Minutes of the 89th meeting of the Committee Constituted for Deciding the Consent under Orange Category, held on 11.12.2008 in the Conference Room of Chairman, DPCC.

The following persons attended the meeting: 1. Sh. J. K Dadoo, Chairman DPCC 2. Dr. Anil Kumar, Member Secretary, DPCC 3. Sh. S.K.Gupta, Head Chemical Engineering Deptt. ,IIT Delhi 4. Sh. B. Kumar, SEE, DPCC 5. Sh. A.N. Singh, Scientist, Dept. of Env,. GNCTD. 6. EEs of CMC – I, II & III/PGRC. 7. AEEs of PGRC. 8. AEEs and JEE of CMC – I, II & III.

Sh. A.N. Singh, Scientist, Dept. of Env., GNCTD was asked to attend the meeting in place of Sh. M. Dwarkanath, SSO, Dept. of Env., GNCTD as he is on training abroad.

Following decisions were taken in the said meeting:-

Agenda Item No.1- Personal hearings

(i) DLF Ltd., Group Housing Society at E Block, G.K-II

The unit came for personal hearing today and has filed a letter of compliance. SIT to inspect and report. Call on 14.01.2009.

(ii) Jai Bhawani Enterprises/ Bhawani Printers, D-21/6, Okhla Indl. Area, Phase II, Delhi

The unit came for personal hearing today. It is supposed to file a letter of compliance of the deficiencies noted. Call on 14.01.2009.

(iii) Asrani Inns and Resorts Pvt. Ltd., (construction of 'JMJ' Hotel'), Wazirpur District Centre, Delhi

The unit came for personal hearing today and says that its Chief Executive Officer was pre-occupied. The decision of the Committee will be informed to the unit in due course. Call on 14.01.2009.

(iv) Mera Baba Reality Associates Pvt. Ltd., Plot No A-1, District Centre, Wazirpur (Netaji Subhash Place), New Delhi

The unit came for personal hearing and filed a letter. It has applied for environmental clearance but not yet received it. Unit states that STP plant has been installed. Let the unit come with environmental clearance on 07.01.2009. Call on 07.01.2009.

(v) Naman Buildcon Ltd Proposed Commercial Complex Namely Pacific Mall at Khyala New Delhi

Nobody came for personal hearing from DMRC. Prosecution proceedings will be continued. Call on 14.01.2009. (vi) Mangla Shree Properties (P) Ltd., D-1669, DSIDC, Narela Industrial Area, Delhi

The unit came for personal hearing today. It claims that it has done only 1/3rd of the excavation and therefore should be treated leniently. The Committee deliberated on this issue and decided to impose Rs. 1 Lakh by way of Environmental Damages and Rs. 1 Lakh by way of Bank Guarantee valid for three years which may be filed by 23.12.2008. If it does so, Consent to Establish will be issued immediately. Call on 23.12.2008.

(vii) Vardhman Land Developers Private Limited Pushpanjali Promoters Private Limited Construction of TDI Mall , Plot no 11, Shivaji Place, District Centre, Rajouri Garden, New Delhi

The unit did not come for personal hearing today. Issue fresh notice for personal hearing on 23.12.2008 at 6.15 PM.

(viii) D.D. Properties Pvt., Plot No 68 & 68/1, Najafgarh Road, Delhi

The unit came for personal hearing today. It has two live applications for environmental clearance and should immediately withdraw its environmental clearance application from MOEF in view of SEIAA notified for Delhi and pursue its environmental clearance application before the SEIAA. Call on 14.01.2009.

(ix) Construction of office complex "Anupam Tower Complex", 23-A, Najfgarh Road Indl. Area, New Delhi by M/s BPTP Ltd.

The unit did not come for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(x) M/s D.J. Infrastructure Developers (P) Ltd, 201, Surya Kiran Building, K.G Marg, New Delhi

The unit came for personal hearing today and admits that it has undertaken the construction upto plinth level. The decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009

(xi) M/s ACG Hospitality Pvt Ltd, GL-13, Kocha Tower, Jail road, New Delhi proposed Hotel at IA, Sub Distt Centre, Hari Nagar , New Delhi.

The unit did not come for personal hearing today but sent a letter. The decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009 (xii) M/s DG Estate (P) Ltd, A-1/14, Paschim Vihar, Main Rohtak Road, New Delhi- 63 Proposed Hotel at IB, Sub Distt. Centre, Hari Nagar

The representative of the unit came for personal hearing today and stated that the concerned manager Mr. Tajinder Singh met with an accident who was to come for the hearing. The decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009

(xiii) M/s S.Chand & Co. Ltd 7361, Ram Nagar, Qutab Road New Delhi, Proposed Hotel at IC, Sub Distt. Centre, Hari Nagar, New Delhi

The unit came for personal hearing today. The decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(xiv) Negolice India Ltd. Construction of Residential Complex named "Victoria Gardens" at Ring Road, Azadpur, New Delhi

The unit came for personal hearing today. It seeks a lenient view in view of the fact that it has applied for Consent to Establish in 2007. SIT inspection shows excavation has been done and dust pollution has been created, no CGWA permission is taken and D.G. Sets operating without acoustic enclosure and without adequate stack height. The unit admits its mistake and Committee decided to impose environmental damages of 0.05 % of the project cost equivalent to Rs. 5 Lakhs and Bank Guarantee of Rs. 5 Lakhs valid for three years. If the unit submits the same, Consent to Establish may be issued across the table. The unit seeks one week time. Call on 23.12.2008.

(xv) Hilton Garden Inn, Plot No. 1 B - 4, Twin District Centre, Sec - 10, Rohini, Delhi – 85

The unit came for personal hearing today. It must submit the tree cutting permission before case of Consent to Establish can be entertained. Call on 23.12.2008.

(xvi) Construction of Hotel at Plot No 32, CBD Shahdara by Mahagun Hotels Pvt. Ltd., C-215, Vivek Vihar, Delhi-95

The unit came for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(xvii) Red Fox Hotel (a unit of Oriole Dr. Fresh Hotels P vt. Ltd.), Plot No 6, Community Centre, Kondli, Delhi

The unit came for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009. (xviii)Construction of Hotel at 4A District Center Mayur Vihar, IFCI Ltd., IFCI Tower, 61, Nehru Place, New Delhi-110019

The unit came for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(xix) Construction of Hotel at 4B-Mayur Vihar ,Antarctica Properties Co. Ltd., SV-12-13, Bhakaji Cama Place, New Delhi

The unit did not come for personal hearing and has not applied for Consent to Establish. The Committee strongly feels that in such cases DDA should be asked to cancel their allotment since the unit has not shown seriousness in the matter. MS to write to Vice Chairman, DDA accordingly. Call on 14.01.2009.

(xx) Construction of Hotel at Community Center Vivek Vihar Kunal Foods Products Pvt. Ltd., G-59, Aggarwal City Plaza, Plot No.17, Mangalam Place, Sec-3, Rohini, Delhi-85

The unit came for personal hearing today. SIT to inspect and report. Call on 14.01.2009.

(xxi) Construction of Hotel at Community Center Vivek Vihar Perfect Learning Pvt.Ltd. A-12, Swasthya Vihar, Vikas Marg, Delhi-92

The unit did not come for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(xxii) Construction of Hotel at Community Center Anand Vihar Best View Properties Ltd. C/o Eldeco Infrastructure & Properties Ltd. SV-12-13, Bhikaji Cama Place, New Delhi

The unit came for personal hearing and has not applied for Consent to Establish. The Committee strongly feels that in such cases DDA should be asked to cancel their allotment since the unit has not shown seriousness in the matter. MS to write to Vice Chairman, DDA accordingly. Call on 14.01.2009.

(xxiii)Construction of Hotel at 6A-Community Center Mandavali Fazalpur Spirit Hotels & Resorts Pvt. Ltd., 59, Pkt-2, Jasola, New Delhi

The unit came for personal hearing and has not applied for Consent to Establish. The Committee strongly feels that in such cases DDA should be asked to cancel their allotment since the unit has not shown seriousness in the matter. MS to write to Vice Chairman, DDA accordingly. Call on 14.01.2009. (xxiv) Construction of Hotel at 6B-Community Center Mandavali Fazalpur SS Infrastructure F-109, Aditya Arcade, Community Centre, Preet Vihar, Delhi-92

The unit came for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(xxv) Construction of Hotel at 6C-Community Center Mandavali Fazalpur Indo Green International 313-315, Vikas Deep Building, Laxmi Nagar District Centre, Delhi-92

The unit came for personal hearing today. Decision of the Committee will be communicated to the unit in due course. Call on 14.01.2009.

(xxvi) Construction of Hotel at Uday Estate Pvt. Ltd. 6, Alipur Road, Ganpati Apptt Civil Lines, Delhi-54

The unit came for personal hearing today. As per the record of the CMC meeting of 03.12.2008, the unit had not applied for Consent to Establish. Therefore, procedure for writing to DDA for cancellation of plots be undertaken. Call on 14.01.2009.

(xxvii) Construction of Hotel at A-1, Community Centre, Pitampura, Delhi by M/s Sita Kiran Inn Pvt. Ltd., 88-C, Civil Lines, Bareily (UP)

The unit came for personal hearing and has not applied for Consent to Establish. The Committee strongly feels that in such cases DDA should be asked to cancel their allotment since the unit has not shown seriousness in the matter. MS to write to Vice Chairman, DDA accordingly. Call on 14.01.2009.

Agenda Item No.2- PGRC cases.

Decisions taken with respect to this agenda are tabulated and annexed as Annexure – 1.

Agenda Item No.3- Special reference cases.

Decisions taken with respect to this agenda are tabulated and annexed as Annexure – 2.

Agenda Item No.4- Shopping Mall cases

Decisions taken with respect to this agenda are tabulated and annexed as Annexure – 3.

Agenda Item No.5- Construction Projects cases

Decisions taken with respect to this agenda are tabulated and annexed as Annexure – 4. Agenda Item No.6- CBI Cases

Decisions taken with respect to this agenda are tabulated and annexed as Annexure – 5.

Agenda Item No. 7- Levy of extra fee for the industrial units which have not obtained Consent to Establish.

A fresh agenda item may be put up in the next DPCC Board meeting clarifying the issue that no Consent to Establish can be exempted. MS, DPCC to draft the agenda item and put up.

Agenda Item No. 8-New item regarding restaurants operating in Khan Market area.

As regard the agenda item of Khan Market, SIT to inspect and report. Call on 21.01.2009 with clear data of waste water generation, hazardous waste generation and information about stack height and acoustic enclosure of the D.G. Set(s).

Agenda Item No 9: Examination of the issue of CGWA clearance by SEE

File be put up administratively.

Table Agenda Item No 01: Court case regarding units operating in Sultanpur Majra.

There is a court matter and SIT report shows that non conforming units are operating in Sultanpur Majra. Inform the court as per the decision of Hon’ble Supreme Court and send the list of the units along with the Court order to Commissioner of Industries and copy may also be sent to concerned Dy. Commissioner for appropriate action. If the units fall under F-27/33 category, send these to concerned Dy. Commissioner and if the units are other than F-27/33, send these to Commissioner of Industries.

Table Agenda Item No 02: Aditya Infracon (P) Ltd, at Plot no 8 Jasola District New Delhi

Call on 17.12.2008.

Table Agenda Item No 03: ABW Infrastructure Ltd 208-210, Rectangle -I , D-4, Saket Dist Centre, New Delhi

Call on 17.12.2008.

Table Agenda Item No 04:

All applications of existing construction projects of Delhi which are lying in MOEF must be withdrawn immediately, by MS, DPCC writing to Mr. Pandey, Advisor, MOEF so that there is no duplicacy of work in environmental clearance in SEIAA and MOEF. This must be done by next week positively. Table Agenda Item No 05:

All the agencies empanelled by DPCC, which are undertaking the work of adequacy report and effluent analysis report must be directed by MS to follow the complete procedure and ensure the following listed issues comprehensively:-

(i) ETP/STP should be based on best suitable treatment process such as biological / physio-chemical. (ii) ETP/STP should have proper piping arrangement, chemical dosing system with mixing device. (iii) Checking of treatment efficiency of individual unit of the ETP/STP. (iv) Checking of proper sludge management system. (v) Non availability of bypass to discharge untreated effluent. (vi) Complete recycling / reuse of treated water, if applicable. (vii) Checking of tertiary treatment process and plumbing system, wherever recycling / reuse facility is applicable.

This letter must be issued within a week.

