This is the Action Programme (AP) for the Local Development Plan (insert year of adoption). The purpose of this document is to set out how North Lanarkshire Council propose to implement the Plan, and in doing so it sets out:

- a list of actions required to deliver each of the Plan’s policies and proposals; - who is to carry out the action; and - the timescale for carrying out actions.

The Action Programme will play a key part in supporting the actions required to take forward the Plan and in doing so will help to drive and co- ordinate the actions and activities of a range of agencies and organisations.

In preparing the Action Programme, key agencies, Scottish Ministers and internal Council departments have been consulted. The Council will review the Action Programme and republish it every two years.

The North Lanarkshire Local Development Plan Modified Proposed Plan and accompanying documents can be viewed at: www.northlanarkshire.gov.uk/index.aspx?articleid=32484

Format of Action Programme

This Action Programme broadly follows the layout of the Local Development Plan, focusing on the implementation of Policies, the Area Strategies and Supplementary Guidance as set out in the order below:

Section 1

Promoting and Protecting Policies

- PROMote Development Locations and Infrastructure (PROM) - PROTecting Assets (PROT)

Placemaking Policies

- Purpose of Place (PP) - Amount of Development (AD) - Contributions to Infrastructure (CI) - Environmental & Design Qualities (EQ)

Section 2

Area Strategies

- Regeneration Area - Airdrie Local Area Partnership - Local Area Partnership - Local Area Partnership - & Local Area Partnership - Local Area Partnership - Northern Corridor Local Area Partnership - Local Area Partnership

Section 3

Supplementary Guidance

Section 1: Promoting and Protecting Policies/Placemaking Policies

Reference Policy Action Additional Specific Responsibility Timescale Progress and Notes Requirements for Delivery Promoting and Protecting Policies

PROM LOC Regeneration Delivery of Town Policy & Strategy Ongoing New Ravenscraig Masterplan approved June 2019. 1 Priorities Centre Action Team/ Growth Creation of a £3.7m public park commenced July Plans, Team, HES 2019 with expected completion 2020. Masterplans & Locality Plans as The Economic Regeneration Delivery Plan was identified in Area published October 2019. Strategies. The Council’s tower re-provisioning programme - Phase 1 of the Tower Strategy’s demolition programme agreed November 2019. The first phase includes 15 tower blocks and a number of low-rise blocks.

Town Centre Visions being prepared for 8 Town Centres to inform new Action Plans. PROM LOC Business Monitor industrial Policy & Strategy Complete Industrial and business land monitoring complete 2 Development and business land Team for 2019. Sites throughout North Lanarkshire.

PROM LOC Housing Undertake Policy & Strategy Ongoing Housing Land Audit undertaken for 2019 and 3 Development monitoring in Team awaiting finalisation. Sites relation to housing sites Strategic Housing Investment Programme 2020/21 throughout North – 2024/25 identifies affordable housing investment Lanarkshire and priorities over next five years. produce the Housing Land Audit. PROM LOC Special Promotion and Deliver green network Policy & Strategy Ongoing Project set to restore Garrell Burn, Kilsyth and 4 Landscape protection of the improvement Team/ GCVGNP improvements to Dumbreck Local Nature Reserve Areas & Green special landscape opportunities identified (NLC and SEPA £2m) areas, Seven in the Area Strategies Network Loch Wetland Planning & Place Creation of a £3.7m public park commenced July Improvements Park and Green Team/NLC 2019 with expected completion 2020. Network. Greenspace The Green Network Blueprint will inform Connecting North Lanarkshire: A Blueprint being developed in conjunction with The Plan for North Lanarkshire. PROM ID1 Transport Delivery of Policy & Strategy Ongoing Infrastructure Fund allocated £172.5 million of Improvements projects listed in Team/ NLC investment across North Lanarkshire – A8/M8 the strategies of Roads/City Deal corridor access improvements; / the Policy and the Team/Transport community growth area and Pan-Lanarkshire orbital Area Strategies /SPT/Sus transport corridor. including trans City Region City Ravenscraig Infrastructure Access (RIA) project, as Deal part of the wider Pan Lanarkshire Orbital Corridor, Infrastructure was approved April 2019. Fund projects. £190m Roads Programme.

PROM ID2 Utilities Encourage use of Promote potential heat Policy & Strategy Current to North Lanarkshire Council (NLC) are participating in Improvements capacity from energy network Team/ 2022 ’s Local Heat and Energy heat producing sources as identified in Infrastructure Efficiency Strategy (LHEES) pilot programme. This sources for heat Area Strategies Team involves a selection of areas/prioritisation of networks opportunities for energy efficiency and/or heat identified through decarbonisation, leading to the designation of the National Heat zones. The NL Report is complete and will inform Map. outcomes at a national level defining future actions and programmes.

Ongoing SPG 12 Wind Turbine Developments to be updated to include all renewables.

PROT A Natural Safeguard Planning & Place Ongoing Continue to protect these assets by making Environment & heritage assets. Team; NLC planning decisions in line with the policy. Green Network Greenspace; Assets SEPA; SNH Ongoing Associated Supplementary Planning Guidance 20 Biodiversity and Development to be updated. PROT B Historic Safeguard historic Planning & Place Complete Conservation Area Regeneration Schemes (CARS), Environment environment Team; HES including the current Coatbridge CARS completed Assets assets. 31st March 2020.

Continue to Ongoing Kilsyth and the Kelvin Valley Framework and Action protect these Plan published May 2018. assets by making decisions in line Ongoing Antonine Wall World Heritage Site HLF Project. with Policy PROT Stage 2 bid approved December 2018. To be B. delivered over three year period.

