2015 Telegraph Avenue Project
CEQA ANALYSIS
Final
City of Oakland Bureau of Planning 250 Frank H. Ogawa Plaza, Suite 2114 Oakland, CA 94612
June 2017
TABLE OF CONTENTS
GENERAL PROJECT INFORMATION ...... 1
I. EXECUTIVE SUMMARY ...... 3
II. BACKGROUND ...... 11
III. PURPOSE AND SUMMARY OF THIS CEQA DOCUMENT ...... 19
IV. PROJECT DESCRIPTION ...... 25
V. SUMMARY OF FINDINGS ...... 37
VI. CEQA CHECKLIST ...... 39 A. Aesthetics, Shadow, and Wind ...... 43 B. Air Quality ...... 53 C. Biological Resources ...... 72 D. Cultural Resources ...... 74 E. Geology, Soils, and Geohazards ...... 81 F. Greenhouse Gas Emissions and Climate Change ...... 85 G. Hazards and Hazardous Materials ...... 93 H. Hydrology and Water Quality ...... 102 I. Land Use, Plans, and Policies ...... 106 J. Noise ...... 108 K. Population and Housing ...... 121 L. Public Services, Parks, and Recreation Facilities ...... 123 M. Transportation and Circulation ...... 125 N. Utilities and Service Systems ...... 148
VII. REFERENCES ...... 153
i 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 TABLE OF CONTENTS FINAL
Attachments
A. Standard Conditions of Approval and Mitigation Monitoring and Reporting Program B. Criteria for Use of Addendum, per CEQA Guidelines Sections 15162, 15164, and 15168 C. Project Consistency with Community Plan or Zoning, per CEQA Guidelines Section 15183 D. Infill Performance Standards, per CEQA Guidelines Section 15183.3 E. Shadow Study F. Wind Tunnel Study G. Air Quality and Health Risk Screening Analysis H. Traffic Noise Outputs I. Proposed Project Traffic Counts
ii JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL TABLE OF CONTENTS
List of Tables
Table 1 Summary of Original (2004) Proposed Uptown Mixed-Use Development ...... 6 Table 2 Uptown Project Area Development Details ...... 7 Table 3 2015 Telegraph Avenue Project Development Details ...... 34 Table 4 Uptown Mixed Use Project Land Use Summary ...... 35 Table 5 City’s Thresholds of Significance ...... 56 Table 6 Summary of Land-Use Input Parameters for CalEEMod ...... 56 Table 7 Summary of Construction Input Parameters for CalEEMod ...... 57 Table 8 Estimated Unmitigated Construction Emissions (Pounds per Day) ...... 58 Table 9 Summary of Operation Input Parameters for CalEEMod ...... 59 Table 10 Estimated Unmitigated Operation Emissions ...... 61 Table 11 Annual Average Concentrations at MEIR during Project Construction ...... 62 Table 12 Health Risks at MEIR During Project Construction ...... 64 Table 13 Health Risks at MEIR from operation of an Emergency Generator at the Project Site ...... 65 Table 14 Summary of Cumulative Health Risks at the MEIR ...... 67 Table 15 Summary of Cumulative Health Risks to Future Project Receptors ...... 70 Table 16 Summary of Land-Use Input Parameters for CalEEMod ...... 86 Table 17 Summary of Project-Specific Assumptions for CalEEMod ...... 88 Table 18 Summary of Average GHG Emissions from Operation of the Project ...... 90 Table 19 Summary of Average GHG Emissions from Emergency Generator ...... 90 Table 20 Reference and Calculated Noise Levels from Construction Equipment, dBA ...... 112 Table 21 Ambient Noise, Project Traffic Volumes, and Predicted Traffic Noise ...... 115 Table 22 Vibration Source Levels for Construction Equipment ...... 118 Table 23 Vibration Criteria to Prevent Disturbance – RMS (Vdb) ...... 118 Table 24 Vibration Criteria to Prevent Damage to Structures ...... 119 Table 25 Daily Vehicle Miles Traveled Summary ...... 131 Table 26 Project Vehicle Trip Generation Summary ...... 133 Table 27 Trip Generation by Travel Mode ...... 134 Table 28 Existing and Existing plus Project Intersection LOS Summary ...... 141 Table 29 Bicycle Parking Requirements ...... 142 Table 30 Automobile Parking Code Requirements ...... 145 Table 31 Project Parking Supply and Demand ...... 146
iii 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 TABLE OF CONTENTS FINAL
List of Figures
Figure 1 Uptown Project Blocks ...... 4 Figure 2 Uptown Project Proposed and Developed Blocks ...... 5 Figure 3 Project Location ...... 26 Figure 4 Proposed Project: Telegraph Avenue Perspective ...... 28 Figure 5 Ground Floor Plan ...... 29 Figure 6 Typical Podium Residential Level Floor Plan ...... 30 Figure 7 Typical Tower Level Floor Plan ...... 31 Figure 8 Thomas L. Berkley Way (20th Street) Building Elevation ...... 32 Figure 9 Telegraph Avenue Building Elevation ...... 33 Figure 10 TAC Sources and Sensitive Receptors ...... 66 Figure 11 Trip Distribution ...... 136 Figure 12 Proposed Project Trip Assignment ...... 137 Figure 13 AM and PM Peak Hour Traffic Volumes ...... 138 Figure 14 Existing and Existing Plus Project ...... 140
iv GENERAL PROJECT INFORMATION
1. Project Title: 2015 Telegraph Avenue
2. Lead Agency Name and Address: City of Oakland Bureau of Planning 250 Frank H. Ogawa Plaza, Suite 2114 Oakland, CA 94612
3. Contact Person and Phone Number: Pete Vollmann, Planner IV City of Oakland, Bureau of Planning 250 Frank H. Ogawa Plaza, Suite 2114 Oakland, CA 94612 (510) 238-6167 [email protected]
4. Project Location: 2015 Telegraph Avenue and 2003 Telegraph Avenue (two parcels located between 21st Street and Thomas L. Berkley Way [20th Street]) Assessor’s Parcel Numbers: 008-0645-004 and 008-0645-005
5. Project Sponsor’s Name and Address: W/L 2003 Telegraph Owner VII, LLC Drew Haydel 644 Menlo Avenue, Suite 204 Menlo Park, CA 94025
6. Existing General Plan Designations: Central Business District
7. Existing Zoning: Central Business District Pedestrian Retail
8. Requested Permits: See Project Approvals in the Project Description, below.
1 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 GENERAL PROJECT INFORMATION FINAL
2 I. EXECUTIVE SUMMARY
The 2015 Telegraph Avenue Project applicant is proposing to redevelop two parcels within Block 7 of the Uptown Mixed Use Project area (Uptown area) with a mid-rise residential tower. The 2015 Telegraph Avenue Project (Proposed Project) would include construction of a 14-story mixed-use residential and retail building, including a parking garage on the northwest corner of Telegraph Avenue and Thomas L. Berkley Way (20th Street) on two parcels comprising an area of approximately 10,267 square feet (0.24-acre). The proposed building would have a maximum height of 160 feet and would be built above one level of subterranean parking.