Meeting ended with thanks to the Chair.

Sno. Name Activity Facts of The Case Earlier Decision Action Taken Decision on 11.12.08

1 Complaint against M/s Mfg. of As approved on file Notice u/s 31(A) of the Air Act, u/s 33(A) of the Water Act Decision on 05.11.08: Call Consent to Establish granted. J.S. Designers Pvt. Ltd Readymade and u/s 5 of EPA with a copy of DOV were issued on 02.07.08. Unit has on 10.12.2008 & others, Plot No. Garments with submitted reply along with affidavit. Noise monitoring report of two DG Sets 190, Patparganj Indl. washing and photographs on 27.06.08 and 11.07.08. Unit informed that deficiency has Area. been rectified, Cess amount has been deposited and requested to waive-off the BG.As approved, reminder letter issued to the unit for submission of BG. Unit has submitted reply to inform that deficiencies have been rectified and requested to waive off the BG.( BG not submitted).As decided in CMC on 30.09.08, letter was issued to the unit on 17.10.08 to file effluent analysis report.The unitsubmitted its reply 26.11.08 alongwith effluent analysis report issued by G.G.S.IP University.

2 Complaint against Trading & Inspection was carried out by Trainee Engineers on 02.07.08 w.r.t. a public Decision on 05.11.08: Issue Notice u/s 31(A) of the Air Unit may be asked for submit Geniun Photocopier, Repairing of complaint received from Sh. Narender Singhal through E-mail. During notice for closure. Call on Act for closure issued on Bank Gurantee of Rs. 10,000 111- Jeeven Villa, Photocopier inspection, M/s Geninun Photocopier was engaged in trading and repairing of 10.12.2008 17.11.08. The unit valid for one year to ensure air daryaganj, Delhi. machine photocopy machine. Waste toner is collected in the container. Soot particle are submitted its reply on pollution control in future. Call blow away into the ambient air by blower. Unit has no DG Set.As decided in 24.11.08 and informed that on 14.01.2009 CMC on 31.07.08, a notice under Air Act was issued on 26.08.08. No reply all the repairing activity are received.One more complaint received from the complainant on 17.09.08.As being done in enclosed area decided in CMC on 30.09.08, final reminder issued to the unit on 17.10.08. and the unit is observing all the norms and rules to keep air neat and clean. 3 Executive Club 439, Farm House Inspection was carried out by Trainee Engineer on 03.07.08. As decided in CMC Decision on 05.11.08: Final Final reminder for full Issue fresh reminder to file full Village Sahurpur,New on 13.08.08, the file was put up admistratively and as approved, letter was issued reminder for full compliance complaince issued on 17.11 compliance of the letter dated Delhi-110074. to the unit on 09.09.08 regarding installation of STP, reuse of the treated water, of CMC decision. Call on .08.Reply received on 17.11.2008 without any further apply for Consent to Establish, submit permission from Central Ground Water 10.12.2008 01.12.08 alongwith delay, failing which, action as Authority for using the ground water and correct all the deficiencies. The unit certificate of 82.5 KVA per law will be taken. Call on submitted it's reply and requested for grant of three months time to do the D.G Set issued by Bhaskar 14.01.2009. needful. As decided in CMC on 30.09.08, letter was issued to the unit on Power Projects Ltd. 17.10.08 to file adequacy report , noise monitoring report of D.G set and CGWA However , nothing has been clearance.The unit submitted its reply on 27.10.08 and informed that two D.G mentioned regarding Sets have been disposed off, there is no working tubewell etc. adequacy report, noise monitoring report and clearance from CGWA.

4 M/s Govinda Colors manufacturing With reference to a public complaint received from Sh. Sukhvinder Singh, the Decision on 05.11.08: Issue Final reminder issued on Call on 14.01.2009 Industries, E-102, of poster unit was inspected by SIT on 24.09.08 and as approved, notice u/s 33(A) of the final reminder for full 17.11.08. The unit Mayapuri Industrial colors. Water Act and u/s 31 (A) of the Air Act were issued to the unit on 13.10.08. compliance of CMC submitted its reply on area. Phase-ll, Delhi- decision. Call on 10.12.2008 18.11.08 informed that they 64. have installed hood & section arrangement, increase the stack height of D.G Set, having no trade effluent discharge and applying for CTE. 5 Adyar Anand Restaurant The unit was inspected by DPCC official on 10.05.08 w.r.t. a public complaint Decision on 05.11.08: Call Call on 14.01.2009 Bhawan,S-18, Main received from the residents of the area. As decided in CMC on 13.05.08, a letter on 10.12.08. Market Green Park was issued to the unit on 05.06.08 for installation of ETP, proper stack height with DG set and use of degradable plastic bags. As decided in CMC on 18.06.2008, reminder issued on 03.07.2008. The unit submitted it's reply on 14.07.2008 regarding correction of deficiencies and grant of three months time for installation of ETP. As decided in CMC on 13.08.08, the file was put up admistratively and as approved, a letter was issued to the unit on 09.09.08 regarding installation of ETP. No reply received.As decided on 30.09.08, final reminder issued on 17.10.08. The unit sumitted it's reply on 21.10.08 and informed that work for installation of ETP has been awarded and requested for grant of 2-3 months time for completion.

6 Ever Green Sweet Restaurant- The unit was inspected by DPCC official on 10.05.08 w.r.t. a public complaint Decision on 05.11.08: Sh. Quoting the exiting notification House, S-29 & 30, cum-sweet received from the residents of the area. As decided in CMC on 13.05.08, a letter B. Kumar, SEE to check the of CGWA, a proper notice Main Market, Green shop was issued to the unit on 05.06.08 regarding submission of CTE, operation of CGWA Acts & Rules and draftd by Sh. B. Kumar, SEE Park, New Delhi ETP and use of degradable of plastic bags. The unit submitted its reply on submit an agenda item on will be issued to the unit for 10.06.08 and applied for CTE on 09.06.08. As decided in CMC on 18.06.2008, this issued in the CMC held compliance by 14.01.2009. the unit was inspected on 09.07.08 and No deficiencies were observed.As on 10.12.2008. Call on 14.01.2009. decided in CMC on 13.08.08, the file was put up admistratively and as approved, a letter was issued to the unit on 17.09.08 regarding submission of BG of Rs. 50,000 under water act and permission from CGWA.The unit submitted it's reply on 30.09.08 along with BG of Rs 50,000 under Water Act and a copy of letter dated 29.09.08 submitted to the CGWA for clearance.As decided in CMC on 30.09.08, letter issued to the unit on 17.10.08.The unit submitted its reply alongwith copy of letter issued by Scientist D ,CGWA and informed that there no provision for clearance of old borewell. 7 State Bank of Indore, Bank The unit was inspected by DPCC official on 10.05.08 w.r.t. a public complaint Decision on 05.11.08: MS Letter was issud to the Issue reminder. Call on S-31, Main Market received from the residents of the area. As per the decision of Consent to write to General Manager, Deputy General Manager 14.01.2009 Green Park Management Committee (CMC) meeting held on 13.05.08 and 18.06.08, letters State Bank of Indore. Call on 21.11.08. were issued on 05.06.08 and 03.07.08 (copy enclosed) to state bank of India in on 10.12.2008 . Repy awaited. place of state bank of Indore due to typographical error. As decided in CMC on 13.08.08, the file was put up admistratively and as approved, a letter was issued to the bank on 09.09.08 for installation of proper acoustic enclosure and adequate stack height with the DG Set. No reply received.As decided on CMC on 30.09.08 , final reminder issued on 17.10.08.

8 Madras café, S-26, Restaurant The unit was inspected by DPCC official on 10.05.08 w.r.t. a public complaint Decision on 05.11.08: Ask Letter was issued to the unit Issue final reminder. Call on Main Market, Green received from the residents of the area. As decided in CMC on 13.05.08, a letter the unit to file effluent on 17.11.08 to submit 14.01.2009 Park was issued to the unit on 05.06.08 regarding installation of oil and grease trap. analysis report at inlet & effluent analysis report. No reply received.As decided in CMC on 18.06.08, final reminder issued on outlet of Oil & Grease Trap. Reply awaited. 03.07.08. which was returned back undelivered. The unit submitted its reply on Call on 10.12.2008 24.07.08 mentioning that the letter was received from the Deptt. and enclosed a newspaper clipping with the heading " Government 'generous' to restaurant owners, sweet-makers" . As decided in CMC on 13.08.08, a letter was issued to the unit on 09.09.08 for personal hearing on 17.09.08 before CMC which was returned back undelivered. The same was delivered by hand by Trainee Engineer on 17.09.08. The unit came for personal hearing 17.09.08.As decided in CMC on 30.09.08, final reminder issued on 17.10.08 . The unit submitted its reply on 07.10.08 and informed that oil & grease trap has been installed . 9 Complaint against House A public complaint was received from Sh. Devesh Singh, Jt. Chief Electoral Decision on 05.11.08: Call No further reply received . Issue final reminder. Call on industrial unit at H. Officer. Inspection was done on 15.04.08. The details of observation are as on 10.12.2008 14.01.2009 No. 5A Flag Staff under:- 1. The premises is being used for residential purpose and no under Road. Delhi 54 industrial activities 2. Adequate stack height & acoustic enclosure has been provided with 100 KVA DG Set installed at the roof top. Significant noise from the AC plant installed at the roof top. Notice u/s 31A of Air Act was issued on 24.04.08. Case is to be ratified by CMC. Noise monitoring report taken from DPCC Lab. which reveals that 1.1 dBA is exceeding from Ambient Air Noise Quality Std.As decided in CMC on 13.08.08, file was put up the administratively and as approved , a letter was issued on 05.09.08 regarding control of noise pollution. Reply received on 15.09.08 and informed that they are consulting experts to acheive zero difference of noise level during operation of the D.G Set and requested for grant of one month time.

10 M/s Sabka Bazar, (A Retail outlets The unit was inspected by DPCC official on 09.04.08 w.r.t. public complaint Decision on 05.11.08: Notice for closure u/s 31(A) PGRC Trainee to inspect and unit of Home Stores received from the residents of the area. As decided in CMC on 23.04.08, letter Issue notice for closure. Call Air Act issued on confirm whether the India Pvt. Ltd.) C- was issued to the unit for the correction of all the deficiencies. A similar on 10.12.2008 17.11.08.Reply received compliance is factually correct. 3/10, Ground Floor, complaint was also received through PGC on 29.04.08. Reply sent on 26.05.08. from the unit on 03.12.08 Call on 14.01.2009 Janakpuri, New Delhi- The unit was again inspected by Trainee Engineer on 24.07.08 and as approved, through it's council Sh. 110058. the unit was called for hearing on 20.08.08/ 22.08.08 before MS. On 22.08.08, Vinod Kumar one Mr. V.K. Singh, Advocate appeared without POA. As approved the unit was Singh,advocate, authorizing called for hearing on 03.09.08 before CMC. No one came for hearing on him to deal with the matter 03.09.08 and as decided by CMC, copy of complaint along with PGRC related to Pollution Control inspection report were sent to the unit on 22.09.2008 to submit its comments. No Committee. It has been reply received. As decided in CMC on 30.09.08, final reminder issued on informed that the public 17.10.08.No reply received. complaint was made by some rival group as there is no noise or air pollution coming out from the air conditioner(split). 11 Tivoli Garden Resorts with Reminder letter issued on 30.10.08 to file Adequacy report and CGWA Decision on 05.11.2008: The unit submitted Call on 14.01.2009 Resorts(A unit of TG Restaurant & clearance. However, a reply was received from the unit on 16.10.2008 informing Call on 10.12.2008. adequacy report issued by Leisure & Resorts P Banquette that they have applied to CGWA for permission to draw the ground water. It was G.G.S.IP University on Ltd) , Chattarpur, Hall also informed that the technical team of Guru Gobind Singh Indraprastha 05.11.08. Mehrauli, N. Delhi- 30 University has already inspected the ETP and the adequacy report will be submitted at the earliest after receipt of the same.