Ongoing Antonine Wall SPG update guidance has been prepared – awaiting consultation and adoption. PROT C Mineral Safeguard Planning & Place Ongoing Continue to protect these assets by making Resources mineral resources Team planning decisions in line with the policy. and prevent sterilisation. Ongoing SPG11 Minerals to be updated to include all identified Minerals Resources. Placemaking Policies

PP 1A Strategic Town Support and Planning & Place Ongoing Town Centre Visions being prepared for 8 Town Centres encourage a Team Centres to inform new Action Plans. range of appropriate uses Ravenscraig Masterplan was approved June 2019 and and the Economic Regeneration Delivery Plan was improvements to published October 2019. the physical environment to Complete Retail Outlet Survey complete for 2019. help maintain the role and function Ongoing Assess related planning applications against the of the Strategic Policy to ensure proposals are compliant with the Town Centres. Purpose of Place strategy in Local Development Plan AD 1A Strategic Town Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the Centres amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 1B Town & Large Support and Planning & Place Ongoing Town Centre Visions being prepared for 8 Town Centres encourage a Team, HES Centres to inform new Action Plans. range of appropriate uses Complete Retail Outlet Survey complete for 2019. and improvements to Ongoing Assess related planning applications against the the physical Policy to ensure proposals are compliant with the environment to Purpose of Place strategy in Local Development help maintain the Plan role and function of the Strategic Town Centres. AD 1B Town & Large Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the Centres amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 1C Local Centres Encourage a Planning & Place Complete Retail Outlet survey complete for 2019. range of uses and Team a level of Ongoing Assess related planning applications against the development in Policy to ensure proposals are compliant with the these centres to Purpose of Place strategy in Local Development meet the needs of Plan their localities. AD 1C Local Centres Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 2A Strategic Encourage large Planning & Place Complete Industrial and business land monitoring complete Business scale business Team for 2019. Centres users to locate in our Strategic Ongoing Assess related planning applications against the Business Centres, Policy to ensure proposals are compliant with the safeguard against Purpose of Place strategy in Local Development other Plan. inappropriate uses and support upgrading of premises, amenities, access, parking and green space. AD 2A Strategic Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the Business amount of assessment as part of Team Policy to ensure proposals are compliant with the Centres development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 2B Local Business Encourage small, Planning & Place Complete Industrial and business land monitoring complete Centres medium and large Team for 2019. sized enterprises to locate in our Ongoing Assess related planning applications against the Local Business Policy to ensure proposals are compliant with the Centres, Purpose of Place strategy in Local Development safeguard against Plan. other inappropriate uses and support upgrading of premises, amenities, access, parking and green space. AD 2B Local Business Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the Centres amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 2C Visitor Economy Support provision Planning & Place Ongoing Ravenscraig public park undergoing construction, Areas & of tourism and Team expected completion Autumn 2020. Locations leisure facilities in the Visitor Complete Broadwood Retail Park opened autumn 2019. Economy Locations. Complete Visitor Centre renovation complete 2019.

Ongoing Assess related planning applications against the Policy to ensure proposals are compliant with the Purpose of Place strategy in Local Development Plan. AD 2C Visitor Economy Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the Areas & amount of assessment as part of Team Policy to ensure proposals are compliant with the Locations development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 3 General Urban Maintain and Planning & Place Ongoing Assess related planning applications against the Area improve the level Team Policy to ensure proposals are compliant with the of amenity in Purpose of Place strategy in Local Development urban areas, by Plan. encouraging development that is in keeping with their residential character and encouraging diversity in more mixed-use areas. AD 3 General Urban Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the Area amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 4 Green Belt Protect setting of Planning & Place Ongoing Assess related planning applications against the communities, Team Policy to ensure proposals are compliant with the support Purpose of Place strategy in Local Development regeneration by Plan. directly growth to urban areas, protect natural assets and promote green belt as defined on the Proposals Maps. AD 4 Green Belt Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. PP 5 Countryside Support the Planning & Place Ongoing Assess related planning applications against the countryside, as Team Policy to ensure proposals are compliant with the defined on the Purpose of Place strategy in Local Development Proposals Maps, Plan. by accommodating limited development such as Visitor Economy related development, extending existing businesses and settlements, and agricultural diversification. AD 5 Countryside Assess the Submit appraisal or Planning & Place Ongoing Assess related planning applications against the amount of assessment as part of Team Policy to ensure proposals are compliant with the development any development Local Development Plan. proposed is proposal, as required. appropriate as required. CI Contributions to Secure developer 20% affordable Planning & Place Ongoing Associated SPG 13 Affordable housing will require Infrastructure contributions for housing provision is Team to be updated. new required in developments Cumbernauld Housing that, individually Sub-Market Area. Ongoing Supplementary Planning Guidance will be prepared or cumulatively, Excluding one to set out the framework of the application of the generate a bedroom dwellings, all policy, identification of need, calculation of requirement for dwellings require a contributions and methods of collection and new or enhanced contribution towards management of funds. infrastructure or education services. infrastructure. For all development, a contribution towards on-site transport infrastructure is required. Dependent on the individual or cumulative impact to existing infrastructure, a contribution to off- site provision identified is required. Assessed on a case-by-case basis. For all development, a contribution towards green infrastructure is required. Dependent on the individual or cumulative impact to existing infrastructure, a contribution to off- site provision identified is required. Assessed on a case-by-case basis. EDQ 1 Environmental Appraise Site appraisal required Planning & Place Ongoing Associated SPG 15 Good design toolkit will require & Design development to accompany Team to be updated. Qualities: Site proposal to planning application. Appraisal ensure it will integrate successfully into the local area and avoid harm to neighbouring amenity. EDQ 2 Environmental Consider When applicable, an Planning & Place Ongoing Noise Supplementary Guidance to be prepared. & Design development in assessment of how Team Qualities: areas subject to constraints affect the Specific hazards site is required to (Hazardous Features for Zones) and other accompany planning Consideration specific features application. (Utilities infrastructure and Management areas) identified in this Policy, in accordance with plans and protocols of the relevant managing agencies. EDQ 3 Environmental Promote and Planning applications Planning & Place Ongoing Associated & Design achieve high will require to take Team SPG 15 Good design toolkit, SPG 01 Landscaping, Qualities: standards of site account of the Site SPG 01A Landscaping supplement, SPG 02 Trees Quality of planning and Appraisal required by and development, Development sustainable Policies EDQ1 and, if SPG 07 Green belt, SPG 17 Accessibility for all, design. appropriate, EDQ2. SPG17 Accessibility appendix, open space and play area standards, minimum standards for space around houses, minimum parking standards will require to be updated.

Section 2: Area Strategies (including Proposed Development Sites)

The tables below highlight possible actions and issues to be dealt with prior to obtaining planning permission, in relation to Proposed Development Sites in the Local Development Plan. However, it should be noted that this list is not exhaustive, and any applicant should contact Development Management for up-to-date information on what may or may not require to be submitted with a planning application. Applicants will always be advised to contact utility or infrastructure providers to obtain up-to-date advice on current requirements and standards. The Development Management process may require relevant site investigations to determine land conditions. The process should also be used to alleviate, mitigate and avoid adverse impacts on the immediate and surrounding environment.

Also outlined below are the ‘Transport Improvements’ listed under each Area Strategy, most of which are related to the Glasgow City Region City Deal Infrastructure Fund.

