CS 630 Quiz #2 Spring 2012
Total Page:16
File Type:pdf, Size:1020Kb
CS 630 Quiz #2 Spring 2012 Name______KEY______
1. What are the phases of the traditional project life cycle? ANSWER: Concept, development, implementation, and close-out 2. What type of organizational structure has project team members reporting to at least two bosses? ANSWER: Matrix 3. What type of organizational structure gives the least amount of authority to project managers? ANSWER: Functional 4. Name two characteristics of organizational culture that help project management. ANSWER: Project work is most successful in an organizational culture where employees identify more with the organization, where work activities emphasize groups, and where there is strong unit integration, high risk tolerance, performance- based rewards, high conflict tolerance, an open-systems focus, and a balanced focus on people, control, and means-orientation.