The Proposed Project would include approximately 1,685 square feet of commercial space along Telegraph Avenue and Thomas L. Berkley Way (20th Street), and up to 114 residential units (76,558 square feet). Approximately 40 vehicle parking spaces are also proposed with a subterranean parking structure (6,486 square feet).
On February 18, 2004, the City certified the Final Uptown Mixed Use Project Environmental Impact Report (2004 Uptown EIR),1 pursuant to the California Environmental Quality Act (CEQA). The Uptown Mixed Use Project (Uptown Project) that was evaluated in that EIR included development on nine blocks (as shown in Figure 1) on 66 individual parcels, containing approximately 1,300 residential units, 1,050 student beds/faculty units, and approximately 43,000 square feet of commercial space. In addition to the 2004 Uptown EIR, the City of Oakland approved subsequent CEQA documents related to the Uptown Project, including three addenda to the Final EIR2,3,4 and a Supplemental EIR.5 Collectively these environmental review documents are referred to as the Uptown EIRs.
Various components of the Uptown Project have been constructed since it was approved in 2004 (Figure 2). Blocks 1, 2, 3, and 6 have all been developed with predominantly residential uses, including market rate and affordable housing. A 25,000-square-foot community park is on the western third of Block 4, with some site infrastructure installation currently underway on the eastern two-thirds. The eastern portion of Block 4 is planned for a residential tower and hotel. One parcel in the western portion of Block 7 (528 Thomas L. Berkley Way) is under development with construction of a 20-unit residential building. This development, in addition to the Proposed Project, would result in
1 City of Oakland, 2004. Uptown Mixed Use Project, Final EIR. Prepared by LSA Associates. February 18. 2 City of Oakland, 2006. Addendum for the Final EIR on the Uptown Mixed Use Project. Prepared by LSA Associates. March. 3 City of Oakland, 2007a. Environmental Review of Changes to Uptown Mixed Use Project. Prepared by LSA Associates. February 8. 4 City of Oakland, 2007b. Environmental Review of Changes to Uptown Mixed Use Project. November 12. 5 City of Oakland, 2012. 1800 San Pablo Avenue Project, Supplemental EIR. July.
3 23rd Street
and West Gr 22nd Street
9
21st Street
Paramount 7 C 21st Street B A 8 20th Street y (20th Street) y Wa Berkle T Thomas L. 3 elegraph Avenue
1 Street w
William Street 4 Broadway
e 2 N Proposed 19th Street
19th Street Street w Fox Theatre 6
San P
e 5 N Proposed
ab lo 18th Street
Ice Skating Facility 17th Street
17th Street
16th Street Latham Square
City Admin. 15th Street
Interstate 980
City Hall Plaza
Franklin Street
Webster Street
14th Street
Legend 13th Street Developed Blocks Preservation NN
Clay Street Park Jefferson Street
Martin Luther King Jr. ProposedCastro Street Project 0 125 250 500 Feet
Source: LSA 2007, Urban Planning Partners 2016 Figure 1 2015 Telegraph Avenue Project CEQA Analysis Uptown Mixed Use Project Boundaries 23rd Street
and West Gr 22nd Street
9
21st Street
Paramount 7 C 21st Street B A 8 20th Street y (20th Street) y Wa Berkle T Thomas L. 3 elegraph Avenue
1 Street w
William Street 4 Broadway
e 2 N Proposed 19th Street
19th Street Street w Fox Theatre 6
San P
e 5 N Proposed
ab lo 18th Street
Ice Skating Facility 17th Street
17th Street
16th Street Latham Square
City Admin. 15th Street
Interstate 980
City Hall Plaza
Franklin Street
Webster Street
14th Street
Legend
Legend Under Construction 13th Street N Developed Blocks Preservation N
Clay Street Park Jefferson Street
Martin Luther King Jr. ProposedCastro Street Project 0 125 250 500 Feet
Source: LSA 2007, Urban Planning Partners 2016 Figure 2 2015 Telegraph Avenue Project CEQA Analysis Uptown Project Proposed and Developed Blocks 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 I. EXECUTIVE SUMMARY FINAL
Block 7 being developed with approximately 300 fewer dwelling units than discussed in the 2012 Uptown Project Supplemental EIR. To date, neither site work or construction has been initiated on Blocks 5, 8, and 9. Table 1 shows the level and type of development associated with each parcel as evaluated in the 2004 Uptown EIR, and Table 2 presents more specific details about each block’s development.
TABLE 1 SUMMARY OF ORIGINAL (2004) PROPOSED UPTOWN MIXED-USE DEVELOPMENT
Parking Units Types Square Footage Block Stories Spaces (Residential) of Units (Commercial) 1 5 190 190 Apartments –
2 5 190 190 Apartments –
3 12 270 250 Apartments 7,500
4 5 294 225 Apartments 14,500
5 19 270 270 Condominiums –
6 5 145 145 Apartments – Student Beds/ 7 19-22 550 1000/50 11,000 Faculty Units 8 – – – – –
9 1 50 – – 10,000
1,000 Apartments
Total – 1,959 270 Condominiums 43,000 Student Beds/ 1,050 Faculty Units Note: Block 8 was identified as an alternative site for the relocation of the former Sears Auto Center previously located on Block 4. Source: LSA Associates Inc., 2003. Uptown Mixed Use Project EIR, September.
The Proposed Project would be developed on a 10,267-square-foot (0.24-acre) area on the western portion of Block 7, as shown in Figure 2, and would include a 14-story building with 114 residential units, 40 parking spaces, and 1,685 square feet of retail space.
The same applicant is also proposing the 2016 Telegraph Avenue Project within Block 8, which is across Telegraph Avenue from the 2015 Telegraph Avenue Project. The development proposed within Block 8 would include an 18-story building with 230 residential units, 78 parking spaces, and 4,622 square feet of retail space. These two projects are independent of each other, and the potential environmental impacts associated with the 2016 Telegraph Avenue Project are evaluated independent of this Proposed Project (2015 Telegraph) in a separate CEQA analysis document.
