Proposed Residential & Commercial Complex at , Chinar Park, - 700136 Form – I Developer – Ambey Realtors LLP

FORM-I (I) Basic Information

Sl. Item Details No. 1. Name of the projects/s Residential complex 2. S. No. in the schedule 8(a) 3. Proposed capacity / area / length / tonnage to be The proposed project is a development of a handled / command area / lease area / number of residential cum commercial complex comprising wells to be drilled of seven residential towers and 1 commercial building alongwith club & community facility area which will be developed by Ambey Realtors LLP. Area of the land is 11869 sq.m. At present, project site is mostly vacant with few trees. Landuse of the project site has been converted to bastu. The residential towers will be B + G + 9 and G+ 4 storied while club house will be G+3 storied and commercial building will be G+2 storied. The car parking facility is provided in basement and common ground floor of all the buildings and it will be availed by the residents and commercial staff of the proposed complex. Proposed total number of residential flats will be 246. Total built up area of the proposed development is 41,015.66 sq.m. The development will be mixed with residential and commercial use. 4. New / Expansion / Modernization New 5. Existing Capacity Nil 6. Category of Project i.e. ‘A’ or ‘B’ B 7. Does it attract the general condition? If yes, please No specify 8. Does it attract the specific condition? If yes, please No specify 9. Location Plot / Survey / Kharsa No. Dag no. – 199, 205, 218, 227, 232 – 236, 248 – 254, Khatian no. – 1276, 1274, 1537 – 1549, 1581, 1824, 1825, 1844, 1863, 1892 - 1894, 1899 - 1902, 2293, 2311, 2452, Mouza – Atghara, J.L. No. – 10, Biswa Bangla Sarani, Chinar Park, Kolkata – 700136, Ward No. 12 of Municipal Corporation. , P.O. – Gopalpur, P.S. – Baguihati. Village - Tehsil - District 24 Parganas (N) State 10. Nearest railway station / airport alongwith distance Railway Station – (3.5 km), in kms Bidhannagar railway stn. (6.3 km), Station (9.6 km) Airport – Netaji Subhas International Airport (2.15 km approx.) – aerial distance. 11. Nearest Town, City, District Headquarters alongwith Kolkata & Rajarhat surrounding the project site distance in kms 12. Village Panchayats, Zilla Parishad, Municipal Bidhannagar Municipal Corporation; Poura Corporation, Local Body (complete postal Bhawan, FD – 415A, Salt Lake, Sector – III, addresses with telephone nos. to be given) Kolkata-700 106

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 1 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

13. Name of the Applicant Ambey realtors LLP 14. Registered Address PS IXL, Unit no. 305, 3rd Floor, Biswa Bangla Sarani, Chinar Park, P.O. – Rajarhat Gopalpur, P.S. – Baguihati, BMC Ward No. – 12, Kolkata – 700136. 15. Address for Correspondence Name Raj Kumar Agarwal Designation (Owner / Partner / CEO) Partner Address PS IXL, Unit no. 305, 3rd Floor, Biswa Bangla Sarani, Chinar Park, P.O. – Rajarhat Gopalpur, P.S. – Baguihati, BMC Ward No. – 12, Kolkata. Pin Code 700136 E - mail Telephone No. 9836232223 Fax. No. 16. Details of Alternative Sites examined, if any. Not Applicable Location of these sites should be shown on a topo sheet 17. Interlinked projects No 18. Whether separate application of interlinked project Not Applicable has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves approval / clearance No under: if yes, details of the same and their status to be give. a) The Forest Conservation Act, 1980? b) The Wildlife Protection Act, 1972? c) The C.R.Z. Notification, 1991? 22. Whether there is any Government Order / Policy The land is owned by Ambey Realtors LLP. No relevant / relating to the site? government order or policy is there related to the project site to the best of knowledge. 23. Forest land involved (hectares) Nil 24. Whether there is any litigation pending against the No project and / or land in which the project is propose to be set up? a) Name of the Court b) Case No. c) Orders / directions of the Court, if any and its relevance with the proposed project.

