2012 Clean and Safe Neighborhood Parks Bond Status Report Presented to the

CITIZENS’ GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE

As of April 2015

Demolition at Joe Dimaggio Playground

Prepared by: Terence Chow, Recreation and Parks Department, Accountant, 581‐2554 [email protected] Maureen Devlin, Recreation and Parks Department, Analyst, 581‐2572, [email protected] James Hurley, , Analyst, 274‐0598, [email protected]

Presented by: Dawn Kamalanathan, Recreation and Parks Department, Director of Planning and Capital Management, 581‐2544, [email protected] Elaine Forbes, Port of San Francisco, Deputy Director of Finance and Administration, 274‐0445, [email protected]

EXECUTIVE SUMMARY

2012 San Francisco Clean and Safe Neighborhood Parks In November 2012, 71.6% of voters approved Budget $M Proposition B for a $195 million General Obligation Neighborhood Parks Bond, known as the 2012 San Francisco Clean and Angelo J. Rossi Playground 8.2 Safe Neighborhood Parks Bond (the “bond”). This Balboa Park 7 Garfield Square 11 funding will continue a decade of investment in the George Christopher Playground 2.8 aging infrastructure of our park system. Specifically, Gilman Playground 1.8 the bond allocates: 12 Hyde & Turk Mini Park 1  $99 million for Neighborhood Parks, selected Joe DiMaggio Playground 5.5 Margaret S. Hayward Playground 14 based on community feedback, their physical Moscone Recreation Center 1.5 condition, the variety of amenities offered, 2 seismic safety risk, and neighborhood density Potrero Hill Recreation Center 4 South Park 1  $21 million for , West Sunset Playground 13.2  Park, and John McLaren Park Willie "Woo Woo" Wong Playground 6  $12 million for the Community Opportunity Fund Program Contingency 6 Issuance and Oversight 2  $15.5 million for Failing Playgrounds 99  $13 million for Forestry, Trails, and Water Citywide Parks Conservation, and Lake Merced Park 2  Golden Gate Park 9 $34.5 million for Waterfront parks and open John McLaren Park 10 spaces 21 Citywide Programs Community Opportunity Fund 12 Program Schedule Failing Playgrounds 15.5 Forestry 4 The slate of Bond projects is structured to be Trails 4 completed over a period of approximately six years, Water Conservation 5 40.5 beginning in early 2013 and concluding with the last Waterfront Parks project closeouts in 2018. The sequence of projects Fisherman's Wharf Plaza 1.5 Northeast Wharf Plaza & Pier 27/29 Tip 17 has been adjusted to allow for project and site Agua Vista Park 2.5 readiness and the workload capacity of Recreation Crane Cove Park 8 Pier 70 Parks 2 and Park, Port, and Department of Public Works staff. Warm Water Cove Park 1.5 In January, the first Neighborhood Park, Joe DiMaggio Islais Creek Improvements 2 34.5 broke ground, and is scheduled to complete in TOTAL $195.0 December 2015. 4 more Neighborhood Parks will enter construction in 2015.

Bond Funding In collaboration with the Office of Public Finance, the first sale occurred in spring 2013, with proceeds appropriated to projects in June 2013. The 1st sale proceeds were reappropriated between projects in April 2015 to reallocate to projects to match the current spend down rate. The second sale is planned for late summer 2015, and the timing of the third and subsequent sale(s) is not yet known.

1

Proceeds from the first sale funds the planning and design of 6 Neighborhood parks, as well as the construction of 5 of those, and partially funds early planning on 5 additional Neighborhood parks. The Citywide Parks all received funding to begin planning and design work, and all of the Citywide Programs also have an allocation from the first issuance to commence planning, design, and construction of the initial projects. The 2012 Community Opportunity Fund continued the 2008 program, and the second round of applications was received in the beginning of April. Water Conservation work, matched with funding from the PUC, has begun at 3 parks, and the Failing Playgrounds, with its Task Force, has developed a list of prioritized parks throughout the city to receive 2012 Bond Funding. On the Waterfront, three project sites will have an allocation for planning and design, and one of those will also receive construction funding. The supplemental reappropriation has rebalanced cash among the Rec and Park projects and programs:

 15 Neighborhood parks  3 Citywide parks, and  5 Citywide programs

Program Management Activities As of March 31, 2015, 1 project is in construction, with 4 more to enter construction in 2015. Funding from the 1st Sale was reappropriated in Spring 2015. This action redistributed the budgetary allocation of the 1st sale proceeds between the 2012 Bond projects, and has delayed the need for a 2nd sale, while providing adequate funding for projects in the program. The 2nd sale is anticipated for late summer 2015 and staff are currently working with the office of Public Finance to determine the exact timing and size of this sale, and strategize future sales.

2

Project Status Summaries

Angelo J. Rossi Playground Project Location: 2 North Willard Street, District 1 Project Manager: TBD

Angelo J. Rossi Playground is located at the corner of Anza Street and Arguello Boulevard. The approximately 300,000 square foot park includes a pool building, maintenance building, and sport courts. The proposed project would include improvements to the Pool building which include plumbing, mechanical and electrical systems. The degraded roof element will be replaced in‐kind, and interior partitions in staff and restroom areas will be adjusted to meet current ADA standards. All features in the site are expected to remain in their current locations and configuration.

