PRE-FEASIBILITY REPORT

EXPANSION OF EXISTING LIME STONE MINE FROM 0.09 MTPA TO 0.8 MTPA (MINING LEASE AREA OF 96.25 HECTARES)

In

VILLAGES - KUJOTA, AJEETPURA, BHAISLANA

TEHSIL-KOTPUTLI, DISTRICT- ()

Submitted by M/s National Limestone Company Private Limited

(Pre-feasibility Report as per MoEF circular J-11013/41/2006-IAII(I) 30-12-2010)

1

Table of Contents

Limestone Mine 1. Executive summary 2. Introduction of the project/ Background information 3 Project Description 4 Site Analysis 5. Planning Brief 6 Proposed Infrastructure 7. Rehabilitation and Resettlement (R & R) Plan 8. Project Schedule & Cost Estimates 9. Analysis of Proposal (Final Recommendations)

2

1. EXECUTIVE SUMMARY

M/s National limestone Co.Pvt. Ltd is established in the year 1981, as per the Companies Act 1956.The business of the company is to acquire mining lease to do mining limestone mineral locally.

The Rajasthan State government granted an area of 415.03 Ha of Mining lease of Limestone and Marble near village Mohanpura Jodhpura to Shri Rameshwar Prasad Praqsad Bajaj, shahpura by Govt. Order dated 14.09.1981. This was then transferred to National Limestone Co.Pvt.Ltd, Shahpura by Govt. Order dated 19.2.1986. The part of the lease area 318.78 Ha was surrendered to the Rajasthan state government in three phases (84.5 ha on 20.5.1999, 183.24 ha on 21.10.2000 and 51.04 ha 31.3.2001) to Government of Rajasthan. Hence the balance area at the end was 96.25 ha is with National Limestone Co.Pvt.Ltd near villages Kujota, Ajeetpura, Bhaislana, Mohanpura Jodhpura of - Kotputli District Jaipur, Rajasthan for mining of limestone & Marble.

M/s National Limestone Company Private Limited has renewed mining lease for Limestone and marble (under minor mineral) near villages Kujota, Ajeetpura,Bhaislana over an area of 96.25 ha. vide Govt. of Rajasthan order number bearing S.No-P.7(15)Mine/Group-2/95, dated 03.05.2005. the duration of Mining lease is from 09.08.1995 to 20 years

National Limestone Company Private Limited has proposed to increase the Limestone production from 99325 tonnes to 0.8 MTPA

2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

(i) Identification of project and project proponent. In case of mining project, a copy of mining lease/letter of intent should be given project, a copy of mining lease / letter of intent should be given.

M/s National Limestone company Private Limited is the one of the leading producers of Limestone in this region with production capacity of 99325 tonnes of limestone and 9184tonnes of Marble per annum.

M/s National Limestone Co.Pvt.Ltd is one of the leading suppliers of limestone and marble in local market.

3

M/s National Limestone Company Private Limited has renewed mining lease for Limestone and marble (under minor mineral) near villages Kujota, Ajeetpura,Bhaislana over an area of 96.25 ha. vide Govt. of Rajasthan order number bearing S.No-P.7(15)Mine/Group-2/95, dated 03.05.2005. the duration of Mining lease is from 09.08.1995 to 20 years

The mining lease area is located at a distance of 45 Km from Dabla railway station which is on the main line of North Western R ailway. The area is well connected by the road network. Mining lease area is about 5 Km from NH 08 and about 13 Km from Tehsil- Kotputli which is located on National Highway no. 08. Letter of Mining lease is attached as Annexure -I

(ii) Brief description of nature of the project.

M/s National Limestone Co.Pvt.Ltd proposes to increase the production of limestone from 99325 tonnes to 0.8 MTPA tonnes and the project proposal comprises of the following:

 0.80 Million TPA Limestone Mining

DETAILS OF LIMESTONE MINE ARE GIVEN BELOW

The deposit is accessible at a distance of 5 kms from Gordhanpura Chowki located in National Highway No 08. Gordhanpura Chowki is at a distance of 112 kms from the district head quarters Jaipur on Jaipur –Delhi National highway No 08

The mining lease area is located at a distance of 45 Km from Dabla railway station which is on the Delhi – Udaipur main line of North Western Railway. The area is well connected by the road network. Mining lease area is about 5 Km from NH 08 and about 13 Km from Tehsil- Kotputli which is located on National Highway no. 08.

