2011/12 and noted that the overall level of slippage into later years (some £6.9m) was significantly lower than in previous years. Slippage of capital spending estimates has been a recurring theme over the years and Members were pleased to note that, following a review of the system for capital monitoring and for estimating the phasing of expenditure, carried out after the 2010/11 final outturn, a more realistic approach towards anticipating slippage was taken in setting the revised estimates in February. There was a net overspend of £0.3m on Environment Portfolio schemes in 2011/12 (mainly on the Chislehurst Road Bridge scheme) and this was analysed in the 1 st quarter’s monitoring report to the PDS Committee meeting in September. No further rephasing opportunities had been identified at that stage, but two schemes were rephased in the 2 nd quarter (see the table in paragraph 3.1). The latest position on 2012/13 capital schemes is outlined in Appendix B.

Post Completion Reviews

3.4 Under approved Capital Programme procedures, capital schemes should be subject to a post- completion review within one year of completion. Following the major slippage of expenditure at the end of 2010/11, Members confirmed the importance of these as part of the overall capital monitoring framework. These reviews should compare actual expenditure against budget and evaluate the achievement of the scheme’s non-financial objectives. While no post-completion

3 Page 39 reports are currently due for completed Environment Portfolio schemes, this quarterly report will monitor the future position and will highlight any future reports required.

4. POLICY IMPLICATIONS

4.1 Capital Programme monitoring and review is part of the planning and review process for all services. The capital review process requires Chief Officers to ensure that bids for capital investment provide value for money and match Council plans and priorities.

5. FINANCIAL IMPLICATIONS

5.1 These were reported in full to the Executive on 24 th October 2012. Changes agreed by the Executive for the Environment Portfolio Capital Programme are set out in the table in paragraph 3.1.

Non -Applicable Sections: Legal and Personnel Implications Background Documents: Departmental monitoring returns September 2012. (Access via Contact Approved Capital Programme (Executive 24/10/12). Officer) Capital Programme Q1 monitoring report (Executive 24/10/12).

4 Page 40 ENVIRONMENT PDS 27/11/12 APPENDIX A

ENVIRONMENT PORTFOLIO - APPROVED CAPITAL PROGRAMME 24th OCTOBER 2012

Total Approved Actual to Estimate Estimate Estimate Estimate Capital Scheme/Project Estimate 31.3.12 2012/13 2013/14 2014/15 2015/16 Responsible Officer Remarks £'000's £'000's £'000's £'000's £'000's £'000's

SCHEMES FULLY FUNDED BY TRANSPORT FOR LONDON 8000 0 4000 4000 London Bus Priority Network (LBPN) 1836 1836 Angus Culverwell 100% TfL funding, based on Borough Spending Plan submission to TfL and will only Cycle Route Network 1279 1279 Malcolm Harris proceed if 100% funding is agreed by TfL. The Capital Programme will be adjusted Safer Routes to Schools 945 945 Angus Culverwell/Louise French to reflect revised TfL approvals as these are received SELTRANS 2012 2012 Alan Lucking Travel Awareness 68 68 Angus Culverwell Bromley Town Centre Access Plan 31 31 Angus Culverwell 20 mph Zones 629 629 Deirdre Farrell/Angus Culverwell Bus Stop accessibility 134 134 Angus Culverwell & Environs WHS bid Access Plan 18 18 Kevin Munnelly *Local Safety Schemes 1927 1927 Deirdre Farrell/Angus Culverwell *Bridge Strengthening /Assessment 675 675 Garry Warner *Structural Maintenance - Principal Roads LBB 1474 1474 Garry Warner Walking 147 147 Angus Culverwell/Alan Lucking Education, training and publicity 134 134 Angus Culverwell Cycle Improvements off London Cycle 436 436 Malcolm Harris TFL - Borough Support 150 137 13 Alan Lucking Local Area Accessability - Orpington Town Centre 20 20 Angus Culverwell Parallel initiatives 24 24 Alan Lucking Station Access 161 161 Alan Lucking Controlled parking zones 125 125 Deirdre Farrell LEPT 574 574 Angus Culverwell Cycling on Greenways 353 153 200 Malcolm Harris Borough Transport Priorities (not allocated) 395 195 100 100 Angus Culverwell Car Clubs 10 0 10 Alan Lucking Chislehurst Road Bridge replacement 4114 2059 1996 59 Paul Redman 100% TfL funding; approved by Executive 22/06/11 Biking Boroughs 163 54 109 Steven Heeley TFL - New funding streams Maintenance 3438 1869 924 645 Angus Culverwell Corridors 3484 3279 205 Angus Culverwell Neighbourhoods 1660 1567 93 Angus Culverwell Smarter Travel 769 769 0 Angus Culverwell LIP Formula Funding 5406 0 2981 2425 Garry Warner/Angus Culverwell

TOTAL SCHEMES FULLY FUNDED BY TRANSPORT FOR LONDON 40591 22731 6631 3229 4000 4000 Page 41

OTHER Winter maintenance - gritter replacement 890 600 170 40 40 40 Paul Chilton Carbon Management Programme (Invest to Save funding) 500 362 138 Alastair Ballie Revenue savings (schemes to be worked up); £250k funded by Salix Orpington Public Realm Improvements 2200 2134 66 Garry Warner £1.2m TfL funding

*Feasibility Studies 40 0 10 10 10 10 Claire Martin

TOTAL OTHER 3630 3096 384 50 50 50

CAR PARKING Station Road Car Park - Miscellaneous works relating to sale 508 487 21 Heather Hosking Funded by capital receipt from disposal of car park The Hill Multi-Storey Car Park - strengthening works 280 212 68 Paul Redman Approved by Executive 29/09/10 Bromley Town Centre - increased parking capacity 520 0 510 10 Paul Redman Approved by Executive 23/05/12

TOTAL CAR PARKING 1308 699 599 10 0 0

TOTAL ENVIRONMENT PORTFOLIO 45529 26526 7614 3289 4050 4050 APPENDIX B-COMMENTS

ENVIRONMENT PORTFOLIO - APPROVED CAPITAL PROGRAMME 2nd QUARTER MONITORING

2012/2013

Estimate Actual to before Q2 Actual to Revised Capital Scheme/Project 31/03/12 monitoring 17/10/12 Estimate Comments for Q2 monitoring £'000's £'000's £'000's £'000's SCHEMES FULLY FUNDED BY TRANSPORT FOR LONDON TFL - Borough Support 137 0 0 13 100% TfL funded. Reflects revised TfL Programme for 2012/13 Cycling on Greenways 153 200 10 200 Borough Transport Priorities (not allocated) 195 100 0 100 Car Clubs 0 15 0 10 100% TfL funded. Reflects revised TfL Programme for 2012/13 Chislehurst Road Bridge replacement 2059 2055 1182 1996 £59k rephased into 2013/14 to reflect retention sums due for release during 2013/14 Biking Boroughs 54 109 13 109 TFL - New funding streams Maintenance 1869 1102 453 924 100% TfL funded. Reflects revised TfL Programme for 2012/13 Corridors 3279 28 100 205 100% TfL funded. Balance of expenditure relating to TfL Programme for 2011-12 Neighbourhoods 1567 44 4 93 100% TfL funded. Balance of expenditure relating to TfL Programme for 2011-12 Smarter Travel 769 0 0 0 LIP Formula Funding 0 1770 427 2981 100% TfL funded. Reflects revised TfL Programme for 2012/13

TOTAL SCHEMES FULLY FUNDED BY TRANSPORT FOR LONDON 10082 5423 2189 6631

OTHER Winter maintenance - gritter replacement 600 170 0 170 Carbon Management Programme (Invest to Save funding) 362 138 0 138 Revenue savings (schemes to be worked up); £250k funded by Salix Orpington Public Realm Improvements 2134 66 3 66 £1.2m TfL funding

*Feasibility Studies 0 10 0 10

TOTAL OTHER 3096 384 3 384

Page 42 CAR PARKING Station Road Car Park - Miscellaneous works relating to sale 487 21 0 21 Funded by capital receipt from disposal of car park The Hill Multi-Storey Car Park - strengthening works 212 68 0 68 Approved by Executive 29/09/10 Bromley Town Centre - increased parking capacity 0 520 0 510 £10k rephased into 2013/14 to reflect retention sums due for release during 2013/14

TOTAL CAR PARKING 699 609 0 599

TOTAL ENVIRONMENT PORTFOLIO 13877 6416 2192 7614 Agenda Item 7c Report No. London Borough of Bromley ES12141 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For Pre-Decision Scrutiny by the Environment PDS Committee on:

Date: 20 November 2012 Decision Type: Non-Urgent Executive Non-Key

Title : BRITTENDEN PARADE, GREEN STREET GREEN – PROPOSED MAKING UP

Contact Officer: Duncan Gray, Development Manager Tel: 020 8313 4556 E-mail: [email protected]

Chief Officer: Nigel Davies, Director of Environmental Services

Ward: and Pratts Bottom

1. Reason for report

1.1 To obtain a Resolution of Approval under the private Street Works Code in respect of Brittenden Parade. This will enable the street to be made-up and adopted as a highway maintainable at public expense.

______

2. RECOMMENDATIONS

2.1 That the specification, plan no. ESD/10542-4 which will be on display on the evening of the PDS committee, sections, estimate and provisional apportionment now submitted by the Director of Environmental Services, in respect of the scheme approved by the Environment Portfolio Holder on 5 th October 2012, be approved without modification.

2.2 That the Environment Portfolio Holder further resolves that the Council bears the whole of the cost of the street works, which will be met from funding provided by Transport for London, under the provisions of s.236(1) of the Highways Act 1980.

1 Page 43 Corporate Policy

1. Policy Status: Existing Policy:

2. BBB Priority: Quality Environment: ______

Financial

1. Cost of proposal: Estimated Cost £48k subject to confirmation of the costs of any necessary alterations to Statutory Undertakers’ mains and services

2. Ongoing costs: Non-Recurring Cost:

3. Budget head/performance centre: TfL LIP Funding 2012/13 – Network Infrastructure and Local Transport Priorities

4. Total current budget for this head: £405k for the former, of which £29k is set aside for this scheme; £100k for the latter, of which £30k is set aside for this scheme

5. Source of funding: TfL LIP Formula Funding 2012/13 ______

Staff

1. Number of staff (current and additional): 3

2. If from existing staff resources, number of staff hours: 75 ______

Legal

1. Legal Requirement: Statutory Requirement: By making a First Resolution in respect of this scheme, the Proper Officer of the Council was required to prepare various documents in accordance with s.205(3) of the Highways Act 1980. These documents must now be approved by a further resolution, the Resolution of Approval. In order to take advantage of the external funding available, it is intended that the Council meets the full cost of the scheme itself, but to do this, must pass a resolution to this effect under s.236(1) of the Highways Act 1980

2. Call-in: Applicable: ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): All users of Brittenden Parade including 5 shops and 5 flats ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? Yes

2. Summary of Ward Councillors’ comments: Ward members support the making up of Brittenden Parade

2 Page 44 3. COMMENTARY

3.1 On 9th May 2012 the Environment Portfolio Holder received a report setting out a number of optional schemes for the improvement of Brittenden Parade, Green Street Green, which has not been made up and adopted as a highway maintainable at the public expense.

3.2 Complaints about the condition of Brittenden Parade have been received from residents, users and the Green Street Green Village Society.

3.3 To enable the street to become a highway maintainable at public expense, the Council needs to adopt it, but is only empowered to do this following improvement to the appropriate standards. The improvement works may be carried out under the provisions of the Private Street Works Code, but for this to occur, the Council has to make two distinct resolutions, a First Resolution giving details of those aspects of the street with which it is dissatisfied and a further resolution, a Resolution of Approval. The latter resolution approves details of the works required to bring the street up to a suitable standard, an estimate of the cost of such works and a Provisional Apportionment of these costs, amongst the owners of the land fronting, adjoining and abutting on to the street.

3.4 The Portfolio Holder made a First Resolution under s.205(1) of the Highways Act 1980, on 5th October 2012. The appropriate documents have now been prepared to enable a Resolution of Approval to be made and these documents will be available for inspection at the meeting. This enables the Provisional Apportionment, which contains details of property ownerships, to be as up to date as possible.

3.5 The results of the consultation show that the majority of the owners and occupiers of the retail and residential premises in Brittenden Parade support making up.