Phase Planning Design Construction Completion Baseline Schedule Jun‐15 Dec‐15 May‐17 Jan‐19 Current Schedule Jun‐15 Dec‐15 May‐17 Dec‐18

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 8.2 0 8.2 Current 8.2 0 8.2 Expenditures to Date 0 0 0

Project Status Summaries

Balboa Park Pool Project Location: 51 Havelock, District 11 Project Manager: Toks Ajike, [email protected], 415‐581‐2543

Balboa Park Pool is located at 51 Havelock Street at San Jose and Ocean Avenues. The renovation will completely renovate the pool building includes new shower and locker rooms, new pool circulation systems, including mechanical and electrical throughout the building, seismic upgrades and accessibility improvements.

Phase Planning Design Construction Completion Original Schedule Mar‐13 Sep‐13 Mar‐15 Oct‐16 Current Schedule Feb‐14 Jun‐14 Dec‐15 May‐17

Budget ($ in millions) 2012 Bond Other Funds Total

Bond Baseline 7.0 0 7.0

Current 7.0 0.6 7.6

Expenditures to Date $431,204 0 $431,204

Project Status Summaries

Garfield Square Project Location: 1271 Treat Avenue, District 9 Project Manager: Marvin Yee, [email protected], 415‐581‐2541

Garfield Square is located at Harrison Street and 26th Street. The park is approximately 169,000 square feet and has a pool building and adjacent club house, sport courts, synthetic fields for soccer, children’s play area, picnic area, landscaping, and related amenities. The proposed project will completely renovate the pool building with new shower and locker rooms, new pool circulation systems, and include mechanical and electrical upgrades throughout the building, and make accessibility improvements. Improvements to the park’s perimeter, pathways, and some site amenities in the clubhouse complex will include repair and/or replacement of the sidewalk, pathways, and benches to meet current ADA standards.

Phase Planning Design Construction Completion Baseline Schedule Jun‐14 Dec‐14 Jun‐16 Nov‐17 Current Schedule Jan‐15 Jun‐15 Nov‐16 May‐18

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 11.0 0 11.0 Current 11.0 0 11.0 Expenditures to Date $122,143 0 $122,143

Project Status Summaries

George Christopher Playground Project Location: 1098 Douglass Street, District 8 Project Manager: Matt Jasmin

George Christopher Playground is located near Duncan Street and Diamond Heights Boulevard. The park is approximately 310,000 square feet and has a clubhouse, baseball field, pathways, tennis courts, playgrounds, and related amenities. The project may include improvements to the children’s play area, exterior clubhouse restrooms, park access, and related amenities.

Phase Planning Design Construction Completion Baseline Schedule Feb‐15 Oct‐15 Apr‐17 Jul‐18 Current Schedule Feb‐15 Oct‐15 Apr‐17 Jul‐18

Budget ($ in millions) 2012 Bond Other Funds Total

Bond Baseline 2.8 13.0 15.8

Current 2.9 13.0 15.8 Expenditures to Date $0 0 $0

Project Status Summaries

Gilman Playground

Project Location: 951 Gilman Street, District 10 Project Manager: Marvin Yee, [email protected], 415‐581‐2541

Gilman Playground is located at the intersection of Gilman and Ingerson Avenues. The park is approximately 224,000 square feet and includes playfields, picnic areas, basketball court, children’s play area, and a clubhouse. The 2012 Bond project will provide new play equipment that will encourage graduated play through the linking of composite structures with a net climber. Numerous swings and independent events (zip line, net spinner, and independent spinners) as well as separate tot area will be created. The underlying rubber surface will depict a shoreline setting in reference to the park’s former proximity to the bay. The construction contract was receiving bids at March 31, 2015 and a contract was presented for Commission Approval in April. Construction will begin in late Spring. Gilman Final Concept Plan

Phase Planning Design Construction Completion Baseline Schedule Mar‐13 Sep‐13 Mar‐15 Aug‐16 Current Schedule Mar‐13 Dec‐13 Jun‐15 Oct‐16

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 1.8 0 1.8 Current 1.8 0 1.8 Expenditures to Date $292,426 0 $292,426

Project Status Summaries

Glen Canyon Park Project Location: 70 Elk Street, District 8 Project Manager: Karen Mauney‐Brodek, karen.mauney‐[email protected], 415‐575‐5601

Glen Canyon Park is located off of O’Shaughnessy Boulevard and Elk Street. The 2012 Bond project will enhance and expand the recreation center. The gymnasium, auditorium, offices, and related amenities will renovated, 4,500 square feet of multi‐purpose space will be added, or provided through both additions and a re‐organization of existing spaces. Overall space will be designed to enhance programmatic flexibility and seating, with increased access, visibility and improved restrooms. The improvement will include and identifiable main entrance, and related outdoor improvements. .

Phase Planning Design Construction Completion Baseline Schedule Mar‐13 Sep‐13 Mar‐15 Oct‐16 Current Schedule Mar‐13 Dec‐13 Aug‐15 Jan‐17

Budget ($ in millions) 2012 Bond Other Funds Total

Bond Baseline 12.0 0 12.0

Current 12.0 0 12.0

Expenditures to Date $2,073,588 0 $2,073,588

Project Status Summaries

Hyde & Turk Mini Park

Project Location: 201 Hyde Street, District 6 Project Manager: TBD

Hyde & Turk Mini Park is located at 201 Hyde Street. The park is approximately 6,500 square feet and has a children’s play area, landscaping, and related amenities.