12 Complaint received Gym & SPA With reference to a public complaint received from Mr. A.K.Jain, inspection was Decision on 05.11.08: Issue Letter issued to the IP MS to talk I.P. University and from A.K.Jain against carried out by Trainee Engineer on 18.07.08, during the inspection, noise was reminder to I.P. University University on 17.11.08. sort this out. Call on Addiction Gym & observed from DG Set and ACs. A letter was issued to the Gym on 28.07.08 for to conduct the required Reply awaited. 14.01.2009. SPA submission of Noise Monitoring report w.r.t. ACs and DG Set within 15 days. monitoring in presence of The unit submitted its reply alongwith noise monitoring report on 20.08.08 for complainant and submit by ACs and DG Set. The ambient noise level are meeting the prescribed standrads. 10.12.2008. Call on However, the stack height of 1 meter is not adequate. The stack height for 40 10.12.2008. kVA D.G. Set should be atleast 1.28 meter from the roof top of the building/enclosure (if D.G. Set installed at roof top). A letter was issued to the M/s MBS Gymkhana to provide adequate stack height with the DG Set. A reply received from the M/s MBS Gymkhana states that they have already provided adequate stack height with the DG Set which was also mentioned in Noise Monitoring report. A letter was also issued to the Guru Gobind Singh Indraprastha University with a copy to the complainant, to conduct noise/air ambient monitoring in presence of complainant. No reply received. 13 Complaint against Sweet shop- With reference to a public compliant, the unit was inspected by DPCC officials Decision on 05.11.08: Ask Letter issued on 19.11.2008 Ask the unit to file an affidavit M/s. New Laxmi cum-mfg. of on 11.06.08. As decided on 18.06.08, a letter was issued to the unit of 02.07.08 the unit to correct all the to correct the deficiencies clariying all the correction of Sweet and snacks for the submission of CTE and BG of Rs 50000 under Air Act. The unit deficiencies noted in the SIT observed by the SIT .Reply deficiencies. Call on Confectioners in submitted its reply on 16.07.08 has applied for CTE on 16.07.08. The unit inspection report. Call on received from the unit on 14.01.2009 residential area of submitted the B.G of Rs 50000 on 19.07.08. As decided in CMC on 13.08.08 the 10.12.08 02.12.08 and informing that Mukherjee nagar case was put up administratively and as decided inspection was carried out by it has rectified all the SIT on 01.10.08. mentioned deficiencies.

14 Complaint against Mall and Joint inspection was carried out by Haryana Pollution Control Board and Delhi Decision on 05.11.08: Send Copy sent to District Town MS to talk to Gurgaon Waste water flowing Housing Pollution Control Committee on 03.07.08. During inspection it was found that copy to CTP, Haryana. Call Planner, Gurgaon on Authoirty, Call on 14.01.2009 from Haryana to Delhi Society the water coming beneath the Ambience Mall meet in barsati nallah and due to on 10.12.2008 17.11.08 with a copy to the from Ambience Mall, blockage cesspool has been formed in Delhi Govt. land area. The Ambience Mall Administrative ,HUDA. Gurgaon, Haryana. owner has been directed not to discharge any type of trade/Domestic Effluent directly or indirectly into the drain with immediate effect and submit undertaking in this regard.As per decision of CMC meeting held on 11.07.2008, letter issued to MS, HPCB and HUDA on 28.07.08. Talked with DCF(W) and it was informed that the concerned file is under submission. Further a letter has been received from the Scientist'C'-I(HQ), HPCB addressed to HUDA, Gurgaon. The file was put up administratively and as approved, reminder letter was issued to HPCB & HUDA on 05.09.2008. As decided by CMC on 17.09.2008, the file was put up administratively and as approved a letter was issued to HUDA on 13.10.2008. As decided in CMC on 15.10.08, case was to be put up in CMC on 24.11.08.Now, two representations have been received from M/s Ambience Mall and M/s Landmark Infracon Pvt. Ltd. which shows that they are alleging on each other with respect to the discharge of the effluent which is being collected in NCT of Delhi in a form of Cess pool. 15 BJCL-BRITE (Joint Construction As directed inspection of NH-1 in the stretch of Samaipur to Jindpur was carried Decision on 07.10.08: The The unit came for personal Call the GM, Projects for Venture) Work out by DPCC officials on 20.08.08.and as approved notice u/s 31(A) of Air Act unit came for personal hearing on 07.10.08 .As personal hearing on NH-1 (Stretch from was issued on 28.08.08. The unit submitted its reply on 02.09.08. As decided on hearing today. It confirms approved in the file letter 14.01.2009, if it does not Samaipur to Jindpur) CMC on 10.09.08 ,a letter was issued to the unit on 22.09.08 to appear before that it will submit a letter was issued to the unit on comply with the direction of CMC on 07.10.08 at 5:15 p.m . from its CMD clarifying that 04.12.08 to submit an CMC issued on 04.12.2008 no dust pollutiion or air affidavit regarding water pollution will be caused sprinkling trice a day.Reply while constructing the awaited. National Highway stretch from Samaipur to Jindpur. This letter must be filed by 11.10.08 and placed on record administratively so that final view may be taken in this regard. If this letter does not come by 11.10.08, orders for effective closure with the help of SDM will be issued immediately and CMD must be summoned on 15.10.08 for personal hearing. Sl.No Name of the unit Activity Earlier Decision, if any ATR/Remarks Decision on 11.12.2008

1 M/s RMP International, 03.09.2008 Letter issued. Call on 14.01.2009 A-51, Okhla Industrial Unit has applied for renewal of consent on 24.05.2007 under Green Reply received on 04.12.2008 stating Area, Phase-I, New Delhi- category. During inspection on 08.01.2008, it was found that unit is that partner of this company is out of 20 operating with oil fired boiler and washing activity. Therefore, unit station so requested 15 days falls under orange category and renewal of consent was refused on 26.02.2008 with Show Cause Notice u/s 31(A) of Air Act and 33(A) extension to apply for Consent to of Water Act. Establish application under Orange category. In view of the above, unit may be asked to apply for Consent to Establish under Orange category. Call on 30.09.2008 30.09.2008 Issue reminder. Call on 30.10.2008 05.11.2008 A speaking order may be passed to immeidatley file an application under orange category giving clear reasons and section of laws. Call on 10.12.2008

2 Rajdhani Floor Mills Pvt. Flour Mill 17.07.2008 Unit has obtained CTO on 12.09.2005 Ask the unit to install Rain Ltd., C-32, Lawrence The unit draws 6 KLD of ground water. Ask the unit to file CGWA (valid upto 15.04.2008) Water Harvesting System Road Industrial Area clearance. Call on 20.08.2008. Unit has applied for CTO(R) on and get itself registered in 21.08.2008 12.03.2008 vide I.D. No. 25164. CGWA and file the report. Let the unit be informed that the payment receipt is not a CGWA Letter issued. Call on 14.01.2009 clearance. Let him file the clearance. Reply along with CGWA clarification 30.09.2008 received. Ask the unit to file CGWA clearance. Call on 30.10.2008 SEE's examination report to be 05.11.2008 discussed. Call on 10.12.2008 after SEE examination on the issue of CGWA clearance. 3 M/s Carlos Elec 03.09.2008 Letter issued on 19.11.2008. Issue final reminder. Call on Industries, 54, C-7, Rama Send him a copy of the High Court order and ask him to comply with Reply awaited. 14.01.2009. Road, Najafgarh Road it and respond. Call on 30.09.2008. Indl. Area, New Delhi 30.09.2008 SIT to inspect and report. Call on 30.10.2008 05.11.2008 Ask the unit to install acoustic enclosure with the D.G.Set and proivde Emmission Control System (ECS) on mixer. Call on 10.12.2008

4 NCR Vehicles Pvt. Ltd., Servicing, 06.08.2008 Applied for CTE on 28.04.2008 vide I.D. Ask the unit to file effluent J-3, B-1, Extension, Repairing & The unit can be granted Consent to Establish if it has started the No. 25591. analysis report and apply for Mohan Cooperative Washing of operation only with installation of ETP. Let the unit confirm it Applied for authorization under HWM Consent to Operate also. Industrial Area Vehilces (Car) through an affidavit. Call on 29.08.2008. Rules on 28.04.2008 vide I.D. No. 4558. Call on 14.01.2009 28.08.2008 Final reminder issued. Call on 30.09.2008 with details of ETP. Reply awaited. 30.09.2008 Call on 30.10.2008 with compliance of ETP installation. 05.11.2008 Final reminder. Call on 10.12.2008 5 SAVERA ENTERPRISES, MFG. OF 27.9.2007 Letter issued. Issue reminder to the unit to PLOT NO 417, SECTOR-5, ALLUMINIUM Disconnection of electricity & water supply and cancellation of MCD license Reply awaited. confirm DJB supply. Call on POCKET-E, DSIDC PRODUCTS in the name of the unit.. 14.01.2009 INDUSTRIAL COMPLEX, (SHEETS, SLUGS & 18.02.2008 Bawana CIRCLE) Let the unit apply for Consent to Establish. 10.3.2008 Restore power / water supply and grant Consent to Establish. 01.5.2008 Inform unit that as per the Consent to Establish application, test report should not be more than 03 months old. Call on 03.06.2008. 11.06.2008 Issue reminder without waiting for minutes. Call on 25.06.2008. 25.06.2008 Call on 31.07.2008 with test report. 06.08.2008 Ask the unit to file a copy of CGWA clearance for ground water drawl. Call on 29.08.2008. 28.08.2008 Call on 30.09.2008 with CGWA clearance. 30.09.2008 Ask the unit to file CGWA clearance. Call on 30.10.2008 05.11.2008 Call on 10.12.2008 to confirm DJB supply.

6 Competent Automobiles Automobile service 28.08.2008 Letter issued. Ask the unit to replace the Najafgarh Road Ind Area, station Ask the unit to file fresh adequacy report. Call on 30.09.2008. Unit has submitted adequacy report. flow measuring device. Call New Delhi - 15 30.09.2008 on 14.01.2009 Call on 30.10.2008 05.11.2008 Call on 10.12.2008 for adequacy report. 7 Hotel Marina, G-59, Hotel 13.08.2008 Letter issued. Ask the unit to fully comply Connaught Circus, New Ask the unit to apply for Consent to Establish. Call on 10.09.2008. Reply awaited. with the directions issued on Delhi 10.09.2008 19.11.2008. Call on Call on 30.09.2008. 14.01.2009 30.09.2008 SIT to inspect and report. Call on 30.10.2008 05.11.2008 A letter may be sent to the unit asking for details of likely air /water/ noise polluton based on the large scale of renovation being done. The unit may also be asked to install Solar Water Heating System, Rain Water Harvesting System & CFL. Call on 10.12.2008

8 Apex Automobile Pvt. Servicing, repairing 30.09.2008 Applied for CTE on 11.07.2008 vide I.D. Consent to Establish issued. Ltd., 470, FIE, Patparganj & washing of two SIT to inspect and report. Call on 30.10.2008 no. 26417. Indl. Area wheeler vehicles 05.11.2008 Applied for authorization on 11.07.2008 Ask the unit to file adequacy report. Call on 10.12.2008 Ground water : Nil. Letter issued. Representation of the unit submitted to LG office received. 9 Prominent Hotel, 17.09.2008 Letter issued. Ask the unit to file clear Connaught Place, New The unit has filed a letter seeking renewal of consent. Ask the unit to Reply received. affidavit of all the Delhi -110001 apply for Consent to Establish. SIT may inspect and report by deficiencies noted by SIT 20.10.2008. Call on 20.10.2008. communicated to it. Call on 21.10.2008 14.01.2009. SIT to inspect and report. Call on 31.10.2008. 05.11.2008 The following deficiencies were noted by SIT be communicated to the unit for correction: (i) Mechanical mixing device with water arrangement need to be provided in the chemical dosing tank (separate for lime, alum and poly electrolyte). (ii) ETP log book should be maintained regularly. (iii) Sludge should be managed as per HWM Rules. (iv) Solar Water Heating system is required to be installed. (v) Stack height of D.G. Set needs to be raised as per norms. Call on 10.12.2008

10 Paradise Plastopack (P) Mfg. of Multi Layer 05.11.2008 As per CMC decision dated 05.11.2008, Issue authorization. Ltd., 57, Rajasthani Films & Rolls with Issue renewal of consent. Link HWM files along with this file. Call consent issued. Udyog Nagar, Delhi Printing on 10.12.2008. 11 Delhi International Airport 17.07.2008 File is under submission. Call on 21.01.2009 Airport Ltd As per emission standard for diesel engine (engine rating more than (Restructuring & 0.8 MW), there are three conditions (i) 14 Q0.3, Q = Total SO2 Modernisation of IGI emission from the plant in kg/hr. (ii) Minimum 6m above the Airport) building where generator set is installed (iii) 30m. As per details available the stack height of the D.G. Set of capacity of 1000 KVA, stack height is 5.8 meter above the roof level. The total stack height form the ground has not been mentioned which should be 30 meters. In view of the request for relaxation in stack height, the unit should install wet scrubber for all the D.G. Sets so that pollution should be controlled adequately. In such case, the stack height may be relaxed. Unit may file compliance report by 20.08.2008. Call on 20.08.2008. 21.08.2008 Ask the unit to comply with the conditions of the DPCC letter dated 24.07.2008 and not to deviate from the issue. Call on 17.09.2008. 17.09.2008 The unit has requested for time for six months. Committee felt that three months time will be appropriate. Call in CMC of November, 2008 end. 05.11.2008 Reiterate the earlier decision for compliance by 10.12.2008.