Present Exploration status

In order to know the subsurface behaviour of the limestone band core drilling was carried out in 2007 and 2010. The total meterage drilled works out to 1613 mts with 11 bore holes.

4

Eastin Northin Bearin BH No g g Depth Angle g 60866 BH 1 3 3060591 117 45 S50E 60846 BH 2 7 3060316 102 45 N30W 60847 BH 3 5 3060304 130 45 S30E 60759 BH 4 3 3059392 108 50 N30E 60937 BH 5 0 3060765 204 45 N30E M/01/1 60957 0 6 3060613 150 50 N M/02/1 60960 0 3 3060780 200 45 N10 E M/03/1 60955 0 5 3060900 143 45 N93 E M/04/1 60854 0 9 3060497 171 50 S46E M/05/1 60976 0 5 3060695 176.5 50 N M/06/1 60792 0 5 3059396 111 50 N Total meterage 1613 m

Geological Cross-Sectional Area Method The basic input in this method is demarcating the various features of the area followed by the preparation of the cross-sectional profile. The profiles are nothing but the line of intersection with the topography generated with GPS. The profiles were then converted into geological sections by incorporating the geological contacts as intersected by the geological mapping and drill hole data.

The major lithological formations encountered viz. Overburden soil. Limestones, Calc silicate, Dolomite were marked in the profiles and geological sections were created. The limestone based on the chemical analysis of the borehole cores were subdivided into 1. Limestone 2. Low grade limestone and 3. Rejects within limestone. The Geological Sections prepared in this way were utilised to calculate the sectional area of the different lithological units. The average cross sectional area was then multiplied by distance to arrive at the volume between the two sections. The volume so determined was converted to weight in tonnes by applying ‘volume to weight’ ratio commonly referred to as ‘tonnage

5 conversion factor’ (TCF). The TCF was taken as 2.5.

Limestone of Mohanpura varies in orientation from place to place due to the folding and overturning. In Block I the deposit shows a gentle dip of 25 o to 45 o whereas in Block II and Block III the dips are sub vertical to vertical. Thus the true thickness of the limestone lies between 80- 100 m, but due to variation in dips it covers different widths in different areas. Keeping the safety zones of 100 m from the villages which overlap the mining lease and 15 m safety zone from ML boundary, the actual Mineable resources has been calculated through conventional cross –sectional area method. The resources thus calculated have been treated as “indicated resources”.

Tonnage Conversion Factor

One cubic meter of in-situ Limestone by weight has been considered to be equivalent to 2.5 tonnes of Limestone by weight.

Block I For the purpose of calculation of mineable resources through section line GG’, LL’ and MM’ safety zone of 100 m towards Ajeetpura village in south- western part and a 100 m safety zone towards Kujota village in north- eastern part has been kept. Total strike length of 485 m has been taken for resource calculation. A village road connecting Ajeetpura and Kujota passes from the lease block, which has to be diverted to win maximum ore.

Block II This is the block where the mining activities are being carried out at present. For the resource calculation, a total strike length of 450m has been taken leaving a safety zone of 100m in north east for Ajeetpura village.

Block III The major part of the block is blocked for resources as the Bhaislana village is situated on a part of it and a safety zone of 100 m is to be kept from ultimate pit boundary. Thus a strike length of only 120 m could be taken for estimation of resources.

6

Summary of the geological Vs Mineable resources in 3 blocks of National Limestone Co.Pvt.Ltd

Block Limestone (T) Subgrade Waste Rock (T) Limestone (T) Geologic Mineabl Mineabl Geologi Mineabl Geologi al e e cal e cal I 2848086 167742 604625 1332712 2073875 2542262 2 37 .5 .5 II 1427770 684540 760000 3037275 2613259 8902362 2 0 .5 III 4144450 174090 0 0 2179950 1868100 0 Total 4690301 253605 1364625 4369988 6867084 1331272 4 37 5 MioT 46.90 25.36 1.36 4.37 6.87 13.31

