1. Pre-Power Checks

Total Page:16

File Type:pdf, Size:1020Kb

1. Pre-Power Checks

CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

______Request No. : Date :

Section : Model No.:

Location/Drwg. No.: Serial No.:

System : Sheet No. 1 of 6 ______

1. Pre-Power Checks

a. Check that the input feeder (and the bypass feeder, if dual-input) current capacity matches the requirement of the system. Refer to the Installation manual for proper feeder sizing. Have the customer set the magnetic trip and GFI setting(s) to maximum (if applicable). Record the recommended and actual feeder sizes.

Input Feed Size

Recommended: Actual Input: Bypass:

b. Check for proper configuration of the system ground and neutral wiring. Indicate which of the following is/are present in the system.

Input Neutral Output Neutral Neutral – Ground (Service Entrance)

c. Record the internal and external (if applicable) battery information, including open- cell voltage reading below:

Battery Data:

(Internal Battery) Model No.: Date Code: Cell Count: Open Cell Volts: CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

Battery Tag No. (External) Model No.: Date Code: Open Cell Volts:

Sheet No. 2 of 6

2. Startup

a. Using the instructions in Liebert Online, perform power supply checks and record the voltages.

Power Supply 1 +24V: +15V: -15V: AC Ripple AC Ripple AC Ripple

Power Supply 2 +24V: +15V: -15V: AC Ripple AC Ripple AC Ripple

b. Record the revision of firmware from the display for the DSP and Monitor boards.

Rectifier Inverter Monitor

3. Operation checks

a. Using a multi-meter, record specified voltages and currents according to the tables

Input AC Volts: A – B: B - C C - A A - N B - N C - N

(Dual – Input Only) Bypass AC Volt/Currents: A – B: B - C C - A A - N B - N C - N CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

I - A I - B I - C

Output AC Volt/Currents (Inverter): A – B: B - C C - A A - N B - N C - N I - A I - B I - C

Output AC Volt/Currents (Static Bypass): A – B: B - C C - A A - N B - N C - N I - A I - B I - C

Sheet No. 3 of 6

Output AC Volts/Current (Maintenance Bypass): A – B: B - C C - A A - N B - N C - N

PFC Voltages Positive Bus Negative Bus (+DC Caps – Gnd): (-DC Caps – Gnd):

Float Voltages

Positive Battery Bus: Negative Battery Bus: AC Ripple: AC Ripple: Current: Current:

Input Current Output Filter Current A Pahse: A Pahse: B Phase: B Phase: C Pahse: C Pahse:

b. Record the following LCD Display readings and verify accurate to +/- 2.5%. CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

Mains A B C L – N Volts : L – N Amps. : Frequency : L- L Volts : Power Factor :

Bypass A B C L – N Volts : Frequency : L- L Volts : Sheet No. 4 of 6

Output A B C L – N Volts : L – N Amps. : Frequency : L- L Volts : Power Factor : E – N Volts

Load A B C Sout (kVA) : Pout (kW) : Qout (kVAR) : Load Level (%) : Crest Factor :

System (N + 1 Only) A B C Sout (kVA) : Pout (kW) : CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

Qout (kVAR) :

Battery Battery Voltage : Battery Current : Battery Temp. : Battery Capacity : Ripple Volts RMS

4. Post – Startup

1. Refer LOL Paramset tables to confirm all UPS firmware are current release, if not shut down the UPS. Carry out LOL flash update procedure for NXe/NXf. Once completed check UPS operation. Enter updated firmware revision.

Completed :

N/A :

Rectifier : Inverter : Monitor : Sheet No. 5 of 6

SL. Description Completed (Yes/No) No. 1 Shut down the UPS. Install any option kits that shipped with the unit. Install each kit carefully, one at a time. Restart the UPS each time an option is installed, to check that it is operating properly. List all options that are present in the unit. 2 Shut down allow voltages to discharge and check then reinstall all sheet metal barriers that were removed in step 8.1.7. Check that no holes or gaps are present inside the UPS cabinet that could interfere with proper airflow for component cooling (examples include conduit holes not filled, and gaps between the access panels and the frame). 3 Clean the exterior of the UPS, battery cabinet(s), maintenance bypass cabinet, and Distribution Panel (if CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

applicable) to remove any dust or foreign material. 4 If load can be applied check all voltages and currents using software to match measured readings with test meter. Note: Load should be 30% or greater for current readings Do not re-calibrate if display readings on load vary +/- 2.5% of test meter document readings and load and report results to technical support 5 Indicate that the startup is complete by recording the name of the customer representative approving the work, and having them sign below.

6 Others

Sheet No. 6 of 6

Remarks: CLIENT

CONSULTANT

EPC Contractor: Drake & Scull Water and Power

Project Title: Msheireb Downtown Doha, District Cooling Plant UPS Commissioning Record (TECR-07)

Check By: Inspected By: Inspected By: Witness By: Emerson/Liebert Third Party DSWP M – Engineering Representative NAME : NAME : NAME : NAME :

SIGN : SIGN : SIGN : SIGN :

DATE : DATE : DATE : DATE :