48283 Revised on 28/04/2008 WATER & WASTEWATER PROJECT CREDIT 4038-AM PROCUREMENT PLAN

YWWP - Procurement plan Year 1,2,3 YWWP Procurement Identification Bidding Document Bidding Process Bid Evaluation Contract Implementation Investmen t Plan Description Prior / Draft Document Review/Approval Invitation Bid opening Bid Evaluation Review/Approval Contract signing Initial Contract Completion Initial Contract Expenditu Proc. Post Supplier/ Contract Type Contract No Price in original re Method Planned Planned Actual- Contractor Price Contract name Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual-WB Planned Actualcurrency Planned Actual Category original Revised PMB (USD) A - Energy saving Sensus Metering A1 Purchase of 29 borehole meters and ancillaries G YWWP/BHMeters/07 Shopping Post 07/12/06 22/12/06 12/12/06 N/A 12/12/06 29/01/07 23/01/07 01/03/07 29/01/07 27/04/07 06/02/07 27/04/07 N/A 28/02/07 18/05/07 20,163.96 € 15,263 30/06/07 03/08/07 System(Slovakia) Public Disclosure Authorized Disclosure Authorized Public Public Purchase of 4 sets borehole pumps and A1 G YWWP/BoreholePumps/005 Shopping Prior 24/11/06 07/12/06 27/11/06 20/12/06 27/11/06 26/12/06 08/01/07 07/02/07 18/01/07 23/02/07 29/01/07 04/05/07 N/A 13/02/07 05/11/07 GRUNDFOS(Austria) 62,466.25 € 48,217.54 15/06/07 16/08/07 ancillaries

A2 Purchase of 5 new pumps at GarniPS G YWWP/GarniPumps/12 ICB Prior 26/11/07 14/11/07 12/12/07 05/12/07 20/12/07 14/12/07 12/02/08 05/02/08 20/03/08 28/03/08 09/04/08 16/04/08 N/A 29/04/08 30/05/08 Farmex(France) 141,153.18 € 95,188.00 27/08/08

A2 Purchase of 10 new valves at GarniPS G YWWP/GarniValves/14 Shopping Post 15/12/07 30/01/08 25/12/08 N/A 15/01/08 08/02/08 14/02/08 11/03/08 10/03/08 17/06/08 29/02/08 N/A N/A 10/03/08 08/07/08 Magga() 38,273.94 AMD 11,822,820 08/06/08 20/11/09

A4 Purchase of 913 valves for distribution system G YWWP/Valves/01 ICB Prior 12/10/06 31/10/06 27/10/06 20/12/06 31/10/06 25/12/06 18/12/06 09/03/07 15/01/07 16/05/07 26/01/07 25/05/07 06/06/08 20/02/07 02/07/07 Ronberg Gruppe (USA) 184,834.92 USD 184,834.92 22/06/07 29/12/07

Purchase of 4,200 m pipes for distribution A4 G YWWP/Pipes/03 ICB Prior 12/10/06 31/10/06 27/10/06 20/12/06 31/10/06 25/12/06 18/12/06 02/03/07 15/01/07 30/03/07 26/01/07 23/05/07 06/06/08 20/02/07 02/07/07 Fuchs Rohr (Germany) 335,233.68 € 253,487.49 22/06/07 08/04/08 system - LOT 2

Purchase of 16.8 km steel pipes for distribution Salsgitter A4 G YWWP/SteelPipes/15 ICB Prior 15/12/07 15/07/08 17/07/08 04/08/08 21/08/08 14/08/08 18/08/08 25/09/08 07/09/08 25/10/08 16/10/08 14/11/08 01/12/08 09/12/08 04/12/08 21/01/09 774,722.18 € 571,329.04 02/06/09 system Mannesman(Germany)

