Application of Hardin Wind Energy LLC for a Third Amendment to its Certificate of Environmental Compatibility Case No. 16-469-EL-BGA

March 2016

Prepared by

Hardin Wind Energy LLC Chicago, Illinois March 24, 2016

COLUMBUSICLEVELAND CINCINNATI-DAYTON Via Hand Delivery MARIETTA Ms. Barcy McNeal BRICKER&ECKLERLLP 100 South Third Street Administration/Docketing Columbus, OH 43215-4291 Ohio Power Siting Board MAIN: 614.227.2300 th FAX: 614.227.2390 180 East Broad Street, 11 Floor www.bricker.com Columbus, Ohio 43215-3793 [email protected] Re: Hardin Wind Energy LLC, Sally W. Bloomfield Case No. 16-469-EL-BGA 614.227.2368 [email protected] Dear Ms. McNeal:

Enclosed for filing in the above-referenced case is a copy of the Application of Hardin Wind Energy LLC for a Third Amendment to its Certificate of Environmental Compatibility granted March 22, 2010 in Case No. 09-479- EL-BGN. In addition, we have provided Staff of the Ohio Power Siting Board (“Board”) ten disks and five hard copies of the Application. Pursuant to Ohio Administrative Code Rule 4906-3-11(B), the Applicant makes the following declarations:

Name of Applicant: Hardin Wind Energy LLC a subsidiary of LLC One Wacker Drive, Suite 1900 Chicago, IL 60606

Name/Location of Proposed Facility: Hardin Lynn, Cessna, Marion, Roundhead, McDonald, and Taylor Creek Townships Hardin County, Ohio

Authorized Representative Technical: Kent Truckor Invenergy LLC One Wacker Drive, Suite 1900 Chicago, IL 60606 (312) 582-1264 [email protected]

10013927v1 Bricker & Eckler ATTORNEYSATLAW

Case No. 16-469-EL-BGA March 24, 2016 Page 2

Authorized Representative Legal: Sally W. Bloomfield Dylan Borchers Bricker & Eckler LLP 100 South Third Street Columbus, OH 43215 Telephone: 614-227-2368, -4914 Facsimile: 614-2990 [email protected] [email protected]

Notarized Statement: See Attached Affidavit of Hardin Wind Energy LLC

Sincerely on behalf of, HARDIN WIND ENERGY LLC

Sally W. Bloomfield

Enclosure

10013927v1

Application for Third Amendment to Siting Certificate for Hardin Wind Energy’s Hardin Wind Farm Hardin County, Ohio

Case No. 16-469-EL-BGA

Prepared by

Hardin Wind Energy LLC Chicago, Illinois

For submittal to

Ohio Power Siting Board Columbus, Ohio

March 22, 2016

10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

TABLE OF CONTENTS

TABLES ...... iv

FIGURES...... iv

ATTACHMENTS...... iv

GLOSSARY ...... v

4906-17-02 Project Summary...... 1

General Procedural Information: ...... 1

Applicant Update: ...... 3

(A) Project Summary and Facility Overview...... 4

(1) General Purpose of the Facility...... 4 (2) Facility Description...... 4 (3) Site Selection Process ...... 4 (4) Principal Environmental Considerations ...... 4 (5) Project Schedule...... 4

4906-17-03 Project Description and Schedule ...... 5

(A) Proposed Facility Description...... 5

(1) Project Description...... 5 (2) Description of Equipment...... 7 (3) Description of New Transmission Lines...... 9

(B) Detailed Project Schedule...... 9

(1) Project Schedule...... 9 (2) Delays ...... 10

4906-17-04 Project area Analyses ...... 11

(A) Site Selection Study...... 11

(1) General...... 11 (2) Constraint Map...... 11

(B) Summary Table of Evaluated Sites...... 11

4906-17-05 Technical Data...... 12

(A) Project Area Site ...... 12

i 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(1) Geography and Topography ...... 12 (2) Aerial Photograph ...... 12 (3) Site Mapping...... 12 (4) Geology and Seismology ...... 12 (5) Hydrology and Wind...... 12

(B) Layout and Construction...... 13

(1) Project Area Site Activities...... 13 (2) Layout Map...... 13 (3) Structures ...... 13 (4) Plans for Construction...... 14 (5) Future Plans ...... 14

(C) Equipment...... 14

(1) Wind-Powered Generation Equipment...... 14 (2) Safety Equipment...... 14 (3) Any Other Major Equipment ...... 14

(D) REGIONAL ELECTRIC POWER SYSTEMS...... 15

4906-17-06 Financial Data ...... 16

(A) Ownership...... 16

(B) Capital and Intangible Costs ...... 16

(C) Operation and Maintenance Costs ...... 16

(D) Delays ...... 16

4906-17-07 Environmental Data...... 17

(A) General...... 17

(B) Air ...... 17

(C) Water...... 17

(D) Solid Waste...... 17

4906-17-08 Social and Ecological Data ...... 18

(A) Health and Safety...... 18

(1) Demographic Characteristics...... 18 (2) Noise ...... 18 (3) Water...... 18

ii 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(4) Ice Throw...... 18 (5) Blade Shear ...... 19 (6) Shadow Flicker ...... 19

(B) Ecological Impact ...... 19

(1) Project Site Information...... 19 (2) Construction...... 20 (3) Operation...... 20

(C) Economics, Land Use and Community Development...... 20

(1) Land Uses...... 20 (2) Economics...... 22 (3) Public Services and Facilities ...... 23 (4) Impact on Regional Development ...... 23

(D) Cultural Impact ...... 23

(1) Map of Landmarks of Cultural Significance and Recreational Areas ...... 23 (2) Estimated Impact on Landmarks ...... 23 (3) Historical Resources ...... 23 (4) Consideration of Landmarks...... 23 (5) Mapping Landmarks ...... 23 (6) Recreational Areas...... 24 (7) Visual Impacts ...... 24

(E) Public Responsibility ...... 24

(1) Public Information Program ...... 24 (2) Liability Insurance ...... 24 (3) Evaluation of Interference with Radio and Television ...... 24 (4) Evaluation of Interference with Military Radar and FAA...... 24 (5) Evaluation of Impact to Roads and Bridges ...... 24 (6) Plan for Decommissioning...... 25

(F) Agricultural District Impact...... 25

(1) Agricultural and Agricultural District Land ...... 25 (2) Agricultural Land Impacts ...... 25 (3) Impacts to Agricultural Lands Viability ...... 25

CERTIFICATE OF SERVICE ...... 26

iii 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

TABLES

Table 03-01 Estimated Area To Be Disturbed

Table 03-02 Turbine Data Comparison

Table 08-01 Wind Energy Facilities within 100 feet of a Residence

FIGURES

Figure 03-01 Project Schedule

ATTACHMENTS

Attachment A Project Layout

Attachment B Layout Comparison Map

Attachment C Constraint Map for GE 2.3-116 on 80m HH

Attachment D Project Layout Mapbook

Attachment E House Locations

Attachment F Draft Safety Manual

Attachment G Hardin Wind Energy Noise Analysis

Attachment H Hardin Wind Energy Shadow Flicker Study

iv 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

GLOSSARY

AEP – American Electric Power, the interconnected utility

Applicant – Hardin Wind Energy LLC dB – decibels

D – diameter of rotor

FAA – Federal Aviation Administration

FEMA - Federal Emergency Management Agency

GE – General Electric

HH – hub height

ISA – Interconnection Service Agreement

ISCA – Interconnection Construction Service Agreement

IEC - International Electrotechnical Commission m - meter

MW – megawatt

MWh – megawatt-hour

NRHP - National Register of Historic Places

O&M – operations and maintenance

OE/AAA - Obstruction Evaluation / Airport Airspace Analysis

ODNR - Ohio Department of Natural Resources

OHS – Ohio Historic Society

OPSB - Ohio Power Siting Board

Project – Hardin County Wind Project

PJM – PJM Interconnect, LLC, the interconnected independent system operator

v 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

POI – point of interconnection

USACE - Army Corps of Engineers

USFWS – United States Fish and Wildlife Service

VOR – VHF (Very High Frequency) Omnidirectional Radar

vi 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-02 PROJECT SUMMARY

General Procedural Information:

Hardin Wind Energy LLC (the Applicant), an affiliate of Invenergy Wind Development LLC

(Invenergy), is certified to construct the Hardin Wind Farm (the Project), a wind-powered electric generation facility to be located in Hardin County, Ohio. The Applicant is aware that the new rules are in effect, but inasmuch as the Application to which this Third Amendment refers was filed under the rules in existence before December 11, 2015, this Third Amendment application tracks the designations of the older rules. Applicant believes that it has addressed substantive changes in the new rules.

Applicant takes the position that this Third Amendment falls squarely within the precedent of the decision in Case No. 14-1591-EL-BGA, In the Matter of the Application of Black Fork Wind

Energy, LLC Regarding Its Certificate of Environmental Compatibility and Public Need in Case

No. 10-2865-EL-BGN issued on August 27, 2015 (“Black Fork Amendment Case”). In the

Black Fork amendment application, as in this Third Amendment, Black Fork was seeking only to change turbine models and not to make any other changes. The Ohio Power Siting Board (OPSB or Board) noted that the Black Fork amendment merely sought to upgrade the turbine models in order to take advantage of the latest technological advances (at 6) and that its decision was

“concentrated solely on the Applicant’s request to add two new turbine models. . .” and that

“there is no material increase in any environmental impact of the facility and no change in any portion of the facility’s location, including the location of the individual turbines, from what was originally approved by the Board in the Black Fork Amendment Case.” Id at 6. The Board concluded in the Black Fork Amendment Case that though Black Fork was required to file an application for an amendment, the Board considers the facts of the case and whether the

Section 4906-17-02 1 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016 provisions of Ohio Revised Code Section (“R.C.”) 4906.201 should be triggered. It found that based upon that facts that the Black Fork Amendment Case did not request that any turbines be relocated nor did it proposed any new or additional environmental impacts beyond those previously approved, the application did not constitute an amendment as that term is used in R.C

4906.201 (B)(2). Id. at 7. The Applicant is filing this Third Amendment, as did the applicant in the Black Fork Amendment Case, so that the Board Staff can review it to make the determination that the precedent of the Black Fork Amendment Case may be followed.

As explained above, Applicant does not believe that this Third Amendment triggers R.C.

4906.201, but if R.C. 4906.201 were to apply, the Applicant additionally meets the requirements of that statute:

• The sole purpose of this Third Amendment is to make changes to one or more turbines

that have been approved under Applicant’s existing certificate, but have not yet been

installed;

• This Third Amendment does not increase the number of turbines to be installed as set

forth in the Certificate;

• The Applicant is seeking the amendment within 180 days of the effective date of the

legislation, Ohio House Bill 64, effective September 29, 2015;

• The turbine to be installed is more efficient and more technologically advanced than the

type approved in the Applicant’s Certificate;

• The turbine proposed to be installed is not more than 8% taller as measured from its base

to the tip of the highest blade, than the turbines approved in the First Amendment; Case

No. 11-3446-EL-BGA;

Section 4906-17-02 2 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

• The Applicant is obligated by contract to provide wind energy to at least one mercantile

customer that consumes 7,000,000 kW hours; and

• The turbines will be installed on the same turbine locations as were approved under

Applicant’s Certificate.

Applicant Update:

Hardin Wind Energy LLC (the Applicant), an affiliate of Invenergy Wind Development LLC

(Invenergy), is certified to construct the Hardin Wind Farm (the Project), a wind-powered electric generation facility to be located in Hardin County, Ohio. The original Application (the

Application) for a Certificate of Environmental Compatibility and Public Need (the Certificate) was filed on July 10, 2009. Applicant filed an amended application on September 18, 2009 (the

Application) which was processed using the same case number. The Board issued an Opinion,

Order and Certificate in Case Number 09-479-EL-BGN on March 22, 2010 for the construction of a 300 megawatt (MW) wind farm consisting of up to 200 wind turbines at the Hardin Wind

Farm in Hardin County, Ohio

On June 3, 2011, Applicant filed an amendment in Case No. 11-3446-EL-BGA (First

Amendment) which the OSB approved on August 29, 2011. The Order on the First Amendment permitted the Applicant to construct the Project in three phases and to use taller turbines in accordance with a modified plan.

On June 5, 2014, Applicant filed a Second Amendment, Case No 14-1030-EL-BGA, which it later withdrew and the OPSB dismissed it on November 12, 2105.

The Applicant seeks to further amend the Certificate through this Amendment (Third

Amendment). This Third Amendment does not change the phases as approved by the Board when it approved the First Amendment.

Section 4906-17-02 3 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(A) Project Summary and Facility Overview

Since filing of the First Amendment application, General Electric (GE) has introduced new turbine models that are more efficient and cost effective than the turbines approved in the First

Amendment. The Applicant proposes to build the project using a GE turbine, Model 2.3-116; however, the approved turbine site locations will not change.

Through this Amendment, the Applicant is proposing to amend the Certificate to change to the

General Electric turbine listed in Table 03-02. With the new turbine model proposed, the total capacity of the Hardin Wind Farm will not exceed the 300 MW permitted under the Certificate.

(1) General Purpose of the Facility

No change.

(2) Facility Description

No change.

(3) Site Selection Process

No change.

(4) Principal Environmental Considerations

No change.

(5) Project Schedule

With the exception of preparation of Final Design and Financing, which will occur in

Third Quarter and Fourth Quarter of 2016, the Facility Construction, expected to begin

during the Fourth Quarter of 2016; and the Commercial Operations are planned for the

Fourth Quarter of 2017, no change.

Section 4906-17-02 4 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-03 PROJECT DESCRIPTION AND SCHEDULE

(A) Proposed Facility Description

(1) Project Description

a. Types of Turbines

The Applicant is proposing to build the Project using the GE 2.3-116 wind

turbine.

b. Area Requirements

The impacted area will be greater during construction than during operation of the

wind farm. Estimated area required during construction and operations are each

summarized in Table 03-01.

Table 03-01. Estimated Area To Be Disturbed Project Area Area of Area of Total Total 35,900 Temporary Permanent Quantity Temporary Permanent Total Acres Disturbance Disturbance Disturbance Disturbance 2.9 acres per 0.04 acres per Turbines 118 turbines 342 acres 4.7 acres turbine turbine Access roads 75 feet wide 20 feet wide 34.4 miles 312.6 acres 83.3 acres Cables 30 feet wide None 45 miles 163.3 acres None Transformer 2 acres 2 acres 1 unit 2 acres 2 acres substation Interconnection 6 acres 6 acres 1 unit 6 acres 6 acres substation O&M building 6 acres 6 acres 1 unit 6 acres 6 acres and parking lot Laydown area 10 acres None 1 unit 10 acres None Permanent 0.55 acres / meteorological None 3 units 1.7 acres None met tower tower TOTAL 843.6 acres 102 acres Average per 7.2 acres 0.9 acres wind turbine

Section 4906-17-03 5 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

Notes: 1. During construction, the wind turbine assembly area will generally be a circular

area with a radius of 200 feet or less. The following construction activities will

take place within this area: foundation excavation and construction, crane pad

construction, component laydown and assembly.

2. During operation, the wind turbine footprint will include the turbine base and a

gravel apron approximately 15 feet wide.

3. The access road construction disturbance width includes area for a gravel

roadway and road shoulders to accommodate movement of the main erection

crane, area for topsoil stockpiles, and area for cable routes beside the road.

4. The access road disturbance width during operation includes area for a gravel

roadway and road shoulders.

5. The cable route construction disturbance width includes room for the actual cable

cut for machines needed to install the cable. The width in the table is the average

width for all cable circuits. Widths may be wider in corridors where more than

one circuit is installed and narrower in corridors with only one circuit. The

calculation of total area impacted temporarily for cable corridors conservatively

over estimates cable disturbances by assuming that no cable routes are in the road

disturbance area.

6. Area disturbances of substation, switchyard, and O&M building are assumed to

be the same as during construction.

7. Average area disturbance per turbine does not include the stationary areas for the

substation, O&M building, and laydown yard.

Section 4906-17-03 6 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

8. The Applicant may be installing up to three permanent meteorological towers to

monitor wind resources during operations. These permanent meteorological

towers will require access roads and underground utilities for their installation.

After construction, the roads will be re-graded and reseeded.

9. At the intersection of the access roads and public roads the turning radius will be

larger than that of typical public roads to accommodate the wind turbine

component delivery vehicles. This area will be re-graded and reseeded after

construction.

10. Temporary disturbances occur during project construction; permanent

disturbances are those that exist during project operation after construction is

complete.

As shown in Table 03-01, the Project would disturb approximately 2.3% of the Project area during construction and 0.2% of the Project area permanently. Table 03-01 is based on the

Project using 118 wind turbines. The areas in this section are conservative estimates that are provided to illustrate the maximum expected area disturbances. Actual disturbed areas should be less.

(2) Description of Equipment

The proposed wind turbines are similar to the GE 1.6-100 that was approved in the First

Amendment. The differences between the proposed GE 2.3-116 turbine and the GE 1.6-

100 turbine are summarized in Table 03-02 below.

Section 4906-17-03 7 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

Table 03-02. Turbine Data Comparison

GE 2.3- Turbine GE1.6-100 116 Model 100m HH 80m HH* OPSB Status Approved Proposed for Hardin (Amend 1)

Rotor 100 m 116 m Diameter (328 ft) (380.6 ft)

100 m 80 Hub Height (328 ft) (262 ft)

150m 138m (453 Tip Height (492 ft) ft)

Maximum 1.6 MW 2.3 MW Generation

Wind Speed 3.0 m/s 3.0 m/s at Cut-In Wind Speed at Rated 11.5 m/s 11.5 m/s Power Wind Speed 25 m/s 22 m/s at Cut-Out Maximum Rotational 16.7 rpm 15.7 rpm Speed Maximum Sound Power 105 dB 107.5 dB Level Reference Wind Speed 37.5 m/s 38 m/s (Vref)

*The GE 2.3-116 presents an option to utilize modified blades (the 2.3116 LNTE option) that can reduce potential noise from operations. The Applicant will evaluate utilizing the 2.3116 LNTE option should noise mitigation be required to meet OPSB conditions in specific turbine locations.

Section 4906-17-03 8 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(3) Description of New Transmission Lines

No change from First Amendment.

(B) Detailed Project Schedule

(1) Project Schedule

Figure 03-01 is the Project schedule bar chart.

a. Land Acquisitions and Land Rights

No change.

b. Wildlife Studies/Surveys

No change.

c. OPSB Application Preparation

No change.

d. OPSB Application for Certificate Submittal

No change from First Amendment.

e. Issuance of the OPSB Certificate

No change.

f. Preparation of Final Design

The Applicant will prepare the final design of the turbine sites using only the sites

approved in the First Amendment during the three to six months preceding start of

construction.

g. Facility Construction

Wind farm construction is scheduled to begin in the Fourth Quarter of 2016.

Construction of the interconnection facilities is scheduled to begin in the Fourth

Quarter of 2016.

Section 4906-17-03 9 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

h. Placement of Facility in Service

The wind farm is scheduled to begin commercial operation in the Fourth Quarter

of 2017.

(2) Delays

No change except of the three potential delays described in the Application; the financing

and interconnection are no longer considered potential delays. PJM has completed

facilities studies for the Project and entered into an Interconnection Services Agreement

for the Project with AEP and the Applicant.

Figure 03-01 Project Schedule 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 Year 0 0 1 1 1 1 1 1 8 9 0 1 2 5 6 7 Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Land Lease Acquisition

Wildlife Studies/Survey OPSB Application Submittal Issuance of the OPSB Certificate Preparation of Final Design

Project Financing Construction and Placement of Facility in Service

Section 4906-17-03 10 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-04 PROJECT AREA ANALYSES

(A) Site Selection Study

(1) General

No change.

(2) Constraint Map

Maps of these constraints for the proposed turbines are provided as Attachment C.

(B) Summary Table of Evaluated Sites

No change.

Section 4906-17-04 11 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-05 TECHNICAL DATA

(A) Project Area Site

(1) Geography and Topography

No change.

(2) Aerial Photograph

No change.

(3) Site Mapping

No change.

(4) Geology and Seismology

a. Site Geology

No change.

b. Soil Suitability

No change.

(5) Hydrology and Wind

a. Water Budgets

No change.

b. Floods and High Winds

The GE 2.3-116 is designed to withstand a Reference Wind Speed of 38 m/s, and

a 50-year Return Gust Speed of 42.6 m/s. The GE 2.3-116 turbines proposed for

the wind farm are rated to withstand wind speeds well in excess of the Project

area specific Reference Wind Speed of 19.2 m/s and 50-year Return Gust Speed

of 26.9 m/s.

Section 4906-17-05 12 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

c. Maps

No change.

(B) Layout and Construction

(1) Project Area Site Activities

No change.

(2) Layout Map

With the exception that not all of the turbine sites approved in the First Amendment will

be used, no change.

(3) Structures

a. Estimated Overall Dimensions

With the exception of the dimensions of the proposed GE 2.3-116 wind turbine as

shown on Table 03-02, no change.

b. Construction Materials

No change.

c. Color and Texture of Facing Surfaces

No change.

d. Photographic Interpretation or Artist’s Pictorial Sketches.

No change.

e. Unusual Features

No change.

Section 4906-17-05 13 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(4) Plans for Construction

Except that access roads may be built using cement stabilization instead of geotextile

fabric, and at some turbine sites soil remediation measures will be installed prior to

forming and installing the foundation re-bar, no change.

(5) Future Plans

Except that Applicant is proposing to construct Phase 1A of the project in 2016 and 2017,

no change.

(C) Equipment

(1) Wind-Powered Generation Equipment

Except for the differences between the proposed turbines and those approved for First

Amendment that are listed in Table 03-02, no change.

(2) Safety Equipment

a. Description of All Proposed Public Safety Equipment

No change.

b. Description of the Reliability of the Equipment

No change.

c. Description of Turbine Manufacturer’s Safety Standards

The draft safety manual for GE turbine model 2.3-116 is attached as Attachment

F.

(3) Any Other Major Equipment

No change.

Section 4906-17-05 14 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(D) REGIONAL ELECTRIC POWER SYSTEMS

No change except that the Applicant, PJM, and AEP executed an Interconnection Construction

Service Agreement (ICSA) and an Interconnection Service Agreement (ISA) for PJM queue position #U2-041 in June 2013. Under the terms of these agreements, the Applicant will self- build the interconnection switchyard.

Section 4906-17-05 15 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-06 FINANCIAL DATA

(A) Ownership

No change.

(B) Capital and Intangible Costs

No change.

(C) Operation and Maintenance Costs

No change.

(D) Delays

No change.

Section 4906-17-06 16 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-07 ENVIRONMENTAL DATA

(A) General

No change.

(B) Air

No change.

(C) Water

No change.

(D) Solid Waste

No change.

Section 4906-17-07 17 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

4906-17-08 SOCIAL AND ECOLOGICAL DATA

(A) Health and Safety

(1) Demographic Characteristics

No change.

(2) Noise

a. Construction Noise Levels

No change.

b. Operational Noise Levels

The Project will meet the criteria listed in Condition 36 of the Staff Report and Condition 36 of the Opinion, Order and Certificate with regard to Operational Noise Levels. The Applicant retained Acentech to evaluate compliance with this Condition. Assumptions and methodologies were held consistent with the noise impact assessment conducted for the Application. Based on the assumptions and methodology described in the Attached Noise Impact Assessment

(Attachment G), the Applicant will meet or exceed this criterion.

c. Noise Sensitive Areas

No change.

d. Mitigation of Noise Emissions

No change.

(3) Water

No change.

(4) Ice Throw

No change.

Section 4906-17-08 18 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(5) Blade Shear

No change.

(6) Shadow Flicker

The Project will meet the criteria listed in Conditions 33, 34 and 35 in Opinion, Order

and Certificate. The Applicant retained Tetra Tech to evaluate compliance with this

Condition. Assumptions and methodologies were held consistent with the shadow flicker

analysis conducted for the Application. Based on the assumptions and methodology

described in the attached Shadow Flicker Analysis (Attachment H), the Applicant will

meet or exceed this criterion.

(B) Ecological Impact

(1) Project Site Information

a. Mapping

No change.

b. Vegetative Survey

No change.

c. Animal Life Survey

No change.

d. Summary of Ecological Studies

Except for the studies conducted and submitted to the OPSB Staff in 2014, no

change from the First Amendment.

Section 4906-17-08 19 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

e. Major Species List

No change.

(2) Construction

No change.

(3) Operation

a. Estimate of Operation Impact on Areas

Area impacts are provided in Table 03-01.

b. Estimate of Operation Impact on Major Species

No change.

c. Mitigation of Impacts

Applicant plans to design, construct, and operate the Project using practices to

avoid or minimize impacts to birds and bats and will document these practices in

a Bird and Bat Conservation Strategy (BBCS) developed in consultation with the

Ohio Department of Natural Resources in coordination with the U.S. Fish and

Wildlife Service.

d. Post-construction Monitoring of Wildlife Impacts

Specific protocols for post-construction monitoring for bird and bat impacts will

be outlined in the BBCS.

(C) Economics, Land Use and Community Development

(1) Land Uses

a. Land Use Map

No change.

Section 4906-17-08 20 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

b. Residential Structures

In April 2014, the Applicant updated its survey of residences in the Project area.

Figure 08-01 shows the residence locations in and within 1,000 feet of the Project

area.

Table 08-01 shows the number of wind energy facilities (other than turbines)

within 100 feet of a residence. The Applicant will continue to work to locate

wind energy facilities as far from residences as practicable. In the case of access

roads located near residences, this is a result of the Applicant using existing roads

or fence lines on landowner’s property as access roads for the wind farm to

minimize new ground disturbance.

Table 08-01. Wind Energy Facilities within 100 feet of a Residence

Underground Permanent Wind Access Distance Collection Substation Meteorological Turbines Roads System Tower <100 feet 0 0 0 0 0

c. Wind Turbine Structure Locations

(i) Property Line Setback

No change from the First Amendment.

(ii) Residence Setback

No change from the First Amendment.

(iii) Waiver of minimum setback

No change.

Section 4906-17-08 21 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

d. Impact of Proposed Facility

Except for the fact that Applicant will use fewer turbine sites than those

previously approved which will lessen overall impacts, no change.

e. Identification of Structures to be Removed or Relocated

No change.

f. Plans for Future Use

No change.

g. Concurrent or Secondary Uses

No change.

(2) Economics

a. Estimated Payroll

Except for an updated estimated on-site construction cost of $65 million to $75

million, construction payroll is expected to range between $19.5 million and

$22.5 million, no change.

b. Estimated Employment

(i) Construction Employment

No change.

(ii) Operations Employment

No change.

c. Estimated Tax Revenue

R.C. 5727.75 allows Ohio wind energy facilities to enter into payment in lieu of

taxes (PILOT) agreements, bringing Ohio's tax rates for wind farms. On

October 5, 2010, Hardin County Commissioners passed a resolution to make

Section 4906-17-08 22 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

Hardin County an Alternative Energy Zone working in coordination with SB 232

for PILOT agreements. The PILOT payment is $9,000 per MW of installed

capacity, which would result in the Project making PILOT payments to Hardin

County in excess of $1.5 million each year.

d. Estimated Economic Impact

No change.