6 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL I. EXECUTIVE SUMMARY
TABLE 2 UPTOWN PROJECT AREA DEVELOPMENT DETAILS
2012 Current 2016 2004 Supplemental (Built To-Date Net Uptown Project EIR & Proposed) Change d Block 1 Residential 190 256 256 0 Commercial 0 0 0 0 Parking 190 224 224 0 Block 2 Residential 190 193 193 0 Commercial 0 0 0 0 Parking 190 137 137 0 Block 3 – Uptown Apartments Residential 250 216 216 0 Commercial 7,500 9,000 9,000 0 Parking 270 171 171 0 Block 4 – 1911 Telegraph Residential 225 380 380 0 Commercial 14,500 19,934 19,934 0 Community Space 14,500 25,000 25,000 0 Parking 294 296 296 0 Block 5 – 1800 San Pablo Avenue Residential 270 0 0 0 Commercial 0 120,000 120,000 0 Parking 270 309 309 0 Block 6 – Fox Courts Residential 145 80 80 0 Commercial 0 0 0 0 Parking 145 72 72 0 Block 7 2015 Telegraph (Proposed Project Site) Residentiala 434 434 114 -320 Commercial 11,000 11,000 1,685 -9,315 Parking 550 550 40 -510
7 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 I. EXECUTIVE SUMMARY FINAL
TABLE 2 UPTOWN PROJECT AREA DEVELOPMENT DETAILS
2012 Current 2016 2004 Supplemental (Built To-Date Net Uptown Project EIR & Proposed) Change d Great Western Power Company Residential 434 434 0 0 Commercial 11,000 11,000 13,000 +2,000 Parking 550 550 0 -510 528 Thomas L Berkley Way Residential 434 434 20 -414 Commercial 11,000 11,000 1,000 -10,000 Parking 550 550 20 -530 Total for Block 7b Residential 434 434 134 -300 Commercial 11,000 11,000 15,685 +4,685 Parking 550 550 60 -490 Block 8c – 2016 Telegraph
Residential – 0 230 +230 Commercial – 10,000 4,622 -5,378 Parking – 50 78 +28 Totals Residential 1,705 1,560 1,492 -67 Commercial 43,000 169,934 169,241 -693 Community Space 14,500 25,000 25,000 0 Parking 1,909 1,809 1,349 -460 Notes: Residential is represented in dwelling units. Commercial, community space, and parking are represented as square feet. Text in italics refers to proposed projects (not yet approved); text in bold refers to projects completed or under construction. a The 2004 Uptown EIR analyzed Block 7 as a student and faculty housing tower with 50 faculty dwelling units and 1,000 student beds. For the sake of this comparative analysis, 1,000 student beds are converted to 385 dwelling units using the Association of Bay Area Governments’ 2015 average of 2.6 occupants per dwelling units. b Block 7 was analyzed in the 2004 Uptown EIR as a student and faculty housing tower with 1,000 student beds and 550 faculty units. For the purpose of this analysis, 1,000 student beds is converted to 362 units based on an average occupancy per unit of 2.75 c In the 2004 Uptown EIR, Block 8 was identified as an alternative relocation site of the former Sears Auto Station previously located on Block 4. Block 9 was evaluated in the 2004 Uptown EIR as the preferred relocation site and was removed from the analysis in Addendum #2 in 2007. d Represents difference between the project considered in 2012 Supplemental EIR and current Proposed Project. Sources: Prior Uptown EIRs. Urban Planning Partners, 2016.
8 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL I. EXECUTIVE SUMMARY
The City is currently in initial negotiations with a developer for the development of Block 4 but a specific proposal has not yet been identified. Additional CEQA analysis for the Uptown Block 4 project will be undertaken separately, as appropriate.
The Uptown EIRs analyzed the environmental impacts of implementation of the Uptown Project. The analysis in the Uptown EIRs directly applies to the Proposed Project site, providing the basis for use of an addendum. Both separately and independently, qualified planning-level documents—specifically program-level EIRs—can also be used as a basis to provide additional CEQA clearance of the Proposed Project under specific CEQA provisions. These program-level EIRs include the City’s 1998 General Plan Land Use and Transportation Element (LUTE) EIR,6 General Plan Housing Element Update EIR7 and its 2014 Addendum,8 and the 2011 Central District Urban Renewal Plan EIR.9
6 City of Oakland, 1998. Land Use and Transportation Element, Final EIR. February. 7 City of Oakland, 2010. 2007–2015 Housing Element Update, Final EIR. 8 City of Oakland, 2014. 2015–2023 Housing Element Addendum to the 2010 Housing Element EIR. 9 Oakland Redevelopment Agency, 2012. Central District Urban Renewal Plan. Adopted June 12, 1969, as amended through April 3, 2012.
9 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 I. EXECUTIVE SUMMARY FINAL
10 II. BACKGROUND
Original 2004 Uptown EIR
The City certified the Uptown EIR in 2004 (2004 Uptown EIR). The project evaluated in the 2004 Uptown EIR included:
. Approximately 1,000 apartments and 270 condominiums . 1,050 student beds/faculty units . Approximately 43,000 square feet of commercial space . 1,959 parking spaces . A 25,000-square-foot public park
The 2004 Uptown EIR found no significant impacts related to land use; population, employment, and housing; utilities and infrastructure; and shade and shadow. Further, impacts to the following environmental topics were found to be reduced to a less-than- significant level with implementation of the recommended mitigation measures: hydrology and water quality, noise, hazards and hazardous materials, aesthetic resources, and wind. Significant and unavoidable effects related to transportation, air quality, and historic architectural resources were found, as described below.
Under the 2010 No Project and Plus Project scenarios, as well as the Year 2025 No Project and Year 2025 Plus Project conditions, the Frontage Road/West Grand Avenue intersection was projected to operate at level of service (LOS) F in the PM peak hour in the 2010 scenarios (and LOS F in the AM and PM peak hour 2025 scenarios), and implementation of the identified mitigation measure10 was found to be economically infeasible resulting in a significant and unavoidable impact.
With regard to air quality, the 2004 Uptown EIR concluded that the development would result in increased regional emissions of criteria air pollutants that exceed the Bay Area Air Quality Management District (BAAQMD) thresholds. However, the City recognized that, as an infill mixed-used development, the Uptown Project supports many smart growth principles, including transit, service, bicycle, and pedestrian measures but concluded that such elements would not reduce the potential impact to a less-than-significant level.
With regard to historic architectural resources, the 2004 Uptown EIR determined that full or partial demolition of the Great Western Power Company building would be a significant
10 Mitigation Measure TRANS-3 suggests widening the intersection to add a second exclusive left turn lane in the eastbound direction and an exclusive right turn lane in the westbound direction. The implementation of this mitigation measure was found to be economically infeasible as it would require additional support columns and the acquisition of a Caltrans right-of-way.
11 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 II. BACKGROUND FINAL
and unavoidable impact. Mitigation measures requiring documentation of the resource were recommended to minimize the impact, but not to a less-than-significant level.
Due to the Uptown Project’s potential for significant unavoidable impacts, a Statement of Overriding Considerations was adopted as part of the City’s approvals.
The 2004 Uptown EIR is hereby incorporated by reference. It can be obtained from the City of Oakland Bureau of Planning at 250 Frank H. Ogawa Plaza, Suite 2114, Oakland, California 94612, and viewed online at: http://www2.oaklandnet.com.
