REQUEST FOR PROPOSALS

PROFESSIONAL SERVICES FOR REPAIR AND IMPROVEMENT OF WATER TRANSMISSION MAIN CATHODIC PROTECTION SYSTEMS PROJECT NO. 7061518AC

December 2018

Florida Keys Aqueduct Authority 1100 Kennedy Drive , 33040 (305) 295-2454

Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

TABLE OF CONTENTS

SECTION PAGE Introduction and Background Information ...... 1 Scope of Work ...... 2 Tentative Schedule...... 2 Questions ...... 3 Submission of Proposals ...... 3 Selection Criteria ...... 4

EXHIBIT NUMBER OF PAGES Exhibit A Draft Technical Memorandum, Assessment of Transmission Main Cathodic Protection Systems ...... 101 Exhibit B Technical Memorandum, FKAA Cathodic Protection – Restoration of Facilities Damaged or Destroyed by ...... 11 Exhibit C Sample Contract Documents ...... 25

i

Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

The Florida Keys Aqueduct Authority (FKAA) is seeking Proposals from qualified professional firms to provide expertise and professional services for design, bid package development and construction phase services for repair and improvement of water transmission main cathodic protection (CP) systems.

INTRODUCTION AND BACKGROUND INFORMATION The FKAA is a political subdivision of the State of Florida, established by Special Act, Ch. 76-441, as amended, for purposes of obtaining, supplying and distributing potable water to the Florida Keys. Potable water is primarily produced by the FKAA at the J. Robert Dean Water Treatment Plant, located in Florida City, and transported alongside the to the FKAA’s customers through approximately 187 miles of water transmission main, crossing 43 bridges, and distributed through approximately 690 miles of smaller-diameter piping. The transmission main ranges in size from 36 inches leaving the water treatment plant in Florida City to 18 inches at the end of the system in Key West. There is an additional section of 12- to 16-inch piping from northward to Ocean Reef.

The FKAA maintains an extensive array of cathodic protection (CP) systems for corrosion control of buried sections of steel water transmission main and submerged interior surfaces of steel water storage tanks. The CP systems are located throughout the Florida Keys and have proven essential for reliable delivery of potable water in the corrosive marine environment.

The FKAA operates its CP systems on a continuous basis and periodically monitors each system. Monitoring by FKAA forces is done annually, and engineering evaluations of the CP facilities are contracted when the need arises. The most recent engineering evaluation was completed by CH2M HILL Engineers, Inc. (CH2M) in August 2017. This evaluation provided a thorough understanding of the condition of the FKAA’s CP facilities prior to the arrival of Hurricane Irma in September 2017 and included recommended CP system improvements. The draft Technical Memorandum (Tech Memo), Assessment of Transmission Main Cathodic Protection Systems is included as Exhibit A.

In December 2017, the FKAA surveyed its CP systems to assess conditions after Hurricane Irma. Results indicated that extensive damage and destruction of many facilities had occurred due to storm surge, high winds, and debris cleanup by heavy equipment. CH2M reviewed the results of the FKAA’s field survey and developed Tech Memo, FKAA Cathodic Protection – Restoration of Facilities Damaged or Destroyed by Hurricane Irma is included as Exhibit B.

Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

These two documents (exhibits A and B) will be the basis for design of the water transmission main CP systems repair and improvements project.

SCOPE OF WORK The selected engineering firm (Consultant) will provide professional engineering services to the FKAA for design, bid package development and construction phase services for repair and improvement of water transmission main CP systems from Florida City to Key West. Design elements will be for the steel transmission pipeline CP only. Storage tank CP systems are not included as part of this Request for Proposal (RFP).

Specific tasks and basis for services should include:

• Repairs to hurricane-damaged CP facilities identified by the FKAA, included in Exhibit B; • Improvements to CP systems at bridge crossing and between Overseas Highway Mile Markers (MM) 121 – 122 (18-Mile Street) as shown in Exhibit A; and • Additional unprotected buried steel transmission main, generally consisting of nine (9) sections totaling at least 10,724 feet of pipeline near the bridge crossings and five (5) crossings of the Overseas Highway that may involve steel casings under the highway, discovered during CH2M’s engineering evaluation and identified in Exhibit A and associated appendices.

Specific tasks not included in this RFP are as follows:

• Storage tank CP systems; and • Key West and Marathon CP system improvements described by Exhibit A.

To facilitate the FKAA’s tracking and possible reimbursement by the Federal Emergency Management Agency (FEMA) for hurricane-related repairs, the bid documents should be cataloged to include hurricane damage repairs, alternative improvements to hurricane damages and improvements to elements that are not a direct result of hurricane damage.

TENTATIVE SCHEDULE Issuance of Request for Proposal (RFP) ...... December 5, 2018 Question Submission Due Date ...... January 11, 2019 Proposal Submission Due Date ...... January 18, 2019 Notification of Selected Firm ...... January 25, 2019 Interview Date ...... TBD Award of Services Contract by Board of Directors ...... February 27, 2019 Final Bid Documents ...... August 23, 2019

2 Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

QUESTIONS

All communications concerning this RFP must be in writing. Written questions regarding details of this RFP will be accepted and must be received by the FKAA no later than 4:00 p.m., local time, five (5) full working days prior to the proposal due date, and addressed to:

David Jackson Department of Purchasing Florida Keys Aqueduct Authority 7000 Front Street, , Florida 33040 Phone: 305-295-2244 E-Mail: [email protected]

SUBMISSION OF PROPOSALS To be responsive to this request for professional services, the interested firm must submit two (2) complete copies and one (1) electronic copy of the Proposal, sealed, to the Florida Keys Aqueduct Authority no later than 4:00 p.m., local time, on the 18th day of January 2019, addressed to:

David Jackson Department of Purchasing Florida Keys Aqueduct Authority 7000 Front Street, Stock Island, Florida 33040

Please Note: U.S. Postal Service does not deliver to this address; only UPS, FedEX and hand delivery.

Packages received by the FKAA after the time specified for receipt will not be considered. Consultants shall assume full responsibility for timely delivery at the location designated for receipt of proposals.

The Proposals should not exceed 15 pages in length, excluding resumes, and should include the following information:

• Technical Approach to the Scope of Work. • Firm Background and Experience: Provide a brief introduction of the firm and areas of expertise, and experience related to CP repair and improvements; list at least four projects showing experience with similar-sized, or larger, CP systems. • Project Team: Identify the key project personnel that will be involved in the project including specific role, availability, commitment to the project and any sub-consultants. Include resumes for key personnel.

3

Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

• Estimated Fee: Propose a maximum, not-to-exceed, estimate of the total fee for the Scope of Work, based on a detailed breakdown of average hourly rates by labor category, sub-consultant fees, and expenses.

• Schedule: Provide a schedule for completing design and bid package development for the project, prepared using whichever software the Consultant considers appropriate for the purpose. The proposed schedule need not be cost or resource-loaded. The Consultant may propose different durations than those specified in the tentative schedule of this RFP, but an explanation for those differences should be included in the Proposal.

SELECTION CRITERIA Review of the Proposal Packages will be performed by the Deputy Executive Director of Utility Operations, or his designee. The Proposals will be the primary basis for determination of the selected Consultant. However, if determined necessary by the FKAA, a short-list of qualified firms may be developed, and interviews requested with such firms in order to make the selection. In such case, the FKAA will send a notification to each selected firm making the short-list and will schedule a time for an oral presentation/interview with information regarding the interview. The FKAA will also notify firms that are not selected at this same time. Selection will be based on the following categories:

• Technical approach to the Scope of Work. (35 percent) • Firm Background and Experience (20 percent) • Project Team (20 percent) • Estimated Fee (20 percent) • Schedule. (5 percent)

The selected Consultant will submit and sign the contract included as Exhibit C.

4

Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

EXHIBIT A

Draft Technical Memorandum, Assessment of Transmission Main Cathodic Protection Systems Request for Proposal EXHIBIT A

TECHNICAL MEMORANDUM- DRAFT

Assessment of Transmission Main Cathodic Protection Systems

Prepared for Florida Keys Aqueduct Authority

October 2017

CH2M HILL INC Request for Proposal EXHIBIT A Contents

Section Page

Contents ...... iii Acronyms and Abbreviations ...... v 1 Introduction ...... 1-1 1.1 Bridge Crossings ...... 1-1 1.2 Key West ...... 1-1 1.3 Marathon ...... 1-2 1.4 The 18-Mile Stretch MM 121-122 ...... 1-2 1.5 Recommended Improvements ...... 1-2 1.6 Construction Cost Estimate ...... 1-2 1.7 Cathodic Protection ...... 1-2 1.7.1 Galvanic Anodes...... 1-3 1.7.2 Impressed Current ...... 1-3 2 Test Methods ...... 2-1 2.1 Pipe-to-Soil Potential Measurement ...... 2-1 2.2 Current Measurement ...... 2-1 2.3 Current Requirement ...... 2-2 2.4 Electronic Location ...... 2-2 2.5 Photographs ...... 2-3 3 Bridge Crossings ...... 3-1 3.1 Background ...... 3-1 3.2 2017 Inspection and Testing ...... 3-1 3.3 Results ...... 3-2 3.4 Road Crossings ...... 3-2 3.5 Recommended CP Improvements ...... 3-3 4 Key West ...... 4-1 4.1 Background ...... 4-1 4.2 2017 Inspection and Testing ...... 4-1 4.3 Conclusions ...... 4-3 5 Marathon ...... 5-1 5.1 Background ...... 5-1 5.2 2017 Inspection and Testing ...... 5-1 5.2.1 Knight’s Key to Marathon Booster Pump Station ...... 5-1 5.2.2 Marathon Booster Pump Station ...... 5-2 5.2.3 Marathon Booster Pump Station to Vaca Cut ...... 5-2 5.3 Conclusions ...... 5-3 6 The 18- Mile Stretch MM 121 – 122 ...... 6-1 6.1 Background ...... 6-1 6.2 2017 Inspection and Testing ...... 6-1 6.3 Conclusions ...... 6-2 Request for Proposal EXHIBIT A CONTENTS Section Page 7 Recommended Improvements ...... 7-1 7.1 Bridge Crossings ...... 7-1 7.2 Other Facilities ...... 7-1 7.3 Operation and Maintenance Improvements ...... 7-1 7.3.1 Organizational Approach to Maintenance of CP Facilities ...... 7-2 7.3.2 Remote Monitoring of Rectifiers ...... 7-2 8 Construction Cost Opinion...... 8-1 8.1 Basis for Estimated Costs ...... 8-1 8.2 Cost Savings ...... 8-2 8.3 Recommendations ...... 8-2

Appendixes A Bridge Crossings B Key West C Marathon D MM 121-122 E Recommended Improvements F Construction Cost Estimate

Tables 3-1 Cathodic Protection Summary- Bridge Crossings ...... 3-2 4-1 Cathodic Protection Station Status- Key West ...... 4-2 5-1 Cathodic Protection Station Status- Marathon West ...... 5-2 5-2 Cathodic Protection Station Status- Marathon East ...... 5-3 6-1 Cathodic Protection Test Results ...... 6-2 8-1 Class 4 Construction Cost Estimate ...... 8-1

Figures 1-1 Typical Cathodic Protection Layout at Bridge Crossings ...... 1-4 1-2 Typical Impressed Current Cathodic Protection Layout for Buried Steel Transmission Mains .... 1-5

IV CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A Acronyms and Abbreviations

AC Alternating Current Ammeter Meter for measurement of electrical current Ampere Unit of electrical current Anode The corroding part of a corrosion cell or cathodic protection system Big Fink Brand name of post-mount test station with colored plastic cover Bond Wire connecting multiple components for electrical continuity Bond Station Box containing bond wire and connections Bond Wire Same as Bond Cable Insulated copper conductor, the same as wire Cathode The protected or non-corroding part of a corrosion cell Cathodic Related to a negative change in DC electrical potential Cathodic Protection Method of corrosion control by galvanic or impressed electrical current CP Cathodic protection Continuity Electrical connection between component parts Cooperative Testing Testing done in cooperation with another agency for stray current control Coating Protective coating, usually on the exterior of the pipeline CSE Copper/Copper Sulfate Reference Electrode used for testing Current Flow of electrical charge Current Density The electrical current applied to a structure divided by its surface area Current Requirement The amount of current required for cathodic protection DC Direct Current Deep Anode A drilled hole in the earth that contains cathodic protection anodes Dielectric Electrically insulating material Diode Electronic device that converts AC electricity to DC Disconnect Switch Electrical switch for turning on and off power to equipment Dresser Coupling Flexible coupling joint for pipe, made with sleeve, rings, and bolts Ductile Iron Pipe material made of cast iron alloyed for ductility Electrochemical Chemical changes with simultaneous electrical current Flexible Coupling Same as Dresser Coupling Flush Mount Installed at ground level, usually in a small concrete pad Flush Fink Brand name of flush-mounted test station made of plastic Foreign Owned or operated by another agency or company Galvanic Naturally occurring electrical differences between metals Request for Proposal EXHIBIT A ACRONYMS AND ABBREVIATIONS

Galvanic Anode Magnesium or zinc bar in a bag of backfill and a lead wire Ground Bed Array of anodes used for cathodic protection, usually impressed current Header Wire Wire used to connect multiple smaller anode wires IJ Insulated Joint Impressed Current Cathodic protection using an external (not galvanic) power source Impressed Current Station Rectifier or other power source, ground bed, and associated wiring Insulated Flange Flanged pipe joint with dielectric gasket, bolt sleeves and washers Insulated Joint Pipe joint with dielectric materials intended to create electrical isolation Insulation Dielectric material Interference Corrosion caused by electrical current departing from intended circuit Interrupt Cycle on and off using a self-timing switch, for purposes of testing IR Voltage resulting from current (I) through resistance (R), also called IR Drop Isolation Electrical insulation Joint Bond Wire for electrical connection of pipe across a gasket joint Junction Box Box for wires and associated connections Lead Same as wire, such as anode lead or test lead Lightning Arrestor Device used to protect equipment from electrical surges MIC Microbial Induced Corrosion Mile Marker Distance from Key West Pump Station, in miles Milliampere One one-thousandth of an ampere (0.001-ampere) Millivolt One one-thousandth of a volt (0.001-volt) MM Mile Marker NACE NACE International (formerly National Association of Corrosion Engineers) Negative DC polarity indicating connection to the Cathode or a more negative point OFF Cathodic protection source turned off or temporarily disconnected Ohm Unit of electrical resistance; 1 ohm requires 1 volt to produce 1 ampere Ohm’s Law Voltage (E) equals current (I) multiplied by resistance (R) or E = IR ON Cathodic protection source turned on Pipe-to-Soil Potential Measurement of voltage of pipe to a reference electrode in contact with earth Positive DC polarity indicating connection to the Anode or a more positive point Post Mount Mounted on a post or conduit, such as a test station Protected Receiving cathodic protection or intended to receive it Potential Electrical voltage PSP Pipe-to-soil potential Rectifier DC power source consisting of step-down transformer and diodes

VI CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A ACRONYMS AND ABBREVIATIONS

Remote Outside of the area where current causes voltage drop in the earth Resistance Bond A bond wire with a fixed or variable resistor to limit current Ribbon Anode A long narrow strip of anodic metal used for galvanic cathodic protection Sacrificial Anode Same as Galvanic Anode Shunt A calibrated resistor for measuring DC current by voltage drop Solid State Decoupler Electrical device that blocks low-level DC while passing AC and high-level DC SSD Solid State Decoupler Steel Material composed of iron with small amounts of carbon and other elements Stray Current Electrical current that departs from its intended circuit or path Taps Controls for rectifier DC output consisting of Coarse and Fine steps Tap Setting Positions of the Taps, such as Coarse-1, Fine-3 Terminal Connection points for wires in a junction box or test station Test Station Box with wires to the pipe for testing cathodic protection Transformer Electrical device used to adjust AC voltage higher or lower Transition Change in pipe material from steel to ductile iron, or the reverse Unprotected Not receiving cathodic protection or not intended to receive it µA/SF Microamperes per square foot VV Valve Vault Wire Insulated copper conductor for electrical use

694334.03.30.01 CH2M HILL INC. VII Request for Proposal EXHIBIT A

SECTION 1 Introduction

This Technical Memorandum presents the results of an assessment of certain cathodic protection (CP) systems for corrosion control of buried steel water transmission mains operated by the Florida Keys Aqueduct Authority (FKAA). The assessment was the Predesign Phase of FKAA Project 1511-17. The FKAA will review the results and may elect to proceed with design of improvements for CP systems. CH2M services for the project were authorized by Contract CH6-17. The assessment included inspection, testing, and evaluation of designated CP facilities to assess their condition and identify needs for restoration or improvement. The approach and test methods used for the assessment are described in Section 2. Field investigations were conducted by CH2M with assistance from FKAA electricians and pipeline operators during June-August 2017. The field investigations were completed prior to Hurricane Irma, and any hurricane damage to facilities is not reflected in this document. The FKAA facilities included in the project are described below. The locations and types of CP facilities are identified on the FKAA’s Pictometry software. 1.1 Bridge Crossings There are 42 active bridge crossings in the Overseas Highway (US 1) along the Florida Keys. The scope of this project included 39 bridges where the steel transmission main is installed on the bridge over the water, and the pipeline is buried in the earth adjacent to the channel. The configuration of the buried pipeline can be different on each side of the channel, so there were 78 separate sections of steel pipeline evaluated for CP in this project. Most steel transmission main bridge crossings are 24-inches (in) diameter, with several 30-in crossings, two 36-in crossings, and one 18-in crossing. The length of buried steel pipeline ranges from 6 feet to several hundred feet or more before the transmission main transitions to ductile iron pipe. Galvanic anodes and test stations were originally installed to provide CP for buried pipelines at the crossings when the bridges were built around 1980. The CP facilities were periodically monitored, and an assessment in 1998 led to the installation of new anodes and test stations at some bridge crossings under Phase 1 CP Improvements in 2003. The typical useful life of an anode is 15 years, and the FKAA recognized that another assessment of the facilities was warranted in 2017. Results of the CP evaluation of bridge crossings in 2017 are described in Section 3. 1.2 Key West The steel transmission main on Key West consists of approximately 8,000 feet of 18-in pipeline and a few feet of 12-in pipeline. The CP system has 5 impressed current CP stations and 7 test stations, all of which are in the streets of Key West. The CP facilities were constructed in 2008, under Phase 2 CP Improvements. There were several known issues with CP facilities in Key West. Access is challenging due to heavy traffic and limited space. In 2016, a CP rectifier station was damaged and required repair. One of the test stations was covered with street pavement. The steel transmission main was known to have inadequate CP near the Key West Pump Station, and this was attributed to incomplete electrical isolation of the steel main near the Monroe County Courthouse. A corrosion leak recently occurred in the pipeline on Request for Proposal EXHIBIT A SECTION 1 – INTRODUCTION

Eaton Street, illustrating the need for an assessment of CP facilities in Key West. Results of the CP evaluation in Key West in 2017 are described in Section 4. 1.3 Marathon There are 5 active sections of 24- and 30-in diameter steel pipeline on Marathon, including sections at and Vaca Cut. The 18-in steel transmission main has been almost entirely deactivated on Marathon, but its CP system provided protection for some active sections of steel transmission main. The FKAA recognized that an assessment of CP was needed to assure continued CP of the 30-in steel main with the 18-in main deactivated. The section of 24-in steel main on Knight’s Key at Seven Mile Bridge had CP from a galvanic anode system installed during Phase 1 CP Improvements in 2003. Recent construction of landscaping improvements cut the anode wires and eliminated CP of the pipeline. The FKAA recognized that an assessment was needed to determine the best way to provide CP for the steel pipeline under present conditions on Knight’s Key. Results of the CP evaluation on Marathon in 2017 are described in Section 5. 1.4 The 18-Mile Stretch MM 121-122 There are two sections of 36-in steel transmission main in the 18-Mile Stretch. One section has an approximate length of 10 miles, from Mile Marker (MM) 106 to 116.5, and it is protected by an impressed current system constructed in 2008. The FKAA monitors the CP system, and it was excluded from the scope of this project. The other section of steel transmission main in the 18-Mile Stretch is located at MM 121-122 and is approximately 3,900 feet in length. CP was originally provided by sacrificial magnesium anodes and 12 test stations installed when the pipeline was constructed in about 1980. In 2008, new anodes were installed and the test stations were modified. Subsequent highway construction destroyed most of the CP facilities. The FKAA repaired several test stations and installed additional anodes in the last few years, but recognized that an assessment of the CP facilities was needed. Results of the CP evaluation at MM 121-122 in 2017 are described in Section 6. 1.5 Recommended Improvements After the field investigations were completed, a list of CP deficiencies was developed with corresponding recommended improvements or corrective actions for each pipeline. Recommended improvements to restore CP at bridge crossings consist mainly of galvanic anodes and test stations. However, other types of work are also required. Recommended improvements and their importance are described in Sections 7 and 8. 1.6 Construction Cost Estimate A preliminary construction cost opinion was prepared for the recommended CP Improvements. This is a Class 4 Estimate as described by AACE International Recommended Practice 18R-97. The cost opinion is preliminary because it is based on elements of work that are anticipated for construction but have not yet been designed. Estimated construction costs are described in Section 8. 1.7 Cathodic Protection CP is an electrochemical method of reducing or preventing corrosion of a metal surface by making it cathodic to its environment. This is accomplished by providing electrical direct current to the metal

1-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 1 – INTRODUCTION

surface from expendable or inert materials through the environment with sufficient intensity to suppress any electrochemical corrosion activity that is occurring on the metal surface. The two methods of applying CP are galvanic anodes and impressed current systems. The FKAA’s CP facilities include both types of systems, described in more detail below. CP of pipeline exterior (soil-side) surfaces requires CP facilities in the earth. Exterior CP does not control corrosion that may occur on internal (water-side) surfaces of the pipeline. CP is one of the most widely used forms of corrosion control. It is adaptable to many forms of metallic corrosion, and, when properly used, provides highly effective and economical protection from corrosion damage. The amount of protection applied can be regulated by the specific requirements of the site. The degree of protection applied and obtained can be measured. 1.7.1 Galvanic Anodes Galvanic anodes are made of active metals, usually zinc or magnesium. When an anode is connected to a buried or submerged steel pipeline, electrochemical oxidation (corrosion) occurs at the anode, while electrochemical reduction (protection) occurs at the steel cathode. The anode is attached by wire directly to the pipe or through a junction box called a test station. Figure 1-1 illustrates the typical arrangement of galvanic anodes and test stations constructed during Phase 1 for CP of the steel transmission mains at bridge crossings. Most of the bridge crossings have or had galvanic anodes, which are more efficient for CP of relatively short pipelines. 1.7.2 Impressed Current Impressed current CP systems use an external power source, which is usually a rectifier that converts alternating current (AC) electricity to direct current (DC). The DC positive terminal is electrically connected to a group of anodes called a ground bed. The DC negative terminal is electrically connected to the steel pipe to make it the cathode. The current is adjusted and monitored at the rectifier. Test stations are used to measure the CP effect along the connected pipeline. Impressed current CP stations were constructed during Phase 2 for CP of the 18-in steel transmission main. Some sections of 24- through 36-in steel transmission mains also have CP by impressed current. Figure 1-2 illustrates the arrangement of impressed current CP stations for buried steel transmission mains.

694334.03.30.01 CH2M HILL INC. 1-3 Request for Proposal EXHIBIT A Request for Proposal EXHIBIT A Request for Proposal EXHIBIT A

SECTION 2 Test Methods

This section describes the approach and methods of field investigation and testing of CP on buried steel transmission mains. The field tests were essentially electrical in nature and were based on established industry practices for CP testing. Selected photographs of the pipelines and test equipment follow the text in this section. The CP facilities included in the scope of work were visited for inspection and testing. Each site was visually examined to find existing test stations and assess their condition. Test stations are post- mounted or flush-mounted boxes containing wires that are connected to the pipe. Other visible pipeline features, such as flexible couplings at bridge crossings, were also noted. At each test station, the wires were inspected and tested to identify their function. A GPS coordinate was collected for each test station that was not previously documented during Phase 1 and Phase 2 CP Improvements. 2.1 Pipe-to-Soil Potential Measurement The pipe-to-soil potential (PSP) was measured at test stations using an MC Miller LC-4 digital electronic voltmeter and a copper sulfate reference electrode (CSE). If a test station was not found at a bridge crossing, direct contact was made to the steel main on the bridge for measurement of PSP. Values of PSP that are -850 millivolts (mV) or more negative to a CSE indicate adequate CP for buried steel. PSP values in the range of -650 to -850 mV CSE indicate marginal protection. PSP values -650 mV CSE or less negative indicate that CP is not adequate for buried steel. The assessment of CP is most accurate when the PSP is measured with the CP momentarily turned OFF so that the steel is tested in a ‘polarized’ condition. If the CP source cannot be turned OFF, the PSP measurement must be made with the CP source ON, and the assessment of CP is made with the knowledge that the assessment may be less accurate than if would be if the CP could be turned OFF for testing. Ductile iron pipe that is used for most of the buried transmission main does not, by design, have CP under most conditions, and PSP values that are -650 mV CSE or less negative are considered normal. Ductile iron pipe with PSP more negative than -650 mV CSE indicates that it has CP or is in metallic contact with a steel pipeline that has CP. At transitions between ductile iron and steel pipelines, connections were made with transition couplings or, less commonly, insulated flanged joints. Both types of connections were intended to provide electrical isolation between the two pipe materials. Test stations at the transitions were installed with test leads to the steel and ductile iron pipes so that the PSP of both materials could be measured. The difference in PSP between steel and ductile iron pipe provides an indication of the quality of electrical isolation at the transition between the two pipe materials. 2.2 Current Measurement Some test stations have wires from anodes or other pipelines that carry an electrical current for CP purposes. Where this configuration existed, the current was measured using a shunt. Shunts are calibrated resistors that have low values of resistance, such as 0.01 ohm. Measurement of voltage drop across the shunt indicates the current by Ohm’s Law. For example, 1.0 mV measured across a 0.01-ohm shunt indicates a current of 100 mA. Some test stations had shunts installed in anode wire connections, and those shunts were used to measure the anode current to the pipeline. Where shunts were not installed, the wires were temporarily

Request for Proposal EXHIBIT A SECTION 2 – TEST METHODS

disconnected and the current was measured with a portable shunt and voltmeter. All other current measurements were also made using a portable shunt and voltmeter. 2.3 Current Requirement If the measured pipe-to-soil potential indicated that CP was inadequate, a temporary electrical current was applied to determine the ‘current requirement’ of the section of pipeline. The current requirement indicates the amount of direct current (DC) electricity required for CP of the tested pipeline. The magnitude of the current requirement, relative to the length of the tested pipeline, also provides an indication of the quality of electrical isolation of the steel pipeline from the bridge or from adjacent buried ductile iron pipe. The temporary current was applied to the pipe using a battery and a ground such as a metallic cable temporarily submerged in the channel near the bridge. The temporary current was measured and cycled on and off while PSP measurements were made at the test points. The amount of applied current required to change the PSP to -850 mV CSE or more negative is the fundamental design parameter for CP of the tested pipeline. Where test leads to the ductile iron were present at test stations, the PSP of the ductile iron was measured while current was temporarily applied to the steel pipeline. The change in PSP with the test current OFF and ON provides another indication of the quality of electrical isolation between the steel and ductile iron. This test was helpful in situations where the PSP values of steel and ductile iron pipes were similar in their as-found condition, such as when CP of the steel was not adequate. 2.4 Electronic Location A Tinker & Rasor ‘Model PD Pipe and Cable Locator’ was used to electronically locate buried steel transmission mains and assess the length and electrical features of the pipelines. This instrument is an accurate locator or tracer of coated metallic pipelines that are electrically continuous across pipe joints. The Tinker & Rasor Model PD is commonly called a ‘short’ locator. A ‘short’ is a point of unintended electrical conductivity between a buried metallic pipeline and some other metallic pipeline or structure. The short locator can also indicate points where electrical conductivity ends, such as at an insulated joint for electrical isolation of a pipeline. The short locator can be used on electrical cables as well as on pipelines, and for submerged or buried environments. The Tinker & Rasor Model PD uses a separate transmitter and a receiver. One terminal of the transmitter is electrically connected to the pipeline, and the other terminal is connected to a separate, low-resistance grounding electrode such as a metal object submerged in seawater. The transmitter produces an audio frequency AC signal that passes through earth and water between the pipe and the grounding electrode. The receiver is placed over the area where the pipe will be located or traced. As the receiver is moved back and forth in a horizontal plane, a sharp null (silence) occurs in the received signal and indicates the exact location of the pipeline directly below the receiver. A well-coated pipeline can be followed for a considerable distance by this method. A short is indicated when the location of the null departs from the pipeline by another conductive path. Most shorts also reduce the strength of the signal and sharpness of the null over the pipeline on the side of the short furthest from the transmitter. This is due to the energy drained from the pipeline by the short. The short has the same adverse effect on CP of the pipeline. Locating a short allows correction of the condition and improved CP after the short is corrected or ‘cleared.’ Electrical isolation of the traced pipeline is indicated where the signal cannot be detected beyond a certain point, and there is not a short somewhere else along the pipeline. Electrical isolation that is weak or semi-conductive will usually cause a gradual decay in the strength of the signal and null as the

2-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 2 – TEST METHODS receiver is moved along the pipeline in the affected area. The pattern of decay is determined by several factors, including the weakness of isolation, the quality of the protective coating, and the conductivity of the earth or water around the pipeline. The differences between the Tinker & Rasor Model PD and most other conductive pipe locators are the frequency of the signal, the power of the transmitter, and the sensitivity of the receiver. Other locators are generally unsuitable for location of shorts and electrical isolation. 2.5 Photographs Selected photographs follow. They show the CP test equipment and steel transmission main at bridge crossings.

Photo 1. Rockland Channel Crossing East Side (), MM 10.0 The 24-in steel transmission main is buried for 479 feet on the land side of the bridge abutment. Test equipment has been set on the wall at the abutment.

694334.03.30.01 CH2M HILL INC. 2-3 Request for Proposal EXHIBIT A SECTION 2 – TEST METHODS

Photo 2. CP Test Equipment at Tea Table Relief, MM 79.8 In foreground, from left: pipe locator transmitter, receiver, and probe; wire reel. In background, from left: test leads, hand tools; 2 voltmeters.

Photo 3. Measurement of Pipe-to-Soil Potential The meter displays the measured potential as -920 mV CSE, which indicates adequate cathodic protection at the test location. The test is being conducted at a flush-mounted test station (cover not shown).

2-4 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 2 – TEST METHODS

Photo 4. Indian Key Channel East Side (Indian Key Fill), MM 78.4 Typical site conditions at bridge crossings with elevated bridge abutments including steep slopes, concrete rip-rap, and guard rail near buried pipeline.

Photo 5. Adams Waterway Crossing, MM 103.4 The 36-in water transmission main, looking toward Florida City. Red paint marks a flush- mounted test station. CP for the buried steel pipeline is provided by the impressed current system on Key Largo.

694334.03.30.01 CH2M HILL INC. 2-5 Request for Proposal EXHIBIT A

SECTION 3 Bridge Crossings

This section covers bridge crossings, where the transmission main is installed on the highway bridge over the water. The scope of the project included 39 bridge crossings from Cow Key Channel to Adams Waterway. Bridge crossings that were not included in the project were: Jewfish Creek flyover; Salt Run Bridge in Key West; and an unnamed bridge on North Roosevelt Boulevard near Key West City Hall. At Snake Creek, the steel transmission main has a subaqueous crossing and is not installed on the bridge. 3.1 Background All the bridge crossing pipelines are constructed from steel pipe. The pipeline is exposed on the bridge except in a few locations where it is within a hollow core concrete bridge structure. The steel pipeline is buried in the earth adjacent to the channel. The steel pipe is coated and is intended to be electrically isolated from the bridge and from the ductile iron transmission main. The buried pipeline on each side of the channel is electrically independent from the pipeline on the other side, so there are 78 discrete pipelines for CP purposes. The steel pipelines are buried for varying distances on each side of the bridges before connecting to ductile iron pipe. The diameter of the steel transmission main is 24-in or 30-in at most bridge crossings. Two crossings are 36-in diameter, and one crossing is 18-in diameter. The length of buried steel pipeline ranges from 6 feet to several hundred feet or more before the transmission main transitions to ductile iron pipe. Galvanic anodes and test stations for pipeline CP were originally installed at the crossings around 1980, when the bridges were built. The facilities were periodically monitored, and an assessment in 1998 led to the installation of new anodes and test stations at some bridge crossings under Phase 1 CP Improvements in 2003. In 2016, field tests were made at a few bridge crossings, and results indicated that CP was deficient at some of the tested locations. 3.2 2017 Inspection and Testing In 2017, all 39 bridge crossings from Cow Key Channel (MM 4.2) to Adams Waterway (MM 103.5) were visited for observation and testing of CP facilities on both sides of the channels. The methods of investigation and testing are described in the Test Methods section of this report. In summary, each site was examined to identify existing test stations and their condition. GPS coordinates were recorded for each test station that was found but not previously documented with GPS. The PSP was measured at each test station to assess the adequacy of CP and to identify test station wires. Where test stations were absent, direct metallic contact was made to the exposed steel pipeline for measurement of PSP. If the PSP indicated that CP was inadequate, a temporary test current was applied to the main to determine the cathodic current requirement for CP. An electronic locator was used at most locations to trace the buried steel pipeline and determine the locations of transition couplings and insulated flanges that provided electrical isolation. Steel pipelines without effective electrical isolation from the bridge or adjacent buried ductile iron pipe were identified based on the current requirement and the results of electronic tracing of the pipeline. Some of the bridge crossings also had a crossing under US 1 or an arterial road at some distance from the bridge. These ‘road crossings’ are believed to be steel pipe at all locations. An effort was made identify and, where possible, test the CP of the crossing pipelines.

Request for Proposal EXHIBIT A SECTION 3 – BRIDGE CROSSINGS 3.3 Results The results of the assessment of CP at bridge crossings are summarized in Table 3-1. Table 3-1. Cathodic Protection Summary- Bridge Crossings Test Date: June-August 2017

No. with No. with No. with Percent Location Adequate CP Marginal CP Inadequate CP Total Adequate CP Key West to Marathon (Cow Key Channel MM 4.2 to Knight’s Key MM 46.7) 14 6 32 52 27 Marathon to Key Largo (Vaca Cut MM 53.2 to Adams Waterway MM 103.4) 9 5 12 26 35

Total 23 11 44 78 29 Excludes Snake Creek subaqueous crossing MM 85.6 - 85.8 and bridge crossings outside MM 4.2 - 103.4

Only 23 of 78 sections of steel transmission main had adequate CP at bridge crossings. A total of 44 sections had essentially no CP, and 11 sections had marginal CP. Details are presented in Appendix A, which includes test results in Table A-1, followed by descriptions of the history and findings at tested locations. Results indicate that CP is adequate for only 27 percent of the steel pipeline sections west of Marathon, and for only 35 percent east of Marathon. Considering that there are 26 bridges west of Marathon and 13 bridges east of Marathon, there are more crossing pipelines at risk for corrosion in the Lower Keys. Test results suggest that most of the original anodes installed around 1980 have been consumed. Many of the original test stations have been destroyed or damaged by other construction or deteriorated from exposure to the elements. Some of the anodes and test stations installed in 2003 are in similar condition but others are intact and functional. An unexpected finding was the length of the buried steel transmission mains at numerous bridge crossings. Field tests showed that some of the steel pipelines are longer than previously thought. Islands that appear to have significantly longer lengths of buried steel pipeline include: Park, Ohio, Missouri, Indian, Indian Key Fill, Tea Table, and Lower Matecumbe Keys. The total length of pipelines that are known or strongly indicated as being steel by test results was 24,701 feet or 4.7 miles. There may be even longer lengths of steel pipelines in certain areas as noted in the detailed descriptions of the bridge crossings. It will be important to verify the lengths of steel pipelines at all locations so that CP can be provided for effective corrosion control. 3.4 Road Crossings Additional lengths of 24- to 36-in steel transmission main may exist at buried crossings of US 1. There appear to be 13 crossings of US 1 by 24- to 36-in transmission main as listed in Table A-2 of Appendix A. Several of these are known to have steel carrier pipe and casing based on work completed during Phase 1 and 2 CP Improvements. There are also other arterial road crossings with steel pipe in addition to the one shown in the table.