For the purpose of clarification and completion, where sites included in the Modified Proposed Plan have since been granted planning permission (or minded to grant subject to planning permission subject to Section 75 Agreement), this has been noted within the tables. It is not expected further actions are required for the purpose of this Action Programme, other than the completion a Section 75 Agreement where specified.

Further Information/Developer Advice

The Scottish Environmental Protection Agency’s (SEPA) Flood Maps can be used to identify areas of functional floodplain to help ensure a precautionary approach is taken to flood-risk from all sources. SEPA is a statutory consultee in the planning process and applicants will always be advised to consult with SEPA on matters pertinent to flood risk.

SEPA Flood Maps - http://map.sepa.org.uk/floodmap/map.htm

SEPA Air Quality Management Areas (also shown on the Local Development Plan Map Book) - http://www.scottishairquality.scot/laqm/aqma?id=379

Please refer to Local Development Plan ‘EDQ 2 Policy Special Features for Consideration’ for further detail on areas subject to hazards and other specific features, in accordance with plans and protocols of the relevant managing agencies. Scottish Natural Heritage (SNH) work to improve the natural environment in Scotland, ensuring it is maintained and enhanced to the benefit of all. When bringing forward development proposals, consideration should be given to any potential impacts on the natural environment. SNH provide useful planning and development advice for developers which can be found here - www.nature.scot/professional-advice/planning-and-development

Coal Authority - Much of North Lanarkshire has been subject to coal mining activity, which can result in unstable land. If a site falls within a high risk area then a risk assessment prepared by a competent person needs to accompany your planning application. This may identify the need for intrusive site investigations and/or remediation measures prior to development.

Historic Environment Scotland (HES) - Developers should give consideration to potential impacts on the historic environment when bringing forward proposals. This should be supported by an assessment where impacts on the areas historic environment are likely.

Scottish Power - There is some general guidance that developers should be aware of when considering development near infrastructure. Energy Networks Association (ENA) Technical Specification 43-8 provides details of overhead line clearances that should be maintained. The Health & Safety Executive has also produced guidance for working near overhead power lines (HSG6) and underground services (HSG47). We would expect that careful consideration is given to potential impact on infrastructure at all stages.

Links to other useful information

o South Cumbernauld Community Growth Area - www.northlanarkshire.gov.uk/index.aspx?articleid=32096 o Gartcosh/Glenboig Community Growth Area - www.northlanarkshire.gov.uk/index.aspx?articleid=27904 o South Wishaw Community Growth Area - www.northlanarkshire.gov.uk/CHttpHandler.ashx?id=7551&p=0

o DPMTAG & - www.northlanarkshire.gov.uk/CHttpHandler.ashx?id=22692&p=0 o Cumbernauld / & Wishaw DPMTAG - https://www.northlanarkshire.gov.uk/CHttpHandler.ashx?id=22693&p=0

o Antonine Wall - www.antoninewall.org/ o Frontiers of the Roman Empire (Antonine Wall) World Heritage Site Supplementary Planning Guidance - www.northlanarkshire.gov.uk/CHttpHandler.ashx?id=7466&p=0 o For full list of Council Supplementary Planning Guidance - www.northlanarkshire.gov.uk/index.aspx?articleid=24294 o Glasgow City Region City Deal - www.northlanarkshire.gov.uk/index.aspx?articleid=31901 o Scottish Planning Policy 2014 - www.gov.scot/publications/scottish-planning-policy/ o Historic Environment Policy for Scotland 2019 and associated Managing Change Guidance notes - www.historicenvironment.scot/advice-and-support/planning-and-guidance/historic-environment-policy-for-scotland-heps/ o Historic Environment Scotland - www.historicenvironment.scot/ o Canmore - https://canmore.org.uk/

Airdrie Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress The installation and upgrade of Strathclyde Partnership for Ongoing Ongoing works improving cycle cycle/walking routes as detailed in Transport/NLC access – particularly around the M8 Strategic Investment Sites and Cycle Access Study 2013 report Station. Funded through SPT capital projects. Improvements to bus and rail NLC/ Strathclyde Partnership for Ongoing Ongoing discussions with SPT with infrastructure Transport/Network Rail regard to setting up a Bus Improvement Partnership along the A89 corridor.

General improvements to bus infrastructure (bus shelter maintenance contract now handled mainly by SPT) along with the proposed installation of Real Time Passenger Information throughout the network – starting with the A89.

Park and Ride facility at Wishaw Station extended 2019. General road safety improvements NLC/ Ongoing Ongoing rolling programme of route for route action plans and accident improvements based on accident improvement plans for locations stats. identified with high numbers of injury accidents. Glasgow City Region City Deal NLC/ Glasgow City Region City Deal Ongoing Strategic Business Case approved Infrastructure Fund projects: A8/M8 August 2015 for A8/M8 corridor Corridor Access Improvements access improvements. Outline Business Case approved June 2017 for Holytown Link Road and Eurocentral Park, Ride and share. £4million investment at Eurocentral – project approval from City Deal June 2017. Planning Application 19/00002/FUL permitted for road link between A8 and existing M8 Overbridge February 2020.

Glasgow City Region City Deal NLC/Glasgow City Region City Ongoing Revised Strategic Business Case of Infrastructure Fund projects: Pan- Deal/Transport Scotland/Strathclyde Pan Lanarkshire Orbital Transport Lanarkshire Orbital Transport Partnership for Transport/ScotRail Corridor approved December 2017. Corridor Glasgow City Region Cabinet approved Outline Business Case for the Motherwell Town Centre Transport Interchange April 2018. Glasgow City Region Cabinet approved new and enhanced Outline Business Case for Motherwell Town Centre Transport Interchange. Consultant has been appointed to generate and appraise options for East Airdrie Link Road. Ravenscraig Masterplan approved June 2019. Ravenscraig Infrastructure Access project approved April 2019. £3.5 million transport project for Motherwell Station approved by Glasgow City Region Cabinet.