(3) Public Services and Facilities

No change.

(4) Impact on Regional Development

No change.

(D) Cultural Impact

(1) Map of Landmarks of Cultural Significance and Recreational Areas

No change.

(2) Estimated Impact on Landmarks

a. Cultural Resources

No change.

(3) Historical Resources

No change.

(4) Consideration of Landmarks

No change.

(5) Mapping Landmarks

No change.

Section 4906-17-08 23 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

(6) Recreational Areas

No change.

(7) Visual Impacts

No change.

(E) Public Responsibility

(1) Public Information Program

No change.

(2) Liability Insurance

No change.

(3) Evaluation of Interference with Radio and Television

a. Microwave Paths

No change from the First Amendment. The Project will meet the criteria listed in

Conditions 7 and 8 from the Order in the First Amendment.

(4) Evaluation of Interference with Military Radar and FAA

a. Military Radar

No change.

b. FAA

No change.

(5) Evaluation of Impact to Roads and Bridges

No change other than in August 2010, the Applicant entered into a Road Use

Agreement with Hardin County and the host townships. The Road Use

Agreement requires the Applicant to perform a pre-construction road survey and

to correct damage to local roads that may be caused by the Project. Prior to

Section 4906-17-08 24 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

construction, the Applicant will conduct a road survey and assess potential

impacts and mitigation efforts in coordination with the Hardin County Engineer.

(6) Plan for Decommissioning

No change.

(F) Agricultural District Impact

(1) Agricultural and Agricultural District Land

No change.

(2) Agricultural Land Impacts

No change other than those noted on Table 03-01, which summarizes the temporary and

permanent area disturbances expected for the Project.

(3) Impacts to Agricultural Lands Viability

No change.

Section 4906-17-08 25 10015520v7 Hardin Wind Energy LLC Application for Third Amendment March 2016

CERTIFICATE OF SERVICE

I hereby certify that the foregoing Application for Third Amendment was served upon the parties of record from Case Nos. 09-469-EL-BGN and 11-3446-EL-BGA via electronic mail this

23rd day of March 2016.

Sally W. Bloomfield

Philip B. Sineneng Chad A. Endsley Thompson Hine LLP Chief Legal Counsel Huntington Center Ohio Farm Bureau Federation 41 South High Street, Suite 1700 280 North High Street Columbus, Ohio 43215-6101 Columbus, OH 43218-2383 [email protected] [email protected]

John H. Jones Sarah Anderson Bloom Sarah Anderson Assistant Attorney General Assistant Attorney General Environmental Enforcement Section Public Utilities Section Office of The Attorney General 180 East Broad Street, 6th Floor 30 East Broad Street, 25th Floor Columbus, OH 43215 Columbus, OH 43215 [email protected] [email protected]

Section 4906-17-08 26 10015520v7 ATTACHMENT A: PROJECT LAYOUT Date Saved: Wednesday, March 23, 2016 10:35:44 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_turbinelayout_lett.mxd LLII B E R T Y W A S H IIN G T O N M A R II O N «¬701 C E S S N A

7

74 8 5

4

80 309

T «¬

S

T 84 N 112

O 9 != R 8

F A

N A

N 5

1 N 111

N 1

O N 90 O = I ! I 5

S

S

0 113

R 1

R

S = 1 5 92 S !

A = A = E ! 12 E 2 ! = M 94 195 M C != 6 ! C 114 != 115 != «¬ 91 != 97 = != = = ! != 7 13 ! = ! != 3 != 83 88 92 ! 124 != 116 = != 85 != 98 8 ! 9 != != != 117 != = 14 != 5 != 4 ! 9 5 84 = = 3 ! ! 100 86 123 != 118 != 20 != 15 != 10 39 101 != 78 != = 16 = != = 103 ! != 11 = ! ! = 104 21 ! 40 76 = ! != 105 != 17 != 127 = 79 ! 108 121 != 132 41 != != ! = != != 18 != != = != 77 ! 104 22 ! != 42 131 != 110 106 != = 80 109 23 ! 133 != = 43 != != 19 ! = 107 33 = 24 125 ! 130 = 35 ! = != 110 ! != = ! 27 44 != 8 ! 5 = 25 34 30 ! != = 46 != 126 4427 != = 28 ! ! = M 10 ! M V# 6 32 = 116 ! = C 26 C != 31 29 47 ! L D L != D = Y ! Y 48 O 120 O 49 N N

38 N = N ! N != N 235 A 4428 A «¬ != 37 50 !=

L 126 V#52 L = 59 D ! D 51 != !=

!= 53 = 7 60 ! 9 M M A R II O N = 54 = 61 ! ! 1 3 = 55 0 R O U N D H E A D ! != B = 130 = 62 ! 63 1 ! 56 3 0 != A 57 != 58 64 !=

9

1 = 140 65 ! != 129 = ! 66 != 73 37 != 1 67 5 7

0 != 68 5 71 != != 69 != = 72 ! 70 6 4426 5 V#

152 154

2 1 102 !=

5 5

2 5 81 = 160 !

DD 1

1 D D

AA 9 L L 67 EE ¬« 99 1 A 70 A

H H !=

N N N D Y N N D LL Y N

O O

N N 180 R E E K D C E D R

U 9 R C 117 U T A Y LL O R ¬ 3 T « C

C O

O

R M R M

Legend != Amendment 3 Turbine Site Collector Substation Collection Line Township W Access Road 0.5 0 0.5 V# Permanent Met Tower Miles

Proposed Project Layout Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 ATTACHMENT B: LAYOUT COMPARISON MAP Date Saved: Wednesday, March 23, 2016 10:46:30 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_comparison_lett.mxd

5

0 7

1 8 8 0 5

4

84 112

9 =!

8

A N A 111 N = 90 ! 5

N

O N O 113 1

I 1

I

S = 5 92 S !

R = R = ! S S 93 ! 1 90 114 A = 2 = A = ! E =! 6 12 ! E ! =! =! 13 =! M 94 = 195 M C ! =! C = = «¬ =! ! 97 309 115 ! 7 91 =! 124 «¬ = =! = 83 ! 3 ! 14 =! 88 =! 116 8 =! =! 85 =! =! 92 =! 98 117 = =! 96 =! ! 4 =! 9 84 5 =! = 123 =! 3 86 ! 100 =! 118 =! =! 100 87 =! 15 =! 10 39 = =! 78 121 20 ! 21 = 101 =! =! 16 = ! =! C ! 11 =! 40 =! E S 104 76 =! 79 =! S N =! 17 = 108 = N A ! =! 41 =! =! ! A 132 =! 80 =! 104 =! L 18 =! =! 22 = =! Y N 127 ! = 131 77 = NN ! 42 = ! 109 19 =! = ! 122 ! 23 =! =! = 133 =! 43 =! 110 ! 107 82 =! 130 33 = 9 35 ! = = NN 24 ! ! 44 110 5 =! =! = 27 OO DD =! 125 ! II LL =! 45 RR = 34 30 25 =! = AA AA ! 126 =! = 28 ! ! =! MM NN 1 47 OO 06 116 32 26 =! 29 46 =! DD =! 31 CC =! 128 =! MM =! 120 49 48 38 =! 37 =! =! =! 50

6

12 7 6 M 51 =! 59 M =! =!

C C

=! 52 7 = L 53 ! 60 D L 9 D

Y Y M A R O M A RII O N =! 54 =! 61 O 235 N 1 N 3 N «¬ N = 0 = N ! 55 N R O U N D H 62 ! B N D H E A D 63 A E A D A = =! 130 L 1 ! L 56 3 0 = D ! 64 D A 57 =! =! 65 58 9 =

1 ! 140 =! 129 = 73 ! 66 =!

37 67 =! 1 68 5 =! 74 0 71 =! =! =! 69 =! 75

7 =! =! 5 72 70 6

5

119 152 =! 154 2 =! 1 120 102 =!

5 5 2 DD 5 81 AA DD =! EE 160 LL HH AA

DD NN

NN OO

U U DD «¬67 O O 170 CC

R = 1 R ! 99 MM Y N N 1 = LL Y N 9 89 ! 95 =! 180 C R E E K T A Y LL O R C

117 9 «¬ 3 8

5

190 Legend =! Amendment 3 Turbine Site =! Amendment 1 Turbine Site W Township 0.5 0 0.5

Miles

Layout Comparison Map Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 ATTACHMENT C: CONSTRAINT MAP FOR GE 2.3-116 ON 80m HH ") ") ") ") ") ") Date Saved: Wednesday, March 23, 2016 10:45:25 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_fig04-01_constraint_map_lett.mxd ") ") ") ") ") ") ") ") 5 ")") ") 0 ") ")") 7 ") ") ") ") ") ") 1 ") ") ") ") ") ") ") ") ") 8 ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") 8 ") ") ")") ") ") ") 0 ")5 ")") ") ") ") ") ")") ") ")")") ") ")") 4 ") ") ") ") ")")")T ")") ") ") ") ") ") ")") ") ") ") ") ") ") ") ") S ") ") ") ") ") ") ") ")") ") ")") ")")")")")") ") ") ") ") T ")") ") ")")")")") ") ") ") ")")")")")")")") ") ") ") ")") ")")N ")") 84 ") ")") ")")")")")")") ") ") ") ")") ") ") 112 ")")") ") ")")")") ")")") ")") ") ")") ") ") ") ")")") ") O ") ") ") ") ") ") ")")")")")")") ") ") ") ") ") ") 9 = ") ")")")")")")")")")")")") ") ") ") ") ! ")")")")")")") R") ") ")")") ")")") ") ") ") 8 ") ") ")")")")")")") ") ") ") ") ")")")")")")")")F ") ") ") ") ") ")") ") ") ")") ") ")") ")")")")") ") ")") ") ") ") ")")")")")")")")")")")")")") ") ") N ") A ")") ") ")")")")")")") N ") ")") ")")") A 111 ") ")")")")")")") ")") ") ")") N ") ")")")")")") ") ")")")") ") ") = 9 ")")") 5 ") ")")") ")")")")") 0 ") ! ") ") ") ") ")") ")")")")") N ")")")") ") O ") ") ") ") ") ") ")")")") N ") ") ") ") ") ") ") ")") ")")")")")") ") ") ")")")")") ")") O 1 ") ") ")")")")")")")")")")")")")")")")")")") ") ")") 113 ") I ")") ") ") ") 1 ") I ") ") ")") S ") = ") 5 92 ") S ! ") 1 ") ") ") ") ") ") ") ") R ") 309") ") ") = R ") ") = ! S ") ") ") ") ! S «¬ ") ") 114 A ") = A ") ") E ") = 12 ! E 94 ") = ") = ! 6 ") ! 115 ") ! 13 =! ") ") ") 2 M 91 = 195 M ") C ! = C ") ") ! = =! 97 ") = ") «¬ ! ") ! 7 = ") ")")") ! ") = ") =! = ")")")")")") ") 83 124 ") ! 3 ! ")")")")")")") ") ")") = ") 11")6 ") 14 ") ")") ")")")")")")")") =! 88 ! ") ") ") 8 =! ")")")") ")")")")")")")")") ")") = = 98 ") ") ") ")")")")")")")")")")")")")")")")")")")") ! 85 =! 92 ! 117 ") ")")")")")")")")")")")")")")")")")")")")") ") ") ") = ")")")")")")")")")") = = ") ! =! ")") ")")")")")") ! 123 ! ") ") ") 4 9 ") ")")")")") 84 ") ") ")") 5 ")")")")")")")")")") = = ") ") ")")")")")")")") ! ! 3 ") ")") 86 = ") ") ")")") ") ! 118 = 10 ") ")") ") ") ") ") =! ! 0 ") ")") 15 =! ") ")") 10 = 101 ") ") ") = ! 78 = 121 ") ")") 20 ! 21 39 = ! ") ") =! 16 = ! =! C ") ") ") ! 11 = ") = 104 E S ") ") ! 40 ! SS ") 104 ") = 76 =! 79 =! S N ! 17 =! 127 = 108 =! A ") =! 41 =! ! = =! ") 132 =! ! ") L ") ") ") ") 18 =! = = 80 Y") ") ! =! ! ") N") ") =! 42 131 77 = 109 ") N ") ") ") ") ! ") ") ") ") ")")")")") ") ") =! 22 = ") ")")") ") ") ") ") ") ") ") 19 ! = = ")") ") ") ") ")")")") ") 23 ! = ! ") ") ") ") =! ")") ") ") ") 133 ! 43 110 ") ")")") 107 ") ") ") = ") ! ")")")") 33 = ") ") ")") 130 ") ") ") ! NN 125 ") ") ")")")") ") ") = 35 24 =! =! 44 DD 110 ") ") ") ") ! =! = 27 OO =! ") ! II L ") ") L ") = 45 RR ") ") ") ") 34 ") 30 ! 25 AA =! ") ") ") =! =! AA 126 4427 ") ") = = 28 ") ") ! ! = MM NN ") ") ") M ") ") ! M # 106 ") ") ") V ") ") 47 OO ") ") ") ") ") ") 26 =! = ") ")") ") ! D C ") 116 = 29 46 D C ") ") ! 32 CC 9 L = D L ")5 ! 31 = MM ") D ") 48 ! Y ") ") Y ") O ") O ") 120 ") N ") N ") ") ") 38 = N ") ") ! N ") ") ") 49 N ") ") 37 =! N ") 235 ") O ")") ") ") ") ") A ") ") = = h ") ") A «¬ ! ! io ") ") ") ") ") ") 50 Po ") ") ") ") L ") ") ") we L ") 1")26 ") ") = V# r") C 51 ! 59 D o D ") =! =! (13 ") 8 k ") ") V ") ") =! 53 52 =! 60 ) 7 ") 9 M ") ") M A R II O N =! 54 =! ") 61 1 ") 3 =! 55 = ") ") ") 0 R O U N D H 62 ! ") ") ") ") ") B ") N D H E A D 63 ") ") ")")") ") ") ") 0 =! ") ") 13 =! ") ") ") 1 ") ") 56 ") ") ") ") ") ") 3 ") ")")") ") ") ") ") ") ")")") ") ") ") =! ") O ")0 ") ") ") ") ") 64 ") ") hio A ") Pow ") 57 =! ") er C ") o ( ") 13 ") = 8 k ") ") ! 58") ") ") ") V) ") ") ") 9 ") = 1 ") 140 ! =! ") ") 65 129 ") = ")") ") ! 66 =! ") ")")") ") ") ")

1") ") 37 67 =! ") ") ") ") ") ") ") ") ") ") ") 73 ") ") ") ")5 ") 68 O ") ") ") 0 ") ") ") ") = ") h ") ! io ") ") ") ") ") ") ") ")") ") ") ") ") 71 P ") ")") ") ") o ") ") =! =! ") w ") ") ") ") ") 69 e ") ") ") ") ") ") ") r 7 ") ") ") C ") = 5 ") ") ") ! =! ") o ") ") ") 72 70 6 ") ") ") ") ") ") ") ( 4426 ") 5 3 ") ") ") ") ") 4 ") ") ") ") ")")") ") ") ") ") 5 ") ") k V# ") ") V ") ") ") ) ") ")") ") ")") ") ") ") ") ") ") ") ") ") 152 ") O ") 154 ") ") ") ") ") ") ") h ") ") ") io ") ") 2 ") ") ") ") ") ") P") ") ") ") 1 o 102 ") ") ") w ") = ") e ")") ")") ") ! ") r ") ") 5 5 ") ") ") C ") ") ") ") 2 ") DD 5 o ") ") ") ") ") ") ( A 3 ") ") ") ") A D = 4 ") ") D ! 81 5 EE ") ") ") ") 160 LL ") k V ") ") HH ")) ") AA ") ") ") ") ") ") ") ") DD ") ")") ") ") ") NN ") ")") ") ") ") NN ") ") ") ") OO ") ") ") U ") U DD ") ") ") ¬67 ") « ") ") ") ") ") ") ") O ") ")") ") O C ") ") ") C ") ") 170 ") ") ") ")") ") ") ") ") R = 1 R ") ") ! 99 ") ") MM ") ") ") 1 ") ")Y N N") ") ") ") ") ") LL")Y N") ") ") 9 ") ") ") ") ") ") 180 ") ")") ")") R E E K ") ") L O R C R ") ") ") T A Y L O ") ") ") ") ") ") ") ") ") ") ") ") ") 11") 7 ") ") ") 9 ") ") ") ") ") «¬ ") 3 8 ") ") ") ") 5 ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") 190 ") ") ")") ") ") ") ") ") ")")")") ")") ") ") ")")") ") ") ") ") ") Legend ") ") Non-Participating Residence Stream, River or Lake ") Participating Residence Township V# Permanent Met Tower Transmission Line W Wetlands =! Amendment 3 Turbine Site 0.5 0 0.5 Wind Turbine Setback Collector Substation Miles

Constraint Map: Amendment 3 Layout Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 ATTACHMENT D: PROJECT LAYOUT MAPBOOK Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index W LEE ST E LEE ST

T

T

S

S

N

T

I

N

A

O

M

R

S

F 4 S 92 1 2 3 5 6 7 5 1 != 8 != 9 «¬235 12 10 6 != 2 != 11 != 13 != 7 != 3 != != 8 != W 1,000 0 1,000

Feet 4 9 != != 1:20,000 Scale

5

3 100 Legend 20 15 != != 10 Proposed != != Turbine Site 21 Proposed != 16 Access Road != 11 != Proposed Collection 17 System != 127 != Township

18 != 22 !=

110

Amendment 3 Layout Summary (Map 1 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

90 4 1 2 3 5 6 7 8 9 10 11 92

!=

14 W A N A RAI N != T LRO A N O N

S D S O T 83 I

I

S

T != S

S R

R

S 84 S

E

T

A A W = E

S ! E W HUNS IC = KER ST ! 1,000 0 1,000

M T M C

C

W SOUTH S H T E SOUTH ST 85 Feet G I MAIN != R ST 1:20,000 Scale

T

R U KENTON ST 86 O = C ALICE ST !

100 W COTTONWOOD RD Legend

!= Proposed Turbine Site 39 «¬195 != Proposed 78 Access Road != 40 Proposed != Collection 79 != System 76 Township 41 131 != != != 80 77 != 132 != != !=

Amendment 3 Layout Summary (Map 2 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

5 8 4 1 2 3 5 6 7 90 8 309 «¬ 9 10 11 94 != 97 91 = != ! 124 != 98 != 88 92 W = = ! ! 1,000 0 1,000

117 Feet != 1:20,000 Scale

5 123 9 != != Legend

!= Proposed 100 Turbine Site AA DD NN LL 101 Proposed SS AA = SS NN ! EE 121 Access Road OO = CC DD ! CC 103 Proposed MM != C E S Collection S N M 104 A M A != L Y System C N C NN

L D L 105 D

Y = Y ! Township O O

N N

N 106 108 N N = N != A ! A

L L

D D

!=

9 1 8 06

Amendment 3 Layout Summary (Map 3 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

80 4 1 2 3 5 6 7

112 8 != 9 10 11

111 !=

113 != W 1,000 0 1,000

5

1 Feet

1 1:20,000 Scale

5

0

1 90 114 != Legend 115 != != Proposed Turbine Site Proposed 116 != Access Road Proposed Collection System 117 «¬309 != Township

118 !=

100

Amendment 3 Layout Summary (Map 4 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

!= 4 5 != 1 2 3 3 != 5 6 7 19 != 23 8 != 133 != 9 10 110 11 24 != 27 33 != != 34 35 != !=

25 != 28 W != 1,000 0 1,000 30 = 26 ! != Feet 1:20,000 Scale

29 != 32 Legend != != Proposed 31 Turbine Site != Proposed Access Road 120 Proposed Collection System 38 != Township 37 !=

Amendment 3 Layout Summary (Map 5 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

AA DD

A N NN A N SS LL

N

O N O SS AA

I

I S NN S EE

R R CC OO S S DD A

A E 4 = E CC

! M M C 1 2 3 C MM != 42 != 5 6 7 195 109 «¬ 8

43 != 9 != 10 NN OO DD 11 II LL RR AA AA NN 110 44 MM OO != DD CC 125 MM !=

126 != W 45 != 1,000 0 1,000 Feet 46 != 1:20,000 Scale

47 != Legend

6 Proposed 5 != Turbine Site

7 48 5 != Proposed Access Road Proposed Collection 49 != System V# Permanent Met Tower 50 != 120 Township 4428 V#

6

7

7

9

Amendment 3 Layout Summary (Map 6 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

4 1 2 3 5 6 7 8 110 = 107 ! 8 9 9 != 10 130 != 11

110

M 1 M 06

C C

L D L D W Y Y

O O 1,000 0 1,000 N N

N N

N N Feet

A A 4427

L 1:20,000 Scale L

V# 9

D D 5

8 5 Legend

= Proposed 1 !

0 5 Turbine Site Proposed Access Road Proposed Collection System V# Permanent Met 120 Tower Township

7

9

Amendment 3 Layout Summary (Map 7 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

4 1 2 3 V# 5 6 7 51 != 8 52 != 59 9 != 10 11 53 6

= 5 ! 6

60 7 !=

54 61 != != M A R II O N W R O U N D H E A D 55 1,000 0 1,000 = 62 ! != Feet 1:20,000 Scale

63 56 != != Legend

64 = Proposed != ! 130 Turbine Site

57 Proposed != Access Road

5 5 DD AA Proposed EE DD 58 L = HH L ! Collection AA DD NN NN System OO UU DD OO Permanent Met CC V# 65 RR != MM Tower Substation 129 != Collector Substation != Township !=

Amendment 3 Layout Summary (Map 8 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

130 4 != 1 2 3 5 6 7 8 9 65 10 != 140 11

66 != 73 !=

37 67 != W 68 1,000 0 1,000 != Feet 1:20,000 Scale «¬235 69 71 != != Legend

!= Proposed Turbine Site 72 = DD 70 ! AA = EE ! Proposed HH DD DD LL Access Road NN AA UU NN OO OO 150 RR DD Proposed CC MM Collection System Township

5

5

Amendment 3 Layout Summary (Map 9 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

4 1 2 3 5 6 7

M M

C 8 C

L D L D

Y Y

O O 9

N N 10 N N

N N

A A

L L 11

D D W

6

5 1,000 0 1,000

Feet 1:20,000 Scale

7

5

150 Legend Proposed Collection System Township

154

!=

Amendment 3 Layout Summary (Map 10 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 Date Saved: Wednesday, March 23, 2016 10:42:27 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mapbook_lett.mxd Index

4 1 2 3

!= 5 102 8 6 7

5 8 9 10 11 81 !=

6 5 W 1,000 0 1,000 ¬67 « Feet 1:20,000 Scale

7

5

Legend

!= Proposed Turbine Site

M M

C 99 C Proposed

L D L != D

Y Y O Access Road O

N N

N N

N N

A Proposed A

L L Collection D D System Township

T T

A A

M Y M Y

L C L C

O O D D

R R O 180 O

N N C C

A A R R

L L E E

D D

E E

K K

Amendment 3 Layout Summary (Map 11 of 11) Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 ATTACHMENT E: HOUSE LOCATIONS " " " " " " Date Saved: Wednesday, March 23, 2016 10:47:16 AM Prepared By: emedina Path: \\arcgis-db\d\_MXDs\US\OH\Hardin\hardin_opsb_mwave_lett.mxd " " " " " " " " " " " " " " "" 7 " " " " " " " " " " " " " 8 " " " " " " " " " " " " " " " " " 8 " " "" " " " 0 "5 "" " " " " "" " """ " "" 4 " " " " """"" " " " " " "" " " " " " " " " " " " " " " "" "" " "" """""" " " " " " """"" " " " """""""" " " " 84 " "" """" " " " """" """""""""" " """"" "" " " " """ " """" " " " "" " " """"""""""" " " " " " " " 9 " """"""""""" " " " " """ """ " " " 8 " " """"""" " " " " """""""""" " " " " " " """"" " "" " " " """""""" """"" " " """"""""""""""" " """"""" "" " "" " """""" " """" " " " 9 """ 5 " " " " """" " """"" 0 " " " """"" " A " " " " """ N " " A " " " " " " " """"" 5 1 " " " " """" " " """" "" N " " """"""""""""""""""" " "" " " " " 1 " " 0 " "" " " " " " N " O N 1 " 9 O " " " " " " 2 " " " " " " I " " I " " " " S " S " " " " R 309 " R S " " S " ¬ " « " " " A

195 A " E " " " " «¬ E " " " "" M "" M C " """ " C " """"""" "" " " " """""""""" " " " " """ "" """ "" " " " """"""""""""""""""" " """"""""""""""" """"" 5 " " " " " """"""""" " "" " 9 " "" """""" " " " " """"" " " "" 5 """""""""" " " """""""" 3 " "" " " """ " 100 " "" " " " " " "" "" " " " " " " " " C E " " " " " S S " " " S N " 104 N A " " " L " LY " " " " " N " "" "N " " " " " " " " """"" " " " """ " " " " " " " "" " " " """" " " " " " "" " " " " """ " " " " """" 110 " " "" " " " NN " " """" " " D " " " " OO D " II LL " " RR " " " " " " " " " AA AA " " " " MM NN " " " " 106 " " " " " " OO " " " " " " " "" " 116 DD " " CC " MM " " " " " " " " 120 " " " " " " " " " " " " " " "" " " " " " " " " " " " " " " " " " " " " " 1"2" " " " 6 M M "

" C 6 C " " " " 7 7

L D L " 9 D

" Y Y " M A R O " M A RII O N O 235 N 1 N 3 N «¬ N " " 0 N " N " " " R O U N D H " " " " " " " B N D H E A D A " " E A D A " " " " " 1"30 " " L 1 " " " "L " " " " "" " 3 "" """ " " "0 " " " " " " D " " " " D " " " " A " " " " " " " " " " " " " " 9 " 1 " 140 " " " " "" """ " " "

1" " 37 " " " " " " " " " " " " " " "5 " " " " 0 " " " " " " " " " " " " " "" " " " " " "" " " " " " " " " " " " " " " " " "" " " 7 " 5 " " " " " " " 6 " " " " " " " " " " 5 " " " " " " " " " " " " " " " " " " " " " "" " "" " " " " " " " " " 152 " " 154 " " " " " " " " " " " " 2 " " " " " " " 1 " " " " " " " " "" "" " " " " 5 5 " " " " " " " 2 " DD 5 " " " " " " A " " " " A D " " D EE " " " " 160 LL " " " HH " " AA " " " " " " " " DD " "" " " " NN " "" " " " NN " " " " OO " " " U " U DD " " " ¬67 " « " " " " " " " O " "" " O C " " " C " " 170 " " " "" " " " " R 1 R " " " " MM " " " 1 " "Y N N" " " " " " LL"Y N" " " 9 " " " " " " 180 " "" "" R E E K " " L O R C R " " " T A Y L O " " " " " " " " " " " " " 11" 7 " " " 9 " " " " " «¬ " 3 8 " " " " 5 " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " " 190 " " "" " " " " " """" "" " " " " " " " " Legend " " Receptor Wind Turbine (116m Diameter) W Township 0.5 0 0.5

Miles

Receptor Summary Rev. 00 One South Wacker Drive Suite 1800 Chicago, Illinois 60606 Hardin Wind Energy Center, Hardin County, Ohio March 23, 2016 (312) 224-1400 ATTACHMENT F: GE WIND TURBINE DRAFT SAFETY MANUAL GE Energy

Technical Documentation Wind Turbine Generator Systems 1.x Series

Safety Manual

-Please read first-

Gepower.com

Visit us at www.gewindenergy.com

imagination at work

© 2011 General Electric Company. All rights reserved GE Energy Safety Manual

All technical data is subject to change in line with ongoing technical development!