Resource calculation of different blocks of deposit

Block SL BH Rock Sect. Distance Sp. Tonnage No Nos Area of Gr (sq.m influence ) (m) I GG' BH-5 Lst 23198 180 2.5 10439100 Sub 910 180 2.5 409500 lst Waste 2038 180 2.5 917100 LL' M/01/ Lst 10779 210 2.5 5658975 10 & Sub 1578 210 2.5 828450 M/02/ lst 10 Waste 1823 210 2.5 957075 MM' M/05/ Lst 2847 95 2.5 676162.5 10 Sub 399 95 2.5 94762.5 lst Waste 2813 95 2.5 668087.5 II AA' BH-1 Lst 5393 90 2.5 1213425 Sub 3056 90 2.5 687600 lst Waste 2985 90 2.5 671625 DD' M/04/ Lst 7673 175 2.5 3356938 10 Sub 807 175 2.5 353062.5 lst Waste 9302 175 2.5 4069625 BB' BH2 & Lst 4919 185 2.5 2275038 BH3 Sub 4317 185 2.5 1996613 lst Waste 8997 185 2.5 4161113 III CC' BH-4 Lst 5803 120 2.5 1740900 Sub 0 120 2.5 0 lst Waste 6227 120 2.5 1868100

7

Mineable Reserves The proved and probable category reserves of the Limestone is of the order of 51.27 tonnes. Around 10% of reserves will be locked under the ultimate pit slope (under 7.5 meters buffer zone line from lease boundary line, Safety zone from the villages, roads etc. will be blocked.Thus the mineable reserves of Limestone are of the order of 26.72 Million tonnes, which may be raised or lowered as per the quality of rocks come across in side and in depth during mining.

SUMMARY Block Limestone Subgrade Waste Proving (T) Limeston Rock (T) level e (T) (m) I 16774237.5 604625 2073875 240 II 6845400 760000 2613259 275 III 1740900 0 2179950 305 Total 25360537.5 1364625 6867084 MioT 25.36 1.36 6.87

Life of Mine:

The total mineable Limestone reserves including all blocks work out to 26.72 Mio. tonnes by considering present rate of production of 0.8 million tones per year the life of mine works out to be 33 years.

Reserves and quality

The quality of limestone from lease area adequate to meet the requirements, The average Run Of Mine quality of limestone is as under:

Average Quality of Limestone

Composition Quality(%)

SiO 2 12.3

Al 2O3 1.8 Fe 2O3 0.7 CaO 43.2 MgO 4.9

Topography, Drainage, General geology and Local geology:

Topography

The area exhibits flat topography and gentle to moderately steep slopes towards Northern and western flanks. Ajeetpura village in the Western part

8 is situated at a higher elevation as compared to eastern part of the area.

Drainage

The lease area is almost flat terrain with some undulations. No nalah is located in the lease area. Drainage in nearby area is towards north eastern side by sota nadi located around 3.0 kilometers NW from the lease area. The Sabi river is around 7.5 Km south of the lease area. Limestone is covered by soil and most of the area is being used for cultivation. Seasonal crops like Bajra, Mustard, pulses are grown. There is no Forest land within the lease area. Average rain fall for the past five years is about 559.18 mm (IMD-Jaipur report for the year2008- 2012 and for the period June- September).

General (Regional) Geology:

The rock formations of this area belong to Ajabgarh series of Delhi system. The regional stratigraphy is as follows

Delhi Limestone, Ajabgarh Intrusive System quartzite, Series granites,pegmatites,quartz Schists, veins and amphibolites Phyllites etc. series Railo series The limestone occurs as bands having variable chemical composition and texture. In the field megascopically one can locate fine grained to coarse grained crystalline light to dark grey bands of superior limestone and also inferior bands having higher percentage of silica/amphibolites limestone which contains high concentration of needles of amphiboles viz. Tremolite and actinolite either sparingly dispersed or as clusters.

The dolomite limestone band which can also be distinguished on keen surface examination occurs side by side without having any regularity. The black crystalline limestone of Bhaislana which posses more or less homogenous texture is famous as Bhaislana black marble and takes good polish.

Petrogenesis : Calcareous sediments were originally deposited with argillaceous and other siliceous impurities. These were subjected to great tectonic disturbances involving folding and faulting. These sediments were further subjected to dynamo thermal metamorphism which on account of

9 changes in the temperature and pressure brought about mineralogical changes. Further recrystallisation by slow cooling has resulted in the formation of crystalline limestone, impure crystalline limestone, development of calcium and magnesium, silicate minerals like Tremolite, Actnolite etc.

Local Geology

Except some small warping and joints no fault fold or other geological disturbances encountered in the lease area.