ƒ Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.,)

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 2 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, landuse, changes in water bodies, etc.)

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 1.1 Permanent or temporary change in No Physically, the project site is vacant with few trees. Landuse landuse, land cover or topography of the project site has been converted to bastu. Thus, including increase in intensity of landuse of proposed project is compatible with the landuse (with respect to local surroundings. Copies of land documents of the project site landuse plan) are enclosed in Annexure-1.1. 1.2 Clearance of existing land, No There are 9 trees existing at site. These will be retained to vegetation and buildings? the extent possible. 1.3 Creation of new landuses? Yes As already stated, the project site landuse has been converted to bastu. Thus, there has been creation of new landuse at the project site as the site will be used for residential and commercial purpose. 1.4 Pre-construction investigations e.g. Yes The sub soil exploration was done during the month of bore houses, soil testing? February, 2016. The sub soil investigation report is enclosed as Annexure – 1.4. 1.5 Construction works? Yes The total built up area for the proposed project will be 41015.66 sq.m. The complex will have 246 residential flats, few shops and office spaces. Total ground coverage after the construction of the project will be 4698.501 sq.m (39.58 % of land area). 1.6 Demolition works? No As already stated, there is no existing structure within the project site. 1.7 Temporary sites used for No The project site itself will be used as partial accommodation construction works or housing of for the construction workers. However, majority of the construction workers? construction workers will come from different areas of locality. 1.8 Above ground buildings, structures Yes Excavation of foundation and earthwork will be required and or earthworks including linear excavated earth will be reused for the backfilling of the structures, cut and fill or proposed construction. excavations? 1.9 Underground works including mining No No underground works are required except construction of a or tunneling? basement, underground reservoirs and other services. 1.10 Reclamation works? No No reclamation work required. 1.11 Dredging? No No Dredging required. 1.12 Offshore structures? No No offshore structures required. 1.13 Production and manufacturing No No production/manufacturing process is involved, as it is a processes? construction project. 1.14 Facilities for storage or goods or Yes Existing sheds will be used for storage of building materials. materials? Around 200 sq.m of area will be identified within the project site. Cement will be separately stored under cover in bales. Sand will be stacked with adequate care. Bricks and steel will be laid in open. No construction materials or waste will be stacked outside the site periphery. 1.15 Facilities for treatment or disposal or Yes Solid Wastes: solid waste or liquid effluents? Solid wastes generated will be 0.71 tonne/day of domestic nature. The wastes will be segregated into biodegradable and non-biodegradable wastes and collected in separate bins. The non-biodegradable recyclable wastes will be sold to recyclers and the biodegradable organic part of the

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 3 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data wastes will be composted in a mechanical compost plant within site. The non - recyclable waste will be disposed off to BMC waste disposable facility. Liquid Effluent: Liquid Effluent: During the construction phase, construction wastewater will be treated, reused and then discharged into the road side drain. Domestic wastewater will be treated and discharged into municipal sewer of B.M.C. During the operation phase also, generated wastewater having volume of 149 kLD which will be treated in STP and partially reused for toilet flushing and other secondary purposes. Remaining part will be discharged into B.M.C. sewer. The domestic wastewater will be collected through vertical stack in building and conveyed to respective disposal points by underground pipes. The underground sewerage system will be designed 3 times of the average flow to carry domestic wastewater. 1.16 Facilities for long term housing or No The project is predominantly residential in nature with a operational workers? commercial building. However, during the operational stage, the complex will be accommodating the residents of the apartments, office and shop employees alongwith other secondary activities. No long term housing facilities for the operational workers will be available. 1.17 New road, rail or sea traffic during No Not Applicable construction or operation? 1.18 New road, rail, air, waterborne or No Not Applicable other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No There will not be any requirement for closure or diversion of transport routes or infrastructure existing transport routes along the abutting road due to leading to changes in traffic following reasons: movements? i) No construction material will be stacked outside the project site. ii) The unloading of construction materials will be done according to the instruction of the regulatory authority. 1.20 New or diverted transmission lines or No Not Applicable pipelines? 1.21 Impoundment, damming, culverting, No No Impoundment, damming, culverting, realignment or other realignment or other changes to the changes to the hydrology of surface watercourse is hydrology or watercourses or proposed. aquifers? 1.22 Stream crossings? No No stream of natural watercourse passes through the project site. 1.23 Abstraction or transfers of water form No Required fresh water will be made available by Bidhannagar ground or surface waters? Municipal Corporation’s supply. During the construction phase also, required water will be available from the said source. 1.24 Changes in water bodies or the land No Surface drainage will not be affected. surface affecting drainage or run-off? 1.25 Transport of personnel or materials Yes Transport of personnel / material during the construction and for construction, operation or operation phase is envisaged. In the construction phase, decommissioning? movement of few trucks is envisaged daily. During operational phase, parking space for around 272 cars will be