12 Taj Palace Hote, 2, Sardar Five Star Hotel 15.10.2008 Letter issued. Call on 14.01.2009 Patel Marg, Diplomatic SIT to inspect and report. Call on 24.11.2008 Reply awaited. Enclave, New Delhi- 24.11.2008 110021 SIT report indicates that while the water consumption is 700 KLD, ETP takes care only 450 KLD. The unit must explain what happens to the rest through a water balance chart. The unit may also indicate why solar water heating system capacity has not been utilized. Thirdly, the unit may also indicate why the treated waste water is not being reused. Call on 10.12.2008. 13 Indian Compressors Ltd. Air & Gas 18.07.2008(CMC Green) Unit has applied for CTO(R) on SEE to draft an appropriate 37, Okhla Industrt Compressors Seek clarification from DDA regarding the activity whether it falls 23.07.2007 vide I.D. No. 22648. reply to the unit based on under the list of negative activities as per MPD-2021. Unit has obtained CTO(R) on 14.07.2007 MPD-2021 and taking into (valid upto 19.12.2008) account DDA's letter and get As per CMC (Green) meeting, letter it approved administratively. issued on 14.08.2008 to DDA. Call on 14.01.2009 Letter has been received from DDA on 03.12.2008 along with the representation of the unit regarding categorization of the activity. S. Ref. Name & EC Status CTE Bult Up Water / Waste Total Date of Earlier Decisions ATR/REMARKS Decision on No No Address status Area Water details Project Commissioning 11.12.2008 Cost

1 SA- Vardhman Not submitted Not _ _ _ _ File is under File to be 16 Plaza, Plot no 3, submitted 13.08.2008 submission. submitted Motia Khan, Sh. Prem Kumar to handle administratively. Paharganj, Delhi this case in future. Call after court hearing in September, 2008.

17.09.2008 Call on 30.09.2008 after High Court hearing.

30.09.2008 File with High Court order be submitted administratively.

03.12.2008 For all these three cases of Vardhman, our advocate be consulted whether early hearing be sought as these malls are getting the benefit despite violation of all pollution control norms. Call on 10.12.2008. In other case of Vardhman Plaza of Motia Khan not listed today, similar action be taken. 2 SA- R G Complex, Not submitted Not 3990 sqm 10 KLD Not reported 20.07.06 Notice for closure SIT to inspect 17 Plot no 2, Motia submitted 24.11.2008 under process. and report. Khan, SIT noted the following Unit has filed a Call on Paharganj, Delhi deficiencies (a) Water write petition in 23.12.2008 consumption of 20 KLD Hon'ble High with approx. waste water Court. generation of 16 KLD Next date of without ETP & STP being hearing is January, installed. (ii) Borewell 2009. being operated without CGWA clearance (c) No rain water harvesting system installed (d) Adequate stack height for the D.G. Set not provided. In view of the above deficiencies, notice for closure be issued. Call on 10.12.2008. The notice for closure to be issued immediately without waiting for minutes. The unit has started water pollution without taking Consent to Establish thereby violating the provisions of Water Act & Air Act. 3 SA- RG City Centre, Not submitted Not 3990 sqm MCD : 10 KLD (in Not reported 29.05.2007 24.11.2008 Notice for closure SIT to inspect 18 Plot no 4, Motia submitted reply) / GW : 20 KLD SIT noted the following under process. and report. Khan, (as per inspection deficiencies (a) Water Unit has filed a Call on Paharganj, New report) / WW - 16 consumption of 20 KLD write petition in 23.12.2008 Delhi KLD without STP (as with approx. waste water Hon'ble High per inspection report) generation of 16 KLD Court. without ETP & STP being Next date of installed. (ii) Borewell hearing is January, being operated without 2009. CGWA clearance (c) No rain water harvesting system installed. In view of the above deficiencies, notice for closure be issued. Call on 10.12.2008. The notice for closure to be issued immediately without waiting for minutes. The unit has started water pollution without taking Consent to Establish thereby violating the provisions of Water Act & Air Act. 4 SA- Vishal Retail Not submitted Applied _ _ _ _ Letter issued. Issue fresh 26 Ltd., B-374, 31.07.2008 Reply awaited. reminder. Call Meera Bagh, Reminder for reply by on 14.01.2009 Paschim Vihar, 20.08.2008. Call on New Delhi 20.08.2008.

21.08.2008 Issue notice for clousre. Call on 17.09.2008

30.09.2008 SIT to inspect and report. Call on 30.10.2008.

05.11.2008 Ask the unit to increase the stack height of D.G. Set as per norms and confirm by 10.12.2008. Call on 10.12.2008

5 SA- Vishal Retail Not submitted Applied _ _ _ _ Letter issued. Issue fresh 28 Ltd., 26.05.2008 Reply awaited. reminder. Call 10209/10210, MS may write to Vishal on 14.01.2009 Padam Singh Retail Ltd. to confirm the Road, karol Water Cess amount paid Bagh, Delhi for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 20000 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.

31.07.2008 Reminder for reply by 20.08.2008. Call on 20.08.2008.

21.08.2008 Issue notice for clousre. Call on 17.09.2008

30.09.2008 SIT to inspect and report. Call on 30.10.2008.

05.11.2008 Ask the unit to increase the stack height of D.G. Set as per norms and confirm by 10.12.2008. Call on 10.12.2008

6 SB- Y.M.C CTE issued 39093.14 MCD-165 KLD 165 crore Consent to Unit may be 2 Buildmore pvt on sq m GW-40 KLD DIS.- 31.07.2008 establish issued asked to comply ltd construction 18.04.2008. 164 KLD Ask SIT to inspect w.r.t. Unit has applied for with of Commercial Applied for construction phase & CTO on 14.07.2008 Environment Complex at plot CTO on operation phase conditions vide I.D. No. 26445 Clearance's no 12 Laxmi 14.07.2008 of Environmental in the name of conditions fully nagar Distt Clearance and for Consent Gahoi Buildwell and install Centre (V3S to Operate application. Ltd. (Commercial composting Mall) Call on 20.08.2008. Complex). facility and Now applied for Solar Water CTO in the 21.08.2008 Heating System name of M/s SIT inspection has found in the mall. Call Gahoi Build certain deficiencies on the on 14.01.2009 Well Ltd. item-wise compliance of Environmental Clearance conditions. These deficiencies may be indicated to the unit for correction by 17.09.2008. Call on 17.09.2008.

17.09.2008 Call on 16.10.2008 in view of time requested.

15.10.2008 No action.

7 SB- Today Homes NA Not 18444.5(as 160(MCD)/ 74(WW) 57.84Cr. 2008 Letter issued on The request of 12 and Applied per letter) 21.10.2008 24.11.2008 giving the unit was InfrastructureLtd For The unit came for personal extension of time. considered and , Proposed Consent to hearing today. It is about to BG and cash the Committee Commercial Establish, complete it’s mall and STP penalty not is of the view Complex (North However within a few months. The submitted. that similary Gate obit plaza) had applied unit claims that it has However, letter placed units at Gujaarawala for NOC applied for Consent to submitted for must pay Town area of W.R.T EC Establish in 2006 after reduction of uniform Model Town-II, on 24-08- taking over partially built environmental Environmental New Delhi 06. The up premises from another damages & Bank Damages and same has builder. It has also installed Guarantee. Bank Guarantee. been an STP of 80 KLD In view of the forwrded to capacity to treat 74 KLD of above, unit may MOEF waste water. By this, the be directed to unit claims that it has fully comply proved its intentions of with the CMC treating waste water and decision dated also applied for the 21.10.2008. requisite permission from Inform the unit DPCC. The Committee accordingly. deliberated on this matter Call on and decided to grant some 14.01.2009 relief to the unit on account of its clear intentions. The unit will file environmental damages of Rs. 10 Lakhs and Bank Guarantee of Rs. 40 Lakhs valid for three years subject to the condition that solar water heating system will be installed before the mall becomes operational. The unit also to file the affidavit prescribed for Consent to Establish, since it is not available in DPCC’s file. Call on 06.11.2008 for compliance.

06.11.2008 Call on 17.12.2008 for compliance.

8 SB- Parsvnath NA 18/03/08 2550.465 MCD-17 KLD GW- 5.9 crore NA 30.09.2008 Letter for applying Point out the 14 Developers Ltd sq m NIL DIS.-7.68 KLD The unit came for personal for CTO issued on deficiencies in in construction hearing today. The unit has 25.11.2008. Consent to with M/s OCL completed the construction Unit has applied for Operate Ltd Commercial and but yet not started its CTO on 04.12.2008 application. Ask Complex at operation. Unit has to pay the unit to file Pratap Nagar damages as a cash penalty the same afresh. Metro of 0.5 % of the project cost Call on and 0.5 % of the project 14.01.2009 cost as Bank Guarantee valid upto three years by 30.10.2008. The unit agreed to do so. Call on 30.10.2008. 05.11.2008 Ask the unit to apply for CTO. Call on 10.12.2008 17.11.2008 CTE is issued only once. The unit should check its own premises properly as letter of CTE has not received back in DPCC. Ask the unit to apply for CTO. Call on 10.12.2008.

9 SB- Pragya Products _ Original Built up MCD : 193 KLD / 76.11 Crores Operational Letter issued on Call on 20 Private Ltd, application area : GW : Not mentioned / (as per latest 17.09.2008 21.11.2008. 14.01.2009 Construcion of dated 27265.42 WW : 54 KLD (as per CTE Let this case be put up Reply received on Commercial 26/04/06 sqm(as per latest CTE application) before SEIAA Committee 08.12.2008 stating Mall name Shop returned. latest CTE application) However, in its first meeting. Let the that they have in Park at Plot Now unit application) as per affidavit no unit be reminded to put up submitted the fee to no 2 Community submitted trade effluent the STP as per its DCE for adequacy Centre Blk B , CTE on discharge. commitment given in its report and noise Shalimar Bagh 07.08.2008 letter. Call on 30.10.2008 monitoring report. New Delhi , for compliance of STP As soon as they get, Pragya Products installation the same will be Private Ltd submitted. 05.11.2008 Ask the unit to file adequacy report of STP and noise monitoring report of D.G. Set. Call on 10.12.2008 10 SB- Mamram Magic _ 39692 888.62 sq MCD-1500 L/D GW- 7.99 crore CTE granted on SIT to inspect 23 Mall , Plot no 4, m 8 KLD DIS.-500 L/D 14.05.2008 23/05/08 and report. CS/0CF Sec-24 The unit appeared for the Call Ph-III Rohini, personal hearing and on14.01.2008 New Delhi-85 pleaded that it s a small unit and is not covered by Environmental Clearance. It also pleaded ignorance of Air & Water Acts and therefore applied for the same when instructed by DPCC. The unit pleaded for lenient treatment and has agreed in writing to submit Bank Guarantee of Rupees Five Lakhs. The Committee feels that since the unit is small and has accepted the mistake of not having filed the Consent to Establish application in time, the unit may be allowed to file a Bank Guarantee of 1 % of project cost which comes about Rupees Eight Lakh. Since, DPCC has rounded of such Bank Guarantees to the nearest Five Lakh, the unit is allowed to file, a Bank Guarantee of Rupees Five Lakh only, before 28.05.2008. If it does so, the Consent to Establish be issued to him at the same time and report to CMC on 28.05.2008. 28.5.08 No action. 15.10.2008 No action. 11 SB- Jaksons 08.07.2008 31/03/08 51393.57 231(MCD)+320(GW)/ 320 crores 2010 Letter issued. Call on 33 Developers Pvt. 347(WW) 21.08.2008 Cash penalty & BG 14.01.2009 Ltd.,, Plot No The unit has represented not yet submitted. 3B1, District against the damages and Centre, Sector- Bank Guarantee stating 10, Rohini, that it is a Common Wealth Delhi project. CMC has taken uniform decision for all projects including CWG projects and therefore no discrimination can be made in the eyes of law. Unit may be asked to comply with the CMC decision on 24.07.2008. and file the required damages and BG latest by 17.09.2008. Call on 17.09.2008.