Limestone of Mohanpura varies in orientation from place to place due to the folding and overturning. In Block I the deposit shows a gentle dip of 25 o to 45 o whereas in Block II and Block III the dips are sub vertical to vertical. Thus the true thickness of the limestone lies between 80- 100 m, but due to variation in dips it covers different widths in different areas. Keeping the safety zones of 100 m from the villages which overlap the mining lease and 15 m safety zone from ML boundary, the actual Mineable resources has been calculated through conventional cross –sectional area method. The resources thus calculated have been treated as “indicated resources”.

The lime stone of this area is sedimentary deposit. The impure calcareous and dolomitic sediments having impurities of silica and iron have given rise to tremolite and actinolite needles. This impure lime stone come across in Block-1 and reduce towards block-3. The white bands in grayish/ blackish marble come across in block-3. When dolomitic lime stone are reworked by hydrothermal solutions, this often given rise to coarse-crystalline mass of dolomite and this named as marble

Limestone occurs in this area under the soil cover of 0.2 meter in massive deposit. The wall rocks are not exposed. White dolomite in small layers are associated with marble and limestone. The rock occurs in this area as marble is a common rock forming mineral. Marble in this region often forms whole blocks or are inter- bedded with limestone.

Colour of limestone is Dark Grey to Light Grey gray and colour of marble of this area is black to grayish and has white bands of dolomite. Grain size varies from medium to coarse. The marble is hard in nature. Bulk density is about 2.5 Lustre is vitreous. Hardness is around 3.5 on mho’s scale.

10

Lithology

Overburden Soil Limestone Calc Silicates Dolomite (iii) Need for the project and its importance to the country and or region (iv) & Demand- Supply Gap.

The limes stone in this area is in good demand. Increase in production increases the sale which in turn develop the region and creates employment and growth of the state.

(v) Imports vs. Indigenous production.

India is self sufficient to meet the demands of the market with the GDP projected at 10 % in the coming decades and in view of the infrastructure. Facilities going across the region the growth rate of demand will increase to meet the expansion of new proposal are muted.

(vi) Export possibility

The entire production is envisaged for domestic market

(vii) Domestic/export Markets.

The entire production is envisaged for the domestic market

(viii) Employment Generation (Direct And Indirect) due to the project.

The project will create the direct employment of 50 people during the operation phase of the project. M/s National Limestone Co.Pvt.Ltd will give preference to the local peoples during operation phase of the project depending upon the skill, job requirement and capability. Several other indirect employment opportunities will be created in the surrounding areas. Transport, business, vehicle drivers and attendants, workshops, grocery and retails, medical, etc.

Adequate number of staff, officers, managers and workmen are deployed at mine to achieve the desired objective. Employment potential is as follows.

11

EMPLOYMENT POTENTIAL MANAGEMENT AND SUPERVISORY PERSONNEL

Designation Nos Qualifications . Manager 1 1st Class Manager’s Certificate of Competency Mining 1 Graduate in Mining Engineering Engineer Asst. 2 Graduate/Diploma in Mining Engineering with 1 st Manager /2 nd Class Manager’s Certificate of Competency Mines 4 Diploma in Mining Engineering or Foreman’s Foremen Certificate of Competency. Mechanical 1 Graduate/Diploma in Mechanical/Automobile Engineer Engineering Engineer 3 Diploma in Mechanical/Automobile Engineering/Electrical Engineer Mining mate 1 Holder of Mining Mate and Blaster certificate of Cum Blaster competency. Geologist 1 Post graduate degree in Geology Total 14 Vocational Training Officer (1), Vocational Training Instructor (1), Part- time Surveyor and Part-time Geologist will also be provided.

For operations of HEMM, skilled and semi skilled manpower is required. And for generic various jobs, unskilled manpower will be required. Need based calculation of skilled, semi skilled and unskilled manpower is detailed below –

Activity Skilled Unskilled Manpower Manpower Drilling 4 - Shovel 8 - Dumper 10 - General Works - 10 Electrical Staff 2 - Clerical & 1 - Administrative Staff Additional for 3 - Leave Total 28 10

3 PROJECT DESCRIPTION.

(i) Types of project including interlinked and interdependent project, if any.

The proposed project is expansion of Limestone production from 99325 tonnes to 0.80 MTPA from limestone mine.