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 4 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data provided. Break up for car parking facilities are as follows: Car Parking Provided: 272 Nos. (gr. fl. Covered = 123, Open = 43, basement = 106). Adequate parking area for service vehicles will also be provided. 1.26 Long-term dismantling or No Not Applicable decommissioning or restoration works? 1.27 Ongoing activity during No Not Applicable decommissioning or restoration works? 1.28 Influx of people to an area in either Yes Construction workers will be temporarily staying at the temporarily or permanently? project site during the construction period. During operational stage, about 1195 persons will be residing in the apartments within the complex. 1.29 Induction of alien species? Yes The landscaping and plantation programme will guide about the exotic as well as native species to be planted within the project site. 1.30 Loss of native species or genetic No Project site have few trees existing. All of them will be diversity? retained. 1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 2.1 Land especially undeveloped or No Area of the land is 11869 sq.m. The project site is a agricultural land (ha) developed land.

2.2 Water (expected source & competing Yes Water Reqd. during construction phase = 18 kLD. users) unit: KLD Water Reqd. during operational phase: No. of daily user: Occupancy Type No. of Occupants Residents 1195 persons Residential Floating 120 persons Service Staff 50 persons Office employee 27 persons Shop employee 26 persons Total Occupants 1418 persons

Break up of Water Consumption: Activity Water Consumption Domestic 186 kLD Car Cleaning 2 kLD Road Cleaning 2 kLD Landscaping 26 kLD Total 216 kLD

Source of Water: Domestic water requirement will be catered by municipal supply and water requirement for secondary activities like landscaping, road cleaning and car cleaning will be catered from treated wastewater from S.T.P. and collected rooftop

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 5 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data rainwater respectively. 2.3 Minerals (MT) No Not Applicable 2.4 Construction material – stone, Yes Cement = 8200 tonne aggregates, and / soil (expected Sand = 22560 tonne source – MT) Stonechip = 20900 tonne Bricks = 664400 pieces Steel = 2130 tonne Steel and cement will be sourced from authorized vendors. Sand & aggregate will be sourced from local supplier. 2.5 Forests and timber (source – MT) No Required timber will be supplied by local vendors. 2.6 Energy including electricity and fuels Yes Daily power requirement for the proposed residential (source, competing users) Unit: fuel complex is assessed as around 1200 kW. WBSEDCL will be (MT), energy (MW) the supply agency. 2.7 Any other natural resources (use No Not Applicable appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 3.1 Use of substances or materials, No There will be no storage of hazardous materials or which are hazardous (as per MSIHC chemicals within the complex. rules) to human health or the environment (flora, fauna and water supplies) 3.2 Changes in occurrence of disease or No Suitable drainage and waste management measures will be affect disease vectors (e.g. insect or adopted in both construction and operational phase, which water borne diseases) will prevent stagnation of water or accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors. 3.3 Affect the welfare of people e.g. by Yes This project will provide employment to approx. 100 local changing living conditions? labours in the construction phase and approx. About 1195 persons will be residing in 246 apartments within this complex in the operational phase. Also, the complex will accommodate about 50 service & security people per day. Thus, during the operational stage of the project about 20 direct employments will be there within the complex. Also, all the apartments within the complex may need household workers; Therefore, we can assume that around 30 indirect employments opportunities might also be generated; as it is expected that almost all the household workers will be coming from the surrounding areas. Thus, the living conditions as well as economic profile of the people living in surrounding areas will be upgraded. 3.4 Vulnerable groups of people who No Proper mitigation measures for the minimization of could be affected by the project e.g. degradation of various environmental parameters like noise hospital patients, children, the elderly abatement, traffic management etc., will be adopted during etc., construction and post-construction stage of the proposed complex. For any effect on school, college or medical institution in the immediate surroundings of the project site, this could be affected from this proposed project. 3.5 Any other causes No --