8/29/08 A4 Purchase of PE pipes and fittings G YWWP/PEPipes/16 Shopping Prior 20/07/08 31/07/08 27/07/08 N/A 29/07/08 31/07/08 19/08/08 28/09/08 03/10/08 08/10/08 26/10/2008 N/A 17/11/08 14/11/08 Farmex(France) 46,757.40 € 32,851.00 15/02/09 19/09/08 €41218.56 and A4 Purchase of 461 valves for distribution system G YWWP/Valves/08 ICB Prior 11/04/07 22/01/07 27/04/07 07/02/07 30/04/07 13/02/07 18/06/07 10/04/07 10/07/07 16/07/07 06/08/07 29/09/07 N/A 31/08/07 01/11/07 Ronberg Gruppe (USA) 153,552.00 31/12/07 06/03/08 USD98443.38 SPTCO&SGAIC JV

A4 Disclosure Authorized Disclosure Authorized Public Public Purchase of flowmeters for distribution system G YWWP/FlowMeters/10 ICB Prior 10/12/06 02/02/07 26/12/06 09/03/07 29/12/06 23.03.2007 15/02/07 04/05/07 05/03/07 10/07/07 30/03/07 30/07/07 N/A 02/05/07 31/08/07 159,681.00 USD 159,681.00 31/08/07 12/03/08 (China)

A1 Installation of 29 borehole meters W YWWP/BHMetersWks/13 Shopping Post 31/10/07 05/11/07 02/11/07 N/A 05/11/07 05/11/07 27/11/07 28/12/07 10/12/07 04/12/07 15/12/07 N/A N/A 25/12/07 24/12/07 GOARSHIN (Armenia) 15,167.68 AMD 4,618,560 25/02/08 5307/2008

A1 Supply of 4 units transformers G YWWP/BoreholePumpsWks/11Shopping Post 15/11/07 24/09/07 20/11/07 20/11/07 24/11/07 20/11/27 21/12/07 05/12/07 21/01/08 15/01/08 25/01/08 N/A N/A 15/02/08 01/02/08 Shaks Gruppe(Armenia) 14,272.81 AMD 4,373,760 25/06/08 22/02/08

Gyumush Pumping Station rehabilitation with A1 W YWWP/GyumoushWorks/ NCB Post * 30/10/08 07/11/08 17/11/08 19/12/08 15/01/09 02/02/09 N/A 10/02/09 10/07/09 installation of pumps and springbox Pumping Station rehabilitation with Univerasl Ltd A2 W YWWP/GarniWks/21 Shopping Post 03/01/08 02/01/09 20/01/09 09/01/09 N/A 14/01/09 20/01/09 11/02/09 18/02/09 26/02/09 26/02/09 06/03/09 N/A N/A 20/03/09 12/03/09 94,998 AMD 28,999,160 18/06/09 installation of pumps and valves (Armenia)

Qanaqer 2nd street pipeline - reconstruction of Shinashkhar LTD A3 W YWWP/QanaqerTS/07 Shopping Post 08.12.07 08/06/07 26/06/2007 N/A 03/07/07 08/06/07 31/07/07 29/06/07 14/08/07 10/07/07 28/08/07 N/A N/A 04/09/07 19/07/07 96,273.85 AMD 32,824,569 10/01/08 30/08/08 from Tsaravaghbjur street to Sarkavag street (Armenia)

Qanaqer-Tsaravaghbjur street - Reconstruction Ecolakt/Astgik JV A3 of pipelines from the 2nd street to Sarkavag W YWWWP/Qanaqer2ndS/08 Shopping Post 06.12.07 08/06/07 26/06/07 N/A 03/07/07 08/06/07 31/07/07 29/06/07 14/08/07 10/07/07 28/08/07 N/A N/A 04/09/07 23/07/07 92,976.19 AMD 31,700,232 10/01/08 31/05/08 (Armenia) street A4 Improvement of Sari Tagh water supply system W YWWP/SariTagh/04 Shopping Post 3/12/07 20/04/07 15/03/07 N/A 15/03/07 10/05/07 05/04/07 31/05/07 16/04/08 12/06/07 26/04/08 N/A N/A 02/05/07 28/06/07 Erknaqer Ltd (Armenia) 96,082.87 AMD 33,424,349 31/10/08 07/11/08

