TEC Register Report as on 02/01/2020 Generation Connection Customer Name Type Directly Awel Y Mor Offshore Wind Farm Ltd Connected Directly Codling Wind Park Ltd Connected Directly Dogger Bank Offshore Wind Farm Project 1 Holdco Limited Connected Directly Dogger Bank Offshore Wind Farm Project 1 Holdco Limited Connected Directly Dogger Bank Offshore Wind Farm Project 3 Holdco Limited Connected Directly Dogger Bank Offshore Wind Farm Project 2 Holdco Limited Connected Directly Dogger Bank Offshore Wind Farm Project 2 Holdco Limited Connected Directly ScottishPower Renewables (UK) Limited Connected Directly East Anglia THREE Limited Connected Directly East Anglia THREE Limited Connected Directly East Anglia FOUR Limited Connected Directly East Anglia FOUR Limited Connected Directly East Anglia FOUR Limited Connected Directly East Anglia FOUR Limited Connected Directly East Anglia One Limited Connected Directly East Anglia One Limited Connected Directly Statkraft Ireland Limited Connected Directly Equinor New Energy Ltd Connected Directly Seagreen Wind Energy Ltd Connected Directly Seagreen Wind Energy Ltd Connected Directly Seagreen Wind Energy Ltd Connected Directly Innogy Renewables UK Ltd Connected Directly Greenwire Transmission Pentir Limited Connected Directly Breesea Limited Connected Directly Soundmark Wind Limited Connected Directly Sonningmay Wind Limited Connected Directly Orsted Hornsea Project Three Uk Ltd Connected Directly Orsted Hornsea Project Three Uk Ltd Connected Directly Orsted Hornsea Project Four Limited Connected Directly Orsted Hornsea Project Four Limited Connected Directly Orsted Hornsea Project Three Uk Ltd Connected Directly Orsted Hornsea Project Three Uk Ltd Connected Directly Inch Cape Offshore Ltd Connected Directly Inch Cape Offshore Ltd Connected Directly Inch Cape Offshore Ltd Connected Embedded Kincardine Offshore Windfarm Limited Directly Moray Offshore Windfarm (East) Ltd Connected Directly Moray Offshore Windfarm (East) Ltd Connected Directly Moray Offshore Windfarm (East) Ltd Connected Directly Moray Offshore Windfarm (West) Limited Connected Directly Moray Offshore Windfarm (West) Limited Connected Directly Neart Na Gaoithe Offshore Wind Ltd Connected Directly Sofia Offshore Wind Farm Limited Connected Directly Sofia Offshore Wind Farm Limited Connected Directly Vattenfall Wind Power Ltd Connected Directly Triton Knoll Offshore Wind Farm Ltd Connected Directly Triton Knoll Offshore Wind Farm Ltd Connected
Project Name
Awel Y Mor Extension
Codling Park Wind Farm
Dogger Bank Project 1
Dogger Bank Project 1
Dogger Bank Project 2
Dogger Bank Project 4
Dogger Bank Project 4
East Anglia 2
East Anglia 3
East Anglia 3
East Anglia 4
East Anglia 5
East Anglia 6
East Anglia 6
East Anglia One
East Anglia One North
Energy Isles
Equinor
Firth of Forth Offshore Wind Farm 2A
Firth of Forth Offshore Wind Farm 2B
Firth of Forth Phase 1
Galloper Extension Offshore Wind Farm
Greenwire Wind Farm - Pentir
Hornsea Power Station 2A
Hornsea Power Station 2B
Hornsea Power Station 2C
Hornsea Power Station 3A-1 (formerly 3A)
Hornsea Power Station 3A-2 (formerly 3B)
Hornsea Power Station 4
Hornsea Power Station 4
Hornsea Power Station Project 3B-1 (formerly 3C)
Hornsea Power Station Project 3B-2 (formerly 3D)
Inch Cape Offshore Wind Farm Platform 1 Inch Cape Offshore Wind Farm Platform 1
Inch Cape Offshore Wind Farm Platform 2
Kincardine Offshore Wind Farm Moray Firth Offshore Wind Farm
Moray Firth Offshore Wind Farm
Moray Firth Offshore Wind Farm
Moray Offshore West Windfarm
Moray Offshore West Windfarm
Neart Na Gaoithe Offshore Wind Farm
Sofia Offshore Wind Farm
Sofia Offshore Wind Farm
Thanet Extension Offshore Wind Farm
Triton Knoll Offshore Wind Farm
Triton Knoll Offshore Wind Farm
MW MW Increase / Connection Site Connected Decrease Gwynt y Mor 132/33kV Offshore Substation 0.00 580.00
Pentir Substation 0.00 1,000.00
Dogger Bank 220/33kV Offshore Substations 0.00 600.00
Dogger Bank 220/33kV Offshore Substations 0.00 600.00
Dogger Bank 220/33kV Offshore Substations 0.00 1,000.00
Dogger Bank 220/33kV Offshore Substations 0.00 600.00
Dogger Bank 220/33kV Offshore Substations 0.00 600.00
Platform EA2A and Platform EA2B 220/33kV Offshore Substations 0.00 860.00
Platform EA3A and Platform EA3B 220/33kV Substations 0.00 600.00