The project may include renovations of the children’s play area, landscaping, site accessibility, and related amenities.

Phase Planning Design Construction Completion Baseline Schedule Jan‐16 Jul‐16 Sep‐17 Sep‐18 Current Schedule Jan‐16 Jul‐16 Sep‐17 Sep‐18

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 1.0 0 1.0 Current 1.0 0 1.0

Project Status Summaries

Joe DiMaggio Playground Project Location: 651 Lombard Street at Mason, District 3 Project Manager: Cara Ruppert, [email protected], 415‐581‐2547

Joe DiMaggio Playground is located at the corner of Mason Street and Lombard Street. The approximately 110,000 square foot current project will expand the children’s play area, relocate and improve the tennis courts, as well as resurfacing other sport courts, upgrade landscaping, improve seating, picnicing and lighting and lighting and providing better access throughout the playground. The project broke ground in January 2015, and as of March 31, demolition is almost complete; the tennis courts will be the first completed portion of the project, with paving to be installed this spring.

Tennis Court Area at Joe DiMaggio

Phase Planning Design Construction Completion

Baseline Schedule Mar‐13 Jul‐13 Mar‐15 Jun‐16 Current Schedule Mar‐13 Sep‐13 Jan‐15 Mar‐16

Budget ($ in millions) 2012 Bond Other Funds Total

Bond Baseline 5.5 0 5.5

Current 6.3 0 6.3

Expenditures To Date $1,787,076 0 $1,787,076

Project Status Summaries

Margaret S. Hayward Playground

Project Location: 1016 Laguna Street, District 5 Project Manager: Marien Coss, [email protected], 415‐581‐2557

Margaret S. Hayward Park is located at the corner of Turk and Gough Streets. The park is approximately 265,000 square feet. It offers recreation facilities including indoor recreation space, storage, and related amenities; sport courts; playfields including bleachers with storage and office space; children’s play area; and an emergency operations facility owned and operated by the Department of Emergency Management. The project may include renovations and/or consolidation of park structures including recreational buildings, storage, and restrooms; improved park access; replacement of sport courts, playfields, children’s play area, and related amenities.

Phase Planning Design Construction Completion Baseline Schedule Feb‐15 Oct‐15 Apr‐17 Aug‐18 Current Schedule Jun‐14 Nov‐15 Jun‐17 Dec‐18

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 14.0 0 14.0 Current 14.0 2.7 16.7 Expenditures To Date $155,949 0 $155,949

Project Status Summaries

Moscone Recreation Center‐East Playground Project Location: 1800 Chestnut Street, District 2 Project Manager: Dan Mauer, [email protected], 415‐581‐2542

Moscone Recreation Center is located between Laguna and Chestnut Streets and is approximately 567,000 square feet. The park includes a mini driving range, putting greens, basketball courts, tennis courts, children’s play areas, four ball fields, grassy areas, a recreation center, and other related recreational amenities and support facilities.

The project may include improvements to the eastern children’s play area, improved access, and related amenities.

Phase Planning Design Construction Completion Baseline Schedule Feb‐15 Aug‐15 Feb‐17 Nov‐17

Current Schedule Feb‐15 Feb‐15 Oct‐16 Nov‐17

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 1.5 0 1.5 Current 1.5 0 1.5 Expenditures To Date 0 0

Project Status Summaries

Mountain Lake Park Project Location: 1000 Lake Street, District 2 Project Manager: Mary Hobson, 415‐581‐2575

Mountain Lake Park is located at 1000 Lake Street. The park is approximately 1,000,000 square feet and has a lake, pathways, children’s play area, tennis courts, and large natural lawn areas. 2012 Bond Project will include a new play area for school age children with climbing structure featuring nets, swings, jumping discs, climbing forest of natural logs and ropes, and see‐saws, as well as an area for pre‐school age children with swings, see‐ saw, slide and an assortment of small climbing, swinging and spring and all elements fall zone fitted with high‐performance poured‐in‐place safety surfacing. Landscape will be terraced, irrigation will be improved, and with its switch back ramps, stairs and bridges, the project will provide additional seating and improved access for people with disabilities. As of March 31, the project is receiving construction bids, and construction is projected to start in early summer.

Phase Planning Design Construction Completion Baseline Schedule Mar‐13 Sep‐13 Mar‐15 Mar‐16 Current Schedule Mar‐13 Jun‐13 Jul‐15 Jun‐16

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 2.0 0 2 Current 2.0 0.3 2.3 Expenditures to Date $168,147 0 $168,147

Project Status Summaries

Potrero Hill Recreation Center Project Location: 801 Arkansas Street, District 10 Project Manager: TBD Potrero Hill Recreation Center is located at 801 Arkansas Street. The park is approximately 455,000 square feet and includes playfields, tennis courts, dog play area, playground and a recreation center.

The project may include improvements to the natural turf playfields and the dog play area.