Copyright and patent rights

This document is to be treated confidentially. It may only be made accessible to authorized persons. It may only be made available to third parties with the expressed written consent of General Electric Company.

All documents are copyrighted within the meaning of the Copyright Act. The transmission and reproduction of the documents, also in extracts, as well as the exploitation and communication of the contents are not allowed without express written consent. Contraventions are liable to prosecution and compensation for damage. We reserve all rights for the exercise of commercial patent rights.

© 2011 General Electric Company. All rights reserved.

GE and are trademarks and service marks of General Electric Company.

Other company or product names mentioned in this document may be trademarks or registered trademarks of their respective companies.

imagination at work

1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Table of Contents

1 Basic Information on the Technical Documentation for GE Energy Wind Turbine Generator Systems ...... 5 Explanation of Abbreviations ...... 5 2 General Safety Principles ...... 6 2.1 Personnel Groups ...... 6 2.2 Proper Use ...... 7 2.3 General Information ...... 8 3 Marks, Signs and Symbols ...... 9 3.1 Danger Classifications and Symbols ...... 9 3.2 Marks and Signs attached by GE Energy ...... 9 4 Information for the Operator / Owner of the Wind Turbine Generator System ...... 23 5 Signs to be attached by the Operator/Owner ...... 24 6 Safety Equipment ...... 25 6.1 Personal Protective Equipment ...... 25 6.2 Safety Harness ...... 26 6.3 Protective Equipment for Measurements on Live Components ...... 31 6.4 Hooking Points ...... 32 6.5 Abseiling Device ...... 32 6.6 Fire Extinguishers (optional feature) ...... 36 6.7 First Aid ...... 38 7 Safety Devices ...... 39 7.1 Emergency Stop Pushbuttons ...... 39 7.2 Rotor Lock ...... 40 8 Residual Risks ...... 42 8.1 Special Dangers – Electric Power ...... 43 8.2 Special Dangers – Hydraulic System ...... 44 8.3 Special Dangers - Noise ...... 44 8.4 Special Dangers - Icing ...... 44 8.5 Exceptional Dangers – Earthquakes ...... 45 9 Safety Information for Individual Plant Components ...... 46 9.1 Down Tower Assembly ...... 46 9.2 Anemometer and Wind Vane ...... 46 9.3 Top Box ...... 47 9.4 Pitch Electrical Control Cabinets Inside the Hub - Axis and Battery ...... 47 10 Conduct in Emergency Situations ...... 48 10.1 Conduct in Case of Fire ...... 48 10.2 Escape Routes ...... 50 10.3 Information for Rescue and Emergency Personnel ...... 50 10.4 Oil Spill – Immediate Measures ...... 51 11 Remaining in and on the Wind Turbine Generator System ...... 52 11.1 Approaching and Entering Frosted Wind Turbine Generator Systems ...... 53 11.2 Shut-down of the Wind Turbine Generator System ...... 53 11.3 Climbing the Tower ...... 54 11.4 Deactivation of the ...... 55 11.5 Entering the ...... 55 11.6 Walking on the Roof of the Nacelle/Entering the Rotor Hub ...... 56 11.7 Activation of the Wind Turbine Generator System ...... 58 12 Information on Maintenance and Troubleshooting ...... 58 13 Power Disconnection and Isolation Procedures (Lock-out/Tag-out Instructions) ...... 60

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

13.1 Identification of Installations, Processes, Circuits ...... 60 13.2 Preparation for Shutdown / Notification of Affected Employees...... 60 13.3 Identification of Energy Sources and Strengths ...... 60 13.4 Deactivation of Energy Sources and the Mounting of Energy Control Devices ...... 60 13.5 Control of Stored Energy ...... 61 13.6 Verification of Isolation ...... 61 13.7 Reconnection of the Installation to the Supply ...... 61 ANNEX: Items and Installations which are subject to Inspection pursuant to the Accident Prevention Regulations ...... 63

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

1 Basic Information on the Technical Documentation for GE Energy Wind Turbine Generator Systems

This "Safety Manual" is a constituent part of the technical documentation for GE Energy wind turbine generator systems. In the case of offshore plants, the supplementary safety information for offshore plants is also to be considered.

The safety manual must be read and understood by the operating and maintenance personnel and the owner, in order to guarantee safety in and on the wind turbine generator system and to prevent accidents and personal injuries.

In addition to the safety manual, the respective specific safety information in the technical documentation, in which e.g. installation or maintenance is described, must always be read.

The basic rules of conduct for safe working in and on the WTG are described in this safety manual.

Any unclear points in the technical documentation, which may jeopardize the correct performance of work in or on the WTGS, must first of all be clarified. Contact GE Energy for advice if necessary.

In addition to the safety manual, the local safety and accident prevention regulations must be complied with to ensure the safety of personnel.

Explanation of Abbreviations

WTGS Wind Turbine Generator System

PPE Personal Protective Equipment

EHS Environment, Health & Safety

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 5/64 GE Energy Safety Manual

2 General Safety Principles

The GE Wind Energy 1.x Series Wind Turbine Generator System (WTGS) has been built according to recognized safety rules.

Hazards for the user or third parties and impairment of the wind turbine generator system and other property may nevertheless arise during the use of this facility if it is

• operated by untrained or uninstructed staff • not used properly • improperly maintained or serviced

The owner / operator responsible for the WTG must ensure that

• The safety manual and the operating manual are available and are complied with • The service conditions and technical data are complied with • The protective devices are used • The prescribed maintenance work is carried out • The maintenance personnel are immediately informed or the plant immediately shut down if higher temperatures, noise, vibration, etc. compared to operation at normal rating should occur.

The operating manual contains the information required for operation of the WTG by qualified personnel.

The warranty of the manufacturer is only provided if the currently valid operating manual is observed and complied with.

Take precautions against malfunctions and thereby prevent personal injury or death and material damage!

2.1 Personnel Groups

Different personnel groups are specified for carrying out the various tasks in and on the WTG. Before work is started, it must be ensured that the personnel in question have the requisite qualifications to carry out the respective tasks. If necessary, suitable training or qualification measures are required, or the work is carried out by other personnel with a suitable qualification.

2.1.1 Qualified Persons Work on electrical equipment and machinery may only be carried out by qualified persons who are familiar with the currently applicable safety and installation regulations. The qualified persons must be authorized to carry out the requisite tasks by the person responsible for safety in the WTG under the health and safety regulations. A qualified person is a person who

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 6/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

• has appropriate training and experience • is familiar with the currently applicable standards, regulations and accident prevention regulations and generally recognized code of practice • has been instructed in the operating principle and service conditions of electrical and mechanical drive systems and • can recognize and avoid dangers

Unqualified persons may not be deployed.

2.1.2 Technically Competent Persons Technically competent persons are persons who have the requisite technical knowledge for the inspection of work equipment as a result of their professional training, their professional experience and their current professional activity.

2.1.3 Experienced Persons An experienced person is someone who, on the basis of his technical training and experience, has gained adequate knowledge in the particular field of the equipment/device to be tested and who is acquainted with the pertinent national industrial safety legislation, the regulations for the prevention of accidents, directives and generally accepted engineering standards (DIN standards, VDE regulations, technical rules of other member states of the European Union or other contracting states of the agreement concerning the European Economic Area as well as OSHA/ANSI/NFPA/CSA and other standards and regulations for the Americas) to the extent that he is able to assess the safe working order of the equipment/device concerned.

2.1.4 Experts Experts are persons who are familiar with the relevant industrial safety regulations, directives and generally recognized code of practice and can verify and authoritatively assess the presence of threats and dangers.

2.2 Proper Use

The GE Energy 1.x Series Wind Turbine Generator Systems are intended solely for the generation of electrical power by means of wind energy.

Any other use or use extending beyond this is deemed to be improper. The operator / owner of the WTG bears the sole responsibility for any damage resulting there from.

The same also applies to any unauthorized modifications made to the WTG. As a general principle, modifications to the WTG may be carried out only after consultation with GE Energy, in order to guarantee the safety and the correct functioning of the WTGS.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 7/64 GE Energy Safety Manual

Proper use also includes compliance with the information on

• Safety • Operation • Service and maintenance provided in the technical documentation of the WTGS.

2.3 General Information

The wind turbine generator system may only be used in a technically perfect condition in line with the technical documentation. In addition, it must be used as intended, as well as with safety in mind and with an awareness of the dangers. Any malfunctions, particularly those which could impair safety, must be reported and remedied immediately.

Anybody who has been authorized to carry out erection, commissioning, operation or maintenance work must have read and understood the complete operating manual, in particular the safety manual.

It is too late to read the manual while carrying out the work. This applies especially to personnel who are only occasionally deployed on the wind turbine generator system.

The operating manual must be readily available at the site of operation of the wind turbine generator system at all times. It is kept in the main cabinet of the WTG.

The relevant regulations for the prevention of accidents (see "Information for the Operator" in "Basic information regarding the operating instructions manual") and any other generally recognized safety and industrial health regulations must also be complied with.

We cannot be held liable for any damage or accidents as a result of non-compliance with the operating instructions, the relevant regulations for the prevention of accidents and any other generally recognized safety and industrial health regulations.

Responsibilities for the different activities within the framework of operation, service and maintenance of the WTG must be clearly defined and complied with. This is the only way to prevent mistakes, particularly in dangerous situations.

The instructions for

• Shutting down the WTG • Maintenance work • Handling the rotor lock • Entering the rotor hub must be followed during the inspection, maintenance and repair of the wind turbine generator system and the safety devices.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 8/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

3 Marks, Signs and Symbols

3.1 Danger Classifications and Symbols

The following danger classifications and symbols are used in the technical documentation for the GE Energy 1.x Series wind turbine generator systems:

Exact description of the danger!

Indicates an imminent threatening danger resulting in death or Danger! serious injury.

Exact description of the danger!

Indicates a potentially hazardous situation that may result in death Warning! or serious injury if the dangerous situation is not avoided.

Exact description of the danger!

Indicates a potentially hazardous situation that may result in slight Caution! or minor injury if the dangerous situation is not avoided.

Exact description of the danger! Indicates a potentially hazardous situation that may result in damage to the WTG or surrounding area if the dangerous situation Attention! is not avoided.

Danger! Electricity! This symbol is used in safety information for electrical energy. Danger!

Notes include user tips and useful information. The notes should be read in the interests of proper use as well as with regard to proper operation and maintenance of the WTG.

All notices and symbols directly attached to the WTG, such as safety signs, operating notices, rotation arrows, component identification markings, etc., must be observed without fail. They may not be removed and must be maintained in a fully legible condition.

3.2 Marks and Signs attached by GE Energy

The personnel in the WTG must be able to check certain data at all times, in order to ensure safe operation of the WTG. The following information must therefore be clearly visible and permanently attached:

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 9/64 GE Energy Safety Manual

1. Marks for identification of the device 2. Characteristic values by means of which the permissible limits for safe use are specified, e.g. permissible load, rotational speed, pressure.

In addition, information about the prescribed use and about possible dangers which could arise when handling a device must be provided.

Safety marks could be texts, signs, signals, pictographs and colors. All texts are to be in two languages, i.e. English and the respective national language. Pictographs must be easy to understand and self-explanatory.

The signs are made of durable materials with stable colors.

The instructions on the safety signs and marks must be followed.

The presence and legibility of the safety signs must be checked as part of the regular maintenance work. Any missing or illegible safety signs must be replaced immediately.

The signs in the wind turbine generator systems may differ as a result of country-specific differences in the environmental and safety regulations.

All possible signs attached by GE Energy are listed in the following:

3.2.1 Tower

Keep escape and rescue routes clear! This sign is attached in the entrance area of the turbine.

Not for USA/Canada!

It is strictly forbidden to leave the WTGS with rotor lock applied! This sign is attached in the tower at the bottom of the ladder.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 10/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Falling hazard warning on trap doors and floor openings! This sign is attached to each platform.

Falling objects hazard warning! This sign is attached to each hatch.

Admissible maximum loading of the platform! This sign is attached to each platform.

Always close hatch after climbing through! This sign is attached to each platform.

Climbing the WTG - Things to do! This sign is attached in the tower near the ladder.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 11/64 GE Energy Safety Manual

Danger: Electricity! This sign is attached to the outside of the door..

Dangerous batteries! This sign is attached to the emergency power supply unit and to the main cabinet.

Attention, confined space! This sign is attached to the underside of the access hatch leading to the transformer section.

No access for persons with pacemakers!

Fire extinguisher! This sign is attached in the tower near the fire extinguisher.

Not for USA/Canada!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 12/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

ONLY WITH TRANSFORMER IN TOWER: Attention! High voltage! This sign is attached to the outside of the door, the switch gear, the transformer cage and the hatch to the tower base.

Access forbidden! This sign is attached to the outside of the door.

First Aid! This sign is attached at the bottom of the tower.

Not for USA/Canada!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 13/64 GE Energy Safety Manual

First Aid! This sign is attached at the bottom of the tower.

Not for USA/Canada!

Climbing the WTG - Things not to do! This sign is attached in the tower at the bottom of the ladder.

Tie off point Only for USA/Canada!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 14/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

3.2.2 Nacelle

Description Sign

Pinch Point (ANSI) This sign is attached in the nacelle during the assembly. Only for USA/Canada!

Pinch Point (ISO) This sign is attached in the nacelle during the assembly. Only for USA/Canada!

Instructions for working in the nacelle! This sign is attached in the nacelle.

Instruction for the rotor lock on the high-speed shaft! This sign is attached to the cover beside the rotor lock on the high-speed shaft.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 15/64 GE Energy Safety Manual

Description Sign

Allowable Loading rotor lock - low-speed shaft! This sign is attached to the rotor lock of the low-speed shaft. This sign shown here is a representative example; versions with the updated wind speeds for newer models may be applied.

It is forbidden to leave the WTGS with rotor lock applied! This sign is attached in the nacelle above the passage to the tower.

Standing on the starter terminal box prohibited – NOT A STEP! This sign is attached to all surfaces which may not be used as a step.

Warning: strong wind currents! This sign is attached to the hatch leading to the roof of the nacelle (exit to the hub).

Falling Hazard Warning! This sign is attached to the hatch leading to the roof of the nacelle (exit to the hub).

Caution! Hot surface. This sign is attached to the generator.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 16/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Description Sign

ONLY FOR PLANTS WITH COLD WEATHER EQUIPMENT! Caution! Hot surface. This sign is attached to the anemometer on the roof of the nacelle.

Instructions for entering the rotor hub! This sign is attached to the hatch leading to the roof of the nacelle (exit to the hub).

Instructions for yaw stop! This sign is attached beside the yaw stop switch on the uppermost tower platform.

ONLY FOR PLANTS WITH AN "EMERGENCY DESCENT HATCH": Falling hazard at hatches! This sign is attached to the optional emergency descent hatch.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 17/64 GE Energy Safety Manual

Description Sign

Maximum load on the bottom surface in the nacelle enclosure! This sign is attached in the nacelle enclosure near the generator.

Warning! Must be tied off at all times! This sign is attached to the hatch leading to the roof of the nacelle (exit to the hub). Only for USA/Canada!

Attention! Danger from rotating parts! This sign is attached to the yaw and the low-speed and the high-speed shaft.

Fire extinguisher! This sign is attached in the nacelle near the fire extinguisher.

Not for USA/Canada!

ONLY FOR PLANTS WITH AN "EMERGENCY DESCENT HATCH": Emergency exit! This sign is attached above the emergency descent hatch!

First Aid! This sign is attached near the First Aid box.

Not for USA/Canada!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 18/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Description Sign

First Aid! This sign is attached near the First Aid box.

Not for USA/Canada!

First Aid! This sign is attached near the First Aid box.

Not for USA/Canada!

Use the railing for hooking! This sign is attached beside the roof hatch in the nacelle enclosure.

Not for USA/Canada!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 19/64 GE Energy Safety Manual

Description Sign

Attention! Use the railing for hooking! This sign is attached beside the roof hatch in the nacelle enclosure.

Only for USA/Canada

Hook onto Spinner! This sign is attached to the hatch leading to the nose cone.

Not for USA/Canada!

Hook onto Spinner! This sign is attached to the hatch leading to the nose cone.

Only for USA/Canada

Lift point (ANSI) This sign is attached to the lifting lugs of the main frame. Only for USA/Canada

Lift point (ISO) This sign is attached to the lifting lugs of the main frame. Only for USA/Canada

Lift point for top cover only (ANSI) This sign is attached to the tie-off points of the top cover. Only for USA/Canada

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 20/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Description Sign

Lift point for top cover only (ISO) This sign is attached to the tie-off points of the top cover. Only for USA/Canada

3.2.3 Hub

Description Sign

Dangerous batteries! This sign is attached to the battery cabinet in the hub.

Attention! Danger from rotating parts! This sign is attached to the pitch drive mechanisms.

Danger: Electricity! This sign is attached to the axis cabinets in the rotor hub.

Falling Hazard Warning! This sign is attached to the hatches of the hub.

Maximum load on the blade root bulkhead This sign is attached above and below each rotor blade connection, so that the signs are exposed to view on entering the rotor blade.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 21/64 GE Energy Safety Manual

Description Sign

Attention! Confined space This sign is attached to the access hatch leading the hub.

Caution! May energize without warning (ANSI) This sign is attached to the pitch drive mechanisms. Only for USA/Canada

Caution! May energize without warning (ISO) This sign is attached to the pitch drive mechanisms. Only for USA/Canada

Secure hatch (ANSI) This sign is attached to the access hatch to the hub Only for USA/Canada

Secure hatch (ISO) This sign is attached to the access hatch to the hub Only for USA/Canada

Caution! Handle or Step only (ANSI) This sign is attached to the handles in the entrance to the hub. Only for USA/Canada

Caution! Handle or Step only (ISO) This sign is attached to the handles in the entrance to the hub. Only for USA/Canada

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 22/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

4 Information for the Operator / Owner of the Wind Turbine Generator System

The operator of the WTG is responsible for ensuring that no unauthorized persons remain inside or on the WTG. The WTG must be kept locked to prevent this.

The wind turbine generator system may only be started up if it has been completely assembled and is in working order.

The wind turbine generator system may only be operated if all safety equipment and safety-relevant devices, e.g. detachable protective equipment, are in place and operational.

If any malfunctions occur or if ice builds up on the rotor blades, the wind turbine generator system must be shut down immediately and secured. Malfunctions are to be remedied without delay by trained technical personnel.

In the case of malfunctions which are not automatically reset by the control system of the WTG, GE Energy must be contacted before a restart is carried out, in order to confirm that the WTG may be placed in the automatic operating mode (i.e. whether the WTG may be restarted).

Follow the switch-on and shut-down procedures and take note of the visual and monitoring displays in accordance with the operating manual!

In addition to this, the operator/owner of the WTG must comply with the following additional safety instructions (if maintenance is not carried out by GE Energy employees):

• If the WTG is not directly connected to the public telephone system, the maintenance personnel must have a cell phone or radio with them when ascending the tower. • The personnel must be informed about who to contact in an emergency. (Telephone numbers of a rescue center, police, fire department...) • For safety reasons, the personnel must be instructed that the WTG may only be entered by a minimum of two persons. • Special authorization from GE Energy is required to carry out inspection and maintenance work inside a WTG while it is in operation. • The personnel must be instructed to keep the WTG escape routes clear at all times when carrying out work as a part of maintenance or operation. • In the case of work involving a fire hazard, the personnel must have a fire extinguisher ready at hand, in order to be able to immediately extinguish any fire that may start. • Personnel are not permitted to remain at a higher level in the WTG while work involving a fire hazard is being carried out. • Personnel instructed to carry out work in or on the WTG must be provided with instructions and the appropriate personal protective equipment (PPE). • The WTGS must only be entered when a second person is available to provide assistance or call for help in case of accident.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 23/64 GE Energy Safety Manual

• If the WTG is part of a wind farm and connected to a plant, this safety manual must be supplemented in cooperation with the local power supply company, so that it also: — describes the safety aspects relevant to the wind farm — describes the exchange of information and names the persons who are to be contacted — describes access to basic first aid facilities

5 Signs to be attached by the Operator/Owner

The operator/owner of the WTG is obliged to attach additional warning signs to the WTG. These are intended to cover safety aspects which are not related to the scope of supply of the manufacturer of the WTG.

The warning signs must state that

• It is dangerous and prohibited for unauthorized persons to enter or climb the WTG • It is prohibited to remain in the vicinity of the WTG while work is being carried out outside the nacelle • Deposits of ice which have formed on the rotor blades (depending on the location of the WTG) could drop off

The operator/owner is responsible for seeing that any components or plant components which he has supplied are properly equipped with signs.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 24/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

6 Safety Equipment

The safety equipment serves to reduce risks and dangers. You will find further information on equipment and items which are subject to inspection in the annex of this safety manual.

6.1 Personal Protective Equipment

Everybody must wear Personal Protective Equipment (PPE) when working on or in the WTG to protect themselves from injury.

Danger of accident!

Never enter or climb the WTG without the personal protective Danger! equipment. Otherwise there is danger of injury and falling.

The PPE is especially required for climbing the tower. It comprises:

• Safety harness • Cable of rail grab device/fall arrestor • Double lanyard with shock absorber • Hard hat • Safety boots • Gloves • Safety glasses • Hearing protection (if required) • Respirator (if required) • Thermal clothing (if required • Suspension travel straps

The PPE must be of an approved type; must be compliant with the applicable local regulators; and must bear marks of conformity stating that it is suitable for the work and protection involved and that it is also suitable for the climatic conditions at the site of the WTGS.

Note! The extent and the equipment of the personal protective equipment may vary in some countries. Please comply with the local regulations!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 25/64 GE Energy Safety Manual

Optionally, safety harness and travelling safety hooks may be supplied by GE Energy. The remaining constituents of the PPE are not part of the scope of supply of the wind turbine generator system. If supplied the safety harnesses and travelling safety hooks must be properly stored in the WTG and must be accessible.

If several persons ascend the tower simultaneously, personal protective equipment must be available for the respective number of persons.

Note! Check the completeness, the condition and the function of your personal protective equipment in good time before entering the WTG. If a piece of the equipment is missing, it must be replaced before starting work.

The safety harness and the entire safety equipment must be checked before use. Damaged equipment must never be used.

The PPE must be inspected and tested by a technically competent person after any fall, or at the intervals recommended by the manufacturer at least.

Follow the manufacturer's directions for use for all component parts of the personal protective equipment!

6.2 Safety Harness

A Safety harness and all safety equipment should never be exposed to acids/caustic chemicals. If this is unavoidable, follow manufacturer instructions for treatment.

Protect from sharp edges and sharp-edged objects. Attention! Wash and dry according to manufacturer’s instructions. Store in a well-aired place out of direct sunlight.

The safety harness is used to protect personnel during the ascent to the nacelle of the WTG, during the descent from the nacelle of the WTGS and, in combination with a lanyard and a shock absorber, when carrying out work in areas where there is a danger of falling.

Optionally, safety harness and travelling safety hooks may be supplied by GE Energy.

The safety harnesses and the entire safety equipment must be cleaned, cared for, maintained and stored in accordance with the manufacturer's instructions.

Follow the manufacturer's instructions when putting on the safety harness.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 26/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

6.2.1 Example of Putting on a Standard Safety Harness As previously mentioned, the manufacturer’s instructions should always be followed when putting on a safety harness. An example of how to wear a safety harness is included below.

1. Hold the safety harness in such a way that you can see in which way it is going to be put on at a later stage. (Fig. 1) Ensure that the loops are not twisted.

Fig. 1: Preparing the safety harness

2. Insert your arms through the yellow shoulder straps and place the safety harness on your shoulders like a rucksack. (Fig. 2 and Fig. 3)

Fig. 2: Insert your arms through the shoulder straps

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 27/64 GE Energy Safety Manual

Fig. 3: Safety harness on the shoulders

3. Closing the stomach strap Take the two loops positioned at stomach height. Pull the right-hand loop (1) through the eyelet (2) and guide the end of the loop through the rectangular frame (3). (Fig. 4) Adjust the strap to ensure a close fit.

Fig. 4: Closing the stomach strap

4. Closing the chest strap Take the two straps positioned at chest height. (Fig. 5) Pull right-hand strap (1) through the eyelet (2) and insert its end through the rectangular frame (3) also located on the right-hand strap. Adjust the strap to ensure a close fit. (Fig. 6)

Fig. 5: Closing the chest strap

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 28/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Fig. 6: Closed chest strap

5. Closing the leg loops Push both loose leg loops from behind through the legs and to the front. Pull the leg loops through the strap closure and pull the leg loops tight. (Fig. 7)

Fig. 7: Closing the leg loops

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 29/64 GE Energy Safety Manual

6. Check that all straps are straight and close fitting and that the buckles are closed correctly. (Fig. 8)

Fig. 8: Safety harness correctly fitted

6.2.2 Cable or Rail Grab Device/Fall Arrestor The manufacturer's instructions for use of cable or rail grab device are to be followed.

In combination with the safety harness, the cable or rail grab device is a safety device for ascending/descending the tower via the ladder. Should somebody slip off the ladder, the cable or rail grab device clamps on tightly to the safety rail and prevents a fall. The system consists of a fixed guide, fastening elements, and a travelling arrestor device. A steady straight-line ascent and descent of the ladder without the user leaning back in the harness is best way to ensure that the travelling safety hook runs freely.

Beware of hand injuries! A free running travelling safety hook can crush your hands if you grasp the device or the safety rail or cable.

Warning! Keep your hands on the sides of the ladder during the ascent/descent.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 30/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Using the Cable or Rail Grab Device Rail Grab Device 1. Insert the travelling safety hook into the retaining eyes of the safety harness. 2. Push the travelling safety hook into the guide rail mounted on the ladder. 3. Ascend and descend the ladder slowly and carefully.

Fig. 9 Cable Grab Device 1. Insert the cable grab fall arrestor and the shock pack assembly into the D-ring (or retaining eyes) of the safety harness. 2. Push the cable grab fall arrestor into the wire rope attached to the ladder. 3. Ascend and descend the ladder slowly and carefully. 4. Ensure to be in contact with the ladder on at least 3 points at all times.

Fig. 10

6.3 Protective Equipment for Measurements on Live Components

Danger! Electricity! Contact can cause extremely serious injuries and even death.

Danger! Life-threatening hazard!

Special PPE is required for measurements on live components. This provides protection against electricity flowing through the body, e.g. as a result of touching live components in operation. Furthermore, it provides protection against accidental arcs caused by insulation breakdowns e.g. as a result of switching operations under load.

Refer to NFPA 70E document (GE Standard) for further guidance on PPE requirements for electrical work.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 31/64 GE Energy Safety Manual

6.4 Hooking Points

As a rule, the hooking points are marked in yellow and are designated with a statement of the permissible safe work load. These hooking points are to be used with a safety harness and lanyard with a shock absorber to provide protection in areas where there is a danger of falling.