Previous Addenda and Supplemental EIR
Modifications to the project evaluated in the 2004 Uptown EIR were considered in several documents: (1) Addendum #1 to the Final EIR (for Block 3 and 4), completed in March 2006; (2) Addendum #2 to the Final EIR (for Block 4), dated February 8, 2007; (3) Addendum #3 to the Final EIR (for Block 4), dated November 12, 2007; and (4) the 2012 Supplemental EIR (for 1800 San Pablo), dated October 2012. As described below, each addendum determined that no further environmental review under CEQA was required in terms of a subsequent or supplemental EIR, pursuant to CEQA Guidelines Section 15162 (Subsequent EIRs) and Section 15164 (Supplements and Addenda to an EIR or Negative Declaration). A Supplemental EIR was prepared in 2012 as a project proposed on Block 5 was determined to represent a change to the development proposed for that block as anticipated in the 2004 Uptown EIR, per CEQA Guidelines Section 15162, as such change would require changes to the Uptown Project due to potential new significant environmental impacts related to roadway intersections. The addenda together with the 2004 Uptown EIR and the 2012 Supplemental EIR are collectively referred to as the Uptown EIRs. Development on Blocks 1, 2, 3, and 6 are now fully constructed and operational; Block 4 is partially completed; Block 7 is partially completed and partially under construction; and Blocks 5, 8, and 9 have not been redeveloped.
The 2006 Addendum #1 evaluated project refinements that included swapping the existing development proposals for Blocks 3 and 4; i.e., the development originally planned for Block 3 shifted to Block 4, and the development originally planned for Block 4 is shifted to Block 3. Up to 20,000 square feet of retail space, 255 residential units, and 343 parking spaces would be provided within one 23-story high-rise tower in the eastern two-thirds of Block 4 and a 25,000-square-foot community park in the western third of that block. Block 3 would contain a five-story building with 9,000 square feet of commercial space, 217 residential units, 133 parking spaces, and no community park as previously proposed. This change would have the same number of residential units and student/faculty units, an increase of 11,000 square feet in commercial space, and 146 fewer parking spaces. Small changes were also proposed to Blocks 1, 2, and 6. As described in Addendum #1, the proposed changes were determined to not result in additional environmental impacts beyond those identified in the 2004 Uptown EIR.
12 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL II. BACKGROUND
The 2007 Addendum #2 evaluated project refinements to Block 4, with minor changes to Blocks 1, 3, and 6 that would reduce the overall development density on the eastern side of Block 4 and the overall Uptown development. The height of the building on the east side of Block 4 was proposed to be 15 stories shorter than proposed in Addendum #1 and would involve a decrease of 55 residential units as well as a 183 fewer parking spaces. The 25,000-square-foot community park on the western third of the block would remain. Addendum #2 concluded these changes would not result in new or more significant impacts nor require new or significantly altered mitigation measures beyond those already identified in the 2004 Uptown EIR and Addendum #1.
The 2007 Addendum #3 evaluated project refinements for Block 4, including a 14-story building with 380 residential units, 19,934 square feet of retail space, and 296 parking space in the eastern two-thirds of the site, with the 25,000 square foot community park on the western third of the site. These changes would result in more development in the Uptown Project site over the project originally analyzed in the 2004 Uptown EIR; however, the total number of parking spaces would be reduced by 189 spaces. Addendum #3 concluded that these changes would not result in new or more significant impacts nor require new or significantly altered mitigation measures beyond those addressed in the 2004 Uptown EIR and Addendums #1 and #2.
The 2012 Supplemental EIR evaluated project refinements for Block 5 to include development of a three-story, above-grade building containing 120,000 square feet of commercial space and three sub-grade levels. The 2004 Uptown EIR assumed construction of a 19-story building containing 270 condominiums and 270 parking spaces on this Block 5 site. The scope of the 2012 Supplemental EIR was limited to transportation. The supplemental analysis found that the shift from residential to commercial would result in a number of new significant intersection impacts under both the Uptown Project and cumulative conditions beyond the findings of the 2004 Uptown EIR and associated addenda.
Applicable Previous CEQA Documents and Program EIRs
The analysis in the 2004 Uptown EIR, its three addenda, and the 2012 Supplemental EIR (collectively referred to as the Uptown EIRs) apply directly to the Proposed Project, providing the basis for use of an addendum. Additionally, a number of program EIRs collectively referred to as the “Program EIRs” are described below. The Uptown EIRs together with the Program EIRs are collectively referred to as “Previous CEQA Documents.” The Program EIRS are as follows:
. 1998 General Plan Land Use and Transportation Element (LUTE) EIR11 . 2010 General Plan Housing Element Update EIR12 and 2014 Addendum13
11 City of Oakland, 1998. 1998 Land Use and Transportation Element, Final EIR. February. 12 City of Oakland, 2010. 2007–2015 Housing Element Update, Final EIR.
13 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 II. BACKGROUND FINAL
. 2011 Central District Urban Renewal Plan EIR14
Each of these documents is hereby incorporated by reference. They can be obtained from the City of Oakland Bureau of Planning at 250 Frank H. Ogawa Plaza, Suite 3315, Oakland, California 94612, and viewed online at: http://www2.oaklandnet.com/government/o/PBN/ index.htm.
Land Use and Transportation Element EIR
The City certified the EIR for the General Plan LUTE in 1998 (1998 LUTE EIR). The LUTE identifies land use policies as change takes place and sets forth an action program to implement the land use policy through development controls and other strategies. The LUTE identifies five Showcase Districts targeted for continued growth and intended to promote a mixture of vibrant and unique districts with around‐the‐clock activity, continued expansion of job opportunities, and growing residential population. The Proposed Project is located within the Downtown Showcase District (Downtown).
As stated previously, the 1998 LUTE EIR is designated as a Program EIR under CEQA Guidelines Sections 15183 and 15183.3. As such, subsequent activities under the LUTE are subject to the requirements of these CEQA sections (see Chapter VI for further discussion).
Applicable mitigation measures identified in the 1998 LUTE EIR are largely the same as those identified in the other Program EIRs prepared after the 1998 LUTE EIR, either as mitigation measures or newer Standard Conditions of Approval (SCAs), the latter of which are described below.
Environmental Effects Summary The 1998 LUTE EIR determined that development consistent with the LUTE would result in impacts that would be reduced to a less-than-significant level with the implementation of mitigation measures and/or SCAs. Mitigation is required for the following resource topics: Aesthetics (views, architectural compatibility and shadow only); Air Quality (construction dust [including particulate matter less than 10 microns in diameter] and roadway emissions Downtown, odors); Cultural Resources (except as noted below as less than significant); Hazards and Hazardous Materials; Land Use (use and density incompatibilities); Noise (use and density incompatibilities, including from transit/transportation improvements); Population and Housing (induced growth, policy
13 City of Oakland, 2014. 2015–2023 Housing Element Addendum to the 2010 Housing Element EIR. 14 Oakland Redevelopment Agency, 2011a. Draft EIR for the Proposed Amendments to the Central District Urban Renewal Plan. March.
14 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL II. BACKGROUND
consistency/clean air plan); Public Services (except as noted below as significant);15 and Transportation and Circulation (intersection operations Downtown).