Phase Planning Design Construction Completion Baseline Schedule Feb‐15 Oct‐15 Apr‐17 Sep‐18 Current Schedule Feb‐15 Oct‐15 Apr‐17 Sep‐18

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 4.0 0 4.0 Current 4.0 0 4.0 Expenditures to Date $0 0 $0

Project Status Summaries

South Park Project Location: 64 South Park Avenue Project Manager: Mary Hobson, [email protected], 415‐581‐2575

South Park is located at 64 South Park Avenue. The park is approximately 34,000 square feet and has children’s play areas, a walkway, natural lawn, landscaping, and related amenities. 2012 Bond Project will be a contemporary interpretation of the classic picturesque park with park amenities and programmatic spaces along a widened pathway that meanders through the park’s trees and landscaped areas. The concept plan proposes a variety of different programmatic spaces, including a children’s play area, a large open meadow, plazas of varying scales, and a variety of areas designed for sitting and/or picnicking. Additional improvements may include bulb‐outs and chicanes for traffic calming, bio‐infiltration swales, and a rainwater cistern for irrigation usage, if funding is available. Project is finishing design, and construction bid is scheduled to start in late Spring.

Phase Planning Design Construction Completion Baseline Schedule Jan‐16 Jul‐16 Nov‐17 Nov‐18 Current Schedule May‐13 Feb‐14 Aug‐15 Jun‐16

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 1.0 0 1.0 Current 1.0 1.5 2.0 Expenditures to Date $177,088 0 $177,088

Project Status Summaries

West Sunset Playground Project Location: 1990 41st Avenue, District 6 Project Manager: Dan Mauer, [email protected], 415‐581‐2542

West Sunset Playground is located between Sunset Elementary School and A.P. Giannini Middle School, at Ortega and Quintara Streets. The park is approximately 738,000 square feet and has a clubhouse, children’s play area, sport courts, multiple playfields, and related amenities. The 2012 Bond project will improve the current 3 baseball fields, including backstops and dugouts, and its 3 soccer fields, including improving drainage and replacing irrigation. Project will address a failing retainer wall between upper and lower baseball fields, fencing, bleacher seating, athletic courts, landscape and irrigation, improve ADA access with new pathways, steps and ramps throughout park and parking area. Project is completing design phase and entering bid/award in Spring 2015.

Phase Planning Design Construction Completion Baseline Schedule May‐13 Jan‐14 Jul‐15 Nov‐16 Current Schedule May‐13 Jan‐14 Nov‐15 Feb‐17

Budget ($ in millions) 2012 Bond Other Funds Total Bond Baseline 13.2 0 13.2 Current 13.2 0 13.2 Expenditures to Date $1,310,535 0 $1,310,535

Project Status Summaries

Willie “Woo Woo” Wong Playground

Project Location: 850 Sacramento Street Project Manager: Cara Ruppert, [email protected], 415‐581‐2547

Willie “Woo Woo” Wong Playground is located between Sacramento and Stockton Streets. The park is approximately 24,000 square feet and has a clubhouse, sport courts, children’s play area, alley open space, and related amenities. The 2012 project is currently in planning and design and may include the renovation of courts and children’s play area, improved park access including the adjacent alleyways, and related amenities, and reconfiguration of park features. The recently completed Historic Resource Evaluation, has provided RPD with a rich history of the playground area, including photographs of the site and the Chinatown neighborhood.

Phase Planning Design Construction Completion Baseline Schedule Feb‐15 Oct‐15 Apr‐17 Sep‐18 Current Schedule Jul‐14 Sep‐15 Nov‐16 Apr‐19

Budget ($ in millions) 2012 Bond Other Funds Total

Bond Baseline 6.0 0 6.0

Current 6.0 0 6.0

Expenditures to Date $140,673 0 $140,673

CITYWIDE PROGRAMS

The Citywide Programs’ goals, defined in more detail below, are determined by various citizen advisory or task force groups. Each program will have community outreach, collaboration with the Parks, Recreation and Open Space Advisory Committee (PROSAC) and review and approval by the RPD Commission in a regular public meeting to provide multiple opportunities for public participation.

Failing Playgrounds

The $15.5 million Failing Playgrounds program focuses on renovating, replacing, and remediating the most dilapidated of the over 170 playgrounds throughout the City. In 2014 a Task Force was appointed by the Recreation and Park Commission, including stakeholders from citywide open space organizations, the school district, children’s advocacy and parent organizations, and the Parks, Recreation and Open Space Advisory Committee (PROSAC).

In December 2014 the Task Force made its recommendations to the RPD Commission, prioritizing 13 playgrounds in 2 Tiers.

Tier 1  Alice Chalmers Tier 2 Playground*  Buchanan Street Mall  John McLaren Park  Golden Gate Heights (Group Picnic)* Park*  Merced Heights  Herz Playground Playground*  Juri Commons*  Panhandle  Richmond Playground* Playground*  Sgt. John Macaulay  Sigmund Stern Park* Recreation Grove*  Washington Square*  West Portal Playground*

The Parks Alliance (SFPA) and Recreation and Parks Department co‐hosted a Community Design Forum to set design goals for future playground renovations. Steve Cancian, of Shared Spaces facilitated the conversation on Feb 28th 2015. Approximately 50 members of the community participated in the forum; Nature Play and Risk Play were prioritized the highest by the Forum participants. Multigenerational play and Inclusive play were also considered high priority. RPD is developing a capital delivery strategy with schedule, which will be delivered to the RPD Commission late spring. There will be a community design process for each of the planned playground renovations (so mechanism to get community input). SFPA is entering into a feasibility study for a major philanthropic campaign for playgrounds, and we anticipate the study results in July.