3-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 3 – BRIDGE CROSSINGS

CP tests were conducted on 4 crossings of US 1 and one arterial road crossing where the transmission main pipe material is steel. Test results indicated that CP was adequate in most cases and marginal at worst. There are 3 additional crossings of US 1 that were not tested but are known to have CP by impressed current from systems constructed in Phase 2 CP Improvements, and these are monitored by the FKAA. There is no information on the transmission main pipe material at 5 other crossings of US 1. They are listed in Table A-2 of Appendix A. Considering that steel pipe is known to exist at several other crossings of US 1, it seems possible that these 5 crossings may also have been constructed from steel pipe. Steel pipe would have had advantages in construction of road crossings, such as the relatively compact size of mitered bends for directional changes in the pipeline and thrust restraint provided by welded joints. It will be important to identify the pipe material at the other crossings and to determine the lengths of steel pipelines so that CP can be provided for effective corrosion control. 3.5 Recommended CP Improvements Recommended CP improvements for the bridges and road crossings are presented in Section 7. Restoration of CP at bridge crossings will require primarily the installation of galvanic anodes and test stations. However, other types of work will also be required at certain locations. It is also recommended that the FKAA verify the pipe material and length of sections of transmission main that are suspected to be constructed of steel pipe, so that CP can be provided for effective corrosion control of all steel pipelines. Similarly, the transmission main pipe material should be identified at 5 crossings of US 1 where the material is unknown, so that CP can be provided for all steel pipelines.

694334.03.30.01 CH2M HILL INC. 3-3 Request for Proposal EXHIBIT A

SECTION 4 Key West

This section covers the 18-in buried steel transmission main on Key West. The pipeline extends from the intersection of Eisenhower Drive and North Roosevelt Boulevard to the Key West Pump Station (KWPS). 4.1 Background The 18-in steel transmission main on Key West is nearly 8,000 feet in length. It transitions to PVC pipe at the intersection of Eisenhower Drive and North Roosevelt Boulevard. The 18-in main reduces to 12-in steel pipe near a valve on Whitehead Street at the Monroe County Courthouse. The 12-in steel pipe is thought to transition to cast iron pipe at the valve. The 12-in buried pipeline continues for approximately 240 feet through the Courthouse parking lot to KWPS. CP facilities for the steel pipeline were constructed in 2008 during Phase 2 CP Improvements. The CP facilities consist of 5 impressed current (rectifier) stations and 7 test stations. All CP facilities are in the streets of Key West, where access is challenging due to heavy traffic and limited space. During Phase 2, the construction contractor tested the 18-in pipeline for electrical continuity and installed joint bonds at 17 buried flexible couplings. All but one of the bonded joints were in Whitehead Street. The contractor’s commissioning report indicated that the 12-in and 18-in pipelines were electrically continuous to a test station in the Courthouse parking lot, but not from the test station to KWPS. The report stated that CP was not attained on the 12-in pipeline near KWPS and attributed this condition to incomplete electrical isolation. A magnesium anode was installed at the test station on the 12-in pipeline at the KWPS to supplement CP provided by the impressed current system. The FKAA has periodically monitored the CP system since it was installed in 2008. In 2016, the rectifier station near the Post Office was found damaged and out of service due to impact by a vehicle or equipment. The station was repaired and returned to service. In 2017, a leak occurred on the 18-in pipeline at 400A Eaton Street, which is about 50 feet north of Whitehead Street and 200 feet from the CP station at the Post Office. Inspection of the excavated pipeline by the FKAA indicated that external corrosion was the cause of the leak, which was subsequently repaired. The FKAA took the opportunity provided by the excavation to install a test station on the pipeline at that location. This action provided an 8th test station on the steel pipeline. The locations of CP facilities on the 18-in steel transmission main in Key West are shown in Figure B-1 in Appendix B. 4.2 2017 Inspection and Testing Inspection and testing of the rectifier stations indicated that all 5 of them were operating normally and were in good condition. The oil coolant was light amber in color, which is a normal discoloration compared to new oil. The rectifiers were tested to verify proper operation. Test results are shown in Table 4-1 (next page). All rectifiers except the one at the Post Office were found operating at the same tap settings and approximately the same current outputs as they were when commissioned after construction. Inspection showed that the tap setting of the Post Office rectifier was reduced from its original setting, and tests showed that the current output was 600 mA compared to 3800 mA as commissioned. The tap setting may have been changed when the station was damaged and repaired in 2016. Tests of PSP at nearby test stations indicated that CP levels were low. The taps were reset to the commissioned settings, which increased the current output as expected.

Request for Proposal EXHIBIT A SECTION 4 – KEY WEST

Table 4-1. Cathodic Protection Station Status- Key West 12- and 18- in Steel Transmission Main Pipe-to-Soil Potential (mV) Current Tap Output, Voltage ON OFF Oil Location Setting mA Output, V -mV CSE -mV CSE Status Post Office - Whitehead St. (As found) C1F2 600 5.7 -1020 -750 OK Post Office - Whitehead St. (As left) C4F2 2750 20.0 -1380 -810 OK

Peacon Ln & Eaton St. C1F5 2900 5.5 -1162 -930 OK

Eaton & White St. C1F3 2370 3.4 -1185 -1116 OK

Eisenhower & Palm Ave. C1F2 460 2.4 -1140 -1120 OK

Eisenhower & N. Roosevelt Blvd. C1F2 220 2.2 -1147 -1106 OK

The PSP of the steel pipeline was measured at all test stations and CP stations. The FKAA provided traffic control for access to the test stations on Eaton Street. Test results are presented in Appendix B, which includes test data in Table B-1 and a chart of the data in Figure B-2. Test results indicated that CP was adequate at all locations tested, except those on the pipeline within about 2,500 feet of KWPS and including the location of the recent corrosion leak. Experience suggested that there were 3 possible causes for this condition: A ‘short’ or unintended conductive connection; lack of electrical isolation; or failure of a joint bond and loss of continuity along the pipeline. Extensive diagnostic tests were conducted to try to identify the reason for the apparent inadequate CP of the 2,500 feet of steel pipeline near the KWPS. The electrical continuity of the pipeline was tested, and it was found continuous between the test stations at 400A Eaton Street and at Fleming Street. This indicated continuity of the pipeline through the area of the Post Office CPS. However, continuity of the pipeline did not extend to the valve on Whitehead Street or to test stations at the Courthouse or KWPS. The steel transmission main was electronically traced in both directions from the Post Office CPS. The pipeline was traced along Whitehead Street toward KWPS to a point just before the valve, suggesting that a pipe joint near the valve was not bonded or that a previous bond had failed. Electronic tracing of the pipeline from the Post Office CPS in the opposite direction (away from KWPS) along Whitehead Street showed that the signal departed from the steel pipeline at the intersection with Eaton Street. The electronic trace continued approximately 480 feet north along Whitehead Street and ended at a fire hydrant at 301 Whitehead Street. This result indicated that a ‘short’ to the steel transmission main exists at the intersection and extends along Whitehead Street. A record drawing provided by the FKAA for this location (see Appendix B) suggested that a 12-in ductile iron distribution watermain was apparently the metallic path followed by the electronic signal. Considering the age of the street, it seems possible that the traced pipeline ‘short’ on Whitehead Street could be cast iron with metallic joints and that it is directly connected to the 18-in steel main in the intersection. The record drawing also shows other buried metallic piping in the intersection, and one or more of these pipelines could be shorted to the steel transmission main at this location.

4-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 4 – KEY WEST 4.3 Conclusions Test results indicated that the steel transmission main in Key West had PSP of -850 mV CSE or more negative, indicating adequate CP, from Eisenhower and North Roosevelt to Eaton Street at Peacon Lane. The length of protected pipeline is approximately 5,600 feet. However, the steel transmission main had PSP less negative than -850 mV CSE, indicating inadequate CP, from around 620 Eaton Street to the KWPS. The length of unprotected pipeline is approximately 2,500 feet and includes the 12-in and 18-in pipelines. The area of inadequate CP is believed to result from a ‘short’ between the 18-in pipeline and one or more metallic distribution mains at the intersection of Eaton and Whitehead Streets. The shorted pipeline drains CP current from the steel pipeline, causing reduced protection of the steel near the short. The recent leak at 400A Eaton Street, which is near the location of the short, was probably a result of inadequate CP. Correction of the CP system deficiencies along Whitehead Street would require the following measures: • Excavation of the pipeline in the intersection of Eaton and Whitehead Streets to locate and clear shorts by installing insulated flexible couplings or flange insulating kits and test stations at the connections found. • Excavation of the valve and adjacent pipeline on Whitehead Street near the Courthouse to bond the joints and install a test station. • Excavation of the 12-in pipeline between the KWPS and the valve on Whitehead Street to locate and bond pipe joints that are not electrically continuous, and to select the point where electrical isolation will be established. In addition, the 3 existing test stations on Eaton Street should be relocated from their present locations in the street to convenient points behind the curb and out of the street. This action will eliminate the need for traffic control during testing and thereby improve safety and encourage monitoring. After this work has been completed, it will be necessary to measure the PSP at all test points and adjust the current outputs from the CP stations if necessary based on the test results. Alternatively, the FKAA could consider replacement of the transmission main with a suitable pipe material between KWPS and Eaton Street. The point of connection to the 18-in main should be located east of the recent corrosion leak to ensure that the corroded pipe is included in the replacement. The length of pipeline would be approximately 1,200 feet including the 12-in pipeline to KWPS. Consideration was reportedly given to replacing the 12-in pipeline during KWPS improvements in 2005, but it was not replaced. Pipeline replacement would require excavation across the Courthouse parking lot or selection of another route around it.

694334.03.30.01 CH2M HILL INC. 4-3 Request for Proposal EXHIBIT A

SECTION 5 Marathon

This section covers CP of buried steel transmission mains on Marathon (MM 47-53). There are 5 active sections of steel transmission main on Marathon. One section consists of approximately 1,150 feet of 24-in pipeline on Knight’s Key adjacent to the Seven Mile Bridge. Another section consists of 545 feet of 30-in pipeline that crosses US 1 at Aviation Boulevard. Another section consists of 551 feet of 30-in pipeline near Vaca Cut. The remaining 2 sections are short lengths of 24-in pipeline that connect Marathon Booster Pump Station to the 18-in steel transmission main and the 30-in ductile iron transmission main. The 18-in steel transmission main on Marathon has been deactivated, but its CP system provides protection for certain active sections of steel transmission main. The deactivated steel pipeline may also have residual value as a conduit for other potential uses, and continued operation of the CP system would help maintain integrity of the pipeline. 5.1 Background The 18-in steel transmission main on Marathon is approximately 30,000 feet in length. Before the pipeline was deactivated, it was connected to the Marathon Booster Pump Station, which is located at MM 48.7 or about 8,500 feet from the west end of Marathon. CP facilities for the 18-in pipeline were constructed in 2008 during Phase 2 CP Improvements. They consisted of 7 impressed current (rectifier) stations and numerous test stations. There were also magnesium anode anodes installed on the 30-in steel pipelines that connect Marathon Booster Pump Station to the 18-in and 30-in water transmission mains. The 30-in steel pipeline crossing US 1 at Aviation Boulevard (MM 51.0) was electrically connected to the 18-in pipeline with a bond wire for CP of the 30-in pipeline. The FKAA has periodically monitored the CP system since it was installed in 2008. Deactivation of the 18-in steel transmission main has been done in stages. Along with other events, deactivation has affected the CP system on Marathon as described below. 5.2 2017 Inspection and Testing 5.2.1 Knight’s Key to Marathon Booster Pump Station In 2017, the FKAA cut and capped the 18-in main at Knight’s Key (MM 47.0), but the portion of the pipeline that crosses US 1 was left active to provide water service to . The active portion of the 18-in main is connected to the 24-in main, which reduces from the 30-in main at Valve Vault S78, located east of 7-Mile Bridge. The FKAA’s work on the 18-in main at Knight’s Key occurred at about the same time as other construction activity cut off CP from 1,153 feet of 24-in steel pipeline on the east side of 7-Mile Bridge. Subsequent activities related to CP are discussed under Bridge Crossings. Test results are presented in Table C-1 in Appendix C. In summary, the impressed current station at Knight’s Key is now used to provide CP for the 24-in steel pipeline to the bridge and for the 18-in steel pipeline crossing US 1. That rectifier station no longer provides CP for any of the 18-in pipeline east of Knight’s Key because the pipeline has been cut and capped. The FKAA plans to cut and cap the 18-in pipeline on the west side of Marathon Booster Pump Station. This action will result in a section of deactivated pipeline about 8,500 feet in length from the pump station to Knight’s Key. This section of pipeline has 2 impressed current stations located at 7-Mile

Request for Proposal EXHIBIT A SECTION 5 – MARATHON

Marina (MM 47.0) and at the FKAA Customer Service Center (MM 48.7). These stations were inspected and tested to assess CP on the pipeline. Test results are summarized in Table 5.1. Inspection of the rectifier stations discovered that the rectifier at MM 48.7 was OFF due to a tripped secondary breaker. The breaker was reset and the station was returned to service. The rectifier stations were otherwise operating normally and were in good condition. The oil coolant was light amber in color, which is a normal discoloration compared to new oil. Table 5-1. Cathodic Protection Station Status- Marathon West 18-in Steel Transmission Main (Deactivated) Pipe-to-Soil Potential (mV) Current Tap Output, Voltage ON OFF Oil CPS Location Setting mA Output, V -mV CSE -mV CSE Status

C1F2 990 2.0 -568 -542 OK 7 Mile Marina MM 47.0 C1F3 4620 2.6 -680 -574 OK

FKAA Customer Service MM 48.7 C1F5 4000 2.8 -782 -674 OK Notes: Rectifier at MM 47.0 left operating at C1F3. Rectifier at MM 48.7 found with secondary AC breaker tripped; reset breaker and left operating at C1F5.

The results of tests made at rectifier stations and test stations are presented in Table C-2 in Appendix C. Results indicate that PSP is less negative than -850 mV CSE, indicating that CP is not adequate for the entire pipeline. It seems that the pipeline has a high cathodic current requirement that exceeds the maximum current output capacity of the rectifiers. The high current requirement is likely due to deteriorated protective coating on the pipeline or an unknown connection (short) to another buried metal pipeline or structure somewhere along the pipeline. It is possible that protection levels will improve after the FKAA cuts and caps the 18-in pipeline on the west side of Marathon Booster Pump Station. This work is expected to result in complete electrical isolation of the pipeline. If the deactivated 18-in pipeline will be preserved, tests should be conducted after completion of the pipeline work to determine if protection levels improve. 5.2.2 Marathon Booster Pump Station Other recent construction activity along US 1 has destroyed the anodes on the 30-in steel pipelines that connect Marathon Booster Pump Station to the 18-in and 30-in water transmission mains. No tests were conducted due to construction activity around existing test stations. It will be necessary to replace the anodes and conduct tests to verify that CP has been restored on the steel pipelines. 5.2.3 Marathon Booster Pump Station to Vaca Cut The easterly portion of the 18-in steel transmission main on Marathon was deactivated a few years ago, and the impressed current station at MM 53.0 was deactivated along with it. The FKAA removed the rectifier from the station and disconnected the AC power service. In 2017, the FKAA cut and capped the 18-in steel transmission main on the east side of Marathon Booster Pump Station. This action resulted in a section of deactivated pipeline about 21,800 feet in length from the pump station to Vaca Cut. This section of pipeline has 3 impressed current stations located at: 46th Street (MM 49.5); 70th Street (MM 50.9); and 100th Street (MM 52.2). These stations were inspected and tested to assess CP on the

5-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 5 – MARATHON

pipeline. Test results are summarized in Table 5-2. It was noted that the rectifier station at MM 50.9 was not shown on Pictometry. Table 5-2. Cathodic Protection Station Status- Marathon East 18-in Steel Transmission Main (Deactivated) Pipe-to-Soil Potential (mV) Current Tap Output, Voltage ON OFF Oil CPS Location Setting mA Output, V -mV CSE -mV CSE Status

th 46 Street MM 49.5 C1F3 2320 3.2 -1123 -1113 OK

th 70 Street MM 50.9 C1F3 2350 3.2 -1203 -1080 OK

th 100 Street MM 52.2 C1F3 2120 3.2 -1112 -1068 OK

Inspection and testing of the rectifier stations indicated that they were operating normally and were in good condition. The oil coolant was light amber in color, which is a normal discoloration compared to new oil. Tests made at the rectifier stations and at test stations are presented in Table C-2 in Appendix C. Results showed that the PSP was more negative than -850 mV CSE, indicating adequate CP, for the entire section of pipeline from Marathon Booster Pump Station to Vaca Cut. This includes the 30-in steel pipeline crossing US 1 at Aviation Boulevard, which has a CP bond wire connection to the 18-in pipeline. The flush-mounted test station that houses the bond wire connection was located and recovered after considerable effort by the FKAA. The search for the bond station ultimately found it buried about 1 foot deep, and it was raised to ground level and marked to aid recovery for future monitoring. There is another section of 30-in steel transmission main located near Vaca Cut. The pipeline is 551 feet in length and is connected to a section of 310 feet of buried steel pipeline west of the bridge. Both sections of steel pipeline were tested for CP as discussed in Bridge Crossings. In summary, the entire section (861 feet) of 30-in steel transmission main has galvanic anodes installed during Phases 1 and 2 CP Improvements, and tests show that PSP is more negative than -850 mV CSE, indicating adequate CP. 5.3 Conclusions Test results indicated that all tested steel sections of 24- and 30 transmission main on Marathon have PSP of -850 mV CSE or more negative, indicating adequate CP. This includes the only active section of 18-in steel main that crosses US 1 at Knight’s Key. However, the 24-in steel pipeline sections at Marathon Booster Pump Station could not be tested for CP due to other construction activity and are probably not protected due to destruction of the installed anodes by that same activity. It will be necessary to replace the anodes and conduct tests to verify that CP has been restored on the steel pipelines. The 18-in deactivated steel transmission main has adequate CP from Marathon Booster Pump Station to Vaca Cut. The CP system for this section provides CP for the 30-in steel pipeline crossing US 1 at Aviation Boulevard, which has a bond to the 18-in pipeline. It will be necessary to continue operation of the CP system on the 18-in deactivated steel transmission main to maintain protection for the 30-in steel pipeline. If the CP system for the 18-in pipeline were to be deactivated, it would be necessary to construct a new CP station to provide for the 30-in steel pipeline. Operation of the existing CP system in its present configuration can protect the 30-in steel pipeline without additional construction while maintaining the integrity of the 18-in deactivated steel pipeline at minimal cost until the CP stations reach the end of their useful life (15 to 20 years).

694334.03.30.01 CH2M HILL INC. 5-3 Request for Proposal EXHIBIT A SECTION 5 – MARATHON

The 18-in deactivated steel transmission main does not have adequate CP between Marathon Booster Pump Station at the end of the pipeline at Knight’s Key. The cathodic current requirement of the pipeline exceeds the capacity of the 2 existing impressed current stations. The high current requirement is likely due to deteriorated protective coating on the pipeline or a short to another buried metal pipeline or structure. Protection may improve after the FKAA cuts and caps the 18-in pipeline on the west side of Marathon Booster Pump Station, because the work will result in complete electrical isolation of the pipeline. If the FKAA (or another party) desires to maintain the integrity of this portion of the deactivated 18-in main, then tests should be conducted after completion of the pipeline work to determine if protection levels improve. Additional impressed current stations would be required to protect the pipeline if isolation does not improve the situation and complete protection of this section of steel pipeline is desired.

5-4 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A

SECTION 6 The 18- Mile Stretch MM 121 – 122

This section covers the section of 36-in buried steel transmission main at MM 121-122 in the 18-Mile Stretch. The transmission main is in the Everglades on the Bay side of US 1. The length of the steel pipeline is 3,900 feet. 6.1 Background Construction records indicate that the steel pipeline section at MM 121-122 was protected by magnesium anodes when it was installed around 1982. The pipeline was connected to ductile iron pipe with transition couplings. Test stations were installed at the transition couplings and at intervals of approximately 360 feet along the steel pipeline. The test stations at the transitions had wires connected to both the ductile iron and steel pipes to permit testing of the dielectric isolation provided by the couplings. At each test station, a 50-pound magnesium anode was installed and connected to the steel pipeline through wires and a shunt on the test station terminal board. A total of 12 test stations were originally installed and had reference numbers 7A1 through 7A12, with the first number and letter indicating the pipeline construction contract. Records indicate that the total current output of the anodes was approximately 400 mA when they were new in 1982, and that the PSP was around -1300 mV CSE at all stations. The test stations were periodically monitored for pipe-to-soil potential and anode current output. Around 2005, other construction work began to affect the test stations. A chain link fence was erected along the Everglades. During Phase 2 CP Improvements in 2008, the test stations were moved outside the fence and converted from post-mount to flush-mount, and a new anode was installed at each station. Then a highway paving and improvement project was constructed that destroyed most of the test stations. In 2012, the FKAA found severed wires at 5 of the 12 test station locations. The recovered wires were from test stations on the northerly end of the steel section. The FKAA extended the test wires to post- mounted stations between the Everglades fence and the highway. The FKAA and CH2M HILL tested the stations to identify wires, and identified the approximate location of the southernmost test station at the ductile iron transition. The FKAA subsequently found severed wires at the southernmost test station and at the adjacent test station. The test wires were extended to post-mounted stations between the Everglades fence and the highway. This work was completed around 2015. Subsequent tests by the FKAA at the 7 recovered test stations suggested that the steel pipeline had adequate CP except at the northerly end of the line. 6.2 2017 Inspection and Testing The 7 test stations on this section of steel pipeline were inspected and tested in 2017. Inspection showed that the wiring arrangements differ among stations. Some stations appear to have more wires than the original stations, and the wire insulation colors vary. All these variations have the potential to create confusion, especially since only a few wires are labeled. Tests showed that most of the wires are functional. However, the test wires to the pipe in the station at MM 121.49 are suspect, and there is only 1 functional wire (there should be 2 wires) to the ductile iron pipe at the northerly and southerly transitions. There are also newer and older anodes connected in some stations, and the older ones are mostly depleted.

Request for Proposal EXHIBIT A SECTION 6 – THE 18- MILE STRETCH MM 121 – 122

Test results are summarized in Table 6-1 (next page) and in Table D-1 of Appendix D. Results showed that the PSP of the steel pipeline ranged from -846 to -1066 mV CSE with the anodes connected (‘ON’) at individual test stations and from -795 to -950 mV CSE disconnected (‘OFF’). The pipe test wires in the station at MM 121.49 are suspect, because they had a highly negative potential without the anode connected and the anode had no measurable current output. The current outputs of the other anodes ranged from 24 to 39 mA and totaled 169 mA. Table 6-1. Cathodic Protection Test Results MM 121-122 36-in Steel Transmission Main

Pipe-to-Soil Potential (mV) Anode Probable Distance from Old TS South End, Pipe ON OFF Current Test Point No. feet Material -mV CSE -mV CSE mA

Steel -910 -795 30 MM 121.06 7A12 0 Ductile Iron -562 -503 -

MM 121.15 7A11 510 Steel -1066 -866 28

MM 121.49 7A6 2280 Steel -982 -950 0

MM 121.55 7A5 2600 Steel -1006 -866 39

MM 121.62 7A4 2960 Steel -1000 -850 24

MM 121.70 7A3 3370 Steel -1056 -850 24

Steel -846 -825 24 MM 121.79 7A1 3870 Ductile Iron -842 -821 -

The PSP of the ductile iron at the southerly transition indicates that it is electrically isolated from the steel pipeline. However, the ductile iron appears to be shorted to the steel at the northerly transition. These conclusions regarding electrical isolation assume that the single test wire to the ductile iron is functional at both test stations. 6.3 Conclusions Test results indicated that the steel pipeline at MM 121-122 has PSP of -850 mV CSE or more negative at all locations except at the transitions, and particularly at the northerly transition where electrical isolation from ductile iron pipe is incomplete. Taken at face value, these PSP values would suggest adequate CP. However, there is reason for concern about the level of protection which is significantly lower than it was when the pipeline was new. The total anode current is about 42 percent of original; and the PSP is about 300 mV more positive. In addition, there is a significant gap in the spacing of anodes between the test stations at MM 121.15 and 121.49. There is the potential for microbial-induced corrosion or MIC in the Everglades environment in which the pipeline is installed. Environments characterized by decomposition of organic matter present elevated risks of MIC and warrant higher levels of CP. This can be accomplished by increasing the cathodic current by increasing the number of anodes. A current requirement test was conducted on the pipeline, and results indicated that an additional 400 mA of current would boost CP to approximately its original level. This amount of current could be provided by 2 additional magnesium anodes at each existing test station, for a total of 14 anodes. The anodes could be connected in the test stations to avoid excavation of the pipeline in the high groundwater conditions that exist at the site. These improvements are recommended for the section of steel transmission main at MM 121-122.

6-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A

SECTION 7 Recommended Improvements

This section presents recommended CP improvements for the FKAA pipelines included in the project. A detailed list of recommended CP improvements is presented in Appendix E. The recommended improvements do not include any work that may be necessary to repair damage caused by Hurricane Irma and any other hurricanes that may occur after August 2017. 7.1 Bridge Crossings For most bridge crossing pipelines, CP can be restored by installing new galvanic anodes as indicated in Table E-1 in Appendix E. The pipelines will require anywhere from 1 to 25 anodes as determined by the current requirement of the pipeline. The anodes can be installed in groups of up to 10 anodes joined through a header wire connected to the pipeline at one location. A total of approximately 350 anodes will be required for all bridge crossings that have inadequate CP. Test stations are recommended for many bridge crossing pipelines that do not have them. Test stations are particularly important at buried transitions to ductile iron pipe. These test stations are used for assessment of the level of CP and the quality of electrical isolation from ductile iron pipe at that location. Test stations are not necessarily required for short pipelines if they have a test station at the transition. In the absence of any test stations, however, it will be necessary to contact the exposed pipe with a sharp metal point whenever a CP test is made. A total of 92 new test stations are recommended for the bridge crossing pipelines. There are 2 bridge crossing pipelines with high current requirements that make galvanic anodes impractical, and an impressed current (rectifier) station will be required at each location. These locations are the west side of Tea Table Relief and the east side of Whale Harbor Channel. However, the length of steel pipeline at each location requires confirmation by the FKAA before a final determination can be made. There are also 11 other locations where the length of steel pipeline requires confirmation, because field tests indicated the possibility that long lengths of steel pipeline could be present. These locations are described in Appendix A. Restoration of electrical isolation will be required at approximately 4 locations. Each location will involve repair of a flange insulating kit or installation of an insulating flexible coupling. Testing and repair of electrical continuity will be required at an estimated 6 locations, and these are associated with the steel pipelines with suspected longer lengths described above. 7.2 Other Facilities Recommended CP improvements for other steel transmission mains on Key West, Marathon, and at MM 121-122 in the 18-Mile Stretch were described with the test results in the respective sections of this report. Less construction work will be required for CP improvements at these locations, compared to the combined work required at bridge crossings. Recommended CP improvements for other facilities are presented in Table E-2 in Appendix E. 7.3 Operation and Maintenance Improvements This section presents suggestions for improved efficiency and effectiveness of CP systems for consideration by the FKAA. These suggestions are based on observations made over the course of the CP assessment in 2017 and our understanding of FKAA operations. Request for Proposal EXHIBIT A SECTION 7 – RECOMMENDED IMPROVEMENTS 7.3.1 Organizational Approach to Maintenance of CP Facilities The FKAA’s CP systems are relatively complex because of the mixture and configuration of steel and ductile iron pipe materials in the water transmission system. This complexity adds time and effort required to maintain the systems. At present, monitoring and maintenance of the FKAA’s CP systems are the responsibilities of the FKAA’s electricians. However, the electricians have other responsibilities, and their time is often spent on other more urgent needs that take priority over CP tasks. While CP is important, its priority will tend to slip with this arrangement and especially if electrician staffing shortages occur. The FKAA electricians also have expertise in other areas that are critical to FKAA operations but are not necessarily required for CP. From this perspective, CP maintenance is an inefficient use of the limited and valuable resources of the FKAA electricians. At the same time, the electricians have relatively limited CP training and rely on contract services for advice in situations where they need assistance to manage the complex CP systems for the water transmission mains. The FKAA electricians could benefit from additional CP training if they continue to maintain the CP systems. A better arrangement might be for the FKAA to assign in-house resources specifically to CP maintenance, with 2 levels of expertise: a basic level for routine work; and a higher level for planning and troubleshooting that will inevitably be needed. One challenge of having an in-house center of expertise is the linear arrangement of the transmission system and the inefficiencies of travel to CP facilities over 125 miles of service area. Experience suggests that CP work is favored by certain interests and aptitudes that may not necessarily match capabilities of available resources. Alternatively, the FKAA could consider contracting for CP services using a staff augmentation approach over a prolonged period. This approach has its advantages and disadvantages, but it has been used by other utilities in an effort to improve leverage of internal resources. 7.3.2 Remote Monitoring of Rectifiers At present, the FKAA manually monitors impressed current CP stations by electricians periodically visiting the sites and observing the rectifier panel meters to determine if the equipment is on and operating properly. Maintaining a regular monitoring schedule is challenging due to the limited electrician resources described above. Moreover, this approach does not promptly disclose problems that automatically turn off rectifiers, such as tripped breakers that may occur during electrical power surges or thunderstorms. The FKAA could consider ‘remote monitoring’ to improve the efficiency and effectiveness of maintaining the rectifier stations. Remote monitoring refers to periodic automated collection of CP rectifier operating data. This is similar to automated reading of water meters and wastewater pumping stations that is already in use by the FKAA. There is an industry trend toward remote monitoring of CP rectifiers to reduce labor costs and provide more timely information than manual methods. Reliability of equipment has been a challenge during development of remote monitoring technology, but reliability has improved, and the benefits of remote monitoring far outweigh the costs. There are several manufacturers of remote monitoring equipment for CP applications. Two of them are Borin and Abriox. All manufacturers offer a free trial use of their equipment in hopes of securing a contract for equipment and monitoring service. The remote monitoring units can be purchased and added to existing rectifiers at a cost of around $3,000 per station. The remote unit collects the information per program instructions and transmits it by digital cellular telephone or satellite. There is also a system that utilizes 900 megahertz radio frequency.

7-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A SECTION 7 – RECOMMENDED IMPROVEMENTS

The data are downloaded by the remote monitoring manufacturer or service provider and placed on a private website accessed by the customer. In addition to regular monitoring, automated alert messages are sent by e-mail or telephone if the reported parameters are outside the limits set for the station. A monthly subscription costs around $10 per unit. The FKAA could try the remote monitoring approach offered by one or more companies on a trial basis. The rectifiers in Key West or Marathon would be good candidates for a trial evaluation.

694334.03.30.01 CH2M HILL INC. 7-3 Request for Proposal EXHIBIT A

SECTION 8 Construction Cost Opinion

This section presents a construction cost opinion for the recommended CP improvements, assuming that the work would be completed under a publicly bid construction contract. The construction cost opinion should be considered preliminary, because it is based on elements of work that are anticipated for construction but have not yet been designed. The cost opinion aligns with a Class 4 Estimate as described by AACE International Recommended Practice 18R-97. Engineer’s cost opinions are based on experience and judgement. Since CH2M has no control over market conditions or bidding procedures, CH2M cannot warrant that bids or ultimate construction costs will not vary from these opinions. Appropriate contingencies should be provided by FKAA. A summary of estimated construction costs is presented in Table 8-1. The total estimated construction cost of the project is $1.4 million, assuming a 20 percent cost premium for the Keys, 5 percent inflation allowance for 2018, and 20 percent project contingency. The cost estimate does not include the cost of additional work that may be needed to mitigate hurricane damage occurring after August 2017, nor does it provide for possible increased construction costs that may result from hurricane damage to property and infrastructure in the Keys. Table 8-1 Class 4 Construction Cost Estimate FKAA CP Improvements FKAA Facility or Location Estimated Construction Cost 2018 Bridge Crossings $1,014,000 Key West 79,000 Marathon 16,000 MM 121-122 47,000 Road Crossings 193,000 Total $1,358,000

The FKAA should also allow for administrative costs associated with construction, including contract management, submittal review, inspection, and documentation such as record drawings. 8.1 Basis for Estimated Costs The cost of construction will be determined by the quantities and types of CP facilities such as test stations and anodes at each pipeline. An itemized list of CP improvements with the estimated cost of construction is presented in Appendix F, Table F-1, and followed by unit cost developments. Elements of work will be essentially the same as those used for Phase 1 and Phase 2 CP Improvements. Estimated costs of the work elements have been updated to reflect current costs. For perspective, the low bid for Phase 1 construction in 2001 was 12 percent less than the Engineer’s cost opinion, and the low bid for Phase 2 construction in 2005 was 18 percent less. Changes during construction of both projects pushed actual costs closer to the Engineer’s cost opinions. The construction costs for CP work at bridge crossings will be affected by the actual lengths of the steel pipelines. The cost estimate is based on pipeline lengths established during Phase 1 or Phase 2 CP Improvements, or on estimated lengths that were strongly indicated by test results in 2017. Costs are not included for lengths of pipeline that may be constructed from steel pipe but could not be tested due

Request for Proposal EXHIBIT A SECTION 8 – CONSTRUCTION COST OPINION

to the absence of test stations. However, costs are included for CP of road crossings, because it is likely that they are all constructed from steel pipe and that CP facilities at all crossings will be like those at other crossings where CP has been installed during Phase 1 or Phase 2 CP Improvements. Design details that have not yet been determined, but will ultimately affect costs, include the exact locations of construction and working conditions at those sites. For example, installation of anodes near bridge abutments will require excavation on sloping ground behind guardrails, and the associated challenges will increase costs compared to work on flat sites with easy access. Bid documents will also include other unit price items that cannot be quantified until construction is underway. Unit price items for this project will likely include exploratory excavations, repair of insulating fittings, installation of continuity bonds on pipe joints, and asphalt pavement repair. 8.2 Cost Savings Some savings in construction cost have already been achieved by actions of the FKAA during the field investigation of the CP systems. The most significant savings resulted from the use of the existing impressed current station at Knight’s Key in Marathon to protect the buried 24-in steel transmission main at Seven Mile Bridge. The FKAA deactivated a section of the 18-in steel transmission main that the station previously protected. The use of the existing station avoided the need to construct new CP facilities for the pipeline and produced estimated construction cost savings of at least $28,000. Cost savings also resulted from the FKAA’s recovery of the bond station on the 30-in steel transmission main at Aviation Boulevard in Marathon. The cost of constructing a new station was avoided, with an estimated savings of approximately $4,000. The FKAA also recovered several other previously buried test stations worth approximately $3,000 per station in replacement cost. The total cost savings achieved by the FKAA through these actions was approximately $40,000. For additional cost savings, the FKAA could consider using its own forces to construct some or all of the recommended CP improvements. Many of the CP improvements are relatively simple, and the FKAA has adequate in-house knowledge and experience necessary to construct them. A CP specialist could be contracted for supplemental technical assistance as needed. The practicality of this approach depends on the priorities and availability of resources within the FKAA. 8.3 Recommendations The current planned CIP funding does not provide adequate budget for the recommended CP system improvements described above. Unlike a typical prioritization of projects, all of the recommended CP systems improvements have more or less the same level of importance – to provide protection of the steel transmission main sections against corrosion and extend their service life. In essence, the CP system serves as insurance to reduce the premature need for costly main emergency repair or replacement. CP is relatively inexpensive in comparison, easy to maintain and proven in its effectiveness. It is strongly recommended that the FKAA formulate a combination of CIP funding and a commitment of internal resources to complete the improvements needed to bring the CP into conformance with the design intent.