17.09.2008 The unit came for personal hearing today and shows the letter of DDA whereby for the sake of Common Wealth project, they were asked to start the construction upto plinth level. This requires consultation with DDA and therefore, the matter be listed on 30.09.2008. Call on 30.09.2008.

07.10.2008 Call on 20.10.2008

21.10.2008 Call on 31.10.2008

05.11.2008 Call on 10.12.2008 12 SB- Commercial EC 88938.06 MCD - 116 KLD / 440 crores October, 2008 Letter issued on Call on 42 cum Multiplex received on sqm GW - Stand By / WW 28.5.08 04.11.2008 14.01.2009 Project by Yogi 23.10.2008 - 244 KLD Call on 03.06.2008. Reply awaited. Raj Promoters (STP Proposed) Pvt. Ltd. Plot No 25.06.2008 SU, Sector-22, SIT to inspect and report Rohini by 18.07.2008. Call on 18.07.2008.

13.08.2008 Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting. 17.09.2008 Ask the unit to submit Environmental Clearance. Call on 30.10.2008.

05.11.2008 Call on 10.12.2008 for itemwise compliance affidavit. 13 SC- Omaxe N A 28.09.2007 19139.25 MCD-I90 KLD 78.57 crore 2007 Letter issued for Call on 4 Construction sqm GW-nil Discharge- 21.08.2008 submitting 21.01.2009 Ltd. 56 KLD While damages and Bank adequacy report of (Construction of Guarantee have been filed STP. Commercial and CTE have been issued. Reply received Complex) at Plot Unit may be asked to set along with STP No 14, Jasola, up STP expeditiously. Call design and Delhi on 17.09.2008. drawing. Also stating that likely 17.09.2008 dae of completion Call on 30.10.2008 for of STP is May, interim report of unit. 2009.

15.10.2008 Ask the unit to file adequacy report of STP. Call on 24.11.2008

05.11.2008 Call on 10.12.2008 for adequacy report.

14 SC- Laxmi Buildtech Obtained on 24/4/07 27670.33 MCD-181KLD GW- 173.88 15.10.2008 Letter issued. Call on 7 Pvt Ltd ,Plot no 31.01.2008 sqm Nil Dis-72 KLD Crore The unit did not come for Reply awaited. 17.12.2008 D-1 & P3-A personal hearing today and Saket Place has sought time. The unit has not complied with the direction of CMC so far, for which notice for closure was also issued to the unit. The unit may be asked to file compliance of the CMC orders by 31.10.2008, failing which appropriate action will be taken as per law. Call on 31.10.2008. 05.11.2008 Call on 10.12.2008 for compliance of CMC decision. 15 SC- Fargo Estate Pvt N A 24/10/08 10100 sq m MCD- 49.5 KLD 46,30,12,260 N A Next DOH is SIT to inspect 10 Ltd C-2 District GW-nil Discharge- 24.11.2008 05.02.2009. and report. Centre Saket, 7000 l/day SIT indicates following File is under Call on New Delhi deficiencies (a) The unit submission. 23.12.2008 consumes 115 KLD of water generating 58 KLD of waste water which is being discharged into the drain without any treatment (b) The unit is generating hazardous waste without applying for authorization under HWM Rules. Also the unit is not maintaining any record or provided display board for the same (c) ETP is non functional and is created to hoodwink the DPCC (d) A 1000 KVA D.G. Set is without adequate stack height. In view of the above, notice for closure be issued immediately. Call on 10.12.2008. 16 SC- Brightways Pending with 01.11.2007 21096.513 source of water not 66 crore proposed No response Call on 15 Housing & Land MoEF sq m mentioned /ground 24.11.2008 received with 17.12.2008 Development, water-- nil The unit came for personal regards to the CMC Construction of discharge--70KLD hearing today. It says that decision dated Office Cum it is facing difficulty on 24.11.2008 Shopping Mall account of economic melt at Plot no 7 Distt down. It also says that only Centre Jasola a small portion of the mall New Delhi is operational which was confirmed by SIT report as about 50 %. It sought a lenient view on this account. The Committee deliberated on this issue and felt that credit may be given to the unit for Rs. 28 Lakhs paid by the unit, as compounding fee, to DDA and therefore the environmental damages may be reduced to Rs. 72 Lakhs and the Bank Guarantee be reduced to Rs. 1.5 Crores valid for three years to enable the unit to comply with the CMC’s decision expeditiously and take Consent to Establish. The unit agrees to do so. The unit may comply with the decision of filing the environmental damages and Bank Guarantee by 10.12.2008. If, it does so Consent to Establish will be issued across the table. Call on 10.12.2008. 17 SC- Eros Metro Area < 20,000 02.05.2008 14491.761 MCD-105 KLD GW- 132.68 crore 2010 Notice for closure Call on 24 Mall, Sec-14, sq. m sq m NIL DIS- 48 KLD 10.09.2008 issued. 21.01.2009 Dwarka , New The unit came for personal Reply awaited. Delhi hearing today. They requested for a leniency in the earlier decision taken by CMC on 25.06.2008 which was considered by the Committee and looking into similarly placed cases decided by CMC recently where only excavation has been done, the Committee decided to impose damages of 10 % of 0.5 % of project cost which comes to Rs. 7 Lakhs approximately and equivalent amount of Bank Guarantee valid for three years to be filed by 07.10.2008. Call on 07.10.2008 for compliance.

07.10.2008 Call on 15.10.2008

15.10.2008 Issue notice for closure. Call on 24.11.2008

24.11.2008 Call on 03.12.2008

03.12.2008 Call on 10.12.2008

18 SC- Manish Built up area : 24.06.2008 8485.75 MCD- 73 KLD / 66,94,71,10 2010 06.11.2008 File is under SIT to inspect 25 Buildwell Pvt. 8485.75 sqm sqm WW-57 KLD (STP) 1 crores The unit did not come for submission. and report. Ltd., Plot No 2, personal hearing today. Call on LSC, Sec-22 From one restaurant and 23.12.2008 Dwarka , New about 250 shops, the figure Delhi of effluent discharge of 57 KLD appears to be incorrect. Let the unit properly calculate the effluent discharge and file a revised Consent to Establish application based on facts. Call for personal hearing on 17.12.2008 at 5.15 PM. 24.11.2008 There has been palpable error in handling this case by the concerned CMC which is warned not to repeat this in future. MS will personally work on this file and issue a Show Cause Notice for closure based on the deficiencies found by SIT. The notice for closure to be issued immediately without waiting for minutes. Inform the advocate accordingly. Call on 10.12.2008.

19 SC- Vardhman Name not Not applied 13.08.2008 Opinion of the SIT to inspect 26 Group, Sec-7 included in the for consent Due to want of time, SIT advocate has been and report. Dwarka, New list of Ecs to Establish report may be submitted obtained and placed Call on Delhi accorded/pending administratively by the SIT for the perusal of 23.12.2008 with MOEF(as team for clear decision to CMC. Advocate provided by be ratified in the next CMC suggested for MOEF) meeting. moving an 17.09.2008 application for Call on 30.09.2008 after modification of the High Court hearing. order interalia 07.10.2008 adding the Call on 06.11.2008 with inspection report of High Court order. continuous 06.11.2008 violation of Water / Call on 03.12.2008 with Air Act. High Court order. 03.12.2008 For all these three cases of Vardhman, our advocate be consulted whether early hearing be sought as these malls are getting the benefit despite violation of all pollution control norms. Call on 10.12.2008. In other case of Vardhman Plaza of Motia Khan not listed today, similar action be taken.

20 SC- Vardhman Name not Not applied 13.08.2008 Opinion of the SIT to inspect 27 Group, Sec-19 included in the for consent Due to want of time, SIT advocate has been and report. Dwarka, New list of Ecs to Establish report may be submitted obtained and placed Call on Delhi accorded/pending administratively by the SIT for the perusal of 23.12.2008 with MOEF(as team for clear decision to CMC. Advocate provided by be ratified in the next CMC suggested for MOEF) meeting. moving an 17.09.2008 application for Call on 30.09.2008 after modification of the High Court hearing. order interalia 07.10.2008 adding the Call on 06.11.2008 with inspection report of High Court order. continuous 06.11.2008 violation of Water / Call on 03.12.2008 with Air Act. High Court order. 03.12.2008 For all these three cases of Vardhman, our advocate be consulted whether early hearing be sought as these malls are getting the benefit despite violation of all pollution control norms. Call on 10.12.2008. In other case of Vardhman Plaza of Motia Khan not listed today, similar action be taken.

21 SC- Vardhman Name not Not applied Opinion of the SIT to inspect 28 Group, Sec-23 included in the for consent 13.08.2008 advocate has been and report. Dwarka, New list of Ecs to Establish Due to want of time, SIT obtained and placed Call on Delhi accorded/pending report may be submitted for the perusal of 23.12.2008 with MOEF(as administratively by the SIT CMC. Advocate provided by team for clear decision to suggested for MOEF) be ratified in the next CMC moving an meeting. application for modification of the 17.09.2008 order interalia Call on 30.09.2008 after adding the High Court hearing. inspection report of continuous 07.10.2008 violation of Water / Call on 06.11.2008 with Air Act. High Court order. 06.11.2008 Call on 03.12.2008 with High Court order.

03.12.2008 For all these three cases of Vardhman, our advocate be consulted whether early hearing be sought as these malls are getting the benefit despite violation of all pollution control norms. Call on 10.12.2008. In other case of Vardhman Plaza of Motia Khan not listed today, similar action be taken.

22 SC- TSL Mall Name not Not applied 31.07.2008 Letter was issued Call on 29 /Shopping Mall, included in the for consent Issue final reminder to on 20.11.2008 in 14.01.2009 Sec-04 Dwarka, list of Ecs to Establish comply with the decision resonse to the CMC New Delhi accorded/pending of CMC meeting dated decision dated with MOEF(as 26.06.2008. Call on 05.11.2008 provided by 03.09.2008. No reply received. MOEF) 03.09.2008 Call for personal hearing on 30.09.2008 at 5.30 PM. 30.09.2008 The unit came for personal hearing today. The unit will submit Consent to Establish application with all the details on which basis it’s case will be considered on 30.10.2008. Call on 30.10.2008. 05.11.2008 Draft an appropaite reply in response to a letter that the unit does not fall under the Air and Water Acts. Show it aministratively for approval before issue. Call on 10.12.2008 for compliance.

23 SC- TSL Mall Name not Not applied 734.4 sq m 9.0 CRORE 31.07.2008 Letter was issued Call on 30 /Shopping Mall, included in the for consent /As per Issue final reminder to on 20.11.2008 in 14.01.2009 Sec-06 Dwarka, list of Ecs to Establish inspection comply with the decision resonse to the CMC New Delhi accorded/pending report of CMC meeting dated decision dated with MOEF(as 26.06.2008. Call on 05.11.2008 provided by 03.09.2008. No reply received. MOEF) 03.09.2008 Call for personal hearing on 30.09.2008 at 5.45 PM. 30.09.2008 The unit came for personal hearing today. The unit will submit Consent to Establish application with all the details on which basis it’s case will be considered on 30.10.2008. Call on 30.10.2008. 05.11.2008 Draft an appropaite reply in response to a letter that the unit does not fall under the Air and Water Acts. Show it aministratively for approval before issue. Call on 10.12.2008 for compliance.

24 SC- Pankaj Group, Name not Not applied 531 sq m aprox.40 lac Next date of Call for personal 31 Sec-12 Dwarka, included in the for consent /as per 03.09.2008 hearing is hearing on New Delhi list of Ecs to Establish inspection The unit came for personal 22.01.2009. 23.12.2008 at accorded/pending report hearing today. Unit claims SIT report to be 6.30 PM. with MOEF(as that there are three small discussed. provided by plots of 135 sqm each for MOEF) which built up area as per the inspection report is 1593 sqm. According to the unit, there is no effluent discharged and there are no food courts proposed and it is only an office complex. The unit also claims that it has no D.G. Sets and no bore well. Let the unit file its application for Consent to Establish and the case will be considered in the CMC on 30.09.2008.