Norq Marash water distribution system Blesk Aremenian A4 W YWWP/Marash/02 NCB Prior 21/06/07 17/07/07 05/07/07 30/07/07 07/07/07 02/08/07 03/08/07 14/09/07 17/08/07 09/11/07 27/08/07 26/11/07 26/11/07 05/09/07 10/12/07 276,636.46 AMD 94,371,761 10/02/08 30/11/08 Public Disclosure Authorized Disclosure Authorized Public Public rehabilitation Branch (Armenia) Reconstruction of pipelines at Fanarjyan, 16th Shinashkhar Ltd A4 W YWWP/Fanarjyan/09 Shopping Post 14/06/07 08/06/07 N/A N/A 14/06/07 08/06/07 05/07/07 29/06/07 19/07/07 10/07/07 N/A N/A N/A 26/07/07 19/07/07 99,197.88 AMD 33,821,517 27/11/07 30/09/08 and 17th streets (Armenia) Zeytun –reconstruction of pipeline at Vahe Vahyan, Qanaqer 14th and 1st streets and A4 W YWWP/Zeytun/01 NCB Prior 12/06/07 15/06/07 26/06/07 09/07/07 03/07/07 18/07/07 31/07/07 16/08/07 14/08/07 10/09/07 28/08/07 19/09/07 N/A 04/09/07 27/09/07 Jilyo P/Co (Armenia) 95,599.51 AMD 32,185,488 10/01/08 30/07/08 rehabilitation of pipeline and sewer at Meliqyan street Bypassing of Dinamo DRR pipeline and A4 W YWWP/DinamoArzni/14 Shopping Post 23/11/07 23/11/07 N/A N/A 11/23/07 23/11/07 10/01/08 21/12/07 08/01/08 15/01/08 N/A N/A N/A 25/01/08 25/01/08 Jilyo P/Co (Armenia) 39,164.70 AMD 13,325,005 30/03/08 10/10/08 installation of the PRVs on main”

Nor bypass -construction of gravity pipeline from DRWR and A4 W YWWP/NorJrvezhWks/ NCB Post 15/05/08 01/12/08 02/02/09 11/12/08 N/A 16/12/08 03/02/09 25/01/09 04/03/09 14/02/09 24/03/09 01/03/09 N/A 11/03/09 07/09/09 connection to the booster pumping station for Mayak upper areas Civil works for sectorisation I phase- W YWWP/SectorWorksNorthern/ NCB Prior 15/04/09 29/04/09 06/05/09 03/06/09 17/06/09 01/07/09 11/07/09 18/11/2009 Sectorisation of Northern district (Lots) Civil works for sectorisation I phase- W YWWP/SectorWorksErebuni/1 NCB Post 30/04/09 14/05/09 21/05/09 18/06/09 02/07/09 16/07/09 26/07/09 03/12/2009 Sectorisation of Erebuni district (Lots) A4 Civil works for sectorisation I phase- W YWWP/SectorWorksArabkir Z NCB Post 10/05/09 17/05/09 24/05/09 21/06/09 05/07/09 19/07/09 29/07/09 04/02/2010 Sectorisation of Arabkir -Zeitun districts (Lots)