8-2 CH2M HILL INC. 694334.03.30.01 Request for Proposal EXHIBIT A

Appendix A Bridge Crossings

Request for Proposal EXHIBIT A TABLE A-1 BRIDGE CROSSINGS SUMMARY FKAA STEEL TRANSMISSION MAINS

2017 Test Results Mile Marker US 1 Length Bridge TS Bridge TS Transition TS Transition TS Current Steel PSP DI PSP Electrical MM Location Key Side Feet Type Condition Type Condition Req. mA mV CSE mV CSE Isolation Notes 4.2 Cow Key Channel - West Key West Median <20 None - None - 40 -540 - Inferred No history 4.3 Cow Key Channel - East Stock Island Median 160 None - None - 161 -510 - Inferred 6.0 Boca Chica Channel - West Stock Island Bay 230 Iron Flush OK CNL - 30 -530 -363 Yes 30 mA for 5' at bridge 6.5 Boca Chica Channel - East Big Coppitt Bay 291 None - CNL - 20 -674 - Yes? Also cased crossing US 1 9.8 Rockland Channel - West Big Coppitt Ocean 328 Iron Flush OK Iron Flush OK - -960 -808 Weak Br TS at rail; Tr TS at V-V 10.0 Rockland Channel - East Rockland Ocean 479 None - None - 47 -383 - Inferred VV S268 at 479' 11.3 Shark Channel - West Shark Ocean 391 None - CNL Under H. Trail - -1099 - Inferred Transition TS 53' E of VV 11.8 Shark Channel - East Saddlebunch No. 5 Ocean 642 Alum. Post OK CNL - 2800 -511 - No Shorted to 18" @ VV S260 12.6 Saddle Bunch No. 5 Ch.- West Saddlebunch No. 5 Ocean 929 None - None - 173 -686 - Yes? e-locate STL to VV S258 12.8 Saddle Bunch No. 5 Ch.- East Saddlebunch No. 4 Ocean 296 None - None - - -1503 - Inferred e-locate to Ph 1 anodes 13.1 Saddle Bunch No. 4 Ch.- West Saddlebunch No. 4 Ocean 238 None - CNL - - -1417 - Inferred e-locate to Ph 1 anodes 13.3 Saddle Bunch No. 4 Ch.- East Saddlebunch No. 3 Ocean 296 None - CNL - - -958 - Inferred e-locate to transition 14.2 Saddle Bunch No. 3 Ch.- West Saddlebunch No. 3 Ocean 237 None - CNL - - -979 - Inferred e-locate to Ph 1 anodes 14.4 Saddle Bunch No. 3 Ch.- East Saddlebunch No. 2 Ocean 327 None - CNL - - -1603 - Inferred e-locate to Ph 1 anodes 14.6 Saddle Bunch No. 2 Ch.- West Saddlebunch No. 2 Ocean 243 None - Iron Flush OK - -1402 -358 Yes PSP -1532 direct to pipe 14.8 Saddle Bunch No. 2 Ch.- East Bay Point Ocean 235 None - Iron Flush Was buried - -1062 -60 Yes PSP -1524 direct to pipe 15.2 Lower Sugarloaf Ch. - West Bay Point Ocean 143 None - None - 60 -292 - Inferred e-locate STL to 143' (?) 15.5 Lower Sugarloaf Ch. - East Unnamed Ocean 279 Flush Iron OK Flush Iron OK 155 -435 -455 Yes Also 12" stl ea side of VV 16.4 Harris Channel - West Unnamed Bay 571 Flush Fink Cut wires None - 110 -292 - Inferred e-locate STL to 571' 16.5 Harris Channel - East Lower Sugarloaf Bay 13 - - Flush Iron OK 140 -587 -545 Inferred e-locate STL to 13' 17.5 Harris Gap Channel - West Lower Sugarloaf Bay 24 None - Flush Iron Was paved 70 -723 -447 Yes 17.5 Harris Gap Channel - East Unnamed Bay 25 None - Flush Iron OK 112 -475 -361 Yes 17.7 North Harris Channel - West Unnamed Bay 25 Flush Fink Cut wires Flush Iron OK 138 -477 -463 Yes e-locate STL to 25' 17.8 North Harris Channel - East Park Bay 25 Flush Fink Cut wires Flush Iron Was paved 51 -627 -502 Yes e-locate STL to 25' 18.7 Park Channel - West Park Bay 448 Flush Fink Broken None - 45 -490 - Inferred e-locate STL to 448'; more? 18.8 Park Channel - East Upper Sugarloaf Bay 18 Flush Fink Broken None - - -967 - Inferred e-locate STL to 18' 20.2 Bow Channel - West Land Side of FC Upper Sugarloaf Ocean 31 None - Iron Flush OK 80 -746 -557 Inferred 20.5 Bow Channel - East Cudjoe Ocean 14 None - None - 45 -458 - Inferred e-locate STL to 14' 23.6 Kemp Channel - West Cudjoe Ocean 11 None - None - 55 -322 - Inferred e-locate STL to 11' 23.8 Kemp Channel - East Summerland Ocean 6 None - Alum. Post OK 100 -340 -359 Yes 25.4 Niles Channel - West Summerland Ocean 138 Alum. post OK Flush Iron OK 198 -638 -257 Yes Bridge PSP -705 26.3 Niles Channel - East Ramrod Ocean 130 Alum. post OK CNL (trees) - - -1100 - Inferred Bridge TS PSP is shown 27.6 Torch Ramrod Channel - West Ramrod Bay 16 Flush Fink Oxidized None - 47 -361 - Inferred e-locate STL to 16' 27.7 Torch Ramrod Channel - East Middle Torch Bay 24 Flush Fink Oxidized None - 52 -384 - Inferred e-locate STL to 24-35' 28.0 Torch Channel - West Middle Torch Bay 14 Flush Fink Cut wires - - 8 -349 - Inferred e-locate STL to 14' 28.1 Torch Channel - East Little Torch Bay 20 Flush Fink Broken None - 55 -380 - Inferred e-locate STL to 20' 28.6 South Pine Ch.- West, Land side of FC Little Torch Bay 25 CNL Cut wires None - 69 -291 - Inferred e-locate STL to 25' 28.8 South Pine Ch.- East, Land side of FC Unnamed Fill Bay 24 CNL - - - 35 -424 - Inferred

Page 1 of 3 Request for Proposal EXHIBIT A TABLE A-1 BRIDGE CROSSINGS SUMMARY FKAA STEEL TRANSMISSION MAINS

2017 Test Results Mile Marker US 1 Length Bridge TS Bridge TS Transition TS Transition TS Current Steel PSP DI PSP Electrical MM Location Key Side Feet Type Condition Type Condition Req. mA mV CSE mV CSE Isolation Notes 29.3 North Pine Ch.- West, Land side of FC Unnamed Fill Bay 25 Flush Iron OK 21 -703 -284 Yes 29.5 North Pine Ch.- East, Land side of FC Big Pine Bay 24 - - Flush Iron Colors reverse - -903 -911 Weak Green = STL ; Blue = DI 33.0 Spanish Harbor Channel- West Big Pine Ocean 6 - - Alum. Post OK 250 -648 -592 Weak 33.6 Spanish Harbor Channel- East West Summerland Ocean 6 - - Alum. Post OK 130 -708 -708 No 35.3 Bahia Honda Channel - West West Summerland Median 970 Big Fink 1 bad wire Flush Iron OK 2000 -196 Inferred e-locate STL to VV @970' 36.6 Bahia Honda Channel - East Bahia Honda Median 1850 Flush Fink Oxidized Flush Iron OK 1000 -395 -653 Yes DI PSP @ VVS116/SA114 38.5 Ohio Bahia Honda Channel - West Bahia Honda Bay 5 CNL Under fence - - 29 -237 - Inferred 38.7 Ohio Bahia Honda Channel - East Ohio Bay 130 None - None - 100 -303 - Inferred 39.0 Ohio Missouri Channel - West Ohio Bay 21 None - Alum. Post OK - -1286 -190 Yes + 1570' STL west; 430 mA 39.3 Ohio Missouri Channel - East Missouri Bay 125 None - Alum. Post OK 125 -230 -216 Weak Confirm I Req. 39.6 Missouri Little Duck Channel - West Missouri Bay 20 Flush Fink Broken None - 85 -214 - Inferred + 1340' STL west; 556 mA 39.7 Missouri Little Duck Channel - East Little Duck Bay 217 Flush Fink Broken None - 40 -301 - Inferred e-locate STL to 217' 40.0 Seven Mile Bridge - West Little Duck Bay 87 None - Alum. Post OK - -966 -945 Weak 46.7 Seven Mile Bridge - East Marathon Ocean 1153 Alum. Post OK Flush Iron OK 2520 -476 -590 Yes Now prot by IC; P/S -1218 53.2 Vaca Cut Channel - West Marathon Bay 861 None - Flush Iron OK - -1168 -679 Yes 53.3 Vaca Cut Channel - East Grassy Bay 996 None - CNL - 110 -796 - Inferred 60.5 Tom's Harbor Channel - West Grassy Ocean 411 Alum. Post OK Flush Iron Was buried - -868 -384 Yes 60.8 Tom's Harbor Channel - East Duck Ocean 368 None - CNL - - -890 - Inferred 61.5 Tom's Harbor Cut - West Duck Ocean 457 None - CNL - 500 -411 - Inferred 61.7 Tom's Harbor Cut - East Conch Ocean 507 None - Flush Iron Was buried 2700+ -470 -470 No Shorted to 18" in VV S4 63.1 Channel - West Conch Ocean 1285 Alum. Post OK CNL - 1000 -394 - Inferred 2 trans TS missing @ VV 65.3 Long Key Channel - East Long Ocean 753 Alum. Post OK CNL - - -1040 - Inferred Protected by IC 70.8 Channel No. 5 - West Long Ocean 154 ? ? Alum. Post OK 17 -822 -475 Yes 71.7 Channel No. 5 - East Craig Ocean 170 ? ? Alum. Post OK 55 -186 -233 Yes 72.6 Channel No. 2 - West Craig Both 231 Flush Iron New Alum. Post Replaced Box 200 -527 -519 Weak Recent leak repair at bridge 73.1 Channel No. 2 - East Lower Matecumbe Bay 189 Flush Fink Cut wires None - 100 -372 - Inferred e-locate STL to 189' 77.6 Lignumvitae Channel - West Lower Matecumbe Bay 27 None - Alum. Post OK 30 -823 -708 Weak Also 64' STL near VV N158 77.8 Lignumvitae Channel - East Indian Bay 17 None - Alum. Post OK 300 -48 -36 Weak +700' STL east? 78.0 Indian Key Channel - West Indian Bay 661 Alum. Post OK None - 423 -120 - Inferred e-locate STL to 661' 78.4 Indian Key Channel - East Indian Key Fill Bay 22 CNL Cut wires None - - -853 - Inferred +4300' STL east? 79.2 Tea Table Channel - West Indian Key Fill Bay 48 None Cut wires None - 100 -590 - Inferred e-locate 48' STL 79.3 Tea Table Channel - East Teatable Both 600 None Cut wires None - 227 -305 - Inferred e-locate 600' STL; US1 Xing 79.7 Tea Table Relief - West Teatable Ocean 260 Big Fink Broken None - 825+ -364 - ? e-locate 260' STL; +1190'? 79.8 Tea Table Relief - East Upper Matecumbe Ocean 410 None - CNL - ? -806 - ? Partial protection by IC 83.9 Whale Harbor Channel - West Upper Matecumbe Bay 874 Big Fink Broken wire Flush Iron OK - -859 -867 Weak 874 ' to VV 84.0 Whale Harbor Channel - East Windley Bay 845 Big Fink OK None - 860+ -583 - No More STL east of VV? 85.6 Snake Creek - West Windley NA 1600 ------1243 - - Info only; subaq. & prot by IC 85.8 Snake Creek - East Plantation NA ------1034 - - Info only; subaq. & prot by IC

Page 2 of 3 Request for Proposal EXHIBIT A TABLE A-1 BRIDGE CROSSINGS SUMMARY FKAA STEEL TRANSMISSION MAINS

2017 Test Results Mile Marker US 1 Length Bridge TS Bridge TS Transition TS Transition TS Current Steel PSP DI PSP Electrical MM Location Key Side Feet Type Condition Type Condition Req. mA mV CSE mV CSE Isolation Notes 90.8 Tavernier Creek - West Plantation Median 326 Alum. Post OK None - 50 -760 -501 Yes Big Fink TS @ 211' 91.0 Tavernier Creek - East Tavernier Median 773 Alum. Post OK Flush Iron OK - -1322 -526 Yes 103.5 Adams Waterway - West Key Largo Median 737 Flush Iron OK Flush Iron OK - -884 -690 Weak Protected by IC 103.5 Adams Waterway - East Key Largo Median 308 None Wires only Flush Iron OK - -954 -694 Weak Protected by IC TOTALS

SUMMARY BRIDGE CROSSINGS 24275 4.6 Unprotected 43 55.1% feet miles Marginal 12 15.4% Protected 23 29.5% Excludes Snake Creek Total 78 100.0% Excludes Snake Creek

Page 3 of 3 Request for Proposal EXHIBIT A

TABLE A-2 ROAD CROSSINGS SUMMARY FKAA 24- to 36- in STEEL TRANSMISSION MAINS

2017 Test Results Mile Marker US 1 Length Transition TS Transition TS Current Steel PSP DI PSP Electrical MM Location Key Roadway Side Feet Type Condition Req. mA mV CSE mV CSE Isolation Notes Bay 140 CNL - - - - - See Bridge Crossings 6.5 East of Boca Chica Channel Boca Chica US 1 Ocean - None - - - - - Insul. Flg. in concrete Ph. 1 15.7 East of Lower Sugarloaf Channel Unnamed US 1 Both ------No information 19.8 West of Bow Channel Upper Sugarloaf US 1 Both ------No information Ocean 100 Flush Iron OK 200 -730 -713 Weak Ph. 2 Anodes & Imp. Current 27.3 West of Niles Channel Ramrod US 1 Bay - Flush Iron OK - -907 -886 Weak Ph. 2 Anodes & Imp. Current Bay 80 Flush Iron OK 32 -715 -314 Yes Ph. 2 Anodes 27.8 Middle Torch Road Middle Torch Middle Torch Bay - Flush Iron OK - -737 -497 Yes Ph. 2 Anodes Bay 110 Flush Iron OK - -1047 -889 Weak Ph. 2 Anodes & Imp. Current 29.6 North Pine Channel East Big Pine US 1 Ocean - Flush Iron OK - -1272 -1272 Shorted Ph. 2 Anodes & Imp. Current 36.9 East of Bahia Honda Channel Bahia Honda US 1 WB Both ------No information Ocean 700 Flush Iron OK - -999 -612 Yes Ph. 2 Imp. Current 50.9 Aviation Boulevard Marathon US 1 Bay - Flush Iron Was buried - -960 -662 Yes Bond 400 mA to 18" Steel Bay 604 Flush Iron Corroded wire - -655 -571 Yes West end of crossing 59.5 Grassy US 1 Bay - Flush Iron Damaged - -693 -645 Weak Casing PSP shown under DI Ocean - Flush Iron Damaged 3000 -642 -498 Yes East end of crossing Ocean ------Ph. 2 Imp. Current 73.5 Anne's Beach Lower Matecumbe US 1 Bay ------Ph. 2 Imp. Current Ocean ------Ph. 2 Imp. Current 79.8 East of Tea Table Relief Upper Matecumbe US 1 Bay ------Ph. 2 Imp. Current 84.8 East of Whale Harbor Channel Windley US 1 Both ------No information Bay ------Ph. 2 Imp. Current 85.8 East of Snake Creek Plantation US 1 Ocean ------Ph. 2 Imp. Current Ocean ------No information 90.8 West of Tavernier Creek Key Largo US 1 EB Median ------See Bridge Crossings

Excludes crossings at bridges where the pipeline buried under US 1 is continuous with the pipeline on or inside bridge: Niles Channel; 7-Mile; Long Key; Channel 5; Channel 2 (west); and Tea Table Channel (east) . The buried pipelines at those locations were tested for CP as shown in the previous table. Excludes all road crossings of the 18-in steel transmission main and all other arterial road crossings.

Page 1 of 1 Request for Proposal EXHIBIT A

Narrative Description of Bridge Crossings

This section describes the history of CP at each bridge crossing of the FKAA’s steel transmission main and the results of an assessment made of the CP status in 2017. The crossings are listed in order of increasing Mile Marker (MM).

Cow Key Channel

West Side ‐ MM 4.2 This section covers the buried 18‐in steel transmission main on Key West at the bridge over Cow Key Channel. The pipeline is in the median of US 1 at this location. There were no CP records found for the buried steel transmission main at this location. In 2017, visual inspection of the site indicated that the pipeline enters the ground near the bridge. No test stations were found. Using direct contact to the exposed steel pipe on the bridge, the pipe‐to‐soil potential (PSP) was ‐540 millivolts (mV) to a copper sulfate reference electrode (CSE), which indicates that the buried steel pipe does not have CP. The cathodic current requirement of the buried steel pipeline was 40 milliamperes (mA), which suggests that it has a short length and is electrically isolated. Electronic location of the buried pipeline indicated that a transition or some other form of electrical isolation occurs within 20 feet of the bridge. East Side – MM 4.3 This section covers the 18‐in buried steel transmission main on Stock Island at the bridge over Cow Key Channel. The pipeline is in the median of US 1 at this location. The CP records show that the PSP of this pipeline was last tested in 1998 at a test station on the east side of the channel. The PSP was ‐780 mV CSE, indicating marginal CP for buried steel. In 2017, visual inspection of the site indicated that the pipeline enters the ground near the bridge. No test stations were found. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐510 mV CSE, indicating that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipeline was 161 mA, which suggests that it has limited length and is electrically isolated. The results of electronic location of the buried steel pipeline were not definitive but suggested that it is electrically isolated near the valve vault located 160 feet from the bridge. Boca Chica Channel West Side ‐ MM 6.0 This section covers the 24‐in buried steel transmission main on Stock Island at the bridge over Boca Chica Channel. The pipeline is on the side of US 1 at this location. The CP Phase 1 redline drawings show that the pipeline adjacent to the bridge has a buried length of approximately 230 feet and extends to Valve Vault (VV) S288. A buried Dresser coupling is shown 5 feet from the bridge. A transition coupling is shown 18 inches west VV S288 where the steel pipeline connected to ductile iron pipe. During Phase 1, a test station was installed eat th Dresser coupling near the bridge, and 2 zinc anodes were installed on the 5‐foot section of steel pipe. Two zinc anodes may have been installed on the longer section of steel pipe (the drawings are unclear on this point). A test station was installed at the transition coupling,e and on zinc anode was installed on the 18‐inch long section of steel pipeline near the vault.

1

Request for Proposal EXHIBIT A

In 2017, testing at the test station near the bridge indicated that the PSP of the buried steel pipeline was ‐530 mV CSE on the channel side of the Dresser coupling and ‐363 mV CSE on the other side. These results indicate that both sections of steel pipeline do not have adequate CP but are electrically isolated from each other. Using the test station, the cathodic current requirement of the short pipeline was determined to be approximately 30 mA, which suggests that the steel pipe has a short length and is electrically isolated. A test station was not found at VV S288; it was presumed buried or destroyed, and no tests were conducted. The 225 feet of steel pipeline can be expected to have cathodic current requirement proportionate to its length. East Side ‐ MM 6.5 This section covers the 24‐in buried steel transmission main on Big Coppitt Key at the bridge over Boca Chica Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the buried steel pipeline extends 291 feet from thee bridg to VV S282. A Dresser coupling is shown 7 feet from the bridge, and a buried transition coupling is shown 6 inches from the vault. A cased crossing of US 1 with 24‐in steel pipe is shown upstream from the vault. During Phase 1, a test station was installed at the Dresser coupling near the bridge, and 1 zinc anode was installed on the 7‐foot section of steel pipe. Two zinc anodes may have been installed on the longer section of steel pipe (the drawings are unclear on this point). Test stations were installed at 2 transition couplingsr nea the vault. In 2017, no test stations were found and were presumed missing or destroyed. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐674 mV CSE, which indicates that the buried section of steel pipeline has marginal CP. The cathodic current requirement of the pipeline was 20 mA, which suggests that the steel pipe at the channel does indeed have short length and is electrically isolated from the longer section of steel pipeline. No tests were conducted on the longer section of steel pipeline or on the cased crossing due to the absence of test stations. The 284 feet ofd burie steel pipeline can be expected to have cathodic current requirement proportionate to its length. The steel carrier pipeline will have a cathodic current requirement proportionate to the length of pipe that is buried or submerged, including the portion inside the casing. Rockland Channel West Side ‐ MM 9.8 This section covers the 24‐in buried steel transmission main on Big Coppitt Key at the bridge over Rockland Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 328 feet, and that the transition to ductile iron pipe occurs at a buried insulated flange 12 inches outside VV S274. A test station and 4 zinc anodes were installed on this section of steel pipeline. Another test station was installed 37 feet from the bridge. In 2017, tests made at the test stations showed that the PSP of the steel pipe was ‐960 to ‐995 mV CSE and that of the ductile iron pipe was ‐808 mV CSE. These results indicate that the buried section of steel pipe has adequate CP, although electrical isolation from the ductile pipe is incomplete. East Side ‐ MM 10.0 This section covers the 24‐in buried steel transmission main on at the bridge over Rockland Channel. The pipeline is on the Atlantic Ocean side of US 1 at this location.

2

Request for Proposal EXHIBIT A

There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, no test stations were found by visual inspection. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐383 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipeline was 47 mA, which suggests that it has limited length and is electrically isolated. Electronic location of the pipeline indicated that the transition or other form of electrical isolation occurs at VV S268, which is located 479 feet from the bridge. Shark Channel

West Side ‐ MM 11.3 This section covers the 24‐in buried steel transmission main in the area of Big Coppitt Key at the bridge over Shark Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 391 feet, with a Dresser coupling 53 feet east of VV S266, where the transition to ductile iron pipe is presumed to occur. A test station was installed at the coupling, and 2 magnesium anodes were installed on the steel section of pipeline. In 2017, the test station was not found by visual inspection and was presumed buried or destroyed by construction of the Heritage Trail at that location. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐1,099 mV CSE, which indicates that the buried section of steel pipeline has adequate CP and is electrically isolated. East Side ‐ MM 11.8 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 5 Key at the bridge over Shark Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 699 feet and transitions to ductile iron pipe at VV S260. Test stations were installed near the bridge abutment and at the vault, and a total of 10 magnesium anodes were installed on this section of steel pipeline. In 2017, only the test station at the bridge was found during visual inspection of the site. Using the test station, the PSP was ‐511 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement was very high at 2,800 mA. Electronic location of the pipeline showed that it is shorted to (electrically continuous with) the 18‐in steel transmission main at the valve vault. This result indicates that failure of the electrical isolation of the 18‐in pipeline has occurred at the vault. The 18‐inch main does not have CP, and the anodes on the 24‐in pipeline cannot provide protection for both pipelines. The anodes installed on the 24‐in pipeline may have been consumed by the high current requirement of the 18‐in pipeline. The distance from the bridge abutment to VV S260 was measured at 642 feet and not 699 feet as shown on the record drawing. Saddlebunch No. 5 Channel West Side ‐ MM 12.6 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 5 Key at the bridge over Saddlebunch No. 5 Channel. The pipeline is on the Ocean side of US 1 at this location. There has been no CP work on the 24‐in buried steel transmission main at this location since it was last tested and found protected in 1998. 3

Request for Proposal EXHIBIT A

In 2017, no test stations were found by visual inspection. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐686 mV CSE, which indicates that the buried steel pipeline has marginal CP. The cathodic current requirement of the pipe was 173 mA. Electronic location of the pipeline indicated that the transition or other isolation occurs at VV S258, which is 929 feet from the bridge.

East Side ‐ MM 12.8 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 4 Key at the bridge over Saddlebunch No. 5 Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 296 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 5 magnesium anodes were installed on this section of pipeline. In 2017, the test station was not found and was presumed buried or destroyed. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐1,503 mV CSE, which indicates that the steel pipeline has adequate CP and is electrically isolated. The pipeline was electronically located from the bridge to the anodes installed during Phase 1. Saddlebunch No. 4 Channel West Side ‐ MM 13.1 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 4 Key at the bridge over Saddlebunch No. 4 Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 238 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 4 magnesium anodes were installed on this section of pipeline. In 2017, the test station was not found; the FKAA’s records indicate that it was buried or destroyed in 2016. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐1,417 mV CSE, which indicates that the buried steel pipeline has adequate CP and is electrically isolated. The pipeline was electronically located from the bridge to the anodes that were installed during Phase 1. East Side ‐ MM 13.3 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 3 Key at the bridge over Saddlebunch No. 4 Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipe adjacent to the bridge has a buried length of 298 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 2 magnesium anodes were installed on this section of pipeline. In 2017, the test station was not found. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐958 mV CSE, which indicates that the buried steel pipeline has adequate CP and is electrically isolated. The pipeline was electronically located from the bridge to anodes installed on the pipe during Phase 1. Saddlebunch No. 3 Channel West Side ‐ MM 14.2 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 3 Key at the bridge over Saddlebunch No. 3 Channel. The pipeline is on the Ocean side of US 1 at this location.

4

Request for Proposal EXHIBIT A

The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 237 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 2 zinc anodes were installed on this section of pipe. In 2017, the test station was not found and was presumed buried or destroyed. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐979 mV CSE, which indicates that the buried steel pipeline has adequate CP and is electrically isolated. The pipeline was electronically located from the bridge to anodes installed during Phase 1. An old test station was found at this location and appears to be on the 18‐inch steel main, which is not in service at this location. The PSP at the test station was ‐988 mV CSE, indicating adequate CP of the buried steel pipeline. East Side ‐ MM 14.4 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 2 Key at the bridge over Saddlebunch No. 3 Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 327 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 8 magnesium anodes were installed on this section of pipe. In 2017, the test station was not found and was presumed buried or destroyed. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐1,603 mV CSE, which indicates that the buried steel pipeline has adequate CP and is electrically isolated. The pipeline was electronically located from the bridge to anodes installed during Phase 1. Saddlebunch No. 2 Channel West Side ‐ MM 14.5 This section covers the 24‐in buried steel transmission main on Saddlebunch No. 2 Key at the bridge over Saddlebunch No. 2 Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 243 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 5 magnesium anodes were installed on this section of steel pipe. The test station at the transition was found and tested. The PSP of the steel pipeline was ‐1,402 mV CSE and that of the ductile iron was ‐358 mV CSE. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐1,532 mV CSE. These results indicate that the buried steel pipeline has adequate CP and is electrically isolated. East Side ‐ MM 14.8 This section covers the 24‐in buried steel transmission main on Bay Point at the bridge over Saddlebunch No. 2 Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 235 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 10 magnesium anodes were installed on this section of pipe. In 2017, the test station at the transition was found and tested. The PSP of the steel pipeline was ‐1,062 mV CSE and that of the ductile iron was +60 mV CSE. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐1,524 mV CSE. These results indicate that the buried steel pipeline has adequate CP and is electrically isolated.

5

Request for Proposal EXHIBIT A

Lower Sugarloaf Channel West Side ‐ MM 15.2 This section covers the 24‐in buried steel transmission main on Bay Point, on the west side of the bridge over Lower Sugarloaf Channel. The pipeline is on the Ocean side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, no test stations were found by visual inspection. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐292 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipe was 60 mA, which suggests that the buried steel pipeline has limited length and is electrically isolated. The results of electronic location of the pipeline were unclear but suggested that the transition or another form of electrical isolation occurs about 143 feet from the bridge abutment and about 125 feet east of VV S238. It is possible that the transition occurs at the vault. East Side ‐ MM 15.5 This section covers the 24‐in buried steel transmission main on an unnamed key on the east side of the bridge over Lower Sugarloaf Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 279 feet. It connects to a buried insulated flange and continues as buried steel pipe for 1 foot before passing through VV S238. On the other side of the vault, the buried steel pipe continues for another 1 foot and then has an insulated flange connection to ductile iron pipe. Test stations were installed at both insulated flanges, and 5 magnesium anodes were installed on the longer section of steel pipe. There is no indication that anodes were installed on the short lengths of buried steel pipe adjacent to the vault. In 2017, tests made at the test station on the channel (west) side of the vault indicated that the PSP of the pipe from the bridge was ‐435 mV CSE and that of the pipe at the vault was ‐455 mV CSE. At the test station on the island (east) side of the vault, the PSP of the steel pipe at the vault was ‐310 mV CSE and that of the ductile iron pipe was ‐370 mV CSE. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐458 mV CSE. These results indicate that the buried steel pipeline does not have adequate CP, although the buried insulated flanges appear to be functional. The cathodic current requirement of the 279 feet of buried steel pipe was 155 mA. This result supports the results of other tests indicating that the pipe is electrically isolated. The cathodic current requirement of the buried pipe adjacent to the vault is minimal but would require an additional anode on each side of the vault for CP. Harris Channel West Side ‐ MM 16.4 This section covers the 24‐in buried steel transmission main on an unnamed key on the west side of the bridge over Harris Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that 2 magnesium anodes were installed on the buried steel pipe near the bridge. No work was done to the existing test station. In 2017, the test station was found near the bridge abutment and was an oxidized ‘Flush Fink’ thermoplastic box. Tests showed that the test leads were not functional. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐292 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. 6 Request for Proposal EXHIBIT A

The cathodic current requirement of the pipe was 110 mA, which suggests that the buried steel pipeline is electrically isolated. Electronic location of the pipeline indicated that the transition or some other form of electrical isolation occurs 571 feet from the bridge abutment. East Side ‐ MM 16.5 This section covers the 24‐in buried steel transmission main on Lower at the bridge over Harris Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 13 feet before its connection to ductile iron pipe at a buried Dresser coupling. A test station was installed at the coupling, and 2 magnesium anodes were installed on this section of pipe. In 2017, the test station was found and tested. The PSP of the steel bridge pipe was ‐587 mV CSE and that of the pipe on the other side of the coupling was ‐545 mV CSE. The cathodic current requirement was 140 mA, which seems high for such a short length of pipe. The high, although manageable, current requirement at this location might be explained by poor quality coating on the pipeline. Tests showed that the Dresser coupling provided electrical isolation of the connecting pipes from each other, and that the pipeline was not electrically continuous across the bridge or ‘shorted’ to it. Electronic location of the pipeline indicated that the coupling was located at the test station and confirmed that it was a functional as an insulator. Harris Gap Channel West Side ‐ MM 17.5 This section covers the 24‐in buried steel transmission main on Lower Sugarloaf Key at the bridge over Harris Gap Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 24 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 2 magnesium anodes were installed on this section of steel pipeline. In 2017, the test station at the transition was found partially covered by asphalt pavement. It was chipped dout an tested. The PSP of the steel pipeline was ‐723 mV CSE and that of the ductile iron was ‐ 447 mV CSE. The tests results indicate that CP is marginal for the buried steel pipeline, although it is electrically isolated from the ductile iron pipe. The cathodic current requirement for full protection of the buried steel pipeline was 70 mA, which is high but manageable for the short length of pipe at this location. East Side ‐ MM 17.5 This section covers the 24‐in buried steel transmission main on an unnamed key on the east side of the bridge over Harris Gap Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 25 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 3 zinc anodes were installed on this section of steel pipeline. In 2017, the test station at the transition was found by visual inspection. The PSP of the steel pipe was ‐ 475 mV CSE and that of the ductile iron was ‐361 mV CSE. These test results indicate that the steel pipe does not have adequate CP, although it is electrically isolated from the ductile iron pipe. The cathodic current requirement of the buried steel pipe was 112 mA, which is high, but manageable, for the short length of pipeline.

7

Request for Proposal EXHIBIT A

North Harris Channel West Side ‐ MM 17.8 This section covers the 24‐in buried steel transmission main on an unnamed key on the west side of the bridge over North Harris Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 25 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 2 magnesium anodes were installed on this section of steel pipe. In 2017, the test station at the transition was found. The PSP of the steel pipeline was ‐477 mV CSE and that of the ductile iron was ‐463 mV CSE. These test results indicate that the steel pipeline does not have adequate CP. The cathodic current requirement of the buried steel pipeline was 138 mA, which is high, but manageable, for the short length of pipeline and confirms that it is electrically isolated. Electronic location of the buried steel pipeline indicated that the transition or another form of electrical isolation occurst at the tes station. An old ‘Flush Fink’ thermoplastic test station was found near the abutment. Inspection of the exposed pipe showed that old test wires were attached to it. However, the wires were cut off a short distance from the pipe and were not functional. East Side ‐ MM 17.8 This section covers the 24‐in buried steel transmission main on at the bridge over North Harris Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 25 feet before it transitions to ductile iron pipe. A test station was installed at the transition and 3 zinc anodes were installed on this section of steel pipe. In 2017, the test station at the transition was found partially covered by asphalt pavement. It was chipped out and tested. The PSP of the steel pipe was ‐627 mV CSE and that of the ductile iron was ‐502 mV CSE. The tests results indicate that CP is marginal for the buried steel pipe, although it is electrically isolated from the ductile iron pipe. The cathodic current requirement of the buried steel pipe was 51 mA, which is moderately high but manageable for the short length of pipe at this location. An old ‘Flush Fink’ thermoplastic test station was found 10 feet near the bridge abutment. The test wires were traced to the pipeline but were cut off a short distance from it and were not functional. Park Channel West Side – MM 18.7 This section covers the 24‐in buried steel transmission main on Park Key at the bridge over Park Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old, broken ‘Flush Fink’ thermoplastic test station was found 16 feet from the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. The test wires were cut or broken and were not functional. Tests showed that the anode produced only 1 mA of current so it was substantially consumed. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐490 mV CSE, which indicates that the buried section of steel pipeline does not have adequate CP. The cathodic current requirement of the pipe was 45 mA, which suggests that the buried steel pipeline is electrically isolated. Electronic

8

Request for Proposal EXHIBIT A location of the pipe indicated that the transition or another form of electrical isolation occurs 448 feet from the bridge abutment. The current requirement seems low for the length of steel pipeline indicated by the electronic locator, so the buried pipe material should be confirmed. There may also be other buried steel transmission main on Park Key. The FKAA’s valve vault drawings showed steel pipe on both sides of VV S222. East Side – MM 18.8 This section covers the 24‐in buried steel transmission main on at the bridge over Park Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that 1 magnesium anode was installed on the buried steel pipe near the bridge. No work was done to the existing test station, and the transition was not located. In 2017, an old test station was found 16 feet near the bridge abutment; it was an old oxidized ‘Flush Fink’ thermoplastic box that broke apart when it was opened. The test station contained 2 test wires to the pipe and 1 wire to a magnesium anode. All wires were functional. One of the pipe wires was connected to the anode wire, and the P/S was ‐967 mV CSE, indicating that CP was adequate. The wires were left connected as they were found. Electronic location of the pipe indicated that the transition or some other form of electrical isolation occurs 18 feet from the bridge abutment and in the immediate vicinity of the test station. Bow Channel West Side – MM 20.2 This section covers the 24‐in buried steel transmission main on Upper Sugarloaf Key at the bridge over Bow Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 31 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 1 magnesium anode was installed on this section of steel pipe. In 2017, the test station at the transition was found. The PSP of the steel pipe was ‐746 mV CSE and that of the ductile iron was ‐557 mV CSE. These test results indicate that the CP is marginal for the buried steel pipe, but that the pipeline is electrically isolated. The cathodic current requirement of the buried steel pipeline was 80 mA, which seems relatively high but confirms electrical isolation. East Side – MM 20.5 This section covers the 24‐in buried steel transmission main on Cudjoe Key at the bridge over Bow Channel. The pipeline is on the Ocean side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, no test stations were found. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐458 mV CSE, which indicates that the buried section of steel pipe does not have adequate CP. The cathodic current requirement of the pipe was 45 mA, which suggests that the buried steel pipeline is electrically isolated. Electronic location of the steel pipeline indicated that the transition or some other form of electrical isolation occurs 14 feet from the bridge abutment. Kemp Channel West Side – MM 23.6 This section covers the 24‐in buried steel transmission main on Cudjoe Key at the bridge over Kemp Channel. The pipeline is on the Ocean side of US 1 at this location.