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 01/07 Stirling Who: Developer Minded to grant planning Road/ Capacity: 300 permission, subject to Section 75 Area: 51.16 Ha Agreement (Planning Application Road 18/01785/PPP)

08/07 Dykehead Coal Authority – Flood Risk Assessment Who: 2020 - 2025 No planning application Road, Golfhill high risk area/low Strategic Network Impact Developer/NLC risk area Assessment undertaken by Capacity: 18 Scottish Water, developer should Area: 0.71 Ha contact to obtain most up to date information. Development Brief

11/07 Easterton Coal Authority – Provide green corridor and active Who: Developer 2020 - 2025 No planning application Farm, high risk area/low travel opportunities (access to Capacity: 78 risk area. NCN75) Area: 3.13 Ha Local concerns Ecological survey raised during Transport Statement (access from consultation adjacent development) regarding adverse Scottish Water: Pre-development impact upon application required residential amenity, Flood Risk Assessment (including noise, pollution, access and traffic strategy for retention of small should be mitigated watercourses) via the Development Possible Noise Assessment Management process. Opportunity to enhance existing planting and deliver a high quality landscape edge at western, southern and eastern boundary. 29/07 Coal Authority – Extended Phase 1 survey and Who: Developer 2020 - 2025 No planning application Roughrigg high risk area protected species survey required Capacity: 19 Road, (NLC Greenspace) Area: 0.75 Ha Access statement may be required Waste Water infrastructure required Provide green corridor and active travel opportunities Retention/enhancement of tree along railway line 01/08 Leaend Site located Flood Risk Assessment Who: 2020 - 2025 No planning application Road, Airdrie adjoining Northburn Provide green corridor and active Developer/NLC Park SINC travel opportunities Capacity: 41 Retain woodland to the north and Area: 1.64 Ha west of site Ecological survey Strategic Network Impact Assessment undertaken by Scottish Water, developer to make contact to obtain most up to date information Development brief required 03/08 Land at Scottish Gas Proposals should take into Who: Developer 2020 - 2025 No planning application Mosside Farm infrastructure consideration the memorial to the Capacity: 200 passes through mining disaster at this location Area: 7.33 Ha site. Coal Authority – Site located on SINC (Northburn high risk area. Park) assessment required to Possible tree grant demonstrate no adverse impact/ conditions. suitable mitigation Ecological Survey

Provide green corridor and active travel opportunities Transport Assessment Possible Noise Assessment Strategic Network Impact Assessment undertaken by Scottish Water, developer to make contact to obtain most up to date information Flood Risk Assessment (including strategy for retention of watercourses) 07/11 Sykeside Site currently Contaminated land survey, and if Who: Developer 2020 - 2025 16/01649/PPP application refused Road operating as a necessary site remediation is Capacity: 22 and appeal dismissed (residential waste management required Area: 0.87 Ha development in principle, with new facility. Ecological survey access and associated The land has Site adjacent infrastructure). physical Scheduled Monument and SINC – constraints, notably development should avoid adverse the remains of impact/suitable mitigation industrial activity Scottish Water: Pre-Development and potential Enquiry required (surface water contamination from sewer and culvert running through previous uses that site which may require diversion) will require to Flood Risk Assessment assess and A former bing is located on the site. remediate. A programme of archaeology Coal Authority – works is required. high risk area. Proposed regeneration sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 04/08 Within Victoria and Flood Risk Assessment Who: Developer 2020 - 2025 Unit 53 is split into two units. 53A is Alexander Town Centre the Wellness Hub and 53 is Street Conservation Area. operating as Puro Pizzeria. Development Unit 55-57 ground floor is vacant. should take South Upper floor is operating as a martial Burn into Scottish Water: Pre-development arts centre (Retail survey, March consideration/avoid Enquiry required 2019). damage to the Scottish Government’s Control of waterway. Woodland Removal policy should Coal Authority – be adhered to. high risk area. Ecological survey Possible Noise Assessment

Bellshill Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress Refer to ‘Transport Improvements’ table above under Airdrie LAP – Area Strategy

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 02/14 Scottish Water: Pre-development Who: Developer/ 2020 - 2025 No planning application Community Enquiry required (existing water NLC Road main north of site may need Capacity: 23 diverted) Area: 0.91 Ha Noise Assessment Development brief 04/14 Flood Risk Assessment (including Who: Developer 2020 - 2025 No planning application Hattonrigg strategy for retention of water Capacity: 75 courses) Area: 3.01 Ha Scottish Water: Pre-development Enquiry required (combined sewer runs through the site) Ecological survey Transport statement Scottish Government’s Control of Woodland Removal policy should be adhered to (development should consider impact on south east wooded area) 01/15 Flood Risk Assessment (including Who: Developer/ 2020 - 2025 No planning application Bairdsland View strategy for retention of water NLC courses) Capacity: 15 Scottish Water: Pre-development Area: 0.60 Enquiry required Scottish Government’s Control of Woodland Removal policy should be adhered to Ecological survey Development brief Noise Assessment 04/15 Who: Developer Minded to grant planning Torrance Park, Capacity: 689 permission, subject to Section 75 Holytown Area:27.57 Agreement (Planning Application 19/00124/FUL)

Proposed regeneration sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 02/13 Who: Developer Minded to grant planning Adjacent to 121 permission, subject to Section 75 Bellshill Road, Agreement (Planning Application Uddingston 17/00518/PPP)

Coatbridge Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress and Notes Refer to ‘Transport Improvements’ table above under Airdrie LAP – Area Strategy

The following sites have been identified for which joint action may be required to mitigate the cumulative effect of development -

• 01/09 Coatbridge Road/Manse Road, Bargeddie • 02/09 Coatbridge Road/Langmuir Road, Bargeddie • 06/09 Former Drumpark School, Bargeddie

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 01/09 Scottish Gas – high Contact Scottish Water as Who: Developer 2020 - 2025 Pre Application 19/01608/PREAPE Coatbridge pressure running mitigation is required for this site. Capacity: 155 – Proposed housing with formation Road/ Manse through centre of Transport Assessment - Area: 6.23 Ha of access, landscaping and Road, the site. Developers should jointly seek to associated works Bargeddie Coal Authority – assess cumulative impact of high risk area/low nearby proposals and where risk area possible mitigate any effect of development. Bargeddie Station capacity investigation Air Quality Impact Assessment Noise Impact Assessment Site bounded by railway line and motorway – provide high quality landscaping at these areas 02/09 Existing bungalows Contact Scottish Water as Who: Developer 2020 - 2025 No planning application Coatbridge on Coatbridge mitigation is required for this site. Capacity: 205 Road/ Langmuir Road utilise septic Area: 8.21 Ha Road, tanks, for which the Bargeddie outflow for the Provide green corridor and active majority of these travel opportunities (connectivity to tanks is into a culvert on the NCR75 and high quality landscaping to northern and northern edge of western edges) the site. Coal Authority – Transport Assessment (access low risk area. take off Langmuir Road and assess roundabout and realignment at Dykehead Road). Developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Bargeddie Station capacity investigation Air Quality Impact Assessment Noise Impact Assessment 03/09 Coal Authority – Who: NLC Planning permission has been St James low risk area granted, no further action (Planning Primary School Application 18/00834/FUL)