Exchange of the rail

The nose cone rail and nacelle rail must be exchanged after any Attention! fall!

6.5 Abseiling Device

Not all wind turbine generator systems are supplied with an abseiling device. There is sometimes only a certain number of devices, especially in larger wind farms.

The abseiling device (e.g. abseiling device AG 10 K – RK Sicherheitstechnik) has a rope which is long enough for the respective height of the tower of the WTG.

The abseiling device is stored in a lead-sealed equipment bag, which is located in a net beside the hatchway to the roof of the nacelle.

Fig. 11: Equipment bag in the net The abseiling device is used by the personnel to abseil from high workplaces. It is not a fall arresting device, instead it is used primarily for the evacuation of personnel in the event of an accident or fire. In case of fire, it can be used to abseil from the roof of the nacelle of the WTG as a 2nd escape route.

As a rule, the hooking points for the abseiling device are marked in yellow and are designated with a statement of the permissible safe work load. The abseiling device is attached to the hooking point by means of a snap hook or to the roof rail by means of a sling rope and a snap hook.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 32/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Danger of accident with a defective abseiling device! In an emergency, your life could depend on the abseiling device working properly! As a result, check the integrity of the seal of the equipment bag on each visit to the nacelle. The abseiling device is pre-assembled and is Attention! ready for use immediately after it has been removed from the equipment bag. Carry out an additional visual inspection of the abseiling device immediately before use.

It is easy to operate the abseiling device incorrectly in emergency situations. As a result, ensure that you know how to operate the device and are familiar with the abseiling operation. Please also read the operating manual. This is the only way to ensure that the correct maneuvers are carried out in an emergency.

6.5.1 Abseiling from the Roof of the Nacelle Abseiling can take place individually or in pairs. The abseiling device may be loaded with a maximum of 225 kg up to a rope pitch of 100 m. Abseiling takes place at a speed of 0.7 m/s. The abseiling speed is regulated by means of a centrifugal brake.

A typical abseiling operation is described in the following. The procedure described may vary depending on the abseiling device. As a general principle, always follow the instructions of the manufacturer of the respective abseiling device!

1. Make sure that your safety harness is put on correctly. 2. Secure yourself against falling by means of the lanyard. Attach the lanyard to tie-off points or nacelle rail. Step out on the roof of the nacelle. 3. Close the roof hatch. 4. Break the lead seal on the equipment bag. 5. Remove the abseiling device from the equipment bag. Leave the rope in the equipment bag.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 33/64 GE Energy Safety Manual

6. Attach the abseiling device to the roof rail of the nacelle by means of the sling rope and the snap hook. 7. Secure the snap hook with the clamping nut. 8. Throw down the equipment bag with the rope.

Fig. 12: Abseiling device

9. Check the condition and the correct functioning of the device.

10. Check the rope for loops and knots.

Interruption of abseiling through loops or knots! Loops or knots in the rope prevent abseiling, since the rope cannot run through the abseiling device if it has a knot. As a result, always check the rope carefully! Danger! REMOVE ALL LOOPS AND KNOTS FROM THE ROPE BEFORE YOU START ABSEILING!

11. Hook the snap hook on the short end of the rope into the two chest rings of your safety harness.

12. Sit in front of the roof rail on the edge of the nacelle.

13. Ensure that the length of rope between the chest rings of your safety harness and the abseiling device is pulled taut.

14. Release the lanyard attached for your safety.

15. Slowly put your weight on the rope of the abseiling equipment. After you have let go of the nacelle and the roof rail, you will abseil at a speed of 0.7 m/s.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 34/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

16. After you have reached the ground, immediately release the snap hook from the chest rings of your safety harness.

17. A second person waiting on the roof can then hook in the snap hook of the end of the rope which is now at the top and abseil as described. The rope may have to be pulled through until the snap hook arrives at the top.

18. The device must be inspected by a technically competent person after a rescue or an abseiling exercise.

6.5.2 Care and Maintenance of the Abseiling Device The textile components of the abseiling equipment may only be cleaned by the manufacturer.

If damage to the rope, snap hook or abseiling device is discovered, the escape equipment must be withdrawn from use and inspected by the manufacturer.

Under normal service conditions, a service period of 4-6 years can be assumed for the textile ropes.

The abseiling device must be inspected by a technically competent person or by the manufacturer after a rescue or an abseiling exercise or at the intervals recommended by the manufacturer at the latest.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 35/64 GE Energy Safety Manual

6.6 Fire Extinguishers (optional feature)

Fire extinguishers are optional in the wind turbine generator systems (WTG). If fire extinguishers are supplied, the WTG is normally provided with a fire extinguisher in the tower and in the nacelle.

The locations of the fire extinguishers are identified by this sign.

Danger: Electricity! De-energize the installation before using the fire extinguisher. After actuation of the medium-voltage circuit-breaker, keep a safe distance of at least one meter from the fire when extinguishing! Danger! The fire extinguisher may only be used on electrical installations up to 1000V!

Ensure that you are familiar with the function and the operation of the fire extinguisher. Only thus can you act quickly and purposefully in emergency situations.

The use of fire extinguishers must be practiced. The personnel deployed in the WTG must therefore be trained in fire-fighting at regular intervals.

The fire extinguishers must be regularly inspected by a technically competent person in accordance with the national regulations. A record of the check with the date must be permanently affixed to the appliance in an easily visible location. The directions for use (on the fire extinguisher) must be followed before fire-fighting.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 36/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

6.6.1 Operating principle of the optional fire extinguisher – An example As a general principle, always follow the instructions of the manufacturer of the respective fire extinguisher.

1. Remove the safety tab (1). 2. Press down the fire-extinguishing button (2).

3. The perforating disk of the CO2 cylinder (3) is opened and the CO2 released for charging the tank. The appliance is ready for use. 4. The extinguishing agent, which is under pressure, flows through the riser pipe (4) to the valve armature. 5. After the fire-extinguishing button has been pressed, the extinguishing agent flows through the hose line to the spray fog nozzle (5). 6. The jet of extinguishing agent can be interrupted at any time by releasing the fire- extinguishing button. (Contents of the fire extinguisher: 5 kg) Fig. 13: Fire extinguisher - An example

6.6.2 Types of Fire Extinguisher

Substances to be extinguished Liquid substances or Flammable metals Solid, glowing Gaseous substances, substances becoming (use only with a substances also under pressure liquid powder nozzle)

Dry powder extinguisher with ABC dry powder + + + -

Dry powder extinguisher with BC dry powder - + + -

Dry powder extinguisher with metal fire powder - - - +

Carbon dioxide fire extinguisher - + - -

Water extinguishers (also with additives, e. g. wetting agent, + - - - antifreeze or corrosion inhibitor)

Water extinguishers with additives Types of Fire Extinguisher Types Fire Extinguisher of which also extinguish liquid substances or substances + + - - becoming liquid in combination with water

Foam extinguisher + + - -

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 37/64 GE Energy Safety Manual

6.7 First Aid

First aid is used for the initial treatment of an accident victim until the arrival of a doctor or until transport to a hospital, in order to avert a life-threatening situation or to prevent secondary injury.

There is a legal obligation to carry out rescue measures provided that this is possible without considerable self-endangerment.

The plant may never be entered alone, so that a second person can send an emergency call. If the interphone has a landline connection, the emergency call can be made via the interphone. An operational cellphone is to be carried at all times, in order to be able to ensure rapid assistance in an emergency.

Proceed as follows in the case of an accident:

1. Keep CALM! 2. In the case of serious accidents and injuries, notify a rescue center by interphone, cell phone or radio. 3. Render first aid immediately. 4. Secure the scene of the accident. 5. Report all accidents (near-accidents, minor accidents, serious accidents) to your immediate supervisor. Also notify the EHS department of GE Energy.

Keep access to the WTG clear! The access roads to the plant must be kept clear at all times and be negotiable by car, in order to guarantee rapid and problem-free ATTENTION! first aid in an emergency.

First Aid Box (Optional) The provision of wind turbine generator systems (WTGS) with first aid boxes is optional.

If provided a first aid box is located in the nacelle of the wind turbine generator system for the treatment of minor injuries. Any material removed is to be replaced immediately after use.

This sign identifies the location of the first aid box in the nacelle.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 38/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

7 Safety Devices

The safety devices of the WTG comply with the requirements of the following standards:

• DIN EN ISO 13857: 2008 - 06 – Safety distances to prevent danger zones from being reached by the upper limbs and lower limbs. The unauthorized removal or the overriding (by-passing) of safety devices is a punishable offence. Any liability claim is invalid in the case of damage.

Any point at which danger can arise and all drive units are provided with protective covers, which can only be undone and removed by means of tools. These protective covers may only be removed by qualified staff and only for the performance of service and maintenance or repair work. The protective covers are to be refitted immediately after completion of the work.

The owner / user of the WTG and the personnel deployed by him for operation, maintenance and repairs bear the responsibility for an accident-free work process.

7.1 Emergency Stop Pushbuttons

Any power-operated work equipment with dangerous movements must have one or - if necessary - several emergency control units for the prevention or reduction of an imminent or arisen danger, by means of which the dangerous movements can be stopped or rendered ineffective in another manner.

The emergency stop pushbuttons are not dependent on electronic logic.

Emergency stop pushbuttons (red mushroom pushbutton on a yellow base) are located on the control cabinet, the top box in the nacelle and the control cabinet in the hub. Fig. 14: Emergency stop pushbutton

The EMERGENCY STOP pushbutton may only be pressed in situations, in which the safety of personnel or the WTGS and its components is threatened.

Pressing the emergency stop pushbutton causes the safety chain to open, and the rotor of the WTG is brought to a standstill via emergency braking. Initiation of the safety chain causes the rotor blades to travel to the feathering position in the [emergency] battery mode! In addition to this, the WTG is de-energized except for the control voltage.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 39/64 GE Energy Safety Manual

7.2 Rotor Lock

The GE 1.x series plants are equipped with two rotor locks.

7.2.1 Rotor Lock on the High-speed Shaft The rotor lock on the high-speed shaft is located on the brake disk of the outgoing shaft of the gearbox. It must be engaged during all regular maintenance work on the drive train and for the physical inspection of the rotor hub.

Maintenance work on the drive train which requires the rotor shaft to be locked may only be carried out at wind speeds up to 15 m/s.

Maintenance work in the rotor hub may only be carried out at average wind speeds of less than 15 m/s. In this connection, the rotor lock on the high-speed shaft must be engaged. The rotor lock on the low-speed shaft must not be engaged.

If the turbine is unable to idle after a malfunction, the lock on the high-speed shaft must be engaged. It must be ensured that all three rotor blades are in the feathering position.

Engaging the Rotor Lock on the High-speed Shaft 1. Manual stop 2. Remove the locking pin of the rotor lock and advance the rotor lock as far as possible by means of the crank 3. If necessary, briefly actuate the "rotor brake" switch on the top box, in order to disengage the brake for a short time, thereby placing the brake disk in a better position. 4. Fully engage the rotor lock until the locking pin locks home again at the lower position.

7.2.2 Rotor Lock on the Low-speed Shaft A lock is located on the rotor shaft flange of the low-speed shaft. This is only used for carrying out special work on the drive train. A sliding block or a sliding bolt which is guided in a fixture on the base frame is pushed onto the shaft flange in grooves or holes. The limit switch in the safety loop is opened as a result.

The rotor lock on the low-speed shaft may only be engaged up to the following average wind speeds:

• 8 m/s in the welded frame version up to 2004 (individual gusts up to a max. of 14 m/s) • 12 m/s in the 1.5-82.5 (individual gusts up to a max. of 19 m/s). • 15 m/s in the cast frame version and in the welded frame version from 2005 (individual gusts up to a max. of 24 m/s)

The current wind speed can be read on the SCADA display!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 40/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Engaging the Rotor Lock on the Low-speed Shaft 1. Manual stop 2. Manually turn the blades to the 0 degree position 3. Position the rotor to engage the lock 4. Engage the rotor lock on the high-speed shaft 5. Actuate the service switch to disconnect the battery in the rotor hub 6. Engage the rotor lock on the low-speed shaft 7. If necessary, release the lock on the high-speed shaft after leaving the hub.

If the wind speed unexpectedly increases, any installation work must be ended immediately, and the rotor lock must be disengaged in the reverse sequence.

Leaving the WTG with the rotor lock applied is strictly prohibited! ATTENTION!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 41/64 GE Energy Safety Manual

8 Residual Risks

Even if all the safety requirements are complied with, a residual risk remains during operation of the GE Energy 1.x Series wind turbine generator systems.

Anyone who works on and with the WTG must be aware of these residual risks and follow the instructions which prevent these residual risks from resulting in accidents or damage.

Danger of injury during ascent! The full-body safety harness must be put on and attached to the safety rail by means of the travelling safety hook during the ascent to the nacelle, in order to prevent the person ascending from falling. Any oil or grease deposits on the ladder must be removed Danger! immediately to prevent anyone from slipping while using the ladder. Ensure that your footwear is clean!

Falling objects hazard warning! An object may be unknowingly and unintentionally dropped and hit and cause injury to somebody. For this reason, only one person at a time may climb a section of the ladder between two platforms. The hatch covers must be Warning! closed again immediately after they have been passed through. Tools and equipments must be secured while climbing and transitioning to the nacelle roof or the hub.

Life-threatening hazard - working under suspended loads! Never stand under suspended loads. Danger!

Danger of falling from the nacelle! The nacelle has a roof hatch for accessing the hub. You are exposed to strong winds when climbing out through the hatch. Danger! Attach your lanyard to the outside rail from inside the nacelle. Climbing out is only allowed at wind speeds up to 15 m/s.

As a general principle, there is a falling hazard at all higher locations / workplaces.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 42/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

8.1 Special Dangers – Electric Power

Note the following rules when carrying out any work on the electrical components of the plant, e.g. assembly, connection, opening of a device, maintenance:

1. DISCONNECTION 2. SECURE against re-connection, following proper Lock Out/Tag Out (LOTO) procedures 3. Ascertain safe isolation from supply 4. Ground and short-circuit 5. Cover up adjacent live components or provide them with barriers

In addition, ensure that all drives are at standstill.

Caution! Danger from electrical voltage! When switched on, electrical installations and machinery have live exposed conductors or rotating parts. They could therefore cause personal injury or death and material damage if the cover and the prescribed safety devices are removed, or in the event of incorrect handling and maintenance and in the case of improper use. The above stated safety regulations must therefore be complied with, particularly when removing a cover. In addition to this, electrical energy is still present in devices with power electronics even after the supply voltage to the device has Danger! been switched off. These devices are secured against unauthorized access. After waiting an appropriate time for the device to discharge (e.g. capacitors), always check for residual voltage before starting work. FOLLOW THE RESPECTIVE LOCKOUT/TAGOUT INSTRUCTIONS! (cf. Chapter 13)

In the case of malfunctions of the of the wind turbine generator system, actuate the EMERGENCY STOP button immediately if the plant has not already been switched off by the automatic control system.

Only use original fuses with the prescribed amperage!

In the case of repairs, care should be taken that design features are not modified, so that safety is compromised (e.g. leakage distances and sparking distances in air) and that distances are not reduced by insulation materials.

As a general principle, maintenance work may only be carried out by two persons, so that the second person can actuate the EMERGENCY STOP button in an emergency.

Only use insulated and approved tools.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 43/64 GE Energy Safety Manual

The control system and interlocking as well as the monitoring and protective functions (thermal motor protection, speed monitoring, over current, fault to ground, etc.) may not be set out of function, even during a test run.

8.2 Special Dangers – Hydraulic System

For maintenance work on the hydraulic system, maintenance staff must be completely acquainted with the hydraulic circuit diagram and must have been instructed about its function and the possible consequences of an operating error.

Prior to any work on the hydraulic accumulators, it must be ensured that the accumulator circuits have been depressurized. The shut-down device is clearly marked and independent of the system management.

Danger through stored residual hydraulic energy!

FOLLOW THE RESPECTIVE LOCKOUT/TAGOUT INSTRUCTIONS! (cf. Danger! Chapter 13)

8.3 Special Dangers - Noise

The A-weighted equivalent continuous sound intensity level in the tower and the nacelle exceeds the permissible 70 dB(A) (per European Standard EN 50308) or the permissible 85 dBA TWA (per OSHA 29 CFR 1910.95) during operation. For some work, it may be necessary to place the WTG in operation or carry out a test run while personnel are in the nacelle.

Anybody carrying out work in the tower or the nacelle when the WTG is in operation must wear hearing protection with an appropriate level of noise protection as part of their personal protective equipment.

8.4 Special Dangers - Icing

8.4.1 Ice Build-up on the Rotor Blades Ice build-up on wind turbine generator systems (WTG) and, in particular, the shedding of ice from rotor blades can lead to problems if wind turbine generator systems are planned in the vicinity of roads, car parks or buildings at locations with an increased risk of freezing conditions, unless suitable safety measures are taken.

If people or objects near the wind turbine generator system (within the distance R*) could be endangered by pieces of ice thrown off during operation, GE Energy always recommends the use of an ice detector.

The ice detector is installed on the nacelle. It is possible to detect the build-up of a small amount of ice by means of the ice detector. If this is the case, the ice detector sends a signal to the turbine controller. The turbine controller disconnects the wind turbine generator system from the grid and the rotor is brought to a standstill or rotates at a very low speed. A message about the icy condition is displayed on the monitor in the

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 44/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

turbine, In addition, a message is sent to the service station and the operator via modem. The turbine does not restart until the detector is free of ice or the operator has satisfied himself of the ice-free condition of the rotor blades, has acknowledged the ice alarm message and restarts the plant.

However, ice may form on the rotor blades considerably more quickly than on the ice sensor on the nacelle. As a result, there is a residual risk for the reliable detection of ice build-up on the rotor blades.

The detector on the nacelle must be set relatively sensitively, in order to ensure that the time from when ice starts to build up on the rotor blades until the detector sends a message about the build-up of ice is as short as possible. As a consequence, a certain number of spurious trippings cannot be excluded. Loss of energy yield may occur as a result of the spurious trippings.

If an ice detector is not used, it is advisable to cordon off an area around the wind turbine generator system with the radius R* during freezing weather conditions, in order to ensure that individuals are not endangered by pieces of ice thrown off during operation (cf. also Section 11.1).

*R = 1.5 x (hub height [m] + rotor diameter [m]) (Recommendation of the German Wind Energy Institute DEWI 11/1999)

8.4.2 Icy Condition of the Access Route During the winter months, access to the plants may be very slippery due to ice or hard-packed snow. There is an increased danger of slipping. cf. Section 11.1 on approaching and entering WTGs which may be frosted.

8.4.3 Icy Condition of the Tread of the Steps outside the Nacelle In the winter months, the tread of the steps outside the nacelle can be icy as a result of ice and hard-packed snow.

8.5 Exceptional Dangers – Earthquakes

In the case of an earthquake, the operator must inspect the WTG for damage. The following procedure is recommended:

• Determination of the acceleration values in the tower top which arose during the earthquake (PCH BOX). • Contact GE Energy, in order to agree on the further procedure and possible inspection schedules.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 45/64 GE Energy Safety Manual

9 Safety Information for Individual Plant Components

9.1 Down Tower Assembly

The down tower assembly is the electrical cabinet lineup consisting of:

• Power distribution cabinet (PDC) • Converter filter cabinet (CFC) • Converter bridge cabinet (CBC) • Main control cabinet (MCC)

Caution! Danger from electrical current! All personnel remaining in the WTG must be located between the person carrying out the measurements and the tower entrance Danger! during voltage measurements on the low voltage main distribution or on the low voltage main control panel.

Attention! Check the work area / control cabinet before completion of the work! Remove all loose parts, tools and materials from the control cabinets. Tools and materials left in the control cabinets lead to

unsafe working conditions for the service technicians when the plant Danger! is put into operation again. Close and lock the control cabinets before returning to service.

Please follow respective Lock Out/Tag Out (LOTO) instructions.

Attention!

9.2 Anemometer and Wind Vane

The anemometer and the wind vane are intensely heated in WTGs with cold weather equipment!

Hot surface! Disconnect the anemometer and the wind vane from the supply and allow both to cool down prior to maintenance. Attention! Physical contact may cause burns.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 46/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

9.3 Top Box

The top box is the electrical cabinet that resides in the nacelle. The main purpose of the top box is to distribute power to the up-tower wind turbine components.

Caution! Danger from electrical current! All personnel remaining in the WTG must be located between the person carrying out the troubleshooting and the nacelle exit during Danger! voltage measurements.

Attention! Check the work area / control cabinet before completion of the work! Remove all loose parts, tools and materials from the cabinet. Tools and materials left in the control cabinets lead to unsafe working

conditions for the service technicians when the plant is put into Danger! operation again. Close and lock the control cabinets before returning to service.

Please follow respective Lock Out/Tag Out (LOTO) instructions.

Attention!

9.4 Pitch Electrical Control Cabinets Inside the Hub - Axis and Battery

Danger from electrical current! Before beginning any maintenance work, ensure that the control cabinets have been disconnected from all the energy sources in accordance with the currently applicable Lock out/Tag out instructions. Danger! In addition to the main circuits, take any supplementary or auxiliary circuits into account. Wear appropriate electrical PPE for entrance into energized cabinets.

Check the work area/control cabinet before completion of the work! Remove all loose parts, tools and materials from the cabinet.

Tools and materials left in the control cabinets lead to unsafe Danger! working conditions for the service technicians when the plant is put to operation again.

Danger from electrical current! All axis and battery cabinet doors must be securely latched in place before the system is reenergized to avoid exposure to the Danger! potentially hazardous transient voltages that are present during start-up.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 47/64 GE Energy Safety Manual

10 Conduct in Emergency Situations

10.1 Conduct in Case of Fire

In principle the WTGS consists of fire-resistant materials. However

Fire, open flames and smoking are prohibited!

If a fire does occur, however, call the fire department immediately!

State the following information:

• Name of the person calling • What is on fire • Where the fire is located (seat of the fire / location of the plant) (You will find the site coordinates on the nameplate) • Wind direction and wind strength

Note the following information in the case of fire:

• Saving lives has priority over fire-fighting • Alarm all personnel who are in the WTG • Use the escape routes described in Chapter 10.2 – ensure that you are familiar with the various escape routes. • Do not use the service lift. • Burning debris can be expected to fall down if there is a fire in the nacelle or the upper part of the tower. • If the wind turbine generator system is still in operation, it must be stopped and a large area around the plant cordoned off. • Close the door of the plant.

10.1.1 Fire-Fighting Fire-fighting may only be carried out by immediately fighting an initial fire using the fire extinguishers that may be available in the plant. The locations of the firefighting equipment (if available) in the tower and the nacelle are marked.

If the initial fire cannot be extinguished within a short time, abandon any further attempts to extinguish the fire and call the fire department immediately.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 48/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

In addition to the direct danger from the fire, a combustion toxicity hazard and the danger of asphyxia could also arise. As a result, move in a crouched position if smoke develops and also crouch down when attempting to extinguish the fire.

Attempts to extinguish a fire may lead to very serious burns! Do not make any attempts to extinguish the fire beyond the initial attempt. Due to confined space limitations, since the required Danger! minimum distance cannot be maintained while attempting to extinguish the fire.

10.1.2 Fire in the Tower - Person in the Nacelle • Leave the WTG immediately via the second escape route (cf. Chapter 10.2). • Abseiling device in the nacelle - emergency exit using the abseiling device

10.1.3 Fire in the Nacelle - Person in the Nacelle • Attempt to extinguish the fire.

If unsuccessful:

• Leave the danger area immediately via the first escape route (cf. Chapter 10.2). • Do not use the service lift. • Do not use the abseiling device.

10.1.4 Fire in the Transformer

Do not make any attempts to extinguish the fire – High voltage! Conventional fire extinguishers are not suitable. Danger!

• Leave the WTG immediately.

In the case of transformers in the tower:

• Leave the WTG via the second escape route

In the case of transformers in the transformer station:

• Leave the WTG via the first escape route

Fire-fighting may only be carried out by trained personnel.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 49/64 GE Energy Safety Manual

10.2 Escape Routes

Keep escape routes clear! The escape and rescue routes must be free of obstructions (tools, equipment, rubbish, etc.), in order to ensure that the turbine can be Attention! evacuated as quickly as possible in an emergency.

10.2.1 First Escape Route In case of fire, leave the plant immediately. The first escape route from the nacelle is down the ladder in the tower. The descent is facilitated and made safer by resting platforms every 6 m. Do not use the hoisting passenger suspension device.

10.2.2 Second Escape Route If the descent through the tower is no longer possible, use the second escape route. (Abseiling with the abseiling device). This either leads over the roof of the nacelle (hooking point on roof rail) or through the emergency descent hatch which may be present (hooking point directly beside the winch in the nacelle, which is also present in this case).

Correct use of the abseiling device:

• Make sure your safety harness if on correctly. • Attach lanyard to approved tie-off point or nacelle rail.

Use of the abseiling device! Your life could depend on the correct use of the abseiling device. The abseiling device can also be used by two people to abseil. Danger! Read the instructions before beginning the abseiling operation!

10.3 Information for Rescue and Emergency Personnel

The rescue services and the emergency personnel must be equipped with their own personal protective equipment (safety harness, etc.). The rescue/emergency personnel must bring with them all the equipment required for rescuing personnel from the hub, nacelle or tower.

The information stated in this safety manual must also be read by the rescue / emergency personnel.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 50/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

10.4 Oil Spill – Immediate Measures

The objective of the immediate measures is to prevent or at least to contain a further uncontrolled escape of water-endangering substances and keep the areas of threatened or contaminated soil as small as possible, under consideration of safety engineering requirements.

Inform yourself about the oils used beforehand. The safety data sheets provide details of Water Hazard Classes and suitable measures for combating oil pollution.

Measures 1. Decide and act quickly, so that the amount of oil reaching the environment is kept as small as possible. 2. Prevent further discharge (closure of valves, temporary sealing of cracks and holes, e.g. by means of sealing rags, sealing bags, sealing wedges, collection in containers, pumping out, transfer, etc.) 3. Bind the discharged oil – use approved oil binding agents and oil binder mats if the oil could not be pumped out or skimmed off in time. The damage can be limited by means of collecting containers, rolled foils and a shovel. 4. Prevent the oil from getting into the soil or bodies of water. 5. Remove contaminated soil. 6. Take the contaminated oil-absorbing materials to a local specialist waste disposal company for material recovery/conversion to energy or disposal. The national regulations are to be complied with.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 51/64 GE Energy Safety Manual

11 Remaining in and on the Wind Turbine Generator System

Fire Hazard! The storage of combustible or highly inflammable materials in the wind turbine generator system is not allowed. Attention!

Personnel may not remain inside the WTG, and maintenance or repair work may not be carried out in or on the WTG under power supply. There is a danger of accident and a danger to life and limb. In order to prevent accidents, the following actions are to be carried out in the following order before and on entering the wind turbine generator system:

1. Shut down the WTG and secure against an unauthorized return to service 2. Put on the personal protective equipment 3. Disable the power supply for the work to be carried out – carry out corresponding Lockout/Tagout instructions (cf. Chapter 13)

Staying in the WTGS while it is in operation is unavoidable in the case of certain maintenance and repair work. In such cases a risk assessment should be developed for the task. Particular care is called for and hearing protection must be worn.