07.10.2008 Call on 06.11.2008.

06.11.2008 Call on 03.12.2008 with High Court order.

03.12.2008 SIT to inspect and report. Call on 10.12.2008.

25 SC- Parsvnath EC submitted. 18/3/2008 89342 sq m MCD- GW-NIL 120.33 crore proposed 18.06.2008 Unit was asked for Consent to 34 Developers Ltd DIS-344 cu.m The unit came for personal submitting an Establish in construction hearing today. Since affidavit of granted. with M/s OCL Consent to Establish and environmental Ltd Commercial Environmental Clearance clearance's Complex at have been filed and no conditions. Seelampur construction has been Reply received on Metro started, case may be taken 25.11.2008 up on 18.07.2008. Meanwhile SIT to inspect and report. Call on 18.07.2008. 13.08.2008 Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting. 17.09.2008 Call for personal hearing on 16.10.2008 at 7.15 PM.

15.10.2008 The unit came for personal hearing today. It says environment clearance has not yet been received but no construction has taken place on the site which stands corroborated by SIT report. Call on 24.11.2008 for environmental clearance.

24.11.2008 Call on 10.12.2008 S. Name & Address EC Status CTE Bult Up Area Water / Total Date of Earlier decisions ATR/Remarks Decision on No Ref. status Waste Project Commissioning 11.12.2008 No Water Cost details Executive 4/10/2007 Applied on 139294 sqm MCD 667 124.80 Dec, 2008 18.02.2008 SIT report to be Consent to Engineer, 21.05.2008 KLD/trade crores Ask him to apply for fresh discussed. Establish CPWD ,Const. of effluent Consent to Establish. granted subject General Pool (185 KLD) 17.3.2008 to the condition Housing at Dev & domestic MS to speak. Take up in that clearance of Nagar effluent April, 2008. tree cutting from (553 KLD) 23.04.2008 the Forest as per Call on 21.05.2008 department will affidavit 03.6.08 be taken. Call on MS to speak to DG, CPWD 14.01.2009 to submit EC and CTE 1 A-5 application expeditiously. Call on 11.07.2008. 30.09.2008 Ask the unit to file an affidavit stating item-wise compliance of environmental clearance's conditions. Call on 30.10.2008. 05.11.2008 SIT to inspect and report. Call on 10.12.2008 2 A-7 DLF Limted, _ 26-03-08 18,553.8 Sqm MCD 3,04,163,47 1991 26.06.2008 Letter issued on Call on Construction of 13.33 KLD 7 crores The unit has not filed 21.11.2008 14.01.2009 Office Complex GW--61.17 confirmation of payment of Reply awaited. at DLF Centre KLD / 34 the water cess amount from Sansad marg KLD 2003 to 2008 as directed by DPCC vide letter dated 13.06.2008. Unit may be directed to do so by 31.07.2008 without fail. The unit may be also asked permission from CGWA for ground water drawl. Call on 31.07.2008. 31.07.2008 Reminder to be issued. Call on 20.08.2008. 21.08.2008 Submit this file administratively after examining all the requirements for Consent to Establish. 05.11.2008 Ask the unit to submit effluent analysis report from an approved laboratroy and stack height of the D.G.Set has to be raised to the appropriate level. Call on 10.12.2008

DMRC , 01.04.2008 Applied on 26,723.66 MCD 252 90 crores June, 2008 SIT report to be Call for personal Construction of 1/4/2008 Sqm as per KLD / 33.6 31.10.2008 discussed. hearing on operation control EC KLD The unit came for personal 23.12.2008 at centre (Metro 26,000 as per (NDMC) hearing today. The MOEF 6.45 PM. Bhawan ) of CTE reply clearly says that the Delhi Metro Rail Environmental Clearance Corporation Ltd was given on the particular at Fire Brigade, date and does not clarify that Lane Connaught any exemption was given to 3 A-8 Place, New Delhi the unit. The unit admits that the 90 % of the construction was completed without obtaining Consent to Establish. SIT to inspect and report. Call on 24.11.2008. 24.11.2008 Call on 10.12.2008 with SIT report. Hotel Queen Not applied Granted on 36.21 Sqm in 255 65.50 crores ___ Letter issued on Examine the Road Pvt. Ltd., 01.06.2006 Application & 07.10.2008 25.11.2008 reply of the unit 19, Ashoka Road, 20991Sqm in Letter be issued by hand Reply awaited. carefully and Connaught Place, Reply tomorrow as decided in submit New Delhi-01 CMC meeting dated administratively. 30.09.2008. File be Call on submitted administratively 14.01.2009 thereafter.

A- 05.11.2008 4 13 SEE to draft an appropriate letter covering the earlier deficiencies in respect of the reply recevied from the unit. File to be shown adminsitratively before issuance of the letter to be signed by MS next week. Compliance of that letter by 10.12.2008. 5 A- Delhi Cricket Not applied Not ______03.6.2008 Reminder Issue final 18 Association, applied Issue reminder and also the issued. reminder. Call Frozeshah unit may be asked to file Reply awaited. on 14.01.2009 Kotla, Delhi clarification on the extent of Gate, Delhi- ground water drawl and the 110002 permission for the same. It may also be asked to file its water cess returns from May, 2003 when it became applicable. Reminder to be sent to site address in the name of Secretary, DDCA. Call on 11.07.2008 30.09.2008 Ask the unit to file the fresh proper consent application form along with requisite affidavit/documents and exact consent fee. Call on 30.10.2008. 05.11.2008 Issue reminder. Call on 10.12.2008

6 A- Bharat Sanchar Structural 25-04-08 13655.1 Sqm MCD-35 48.42crores 31-07-07 03.6.08 Reminder MS to write to 20 Nigam Ltd., CTO Fabricators KLD And Ask the unit to file details of issued on CMD. Call on Project, ARA Pvt Ltd GW 30 waste water discharge, D.G. 21.11.2008. 14.01.2009 Centre, (Anant Raj KLD / 40 Set, ground water drawl and According to Jhandewalan, Agencies P (STP) water cess payment as per the analysis Delhi ltd ) Cess Act. report of mini Commercial 27.06.2008 STP for the Complex at SIT to inspect and report. month of 67 Call on 31.07.2008. September, Najafgarh 31.07.2008 2008 shows "no Road, Kirti SIT report indicates drawl of flow during the Nagar ground water without monitoring". CGWA permission. Ask the unit to file water cess payment details and CGWA clearance. Call on 20.08.2008.

21.08.2008 The unit may be communicated the deficiencies noted by SIT and the water sampling done by DPCC and deficiencies of noise monitoring report along with CGWA clearance . Unit to file response by 17.09.2008. Call on 17.09.2008. 30.09.2008 Issue reminder. Call on 30.10.2008 05.11.2008 Issue final reminder. Call on 10.12.2008

Construction of 03.06.2008 Reminder Issue final Bakkarwala DDA has filed Consent to issued on reminder. Call Housing Complex Establish application for 21.11.2008, the on 14.01.2009 by DDA Bakkarwala Housing letter addressed Complex. Since the built up at site address area is more than 20000 has received sqm, ask the unit to apply back for EC in MOEF undelievered. A- 7 expeditiously. Call on 23 11.07.2008. 30.09.2008 Ask the unit to file environmental clearance. Call on 30.10.2008 05.11.2008 Issue fresh reminder. Call on 10.12.2008 Genger Rail Yatri _ Applied on 4842.456 sqm MCD : 20 1013.97 July, 2008 30.09.2008 Letter issued on MS to write to Niwas (Roots 15.07.2008 KLD / GW Lakhs SIT to inspect and report. 20.11.2008 GM. Call on Corporation Ltd.), : 30 KLD / Call on 30.10.2008 Reply awaited. 14.01.2009 Rail Yatri Niwas, 45 KLD 05.11.2008 New Delhi (STP) The following deficiencies Railway Station, were noted by SIT be Gate No 2, communicated to the unit for Ajmeri Gate Side correction:

(i) Stack height of the D.G. Set needs to be raised as per A- 8 norms. 25 (ii) Approach and inspection platform need to be installed in the STP. (iii) Sludge tray and channelization for filtrate need to be provided with filter press (iv) Cleaning is required in rain water harvesting pits.

Call on 10.12.2008 Redevelopment Pending Not Plot area Total water 671 crores 30.09.2008 Letter issued on SIT to inspect of Connaught with MOEF applied 3,00,231.639 4130 Ask the NDMC to file 05.11.2008 and report. Place, New Delhi 3 sqm KLD / Consent to Establish and Reply awaited. Call on by M/s New Domestic Environmental Clearance. 14.01.2009 A- Delhi Municipal & Call on 30.10.2008 9 30 Council commercial 05.11.2008 use : 2700 Call on 10.12.2008 KLD / WW : 2430 KLD General Pool __ Not ______18.02.2008 Letter pasted on Call on Office Complex, applied Ask the unit to apply for the correct 14.01.2009 Shahdara Consent to Establish. Also address. ask them to file EIA Reply awaited. clearance. 17.3.2008 MS to speak to the concerned authority. Take up in April, 2008. 23.04.2008 10 B-2 Fresh letter at correct address be sent. 03.6.08 Send reminder. Call on 11.07.2008. 30.09.2008 Issue reminder at correct address. Call on 30.10.2008 05.11.2008 Paste the letter on correct address. Call on 10.12.2008 DDA , New Pending Not 1,20,100sqm 3766KLD 121 crores __ 18.02.2008 Letter issued on Issue fresh Construction with Moef applied in EC Ask the unit to apply for 25.11.2008 reminder. Call Project of a Consent to Establish. Also Reply awaited. on 14.01.2009 Housing Complex ask them to file EIA for economically clearance. weaker section at 17.3.2008 siraspur in Delhi MS to speak to the concerned authority. Take up in April, 2008. 23.04.2008 The minutes of the meeting of MOEF and other relevant papers may be sent by MS to the concerned Chief Engineer to clarify the issue. 03.6.08 11 B-5 Issue reminder. Call on 11.07.2008. 30.09.2008 Ask the unit to file Consent to Establish and give them downloaded address. Also ask for Environmental Clearance. Call on 30.10.2008. 05.11.2008 Ask the unit to download the Consent to Establish application form from DPCC's wbesite and file by 10.12.2008 and also file Environmental Clearance by 10.12.2008 Indian Institute of 16-01-08 17-03-08 87,112.5 sqm MCD 170 65.82 crores __ 18.02.2008 SIT report to be Consent to Information KLD GW The explanation of discussed. Establish Technology 80 KLD / concerned EE must be called Reply regarding granted. Call Campus of 190 KLD for why the decision given the letter issued on 14.01.2009 Indraprastha on the file has not been for itemwise University at implemented. Ask the unit compliance Surajmal Vihar, to apply for Consent to received on Shahdara Establish immediately. 21.11.2008

