Expanding the U.S. Nuclear Infrastructure by Building a New Enrichment Facility

Pre-application Meeting with the NRC May 21, 2007

1 Participants

X Michael McMurphy, Executive Sponsor X Sam Shakir, General Manager, Strategic Enrichment Program X Nicolas DeTurckheim, Project Director, George Besse II X George Harper, Technical Director X Bob Poyser, Project Manager, Site Selection X Antoine Genevois, Project Legal Council X Jim Curtiss, Winston & Strawn X Tyson Smith, Winston & Strawn

AREVA NC 2 Contents

1. Overview of Michael McMurphy 2. AREVA’s Enrichment Operation Nicolas DeTurckheim 3. Why the U.S. Needs Additional Enrichment Capacity Sam Shakir 4. Overview of the New U.S. Project George Harper 5. The Project Structure Sam Shakir 6. Site Selection Bob Poyser 7. International Government Agreements Jim Curtiss 8. Licensing Approach Sam Shakir 9. Tails Management Sam Shakir 10.Proposed Pre-Application Schedule Sam Shakir 11.Wrap Up Sam Shakir

AREVA NC 3 Our Long Term Business Objectives

X Meet our strategic business plan of expanding the U.S. commercial nuclear infrastructure to ensure safe and secure supply of CO2 free nuclear energy X Provide domestic US supply to meet the growing demand for enrichment services X Our aim: Š Build a new enrichment facility in the U.S. using the ETC centrifuge technology Š Start production in 2013 Š Initial plant capacity of 3 million SWU per year

AREVA NC 4 Key Considerations

X Key considerations for this significant investment in US infrastructure 1.Short and predictable licensing process 2.Customer commitments to plant output 3.Supportive host state and community 4.Access to US tails disposal route

AREVA NC 5 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. International Government Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 6 Overview of AREVA

X World leader in the energy business

Š Number 1 in the entire nuclear cycle

Š Number 3 in electricity transmission and distribution

X Our mission

Š Enabling everyone to have access to ever cleaner, safer and more economical energy

AREVA NC 7 An integrated offer serving energy professionals

Enrichment Fuel fabrication Reactors Renewable energies

Chemistry

Recycling MOX fuel Mining fabrication

Used fuel treatment Services Transmission OTHER SOURCES OF ELECTRIC POWER

Distribution

Front End Reactors and Services Back End Transmission & Distribution Division Division Division Division

AREVA NC 8 Key data for 2006

Sales revenue by division Sales revenue by business (in %) (in %)

Total sales: $14B Employees: 61,100

32% 26% 34%

66% 19% 23%

Front End Division Back End Division Nuclear

Reactors and Services Division Transmission Transmission and Distribution & Distribution Division

AREVA NC 9 AREVA across the globe

41 countries 100 countries Production & Manufacturing Marketing & Sales

EUROPE & CIS

62% of sales - Nuclear: 76% -T&D: 24% 73% of employees

NORTH & SOUTH AMERICA

17% of sales - Nuclear: 67% ASIA-PACIFIC -T&D: 33 % 12% 14% of sales of employees AFRICA & - Nuclear: 47% -T&D: 53% MIDDLE EAST 11% of sales 7% of employees - Nuclear: 9% -T&D: 91% 4% Production & manufacturing of employees

AREVA NC 10 Organization of the group

TRANSMISSION FRONT END REACTORS & SERVICES BACK END & DISTRIBUTION division division division division

• Mining • Plants • Treatment • Products • Chemistry • Equipment • Recycling • Services • Nuclear Services • Enrichment • Logistics • Systems • Nuclear Measurement • Fuel • Clean-up • Consulting • Automation & Information Systems • Engineering • AREVA TA • Renewable Energies

AREVA NC 11 Front End division

X All of the activities leading up to the generation of :

Š Uranium exploration and mining Š Uranium conversion and enrichment Š design and fabrication

$3.8B Sales

11,995 Employees

AREVA NC 12 Reactors and Services division

X Design and construction of nuclear power plants and of biomass plants

X Inspection, servicing and retrofitting of all reactor types

X Heavy component design, manufacturing and replacement

$3B Sales

14,936 Employees

AREVA NC 13 Back End division

X Solutions for used fuel treatment and recycling of reusable materials X Solutions for used fuel storage X Facility decommissioning at the end of service life