3.6 The support of one of the residents for making up Brittenden Parade was conditional upon future consideration being given to the control of parking in the street. The street is located within the area currently being considered for a scheme of waiting restrictions for this part of Green Street Green and following the implementation of that scheme and the completion of the adoption of Brittenden Parade the situation in the street will be monitored with a view to introducing restrictions as necessary.

4. POLICY IMPLICATIONS

4.1 The proposal is within existing Council policy. Policy T14 of the Council’s Unitary Development Plan 2006 safeguards the frontagers, who usually have to meet most of the cost of making-up. It is intended that the Council will meet the whole of the expense of the street works, but the Portfolio Holder considered it appropriate in this specific case to consult the owners and occupiers of the retail and residential premises in Brittenden Parade.

5. FINANCIAL IMPLICATIONS

5.1 The estimated cost of the works is £48k, excluding any costs that may be necessary relating to the mains and utility services. These works will be met from the 2012/13 TfL LIP funding. In total, £59k is available for this scheme, made up of £29k from the 2012/13 Network Infrastructure budget allocation and £30k from the 2012/13 Local Transport Priorities budget allocation.

5.2 It should be noted that all Private Street Works include an amount of 15% of the estimated construction costs to cover staff time associated with the administration and supervision of the works. In this case, this amounts to £6,100 and is included in the total cost of the scheme as referred to in 5.1 above.

3 Page 45

6. LEGAL IMPLICATIONS

6.1 S.228 of the Highways Act 1980 permits the Council to adopt any private street by means of notices, displayed in the street for a period of one month, after street works have been executed in the street.

6.2 During the period that the s.228 notice is displayed, the owner of the street is able to object to its adoption as a highway maintainable at public expense. In such a case, the Council is able to apply to the Magistrates Court for an Order overruling the objection.

Non -Applicable Sections: Personnel Implications Background Documents: Brittenden Parade Green Street Green – (Access via Contact Officer) First Resolution 5th October 2012

4 Page 46 Agenda Item 7d

Report No. London Borough of Bromley ES12134 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For Pre-Decision Scrutiny by the Environment PDS Committee on: Date: 20 November 2012 Decision Type: Non-Urgent Executive Non-Key

Title : CONGESTION RELIEF SCHEME: BLACKBROOK LANE / BICKLEY PARK ROAD - JUNCTION IMPROVEMENT

Contact Officer: Malcolm Harris, Team Leader, Sustainable Transport Tel: 020 8313 4500 E-mail: [email protected] Chief Officer: Nigel Davies, Director of Environmental Services

Ward: Bickley

1. Reason for report

To improve the junction of Blackbrook Lane with Bickley Park Road in order to reduce traffic congestion.

______

2. RECOMMENDATION(S)

2.1 That the Portfolio Holder approves consultation on a new layout of this junction to improve traffic flow of vehicles both into and out of Bickley Park Road and Blackbrook Lane. This to include any road widening required, along with any footway or path works. There are two designs being put forward: VN 50092-ECC-DG-002, if a new pedestrian path can be built. Alternatively 11252-01, if a new path cannot be built.

2.2 That the Portfolio Holder delegates decisions regarding details of any designs to the Director of Environmental Services, in consultation with Ward Members and the Portfolio Holder, having regard to the outcomes of consultation. This to also include any location, design and type material for a new footway or path to be constructed.

2.3 That the costs of the above work be met from Section 106 funding.

1 Page 47 Corporate Policy

1. Policy Status: Existing Policy:

2. BBB Priority: Quality Environment Safer Bromley: ______

Financial

1. Cost of proposal: Estimated Cost £275k:

2. Ongoing costs: Non-Recurring Cost:

3. Budget head/performance centre: Section 106 funding

4. Total current budget for this head: £275.8k

5. Source of funding: Developer S106 funding ______

Staff

1. Number of staff (current and additional): one

2. If from existing staff resources, number of staff hours: 40 ______

Legal

1. Legal Requirement: Non-Statutory - Government Guidance:

2. Call-in: Applicable ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): All road users, including pedestrians which pass through this junction, on route through to Bromley, Sidcup or . ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? Yes

2. Summary of Ward Councillors comments: No comments have been received to date

2 Page 48 3. COMMENTARY

3.1. The junction of Blackbrook Lane and Bickley Park Road on the A222 has long been a cause of congestion and peak period delays on the routes from Petts Wood to Bromley and Sidcup, and from Sidcup to Bromley. An investigation was carried out by the Councils consultants to look at reducing congestion. It was originally thought that signalising the junction would be the solution to reducing congestion and improving road safety. However, this has been modelled and the results indicated much higher levels of queuing and delays, so was not taken any further. This design would also require land take of the grass verge nearby ‘ Lane End ‘ house site and the removal of mature trees, which is not considered viable by Officers.

3.2. Bromley has not programmed any scheme here while there were restricted flows over the Chislehurst bridge, since the latter part of 2008, or its subsequent closure in 2011. Bromley had upgraded another roundabout at the other end of Blackbrook Lane (as approved under Report ES10070 ) and are content this junction improvement is working as intended; therefore officers believe that a redesign can now be considered at the junction with Bickley Park Road with the opening of the new road over rail bridge in Chislehurst Road.

3.3. The main issues at the junction are: a). Delays as a result of high traffic volumes on the A222, b) narrow lanes restricting flows on Bickley Park Road, east bound and c) high volumes of traffic entering the junction from Blackbrook Lane which in turn conflicts with turning traffic on Bickley Park Road.

3.4. Due to the Chislehurst Road bridge works, we are unable to predict precise levels of future traffic flows at this junction with Blackbrook Lane, however the highest levels of congestion tend to be north bound on Bickley Park Road, that is traffic towards Bromley Town Centre from Chislehurst. Current traffic flows are not tidal, that is, they are different during the mornings compared to the evening flows.

3.5. As signalising the junction would increase congestion a design retaining a roundabout layout is still proposed, but with two traffic lanes in both Bickley Park Road (north bound) and Blackbrook Lane where there is currently only one lane. Bickley Park Road (south bound) already has two lanes, one for right turning vehicles into Blackbrook Lane and the other left towards Sidcup. The refuge in Blackbrook Lane would need to be slightly relocated to achieve an improved junction flare to give increased capacity for turning vehicles.

3.6. It is not yet clear which will be the better way of providing a path for pedestrians if the carriageway is fully widened. One solution is to build in the adjacent land towards Wellsmoor Gardens. Officers are investigating land ownership issues with an alternative option of just taking part of the footway width in Bickley Park Road, as detailed below.

3.7. Drawing number VN 50092-ECC-DG-002 shows a layout if a new path for pedestrians can be built. Drawing number 11252-01 shows an alternative layout, if a new path for pedestrians can’t be built, indicating a reduced footway width from 2.8m to 1.8m (which is a permitted width for footways in the Borough). This will increase the carriageway by 1m in Bickley Park Road providing two slightly narrower lanes northbound, with the advantage of reduced approach speeds. This is similar to the current layout for the eastbound flows in Bickley Park Road travelling away from Bromley Town Centre. With this alternative design no alterations are proposed for Blackbrook Lane.

3.8. Statutory utility services have been investigated, with trial holes dug. It is not anticipated that any will require moving in order to widen the carriageway in either Bickley Park Road or Blackbrook Lane, under the current footways.

3 Page 49 Consultation

3.9 No consultation has taken place yet.

4. POLICY IMPLICATIONS

The proposals in this report are within existing policy. In ‘Building a Better Bromley 2020 vision - Quality Environment‘ one of the stated issues is : Improving the road network for all users.

5. FINANCIAL IMPLICATIONS

The development at Golf Road provided a sum of £335k through a S106 agreement for highways works. Just over £59k has been spent on footway improvements at Goss Hill/Barfield Road, leaving a balance of £275.8k to fund works relating to the design and implementation of a scheme to reduce congestion at the Blackbrook Lane and Bickley Park Road junction. It is estimated that highway costs will be well within this allocation, and will obviously depend on extent of works. This will be reported to Ward Members should a scheme proceed after consultation and a subsequent detailed design. Any unspent funds will be returned to the developer.

6. LEGAL IMPLICATIONS

They are detailed within the section 106 agreement dated 4 th December 2003. The agreement provides for an Additional highway Works Commuted Sum to be used, amongst other matters, for signalisation of the Blackbrook Lane / Bickley Park Road junction. If the works are agreed by the Portfolio Holder for consultation the Council will also consult with the company that made the payment.

Non -Applicable Sections: Personnel Background Documents: Consultants report VN50092 dated August 2012 (Access via Contact Officer)

4 Page 50 Page 51 This page is left intentionally blank

Page 52 Page 53 This page is left intentionally blank

Page 54 Agenda Item 7e Report No. London Borough of Bromley ES12135 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For Pre-Decision Scrutiny by the Environment PDS Committee on

Date: 20 November 2012 Deci sion Type: Non-Urgent Executive Non-Key

Title : ROAD SAFETY SCHEME: SEVENOAKS WAY / MAIN ROAD

Contact Officer: Malcolm Harris, Team Leader, Traffic Engineer Tel: 020 8313 4500 E-mail: [email protected]

Chief Of ficer: Nigel Davies, Director of Environmental Services

Ward: Cray Valley West

1. Reason for report

Long queuing and traffic delays occur in Main Road at its junction with Sevenoaks Way, particularly at peak times along with problems for pedestrians and cyclists wishing to cross. As traffic returns to previous levels in Sevenoaks Way as Chislehurst Road opens after bridge repairs, the Council can consider adding traffic signals at this junction.

______

2. RECOMMENDATIONS That:

2.1 The Environment Portfolio Holder approves consultation based on a new layout of this junction to reduce traffic delays in Main Road, as shown in drawing number 11245-1.

2.2 The Environment Portfolio Holder delegates the decision regarding final detail of the design to the Director of Environmental Services, in consultation with Ward Members and the Portfolio Holder, having regard to the outcome of the consultation; this to include any alterations to the Pelican facility 70m away.

2.3 The costs of the above work are met from the TfL LIP formula funding allocation, along with additional Greenway funding.

1 Page 55 Corporate Policy

1. Policy Status: Existing Policy:

2. BBB Priority: Quality Environment ______

Financial

1. Cost of proposal: Estimated Cost:£120k

2. Ongoing costs: Non-Recurring Cost:

3. Budget head/performance centre: TfL funding for Congestion Relief 2013/14

4. Total current budget for this head: £390k

5. Source of funding: Transport for London LIP funding for 2013/14 ______

Staff

1. Number of staff (current and additional): 2 plus consultants

2. If from existing staff resources, number of staff hours: 80 ______

Legal

1. Legal Requirement: Non-Statutory - Government Guidance:

2. Call-in: Applicable: ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): All road users which pass through the junction of Main Road and Sevenoaks Way. In addition, any pedestrians, particularly parents taking their children to nearby schools, along with cyclists who want to cross more safely here. ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? Yes

2. Summary of Ward Councillors comments: Cllrs Fortune, Ince and Stranger are supportive of this proposal.

2 Page 56 3. COMMENTARY

3.1 Vehicles wishing to turn from Main Road can wait long periods for a break in traffic before being able to exit. This causes considerable congestion back into St Mary Cray village; also drivers often take risks to emerge into the steady flow of traffic in Sevenoaks Way.

3.2 With the opening of Chislehurst Road bridge consideration can be given to reducing traffic delays in Main Road at its junction with Sevenoaks Way. Delays also occur in Sevenoaks Way from persistent use of the Pelican facility 70m to the north of the junction with Main Road.

3.3 A new layout has been designed showing a signalised junction, see attached drawing 11245-1. A Toucan facility has been proposed as there is a new ‘on road‘ cycle route (Greenways: Cray Valley route) which goes from Park to Bexley, via Millbrook Road, Main Road and Sevenoaks Way. There is a dedicated off road cycle route along Sevenoaks Way with a segregated cycle path which would directly link to it. The new crossing has been designed incorporating facilities for cyclists connecting up these routes to secure some funding from TfL under the Mayor for London’s Greenways programme.

3.4 Officers are mindful that repeated use of the Pelican crossing 70m away from Main Road causes delays in Sevenoaks Way. Drawing 11245-2 shows the relative locations of the Pelican and the junction with Main Road. Pedestrian facilities are incorporated within the signal junction design, therefore signal elements of the Pelican should be removed, if the junction is signalised. This retains the status quo in terms of signal facilities in the Borough. However, there might still be a desire for the public to cross where the Pelican is currently located, therefore the central refuges could be left along with any other features apart from the signal poles and heads, as this greatly reduces de-commissioning and removal costs. The new signalised junction would provide a safe crossing facility for pedestrians both across Main Road and across Sevenoaks Way.