9 Request for Proposal EXHIBIT A

There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐322 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipeline was 55 mA, which suggests that it is electrically isolated. Electronic location of the pipe indicated that the transition or some other form of isolation occurs 11 feet from the bridge abutment. East Side – MM 23.8 This section covers the 24‐in buried steel transmission main on at the bridge over Kemp Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel transmission main adjacent to the bridge has a buried length of 6 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 1 zinc anode was installed on this section of steel pipe. In 2017, the test station at the transition was found by visual inspection. The PSP of the steel pipeline was ‐340 mV CSE and that of the ductile iron was ‐359 mV CSE. These test results indicate that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the buried steel pipeline was 100 mA which seems relatively high. Test results indicate that the steel pipeline is electrically isolated from the ductile iron pipe. Niles Channel West Side – MM 25.4 This section covers the 24‐in buried steel transmission main on Summerland Key at the bridge over Niles Channel. The Niles Channel bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 138 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 3 magnesium anodes were installed on this section of pipeline. Another test station was installed at the bridge with leads to the pipeline inside the concrete bridge. In 2017, the test stations were found. Tests made at the test stations indicated that the PSP of the steel pipeline was ‐638 to ‐705 mV CSE and that of the ductile iron pipe was ‐257 mV CSE. These results indicate that the buried steel pipeline has marginal CP, although it appears to be electrically isolated from the bridge and from the ductile iron pipe. The cathodic current requirement of the buried steel pipeline was 198 mA. East Side – MM 26.3 This section covers the 24‐in buried steel transmission main on at the bridge over Niles Channel. The Niles Channel bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 130 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 10 magnesium anodes were installed on this section of pipeline. Another test station was installed at the bridge with leads to the pipeline inside the concrete bridge. In 2017, the test station at the bridge was found. The site of test station at the transition was covered with trees and brush, and the test station was not found. Tests made at bridge test station indicated

10 Request for Proposal EXHIBIT A that the PSP of the steel pipe was ‐1,100 mV CSE. These results indicate that the buried steel pipeline has adequate CP, and that it is electrically isolated from the bridge and from the ductile iron pipe. Torch Ramrod Channel West Side – MM 27.6 This section covers the 24‐in buried steel transmission main on Ramrod Key at the bridge over Torch Ramrod Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old ‘Flush Fink’ thermoplastic test station was found 16 feet from the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. The test wires to the pipe were functional and the PSP was ‐361 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. Tests showed that the anode produced only 2 mA of current so it was substantially consumed. The cathodic current requirement of the steel pipeline was 47 mA, which suggests that it is electrically isolated. Electronic location of the steel pipeline indicated that the transition or some other form of electrical isolation occurs 16 feet from the bridge abutment and at the location of the test station. East Side – MM 27.7 This section covers the 24‐in buried steel transmission main on at the bridge over Torch Ramrod Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the 24‐in buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old ‘Flush Fink’ thermoplastic test station was found at the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. The test wires to the pipe were functional Pand the PS was ‐384 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. Tests showed that the anode produced only 3 mA of current so it was substantially consumed. The cathodic current requirement of the pipe was 52 mA, which suggests that the buried steel pipeline is electrically isolated. Electronic location of the pipe indicated that the transition or some other form of electrical isolation occurs 24 to 35 feet from the bridge abutment. Middle Torch Road Crossing MM 27.8 This section covers the 24‐in buried steel transmission main on that crosses Middle Torch Road on Little Torch Key. The pipeline is on the Bay side of US 1 at this location. The crossing of Middle Torch Road is constructed from steel pipe in a steel casing and is approximately 80 feet long. The carrier pipe has a transition to ductile iron pipe outside the casing. A test station was installed at the transition and a zinc anode was installed on the steel carrier pipe at each end of the casing during the Phase 2 Cathodic Protection Improvements. In 2017, the westerly test station was found and tested. The PSP of the steel pipe was ‐737 mV CSE and that of the ductile iron was ‐497 mV CSE. The easterly test station was also found and tested. The PSP of the steel pipe was ‐715 mV CSE and that of the ductile iron was ‐314 mV CSE. These results indicate that the buried section of steel pipe has marginal CP, although the pipeline appears to be electrically isolated from the ductile iron pipe. The cathodic current requirement was 32 mA.

11

Request for Proposal EXHIBIT A

Torch Key Channel West Side – MM 28.0 This section covers the 24‐in buried steel transmission main on at the bridge over Torch Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old ‘Flush Fink’ thermoplastic test station was found 16 feet from the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. The test wires were cut off at the pipe and not functional. Using direct contact to the pipe on the bridge, the PSP was ‐349 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. Tests showed that the anode produced only 3 mA of current so it was substantially consumed. The cathodic current requirement of the buries steel pipeline was 8 mA, which suggests that it is electrically isolated. Electronic location of the steel pipeline indicated that the transition or some other form of electrical isolation occurs 14 feet from the bridge abutment. East Side – MM 28.1 This section covers the 24‐in buried steel transmission main on Little Torch Key at the bridge over Torch Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old ‘Flush Fink’ thermoplastic test station was found near the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. Only one of the pipe test wires was functional. Using that ewire, th PSP was ‐380 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. Tests showed that the anode produced only 2 mA of current so it was substantially consumed. The cathodic current requirement of the steel pipeline was 55 mA, which suggests that it is electrically isolated. Electronic location of the steel pipeline indicated that the transition or some other form of electrical isolation occurs approximately 20 feet from the bridge abutment. South Pine Channel West Side – MM 28.6 This section covers the 24‐in buried steel transmission main on Little Torch Key at the bridge over South Pine Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 26 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 1 magnesium anode was installed on this section of pipe. In 2017, the test station was not found by visual inspection and was presumed missing or destroyed. Test wires were found but were cut off at the pipe. A wire from an anode was also found but was damaged. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐291 mV CSE, which indicates that the buried section of steel pipe does not have adequate CP. The cathodic current requirement of the buried steel pipeline was 69 mA, which suggests that it has a short length and is electrically isolated. East Side – MM 28.8 This section covers the 24‐in buried steel transmission main on a fill area on the east side of the bridge over South Pine Channel. The pipeline is on the Bay side of US 1 at this location. 12

Request for Proposal EXHIBIT A

The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 24 feet before it transitions to ductile iron pipe. A test station was installed at the transition and 1 magnesium anode was installed on this section of pipe. In 2017, the test station was not found and was presumed missing or destroyed. Test wires were found but were attached to the channel side of a flexible coupling on the exposed pipe, which precludes their use in testing the buried pipe. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐424 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipeline was 35 mA, which suggests that it has a short length and is electrically isolated. North Pine Channel West Side – MM 29.3 This section covers the 24‐in buried steel transmission main on a fill area on the west side of the bridge over North Pine Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 25 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 2 magnesium anodes were installed on this section of pipeline. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐703 mV CSE and that of the ductile iron was ‐284 mV CSE. These test results indicate that CP is marginal for the buried steel pipeline, but that the pipeline appears to be electrically isolated. The cathodic current requirement for full CP of the buried steel pipeline was 21 mA. There is a flexible coupling on the exposed pipe at the abutment. Tests showed that the coupling has some resistance across it, so it is neither completely dielectric nor completely conductive. This could change with movement of the pipe as might occur from bridge vibration or thermal changes. East Side – MM 29.5 This section covers the 24‐in buried steel transmission main on Big Pine Key west of the bridge over North Pine Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the buried steel pipeline adjacent to the bridge has a length of 24 feet before it transitions to ductile iron pipe at a Dresser coupling. A test station was installed at the transition, and 3 zinc anodes were installed on this section of pipe. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐903 mV CSE and that of the ductile iron was ‐911 mV CSE. It is unusual when the steel PSP is less negative than the ductile iron. Further tests indicated that the wire insulation colors were reversed at this station; the blue wires are connected to the ductile iron (instead of steel) and the green wires are connected to steel (instead of ductile iron). The test results indicate that CP is adequate for the buried steel pipeline but that the transition is ‘shorted’ (conductive), and the piece of ductile iron pipe to which the test wires are connected is also protected. This situation does not require correction if adequate CP is maintained on the steel pipeline. There is also a flexible coupling on the exposed pipe at the abutment. Tests showed that the coupling had some resistance across it, so it was neither completely dielectric nor completely conductive. This could change with movement of the pipe as might occur from bridge vibration or thermal changes. Spanish Harbor Channel West Side – MM 33.0 This section covers the 24‐in buried steel transmission main on Big Pine Key at the bridge over Spanish Harbor Channel. The pipeline is on the Ocean side of US 1 at this location. 13 Request for Proposal EXHIBIT A

The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 6 feet before it transitions to ductile iron pipe at a Dresser coupling. A test station was installed at the transition, and 4 zinc anodes were installed on this section of pipe. The CP Phase 1 commissioning report by the construction contractor described the conditions found upon excavation of the pipe. It revealed that a non‐insulating Dresser coupling was used at the transition, and that the pipe was under a cap of flowable fill (i.e., low‐strength Portland cement mortar) that created a dry, unfavorable environment for the anodes. The contractor recommended installation of additional anodes on the ductile iron side of the transition to boost CP, or, alternatively, replace the Dresser coupling with an insulating type. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐648 mV CSE and that of the ductile iron was ‐592 mV CSE. The test results indicate that CP is marginal for the buried steel pipeline, and that electrical isolation is weak at the transition. The cathodic current requirement for CP of the buried steel pipeline was 250 mA, which is high for the length of the pipeline but not unusual considering weak electrical isolation. East Side – MM 33.6 This section covers the 24‐in buried steel transmission main on West Summerland Key at the bridge over Spanish Harbor Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the buried steel pipeline adjacent to the bridge has a length of 6 feet before it transitions to ductile iron pipe at a Dresser coupling. A test station was installed at the transition, and 4 zinc anodes were installed on this section of pipe. The CP Phase 1 commissioning report by the construction contractor described the conditions found upon excavation of the pipe. It revealed that a non‐insulating Dresser coupling was used at the transition, and that the pipe was under a cap of flowable fill (i.e., low‐strength Portland cement mortar) that created a dry, unfavorable environment for the anodes. The contractor recommended installation of additional anodes on the ductile iron side of the transition to boost CP, or, alternatively, replace the Dresser coupling with an insulating type. In 2017, the test station at the transition was found and tested. The PSP of the steel pipeline was ‐708 mV CSE and that of the ductile iron was ‐708 mV CSE. The test results indicate that CP is marginal for the buried steel pipe, and that the transition is ‘shorted’ (conductive) such that the piece of ductile iron pipe to which the test wires are connected is also protected. The cathodic current requirement for CP of the buried steel pipeline was 130 mA, which is high for the length of thet pipeline bu not unusual considering the ‘shorted’ electrical isolation. Bahia Honda Channel West Side – MM 35.3 This section covers the 24‐in buried steel transmission main on West Summerland Key at the bridge over Bahia Honda Channel. The pipeline is in the median of US 1 at this location. The CP Phase 1 redline drawings show that the buried steel pipeline adjacent to the bridge has a Dresser coupling 6 feet west of a thrust block at the bridge. A test station was installed 10 feet from the thrust block, and 2 magnesium anodes were installed on this section of pipe. The anode leads were connected to a pipe lead in the test station. In 2017, the test station was found and tested. It was a ‘Big Fink’ post type that contained 2 wires from the pipe and 2 wires from the anodes. Tests showed that only 1 pipe lead and 1 anode lead were functional. Using the functional pipe test lead, the PSP was ‐196 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The low value of the potential suggests that the pipe is embedded in the buried concrete thrust block as it appears by inspection.

14 Request for Proposal EXHIBIT A

The cathodic current requirement of the pipe was 2,000 mA which seems high. However, electronic location of the pipe indicated that it is continuous from the test station at the bridge to the test station near VV S122/SA124, located approximately 970 feet from the bridge. The test station at VV S122/SA124 was installed during Phase 2 CP Improvements. Tests showed that the green insulated wires in the test station were connected to the steel pipeline from the bridge. Based on current requirement tests and electronic location, the buried steel pipeline appears to extend 970 feet from the bridge to the east side of VV S122/SA124. East Side – MM 36.6 This section covers the 24‐in buried steel transmission main on at the bridge over Bahia Honda Channel. The pipeline is in the median of US 1 at this location. There was no CP work done on the buried steel transmission main at this location during Phase 1 CP Improvements, because the pipe was tested and found protected in 1998. In 2017, inspection of the site revealed an old ‘Flush Fink’ thermoplastic test station near the bridge abutment in the median. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. The wire connections were corroded in the test box so they were disconnected and cleaned. After cleaning, the P/S of the pipe lead was ‐395 mV CSE without the anode connected and ‐ 589 mV CSE with it connected; the anode current was 51 mA. The test results indicate that the buried steel pipeline does not have adequate CP even with the anode connected. Electronic location of the steel pipeline indicated that it was continuous for some distance east of the bridge. Tracing the pipe led to a flush iron test station in the median approximately 500 feet from the bridge. The test station contained two wires to the pipe and 3 wires to old anodes. Only 1 of the pipe leads was functional and was used to measure the P/S at ‐559 mV CSE. The electronic trace continued east beyond the test station, and it became apparent that the steel pipe probably continued all the way to VV S116/SA114, which is located approximately 1,850 feet from the bridge. Test stations were installed at VV S116/SA114 during Phase 2 CP Improvements. A cathodic current requirement test was conducted on the buried steel pipeline at the bridge, and results indicated continuity of the pipeline to the test station 500 feet from the bridge and to the test station on the west side VV S 116 / SA 114. Results indicated that 1000 mA of CP current would be required to protect the buried steel pipeline. Based on current requirement tests and electronic location, the buried steel pipeline appears to extend 1,800 feet from the bridge to the west side of VV S116/SA114. Ohio Bahia Honda Channel West Side – MM 38.5 This section covers the 24‐in buried steel transmission main on Bahia Honda Key at the bridge over Ohio Bahia Honda Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, visual inspection of the site found 2 test wires attached to the pipe. The wires ran under a fenced area on the Heritage Trail, and it could not be determined if there was test station in the enclosure. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐237 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipe was 29 mA, which suggests that the buried steel pipeline at the channel has a short length and is electrically isolated. Electronic location of the buried steel pipeline indicated that the transition occurs just outside the bridge abutment.

15 Request for Proposal EXHIBIT A

East Side – MM 38.7 This section covers the 24‐in buried steel transmission main on at the bridge over Ohio Bahia Honda Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, no test stations were found. The exposed pipe appeared to have Cadweld wire connections under the coating, but the ends of the wires were not found. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐303 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipeline was 100 mA, which suggests that it has moderate length and is electrically isolated. Electronic location of the pipeline indicated that the transition or some other form of electrical isolation occurs approximately 130 feet east of the bridge, near a service tap and meter. Ohio Missouri Channel West Side – MM 39.0 This section covers the 24‐in buried steel transmission main on Ohio Key at the bridge over Ohio Missouri Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 21 feet before it transitions to ductile iron pipe at a Dresser coupling. A post‐mounted test station was installed at the transition, and 1 magnesium anode was installed on this section of steel pipe. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐1,286 mV CSE and that of the ductile iron was ‐190 mV CSE. These test results indicate that the buried steel pipeline has adequate CP and is electrically isolated. Electronic location of the buried steel pipeline using the blue (‘steel’) leads at the test stationd indicate that the transition occurs at the same location as the test station. However, there is reason to believe that the transmission main is constructed entirely of steel pipe on Ohio Key. Electronic location using the green (‘ductile iron’) leads at the test station traced the pipe for approximately 1,570 feet to the same area found by testing on the east side of Ohio Bahia Channel (MM 38.7) discussed above. The cathodic current requirement was 430 mA which is not unusual considering the length of the pipeline. Therefore, the ‘transition’ coupling near MM 38.7 is probably a Dresser coupling with steel pipe on each side. East Side – MM 39.3 This section covers the 24‐in buried steel transmission main on at the bridge over Ohio Missouri Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 25 feet before it transitions to ductile iron pipe at a Dresser coupling. A post‐mounted test station was installed at the transition, and 1 magnesium anode was installed on this section of steel pipe. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐230 mV CSE and that of the ductile iron was ‐216 mV CSE. The cathodic current requirement was 125 mA. These test results indicate that the buried steel pipeline does not have adequate CP, and that isolation from the ductile iron pipe is weak. Electronic location of the pipeline suggested that the transition or other form of electrical isolation occurs at the location of the test station. However, the pipeline trace continued beyond the test station for approximately 125 feet. Considering the results of testing at the west side of Missouri Little Duck Channel (discussed below), it is possible that the transmission main on Missouri Key may be constructed entirely from steel pipe.

16

Request for Proposal EXHIBIT A

Missouri Little Duck Channel West Side – MM 39.6 This section covers the 24‐in buried steel transmission main on Missouri Key at the bridge over Missouri Little Duck Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old ‘Flush Fink’ thermoplastic test station was found near the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. Only one of the pipe test wires was functional. Using that wire, the PSP was ‐280 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. Tests showed that the anode produced only 2 mA of current so it was substantially consumed. The cathodic current requirement of the pipeline was 55 mA, which suggests that it is electrically isolated. Electronic location of the pipe using the blue (‘steel’) leads at the test station indicated that the transition or some other form of electrical isolation occurs at the same location as the test station, approximately 20 feet from the bridge abutment. However, there is reason to believe that the transmission main is constructed entirely of steel pipe on Missouri Key. Electronic location using the green (‘ductile iron’) leads at the test station traced the pipe for approximately 1,350 feet to the same area found by testing on the east side of Ohio Missouri Channel (MM 39.3) discussed above. The cathodic current requirement was 556 mA which is not unusual considering the length of the pipeline. Therefore, the ‘transition’ coupling near MM 39.3 is probably a Dresser coupling with steel pipe on each side. East Side – MM 39.7 This section covers the 24‐in buried steel transmission main on Little at the bridge over Missouri Little Duck Channel. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old broken ‘Flush Fink’ thermoplastic test station was found near the bridge abutment. The test box contained 2 wires from the pipe and 1 wire from an old magnesium anode. Only 1 of the pipe test leads was functional. Using the test wire, the PSP was ‐301 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. Tests made using the anode wire indicated that the anode was substantially consumed. The cathodic current requirement of the pipeline was 30 mA, which suggests that it is electrically isolated. Electronic location of the steel pipeline indicated that the transition or some other form of electrical isolation occurs 217 feet from the bridge abutment. The transmission pipeline is probably ductile iron east of this point. The CP Phase 1 redline drawing for the west side of 7 Mile Bridge (discussed below) indicates that the contractor made 10 exploratory excavations about 300 feet east of the indicated location of the transition and found ductile iron pipe at all of them. 7 Mile Bridge West Side – MM 40.0 This section covers the 24‐in buried steel transmission main on at 7 Mile Bridge. The 7 Mile bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 87 feet before it transitions to ductile iron pipe at a Dresser coupling. A post‐mounted test station 17

Request for Proposal EXHIBIT A was installed at the transition, and 1 magnesium anode was installed on this section of steel pipeline. Another post‐mounted test station was installed at the abutment with leads to the pipeline inside the concrete bridge. In 2017, the test station at the transition was found and tested. The PSP of the steel pipeline was ‐966 mV CSE and that of the ductile iron was ‐945 mV CSE. These test results indicate that the buried steel pipeline has adequate CP, but the insulating quality of the transition is weak, and the piece of ductile iron pipe to which the test wires are connected is also protected. This situation does not require correction if adequate CP is maintained on the steel pipe. East Side – MM 46.7 This section covers the 24‐in buried steel transmission main on Marathon Key at 7 Mile Bridge. The 7 Mile bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 1,153 feet before it transitions to 30‐in ductile iron pipe near VV S76/SA78. A flush‐mounted iron test station was installed at the transition, and 30 zinc anodes were installed on this section of steel pipe. Another post‐mounted test station was installed at the abutment with leads to the pipe inside the concrete bridge. During Phase 2 of the CP Improvements, an impressed current CP station was constructed near VV S76/SA78 to provide protection for the 18‐in steel main on Marathon. An additional test station was also installed at the vault. The 18‐in main is connected at the vault and crosses US 1 to Bay side, where it has a service tap to Pigeon Key. The 18‐in main was electrically isolated in the vault at its connection to the 24‐in main during Phase 2 construction. In 2017, all test stations were found and tested. Initial tests showed that the steel pipeline had a PSP of ‐476 mV CSE at the bridge and ‐438 mV CSE at the valve vault. These results indicate that it did not have adequate CP. The FKAA reported that recent landscaping work along US 1 by the City of Marathon cut the wire from the anodes to the pipeline and that the wire had not been repaired. Tests also showed that the flange insulation had failed in the 18‐in main connection in the vault, resulting in the 18‐in and 24‐in steel pipelines ‘shorted’ together. A few days after these tests were completed, the FKAA took the 18‐in main out of service and cut the pipeline on the Bay side of US 1 and a short distance from the service tap for Pigeon Key. Tests were conducted to determine if the impressed current station could be used to provide CP for the 24‐in steel pipeline to the bridge and for the 18‐in steel main crossing US 1. Test results indicated that this approach would be feasible, and that no other construction would be required. Therefore, the output of the impressed current station was adjusted to provide protection to the 18‐ and 24‐in steel pipelines. The rectifier output at the impressed current station at Knight’s Key was left at 2.52 amperes at 3.1 volts DC. The PSP on the 24‐in pipe at the bridge was ‐1,218 mV CSE and ‐924 mV CSE Instant‐Off. Similar values of PSP were measured at test stations at the vault and on the 18‐in steel main near the tap to Pigeon Key. No work other than continued monitoring is required for protection at this location. Vaca Cut West Side – MM 53.2 This section covers the 30‐in buried steel transmission main on Marathon Key at the bridge over Vaca Cut. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 861 feet before it transitions to ductile iron pipe at a buried Dresser coupling. The steel main passes through VV SA38/SA40 at 310 feet from the channel. The pipe material changes to ductile iron pipe in

18

Request for Proposal EXHIBIT A the vault but is steel on both sides of it. The 18‐in steel main was originally connected at the vault, with an insulated flange, but has since been taken out of service by the FKAA. Flush‐mounted iron test stations were installed at VV SA38/SA40 and at the transition. A total of 10 magnesium anodes and 9 zinc anodes were installed on this section of buried steel pipeline. During Phase 2 of the CP Improvements, a total of 6 additional magnesium anodes were installed here. In 2017, the test stations were found and tested. At the valve vault, the PSP of the steel pipe (with green test wires) was ‐896 mV CSE and that of the 18‐in steel main (blue test wires) was ‐900 mV CSE. At the transition, the PSP of the steel pipe was ‐1369 mV CSE and that of the ductile iron was ‐679 mV CSE, with the CSE placed on the grassy curb strip next to US 1. Using direct contact to the exposed pipe on the bridge, the PSP of the steel pipe was ‐1168 mV CSE. These test results indicate that the buried section of steel pipe has adequate CP and is electrically isolated from the ductile iron pipe at the transition. However, the insulating flange on the 18‐in steel main at the vault is not functional, and some of the CP current from the 30‐in main is going to any buried 18‐in main that still has metallic connection at the vault. East Side – MM 53.3 This section covers the 30‐in buried steel transmission main on Grassy Key at the bridge over Vaca Cut. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 996 feet before it transitions to ductile iron pipe. A test station was installed at the transition, and 10 zinc anodes were installed on this section of pipe. In 2017, the test station at the transition was not found and was presumed buried or destroyed. Using direct contact to the steel pipe on the bridge, the PSP was ‐796 mV CSE. The test results indicate that the CP is marginal for the buried steel pipeline. The cathodic current requirement for full protection of the pipeline was 110 mA, which seems reasonable for the length of pipe, and suggests that the pipe is electrically isolated at the transition. A flexible coupling is installed on the exposed pipe adjacent to the bridge abutment. Tests showed that the coupling electrically isolated the buried pipe from the exposed pipe. In addition, the pipe on the channel side of the coupling was electrically continuous with the pipe on the west side of Vaca Cut (described above). The insulating quality of the coupling could change with movement of the pipe as might occur from bridge vibration or thermal changes. US 1 Crossing on Grassy Key MM 59.5 This section covers the 30‐in buried steel transmission main on Grassy Key at Vaca Cut. The pipeline crosses US 1 at this location. The CP Phase 1 redline drawings show that the steel transmission main crossing US 1 at this location has a buried length of 604 feet, with a transition coupling to ductile iron pipe at each end. The actual crossing is the middle one‐third of this length and has a steel carrier pipe in a steel casing. The westerly portion of the steel pipeline is on the Bay side of US 1, and the easterly portion is on the Ocean side. Test stations were installed at each end of the steel pipe where it transitions to ductile iron pipe. A test station was also installed at the angle point on the Bay side of the crossing and had test wires to both the carrier pipe and the casing pipe. A total of 10 magnesium anodes were installed on this section of steel pipe, and they were installed in 2 groups of 5 anodes. In 2017, all 3 test stations were found by visual inspection and tested. The test stations at the easterly transition and at the crossing were damaged by vehicles driving over them. At the easterly transition,

19

Request for Proposal EXHIBIT A the PSP of the steel pipe was ‐642 mV CSE and that of the ductile iron was ‐498 mV CSE. At the westerly transition, the PSP of the steel pipe was ‐655 mV CSE, and that of the ductile iron was ‐571 mV CSE. At the US 1 crossing, the PSP of the steel carrier pipe was ‐693 mV CSE and that of the steel casing was ‐ 645 mV CSE, which indicates weak electrical isolation. An anode wire was found connected to a carrier pipe lead in the test station. With the anode temporarily disconnected, the PSP of the carrier pipe was ‐ 612 mV CSE. The anode current was 200 mA when connected to the pipe. The results indicate that the buried section of steel pipe has marginal CP, although it appears to be electrically isolated from the ductile iron pipe. The cathodic current requirement was 3,000 mA which seems relatively high but could be due to weak electrical isolation between the carrier pipe and the casing, or deterioration of the protective coating on the pipe, or both. Tom’s Harbor Channel West Side – MM 60.5 This section covers the 30‐in buried steel transmission main on Grassy Key at the bridge over Tom’s Harbor Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 411 feet before transitioning to ductile iron pipe. A post‐mounted test station was installed at the bridge, an iron flush‐mounted test station was installed at the transition, and 4 magnesium anodes were installed on this section of steel pipe. In 2017, the test station at the bridge was found and tested. The test station at the transition was found later by the FKAA and subsequently was also tested. The PSP of the steel pipe at the bridge was ‐868 mV CSE. At the transition, the PSP of the steel pipe was ‐1121 mV CSE and that the ductile iron was ‐ 384MV CSE. These test results indicate that the buried steel pipeline has adequate CP and is electrically isolated. Electronic location of the steel pipeline indicated that the transition occurs at the same location as the test station. East Side – MM 60.8 This section covers the 30‐in buried steel transmission main on Duck Key at the bridge over Tom’s Harbor Channel. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 368 feet before transitioning to ductile iron pipe. A flush‐mounted test station was installed at the transition, and 3 zinc anodes were installed on this section of steel pipe. In 2017, the test station was not found and was presumed buried or destroyed. Using direct contact to the steel pipe at the bridge, the PSP of the steel pipeline was ‐890 mV CSE, indicating that the buried steel pipeline has adequate CP. Electronic location of the steel pipeline traced it to the approximate location of the transition, suggesting that the pipeline is electrically isolated at the transition. Tom’s Harbor Cut West Side – MM 61.4 This section covers the 30‐in buried steel transmission main on Duck Key at the bridge over Tom’s Harbor Cut. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 457 feet on Duck Key before transitioning to ductile iron pipe. A flush‐mounted test station was installed at the transition, and 5 magnesium anodes were installed on this section of steel pipe. In 2017, the test station was not found and was presumed buried or destroyed. Using direct contact to the steel pipe at the bridge, the PSP was ‐411 mV CSE, which indicates that the buried steel pipeline

20

Request for Proposal EXHIBIT A does not have adequate CP. The cathodic current requirement of the pipeline was approximately 500 mA. Electronic location of the buried steel pipeline traced it to the location of the transition, which suggests that the steel pipe is probably electrically isolated at the transition. East Side – MM 61.7 This section covers the 30‐in buried steel transmission main on Conch Key at the bridge over Tom’s Harbor Cut. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 507 feet before transitioning to ductile iron pipe at VV S4. A flush‐mounted test station was installed at the transition. A total of 10 magnesium anodes were installed on this section of steel pipe, and they were installed in 2 groups of 5 anodes. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐470 mV CSE and that of the ductile iron was ‐470 mV CSE. These test results indicate that the buried steel pipeline does not have adequate CP and is not electrically isolated from the ductile iron pipe. Using direct contact to the steel pipe at the bridge, the PSP of the steel pipe at the bridge was ‐443 mV CSE. The cathodic current requirement of the pipe could not be determined, because the pipe line could not be polarized to a protected potential with the maximum available current of 2,700 mA. The test results indicate that the steel pipe is ‘shorted’ (conductive) to a large area of buried metal. It seems possible that the abandoned 18‐in steel main may have a metallic connection at or near VV S4 and will require electrical isolation before CP can be effectively applied to the buried steel pipeline at this location. Long Key Channel West Side – MM 63.1 This section covers the 30‐in buried steel transmission main on Conch Key at the bridge over Long Key Channel. The Long Key bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 1,244 feet before transitioning to ductile iron pipe near VV N4. A total of 8 magnesium anodes were installed on this section of steel pipeline, and they were installed in 2 groups of 4 anodes. A post‐ mounted test station was installed at the bridge with leads to the pipe inside the bridge. Two flush‐ mounted test stations were installed at 2 transitions near the vault, and 2 magnesium anodes were installed on approximately 20 feet of buried steel pipe west of the vault. In 2017, the test stations near VV N4 were not found and were presumed missing or destroyed. The test station at the bridge was found and tested. The PSP was ‐394 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the pipeline was approximately 1,000 mA. Test results suggested that the steel pipeline is electrically isolated at the transition, but isolation cannot be confirmed without recovery or replacement of the test stations near VV N4. East Side – MM 65.5 This section covers the 30‐in buried steel transmission main on Long Key at Long Key Bridge. The Long Key Bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location.

21

Request for Proposal EXHIBIT A

The steel pipeline adjacent to Long Key Bridge has a buried length of 710 feet before transitioning to ductile iron pipe. This length was determined during Phase 2 CP Improvements. There was no CP work done on the 30‐in buried steel transmission main at this location during Phase 1 CP Improvements, because the pipe was tested and found protected in 1998. During Phase 2 CP Improvements, an impressed current CP system was constructed on Long Key for protection for the 18‐in and 30‐in steel transmission mains. The rectifier station nearest to Long Key Bridge is located at MM 66.5. At MM 65.5, the 30‐in steel pipeline receives CP via its connection to the 18‐in steel main in VV N198, located about 200 feet from the bridge. Test stations were installed at VV N198, at the bridge, and at the 30‐in transition to ductile iron pipe. The test station at the bridge was found and tested. It had blue test wires and green test wires with blue tape marked W, presumably for west. This station allowed testing of the insulating quality of the flexible coupling inside the concrete bridge. The PSP using the blue wires was ‐1040 mV CSE and ‐1055 mV CSE using the green wires. These results indicate that the buried steel pipe has adequate CP, but the electrical isolation is weak at the transition. The test station at VV N198 was also found and tested. The PSP was ‐1032 mV CSE, indicating that CP is adequate for the buried steel pipe. The test station at the transition was not found and was presumed buried or destroyed. There has been recent construction work on the Heritage Trail at the location of the test station. Channel 5 West Side – MM 70.8 This section covers the 30‐in buried steel transmission main on Long Key at Channel 5 Bridge. The bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 154 feet before transitioning to ductile iron pipe. A post‐mounted test station was installed at the transition. A total of 6 magnesium anodes were installed on this section of steel pipe, in a group of 2 and a group of 4. Another test station was installed at the bridge with leads to the pipeline inside the concrete bridge. In 2017, the test station at the transition was found and tested. The PSP of the steel pipe was ‐822 mV CSE and that of the ductile iron was ‐475 mV CSE. The test station at the bridge was found, and tests indicate that the wire connections to the pipe are broken within the bridge. However, tests made at the other station were sufficient to assess CP. These test results indicate that the buried section of steel pipe has marginal CP but is electrically isolated from the ductile iron pipe. The cathodic current requirement for full protection of the buried steel pipeline was 17 mA. East Side – MM 71.1 This section covers the 30‐in buried steel transmission main on at Channel 5 Bridge. The bridge is a box girder design with a hollow space where the transmission main is located. After the steel transmission main exits the bridge, the pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 170 feet. A post‐mounted test station was installed at the transition, and 2 magnesium anodes were installed on this section of steel pipeline. Another test station was installed at the bridge with leads to the pipeline inside the bridge.

