Council Traffic & Transport Committee SKDC(TTC) Paper no. 151/18 Report on Progress of Major Projects As at 30 June 2018

Project Estimated Responsible Commence- Completion No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 703TH Dualling of Hiram's 1,774.4 Secretary for 3/2016 End 2020 The project scope mainly Works commenced in March Highway between Transport and comprises widening two 2016. Construction of Ho Cat. A Housing sections of Hiram’s Highway Chung Bridge (Kowloon Road and Marina between Clear Water Bay Bound), Nam Pin Wai Cove and Road and Ta Ku Ling and Footbridge, noise barrier and TD Improvement to between Nam Pin Wai retaining walls were in Local Access to Ho HyD Roundabout and Marina progress. Chung Cove to dual carriageway.

- 1 -

As at 30 June 2018

Project Estimated Responsible Commence- Completion No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 872TH Tseung Kwan O – 15,093 Secretary for 7/2016 2021 The main tunnel and The main tunnel, Road P2 and Transport and associated works of Tseung northern footbridge works Cat A Lam Tin Tunnel – Housing Kwan O – Lam Tin Tunnel contracts commenced in Main Tunnel and (TKO – LTT) will connect 2016. Road P2/D4 works Associated Works CEDD Tseung Kwan O and Lam Tin contract and Tseung Kwan O to meet the transport needs Interchange works contract arising from the continuous commenced in November development of Tseung 2017 and February 2018 Kwan O. respectively. The remaining works contracts of the project The main tunnel and will be tendered associated works comprise progressively. a dual two-lane trunk road of approximately 3.8 km long Construction of tunnel (about 2.2 km in the form of portals, main tunnel, open a tunnel) connecting Tseung blasting works, marine Kwan O Town Centre in the viaduct foundation, Northern east to Lam Tin, Eastern Footbridge decking, and the Harbour Crossing and Cha dredging and filling works in Kwo Ling Road in the west. were in progress.

Reclamation provides 3 ha. of land for construction of the depressed Road P2.

- 2 -

As at 30 June 2018

Project Estimated Responsible Commence- Completion No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) Head 706 Provision of 87 Secretary for 4/2015 2/2019 The project aims to provide Universal Access Transport and lift facilities for the following Subhead Facilities at Public Housing 3 footbridges in Sai Kung 6101TX Footbridges, Elevated District: Cat D Walkways and CEDD Subways Package 2 – 1. Footbridge across For NF193, testing and Investigation, Design Road North near Lam commissioning at Lifts 1 and and Construction Shing Road (Structure No. 2 were in progress. NF193);

2. Footbridge across Po Ning For NF309, lift shaft Road near Po Shun Road construction works at Lifts 1 (Structure No. NF309); and 2 were in progress. and

3. Footbridge across Tong For NF336, the lift had been Ming Street near Sheung opened for public use. Tak Shopping Centre (Structure No. NF336).

- 3 -

As at 30 June 2018

Project Estimated Responsible Commence- Completion No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 158TB Elevated Walkway 221.6 Secretary for 12/2016 Mid 2019 Works mainly include the Construction commenced on Cat. A between Tong Ming Transport and construction of an elevated 30 December 2016. Street and Tong Tak Housing walkway between Tong Ming Street, Tseung Kwan Street and Tong Tak Street, The foundation works for the O TD and a lift at the end of the elevated walkway and lift HyD walkway near Tong Tak shaft were substantially Street. completed and the construction of piers was in progress.

716CL Infrastructure Works Under Secretary for Under Under Works comprise the Detailed design was near Cat B for Tseung Kwan O review Development review review construction of a feature completion. Stage I Landfill Site footbridge (Southern Bridge) CEDD across the southern tip of the The authorization notices Eastern Channel, a sewage under Roads (Works, Use and pumping station and the Compensation) Ordinance associated landscaping and the amendment of the works. sewerage scheme under Roads Ordinance as applied by the Water Pollution Control (Sewerage) Regulation were published on 25 September 2015 and 30 April 2015 respectively.

- 4 -

As at 30 June 2018

Project Estimated Responsible Commence- Completion No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 822TH Cross Bay Link 5,625 Secretary for 7/2018 2022 Cross Bay Link will connect The first works contract for Cat. A Transport and Tseung Kwan O – Lam Tin bridge works were awarded in Housing Tunnel to Wan Po Road near end of June 2018 for Area 86 to cope with the commencement in July 2018. CEDD anticipated traffic demand. It Tendering of remaining works will provide alternative route contracts was in progress. to divert traffic from the town centre south so as to improve the living environment of the residential areas.

The Cross Bay Link comprises the construction of an approximately 1.8 km long dual two-lane carriageway with cycle track and footpath.

- 5 -

As at 30 June 2018

Project Estimated Responsible Commence- Completion No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 806TH Dualling of Hiram’s Under Secretary for Under Under The major scope of works The improvement proposal Cat. B Highway from review Transport and review review comprises improving the was being reviewed and Marina Cove to Sai Housing section of Hiram’s Highway refined on the basis of Kung Town from Marina Cove to Sai received views and updated TD Kung Town, Po Tung Road information. The and the section of Tai Mong implementation of project HyD Tsai Road in the south of Sha would be continued according Ha. The project aims to cope to Public Works Programme with the existing and procedures. anticipated traffic needs and to alleviate the congested traffic condition.

- 6 -