06/09 Local concerns Flood Risk Assessment (including Who: Developer/ 2020 - 2025 No planning application. Former raised through strategy for retention of NLC Drumpark consultation watercourses) Capacity: 55 Education and Families Committee School, regarding Contact Scottish Water as Area: 2.18 Ha approved a new primary school for Bargeddie sewerage/drainage/ mitigation is required for this site. St Kevin’s Primary School be traffic/access/lands provided at this location in May caping/layout/air Transport Assessment - 2019. Developers should jointly seek to quality and the provision of assess cumulative impact of nearby proposals and where consequential possible mitigate any effect of physical and social development. infrastructure. Tree Protection Order on site. Where feasible, Preparation of a tree management address through plan. the Development Management Scottish Government’s Control of process. Woodland Removal policy should be adhered to.

Ecological survey

Bargeddie Station capacity investigation Development brief 01/10 Sweethill Coal Authority – Early and ongoing discussion Who: Developer 2020 - 2025 15/01799/EIASCR - Terrace/ high risk area/low required with Scottish Power Capacity: 55 EIA Screening Opinion approved Deanston Place, risk area Energy Network Area: 2.21 Ha October 2015. Residential Carnbroe development c.55-58 units. Contact Scottish Water as mitigation is required for this site.

Transport - Access via Deanstone Walk. Scottish Government’s Control of Woodland Removal policy should be adhered to. Proposed business development sites 02/10 Flood Risk Assessment Who: Developer 2020 - 2025 17/00571/PAN - 1 Carnbroe, Proposal of Application Notice: Coatbridge Strategic Network Impact Proposed Class 4, 5, & 6 with Assessment undertaken by Associated Access Works, Scottish Water, developer to make Landscaping & SUDS Pond contact to obtain most up to date information Scottish Government’s Control of Woodland Removal policy should be adhered to. SINC - development should avoid adverse impact/suitable mitigation Ecological survey Air Quality Impact Assessment Noise Impact Assessment

Cumbernauld & Kilsyth Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress and Notes Improvements to bus and rail NLC/Strathclyde Partnership for Ongoing Ongoing discussions with SPT with infrastructure within North Transport/Network Rail regard to setting up a Bus Lanarkshire Council Improvement Partnership along the A89 corridor.

General improvements to bus infrastructure (bus shelter maintenance contract now handled mainly by SPT) along with the proposed installation of Real Time Passenger Information throughout the network – starting with the A89.

Park and Ride facility at Wishaw Station extended 2019. General road safety improvements NLC/Police Scotland Ongoing Ongoing rolling programme of route for route action plans and accident improvements based on accident improvement plans for locations stats. identified with high numbers of injury accidents.

The following sites have been identified for which joint action may be required to mitigate the cumulative effect of development -

• 05/02 72-74 Napier Road, Cumbernauld • 12/02 28 Napier Road, Cumbernauld

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 10/01 Coal Authority – Flood Risk Assessment (including Who: Developer 2020 - 2025 No planning application Lammerknowes high risk area strategy for retention of small Capacity: 57 Road, Banton watercourses) Area: 2.28 Ha Early discussion with NLC roads officers to address access North Marsh SINC - development should avoid adverse impact/suitable mitigation Ecological survey Site is located adjacent to Special Landscape Area - assessment of impact may be required. 20% affordable housing provision required (Cumbernauld HSMA) 05/02 Scottish Gas Flood Risk Assessment Who: Developer 2020 - 2025 No planning application 72-74 Napier infrastructure within Scottish Water: Pre-Development Capacity: 142 Road site boundary Enquiry required Area: 5.71 Ha Transport Assessment - developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development (consider DPMTAG study) Ecological survey

Noise Impact Assessment Enhanced screening to provide good landscape edge 20% affordable housing provision required (Cumbernauld HSMA) 12/02 Flood Risk Assessment Who: 2020 - 2025 No planning application 28 Napier Road Developer/NLC Contact must be made with Capacity: 135 Scottish Water early on in the Area: 5.43 Ha process to discuss existing 12” Trunk main within site boundary, please note this could impact on the site layout Transport Assessment - developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development (consider DPMTAG study) Ecological survey Noise Impact Assessment 20% affordable housing provision required (Cumbernauld HSMA) Development brief 14/02 Scottish Gas Archaeology assessment and Who: Developer 2020 - 2025 No planning application Tollpark Road, infrastructure within consultation with Historic Capacity: 49 site boundary. Environment Scotland (Antonine Area: 2 Ha Coal Authority – Wall World Heritage Site and high risk area. associated Scheduled Monument) Tree Preservation Provide green corridor and active Order at southern travel opportunities boundary of site. Ecological survey. Opportunity for woodland and wildlife corridor enhancements There is existing Scottish Water infrastructure within site; contact must be with the Asset Impact team to discuss potential impact on site layout Consult with NLC Roads regarding access 20% affordable housing provision required (Cumbernauld HSMA) Noise Impact Assessment 04/04 Coal Authority – Protected Species Survey Who: 19/01485/CAC | Substantial Partial Village Primary high risk area Developer/NLC Demolition of Former School Scottish Water: Pre-development School Capacity: 13 Building | Cumbernauld Primary application required Area: 0.52 Ha School Glasgow Road Cumbernauld Listed Building North Lanarkshire. Development brief 19/01484/FUL | Nursery with 20% affordable housing provision Associated Vehicular & Pedestrian required (Cumbernauld HSMA) Access and Car Parking – planning permission granted. Proposed business development sites 03/02 Sports pitch on site. Flood Risk Assessment (including Who: 2020 - 2025 No planning application Land at consideration of Board Burn) Developer/NLC Westfield contact SEPA Area: 3.73 Ha Contact must be made with Scottish Water early on in the process to discuss existing 54” Trunk main within site boundary, please note this could impact on the site layout Ecological survey Development brief Possible Noise Impact Assessment