$2.5B Sales

10,697 Employees

AREVA NC 14 Transmission & Distribution division

X Design, manufacturing and installation of high and medium voltage equipment and systems X Development and installation of grid control systems

$4.8B Sales

22,988 Employees

AREVA NC 15 U.S. Locations

Seattle, WA (293) Richland, WA (636) AREVA T&D AREVA NP (571);AREVA NC Meriden, CT (361) Canberra (53);Canberra (10); Transnuclear (2) Chicago, IL (21) Toronto, Canada Tacoma, WA (21) (60) AREVA NP (17); Transnuclear AREVA NP Marlborough, MA (85) Canberra (4) Dover, NJ (53) AREVA NP • Canada Ltd Canberra Idaho Falls, ID – (16) • Denver, CO (15) AREVA NP (1); • Pittsburgh, PA (20) Canberra (14); AREVA NP (7), AREVA NP Westborough, MA Transnuclear (1) Canberra (8) (13) Columbia, MD (51) AREVA NP • Charleroi, PA (162) Medford, OR (124) Transnuclear • • • AREVA T&D •• AREVA T&D-Sold 12/6 • Mills, WY (23) • • Philadelphia, PA (46) Benicia, CA (45) • • • • • AREVA NP(8); AREVA AREVA NP Cogema Mining, • Bethlehem, PA (61) • T&D(38) • Cogema Resources, • San Jose, CA (10) • AREVA T&D Pathfinder Mining Erwin, TN (9) • Lynchburg, VA (1,512) AREVA T&D AREVA NP (4 AREVA NP locations) • • • Modesto, CA (4) ••• • Oak Ridge, TN (25) Charlotte, NC (501) Canberra Canberra Washington, DC •• AREVA NP /Bethesda, MD (49) • Los Alamos, NM (14) AREVA (15); AREVA Ft. Worth, TX (52) • Canberra NC (34) Aiken, SC – (55) AREVA NP Atlanta, GA (44) AREVA NP (1); Albuquerque, NM (87) • AREVA NC (48); AREVA NP (42); • AREVA NP (4); Canberra (3); Houston, TX (3) Canberra (2) Canberra (83) Transnuclear (3) AREVA T&D • Waynesboro, GA (134) Rockledge, FL (5) 45 Locations Bruni, TX (3) AREVA T&D AREVA T&D 4,613 Employees Cogema Mining

AREVA NC 16 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. International Government Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 17 Enrichment Experience

X 1973: establishment of , AREVA’s affiliate in enrichment business

X 1974: Start construction of the GB-I plant, based on technology

X 1979: Start commercial operation and supply the first SWU

X 1982: Completion of GB-I

X 1984: First supply of SWU to US utilities

X Today: 190 million SWU have been supplied, including 26 million SWU to US market

AREVA NC 18 The Eurodif Enrichment Plant

Control Blending Eurodif UF6 Annexe

Single •Capacity 10.8 MSWU/yr cascade •In operation for 29 years without 4 plants interruption

•190 MSWU produced

GBll •UNAT maximum 5% South unit •No major technical or safety problems

•Will be decommissioned due to economical effects (electricity)

AREVA NC 19 The Creation of ETC Joint Venture Between AREVA and URENCO

Etat RWE BNFL AREVA NL +E.on

33% 33% 33% ETC(1) ( URENCO-AREVA JV) 100%

New 50% 50% URENCO Design AREVA NC (Holding) Manufacturing Technology R&D 100%

Centrifuges Centrifuges UEC – URENCO SET Enrichment services & services & services « GBII Project » Sales & Marketing Enrichment services

(1) Enrichment Technology Company

AREVA NC 20 The GBII plant An investment …

X … essential to the global SWU supply demand balance Š At least 7.5 MSWU in a context of increasing demand

X … based on the best existing technology Š A worldwide reference technology that will be implemented in all enrichment facilities within 10 years

X … with a modular capacity to adapt to market future needs Š 7.5 MSWU to 11 MSWU