17.3.2008 Unit be asked to submit item-wise compliance of conditions laid down in Environmental Clearance through an affidavit and MS to speak to Registrar w.r.t. applying for Consent to Establish.Take up in April 12 B-6 2008. 23.04.2008 Compliance affidavit by 21.05.2008. Call on 21.5.2008. 03.6.08 Environmental Clearance has been filed. But for item- wise compliance, unit says that construction yet to be started and it will be filed. Call on 11.07.2008. 30.09.2008 Issue reminder. Call on 30.10.2008 05.11.2008 SIT to inspect and report. Call on 10.12.2008 Residential EC received 30-08-07 29,889.65 MCD 221 93.28 Crores 2008 11.07.2008 Letter issued on Ask the unit to Complex near on Sqm KLD/ 170 The unit came for personal 21.11.2008 file itemwise Rithala Metro 17.10.2008 KLD (STP) hearing today. Since it has Reply received compliance Station by A.P. not done any construction so on 25.11.2008. affidavit of Real Estates far and since it is yet to get the building plan clearances, environmental it may be prudent to wait for clearance's the Environmental conditions as Clearance first before per earlier decision on Consent to CMC decision Establish. However, in the dated meantime unit be directed to 05.11.2008. file an affidavit saying it Call on 13 B-8 will not start any 14.01.2009 construction till it gets the Environmental Clearance. Call on 06.08.2008. 30.09.2008 Ask the unit to file Environmental Clearance. Call on 30.10.2008 05.11.2008 Ask the unit to file itemwise compliance affidavit of Environmental Clearance's conditions. Call on 10.12.2008 Executive __ 12/11/2007 20, 217.6 __ / 117 38 Crores Dec----07 18.02.2008 Reminder Get it pasted. Enmgineer ( C) Sqm KLD (STP) Not discussed in the CMC issued on Call on Building Projects meeting dt 18.02.08 21.11.2008 14.01.2009 Division, 17.3.2008 The same was Proposed MS to speak . Take up in returned back Maharaja April, 2008. undelievered. Agrasen 23.04.2008 College,Delhi Unit may be asked to University, submit sanctioned building Village plan by 21.05.2008. Call on Dallupura, 21.05.2008. Vasundhara 03.6.08 Enclave, Delhi Issue reminder for submission of a copy of Environmental Clearance, an affidavit indicating date of start of construction & 14 B-9 date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets . Call on 11.07.2008. 30.09.2008 Paste letter on premises. Call on 30.10.2008 05.11.2008 Issue final reminder. Call on 10.12.2008 Executive Not applied 18-01-08 76160 Sqm MCD 62.37 Crores March-----2010 18.02.2008 Meeting of Case be put up Engineer 634.1 KLD Not discussed in the CMC SEIAA is yet to in next agenda Rohini Project / 539 KLD meeting dt 18.02.08 take place. of SEIAA. Division - 13 (STP) Call on proposed the MS may write to MOEF to Construction of find out the status of EIA 14.01.2009 HIG Multistoried clearance. Take up in April, Houses 2008. Sec - 29, Rohini, 23.04.2008 Phase - IV,Delhi - MS to remind Addl. 85 Secretary, MOEF about the Environmental Clearance of 15 B-11 the unit. 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue reminder for Environmental Clearance. Call on 30.10.2008. 05.11.2008 The case be put up in first agenda of SEIAA meeting. Call on 10.12.2008 16 B-12 Executive Issued on 10/12/2007 53600 Sqm 1117 108 Crores __ 18.02.2008 Reminder for Ask the unit to Engineer, 16.10.2008 KLD / Not discussed in the CMC EC issued on file itemwise Rohini Project 950(STP meeting dt 18.02.08 04.11.2008 compliance Division - 9, RITHALA Reply regarding affidavit of proposed the ) KLD MS may write to MOEF to EC received on Construction of find out the status of EIA 24.11.2008 environmental Slum houses near clearance. Take up in April, clearance's STP, Sector - 26, 2008. conditions. Phase - IV, 23.04.2008 Call on Rohini,Delhi - 85 MS to remind Addl. 21.01.2009 Secretary, MOEF about the Environmental Clearance of the unit. 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue reminder for Environmental Clearance. Call on 30.10.2008. 05.11.2008 Call on 10.12.2008

Construction of Pending Not __ 18, 146.9 Crores __ 23.04.2008 Fresh letter Issue fresh Zonal with Moef applied 149KLD Send notice to concerned issued at correct reminder. Call Development IN EC / 10 Chief Engineer, DDA for address. on 14.01.2009 Plan of Narela MLD compliance. No reply Sector-A-1 to A-4 (STP) 03.6.08 received. Narela Sub City Issue reminder. Call on 17 B-13 Narela, Delhi 11.07.2008. Development 30.09.2008 Authority Issue fresh letter at correct address. Call on 30.10.2008. 05.11.2008 Call on 10.12.2008 Delhi 17.06.2008 26.06.2008 45,560.716 253 KLD / 54 Crores __ Letter issued. In view of the Administration Sqm MCD - 135 23.04.2008 Reply awaited. clarification Staff Quarters at KLD / MS to speak to Engineer in submitted by Shalimar Bagh WW- 190 Chief about Consent to PWD that being constructed KLD / Day Establish application after encroachment by PWD revealing to him the has been directions of MOEF. Call on protected / 21.5.2008 prevented. 18 B-16 03.6.08 Committee Issue reminder. Call on decided to issue 11.07.2008. Consent to 30.09.2008 Establish. Call Take up with Secretary, on 14.01.2009 PWD.Call on 30.10.2008. 05.11.2008 Call on 10.12.2008 Rugby Stadium Issued on Applied 9549 sqm + 240 KLD / 224 crores Nov, 2009 01.05.2008 Letter issued on Issue fresh and Multipurpose 19.09.2008 for CTE on 20280 sqm MCD-240 This case is listed in MOEF 21.11.2008 reminder. Call Hall 12.6.08. KLD / STP for discussion on Reply awaited. on 14.01.2009 North Campus, proposed 02.05.2008. Call on Delhi University, 14.05.2008. Delhi 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 19 B-18 Ask the unit to file Environmental Clearance. Call on 30.10.2008 05.11.2008 Ask the unit to file itemwise compliance affidavit of Environmental Clearance's conditions. Call on 10.12.2008 Shalimar Social Built up 21-05-08 3450 Sqm MCD .8 7.44 Crores June ----2008 03.6.08 Letter issued on Call on Club Society area is 3450 KLD & SIT to inspect and report. 21.11.2008 14.01.2009 (REGD.), Plot No Sqm GW .4 Call on 11.07.2008 Reply awaited. 9, B Block, KLD / 1.8 30.09.2008 Community KLD (Oil Call on 30.10.2008 20 B-20 Centre, Club and Grease 05.11.2008 Road, Shalimar Trap) Ask the unit to file effluent Bagh, Delhi-88 analysis report at the inlet and outlet from approved laboratory by DPCC. Call on 10.12.2008 Executive Built up Not 17065.59 __ __ 2009 03.6.08 Letter issued on Issue fresh Engineer, area is applied. Sqm Ask the unit to file 21.11.2008 reminder. Call Provisional 17065.59 application fro Consent to Reply awaited. on 14.01.2009 Division PWD Sqm Establish, a copy of (B& R) Civil Environmnetal Clearance, Line, Gurgaon an affidavit indicating date Poposed of start of construction & Construcion of date of completion, Housing Complex completion certificate, at Plot no1 Near approved architectural Single Pur drawing, details of builtup Village, Shalimar area, plot area, waste water 21 B-21 bagh , Delhi-81 discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008. 30.09.2008 Issue reminder. Call on 30.10.2008 05.11.2008 Issue reminder.Call on 10.12.2008 Construction of Letter issued on Call on HIG Flats at 18.06.2008 21.11.2008 14.01.2009 Mukherjee Nagar A letter received from Reply awaited. by DDA MOEF for taking action under EPA against HIG Flats at Mukherjee Nagar. A well drafted letter may be put up by MS to Vice Chairman, DDA by 25.06.2008. 30.09.2008 22 B-22 Issue reminder for Consent to Establish and send a copy of MOEF letter to VC, DDA through a D.O. letter. Call on 30.10.2008 05.11.2008 Issue reminder for affidavit for itemwise compliance of Environmental Clearance's conditions and also apply for Consent to Estabilsh. Call on 10.12.2008. 23 B-23 Construction of Letter issued on Call on Anand Vihar 03.06.2008 21.11.2008 14.01.2009 Railway Station The issue of Anand Vihar Reply awaited. at Anand Vihar Railway Station was taken up by the Committee and it was decided to issue notice to GM, Northern Railway for applying for Consent to Establish for Anand Vihar Railway Station. 30.09.2008 Ask the unit to apply for Consent to Esablish and Environmental Clearance. Call on 30.10.2008

05.11.2008 Issue reminder. Call on 10.12.2008

UGC Campus, Obtained on CTE 42349 sqm WW - 110 45.29 Cr. 2009 18.02.2008 Reminder SIT to inspect Pocket 7 Sector B 30.7.08 applied on KLD / Ask the unit to file EIA issued on and report. Vasant Kunj, 10.09.2007 MCD - 305 clearance. Separately a 14.11.2008 Call on Nelson Mandela KLD copy of this letter may be Reply received 21.01.2009 Road, Delhi sent to Addl. Secretary, on 25.11.2008 MoE&F to ascertain the along with latest status of the unit and affidavit of whether any order has been enviromental passed on their application clearance's by MoE&F. conditions. Take up in April, 2008. 23.04.2008 Call on 21.05.2008. 24 C-1 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Ask the unit to file an affidavit stating item-wise compliance of environmental clearance's conditions. Call on 30.10.2008. 05.11.2008 Issue reminder. Call on 10.12.2008 Delhi Judicial 22-01-07 Applied 68186 sqm MCD - 125 Cr. March, 2009 18.02.2008 Reminder Issue fresh Academy, 178.2 KLD Ask the unit to submit an issued. reminder. Call National Law / GW - affidavit seeking itemwise Reply awaited. on 14.01.2009 School ad 118.8 KLD compliance of EIA National Institute / WW - conditions. of Mediation & 250 KLD 17.3.2008 Concilation , MS to speak . Take up in Sector 14, April, 2008. Dwarka Phase-I, 23.04.2008 25 C-2 New Delhi Call on 21.05.2008. 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue reminder. Call on 30.10.2008 05.11.2008 Issue reminder. Call on 10.12.2008 Cabinet 29-12-06 Applied 18.02.2008 Reminder Consent to Secretariate Ask the unit to submit an issued. Establish Biuilding , Plot affidavit seeking itemwise Reply received granted. No. 5A, CGO compliance of EIA on 02.12.2008 Complex, Lodhi conditions. Road, New Delhi 17.3.2008 MS to speak . Take up in April, 2008. 23.04.2008 Call on 21.05.2008. 26 C-4 03.6.08 SIT to inspect and report. Call on 11.07.2008 30.09.2008 Ask the unit to correct the deficiencies noted by SIT. Call on 30.10.2008. 05.11.2008 Issue reminder. Call on 10.12.2008 CPWD, 5/6/2007 Not 88.742metre NA NA 18.02.2008 Reminder Issue fresh Construction of applied square Ask the unit to apply for issued. reminder. Call general pool Consent to Establish. Also Reply awaited. on 14.01.2009 office ask them to file an affidavit Accomodation, for compliance of EIA Phase-II , Pushpa clearance conditions. Bhawan, Pushp 17.3.2008 Vihar, Delhi MS to speak . Take up in April, 2008. 23.04.2008 27 C-11 Call on 21.05.2008 with response. 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue final reminder. Call on 30.10.2008. 05.11.2008 Issue reminder.Call on 10.12.2008 28 C-14 DDA LIG Houses _ 4/12/2007 33465metre MCD- 38 Crores Not mentioned 18.02.2008 Reminder Call on , Molar Bandh, square Quanitiy Ask him to file EIA issued. 14.01.2009 New Delhi not clearance. Separately a copy Reply received mentioned, of this letter may be sent to stating that GW-Nil, Addl. Secretary, MoE&F to matter is under Waste ascertain the latest status of consideration of Water the unit and whether any MOEF and EC Discharge- order has been passed on will be cleared NA their application by MoE&F. in the next EAC meeting. 17.3.2008 MS to speak . Take up in April, 2008. 23.04.2008 Call on 21.05.2008 with response. 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue reminder. Call on 30.10.2008 05.11.2008 Issue final reminder.Call on 10.12.2008

Guru Gobind 12/2/2007 13-6-6 88694Sq,. MCD-550 163.24 crore 2008 18.02.2008 Reminder SIT to inspect Singh Metre KLD, GW- Unit may be asked to file an issued for & report. Call Indraprastha Nil, affidavit for compliance of submitting on 21.01.2009 University, Sector Discharge- EIA clearance conditions. proper affidavit 16 Dwarka, New 104 KLD of EC's Delhi 17.3.2008 conditions. MS to speak . Take up in No reply April, 2008. received. 23.04.2008 Call on 21.05.2008. Let the 29 C-15 unit download the proforma from the net. 03.6.08 Issue last reminder. Call on 11.07.2008. 30.09.2008 Call on 30.10.2008 05.11.2008 Issue final reminder.Call on 10.12.2008 Construction of _ Not 18.02.2008 Reminder Issue fresh General Pool applied Ask the unit to apply for issued for CTE reminder. Call Accomodation at afresh Consent to Establish. & EC. on 14.01.2009 Vasant Vihar Also ask them to file EIA Reply awaited. clearance. 17.3.2008 MS to speak . Take up in April, 2008. 23.04.2008 Call on 14.05.2008 reminding about Consent to Establish and Environmental Clearance. 13.05.2008 MS to speak CPWD and ensure that application for 30 C-19 Consent to Establish and a copy of Environmental Clearance are filed by 10.06.2008. Call on 10.06.2008. 03.6.08 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue final reminder. Call on 30.10.2008 05.11.2008 Issue reminder. If no response received, action will be taken as per law. Call on 10.12.2008 Redevelopment _ Not NA NA NA NA 18.02.2008 Reminder Send the letter at of GPRA , applied Ask the unit to apply for issued. new address. Aliganj, Jorbagh afresh Consent to Establish. Reply received Call on Also ask them to file EIA stating that this 14.01.2009 clearance. work has been 17.3.2008 transferred to MS to speak . Take up in SE, Dec, 2007, April, 2008. R.K. Puram, 23.04.2008 CPWD, New Call on 21.05.2008. Delhi 03.6.08 31 C-20 Issue reminder. Call on 11.07.2008. 30.09.2008 Issue final reminder for Consent to Establish and Environmental Clearance. Call on 30.10.2008 05.11.2008 Issue reminder. If no response received, action will be taken as per law. Call on 10.12.2008 S. Name of Address Activity Earlier decisions ATR FOR DECISION No. Industry 11.12.2008 ON 11.12.2008