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 6 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 4.1 Spoil, overburden or mine wastes No Not Applicable 4.2 Municipal waste (domestic and or Yes During the operational period, solid waste will be generated commercial wastes) from different residential apartments, offices, shops as well as from the daily users and visitors. Solid waste will also be generated from site cleaning and maintenance activities. The daily generated quantity of such waste has been primarily assessed as 711 kg or 0.71 tonne. Break up of the quantity is as follows:

Per Capita Waste No. Of Solid Waste Type Of Generation Users Generation User (kg/cap/day) (Persons) (kg/day) Residential 0.5 1195 597.5 Residential 0.1 120 12.0 Floating Service Staff 0.3 50 15.0 Office 0.3 27 8.1 Employee Shop 0.3 26 7.8 Employee Site 0.05 1418 70.9 Maintenance Total 711.3 or 0.71 tonne/day Generated solid waste will be collected as Door to Door basis from designated locations & segregated into biodegradable and non – biodegradable waste by agency dealing in collection and disposal of garbage. The segregated non-biodegradable solid waste will be disposed into B.M.C. waste collection department and to recyclers. Biodegradable organic waste will be composted in a mechanical compost plant within site. Adequate number of collection bins, separates for biodegradable and non-biodegradable waste will be provided as per Municipal Solid Waste (Management and Handling) Rule, 2000. Waste from such bins will be collected separately on daily basis. All the collection bins will be properly maintained on regular basis. Arrangement will be made with collection agencies for providing garbage station or transfer point, from where all wastes collected from bins will be disposed off for further disposal by the municipal collection department. 4.3 Hazardous wastes ( as per No There will be no storage of hazardous waste within the Hazardous Waste Management complex except little amount of spent oil from D.G. Sets, Rules) which will be either reused or disposed off to an authorized collection agencies. 4.4 Other industrial process wastes No Not Applicable 4.5 Surplus product No Not Applicable 4.6 Sewage sludge or other sludge from Yes The sludge generated from the Inspection Pits of the Sewer effluent treatment Line and sludge from STP will be periodically disposed to the municipal collection agency. 4.7 Construction or demolition wastes Yes Construction and demolition waste will be reused for site development activities. 4.8 Redundant machinery or equipment No Not Applicable Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 7 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 4.9 Contaminated soils or other materials No Not Applicable 4.10 Agricultural wastes No Not Applicable 4.11 Other solid wastes No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 5.1 Emissions from combustion of fossil No The operation of proposed project does not envisage any fuels from stationary or mobile major air pollutant generating sources except DG sets (1 X sources 500 kW) and vehicular movement. 5.2 Emissions from production No Not Applicable as no production process is involved with this processes project 5.3 Emissions from materials handling Yes This will be restricted to the construction phase and to the including storage or transport construction site only. 5.4 Emissions form construction No This will be restricted to the construction phase and to the activities including plant and construction site only. equipment 5.5 Dust or odours from handling or Yes Certain amount of dust particulate might be generated materials including construction during the handling of construction materials, excavation & materials, sewage and waste earthworks, construction activities etc. But, proper control measures will be taken to minimize the generated volume of dust and dirt. 5.6 Emissions from incineration of waste No No incineration of waste will take place within the premises both during the construction as well as operational period. 5.7 Emissions from burning of waste in No Open burning of biomass / other material will be avoided. open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No - 6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 6.1 From operation of equipment e.g. Yes During construction, the machinery used for construction engines, ventilation plant, crushers will be of required standard and of reputed make and will adhere to national standards, which will take care of noise pollution control/ vibration control and air emission control. Hence, insignificant impacts due to construction machinery are envisaged. Apart from this, construction activities will be restricted to daytime only. Noise in the operational phase might be from DG sets only. DG sets will operate during power failure and will generate noise level below 75 dB (A) each as they will be of silent in nature. 6.2 From industrial or similar processes No Not Applicable 6.3 From construction or demolition Yes Due to various construction activities, there will be short- term noise impacts in the immediate vicinity of the project site. The construction activities will include the following noise generating activities: ƒ Operation of DG sets, concreting and mixing ƒ Excavation activities ƒ Construction of structures and running of construction equipments like Mixer Machine, Vibrators, Earth