AREVA NC 21 GBll Time Schedule

• AREVA - URENCO signature November 2003

• Preliminary safety report June 2004

• Public hearing September 2004

• Technical safety approval by ASN June 2005

• Public inquiries June 2006

• Cardiff treaty (F UK D NL) ratification July 2006

• Start of construction September 2006

• GBll Nuclear license 8.2MSWU/yr -Max 6% April 2007

• 1st cascade on line 1st half 2009

AREVA NC 22 ‰ 4 MSWU/yr GB II South Unit

‰ TC12 Centrifuges

‰ U235 limit 6%

1 module (0,5 MSWU/yr)

Centrifuge assembly building

Centrifuge utility building

AREVA NC 23 GBll Construction

P Eurodif Plant roce co ss Centrifuge rri UF6 building dor assembly Feed, Product, Tails building

Centrifuge slab

AREVA NC 24 5 Minute Video The GB II Project

25 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. International Government Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 26 Unbalanced Demand and Supply A Clear Market Argument

X US needs : 12.7 M SWUs to 15.5 M SWUs/year (WNA reference scenario) X Today the US relies on imports for more than 90% of their enrichment needs X Russian HEU provides 50% of the US demand, but the HEU agreement expires in 2013 X US domestic production: Š NEF-LES (start up in 2009 but fully committed), Š USEC ACP to replace GDP (No added capacity)

z Only a small part of the current USEC GDP production is sold to US customers. The rest is exported to Asia X The US demand is larger than the capacity of NEF + ACP + AREVA US plant. X The shortfall has to be imported or be fulfilled by additional domestic capacity

AREVA NC 27 Additional Domestic Capacity is Necessary

X To cover some of the significant shortfall in domestic supply and reduce reliance on imports, an important US energy security objective X Maintain a viable, competitive, domestic uranium enrichment industry X To help the US achieve our non-proliferation objectives by being in a position to meet the needs of non fuel cycle countries that want to adopt or expand nuclear energy X Building the US nuclear infrastructure to support and sustain a

AREVA NC 28 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. International Government Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 29 Overview of U.S. Plant

X Plant will be designed to enrich commercial natural uranium

X Plant initial capacity is 3 MSWU

X

X Feed will comply with ASTM C 787-03, “Standard Specification for for Enrichment”

X

X Š

AREVA NC 30 Overview of U.S. Plant

X

AREVA NC 31 Overview of U.S. Plant

X Each module will have a service life of 20 years as estimated by ETC

X The cascades will be earthquake resistant to a specified level for investment protection

AREVA NC 32 Separation Module

UF6 UF6 UF6 Feed Tail Product Feed Depleted Enriched exit exit Process corridor 8 - 12 Cascades/module 1 module

AREVA NC 33 Separation Module

UF6 Annex

Enrich UF6

UF6 cooling Cooling box with cylinder with enriched UF6 Heating Gas / Solid sub atmospheric pressure Feed station with UF6 cylinder Solid / Gas sub cooling Depleted UF6 atmospheric Cooling box with cylinder pressure with depleted UF6 Gas / Solid sub atmospheric pressure

AREVA NC 34 Overview of U.S. Plant

X Main plant structures

Š Centrifuge Assembly Building (CAB)

Š Utilities, Control and Service Building

Š Centrifuge Modules

z Hall of 8 – 12 cascades

z UF6 Annex for feed and take-off operations

z Half an inter-module corridor

Š Blending and Liquid Sampling Area

z Includes laboratory

AREVA NC 35 Overview of U.S. Plant

X Main plant structures (continued)

Š Cylinder Receipt and Dispatch Building

Š Electrical Equipment Room

Š Cylinder Storage Yard

z Empty UF6 cylinders

z Feed Cylinders

z Tail Cylinders

AREVA NC 36 Overview of U.S. Plant

X Utilities required for operation and CAB support

Š Cooling water

Š Compressed air

Š Nitrogen

Š Demineralized water

Š Potable water

Š Electrical distribution

AREVA NC 37 Overview of U.S. Plant

X UF6 Cylinders Š Feed and tail cylinders will be of 48-inch type

Š Either 48Y or 30B cylinders will be used for product take-off

AREVA NC 38 Overview of U.S. Plant

X Cylinder Logistics

Š Receipt, shipment, weighing and overpacking operations will be performed in the CRDB

