EESC Conference Shaping the future of Core Network Corridors Thomas Bühler Chief of south line AlpTransit Gotthard AG
1 The Gotthard Base Tunnel Commissioning
Commissioning Gotthard Base Tunnel: 11th december 2016
- 48
2 Part 1
The project
4 The Gotthard Base Tunnel Freight corridor 1: Rotterdam−Genoa
5 The Gotthard Base Tunnel Development of transalpine goods traffic
6 The Gotthard Base Tunnel Development of transalpine goods traffic in Switzerland
Opening Gotthard road tunnel
7 The Gotthard Base Tunnel New railway lines in Switzerland
Lötschberg 2007 34.6 km 57 km Gotthard 2016
15.4 km Ceneri 2020
8 The Gotthard Base Tunnel Political acceptance
1992 A 64% majority acceptance of the proposal for the New Rail Link through the Alps (NRLA)
1994 Swiss electorate initiated the transfer policy voting in favour of the Alps Initiative
1995 Beginning of procedural approvement of the Gotthard project
1998 The Swiss electorate voted with 63.5% in favour of the phased NRLA and cleared the
way of financing
1999 Approvement of the Gotthard project
10 Part 2
Costs and financing requirements
11 The Gotthard Base Tunnel Allocation of Public Transport Financial Fund
NRLA (45%) Heavy road vehicle New Rail Link through the Alps tax (64%)
Rail 2000 Phase 1 and ZEB (44%) ZEB: Future Development of the Railway Infrastructure Fund for the Oil tax financing of (23%) public transport HSR (4%) European High-Speed Rail Network
Value added tax Noise mitigation (VAT) (13%) (7%)
12 The Gotthard Base Tunnel Development of final cost forecast and potential risks
Exchange rate: 1 Euro = 1.10 CHF
Potential risks Forecast final costs
13 Part 3
Project management
14 The Gotthard Base Tunnel Interest partners
15 Part 4
Project description and commissioning
16 The Gotthard Base Tunnel Overview
17 The Gotthard Base Tunnel Tunnel system of the Gotthard Base Tunnel
18 The Gotthard Base Tunnel A flat railway through the Alps
• Mixed operation • Maximum speed passenger trains: 250 km/h • Maximum speed goods trains: 160 km/h • Loaded vehicles: max. height 4.2 m
19 The Gotthard Base Tunnel Trains per day through the Gotthard (workdays)
Present
Future
daily + 80100 goods trains
20 The Gotthard Base Tunnel Journey times Zurich–Bellinzona / –Lugano / –Milan
21 The Gotthard Base Tunnel Completed tunnel equipment
22 The Gotthard Base Tunnel Commissioning
2’873 runs 111’000 km
Functionality and fulfilment of
safety
requirements
7 months
10.2015 1.6.2016
23 The Gotthard Base Tunnel Commissioning: Opening ceremony 1st June 2016
24 The Gotthard Base Tunnel Commissioning
- Simulation of normal passenger and goods traffic - Incident and 2’873 runs maintenance 111’000 km management
Functionality and fulfilment of
safety
requirements
7 months 6.5 months
10.2015 11.12.2016 1.6.2016
25 The Gotthard Base Tunnel Commissioning
Commissioning Gotthard Base Tunnel: 11th december 2016
- 48
Thank you for your attention!