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 8 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data Cutting Machines, Pay Loader etc. It has been assessed that the average noise level will be around 80-85 dB(A) during peak construction hours. But this will be confined within the project site and within construction period only. 6.4 From blasting or piling Yes No scope of blasting is involved in the proposed development, but piling work will be done. While conducting the piling works, D.M.C. piles will be used. Hence, the magnitude of generated noise and vibration will be minimized. 6.5 From construction or operational Yes During the construction and operational stage of the traffic project, traffic movement will be inside the project site resulting in low generation of noise in the surroundings. But, due to adoption of good traffic management practices, generated impacts, if any, will be minimized. 6.6 From lighting or cooling systems No - 6.7 From any other sources No -

7. Risks or contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 7.1 From handling, storage, use or No There will be no storage of hazardous materials or spillage of hazardous materials chemicals within the complex. 7.2 From discharge of sewage or other No During the construction period of the project, generated effluents to water or the land domestic sewage from the labourers’ daily use will be (expected mode and place or treated in the temporarily built septic tanks within the discharge) complex and the treated wastewater will be finally be discharged into roadside drain. The construction wastewater will be collected into a couple of Sediment Trap within the project site and after the sedimentation process it will be discharged into roadside drain. Sediment traps will have half an hour retention periods and their approximate size will be 2.5m(L) X 2.5m(W) X 0.75m (D). During the operational period, the generated wastewater will be discharged into roadside drain. 7.3 By deposition of pollutants emitted No No pollutants in terms of emission, effluent or solid waste to air into the land or into water will be emitted or discharged into the air, land or the surface water. 7.4 From any other sources No Not Applicable 7.5 Is there a risk of long term build up No Not Applicable or pollutants in the environment form these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health of the environment

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 8.1 From explosions, spillages, fires etc No This is basically a construction project and does not from storage, handling, use or involve major hazardous construction activity. Hence, production or hazardous chances of explosions, spillages, fires are minimal.