Š Liquid sampling of all Product cylinders

Š Leak tests on 30B cylinders prior to filling

Š Leak tests on 30B cylinder needle valves prior to shipment

AREVA NC 39 Overview of U.S. Plant

X Operation

Š Plant operation and staffing will be developed using input from ETC and GB II

Š Installation and start-up tests

z Factory acceptance tests (FAT) at manufacturers

z Site acceptance tests (SAT) by suppliers

z Integration tests by main contractor, suppliers and operator

z UF6 tests by operator with ETC for cascades Š Radiological protection integrated into design through ALARA principle

AREVA NC 40 Overview of U.S. Plant

X Safety

Š Based on 10CFR70, precedent and design principles of NEF and GBII plants

X Inspections

Š NRC

Š IAEA

Š Supported by precision scales, autoclaves for homogeneous sampling and physical traceability of nuclear materials

AREVA NC 41 Overview of U.S. Plant

X Decommissioning Strategy

Š Dismantling, decontamination and disposal defined for each type of equipment

Š ETC responsible for centrifuges and piping

X Training

Š Theoretical and practical training by ETC for core team at GBII Plant

Š On-site training at AREVA U.S. Plant

Š Simulator

Š Centrifuge assembly training by ETC

AREVA NC 42 Overview of Technology

X

X

X CAB facilities and utilities will be supplied by AREVA based on ETC specifications

X Tools required to assemble, check and assess centrifuges will be supplied by ETC

X ETC responsible for conveying components and assembling centrifuges in CAB

X ETC in charge of centrifuge transport from the CAB to modules and installation

AREVA NC 43 X Š

AREVA NC 44 Building on Existing Experience

X We have a good starting point

Š Reference plant – (Almelo vs GBII)

Š Licensing precedent exists today

Š Leverage publicly available licensing data from recent NRC licenses (ISA Summary, ER, SAR, etc..)

Š US based AREVA resources with licensing experience

Š Experience of NRC with ETC technology

AREVA NC 45 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. International Government Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 46 A Partnership Structure

X X X X This US company will be the applicant for the license and ultimately the license holder for the enrichment facility X The US company will be formally in place by Q3 2007

AREVA NC 47 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. International Government Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 48 Site Selection

X Aim: Select a site by end of 2007

X Status: Award contract to perform site selection study in next 30 days X Follow 10 CFR 51 requirements X Utilize a multi attribute utility method Š EPRI Siting Guide Š NUREG-1520 Š NUREG 1478 X Incorporate lessons learned from LES and other nuclear facility site selection activities

AREVA NC 49 The MAUA Process

»Multi-Attribute-Utility Method

Final Site Community/political Selected support CRITICAL to site selection Phase II – Screening •Operational Requirements •Environmental Acceptability •Schedule for Commencing Operations •Operational Efficiencies

Phase I – Screening

Seismology/Geology Land Not Contaminated Site Characterization Surveys Size of Pilot Redundant Electrical Power

Initial Prospective Sites

AREVA NC 50 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. Approach to International Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 51 Key Objectives

X As with LES’s National Enrichment Facility, the proposed AREVA facility would be subject to and would abide by the all applicable U.S. laws and regulations, including export licenses and controls of sensitive nuclear technology. X Maximize use of the existing international agreements to facilitate a framework consistent with the framework used by LES and to expedite the project schedule.

AREVA NC 52 Existing International Agreements

X Treaty of Almelo (1970) – This agreement permits the UK, Germany and the Netherlands to collaborate on and jointly develop centrifuge enrichment technology through Urenco. X Washington Agreement (1992) – This agreement between the US and the parties to the Treaty of Almelo establishes a framework for the transfer of centrifuge enrichment technology into the US in connection with the construction of a uranium enrichment facility by Urenco. X Cardiff Agreement (2006) – This agreement between and the parties to the Treaty of Almelo establishes a framework for collaboration, through Enrichment Technology Company, Ltd. (“ETC”), with respect to all aspects of centrifuge enrichment technology previously held by Urenco. Š The Agreement provides that the Cardiff Quadripartite Committee must approve a transfer of technology to a non-Cardiff country, including the U.S. Š The Agreement recognizes the Washington Agreement and commits to honoring all its requirements. Š The Agreement also explicitly recognizes that Urenco and AREVA may elect to develop additional enrichment facilities beyond those contemplated at the time of the Agreement.