In addition, the following safety regulations are to be complied with without fail:

• As a general principle, no person may stay in the WTG during a gale or a thunderstorm! If a thunderstorm comes up, the WTG must be left immediately. • The WTG may only be entered in the company of a second person who can provide assistance or call for help in the case of an accident. • The entrance door to the tower must be kept closed or if it is kept open, it must be properly secured to prevent it from flying open and getting warped. • Long open hair, loose clothing (e.g. flapping coats, tops with wide sleeves or trousers with wide legs) and scarves, ribbons, headscarves or jewelry may not be worn in the WTG! There is a fundamental danger of injury as a result of getting caught, trapped or drawn in by rotating elements! Clothing must always be tailored to suit the respective work and the weather conditions. • Switch-on and shut-down procedures in accordance with the operating manual are to be complied with for all work which concerns the operation and adjustment of the WTG and its safety equipment. • If any changes in the operating characteristics which are relevant to safety or any faults arise in the WTG, it must be shut down immediately and the event reported to GE Energy or the customer (if a maintenance contract has not been concluded with GE Energy).

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 52/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

11.1 Approaching and Entering Frosted Wind Turbine Generator Systems

Before parking near the turbine, stop approx. 350 m from the turbine and check the rotor blades for ice by means of binoculars and the sound of the rotation of the blades. If the turbine is running and ice is present on the rotor blades, call for a remote stop. Once the blades have come to a complete standstill, verify that none of the blades is located over the entrance door of the turbine. If this is the case, call for a remote traverse of the yaw drive in any direction, so that the rotor is positioned on the side of the turbine opposing the door. As soon as the rotor is correctly positioned, call for a remote stop of the yaw drive and ask for confirmation of this operation.

Once the above conditions have been complied with, park your vehicle at a safe distance from the WTGS (at least 100 m). Watch out for falling ice as you approach the tower. If the wind is blowing against the opposite side of the door (or into the rotor at this point), you must proceed with extreme caution, since falling ice could be blown in your direction.

Danger of slipping as a result of icy conditions! There is danger of slipping as a result of the frozen ground and ice on the foundation and the stairs.

Warning! Sprinkle de-icing salt or sand over the foundation. Use the handrail when going up the stairs.

Leave the immediate vicinity of the WTG after completing your work. Watch out for falling ice. Get into your vehicle. Do not call for a remote re-activation of the yaw drive and restart of the turbine until you are approximately 350 m away from the WTG.

11.2 Shut-down of the Wind Turbine Generator System

Before starting any service work, the wind turbine generator system must be deactivated. Proceed as follows:

1. Contact any remote monitoring groups that are supervising the site (before entering the wind turbine) 2. Contact any site operators or maintenance people (before entering the wind turbine) 3. Temporarily disconnect the Mark VIe controller from the site SCADA network: — Locate the SCADA network switch in the down tower assembly that houses the SCADA network switch — Disconnect the two fiber pairs (RX-TX and RX-TX) from the switch, taking the turbine off the site network 4. Press the "Stop-Reset" button to shut-down the plant manually. 5. Set the key-operated switch to "Repair".

Follow lock-out-tag-out procedures to de-energize, lock-out and tag-out equipment to ensure that unit equipment is always put in a safe condition. Wind conditions must be continuously monitored manually if LOTO procedures used mean that the unit is not

capable of moving to minimum load condition.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 53/64 GE Energy Safety Manual

Danger of accident! The WTG must remain shut down as long as personnel are in the plant. Before it is returned to service by authorized personnel, check without fail that nobody is in the plant. Otherwise there is the danger of an accident!

11.3 Climbing the Tower

• Only persons who are physically fit, are wearing appropriate PPE and are capable of coping with the ascent may climb the WTGS. • The WTGS must be shut down and secured against unauthorized start-up before the tower is ascended. The WTGS must remain shut down as long as anybody is climbing the tower or is on the tower platform. • The entrance door to the tower must be kept locked, in order to inhibit access to unauthorized persons. • In order to avoid accidents caused by falling objects, nobody may stand under the ladder while somebody is ascending the tower. Even a small screwdriver can cause very serious injuries if it drops from a great height.

Danger through falling objects! Falling objects can cause very serious injuries irrespective of their size and weight! Never stay in the vicinity of the ladder while somebody is ascending or descending. The ladder may only be used by one

person at a time. Only after this person has reached an Danger! intermediate platform and has closed the tower hatch or has reached the ground in the tower base and stepped back from the ladder may the next person approach the ladder. Tools and equipment must be secured while climbing.

• Fall protection PPE must always be put on correctly before ascending the tower. • Always check the safety harness and the entire safety equipment prior to use. Damaged PPE may never be used. • Safety boots and a hardhat must be worn when ascending the tower. Gloves must be worn while climbing. • The maximum possible fall path must be kept to a minimum by means of rope-shortening devices or similar. • Only use marked hooking points with an adequate load-bearing capacity. • The tower may only be ascended by means of the ladder installed inside the tower or (if the person is properly trained) the hoisting passenger suspension devices/service platform which may be installed. (Follow the operating instructions of the manufacturer).

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 54/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

• The rail or cable grab must run freely in the rail while ascending and descending the tower. Never touch the travelling safety hook, otherwise there is a danger of injury! • Both hands must be kept free during the ascent or descent. Tools, lubricants and other material may only be transported in a suitable bag. Permanent "3-point contact" with the ladder is only guaranteed by this means. • Greater care needs to be exercised when climbing the ladder experiencing wet conditions or if the tower is covered in ice. • Only unhook the lanyard after you have reached the tower platform and the access hatch has been closed. • Ensure that you are always protected by at least one lanyard with a fall arrest block. • The rest platforms in the tower are fitted with hatches that must be kept closed at all times. The platform hatches must therefore be opened on reaching a platform and closed again immediately after crossing to the next section of the tower. Tie off to anchor points while on platforms when hatches are open.

11.4 Deactivation of the Yaw Drive

Yaw stop switches are located in the tower base, below the nacelle and on the top box in the nacelle. The yaw drive and the automatic nacelle adjustment are disabled in the "Off" switch position, so that the nacelle is technically prevented from moving if there is a change in wind direction.

11.5 Entering the Nacelle

The yaw stop switch on the uppermost tower platform must be placed in the "Off" position before crossing from the tower to the nacelle. The yaw drive and the automatic nacelle adjustment are thereby disabled.

Depending on the position of the nacelle, the available simple ladder is hooked into one of the holders to prevent the ladder from slipping. Some of the WTGs are provided with a permanently installed extension ladder.

Hooking points are available in the vicinity of every platform.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 55/64 GE Energy Safety Manual

11.6 Walking on the Roof of the Nacelle/Entering the Rotor Hub

The roof of the nacelle may only be accessed for entering the rotor hub and for carrying out work on the wind vane, the anemometer and the obstruction light.

Only trained or instructed staff are permitted to enter the hub or walk on the roof of the nacelle. The rotor hub may only be entered at maximum wind speeds up to 15 m/s. The rotor lock on the high-speed shaft (brake disk on the coupling) must be engaged before the rotor hub is entered.

1. Place the yaw stop switch on the top box in the "Off" position. 2. Turn the rotor to the "Y" position, so that the rotor hub can be entered. 3. Engage the rotor lock on the high-speed shaft. 4. Turn the rotor blades to the 85° feathering position.

Fig. 15: Rotor in the "Y" position

Life-threatening hazard through sudden start-up of the rotor if the rotor lock (brake disk on the coupling) on the high-speed shaft has not been engaged! Always engage the rotor lock on the high-speed shaft before

entering the rotor hub. Danger! FOLLOW THE RESPECTIVE LOCKOUT/TAGOUT INSTRUCTIONS! (cf. Chapter 13)

Maintenance work inside the hub may only be carried out at maximum wind speeds up to 15 m/s!

Always engage the rotor lock on the high-speed shaft. Use of the Warning! rotor lock on the low-speed shaft or only the brake on the high- speed shaft for this purpose is prohibited.

Falling Hazard! Warning: strong wind currents! Before climbing out of the nacelle enclosure through the roof hatch above the gearbox, the lanyard must be hooked on to the rail on the nacelle, then transfer to the spinner if transitioning to the hub. The roof rail is to be selected as a hooking point for all other work on the roof of the nacelle. Follow the hub access and rotor Lock Out/Tag Out (LOTO) procedures, in addition to proper JSA/EHS Danger! procedures.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 56/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

5. In the hub, place the battery maintenance switch and the pitch maintenance switch on all three axis cabinets in the "Off" position.

Fig. 16: Battery maintenance switch

6. Switch the pitch controller on the control cabinet to "Manual".

Fig. 17: Pitch controller

Walking on the Roof with Ice and Snow If you have to walk on the roof of the nacelle or climb into the hub, first of all ensure that the rotor blades are in the Y position before you open the hatch. Otherwise there is danger of injury from falling pieces of ice.

Danger of Slipping and Falling Hazard as a result of icy conditions! There is a high risk of slipping and falling if the roof of the nacelle and the spinner are covered by snow and ice. Completely remove any snow and ice from the roof before walking on it. Sprinkle sand on the cleared areas Danger! Do not walk on the roof/spinner if the snow and ice cannot be removed completely and the danger of slipping cannot be excluded. Proper JSA/EHS procedures should be followed at all times.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 57/64 GE Energy Safety Manual

11.7 Activation of the Wind Turbine Generator System

Danger of accident! The WTG must remain shut down as long as personnel are in the turbine. Before it is returned to service by authorized personnel, check without fail that nobody is in the turbine. Otherwise the danger of an accident arises!

Proceed as follows to return the WTG to service:

1. Make an entry in the service life card of the WTG 2. Connect the Mark VIe controller to the site SCADA network: • Locate the SCADA network switch in the down tower assembly that houses the SCADA network switch • Reconnect the two fiber pairs (RX-TX and RX-TX) from the switch, putting the turbine on the site network 3. Set the key-operated switch to "Operation". 4. Check the alarm message panel in home web page for error messages 5. Press the "Stop-Reset" button and then the "Start" button. 6. Inform the remote monitoring division that wind turbine is back in operation 7. Inform the operator / customer that wind turbine is back in operation

12 Information on Maintenance and Troubleshooting

Only trained or instructed staff may be deployed!

Trainee personnel or personnel undergoing orientation or general training may only carry out work on the wind turbine generator system under the constant supervision of an experienced person.

Personnel must familiarize themselves with the work environment around the wind turbine generator system before starting work!

As it is possible to start the plant by means of the remote monitoring system, the WTG must be shut down for maintenance work as described in Chapter 11.2. In addition, the service switch on the control cabinet must be placed in the "Maintenance" or "Repair" position. Once the maintenance or repair work has been completed, the service switch must be returned to the "Automatic" position.

Maintenance/inspection of the cable winch in the tower is the responsibility of the operator and must be carried out in accordance with the operating and maintenance instructions of the supplier of the cable winch.

Time limits for recurring tests/inspections prescribed or stated in the operating manual must be adhered to.

Suitable workshop equipment is essential for carrying out maintenance measures.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 58/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

Work on electric equipment of the WTGS may only be carried out by a skilled electrician, equipment specific trained technician or by instructed persons under the guidance and supervision of a skilled electrician in accordance with the electrical engineering regulations.

Any safety equipment which has to be dismantled to carry out maintenance and repair work must be re- installed and checked immediately after the maintenance and repair work has been completed!

The wind turbine generator system, in particular the connections and bolted connections, must be cleaned of any oil, consumables and process materials, dirt or old preservative agents at the beginning of any maintenance/ repair / conservation work.

Only entrust experienced persons with the fastening of loads.

Individual components and larger modules which need to be exchanged must be carefully attached and secured to lifting gear, in order to minimize the danger that emanates from them. Only use suitable lifting gear and load suspension devices which are in a technically perfect condition and have an adequate load bearing capacity!

Follow the operating instructions of the winch manufacturer.

Never stand or work below suspended loads.

Use the specified or other safe ascent equipment and working platforms to carry out installation work above head height. Wear fall protection equipment when carrying out maintenance work at great heights. Keep all handles, steps, safety rails, platforms, stages and ladders free of dirt.

Ensure that consumables and process materials and replacement parts are disposed of safely and in an environmentally-friendly manner!

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 59/64 GE Energy Safety Manual

13 Power Disconnection and Isolation Procedures (Lock-out/Tag-out Instructions)

Pursuant to EN 50308 and OSHA standard 29 CFR 1910.147, wind turbine generator systems must be equipped with devices to disconnect and isolate them from all their energy sources during inspection and maintenance work.

These disconnecting/energy-isolating devices are prescribed for all mechanical, electrical and hydraulic energy sources.

GE Energy advises the plant operator/owner to develop specific procedures for the power disconnection and isolation of every individual subsystem.

Local and national regulations must be taken into account when developing workplace-specific Lockout/Tagout instructions.

The disconnection/isolation points are marked in the plant-specific circuit diagrams and hydraulic schematics supplied with the respective WTG.

Procedures for the Lock-out/Tag-out of power disconnection and isolation devices must consider the following aspects:

13.1 Identification of Installations, Processes, Circuits

(Individual mechanical, electrical or hydraulic subsystems)

13.2 Preparation for Shutdown / Notification of Affected Employees

• All personnel who may be affected must be notified before Lock-out/Tag-out devices are installed and after they have been removed. In addition to this procedure, authorized employees must be aware of any additional safety requirements prescribed for working on this type of equipment. • Affected employees who work on or near an installation which is about to be disconnected and on which Lock-out/Tag-out devices are to be mounted must be notified thereof.

13.3 Identification of Energy Sources and Strengths

13.4 Deactivation of Energy Sources and the Mounting of Energy Control Devices

• The power disconnection and isolation devices (e.g. disconnecting switches or load interrupter switches, valves etc.) must be positioned in such a way that they interrupt the energy flow to installations, processes or circuits. The authorized employees are obliged to mount and secure Lock-out/Tag-out devices to these. They must hereby ensure that the power disconnection and isolation devices are "locked out" until further notice and remain in their safety or "Off" position.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 60/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

13.5 Control of Stored Energy

Residual risks from stored energy!

PLEASE OBSERVE THE RESPECTIVE LOCKOUT / TAGOUT Attention! INSTRUCTIONS!

• The authorized employee must ensure that all potentially hazardous energy in any form (stored, residual, chemical or potential energy) is relieved, dissipated, contained, discharged or otherwise controlled. Additional measures may be necessary to prevent the re-accumulation or re-storage of energy, in order to protect personnel. Stored energy can form e.g. in batteries, capacitors, through gravity or in chemical lines.

13.6 Verification of Isolation

• The authorized employee must verify that the isolation and de-energization of the respective installation, process or circuit has actually been carried out before maintenance work may be started. The check must confirm that the installation, process or circuit has achieved a "zero" energy state. (Test equipment, circuit activation attempts, measuring devices, visual inspections, etc. can be used to verify the zero energy state.)

13.7 Reconnection of the Installation to the Supply

The authorized employee must carry out the following measures before returning the installation to service:

• Inspection of the work area to ensure that all items which are not required for the operation of the installation have been removed and that all the guards have been replaced, that the machine/installation, process or circuit is operational and that all personnel are in a safe location. • Removal of all locks, tags and other Lock-out/Tag-out devices from all power disconnection and isolation devices by the authorized employee who previously attached these LOTO devices. • Notification of affected personnel that the energy supply is about to be restored to the machine/installation, process or circuit. • Visual inspection and/or cycle test to verify that the service or maintenance work has been successfully completed. Provided that the work has been completed, the machine/installation, process or circuit may be returned to service. Otherwise, the requisite procedural steps must be repeated. • Correct sequential run-up of the installation, process or circuit.

WTG operators must ensure that suitable disconnection regulations are available for their plants and construction sites and those they are implemented. GE Energy has developed installation-specific Lock-out/Tag-out procedures for the activities listed below. This list does not claim to be complete, however. It may be advisable to develop additional procedures as a result of changes to installations or to comply with construction site-specific disconnection regulations.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 61/64 GE Energy Safety Manual

Service Jobs / Subsystems Installations, Processes, Circuits Gear box / gearing lubricant Nacelle – protection of the gear lubricant flow Work in the converter cabinet / on the generator Isolation of converter cabinet from dangerous energy / isolation of generator from dangerous energy Surge protector / medium voltage De-energize power distribution cabinet (PDC) at MV transformer. Surge protector / high voltage De-energize power distribution cabinet (PDC) at MV transformer. Work on the synchronization switch Isolation of the synchronization switch. De-energize power distribution cabinet (PDC) at MV transformer. Work on the safety isolated WTG Disconnection of the power distribution cabinet. Disconnection of the 400 V power supply Disconnection of the 400 V power supply to the power distribution cabinet in the tower base and to the top control cabinet in the nacelle and to the hub. Disconnection of the 690 V power supply Disconnection of the 690 V power supply to the power distribution cabinet in the tower base and to the top control cabinet in the nacelle. Work on the transformer in the DTA converter Disconnection of the transformer in the DTA converter filter cabinet filter cabinet Work on the UPS voltage output Disconnection of the 230 V UPS voltage output in the main cabinet and the control cabinet, the nacelle and the hub Disconnection of the 24 V power supply unit in Disconnection of the 24 V power supply unit in the main cabinet the main cabinet Isolation of the 400 V power supply from the Isolation of the 400 V power supply from the nacelle (top control cabinet) nacelle to the hub to the hub Nacelle hydraulics 24 V transformer / interruption of the hydraulic supply 24 V transformer in the nacelle 24 V transformer in the top control cabinet (e.g. for exchanging the transformer) Battery charging voltage nacelle / hub Disconnection of the battery charging voltage to the hub 230 V power supply to the nacelle Disconnection of the battery charger, interruption of the 230 V power supply Nacelle / motors Disconnection of the motor 400 V motor circuit breaker in the nacelle Disconnection of the 400 V motor circuit breaker Work in the hub Disconnection of the motor (hub) Work in the hub Back-up battery pack in the hub Locking the high-speed shaft Nacelle / high-speed shaft (gear box) Locking the low-speed shaft Nacelle / low-speed shaft (gear box) Work on the transformer Isolation of the transformer in WTGS with a transformer in the tower

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 62/64 1.x_OM_allComp_safety_ESS.ENxxx.00 GE Energy Safety Manual

ANNEX: Items and Installations which are subject to Inspection pursuant to the Accident Prevention Regulations

Test before the Regular Proof of Article to be tested Exceptional tests Regulations initial operation tests test Winches To be checked by a Regular check by a Inspect Manufacturer' technically competent technically competent person and test s instructions person in accordance with the log book manufacturer's instructions and and operational conditions. inspection sticker Doors To be checked by a Regular check by the Document Manufacturer' Emergency exits technically competent operator. Once a year by a ary s instructions person. Doors must be technically competent evidence executed so that they are person. self-closing, open in the direction of escape and can be easily opened from the inside at all times without auxiliary means. Escape routes In case of danger, the work areas must be able to evacuated via escape routes or escape equipment. It must be ensured that at least one escape route can also be used in the case of a power failure. Escape routes or escape equipment are: routes via ladders and abseiling devices. Service lift To be checked by an The operator must All components of the Document Manufacturer' expert. ensure that hoisting hoisting passenger ary s instructions In addition to the experts passenger suspension suspension device must be evidence of the Technical devices are subjected inspected for operational Inspection Association to an exceptional test safety by a technically (TÜV), only experts for the by a qualified person competent person at least inspection of hoisting after cases of damage once a year. passenger suspension or particular events Shorter test intervals may devices who are which could affect the arise as a result of the service authorized by the trade carrying capacity, as conditions. association are well as after any repair The manufacturer's considered to be experts work. instructions are to be for the purposes of this followed. safety regulation. The operator must ensure that a test run is carried out at the installation location in all directions of movement with the working load of the passenger suspension device in the presence of the supervisor before the initial operation. Fire extinguishers Regular check by a Inspection (optional feature) technically competent person sticker or or expert in accordance with test report the national regulations.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 1.x_OM_allComp_safety_ESS.ENxxx.00 63/64 GE Energy Safety Manual

Test before the Regular Proof of Article to be tested Exceptional tests Regulations initial operation tests test Personal protective Check of the fall Users must check the PPE for Inspect Manufacturer' equipment against protection rail by an its orderly condition and and test s instructions falling (safety experienced person. correct function before it is log book, harness) used. inspection An experienced person must sticker check the PPE for perfect condition at regular intervals. The manufacturer's instructions are to be followed. Abseiling device To be checked by an To be checked by an Users must check the Inspect Manufacturer' experienced person. experienced person abseiling device for its orderly and test s instructions after use. condition and correct log book, function before it is used. inspection An experienced person must sticker check the abseiling device for perfect condition at regular intervals. The manufacturer's instructions are to be followed. Ladder A technically A technically competent Inspect Manufacturer' competent person person checks the orderly and test s instructions checks the orderly condition of the ladders and log book, condition of steps once a year. inspection mechanical ladders Irrespective of this, the user sticker after any alterations or must check the suitability and repairs. condition of the ladders before use. The manufacturer's instructions are to be followed. Electrical Check by a qualified At specified intervals: Inspect Manufacturer' equipment electrician or under the The intervals are to be and test s instructions supervision of a qualified calculated in such a way that log book electrician. (Also after any defects which can be alteration or repair) expected to arise are found in The test before the initial due time. operation in accordance The relevant electro-technical with Section 1 is not regulations are to be necessary if the complied with for the check. manufacturer or installer At the request of the trade confirms that the association, an inspection electrical installations and and test log book with equipment are designed specified entries is to be kept. to comply with the The manufacturer's provisions of this accident instructions are to be prevention regulation. followed. First aid box Pursuant to the Law on Medical Devices, which has been in force since 1st January 1995*, bandaging materials (optional feature) must have a CE-marking but do not have to have a use-by date. If a use-by date is stated, however, the Law on Medical Devices prohibits further use after expiry of the use-by date under penalty of a fine. First aid material without a use-by date must only be replaced in the event of soiling or damage. With the exception of plaster material, it remains usable over a long period, provided that it is stored in a clean and dry place.

CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2011 General Electric Company. All rights reserved 64/64 1.x_OM_allComp_safety_ESS.ENxxx.00 ATTACHMENT G: NOISE ANALYSIS

17 March 2016

Invenergy LLC Hardin Wind Energy LLC One South Wacker Drive Suite 1900 *** via email ([email protected]) *** Chicago, IL 60606

Attention: Kent N. Truckor Manager, Business Development

Subject: Sound Model for Additional Updated Turbine Layout (11 March 2016) Proposed Hardin Wind Farm Hardin County, Ohio Acentech Project No. 627334

References: Your February and March 2016 emails to me Acentech Project Nos. 620456 & 624960

Dear Mr. Truckor:

At your request, Acentech developed updated sound models (March 2016) of the proposed nominal 270 MW Hardin Wind Farm. The current plan for this wind farm consists of 118 wind turbine generators (WTGs), which may be either the GE Model 2.3-116 or the GE Model 2.3-116 LNTE version. The project area is mostly agricultural land that includes about 1311 residences located over the site and within one mile of the site boundary. This turbine layout supersedes earlier layouts that were under consideration and that were modeled in 2009 and 2014. The results of our updated sound model for the currently proposed Hardin Wind farm are presented in this letter report and additional files.

We updated our Cadna/A computer sound model for the Hardin Wind project and estimated the sound contributions of the proposed 118 turbines. The source levels were based on turbine vendor data that you provided us. Our studies assumed all wind turbines were operating at the maximum sound levels provided by the vendor. The model included all residential receptor locations that were provided by Invenergy and the results show all residences within one-mile of the 118 proposed wind turbine project area.

Sound Model Description The estimated sound levels and contours, which apply to both daytime and nighttime hours for the operating phase, were developed with the computer noise modeling program, Cadna/A. This commercial software program, which was developed by DataKustik GmbH (www.datakustik.de), is widely-accepted by the international acoustics community for the calculation of community sound levels due to industrial sources. The calculations are performed for industrial sources according to the following international standards:

acoustics  av/it/security  vibration Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 2 of 19

• ISO 9613-1: Acoustics - Attenuation of sound during propagation outdoors, Part 1: Calculation of the absorption of sound by the atmosphere, and

• ISO 9613-2: Acoustics - Attenuation of sound during propagation outdoors, Part 2: General method of calculation.

Inputs to the program include: source locations and associated sound power emissions, receptor locations, land topography, and meteorological conditions. The calculations account for spreading losses, atmospheric attenuation, ground effects, terrain and other barrier shielding, and reflections for the sound between each source and each receptor. For this study, the sound propagation routines and barrier calculations in the Cadna/A model are based on octave band sound pressure levels and on downwind conditions with a moderate temperature inversion. The following describes significant parameters used in the sound model at your request:

• Turbine, project boundary, 1-mile boundary, and residence locations – the shape files with these data were owner-provided.

• Land elevation contours – the shape files with these data were owner-provided.

• Wind turbine data – Model GE 2.3-116 and Model GE 2.3-116 LNTE version with respective maximum A-weighted sound power levels (LwA) of 107.5 and 106 dBA and hub height at 80 meters (turbine input as point source at 80m height above local terrain). Spectral values based on published vendor data.

• Meteorological conditions are 10°C (50°F) and 70%RH, moderate inversion, and all receptors downwind from turbines.

• Ground conditions – moderate soft ground with parameter G = 0.5 and spectral calculations for all sources.

• Receptor heights – 1.5m above local ground elevation.

Sound Model Results Figures 1 and 2 present the proposed wind farm layout with the 118 GE 2.3-116/GE 2.3-116 LNTE turbines, project boundary, one-mile boundary from the project, the residences within the one-mile boundary, and the estimated sound level contours in 5 dBA increments. The computer shape files of the sound level contours (1 dBA increments) and an Excel file with the estimated facility sound level at each of the 1311 residences within one-mile boundary of the project site are provided in a separate transmittal. The estimates are based on the greatest sound output condition for each turbine model (e.g., LwA=107.5 dBA and 106 dBA at ≥9.8 m/s wind speed at the hub height elevation). Table 1 lists the overall turbine facility sound levels (dBA) for the 390 residences within the one-mile boundary of the project with GE 2.3- 116 turbines installed that have estimated levels at or above 43 dBA. The estimated sound levels produced only by the wind farm range at the residences within the one-mile boundary of the project from less than 10 dBA to about 51 dBA for the GE 2.3-116 turbine layout and 49 dBA for the GE 2.3-116 LNTE turbine layout. Note that these results represent typical upper levels that apply to both daytime and nighttime hours; levels up to about 4 dB greater than these should be expected at times under certain meteorological and operating conditions.

Although the turbines will be heard at community locations at times during turbine operation and quieter ambient sound levels, the WTG sound emissions will be less under conditions of reduced wind speeds, including the times below the minimum cut-off wind speed when the turbine does not operate. For example, the estimated sound levels will be less than the displayed values by about 3 dBA for hub-height wind speeds of 8 m/s and about 6 dBA less for 7 m/s.

* * * * *

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 3 of 19

Please contact me if you have any questions regarding our analysis or this letter.