In the 1998 LUTE EIR, less than significant impacts were identified for the following resource topics: Aesthetics (scenic resources, light and glare); Air Quality (clean air plan consistency, roadway emissions in Downtown, energy use emissions, local/regional climate change); Biological Resources; Cultural Resources (historic context/settings, architectural compatibility); Energy; Geology and Seismicity; Hydrology and Water Quality; Land Use (conflicts in mixed use projects and near transit); Noise (roadway noise Downtown and citywide, multi-family near transportation/transit improvements); Population and Housing (exceeding household projections, housing displacement from industrial encroachment); Public Services (water demand, wastewater flows, stormwater quality, parks services); and Transportation and Circulation (transit demand). No impacts were identified for Agricultural and Forestry Resources or Mineral Resources.
Significant unavoidable impacts were identified for the following environmental resources in the 1998 LUTE EIR: Air Quality (regional emissions, roadway emissions Downtown); Noise (construction noise and vibration in Downtown); Public Services (fire safety); Transportation and Circulation (roadway segment operations); Wind Hazards; and Policy Consistency (clean air plan). Due to the potential for significant unavoidable impacts, a Statement of Overriding Considerations was adopted as part of the City’s approvals.
Oakland Housing Element Update EIR and 2014 Addendum
Since the 2004 Uptown EIR, the City has twice amended its General Plan to adopt updates to the Housing Element. The City certified a 2010 EIR plus a 2014 addendum (2010 Housing Element Update EIR) for the Housing Element. The General Plan identifies the City’s current and projected housing needs, and sets goals, policies, and programs to address those needs, as specified by the State of California Regional Housing Needs Allocation process. The Uptown Project contributes to the total number of housing units needed within Oakland to meet its needs allocation target. Applicable mitigation measures and SCAs identified in the 2010 Housing Element Update EIR are considered in the analysis of the residential components in this document. As stated previously, the 2010 Housing Element Update EIR was designated as a Program EIR under CEQA Guidelines Sections 15183 and 15183.3. As such, subsequent activities under the Housing Element that involve housing are subject to requirements under these CEQA sections (see Chapter III for further discussion).
Applicable mitigation measures and SCAs (also described in Chapter V) identified in the 2010 Housing Element Update EIR are considered in the analysis of this document.
15 The 1998 LUTE EIR addressed effects on solid waste demand and infrastructure facilities for water, sanitary sewer and stormwater drainage under Public Services.
15 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 II. BACKGROUND FINAL
Environmental Effects Summary The 2010 Housing Element Update EIR, including its Initial Study Checklist, determined that housing developed pursuant to the Housing Element would result in impacts that would be reduced to a less-than-significant level with the implementation of mitigation measures and/or SCAs (described in Attachment A). Mitigation is required for the following resource topics: Aesthetics (visual character/quality and light/glare only); Air Quality (except as noted below); Biological Resources; Cultural Resources; Geology and Soils; Greenhouse Gas Emissions; Hazards and Hazardous Materials (except as noted below, with no impacts regarding airport/airstrip hazards and emergency routes); Hydrology and Water Quality (except as noted below); Noise; Public Services (police and fire only); and Utilities and Service Systems (except as noted below).
Less-than-significant impacts were identified for the following resources in the Housing Element Update EIR: Hazards and Hazardous Materials (emergency plans and risk via transport/disposal); Hydrology and Water Quality (flooding/flood flows, and inundation by seiche, tsunami, or mudflow); Land Use (except for no impact regarding community division or conservation plans); Population and Housing (except for no impact regarding growth inducement); Public Services and Recreation (except as noted above, and no impact regarding new recreation facilities); and Utilities and Service Systems (landfill, solid waste, and energy capacity only, and no impact regarding energy standards). No impacts were identified for Agricultural and Forestry Resources or Mineral Resources.
Significant unavoidable impacts were identified for the following environmental resources in the Housing Element Update EIR: Air Quality (toxic air contaminant exposure) and Transportation and Circulation (traffic delays). Due to the potential for significant unavoidable impacts, a Statement of Overriding Considerations was adopted as part of the City’s approvals.
The 2011 Central District Urban Renewal Plan EIR
The Proposed Project site is located within the Central District Urban Renewal Plan (Renewal Plan) area, which generally encompasses the entire Downtown. It covers approximately 250 city blocks (828 acres) and is generally bounded by Interstate 980 (I- 980), Lake Merritt, 27th Street, and the Embarcadero. The Oakland City Council adopted the Renewal Plan for the project area in June 1969. The City prepared and certified an EIR for proposed amendments to the Central District Urban Renewal Plan in 2011 (2011 Renewal Plan EIR), and amended the plan up to April 3, 2012.,16 As stated previously, the
16 The 2011 Redevelopment Plan EIR addressed two amendments. A 17th Amendment to the Redevelopment Plan to: (1) extend the duration of the plan from 2012 to 2022 and extend the time period in which the then‐ Redevelopment Agency could receive tax increment funds from 2022 to 2032, as allowed by Senate Bill 211 (codified as Health and Safety Code Section 33333.10 et seq.); (2) increase the cap on the receipt of tax increment revenue to account for the proposed time extensions; and (3) renew the then‐Redevelopment Agency’s authority to use eminent domain in the project area. An 18th amendment further extended the plan
16 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL II. BACKGROUND
2011 Renewal Plan EIR was designated as a Program EIR under CEQA Guidelines Section 15180, and as such, subsequent activities are subject to the requirements of CEQA Guidelines Section 15168.
Applicable mitigation measures and SCAs (described in Chapter V) identified in the 2011 Renewal Plan EIR are considered in the analysis in this document.
Environmental Effects Summary
The 2011 Renewal Plan EIR determined that development facilitated by the proposed amendments would result in impacts that would be reduced to a less‐than‐significant level with the implementation of identified mitigation measures and/or SCAs (described in Chapter V). Mitigation would be required in the following topic areas as follows: Aesthetics (light/glare), Air Quality (except as noted below as significant), Biological Resources, Cultural Resources (except as noted below as significant), Geology and Soils, Greenhouse Gas Emissions, Hazards and Hazardous Materials, Hydrology and Water Quality, Noise (except as noted below as significant), Traffic and Circulation (except as noted below as significant), and Utilities and Service Systems.
Less‐than‐significant impacts were identified for the following resources in the 2011 Renewal Plan EIR: Land Use and Planning; Population, Employment, and Housing; Public Services and Recreation Facilities.
The 2011 Renewal Plan EIR determined that the proposed amendments would have significant unavoidable impacts on the following environmental resources: Air Quality; Cultural Resources; and Traffic and Circulation.17 Due to the potential for significant unavoidable impacts, a Statement of Overriding Considerations was adopted as part of the City’s approvals.
time limit from 2022 to 2023 and extended the time period in which the then‐Redevelopment Agency could receive tax increment funds from 2032 to 2033, as allowed by Health and Safety Code Section 33331.5. 17 The 2011 Redevelopment Plan EIR also identified significant and avoidable noise effects (specifically associated with the potential development of a new baseball stadium at Victory Court) and multimodal safety at at-grade rail crossings, both near the Oakland Estuary. These effects would not pertain to the Proposed Project given the distance and presumably minimal contribution of multimodal trips affecting these impacts.