Platform EA3A and Platform EA3B 220/33kV Substations 0.00 600.00
Platform EA4A and Platform EA4B 220/33kV Offshore Substations 0.00 900.00
Platform EA5A and Platform EA5B 220/33kV Substations 0.00 900.00
Platform EA6A and Platform EA6B and Platform EA6C 220/33kV Substations 0.00 900.00
Platform EA6A and Platform EA6B and Platform EA6C 220/33kV Substations 0.00 900.00
Platform EA One 220/66kV Offshore Substation 0.00 340.00
0.00 860.00
0.00 120.30
Sheringham Shoal and Dudgeon Offshore Windfarms 0.00 719.00
0.00 700.00
Branxton 400kV 0.00 700.00
Tealing 275/33kv 0.00 1,075.00
0.00 348.00
Pentir 400kV Substation 0.00 1,000.00
Hornsea Platform 2A Offshore Substation 0.00 440.00
Hornsea Platform 2B Offshore Substation 0.00 440.00
Hornsea Power Station 2C Offshore platform 0.00 440.00
Hornsea Platform 3A Offshore Substation 0.00 500.00
Hornsea Platform 3B Offshore Substation 0.00 500.00
Hornsea Offshore Substation Platform 4 0.00 1,100.00
Hornsea Offshore Substation Platform 4 0.00 1,500.00
Hornsea Platform 3C Offshore Substation 0.00 500.00
Hornsea Platform 3D Offshore Substation 0.00 500.00
Cockenzie 275kV 0.00 200.00 Cockenzie 275kV 0.00 130.00
Cockenzie 275kV 0.00 370.00
Redmoss 132/33kV Grid Supply Point Substation 0.00 47.60 Moray Firth 220/33kV Platform 1 & 2 Offshore Substation 0.00 300.00
Moray Firth 220/33kV Platform 1 & 2 Offshore Substation 0.00 520.00
Moray Firth 220/33kV Platform 1 & 2 Offshore Substation 0.00 80.00
Moray Firth 220/33kV Platform 1 & 2 Offshore Substation 0.00 400.00
Moray Firth 220/33kV Platform 1 & 2 Offshore Substation 0.00 400.00
0.00 450.00
Dogger Bank 220/33kV Offshore Substations 0.00 600.00
Dogger Bank 220/33kV Offshore Substations 0.00 600.00
0.00 340.00
Triton Knoll Offshore Substation 0.00 540.00
Triton Knoll Offshore Substation 0.00 360.00
MW Effective MW Total Project Status HOST TO Plant Type Date 580.00 01-04-2027 Scoping OFFSHORE Wind Offshore
1,000.00 31-10-2024 Scoping NGET Wind Offshore
1,200.00 01-04-2023 Consents Approved NGET Wind Offshore
600.00 01-04-2023 Consents Approved NGET Wind Offshore
1,000.00 01-04-2024 Awaiting Consents NGET Wind Offshore
1,200.00 01-04-2023 Consents Approved NGET Wind Offshore
600.00 01-04-2023 Consents Approved NGET Wind Offshore
860.00 01-04-2026 Scoping NGET Wind Offshore
1,200.00 01-04-2023 Consents Approved NGET Wind Offshore
600.00 01-04-2023 Consents Approved NGET Wind Offshore
900.00 01-04-2027 Scoping NGET Wind Offshore
900.00 01-04-2027 Scoping NGET Wind Offshore
1,800.00 01-04-2024 Scoping NGET Wind Offshore
900.00 01-04-2024 Scoping NGET Wind Offshore
680.00 30-11-2019 Under Construction/Commissioning NGET Wind Offshore
860.00 01-04-2027 Scoping OFFSHORE Wind Offshore
120.30 31-03-2024 Scoping SHET Wind Offshore
719.00 01-09-2025 Scoping NGET Wind Offshore
700.00 01-04-2023 Scoping SPT Wind Offshore
700.00 01-04-2024 Scoping SPT Wind Offshore
1,075.00 31-10-2021 Consents Approved SHET Wind Offshore
348.00 01-04-2029 Awaiting Consents NGET Wind Offshore
1,000.00 31-12-2024 Scoping NGET Wind Offshore
440.00 01-10-2020 Consents Approved NGET Wind Offshore
440.00 01-04-2021 Consents Approved NGET Wind Offshore
440.00 01-10-2021 Consents Approved NGET Wind Offshore
500.00 01-04-2023 Scoping NGET Wind Offshore
500.00 01-10-2023 Scoping NGET Wind Offshore
2,600.00 31-10-2028 Awaiting Consents NGET Wind Offshore
1,500.00 01-04-2025 Awaiting Consents NGET Wind Offshore
500.00 01-04-2024 Scoping NGET Wind Offshore
500.00 01-10-2024 Scoping NGET Wind Offshore
330.00 31-10-2023 Consents Approved SPT Wind Offshore 130.00 01-04-2023 Consents Approved SPT Wind Offshore
370.00 01-04-2023 Consents Approved SPT Wind Offshore
49.60 01-04-2020 Under Construction/Commissioning SHET Wind Offshore 900.00 01-04-2021 Consents Approved SHET Wind Offshore
600.00 01-04-2021 Consents Approved SHET Wind Offshore
80.00 01-01-2021 Consents Approved SHET Wind Offshore
400.00 31-03-2024 Scoping SHET Wind Offshore
800.00 01-04-2024 Scoping SHET Wind Offshore
450.00 26-02-2021 Consents Approved SPT Wind Offshore
1,200.00 01-04-2024 Awaiting Consents NGET Wind Offshore
600.00 01-04-2023 Awaiting Consents NGET Wind Offshore
340.00 30-04-2023 Scoping OFFSHORE Wind Offshore
900.00 01-04-2021 Under Construction/Commissioning NGET Wind Offshore
360.00 01-06-2020 Under Construction/Commissioning NGET Wind Offshore