CITYWIDE PROGRAMS

Forestry

The 2012 Bond allocates $4 million to improve the urban forest within the Rec and Park system. Trees are a critical element of San Francisco’s parks: cleaning the air, providing shelter to animals, contributing to the aesthetic character of each park. The Recreation and Park Department’s forest is estimated to contain well over 100,000 trees – most of which have not received assessment or attention since planting.

In 2010 RPD staff consulted with professional arborists and park stakeholders to develop a Tree Hazard Area Prioritization and Implementation Plan (the Plan) to guide the expenditure of bond funds. Accepted urban forest management techniques such as the hazard rating system were applied to park properties, identifying those parks, areas and trees most in need of tree repair.

The Plan relies upon tree hazard assessment and risk abatement principles, focusing on those trees which are deemed hazardous and nearby a high use area (e.g. playground, or major thoroughfare). Trees are not selected for removal based on their species or location, only due to the risk posed to life or property.

RPD staff will develop a capital plan based on the Tree Hazard Area Prioritization with scopes, budgets, and schedules to guide the allocation of this $4 million in Forestry program funds. This plan will be reviewed and approved by the RPD Commission prior to expenditure.

CITYWIDE PROGRAMS

Water Conservation

In 2009, the SF Public Utilities Commission conducted an audit of the highest water using parks and prepared the “Water Conservation Plan” to assess problems and recommend solutions. Many neighborhood parks operate with antiquated irrigation systems, installed with the original park development, that result in millions of gallons of water lost due to uneven spray coverage and leaking pipes. Most of these water‐wasting systems also require manual operation, which is labor intensive and inefficient.

The 2012 Park Bond funds $5 million in conservation measures. In collaboration with the PUC water conservation team and RPD operations staff, several sites throughout the park system have been prioritized and funded and work has begun to reduce waste, reclaim and recycle where possible, improve irrigation. An irrigation retrofit at Sharp Park Golf course has already been completed in the eastern portion of the golf course.

The PUC’s partnership includes grants which will expand the scope of the projects, and result in substantial long‐term water use reduction; project goals are up to 33% water‐use reduction post‐ renovation. The additional funding support will improve RPD’s ability to innovate and be site specific, replace antiquated irrigation systems with better designed and positioned to match the park’s unique topography. Water conservation projects improve staff efficiencies, by incorporating “smart” controllers and reducing the need for RPD staff. Alamo Square Park is currently in bid/award with construction to start in Summer 2015, North is in design, and the Moscone Recreation Center improvement is being planned.

All park planning and design is now done with an eye to water conservation, and include planting lawn alternatives where appropriate.

CITYWIDE PROGRAMS

Trails

The 2004 Recreation Assessment identified walking and biking trails as the #1 most desired amenity by San Francisco residents. The 2012 Bond funds will build on the success of the 2008 Bond program to improve access and opportunities to walk and hike, allowing residents to better enjoy and experience nature in San Francisco parks.

The 2012 Bond’s $4 million trails program shall be used to repair and reconstruct park nature trails, pathways, and connectivity in Golden Gate Park and John McLaren Park.

RPD staff, in consultation with PROSAC, trail building experts, and park stakeholders, will make recommendations on proposed trail projects to the Recreation and Park Commission for approval prior to the expenditure of these funds. After identification and development of specific projects, environmental review required under CEQA will be completed.

CITYWIDE PROGRAMS

Community Opportunity Fund (COF)

The COF program provides an opportunity for neighborhoods community groups and park partners to improve their parks by proposing projects and demonstrating their commitment by leveraging private gifts, volunteer time and additional public funding. The Community Opportunity Fund (COF) has three main policy goals:

 Foster community stewardship and improve RPD partnerships  Enhance park identity and experience  Leverage additional resources from the community

Established in the 2008 Clean and Safe Neighborhood Parks Bond, the COF has already leveraged an additional $13.7 million in donations, in kind resources, sweat equity, and philanthropic investment against the $5 million allocated within the 2008 bond. Previously funded projects include a playground in McLaren Park, renovation of the Sunnyside Conservatory, and the reimagining of LeConte Park to the Rolph D. House Community Park.

Encouraged by the success of this program, the Recreation and Park Department included an expansion of the Community Opportunity Fund, allocating $12 million from the 2012 San Francisco Clean and Safe Neighborhood Parks Bond, with$6 million to be used to continue funding projects under the existing COF selection process. Round 4 was completed in Fall 2015 and the Rec and Park Commission approved the staff recommended Round 4 projects:

1. Hilltop Skate Park 2. Lake Merced – North Lake Dock Renovation 3. MLK‐Bayview Park Improvement Project 4. Tank Hill Trail Improvements 5. West Portal Playground

Round 5 was accepting applications as of March 31, 2015, and staff will be recommending projects to Commission in late Spring 2015.