17 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 II. BACKGROUND FINAL
18 III. PURPOSE AND SUMMARY OF THIS CEQA DOCUMENT
The purpose of this CEQA document is to evaluate the potential environmental effects of the Proposed Project and to determine whether such impacts were adequately covered under the Uptown EIRs or Program EIRs such that CEQA streamlining and/or tiering provisions and exemptions could be applied. The analysis herein incorporates information from the Uptown EIRs and Program EIRs. It includes a CEQA Checklist and supporting documentation to provide comprehensive review and public information for the basis of any determination.
Based on the environmental evaluation, and as the checklist demonstrates, the Proposed Project qualifies for several CEQA streamlining and/or tiering provisions and CEQA exemptions, each of which separately and independently provide a basis for CEQA compliance. These provisions and exemptions are discussed below.
Addendum
Public Resources Code Section 21166 and CEQA Guidelines Section 15164 (Subsequent EIRs, Supplements, and Addenda to an EIR or Negative Declaration) state that an addendum to a certified EIR is allowed when minor changes or additions are necessary and none of the conditions for preparation of a subsequent EIR or Negative Declaration pursuant to Sections 15162 and 15164 are satisfied. As discussed under Project Characteristics below, the Proposed Project represents a minor change to the Block 7 development from that analyzed in the Uptown EIRs. The Proposed Project does not represent a substantial change from what was described for Block 7 in the original Uptown Project; while the development proposed for Block 7 includes slightly different uses (residential as opposed to student/faculty unit), it involves construction of a shorter building than the one evaluated in the 2004 Uptown EIR. The Proposed Project therefore meets the requirements for an addendum (see Attachment B), and the analysis in the Uptown EIRs directly applies to the Proposed Project, providing the basis for the use of an addendum.
Community Plan Exemption
Public Resources Code Section 21083.3 and CEQA Guidelines Section 15183 (Projects Consistent with a Community Plan or Zoning) allow streamlined environmental review for projects that are “consistent with the development density established by existing zoning, community plan or general plan policies for which an EIR was certified, except as might be necessary to examine whether there are project‐specific significant effects which are peculiar to the project or its site.” Section 15183(c) specifies that “if an impact is not peculiar to the parcel or to the Proposed Project, has been addressed as a significant effect in the prior EIR, or can be substantially mitigated by the imposition of uniformly applied development policies or standards…, then an EIR need not be prepared for the
19 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 III. PURPOSE & SUMMARY OF THIS CEQA DOCUMENT FINAL
project solely on the basis of that impact.” The analysis in the Uptown EIRs and the Program EIRs—1998 LUTE EIR, 2011 Renewal Plan EIR, and 2010 Housing Element Update EIR—are applicable to the Proposed Project and are the Previous CEQA Documents providing the basis for use of the Community Plan Exemption.
Qualified Infill Exemption
Public Resources Code Section 21094.5 and CEQA Guidelines Section 15183.3 (Streamlining for Infill Projects) allow streamlining for certain qualified infill projects by limiting the topics subject to review at the project level, if the effects of infill development have been addressed in a planning level decision, or by uniformly applicable development policies. Infill projects are eligible if they (1) are located in an urban area on a site that either was previously developed or that adjoins existing qualified urban uses on at least 75 percent of the site’s perimeter; (2) satisfy the performance standards provided in CEQA Guidelines Appendix M; and (3) are consistent with the general use designation, density, building intensity, and applicable policies specified for the project area in either a sustainable communities strategy or an alternative planning strategy. No additional environmental review is required if the infill project would not cause any new specific effects or more significant effects, or if uniformly applicable development policies or standards would substantially mitigate such effects. The analysis in the Uptown EIRs and the Program EIRs—1998 LUTE EIR, 2011 Renewal Plan EIR, and (for only the residential components of the Proposed Project) 2010 Housing Element Update EIR are applicable to the Proposed Project and are the Previous CEQA Documents providing the basis for use of the Streamlining for Infill Projects under CEQA Guidelines Section 15183.3.
Program EIRs and Redevelopment Projects
CEQA Guidelines Section 15168 (Program EIRs) and Section 15180 (Redevelopment Projects) provide that the 2011 Renewal Plan EIR can be used as a Program EIR in support of streamlining and/or tiering provisions under CEQA. The 2011 Renewal Plan EIR is a Program EIR for streamlining and/or tiering provisions by CEQA Section 15168. The section defines the Program EIR as one prepared on a series of actions that can be characterized as one large project and that are related geographically and by other shared characteristics. Section 15168 continues that “subsequent activities in the program EIR must be examined in the light of the program EIR to determine whether an additional environmental document must be prepared.” If the agency finds that, pursuant to CEQA Guidelines Section 15162, no new effects could occur or no new mitigation measures would be required, the agency can approve the activity as being within the scope of the Proposed Project covered by the Program EIR, and no new environmental document would be required.
Further, CEQA Guidelines Section 15180 specifies that “if a certified Redevelopment Plan EIR is prepared, no subsequent EIRs are required for individual components of the
20 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL III. PURPOSE & SUMMARY OF THIS CEQA DOCUMENT
Redevelopment Plan unless a subsequent EIR or supplement to the EIR would be required by Section 15162 or 15163.”
Previous Mitigation Measures and Current Standard Conditions of Approval
The CEQA Checklist provided in Chapter VI of this document evaluates the potential environmental effects of the Proposed Project, and evaluates whether such impacts were adequately analyzed and addressed in the Uptown EIRs (as well as the Program EIRs previously described in Chapter II) to allow the CEQA streamlining provisions to apply. The analysis conducted incorporates by reference the information contained in the Uptown EIRs and each of the Program EIRs. The Proposed Project is legally required to incorporate and/or comply with any applicable requirements and mitigation measures identified in the Uptown EIRs. Therefore, the measures are herein assumed to be included as part of the Proposed Project, including those that have been modified to reflect the City’s current standard language and requirements, as discussed below.
SCA Application in General
The City of Oakland established SCAs and Uniformly Applied Development Standards after certification of the 2004 Uptown EIR and the 1998 LUTE EIR. The City also recently adopted an updated version of the SCAs from those included in the 2010 Housing Element Update EIR. The City’s SCAs are incorporated into and applied to new and changed projects as conditions of approval, regardless of a project’s environmental determination. The SCAs incorporate policies and standards from various adopted plans, policies, and ordinances (e.g., Oakland Planning Code and Municipal Code, Creek Protection Ordinance, Stormwater Water Management and Discharge Control Ordinance, Tree Protection Ordinance, Grading Regulations, National Pollutant Discharge Elimination System [NPDES] permit requirements, Housing Element-related mitigation measures, California Building Code and Uniform Fire Code). The implementation of these policies and standards has been found to substantially mitigate environmental effects. The SCAs are adopted as requirements of an individual project when it is approved by the City and are designed to, and would, substantially mitigate environmental effects.