Proposed regeneration area 13/02 Scottish Gas Flood Risk Assessment Who: 2020 - 2025 Ironside Farrar appointed to produce Orchardton infrastructure within Developer/Scottis Scottish Water: Pre-Development Masterplan Woods site boundary. h Enterprise Enquiry required NATS Holdings Ltd Area: 11 Ha (formerly known as Early and ongoing discussion with National Air Traffic Scottish Power Energy Network Services) has air (infrastructure passes nearby) traffic control Tree felling application infrastructure on FCS woodland planted under site. Woodland Grant Scheme 3, Cumbernauld Woods WIAT Scheme (Control of Woodland Removal Policy) Ecological survey Transport Assessment

Takes in part of Orchard Pond and Broadwood Loch SINC Masterplan

Motherwell Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress and Notes Refer to ‘Transport Improvements’ table above under Airdrie LAP – Area Strategy

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 06/17 Local concerns Mineral Stability Risk Assessment, Who: Developer 2020 - 2025 17/00062/PPP High Street, raised through and if required remediation Capacity: 51 19/00416/FUL- Erection of two consultation Flood Risk Assessment Area: 2.06 Ha detached dwellinghouses (small regarding privacy, Ecological survey section of south east corner of site). traffic and drainage. Where feasible Contaminated land survey, and if address through required remediation Development Noise Impact Assessment Management Possible Air Quality Impact process. Assessment 02/18 Coal Authority – Early and ongoing discussion with Who: 2020 - 2025 No planning application St Matthew’s high risk area/low Scottish Power Energy Network Developer/NLC Primary School, risk area (infrastructure passes through site Capacity: 142 Wishaw boundary) Area: 5.68 Ha Scottish Water: Pre-Development Enquiry required Retain watercourse Active travel link along north edge of site Consideration of Control of Woodland Removal Policy Ecological survey Possible Air Quality Impact Assessment Noise Impact Assessment Development brief 03/18 Scottish Gas Scottish Water: Pre-Development Who: Developer 2020 - 2025 17/00146/PRD – Permitted Netherton infrastructure within Enquiry required Capacity: 16 Development -Prior Notification for Street, Wishaw site. Previous gas Protected Species survey Area: 0.67 Ha Demolition of Gasholder. holder site with Contaminated land survey active regulator. Transport Assessment - Gasholder has been demolished. developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development.

Northern Corridor Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress and Notes Improvements to bus and rail NLC/ Strathclyde Partnership for Ongoing Ongoing discussions with SPT with infrastructure within North Transport/Network Rail. regard to setting up a Bus Lanarkshire Council Improvement Partnership along the A89 corridor.

General improvements to bus infrastructure (bus shelter maintenance contract now handled mainly by SPT) along with the proposed installation of Real Time Passenger Information throughout the network – starting with the A89.

Park and Ride facility at Wishaw Station extended 2019. General road safety improvements NLC/ Police Scotland Ongoing Ongoing rolling programme of route for route action plans and accident improvements based on accident improvement plans for locations stats. identified with high numbers of injury accidents. Glasgow City Region City Deal Complete Glenboig link road opened in June Infrastructure Fund projects: 2018. Gartcosh/ Glenboig Community The project also delivered – Growth Area Landscaping new ponds/restoring areas of existing nature reserve; improvements to Auldyards Road within Gartcosh Business Park; extended areas to Gartcosh Local Nature Reserve; cycling/walking paths either side of road; replacement of entrance feature to the business park.

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 04/05 Flood Risk Assessment (including Who: Developer 2020 - 2025 No planning application. Lanrigg Old strategy for retention of Capacity: 34 Lindsaybeg watercourses) Area: 1.36 Ha Road, Contact Scottish Water as mitigation on the water network is required for this site. Transport assessment – contact NLC Roads regarding access. Ecological survey and opportunity for habitat and wildlife corridor enhancements. 20% affordable housing provision required (Cumbernauld HSMA) 10/05 Who: Developer Minded to grant planning Gartferry Road, permission, subject to Section 75 Agreement (Planning Application 18/00444/FUL)

18/05 TPO at west side of Flood Risk Assessment (including Who: Developer 2020 - 2025 No planning application. The Neuk, boundary strategy for retention of small Capacity: 23 Auchinloch watercourses) Area: 0.91 Ha Scottish Water: Pre-Development Enquiry required. Contact Asset Impact Team regarding nearby infrastructure. Ecological survey. Water vole present on site. Access off adjacent development and replicate existing road design (contact NLC Roads) Possible Noise Impact Assessment 20% affordable housing provision required (Cumbernauld HSMA)

29/05 Flood Risk Assessment (including Who: Developer 2020 - 2025 Proposal of Application Notice East of strategy for retention of small Capacity: 105 19/01623/PAN – residential Auchengeich watercourses) Area: 4.18 Ha development with associated Road, Contact Scottish Water as access, landscaping an ancillary Moodiesburn mitigation on the water network is works. required for this site. Ecological survey Opportunity for habitat and wildlife enhancements Masterplan to include Stoneyetts Hospital site and adjacent 29/05 proposed housing site Air Quality Impact Assessment (near AQMA) Noise Impact Assessment 20% affordable housing provision required (Cumbernauld HSMA)

Wishaw Corridor Local Area Partnership – Area Strategies

Transport Improvements Project/ Action Responsibility for Delivery Timescales Progress and Notes Improvements to bus and rail NLC/Strathclyde Partnership for Ongoing Ongoing discussions with SPT with infrastructure within North Transport/Network Rail regard to setting up a Bus Lanarkshire Council Improvement Partnership along the A89 corridor.

General improvements to bus infrastructure (bus shelter maintenance contract now handled mainly by SPT) along with the proposed installation of Real Time Passenger Information throughout the network – starting with the A89.

Park and Ride facility at Wishaw Station extended 2019. General road safety improvements NLC/Police Scotland Ongoing Ongoing rolling programme of route for route action plans and accident improvements based on accident improvement plans for locations stats. identified with high numbers of injury accidents.