12

M/s National Limestone Company Private Limited has renewed mining lease for Limestone and marble (under minor mineral) near village Kujota, Ajeetpura, Bhaislana over an area of 96.25 ha. vide Govt. of Rajasthan order number bearing S.No-P.7(15)Mine/Group-2/95, dated 03.05.2005. the duration of Mining lease is from 09.08.1995 to 20 years

(ii) Location (map showing general location, specific location, and project boundary & project site layout with coordinates.

The mining lease area is located at a distance of 45 Km from Dabla railway station which is on the Delhi – Udaipur main line of North Western Railway. The Neem Ka thana Railway station is located around 50 Km from the mine area on Delhi-Udaipur Railway line of North Western Railway. The area is well connected by the road network. Mining lease area is about 5 Km from NH 08 and about 13 Km from Tehsil- Kotputli which is located on National Highway no. 08.

Location map is enclosed as Annexure 2.

(iii) Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted.

The mining project is site specific project as it is related to occurrence of limestone in the mother earth. Hence no alternative sites were studied for the purpose.

(iv) Size or magnitude of operation.

Expansion of existing lime stone mine from 0.09 MTPA to 0.8 MTPA, (mining lease area of 96.25 hectares)

(v) Project description with process details (a schematic diagram/flow chart showing the project layout, components of the project etc. should be given.

The mine will be worked by Mechanized Opencast Method of working. Heavy earth moving machinery in conjunction with deep hole drilling and blasting will be utilized for the mining. The height of the bench will be kept of 8 – 10 Meter and width of the bench will be kept 15-20 Meter.

13

The blast holes of 100 - 115 mm dia will be drilled using hydraulic drills. The blast holes will be drilled in staggered pattern keeping burden of 2.5 to 3.5 Meter and spacing of 4.0 to 5.0 Meter

The blast holes will be charged with combination of ANFO and slurry explosives (booster charge). Almost 30 % of blast hole depth will be stemmed for effective blasting and to reduce noise and fly rock. The explosives will be blasted by using non – electric detonator (NONEL). This enables bottom initiation in the holes and with this technique each hole is blasted separately by providing delay in each hole. The bottom initiation and delay in each hole not only control the throw of the blast but also reduce the ground vibration and noise pollution.

The shovel dumper combination will be used for excavation of the limestone. Shovels of 1.8 m3 and 4 m3 will be deployed in combination with 40 / 50 T class dumpers/tippers. The blasted stone will be excavated using these shovels and transported using these dumpers/tippers. All the benches and roads will be sloped properly to maintain the safety of these equipments / machineries.

For removal of overburden soil, excavators with dumpers will be deployed for development. The overburden soil thus excavated will be dumped and stacked as waste dump. For scrapping of top soil dozer in combination with shovel / loader will be used.

To achieve the desired production and productivity, adequate number of staff, officers, managers and workmen (skilled and unskilled) will be deployed

The mine working will be highly mechanized. For operations like drilling, excavating and hauling, heavy earth moving machineries viz. drill machine, hydraulic excavator and dumpers will be used. Hydraulic drill machine will be used for drilling 100 - 115 mm dia blast holes. Hydraulic Excavators will be used for loading of blasted material. The dumpers of 40 / 50 tons payload will be used for transportation. Dozer will be used for levelling & compacting of overburden dump as well as face preparation and road maintenance

14

Machinery requirement for proposed enhanced production & Development

TYPE OF PROPOS CAPACITY/ MOTIVE POWER MACHINE ED SIZE UNITS 1 HYD. 4 4.0 CU.M DIESEL ENGINE SHOVEL

2 HYD. BACK 1 1.8 Cum DIESEL ENGINE HOE with Backhoe/ rock Breaker 3 DUMPER 06 40/50 T DIESEL ENGINE

4 Hydraulic 2 100 -115 MM DIESEL ENGINE Drill DIA.

5 PAYLOADER 1 3.5 CU.M. DIESEL ENGINE BUCKET 6 DOZER 1 DIESEL ENGINE

7. EXPLOSIVE 1 DIESEL ENGINE VAN 9. WATER 1 5 KL DIESEL ENGINE TANKER 10 DIESEL 1 3 KL DIESEL ENGINE TANKER 11 MOBILE 1 DIESEL ENGINE SERVICE VAN 12 Pickup Van 1 DIESEL ENGINE

(vi) Raw material required along with estimated quantity, likely source, marketing area of final products/s, mode of transport of raw material and finished product.