Consistent with the requirements of CEQA, a determination of whether the Proposed Project would have a significant impact was made prior to the approval of the Proposed Project and, where applicable, SCAs and/or mitigation measures in the Program EIRs have been identified to mitigate those impacts. In some instances, exactly how the measures/ conditions identified will be achieved awaits completion of future studies, an approach that is legally permissible where measures/conditions are known to be feasible for the impact identified; where subsequent compliance with identified federal, state, or local regulations or requirements apply; where specific performance criteria is specified and required; and where the Proposed Project commits to developing measures that comply with the requirements and criteria identified.
21 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 III. PURPOSE & SUMMARY OF THIS CEQA DOCUMENT FINAL
SCA Application in this CEQA Document
Several SCAs would apply to the Proposed Project because of its characteristics and proposed changes to the Uptown Project; they are triggered by the City’s consideration of a discretionary action for the Proposed Project. Because the SCAs are mandatory City requirements, the impact analyses for new and modified projects assumes that all applicable SCAs will be imposed and implemented by the project in question.
Mitigation measures identified in the Uptown EIRs would apply to the Proposed Project and are listed in Attachment A to this document. Certain mitigation measures identified in the Uptown EIRs have since been adopted by the City as SCAs for all projects. Therefore, some of the previously identified mitigation measures have been modified, and in some cases wholly replaced, to reflect the City’s current standard language and requirements of its SCAs. All mitigation measures and applicable SCAs for the Proposed Project are listed in Attachment A to this document. Some of the SCAs identified in this document apply to the Proposed Project and were also identified in the 2011 Renewal Plan EIR, 2010 Oakland Housing Element Update EIR, and 1998 LUTE EIR prior to the City’s application of SCAs.
Aesthetics and Parking Analysis
CEQA Section 21099(d) states, “Aesthetic and parking impacts of a residential, mixed-use residential, or employment center project on an infill site located within a transit priority area shall not be considered significant impacts on the environment.”18 Accordingly, aesthetics and parking, for such projects, are no longer to be considered in determining if a project has the potential to result in significant environmental effects for projects that meet all three of the following criteria:
. The project is in a transit priority area.19 . The project is on an infill site.20 . The project is residential, mixed-use residential, or an employment center.21
The Proposed Project meets each of the above three criteria because it: (1) is located immediately adjacent to the 19th Street BART Station as well as the intersection of two or more major bus routes with a frequency of service interval of 15 minutes or less during
18 CEQA Section 21099(d)(1). 19 CEQA Section 21099(a)(7) defines a “transit priority area” as an area within one-half mile of an existing or planned major transit stop. A "major transit stop" is defined in CEQA Section 21064.3 as a rail transit station, a ferry terminal served by either a bus or rail transit service, or the intersection of two or more major bus routes with a frequency of service interval of 15 minutes or less during the morning and afternoon peak commute periods. 20 CEQA Section 21099(a)(4) defines an “infill site” as a lot located within an urban area that has been previously developed, or a vacant site where at least 75 percent of the perimeter of the site adjoins, or is separated only by an improved public right-of-way from, parcels that are developed with qualified urban uses. 21 CEQA Section 21099(a)(1) defines an “employment center” as a project located on property zoned for commercial uses with a floor area ratio (FAR) of no less than 0.75 and located within a transit priority area.
22 JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL III. PURPOSE & SUMMARY OF THIS CEQA DOCUMENT
the morning and afternoon peak commute periods; (2) is located on a project site that was previously developed and within a developed urban area of Oakland that includes commercial, office and residential uses; and (3) would be a residential project. Thus, this CEQA Analysis does not consider aesthetics and the adequacy of parking in determining the significance of project impacts under CEQA.
The City of Oakland recognizes that the public and decision makers nonetheless may be interested in information pertaining to the aesthetic effects and may desire that such information be provided as part of the environmental review process. Parking is not generally considered for CEQA purposes; however, this information is provided solely for informational purposes and is not used to determine the significance of the environmental impacts of the Proposed Project, pursuant to CEQA Section 21099 (d).
2015 Telegraph Avenue Project CEQA Compliance
The 2015 Telegraph Avenue Project separately and independently satisfies each of the CEQA streamlining provisions relied upon, as summarized below.
. Addendum. The analysis conducted in this document indicates that an addendum to the Uptown EIRs applies; therefore, this CEQA Analysis is considered to be the addendum. As discussed under Project Characteristics below, the Proposed Project represents a minor change to the Block 7 development from that analyzed under the project analyzed in the Uptown EIRs. The Proposed Project does not represent a substantial change from that described for Block 7 in the project analyzed in the Uptown EIRs; while the development proposed for Block 7 includes slightly different uses (residential as opposed to student/faculty unit) evaluated in the Uptown EIRs, it would involve construction of a building that is shorter than that evaluated in the 2004 Uptown EIR. None of the conditions described in CEQA Guidelines Section 15162 have occurred. The Proposed Project therefore meets the requirements for an addendum, as evidenced in Attachment B to this document.
. Community Plan Exemption. Based on the analysis conducted in this document, the Proposed Project also qualifies for a community plan exemption. The Proposed Project is permitted in the zoning district in which the site is located, and is consistent with the bulk, density, and land uses envisioned for the site. The analysis herein considers the analysis in the 2010 Oakland Housing Element Update EIR for the evaluation of the housing components of the Proposed Project, and further reconsiders the analysis in the 1998 LUTE EIR for the overall project. This CEQA Analysis concludes that the Proposed Project would not result in significant impacts that: (1) are peculiar to the project or project site; (2) were not identified as significant project‐level, cumulative, or off-site effects in the 2004 Uptown EIR; or (3) were previously identified as significant effects, but are determined to have a more severe adverse impact than discussed in the EIR. Findings regarding the Proposed Project’s consistency with the zoning are included as Attachment C to this document.
23 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS JUNE 2017 III. PURPOSE & SUMMARY OF THIS CEQA DOCUMENT FINAL
. Qualified Infill Exemption. The analysis indicates that the Proposed Project qualifies for a qualified infill exemption and is generally consistent with the required performance standards provided in CEQA Guidelines Appendix M, as evaluated in Table D‐1 in Attachment D to this document. This CEQA analysis concurs that the Proposed Project would not cause any new specific effects or more significant effects than previously identified in applicable planning-level EIRs and that uniformly applicable development policies or standards (SCAs) would substantially mitigate the Proposed Project’s effects. The Proposed Project is proposed on a previously developed site in an urbanized area of Oakland and is surrounded by urban uses. The Proposed Project is consistent with the land use, density, building intensity, and applicable policies for the site. The analysis herein considers the analysis in the Uptown EIRs, 1998 LUTE EIR, 2011 Renewal Plan EIR, and 2010 Housing Element Update EIR.