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 9 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data substances During construction, all the labourers will be provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Training and awareness about the safety norms will be provided to all supervisors and labours involved in construction activity. No major hazardous waste is being stored within the project site. No industrial or process activity is involved in this project hence chances of chemical hazards and accidents are minimal. However, suitable fire-fighting measures recommended by the fire department of Govt. of West Bengal will be adopted. 8.2 From any other causes No Not Applicable 8.3 Could the project be affected by No The area under study falls in Zone-III according to the natural disasters causing Indian Standard Seismic Zoning Map. Suitable seismic environmental damage (e.g. floods, coefficients in horizontal and vertical directions earthquakes, landslides, cloudburst respectively, have to be adopted while designing the etc)? structures. There are no chances of floods and landslide.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Sl. Information / Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 9.1 Lead to development of supporting Yes The local landuse of the area and along the Biswa Bangla facilities, ancillary development Sarani is predominantly mixed in nature. All the sides stimulated by the project which around the project site are occupied by structures. The could have impact on the drainage & sewerage network of the area is laid along the environment e.g.: abutting road. WBSEDCL supplies electricity in the entire area. Thus, while developing the project, the surrounding Supporting infrastructure (roads, areas have been adequately considered so that the power supply, waste or waste water cumulative impact on the surrounding environment can be treatment etc.) minimized.

Housing development No The project itself accommodates housing.

Extractive industries No Not Applicable

Supply industries No Not Applicable

Other No Not Applicable 9.2 Lead to after-use of the site, which No Not Applicable could have an impact on the environment. 9.3 Set a precedent for later No Not Applicable developments. 9.4 Have cumulative effects due to Yes Similar kind of residential complexes with different volume proximity to other existing or are coming up in the region. planned projects with similar effects

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 10 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

(III) Environmental Sensitivity

Sl. Areas Name / Aerial distance (within 15 km) No. Identity Proposed project location boundary 1. Areas protected under international None - conventions, national or local legislation for their ecological, landscape, cultural or other related value 2. Areas which are important or sensitive for None - ecological reasons – Wetlands, watercourses or other water bodies, coastal zone, biospheres,

mountains, forests 3. Areas used by protected, important or sensitive None - species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4. Inland, coastal, marine or underground waters None No coastal or marine areas within 15 km radius of the site. 5. State, National boundaries None - 6. Routes or facilities used by the public for access No Not applicable. to recreation or other tourist, pilgrim areas 7. Defense installation No Not applicable. 8. Densely populated or built-up area Yes The project site is located within ward no 12 of Bidhannagar Municipal Corporation. The site is surrounded by low to medium rise houses which are being developed gradually. The area is moderately populated. 9. Areas occupied by sensitive man-made land Yes Ranging from 1.0 km to 15 km from the uses (hospitals, schools, places of worships, project site. community facilities) 10. Areas containing important, high quality or None Not applicable scarce resources (groundwater resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas already subjected to pollution or No The ambient air quality of the region environmental damage, (those where existing shows that the pollutants, like RPM, SO2 legal environmental standards are exceeded) and NOX, are well within the permissible limits of the NAAQS standards prescribed by CPCB. 12. Areas susceptible to natural hazard which could None cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 11 Proposed Residential & Commercial Complex at Biswa Bangla Sarani, Chinar Park, Kolkata - 700136 Form – I Developer – Ambey Realtors LLP

(IV) Proposed Terms of Reference for EIA studies: Not applicable “I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Date:………………..

Place: KOLKATA……….

(Signature of the Applicant)

Name : Raj Kumar Agarwal Designation: Partner Ambey Realtors LLP PS IXL, Unit no. – 305, 3rd Floor, Biswa Bangla Sarani, Chinar Park, P.O. – R.G., P.S. – Baguihati, Kolkata - 700136. Note: a. The projects involving clearance under Coastal Regulation Zone Notification 1991 shall submit with the application a C.R.Z. map duly demarcated by one of the authorized agencies, showing the project activities w.r.t. C.R.Z. and the recommendations of the State Coastal Zone Management Authority. Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z. Notification, 1991 for the activities to be located in the C.R.Z.

b. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves, Migrating Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden thereon (at the stage of E.C.).

c. All correspondence with the Ministry of Environment & Forest including submission of application for TOR/Environmental Clearance, subsequently clarifications, as may be required from time to time participation in the EAC Meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for the specific project.

Consultant – CENTRE FOR SUSTAINABLE DEVELOPMENT 12