The major raw material required for the mine will be explosives for blasting. ANFO with Cast Booster/ Cartridge Slurry or Emulsion Explosive is to be used. Column charge is ANFO consisting 5% fuel oil mixed with prilled ammonium nitrate. Booster explosive is available in 2.78 kg cartridges. Nonel tubes and electric detonators are other explosive materials that are required for blasting.

It is proposed to outsource the blasting activity with our supervision to licensed vendor. It is proposed to establish an explosives magazine of following capacity –

15

SL. EXPLOSIVES CLASS DIV. MAGAZINE NO CAPACITY 1. NITRATE MIXTURE 2 - 5000 KG 2. NITRO COMPOUND 3 2 1000 KG 3. DETONATOR 6 1 2000 Nos 4. DETONATING FUSE 6 2 10000 Mtrs

(vii) Resources optimization/ recycling and reuse envisaged in the project, if any, should be brief outlined.

The total mining lease area comprises of dark grey limestone, light grey limestone, dolomitic limestone and overburden soil. Initially mining operations will be started in the Block-II of mining lease area. Overburden will be stacked separately. As the pit is already opened a very little soil is available which will be directly used for plantation purpose.

on of the Green belt along the mines/lease boundary. And sooner mines is matured enough for reclaimation , the mining benches of worked out portion of the pit will be levelled by overburden & top soil will be spread over before doing plantation over it for reclaimation. and balance area will be converted into water reservoir.

(viii) Availability of water its sources, Energy /power requirement and sources should be given,

Water

Water requirement during operation of the mine and plantation purpose will be 5.0 KLD/day. During construction activities the water requirement will be 10.0 KLD/day. This requirement will be sourced from the reservoirs developed in the mining lease area. For domestic purpose the requirement of water will be 1.0KLD will be sourced from outside.

Power

Power will be required for office lighting only & for this, single Phase supply is already provided by State Electricity Board. (Phase-Neutral 230V AC). Electricity consumption will be 5KW. For general lighting in the mines & pumping 5-7.5 KVA DG sets will be utilized.

16

(ix) Quantity of wastes to generated (liquid and solid) and scheme for their management/disposal.)

Some parts of the mineable part of the deposit area is covered under an overburden soil bed varying in thickness from 0 to maximum 1.0 m and the pits are also already opened. As the pit is already developed and there is very less quantity is of top soil will be available, it will be used directly for plantation purpose. The overburden will be stacked separately in the southern side of the pit. For the initial five years, dumping will be carried out in this area.

And once the ultimate depth of the limestone in the deposit will be established and sooner the mine will be matured, backfilling will be started in the mined out area.

The quantum of overburden waste generation in first five years is tabulated below –

Development Year (Tonnes). 1st YEAR 108270 2nd YEAR 345060 3rd YEAR 261150 4th YEAR 198150 5th YEAR 392970

(x) Schematic representations of the feasibility which give information of EIA purpose.

Detailed schematic representations of the feasibility covering the purpose of EIA will be given in the Environmental Impact Assessment report

4 SITE ANALYSIS

(i) Connectivity.

The deposit is accessible at a distance of 5 kms from Gordhapura Chowki located in National Highway No 08. Gordhanpura Chowki is at a distance of 112 kms from the district head quarters Jaipur on Jaipur –Delhi National highway No 08

17

The mining lease area is located at a distance of 45 Km from Dabla railway station which is on the Delhi – Udaipur main line of North Western Railway. The area is well connected by the road network. Mining lease area is about 4 Km from NH 08 and about 13 Km from Tehsil- Kotputli which is located on National Highway no. 08.

The nearest airport is Jaipur located about 120 kms

(ii) Land form, land use and land ownership.

M/s National Limestone Company Private Limited having a lease area of 96.25 Ha in the villages of Kujota, Ajeetpura, Bhaislana Tehsil Kotputli, District: Jaipur, Rajasthan State.

The land details is as follows Government Land 45 Hectares Lessse’s own land 4.00 Hectares Private Land 47.25 Hectares Total land 96.25 Hectares

There is no forest land in the mining lease area.