With the remaining $6 million, the RPD Commission will establish a Partnership Projects fund. The Partnership Projects fund will support larger scale projects that have:

 Completed environmental review, as governed by the California Environmental Quality Act  Provided evidence of broad‐based community support  Obtained commitments of significant match in philanthropic funding against requested bond funds  Demonstrated consistency with existing department and city policy and capital planning documents

CITYWIDE PARKS

The San Francisco Recreation and Park Department cares for and stewards many of the city’s most beautiful and cherished landscapes. Each of these parks contributes immeasurably towards our quality of life in the city, and helps to define each neighborhood’s identity.

Our citywide serving parks, which include Golden Gate Park, McLaren Park, and Lake Merced Park, define the City of San Francisco’s special identity as an urban oasis that offers both the best urban amenities and convenient access to unique open spaces. Together, these three parks comprise almost 2,000 acres of open space, each with capital needs just as vast. Golden Gate Park alone is estimated to need over $500 million in capital investment to renovate and improve park features.

The 2012 Bond Citywide Parks program allocates $21 million for investment as follows: Golden Gate Park $9 million, McLaren Park (and those properties contiguous to it under the Recreation and Park Commission’s jurisdiction) $10 million, and Lake Merced Park $2 million. These funds can be used for capital improvements at these parks, and may include, but are not limited to, the following types of projects:

 Restoration of natural features, including lakes, meadows, and landscapes  Recreational Assets, such as playgrounds, playfields, courts, and picnic areas  Connectivity and Access, such as roads, pedestrian safety, paths, and trails

$6.5 million of funds allocated to Golden Gate Park, and $1.5 million of funds allocated to John McLaren Park, shall be allocated to projects that create or restore:

 Natural features, such as lakes, meadows, and landscapes  Habitat for the park's many species of plants and animals

RPD staff will make recommendations to PROSAC and the RPD Commission on a capital plan to guide expenditure of these funds. These recommendations will be informed by:

 Community process and outreach  Existing master plans and policy documents  Scoping by RPD capital staff  Overall project readiness

2012 Clean & Safe Neighborhood Parks G.O. Bond Program Budget Reports - Revenues as of 4/30/15

PROGRAMS ORIGINAL BUDGET 2012 2008 CSP OPEN SPACE REVENUE GENERAL OTHER PORT/ TOTAL BONDS BONDS FUNDS BONDS FUND GRANTS GIFTS RPD FUNDS SOURCES

NEIGHBORHOOD PARKS Angelo J. Rossi Playground 8,200,000 ------Balboa Park 7,000,000 2,109,000 - - - - 610,425 - - 2,719,425 Garfield Square 11,000,000 1,604,000 ------1,604,000 George Christopher Playground 2,800,000 300,000 ------300,000 Gilman Playground 1,800,000 1,800,000 ------1,800,000 Glen Canyon Park 12,000,000 12,000,000 ------12,000,000 Hyde & Turk Mini Park 1,000,000 ------Joe DiMaggio Playground 5,500,000 6,300,000 ------6,300,000 Margaret S Hayward Playground 14,000,000 850,000 ------150,000 1,000,000 Moscone Recreation Center - East Playground 1,500,000 300,000 ------300,000 Mountain Lake Park 2,000,000 2,000,000 - - - 278,710 - - - 2,278,710 Potrero Hill Recreation Center 4,000,000 300,000 ------300,000 South Park 1,000,000 1,000,000 ------1,500,000 2,500,000 West Sunset Playground 13,200,000 13,200,000 ------13,200,000 Willie "Woo Woo" Wong Playground 6,000,000 950,000 ------950,000 Program Contingency 6,000,000 2,666,070 ------2,666,070 SUBTOTAL FOR NEIGHBORHOOD PARKS 91,000,000 42,713,000 - - - 278,710 610,425 - 1,650,000 45,252,135

CITYWIDE PARKS Golden Gate Park 9,000,000 457,000 ------457,000 John McLaren Park 10,000,000 2,500,000 ------2,500,000 Lake Merced Park 2,000,000 645,200 ------645,200 SUBTOTAL FOR CITYWIDE PARKS 21,000,000 3,602,200 ------3,602,200 SPECIAL CITY-WIDE PROGRAMS Community Opportunity Fund 12,000,000 1,900,000 ------1,900,000 Failing Playground 15,500,000 1,075,000 ------1,075,000 Forestry 4,000,000 31,230 ------31,230 Trail 4,000,000 ------Water Conservation 5,000,000 1,200,000 - - - 5,000 250,000 - - 1,455,000 SUBTOTAL FOR SPECIAL CITY-WIDE PROGRAMS 40,500,000 4,206,230 - - - 5,000 250,000 - - 4,461,230 WATERFRONT PARKS Agua Vista Park 2,500,000 ------Crane Cove Park 21,324,148 - 1,813,250 - - - - - 1,100,000 2,913,250 Fisherman's Wharf Plaza 1,500,000 ------Islais Creek Improvements 2,000,000 600,000 ------600,000 Northwest Wharf Plaza & Pier 27/29 Tip 17,000,000 17,000,000 ------17,000,000 Pier 70 Parks 2,000,000 600,000 ------600,000 Warm Water Cove Park 1,500,000 ------SUBTOTAL FOR WATERFRONT PARKS 47,824,148 18,200,000 1,813,250 - - - - - 1,100,000 21,113,250 PROGRAM-WIDE SERVICES Controller's Audit 585,000 214,745 ------214,745 Bond Issuance Cost 1,415,000 188,583 ------188,583 SUBTOTAL FOR PROGRAM-WIDE SERVICES 2,000,000 403,329 ------403,329 GRAND TOTAL 208,324,148 71,790,829 1,813,250 - - 283,710 860,425 - 2,750,000 77,498,214