3.5 All necessary traffic surveys and counts in support of this scheme have been conducted and can be reported to members.

3.6 There would be no displacement of any parking at this location.

3.7 An opportunity now exists to secure additional TfL Greenways funding to add to LIP funding should the scheme proceed. The bid date is 24 October and the outcome will be reported to members. This will be additional funding to that already allocated to Bromley by TfL.

Consultation

3.8 This report recommends that consultation take place on the proposed scheme.

4. POLICY IMPLICATIONS

The proposals in this report are within existing policy. In the 2012/15 Environment Portfolio Plan, one of the stated aims is “Improving the road network and journey times for all users”.

5. FINANCIAL IMPLICATIONS

The estimated cost of the works is £120k. This will be funded from the 2013/14 TfL LIP budget for Congestion Relief, which has an allocation of £390k for the Orpington By-Pass area. Officers will be applying to TfL for further Greenway funding for 2013/14 to contribute towards the cost of this scheme, which if successful would free up LIP funding for alternative projects.

Non -Applicable Sections: Legal and Personnel Implications

Background Document s (Access via Contact Officer) PDS report: Cray Valley Study (London Greenways) dated 18/1/10

3 Page 57 This page is left intentionally blank

Page 58 Page 59 This page is left intentionally blank

Page 60 Page 61 This page is left intentionally blank

Page 62 Agenda Item 7f Report No. London Borough of Bromley ES12113 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For Pre-Decision Scrutiny by the Environment PDS Committee on Date: 20 th November 2012 Decision Type: Non-Urgent Executive Non-Key

Title : 2013/14 PLANNED HIGHWAY MAINTENANCE PROGRAMME

Contact Officer: Paul Redman, Highway Assets Manager Tel: 020 8313 4930 E-mail: [email protected]

Chief Officer: Nigel Davies, Director of Environmental Services

Ward: All

1. Reason for report

This report identifies the planned highway maintenance programme of work for 2013/14 and future years. ______

2. RECOMMENDATIONS

The Portfolio Holder for Environment is invited to:

(i) Agree the schemes listed in Appendix ‘A’ to form the basis of the Council’s programme of planned highway maintenance for 2013/14 and subject to budgetary provision, for the works to be progressed;

(ii) Note the outline programmes for future years, as listed in Appendices 'B' and ‘C’;

(iii) Note the proposed TfL funded programme of works (Principal Roads) as Appendix ‘D’;

(iv) Agree the schemes listed in Appendix ‘E’ to be funded from the the ‘one-off spend’ programme;

(v) Agree the additional schemes listed in Appendix ’F’ to be funded from the NTL resources and recommends that the Executive agree to release the £483k from the Street Services Reinstatement Fund from 1 st April 2013.

(vi) Note the potential impact on the highway asset of any reduction in the planned maintenance budget.

1 Page 63

Corporate Policy

1. Policy Status: Existing Policy

2. BBB Priority: Quality Environment ______

Financial

1. Cost of proposal: Estimated Cost £4.258m

2. Ongoing costs: Recurring Cost £3.025m

3. Budget head/performance centre: Highways, TfL funding and Earmarked Reserves

4. Total current budget for this head: £2.261m, £764k, £750k and £483k

5. Source of funding: Existing highways revenue budget for 2012/13, 2013/14 principal road maintenance capital allocation from TfL and earmarked reserves ______

Staff

1. Number of staff (current and additional): 5

2. If from existing staff resources, number of staff hours: 5 fte ______

Legal

1. Legal Requirement: Statutory Requirement

2. Call-in: Applicable ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): Borough wide ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? Yes

2. Summary of Ward Councillors comments:

Comments were received as follows:-

Councillor Getgood – Assessment of Hawthorne Grove and Graveney Grove. Councillor Fawthrop – Road locations within Wards. Councillor Grainger – Suggestions (various) for planned maintenance. Councillor Fookes – Review of Royston Road.

2 Page 64

3. COMMENTARY

3.1 Bromley’s highway network comprises 856 miles (1370 km) of footway and 552 miles (884 km) of carriageway. A description of each carriageway classification and corresponding length is shown in the table below together with the corresponding condition indicator for 2011/12. Highway condition figures indicate the percentage of carriageways or footways likely to be in need of maintenance.

Length Indicator Likely in Need of Route Classification Reference Maintenance Principal ( A roads ) 45 miles (72 km) NI 168 3 % Non-Principal ( B & C roads ) 58 miles (93 km) NI 169 6 % Unclassified roads 423 miles (677 km) ES 224b 20 % Footways ( Cat 1, 1A & 2 ) 26 miles (42 km) ES 187 18 %

3.2 Regular surveys of the carriageway and footway networks are undertaken to determine their condition, identify those areas that are in most need of planned maintenance, and to determine the relevant condition indicator.

3.3 SCANNER surveys are undertaken every year on the classified road network (A, B and C roads). These machine based surveys use vehicle mounted lasers, digital camera’s and electronic measuring equipment to identify defects. Bromley procures SCANNER surveys through a London consortium led by the London Borough of Hammersmith and Fulham. Scanner survey results currently determine carriageway National Indicators (NI’s).

3.4 Detailed Visual Inspection ( DVI ) of all footways and carriageways on the principal road network is completed each year by accredited survey inspectors. These are walked surveys designed to identify and categorise highway defects. DVI surveys are funded by TfL through the Road 2010 project which is also project managed by the London Borough of Hammersmith and Fulham.

3.5 The output from condition surveys informs the engineer which roads should be “considered for planned maintenance soon” and a ‘long list’ of such roads is generated from the survey information. The latest survey result indicates that 20% of the unclassified network is likely to be in need of maintenance which is an increase from the previous survey result of 18%. Further criteria are applied to those roads on the ‘long list’ to help prioritise schemes in order that published programmes can be contained within the expected budget allocation. The further criteria includes:- Ward member consultation, results of coarse assessments by area inspectors undertaken during routine safety inspections, location on the network – main roads/busy roads/bus routes etc, proximity to rail and bus stations/schools/hospitals/libraries/homes for the elderly etc, records of frequent inspections, co-ordination with other programmes of work.

3.6 The Appendices to this report identify the results of the prioritisation system and show the locations and year of proposed planned maintenance. All proposed programmes of maintenance have been drawn up according to current known budget levels and external influences such as known programmes of utilities work. Subsequent changes to the budget or utilities works may impact on delivery of the programmes of work in the Appendices.

3 Page 65

Planned Maintenance Programme

3.7 Appendix ‘A’ proposes footway and carriageway maintenance schemes for completion during 2013/14 funded from revenue budgets, with Appendices ‘B’ and ‘C’ detailing those roads that will be monitored for inclusion in future years programmes; these are subject to change following any adverse weather conditions. Appendix ‘D’ proposes principal road schemes to be funded by Transport for London.

Member Initiatives

3.8 In July 2012 ES PDS approved a number of one-off spends by way of Member initiatives. The proposals included £750k for additional highway maintenance schemes, with details of the first phase of the programme detailed in the report. Appendix ‘E’ details the remaining schemes to be completed during 2012/13 from this initiative.

NTL Budget

3.9 During the late 1990’s cable television infrastructure was installed by NTL, which involved excavating the highway. At the time inspections identified a number of trenches which required remedial works to comply with nationally agreed reinstatement standards. Rather than deal with individual sites, an agreement was reached between NTL & LB Bromley in 2003 to transfer responsibility for future maintenance of the trench reinstatements to the Council, as Highway Authority, in return for a one-off payment of £750k. £200k of this sum was transferred to the insurance fund to deal with any potential claims and the balance of £550k was set aside in an earmarked fund.

3.10 This budget has funded a number of minor repairs relating to NTL’s original works during 2004/05. As no further reactive repairs are likely to be required, it is recommended that that the remaining budget of £483k is drawn down and used to fund additional planned maintenance schemes, as detailed in Appendix ‘F’.

Asset Management

3.11 The highway network is LB Bromley’s most valuable asset, with a replacement value of £1.6 billion. The level of investment made in the Council’s highway assets may become more visible in future years with the introduction of Whole of Government Accounts (WGA). WGA utilises local indicator information to determine the annual depreciation of the asset. This is applied to the gross value to determine the depreciated asset value. Year on year comparisons will then be possible and this will provide an indication of whether the level of investment is appropriate. A continually diminishing asset value may be an indication of an investment level that is too low. Introduction of WGA has been the subject of delay but is likely to be a formalised submission within the next two years.

3.12 The carriageway infrastructure accounts for 75% of the asset valuation. The key to managing the highway asset is timely intervention to minimise expensive structural repairs, as low cost protective maintenance can return the highway asset to near new condition. The latest condition surveys identified that 20% of the borough’s unclassified roads are in need of maintenance, an increase of 2% since the previous survey. This ‘backlog’ of maintenance works is valued as £8m.

3.13 The results of condition modelling in the table below shows how the state of the borough’s carriageways will change during the next five year for various maintenance scenarios;

4 Page 66

Carriageway Deterioration Against Budget

40

35

30

25 Do nothing 20 £1m pa

£2m pa 15

10 % in need of maintenance 5

0 2012/13 2013/14 2014/15 2015/16 2016/17

3.14 It can be seen that the current budget of £1m is insufficient to prevent a growing maintenance backlog, whereas a relatively small additional annual investment would enable the Council to start reducing the backlog.

3.15 All highways will deteriorate in a similar manner; the diagram below compares condition against time;

Good A B Condition C

Bad D

Time

5 Page 67

3.16 The highway network includes all classes of road which deteriorate at different rates; the busy principal road network will initially fail due to physical damage whereas quiet cul-de-sac’s will suffer from chemical deterioration. It can be seen that once the initial physical and / or chemical damage has occurred, the rate of deterioration increases due to environmental effects. Unless maintenance works are undertaken the highway will eventually suffer structural failure.

3.17 The key to managing the highway asset is timely intervention to minimise expensive structural repairs, as low cost protective maintenance can return the highway asset to near new condition. The graph above identifies timescales for possible treatment options;

A – Reactive maintenance (patching); £26.68 /sq.m

B – Surface treatment; £ 6.33 /sq.m

C – Replace surface; £ 15.85 /sq.m

D – Full reconstruction; £ 60.08 /sq.m

3.18 Although this model over simplifies the situation, as a proportion of the network has already deteriorated beyond the level for resurfacing or surface replacement, it clearly demonstrates the business case for investment in planned maintenance works and life cycle planning.

3.19 The condition of the borough’s footways is also deteriorating with current investment levels, and while it is not possible to model footway the decline with such accuracy due to the modes of deterioration; utility works, over-running vehicles etc, the ‘backlog’ of repairs will continue to increase, with a commensurate increase in customer complaints and accident claims.

4. POLICY IMPLICATIONS

4.1 The borough’s carriageways and footways have a high profile and are used by most residents and businesses on a daily basis. Maintaining these assets will contribute to the Council’s vision of providing a place where people choose to live and do business and links well with policy priorities of a quality environment, vibrant thriving town centres and supporting independence/ safer communities.

5. FINANCIAL IMPLICATIONS

5.1 Planned maintenance works for Borough roads are funded from the annual revenue highway maintenance budget. The budgets for carriageways and footways are indicated in the table below. It should be noted that these budgets are subject to change following any decisions taken during the forthcoming 2013/14 budget setting process.

5.2 Maintenance of the Principal Road Network is funded by TfL. These funds can only be used for maintenance work on these classified principal roads.

6 Page 68

5.3 A summary of the available funding is set out in the table below: -

Funding £'000 £'000

Revenue - Appendix A Carriageway maintenance 2012/13 budget 1,187 Footway maintenance 2012/13 budget 1,074 2,261

Capital - Appendix D Primary Route Network 2013/14funding from TfL 764

Earmarked Reserves - Appenidces E & F Member Priority Initiatives 750 Street Services Reinstatement Fund 483 1,233

Total funding available 4,258

5.4 Council on the 26 th March 2012 approved the setting aside of £2.26m in an earmarked reserve for Member priority initiatives, £750k of which was allocated to footways, highways and general improvement projects. The Environment Portfolio Holder subsequently agreed a list of schemes that would be funded by this money on 3 July 2012. Officers have been discussing the works with the contractor and orders will be placed imminently to enable the works to be completed by the end of January 2013. Approval is sought for the schemes listed in Appendix E to be funded from the balance of this one-off money.