. Program EIRs and Redevelopment Plan. Overall, based on an examination of the analysis, findings, and conclusions of the Uptown EIRs, as well as those of the 1998 LUTE EIR, the 2011 Renewal Plan EIR and the Housing Element Update EIR (all of which are as summarized in the CEQA Checklist in Chapter II of this document), the potential environmental impacts associated with the Proposed Project have been adequately analyzed and covered in prior Program EIRs. Therefore, no further review or analysis under CEQA is required.
24 IV. PROJECT DESCRIPTION
This section describes the Proposed Project, which is evaluated in this CEQA analysis. The Proposed Project site and existing site conditions are described, the project details are discussed, and the required project approvals are presented.
Project Location
As shown in Figure 3, the Proposed Project site is at 2015 Telegraph Avenue and 2003 Telegraph Avenue, at the northwest corner of the Thomas L. Berkley Way (20th Street)/ Telegraph Avenue intersection. The Proposed Project site is 10,267 square feet (0.24-acre) and includes the following assessor’s parcel numbers (APNs): 008-0645-004 and 008- 0645-005.The site occupies the eastern portion of Block 7 of the Uptown Project (Figure 2). The Proposed Project site is bound by Telegraph Avenue to the east, 20th Street to the south, the Great Western Power Company building to the west, and a commercial building and surface parking area adjacent to 21st Street to the north.
Existing Site Conditions
The Proposed Project site is currently developed and includes a one-story retail structure (APN 008-0645-005) and surface parking area (APN 008-0645-004). Existing conditions for Block 7 are unchanged from those described in the Uptown EIRs, with the exception of a newly constructed 20-unit housing development west of the Great Western Power Company building.
Surrounding Context
The Proposed Project site is bordered by a commercial building and surface parking area to the north, Thomas L. Berkley Way (20th Street) to the south, Telegraph Avenue to the east, and the Great Western Power Company (now a rock climbing gym) to the west. It is within the Central Business District (CBD) under the Oakland General Plan and is zoned Central Business District Pedestrian Retail (CBD-P).
The City of Oakland General Plan land use designation for the Proposed Project site is CBD; this classification is intended to encourage, support, and enhance the downtown area as a high-density, mixed-use urban center of regional importance, and a primary hub for business, communications, office, government, high technology, retail, entertainment, and transportation.
Land uses in the Proposed Project vicinity include commercial, residential, and entertainment. The Great Western Power Company Gym, SEIU United Healthcare Workers, and Alameda County Social Services are located to the west. Fox Courts and the Uptown Apartments are residential uses located to the south, in addition to the Fox Theater,
25 BERKELEY
80
EMERYVILLE 24 Project Vicinity 23rd Street OAKLAND
ridge y B Ba 980 580
ALAMEDA
SAN 880 FRANCISCO Grand Avenue
22nd Street
Broadway 21st Street
Telegraph Avenue Avenue Telegraph Telegraph Project Site The Paramount Theater
Thomas L. Berkley Way (20th Street)
Henry J. 19th Street Kaiser BART Station Memorial Park
19th Street
San Pablo Avenue 18th Street
Martin Luther King Jr. Boulevard
Franklin Street
Webster Street 17th Street
Jefferson Street
Clay Street
N 0 125 250 500 Feet
Source: Google Earth Pro, 2016 Figure 3 2015 Telegraph Avenue Project CEQA Analysis Project Location JUNE 2017 2015 TELEGRAPH AVENUE PROJECT – CEQA ANALYSIS FINAL IV. PROJECT DESCRIPTION
Henry J. Kaiser Memorial Park, and the Oakland Ice Center. The Proposed Project site is located north of the growing entertainment area of Uptown, which includes bars, restaurants, and night clubs. Various proposed developments and projects currently under construction are located to the east of the Proposed Project site. These include 2100 Telegraph Avenue, 2016 Telegraph Avenue, and the Uptown Station, located at 1954 Telegraph Avenue.
The Proposed Project site is accessible from Interstate 980 (I-980), approximately 0.25 mile to the west; I-580, approximately 1 mile to the north; and Interstate 880 (I-880), approximately 1 mile south. The 19th Street Bay Area Rapid Transit District (BART) station is one block (0.1-mile) southeast of the site, and the 12th Street Oakland City Center BART station is approximately 0.5-mile south of the site, and multiple AC Transit bus lines are immediately adjacent to or within one block of the site.
Project Characteristics
The Proposed Project would be located within the southeastern portion of Block 7. The Proposed Project would include a 14-story (160-foot) building with a mezzanine, 114 residential units, 40 parking spaces, and 1,685 square feet of retail space. Retail space would be located on the ground floor. Approximately 6,486 square feet of parking would also be located on the ground floor of the structure, and the residential units would be on the 2nd through 14th floors. The 114 residential units would include 76 studios apartments, 24 one-bedroom apartments, and 14 two-bedroom apartments. Table 3 outlines the Proposed Project development details. Figure 4 shows the Proposed Project looking northwest from Telegraph Avenue and Thomas L. Berkley Way (20th Street). Figures 5, 6, and 7 show cross-sections of the Proposed Project, and Figures 8 and 9 show the conceptual elevation of the Proposed Project.
The Uptown EIRs evaluated the following developments on Block 7: (1) a 19-story student housing tower with 1,000 beds and 50 faculty units and 11,000 square feet of commercial; (2) a five-story, 550-space parking structure; and (3) a seven-story structure with 50 units of facility housing. While the Proposed Project site does not include the entirety of Block 7, and the Proposed Project proposes residential units as opposed to student/faculty housing, the Proposed Project has approximately 320 fewer dwelling units/students beds,22 510 fewer parking spaces, and 9,315 square feet less commercial square footage than that evaluated for Block 7 in the most recent 2012 Supplemental EIR. One parcel (528 Thomas L. Berkley Way) is currently under construction in the western portion of Block 7 and will contain a 20-unit residential building. With this development, Block 7 would have approximately 300 fewer dwelling units than discussed in the 2012 Supplemental EIR.
22 LSA Associates, 2006. Attachment F: Addendum for the Final Environment Impact Report on the Uptown Mixed Use Project. March.
27 Source: brick, 2016 Figure 4 2015 Telegraph Avenue Project CEQA Analysis Proposed Project: Telegraph Avenue Perspective
Parking Leasing
Lobby
Parking Avenue Telegraph Retail
Retail
Loading / Entry
N
*Not to Scale 20th Street
Source: brick, 2016 Figure 5 2015 Telegraph Avenue Project CEQA Analysis Ground Floor Plan
Courtyard 1 B1ed Bredoomroom Courtyard
MMechanicalechanical
Lounge / Fitness Lounge / Fitness TrTashrash enue 1 Bedroom v 1 Bedroom Electrical Electrical ele gr aph A T