Public Disclosure Authorized Disclosure Authorized Public Public Civil works for sectorisation I phase- W YWWP/SectorWorksAjapnjak/ NCB Post 10/05/09 17/05/09 24/05/09 21/06/09 05/07/09 19/07/09 29/07/09 04/02/2010 Sectorisation of Ajapnyak districts (Lots) Civil works for sectorisation -II phase W YWWP/SectorWorksKentron/1 NCB Post 10/06/09 17/06/09 24/06/09 22/07/09 05/08/09 19/08/09 29/08/09 05/02/2010 Sectorisation of Kentron districts (Lots) Civil works for sectorisation -II phase A4 W YWWP/SectorWorksArevmutq NCB Post 25/06/09 02/07/09 09/07/09 06/08/09 20/08/09 03/09/09 13/09/09 21/01/2010 Sectorisation of Arevmutq districts (Lots) Civil works for sectorisation -II phase W YWWP/SectorWorksShengavit NCB Post 10/07/09 17/07/09 24/07/09 21/08/09 04/09/09 18/09/09 28/09/09 16/04/2010 Sectorisation of Shengavit districts Mapping Arzni source captations, mains, Elektrolamper and Davtashen Nerqin DWRs’ A1 Cs YWWP/ArzniStudyTop/04 CQS Post 26/11/07 29/11/07 03/12/07 N/A 03/12/07 N/A 24/12/07 08/04/08 14/01/08 17/06/08 30/01/08 N/A N/A 10/02/08 30/06/08 HGSN(Armenia) 12,719.52 AMD 3,808,000 25/09/08 30/06/08 sanitary zones of Arzni-Yerevan water supply system A3 Investigation & definition of W - Southern Cs YWWP/SouthernSectorisation/ CQS Post 26/11/07 01/12/07 05/12/08 N/A 14/12/07 27/02/08 21/01/08 08/04/08 10/02/08 26/05/08 15/02/08 N/A N/A 29/02/08 11/06/08 Jinj (Armenia) 71,149.18 AMD 21,700,500 30/10/08 A3 Investigation & definition of W - Western Cs YWWP/WesternSectorisation/0 CQS Post 31/12/07 25/12/07 10/01/08 N/A 14/01/08 27/02/08 11/02/08 08/04/08 25/02/08 26/05/08 17/03/08 N/A N/A 05/04/08 11/06/08 Jinj (Armenia) 61,078.69 AMD 18,629,000 25/12/08 Investigation & definition of Yerevan and YWWP/YerevanVillageSectori A3 Cs QCBS Prior 31/03/09 09/06/09 19/06/09 29/07/09 17/09/09 07/10/09 20/10/09 20/10/10 villages sation/ B - Improved reliability B1 Purchase of 100 air valves G YWWP/AirValves/03 ICB Prior 29/08/07 29/08/07 09/10/07 09/10/07 17/10/07 17/10/07 30/10/07 30/10/07 30/11/07 30/11/07 15/12/07 26/11/07 N/A 23/12/07 21/12/07 Tecofi (France) 40,406.84 € 28,078.00 30/03/08 30/07/08