5.5 Following the agreement of a Deed of Settlement between the Council and NTL in 2003, the Council received a sum of £750k. £200k was transferred to the insurance fund to meet the costs of any potential claims and the balance of £550k was transferred to an earmarked fund for highway works as agreed by the Executive on 23 rd June 2003.

5.6 Highways works totalling £67k were completed during 2004/05, leaving a balance of £483k available for future highways works. This report seeks approval from the Environment Portfolio Holder to use these resources to fund the schemes listed in Appendix F and therefore approval will be sought from the Executive to drawdown these funds during 2013/14.

6. LEGAL IMPLICATIONS

6.1 Under the Highways Act 1980 the Council as Highway Authority has duties and is in keeping with its obligations to ensure the safe passage of users of the highway and to maintain the highway.

Non -Applicable Sections: Personnel Background Documents: London Wide Survey data – Hammersmith and Fulham (Access via Contact Council. Officer)

7 Page 69 This page is left intentionally blank

Page 70 APPENDIX A PRIORITY 1 - PLANNED HIGHWAY MAINTENANCE PROGRAMME APRIL 2013 TO MARCH 2014

CARRIAGEWAY SCHEMES ON NON-PRINCIPAL AND UNCLASSIFIED ROADS

PRIORITY ROAD NAME & DISTRICT SECTION of ROAD WARDS

31 Avenue Road, Beckenham Ravenscroft Road to Percy Road Clock House / Penge and Cator 8 Baston Road, Hayes Croydon Road to Five Elms Road Hayes and 9 Baston Road, Hayes Fox Hill to Croydon Road Hayes and Coney Hall 13 Beaumont Road, Petts Wood Complete Length Petts Wood and Knoll 20 Burnhill Road, Beckenham Complete Length Copers Cope 26 Church Hill, Orpington Bark Hart Road to High Street Orpington Orpington 17 Crescent Road, Beckenham Complete Length Copers Cope 23 Downsbridge Road, Beckenham Complete Length Copers Cope

15 Farnborough Hill, Green St Green Durrant Way (Change of surface) to Chartwell Drive Chelsfield and Pratts Bottom

27 Forest Way, Orpington Complete Length Cray Valley West 30 Hartfield Crescent, NO 9 TO Croydon Road Hayes and Coney Hall 24 Hartfield Road, West Wickham Complete Length Hayes and Coney Hall 16 Highland Road, Bromley Complete Length Bickley

Page 71 3 Homesdale Road, Bromley A21 to Old Homesdale Road Bromley Town 10 Leesons Hill, Chislehurst St Pauls Wood Hill to Clarendon Way Cray Valley West/Chislehurst 7 London Road, Bromley Beckenham Lane to Tweedy Road Bromley Town 21 Lynton Avenue, Orpington Stanley Way to Cray Valley Road Cray Valley East 32 Marion Crescent, Orpington Hayfield Road to Stanley Way Cray Valley East / Cray Valley West 11 Monks Orchard Road, Beckenham South Eden Park Rd to house no.77 Kelsey and Eden Park 37 Murray Avenue, Bromley Short section from Wendover Road to No 9 Bromley Town 12 Page Heath Lane, Bromley Heath Park Drive to Homesdale Road Bickley 33 Paxton Road, Bromley Complete Length Plaistow and Sundridge 28 Pinewood Drive, Orpington Complete Length Chelsfield and Pratts Bottom 29 Ramsden Road, Orpington Bark Hart Road to Court Road Orpington 22 Rose Walk, West Wickham Wickham Court Road to Glebe Way West Wickham 35 , Main Rd to Oaklands Lane Biggin Hill 4 Shepperton Road, Petts Wood Jersey Drive (Change of Surface) to Nightingale Road Petts Wood and Knoll 25 Sherbourne Road, Orpington Chislehurst Road to Sefton Road Cray Valley West North End Lane to Pedestrian Crossing (Change of 18 Shire Lane, Green St Green Darwin Surface) South Eden Park Road rab to Creswell Drive including 5 South Eden Park Road, Beckenham West Wickham roundabout 19 Thicket Road, Penge Park Road to Crystal Palace Road Crystal Palace

6 Warren Road, Chelsfield Sevenoaks Road to Cloonmore Avenue Chelsfield and Pratts Bottom 34 Warren Road, Chelsfield Orchard / Cottage to Five Bells Pub Chelsfield and Pratts Bottom 36 Wendover Road, Bromley Complete Length Bromley Town 1 Whitecroft Way, Beckenham Complete Length 2 Woodlea Drive, Bromley Complete Length Shortlands

14 Worlds End Lane, Green St Green Vine Road to Dowlerville Road Chelsfield and Pratts Bottom Page 72 APPENDIX A PRIORITY 1 - PLANNED HIGHWAY MAINTENANCE PROGRAMME APRIL 2013 TO MARCH 2014

FOOTWAY SCHEMES ON NON-PRINCIPAL AND UNCLASSIFIED ROADS

PRIORITY ROAD NAME & DISTRICT SECTION of ROAD WARDS

1 Homesdale Road, Bromley A21 to Old Homesdale Road Bromley Town

2 Shepperton Road, Petts Wood Cresent Drive to Nightingale Lane Petts Wood and Knoll

3 Augustine Road, St Pauls Cray Complete Length Cray Valley East

4 South Eden Park Road, Beckenham South Eden Park Road rab to Creswell Drive Kelsey and Eden Park

5 Barfield Road, Bromley Complete Length Bickley

6 London Road, Bromley Beckenham Lane to Tweedy Road Bromley Town

7 Martins Road, Bromley Complete Length Bromley Town

8 Homefield Road, Bromley Complete Length Bickley

9 Bournewood Road, Orpington Complete Length Orpington

10 Page Heath Lane, Bromley Homesdale Road to Birds in Hands Lane Bickley

11 St. Augustine Avenue, Bromley Complete Length Bickley

Page 73 12 Clarendon Way, Chislehurst Leesons Hill to Claredon Close Chislehurst/Cray Valley West

13 Freelands Road, Bromley Complete Length Plaistow and Sundridge

14 Green Lane, Chislehurst Complete Length Chislehurst

15 East Way, Hayes Complete Length Hayes and Coney Hall

16 Grosvenor Road, Orpington Complete Length Cray Valley West

17 Raglan Road, Bromley Complete Length Bromley Town

18 Aylesford Avenue, Beckenham Complete Length Kelsey and Eden Park 19 Valley Road, St Pauls Cray Midfield Way to No 56 Cray Valley West

20 Southbourne, Hayes Complete Length Hayes and Coney Hall

21 Garden Road, Bromley Complete Length Plaistow and Sundridge

22 Highwood Drive, Orpington Complete Length Farnborough and Crofton

23 Mells Crescent, Complete Length Mottingham and Chislehurst North

24 Starts Hill Road, Orpington Wellbrook Road to Bassetts Way Farnborough and Crofton

25 Sundridge Avenue, Bromley Orchard Road to Plaistow Lane Bickley

26 Hawes Road, Bromley Complete Length Plaistow and Sundridge

27 Dunkery Road, Mottingham Widecombe Road to Ravensworth Road Mottingham and Chislehurst North

28 Elmstead Lane, Chislehurst Walden Road to Wood Drive Chislehurst

29 Cromwell Road, Beckenham Complete Length Clockhouse

30 Glentrammon Road, Green St Green Glentrammon Avenue to Sevenoaks Road Chelsfield and Pratts Bottom

31 Repton Road, Orpington Eton Road to Sevenoaks Road Orpington

32 Whitehall Road, Bromley Complete Length and Keston

33 Ramsden Road, Orpington Court Road to Kynaston Road including roundabout Orpington

34 Lynton Avenue, Orpington Stanley Way to Cray Valley Road Cray Valley East Page 74 35 Hawkhurst Way, West Wickham Complete Length (Concrete Columns) West Wickham

36 Durham Avenue, Bromley Complete Length (Concrete Columns) Shortlands

37 Warren Drive, Chelsfield Complete Length (Concrete Columns) Chelsfield and Pratts Bottom

38 Wood Drive, Chislehurst T Junction Left and Right L sections (Concrete Columns) Chislehurst

39 Shrewsbury Road, Beckenham Complete Length (Concrete Columns) Clockhouse

40 Eagles Drive, Biggin Hill Complete Length (Concrete Columns) Biggin Hill 41 Abbotsbury Road, Hayes Complete Length (Concrete Columns) Hayes and Coney Hall

42 Dowding Road, Biggin Hill Complete Length (Concrete Columns) Biggin Hill

43 Station Approach, Chelsfield Complete Length (Concrete Columns) Chelsfield and Pratts Bottom Page 75 APPENDIX B PRIORITY 2 - PLANNED HIGHWAY MAINTENANCE PROGRAMME

CARRIAGEWAY SCHEMES ON NON-PRINCIPAL AND UNCLASSIFIED ROADS

ROAD NAME & DISTRICT SECTION of ROAD WARDS

Ambleside Avenue, Beckenham Complete Length Kelsey and Eden Park Augustine Road, St Pauls Cray Complete Length Cray Valley East Barfield Road, Bromley Complete Length Bickley Bournewood Road, Orpington Complete Length Orpington Clarendon Way, St Pauls Cray Complete Length St Pauls Cray/Chislehurst Cumberland Road, Bromley Winchester Road to Westmoreland Road Shortlands East Way, Hayes Complete Length Hayes and Coney Hall Eden Park Avenue, Beckenham Complete Length Kelsey and Eden Park Freelands Road, Bromley Complete Length Plaistow and Sundridge Garden Road, Penge Complete Length Penge and Cator Graveney Grove, Penge Complete Length Penge and Cator Hawkhurst Way, West Wickham Complete Length West Wickham Highwood Drive, Orpington Complete Length Farnborough and Crofton Homefield Road, Bromley Complete Length Bickley Kent House Road, Beckenham Thesiger Road to Lennard Road Penge and Cator

Page 76 Letchworth Drive, Bromley Complete Length Hayes and Coney Hall Lower Gravel Road, Bromley Princes Plain to Bromley Common Bromley Common and Keston Madeira Avenue, Bromley Complete Length Bromley Town Martins Road, Bromley Complete Length Bromley Town Mells Crescent, Mottingham Complete Length Mottingham and Chislehurst Midfield Way, St Pauls Cray St.Paul's Wood Hill to Grovelands Road Cray Valley West Mitchell Road, Orpington Complete Length Chelsfield and Pratts Bottom North Drive, Orpington Complete Length Chelsfield and Pratts Bottom Old Homesdale Road, Bromley Complete Length Bromley Town Plantation Drive, Orpington Complete Length Orpington Quilter Road, Orpington Complete Length Orpington

Raglan Road, Bromley Complete Length Bromley Town Rookesley Road, Orpington Complete Length Cray Valley East Roseberry Gardens, Orpington Complete Length Chelsfield and Pratts Bottom

Sandway Road, St Mary Cray Belgrave Close to Mill Brook Lane Cray Valley East Southborough Road, Bromley Oldfield Rd to bridge Bickley Southbourne, Hayes Complete Length Hayes and Coney Hall St Mary's Avenue, Bromley Complete Length Shortlands St. Augustine Avenue, Bromley Complete Length Bickley

Turpington Lane, Bromley Complete Length Bromley Common and Keston Valley Road, St Pauls Cray Complete Length Cray Valley West

Waldens Road, St. Mary Cray Complete Length Cray Valley East Walsingham Road, St. Paul's Cray Complete Length Cray Valley West Warren Drive, Chelsfield Complete Length Chelsfield and Pratts Bottom Worsley Bridge Road, Beckenham Poole Close to Headingly Drive Copers Cope Page 77 APPENDIX B PRIORITY 2 - PLANNED HIGHWAY MAINTENANCE PROGRAMME

FOOTWAY SCHEMES ON NON-PRINCIPAL AND UNCLASSIFIED ROADS

ROAD NAME & DISTRICT SECTION of ROAD WARDS

Ashley Gardens, Orpington Complete Length Chelsfield and Pratts Bottom

Barnet Drive, Bromley Complete Length Bromley Common and Keston

Barnfield Wood Close, West Wickham Complete Length West Wickham

Beckenham Grove, Beckenham Complete Length (Concrete Column) Copers Cope

Beddington Road, St Pauls Cray Complete Length Cray Valley West

Bedford Road, Orpington Complete Length (Concrete Column) Orpington

Benenden Green, Bromley Complete Length Hayes and Coney Hall

Broad Walk, Orpington Complete Length (Concrete Column) Orpington

Bruce Grove, Orpington Complete Length (Concrete Column) Orpington

Chesham Road, Penge Complete Length Penge and Cator

Clifford Avenue, Chislehurst Complete Length Chislehurst

Clovelly Way, Orpington Complete Length (Concrete Column) Cray Valley East

Page 78 Cotswold Rise, Orpington Complete Length (Concrete Column) Cray Valley East