(iii) Topography (along with map)

The area exhibits flat topography and gentle to moderately steep slopes towards Northern and western flanks. Ajeetpura village in the Western part is situated at a higher elevation as compared to eastern part of the area

(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under CRZ)), shortest distances from the periphery fo the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance form the HFL of the river), CRZ. In case of notified industrial area, a copy of the Gazette notification should be given)

The Mining lease area site does not falls under the CRZ area or notified industrial area. Gadrata Protected Forest (6 km in NW direction), Hasampur Protected Forest (8 km in N direction), Ramsinghpura Protected Forest (9 km in NE direction), Dantil Protected Forest (8 km in W direction), Buchara P. F (10 km in SW direction)

18

(v) Existing infrastructure.

The nearest airport is Jaipur which is 120 Km from the mine area.

Dabla Railway station is 45 Km from the mine area on New Delhi-Udaipur Railway line on North west railway. Neem Ka Thana Railway station is about 50KM from the mine area on New Delhi-udaipur Line.also on North West Railway.

The area is well connected by the road network. Mining lease area is about 5 Km from NH 08 and about 13 Km from Tehsil Head quarters Kotputli located on National Highway no. 08.

Communication facilities such as telephone, tele-fax and Internet are available near the Mining lease area.

(vi) Soil classification

TEXTURE SANDY Loom PH 7.9 CONDUCTIVITY 185 SULPHITE as SO4(ppm) 2.2 CHLORIDE as CI(ppm) 5.4 CARBONATE as NA(ppm) 19.4 POTASSIUM as K(ppm) 3.1 ORGANIC MATTER(%) 0.71 PERCOLATION & 4.9 INFILTERATION RATE(ML/min

(vii) Climatic data form the secondary sources.

Climate of the area is semi arid zone type. The maximum and minimum temperatures of the region in summer (April-June ) are 43 0C to 27 0C and June is the hottest moth where temperature reaches 49 0C respectively. May and June are the hottest months. Dry winds come across during day hours in the may while sandy winds come across during evening hours. Monsoon starts in the end of June and remains upto end of September. The temperature during this season is 42 0C to 33 0C Cold weather season starts from November and last up to February and march. December and January are the coldest months. Some retreating monsoon also come across during cold weather season due to western disturbances The temperature during winter is 17 0C to 5 0C. The rainfall remains between Min. 33.6mm to Max.407.4mm (June to September for the period 2008- 2012). Predominant wind direction is northwest to southeast. Average rain fall for the last five years is about 559.18 (IMD-Jaipur report for the year2008- 2012 and for the period June-September)

19

Average Climatological Data – IMD jaipur ( Year-2008 -2012) reveals that Maximum temperature :48º Minimum temperature :05º

Relative Humidity (%): 27%-85% Average Monthly Rainfall (mm):139.79(June-September for the year 2008 to 2012)

(viii) Social Infrastructure available.

All infrastructure facilities such as education, health facilities and other social facilities are sufficient at the tehsil head quarters kotputli. Kotputli make the region sufficient in amenities.

(i) Planning Concept (types of industries, facilities, transportation etc) and Country planning/Development authority Classification

The expansion of the limestone mine from 99325 tonnes to 0.8MTPA will increase the employment of the local villagers and nearby people. During construction activities an indirect employment of atleast 50 people will get benefited. During operation of the mine atleast 50 people will get direct employment and around 200 people will be envisaged for indirect employment .

(ii) Population projection

The establishment of the mine would aid in the overall social and economic development of the region. The mine will give direct employment to about 50 people, in addition there will be indirect employment to many more people in the form of out sourcing jobs, business opportunities, service facilities etc. This will enhance the economic status of the local region.

(iii) Land use planning (breakup along with green belt etc)

The Mining Lease of 96.25 Ha is located in the villages of Kujota, ajeetpura, Bhaislanan , Tehsil: Kotputli , district-Jaipur of Rajasthan State.

(iv) Assessment of Infrastructure Demand (physical & social).

20

Adequate physical and social facilities are available in this area.

(v) Amenities/ Facilities.

All infrastructure facilities such as education, health facilities and other social facilities are adequate at Tehsil headquarter kotputli which is 13 Km from the mine area makes the region adequate in amenities

6 PROPOSED INFRASTRUCTURE

(i) Industrial Area (Processing Area).

Infrastructures are required for mining activates with allied facilities.

(ii) Residential Area ( Non Processing Area)

As the mine area is close to gordhanpura chowki and tehsil head quarters kotputli residential problem will not envisaged.

(iii) Green belt.