22

Request for Proposal EXHIBIT A

The test station at the transition was found and tested. The PSP of the steel pipe was ‐186 mV CSE and that of the ductile iron was ‐233 mV CSE. The test station at the bridge was found, and tests indicate that the wire connections to the pipe are broken withine th bridge. However, tests made at the other station were sufficient to assess CP. These test results indicate that the buried section of steel pipe does not have adequate CP and that electrical isolation is weak at the transition to ductile iron pipe. The cathodic current requirement for CP of the buried steel pipeline was 55 mA. Channel 2 West Side – MM 72.6 This section covers the 30‐in buried steel transmission main on Craig Key at Channel 2 Bridge. The pipeline leaves the bridge on the Bay side of US 1 and crosses the highway to the Ocean side at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 231 feet before transitioning to ductile iron pipe. A post‐mounted test station was installed at the transition, which was made at a buried insulated flange. A total of 4 magnesium anodes were installed on this section of steel pipeline. Another magnesium anode was installed on the ductile iron pipe at the insulated flange. In 2017, the test station at the transition was found and tested. The test box was broken off the post and was replaced by the FKAA. The PSP of the steel pipeline was ‐527 mV CSE and thate of th ductile iron was ‐519 mV CSE. These test results indicate that the buried steel pipeline does not have adequate CP and that electrical isolation may be weak at the transition to ductile iron pipe. The cathodic current requirement for CP of the buried steel pipeline was 200 mA. The FKAA recently discovered a corrosion leak in the steel pipe where it passed through the bridge abutment and replaced a short (20 feet) section of the pipe. New test leads and 3 new magnesium anodes were installed while the excavation was open and the pipe was exposed. The new wires from the pipe and anodes had been terminated at a new flush‐mounted test station at the abutment. The new leads were tested, and the PSP was ‐497 mV CSE, consistent with the results of tests made at the transition test station. The anodes were tested and found to be non‐functional. It is possible that the anodes or their wires were damaged during backfilling, or that the anodes were backfilled with flowable fill, rock or some other unfavorable material. East Side – MM 73.0 This section covers the 30‐in buried steel transmission main on at Channel 2 Bridge. The pipeline is on the Bay side of US 1 at this location. There has been no CP work on the 24‐in buried steel transmission main at this location since it was last tested and found protected in 1998. In 2017, an old ‘Flush Fink’ thermoplastic test station was found near the abutment. Inspection of the exposed pipe showed that old test wires were attached to it. However, the wires were cut off a short distance from the pipe and were not functional. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐372 mV CSE, which indicates that the buried section of steel pipe does not have adequate CP. The cathodic current requirement of the pipe was 100 mA, which suggests that the buried steel pipeline has limited length and is electrically isolated. Electronic location of the pipe indicated that the transition or some other form of electrical isolation occurs 189 feet from the bridge and at the edge of the parking area. 23

Request for Proposal EXHIBIT A

Lignumvitae Channel West Side – MM 77.6 This section covers the 30‐in steel transmission main on Lower Matecumbe Key at the bridge over Lignumvitae Channel. The pipeline is on the Bay side of US 1 at this location. CP work was completed on the pipeline during Phase 1 and Phase 2 CP Improvements. Although the projects were completed by the same construction contractor, the commissioning reports for the 2 projects differ on some points regarding the pipeline. Based on study of the reports, the probable configuration of the pipeline and history of work is summarized as follows: The steel pipeline adjacent to the bridge is buried for a length of 27 feet before transitioning to ductile iron pipe, which continues for 154 feet to a flanged joint on the east side of VV N158. Steel pipe continues from that flanged joint through the vault to another Dresser coupling 64 feet west of VV N158. The 18‐in steel main is mechanically connected in the vault and has an insulated flange at the wye to electrically isolate the 18‐in main from the 30‐in main. The 18‐in main on Lower Matecumbe Key is protected with an impressed current system. During Phase 1, a single magnesium anode was installed on the easterly 27 feet of steel pipe along with a test station at the coupling. A total of 6 magnesium anodes were installed on buried steel pipe just east of the vault, and 1 magnesium anode was installed west of the vault. During Phase 2, it was recognized that the buried flange east of VV N 158 would require installation of a flange insulating kit to achieve CP of the buried steel near the vault. However, flange insulation was not pursued due to perceived risks associated with excavation of the pipe in the steep embankment near the vault. In 2017, the post‐mounted test station 27 feet from the bridge was found and tested. The PSP of the steel was ‐823 mV CSE and that of the ductile iron was ‐708 mV, suggesting that CP is marginal for the buried steel pipe and that it is electrically isolated. The cathodic current requirement for full CP of the buried steel pipe was 30 mA. The post‐mounted test station at VV N158 was also found and tested. The leads marked “30‐in DI Wye” had a PSP of ‐753 mV CSE, and probably represent the steel main on the east side of the vault. The test leads marked “18‐in Steel” were non‐functional; the wire connections may have been made in the vault and may be broken. A test station for the 18‐in steel main on the Ocean side of US 1 was checked and had a PSP of ‐934, indicating adequate CP of the 18‐in steel main by the impressed current system. The post‐mounted test station at the transition west of VV N158 was also found and tested. The leads marked “30‐in Steel” had a PSP of ‐522 mV CSE, indicating that CP is not adequate for buried steel pipe. The leads marked “30‐in DI” had a PSP of ‐269 mV CSE and indicate electrical isolation from the steel pipe. The cathodic current requirement for CP of the buried steel pipe was approximately 300 mA, which seems high and may reflect poor quality coating on the buried steel pipe around the valve vault. East Side – MM 77.8 This section covers the 30‐in steel transmission main on Indian Key at the bridge over Lignumvitae Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 17 feet on before transitioning to ductile iron pipe. A post‐mounted test station was installed at the transition, and 3 magnesium anodes were installed on this section of steel pipe. In 2017, the test station was found and tested. The PSP of the steel pipe at the bridge was ‐49 mV CSE, and that of the ductile iron pipe was ‐36 mV CSE. These values seemed unusually low, so the integrity of the leads to steel pipe was verified by repeating the test with direct contact to the exposed pipe on the

24 Request for Proposal EXHIBIT A bridge, and the values were the same. The value of the PSP indicates that the buried section of steel pipe does not have adequate CP. The cathodic current requirement was approximately 240 mA, which seems very high for the short length of the buried steel pipeline. Electronic location of the pipe traced it to the location of the test station, which is 18 feet east of the abutment and suggests that the steel pipe is electrically isolated at that point. Tests verified that the flexible coupling on the exposed pipe was not highly conductive to the pipe on the bridge. It seems possible that the buried transmission main on Indian Key might be constructed entirely of steel pipe. The following section provides additional evidence for this possibility. Indian Key Channel West Side – MM 77.6 This section covers the 30‐in buried steel transmission main on Indian Key at the bridge over Indian Key Channel. The pipeline is on the Bay side of US 1 at this location. Records indicate that there has been no CP work on the pipeline at this location since it wasd last teste and found protected in 1998. In 2017, a newer post‐mounted test station in good condition was found behind the guardrail near the abutment. The test station had 2 blue wires, and tests confirmed that the wires were electrically connected to the exposed steel pipe on the island eside of th flexible coupling and presumably to the buried steel pipe. The PSP of the test wires was ‐120 mV CSE, which is a low value and not indicative of adequate CP for buried steel pipe. The cathodic current requirement of the buried steel pipe was 423 mA. Electronic location of the pipe using the test station wires traced it to a point 661 feet from the bridge and at the west edge of a large asphalt patch in the bike path. The indicated location has some form of electrical isolation in the pipeline, such as a flexible coupling or transition coupling. The length of Indian Key is approximately 1,400 feet between bridges, and steel pipeline was electronically traced for nearly half of that distance. Considering the low elevation and narrow width of the key, it seems possible that steel pipe might have been used for construction of all the transmission main on Indian Key. East Side – MM 78.4 This section covers the 30‐in buried steel transmission main on Indian Key Fill at the bridge over Indian Key Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 22 feet before transitioning to ductile iron pipe. An existing test station was replaced with a flush‐ mounted test station, and 3 magnesium anodes were installed on this section of steel pipe. In 2017, the test station was not found and was presumed destroyed. Test wires were found on the ground surface and were not continuous with wires that were attached to the pipe, so the wires were severed somewhere along their length. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐853 mV CSE, which indicates that CP is adequate, but barely, on the buried steel pipeline. As discussed in the following section, there is a possibility that the transmission main on Indian Key Fill may be constructed entirely from steel pipe.

25

Request for Proposal EXHIBIT A

Tea Table Key Channel West Side – MM 79.2 This section covers the 30‐in buried steel transmission main on Indian Key Fill at the bridge over Tea Table Key Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that 2 magnesium anodes installed on the pipeline, and an existing test station was replaced with a flush‐mounted test station. The location of the transition to ductile iron pipe was not indicated. In 2017, inspection of the site revealed broken pipe test wires and an anode wire in a saw cut in the shotcrete surfacing near the bridge abutment. The test station was apparently destroyed. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐590 mV CSE, which indicates that the buried steel pipe does not have adequate CP. The cathodic current requirement of the buried steel pipe was 100 mA. Electronic location of the pipe using the test station wires traced it to a point 48 feet from the bridge. The trace continued beyond that point but results were not as clear. It seems possible that the transmission main on Indian Key Fill may be constructed entirely of steel pipe. The length of the key is approximately 2,000 feet and a total of 709 feet of steel pipeline was indicated by electronic location. Because the island is fill at a low elevation, steel pipe with a few flexible couplings might have been used for construction of the transmission main. Confirmation of the pipe material on Indian Key Fill is needed so that CP can be provided if the pipeline is steel. East Side – MM 79.3 This section covers the 30‐in steel transmission main on Tea Table Key at the bridge over Tea Table Key Channel. The pipeline crosses US 1 at this location. The westerly portion of the steel pipeline is on the Bay side of US 1, and the easterly portion is on the Ocean side. The CP Phase 1 redline drawings show that the pipeline had 3 magnesium anodes installed, and an existing test station was replaced with a flush‐mounted test station. The location of the transition to ductile iron pipe was not indicated. In 2017, the test station was not found and appeared to have been destroyed. Severed test wires were found on the ground surface near new guardrail, and only one of leads to the pipe was functional. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐305 mV CSE, which indicates that the buried steel pipeline does not have adequate CP. The cathodic current requirement of the buried steel pipeline was 227 mA. Electronic location of the pipeline traced it to a point 600 feet from the bridge and included a crossing of US 1. The point at which the trace ended is probably a transition coupling or a flexible coupling that has insulating qualities. Tea Table Relief West Side – MM 79.7 This section covers the 30‐in steel transmission main on Tea Table Key at the bridge over Tea Table Relief. The pipeline is on the Ocean side of US 1 at this location. Records indicate that there has been no CP or other corrosion control work on the pipeline at this location since it was last considered in 1998. The steel transmission main is embedded in a concrete thrust block at the end of the bridge. In 2017, using direct contact to the exposed steel pipe outside the thrust block, the PSP was ‐364 mV CSE. This value indicates that the pipe is neither protected by CP nor fully passivated (i.e., made immune to corrosion) by embedment in the concrete. The condition is not significant unless there is buried steel

26 Request for Proposal EXHIBIT A pipe outside of the thrust block. If there is buried pipe, it would have increased risk of corrosion by galvanic action with the embedded pipe. To investigate the possibility of buried steel pipeline beyond the thrust block, the pipeline was electronically located using direct contact to the exposed steel pipe. Electronic location of the pipeline traced it to a point 260 feet from the thrust block. The point at which the trace ended is probably a transition coupling or a flexible coupling that has insulating qualities. The cathodic current requirement of the embedded and buried steel pipeline was greater than 825 mA, the maximum available test current. This value seems high for the length of the pipeline and suggests that the embedded pipe may be bare steel. Further investigation is recommended to develop a better understanding of pipeline conditions at this location and determine the best approach to CP of the buried steel transmission main. Additionally, it seems possible that the transmission main on Tea Table Key may be constructed entirely from steel pipe. Part of the key appears to be a fill area approximately 4,300 feet in length. A total of 860 feet of steel pipeline was indicated by electronic location. Because the island is fill at a low elevation, steel pipe with flexible couplings might have been used for construction of the transmission main. Confirmation of the pipe material on Tea Table Key is needed so that CP can be provided if the pipeline is steel. East Side – MM 79.8 This section covers the 30‐in steel transmission main on at the bridge over Tea Table Relief. The pipeline is on the Ocean side of US 1 at this location. Records indicate that there has been no CP or other corrosion control work on the pipeline at this location since it was last considered in 1998. The east side of the Teatable Relief crossing is configured like the west side described above. However, the steel transmission main extends from the concrete thrust block to VV N140/NB142, located 430 feet west of the bridge. The 18‐in steel transmission main is also present in N140/NB142, and it receives CP from the impressed current CP system constructed for this purpose on Upper Matecumbe Key. The nearest rectifier station to Teatable Relief is located near VV N140/NB142, on the Bay side of US 1. The 30‐in steel transmission main crosses USe 1 near th rectifier station. Using direct contact to the exposed steel pipe outside the thrust block, the PSP was ‐806 mV CSE. This value indicated that the pipe was receiving some degree of CP from the impressed current system on Upper Matecumbe Key. For confirmation, the current output of ythe nearb rectifier station was temporarily increased from 1,500 to 3,500 mA. The resulting PSP of the exposed pipe was ‐828 mV CSE, reflecting increased cathodic polarization from the increased current output at the rectifier station. Further tests were not possible, because test stations that were constructed at VV N140/NB142 during the Phase 2 CP Improvements could not be found. The test stations were presumed buried or destroyed. Whale Harbor Channel West Side – MM 83.9 This section covers the 30‐in steel transmission main on Upper Matecumbe Key at the bridge over Whale Harbor Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length of 874 feet before transitioning to ductile iron pipe at VV NB134. A total of 12 magnesium anodes were installed on this section of steel pipeline, and they were installed in 2 groups of 6 anodes. An existing post‐mounted test station was replaced with a flush‐mounted station at the vault. Another existing post‐mount at the bridge was left in place.

27

Request for Proposal EXHIBIT A

In 2017, both test stations were found and tested, along with another test station installed during Phase 2 CP Improvements on the 18‐in steel transmission main at VV NB134. The PSP of the steel pipeline at the vault was ‐863 mV CSE and that of the ductile iron was ‐867 mV CSE. These test results indicate that the buried section of steel pipeline has adequate CP and that electrical isolation is weak at the transition to ductile iron pipe. The PSP of the 18‐in steel main was ‐895 mV CSE and that of the connected vault piping was ‐672 mV CSE. The test station at the bridge was an old ‘Big Fink’ thermoplastic post‐mount station. Tests showed that one of the 2 pipe leads was non‐functional, and the anode was consumed. Using the functional test lead, the PSP of the 30‐in steel main at the bridge was ‐859 mV CSE, indicating that CP is adequate. However, the anodes are probably near the end of their useful life. East Side – MM 84.0 This section covers the 30‐in steel transmission main on at the bridge over Whale Harbor Channel. The pipeline is on the Bay side of US 1 at this location. The CP Phase 1 redline drawings show that the steel pipeline adjacent to the bridge has a buried length that exceeds 845 feet. A flush‐mounted test station was installed 845 feet from the bridge and adjacent to VV N130. This vault is under the westbound travel lane of US 1 and requires an FDOT permit for traffic control to access it for more than 5 minutes. The 30‐in transmission main continues east of the vault under the travel lanes of the highway for at least 3,500 feet. The location of the transition from steel to ductile iron pipe, if any, is unknown. The CP Phase 1 redline drawings also show that total of 6 magnesium anodes were installed on this section of steel pipeline, and they were installed in 2 groups of 3 anodes. One group of anodes was installed at VV N130, and the wire connections to the pipe were made in the vault. The wire connections of the test station were also made in the vault. Another existing post‐mount at the bridge was left in place. In 2017, both test stations were found and tested. The test station at the bridge was an old ‘Big Fink’ thermoplastic post‐mount station. Tests showed that both pipe leads were functional, and that the connected anode was consumed. Using the test leads, the PSP of the pipeline at the bridge was ‐583 mV CSE, indicating that CP was not adequate. The PSPs of the 2 test leads at the test station near VV N130 were ‐570 and ‐606 mV CSE. These results indicate that CP was not adequate for buried steel pipeline, and that one or both wire connections were deteriorated. A cathodic current requirement test was conducted using the test station at the bridge. A test current of 860 mA produced only a ‐15 mV change in PSP which was not adequate for CP. Additionally, no effect from the test current was seen at the test station near VV N130. The FKAA identified another old post‐mounted ‘Big Fink’ test station on the 30‐in transmission main approximately 3,100 feet east of the bridge and north of US 1. This test station had 2 pipe leads, and the PSP was ‐679 mV CSE. The leads were electronically traced to the pipeline in the westbound travel lane of US 1. It was not possible to safely trace the pipeline in US 1 due to traffic conditions. A cathodic current requirement test was conducted using the test station at 3,100 feet from the bridge. A test current of 2,550 mA produced only a ‐40 mV change in PSP which was not adequate for CP. Additionally, no effect from the test current was seen at the test station near VV N130 or at test points on the 18‐in steel transmission main further east. None of the test results provided any insights regarding the extent or condition of the 30‐in steel transmission main at this location. Additional investigation is needed to identify the location and extent of steel pipeline so that CP can be applied.

28

Request for Proposal EXHIBIT A

Snake Creek MM 85.6 – 85.8 The 30‐in steel transmission main has a subaqueous crossing of Snake Creek between Windley Key and . The pipeline is protected by an impressed current system, primarily the rectifier station at MM 85.4, that was constructed during the Phase 2 CP Improvements. The FKAA monitors the impressed current systems. The rectifier station at MM 85.4 was checked to verify that it was operating. No other tests were conducted at this location. Tavernier Creek West Side – MM 90.8 This section covers the 36‐in steel transmission main on Plantation Key on the west side of the bridge over Tavernier Creek. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that 2 magnesium anodes were installed on this section of steel pipeline, and an existing test station at the bridge was replaced with a post‐mounted station. The length of the steel pipeline and the location of the transition to ductile iron pipe were not indicated. Another existing post‐mount test station further west of the bridge was left in place. In 2017, both test stations were found and tested. Using the test station wires, the PSP of the 30‐in steel main at the bridge was ‐1014 mV CSE. These test results indicate that the buried steel pipeline has adequate CP. The post‐mounted test station was located 211 feet from the bridge. The cover and terminal board were missing, and the test wires were loose on the post. (The FKAA plans to replace the missing items and terminate the wires.) The two black test leads had a PSP of ‐760 mV CSE and that of the two white leads was ‐501 mV CSE. A single white wire to an old anode was also present. Tests showed that the black test leads were continuous with the test leads at the bridge test station and were therefore connected to the steel transmission main. The test results indicate marginal CP for the buried steel pipeline at this location. The white test leads were not identified as to their connection or purpose. Electronic location of the steel pipeline using the test station wires traced it a point 326 feet from the bridge. This is the indicated location of the transition. There were no signs of a test station at the transition. East Side – MM 91.0 This section covers the 36‐in steel transmission main on Tavernier Key at the east side of bridge over Tavernier Creek. The pipeline is on the Ocean side of US 1 at this location. The CP Phase 1 redline drawings show that the pipeline adjacent to the bridge has a buried length of 783 feet before transitioning to ductile iron pipe. A total of 16 magnesium anodes were installed on this section of steel pipeline, and they were installed in 2 groups of 8 anodes. An existing post‐mounted test station at the bridge was replaced with a similar station. Another flush‐mounted test station was installed at the transition. In 2017, both test stations were found and tested. At the bridge test station, the PSP of the steel main pipeline was ‐1191 mV CSE. At the transition test station, the PSP of the 30‐in steel main was ‐1322 mV CSE and that of the ductile iron was ‐511 mV CSE. These test results indicate that the buried steel pipeline has adequate CP and is electrically isolated from the ductile iron pipe.

29

Request for Proposal EXHIBIT A

Adams Waterway West Side – MM 103.4 This section covers the 36‐in steel transmission main on Key Largo at the west side of the bridge over Adams Waterway (also known as Adams Cut). The pipeline is in the median of US 1 at this location. No CP work was done at this location during Phase 1 CP Improvements. In Phase 2, the 30‐in steel transmission main from the bridge to VV NB 50 was bonded (electrically connected by wires) to the 18‐ in steel main at the vault. The bond wires consist of 2 No. 2 AWG insulated copper cables that are connected between a test station on the 18‐in main and a test station on the 30‐in main. The bond wires are direct buried outside the vault. The length of the connected, buried steel main is 737 feet. The 18‐in steel transmission main receives CP from the impressed current CP system constructed for this purpose on Key Largo. The nearest rectifier station to Adams Waterway is located at MM 104.1, on the Ocean side of US 1. Both test stations near the vault were found by visual inspection. They had test leads to the steel and ductile iron pipe at transitions buried outside the vault. The PSP of the 30‐in steel pipeline was ‐884 mV CSE, and that of the ductile iron was ‐690 mV CSE. The PSP of the 18‐in steel main was ‐912 mV CSE, and that of the ductile iron was ‐647 mV CSE. These test results indicate that both the 18‐ and 30‐in steel transmission mains have adequate CP and are electrically isolated from the ductile iron pipe at the vault. There was no evidence of a test station near the bridge. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐920 mV CSE. These test results indicate that the buried section of steel pipe has adequate CP. The 30‐in steel pipeline was electronically located from the bridge to the vault to confirm that it was electrically continuous to the vault and not beyond it. No CP work is required at this location except for continued monitoring and maintenance of CP facilities. East Side – MM 103.4 This section covers the 36‐in steel transmission main on Key Largo at the east side of the bridge over Adams Waterway (also known as Adams Cut). The pipeline is in the median of US 1 at this location. CP work was done at this location during both Phase 1 and Phase 2 CP Improvements. The CP Phase 1 redline drawings show that the pipeline adjacent to the bridge has a buried length of 308 feet before transitioning to ductile iron pipe at VV N45/NB44. The transition occurs at a buried insulated flange on the west side of the vault. A post‐mounted test station was installed at the insulated flange, and 9 magnesium anodes were installed on this section of pipeline. In Phase 2, the 30‐in steel pipeline from the bridge to VV N45/NB44 was bonded (electrically connected by wires) to the 18‐in steel transmission main at the vault. The bond wires consist of 2 No. 2 AWG insulated copper cables that are connected between a test station on the 18‐in main and a test station on the 30‐in main. The bond wires are direct buried outside the vault. The 18‐in steel transmission main receives CP from the impressed current CP system constructed for this purpose on Key Largo. The nearest rectifier station to Adams Waterway is located at MM 104.1, on the Ocean side of US 1. In 2017, both test stations near the vault were found by visual inspection. They had test leads to the steel and ductile iron pipe at transitions buried outside the vault. The PSP of the 30‐in steel pipeline was ‐996 mV CSE, and that of the ductile iron was ‐694 mV CSE. The PSP of the 18‐in steel main was ‐954 mV CSE, and that of the ductile iron was ‐647 mV CSE. These test results indicate that both the 18‐ and 30 Request for Proposal EXHIBIT A

30‐in steel transmission mains have adequate CP and are electrically isolated, although somewhat weakly, from the ductile iron pipe at the vault. The bond wire was temporarily disconnected to measure the bond current, which was 55 mA returned to the 18‐in from the 30‐in pipeline. With the bond temporarily disconnected, the 30‐in steel pipeline at the vault had a PSP of ‐916 mV CSE and that of the ductile iron was ‐773 mV CSE. The bond was reconnected after the tests were completed. At the bridge, there were test wires attached to the pipe and they went into the earth, but no test station was found. Using direct contact to the exposed steel pipe on the bridge, the PSP was ‐900 mV CSE. These test results indicate that the buried section of steel pipe has adequate CP. The 30‐in steel pipeline was electronically located from the bridge to the vault to confirm that it was electrically continuous to the vault and not beyond it. No CP work is required at this location except for continued monitoring and maintenance of CP facilities.

31 Request for Proposal EXHIBIT A

Appendix B Key West Request for Proposal EXHIBIT A

Figure B-1 Cathodic Protection Features of the FKAA Steel Transmission Main in Key West

CP Features include test stations and rectifier stations shown as icons. Colors indicate status of CP: Green is Adequate. Yellow is Marginal. Red is Inadequate.

Request for Proposal EXHIBIT A

Figure B-2 Cathodic Protection Test Results: 18-in Steel Transmission Main in Key West

-1400

-1300

-1200

-1100 Eisenhower CPS White CPS Bike Path TS Palm CPS -1000 1007 Eaton TS mV CSE

- Post -900 Office Peacon CPS CPS Adequate CP -850 Marginal or Inadequate CP -800 Soil Potential, - to - 620 Eaton TS

Pipe -700 Fleming TS 400A Eaton TS & recent leak -600 CP ON

Fleming TS CP OFF -500 Courthouse TS CPS CP Rectifier Station TS Test Station -400 KWPS

0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 -300 Distance from Key West Pump Station, feet Request for Proposal EXHIBIT A Table B-1 Cathodic Protection Test Results FKAA Steel Transmission Mains - Key West

Date: 7/11 - 7/17/2017 PSP PSP Mile Distance Wire Wire On Off Delta Marker (feet) Description TS Type Pipe Material Size Color (mV) (mV) (mV) Comments 12" Ductile Iron #8 Green -446 -280 -166 Off= TS anode disconn. 12" Ductile 0.00 0 TS at KWPS Fence Post Iron #12 Green -446 -280 -166 12" Steel #8 Blue -493 -468 -25 0.01 75 TS at Courthouse Lot Flush 12" Steel #12 Blue -493 -468 -25

0.05 240 Valve Courthouse Curb None 12" Steel - - -560 -545 -15 18" Steel #8 Blue -769 -722 -47 TS at Fleming & 0.11 558 Whitehead Flush 18" Steel #12 Blue -769 -722 -47 18" Steel #8 Blue -1380 -810 -570 Output 2750 mA at 3.4V 0.17 893 Rectifier at USPS Junction Box 18" Steel #12 Blue -1311 -740 -571 Suspect bad pipe conn 18" Steel #8 Blue -769 -711 -58 0.21 1093 TS at 400A Eaton Junction Box 18" Steel #12 Blue -769 -711 -58 18" Steel #8 Blue -822 -752 -70 0.43 2290 TS at 620 Eaton Flush 18" Steel #12 Blue -822 -752 -70 18" Steel #8 Blue -1162 -930 -232 Output 2900 mA at 5.5V 0.50 2659 Rectifier at Peacon Ln Junction Box 18" Steel #12 Blue -1162 -930 -232 18" Steel #8 Blue -1092 -1030 -62 0.73 3839 TS at 1007 Eaton Flush 18" Steel #12 Blue -1092 -1030 -62 18" Steel #8 Blue -1185 -1116 -69 Output 2370 mA at 3.4V Rectifier at Eaton & 0.93 4919 White Junction Box 18" Steel #12 Blue -1185 -1116 -69 18" Steel #8 Blue -1129 -1083 -46 1.13 5979 TS at Bike Path Flush 18" Steel #12 Blue -1129 -1083 -46 18" Steel #8 Blue -1140 -1120 -20 Output 460 mA at 2.4V Rectifier at Eisenhower 1.32 6949 & Palm Junction Box 18" Steel #12 Blue -1140 -1120 -20 18" Steel #8 Blue -1147 -1106 -41 Output 220 mA at 2.2V Rectifier at Eisenhower 1.51 7999 & N. Roosevelt Junction Box 18" Steel #12 Blue -1147 -1106 -41

1.53 8099 Connection to PVC None ------

Page 1 of 1 Request for Proposal EXHIBIT A Request for Proposal EXHIBIT A Request for Proposal EXHIBIT A Request for Proposal EXHIBIT A

Appendix C Marathon Request for Proposal EXHIBIT A Table C-1 Cathodic Protection Test Results FKAA Steel Transmission Mains - Marathon Knight's Key

Date: 6/19 & 7/20/2017

PSP PSP Mile Wire On Off Delta Marker Description TS Type Pipe Material Size Wire Color (mV) (mV) (mV) Comments #12 Black -1210 -980 -230 Interrupt CPS MM 47.0 47.1 TS near Pigeon Key Tap Post Mount 18" Steel #12 Black -1210 -980 -230 Ignore red = old anodes #8 Blue -1060 -899 -161 See note 24" Steel #12 Blue -1060 -899 -161 #8 Green -736 -705 -31 47.0 TS at Valve Vault S78 Flush 24" Ductile Iron #12 Green -736 -705 -31 #12 Black -1055 -880 -175 47.0 TS at Valve Vault S78 Flush 18" Steel #12 Black -1055 -880 -175 #8 Blue -1280 -920 -360 47.0 Rectifier at Knight's Key Junction Box 18" Steel #12 Blue -1280 -920 -360 #10 Blue -1218 -924 -294 See note 46.7 TS at 7-Mile Bridge Post Mount 24" Steel #10 Blue -1218 -924 -294

Note: Connection of CPS to 24" steel occurs by 'shorted' 18" insulated flange at wye in valve vault

Page 1 of 1 Request for Proposal EXHIBIT A Table C-2 Cathodic Protection Test Results FKAA Steel Transmission Mains - Marathon

Date: 7/17 - 7/21/2017

PSP PSP Mile Wire On Off Delta Marker Description TS Type Pipe Material Size Wire Color (mV) (mV) (mV) Comments #8 Blue -932 - - 18" Steel #12 Blue -869 - - 18" deactivated #8 Green -896 - - 53.0 TS South of VV S40 Flush 30" Steel #12 Green -896 - - Has mag anodes from Ph. 1 & 2

#8 Black w/ 2 -1075 - - 30" Steel #12 wire ties -1075 - - Vault side of insulated joint?

#8 Black w/ 1 -1203 - - 53.0 TS West of VV S40 Big Fink Post 30" Steel #12 wire tie -1203 - - Has mag anodes Ph. 1 & 2 30" Steel #8 Blue -1369 - - Steel to E; mag anodes Ph. 1 & 2 52.7 TS at Design Source Flush 30" Ductile Iron #8 Green -679 - - DI to west; CSE at US1 #12 Blue -1064 -1038 -26 Interrupt CPS MM 52.2 52.6 TS Median at Burger King Flush 18" Steel #8 Blue -1064 -1038 -26 #12 Blue -1107 -1075 -32 Interrupt CPS MM 52.2 52.3 TS N side US1 at Sheriff Bldg Flush 18" Steel #12 Blue -1107 -1075 -32 #8 Blue -1112 -1068 -44 52.2 Rectifier at 100th St. Picnic Junction Box 18" Steel #12 Blue -1112 -1068 -44 Output 2120 mA at 3.2V #8 Black - - - 51.8 TS at Airport parking lot Post Mount 18" Steel #12 Black - - - #8 Black -1089 - - Ignore Ignore red= old anodes 51.3 TS N of US 1 at 85th St. Post Mount 18" Steel #12 Black -1089 - - #8 Black -1075 - - Ignore red= old anodes 51.1 TS N of US 1 & E of 76th St. Post Mount 18" Steel #12 Black -1075 - - #8 Black -1049 - - Ignore red= old anodes 51.0 TS NE side of Aviation Blvd Post Mount 18" Steel #12 Black -1049 - - #8 Blue -960 -905 -55 Interrupt CPS MM 49.5 & 50.9 #12 Blue -960 -905 -55 East end of steel crossing US 1 30" Steel #8 Black - - - Bond to 18"; ON current=400 mA #8 Green -662 -642 -20 Interrupt CPS MM 49.5 & 50.9 51.0 Bond TS at Aviation Blvd Flush 30" Ductile Iron #12 Green -662 -642 -20 #12 Black -648 - - 51.0 TS Aviation Blvd-Casing only Flush Steel Casing #12 Black -648 - - #12 Blue -999 - - West end of steel crossing US 1 30" Steel #8 Blue -999 - - #12 Green -612 - - 50.9 TS in Tarpon Harbor driveway Flush 30" Ductile Iron #8 Green -612 - - #12 Blue -1203 -1080 -123 Output 2350 mA at 3.2V 50.9 Rectifier at 70th St. Junction Box 18" Steel #8 Blue -1203 -1080 -123 #12 Blue -993 -962 -31 Interrupt CPS MM 50.9 & 52.2 50.6 TS at E side of 63rd Ct. Flush 18" Steel #8 Blue -993 -962 -31 #12 Blue -984 -954 -30 Interrupt CPS MM 49.5 & 50.9 50.1 TS at Gulfside Village Plaza Flush 18" Steel #8 Blue -984 -954 -30 #12 Blue - - - 49.8 TS W of 52nd St. in Bike Path Flush 18" Steel #8 Blue - - - #8 Blue -1123 -1113 -10 Output 2320 mA at 3.2V 49.5 Rectifier at 46th St. Dive Shop Junction Box 18" Steel #12 Blue -1123 -1113 -10 #8 Black - - - Centennial Bank 49.5 TS W of 46th St. Bike Path Post Mount 18" Steel #12 Black - - - #8 Blue - - - Barracuda Grill 49.3 TS W of 43rd St. Bike Path Flush 18" Steel #12 Blue - - - #8 Blue - - - CNL; thought destroyed 49.0 TS at Border Patrol Flush 18" Steel #12 Blue - - -

Page 1 of 2 Request for Proposal EXHIBIT A Table C-2 Cathodic Protection Test Results FKAA Steel Transmission Mains - Marathon

Date: 7/17 - 7/21/2017

PSP PSP Mile Wire On Off Delta Marker Description TS Type Pipe Material Size Wire Color (mV) (mV) (mV) Comments

30" DIP #8 Green - - - No access; active construction Upstream #12 Green - - - #8 Blue - - - 24" Steel #12 Blue - - -

TS by Valve S-56 (Discharge 30" DIP #8 Green - - - 48.7 Side of Pump Station) Flush Downstream #12 Green - - -

30" DIP #8 Green - - - No access; active construction Upstream #12 Green - - - Wires to DI at intersection #8 Blue - - - 24" Steel #12 Blue - - -

TS W of Valve (Suction Side of 30" DIP #8 Green - - - No access; active construction 48.7 Pump Station) Flush Downstream #12 Green - - - Wires to DI at intersection

18" DIP #8 Blue - - - No access; active construction RO Line #12 Blue - - -

30" DIP #8 Green - - - 48.7 TS W of FKAA Driveway Flush Downstream #12 Green - - - #8 Blue -782 -674 -108 Found off; tripped sec. breaker 48.7 Rectifier at 33rd St.Cust. Serv. Junction Box 18" Steel #12 Blue -782 -674 -108 Output ON 4000 mA at 2.8V #8 Blue -841 -729 -112 After 2 days ON 48.7 Rectifier at 33rd St.Cust. Serv. Junction Box 18" Steel #12 Blue -841 -729 -112 #12 Blue -721 -675 -46 Interrupt CPS at MM 47.4 & 48.7 48.3 TS at Turtle Hospital driveway Flush 18" Steel #8 Blue -721 -675 -46 #12 Black -505 -497 -8 Interrupt CPS at MM 47.4 & 48.7 48.0 TS Bike Path 50' E Hyatt Drive Flush 18" Steel #12 Black -505 -497 -8 Ignore red= old anodes #12 Blue -640 -634 -6 Interrupt CPS at MM 48.7 47.7 TS across US1 from 15th St. Flush 18" Steel #8 Blue -640 -634 -6 #12 Blue - - - CNL; thought destroyed 47.55 TS Flush 18" Steel #8 Blue - - - #8 Blue -680 -574 -106 Output found 990 mA at 2.0V 47.4 Rectifier at 11th St.7-Mi Marina Junction Box 18" Steel #12 Blue -680 -574 -106 Adjusted to 4620 mA at 2.6V #12 Black -614 -575 -39 Interrupt CPS at MM 47.4 & 48.7 47.3 TS Bay Side Bike Path Post Mount 18" Steel #12 Black -614 -575 -39 #12 Black -624 -575 -49 w/ 260 mA temporary CP 47.3 TS Bay Side Bike Path Post Mount 18" Steel #12 Black -770 -575 -195 w/ 4380 mA temporary CP 47.1 End of main (cut and capped) None 18" Steel - - - - -