Crockenhill Road, Crockenhill Service Road Only (Concrete Column) Cray Valley East

Crofton Avenue, Orpington Complete Length (Concrete Column) Farnborough and Crofton

Dene Drive, Orpington Complete Length Orpington

Dyke Drive, Orpington Zelah Road to End Orpington

Edenbridge Close, St Mary Cray Complete Length Cray Valley East

Eldred Drive, Orpington Moyser Drive to End - Chelsfield Lane (Concrete Column) Orpington Elmcroft Road, Orpington Perry Hall Road to Chislehurst Road Cray Valley East

Elysian Avenue, Petts Wood Complete Length Cray Valley West

Felstead Road, Orpington Complete Length Orpington

Florence Road, Bromley Complete Length Bromley Town

Goodhart Way, West Wickham Pickhurst Lane to West Way (Concrete Column) West Wickham

Greenview Avenue, Beckenham Complete Length Kelsey and Eden Park

Lancing Road, Orpington Complete Length (Concrete Column) Orpington

Langley Way, West Wickham Pickhurst Rise to No 104 West Wickham

Leesons Hill, Chislehurst St Pauls Wood Hill to Sunnyfield Chislehurst

Orchard Grove, Orpington Complete Length Orpington

Petten Grove, Orpington Complete Length Orpington

Springpark Drive, Beckenham Complete Length (Concrete Column) Copers Cope

Tintagel Road, Orpington Complete Length Orpington

Tudor Gardens, West Wickham Complete Length (Concrete Column) West Wickham

Walden Road, Chislehurst Complete Length Chislehurst

Waring Close, Green St Green Complete Length Chelsfield and Pratts Bottom

Waring Drive, Green St Green Complete Length Chelsfield and Pratts Bottom Page 79 Weald Close, Bromley Complete Length Bromley Common and Keston

Wyvern Close, Orpington Complete Length (Concrete Column) Orpington APPENDIX C PRIORITY 3 - PLANNED HIGHWAY MAINTENANCE

ROAD NAME & DISTRICT SECTION of ROAD WARD

Addison Road, Bromley Complete Length Bromley Common & Keston CW Anglesea Road, Orpington Complete Length Cray Valley East CW Road, Biggin Hill Complete Length Biggin Hill CW Artington Close, Orpington Complete Length Farnborough & Crofton CW Ashley Gardens, Orpington Complete Length Chelsfield and Pratts Bottom CW Aylesford Avenue, Beckenham Complete Length Kelsey & Eden Park CW Balfour Road, Bromley Complete Length Bromley Common and Keston CW Balmoral Avenue, Beckenham Complete Length Kelsey & Eden Park CW Barham Close, Chislehurst Complete Length Chislehurst FW Baston Manor Road, Hayes Complete Length Hayes & Coney Hall CW Beadon Road, Bromley Complete Length Bromley Town FW Beckenham Grove, Beckenham Park Hill Lane to Scotts Lane Copers Cope CW Beechwood Avenue, Green St Green Complete Length Darwin CW Belmont Lane, Chislehurst Edgebury to Green Lane Chislehurst CW Benenden Garden, Bromley Complete Length Hayes & Coney Hall CW Betts Way, Beckenham Complete Length Crystal Palace CW Birchington Close, Orpington Complete Length Orpington CW Blackthorne Road, Biggin Hill Complete Length Biggin Hill CW Bourne Road, Bromley Complete Length Bromley Town CW Bournewood Road, Orpington Complete Length Orpington CW Page 80 Brackley Road, Beckenham Complete Length Copers Cope CW Bramerton Road, Beckenham Complete Length Kelsey and Eden Park CW Bramley Close, Orpington complete Length Farnborough & Crofton FW Broxbourne Road, Orpington Complete Length Petts Wood & Knoll Both Bucks Cross Road, Chelsfield Complete Length Chelsfield & Pratts Bottom CW Cambray Road, Orpington Complete Length Cray Valley East CW Chatterton Road, Bromley Complete Length Bromley Common & Keston CW Chesham Road, Penge Complete Length Penge and Cator CW Church Road, Biggin Hill Complete Length Biggin Hill CW Church Road, Chelsfield Complete Length Chelsfield & Pratts Bottom CW Clarendon Way, St. Paul's Cray Leesons Way to Clarendon Close Chislehurst / Cray Valley West CW Cleave Avenue, Green Street Green Complete Length Darwin CW Clifford Avenue, Chislehurst Clifford Avenue, Chislehurst Chislehurst CW Cockmannings Road, Orpington Complete Length Cray Valley East CW Cocksett Avenue, Green Street Green Complete Length Darwin CW Constance Crescent, Hayes Complete Length Hayes & Coney Hall CW Cotmandene Crescent, Orpington Complete Length Cray Valley West CW Court Farm Road, Mottingham Castlecombe Road to Castleton Road Mottingham and Chislehurst North CW Courtlands Avenue, Hayes Complete Length Hayes and Coney Hall CW Cromwell Road, Beckenham Complete Length Clock House CW Cromwell Road, Bromley Complete Length Bromley Town CW Dene Drive, Orpington Complete Length Orpington CW Devonshire Road, Complete Length Petts Wood & Knoll FW Drayton Avenue, Orpington Complete Length Farnborough and Crofton CW Durham Avenue, Bromley Complete Length Shortlands CW Eagles Drive, Biggin Hill Complete Length Biggin Hill CW Eastry Avenue, Bromley Complete Length Hayes & Coney Hall Both Eden Park Avenue, Beckenham Overstand Close to Upper Road Kelsey & Eden Park CW Eden Way, Beckenham Complete Length Kelsey & Eden Park FW Eldred Drive, Orpington Complete Length Orpington CW Elizabeth Way, St Mary Cray Complete Length Cray Valley East CW Elizabeth Way, St. Mary Cray Complete Length Cray Valley East CW Elvington Green, Bromley Complete Length Hayes & Coney Hall CW Elysian Avenue, Orpington Complete Length Cray Valley West CW Empress Drive, Chislehurst Complete Length Chislehurst Both Fairbank Avenue, Orpington Complete Length Farnborough & Crofton CW Fairfield Road, Beckenham Complete Length Copers Cope CW Page 81 Farleigh Avenue, Hayes Complete Length Hayes & Coney Hall CW Farnaby Road, Bromley Complete Length Bromley Town CW Fontwell Drive, Bromley Complete Length Bromley Common & Keston CW Forde Avenue, Bromley Complete Length Bromley Town CW Franklin Road, Penge Complete Length Penge and Cator CW Freelands Road, Bromley Complete Length Plaistow and Sundridge CW Gilroy Way, Orpington Complete Length Orpington CW Glebe Road, Bromley Complete Length Bromley Town Both Glendower Crescent, Orpington Complete Length Cray Valley East CW Goddington Lane, Orpington Complete Length Orpington CW Goodhart Way, West Wickham Complete Length West Wickham CW Goodhart Way, West Wickham West Way to The Avenue West Wickham CW Gorse Road, Orpington Complete Length Cray Valley East CW Gravel Road, Bromley Complete Length Bromley Common & Keston CW Graveney Grove, Penge Complete Length Penge and Cator CW Grosvenor Road, Orpington Complete Length Cray Valley West CW Haddon Road, St Mary Cray Complete Length Cray Valley East CW Haig Road, Westerham Complete Length Biggin Hill CW Harwood Avenue, Bromley Complete Length Bromley Town CW Hawthorne Grove, Penge Between No 54 and 42 Penge and Cator Hawthorndene Road, Bromley Complete Length Hayes & Coney Hall CW Hayes Lane, Bromley Nuffield Health Centre o/s no 26 to Mead Way Bromley Town/Hayes and Coney Hall CW Hayes Way, Beckenham Whitecroft Way to Wickham Way Shortlands CW Hayesford Park Drive, Bromley Complete Length Hayes & Coney Hall CW Haywood Rise, Orpington Complete Length Chelsfield & Pratts Bottom Both High Street, Bromley Train station to Mason Hill Bromley CW Highfield Road, Bromley Complete Length Bickley Both Hilldown Road, Hayes Complete Length Hayes and Coney Hall CW Homestead Road, Chelsfield Complete Length Chelsfield and Pratts Bottom Both Hurstfield, Bromley Complete Length Hayes & Coney Hall CW Jackass Lane, Keston Complete Length Bromley Common and Keston CW Jasmin Close, Orpington Complete Length Farnborough & Crofton FW Jasmine Close, Orpington Complete Length Farnborough & Crofton CW Kelsey Park Road, Beckenham Manor Road to High Street Kelsey & Eden Park CW Kennedy Close, Petts Wood complete Length Petts Wood & Knoll CW Kent House Road, Beckenham Beckenham Road to White Hall Road Penge and Cator CW Kent House Road, Beckenham Beckett Walk to Kent House Lane Penge and Cator FW

Page 82 Keswick Road, Orpington Complete Length Petts Wood & Knoll CW Kevington Drive, Chislehurst Marlings Park Avenue to Wimbourne Avenue Chislehurst CW Kimmeridge Road, Mottingham Beaconsfield Road to St. Keverne Road Mottingham & Chislehurst North CW Kings Hall Road, Beckenham Complete Length Penge and Cator CW Kingswood Road, Penge Complete Length Penge and Cator CW Kinnaird Avenue, Bromley Complete Length Plaistow & Sundridge FW Knowlton Green, Bromley Complete Length Hayes & Coney Hall CW Langley Way, West Wickham Complete Length West Wickham CW Langley Way, West Wickham No 104 to Pickhurst Lane West Wickham FW Lansdowne Avenue, Orpington Complete Length Farnborough and Crofton CW Lawrie Park Crescent, Crystal Palace Complete Length Crystal Palace CW Lime Grove, Orpington Complete Length Farnborough & Crofton FW London Lane, Bromley Warner Road to Redland Court Plaistow and Sundridge CW Lych Gate Road, Orpington Complete Length Orpington CW Mackenzie Road, Beckenham Complete Length Clock House Both Madeira Avenue, Bromley Complete Length Bromley Town CW Mapleton Close, Bromley Complete Length Hayes & Coney Hall CW Marlings Park Avenue, Chislehurst Complete Length Chislehurst FW Marlow Road, Penge Complete Length Clock House CW Marsham Close, Chislehurst Complete Length Chislehurst FW Martins Road, Bromley Complete Length Bromley Town CW Masons Hill, Bromley Kentish Way to Westmoreland Road (including short Bromley Town CW Matfield Close, Bromley Complete Length Hayes & Coney Hall CW Meaford Way, Penge Complete Length Penge and Cator FW Meldrum Close, Orpington Complete Length Cray Valley East CW Melvin Road, Penge Complete Length Penge and Cator CW Merewood Close, Bromley Complete Length Bickley FW Morley Close, Orpington Complete Length Farnborough & Crofton FW Murray Avenue, Bromley Rochester Avenue to Harwood Avenue Bromley Town CW Newnhams Close, Bromley complete Length Bickley Both North Drive, Orpington Complete Length Chelsfield & Pratts Bottom Both Oak Grove Road, Penge Complete Length Penge and Cator CW Oak Tree Gardens, Bromley Complete Length Plaistow & Sundridge CW Oaklands Lane, Biggin Hill change of surface Victoria Gardens to Saltbox Hill Biggin Hill CW Oaklands Road, Bromley Complete Length Bromley Town FW Oaklands Road, Bromley Complete Length Bromley Town CW Oakmead Avenue, Hayes Complete Length Hayes & Coney Hall CW