1 M/s New K-31/S-1, Zn Plating (with 27.09.2007 Reminder Issue fresh O.K. Anand Parbat Cr. passivation) New OK electroplating has stopped his electroplating issued. reminder. Electroplating, Industrial Area activity another unit M/s Sarla Engg. Works was found No compliance Call on Delhi operating involved in cutting of steel sheets. Power report 21.01.2009 connection found intact. Ask for compliance report for received. power disconnection both for this unit and for the substitute unit in whatever it may be. 24.10.2007 Take up on 20.11.07. 20.11.2007 To be taken up on 27.12.2007 since compliance report by BSES has not come yet. 30.01.2008 Seek the compliance report from BSES. 19.09.2008 Issue reminder for compliance report. Call on 20.10.2008 05.11.2008 Issue final reminder to NDPL. Call on 10.12.2008 2 M/s Alipur M- 6, Phase I, Manufacturing of 27.09.2007 Letter issued. Call on Pipe & Steel Badli Industrial Copper sheets While he has corrected his deficiencies accordng to latest Reply received 21.01.2009 Tubing Area, Delhi – involving inspection reports. His documents of production may be on 10.12.2008. Industries (P) 42. pickling. analysed to confirm his claims. Put up in next month Unit has Ltd., CMC. informed that 24.10.2007 they have shut Analysis on file. Case to be decided on 20.11.07. down the 20.11.2007 production due The case to be taken on 27.12.2007 to maintenace 30.01.2008 of building and Since this is highly polluting activity and the Bank machinery. Guarantee was taken only for six months which period is Themaintenace over now, the Bank Guarantee may be taken afresh for work is in one year beginning January, 2008. progress but at 19.09.2008 the same time SIT to inspect and report. Call on 20.10.2008. due to drastic 05.11.2008 fall in copper SIT report indicates ETP found in defunct condition and metal prices & ECS without hood found at site and unit was also not heavy slump in functional during inspection. Ask the unit to correct the demand at deficiencies and submit an affidavit. Call on 10.12.2008 least they will take another two months to restart the production. 3 M/s Rakhi S- 76, Phase I, Fabrication of 27.09.2007 Letter issued. Ask the unit Export, Badli Industrial M.S. engineering Put up in next CMC with all their applications and Reply received to file Area, Delhi – goods (involving documents. on 10.12.2008 affidavit 42. cutting, shearing 24.10.2007 stating the and welding) No action pending. compliance of 30.01.2008 earlier CMC Since the Bank Guarantee was taken only for six months decision which period is over now, the Bank Guarantee may be dated taken afresh for one year beginning January, 2008. 05.11.2008. 19.09.2008 Call on SIT to inspect and report. Call on 20.10.2008. 21.01.2009 05.11.2008 During inspection by SIT, domestic waste water was being discharged into the drain and needs to be connected with the existing conveyance system. Call on 10.12.2008 4 M/s Ideal Plot No. 102, Manufacturing of 27.09.2007 Matter is Call on Udyog, Phase II, Badli Cu and brass Put up in next CMC with the Appellate Authority orders. subjudice 21.01.2009 Industrial Area, sheets/ circles 24.10.2007 before Hon'ble Delhi – 42. involving Wait for order. High Court. annealing and 20.11.2007 pickling. In this case Applleate Authority namely Financial Commissioner has completed the hearing on 10.07.07 and reserved the order. Wait for orders 30.01.2008 It does not stand to reason that the polluting unit continues to violate the Air / Water Acts and HWM Rules on account of a long date given by Appellate Authority under Water Act, which harms public interest. Therefore the Committee felt to file immediate application for early hearing.

Since the unit has been ordered closure u/s 5 of the EP Act, 1986 which covers the HWM Rules also and immediate inspection must be done by the concerned CMC and reported by 11th February, 2008 on the status of the unit and whether it is operating in violation of the directions under EP Act. 19.09.2008 Call on 20.10.2008 with High Court order. 05.11.2008 Put up on file administrative with High Court order when it comes on 13.01.2009. 5 M/s C.V. Plot No. 103, Manufacturing of 27.09.2007 Letter issued. Ask the unit Mathur & M. Phase II, Badli aluminum sheets Put up in next CMC for want of time. Unit has to file K. Unithan/ Industrial Area, and circles. 24.10.2007 submitted 2nd adequacy Swastic Delhi – 42. Ask him to apply for consent to establish. BG on report of Aluminum, 20.11.2007 15.10.2008, as ECS. Call on Issue letter for applying for Consent to Establish. per CMC 21.01.2008 30.01.2008 decision dated Before his consent application is considered, let him file a 19.09.2008. fresh Bank Guarantee valid for one year. SIT report to 19.09.2008 be discussed. Let the unit file 2nd Bank Guarantee valid for one year. Call on 20.10.2008. 05.11.2008 SIT to inspect and report. Call on 10.12.2008

6 M/s Maruti Plot No. 83, Pickling of SS 27.09.2007 Letter issued. Ask the unit Industries, Phase II, Badli sheets Not applied for consent to establish. Put up in next CMC. Unit has to correct the Industrial Area, submitted deficiencies Delhi – 42. Applied for consent to establish on 14.9.07 with ID No. revalidiated noted by SIT. 13497 BG of Rs. One Call on 24.10.2007 Lakh. 21.01.2009 Call such cases next month on 20.11.07. SIT report to 20.11.2007 be discussed. Let the CMC study the project report submitted with the Consent to Establish. The case will be taken up on 27.12.2007 30.01.2008 Before his consent application is considered, let him file a fresh Bank Guarantee valid upto 06.02.2010. 19.09.2008 The plea of the unit cannot be accepted. Let him file fresh Bank Guarantee of Rs. One Lakh valid upto 06.02.2010 and confirm by 20.10.2008. Call on 20.10.2008. 05.11.2008 SIT to inspect and report. Call on 10.12.2008 7 M/s Powercon Plot No. 45, Annealing, re- 27.09.2007 Letter issued. Unit may be Industries, Phase II, Badli rolling and Video graphy to be seen by Prof. Gupta, after refernce of BG of Rs. One asked to shift Industrial Area, pickling of SS reasons of videography are given to him. Take up in next lakh submitted oil tank inside Delhi – 42. sheets. CMC. on 17.10.2008 the premises. 24.10.2007 as per the Call on Call such cases next month on 20.11.07. CMC decision 21.01.2009 20.11.2007 dated A fresh CD to be provided to Prof. S K Gupta. 19.09.2008 30.01.2008 SIT report to Based on the videography CD seen by Prof. Gupta, the be discussed. unit appears to be big but having sloppy operations. Since the unit is highly polluting it can not run on sloppy lines and create adverse public interest. The unit may be asked to file Bank Guarantee of Rupees One Lakh under three acts valid upto 06.02.2010. It must also be directed to have efficient ETP, ECS & HWM systems. Let the unit file an affidavit to this effect along with the Bank Guarantee. 19.09.2008 The plea of the unit cannot be accepted. Let him file fresh Bank Guarantee of Rs. One Lakh valid upto 06.02.2010 and confirm by 20.10.2008. Call on 20.10.2008. 05.11.2008 SIT to inspect and report. Call on 10.12.2008 8 M/s Jwell K-31-5, Anand Ni Plating (with 27.09.2007 No action. No action. Electroplating, Parbat Cr. dip) with Inspection report indicates that unit has stopped the Industrial Area buffing (1 activity machinery of electroplating and buffing found Delhi machine) removed and premises is empty. Therefore no action pending with this orange CMC. 24.10.2007 No action pending. 20.11.2007 No action pending 30.01.2008 No action by this Committee. 19.09.2008 No action. 05.11.2008 No action. 9 M/s Asrani A-4, Wazirpur Pickling, 27.09.2007 Letter issued. Call on Steel Industrial Area Annealing, Re- Same team to inspect and report for next month CMC. Reply 21.01.2009 Industries, rolling, Circle 24.10.2007 received on Cutting Ask him to apply for consent to establish. 01.12.2008. 20.11.2007 Unit had Issue letter for applying for Consent to Establish. informed that 30.01.2008 they Since this is the highly polluting activity and the Bank disconnected Guarantee was taken only for six months which period is all the over now, the Bank Guarantee may be taken afresh valid machines upto 06.02.2010. and will be 19.09.2008 sold the SIT to inspect and report. Call on 20.10.2008. same when 05.11.2008 some buyer, Unit may be asked to remove equipments related to cames. So rerolling activity and annealing furance. Call on requesting for 10.12.2008 giving sometime. 10 M/s Manish A-83, Wazirpur Pickling, cold 27.09.2007 Letter issued Compliance Industries, Industrial Area rolling, Circle Same team to inspect and report for next month CMC. for correction to be done by Cutting 24.10.2007 of Account Let him correct the deficiencies and ask him to apply for deficiencies. Officer within consent to establish. Reply 15 days. Call 20.11.2007 received on on Let him correct the deficiencies and ask him to apply for 28.11.2008. 21.01.2009 Consent to Establish. Unit informed 30.01.2008 that they Since this is the highly polluting activity and the Bank have Guarantee was taken only for six months which period is corrected,all over now, the Bank Guarantee may be taken afresh valid the upto 06.02.2010. deficiencies, 19.09.2008 noted by SIT. SIT to inspect and report. Call on 20.10.2008. Process of 05.11.2008 forfeiture of The following deficiencies were noted by SIT be BG under communicated to the unit for correction: way as the (i) Leakage observed in pipe fitting of reaction tank's unit had hoppers of ETP. submitted a (ii) Stirrer of reaction tank needs to be repaired as same is single BG for not functioning properly. Rs. 3 Lakhs. (iii) pH of treated water chamber connected with sewer line was found to be 4.0.

Also forfeit the Bank Guarantee under Water Act immediately. Call on 10.12.2008 11 M/s Jai Paras A-16, Wazirpur Pickling, 27.09.2007 Letter issued. Ask the unit Steel, Indl. Area Same team to inspect and report for next month CMC. Reply awaited. to file 24.10.2007 adequacy Ask him to apply for consent to establish. report. Call 20.11.2007 on Issue letter for applying for Consent to Establish. 21.01.2008 30.01.2008 Since this is the highly polluting activity and the Bank Guarantee was taken only for six months which period is over now, the Bank Guarantee may be taken afresh valid upto 06.02.2010. 19.09.2008 SIT to inspect and report. Call on 20.10.2008. 05.11.2008 The following deficiencies were noted by SIT be communicated to the unit for correction: (i) ECS needs to be repaired as fumes were observed around pickling area. Call on 10.12.2008 12 M/s Ravi 69 & 70 Shed, Pickling, 27.09.2007 Letter issued. No action. Steel Wazirpur Indl. Annealing, Re- Same team to inspect and report for next month CMC. Reply received Industries, Area. rolling 24.10.2007 on 05.10.2008. Ask him to apply for consent to establish. Unit submitted 20.11.2007 affidvit for SIT Issue letter for applying for Consent to Establish. correction. 30.01.2008 He may be asked to file Bank Guarantee of Rupees One Lakh under Air Act valid upto 06.02.2010. 19.09.2008 Call on 20.10.2008 with compliance of correction of deficiencies. 05.11.2008 Ask the unit to file affidavit for correction of deficiencies noted by SIT. Call on 10.12.2008 13 M/s Shree A-16, Wazirpur As informed by 27.09.2007 Reminder Issue fresh Krishna Indl. Area other units in No confirmation received about power by this name. MS issued. reminder. Rolling same premises, to write to Gen. Manager, NDPL asking for about the No compliance Call on Industries, M/s Krishna power disconnection in this name. Compliance of DJB report 21.01.2009 Rolling is not and MCD also not received. MS to write to their senior received. existing officials. 24.10.2007 put up in next CMC on 20.11.07. 20.11.2007 Ask for compliance by DJB and MCD. 30.01.2008 Seek the compliance report. 19.09.2008 Issue reminder for compliance report. Call on 20.10.2008 05.11.2008 Issue final reminder for compliance report. Call on 10.12.2008