ITU Capital Projects Master Project List and Activities 09/21/2012 (Priority Action in Red) ( = New Information)
Campus Drive West Campus Connector Road Brad Glatfelter______ Precon meeting attended this week. Design/Build project. Design “Charette”(planning input) meeting for bridge over Rt. 123 and throwing field south of Field House attended this week. More segment design meetings in following weeks. Scope includes construction of restrooms, maintenance building, tennis courts, pavilion and various athletic fields. Plans on Facilities Docushare. Site work likely to begin in the 4th quarter.
Conservation Studies Program Residence (Front Royal) Nancy Pickens Alt. Thursdays 10:30 . Smithsonian partnership – 128 bed Housing, Dining Hall and Academic Building. NET has resolved major student wireless access issues. Updated deficiencies list sent to GC. Cable TV installed.
Fenwick Library Expansion Brian Snyder
. Occupancy August 2014. Project funding commitment in place. Net Eng met with General Contractor, Civil Engineer and PM. IT infrastructure design drawings issued for comment and pricing. Net Eng developing scope of reconnection work this week to provide GC for pricing. IT wiring design to be managed by AE
Fine Arts Renovation Hieu Tran Alt. Wednesdays 10:00 . Substantial completion is May 10, 2013. Construction schedules posted on Docushare. Net Eng determined path for replacement Johnson Center loading dock security camera. IT wiring likely in November. Awaiting cabling submittals. Will conduct a pre-construction meeting prior to cable work starting. Site requirements: check in with Mason Inspector and wearing hardhat, neon vest, glasses and boots.
Housing VIIIB Shenandoah Nancy Pickens . Construction start 01/13. 300 Freshman beds in Presidents Park area. Completion expected Summer 2014. RFP respondent’s interviews two weeks ago.
PWC PPEA Life Sciences Building Micky Boeckl Alt. Wednesdays 10:00 January 2013 completion. 75,000 square feet, 3 stories, BSL II. Second story pour underway. 60% drawings on Docushare, they are responsive to our comments, details should be reviewed OSP conduit installed.
PWC PPEA Graduate Dorm - Beacon Hall Micky Boeckl Alt. Wednesdays 10:00 . Planned building turnover of October 19 with move in on October 20. OSP and life safety line requirements questions resolved with contractors. Look for switch install the week of October 8, if floor TRs are available TR work is underway, racks being installed, OSP planned for this week. Upper level student housing – 152 beds, 4 stories, above a floor of 10,000 GSF Mason space and 15,000 GSF retail space with 212 parking spaces.
Point of View Center Nancy Pickens______. Startup planned for September, completion in one year. Network site provider connection proposal and costs needed.
ITU Project Engineering: A. Norcott/J. Callahan 5/3/18 County requirements for sewage treatment worked out.
Science and Tech II Addition/Renovation Alex Iszard Tuesdays 11:00 . Substantial completion 3-23-2013. Classroom use in fall 2013. S&T II is now Exploratory Hall. . From Facilities “Project Partners” meeting, planned move is week of May 20, 2013. Mason Proj. Manager called for General Contractor to have telecom rooms complete on January 15, 2013. Telecom room termination in progress. AV Scope nearly complete. Site requires Safety Orientation, helmet, vest, glasses, and hard shoes; access via trailer check in only.
SUB I Dining Renovation Nancy Pickens Wednesdays 12:30 Taco Bell opens Tuesday, 9/18. All University Card office (photo ID and Mason Money) moves in late October.
University Commons Renovation Hieu Tran Tuesdays 11:00 Hanover BCOM 9/27. Furniture 10/8. Horizontal cabling should be finished next week. Fire alarm dial tone installation next week. Plan for switch install if the room is ready.
Farther Out and Smaller Projects
Shenandoah Dining Expansion Hieu Tran Schematic closer to approval and completion. $8 million project. Construction likely concurrent with Housing VIIIB. Possible Fall 2014 completion.
Housing VIIIB Rappahannock Nancy Pickens . Completion planned Fall 2015. Located north of Fenwick, partially on Lecture Hall site. RFP being prepared. Currently 210 beds, 13 classrooms. Mixed use of housing, classroom and academic center. Ductbank relocation part of the plan.
Field House Renovation Alex Iszard WAP installation completed.
University Hall Retail Fit-out Kim Greene
Einstein Bagels construction underway. Anticipate October opening. Net Infrastructure will do assessment. Everlasting Café – possibly January.
Tyson’s Corner Leased Academic Space
Project on hold per VP of Facilities.
Belmont Bay Alex Iszard Has been approved by DPB for PPEA. Land arrangement must be obtained.
ITU Project Engineering: A. Norcott/J. Callahan 5/3/18