Page 83 Oakwood Gardens, Orpington Complete Length Farnborough and Crofton FW Oregon Square, Orpington Complete Length Farnborough & Crofton CW Ormonde Avenue, Orpington Complete Length Farnborough & Crofton FW Overhill Way, Beckenham Complete Length Shortlands CW Oxenden Wood Road, Chelsfield Complete Length Chelsfield & Pratts Bottom Both Palace Road, Crystal Palace Complete Length Crystal Palace CW Palace Square, Crystal Palace Complete Length Crystal Palace CW Park Hill, Bickley Complete Length Copers Cope CW Park Road, Beckenham Park Road to Copers Cope Road Copers Cope CW Parkwood, Beckenham Complete Length Copers Cope CW Partridge Drive, Orpington Complete Length Farnborough and Crofton FW Percival Road, Orpington Complete Length Farnborough & Crofton CW Pickhurst Park, Bromley Complete Length Shortlands CW Place Farm Avenue, Orpington Complete Length Farnborough & Crofton CW Pleydell Avenue, Crystal Palace Complete Length Crystal Palace CW Plymouth Road, Bromley Complete Length Plaistow & Sundridge CW Poplar Avenue, Orpington Complete Length Farnborough & Crofton CW Rafford Way, Bromley Complete Length Bromley Town CW Ramus Wood Avenue, Green Street Green Complete Length Darwin CW Ravensbury Road, St Paul's Cray Complete Length Cray Valley West FW Ravensworth Road, Mottingham Complete Length Mottingham and Chislehurst North FW Raymond Road, Beckenham Complete Length Kelsey and Eden Park FW Romanhurst Gardens, Bromley Complete Length Shortlands CW Rookery Gardens, St Mary Cray Complete Length Cray Valley East FW Rose Dale, Orpington Complete Length Farnborough & Crofton CW Roseberry Gardens, Orpington Complete Length Chelsfield & Pratts Bottom CW Roseneath Close, Pratts Bottom Complete Length Chelsfield & Pratts Bottom Both Saltwood Close, Orpington Complete Length Orpington FW Scotts Lane, Shortlands Complete Length Copers Cope CW Shrewsbury Road, Beckenham Complete Length Clock House CW Silver Lane, West Wickham Glebe Way to Hawes Lane West Wickham CW Cray Valley East / Chelsfield and Pratts Bottom / Skeet Hill Lane, Chelsfield Skibbs Lane to Chelsfield Lane CW Orpington Sloane Gardens, Orpington Complete Length Farnborough and Crofton FW South Hill Road U2024 Complete Length Shortlands FW Southlands Aveneue Complete roundabout with Fairview Chelsfield and Pratts Bottom CW Spinney Oak, Bromley Complete Length Bickley FW

Page 84 St. Andrews Drive, Orpington Complete Length Cray Valley East CW St Leonards Rise, Orpington Complete Length Chelsfield and Pratts Bottom Both St. Mathews Drive, Bromley Complete Length Bickley FW St. Michaels Close, Bromley Complete Length Bickley Both St. Paul's Square, Bromley Complete Length Bromley Town CW St. Mary's Avenue, Bromley Complete Length Shortlands CW St. Thomas Drive, Orpington Complete Length Farnborough & Crofton CW Stanley Way, Orpington Complete Length Cray Valley East CW Stanstead Close, Bromley Complete Length Hayes & Coney Hall CW Steep Close, Green Street Green Complete Length Chelsfield and Pratts Bottom FW Sundridge Avenue, Chislehurst Orchard Road to Plaistow Lane Bickley CW Sussex Road, Orpington Complete Length Cray Valley East FW Sutherland Avenue, Orpington Complete Length Cray Valley West CW Sylvan Way, West Wickham Complete Length Hayes & Coney Hall CW The Alders, West Wickham Complete Length West Wickham CW The Avenue, Orpington Complete Length Orpington FW The Avenue, St Pauls Cray Complete Length Cray Valley West FW The Avenue, West Wickham Complete Length West Wickham FW The Green, Hayes Complete Length Hayes and Coney Hall CW The Greenway, Orpington Complete Length including Willow Close Cray Valley East CW The Knoll, Beckenham Complete Length Hayes & Coney Hall CW Thirlmere Rise, Bromley Complete Length Plaistow and Sundridge Both Tillingbourne Green, Orpington Complete Length Cray Valley West CW Valley Road, Shortlands Complete Length Shortlands CW Village Way, Beckenham Whitmore Road to Uplands Kelsey and Eden Park CW Wadhurst Close, Crystal Palace Complete Length Crystal Palace CW Weald Close, Bromley Complete Length Bromley Common & Keston CW Westbury Road, Penge Complete Length Penge and Cator CW Westmoreland Road, Bromley Newbury Road to Mason Hill Shortland / Bromley Town CW Wickham Crescent, West Wickham Complete Length West Wickham CW William Booth Road, Crystal Palace Complete Length Crystal Palace CW Wiltshire Road, Orpington Complete Length Petts Wood & Knoll FW Windermere Road, West Wickham Complete Length West Wickham CW Wistaria Close, Orpington Complete Length Farnborough & Crofton FW Woldham Road, Bromley Complete Length Bromley Town CW Wood Lodge Lane, West Wickham Complete Length West Wickham CW Worlds End Lane, Chelsfield Beech Road to Julian Road Chelsfield and Pratts Bottom CW

Page 85 Wyndham Close, Orpington Complete Length Farnborough & Crofton FW APPENDIX D PRIORITY 1 - PLANNED HIGHWAY MAINTENANCE PROGRAMME APRIL 2013 TO MARCH 2014

CARRIAGEWAY AND ASSOCIATED FOOTWAY SCHEMES ON PRINCIPAL ROADS

ROAD NAME & DISTRICT SECTION of ROAD WARDS

Cray Valley West, Cray Valley East and Petts Wood and A208 Chislehurst Road, Orpington Grosvenor Road to Aylesham Road Knoll A208 White Horse Hill / Mottingham Road, Mottingham Dunkery Road to Mainridge Road Mottingham and Chislehurst A208 White Horse Hill, Mottingham Green Way to Mainridge Road Mottingham and Chislehurst A222 Bromley Road, Chislehurst Centre Common Road to Prince Imperial Road Chislehurst A223, Sevenoaks Road, Orpington Tower Road to Stapleton Road Orpington CW = War memorial Roundabout to Felstead Road A232 Spur Road / Station Road, Orpington (Change of surface) FW = Orchard Grove to Station Orpington Approach A233 Main Road, Biggin Hill Lunar Close to Churchill Way including roundabout Biggin Hill A234 High Street, Penge Mosslea Road to St. Johns Road Penge and Cator Page 86 APPENDIX E PLANNED HIGHWAY MAINTENANCE PROGRAMME APRIL 2012 TO MARCH 2013

MEMBERS PRIORITIES - ADDITIONAL CARRIAGEWAY SCHEMES ON NON-PRINCIPAL AND UNCLASSIFIED ROADS

PRIORITY ROAD NAME & DISTRICT SECTION of ROAD WARDS

3 Baston Road, Hayes Pickhurst Lane to Five Elms Road Hayes and Coney Hall 2 Blackbrook Lane, Bromley Bickley Park Road to Barfield Road Bickley 9 Bourne Vale, Bromley Farleigh Avenue to Marden Avenue Hayes and Coney Hall 10 Brabourne Rise, Beckenham Complete Length Shortlands 7 Cameron Road, Bromley Hayes Road to Stone Road Bromley Town / Hayes and Coney Hall 8 Church Hill Wood, Orpington Complete Length Cray Valley West 4 Crofton Avenue, Orpington Lovibonds Avenue to No 28 (Slip Road) Farnborough and Crofton 5 Crowhurst Way, St. Mary Cray Complete Length Cray Valley East 6 Dittisham Road, Mottingham Complete Length Mottingham and Chislehurst North Kings Hall Road including roundabouts to High Street 1 Kent House Road, Beckenham Penge and Cator Beckenham Page 87 APPENDIX F PLANNED HIGHWAY MAINTENANCE PROGRAMME APRIL 2013 TO MARCH 2014

NTL - ADDITIONAL CARRIAGEWAY SCHEMES ON NON-PRINCIPAL AND UNCLASSIFIED ROADS

PRIORITY ROAD NAME & DISTRICT SECTION of ROAD WARDS

Beckenham Grove, Beckenham Complete Length Copers Cope Highfield Road, Bromley Complete Length Bickley Beddington Road, St Pauls Cray St Paul's Wood Hill to No 22 Cray Valley West Hayes Way, Beckenham Whitecroft Way to Wickham Way Shortlands Durham Road, Bromley No.44 to Westmoreland Road Shortlands Farwig Lane, Bromley Complete Length Plaistow and Sundridge Anerley Station Road, Penge Complete Length Penge and Cator Laxey Road, Green Street Green No 29 to High Street Chelsfield and Pratts Bottom

from Biggin Hill, Chelsfield and Pratts Bottom, Plus surface dressing on various classified and To be determined Cray Valley East, Darwin and Hayes and Coney unclassified county lanes Hall wards etc Page 88 Agenda Item 9

Report No. London Borough of Bromley ES 12143 PART 1 - PUBLIC

Decision Maker: Environment PDS Committee

Date: 20 th November 2012 Decision Type: Non-Urgent Non-Executive Non-Key

Title : ENVIRONMENT PORTFOLIO PLAN 2012/13; HALF-YEAR PROGRESS REPORT

Contact Officer: Gavin Moore, Assistant Director Customer and Support Services Tel: 020 8313 4539 E-mail: [email protected]

Chief Officer: Nigel Davies, Director of Environmental Services

Ward: All

1. Reason for report

The report outlines progress at the half-year stage against the commitments made in the 2012/13 Environment Portfolio Plan.

______

2. RECOMMENDATION(S)

The Committee is asked to note and comment on the progress of the 2012/13 Environment Portfolio Plan.

1 Page 89 Corporate Policy

1. Policy Status: Existing policy.

2. BBB Priority: Quality Environment. ______

Financial

1. Cost of proposal: N/A

2. Ongoing costs: N/A.

3. Budget head/performance centre: Environment Portfolio Revenue Budget 2012/2013 & LIP

4. Total current budget for this head: £31.7m, and £6.33m LIP funding from TfL

5. Source of funding: 2012/13 revenue budget and 2012/13 LIP funding agreed by TfL ______

Staff

1. Number of staff (current and additional): 206fte

2. If from existing staff resources, number of staff hours: ______

Legal

1. Legal Requirement: No statutory requirement or Government guidance.

2. Call-in: Call-in is not applicable. ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? N/A.

2. Summary of Ward Councillors comments:

2 Page 90 3. COMMENTARY

3.1 The final draft of the Environment Portfolio Plan for 2012/13 was considered by the PDS Committee on 3 July 2012, and then subsequently agreed by the Portfolio Holder.

3.2 Earlier this year, in consultation with the Environment Portfolio Holder, a selection of priority aims drawn from the Portfolio Plan was put forward for the Council’s 2012/13 Building a Better Bromley commitment. Appendix 1 sets out the progress which has been made on these priority aims.

3.3 A summary of half-year performance against the full set of milestones agreed in the Environment Portfolio Plan 2012/13 is included as Appendix 2.

3.4 With regard to measurable performance, many indicators in the Portfolio Plan are monitored on an annual basis. Where monitoring is more frequent, half-year results are set out below.

3.4.1 During the first half of the year recycling rates have been around 50%. This is comparable to performance in 2011/12, but has fallen slightly short of the aim this year for a 51% recycling rate. Quantities of residual household waste have been marginally higher than in 2011, but should still meet expected levels by the end of the year. The proportion of waste sent to landfill has also been higher than expected, mainly due to the closure of the SELCHP incinerator for 6 weeks. However, it is anticipated that Veolia will provide sufficient incinerator capacity for the annual target to be achieved.

3.4.2 The first tranche street cleansing survey was affected by the adverse wet weather during the spring and summer period. As a result, a higher level of litter and detritus was found in the Rural Roads category. An additional factor was the change of cleansing frequency for country lanes during the summer period. This was changed from fortnightly to four-weekly in the new cleansing contract which commenced on 29 th March 2012. The second and third tranche surveys will be carried out during the latter period of the year where the cleaning frequency remains fortnightly – this should reduce the volume of detritus at survey time and performance should improve. Small increases in litter and detritus were also found in the Industry and Warehousing and High Obstruction Housing categories, attributable to a problem with overflowing litter bins. Changes have been implemented to increase the respective emptying frequencies. Graffiti and fly-posting clearance has been sustained at the high performance level achieved in previous years.

3.4.3 The number of fly-tipping incidents increased during the July-August period. This may not however reflect long-term trends.

3.5 Finally, comparative road safety data for all London boroughs has now been published for 2011. In Bromley during 2011 there were 81 people killed or seriously injured, with 870 injuries and deaths in total.