The following sites have been identified for which joint action may be required to mitigate the cumulative effect of development –

• 03/18 Netherton Street, Wishaw (shown on Motherwell Local Area Partnership – Area Strategy table) • 13/19 Woodhall Road, Newmains, Wishaw • 17/19 Royal George, Newmains • 20/19 West of Morningside, Newmains • 23/19 348-414 Street, Wishaw • 02/20 Overtown Road, Waterloo • 13/20 Gowkthrapple near Priory Lodge, Wishaw • 07/20 Garrion Farm, Overtown • 11/20 No 1 Netherton Road, Wishaw • 12/20 No 4 Netherton Road, Wishaw

Proposed housing development sites Site/ Project Site Comments/ Specific Requirements/Actions Responsibility Timescales Progress and Notes Constraints for Delivery 05/12 Coal Authority – Flood Risk Assessment (including Who: Developer 2020 - 2025 No planning application. East of Benhar high risk area/low strategy for retention of Capacity: 200 Road, risk area watercourses and pond) area Area: 29.29 Ha Torbothie, overlaps into The Voe SINC Drainage impact assessment required. Shotts WWTW has limited capacity and a growth project may be required. Scottish Government’s Control of Woodland Removal policy should be adhered to (Woodland present on site) Ecological survey Transport assessment

Air Quality Impact Assessment Noise Impact Assessment 14/12 A Strategic drainage impact Who: Developer Planning permission has been Springhill Farm, assessment is required to granted, no further action Shotts determine if mitigation is required (Planning Application for this site. A study is underway, 17/00389/PPP) developer should liaise with Scottish Water for updates.

04/19 Drainage impact assessment. Who: Developer 2020 - 2025 No planning application Mauldslie WWTW has limited Capacity: 4 capacity and a growth project may Area: 0.16 Ha Adjacent to 499 be required. Pre Development Wishaw Road, Enquiry to Scottish Water Bogside Access statement (if direct access is alternate to Wishaw Road) Possible Noise Impact Assessment 09/19 Coal Authority – Drainage impact assessment. Who: Developer 2020 - 2025 No planning application 18a Biggar high risk area/low Swinstie WWTW has limited Capacity: 17 Road, Cleland risk area capacity and a growth project may Area: 0.73 Ha be required. Pre Development Enquiry to Scottish Water. Transport statement Consider quality of pedestrian and cycle links to station and adjoining areas. Possible Noise Impact Assessment 13/19 Scottish Gas Scottish Water: Pre-Development Who: Developer 2020 - 2025 No planning application Woodhall Road, infrastructure Enquiry required. Swinstie WWTW Capacity: 207 Newmains passes through part may require a growth project Area: 8.26 Ha of the site. SNH: Incorporate woodland and Coal Authority – enhance connectivity between and high risk area/low out with site risk area. Ecological survey Local concerns raised through Transport assessment – consultation developers should jointly seek to regarding the assess cumulative impact of natural nearby proposals and where environment, site possible mitigate any effect of location and development. suitability. Where Possible Noise Impact Assessment feasible address through Development Management process.

17/19 Coal Authority – Flood Risk Assessment (including Who: Developer 2020 - 2025 15/01637/PPP – Refused – Appeal Royal George, high risk area/low strategy for retention of small Capacity: 200 Dismissed Newmains risk area. watercourses and ponds at site) Area: 19.03 Hot Water Pond SINC overlaps Business and Industrial part of site Development (Use Classes 4, 5 and 6) (In Principle) - Hydracrat Ltd Ecological survey

Scottish Water would require further investigation to determine impact on existing network and best point of connection Early and ongoing discussion with Scottish Power Energy Network (infrastructure passes through site boundary) Transport assessment – Developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Possible Air Quality Impact Assessment Noise Impact Assessment 20/19 Coal Authority – Who: Developer Minded to grant planning West of high risk area/low permission, subject to Section 75 Morningside, risk area. Agreement (Planning Application Newmains 19/00278/AMD)

22/19 Planning Scottish Water: Pre-development Who: Developer 2020 - 2025 16/02002/AMD (Planning application North & South permission on application required. Swinstie Capacity: 39 relates to the housing development Road, northern part of WWTW may require a growth Area: 1.55 Ha north of this site that overlaps the Bellside, site. project northern portion of this site). Cleland Coal Authority – Transport assessment or sensitivity Amendment to Planning Permission high risk area/low tests considering other nearby 09/01014/AMD to change house risk area. development proposals types on plots 4, 5 and 27, and to Impact on Cleland Station obtain approval of site contours and depending on proposals/capacity. levels. Possible Air Quality Impact Assessment Noise Impact Assessment

23/19 Coal Authority – Scottish Water: Pre-Development Who: Developer/ 2020 - 2025 No planning application 348-414 high risk area/low Enquiry required and network NLC Cambusnethan risk area. impact assessment. Capacity: 8 Street, Transport assessment – Area: 0.34 Ha Newmains Developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Development brief

26/19 Coal Authority – Flood Risk Assessment (including Who: Developer 2020 - 2025 18/01663/FUL North & South high risk area/low strategy for retention of small Capacity: 45 18/01664/FUL Road, risk area. watercourses) Area: 1.78 Ha 18/01665/FUL Bellside, Scottish Water: Pre-Development Planning applications for 3 single Cleland Enquiry required. Swinstie WWTW dwellings across the site by Taylor may require a growth project Homes pending consideration.

Ecological survey. : Murdostoun Estate SINC overlaps western boundary. Transport assessment or sensitivity tests considering other nearby development proposals. Impact on Cleland Station depending on proposals/capacity. 01/20 Excelsior Coal Authority – Scottish Water: Pre-Development Who: Developer 2020 - 2025 No planning application Street, Wishaw high risk area/low Enquiry required Capacity: 15 risk area. Transport statement Area: 0.61 Ha

Noise Impact Assessment 02/20 Overtown Coal Authority – Flood Risk Assessment (including Who: 2020 - 2025 No planning application Road, Waterloo high risk area/low strategy for retention of Developer/NLC risk area. watercourses) Capacity: 40 Scottish Water: Pre-Development Area: 1.61 Ha Enquiry required and network impact assessment Transport assessment – Developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Noise Impact Assessment Development brief 07/20 Garrion Scottish Gas Flood Risk Assessment (including Who: Developer 2020 - 2025 No planning application Farm, Overtown infrastructure retention of small watercourses) Capacity: 98 passes partly Pre-app discussion with SEPA Area: 3.92 Ha 16/00956/PAN - Glasshouse through site. regarding private sewer treatment Developments - Proposed Coal Authority – on site Residential Development high risk area/low Site is located within a Special risk area. Landscape Area - assessment of impact required. Site adjacent to Garrion Gill & Horsely Brae SINC Ecological survey Transport assessment – developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. 11/20 Scottish Gas Seek to retain trees at northern Who: Developer 2020 – 2025 No planning application No 1 Netherton infrastructure edge of site boundary within site Capacity: 167 Road, Wishaw passes through site design Area: 6.68 Ha Early and ongoing discussion with Scottish Power Energy Network (infrastructure passes nearby) Scottish Water: Pre-Development Enquiry required and network impact assessment Transport assessment – Developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Wishaw Station capacity investigation Protected species survey 12/20 Seek to retain trees at southern Who: Developer 2020 - 2025 No planning application No 4 Netherton boundary within site design Capacity: 63 Road, Wishaw Noise impact assessment Area: 2.52 Ha Early and ongoing discussion with Scottish Power Energy Network (infrastructure passes nearby site) Scottish Water: Pre-Development Enquiry required and network impact assessment Transport assessment – developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Wishaw Station capacity investigation Protected species survey 13/20 Scottish Gas Flood Risk Assessment (including Who: Developer No planning application Gowkthrapple infrastructure within strategy for retention of small Capacity: 50 near Priory boundary watercourses) Area: 2.08 Ha Lodge, Wishaw Scottish Water: Pre-Development Enquiry required and network impact assessment Early and ongoing discussion with Scottish Power Energy Network Ecological survey Cumbusnethan Woods SINC surrounds site and existing woodland (allocated TPO) offers potential for links to wider countryside and strong landscape framework to deliver a high quality development.