Sincerely yours,

James D. Barnes Acentech Incorporated

Figures 1 to 2 Table 1

J:/627334-Invenergy-Hardin-AdditionalUpdateWTGs031716.docx

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 4 of 19

Figure 1a. Map Showing Residences (O) and Project Site with Proposed 118 Turbine GE 2.3-116 Locations (+), Project Boundary Line (Gray), One-Mile Buffer Line (Red), and Turbine Sound Level Contours.

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 5 of 19

Figure 1b. Map Showing Residences (O) and Project Site with Proposed 118 Turbine GE 2.3-116 Locations (+), Project Boundary Line (Gray), One-Mile Buffer Line (Red), and Turbine Sound Level Contours.

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 6 of 19

Figure 1c. Project Layout Showing Residences (O) and Project Site with Proposed 118 Turbine GE 2.3- 116 Locations (+), Project Boundary Line (Gray), One-Mile Buffer Line (Red), and Turbine Sound Level Contours.

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 7 of 19

Figure 2a. Map Showing Residences (O) and Project Site with Proposed 118 Turbine GE 2.3-116 LNTE Locations (+), Project Boundary Line (Gray), One-Mile Buffer Line (Red), and Turbine Sound Level Contours.

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 8 of 19

Figure 2b. Map Showing Residences (O) and Project Site with Proposed 118 Turbine GE 2.3-116 LNTE Locations (+), Project Boundary Line (Gray), One-Mile Buffer Line (Red), and Turbine Sound Level Contours.

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 9 of 19

Figure 2c. Project Layout Showing Residences (O) and Project Site with Proposed 118 Turbine GE 2.3- 116 LNTE Locations (+), Project Boundary Line (Gray), One-Mile Buffer Line (Red), and Turbine Sound Level Contours.

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 10 of 19

Table 1. Estimated Overall Turbine Facility Sound Levels (dBA) for 241 Residences at or above 43 dBA for Proposed 118 GE 2.3-116 and GE 2.3-116 LNTE Turbine Layouts. (operating condition at maximum sound output for each turbine model, i.e., A-weighted sound power level of 107.5 and 106 dBA with ≥10 m/s hub-height wind speed)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 50.7 49.1 268136.07 4507049.77 298.68 50.2 48.6 264571.13 4502498.6 298.93 49.6 48 268461.17 4506891.35 298.68 49.5 47.9 268532.94 4506871.18 298.68 49.5 47.9 264287.76 4501900.9 299.43 49.1 47.5 268538.46 4506848.3 298.68 49.1 47.5 263421.38 4500994.83 303.65 48.5 46.8 264646.54 4507480.05 297.76 48.4 46.8 267997.16 4506542.43 297.57 48.1 46.4 265734.19 4506288.21 297.16 47.8 46.2 260638.42 4506535.82 297.91 47.8 46.2 263939.3 4508068.53 298.33 47.8 46.1 265437.32 4507939.63 298.58 47.7 46 268361.42 4506761.4 298.66 47.7 46 268300.77 4506759.39 298.48 47.7 46.1 268267.7 4506767.99 298.39 47.5 45.9 268402.09 4506744.89 298.68 47.5 45.9 265046.44 4508343.88 298.68 47.5 45.9 268359.64 4506748.81 298.65 47.5 45.9 260573.96 4509788.45 298.68 47.5 45.9 260603.41 4509787.47 298.68 47.4 45.8 268455.55 4506737.56 298.68 47.4 45.8 260155.56 4506499.43 298.68 47.4 45.8 265823.6 4505862.45 297.16 47.4 45.8 267132.92 4506298.16 296.7 47.3 45.6 268407.5 4506723.44 298.68 47.3 45.7 260633.13 4506403.52 297.79 47.3 45.7 261265.49 4504864.31 297.16 47.3 45.6 268352.1 4506721.17 298.62 47.2 45.6 262472.87 4501924.6 297.73 47.2 45.6 268289.53 4506711.1 298.45 47.2 45.7 265069.11 4508290.28 298.68 47.1 45.5 264963.15 4508420.86 298.68 47.1 45.5 268380.15 4506708.46 298.68 47.1 45.5 259837.87 4508757.29 298.44 47.1 45.4 260223.03 4506537.8 298.68 47.1 45.5 259840.71 4508905.09 298.68

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 11 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 47 45.3 268322.22 4506683.11 298.52 47 45.4 268340.46 4506693.24 298.58 47 45.4 260191.28 4506543.09 298.68 47 45.4 259408.77 4506491.5 299.93 47 45.4 264997.9 4508351.13 298.68 47 45.4 260135.71 4506546.4 298.68 47 45.4 260501.06 4509812.64 298.7 47 45.4 260402.17 4509792.71 298.81 47 45.4 267051.86 4506298.16 296.99 47 45.3 268206.84 4506644.96 298.19 46.9 45.3 268372.21 4506685.3 298.66 46.9 45.2 260263.72 4506566.61 298.68 46.9 45.3 265262.39 4507947.77 298.6 46.8 45.2 268251.54 4506639.71 298.31 46.8 45.2 260440.84 4509815.11 298.79 46.8 45.2 264998.47 4508320.44 298.68 46.7 45.1 259827.92 4508333.81 297.6 46.7 45.1 260592.78 4505816.15 298.64 46.7 45.1 264141.31 4501201.21 303.5 46.7 45.1 270821.5 4508647.88 301.76 46.6 44.9 259770.37 4508215.15 298.25 46.6 44.9 259820.82 4508367.92 297.73 46.6 45 259739.81 4508112.12 297.7 46.6 44.9 264636.28 4504407.24 296.61 46.6 45 264994.9 4508291.07 298.68 46.6 45 264952.83 4508356.95 298.68 46.5 44.9 268304.74 4506617.84 298.45 46.5 44.9 259856.91 4507457.56 298.68 46.5 44.9 265456.49 4506385.66 297.16 46.5 44.8 259812.29 4508542.71 298.16 46.5 44.9 259564.87 4506563.6 299.39 46.5 44.9 264907.98 4508444.26 298.68 46.5 44.9 264966.32 4508322.42 298.68 46.5 44.9 264994.81 4508272.12 298.68 46.4 44.8 259810.87 4508489.42 298.06 46.4 44.8 260286.68 4509785 298.9 46.4 44.8 264614.12 4506311.14 295.7 46.4 44.8 263257.87 4499913.74 303.11 46.4 44.8 264909.57 4508430.77 298.68 46.4 44.7 265024.27 4508193.04 298.68 46.4 44.8 264994.9 4508244.24 298.68 46.4 44.8 264966.72 4508299.4 298.68

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 12 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 46.3 44.7 259907.18 4507362.97 298.68 46.3 44.7 260686.71 4504842.48 299.31 46.3 44.7 264935.76 4508322.82 298.68 46.3 44.7 264915.92 4508385.13 298.68 46.2 44.6 264960.71 4508269.2 298.68 46.2 44.6 263497.36 4500338.25 303.95 46.1 44.4 268328.55 4506562.93 298.49 46.1 44.5 266385.88 4498289.53 321.16 46.1 44.6 264880.2 4508448.63 298.68 46.1 44.4 264992.52 4508150.18 298.68 46.1 44.5 264986.96 4508194.63 298.68 46.1 44.5 264892.5 4508370.84 298.68 46.1 44.5 264888.53 4508385.13 298.68 46.1 44.4 265021.49 4507956.5 298.63 46 44.3 264987.59 4508102.23 298.68 46 44.4 266353.5 4498527.06 318.83 46 44.4 264990.93 4508123.99 298.68 46 44.4 264955.21 4508196.61 298.68 46 44.4 264890.12 4508352.98 298.68 46 44.4 263501.79 4500302.52 304 45.9 44.2 268329.83 4506531.89 298.48 45.9 44.3 264987.74 4508078.31 298.68 45.9 44.3 264890.69 4508327.98 298.68 45.9 44.3 264862.34 4508409.74 298.68 45.9 44.3 264959.58 4508152.16 298.68 45.8 44.2 260221.96 4509788.82 298.93 45.8 44.2 263499.96 4500258.23 304.14 45.8 44.2 260959.28 4504873.55 298.66 45.8 44.2 264953.23 4508119.22 298.68 45.8 44.2 264946.48 4508086.28 298.68 45.8 44.1 264913.14 4508204.55 298.68 45.8 44.2 264886.55 4508294.64 298.68 45.8 44.2 264859.96 4508383.94 298.68 45.7 44.1 264859.77 4508327.62 298.68 45.7 44.1 264885.76 4508277.58 298.68 45.7 44.1 264884.96 4508251.78 298.68 45.7 44.2 264857.98 4508371.24 298.68 45.7 44.1 264559.45 4507916.7 298.5 45.6 44 270530.32 4508791.65 301.92 45.6 43.9 259858.84 4509415.79 298.68

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 13 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 45.6 44 264830.26 4508432.5 298.68 45.6 43.9 268353.03 4506494.8 298.52 45.6 43.9 270935.68 4509539.42 313.92 45.6 44 264827.42 4508411.72 298.68 45.6 44 264829 4508423.23 298.68 45.6 44 264855.2 4508278.37 298.68 45.6 44 264827.81 4508446.25 298.68 45.6 44 264886.95 4508180.74 298.68 45.6 44 264888.93 4508197.8 298.68 45.5 43.9 264879.38 4508154.31 298.68 45.5 43.8 264847.09 4508084.59 298.68 45.5 43.8 270969.71 4509188.04 313.4 45.5 43.9 264723.04 4507957.69 298.6 45.5 43.9 264706.77 4507962.06 298.6 45.5 43.9 264851.63 4508250.99 298.68 45.5 43.9 264879.01 4508105.33 298.68 45.5 43.9 264502.69 4507986.65 298.62 45.5 43.8 264851.63 4508200.98 298.68 45.5 43.8 264651.6 4507970.79 298.6 45.4 43.8 268345.8 4506471.8 298.5 45.4 43.8 264801.98 4508446.18 298.68 45.4 43.8 264850.89 4508119.22 298.68 45.4 43.8 262530.4 4502115.21 297.55 45.4 43.7 260168.51 4509789.18 298.94 45.4 43.8 264670.65 4507973.57 298.61 45.4 43.8 264845.67 4508185.1 298.68 45.4 43.8 264837.34 4508159.7 298.68 45.4 43.8 264850.04 4508159.31 298.68 45.3 43.7 270837.14 4507753.89 297.16 45.3 43.6 271034.63 4508608.69 301.96 45.3 43.7 264662.71 4508024.37 298.68 45.3 43.7 264816.7 4508195.42 298.68 45.3 43.7 264821.07 4508163.67 298.68 45.2 43.6 268350.95 4506435.01 298.49 45.2 43.6 264768.86 4508129.87 298.68 45.2 43.7 259764.22 4504815.63 302.15 45.2 43.5 264688.03 4508073.89 298.68 45.2 43.6 268837.62 4509448.9 308.15 45.2 43.6 264963.64 4501871.93 301.98 45.2 43.6 270985.63 4508693.2 304.07

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 14 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 45.2 43.6 264668.27 4508041.04 298.68 45.2 43.6 264760.14 4508096.75 298.68 45.2 43.5 264770.27 4508162.09 298.68 45.2 43.6 264782.57 4508358.54 298.68 45.2 43.6 264779.79 4508385.92 298.68 45.1 43.5 272509.46 4508647.01 308.5 45.1 43.5 269231.1 4506995.86 297.16 45.1 43.5 264776.8 4508332.12 298.68 45.1 43.5 264743.82 4508129.18 298.68 45.1 43.5 268977.16 4509441.84 309.52 45.1 43.5 270963.07 4510327.48 312.4 45.1 43.5 264777.41 4508268.05 298.68 45.1 43.5 264779.39 4508246.62 298.68 45.1 43.5 264607.15 4508064.85 298.68 45.1 43.5 264767.88 4508203.36 298.68 45.1 43.5 264772.95 4508230.57 298.68 45 43.4 260124 4509787.37 298.95 45 43.4 264748.44 4508387.75 298.68 45 43.4 264745.06 4508359.69 298.68 45 43.4 264618.09 4508108.68 298.68 45 43.4 259320.13 4506582.78 299.92 45 43.4 270970.93 4508960.22 309.33 45 43.4 264753.99 4508495.46 298.68 45 43.4 264730.98 4508203.36 298.68 45 43.4 264665.09 4508114.06 298.68 45 43.4 264667.47 4508133.51 298.68 44.9 43.3 264719.26 4508319.21 298.68 44.9 43.3 269333.64 4506773.61 297.29 44.9 43.3 269324.71 4506810.98 297.22 44.9 43.3 259771.25 4506799.74 298.68 44.9 43.3 264612.31 4508135.1 298.68 44.9 43.3 264723.43 4508334.73 298.68 44.9 43.3 264664.7 4508163.28 298.68 44.9 43.3 264661.12 4508180.74 298.68 44.8 43.2 268565.89 4509561.96 309.62 44.8 43.2 264728.05 4508512.5 298.68 44.8 43.2 264724.8 4508487.18 298.68 44.8 43.2 262680.41 4502293.81 297.3 44.8 43.1 269340.25 4506891.35 296.83 44.8 43.3 265556.71 4496997.37 330.68

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 15 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 44.8 43.1 263511.08 4500084.4 304.67 44.8 43.2 264719.86 4508385.13 298.68 44.8 43.2 264666.28 4508201.38 298.68 44.7 43 262683.71 4502338.63 297.24 44.7 43.1 260106.81 4509803.26 299 44.7 43.1 269305.53 4506573.52 297.48 44.7 43.1 267991.55 4509552.23 303.77 44.7 43 269248.59 4508024.78 297.16 44.7 43.1 264667.47 4508285.51 298.68 44.7 43.1 264665.49 4508261.3 298.68 44.7 43.1 264671.44 4508306.94 298.68 44.6 43 264679.7 4508377.49 298.68 44.6 43 259862.4 4509558.36 298.68 44.6 43 264673.82 4508362.9 298.68 44.5 42.9 272536.58 4509052.01 307.6 44.5 42.9 269312.14 4506499.43 297.5 44.5 43 259267.88 4506588.73 300.06 44.5 43 264673.43 4508418.47 298.68 44.5 43 264679.78 4508454.98 298.68 44.5 42.9 264673.43 4508478 298.68 44.5 42.9 264678.19 4508499.43 298.68 44.5 42.8 272577.5 4508873.02 308.51 44.4 42.8 262588.61 4502300.47 297.34 44.4 42.8 259864.71 4509587.39 298.68 44.4 42.8 264634.14 4508423.63 298.68 44.4 42.9 264680.57 4508535.15 298.68 44.4 42.8 266455.89 4498573.1 318.33 44.4 42.8 264700.81 4508633.97 298.68 44.3 42.7 264637.08 4508469.86 298.68 44.3 42.7 267635.63 4509515.14 305.67 44.3 42.7 268358.32 4506289.75 298.45 44.3 42.6 260036.46 4509791.14 298.99 44.3 42.7 259111.11 4504205.49 306.28 44.3 42.7 264031.78 4500845.61 304.78 44.3 42.7 264713.89 4508713.43 298.68 44.2 42.6 269112.2 4509494.71 310.87 44.2 42.5 270616.83 4509457.64 309.35 44.2 42.6 268360.15 4506265.76 298.46 44.2 42.6 269279.73 4506491.5 297.6 44.2 42.6 269367.04 4506356.56 297.4

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 16 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 44.2 42.5 259868.03 4509624.79 298.68 44.2 42.6 260081.36 4509832.21 299.09 44.2 42.5 260037.2 4509803.38 299.02 44.2 42.7 264696.84 4508671.67 298.68 44.2 42.7 264634.53 4508501.02 298.68 44.1 42.5 264562.98 4508423.65 298.68 44.1 42.6 264105.99 4508388.63 298.72 44.1 42.5 269380.93 4506328.12 297.37 44.1 42.5 260079.07 4509843.62 299.12 44.1 42.5 260039.68 4509814.51 299.05 44.1 42.5 264061.84 4508407.35 298.69 44.1 42.6 259080.02 4504340.43 306.21 44.1 42.5 263419 4499861.36 304.2 44.1 42.5 270222.4 4507802.93 297.16 44 42.4 264181.92 4508403.8 298.82 44 42.4 269157.36 4506547.72 297.91 44 42.4 259651.52 4506952.53 298.83 44 42.4 268990.4 4509542.52 310.87 44 42.4 269481.44 4509313.78 306.49 44 42.4 260078.88 4509855.99 299.15 44 42.3 260038.32 4509825.77 299.08 44 42.4 263990.8 4508441.49 298.68 44 42.4 264561.51 4508470.85 298.69 44 42.5 264528.17 4508424.02 298.68 44 42.4 264501.18 4508424.82 298.68 44 42.4 264526.98 4508439.9 298.68 44 42.4 269231.86 4506510.91 297.73 44 42.4 264613.1 4508568.49 298.73 44 42.4 264644.85 4508646.27 298.7 43.9 42.3 259180.76 4506583.94 300.2 43.9 42.4 264245.81 4508401.77 298.76 43.9 42.3 260080.41 4509867.26 299.18 43.9 42.2 260038.99 4509837.59 299.11 43.9 42.4 259134.92 4504115.53 305.45 43.9 42.4 264501.18 4508437.91 298.68 43.9 42.3 264527.38 4508472.05 298.72 43.9 42.3 264477.37 4508427.6 298.68 43.9 42.3 264440.46 4508427.6 298.68 43.9 42.3 272603.12 4508747.65 308.32 43.8 42.3 263957.43 4508469.65 298.7

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 17 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 43.8 42.2 264319.24 4508435.78 298.79 43.8 42.2 260081.08 4509879.08 299.21 43.8 42.2 259998.14 4509805.72 299.04 43.8 42.2 259865.87 4509671.93 298.71 43.8 42.3 264411.49 4508429.98 298.7 43.8 42.2 264474.2 4508461.73 298.73 43.8 42.3 264498.41 4508470.46 298.73 43.8 42.3 264529.76 4508502.6 298.79 43.8 42.2 264367.44 4508429.98 298.74 43.8 42.2 264188.45 4508437.91 298.89 43.8 42.3 264146.77 4508439.9 298.93 43.8 42.2 268399.77 4506222.02 298.59 43.8 42.2 264574.21 4508589.92 298.83 43.8 42.3 264587.31 4508585.95 298.8 43.7 42.1 264397.9 4508473.45 298.82 43.7 42.2 264240.45 4508446.04 298.87 43.7 42.2 267923.74 4505855.83 298.22 43.7 42.1 264359.17 4508462.36 298.82 43.7 42.1 269318.76 4506345.31 297.53 43.7 42.2 264254.79 4508439.19 298.85 43.7 42.2 269294.28 4506381.03 297.59 43.7 42 260081.5 4509892.21 299.25 43.7 42.1 260039.27 4509849.9 299.15 43.7 42 260040.18 4509860.4 299.17 43.7 42.1 259998.59 4509816.29 299.07 43.7 42.2 264441.26 4508466.89 298.77 43.7 42.1 264473.8 4508506.18 298.84 43.7 42.2 264562.7 4508593.89 298.86 43.6 42 263887.98 4508531.46 298.72 43.6 42 264275.26 4508475.54 298.92 43.6 42 264194.01 4508478.79 298.99 43.6 41.9 260040.31 4509871.88 299.21 43.6 42 259997.93 4509828.73 299.1 43.6 42 259958.43 4509793.68 299.02 43.6 42.1 264446.42 4508505.78 298.86 43.6 42 264254.72 4508478.4 298.94 43.6 42 264226.55 4508479.98 298.96 43.6 42.1 264334.1 4508474.43 298.87 43.6 42.1 264552.38 4508599.84 298.89 43.6 42 264413.08 4508506.18 298.89

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 18 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 43.5 41.9 271052.69 4510774.05 309.39 43.5 42 264065.22 4508506.36 298.97 43.5 42 263948.19 4508534.67 298.91 43.5 41.9 264332.9 4508512.02 298.96 43.5 41.8 260041.53 4509884.04 299.24 43.5 41.9 259997.66 4509840.69 299.13 43.5 41.9 259958.71 4509805.98 299.05 43.5 41.9 259961.11 4509816.7 299.08 43.5 41.9 259871 4509716.72 298.83 43.5 42 263994.77 4508523.24 298.95 43.5 42 264151.93 4508493.08 299.05 43.5 42 264454.35 4508535.94 298.93 43.5 41.9 265222.4 4501829.07 302.75 43.5 41.9 272022.76 4508265.13 308.16 43.5 42 264525.39 4508612.94 298.96 43.5 42 264411.49 4508522.05 298.92 43.5 41.9 264413.08 4508538.32 298.96 43.4 41.9 269259.02 4506365.28 297.68 43.4 41.9 264274.08 4508516.45 299.02 43.4 41.8 264451.63 4508592.4 299.06 43.4 41.8 269970.29 4506181.27 297.34 43.4 41.8 259928.04 4509796.02 299.03 43.4 41.8 260044.15 4509896 299.27 43.4 41.8 259998.65 4509851.61 299.16 43.4 41.8 259960.84 4509828.65 299.11 43.4 41.9 264226.55 4508512.53 299.04 43.4 41.9 264288.06 4508511.73 298.99 43.4 41.9 264510.71 4508619.68 299 43.4 41.9 264306.71 4508512.13 298.98 43.4 41.9 264412.68 4508553.8 299 43.3 41.8 263911.82 4508579.47 298.95 43.3 41.8 264203.91 4508535.97 299.12 43.3 41.6 259998.98 4509874.98 299.23 43.3 41.7 259997.44 4509863.71 299.2 43.3 41.7 259960.57 4509840.61 299.14 43.3 41.7 259866.89 4509747.55 298.92 43.3 41.7 266507.62 4497961.78 327 43.3 41.6 266559.21 4498204.66 324.53 43.3 41.8 264749.08 4508978.56 298.68 43.3 41.8 264395.22 4508571.66 299.06

Kent N. Truckor Hardin Wind, Hardin County, OH 17 March 2016 Page 19 of 19

Table 1 (Con’t.)

Sound Level Sound Level Coordinates GE 2.3-116 GE 2.3-116 LNTE X Y Z (dBA) (dBA) (m) (m) (m) 43.3 41.7 264163.44 4508556.98 299.2 43.2 41.7 264333.08 4508586.42 299.14 43.2 41.7 264209.04 4508561.26 299.17 43.2 41.7 264165.97 4508571.4 299.23 43.2 41.6 268656.57 4509700.6 310.7 43.2 41.6 269483.21 4509425.06 307.66 43.2 41.5 263482.5 4499828.02 304.55 43.2 41.7 269262.53 4506328.78 297.66 43.2 41.6 268550.14 4506215.67 298.68 43.2 41.6 259907.82 4509796.01 299.04 43.2 41.6 259999.58 4509886.38 299.26 43.2 41.6 259961.24 4509852.43 299.18 43.2 41.6 259875.41 4509770.98 298.98 43.2 41.7 264372.6 4508588.73 299.11 43.1 41.6 264208.12 4508590.42 299.24 43.1 41.6 264166.29 4508590.19 299.28 43.1 41.5 267111.04 4509495.71 304.85 43.1 41.5 259999.31 4509898.34 299.29 43.1 41.5 259961.3 4509863.49 299.21 43.1 41.6 269320.08 4506262.63 297.5 43.1 41.6 264364.66 4508626.03 299.21 43 41.5 264270.32 4508627.44 299.29 43 41.5 264339.06 4508634.26 299.25 43 41.5 264162.64 4508624.56 299.36 43 41.4 270899.32 4507615.65 297.16 43 41.5 269376.97 4506213.02 297.35 43 41.4 259962.29 4509874.41 299.23 43 41.5 264293.62 4508622.46 299.26 43 41.5 264310.29 4508632.78 299.27 43 41.5 264204.72 4508616.51 299.31 43 41.5 264413.08 4508680.8 299.26

ATTACHMENT H: SHADOW FLICKER STUDY Shadow Flicker Impact Analysis for the Hardin Wind Farm

Prepared for Hardin Wind Energy LLC

Prepared by

160 Federal Street Boston, MA 02110

July 2009 Updated December 2009 Updated June 2011 Updated June 2014 Updated March 2016 Hardin Wind Farm – Shadow Flicker Analysis

TABLE OF CONTENTS

EXEXCUTIVE SUMMARY ...... 1 1.0 BACKGROUND ...... 2 2.0 WINDPRO SHADOW FLICKER ANALYSIS ...... 3 3.0 WINDPRO SHADOW FLICKER ANALYSIS RESULTS...... 5 4.0 CONCLUSION ...... 7

TABLES

Table 1. Receptors with Over 30 Expected Annual Average Shadow Hours...... 5 Table 2. Statistical Summary of Expected Annual Average Shadow Hours ...... 6

FIGURES

Figure 1 Sensitive Receptors Modeled with WindPro to Predict Expected Shadow Flicker Impacts...... 8 Figure 2 Map of WindPro Estimated Shadow Flicker Impacts for the Hardin Wind Farm (Expected Hours per Year) ...... 9

ATTACHMENT

Attachment A Detailed Summary of WindPro Shadow Flicker Analysis Results

i Hardin Wind Farm – Shadow Flicker Analysis

EXEXCUTIVE SUMMARY

A shadow flicker impact analysis was originally conducted for the Hardin Wind Farm Project (Project) in July 2009. That analysis was based on the original 212 wind turbine layout project design. The July 2009 analysis was updated in December of 2009 to evaluate the revised Project based on a layout design comprising 203 wind turbines. The analysis was again updated to evaluate the Phase 1a project layout of 132 wind turbines in June of 2011. The analysis was further updated in June 2014 to evaluate the revised project layout of 121 wind turbines and a new wind turbine model (GE 2.5 – 120). The analysis presented here is based on an updated layout of 118 turbine locations and new turbine model (GE 2.3-116) as of March 2016.

The calculated sunshine probability data is presented in Section 2. The WindPro prediction results are presented in Section 3.

1 Hardin Wind Farm – Shadow Flicker Analysis

1.0 BACKGROUND

A wind turbine’s moving blades can cast a moving shadow on locations within a certain distance of a turbine. If the shadows pass over a window of a home or public gathering place, they can create alternating periods of low and high light, a temporary phenomena referred to as “shadow flicker”. The maximum length of the shadows depends on the time of year and day (which determines the sun’s azimuth and altitude angles) and the wind turbine’s physical characteristics (height, rotor diameter, blade width, and orientation of the rotor blades). Shadows are longest during low angle sunlight conditions, typical during sunrise and sunset times of the day. However, when the sun angle gets very low (less than 3 degrees), the light has to pass through more atmosphere and becomes too diffuse to form a coherent shadow. Shadow flicker will not occur when the sun is obscured by clouds or fog, at night, or when the source turbine(s) are not operating.

Shadow flicker intensity is defined as the difference in brightness at a given location in the presence and absence of a shadow. Shadow flicker intensity diminishes with greater receptor-to- turbine separation distance. Shadow flicker intensity for receptor-to-turbine distances beyond 1,500 meters is very low and generally considered imperceptible. Shadow flicker intensity for receptor-to-turbine distances between 1,000 and 2,000 meters (between 3,281 and 6,562 feet) is also low and generally considered barely noticeable. At this distance shadow flicker intensity would only tend to be noticed under conditions that would enhance the intensity difference, such as observing from a dark room with a single window directly facing the turbine casting the shadow. At distances less than 1,000 meters (3,281 feet), shadow flicker may be more noticeable. In general, the largest number of potential shadow hours, along with greatest potential shadow flicker intensity, occurs nearest the wind turbines.