Proc_Plan_eng-arm 21.04 2009 WB pdf Revised on 28/04/2008

YWWP Procurement Identification Bidding Document Bidding Process Bid Evaluation Contract Implementation Investmen t Plan Description Prior / Draft Document Review/Approval Invitation Bid opening Bid Evaluation Review/Approval Contract signing Initial Contract Completion Initial Contract Expenditu Proc. Post Supplier/ Contract Type Contract No Price in original re Method Planned Planned Actual- Contractor Price Contract name Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual-WB Planned Actualcurrency Planned Actual Category original Revised PMB (USD) B1 Purchase of 50 large valves G YWWP/LargeValves/09 ICB Prior 12/19/06 22/01/07 26/12/06 07/02/07 07/01/07 13/02/07 23/02/07 03/04/07 16/03/07 07/06/07 06/04/07 30.07.07 10/05/07 28/08/07 Belgicast (Spain) 259,709.26 € 194,307.79 10/10/07 16/04/08 B1 Fabrication of 68 steel tapers G YWWP/SteelTapers/ Shopping Post 15/03/08 15/12/08 30/12/08 06/01/09 03/02/09 05/03/09 19/03/09 N/A N/A 18/04/09 16/08/09 B3 Purchase of 13 level meters G YWWP/LevelMeters/006 Shopping Prior 04/01/07 07/12/06 12/01/07 19/01/07 12/01/07 29/01/07 23/02/07 21/03/07 16/03/07 31/05/07 06/04/07 03/07/07 N/A 30/03/07 29/12/07 ENIP(Germany) 25,541.72 € 19,210.00 31/07/07 20/05/08 Purchase of 5,020 m pipes for Miasnikyan B4 G YWWP/MiasnikyanPipes/07 ICB Prior 09/02/07 22/01/07 20/02/07 05/02/07 28/02/07 12/02/06 17/04/07 06/04/07 30/04/08 26/04/07 30/05/08 25/05/07 06/06/07 02/07/07 07/08/07 Saint Gobain (France) 621,539.17 € 464,771.09 31/12/07 18/07/08 pipeline Hydromashservise B6 Purchase of 100 booster pumps G YWWP/BoosterPumps/04 ICB Prior 10/12/06 31/10/06 24/10/06 20/12/06 31/10/06 25/12/06 18/12/06 27/02/07 15/01/07 12/04/07 26/01/07 23/05/07 06/06/07 20/02/07 25/06/07 616,865.27 € 468,742.24 22/06/07 30/05/08 (Russia) Feljas&Masson B6 Purchase of 100 booster pumps G YWWP/BoosterPumps/13 ICB Prior 30/11/07 11/23/07 10/12/07 10/12/07 17/12/07 16.01.2008 08/02/08 29/02/08 09/03/08 21/04/08 25/03/08 13/06/08 15/04/08 12/08/08 517,770.11 € 329,789.88 13/08/08 (France) Universal Ltd B2 W YWWP/VillagePSWks/14 Shopping Post 31/10/07 05/11/07 02/11/07 N/A 05/11/07 05/11/07 27/11/07 28/12/07 10/12/07 04/12/07 15/12/07 N/A N/A 25/12/07 12/12/07 37,700.58 AMD 11,482,090 23/04/08 30/05/08 Pumping station W, pumps , fitting, contol panel (Armenia) installation YWWP/VillagePSWks/19 Universal Ltd B2 W Shopping Post 03/03/08 12/07/08 29/04/08 17/07/08 N/A 22/07/08 29/04/08 19/08/08 29/05/08 09/09/08 29/07/08 19/09/08 N/A N/A 04/10/08 14/08/08 23,255.21 AMD 6,998,655 02/01/09 Zovuni, (Armenia) Rehabilitation and reconstruction of Garni B2 W YWWP/GarniVillageWks/ NCB Post 01/04/08 ** 10/04/08 14/04/08 12/05/08 26/05/08 10/06/08 N/A N/A 20/06/08 20/10/08 village water supply system Universal Ltd B2 Eghvardt City W W YWWP/EghvardtWks/03 NCB Post 05/01/08 09/04/08 12/05/08 N/A 12/05/08 24/04/08 09/06/08 23/05/08 25/06/08 29/07/08 07/07/08 N/A N/A 21/07/08 14/08/08 119,596.94 AMD 35,992,700 31.02.2009 24/12/08 (Armenia) Universal Ltd B2 City and Nar-Dos streets W YWWP/EghvardtWks/06 NCB Post 20/07/07 20/07/07 20/07/07 N/A 25/07/07 26/07/07 24/08/07 24/08/07 20/09/07 05/10/07 25/09/07 N/A N/A 01/10/07 12/10/07 23,690.81 AMD 7,988,068 10/01/08 29/02/08 (Armenia) B2 Village netW multiple contracts W YWWP/Zovuni/15 Shopping Post 26/11/07 23/11/07 04/12/07 N/A 07/12/07 23/11/07 27/12/07 21/12/07 21/01/08 18/01/08 25/01/08 N/A N/A 15/02/08 29/02/08 GranitLtd (Armenia) 50,237.45 AMD 15,254,100 15/02/09 7/07/2008 B2 Village netW multiple contracts W YWWP/Qasakh/20 Shopping Post 03/01/08 22/05/08 22/05/08 27/05/08 N/A 02/06/08 03/06/08 02/07/08 20/06/08 17/07/08 26/06/08 22/07/08 N/A N/A 01/08/08 09/07/08 Granit Ltd (Armenia) 40,449.38 AMD 12,214,500 30/10/08 4/11/2008 B2 Village netW multiple contracts W YWWP/Erznka/18 Shopping Post 04/01/08 09/04/08 10/04/08 N/A 12/04/08 29/04/08 08/05/08 29/05/08 29/05/08 29/07/08 06/06/08 N/A N/A 20/06/08 01/08/08 Granit Ltd (Armenia) 75,029.88 AMD 22,580,241 20/06/09 25/12/08 B2 Kharberd Graveyard bypass W YWWP/KharberdGrave/02 Shopping Prior 09/01/07 20/04/07 15/01/07 27/04/07 15/01/07 08/05/07 05/02/07 29/05/07 09/02/07 12/06/07 15/02/07 16/06/07 N/A 26/02/07 28/06/07 Jilyo P/Co (Armenia) 29,280.61 AMD 10,218,054 28/10/07 24/09/2007 Univarsal Ltd B2 Eghvardt Yerevan Line W YWWP/EghvardtWks/05 Shopping Post 09/01/07 20/04/07 15/01/07 N/A 15/01/07 10/05/07 05/02/07 31/05/07 09/02/07 12/06/07 15/02/07 N/A N/A 26/02/07 28/06/07 43,026.07 AMD 14,967,480 28/10/07 20/12/07 (Armenia) B2 Aramous Network W YWWP/AramousNet/03 Shopping Post 03/01/07 20/04/07 10/01/07 N/A 10/01/07 08/05/07 31/01/07 29/05/07 09/02/07 12/06/07 16/02/07 N/A N/A 26/02/07 28/06/07 Granit Ltd (Armenia) 99,239.10 AMD 34,631,468 28/10/07 29/11/2007 Yerevan jrshin B2 Aramous Feeder Line W YWWP/AramousFeed/04 NCB Post 03/01/07 20/07/07 10/01/07 N/A 10/01/07 21/07/07 31/01/07 21/08/07 09/02/07 05/10/07 16/02/07 N/A N/A 26/02/07 12/10/07 115,036 AMD 38,759,092 28/10/07 21/07/2008 (Armenia) B2 Jrashen Network W YWWP/JrashenNet/06 Shopping Post 09/01/07 20/04/07 15/01/07 N/A 15/01/07 10/05/07 05/02/07 31/05/07 09/02/07 12/06/07 15/02/07 N/A N/A 26/02/07 27/06/07 Gavat Ltd (Armenia) 63,648.33 AMD 22,141,344 28/10/07 30/07/08 B3 Reservoir rehabilitation W YWWP/ReservRehabWks/ ICB Prior 28/02/08 01/04/09 11/05/09 18/05/09 17/07/09 31/08/09 20/09/09 10/10/09 28/02/11 B4 Installation of pipes for Miasnikyan W YWWP/MiasnikyanWks/ ICB Prior 01/04/08 01/03/09 31/03/09 31/03/09 07/04/09 19/05/09 03/07/09 23/07/09 12/08/09 19/04/10 "Yerjrmughkoyughshin" B6 Installation of 25 booster pumps W YWWP/Booster pumps/17 Shopping Prior 30.11.07 30.11.07 5.12.07 N/A 5.12.07 7.12.07 26.12.07 15.1.08 22.1.08 29.1.08 25.1.09 N/A N/A 11/02/08 29/02/08 23,958.28 AMD 7,390,410 05/06/09 20/10/08 LTD (Armenia) B6 Installation of 150 booster pumps W YWWP/Booster pumpsInstall/0 ICB Prior 30/10/08 10/01/09 16/02/09 24/02/09 03/04/09 03/03/09 09/04/09 14/04/09 14/05/09 11/06/09 01/07/09 01/07/10 Soil stabilization study and pipeline diagnostic B1 Cs YWWP/ArzniSD/ QCBS Prior 30/10/08 30/01/09 21/03/09 23/03/09 04/05/09 13/06/09 03/07/09 23/07/09 19/01/10 Arzni B1 Study of water sources operation resources Cs YWWP/SourcesStudy/ QCBS Prior 28/12/08 16/02/09 18/02/09 01/04/09 11/05/09 31/05/09 20/06/09 17/12/09