Page 2 of 2 Request for Proposal EXHIBIT A

Appendix D MM 121 - 122

Request for Proposal EXHIBIT A Table D-1 Cathodic Protection Test Results FKAA Steel Transmission Mains - MM 121 - 122

Date: 7/31/2017 Test Point Description Pipe-to-Soil Potential (mV) Delta GPS & Comments ON OFF (mV) -mV CSE -mV CSE . MM 121.06 Post test station - anode and transition Lat 25.354043; Long -80.4589 Blue #10 ( Steel ) -910 -795 -115 300' N of MM 121; Old No. 7A12 Blue #10 ( Steel ) -910 -795 -115 Blue #10 ( Steel ) -910 -795 -115 Blue #10 ( Steel ) -910 -795 -115 Green #12 ( Ductile Iron ) -562 -503 -59 Black #12 ( Newer Anode) - -1376 - connected to blue; 30 mA total Black #12 ( Old Anode) - -1140 - connected to blue Black #12 ( Old Anode) - -1132 - connected to blue MM 121.15 Post test station - anode Lat 25.355427; Long -80.4593 Blue #10 ( Steel ) -1066 -866 -200 800' N of MM 121; Old No. 7A11 Blue #10 ( Steel ) -1066 -866 -200 Black #12 ( Anode) - -1700 - connected to blue; 26 mA Black #12 ( Anode) - -1170 - connected to blue; 1 mA Black #12 ( Anode) - -1177 - connected to blue; 1 mA Yellow # 12 ( Old Anode ) - -1070 - disconnected MM 121.49 Post test station - anode Lat 25.36315; Long -80.4609 Blue #10 ( Steel ) -982 -950 -32 2580' N of MM 121; Old No. 7A6 Blue #10 ( Steel ) -970 -930 -40 suspect bad wire connection Black #12 ( Anode) - -1388 - connected to blue Black #12 ( Anode) - -1745 - connected to blue Black #12 ( Anode) - -1200 - connected to blue; 0 mA total MM 121.55 Post test station - anode Lat 25.361064; Long -80.4604 Blue #10 ( Steel ) -1006 -866 -140 2900' N of MM 121; Old No. 7A5 Blue #10 ( Steel ) -1006 -866 -140 Black #12 ( Anode) - -1316 - connected to blue Black #12 ( Anode) - -1765 - connected to blue; 39 mA total MM 121.62 Post test station - anode Lat 25.362044; Long -80.4606 Blue #10 ( Steel ) -1000 -850 -150 3260' N of MM 121; Old No. 7A4 Blue #10 ( Steel ) -1000 -850 -150 Black #12 ( Anode) - -1635 - connected to blue Black #12 ( Anode) - -1268 - connected to blue; 24 mA total MM 121.70 Post test station - anode Lat 25.36315; Long -80.4609 Blue #10 ( Steel ) -1056 -850 -206 3670' N of MM 121; Old No. 7A3 Blue #10 ( Steel ) -1058 -850 -208 Black #12 ( Anode) - -1740 - connected to blue Black #12 ( Anode) - -1550 - connected to blue; 24 mA total Black #12 ( Anode) - -1192 - disconnected Yellow # 12 ( Old Anode ) - -1339 - disconnected MM 121.79 Post test station - anode & transition Lat 25.364509; Long -80.4612 Blue #10 ( Steel ) -846 -825 -21 4170' N of MM 121; Old No. 7A1 Blue #10 ( Steel ) -846 -825 -21 Blue #10 ( Anode) - -1571 - connected to blue steel; 24 mA Blue #10 ( Steel ) -844 -821 -23 Blue #10 ( Steel ) -847 -825 -22 Blue #10 ( Steel ) -847 -825 -22 Green #12 ( Ductile Iron ) -114 -150 36 suspect bad wire connection Green #12 ( Ductile Iron ) -842 -821 -21 shorted to steel

Page 1 of 1 Request for Proposal EXHIBIT A

Appendix E Recommended Improvements

Request for Proposal EXHIBIT A TABLE E-1 RECOMMENDED IMPROVEMENTS FKAA STEEL TRANSMISSION MAINS CATHODIC PROTECTION 2017

Impressed Test Station No. of Galvanic Anodes Current Electrical Isolation Electrical Continuity Verify Flex Flange Length of BRIDGE CROSSINGS Type T Type I 1 2 3 4 5 9 10 Station Coupling Repair Test Repair Steel Main Cow Key Channel - West 1 1 Cow Key Channel - East 1 1 1 1 Boca Chica Channel - West 1 1 1 1 1 Boca Chica Channel - East 1 2 1 1 1 1 Rockland Channel - West Rockland Channel - East 1 1 1 1 Shark Channel - West 1 1 Shark Channel - East 1 1 1 1 Saddle Bunch No. 5 Ch.- West 1 1 1 Saddle Bunch No. 5 Ch.- East 1 1 Saddle Bunch No. 4 Ch.- West 1 1 Saddle Bunch No. 4 Ch.- East 1 1 Saddle Bunch No. 3 Ch.- West 1 1 Saddle Bunch No. 3 Ch.- East 1 1 Saddle Bunch No. 2 Ch.- West 1 Saddle Bunch No. 2 Ch.- East 1 Lower Sugarloaf Ch. - West 1 1 1 Lower Sugarloaf Ch. - East 1 1 Harris Channel - West 1 1 Harris Channel - East 1 1 1 Harris Gap Channel - West 1 Harris Gap Channel - East 1 North Harris Channel - West 1 North Harris Channel - East 1 Park Channel - West 1 1 1 1 1 1 Park Channel - East 1 Bow Channel - West 1 1 1 Bow Channel - East 1 1 Kemp Channel - West 1 1 Kemp Channel - East 1 1 Niles Channel - West 1 Niles Channel - East 1 Torch Ramrod Channel - West 1 1 Torch Ramrod Channel - East 1 1 Torch Channel - West 1 1 Torch Channel - East 1 2 South Pine Ch.- West 1 1 South Pine Ch.- East 1 1 North Pine Ch.- West 1 North Pine Ch.- East Spanish Harbor Ch. - West 1 Spanish Harbor Ch. - East 1 Bahia Honda Channel - West 1 5 Bahia Honda Channel - East 1 2 1 2 Ohio Bahia Honda Ch. - West 1 1 Ohio Bahia Honda Ch. - East 1 1 1 Ohio Missouri Channel - West 1 2 1 1 Ohio Missouri Channel - East 1 1 Missouri Little Duck Ch. - West 1 1 1 2 1 Missouri Little Duck Ch. - East 1 1 Seven Mile Bridge - West Seven Mile Bridge - East Vaca Cut Channel - West Vaca Cut Channel - East 1 1 Tom's Harbor Channel - West Tom's Harbor Channel - East 1 1 Tom's Harbor Cut - West 1 1 1 2 Tom's Harbor Cut - East 1 2 2 1 1 Long Key Channel - West 2 5 Long Key Channel - East 1 Channel No. 5 - West 1 1 Channel No. 5 - East 1 1 Channel No. 2 - West 1 Channel No. 2 - East 1 1 Lignumvitae Channel - West 1 1 1 Lignumvitae Channel - East 1 1 1 Indian Key Channel - West 1 3 1 Indian Key Channel - East 1 1 1 1 Tea Table Key Ch. - West 1 1 1 Tea Table Key Ch. - East 1 2 1 Tea Table Relief - West 1 1 1 1 Tea Table Relief - East 1 2 Whale Harbor Ch. - West 1 Whale Harbor Ch. - East 1 1 1 1 2 1 Snake Creek - West Snake Creek - East Tavernier Creek - West 1 1 Tavernier Creek - East Adams Waterway - West Adams Waterway - East 1

TOTAL BRIDGE CROSSINGS 29 53 5 14 17 12 24 0 9 2 1 3 6 6

Page 1 of 1 Request for Proposal EXHIBIT A TABLE E-2 RECOMMENDED IMPROVEMENTS FKAA STEEL TRANSMISSION MAINS CATHODIC PROTECTION 2017

Impressed Test Station No. of Galvanic Anodes Current Electrical Isolation Electrical Continuity Determine Flex Flange Length of OTHER FACILITIES Type T Type I 1 2 3 4 5 9 10 Station Coupling Repair Test Repair Steel Main KEY WEST 3 4 3 1 MARATHON 2 MM 121-122 7 2 ROAD CROSSINGS East of Boca Chica Ch. / US 1 1 2 1 East Lower Sugarloaf Ch./US 1 2 1 West of Bow Channel / US 1 2 1 West of Niles Channel / US 1 1 Middle Torch Road 2 East of Bahia Honda / US 1 WB 2 1 Grassy Key / US 1 1 Windley Key / US 1 2 1 West of Tavernier Ck / US 1 EB 2 1 Subtotal Road Crossings 1 10 0 2 0 1 0 5 0 1 0 0 0 0 0 TOTAL OTHER FACILITIES 5 26 0 11 0 2 5 10 0 2 3 0 1 0 0

Page 1of 1 Request for Proposal EXHIBIT A

Appendix F Construction Cost Opinion

Request for Proposal EXHIBIT A

TABLE F-1 CONSTRUCTION COST OPINION FKAA STEEL TRANSMISSION MAINS CP 2017 Type T Type I IC Insulated Test Test Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic System-3 Insulated Flg Continuity Continuity Subtotal Energizing Item Station Station Anode -1 Anode -2 Anode -3 Anode -4 Anode -5 Anode -9 Anode -10 Anode Flex Cplg Repair Check Repair $ & Testing $ Total $

Unit EA EA EA EA EA EA EA EA EA EA EA EA EA EA $ 2,538 3,038 2,367 3,375 4,235 4,621 5,954 11,303 11,681 27,818 6,902 3,156 900 3,631 10%

BRIDGE CROSSINGS Cow Key Channel - West Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Cow Key Channel - East Qty 1 1 1 1 $ 3,038 4,621 900 3,631 12,189 1,219 13,408 Boca Chica Channel - West Qty 1 1 1 1 1 $ 3,038 3,375 5,954 900 3,631 16,898 1,690 18,588 Boca Chica Channel - East Qty 1 2 1 1 1 1 $ 2,538 6,075 4,235 5,954 900 3,631 23,333 2,333 25,667 Rockland Channel - West Qty $ 0 0 0 Rockland Channel - East Qty 1 1 1 1 $ 2,538 3,038 3,375 6,902 15,853 1,585 17,438 Shark Channel - West Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Shark Channel - East Qty 1 1 1 1 $ 3,038 5,954 11,681 3,156 23,829 2,383 26,212 Saddle Bunch No. 5 Ch.- West Qty 1 1 1 $ 2,538 3,038 5,954 11,530 1,153 12,683 Saddle Bunch No. 5 Ch.- East Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Saddle Bunch No. 4 Ch.- West Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Saddle Bunch No. 4 Ch.- East Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Saddle Bunch No. 3 Ch.- West Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Saddle Bunch No. 3 Ch.- East Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Saddle Bunch No. 2 Ch.- West Qty 1 $ 2,538 2,538 254 2,792 Saddle Bunch No. 2 Ch.- East Qty 1 $ 2,538 2,538 254 2,792 Lower Sugarloaf Ch. - West Qty 1 1 1 $ 2,538 3,038 3,375 8,951 895 9,846 Lower Sugarloaf Ch. - East Qty 1 1 $ 2,538 4,621 7,158 716 7,874 Harris Channel - West Qty 1 1 $ 3,038 4,235 7,273 727 8,000 Harris Channel - East Qty 1 1 1 $ 2,538 3,038 4,621 10,196 1,020 11,216 Harris Gap Channel - West Qty 1 $ 3,375 3,375 338 3,713 Harris Gap Channel - East Qty 1 $ 4,621 4,621 462 5,083 North Harris Channel - West Qty 1 $ 4,621 4,621 462 5,083 North Harris Channel - East Qty 1 $ 3,375 3,375 338 3,713 Park Channel - West Qty 1 1 1 1 1 $ 2,538 3,038 11,681 900 3,631 21,788 2,179 23,966 Park Channel - East Qty 1

Page 1 of 4 Request for Proposal EXHIBIT A

TABLE F-1 CONSTRUCTION COST OPINION FKAA STEEL TRANSMISSION MAINS CP 2017 Type T Type I IC Insulated Test Test Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic System-3 Insulated Flg Continuity Continuity Subtotal Energizing Item Station Station Anode -1 Anode -2 Anode -3 Anode -4 Anode -5 Anode -9 Anode -10 Anode Flex Cplg Repair Check Repair $ & Testing $ Total $

Unit EA EA EA EA EA EA EA EA EA EA EA EA EA EA $ 2,538 3,038 2,367 3,375 4,235 4,621 5,954 11,303 11,681 27,818 6,902 3,156 900 3,631 10%

$ 2,538 2,538 254 2,792 Bow Channel - West Qty 1 1 1 $ 2,538 3,375 450 6,363 636 7,000 Bow Channel - East Qty 1 1 $ 3,038 3,375 6,413 641 7,054 Kemp Channel - West Qty 1 1 $ 3,038 3,375 6,413 641 7,054 Kemp Channel - East Qty 1 1 $ 3,038 4,235 7,273 727 8,000 Niles Channel - West Qty 1 $ 5,954 5,954 595 6,550 Niles Channel - East Qty 1 $ 3,038 3,038 304 3,341 Torch Ramrod Channel - West Qty 1 1 $ 3,038 3,375 6,413 641 7,054 Torch Ramrod Channel - East Qty 1 1 $ 3,038 3,375 6,413 641 7,054 Torch Channel - West Qty 1 1 $ 3,038 2,367 5,404 540 5,945 Torch Channel - East Qty 1 2 $ 3,038 6,751 9,788 979 10,767 South Pine Ch.- West Qty 1 1 $ 3,038 3,375 6,413 641 7,054 South Pine Ch.- East Qty 1 1 $ 3,038 2,367 5,404 540 5,945 North Pine Ch.- West Qty 1 $ 2,367 2,367 237 2,603 North Pine Ch.- East Qty $ 0 0 0 Spanish Harbor Ch. - West Qty 1 $ 5,954 5,954 595 6,550 Spanish Harbor Ch. - East Qty 1 $ 4,235 4,235 423 4,658 Bahia Honda Channel - West Qty 1 5 $ 2,538 58,405 60,943 6,094 67,037 Bahia Honda Channel - East Qty 1 2 1 2 $ 2,538 6,075 5,954 23,362 37,929 3,793 41,722 Ohio Bahia Honda Ch. - West Qty 1 1 $ 3,038 2,367 5,404 540 5,945 Ohio Bahia Honda Ch. - East Qty 1 1 $ 3,038 4,235 7,273 727 8,000 Ohio Missouri Channel - West Qty 1 2 1 $ 4,235 9,241 900 14,377 1,438 15,814 Ohio Missouri Channel - East Qty 1 $ 4,235 4,235 423 4,658 Missouri Little Duck Ch. - West Qty 1 1 1 2 $ 3,038 4,235 4,621 11,908 23,802 2,380 26,182 Missouri Little Duck Ch. - East Qty 1 1 $ 3,038 3,375 6,413 641 7,054 Seven Mile Bridge - West Qty $ 0 0 0 Seven Mile Bridge - East Qty

Page 2 of 4 Request for Proposal EXHIBIT A

TABLE F-1 CONSTRUCTION COST OPINION FKAA STEEL TRANSMISSION MAINS CP 2017 Type T Type I IC Insulated Test Test Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic System-3 Insulated Flg Continuity Continuity Subtotal Energizing Item Station Station Anode -1 Anode -2 Anode -3 Anode -4 Anode -5 Anode -9 Anode -10 Anode Flex Cplg Repair Check Repair $ & Testing $ Total $

Unit EA EA EA EA EA EA EA EA EA EA EA EA EA EA $ 2,538 3,038 2,367 3,375 4,235 4,621 5,954 11,303 11,681 27,818 6,902 3,156 900 3,631 10%

$ 0 0 0 Vaca Cut Channel - West Qty $ 0 0 0 Vaca Cut Channel - East Qty 1 1 $ 3,038 4,235 7,273 727 8,000 Tom's Harbor Channel - West Qty $ 0 0 0 Tom's Harbor Channel - East Qty 1 1 $ 2,538 3,038 5,575 558 6,133 Tom's Harbor Cut - West Qty 1 1 1 2 $ 2,538 3,038 4,235 11,908 21,719 2,172 23,890 Tom's Harbor Cut - East Qty 1 2 2 1 $ 2,538 6,075 11,908 3,156 23,677 2,368 26,045 Long Key Channel - West Qty 2 5 $ 6,075 29,771 35,846 3,585 39,431 Long Key Channel - East Qty 1 $ 3,038 3,038 304 3,341 Channel No. 5 - West Qty 1 1 $ 3,038 5,954 8,992 899 9,891 Channel No. 5 - East Qty 1 1 $ 3,038 5,954 8,992 899 9,891 Channel No. 2 - West Qty 1 $ 5,954 5,954 595 6,550 Channel No. 2 - East Qty 1 1 $ 3,038 4,235 7,273 727 8,000 Lignumvitae Channel - West Qty 1 1 1 $ 2,538 2,367 5,954 10,859 1,086 11,944 Lignumvitae Channel - East Qty 1 1 $ 4,235 5,954 10,189 1,019 11,208 Indian Key Channel - West Qty 1 3 $ 2,538 13,862 16,400 1,640 18,040 Indian Key Channel - East Qty 1 1 1 $ 2,538 3,038 4,235 9,810 981 10,791 Tea Table Key Ch. - West Qty 1 1 $ 3,038 4,235 7,273 727 8,000 Tea Table Key Ch. - East Qty 1 2 $ 3,038 8,470 11,508 1,151 12,658 Tea Table Relief - West Qty 1 1 1 $ 2,538 3,038 27,818 33,394 3,339 36,733 Tea Table Relief - East Qty 1 2 $ 2,538 6,075 8,613 861 9,474 Whale Harbor Ch. - West Qty 1 $ 5,954 5,954 595 6,550 Whale Harbor Ch. - East Qty 1 1 1 1 2 $ 3,038 4,235 27,818 3,156 7,262 45,508 4,551 50,059 Snake Creek - West Qty $ 0 0 0 Snake Creek - East Qty $ 0 0 0 Tavernier Creek - West Qty 1 1 $ 3,038 4,621 7,658 766 8,424 Tavernier Creek - East Qty

Page 3 of 4 Request for Proposal EXHIBIT A

TABLE F-1 CONSTRUCTION COST OPINION FKAA STEEL TRANSMISSION MAINS CP 2017 Type T Type I IC Insulated Test Test Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic Galvanic System-3 Insulated Flg Continuity Continuity Subtotal Energizing Item Station Station Anode -1 Anode -2 Anode -3 Anode -4 Anode -5 Anode -9 Anode -10 Anode Flex Cplg Repair Check Repair $ & Testing $ Total $

Unit EA EA EA EA EA EA EA EA EA EA EA EA EA EA $ 2,538 3,038 2,367 3,375 4,235 4,621 5,954 11,303 11,681 27,818 6,902 3,156 900 3,631 10%

$ 0 0 0 Adams Waterway - West Qty $ 0 0 0 Adams Waterway - East Qty 1 $ 2,538 2,538 254 2,792

Subtotal Bridge Crossings Qty 29 53 5 14 17 12 24 0 9 2 1 3 6 6 $ 73,596 160,996 11,833 47,255 71,994 55,448 142,899 0 105,129 55,637 6,902 9,468 4,952 21,785 767,893 76,789 844,682 Contingency at 20% $ 168,936 TOTAL BRIDGE CROSSINGS $ 1,013,618

KEY WEST Qty 3 4 3 1 $ 7,613 12,151 20,706 900 41,370 4,137 45,507 Special excavation & traffic 20,000 Contingency at 20% $ 13,101 TOTAL KEY WEST 78,609

MARATHON Qty 2 $ 11,908 11,908 1,191 13,099 Contingency at 20% $ 2,620 TOTAL MARATHON 15,719

MM 121-122 Qty 7 2 $ 23,627 11,908 35,536 3,554 39,089 Contingency at 20% $ 7,818 TOTAL MM 121-122 46,907

ROAD CROSSINGS East of Boca Chica Ch. / US 1 Qty 1 2 1 $ 2,538 6,075 4,621 13,234 1,323 14,557 East of Lower Sugarloaf Ch. Qty 2 1 $ 6,075 11,303 17,378 1,738 19,116 West of Bow Channel / US 1 Qty 1 $ 11,303 11,303 1,130 12,433 West of Niles Channel / US 1 Qty 1 $ 11,303 11,303 1,130 12,433 Middle Torch Road Qty 2 1 $ 6,751 11,303 18,053 1,805 19,859 East of Bahia Honda Ch / US 1 Qty 2 1 $ 6,075 11,303 17,378 1,738 19,116 Grassy Key / US 1 Qty 1 $ 27,818 27,818 2,782 30,600 Windley Key / US 1 Qty 2 1 $ 6,075 11,303 17,378 1,738 19,116 West of Tavernier Ck / US 1 EB Qty 2 1 $ 6,075 5,954 12,029 1,203 13,232 Subtotal Road Crossings Qty 1 10 0 2 0 1 1 6 0 1 0 0 0 0 $ 2,538 30,377 0 6,751 0 4,621 5,954 67,815 0 27,818 0 0 0 0 0 14,587 160,461 Contingency at 20% $ 32,092 TOTAL ROAD CROSSINGS $ 192,553

GRAND TOTAL 1,347,406

Page 4 of 4 Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS Type T Test Station

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1516 2 No. 12 AWG wire FT 100 0.5 46 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Lug connectors EA 2 0.8 2

Subtotal 467 1516 Shipping @ 10% 47 Keys 2018 @ 25% 128 379 Total Material Cost $642 Notes: Total Labor Cost $1,895 Total Cost $2,538

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS Type I or F Test Station

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1820 2 No. 12 AWG wire FT 50 0.5 23 3 No. 8 AWG wire FT 50 0.6 30 4 Thermite Welder EA 1 76 76 5 Thermite Weld Material EA 4 1.5 6 6 Thermite Weld Cap EA 4 38 152 7 Lug connectors EA 4 0.8 3

Subtotal 555 1820 Shipping @ 10% 55 Keys 2018 @ 25% 153 455 Total Material Cost $763 Notes: Total Labor Cost $2,275 Total Cost $3,038

Cost Estimate.xlsx TS Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 1-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 1 227 227 1516 2 No. 10 AWG header cable FT 0 0.5 0 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 1 1.5 2 5 Thermite Weld Cap EA 1 38 38 6 Splice kit EA 0 45 0 7 Wire slice EA 0 2.3 0

Subtotal 343 1516 Shipping @ 10% 34 Keys 2018 @ 25% 94 379 Total Material Cost $471 Notes: Total Labor Cost $1,895 Total Cost $2,367

Cost Estimate.xlsx Galv-1A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 2-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 2 227 455 1895 2 No. 10 AWG header cable FT 50 0.5 27 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Splice kit EA 2 45 91 7 Wire slice EA 2 2.3 5

Subtotal 732 1895 Shipping @ 10% 73 Keys 2018 @ 25% 201 474 Total Material Cost $1,006 Notes: Total Labor Cost $2,369 Total Cost $3,375

Cost Estimate.xlsx Galv-2A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 3-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 3 227 682 2275 2 No. 10 AWG header cable FT 60 0.5 32 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Splice kit EA 3 45 136 7 Wire slice EA 3 2.3 7

Subtotal 1012 2275 Shipping @ 10% 101 Keys 2018 @ 25% 278 569 Total Material Cost $1,392 Notes: Total Labor Cost $2,843 Total Cost $4,235

Cost Estimate.xlsx Galv-3A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 4-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 4 227 910 2275 2 No. 10 AWG header cable FT 70 0.5 37 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Splice kit EA 4 45 182 7 Wire slice EA 4 2.3 9

Subtotal 1293 2275 Shipping @ 10% 129 Keys 2018 @ 25% 355 569 Total Material Cost $1,777 Notes: Total Labor Cost $2,843 Total Cost $4,621

Cost Estimate.xlsx Galv-4A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 5-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 5 227 1137 3033 2 No. 10 AWG header cable FT 80 0.5 42 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Splice kit EA 5 45 227 7 Wire slice EA 5 2.3 11

Subtotal 1573 3033 Shipping @ 10% 157 Keys 2018 @ 25% 433 758 Total Material Cost $2,163 Notes: Total Labor Cost $3,791 Total Cost $5,954

Cost Estimate.xlsx Galv-5A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 9-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 9 227 2047 6065 2 No. 10 AWG header cable FT 140 0.5 74 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Splice kit EA 9 45 409 7 Wire slice EA 9 2.3 20

Subtotal 2706 6065 Shipping @ 10% 271 Keys 2018 @ 25% 744 1516 Total Material Cost $3,721 Notes: Total Labor Cost $7,582 Total Cost $11,303

Cost Estimate.xlsx Galv-9A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 10-Anode Galvanic Ground bed

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 32# Hi-potential magnesium EA 10 227 2275 6065 2 No. 10 AWG header cable FT 140 0.5 74 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Splice kit EA 10 45 455 7 Wire slice EA 10 2.3 23

Subtotal 2981 6065 Shipping @ 10% 298 Keys 2018 @ 25% 820 1516 Total Material Cost $4,099 Notes: Total Labor Cost $7,582 Total Cost $11,681

Cost Estimate.xlsx Galv-10A Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS 3-Anode Impressed Current Ground bed and Utility Rectifier

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1516 2 No. 12 AWG wire FT 100 0.5 45 0 3 Thermite Welder EA 1 76 76 0 4 Thermite Weld Material EA 4 1.5 6 0 5 Thermite Weld Cap EA 4 38 152 0 6 Lug connector EA 2 0.8 2 0 7 Rectifier EA 1 2275 2275 1516 8 Duriron anodes EA 3 379 1137 1365 9 Junction Box EA 1 303 303 379 10 No. 4 AWG wire FT 100 0.8 76 758 11 Power Pole EA 1 4246 4246 1516 12 AC meter EA 1 303 303 227 13 Power Box EA 1 341 341 227 Hole Depth FT 40 76 4599 Subtotal 9227 12105 Shipping @ 10% 923 Keys 2018 @ 25% 2537 3026 Total Material Cost $12,687 Notes: Total Labor Cost $15,131 Total Cost $27,818

Cost Estimate.xlsx Rect-Util-3 Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS Electrical Continuity Testing

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Continuity Testing EA 1 0 720

Subtotal 0 720 Shipping @ 10% 0 Keys 2018 @ 25% 0 180 Total Material Cost $0 Notes: Total Labor Cost $900 Total Cost $900

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS Electrical Continuity Repair

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 3 #2 AWG wire jumper cable EA 1.0 5 5 2729 4 Thermite Welder EA 1.0 76 76 5 Thermite Weld Material EA 2.0 2 3 6 Thermite Weld Cap EA 2.0 38 76

Subtotal 159 2729 Shipping @ 10% 16 Keys 2018 @ 25% 44 682 Total Material Cost $219 Notes: Total Labor Cost $3,412 Total Cost $3,631

Cost Estimate.xlsx Continuity Request for Proposal EXHIBIT A

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS Insulated Flexible Coupling

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Insulating Coupling EA 1 379 379 4549 2 Standard Coupling FT 1 303 303 3 #2/ #12 AWG wire jumper cable EA 1 8 8 4 Thermite Welder EA 1 76 76 5 Thermite Weld Material EA 3 1.5 5 6 Thermite Weld Cap EA 3 38 114

Subtotal 884 4549 Shipping @ 10% 88 Keys 2018 @ 25% 243 1137 Total Material Cost $1,216 Notes: Total Labor Cost $5,686 Total Cost $6,902

UNIT COST ESTIMATE CATHODIC PROTECTION ITEMS Insulated Flange Repair

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Insulating bolt sleeves w/ Insulating washers EA 1 227 227 2275

Subtotal 227 2275 Shipping @ 10% 23 Keys 2018 @ 25% 63 569 Total Material Cost $313 Notes: Total Labor Cost $2,843 Total Cost $3,156

Cost Estimate.xlsx Insul Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

EXHIBIT B

Technical Memorandum, FKAA Cathodic Protection – Restoration of Facilities Damaged or Destroyed by Hurricane Irma Request for Proposal EXHIBIT B

TECHNICAL MEMORANDUM FKAA Cathodic Protection - Restoration of Facilities Damaged or Destroyed by Hurricane Irma

PREPARED FOR: Florida Keys Aqueduct Authority PREPARED BY: CH2M DATE: January 29, 2018 PROJECT NUMBER: 694334.03.30.03

This Technical Memorandum summarizes restoration needs for cathodic protection (CP) systems operated by the Florida Keys Aqueduct Authority (FKAA). A spreadsheet with a detailed list of CP facilities damaged by Hurricane Irma and cost estimate for restoration was developed under FKAA Project 1511-17. The spreadsheet is a separate, editable Excel file that is transmitted with this report. Background The FKAA maintains an extensive array of CP systems for corrosion control of buried steel water transmission mains and submerged interior surfaces of steel water storage tanks. The CP systems are located throughout the Florida Keys and have proven essential for reliable delivery of fresh water in the corrosive marine environment of the Keys. CP is an electrochemical method of reducing corrosion of a metal surface in contact with earth or water. The FKAA’s CP facilities include galvanic anodes and impressed current systems. Impressed current systems use rectifiers to convert utility AC electrical power to DC electricity for CP. All CP facilities include ‘test stations’ that are essential for monitoring and adjusting system performance. Test stations include wires connected to buried pipe for electrical contact by workers at ground level. The FKAA operates its CP systems on a continuous basis and periodically monitors each system. Monitoring by FKAA forces is done at least annually, and engineering evaluations of the CP facilities are contracted when the need arises. The most recent monitoring of the FKAA CP facilities was done in late 2016, and an engineering evaluation by CH2M was completed in August 2017. These activities provided a thorough understanding of the condition of the FKAA’s CP facilities prior to the arrival of Hurricane Irma in September 2017. Condition Assessment In December 2017, the FKAA surveyed its CP systems to assess conditions after Hurricane Irma. Results indicated that extensive damage and destruction of many facilities had occurred due to storm surge, high winds, and debris cleanup by heavy equipment. This was not surprising because CP facilities are located outdoors and at ground level. Many test stations and rectifiers were destroyed, missing, or damaged beyond repair. CH2M is familiar with the FKAA’s CP facilities from extensive prior work including design and services during construction. CH2M reviewed the results of the FKAA’s field survey and developed a list of restoration needs by location. A total of 237 items were identified, and they were distributed over 35 islands covering 108 miles along the Florida Keys. The restoration needs were grouped in 5 categories of work: 2 types of rectifier replacement; 1 rectifier repair; and 2 types of test station replacement.

CH2M Request for Proposal EXHIBIT B FKAA CATHODIC PROTECTION - RESTORATION OF FACILITIES DAMAGED OR DESTROYED BY HURRICANE IRMA Restoration Cost Estimate CH2M prepared cost estimates for the 5 types of restoration required for CP facilities that were damaged or destroyed by Hurricane Irma. Unit costs used in the estimate were essentially the same as those used for prior CP construction contracts completed by the FKAA and known to be representative of expected costs. Unit cost estimates for the 5 types of work are attached to this report. The cost estimates for restoration of CP facilities were presented using the same spreadsheet format used for other FKAA facilities damaged by Hurricane Irma. However, all CP work was listed on a single worksheet because of the CP facilities are widely distributed throughout the Keys and the types of restoration work are similar in all affected areas. The contents of the spreadsheet columns for CP facilities are described below. Column Title Description A - B Various Not Used C Name of damage/facility Type of CP facility D Address 1 US Highway 1 Mile Marker E Address 2 Not Used F City Island/Key or Location G - L Various As Stated M Approx. Cost ($) Per spreadsheet formula N - R Various Not Used S Asset identifier Restoration Task No. (1-5) T - U Various As Stated V Man-Hours Not Used W Labor Cost per Unit ($) CH2M Estimate X Equipment cost per Unit ($) CH2M Estimate Y Material/ODC/Sub cost Per Unit ($) ODC Commissioning at 10% of Total Unit Cost Z Total Unit Cost ($) Per spreadsheet formula AA Total cost ($) Per spreadsheet formula AB - AD Various Not Used

As shown in the spreadsheet, the total estimated restoration cost for the FKAA CP facilities damaged or destroyed by Hurricane Irma is $2,139,179. This includes an allowance for necessary commissioning and testing, estimated at 10 percent of the associated cost of labor and equipment. We appreciate the opportunity to assist the FKAA in this matter. Please contact us if there are questions or if additional information is required.