3 2012 Clean & Safe Neighborhood Park G.O. Bond Program Budget Reports - Expenditures as of 4/30/15

FAMIS Baseline Budget Budget Reserve Expended Encumbered Balance Project Phase Category All Sources 2012 NP Bond All Sources 2012 NP Bond 2012 NP Bond All Sources 2012 NP Bond All Sources 2012 NP Bond 2012 NP Bond Neighborhood Parks Angelo J. Rossi Playground PLANNING/DESIGN Soft Costs 2,034,586 2,034,586 Construction Costs 6,165,414 6,165,414 Project Contingency - - SUBTOTAL 8,200,000 8,200,000 ------Balboa Park PLANNING/DESIGN Soft Costs 1,736,842 1,736,842 Construction Costs 5,263,158 5,263,158 Project Contingency - - SUBTOTAL 7,000,000 7,000,000 2,719,425 2,109,000 - 431,204 431,204 596,957 596,957 1,080,839 Garfield Square PLANNING/DESIGN Soft Costs 2,729,323 2,729,323 Construction Costs 8,270,677 8,270,677 Project Contingency - - SUBTOTAL 11,000,000 11,000,000 1,604,000 1,604,000 - 122,143 122,143 1,810 1,810 1,480,047 George Christopher Playground PLANNING/DESIGN Soft Costs 694,737 694,737 Construction Costs 2,105,263 2,105,263 Project Contingency - - SUBTOTAL 2,800,000 2,800,000 300,000 300,000 - - - - - 300,000 Gilman Playground PLANNING/DESIGN Soft Costs 446,617 446,617 Construction Costs 1,353,383 1,353,383 Project Contingency - - SUBTOTAL 1,800,000 1,800,000 1,800,000 1,800,000 - 292,426 292,426 1,923 1,923 1,505,652 Glen Canyon Park PLANNING/DESIGN Soft Costs 2,977,444 2,977,444 Construction Costs 9,022,556 9,022,556 Project Contingency - - SUBTOTAL 12,000,000 12,000,000 12,000,000 12,000,000 - 2,073,588 2,073,588 102,449 102,449 9,823,963 Hyde & Turk Mini Park PLANNING/DESIGN Soft Costs 248,120 248,120 Construction Costs 751,880 751,880 Project Contingency - - SUBTOTAL 1,000,000 1,000,000 ------Joe DiMaggio Playground PLANNING/DESIGN Soft Costs 1,364,662 1,364,662 Construction Costs 4,135,338 4,135,338 Project Contingency - - SUBTOTAL 5,500,000 5,500,000 6,300,000 6,300,000 - 1,787,076 1,787,076 3,887,046 3,887,046 625,878 Margaret S Hayward Playground PLANNING/DESIGN Soft Costs 3,473,684 3,473,684 Construction Costs 10,526,316 10,526,316 Project Contingency - - SUBTOTAL 14,000,000 14,000,000 1,000,000 850,000 - 158,949 158,949 224 224 690,828 Moscone Recreation Center - East PLANNING/DESIGN Soft Costs 372,180 372,180 Playground Construction Costs 1,127,820 1,127,820 Project Contingency - - SUBTOTAL 1,500,000 1,500,000 300,000 300,000 - - - - - 300,000 Mountain Lake Park PLANNING/DESIGN Soft Costs 496,241 496,241 Construction Costs 1,503,759 1,503,759 Project Contingency - - SUBTOTAL 2,000,000 2,000,000 2,278,710 2,000,000 - 168,147 168,147 30,599 30,599 1,801,254 Potrero Hill Recreation Center PLANNING/DESIGN Soft Costs 992,481 992,481 Construction Costs 3,007,519 3,007,519 Project Contingency - - SUBTOTAL 4,000,000 4,000,000 300,000 300,000 - - - - - 300,000 South Park PLANNING/DESIGN Soft Costs 248,120 248,120 Construction Costs 751,880 751,880 Project Contingency - - SUBTOTAL 1,000,000 1,000,000 2,500,000 1,000,000 - 177,088 177,088 36,926 36,926 785,986 West Sunset Playground PLANNING/DESIGN Soft Costs 3,275,188 3,275,188 Construction Costs 9,924,812 9,924,812 Project Contingency - - SUBTOTAL 13,200,000 13,200,000 13,200,000 13,200,000 - 1,310,535 1,310,535 44,089 44,089 11,845,376 Willie "Woo Woo" Wong Playground PLANNING/DESIGN Soft Costs 1,488,722 1,488,722 Construction Costs 4,511,278 4,511,278 Project Contingency - - SUBTOTAL 6,000,000 6,000,000 950,000 950,000 - 140,673 140,673 678,883 678,883 130,443