AREVA NC 53 FORMATION AND ROLE OF ETC

UK NL GER FRA

ALMELO TREATY 1970

CARDIFF Agreement 2006

URENCO AREVA 50 50 ETC

Centrifuge Centrifuge Centrifuge Centrifuge R&D Manufacture Installation Technology

54 ETC PROJECTS ETC, provider of centrifugation technology for all the projects

URENCO AREVA 50 50 ETC

Contracts for technology, centrifuges, and associated services

Urenco Europe Urenco US LES NEW AREVA US AREVA France plants plant plant GBII Plant

AREVA NC 55 X

AREVA NC 56 X

AREVA NC 57 X

AREVA NC 58 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. Approach to International Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 59 Organization

X X The project organization is being assembled X A Licensing Manager will be assigned to the team in the next two months. That individual will become the NRC point of contact X Interim Licensing Manager is Sam Shakir, AREVA NC Inc

AREVA NC 60 Applicable Regulations and Guidance

X Two main regulations: Š 10 CFR 40: Domestic Licensing of Source Material Š 10 CFR 70: Domestic Licensing of Special Nuclear Material X 10 CFR 40 and 10 CFR 70 require Š Compliance with 10 CFR 51 “Environmental protection regulations for domestic licensing and regulatory functions” Š Compliance with 10 CFR 95 “Facility security clearance and safeguard of national security information and restricted data” X Guidance Documents: Š Regulatory Guide 3.25 “Standard format and content of Safety Analysis Reports for Uranium Enrichment Facilities” Š NUREG – 1520 “Standard Review Plan for a License Application for a Fuel Cycle Facility” Š NUREG – 1513 “Integrated Safety Analysis Guidance Document”

AREVA NC 61 Proposed Timeline

X Pre application review Starting in May 2007 X Site selection Q4 2007 X License application Q2-Q3 2008 X NRC Final Decision Q2 2010 X Site preparation Q2 2010 X Start construction Q3 2010 X First 0.5 MSWU production 2013 X Reach 3 MSWU/yr 2017

AREVA NC 62 Application Schedule

X Pre application review: ………………………….May 07-April 08 X Application submittal: …………………………..June/July 2008 X Propose NRC complete technical/ environmental review……….……………………12-15 Months X Complete hearings and NRC decision………..Q2 2010

AREVA NC 63 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. Approach to International Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 64 Tails Management Strategy

X Conversion and disposal of the byproducts by a private, commercial company Š A conversion facility will not be part of the enrichment plant license application Š AREVA owns a conversion technology

X DOE disposition of tails in accordance with Section 3113 of the USEC Privatization Act

X Both approaches were deemed “Plausible” in the LES license

AREVA NC 65 Contents

1. Overview of AREVA 2. AREVA’s Enrichment Operation 3. Why the U.S. Needs Additional Enrichment Capacity 4. Overview of the New U.S. Project 5. The Project Structure 6. Site Selection 7. Approach to International Agreements 8. Licensing Approach 9. Tails Management 10. Proposed Pre-Application Schedule 11. Wrap Up

AREVA NC 66 Pre-Application Schedule

X June 07: International agreements X Aug 07: Information Security X Sep 07: Codes and Standards X Fall 07: AREVA would like to invite the NRC to visit the GB II facility currently under construction to learn about the features of this facility which will be a reference facility for the US plant X Additional meeting to be scheduled later as we progress through the initial phase of LA preparation

AREVA NC 67 Wrap Up

X Our aim is to expand our domestic nuclear infrastructure and to meet the increasing demand for enrichment services X The project is strongly backed by the industry X X The recent licensing of 2 enrichment facilities by the NRC provide an excellent starting point for this application X AREVA will leverage it’s financial strength and our large US based engineering and operational expertise to successfully execute this project X Our expertise on the GB II facility adds to our confidence X An assured and predictable licensing process is a key consideration

AREVA NC 68