• Bromley’s killed and seriously injured casualties were 10% lower than in 2010; this was better than the outer London average reduction of 4% • Bromley’s serious injury casualties were down 15% on 2010 levels; this was better than the outer London average (-6%) • However Bromley had 7 fatalities, up from 3 in 2010 • Total casualties in Bromley during 2011 were up 7%, compared to an outer London average reduction of 1% • Casualties (by mode) were up 18% for pedestrians, no change for cyclists, down 14% for motorcycles, and up 4% for car occupants.

3 Page 91

4. POLICY IMPLICATIONS

4.1 The 2012/13 Environment Portfolio Plan reflects current policy.

5. FINANCIAL IMPLICATIONS

5.1 The priorities, as set out in this report will be delivered within the resources identified in the Portfolio budget for 2012/13 and any external funding that can be secured.

Non - Legal and personnel implications Applicable Sections: Background Environment Portfolio Plan 2012/13 Documents: http://sharepoint.bromley.gov.uk/documents/s50001631/Enc.%201%20for%20Environment%20Portfolio%20Plan%2020.pdf

(Access via Contact Officer)

4 Page 92 Appendix 1

Building a Better Bromley 2012/13; Half-Year Progress Report

Environment Portfolio

Improve recycling and composting rates, building on the success of Recycling and Composting for all to divert even more waste from landfill

The Waste team continue to visit approx 14,000 customers pa, assisting with practical issues, which includes advice on waste minimisation, recycling, composting and re-use. Presentations have been given to a variety of resident groups, along with activities utilising the Waste promotions vehicle. Waste are co-ordinating with Friends groups and the Bromley Sustainable Schools Forum to provide advice and guidance to schools, businesses and community groups. “Trips to the Tip” and regular presentations to resident’s groups assist in raising the profile of the importance of recycling, re-use and waste minimization.

Introduce a new used textile collection service

New textile bring banks have been installed on all Council sites, and the upgrading of the paper, glass, can and plastic banks will be completed by Q4. Funding is being sought from WRAP to explore the most effective methodology for a kerbside textile service. This will be introduced in Q3, with the aim of expanding borough-wide in Q4. It is intended that this service will be fortnightly, maximising convenience for residents.

Improve our facilities for producing energy and fertiliser from organic waste

We have continued to provide assistance to businesses looking to introduce Anaerobic Digestion (AD) facilities in Bromley, or sufficiently nearby to provide an economic option for the disposal of organic waste. Planning permission has been granted to CountryStyle for an AD plant.

Sustain our standards of street cleanliness

Enforcement by XFOR started on 10 September 2012; the company are issuing an average of 100 FPNs each week. Kier’s vehicle tracking information is now being used to help monitor operations. Overflowing litter bins and weed growth are being addressed by additional programmes of work funded from the £200k contract contingency sum, involving weekend channel sweeping, deep cleaning of residential streets, mobile ‘hot spot’ litter picking beats, and additional litter bin emptying. Discussions with the Probation Service have been held to extend the Community Payback Operations from 2 to 5 days a week, 4 of which could be to assist with street cleansing.

Page 93

Continue to take effective action to improve road safety and reduce accidents

Identified locations for road safety improvement works have been fully investigated – priority locations are being developed further, in consultation with ward Members. Implementation of works will depend on the outcome of the consultation and are programmed for implementation in Q3/Q4. Skid resistant road surfacing:

v Sites have been identified and tests have been carried out. v Further testing will be carried out for new sites. v There are currently 8 large schemes scheduled for implementation, with some already. complete and the rest to be in place by the end of 2012.

Seek to reduce traffic congestion and improve journey times

Chislehurst Bridge reconstruction due for completion November 2012. Resurfacing of A233 ( Road) completed. Resurfacing of A208 (White Horse Lane) due for completion on target. ‘Smarter Travel Bromley’ launched in September. Preliminary investigation of congestion by Nugent Centre entrance completed. 87% of schools are still engaged in the school travel program.

Improve energy efficiency in the borough

Statutory Carbon Reduction Commitment reports submitted to the Environment Agency – CRC Allowances have been purchased and surrendered for 2011/12. Business case approved for SEELS invest-to-save Street Lighting scheme. Launched extranet in September to improve working with LASER. Submitted statutory emissions data for the Council’s own estate and operations to DECC. Salix street lighting project upgraded to LED technology. Discussions held with The Glades to discuss their trial of ultra-efficient LED lighting.

Implement an ‘invest to save’ programme to replace 8,000 aged lamp columns

Tenders have been returned and the programme will be presented to the Executive following Environment PDS on 20 November.

Expand the Street Friends scheme

Residents can now apply on-line to become a Snow Friend or Street Friend, or to join a Friends of Parks group. BYAP (Bromley Youth Advisory Panel) is considering realigning its constitution to encompass voluntary action for streets, in addition to parks and green spaces. Its remit would be to advise on ways to promote and encourage youth engagement to improve the environment.

Promote responsible dog ownership

Responsible dog ownership events have been held in Bromley High Street, Priory Gardens and Bromley Civic Centre.

Page 94 Appendix 2

Outcome 1 Improving the Street Scene

Clean streets are a high priority for residents Issues Satisfaction with the street scene has a significant impact on residents’ confidence in the Council

Aims Maintain street cleanliness

In the coming year we will: Implement a contract for the issuing of fixed penalty notice for littering and dog fouling, through a private See Appendix 1 enforcement company.

Expand the Street Friends scheme, and forge greater See Appendix 1 links with Friends of Parks

Successfully manage the transition to the new street See Appendix 1 cleansing contract.

Continue to monitor street cleanliness standards See Appendix 1 effectively and accurately • 25 temporary street trading Continue to develop the borough’s street café culture, licenses issued to cafes and and increase visits by specialist street markets, restaurants. • Continental street market in Bromley town centre Q3.

1 Page 95 Appendix 2

Minimising Waste, and Increasing Recycling and Outcome 2 Composting Encouraging greater public involvement in waste minimisation and Issues recycling

Increasing the proportion of waste recycled and composted Aims Reducing the amount of waste sent to landfill

In the coming year we will: Consolidate the borough-wide implementation of our See Appendix 1 Recycling for All policy

Through our waste advisers, assist residents to See Appendix 1 minimise their waste and recycle more

Host a trial Green Garden Waste collection service, and See Appendix 1 assess demand for a borough-wide roll out

Introduce a textile collection service, incorporating new See Appendix 1 ‘bring banks’ and a kerbside service

Support schools and businesses to recycle, working See Appendix 1 closely with other initiatives such as Friends groups.

2 Page 96 Appendix 2

Outcome 3 Enhancing Bromley’s Parks and Green Spaces

Issues Develop community involvement in our parks

Aim Conserve and enhance Bromley’s parks and green spaces In the coming year we will: • Queens Gardens prepared Maintain the cleanliness of parks, open spaces and for visit during the Diamond verges Jubilee celebrations • Litter picking undertaken by volunteers and Friends • Glentrammon R/G improvements opened in Q2 • Countryside Day in Q2 • Friends toolkit jointly developed • Friends Visitor Centre at Promote the activities of Friends groups in enhancing Kelsey completed. Handed the borough’s parks and street scene over to Friends Group; opening planned for Q3 • Kelsey Friends responsible for bridges – painted/cleaned in Q2 • Lubbock’s Life timeline mural and educational project (High Elms) open Q2 • Farnborough Recreation Ground and Betts Park ‘Outdoor Gyms’ opened Q2. • BMX facility at Tubbenden R/G opened Q2. Continue to develop healthy activities for both young • Brook Lane former allotment and old developed Q3 for healthy lifestyles and growing plots. • Joint work with Environment Agency in the Crays; outreach programmes planned in Q3 and Q4 for the Ravensbourne. • Bollards at Leaves Green • Maintain safety and security in parks and green spaces Vehicle height barriers erected at Harvington with others under design • Review of procurement Ensure that good value for money is provided when procedures and contracting work is commissioned to maintain and improve being undertaken. Gateway Bromley’s parks Report being written. • Framework contract for sponsorship completed Q2. Promote responsible dog ownership; and work with the police to enable owners of dangerous dogs to be See Appendix 1 prosecuted.

3 Page 97 Appendix 2

Outcome 4 Securing our transport infrastructure

Satisfaction with the condition of roads and pavements has a significant impact on residents’ confidence in the Council Issues Ensure maintenance of the borough’s infrastructure is carried out in a timely and effective way.

Aim Maintain roads, pavements and street lighting in a good condition In the coming year we will: Commence a new street lighting programme to replace See Appendix 1 8,000 old lamp columns during 2012/14 • Street lighting replacement Continue street light dimming through replacement of programme awaiting ‘Invest old columns in residential areas, and commence a new to Save’ bid outcome trial on traffic routes • Lantern replacements on traffic routes planned Q3

Review the effectiveness and priorities of the winter • Routes and policy being service in the light of experience reviewed for publication Q3

Complete the reconstruction of Chislehurst Bridge See Appendix 1

Complete a major programme of carriageway resurfacing works on principal roads including A208 See Appendix 1 (White Horse Lane) and A233 (Leaves Green Road).

Aim Improve the standard of work carried out by the utilities In the coming year we will: Continue to inspect 80 % of utilities works, 50% more • Achieved than expected in the national code of practice

Work with utility companies to improve the speed and • quality of their work, taking enforcement action where Quarterly co-ordination and progress meetings held necessary

4 Page 98 Appendix 2

Aim Minimise the risk of flooding In the coming year we will: • Working with ‘Group 6’ Develop the role of Lead Local Flood Authority under boroughs to develop local the Flooding & Water Management Act including strategy preparation of a Local Flood Risk Strategy • Investigating joint procurement for survey requirements

Adopt the role of Sustainable Urban Drainage Systems • Awaiting outcome of Approval Body (SAB) consultation – due Q3 • Text has been drafted Develop the LBB web site to provide flood risk • Developing scripts and information for the public logging requirements for flooding enquiries.

5 Page 99 Appendix 2

Outcome 5 Improving Transportation

Predicted long-term increase in car ownership Issues Transport needs of those without private cars

Promotion of cycling, walking and public transport to: improve access to services, facilities, and employment; reduce peak time congestion; and lower carbon emissions Aims Improve the road network and journey times for all users

Promote safe and secure parking provision In the coming year we will: Continue implementing the traffic element of the • Capacity will be Bromley Town Centre Area Action Plan, including : increased at Mitre • Close, St Blaise, on- introducing a strategy to meet parking demand after street and the Hill the planned closure of Westmoreland Road MSCP; (phase 1) in time for • working towards a medium-term 10% modal shift Christmas 2012 reduction in journeys by car to Bromley Town • Westmoreland Road will Centre. not close until 2013

Lobby for extensions of the Docklands Light Railway • DLR options report and Tramlink into the borough received from TfL/DLR on 21 st September 2012. Officers will review and analyse report in Q3.

Look to decrease congestion and reduce journey times See Appendix 1 on priority routes, focusing on the A224 and A222. • Bus routes resurfacing Improve priority bus routes and, where practicable, programme implementation reduce bus journey delays due to commence in Q3. • Possible re-routing of 273 bus service via the Crays being investigated

Continue to support schools, developers and • 34 schools have bought in businesses in implementing effective Travel Plans to School Crossing Patrol with reduce traffic congestion, improve road safety and others interested. encourage walking and cycling. • Engineering measures being introduced at selected sites. • On target to deliver cycle training to 1,600 people • Successful trial of Get Back on Your Bike courses for adults who have lost confidence cycling

6 Page 100 Appendix 2

• Planning application Extend the New Beckenham (Lennard Road) car park submitted • If agreed, programmed for construction 2013 • Due for completion Q3 Resurface and adopt Kent House Station Approach to • improve access to the station Adoption is then planned for Jan 2013

Aim Fewer road casualties In the coming year we will: Implement a programme of accident reduction measures in key locations, alongside a programme or See Appendix 1 road safety education

Identify and prioritise locations for accident reduction Assessment will commence in Q4 with a survey of the measures in 2013/14 most recent accident data Deliver a programme of skid resistant road surfacing to See Appendix 1 improve safety

7 Page 101 Appendix 2

Outcome 6 Customer Services and cross-cutting themes

Opportunities to contribute to wider environmental improvements

Issues Motorists expect parking enforcement to be fair and effective

Meet public expectations for high standards of customer service

Aim Reducing energy costs and emissions In the coming year we will: Lead a programme of activity, including energy efficiency improvements, to reduce the Council’s carbon See Appendix 1 emissions and mitigate the impact of the carbon tax

• Held successful 23 rd BEAs Provide exemplars of good practice and celebrate the achievements of Bromley’s residents and businesses at event on 13 July 2012 • Sponsored by News the Bromley Environment Awards Shopper & Coolings

Work with local private and public sector organisations to minimise waste, improved environmental resilience See Appendix 1 and reduce carbon emissions across the borough

Aim Provide fair and effective parking services In the coming year we will: • Introduction of Body Worn Video for enforcement staff Continue to improve the effectiveness and fairness of • PCN hot spots the Council’s parking enforcement activities identified. Publicity and information signs are being developed to help increase compliance. • Provide a choice of parking payment methods for Report via September PDS motorists shows steady growth in mobile phone parking. • Safer Parking Awards in Ensure that good parking facilities and reasonable place for all our car parks • Shared service and charges support the vitality of the borough’s town improved ICT contract centres reports, via November PDS

• Adverts and information signs ensured smooth Ensure motorists are fully informed about the revised implementation. parking charges introduced in April 2012 • The charges increase has not significantly affected demand on or off street.