Program Contingency 6,000,000 6,000,000 2,666,070 2,666,070 - - - - - 2,666,070

Soft Costs 22,578,947 22,578,947 Construction Costs 68,421,053 68,421,053 NEIGHBORHOOD PARKS Project Contingency 6,000,000 6,000,000 SUBTOTAL 97,000,000 97,000,000 47,918,205 45,379,070 - 6,661,829 6,661,829 5,380,907 5,380,907 33,336,335

4 2012 Clean & Safe Neighborhood Park G.O. Bond Program Budget Reports - Expenditures as of 4/30/15

FAMIS Baseline Budget Budget Reserve Expended Encumbered Balance Project Phase Category All Sources 2012 NP Bond All Sources 2012 NP Bond 2012 NP Bond All Sources 2012 NP Bond All Sources 2012 NP Bond 2012 NP Bond

Golden Gate Park PLANNING/DESIGN Soft Costs 2,233,083 2,233,083 Construction Costs 6,766,917 6,766,917 Project Contingency - - SUBTOTAL 3,300,000 9,000,000 457,000 457,000 - 53,642 53,642 3,325 3,325 400,033 John McLaren Park PLANNING/DESIGN Soft Costs 2,481,203 2,481,203 Construction Costs 7,518,797 7,518,797 Project Contingency - - SUBTOTAL 3,300,000 10,000,000 2,500,000 2,500,000 - 63,998 63,998 31,215 31,215 2,404,788 Lake Merced Park PLANNING/DESIGN Soft Costs 496,241 496,241 Construction Costs 1,503,759 1,503,759 Project Contingency - - SUBTOTAL 3,300,000 2,000,000 645,200 645,200 - 3,229 3,229 - - 641,971

Soft Costs 5,210,526 5,210,526 Construction Costs 15,789,474 15,789,474 CITYWIDE PARKS Project Contingency - - SUBTOTAL 21,000,000 21,000,000 3,602,200 3,602,200 - 120,869 120,869 34,540 34,540 3,446,792

Community Opportunity Fund PLANNING/DESIGN 12,000,000 12,000,000 1,900,000 1,900,000 - 153,966 153,966 105,396 105,396 1,640,638

Failing Playground PLANNING/DESIGN 15,500,000 15,500,000 1,075,000 1,075,000 - 75,799 75,799 - - 999,201

Forestry PLANNING/DESIGN 4,000,000 4,000,000 31,230 31,230 - 1,198 1,198 - - 30,032

Trail PLANNING/DESIGN 4,000,000 4,000,000 ------

Water Conservation PLANNING/DESIGN 5,000,000 5,000,000 1,455,000 1,200,000 - 663,397 413,397 7,418 7,418 779,185

CITY-WIDE PROGRAMS SUB-TOTAL: 40,500,000 40,500,000 4,461,230 4,206,230 - 894,361 644,361 112,813 112,813 3,449,056

Agua Vista Park Soft Costs 750,000 750,000 Construction Costs 1,750,000 1,750,000 Project Contingency SUBTOTAL 2,500,000 2,500,000 ------Crane Cove Park Soft Costs 1,813,250 Construction Costs 19,510,898 8,000,000 Project Contingency SUBTOTAL 21,324,148 8,000,000 2,913,250 - - 1,041,589 - 1,688,667 - - Fisherman's Wharf Plaza Soft Costs 450,000 450,000 Construction Costs 1,050,000 1,050,000 Project Contingency SUBTOTAL 1,500,000 1,500,000 ------Islais Creek Improvements Soft Costs 600,000 600,000 Construction Costs 1,400,000 1,400,000 Project Contingency SUBTOTAL 2,000,000 2,000,000 600,000 600,000 - - - - - 600,000 Northwest Wharf Plaza & Pier 27/29 Tip Soft Costs 2,400,000 2,400,000 Construction Costs 14,600,000 14,600,000 Project Contingency SUBTOTAL 17,000,000 17,000,000 17,000,000 17,000,000 - 13,504,248 13,504,248 2,418,831 2,418,831 1,076,921 Pier 70 Parks Soft Costs 600,000 600,000 Construction Costs 1,400,000 1,400,000 Project Contingency SUBTOTAL 2,000,000 2,000,000 600,000 600,000 - - - - - 600,000 Warm Water Cove Park Soft Costs 450,000 450,000 Construction Costs 1,050,000 1,050,000 Project Contingency SUBTOTAL 1,500,000 1,500,000 ------

WATERFRONT PARKS Soft Costs 7,063,250 5,250,000 Construction Costs 40,760,898 29,250,000 Project Contingency - - SUBTOTAL 47,824,148 34,500,000 21,113,250 18,200,000 - 14,545,837 13,504,248 4,107,498 2,418,831 2,276,921

Controller's Audit 585,000 585,000 214,745 214,745 - 107,952 107,952 106,793 106,793 (0) Bond Issuance Cost 1,415,000 1,415,000 188,583 188,583 - 188,583 188,583 - - - TOTAL PROGRAM: 208,324,148 195,000,000 77,498,214 71,790,829 - 22,519,430 21,227,841 9,742,551 8,053,884 42,509,103