Shadow flicker intensity is also affected by the relative percentage of the solar disk which is masked (covered) by the turbine rotor. WindPro calculations also implements German guidance which indicates that when less than 20% of the solar disk is masked, the shadow will be too diffuse to cause a significant impact.

Shadow flicker frequency is related to the wind turbine’s rotor blade speed and the number of blades on the rotor. From a health standpoint, such low frequencies are harmless. For comparison, strobe lights used in discotheques have frequencies which range from about 3 Hertz (Hz) to 10 Hz (1 Hz = 1 flash per second). As a result, public concerns that flickering light from wind turbines can have negative health effects, such as triggering seizures in people with epilepsy are unfounded. The Epilepsy Action (working name for the British Epilepsy Foundation), states that there is no evidence that wind turbines can cause seizures. However, they recommend that wind turbine flicker frequency be limited to 3 Hz (http://www.epilepsy.org.uk/info/photo_other.html). Since the proposed Project’s wind turbine blade pass frequency is approximately 0.79 Hz (less than 1 alternation per second), no negative health effects to individuals with photosensitive epilepsy are anticipated.

2 Hardin Wind Farm – Shadow Flicker Analysis

2.0 WINDPRO SHADOW FLICKER ANALYSIS

Tetra Tech estimated potential shadow flicker impacts from the Hardin Wind Farm using the WindPro software package and the following information provided by Hardin Wind Energy LLC (HWE):

• 118 turbines located at the coordinates listed in Attachment B and as shown on Figure 1.

• The wind turbines are assumed to have the dimensions of the GE Wind Energy GE 2.3- 116, a 3-blade 116-meter-diameter rotor wind turbine with a hub height of 80 meters. The GE 2.3-116 has a nominal rotor speed of 15.7 rpm which translates to a blade pass frequency of 0.79 Hz (less than 1 alternation per second).

• 532 receptors (residences) are located at the coordinates listed in Attachment A and as shown on Figure 1.

The analysis makes the following assumptions:

• The elevations of the wind turbines and receptors are determined using USGS digital elevation model (DEM) data.

• The position of the sun and the incident sunlight relative to the wind turbine and receptors on a minute by minute basis over the course of a year.

• Annual average sunshine rates for the area are based on an average of National Climatic Data Center (NCDC) data for stations located in Columbus and Toledo, Ohio and are assumed to be:

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 38% 45% 46% 51% 56% 58% 60% 58% 57% 53% 34% 29%

Values from Columbus and Toledo were used because NCDC sunshine data is not available for Kenton, Ohio1, but it is available for measurement stations in both Columbus and Toledo, Ohio. The sunshine probability data from these stations were averaged together to calculate sunshine probability data assumed to be representative of the of the project area. Tetra Tech considers this to be a conservative assumption that underestimates cloud cover since it evenly averages data from both sites, even though the project is slightly closer to Columbus and Columbus has a higher cloud cover rate.

• Wind turbine operating hours and orientations are based on approximately 1 year of data measured on-site from 5/21/08 to 6/22/09. Based on this data, wind turbine orientations are assumed to be as follows:

N NNE ENE E ESE SSE S SSW WSW W WNW NNW 4.1% 5.4% 7.7% 6.7% 4.9% 6.3% 8.7% 15.1% 13.1% 13.1% 9.1% 5.8%

1 Alan Black, NOAA Midwestern Regional Climate Center, data request response via email on 11/4/09.

3 Hardin Wind Farm – Shadow Flicker Analysis

• Receptor viewpoint (i.e., house windows) is assumed to always be directly facing turbine to sun line of sight (“greenhouse mode”).

• Every receptor is modelled as a 1 m2 area (approximate size of a typical window), 1 meter (3.28 feet) aboveground level. Approximate eye level is set at 1.5 meters (4.9 feet).

• Screening from trees, shrubs, barns, or other obstacles was conservatively not assumed to block shadows. In reality, such factors can block shadows from falling on to windows of receptors.

WindPro incorporates terrain elevation contour information and the analysis accounts for terrain elevation differences. WindPro calculates the sun’s path with respect to each turbine location to determine the shadow paths for every minute in a full year. Sun angles less than 3 degrees above the horizon were excluded, for the reasons identified in Section 1. WindPro calculates shadow flicker for conditions when at least 20% of the sun disc is covered by the turbine blades. When less than 20% of the solar disk is masked by the blades, the shadow will be too diffuse to cause a coherent shadow

HWE identified 532 receptors within 1,000 meters of a proposed wind turbine. Only these receptors were analyzed in the WindPro analysis. Figure 1 shows the locations of the modelled receptors and turbines.

4 Hardin Wind Farm – Shadow Flicker Analysis

3.0 WINDPRO SHADOW FLICKER ANALYSIS RESULTS

Expected annual average shadows are provided in Attachment A for all modelled receptors. Table 1 presents the expected annual average shadow hours for the receptors expected to receive over 30 hours of shadows per year. Figure 2 illustrates the WindPro predicted shadow flicker impacts for the Project. Table 2 summarizes the expected annual average shadow hours for all receptors modelled. Table 1. Receptors with Over 30 Expected Annual Average Shadow Hours Expected Annual Project Shadow Percent of Receptor ID Average Shadow Hours Participation Available Sunlight [Hours:Minutes/Year] Status Hours H-1179 66:46 Participant 1.49% H-2051 61:48 Participant 1.38% H-40 49:08 Participant 1.10% H-1305 48:23 Participant 1.08% H-808 46:58 Participant 1.05% H-2569 41:49 Non-Participant 0.94% H-738 41:44 Non-Participant 0.93% H-1805 41:26 Non-Participant 0.93% H-2672 41:12 Non-Participant 0.92% H-2106 40:36 Non-Participant 0.91% H-2513 40:11 Non-Participant 0.90% H-1780 40:09 Non-Participant 0.90% H-41 39:39 Participant 0.89% H-2102 38:47 Participant 0.87% H-733 38:04 Non-Participant 0.85% H-2073 37:25 Non-Participant 0.84% H-1959 37:08 Participant 0.83% H-1675 35:39 Non-Participant 0.80% H-2064 35:34 Participant 0.80% H-1677 35:25 Non-Participant 0.79% H-2553 35:24 Non-Participant 0.79% H-2512 34:52 Non-Participant 0.78% H-1744 34:28 Non-Participant 0.77% H-2006 34:11 Non-Participant 0.77% H-2571 34:06 Non-Participant 0.76% H-1991 33:58 Non-Participant 0.76% H-1924 33:01 Non-Participant 0.74% H-779 32:56 Non-Participant 0.74% H-2496 32:53 Non-Participant 0.74% H-2078 32:45 Non-Participant 0.73% H-798 32:19 Non-Participant 0.72% H-2515 32:02 Non-Participant 0.72% H-689 31:44 Non-Participant 0.71% H-1187 31:29 Non-Participant 0.70% H-2302 31:29 Non-Participant 0.70% H-653 31:12 Non-Participant 0.70% H-1185 30:56 Non-Participant 0.69% H-2465 30:03 Non-Participant 0.67%

5 Hardin Wind Farm – Shadow Flicker Analysis

Table 2. Statistical Summary of Expected Annual Average Shadow Hours Number of Number of Number of Annual Average Non-Participating Participating Total Shadow Hours Receptors Receptors Receptors = 0 Hours 20 1 21 > 0 and < 10 Hours 189 11 200 ≥ 10 and < 20 Hours 186 7 193 ≥ 20 and < 30 Hours 75 5 80 > 30 hours 29 9 38 Total 499 33 532

6 Hardin Wind Farm – Shadow Flicker Analysis

4.0 CONCLUSION

This report represents an update to the shadow flicker analysis conducted and submitted in support of the Hardin Wind Energy Amendment 1 application to the Ohio Power Siting Board in June 2011. This analysis was completed utilizing the same modeling assumptions that were utilized in the June 2011 shadow flicker analysis, with the exception of the GE 2.3-116 turbine model characteristics. Shadow flicker impacts within the area of study are expected to be minor. The analysis assumes that the houses all have a direct in line view of the incoming shadow flicker sunlight and does not account for all the trees or other obstructions which may block sunlight. In reality, the windows of many houses will not face the sun directly for the key shadow flicker impact times. For these reasons, shadow flicker impacts are expected to be less than estimated with this conservative analysis, and shadow flicker is not expected to be a significant environmental impact.

7 UV69 H-2109 H-2092 H-2086 ") ") ") H-45 HARDIN WIND ENERGY, LLC H-30 ") ") HARDIN WIND FARM !. UV235 H-2102 HARDIN COUNTY ") OHIO ")") H-13 H-2604 ")")") ")")")")")")")") H-2639 ") !. H-44 ") ")")") ") ") ")") ") H-6 H-1506 H-1504 ") H-1850 ")") ")")")")") ") H-16 ")") ") ")")")")")") ")") H-1899 ") ") ") H-2106 !. ")")")")")")")")")")")")")")")")")") ") ")") H-1511 H-1505 H-1516 H-31 H-1738 ")") ") H-1512 ") H-4 ") ") ") ") H-2117 ") ") ") ") ") ") ") FIGURE 1 ") H-1820 ") ") H-1736 ") H-1513 H-1514 ") H-2111 ") H-653 !. !. H-36 H-35 ") !. H-41 !. H-345 H-1517 ") ") SENSITIVE RECEPTORS MODELED !. ") !. ") !. ") H-2069 H-2078 !. ") H-2230 !. H-34 ") H-1744 !. !. ") H-2080 ") ") H-713 !. !. H-2073 WITH WINDPRO TO PREDICT !. H-2520 ") ") H-40 ") ")")") ") H-2572 H-2091 ") H-2077 ") H-167!.7 !. ")")")")")")") ") ")") !. ") ") ")") ")")")")")")") H-2513!. H-12 H-673 ")")") ")")")")")")")")")") ")")") !. !. !. H-2728 H-2070 EXPECTED SHADOW ") H-1654 !. ") ")")")")")")")")")")")")")")")")")")")")")") H-1653 ") ")")")")")")")")")")")")")")")")")")")")")")")") !. ") ") ")") ")")")")")")")")")") !. H-1 H-2081 ") ") ")")")")")") H-2624 H-2067 H-1676 H-1656 !. !. H-783 H-2547 ")")")")")")")")")") !. H-2104 ") ") ")")")")")")")")") !. !. H-37 FLICKER IMPACTS H-2389 ") H-2521 ")")")")")")")") H-2634 ") ") ") ") !. H-2103 30 ") H-2083 H-2606 ") ")")") ") ") ") H-2588 H-1063 9 H-1780 !. ") ") ") !. !. H-2667 H-2671 !. !. ") H-1061 !. H-1305 !. !. UV309 H-1184 !. ") !. MARCH 2016 ") !. !. !. ") H-1183 !. !. !. H-1727 H-353 !. !. !. !. !. ") !. !. H-1202 ") H-1195 !. ")") ") H-1187 !. Turbine Location ") !. !. !. ") ") H-1777 !. ")")")")")") H-1107 ") H-2985 ")")")")") H-1203 H-1104 !. ")") ") ") H-1112!. ") H-1809 H-1751 H-2286 H-1185!. H-1179 ") ")") H-1586 ")")") Receptor (Participating) H-1817 ") !. H-1324 ") ") ") ") H-1682 ")")")") ") !. !. H-2497 H-2551 ")")") ")") ") ") ") H-1909 ") H-501 !. H-1587 H-1725 ")")") H-1188 H-1808 ") H-1664 ")") ") ") H-1602 ") H-1208 H-1723 ") ") ") ") ")")")") ") ") H-1663 ")") ") Receptor (Non-Participating) !. !. !. H-2154 H-329 H-1209 H-2229 ") !. !. H-1977 H-766 H-1638 !. ") ") H-1882 ") !. Interstate Highway H-682 ") !. ") !. !. !. !. !. Major Road ") H-1662 !. !. !. H-455 !. ") H-1765 H-1724 !. 69 H-1192 ") ") 195 UV ") ") UV H-1792 H-2302 ") !. H-2008 ") H-1791 ") H-1790 !. ") !. !. ") H-1805 H-1797 ") ") !. H-1806 !. !. !. !. !. !. !. !.

H-20!.64 !. ") H-48 H-74 !. ")") H-1520 ") H-1069 !. H-2051 H-2056 H-1988 ") H-47 !. ") ") ") !. !.

!. H-2057 !. ") !. H-1959 ") H-2050 ¯ !. ") 0 0.5 1 1.5 2 MILES !. !. H-808 H-2672 ") ") H-1960 !. !. ") H-1533 H-2031 H-1961 ") ") H-449 H-1530 ") ")")") ") ") MICHIGARNEFERENCE MAP ") H-2049 H-2004 H-1822 ") ") H-434 H-1322 ") ")

H-2052 UV117 !. ") H-1320 !. ")") H-2024 235 UV H-2006 ") H-2053 ") !. ") H-1991 OHIO

H-2039 ")") H-2037 H-1993 ") ")") ") ") H-2032 ") H-2033 H-2000 ") ") H-1318 H-388 ") H-1835 ")") H-1836 UV67 !. WEST UV117

Document Path: P:\GIS\Invenergy_HardinWindFarm\GIS\Spatial\MXD\ShadowFlicker\20160315\Fig1_Receptors.mxd UV69

") ") ") HARDIN WIND ENERGY, LLC ") ") HARDIN WIND FARM !. HARDIN COUNTY ") UV235 OHIO ")") ")")")") ") !. ")")")")")")")") ")")")")") ") ") ")")")")") ")")") ")")")")")") ")") ") ") ") !. ")")")")")")")")")")")")")")")")")")")") ") ")") ") ")") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") ") FIGURE 2 ") !. ") ") !. ") !. !. ") ") ") MAP OF WINDPRO ESTIMATED !. ") !. ") !. !. ") !. 30 ") !. !. 9 ") !. ") SHADOW FLICKER IMPACTS FOR ") !. ") ") !. ") ") ") ") ") ")")")")") ")") !. !. !. ")")")")")")")")")")") ") !. ") ")")")") ")") ")") ")")") !. THE HARDIN WIND FARM ") !. ") ")")")")")")")")")")")")")")")")")")")")")")") !. !. UV309 ") ")")")")")")")")")")")")")")")")")")")")")")")") !. ") ") ")") ")")")")")")")")")") !. ") !. !. ") ")")")")")") ")")")")")")")")")") !. !. !. ") (EXPECTED HOURS PER YEAR) ") ")")")")")")")") ") ") ") ")")") ")") ") ")")") ") ") ") !. !. !. !. ") ") ") !. !. ") !. !. !. !. ") !. MARCH 2016 ") !. !. !. ") !. !. !. !. !. !. !. !. !. !. ") ") ") ") !. !. !. ") ") Turbine Location ") !. !. ")")") ") !. ")")")")")") ") ")")") ") !. !. ") ") ") ") !. !. ")") ")")") Receptor (Participating) ")")") ") ")")")") ") !. !. ") ") ")") ") ") ") ") !. ")")") ") ") ")") ") ") ") ") ") ") ")")")") ")") ") Receptor (Non-Participating) !. !. !. ")") ") !. !. !. !. ") !. ") ") Interstate Highway ") !. !. ") !. !. ") !. Major Road !. !. UV69 Shadow Flicker Iso Line (Expected Hours per Year) !. ") !. !. 15 ") ") 195 ") ") UV ") !. 30 ") !. ") ") !. !. 50 ") ") ") !. !. !. 100 !. !. 200 !. !. !. !. !. !. ") !. ")") ") !. ") !. ") ") ") !. !. !. !. ") !. ") ¯ !. ") 0 0.5 1 1.5 2 MILES !. !. ") ") !. !. ") ") ") ") ") ") ") ") REFERENCE MAP ") MICHIGAN ") ") ") ")

UV117 !. ")

!. ")") 235 UV ") ") !. ") OHIO

")") ") ")") ") ") ") ") ") UV67 ") ")") !. WEST VIRGINIA UV117 KENTUCKY

Document Path: P:\GIS\Invenergy_HardinWindFarm\GIS\Spatial\MXD\ShadowFlicker\20160315\Fig2_Isolines.mxd Hardin Wind Farm – Shadow Flicker Analysis

ATTACHMENT A

Detailed Summary of WindPro Shadow Flicker Analysis Results

A-1 Hardin Wind Farm – Shadow Flicker Analysis

Hardin Wind Farm WindPro Predicted Annual Expected Shadow Flicker

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1 272,136 4,508,078 1:15:00 Non-Participant H-4 268,566 4,509,562 3:06:00 Participant H-6 267,764 4,509,731 0:46:00 Non-Participant H-12 272,588 4,508,485 5:34:00 Non-Participant H-13 268,592 4,509,997 0:00:00 Non-Participant H-15 269,112 4,509,495 6:39:00 Non-Participant H-16 269,319 4,509,660 4:57:00 Participant H-30 271,053 4,510,774 19:03:00 Participant H-31 270,617 4,509,458 12:26:00 Non-Participant H-34 270,530 4,508,792 13:43:00 Participant H-35 270,148 4,509,058 10:39:00 Non-Participant H-36 269,919 4,509,096 11:03:00 Non-Participant H-37 272,461 4,507,933 0:00:00 Non-Participant H-40 272,509 4,508,647 49:08:00 Participant H-41 272,537 4,509,052 39:39:00 Participant H-44 272,567 4,509,787 4:31:00 Non-Participant H-45 272,035 4,510,845 9:35:00 Non-Participant H-47 262,473 4,501,925 24:15:00 Non-Participant H-48 262,589 4,502,300 7:56:00 Non-Participant H-74 262,684 4,502,339 10:05:00 Non-Participant H-247 268,252 4,506,640 22:01:00 Non-Participant H-248 268,330 4,506,532 18:14:00 Non-Participant H-251 268,346 4,506,472 18:01:00 Non-Participant H-252 268,351 4,506,435 18:12:00 Non-Participant H-253 268,360 4,506,266 21:23:00 Non-Participant H-259 268,322 4,506,683 17:35:00 Non-Participant H-260 268,361 4,506,761 15:25:00 Non-Participant H-265 268,407 4,506,723 13:50:00 Non-Participant H-266 268,402 4,506,745 13:49:00 Non-Participant H-273 269,259 4,506,365 24:21:00 Non-Participant H-329 269,409 4,506,166 0:00:00 Non-Participant H-345 264,640 4,509,113 9:18:00 Non-Participant H-346 264,065 4,508,506 6:29:00 Non-Participant H-347 263,912 4,508,579 7:15:00 Non-Participant H-353 269,231 4,506,996 29:30:00 Non-Participant H-354 268,538 4,506,848 9:52:00 Non-Participant H-357 263,948 4,508,535 7:12:00 Non-Participant H-388 264,557 4,496,908 3:48:00 Non-Participant

B-2 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-422 259,935 4,510,282 2:00:00 Non-Participant H-434 266,787 4,499,261 5:20:00 Participant H-448 263,529 4,499,861 18:44:00 Non-Participant H-449 263,732 4,499,778 12:35:00 Non-Participant H-455 265,901 4,505,040 1:25:00 Non-Participant H-467 266,249 4,497,358 0:00:00 Non-Participant H-501 265,734 4,506,288 25:26:00 Non-Participant H-644 259,738 4,509,983 6:54:00 Non-Participant H-653 259,859 4,509,416 31:12:00 Non-Participant H-655 259,886 4,510,088 2:37:00 Non-Participant H-656 259,912 4,509,867 11:31:00 Non-Participant H-662 259,549 4,509,729 6:46:00 Non-Participant H-666 259,801 4,510,028 5:47:00 Non-Participant H-673 263,888 4,508,531 8:18:00 Non-Participant H-674 259,181 4,506,584 8:46:00 Non-Participant H-680 263,957 4,508,470 8:34:00 Non-Participant H-682 258,811 4,505,776 6:55:00 Non-Participant H-689 264,680 4,508,377 31:44:00 Non-Participant H-695 264,270 4,508,627 5:21:00 Non-Participant H-696 264,333 4,508,586 6:45:00 Non-Participant H-697 264,339 4,508,634 6:12:00 Non-Participant H-701 259,519 4,509,772 5:04:00 Non-Participant H-705 259,921 4,509,950 7:44:00 Non-Participant H-706 259,922 4,510,052 2:55:00 Non-Participant H-713 264,285 4,508,716 4:40:00 Non-Participant H-714 264,719 4,508,319 19:36:00 Non-Participant H-715 264,963 4,508,421 17:41:00 Non-Participant H-716 259,922 4,510,153 1:57:00 Non-Participant H-717 259,924 4,510,173 1:32:00 Non-Participant H-718 264,398 4,508,473 9:20:00 Non-Participant H-720 259,935 4,510,231 1:47:00 Non-Participant H-724 264,240 4,508,446 6:31:00 Non-Participant H-725 264,208 4,508,590 5:17:00 Non-Participant H-726 264,274 4,508,516 6:19:00 Non-Participant H-727 259,690 4,510,033 5:54:00 Non-Participant H-731 264,988 4,508,078 15:48:00 Non-Participant H-732 264,988 4,508,102 15:13:00 Non-Participant H-733 264,830 4,508,432 38:04:00 Non-Participant H-734 264,637 4,508,470 21:02:00 Non-Participant H-738 264,802 4,508,446 41:44:00 Non-Participant H-739 264,728 4,508,512 25:46:00 Non-Participant

B-3 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-740 264,275 4,508,476 6:41:00 Non-Participant H-741 264,204 4,508,536 5:40:00 Non-Participant H-742 260,222 4,509,789 14:51:00 Non-Participant H-744 259,633 4,509,773 4:21:00 Non-Participant H-747 264,563 4,508,424 17:15:00 Non-Participant H-748 260,124 4,509,787 17:39:00 Non-Participant H-749 260,107 4,509,803 16:08:00 Non-Participant H-750 264,961 4,508,269 28:31:00 Non-Participant H-752 264,725 4,508,487 29:12:00 Non-Participant H-753 264,209 4,508,561 5:30:00 Non-Participant H-754 264,452 4,508,592 9:07:00 Non-Participant H-755 264,194 4,508,479 6:00:00 Non-Participant H-756 259,665 4,509,778 4:47:00 Non-Participant H-757 259,681 4,509,773 5:00:00 Non-Participant H-758 259,808 4,509,757 7:54:00 Non-Participant H-759 259,837 4,509,765 8:37:00 Non-Participant H-766 267,924 4,505,856 0:31:00 Non-Participant H-767 264,879 4,508,154 18:52:00 Non-Participant H-772 264,891 4,508,328 19:34:00 Non-Participant H-773 264,860 4,508,328 18:20:00 Non-Participant H-776 264,851 4,508,119 16:42:00 Non-Participant H-777 264,847 4,508,085 14:40:00 Non-Participant H-778 264,769 4,508,130 20:01:00 Non-Participant H-779 265,046 4,508,344 32:56:00 Non-Participant H-780 264,359 4,508,462 8:30:00 Non-Participant H-782 259,872 4,509,841 9:47:00 Non-Participant H-783 264,106 4,508,389 6:06:00 Non-Participant H-784 264,246 4,508,402 6:47:00 Non-Participant H-785 264,182 4,508,404 6:19:00 Non-Participant H-786 264,319 4,508,436 7:53:00 Non-Participant H-788 260,002 4,510,103 2:22:00 Non-Participant H-797 264,777 4,508,332 16:21:00 Non-Participant H-798 264,748 4,508,388 32:19:00 Non-Participant H-799 264,745 4,508,360 26:11:00 Non-Participant H-800 264,744 4,508,129 20:02:00 Non-Participant H-801 264,166 4,508,571 5:16:00 Non-Participant H-802 264,166 4,508,590 5:05:00 Non-Participant H-803 264,163 4,508,625 4:52:00 Non-Participant H-804 264,169 4,508,672 4:36:00 Non-Participant H-808 263,497 4,500,338 46:58:00 Participant H-1061 270,899 4,507,616 0:00:00 Non-Participant

B-4 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1063 270,837 4,507,754 0:00:00 Non-Participant H-1069 262,680 4,502,294 11:20:00 Non-Participant H-1104 269,157 4,506,548 12:36:00 Non-Participant H-1105 269,312 4,506,499 28:29:00 Non-Participant H-1107 269,334 4,506,774 25:51:00 Non-Participant H-1108 269,325 4,506,811 29:37:00 Non-Participant H-1112 269,306 4,506,573 20:33:00 Non-Participant H-1133 268,372 4,506,685 15:22:00 Non-Participant H-1134 268,305 4,506,618 18:53:00 Non-Participant H-1135 268,340 4,506,693 16:37:00 Non-Participant H-1137 268,301 4,506,759 18:46:00 Non-Participant H-1138 268,360 4,506,749 15:28:00 Non-Participant H-1145 269,377 4,506,213 0:28:00 Non-Participant H-1147 268,380 4,506,708 14:53:00 Non-Participant H-1160 269,319 4,506,345 12:07:00 Non-Participant H-1179 267,997 4,506,542 66:46:00 Participant H-1181 268,737 4,506,203 11:04:00 Non-Participant H-1183 259,907 4,507,363 11:38:00 Non-Participant H-1184 259,857 4,507,458 14:28:00 Non-Participant H-1185 260,638 4,506,536 30:56:00 Non-Participant H-1186 260,191 4,506,543 15:10:00 Non-Participant H-1187 269,340 4,506,891 31:29:00 Non-Participant H-1188 269,970 4,506,181 0:00:00 Non-Participant H-1192 259,764 4,504,816 20:16:00 Non-Participant H-1195 259,652 4,506,953 5:40:00 Non-Participant H-1201 268,461 4,506,891 13:06:00 Non-Participant H-1202 268,533 4,506,871 10:08:00 Non-Participant H-1203 268,456 4,506,738 12:19:00 Non-Participant H-1208 259,409 4,506,491 15:17:00 Non-Participant H-1209 258,656 4,506,080 6:44:00 Non-Participant H-1291 264,333 4,508,512 7:35:00 Non-Participant H-1303 264,255 4,508,439 6:42:00 Non-Participant H-1304 264,618 4,508,109 18:25:00 Non-Participant H-1305 264,647 4,507,480 48:23:00 Participant H-1307 264,998 4,508,351 27:37:00 Non-Participant H-1314 264,688 4,508,074 19:12:00 Non-Participant H-1318 265,557 4,496,997 0:00:00 Non-Participant H-1320 266,353 4,498,527 27:57:00 Participant H-1322 266,583 4,499,167 7:43:00 Participant H-1324 265,456 4,506,386 27:00:00 Non-Participant H-1504 268,884 4,509,727 0:58:00 Non-Participant