Transport assessment – developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Wishaw Station capacity investigation

Any development proposals should take into consideration the adjacent kennels in terms of impact Proposed leisure development sites 03/19 Scottish Water: Pre-Development Who: Developer 2020 - 2025 No planning application Enquiry required and network Area: 0.30 Ha Hotel, Cleland impact assessment Scottish Government’s Control of Woodland Removal policy should be adhered to (woodland present on site). TPO on site. Ecological survey

Possible Noise Impact Assessment

Proposed regeneration sites 07/19 Coal Authority – Flood Risk Assessment (including Who: Developer No planning application Morningside high risk area/low strategy for retention of Area: 2.77 Ha Road, risk area watercourses) Newmains Scottish Water: Pre-Development Enquiry required. Swinstie WWTW may require a growth project Scottish Government’s Control of Woodland Removal policy should be adhered to (woodland present on site) Ecological survey

Transport statement – depending on proposal, developers should jointly seek to assess cumulative impact of nearby proposals and where possible mitigate any effect of development. Noise Impact Assessment

Section 3: Supplementary Guidance

The table below outlines where the Local Development Plan has indicated that new or updated supporting Supplementary Guidance is required/actioned in association with specific policies, and where there is existing guidance included as part of the Local Development Plan.

The Council is currently undertaking a review of all existing Supplementary Planning Guidance, with a view to future development of new, updated and amended Supplementary Guidance (previously termed Supplementary Planning Guidance) as described below.

Local Development Content Status/Action Responsibility Timescale Plan Policies PROM ID1 Transport Contained in Guidance Individual projects will be NLC/Glasgow Ongoing Improvements Glasgow section of the Policy subject to the City Region City City Region Deal requirements of any Deal statutory requirements under the Environmental Assessment (Scotland) Act 2005, dependent on nature and scale. PROM ID2 Utilities General Guidance on SPG 12 Wind turbine NLC in 2020 onwards Improvements Renewable renewables and capacity developments Guidance conjunction with Energy for wind turbine to be updated to include relevant Key developments is contained all renewables. Agencies in Guidance section of the Policy PR O T A Natural Contained in Guidance Associated NLC in 2020 onwards Environment and Green section of the Policy Supplementary Planning conjunction with Network Assets Guidance 20 Biodiversity relevant Key A1 International and Development to be Agencies (Designated by Scottish updated. Natural Heritage) PROT C Mineral General Guidance on Associated SPG 11 NLC in 2020 onwards Resources Mineral Resources is Minerals to be updated to conjunction with contained in Guidance include all identified relevant Key section of the Policy Mineral Resources Agencies 1A Strategic Town General Guidance on the Town Centre Action Plans NLC in To be updated Centres Purpose of Place Policy as to be updated as conjunction with following PP 1A Purpose of Place it affects Strategic Town appropriate. relevant Key preparation of Policy Centres is contained in Agencies Town Centre Guidance section of the Visions - Policy. 2020 onwards 1B Town & Large General Guidance on the Town Centre Action Plans NLC in To be updated Centres Purpose of Place Policy as to be updated as conjunction with following PP 1B Purpose of Place it affects Town & Large appropriate. relevant Key preparation of Policy Centres is contained in Agencies Town Centre Guidance section of the Visions - Policy. 2020 onwards CI Contributions to Explanation of the Associated SPG 13 NLC 2020 onwards Infrastructure Policy application of the Policy as Affordable housing will Category CI1 Affordable it applies to Affordable require to be updated. Housing Housing is contained in the Guidance Section of the Policy.

Education is contained in the Guidance Section of Supplementary Planning Category CI2 Education the Policy Guidance will be prepared NLC to set out the framework of the application of the policy, identification of need, calculation of contributions and methods of collection and management of funds. Transport is contained in the Guidance Section of Category CI3 Transport the Policy

Green Infrastructure, Amenity Space and Play is Category CI4 Green contained in the Guidance Infrastructure, Amenity Section of the Policy. Space and Play

EDQ 1 Site Appraisal General Guidance on Site Associated SPG 15 Good NLC 2020 onwards Policy Appraisal is contained in design toolkit will require Guidance section of the to be updated. Policy EDQ 2 Specific Features Explanation of the Contained in Guidance n/a n/a for Consideration Policy application of the Policy as section of the Policy Category EDQ 2A it applies to Flood Risk is Hazardous Zones Flood contained in the Guidance Risk Section of the Policy Contaminated Land Contaminated Land is contained in the Guidance Section of the Policy Category EDQ 2B Utilities Explanation of the Contained in Guidance n/a n/a Infrastructure application of the Policy as section of the Policy Pipelines/Cables it applies to Pipelines/Cables is contained in the Guidance Section of the Policy

Category EDQ 2C Explanation of the Noise Supplementary NLC 2020-2021 Management Areas application of the Policy as Guidance is to be Air Quality Management it applies to Air Quality prepared by the Council. Areas Management Areas is contained in the Guidance Section of the Policy. Noise Management Areas Noise Management Areas is contained in the Guidance Section of the Policy. EDQ 3 POLICY Quality of General Guidance on Associated NLC in 2020 onwards Development Quality of Development is SPG 15 Good design conjunction with contained in Guidance toolkit, relevant Key section of the Policy SPG 01 Landscaping, Agencies SPG 01A Landscaping supplement SPG 02 Trees and development, SPG 07 Green belt, SPG 17 Accessibility for all, SPG17 Accessibility appendix, open space and play area standards, minimum standards for space around houses, minimum parking standards will require to be updated.