2 CH2M Request for Proposal EXHIBIT B UNIT COST ESTIMATE RESTORE CATHODIC PROTECTION - TASK 1 Tank (Interior) Rectifier Replacement Including AC Service

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1516 2 No. 12 AWG wire FT 100 0.5 45 0 3 Lug connector EA 2 0.8 2 0 4 Rectifier EA 1 2275 2275 1516 5 Power Box EA 1 341 341 227 Subtotal 2928 3260 Shipping @ 10% 293 Keys 2018 @ 0% 0 0 Total Material Cost $3,221 Total Labor Cost $3,260 Total Cost $6,481

UNIT COST ESTIMATE RESTORE CATHODIC PROTECTION - TASK 2 4-Wire (Type I or F) Test Station Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1820 2 No. 12 AWG wire FT 50 0.5 23 3 No. 8 AWG wire FT 50 0.6 30 4 Thermite Welder EA 1 76 76 5 Thermite Weld Material EA 4 1.5 6 6 Thermite Weld Cap EA 4 38 152 7 Lug connectors EA 4 0.8 3

Subtotal 555 1820 Shipping @ 10% 55 Keys 2018 @ 0% 0 0 Total Material Cost $610 Total Labor Cost $1,820 Total Cost $2,430

UNIT COST ESTIMATE RESTORE CATHODIC PROTECTION - TASK 3 Rectifier Oil Replacement Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Transformer Oil EA 1 102 102 300 Subtotal 102 300 Shipping @ 10% 10 Keys 2018 @ 0% 0 0 Total Material Cost $112 Total Labor Cost $300 Total Cost $412

Hurricane Restoration of CP Page 1 of 2 Request for Proposal EXHIBIT B UNIT COST ESTIMATE RESTORE CATHODIC PROTECTION - TASK 4 Pipeline Rectifier Replacement Including AC Service

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1516 2 No. 12 AWG wire FT 100 0.5 45 0 3 Thermite Welder EA 1 76 76 0 4 Thermite Weld Material EA 4 1.5 6 0 5 Thermite Weld Cap EA 4 38 152 0 6 Lug connector EA 2 0.8 2 0 7 Rectifier EA 1 2275 2275 1516 8 Junction Box EA 1 303 303 379 9 No. 4 AWG wire FT 100 0.8 76 758 10 Power Pole EA 1 4246 4246 1516 11 AC Meter EA 1 303 303 227 12 Power Box EA 1 341 341 227 13 AC Service Replacement EA 1 0 0 3000 Subtotal 8090 9141 Shipping @ 10% 809 Keys 2018 @ 0% 0 0 Total Material Cost $8,899 Total Labor Cost $9,141 Total Cost $18,040

UNIT COST ESTIMATE RESTORE CATHODIC PROTECTION - TASK 5 2-Wire (Type T) Test Station

Item Unit Total cost Labor cost No. Description Unit Quantity Cost $ per Item $ per item 1 Test station with terminal board EA 1 265 265 1516 2 No. 12 AWG wire FT 100 0.5 46 3 Thermite Welder EA 1 76 76 4 Thermite Weld Material EA 2 1.5 3 5 Thermite Weld Cap EA 2 38 76 6 Lug connectors EA 2 0.8 2

Subtotal 467 1516 Shipping @ 10% 47 Keys 2018 @ 0% 0 0 Total Material Cost $514 Total Labor Cost $1,516 Total Cost $2,030

Hurricane Restoration of CP Page 2 of 2 Damage Inventory

Applicant Point of Contact Email: ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes Rectifier for tank internal CP 0.0 Key West FL 33040 24.554170 ‐81.804322 Corroded by wind‐driven rain Hurricane 7,129 1 1 EA 3,260 3,221 648 7,129 7,129 Rectifier for tank internal CP 4.3 Stock Island FL 33040 24.575001 ‐81.748795 Corroded by wind‐driven rain Hurricane 7,129 1 1 EA 3,260 3,221 648 7,129 7,129 Test station, 4‐wire 7.0 Boca Chica FL 33040 24.578846 ‐81.707844 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier for buried pipeline 7.0 Boca Chica FL 33040 24.578871 ‐81.707528 Water in oil compartment Hurricane 453 3 1 EA 300 112 41 453 453 Rectifier for buried pipeline 8.0 Boca Chica FL 33040 24.579832 ‐81.701244 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire 8.5 Boca Chica FL 33040 24.580719 ‐81.695633 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 9.0 Boca Chica FL 33040 24.581513 ‐81.690521 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 9.8 Rockland FL 33040 24.591081 ‐81.669617 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 9.8 Rockland FL 33040 24.591344 ‐81.669044 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 9.8 Rockland FL 33040 24.593680 ‐81.663901 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 9.8 Big Coppitt FL 33040 24.596116 ‐81.658570 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 9.8 Big Coppitt FL 33040 24.593383 ‐81.664481 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 10.2 Big Coppitt FL 33040 24.596116 ‐81.658570 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 10.9 Big Coppitt FL 33040 24.600013 ‐81.650439 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire 11.1 Shark FL 33040 24.601902 ‐81.646202 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier for buried pipeline 11.2 Shark FL 33040 24.602213 ‐81.645301 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire, at vault 11.4 Shark FL 33040 24.602915 ‐81.644108 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 11.4 Shark FL 33040 24.602805 ‐81.644269 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2‐wire, at bridge 11.8 Saddlebunch No. 5 W FL 33040 24.606047 ‐81.637472 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 11.8 Saddlebunch No. 5 W FL 33040 24.606767 ‐81.635797 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 12.6 Saddlebunch No. 5 E FL 33040 24.612997 ‐81.622375 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 13.1 Saddlebunch No. 4 E FL 33040 24.614400 ‐81.619465 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 13.1 Saddlebunch No. 4 E FL 33040 24.614686 ‐81.618844 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2‐wire, at bridge 13.2 Saddlebunch No. 3 W FL 33040 24.615801 ‐81.616427 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 14.2 Saddlebunch No. 3 E FL 33040 24.622174 ‐81.604237 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 14.2 Saddlebunch No. 3 E FL 33040 24.622553 ‐81.603628 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 14.4 Saddlebunch No. 2 W FL 33040 24.624290 ‐81.600739 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 14.6 Saddlebunch No. 2 E FL 33040 24.625623 ‐81.598630 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2‐wire, at bridge 14.7 Saddlebunch No. 1 W FL 33040 24.626586 ‐81.597055 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 14.8 Saddlebunch No. 1 W FL 33040 24.626986 ‐81.596417 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 15.2 Saddlebunch No. 1 E FL 33040 24.631827 ‐81.588551 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, at road crossing 15.4 Lower Sugarloaf FL 33040 24.634448 ‐81.584152 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 1 of 7 FKAA All Cathodic Protection Damage Inventory ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes Test station, 4‐wire, at transition 17.8 Park FL 33040 24.650600 ‐81.554972 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire, at transition 23.8 Summerland FL 33040 24.662162 ‐81.459589 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 24.0 Summerland FL 33040 24.662162 ‐81.459589 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier for buried pipeline 24.0 Summerland FL 33040 24.662085 ‐81.459031 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 24.2 Summerland FL 33040 24.662169 ‐81.456360 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 24.5 Summerland FL 33040 24.661796 ‐81.449888 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 24.7 Summerland FL 33040 24.661551 ‐81.446209 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 24.9 Summerland FL 33040 24.661568 ‐81.443293 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire, at insul. Flg. 25.0 Summerland FL 33040 24.661106 ‐81.442102 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 25.4 Summerland FL 33040 24.660917 ‐81.436875 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 25.4 Summerland FL 33040 24.660953 ‐81.436458 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2‐wire, at bridge 26.3 Ramrod FL 33040 24.660152 ‐81.422768 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 26.3 Ramrod FL 33040 24.660132 ‐81.422378 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier for buried pipeline 26.9 Ramrod FL 33040 24.660703 ‐81.413186 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire 27.0 Ramrod FL 33040 24.660931 ‐81.411282 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.0 Ramrod FL 33040 24.661032 ‐81.411319 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.0 Ramrod FL 33040 24.661046 ‐81.411307 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.0 Ramrod FL 33040 24.661111 ‐81.411055 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.0 Ramrod FL 33040 24.661098 ‐81.411058 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.0 Ramrod FL 33040 24.660978 ‐81.411012 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.3 Ramrod FL 33040 24.661844 ‐81.407971 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.3 Ramrod FL 33040 24.662091 ‐81.407567 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 27.3 Ramrod FL 33040 24.662063 ‐81.407625 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 27.6 Ramrod FL 33040 24.662805 ‐81.403692 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 27.7 Middle Torch FL 33040 24.663395 ‐81.401721 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 27.8 Middle Torch FL 33040 24.664031 ‐81.398626 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 27.8 Middle Torch FL 33040 24.664086 ‐81.398399 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 28.0 Middle Torch FL 33040 24.664250 ‐81.397657 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 28.1 Little Torch FL 33040 24.664782 ‐81.395139 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 28.6 Little Torch FL 33040 24.666691 ‐81.386384 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 28.8 Unnamed Fill FL 33040 24.667274 ‐81.383618 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 29.3 Unnamed Fill FL 33040 24.669187 ‐81.374187 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at transition 29.5 Big Pine FL 33040 24.669652 ‐81.371957 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 29.9 Big Pine FL 33040 24.669893 ‐81.370024 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 29.9 Big Pine FL 33040 24.669723 ‐81.368648 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 30.3 Big Pine FL 33040 24.669859 ‐81.362769 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 30.5 Big Pine FL 33040 24.669517 ‐81.356621 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 2 of 7 FKAA All Cathodic Protection Damage Inventory ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes Test station, 2‐wire 30.5 Big Pine FL 33040 24.669777 ‐81.357303 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 30.5 Big Pine FL 33040 24.669803 ‐81.357114 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 30.8 Big Pine FL 33040 24.669665 ‐81.351304 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 31.1 Big Pine FL 33040 24.669706 ‐81.348120 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 31.2 Big Pine FL 33040 24.669389 ‐81.346268 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 31.3 Big Pine FL 33040 24.667981 ‐81.342119 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 31.3 Big Pine FL 33040 24.667372 ‐81.341506 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 31.8 Big Pine FL 33040 24.662005 ‐81.339047 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 31.8 Big Pine FL 33040 24.656903 ‐81.336776 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 31.8 Big Pine FL 33040 24.650247 ‐81.333793 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 32.3 Big Pine FL 33040 24.656903 ‐81.336776 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 32.7 Big Pine FL 33040 24.650247 ‐81.333793 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 32.8 Big Pine FL 33040 24.648973 ‐81.332732 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire, at transition 32.8 Big Pine FL 33040 24.648978 ‐81.332683 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 32.8 Big Pine FL 33040 24.649035 ‐81.332758 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 33.0 Big Pine FL 33040 24.647945 ‐81.329698 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 33.6 Scout (Spanish Harbor) FL 33040 24.648935 ‐81.319219 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Rectifier for buried pipeline 34.0 Scout (W.Summerland) FL 33040 24.649385 ‐81.313703 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire, at transition 34.0 Scout (W.Summerland) FL 33040 24.649391 ‐81.315102 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 34.0 Scout (W.Summerland) FL 33040 24.649372 ‐81.315128 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire 34.2 Scout (W.Summerland) FL 33040 24.649781 ‐81.310993 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2‐wire 34.6 Scout (W.Summerland) FL 33040 24.652419 ‐81.304697 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Rectifier for buried pipeline 35.1 Scout (W.Summerland) FL 33040 24.655164 ‐81.299244 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire, at insul. Flg. 35.1 Scout (W.Summerland) FL 33040 24.654954 ‐81.300098 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at insul. Flg. 35.1 Scout (W.Summerland) FL 33040 24.654967 ‐81.300053 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire, near bridge 35.3 Scout (W.Summerland) FL 33040 24.656140 ‐81.297569 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 36.6 Bahia Honda FL 33040 24.659997 ‐81.275709 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4‐wire, at insul. Flg. 36.9 Bahia Honda FL 33040 24.660780 ‐81.272266 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at insul. Flg. 36.9 Bahia Honda FL 33040 25.163311 ‐82.148124 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 4‐wire, at casing 36.9 Bahia Honda FL 33040 24.660736 ‐81.272124 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 36.9 Bahia Honda FL 33040 24.661325 ‐81.270496 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 37.0 Bahia Honda FL 33040 24.661481 ‐81.270185 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 37.0 Bahia Honda FL 33040 24.661698 ‐81.269711 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 3 of 7 FKAA All Cathodic Protection Damage Inventory ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes Rectifier for buried pipeline 37.1 Bahia Honda FL 33040 24.661849 ‐81.269283 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 37.8 Bahia Honda FL 33040 24.665252 ‐81.261613 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 37.9 Bahia Honda FL 33040 24.666123 ‐81.259634 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 38.0 Bahia Honda FL 33040 24.666980 ‐81.257673 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 38.1 Bahia Honda FL 33040 24.667476 ‐81.256574 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier for buried pipeline 38.2 Bahia Honda FL 33040 24.668378 ‐81.254479 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4‐wire, at transition 38.2 Bahia Honda FL 33040 24.668978 ‐81.253593 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire, at transition 38.2 Bahia Honda FL 33040 24.668903 ‐81.253777 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4‐wire 39.0 Ohio FL 33040 24.673581 ‐81.243692 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station 39.2 Missouri FL 33040 24.673635 ‐81.243625 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station 39.4 Missouri FL 33040 24.675879 ‐81.240015 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station 39.5 Little Duck FL 33040 24.678182 ‐81.236312 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier for buried pipeline 47.4 Marathon FL 33040 24.708122 ‐81.113416 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844

Rectifier for tank internal CP 50.8 Marathon 69th St Dist. FL 33040 24.718389 ‐81.064939 Corroded by wind‐driven rain Hurricane 7,129 1 1 EA 3,260 3,221 648 7,129 7,129 Test station, 4 wire, at transition 53.0 Marathon FL 33040 24.730274 ‐81.030989 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 53.0 Marathon FL 33040 24.729949 ‐81.032624 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Marathon Vaca Cut Rectifier for tank internal CP 53.1 Dist. FL 33040 24.730693 ‐81.031626 Corroded by wind‐driven rain Hurricane 7,129 1 1 EA 3,260 3,221 648 7,129 7,129 Test station, 4 wire, at transition 53.4 Marathon FL 33040 24.731222 ‐81.025997 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Marathon Rectifier for tank internal CP 54.3 Dist. FL 33040 24.734501 ‐81.012792 Destroyed by storm surge Hurricane 7,129 1 1 EA 3,260 3,221 648 7,129 7,129 Test station, 4 wire, at transition 59.5 Grassy FL 33040 24.774542 ‐80.930633 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at casing 59.6 Grassy FL 33040 24.774828 ‐80.929833 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 59.7 Grassy FL 33040 24.775011 ‐80.928900 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 60.5 Grassy FL 33040 24.776586 ‐80.924744 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 60.5 Grassy FL 33040 24.777019 ‐80.923647 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire, at transition 60.8 Duck FL 33040 24.778894 ‐80.918264 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 61.4 Duck FL 33040 24.781430 ‐80.911231 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 61.7 Duck FL 33040 24.783706 ‐80.904778 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 63.1 Conch FL 33040 24.789642 ‐80.887908 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 63.1 Conch FL 33040 24.789664 ‐80.887861 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2‐wire, at bridge 63.1 Conch FL 33040 24.791064 ‐80.884436 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 4 of 7 FKAA All Cathodic Protection Damage Inventory ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes

Test station, 2‐wire, at bridge 65.6 Long FL 33040 24.803334 ‐80.850007 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 65.6 Long FL 33040 24.803334 ‐80.850007 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire, at vault 65.6 Long FL 33040 24.803336 ‐80.849991 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 65.9 Long FL 33040 24.804890 ‐80.845144 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 66.2 Long FL 33040 24.807025 ‐80.839197 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 66.8 Long FL 33040 24.809955 ‐80.830974 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 67.1 Long FL 33040 24.812947 ‐80.826784 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 67.3 Long FL 33040 24.815359 ‐80.824934 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 67.6 Long FL 33040 24.818713 ‐80.822354 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 67.9 Long FL 33040 24.821578 ‐80.819238 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 68.1 Long FL 33040 24.822321 ‐80.818318 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 68.5 Long FL 33040 24.826458 ‐80.812923 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2‐wire 68.8 Long FL 33040 24.830136 ‐80.808181 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 69.0 Long FL 33040 24.831713 ‐80.806131 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 69.4 Long FL 33040 24.835696 ‐80.800958 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2‐wire 69.9 Long FL 33040 24.837892 ‐80.797159 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire 69.9 Long FL 33040 24.837953 ‐80.797065 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 70.3 Long FL 33040 24.839586 ‐80.791764 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4 wire 70.3 Long FL 33040 24.839748 ‐80.792035 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2‐wire 70.3 Long FL 33040 24.839625 ‐80.791783 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire 70.3 Long FL 33040 24.839925 ‐80.791555 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire 70.3 Long FL 33040 24.839945 ‐80.791498 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire 70.3 Long FL 33040 24.839950 ‐80.791473 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2 wire 70.4 Long FL 33040 24.841036 ‐80.787018 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire 70.8 Long FL 33040 24.840399 ‐80.784371 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2 wire, at bridge 71.7 Craig FL 33040 24.836431 ‐80.766128 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire, at transition 71.7 Craig FL 33040 24.836192 ‐80.765672 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 72.0 Craig FL 33040 24.838226 ‐80.758826 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 72.0 Craig FL 33040 24.838552 ‐80.758364 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 72.6 Craig FL 33040 24.841561 ‐80.753085 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 73.5 Lower Matecumbe FL 33040 24.848697 ‐80.741467 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 73.5 Lower Matecumbe FL 33040 24.847576 ‐80.743322 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 73.5 Lower Matecumbe FL 33040 24.847526 ‐80.743343 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 73.5 Lower Matecumbe FL 33040 24.847579 ‐80.743234 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 73.5 Lower Matecumbe FL 33040 24.844414 ‐80.748642 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 73.5 Lower Matecumbe FL 33040 24.849253 ‐80.740453 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 5 of 7 FKAA All Cathodic Protection Damage Inventory ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes Test station, 4 wire, at transition 73.8 Lower Matecumbe FL 33040 24.849723 ‐80.740108 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 74.0 Lower Matecumbe FL 33040 24.852620 ‐80.735336 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 74.2 Lower Matecumbe FL 33040 24.854866 ‐80.731466 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2 wire 74.5 Lower Matecumbe FL 33040 24.857468 ‐80.727187 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 74.7 Lower Matecumbe FL 33040 24.858764 ‐80.725017 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 75.0 Lower Matecumbe FL 33040 24.860144 ‐80.721662 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 75.2 Lower Matecumbe FL 33040 24.861610 ‐80.718304 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 75.3 Lower Matecumbe FL 33040 24.862498 ‐80.716304 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 75.6 Lower Matecumbe FL 33040 24.864368 ‐80.712695 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 75.9 Lower Matecumbe FL 33040 24.867206 ‐80.709342 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 76.0 Lower Matecumbe FL 33040 24.868487 ‐80.707657 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 76.2 Lower Matecumbe FL 33040 24.870221 ‐80.705758 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 76.5 Lower Matecumbe FL 33040 24.872538 ‐80.703111 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station 76.8 Lower Matecumbe FL 33040 24.875749 ‐80.699621 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 77.2 Lower Matecumbe FL 33040 24.879386 ‐80.695493 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 77.5 Lower Matecumbe FL 33040 24.881333 ‐80.692045 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire, at transition 77.6 Lower Matecumbe FL 33040 24.882175 ‐80.691018 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 77.6 Lower Matecumbe FL 33040 24.882249 ‐80.690908 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 77.6 Lower Matecumbe FL 33040 24.882454 ‐80.690439 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 2 wire, at bridge 78.4 Indian Key Fill FL 33040 24.888275 ‐80.678861 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2 wire, at bridge 79.2 Indian Key Fill FL 33040 24.894022 ‐80.667469 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Test station, 2 wire, at bridge 79.3 Tea Table FL 33040 24.895033 ‐80.665494 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire, at vault 79.8 Upper Matecumbe FL 33040 24.898559 ‐80.658044 Destroyed by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire, at transition 79.8 Upper Matecumbe FL 33040 24.899002 ‐80.657708 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 79.8 Upper Matecumbe FL 33040 24.898917 ‐80.658017 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 80.1 Upper Matecumbe FL 33040 24.901472 ‐80.654192 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 80.5 Upper Matecumbe FL 33040 24.904451 ‐80.650739 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 81.0 Upper Matecumbe FL 33040 24.909712 ‐80.644734 Damaged by storm surge Hurricane 0 5 1 EA 0 0 0 Rectifier 81.2 Upper Matecumbe FL 33040 24.911964 ‐80.642139 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 81.4 Upper Matecumbe FL 33040 24.914465 ‐80.639278 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233

Rectifier for tank internal CP 81.8 Upper Matecumbe Dist. FL 33040 24.918072 ‐80.918072 Corroded by wind‐driven rain Hurricane 7,129 1 1 EA 3,260 3,221 648 7,129 7,129 Test station, 2 wire 82.1 Upper Matecumbe FL 33040 24.920830 ‐80.631969 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 82.4 Upper Matecumbe FL 33040 24.923861 ‐80.628476 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 82.8 Upper Matecumbe FL 33040 24.927627 ‐80.624159 Destroyed by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 83.3 Upper Matecumbe FL 33040 24.932152 ‐80.618930 Destroyed by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844

Test station, 2 wire, at bridge 84.0 Windley FL 33040 24.940068 ‐80.610010 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2 wire, at vault 84.0 Windley FL 33040 24.941610 ‐80.608154 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2 wire 84.9 Windley FL 33040 24.947575 ‐80.599634 Damaged by storm surge Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 4 wire 84.9 Windley FL 33040 24.937094 ‐80.613349 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 6 of 7 FKAA All Cathodic Protection Damage Inventory ? y ast? p Approx. Cost Name of damage/facility State Zip Latitude Longitude Describe Damage in a ortunit

($) y Category Address 1 Address 2 pp Labor Type o facilit Applicant priority % Work Complete (US 1 Mile Marker) Primary Cause of Damage City (Island/Key or Location) Is there a potential mitigation Has received PA grant(s) on this Asset identifier (Restoration Task No.) Quantity Unit of Measure Man‐hours Labor Cost per Unit ($) Equipment cost per Unit ($) Material/ODC/Sub cost Per Unit ($) Total Unit Cost ($) Total cost ($) Information Source Source code Notes Test station, 4 wire 84.9 Windley FL 33040 24.937116 ‐80.613314 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 4 wire 84.9 Windley FL 33040 24.947653 ‐80.599440 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 85.0 Windley FL 33040 24.948355 ‐80.597665 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Rectifier 85.5 Windley FL 33040 24.950706 ‐80.591606 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4 wire 85.5 Windley FL 33040 24.950576 ‐80.592069 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 4 wire, at insul. Flg 85.5 Windley FL 33040 24.950586 ‐80.591956 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673

Test station, 4 wire, at insul. Flg 85.5 Windley FL 33040 24.950578 ‐80.592028 Damaged by storm surge Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 85.8 Plantation FL 33040 24.953237 ‐80.585628 Damaged by storm surge Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4 wire, at transition 85.8 Plantation FL 33040 24.953257 ‐80.585553 Damaged by debris pickup Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Test station, 2 wire 85.8 Plantation FL 33040 24.953288 ‐80.585543 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 86.3 Plantation FL 33040 24.955558 ‐80.579522 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Rectifier 86.7 Plantation FL 33040 24.958696 ‐80.571445 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 87.0 Plantation FL 33040 24.959956 ‐80.568349 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 87.2 Plantation FL 33040 24.962793 ‐80.564796 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 87.4 Plantation FL 33040 24.964537 ‐80.563195 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 87.9 Plantation FL 33040 24.970279 ‐80.558051 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 88.0 Plantation FL 33040 24.971022 ‐80.557363 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2 wire 88.5 Plantation FL 33040 24.975062 ‐80.553739 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 88.8 Plantation FL 33040 24.977934 ‐80.551045 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 88.9 Plantation FL 33040 24.980583 ‐80.548750 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2 wire 89.2 Plantation FL 33040 24.984744 ‐80.545036 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Test station, 2 wire 89.8 Plantation FL 33040 24.991325 ‐80.540407 Damaged by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 90.3 Plantation FL 33040 24.998508 ‐80.537450 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 4 wire, at transition 90.5 Plantation FL 33040 25.002358 ‐80.534434 Damaged by debris pickup Hurricane 2,673 2 1 EA 1,820 610 243 2,673 2,673 Rectifier 94.5 Key Largo FL 33040 25.039072 ‐80.495785 Damaged by wind‐driven rain Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 97.2 Key Largo FL 33040 25.069164 ‐80.468147 Destroyed by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 97.5 Key Largo FL 33040 25.071497 ‐80.465971 Damaged by debris pickup Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Test station, 2 wire 97.8 Key Largo FL 33040 25.074810 ‐80.462519 Destroyed by debris pickup Hurricane 2,233 5 1 EA 1,516 514 203 2,233 2,233 Rectifier 107.8 Jewfish FL 33040 25.174531 ‐80.374725 Corroded by wind‐driven rain Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 Rectifier 108.2 Jewfish FL 33040 25.188846 ‐80.395809 Corroded by wind‐driven rain Hurricane 19,844 4 1 EA 9,141 8,899 1,804 19,844 19,844 00 00 Subtotal $1,371,269 $731,404 $515,204 $124,661 $1,371,269 $1,371,269 Area/Market Allowance $411,381 30 % $219,421 $154,561 $37,398 $411,381 Contractor's Markup $274,254 20 % $146,281 $103,041 $24,932 $274,254 Owners SIOH $82,276 6 % $43,884 $30,912 $7,480 $82,276 Total $2,139,179 $1,140,990 $803,718 $194,471 $2,139,179

EXHIBIT B ‐ Cathodic Protection Damages.xlsx Page 7 of 7 FKAA All Cathodic Protection Florida Keys Aqueduct Authority Request for Proposals Project No. 7061518AC

EXHIBIT C

Sample Contract Documents Request for Proposal EXHIBIT C

CONTRACT FKAA PROJECT NO.

THIS AGREEMENT, made and entered into this day of , by and between the Florida Keys Aqueduct Authority, hereinafter “FKAA”, and , hereinafter referred to as “CONSULTANT”.

WHEREAS, the FKAA has provided notice of the desired professional services and carried out the proper selection process pursuant to and in accordance with CONSULTANT's Competitive Negotiation Act, and;

WHEREAS, the FKAA represents that it is a Utility, organized under the State of Florida with the authority to engage CONSULTANT and accept the obligation for payment for the services desired, and;

WHEREAS, the FKAA desires to engage CONSULTANT to perform certain professional services pertinent to such work in accordance with this AGREEMENT, and;

WHEREAS, CONSULTANT shall provide such professional services in accordance with this AGREEMENT.

NOW, THEREFORE, in consideration of the premises and the mutual benefits which will accrue to the parties hereto in carrying out the terms of this AGREEMENT, it is mutually understood and agreed as follows:

I. DEFINITIONS; GENERAL CONDITIONS

A. THE SCOPE OF SERVICES is to be implemented as set forth by this AGREEMENT and by Exhibit A, Project Documentation as attached to this agreement that are made part hereof.

B. CONSTRUCTION COSTS shall be the total estimated cost to the FKAA of all elements of the project designed or specified by CONSULTANT. Construction costs shall include the cost at current market rates of labor and materials furnished by the Contractor and equipment designed, specified, selected or specially provided for by CONSULTANT, plus a reasonable allowance for the contractor’s overhead and profit. In addition, a reasonable allowance for contingencies shall be included for market conditions at the time of bidding and for changes in the work during construction. Construction costs does not include the compensation of CONSULTANT or CONSULTANTS subconsultants, the cost of the land, rights-of-way, financing or other costs which are the responsibility of the FKAA. CONSULTANT shall use its best judgment as a design professional familiar with the construction industry in estimating the construction cost. FKAA acknowledges that construction cost estimates, financial analyses and feasibility projections are subject to many influences including, but not limited to, price of labor and materials, unknown or latent conditions of existing equipment or structures, and time or quality of performance by third parties. FKAA acknowledges that such influences may not be precisely forecasted and are beyond the control of CONSULTANT and that actual costs incurred may vary substantially from the estimates prepared by CONSULTANT. CONSULTANT does not warrant or guarantee the accuracy of construction or development cost estimates.

C. PHASES: A phased approach may be utilized. The FKAA and CONSULTANT shall have the right to negotiate the terms of each phase. In the event the parties cannot agree, the FKAA may select another CONSULTANT or go out for additional proposals in order to complete the subsequent phase(s) of the project. This phased approach shall not waive the FKAA’s right to terminate this AGREEMENT during any phase of the project. 1 Request for Proposal EXHIBIT C

II. GENERAL DUTIES OF CONSULTANT

A. The relationship of CONSULTANT to the FKAA will be that of a professional CONSULTANT, and CONSULTANT will provide the professional and technical services required under this AGREEMENT in accordance with acceptable practices and ethical standards which may include, but are not limited to professional engineering services as identified in the attached Exhibit A, Project Documentation. No employer/employee relationships shall be deemed to be established and CONSULTANT, its agents, subcontractors, and employee shall be independent contractors at all times.

B. Professional and Technical Services. It shall be the responsibility of CONSULTANT to work with the FKAA and appraise it of solutions to problems and the approach or technique to be used towards accomplishment of the FKAA’s objectives as set forth in this AGREEMENT upon execution by both parties.

C. Exhibit A-1 establishes a budget for the project. CONSULTANT shall be responsible for providing, at no additional cost to the FKAA, completed designs, drawings, specifications, reports and other applicable services if the budget for the entire project is exceeded during and up to completion of the final design phase of the project; however, nothing contained herein shall require CONSULTANT to bear additional costs if the additional costs are a result of a change in the scope of services directed by the FKAA.

D. CONSULTANT shall be responsible for the professional quality, technical accuracy, timely completion, compliance with regulations and rules, and the coordination with all appropriate agencies of all drawings, specifications, reports and other services furnished by CONSULTANT. CONSULTANT shall perform its services in accordance with generally accepted standards and practices customarily utilized by competent engineering firms in effect at the time CONSULTANT’s services are rendered. CONSULTANT shall, without additional compensation, correct or revise said error or omissions to the satisfaction of the FKAA.

E. Approval by the FKAA of drawings, designs, specifications, reports and incidental professional services or materials furnished hereunder shall not in any way relieve CONSULTANT of responsibility for the technical adequacy of its work. The FKAA’s review, approval or acceptance of, or payment for, any of the services shall not be construed to operate as a waiver of any rights under this AGREEMENT or of any cause of action arising out of the performance of this AGREEMENT.

F. CONSULTANT designates . , as its representative to act as liaison with the FKAA. The representative shall manage and coordinate FKAA projects and is hereby authorized to act on behalf of CONSULTANT to act on related matters with respect to performance of services for the FKAA in accordance with the AGREEMENT. Any change to name other person shall be requested in writing to the FKAA, and shall be approved by the FKAA.

G. CONSULTANT shall attend all meetings, as specified or as defined where the project is discussed, unless the FKAA’s representative declares such attendance and participation is not necessary. In addition, CONSULTANT shall attend all additional meetings as may be required to facilitate the project.

2 Request for Proposal EXHIBIT C

III. DUTIES OF CONSULTANTS; STUDY AND REPORT PHASE THROUGH CONSTRUCTION PHASE AND RESIDENT PROJECT REPRESENTATIVE SERVICES PHASE - The following Duties of CONSULTANT are separated into phases of the project that shall be performed by CONSULTANT. The FKAA may require additional requirements applicable to the project that will be specified in attached Exhibits. The FKAA must authorize the commencement of each phase of the work unless otherwise agreed upon.

A. Phase I - Study and Report Phase If the Study and Report Phase is authorized, the following requirements shall apply.

1. CONSULTANT shall consult with the FKAA to clarify and define the FKAA’s requirements for the Project and review available data.

2. CONSULTANT shall advise the FKAA as to the necessity of the FKAA’s providing or obtaining from others, data or services.

3. CONSULTANT shall identify and analyze permit and approval requirements of all governmental authorities having jurisdiction to approve the design of the Project and participate in consultations with such authorities.

4. CONSULTANT shall provide analyses of the FKAA’s needs, planning surveys, site evaluations and comparative studies of prospective sites and solutions.

5. CONSULTANT shall provide a general economic analysis of Owner’s requirements applicable to variable alternatives.

6. CONSULTANT shall prepare a Report containing schematic layouts, sketches and conceptual design criteria with appropriate exhibits to indicate clearly the considerations involved (including applicable requirements of governmental authorities having jurisdictions as aforesaid) and the alternative solutions available to the FKAA and setting forth CONSULTANTS findings and recommendations. This Report will be accompanied by CONSULTANTS pre-design opinion of probable costs for the Project, including, but not limited to the following which will be separately itemized: Construction Cost, allowance for engineering costs and contingencies allowances for such other items, such as charges of all other professionals and consultants, for the cost of land and rights-of-way, for compensation for or damages to properties, and for permit, review and/or approval fees by other governmental agencies, if required. CONSULTANT shall also provide a preliminary evaluation of the FKAA’s Project Schedule. The FKAA’s Project Schedule and probable construction costs shall be evaluated and updated throughout subsequent phases of the work.

7. CONSULTANT shall furnish the number of copies of the Study and Report documents as provided in this AGREEMENT and review them with the FKAA.

B. Phase II - Preliminary Design Phase

If the Preliminary Design Phase is authorized, the following requirements will apply:

1. CONSULTANT, in consultation with the FKAA shall determine the general scope, extent and character of the Project.

2. Prepare Preliminary Design documents consisting of final design criteria, preliminary drawings, outline specifications and written descriptions of the Project. 3 Request for Proposal EXHIBIT C

3. Advise the FKAA if additional data or services are necessary and assist the FKAA in obtaining such data and services.

4. Furnish the specified number of copies of the above Preliminary Design documents as contained within the Project Documentation and present and review them with the FKAA.

5. CONSULTANT shall submit to the FKAA a preliminary estimate of construction costs based on current area, volume or other unit costs, which shall be updated throughout the design development phase.

6. CONSULTANT shall prepare a development schedule, which shall include, but shall not be limited to, the review and approval times by all governmental agencies as may be required.

7. CONSULTANT shall make available all design calculations and associated Data, and participate in meetings in which Value Engineering Analysis of the project takes place, at such times and places as shall be determined by the FKAA.

C. Phase III - Final Design Phase

If the Final Design Phase is authorized, the following requirements shall apply:

1. CONSULTANT shall prepare construction documents which shall include but not be limited to drawings and technical specifications, general and supplementary conditions, bid forms, invitations to bid, instructions to bidders, with technical criteria, descriptions and design data necessary for permitting by governmental authorities, and shall include any further adjustments in the scope or quality of the project or in the construction budget authorized by the FKAA.

2. CONSULTANT shall in the preparation of construction documents, technical criteria, written descriptions and design data, take into account all currently prevailing codes and regulations governing construction in the Florida Keys and shall meet the requirements of all other agencies or governmental authorities having jurisdiction over the project.

3. CONSULTANT shall prepare a detailed opinion of probable cost that shall be reviewed by the FKAA prior to going out for bids.

4. CONSULTANT shall provide the required documents and attend meetings as necessary, for the approval of governmental boards, agencies or authorities having jurisdiction over the project.

5. CONSULTANT shall use front end bid documents provided by the FKAA including bidding forms, conditions of the contract, and form of AGREEMENT between the FKAA and CONTRACTOR.

6. CONSULTANT shall prepare all documents including design and plan revisions required for the approval of governmental authorities having jurisdiction over the project. Said approvals are required prior to the public notice for the Invitation to Bid and submission of application and therefore are the responsibility of CONSULTANT.

a. CONSULTANT shall provide the FKAA the number of copies of contract documents as specified in this AGREEMENT. 4 Request for Proposal EXHIBIT C

D. Phase IV - Bidding/Negotiation Phase

If the biding phase is authorized, the following requirements shall apply

1. CONSULTANT shall assist the FKAA in obtaining bids or negotiated proposals, assist in awarding and preparing contracts for construction, attend pre-bid conferences, prepare addenda, provide written recommendation of award, assist in the compilation/preparation of contract documents, and after the award assist the FKAA in securing the required bonds and certificates of insurance, and in the review of the contract documents for completeness.

2. CONSULTANT shall attend the bid opening, prepare bid tabulation sheets and assist the FKAA in evaluating bids or proposals and in assembling and awarding contracts for construction, materials, equipment and services.

3. CONSULTANT shall issue addenda as appropriate to interpret, clarify or expand the Bidding Documents.

4. CONSULTANT shall consult with and advise the FKAA as to the acceptability of subcontractors, suppliers and other persons and organizations proposed by the prime contractor(s) (herein called CONTRACTOR(S)) for those portions of the work as to which such acceptability is required by the Bidding Documents.

5. Consult with the FKAA concerning and determine the acceptability of substitute materials and equipment proposed by CONTRACTOR(S) when substitution prior to the award of contracts is allowed by the Bidding Documents.

E. Phase V - Construction Phase

If Contract Administration is authorized, the following requirements shall apply:

1. CONSULTANT shall provide administration of the contract for construction as set forth herein and as contained with the general conditions of the contract for construction.

2. CONSULTANT shall be a representation of and shall advise and consult with the FKAA during construction and until final payment to the contractor is due. CONSULTANT shall have authority to act on behalf of the FKAA only to the extent provided in this AGREEMENT and as provided in the contract for construction unless otherwise modified by written instrument.

3. CONSULTANT shall visit the site at regular intervals appropriate to the stage of construction or as otherwise agreed to by the FKAA and CONSULTANT, in writing, to become generally familiar with the progress and quality of the work completed and shall determine in general if the work is being performed in a manner indicating that the work when completed will be in accordance with the contract documents. CONSULTANT shall keep the FKAA informed of the progress and quality of the work and shall provide certification to the FKAA of satisfactory completion of all phases of the work in compliance with the plans, specifications, and/or approved changes or modifications thereto.