B-5 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1505 267,992 4,509,552 1:33:00 Participant H-1506 268,657 4,509,701 1:32:00 Non-Participant H-1507 268,990 4,509,542 9:13:00 Non-Participant H-1511 267,636 4,509,515 5:46:00 Participant H-1512 267,111 4,509,496 2:30:00 Non-Participant H-1513 268,838 4,509,449 13:18:00 Non-Participant H-1514 268,977 4,509,442 9:40:00 Non-Participant H-1516 269,638 4,509,481 3:52:00 Non-Participant H-1517 269,481 4,509,314 13:19:00 Participant H-1518 269,483 4,509,425 5:57:00 Non-Participant H-1520 262,530 4,502,115 11:30:00 Non-Participant H-1530 261,273 4,499,918 5:02:00 Non-Participant H-1533 261,289 4,499,980 7:58:00 Non-Participant H-1564 263,482 4,499,828 10:05:00 Non-Participant H-1574 269,280 4,506,491 24:18:00 Non-Participant H-1581 268,329 4,506,563 17:51:00 Non-Participant H-1586 268,353 4,506,495 17:24:00 Non-Participant H-1587 268,358 4,506,290 21:34:00 Non-Participant H-1591 268,290 4,506,711 19:05:00 Non-Participant H-1592 268,268 4,506,768 21:45:00 Non-Participant H-1602 269,381 4,506,328 0:27:00 Non-Participant H-1617 269,367 4,506,357 8:08:00 Non-Participant H-1618 269,294 4,506,381 26:31:00 Non-Participant H-1619 269,263 4,506,329 14:00:00 Non-Participant H-1638 270,134 4,505,832 0:00:00 Non-Participant H-1652 259,868 4,509,625 10:24:00 Non-Participant H-1653 259,811 4,508,489 10:33:00 Non-Participant H-1654 259,812 4,508,543 27:15:00 Non-Participant H-1656 259,828 4,508,334 19:38:00 Participant H-1662 258,786 4,505,589 5:48:00 Non-Participant H-1663 258,639 4,506,484 4:46:00 Non-Participant H-1664 260,633 4,506,403 27:27:00 Non-Participant H-1665 268,550 4,506,216 13:11:00 Non-Participant H-1675 259,770 4,508,215 35:39:00 Non-Participant H-1676 259,821 4,508,368 14:46:00 Non-Participant H-1677 259,838 4,508,757 35:25:00 Non-Participant H-1682 260,136 4,506,546 15:04:00 Non-Participant H-1683 260,223 4,506,538 15:43:00 Non-Participant H-1684 259,917 4,509,887 11:09:00 Non-Participant H-1685 259,908 4,509,796 11:04:00 Non-Participant H-1686 259,928 4,509,796 11:48:00 Non-Participant

B-6 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1687 260,082 4,509,892 7:38:00 Non-Participant H-1688 260,081 4,509,879 8:52:00 Non-Participant H-1689 260,080 4,509,867 10:02:00 Non-Participant H-1690 260,079 4,509,856 11:13:00 Non-Participant H-1691 260,079 4,509,844 12:27:00 Non-Participant H-1692 260,081 4,509,832 13:32:00 Non-Participant H-1693 260,036 4,509,791 17:13:00 Non-Participant H-1694 260,037 4,509,803 16:36:00 Non-Participant H-1695 260,040 4,509,814 15:50:00 Non-Participant H-1696 260,038 4,509,826 14:59:00 Non-Participant H-1697 260,039 4,509,838 13:56:00 Non-Participant H-1698 260,039 4,509,850 12:49:00 Non-Participant H-1699 260,040 4,509,860 11:52:00 Non-Participant H-1700 260,040 4,509,872 10:48:00 Non-Participant H-1701 260,042 4,509,884 9:36:00 Non-Participant H-1702 260,044 4,509,896 8:28:00 Non-Participant H-1703 259,999 4,509,898 9:36:00 Non-Participant H-1704 260,000 4,509,886 10:37:00 Non-Participant H-1705 259,999 4,509,875 11:29:00 Non-Participant H-1706 259,997 4,509,864 12:26:00 Non-Participant H-1707 259,999 4,509,852 13:16:00 Non-Participant H-1708 259,998 4,509,841 13:59:00 Non-Participant H-1709 259,998 4,509,829 14:36:00 Non-Participant H-1710 259,999 4,509,816 15:07:00 Non-Participant H-1711 259,998 4,509,806 15:25:00 Non-Participant H-1712 259,958 4,509,794 13:19:00 Non-Participant H-1713 259,959 4,509,806 13:37:00 Non-Participant H-1714 259,961 4,509,817 13:49:00 Non-Participant H-1715 259,961 4,509,829 13:39:00 Non-Participant H-1716 259,961 4,509,841 13:21:00 Non-Participant H-1717 259,961 4,509,852 12:59:00 Non-Participant H-1718 259,961 4,509,863 12:31:00 Non-Participant H-1719 259,962 4,509,874 12:01:00 Non-Participant H-1720 259,963 4,509,898 10:29:00 Non-Participant H-1722 259,877 4,510,107 2:30:00 Non-Participant H-1723 260,156 4,506,499 14:21:00 Non-Participant H-1724 261,265 4,504,864 7:21:00 Non-Participant H-1725 268,850 4,506,225 14:01:00 Non-Participant H-1726 269,320 4,506,263 0:33:00 Non-Participant H-1727 268,136 4,507,050 28:59:00 Participant H-1731 259,842 4,510,091 2:17:00 Non-Participant

B-7 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1733 259,865 4,509,587 11:39:00 Non-Participant H-1734 259,866 4,509,672 9:59:00 Non-Participant H-1735 259,871 4,509,717 9:53:00 Non-Participant H-1736 259,380 4,509,500 6:18:00 Participant H-1738 259,469 4,509,716 7:24:00 Non-Participant H-1744 259,841 4,508,905 34:28:00 Non-Participant H-1751 259,320 4,506,583 11:09:00 Participant H-1752 259,841 4,510,108 2:19:00 Non-Participant H-1758 259,790 4,510,109 1:52:00 Non-Participant H-1759 258,834 4,506,519 9:05:00 Participant H-1765 260,687 4,504,842 20:55:00 Non-Participant H-1771 268,641 4,506,141 13:44:00 Non-Participant H-1774 260,441 4,509,815 8:44:00 Non-Participant H-1775 260,574 4,509,788 13:38:00 Non-Participant H-1777 259,771 4,506,800 10:19:00 Non-Participant H-1780 259,740 4,508,112 40:09:00 Non-Participant H-1784 264,062 4,508,407 5:56:00 Non-Participant H-1785 263,995 4,508,523 6:48:00 Non-Participant H-1786 263,991 4,508,441 8:18:00 Non-Participant H-1790 259,080 4,504,340 27:39:00 Non-Participant H-1791 258,957 4,504,457 13:01:00 Non-Participant H-1792 259,017 4,504,627 14:15:00 Non-Participant H-1797 258,861 4,504,032 12:11:00 Non-Participant H-1801 268,801 4,506,208 12:17:00 Non-Participant H-1802 268,661 4,506,218 10:47:00 Non-Participant H-1805 259,111 4,504,205 41:26:00 Non-Participant H-1806 259,135 4,504,116 6:08:00 Non-Participant H-1808 259,565 4,506,564 9:11:00 Non-Participant H-1809 259,268 4,506,589 8:44:00 Participant H-1817 258,575 4,506,501 3:55:00 Non-Participant H-1820 259,862 4,509,558 15:07:00 Non-Participant H-1821 263,419 4,499,861 11:18:00 Non-Participant H-1822 263,542 4,499,707 2:13:00 Non-Participant H-1835 264,527 4,496,886 3:37:00 Non-Participant H-1836 264,562 4,496,870 4:00:00 Non-Participant H-1847 259,735 4,509,853 5:26:00 Non-Participant H-1848 259,734 4,509,871 5:26:00 Non-Participant H-1849 259,640 4,509,816 4:19:00 Non-Participant H-1850 259,545 4,509,815 3:23:00 Non-Participant H-1852 264,152 4,508,493 5:46:00 Non-Participant H-1855 259,528 4,509,783 4:19:00 Non-Participant

B-8 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1856 259,925 4,510,091 2:46:00 Non-Participant H-1857 259,919 4,510,108 2:39:00 Non-Participant H-1865 259,949 4,510,150 1:45:00 Non-Participant H-1866 259,922 4,510,191 1:27:00 Non-Participant H-1867 264,446 4,508,506 10:13:00 Non-Participant H-1868 264,411 4,508,430 10:06:00 Non-Participant H-1872 259,923 4,510,254 1:52:00 Non-Participant H-1881 264,255 4,508,478 6:26:00 Non-Participant H-1882 260,593 4,505,816 16:13:00 Non-Participant H-1891 259,626 4,509,853 4:00:00 Non-Participant H-1896 264,474 4,508,462 11:44:00 Non-Participant H-1897 264,441 4,508,467 10:32:00 Non-Participant H-1898 264,634 4,508,424 27:45:00 Non-Participant H-1899 260,603 4,509,787 15:19:00 Non-Participant H-1900 260,287 4,509,785 12:09:00 Non-Participant H-1902 259,867 4,509,748 9:37:00 Non-Participant H-1904 264,562 4,508,471 15:16:00 Non-Participant H-1905 264,227 4,508,513 6:02:00 Non-Participant H-1906 259,673 4,509,888 4:26:00 Non-Participant H-1907 259,576 4,509,771 3:56:00 Non-Participant H-1909 264,614 4,506,311 20:35:00 Participant H-1917 264,528 4,508,424 14:48:00 Non-Participant H-1918 264,501 4,508,425 13:45:00 Non-Participant H-1919 260,169 4,509,789 16:31:00 Non-Participant H-1920 260,501 4,509,813 9:19:00 Non-Participant H-1921 260,402 4,509,793 10:13:00 Non-Participant H-1922 259,890 4,510,251 1:29:00 Non-Participant H-1924 264,673 4,508,418 33:01:00 Non-Participant H-1925 264,680 4,508,455 29:15:00 Non-Participant H-1926 264,673 4,508,478 23:47:00 Non-Participant H-1927 264,678 4,508,499 22:00:00 Non-Participant H-1928 264,681 4,508,535 19:13:00 Non-Participant H-1929 264,501 4,508,438 13:19:00 Non-Participant H-1930 264,527 4,508,440 14:11:00 Non-Participant H-1931 264,498 4,508,470 12:34:00 Non-Participant H-1932 264,527 4,508,472 13:25:00 Non-Participant H-1933 264,530 4,508,503 12:56:00 Non-Participant H-1934 264,454 4,508,536 10:12:00 Non-Participant H-1939 259,698 4,509,775 5:15:00 Non-Participant H-1940 259,745 4,509,768 6:30:00 Non-Participant H-1941 259,764 4,509,769 6:52:00 Non-Participant

B-9 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-1942 259,875 4,509,771 9:53:00 Non-Participant H-1955 264,474 4,508,506 11:14:00 Non-Participant H-1956 264,477 4,508,428 12:29:00 Non-Participant H-1957 264,440 4,508,428 11:05:00 Non-Participant H-1958 264,367 4,508,430 8:58:00 Non-Participant H-1959 263,421 4,500,995 37:08:00 Participant H-1960 263,500 4,500,258 29:31:00 Non-Participant H-1961 263,511 4,500,084 13:45:00 Non-Participant H-1970 259,875 4,509,817 9:52:00 Non-Participant H-1971 259,873 4,509,801 9:51:00 Non-Participant H-1972 259,817 4,509,803 8:00:00 Non-Participant H-1973 264,188 4,508,438 6:11:00 Non-Participant H-1974 264,227 4,508,480 6:13:00 Non-Participant H-1975 264,334 4,508,474 7:51:00 Non-Participant H-1977 265,824 4,505,862 22:14:00 Non-Participant H-1978 259,733 4,509,811 5:33:00 Non-Participant H-1979 259,973 4,510,102 2:37:00 Non-Participant H-1984 264,147 4,508,440 6:00:00 Non-Participant H-1988 265,222 4,501,829 5:41:00 Non-Participant H-1991 266,508 4,497,962 33:58:00 Non-Participant H-1993 266,057 4,497,360 0:00:00 Participant H-1999 265,770 4,497,284 0:00:00 Non-Participant H-2000 265,145 4,497,128 0:00:00 Non-Participant H-2004 266,380 4,499,510 0:00:00 Non-Participant H-2006 266,386 4,498,290 34:11:00 Non-Participant H-2008 264,636 4,504,407 11:51:00 Non-Participant H-2024 266,456 4,498,573 24:11:00 Participant H-2031 263,258 4,499,914 6:35:00 Participant H-2032 265,339 4,497,177 0:00:00 Non-Participant H-2033 266,383 4,497,439 0:00:00 Non-Participant H-2034 266,574 4,497,478 1:34:00 Non-Participant H-2035 266,575 4,497,489 1:19:00 Non-Participant H-2036 266,571 4,497,500 0:56:00 Non-Participant H-2037 266,572 4,497,512 0:33:00 Non-Participant H-2038 266,572 4,497,524 0:09:00 Non-Participant H-2039 266,539 4,497,520 0:00:00 Non-Participant H-2040 266,540 4,497,506 0:08:00 Non-Participant H-2041 266,540 4,497,495 0:32:00 Non-Participant H-2042 266,540 4,497,484 0:54:00 Non-Participant H-2043 266,543 4,497,470 1:27:00 Non-Participant H-2049 265,206 4,499,524 2:08:00 Non-Participant

B-10 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-2050 264,032 4,500,846 12:29:00 Non-Participant H-2051 264,288 4,501,901 61:48:00 Participant H-2052 266,580 4,498,843 16:09:00 Participant H-2053 266,559 4,498,205 16:50:00 Non-Participant H-2056 264,964 4,501,872 14:49:00 Non-Participant H-2057 264,141 4,501,201 18:58:00 Non-Participant H-2064 264,571 4,502,499 35:34:00 Participant H-2067 272,023 4,508,265 1:40:00 Non-Participant H-2069 270,971 4,508,960 15:14:00 Non-Participant H-2070 272,494 4,508,253 0:00:00 Non-Participant H-2073 272,603 4,508,748 37:25:00 Non-Participant H-2077 271,035 4,508,609 28:55:00 Non-Participant H-2078 272,577 4,508,873 32:45:00 Non-Participant H-2080 270,986 4,508,693 25:07:00 Non-Participant H-2081 272,549 4,508,246 0:00:00 Non-Participant H-2083 272,536 4,507,882 0:00:00 Non-Participant H-2086 271,813 4,510,998 0:00:00 Non-Participant H-2091 270,822 4,508,648 26:11:00 Non-Participant H-2092 271,487 4,511,014 0:00:00 Non-Participant H-2102 270,963 4,510,327 38:47:00 Participant H-2103 270,222 4,507,803 0:37:00 Participant H-2104 269,249 4,508,025 13:11:00 Non-Participant H-2106 270,936 4,509,539 40:36:00 Non-Participant H-2109 270,663 4,511,005 4:05:00 Non-Participant H-2111 270,970 4,509,188 24:12:00 Non-Participant H-2117 272,538 4,509,507 9:39:00 Non-Participant H-2147 269,232 4,506,511 17:25:00 Non-Participant H-2154 268,400 4,506,222 19:40:00 Non-Participant H-2155 268,352 4,506,721 15:50:00 Non-Participant H-2229 268,723 4,506,122 14:53:00 Participant H-2230 264,749 4,508,979 14:04:00 Non-Participant H-2286 260,264 4,506,567 15:59:00 Non-Participant H-2295 259,887 4,510,189 1:32:00 Non-Participant H-2296 259,887 4,510,170 1:57:00 Non-Participant H-2298 259,883 4,510,059 2:36:00 Non-Participant H-2299 259,887 4,510,024 3:49:00 Non-Participant H-2300 259,879 4,509,994 5:58:00 Non-Participant H-2302 260,959 4,504,874 31:29:00 Non-Participant H-2310 259,882 4,509,973 7:06:00 Non-Participant H-2389 263,939 4,508,069 7:18:00 Non-Participant H-2465 264,674 4,508,363 30:03:00 Non-Participant

B-11 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-2466 264,723 4,507,958 15:04:00 Non-Participant H-2467 264,707 4,507,962 15:17:00 Non-Participant H-2468 264,671 4,507,974 16:11:00 Non-Participant H-2469 264,294 4,508,622 5:34:00 Non-Participant H-2471 264,310 4,508,633 5:34:00 Non-Participant H-2472 264,207 4,508,648 4:50:00 Non-Participant H-2484 259,922 4,509,987 5:10:00 Non-Participant H-2485 259,919 4,510,029 2:53:00 Non-Participant H-2496 264,720 4,508,385 32:53:00 Non-Participant H-2497 267,052 4,506,298 26:18:00 Non-Participant H-2498 264,666 4,508,201 15:59:00 Non-Participant H-2499 264,574 4,508,590 11:11:00 Non-Participant H-2500 264,563 4,508,594 10:43:00 Non-Participant H-2501 264,525 4,508,613 9:42:00 Non-Participant H-2502 264,358 4,508,690 5:43:00 Non-Participant H-2503 264,613 4,508,568 13:49:00 Non-Participant H-2511 264,910 4,508,431 27:47:00 Non-Participant H-2512 264,908 4,508,444 34:52:00 Non-Participant H-2513 264,880 4,508,449 40:11:00 Non-Participant H-2514 264,862 4,508,410 26:36:00 Non-Participant H-2515 264,827 4,508,412 32:02:00 Non-Participant H-2518 264,205 4,508,616 5:05:00 Non-Participant H-2519 264,697 4,508,672 12:58:00 Non-Participant H-2520 264,204 4,508,668 4:41:00 Non-Participant H-2521 264,612 4,508,135 17:49:00 Non-Participant H-2522 264,288 4,508,512 6:32:00 Non-Participant H-2547 264,667 4,508,285 18:06:00 Non-Participant H-2548 264,665 4,508,261 15:59:00 Non-Participant H-2549 264,777 4,508,268 17:38:00 Non-Participant H-2550 264,779 4,508,247 19:09:00 Non-Participant H-2551 267,133 4,506,298 29:46:00 Participant H-2552 264,991 4,508,124 14:44:00 Non-Participant H-2553 264,829 4,508,423 35:24:00 Non-Participant H-2556 264,635 4,508,501 18:47:00 Non-Participant H-2566 264,852 4,508,251 24:36:00 Non-Participant H-2567 264,855 4,508,278 22:25:00 Non-Participant H-2569 264,828 4,508,446 41:49:00 Non-Participant H-2571 264,754 4,508,495 34:06:00 Non-Participant H-2572 264,714 4,508,713 11:57:00 Non-Participant H-2582 264,645 4,508,646 11:57:00 Non-Participant H-2588 265,437 4,507,940 24:15:00 Non-Participant

B-12 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-2590 264,886 4,508,278 26:00:00 Non-Participant H-2591 264,885 4,508,252 26:10:00 Non-Participant H-2593 264,993 4,508,150 14:20:00 Non-Participant H-2594 264,987 4,508,195 17:22:00 Non-Participant H-2595 265,024 4,508,193 14:12:00 Non-Participant H-2596 264,955 4,508,197 19:41:00 Non-Participant H-2597 264,960 4,508,152 14:31:00 Non-Participant H-2598 264,953 4,508,119 14:50:00 Non-Participant H-2599 264,946 4,508,086 15:07:00 Non-Participant H-2601 264,995 4,508,244 24:09:00 Non-Participant H-2602 264,995 4,508,291 29:16:00 Non-Participant H-2603 264,998 4,508,320 29:20:00 Non-Participant H-2604 259,889 4,510,203 1:18:00 Non-Participant H-2605 264,879 4,508,105 14:52:00 Non-Participant H-2606 264,503 4,507,987 18:34:00 Non-Participant H-2607 264,587 4,508,586 11:40:00 Non-Participant H-2608 264,511 4,508,620 9:12:00 Non-Participant H-2609 264,552 4,508,600 10:13:00 Non-Participant H-2622 264,607 4,508,065 18:32:00 Non-Participant H-2623 264,701 4,508,634 15:03:00 Non-Participant H-2624 265,069 4,508,290 26:00:00 Non-Participant H-2625 264,668 4,508,041 18:19:00 Non-Participant H-2626 264,663 4,508,024 17:36:00 Non-Participant H-2634 265,262 4,507,948 20:51:00 Non-Participant H-2637 260,044 4,509,975 4:12:00 Non-Participant H-2638 260,035 4,510,142 2:10:00 Non-Participant H-2639 260,061 4,510,110 2:14:00 Non-Participant H-2640 260,044 4,510,082 2:28:00 Non-Participant H-2641 260,044 4,510,059 3:05:00 Non-Participant H-2642 260,042 4,510,030 3:34:00 Non-Participant H-2643 264,887 4,508,181 21:16:00 Non-Participant H-2644 264,889 4,508,198 22:59:00 Non-Participant H-2645 264,913 4,508,205 22:47:00 Non-Participant H-2646 264,852 4,508,201 24:05:00 Non-Participant H-2647 264,817 4,508,195 23:46:00 Non-Participant H-2648 264,846 4,508,185 23:00:00 Non-Participant H-2652 264,953 4,508,357 19:56:00 Non-Participant H-2653 264,967 4,508,299 28:50:00 Non-Participant H-2654 264,966 4,508,322 27:34:00 Non-Participant H-2655 264,936 4,508,323 23:57:00 Non-Participant H-2656 264,887 4,508,295 23:35:00 Non-Participant

B-13 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-2657 264,890 4,508,353 17:40:00 Non-Participant H-2658 264,893 4,508,371 16:42:00 Non-Participant H-2659 264,889 4,508,385 15:58:00 Non-Participant H-2660 264,916 4,508,385 16:31:00 Non-Participant H-2661 264,860 4,508,384 17:41:00 Non-Participant H-2662 264,858 4,508,371 16:22:00 Non-Participant H-2663 264,821 4,508,164 21:46:00 Non-Participant H-2664 264,837 4,508,160 21:07:00 Non-Participant H-2665 264,850 4,508,159 20:40:00 Non-Participant H-2666 264,760 4,508,097 17:57:00 Non-Participant H-2667 264,559 4,507,917 17:57:00 Non-Participant H-2668 264,413 4,508,506 9:20:00 Non-Participant H-2669 264,411 4,508,522 9:08:00 Non-Participant H-2670 264,413 4,508,538 8:57:00 Non-Participant H-2671 265,021 4,507,956 24:20:00 Non-Participant H-2672 263,502 4,500,303 41:12:00 Non-Participant H-2677 264,652 4,507,971 16:26:00 Non-Participant H-2678 264,307 4,508,512 7:11:00 Non-Participant H-2685 264,770 4,508,162 21:58:00 Non-Participant H-2689 264,783 4,508,359 22:27:00 Non-Participant H-2690 264,780 4,508,386 29:44:00 Non-Participant H-2691 264,723 4,508,335 22:16:00 Non-Participant H-2692 264,671 4,508,307 21:16:00 Non-Participant H-2693 264,768 4,508,203 22:22:00 Non-Participant H-2694 264,731 4,508,203 20:20:00 Non-Participant H-2695 264,665 4,508,114 19:26:00 Non-Participant H-2696 264,667 4,508,133 19:17:00 Non-Participant H-2697 264,665 4,508,163 18:39:00 Non-Participant H-2698 264,661 4,508,181 16:37:00 Non-Participant H-2700 264,279 4,508,655 5:07:00 Non-Participant H-2701 264,373 4,508,589 7:35:00 Non-Participant H-2702 264,413 4,508,554 8:50:00 Non-Participant H-2703 264,395 4,508,572 8:13:00 Non-Participant H-2704 264,365 4,508,626 6:09:00 Non-Participant H-2705 264,413 4,508,681 5:53:00 Non-Participant H-2706 264,163 4,508,557 5:20:00 Non-Participant H-2707 264,164 4,508,638 4:47:00 Non-Participant H-2708 264,165 4,508,654 4:42:00 Non-Participant H-2728 271,597 4,508,268 5:53:00 Non-Participant H-2899 263,542 4,499,759 4:08:00 Non-Participant H-2910 264,995 4,508,272 27:51:00 Non-Participant

B-14 Hardin Wind Farm – Shadow Flicker Analysis

WindPro Predicted Expected Shadow Hardin Flicker Project Receptor UTM-E UTM-N (Hours per Participation ID (m) (m) Year) Status H-2911 264,773 4,508,231 20:49:00 Non-Participant H-2985 268,207 4,506,645 25:20:00 Non-Participant

B-15 Hardin Wind Farm – Shadow Flicker Analysis

ATTACHMENT B

Turbine Locations for the Hardin Wind Farm

B-1 Hardin Wind Farm – Shadow Flicker Analysis

Turbine UTM-E UTM-N ID (m) (m) 1 260483 4509447 2 260245 4509129 3 260245 4508748 4 260562 4508352 5 261039 4509479 6 261126 4509185 7 261190 4508860 8 261348 4508566 9 261586 4508328 10 261690 4507883 11 261769 4507526 12 262515 4509248 13 262674 4508979 14 262817 4508709 15 260856 4507955 16 260856 4507597 17 260872 4507296 18 260943 4507010 19 261031 4506716 20 260130 4507951 21 260265 4507691 25 262136 4505892 26 262358 4505647 27 262913 4506190 28 262936 4505790 29 263085 4505380 30 261604 4505674 31 261524 4505062 32 260656 4505232 33 259485 4506158 34 259836 4506105 35 260233 4506085 37 259489 4504339 38 260117 4504478 39 263832 4507752 40 263829 4507458 41 263822 4507167 42 263806 4506869 43 263799 4506549 44 263832 4506208 45 263789 4505751

B-2 Hardin Wind Farm – Shadow Flicker Analysis

Turbine UTM-E UTM-N ID (m) (m) 46 264083 4505586 47 264335 4505328 48 264358 4504964 49 263647 4504591 50 263584 4504316 51 263472 4503989 52 264001 4503876 53 263333 4503615 54 263366 4503258 55 263521 4502950 56 263591 4502606 57 263710 4502176 58 263938 4501955 59 264477 4503843 60 264517 4503546 61 264543 4503271 62 264579 4502920 63 264828 4502676 64 264940 4502401 65 262691 4501653 66 262754 4501382 67 262830 4501094 68 262979 4500830 69 263055 4500502 70 262955 4500135 71 262258 4500476 72 262198 4500158 73 263557 4501303 76 265018 4507197 77 265216 4506987 78 265782 4507601 79 265928 4507339 80 266039 4507059 81 266069 4498106 82 266085 4506497 83 265269 4508621 84 265613 4508536 85 266015 4508380 86 266272 4508187 88 266785 4508512 91 267543 4508924

B-3 Hardin Wind Farm – Shadow Flicker Analysis

Turbine UTM-E UTM-N ID (m) (m) 92 267691 4508520 94 268330 4509086 97 269063 4508952 98 269055 4508642 99 265417 4496676 100 268331 4507991 101 267307 4507677 102 265941 4498603 103 267880 4507465 104 268161 4507349 105 268435 4507234 106 268720 4507118 107 269765 4506575 108 266943 4507104 109 267255 4506866 110 267509 4506615 111 270596 4509993 112 271437 4510527 113 271469 4509681 114 271432 4509199 115 271998 4509030 116 272136 4508765 117 270570 4508379 118 270660 4508104 120 265891 4498894 121 267602 4507587 123 267868 4508198 124 268287 4508814 125 266185 4506127 126 266267 4505846 127 261760 4507229 129 264304 4501576 130 267670 4506408 131 264416 4507151 132 262960 4506939 133 263023 4506606

B-4