Haygyughshinnakhagits B2 Study of Garni and Eghvardt pipe systems Cs YWWP/GarniEghvardtStudy/0 CQS Post 10/9/06 24/11/06 12/10/06 N/A 13/10/06 25/11/06 20/12/06 05/12/06 28/12/06 26/12/06 15/01/07 26/12/06 24/01/07 16/03/06 51,801.86 AMD 18,615,000 03/05/07 22/06/2007 Ltd (Armenia) C - Environmental C Supply of 2 pump sets Verin Charba G YWWP/VCharbaGoods/ Shopping Post * Construction of pumping station and 500m C W YWWP/VShengavitWks/ Shopping Post * pipeline for Verin Shengavit Reconstruction of sewerage splitting chamber at "Yerjrmughkoyughshin" C W YWWP/KievyanWks/12 Shopping Post 16/04/07 19/11/07 19/04/07 N/A 19/04/07 19/11/07 10/05/07 18/12/07 14/05/07 28/12/07 22/05/07 N/A N/A 31/05/07 25/01/08 47,974 AMD 14,553,409 30/11/07 10/10/2008 Kievyan Bridge LTD(Armenia) Construction of 2,500m of sewers adjacent to "Yerjrmughkoyughshin" C W YWWP/MiasnikyanSewers/10 Shopping Post 06/04/07 24/06/07 13/04/07 N/A 13/04/07 25/06/07 04/05/07 17/07/07 11/05/07 25/07/07 21/05/07 N/A N/A 31/05/07 06/08/07 38,205.74 AMD 12,920,799 30/11/07 25/12/07 Miasnikyan Street LTD(Armenia) Reconstruction of 2,000m of sewers adjacent "Yerjrmughkoyughshin" C W YWWP/BiochimiqueSewer/11 Shopping Post 06/04/07 19/11/07 13/04/07 N/A 13/04/07 19/11/07 04/05/07 18/12/07 11/05/07 12/01/08 21/05/07 N/A N/A 31/05/07 25/01/08 75,239 AMD 22,824,642 30/11/07 20/08/08 Biochemique LTD(Armenia) "Yerjrmughkoyughshin" C Reconstruction of Galshoyan Street sewer W YWWP/GalshoyanSewer/01 Shopping Prior 16.04.2007 20/04/07 19/04/07 27/04/07 19/04/07 08/05/07 10/05/07 29/05/07 14/05/07 12/06/07 22/05/07 16/06/2007 N/A 31/05/07 29/06/07 67,709.85 AMD 23,628,708 30/09/07 14/12/2007 LTD(Armenia)