4. CONSULTANT shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures of construction or for safety precautions and programs in connection with the work, since these are solely the 5 Request for Proposal EXHIBIT C

CONTRACTOR’S responsibility under the contract for construction. CONSULTANT shall make every reasonable effort to ensure that the CONTRACTOR completes the work in accordance with the current approved schedule and carries out the work in accordance with the contract documents. CONSULTANT makes no warranty or guarantee with respect to the performance of a CONTRACTOR.

5. CONSULTANT based on observations and evaluations of CONTRACTOR’S applications for payment, shall review and certify the amounts due the CONTRACTOR within seven (7) days of receipt.

6. CONSULTANTS certification for payment shall constitute a representation to the FKAA, based on CONSULTANTS observations at the site as provided herein and on the data comprising the CONTRACTOR’S application for payment, that the work has progressed to the point indicated and that, to the best of CONSULTANTS knowledge, information, and belief, the quality and quantity of work is in accordance with the contract documents. The foregoing representations are subject to an evaluation of the work for conformance with the contract documents, correctable prior to completion and to specific qualifications expressed by CONSULTANT. The issuance of the certificate of payment shall further constitute a representation that CONSULTANT has made observations to review the quality or quantity of the work.

7. CONSULTANT shall recommend disapproval or rejection of CONTRACTOR’S WORK to the FKAA which does not conform to the contract documents. CONSULTANT will have authority to require additional inspection or testing of the work in accordance with the provisions of the contract documents, whether or not such work is fabricated, installed or completed.

8. CONSULTANT shall review and approve or take other appropriate action upon CONTRACTOR’S submittals such as shop drawings, product data, and samples for the purpose of checking for conformance with information given and the design concept expressed in the contract documents. CONSULTANT shall evaluate and determine the acceptability of substitute materials and equipment proposed by CONTRACTORS.

9. CONSULTANT shall prepare change orders and construction change directives with supporting documentation and data if deemed necessary by CONSULTANT, for the FKAA’s approval and execution in accordance with the contract documents, and may authorize minor changes in the work not involving an adjustment in the contract sum or an extension of the contract time which is consistent with the intent of the contract documents.

10. CONSULTANT shall conduct inspections to determine the date or dates of substantial completion and the date of final completion, shall receive and forward to the FKAA for the FKAA’s review and records, written warranties and related documents required by the contract documents and assembled by the CONTRACTOR and shall issue a final certificate for payment upon compliance with the requirements of the contract documents.

11. CONSULTANT shall interpret matters concerning performance of the FKAA and CONTRACTOR under the requirements of the contract documents on written request of either the FKAA or CONTRACTOR. CONSULTANT’S response to such requests shall be made with reasonable promptness and within any time limits agreed upon.

12. Interpretations of CONSULTANT shall be consistent with the intent of and reasonably inferable from the contract documents and shall be in writing or in the form of drawings. 6 Request for Proposal EXHIBIT C

When making such interpretations, CONSULTANT shall endeavor to secure faithful performance by both the FKAA and the CONTRACTOR.

13. The FKAA shall be the final arbiter on matters relating to aesthetics.

14. CONSULTANT shall render written interpretations within a reasonable time on all internal disputes between the FKAA and CONTRACTOR relating to the execution of the progress of the work as provided in the contract documents. CONSULTANT’S interpretations on internal disputes are not binding on the FKAA and the FKAA may result to remedies afforded by this contract to resolve the issue.

15. CONSULTANT shall provide the number of sets of the construction documents to the CONTRACTOR as specified in this AGREEMENT

16. Upon completion of construction CONSULTANT shall provide to the FKAA, three sets of record drawings, signed and sealed, plus one electronic set incorporating record conditions and other data furnished by CONTRACTOR(S) to CONSULTANT.

17. In company with the FKAA, CONSULTANT shall visit the Project to observe any apparent defects in the complete construction, assist the FKAA in consultations and discussions with CONTRACTOR(S) concerning correction of such deficiencies, and make recommendations as to replacement or correction of defective work.

18. The presence or duties of CONSULTANT's personnel at a construction site, whether as onsite representatives or otherwise, do not make CONSULTANT or CONSULTANT's personnel in any way responsible for those duties that belong to FKAA and/or the construction contractors or other entities, and do not relieve the construction contractors or any other entity of their obligations, duties, and responsibilities, including, but not limited to, all construction methods, means, techniques, sequences, and procedures necessary for coordinating and completing all portions of the construction work in accordance with the construction Contract Documents and any health or safety precautions required by such construction work.

19. CONSULTANT and CONSULTANT's personnel have no authority to exercise any control over any construction contractor or other entity or their employees in connection with their work or any health or safety precautions and have no duty for inspecting, noting, observing, correcting, or reporting on health or safety deficiencies of the construction contractor(s) or other entity or any other persons at the site except CONSULTANT's own personnel.

20. The presence of CONSULTANT's personnel at a construction site is for the purpose of providing to FKAA a greater degree of confidence that the completed construction work will conform generally to the construction documents and that the integrity of the design concept as reflected in the construction documents has been implemented and preserved by the construction contractor(s). CONSULTANT neither guarantees the performance of the construction contractor(s) nor assumes responsibility for construction contractor's failure to perform work in accordance with the construction documents

F. Phase VI - Resident Project Representative Services Phase

If the Resident Project Representative Services Phase is authorized the following requirements 7 Request for Proposal EXHIBIT C

shall apply:

1. Resident Project Representative will be assigned to assist CONSULTANT in carrying out his responsibilities to FKAA at the site. Resident Project Representative is CONSULTANTS agent at site, will act as directed by and under the supervision of CONSULTANT, and will confer with CONSULTANT regarding Resident Representative’s actions. Resident Representative’s dealing in matters pertaining to the on-site work shall in general be with CONSULTANT and CONTRACTOR keeping the FKAA advised as necessary. Resident Project Representative’s dealings with subcontractors shall only be through or with the full knowledge and approval of CONTRACTOR. Resident Project Representative shall generally communicate with the FKAA with the knowledge of and under the director of CONSULTANT.

2. Resident Project Representative shall where applicable:

a. Review the progress schedule, schedule of Shop Drawing submittals and schedule of values prepared by CONTRACTOR and consult with CONSULTANT concerning its general acceptability.

b. Attend meetings with CONTRACTOR, such as preconstruction conferences, progress meetings, job conferences and other project-related meetings, and prepare and circulate copies of minutes thereof.

c. Working principally through CONTRACTOR’S superintendent, assist CONSULTANT in serving as the FKAA’s liaison with CONTRACTOR, when CONTRACTOR’S operations affect the FKAA’s on-site operations.

d. Assist in obtaining from the FKAA additional details or information, when required for proper execution of the Work.

e. Record date of receipt of Shop Drawings and samples.

f. Receive samples which are furnished at the site by CONTRACTOR, and notify CONSULTANT of availability of samples for examination.

g. Advise CONSULTANT and CONTRACTOR for the commencement of any Work requiring a Shop Drawing if the submittal has not been approved by CONSULTANT.

h. Conduct on-site observations of the Work in progress to assist CONSULTANT in determining if the Work is, in general, proceeding in accordance with the Contract Documents. CONSULTANT makes no warranty or guarantee with respect to the performance of a CONTRACTOR.

i. Report to CONSULTANT whenever Residential Project Representative believes that any Work is unsatisfactory, faulty or defective or does not conform to the Contract Documents, or has been damaged, or does not meet the requirements of any inspection, test or approval required to be made; and advise CONSULTANT of Work that Resident Project Representative believes should be uncovered for observation, or requires special testing, inspection or approval. Nothing herein shall relieve the CONTRACTOR or CONSULTANT from the duties imposed by the contract.

j. Verify that tests, equipment and systems start-up, and operating and maintenance training 8 Request for Proposal EXHIBIT C

are conducted in the presence of appropriate personnel, and that CONTRACTOR maintains adequate records, thereof; and observe, record and report to CONSULTANT appropriate details relative to the test procedures and start-ups. k. Accompany visiting inspectors representing public or other agencies having jurisdiction over the Project, record the results of these inspections and report to CONSULTANT. l. Report to CONSULTANT when clarifications and interpretations of the Contract Documents are needed and transmit to CONTRACTOR clarifications and interpretations as issued by CONSULTANT. m. Consider and evaluate CONTRACTOR’S suggestions for modifications in Drawings or Specifications and report with Resident Project Representative’s recommendations to CONSULTANT. Transmit to CONTRACTOR decisions as issued by CONSULTANT. n. Maintain at the job site orderly files for correspondence, reports of job conferences, Shop Drawings and samples, reproductions of original Contract Documents including all Work Directive Changes, Addenda, Change Orders, Field Orders, additional Drawings issued subsequent to the execution of the Contract, CONSULTANT’S clarifications and interpretations of the Contract Documents, progress reports, and other Project related documents. o. Keep a diary or log book, recording CONTRACTOR hours on the job site, weather conditions, data relative to questions of Work Directive Changes, Change Orders or changed conditions, list of job site visitors, daily activities, decisions, observations in general, and specific observations in more detail as in the case of observing test procedures; and send copies to CONSULTANT. p. Record all names, addresses and telephone numbers of the CONTRACTOR, all subcontractors and major suppliers of material and equipment. q. Furnish CONSULTANT periodic reports as required of progress of the Work of the CONTRACTOR’S compliance with the progress schedule and schedule of Shop drawing and sample submittals. r. Consult with CONSULTANT in advance of schedule major tests, inspections or start of important phases of the Work. s. Draft proposed Change Orders and work Directive Changes, obtaining backup material from CONTRACTOR and recommend to CONSULTANT, Change Orders, Work Directive changes, and Field Orders. t. Report immediately to CONSULTANT and the FKAA upon the occurrence of any accident. u. Review applications for payment with CONTRACTOR for compliance with the established procedure for their submission and forward with recommendations to CONSULTANT, noting particularly the relationship of the payment requested to the schedule of values, work completed and materials and equipment delivered at the site but not incorporated in the work. v. During the course of the work, verify that certificates, maintenance and operation 9 Request for Proposal EXHIBIT C

manuals and other data required to be assembled and furnished by CONTRACTOR are applicable to the items actually installed and in accordance with the Contract Documents, and have this material delivered to CONSULTANT for review and forwarding to FKAA prior to final payment for the work.

w. Before CONSULTANT issues a Certificate of Substantial Completion, submit to CONTRACTOR a list of observed items requiring completion or correction.

x. Conduct final inspection in the company of CONSULTANT, the FKAA and the CONTRACTOR and prepare a final list of items to be completed or corrected.

y. Observe that all items on final list have been completed or corrected and make recommendations to CONSULTANT concerning acceptance.

3. The Resident Project Representative shall not:

a) Authorize any deviation from the Contract Documents or substitution of materials or equipment.

b) Exceed limitations of CONSULTANT’S authority as set forth in the Contract Documents.

c) Undertake any of the responsibilities of CONTRACTOR, subcontractors, or CONTRACTOR’S superintendent.

d) Advise on, issue directions relative to or assume control over any aspect of the means, methods, techniques, sequences or procedures of construction unless such advice or directions are specifically required by the Contract Documents.

e) Advise on, issue directions regarding or assume control over safety precautions and programs in connection with the work.

f) Accept Shop Drawing or sample submittals from anyone other than CONTRACTOR.

g) Authorize the FKAA to occupy the Project in whole or in part.

h) Participate in specialized field or laboratory tests or inspections conducted by others except as specifically authorized by CONSULTANT.

IV. DATA AND SERVICES TO BE PROVIDED BY THE FKAA

The FKAA shall provide the following:

A. Furnish or cause to be furnished such reports, studies, instruments, documents, and other information as CONSULTANT and FKAA mutually deem necessary and which are under control of the FKAA.

B. Pay for all legal advertisements incidental to obtaining bids or proposals from contractors.

C. The Executive Director or his designee shall act as the FKAA’s representative with respect to the work to be performed under this AGREEMENT. The Executive Director or his designee shall have the authority to the extent authorized by the FKAA Board of Directors to exercise the rights 10 Request for Proposal EXHIBIT C

and responsibilities of the FKAA provided in this contract. Said authority may include but is not limited to: transmit instructions, stop work, receive information, interpret FKAA’s policies and decisions with respect to materials, equipment, elements, and systems pertinent to the services covered by this AGREEMENT.

D. Pay all permit application filing fees.

E. Provide access to FKAA facilities.

V. TIME OF PERFORMANCE

A. CONSULTANT will begin work promptly after issuance of a notice to proceed.

B. CONSULTANT’S services called for under the AGREEMENT shall be completed in accordance with the schedule contained in the Project Documentation. If CONSULTANT’S services are unreasonably delayed by the FKAA in excess of 180 days, the time of performance and compensation shall be renegotiated, provided, however, CONSULTANT as a condition precedent to renegotiation shall notify the FKAA within fifteen (15) calendar days from the end of the delay of CONSULTANT’S proposed additional costs incurred by reason of said delay.

VI. AGREEMENT PERIOD

The period of service is from the date of execution of this AGREEMENT. This AGREEMENT will terminate at such time as the engineering services required by this AGREEMENT have been completed.

VII. COMPENSATION

A. The FKAA will compensate CONSULTANT for the services in accordance with a negotiated lump sum, or a not to exceed budgeted amount based on time charges which are based upon hourly rates, plus reimbursable expenses if compensation is based on Method II and other related costs as are specified in this AGREEMENT.

1. METHOD 1 - LUMP SUM

Wherever possible, the scope of services for Services, Projects or Programs shall be thoroughly defined and outlined prior to its authorization. The FKAA and CONSULTANT shall mutually agree to a lump sum amount for services to be rendered and a detailed scope of services. Should the FKAA deem that a change in the scope of services is appropriate, then a decrease or increase in compensation shall be authorized in writing. In lump sum contracts, CONSULTANT shall submit the estimated man hours, wage rates and other actual unit costs supporting the compensation. CONSULTANT shall submit a truth in negotiation certificate stating that all data supporting the compensation is accurate, complete and current at the time of contracting.

2. METHOD II - TIME/CHARGES NOT TO EXCEED BUDGETED AMOUNT

When a service is to be compensated for a time charge/not to exceed basis, CONSULTANT will submit a not to exceed budget cost to the FKAA for prior approval based on actual time charges which shall not exceed established hourly rates as shown in Exhibit B attached hereto, plus reimbursable expenses and other related costs. The FKAA shall not be obligated to reimburse CONSULTANT for costs incurred in excess of the not to exceed cost amount. 11 Request for Proposal EXHIBIT C

a. The FKAA agrees to pay CONSULTANT compensation for services rendered based upon the established raw hourly salary rates as shown in Exhibit B for services rendered on FKAA projects multiplied by an overhead factor containing a ten percent (10%) profit, which shall not exceed 3.0. The overhead factor may be subject to audit. The schedule of hourly rates as set forth in Exhibit B is attached hereto and made a part hereof. The rates listed in Exhibit B may be adjusted upon AGREEMENT of the parties.

b. In addition, the FKAA shall pay for reimbursable expenses invoiced at the actual cost of expenditures incurred by CONSULTANT if provided in this AGREEMENT as follows:

1. Transportation and subsistence when traveling in connection with the work required of this AGREEMENT shall be reimbursed in accordance with the FKAA Travel and Business Reimbursement Policy and Florida Statute; FS 112.061. The method of transportation shall be by the most efficient and economical means of travel (considering time of the traveler, cost of transportation and per diem or subsistence required). Lodging of CONSULTANT’S while on official FKAA business in Monroe County should be arranged and paid for directly by CONSULTANT. FKAA will reimburse lodging for hotels in comparable value to Hampton Inn, Holiday Inn, Fairfied Inn, etc. Mileage and per diem will be reimbursed in accordance with the FKAA Travel and Business Reimbursement Policy and F.S. 112.061.

2. Actual expense of reproductions of documents in excess of that stipulated in the Project Documentation.

3. Actual expenses of testing, laboratory services, and field equipment, postage, supplies incurred directly for the project, and CONSULTANT’S standard project charges for special health and safety requirements of OSHA.

4. Actual expenses of overtime work requiring higher than regular rates, when authorized by the FKAA.

5. Express courier services shall only be utilized with the approval of the Director of Environmental Services or Director of Engineering.

6. Travel expenses for CONSULTANT’S employees traveling to and from CONSULTANT’S offices shall not be reimbursable unless the travel is required for meetings with FKAA personnel, or as otherwise approved by the Director of Environmental Services or Director of Engineering.

B. Subcontractual service shall be invoiced at the actual fees paid by CONSULTANT, plus an additional ten percent (10%) of the cost of these services to compensate CONSULTANT, for the procuring and management of the subconsultant, and for the other financial and administrative costs. Subcontractual services shall be approved by the FKAA in writing prior to performance of the Subcontractual work.

C. Total Compensation (including, but not limited to compensation for subconsultants) for all services and expenses shall not exceed the budget cost listed in this AGREEMENT, without written approval.

D. If the FKAA determines that any price for services, however calculated, provided by CONSULTANT, including profit, negotiated in connection with this AGREEMENT or any cost 12 Request for Proposal EXHIBIT C

reimbursable under this AGREEMENT was increased by any significant sums because CONSULTANT or any subcontractor furnished incomplete or inaccurate costs or pricing data, then such price or cost of profit shall be reduced accordingly and the AGREEMENT shall be reduced accordingly and the AGREEMENT shall be modified in writing to reflect such reduction.

VIII. PAYMENT

The FKAA agrees that it will use its best effort to pay CONSULTANT within thirty (30) calendar days from presentation of CONSULTANTS itemized report and invoice and approval of the FKAA’s representative, unless additional time for processing is required for payments for basic services, Subcontractual services, and reimbursable expenses as defined in Section VII. CONSULTANT shall submit monthly invoices, as required in this AGREEMENT, which shall include a report of work completed during the respective invoice period. Invoices shall be in a format consistent with those shown in Exhibit C. The report shall be adequate in detail to describe work progress (% completed for each task) and written summaries of work completed. No payment request shall exceed the value of work and services performed by CONSULTANT under this AGREEMENT.

IX. MISCELLANEOUS PROVISIONS

A. Ownership of Documents

A set of reproducible mylar drawings and electronic documents in a format compatible with AutoCadd, Latest Edition, FKAA’s computer system, shall be given to the FKAA. Details, design calculations, and all other documents and plans that result from CONSULTANT’S SERVICES under this AGREEMENT shall become and remain the property of the FKAA, including patent and copyright rights, whether the project is completed or not, and will be delivered to the FKAA upon demand. CONSULTANT reserves the right to retain a copy of all such documents for record purposes. Where such documents are required to be filed with governmental agencies, CONSULTANT will furnish copies to the FKAA upon request. The contract work is represented by hard copy documentation; software, is provided to the FKAA for convenience only.

B. Copies of Documents

CONSULTANT shall prepare sufficient copies of all documents necessary to obtain approval through the FKAA’s processes, as well as other governmental authorities. See also Section III for additional requirements. The FKAA acknowledges that the materials cited in Paragraph IX and other data provided in connection with this AGREEMENT which are provided by CONSULTANT are not intended for use in connection with any project other than the project for which such materials are prepared. Any use by the FKAA of such materials in connection with a project other than that for which such materials were prepared without prior written consent and adaption by CONSULTANT shall be at the FKAA’s sole risk, and CONSULTANT shall have no responsibility or liability therefore.

C. Insurance

Without limiting any of the other obligations or liabilities of CONSULTANT, CONSULTANT shall, at his own expense provide and maintain in force, until all of its services to be performed under this AGREEMENT have been completed and accepted by the FKAA (or for such duration as it otherwise specified hereinafter), the following insurance coverage:

13 Request for Proposal EXHIBIT C

1. Worker’s Compensation Insurance to apply to all of CONSULTANT’S employees in compliance with the “Worker’s Compensation Law” of the State of Florida and all applicable Federal Laws.

a. Employer’s Liability with limits of $100,000 per person, $500,000 per occurrence and $100,000 per each disease.

2. Commercial General Liability with minimum limits of $1,000,000 per occurrence combined single limit for Bodily Injury Liability and Property Damage Liability. Certified and complete copies of all required insurance policies be provide to FKAA if requested by FKAA. Coverage must be afforded on a form no more restrictive than the latest edition of the Commercial General Liability policy, without restrictive endorsements other than ISO Endorsement GL 21 06 (Engineers, Architects, or Surveyors Professional Liability exclusion), as Filed by the Insurance Services Office and must include:

a. Premises and/or Operations

b. Independent Contractors

c. Products and Complete Operations - CONSULTANTS shall maintain in force until at least three years after completion of all services required under this AGREEMENT, coverage for Products and Completed Operations, including Broad Form Property Damage.

d. Broad Form Property Damage

e. Contractual Coverage applicable to this specific AGREEMENT.

f. Personal Injury Coverage with minimum, limits of coverage equal to those required for Bodily Injury Liability.

3. Business Automobile Liability with minimum limits of $1,000,000 per occurrence combined single limit for Bodily Injury Liability and Property damage Liability. Coverage must be afforded on a form no more restrictive than the latest edition of the Business Automobile Liability policy, without restrictive endorsements, as filed by the Insurance Services Office and must include:

a. Owned Vehicles

b. Hired and Non-Owned Vehicles

c. Employer’s Non-Ownership

4. Professional Liability Insurance with minimum limits of $1,000,000 per claim. Coverage shall be afforded on a form acceptable to the FKAA. CONSULTANT shall maintain such professional liability insurance until at least four years after a Certificate of Occupancy is issued.

5. Prior to commencement of services, CONSULTANT shall provide to the FKAA Certificates of Insurance evidencing the insurance coverage specified in the foregoing Paragraphs. All policies covered within subparagraphs of section C shall be endorsed to provide the FKAA with thirty (30) days notice of cancellation and/or restriction (ten (10) days notice for 14 Request for Proposal EXHIBIT C

cancellation due to non-payment of premium). The FKAA shall be named as an additional insured as to CONSULTANTS liability on policies referenced except Workers Compensation and Professional liability.

6. If the initial insurance policies required by this AGREEMENT expire prior to the completion of the services, renewal Certificates of Insurance of policies shall be furnished thirty (30) days prior to the date of their expiration. For Notice of Cancellation and/or Restriction; the policies must be endorsed to provide the FKAA with thirty (30) days notice of cancellation and/or restriction (ten (10) days notice for cancellation due to non-payment of premium).

7. CONSULTANT’S insurance, including that applicable to the FKAA as an additional Insured, shall apply on a primary basis.

D. Litigation Services

It is understood and agreed that CONSULTANT’S services include reasonable participation in litigation or dispute resolution arising from this AGREEMENT. CONSULTANTS participation shall include up to 20 hours of services related to litigation or dispute resolution. Any such services in excess of 20 hours shall be an additional service.

E. Authority to Contract

The FKAA represents that it is an Agency of the State of Florida with the authority to engage CONSULTANT for professional services and to accept the obligation for payment for the services described in this Agreement.

F. Assignment

The FKAA and CONSULTANT each binds itself and its successors, legal representatives, and assigns to the other party to this AGREEMENT and to the partners, successors, legal representatives, and assigns of such other party, in respect to all covenants of this AGREEMENT subject to budget considerations and requirements of law; and, neither the FKAA nor CONSULTANT will assign or transfer their interest in this AGREEMENT without the written consent of the other.

G. Confidential Information

During all times that CONSULTANT is employed on behalf of the FKAA and at all times subsequent to the date of this contract, all discussions between the FKAA and CONSULTANT and all information developed or work products produced by CONSULTANT during its employment and all matters relevant to the business of the FKAA not otherwise being a matter of public record shall be deemed to be confidential. All such information and work product shall be protected by CONSULTANT and shall not be revealed to other persons without the express written permission of the FKAA, unless mandated by order of the court.

H. Non-Exclusive Contract

The FKAA reserves the right to award projects to other firms pursuant to the Florida Statutes Consultant’s Competitive Negotiations Act during the period of service of CONSULTANT. CONSULTANT agrees to cooperate with the FKAA and other firms in accomplishing work that may require joint efforts to accomplish the FKAA’s goals. This cooperation, when requested by the FKAA, will include but not be limited to: 15 Request for Proposal EXHIBIT C

1. Sharing technical information developed under contract with the FKAA.

2. Joint meeting for project coordination.

3. Establish lines of communication.

I. Subconsultants

In the event CONSULTANT, during the course of the work under this AGREEMENT requires the services of any subcontractors or other professional associates in connection with services covered by this AGREEMENT, CONSULTANT must secure the prior written approval of the FKAA.

J. Notices

Whenever either party desires to give notice unto the other, it must be given by written notice, sent by registered United States mail, with return receipt requested, addressed to the party for whom it is intended at the place last written, as the place for giving of notice in compliance with the provisions of this paragraph. For the present, the parties designate the following as the representative places of giving notice to with:

Florida Keys Aqueduct Authority 1100 Kennedy Drive Key West, Florida 33040

CONSULTANT

NAME Address

K. Attachments

Request for Qualifications is hereby incorporated within and made an integral part of this AGREEMENT.

L. Truth-In-Negotiation Certificate

Signature of the AGREEMENT by CONSULTANT shall act as the execution of a truth in negotiation certificate stating that wage rates and other factual unit costs supporting the compensation of this AGREEMENT are accurate, complete, and current. The original contract price and any additions thereto shall be adjusted to exclude any significant sums by which the FKAA determines the contract price was increased due to inaccurate, incomplete, or non-current wage rates and other factual unit costs.

M. Records

Records of all expenses relative to project shall be kept on a general recognized accounting basis and shall be available to the FKAA or its authorized representative at mutually convenient times.

16 Request for Proposal EXHIBIT C

N. Personnel

CONSULTANT represents that it has or will secure at its own expense, qualified personnel required in performing the services under this AGREEMENT. All work shall be performed under the direction of a professional, registered under the State of Florida in the field for which he is responsible for performing such services. The project manager shall be approved by the FKAA. Key personnel will be identified for each project and expected to perform the work assignment as can reasonably be expected, and as approved by the FKAA.

O. Equal Opportunity Employment; Non-Discrimination

CONSULTANT agrees that it will not discriminate against employees or applications for employment because of race, creed, color, religion, sex, age, handicapped status or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion or transfer; recruitment advertising; lay-off or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. CONSULTANT agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth this non-discrimination clause. This provision applies to all CONSULTANT’S subcontractors and it is the responsibility of CONSULTANT to ensure subcontractor’s compliance.

P. Prohibition Against Contingent Fees

CONSULTANT warrants that he has not employed or retained any company or person, other than a bonafide employee working solely for CONSULTANT, to solicit or secure this AGREEMENT, and that he has not paid or agreed to pay any persons, company, corporation, individual or firm, other than a bonafide employee working solely for CONSULTANT any fee, commission, percentage, gift, or any other consideration, contingent upon or resulting from the award or making of this AGREEMENT.

Q. Termination

This AGREEMENT may be terminated by either party by seven (7) calendar days prior written notice, in the event of substantial failure to perform in accordance with the terms hereof by the other party through no fault of the terminating party. CONSULTANT and the FKAA shall also have a right to terminate this AGREEMENT for convenience at any time by thirty (30) calendar days written notice to either one or the other. In the event the project described in this AGREEMENT, or the services of CONSULTANT called for under this AGREEMENT, is or are suspended, canceled, or abandoned by the FKAA, CONSULTANT shall be given five days prior written notice of such action and shall be compensated for the professional services provided and reimbursable expenses incurred up to the date of suspension, cancellation or abandonment. CONSULTANT agrees to provide all documents to the FKAA (specifically those referenced within). Further, prior to CONSULTANT’S destruction of any of the above referenced documents, the FKAA shall be notified and allowed a reasonable period of time to gain access to and make copies of any such documents. Upon any termination of this AGREEMENT, CONSULTANT agrees that it shall use its best efforts to work harmoniously with any successor who enters an AGREEMENT to provide services for the FKAA in order to provide for a smooth transition period.

R. Indemnification

CONSULTANT will at all times indemnify, save and hold harmless and defend the FKAA, its 17 Request for Proposal EXHIBIT C

officers, agents (the term agents shall not include the CONTRACTOR(s), any subcontractors, any materialman or others who have been retained by the FKAA or CONTRACTOR, or materialman to supply goods or services to the project) and employees, from and against liability, claim, demand, damage, loss, expense or cause of action and costs (including attorney’s fees at trail or appellate levels) to the proportionate extent arising out of negligent action of CONSULTANT, its agents, servants or employees in the performance of services under this AGREEMENT. The indemnifications contained herein shall survive the expiration or earlier termination of this AGREEMENT

Nothing in this AGREEMENT shall be deemed to affect the rights, privileges and immunities of the FKAA as set forth in Florida Statutes 768.28.

S. Interest of CONSULTANT

CONSULTANT covenants that it presently has no interest and shall not acquire any interest, direct or indirect, in any Project to which this AGREEMENT pertains or any other interest which would conflict in any manner or degree with the performance of its service hereunder. CONSULTANT further covenants that in the performance of this AGREEMENT, no person having such interest shall be employed.

T. Prohibited Practices

CONSULTANT during the period of this AGREEMENT shall not hire, retain, or utilize for compensation any member, officer, or employee of FKAA or any person who, to the knowledge of CONSULTANT, has a conflict of interest.

U. Compliance With Laws

1. CONSULTANT shall comply with the applicable requirements of State, Federal and applicable County laws and all Codes of Ordinances of the local municipality as amended from time to time, and that exist at the time of building permit issuance.

2. For Projects involving work under Federal or State Grantors or Approving Agencies, the FKAA and CONSULTANT shall review and approve the applicable required provisions or any other supplemental provisions as may be included.

V. Jurisdiction; Venue

CONSULTANT hereby covenants, consents and yields to the jurisdiction of the State Courts of the 16th Judicial Circuit, in and for Monroe County, Florida. Any dispute between CONSULTANT and the FKAA shall be governed by the laws of Florida with venue in the State Courts of the 16th Judicial Circuit, in and for Monroe County, Florida.

W. Attorney’s Fees

In the event a suit is filed in court arising out of this AGREEMENT, the prevailing party shall be entitled to recover from the other party all costs incurred, including reasonable attorney’s fees and costs on appeal.

X. Internal Dispute Between FKAA and Consultant

The Executive Director shall be the final decision maker regarding internal disputes between 18 Request for Proposal EXHIBIT C

FKAA and CONSULTANT.

Y. Project Scheduling

CONSULTANT shall provide scheduling to FKAA, within ten (10) days of the date of commencement as contained within this AGREEMENT. During the course of the work, CONSULTANT shall provide monthly updates with a written description of any changes in the schedule.

Z. Extent of Agreement

This AGREEMENT represents the entire integrated AGREEMENT between the FKAA and CONSULTANT and supersedes all prior negotiations, representations or AGREEMENTS, written or oral. This AGREEMENT may not be amended, changed, modified, or otherwise altered in any way, at any time after the execution hereof, except by approval of the FKAA Board of Directors and CONSULTANT.

AA. Audit and/or Access to Records

1. At all times during the period that the CONTRACT is in force and for a period of not less than three (3) years thereafter, the CONTRACTOR shall provide all authorized representatives of the FKAA with full access/audit to all its financial records that pertain to services performed and determination of amounts payable under the CONTRACT including access to appropriate individuals with knowledge of financial records and full access to all additional records, that pertain to services performed and determination of amounts payable under the CONTRACT, permitting such representatives to examine, audit and copy such records at the site at which they are located. Such access/audit shall include both announced and unannounced inspections and on-site audits.

2. Audits conducted under this provision shall be in accordance with generally accepted auditing standards and within established procedures and guidelines of the reviewing or auditing agency.

3. This right to access/audit clause applies to financial records pertaining to all contracts, all contract change orders, and all contract amendments. In addition, this right to access applies to all records pertaining to all contracts, additional work clause items and contract amendments.

4. To the extent the records pertain directly to contract performance. If there is any indication that fraud, gross abuse or corrupt practices may be involved; or if the CONTRACT is terminated for default or for convenience.

5. If an audit, litigation, or other action involving the records is started before the end of the three (3) year period, the records must be retained until all issues arising out of the action are resolved or until the end of the three (3) year period, whichever is later.

19 Request for Proposal EXHIBIT C

IN WITNESS WHEREOF, the FKAA has caused these presents to be executed in its name by its Executive Director, and attested and its official Seal to be hereunto affixed by its Records Clerk, and CONSULTANT has hereunto set its hand and Seal the day and year first written above:

FLORIDA KEYS AQUEDUCT AUTHORITY

Date______Kirk C. Zuelch, Executive Director

Date______Reviewed by: Legal Counsel

Date______Jolynn Reynolds, P.E., Manager of Engineering

ENGINEERING CORPORATION

Witness:______Typed Name, and Job Title

Witness: ______

BOARD APPROVAL DATE:______

20 Request for Proposal EXHIBIT C

CORPORATE ACKNOWLEDGMENT STATE OF FLORIDA COUNTY OF MONROE

The foregoing instrument was acknowledgment before me this day of 20__, by (name of officer or agent title of officer of agent, of (name of corporation acknowledging), a (State or place of incorporation) corporation, on behalf of the corporation. He/She is (personally know to me) (or has produced identification) (type of identification) as identification and (did/did not) take an oath.

______Signature of Person Taking Acknowledgment

______Name of Acknowledger – Typed Printed or Stamped

21 Request for Proposal EXHIBIT C

ACKNOWLEDGMENT IF PARTNERSHIP STATE OF

COUNTY OF

The foregoing instrument was acknowledged before me this day of by (name of acknowledging partner or agent) of (name of partnership), a partnership. He/she is (personally know to me) (or has produced identification) (type or identification) (as identification) and (did/did not) take an oath.

______Signature of Person Taking Acknowledgment

______Name of Acknowledger – Typed Printed or Stamped

BOARD APPROVAL DATE______(Required if under $10,000.00)

22 Request for Proposal EXHIBIT C

SCHEDULE OF HOURLY RATES EXHIBIT B (SAMPLE)

Range of Hourly Raw Salary Rates Average Hourly Raw Salary Rate Times 3.00 Multiplier

Employer Category

Professionals: Engineers, Architects, Planners, Economists, Scientists, Hydrologists, Hydrogeologists, Geologists

Engineer 8 Engineer 7 Engineer 6 Engineer 5 Engineer 4 Engineer 3 Engineer 2 Engineer 1

Technicians: Drafters, Graphic Artists, Computer, Surveyors, Cartographics, Construction Inspectors

Technician 5 Technician 4 Technician 3 Technician 2 Technician 1 Technical Aide

Office Support

Specification Processor Clerical/Office Support

Note: Rates applicable through [ ]

23 Request for Proposal EXHIBIT C

EXHIBIT C SAMPLE INVOICE COST NOT TO EXCEED FORMAT

Florida Keys Aqueduct Authority

Project No. Date Purchase Order No. FKAA Ref. No. Project No. Invoice No.

Description of services under Project No.

Period ending:

LABOR

Class Employee Rate Hours Amount

Subtotal $

EXPENSES

Auto Rental Postage/Freight Air Transportation Print/Reprographics Supplies

Subtotal Expenses

TOTAL AMOUNT DUE THIS INVOICE $

COST SUMMARY

Contract Amount $ Amount Earned This Period $ Amount Previously Earned $ Amount Remaining $

24 Request for Proposal EXHIBIT C

EXHIBIT C (Continued) SAMPLE INVOICE LUMP SUM FORMAT

INVOICE

Florida Keys Aqueduct Authority

Project No. Date Purchase Order No. FKAA Ref. No. Project No. Invoice No.

Description of services under Project No.

Period ending:

Total Fee $

% Complete $ Less Previous Billings

Total Earned This Period $

TOTAL AMOUNT DUE THIS INVOICE

25