8 Page 102 Appendix 2

Maintain high standards of customer service Aim Ensure services are efficient and provide value for money Uph old good governance and accountable decision making

In the coming year we will: • Customer Service Excellence standards are being sustained • ‘Channel Shift’ programme in Sustain improvements in our standards of customer place to improve access to service and make it easier for customers to contact us services by ICT, including via Social Media • Greenspace services CRM went live Q2.

• Co-ordinating consultation Use customer feedback to help us improve service (eg traffic/parking) and feedback surveys performance • Street cleansing contractor monitoring satisfaction. • Portfolio Plan and 12/13 Embed coherent and effective business planning and outcomes agreed performance management • Regular recommendations/ updates to DMT from dept ICT group. • Corporate IT now provide Continue to improve the use of ICT and flexible mobile updated work plans for ESD working to benefit our customers tasks which includes the Development teams future work. • Dept. meetings increased to bi-monthly • Contract has commenced Relocate street cleansing services to the Central Depot for completion in Q3 to secure improvements in service and efficiency • Kier to relocate in the New Year

9 Page 103 This page is left intentionally blank

Page 104 Agenda Item 10

Report No. London Borough of Bromley ES 12140 PART ONE - PUBLIC

Decision Maker: Environment PDS Committee

Date: 20th November 2012 Decision Type: Non-Urgent Non-Executive Non-Key

Title : FORWARD WORK PROGRAMME, MATTERS ARISING FROM PREVIOUS MEETINGS, AND CONTRACTS REGISTER Contact Officer: Linda Winder, Office Resources Manager Tel: 020 8313 4512 E-mail: [email protected]

Chief Officer: Nigel Davies, Director of Environmental Services

Ward: Borough Wide

1. Reason for report

1.1 Members are asked to review the Committee’s work programme for 2012/13 and to consider:

• progress on requests from previous meetings of the Committee; • the contracts summary for the Environment Portfolio. ______

2. RECOMMENDATIONS

2.1 That the Committee:

(a) Review the draft work programme attached as Appendix 1;

(b) Review the progress report related to previous Committee requests as set out in Appendix 2; and

(c) Note the Environment Portfolio contracts listed in Appendix 3.

1 Page 105 Corporate Policy

1. Policy Status: Existing Policy

2. BBB Priority: Quality Environment ______

Financial

1. Cost of proposal: No Cost

2. Ongoing costs: Not Applicable

3. Budget head/performance centre: Environment Portfolio 2012/13 approved budget

4. Total current budget for this head: £31.7m and £6.33m of LIP funding from TfL.

5. Source of funding:2012/13 revenue budget and 2012/13 LIP funding agreed by TfL ______

Staff

1. Number of staff (current and additional): 206 fte

2. If from existing staff resources, number of staff hours: N/A ______

Legal

1. Legal Requirement: Non-Statutory - Government Guidance

2. Call-in: Not Applicable ______

Customer Impact

1. Estimated number of users/beneficiaries (current and projected): Whole borough ______

Ward Councillor Views

1. Have Ward Councillors been asked for comments? Not Applicable

2. Summary of Ward Councillors comments:

2 Page 106 3. COMMENTARY

3.1 Forward Programme

3.1.1 The table in Appendix 1 sets out the Environment Forward Programme for the remainder of 2012/13, as far as it is known. The Environment Forward Programme indicates which division is providing the lead author for each report. The Committee is invited to comment on the schedule and propose any changes it considers appropriate.

3.1.2 Other reports may come into the programme. Schemes may be brought forward or there may be references from other Committees, the Portfolio Holder or the Executive.

3.2 Previous Requests by the Committee

The regular progress report on requests previously made by the Committee is given at Appendix 2. This list is rigorously checked after each Committee meeting so that outstanding issues can be addressed at an early stage.

3.3 Contracts Register

Information extracted from the current Contracts register, in a format which addresses the responsibilities of the Environment Portfolio, is attached as Appendix 3. Future contracts are marked in italics . The Appendix indicates in the final column when the Committee’s input to contracts will next be sought. Unless otherwise stated this is the date when contract approval, or approval to an extension, will be sought.

4. POLICY IMPLICATIONS

4.1 Each PDS Committee is responsible for setting its own work programme.

Non -Applicable Sections: Financial, Legal and Personnel Background Documents: Environment PDS agendas and minutes for the years (Access via Contact 2006/07 to 2012/13 Officer) http://sharepoint.bromley.gov.uk/default.aspx

3 Page 107 APPENDIX 1

ENVIRONMENT PDS COMMITTEE FORWARD PROGRAMME FOR MEETINGS 2012/13

Environment PDS – 15 Jan 2013

Forward Work Programme, Matters Arising C&SS PDS Committee from Previous Meetings and Contracts Register

Budget Monitoring 2011/12 Finance For pre-decision scrutiny

Street Environment Contracts Review SS&GS For pre-decision scrutiny

Review of Enforcement Services for Issuing SS&GS For pre-decision scrutiny Fixed Penalty Notices Environment PDS – 5 March 2013

Forward Work Programme, Matters Arising C&SS PDS Committee from Previous Meetings and Contracts Register

Budget Monitoring 2011/12 Finance For pre-decision scrutiny

Environment Portfolio Plan 2013/16 C&SS For pre-decision scrutiny

Parking capacity T&H For pre-decision scrutiny

Parking Charges Review C&SS For pre-decision scrutiny

4 Page 108 APPENDIX 2

Progress Report on Previous Requests of the Committee

PDS Ctte e Committee Request Progress

Minute & Date

28.02.12 Investigate the feasibility of developing a This will be considered by the Parking Working faith parking permit for weekend use at Group later this year (see below) recognised places of worship

3.07.12 A Parking Working Group to be convened Meeting will be convened in December 2012 or after the 6 month review of parking January 2013, following a decision on whether charges has been completed to proceed with a parking shared service

25.09.12 Information to be provided to the To be completed before 16 November 2012 Committee on the Pinch Point and Smarter Driving programmes

5 Page 109

Contracts Register Summary Appendix 3

Contract Start Complete Extension Contractor Total Annual Environment PDS granted to Value £ Value £ Parking ICT 01.04.13 30.09.16 n/a Currently in 750,000 150,000 Environment PDS on tender est. est. 20 November 2012 will process consider shared service with LB Bexley.

Bus Route 01.01.08 01.01.13 Mott 1.5m 300,000 These contacts will design (Pan- Macdonald continue to Jan 2013, London as consultancy advice contract) on a previous scheme may be needed. The contracts will end in 2013 and will not be replaced. Bus Route 01.01.08 10.01.13 Buchanan 1.5m 300,000 As above design (Pan- London contract) Street Works 01.04.10 31.03.12 31.03.13 B&J 900,000 312,000 (NRSWA) Enterprises Street Works 01.04.13 31.03.16 Option for Up to 350,000 Environment PDS (NRSWA) 1/2 x 2 yr 1.75m (estimate) 20th Nov 2012 extensions (estimate) ending Executive 28 th Nov 31.03.18 or 2012 31.03.20 Street Lighting 01.04.07 31.03.11 31.03.13 May Gurney 7.1m 1.8m Maintenance & Improvements Contract – Street Lighting 01.04.13 31.03.23 20.0m 2.0m Environment PDS Maintenance (estimate) (estimate) 20th Nov 2012 & Subject to Improvements Capital Executive 28 th Nov Contract – Investment 2012 Parking Bailiff 1.10.11 31.03.13 n/a JBW & Swift 320,000 240,000 Services est. est.

Parking Bailiff 1.04.13 31.03.16 n/a ESPO 600 to 240k est. Services framework 750k est.

Removal of 01.05.10 30.04.12 29.04.13 Holwood GM 19,858 59,574 12-month extension surface Ltd was agreed with the vegetation contractor in Dec 2011 from Public Rights of Way Hanging 30.05.11 30.04.12 30.04.13 CJS Plants & 84,000 42,000 12 month extension Baskets Village was agreed with Contract A&B Gardens current contractor for hanging baskets at current costs. Rural Grass 30.5.11 29.05.13 Landmark 90.000 45.000 Contract let on a 2 cutting Services year basis with option to extend 1 further year.

6 Page 110 Contract Start Complete Extension Contractor Total Annual Environment PDS granted to Value £ Value £ Removal of 01.10.10 30.09.13 Extension Pick a Part 33,800 10,600 Within Director of Abandoned for twelve Environmental Vehicles months Services’ remit taken up Council Fleet 05.11.06 04.11.12 05.11.13 London Hire 674,383 112,383 Extension agreed with Hire (<85,000 contractor from 2012)

Playground 01.01.08 31.12.13 Safeplay 369,300 61,550 Extension to the maintenance contract will be considered early in 2013. Transportation 01.06.11 Open 30.11.13 AECOM, 1.2m 200,000 Env PDS Committee in Consultancy ended through TfL (if max. 6 April 2012 agreed Framework years is further use until Nov agreed) 2013

Depot 01.04.10 31.03.15 N/A Sight and 126,000 126,000 Security Sound

Staff Leased 01.09.09 31.08.12 31.08.15 OGC 1,923m 641k Report to E&R PDS Car Contract Framework and Executive 20 June 2012 agreed use of GPS framework agreement until 2015.

Ambulance 05.11.07 04.11.13 04.11.15 London Hire 2.03m 339,000 ACS will be consulted Hire during summer 2012 over the option to extend the accessible bus fleet contract for 2 years from November 2013

Parking 01.10.06 30.09.11 30.09.16 Vinci Park 10.79m 2.16m Street 29.03.12 28.03.17 Kier (public 281,983 56,397 Awarded a five year Environment toilets); contract with the option Contract of a two year extension Community 1,221,800 244,360 at the Council’s Clean discretion. (graffiti removal);

Veolia 1,463,538 292,708 (Gulley cleansing)

Kier 15,798,212 3,159,642 (Cleansing, Highway Drainage ) Maintenance 01.04.10 31.03.17 KCC 940,000 134,000 Option for 2 year & repair of extension vehicles

CCTV Repair 01.04.12 31.03.17 Eurovia 214,256 42,852 & Infrastructure Maintenance Services Ltd Contract CCTV Control 01.04.12 31.03.17 OCS Ltd 1,263,258, 252,652 Room Monitoring

7 Page 111 Contract Start Complete Extension Contractor Total Annual Environment PDS granted to Value £ Value £ Highway 01.07.10 30.06.17 O’Rourke 17m 2.4m Option for one year Maintenance extension – Minor & Reactive Arboriculture 18.07.08 17.07.17 Gristwood 5.12m 568,860 and Toms Coney Hill 28.07.10 27.07.17 Enitial 952,000 136,000 Option for 2 year Landfill Site extension Monitoring

Highway 01.10.10 30.09.17 FM Conway 26m 3.7m Option for one year Maintenance extension – Major Grounds 01.01.08 31.12.17 The 26.1m 2.75m Maintenance Landscape Group Waste 01.11.01 31.03.19 Extended to Veolia 127.5m 8.5m Collection March 2019 Extension approved by Executive on 16 Nov 2011

Waste 24.02.02 31.03.19 Extended to Veolia 147m 10.5m Extension approved by Disposal March 2019 Executive on 16 Nov 2011

Parks Security 01.04.10 31.03.20 Ward 4.2m 420,000 Security

8 Page 112 Agenda Item 12a By virtue of paragraph(s) 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

Document is Restricted

Page 113 This page is left intentionally blank

Page 120 By virtue of paragraph(s) 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

Document is Restricted

Page 121 This page is left intentionally blank

Page 122