Gareguin Njdehh street - Reconstruction of the mahnole and installation of valves and YWWP/GareguinMetroWksPh C Metro/ -Construction of sewer with W Shopping Post 01/04/08 10/02/09 29/01/02 24/02/09 N/A 28/02/09 16/02/09 30/03/09 13/03/09 29/04/09 24/03/09 09/05/09 N/A N/A 24/05/09 09/04/09 Granit Ltd (Armenia) 56,048 AMD 20,757,000 21/09/09 1/ 22 L=100m and D= 1000 mm, destroyed during the construction of metro -Phase 1

Gareguin Njdehh street - Reconstruction of C concrete sewer with L=500m and D= 1000 mm - W YWWP/GareguinWksPh2/ NCB Post 01/04/08 21/10/09 04/11/09 N/A 08/11/09 08/12/09 07/01/10 17/01/10 N/A N/A 01/02/10 29/09/10 Phase 2

Polyplastics- Construction of new p/s and sewer C W YWWP/PolyplastWks/ NCB Post 01/04/08 * N/A with L=800m and D= 200mm

Reconstruction and construction of sewers of C W YWWP/Sewer/09 NCB Post 30/09/08 03/11/08 30/10/08 N/A 05/11/08 05/11/08 15/12/09 10/12/08 20/02/09 21/01/2009 20/03/09 N/A 27/02/09 05/04/09 16/03/09 Jilyo P/Co (Armenia) 453,340 AMD 139,850,716 05/04/10 Yerevan city and Qanaqeravan

Metropole -Construction of sewer from Khorhradaranakan Street, adjacent to the Wine Gyughtntshinmontaj 1 C W YWWP/WineFactoryWks/08 NCB Post 04/01/08 04/11/08 04/11/08 10/11/08 N/A 14/11/08 04/11/08 14/12/08 02/12/08 13/01/09 19/12/2008 23/01/09 N/A 27/02/09 07/02/09 16/03/09 248,028 AMD 75,827,140 05/10/09 Factory over river to Echmiatsin old CJSC(Armenia) highway TOTAL 6,846,484 Note * Problems connected with land allocation. After solving this issue corresponding **The start date will be determind when the issue of reservoir legal status is solved.

Proc_Plan_eng-arm 21.04 2009 WB pdf