The overburden will be stacked separately in the south side of the working pit. On these overburden dumps, Afforestation will be done all along the periphery for development of green belt. There is enough space in the present reject yard to accommodate the reject/waste rock generated over the years. Back filling is also envisaged in the worked out pits. when part of the mines in Western boundary is matured for reclamation. Afforestation will be developed on the back filled worked out areas.

(iv) Social Infrastructure.

National Limestone Company Private Limited will carryout social development and welfare measures in the surrounding villages. Under CSR activity the company will initiate community development projects, in the fields of health, education and environmental preservation, in the study area around the Mine.

(v) Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)

The nearest airport is Jaipur which is 120 Km from the mine area.

21

Dabla Railway station is 45 Km from the mine area on New Delhi-Udaipur Railway line on North west railway. Neem Ka Thana Railway station is about 50KM from the mine area on New Delhi-udaipur Line.also on North West Railway.

The area is well connected by the road network. Mining lease area is about 5 Km from NH 08 and about 13 Km from Tehsil Head quarters Kotputli, and 120 Km from district head quarter Jaipur located on National Highway no. 08 on Jaipur-Delhi Highway No-08.

(vii ) Sewerage system.

The production of limestone will be based on Dumper-Shovel combination, hence no waste water will be generated from the Mine.

(viii) Industrial waste management.

Some parts of the mineable part of the deposit area is covered under an overburden soil bed varying in thickness from 0 to maximum 1.0 m and the pits are also already opened. The top soil which will be generated in the initial stages will be very less as the pits are already opened. The top soil will be either used directly for plantation purpose or will be stacked separately. The overburden will be stacked separately in the southern side of the working pit. For the initial five years, dumping will be carried out in this area.

(ix) Solid waste management

Same as above

(x) Power Requirement & Supply / Source.

Power will be required for office lighting only & for this, single Phase supply is already provided by State Electricity Board has been in use (Phase-Neutral 230V AC). Electricity consumption will be about 5KW. For general lighting of mines & any other requirement 5KVA DG sets will be utilized.

It is also envisaged that the power requirement during construction of infrastructures phase shall be met by grid / installing DG set

22

7. REHABILITATION AND RESETTLEMENT (R & R) PLAN.

(i) Policy to be adopted (Central/ State) in respect of the project affected persons including home oustees, land oustees and landless laborers (a brief outline to be given).

The R&R policy will be adopted as per the guidelines of Central/State policy if applicable

8. PROJECT SCHEDULE & COST ESTIMATES

(i) Likely date of start of construction and likely date of completion (time schedule for the project to be given).

The expansion of the mine will be executed by the company from its own source and will be executed within 24 months from the starting date i.e. from the date of receiving all the statutory clearances for starting the project.

(ii) Estimated project cost along with analysis in terms of economic viability of the project.

unit S No Particulars Units cost Lac RS 1 Excavators (4 m3) 4 150 600 2 Drill Machine LM 100 equvalent 2 20 40 3 Compressor IR 450 cfm 2 20 40 4 Dumpers BH50 equvalent 6 200 1200 5 Explosive van & Licencing 1 25 25 6 Fuel bouser & licencing 2.5 KL 1 20 20 7 Pay loader Hind 2022 1 35 35 Anciallary equipments /jeep/Mobile DG welding/ Gas 8 curtting set etc 1 30 30 9 Dozer 1 40 40 10 Maintenanace Van 1 18 18 Civil work weigh bridge & lab Ofiice 11 etc. 1 70 70 12 Private land aqusition 37 20 740 13 Pakka & Kacha House rehabilitation 600 9 5400 14 Pumping with line laying 2 6 12 15 Magazine construction & Licencing 1 12 12 Total 8282

23

The limestone is a main raw material for manufacturing of cement. The project cost calculated above will be invested in a phase manner balancing with the realization from sale of mineral in the local market.

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS).

(i) Financial and social benefits with special emphasis on the benefit to the local people including tribal population, if any in the area.

Based on the growing demand in the state of Rajasthan and Jaipur over the next 10 years, the proximity of the mine location to this market is an advantage with respect reduction in freight of limestone to these markets.

Employment: Preference will be given for locals for employment based on qualifications & requirement

24

Annexure – I Letter of National Limestone Mining Lease

25

26

27

28

29

30

31

32

33

34

35

36

37

38

Annexure – II Location map of the project site