E2048 V4 PEOPLE’S REPUBLIC OF & GANSU PROVINCIAL GOVERNMENTS THE WORLD BANK Public Disclosure Authorized Public Disclosure Authorized

WENCHUAN EARTHQUAKE RECOVERY PROJECT (WERP)

SICHUAN INFRASTRUCTURE SUB-PROJECTS (BATCH 2)

Public Disclosure Authorized VOLUME 2 YUANBA SUBPROJECT

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT SUMMARY REPORT

APRIL 2010

Public Disclosure Authorized DRAFT VERSION Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

TABLE OF CONTENTS

1 INTRODUCTION ...... 1 1.1 GENERAL...... 1 1.1.1 Wenchuan Earthquake Recovery Program (WERP) ...... 1 1.1.2 Project Organization...... 2 1.1.3 Batch 2 Infrastructure Sub-projects in Sichuan...... 3 1.2 PURPOSE AND SCOPE OF THIS REPORT ...... 5 1.3 LAYOUT OF THE SUMMARY EA ...... 5 2 BACKGROUND AND DESCRIPTION OF YUANBA SUBPROJECT...... 7 2.1 PROJECT BACKGROUND...... 7 2.2 COMPLIANCE WITH LOCAL PLANNING ...... 8 2.3 PROJECT COMPOSITION ...... 8 2.4 LINKAGE PROJECTS ...... 9 3 ALTERNATIVE ANALYSIS...... 11

3.1 WITH AND WITHOUT YUANBA SUBPROJECT...... 11 3.2 SOLID WASTE ...... 11 3.2.1 Project Location...... 12 3.2.2 Leachate Treatment ...... 13 3.2.3 Type of Solid Waste Transfer Station ...... 13 3.3 WTP...... 14 3.4 WWTP ...... 15 3.4.1 Project Location...... 15 3.4.2 Wastewater Treatment Process...... 15 3.4.3 SLUDGE TREATMENT PROCESS ...... 17 4 ENVIRONMENTAL BASELINE SITUATION ...... 19 4.1 PHYSICAL SETTINGS ...... 19 4.1.1 Geography ...... 19 4.1.2 Geology ...... 19 4.1.3 Climate ...... 20 4.1.4 Hydrology...... 21 4.1.5 Ecology...... 22 4.2 SOCIAL & ECONOMIC SETTINGS...... 22 4.2.1 Economic Development...... 22 4.2.2 Historic Relics and Tourism Resource...... 22 4.2.3 Wangjia Town and Hongyan Town...... 22 5 IMPACT ASSESSMENT & MITIGATION MEASURES...... 24 5.1 ANTICIPATED BENEFITS FROM YUANBA SUBPROJECT ...... 24 5.2 IMPACTS AND MITIGATION MEASURES RELATED TO PROJECT LOCATION...... 25 5.2.1 Land Acquisition & Resettlement ...... 25 5.2.2 Physical & Cultural Heritage...... 25 5.2.3 Ecological Resources ...... 25 5.2.4 Stability and Hydro-geological Conditions of Yuanba Landfill Site...... 25 5.3 SENSITIVE RECEPTORS...... 27 5.4 IMPACTS AND MITIGATION MEASURES RELATED TO CONSTRUCTION PERIOD ...... 28 5.4.1 General Impacts ...... 28 5.4.2 Specific Impacts...... 30 5.5 IMPACTS AND MITIGATION MEASURES RELATED TO OPERATION PERIOD...... 32 5.5.1 Solid Waste...... 32 5.5.2 Road...... 33 5.5.3 Water Supply...... 34 5.5.4 Wastewater Treatment ...... 35 6 RESETTLEMENT ACTION PLAN ...... 37

DRA consulting team i January 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) 6.1 PEOPLE AND NUMBER OF PEOPLE AFFECTED BY LAND ACQUISITION AND HOUSEHOLD DEMOLITION OF THIS PROJECT...... 37 6.2 COMPENSATION CRITERIA OF LAND ACQUISITION AND HOUSEHOLD DEMOLITION IN THIS PROJECT 37 6.3 BUDGET OF MIGRATION EXPENDITURE IN THIS PROJECT ...... 37 6.4 RESETTLEMENT OF LAND REQUISITION...... 38 6.5 RESETTLEMENT OF HOUSE DEMOLITION ...... 38 6.6 PUBLICATION, PUBLIC CONSULTATION AND MONITORING...... 38 7 SOCIAL ASSESSMENT ...... 39 7.1 INTRODUCTION OF THE RESETTLEMENT AREA...... 39 7.2 RESETTLEMENT HOUSE CONSTRUCTION AND ALLOCATION...... 39 7.3 RESETTLEMENT HOUSEHOLDS’ WILLINGNESS AND ABILITIES ...... 39 7.4 LAND ACQUISITION AND COMPENSATION STANDARD ...... 40 7.5 HOUSE DEMOLITION, RELOCATION AND SETTLEMENT...... 40 7.6 PUBLIC PARTICIPATION...... 40 8 PUBLIC CONSULTATION & INFORMATION DISCLOSURE ...... 41 8.1 PUBLIC CONSULTATION...... 41 8.2 INFORMATION DISCLOSURE ...... 43 9 ENVIRONMENTAL MANAGEMENT PLAN ...... 44 9.1 ORGANIZATION...... 44 9.2 ENVIRONMENTAL MONITORING PLAN ...... 44 9.2.1 Construction Period...... 44 9.2.2 Construction Period...... 45 9.3 CAPACITY BUILDING ...... 46 9.4 BUDGET ESTIMATE AND SOURCE OF FUNDING ...... 47 APPENDIX 1 BIBLIOGRAPHY ...... 1 APPENDIX 2 SUBMITTED DOCUMENTS RELATED TO DAM SAFETY OF YUANBA WTP COMPONENT...... 2 APPENDIX 3 ENVIRONMENTAL STANDARDS ...... 1 ENVIRONMENTAL AIR QUALITY STANDARDS ...... 1 ENVIRONMENTAL QUALITY STANDARDS FOR SURFACE WATER...... 1 ENVIRONMENTAL QUALITY STANDARDS FOR NOISE ...... 2 WASTE WATER ...... 3 AIR EMISSION...... 5 NOISE ...... 6 APPENDIX 4 FIGURES AND DRAWINGS...... 1

DRA consulting team ii January 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

LIST OF TABLES

Table 1-1: Project Implementing Unit of Batch 2 Urban Infrastructure Sub-projects in Sichuan under WERP ...... 3 Table 1-2: List of Sub-project Cost...... 4 Table 2-1: Detailed Project Composition of Yuanba Subproject...... 8 Table 2-2: Project Linkage for Yuanba Subproject ...... 9 Table 3-1: Alternative Analysis for the Location of Yuanba Landfill Site ...... 12 Table 3-2: Alternative Analysis for Leachate Treatment of Yuanba Landfill Site...... 13 Table 3-3: Comparison of Different Modes of Solid Waste Transfer System ...... 13 Table 3-4: Comparison of Two Water Treatment Processes...... 14 Table 3-5: Comparison of Proposed Locations for Wangjia Town WWTP...... 15 Table 3-6: Comparison of Wastewater Treatment Process...... 15 Table 3-7: Comparison of Sludge Treatment Process...... 17 Table 3-8: Comparison of Sludge Mechanical Treatment Process ...... 18 Table 4-1: Socio-economic conditions of Wangjia Town and Hongyan Town...... 23 Table 5-1: Pollution Abatement Assessment ...... 24 Table 5-2: List of Sensitive Receptors for Yuanba Subprojects ...... 27 Table 5-3: Summary of general environmental impacts and mitigation measures during construction of Yuanba Subproject...... 29 Table 5-4: Earthworks Balance for the Construction of Yuanba Subproject ...... 30 Table 5-5: Characteristics of Xinhua Reservoir ...... 35 Table 8-1: Summary of Public Consultation for Yuanba Subproject...... 41 Table 8-2: Summary of Information Disclosure for Yuanba Subproject...... 43 Table 9-1: Monitoring Program during Construction...... 44 Table 9-2: Monitoring Program during Operation ...... 45 Table 9-3: Budget of EMP for Solid Waste Component of Yuanba Subproject during Construction ...... 47 Table 9-4: Budget of EMP for Solid Waste Component of Yuanba Subproject during Operation.. 47 Table 9-5: Budget of EMP for Road Component of Yuanba Subproject during Construction...... 48 Table 9-6: Budget of EMP for Road Component of Yuanba Subproject during Operation ...... 48 Table 9-7: Budget of EMP for Water Supply Component of Yuanba Subproject druring Construction...... 48 Table 9-8: Budget of EMP for Water Supply Component of Yuanba Subproject druring Operation ...... 49 Table 9-9: Budget of EMP for Wastewater Component of Yuanba Subproject during Construction ...... 50

LIST OF FIGURES

Figure 1-1: Institutional Organization of WERP ...... 2 Figure 1-2: Locations of Project Counties/Cities under Infrastructure Component (Batch 2) in Sichuan ...... 3 Figure 4-1: Project Location ...... 19

DRA consulting team iii January 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

ABBREVIATIONS, ACRONYMS AND UNITS CMSC Construction Management and Supervision Cost CSC Construction Supervision Company CSE Construction Supervision Engineer CSEE Construction Supervision Environmental Engineer CSEMP Construction Site Environmental Management Plan DI Design Institute DRA Design Review and Advisory (services) EIA Environmental Impact Assessment EMC Environmental Management Coordinator EMP Environmental Management Plan EMS Environmental Monitoring Station EPB Environmental Protection Bureau ESU Environmental Supervision Unit IA Implementing Agency NCP Nuisance Control Plan PIU Project Implementation Unit PMC Project Management Cost PMO Project Management Office PPE Personal Protective Equipment PRC The People’s Republic of China RAP Resettlement Action Plan SA Social Assessment SE Supervision Engineer SEPA State Environmental Protection Administration SEPB Sichuan Provincial Environmental Protection Bureau TAC Technical Assistance Cost ToR Terms of Reference WB World Bank WERP Wenchuan Earthquake Recovery Project WS Water Supply WTP Water Treatment Plant WW Wastewater WWTP Wastewater Treatment Plant

DRA consulting team iv January 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) MSW Municipal Solid Waste

DRA consulting team v January 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

CURRENCIES & OTHER UNITS mu Area Unit (1mu0.0667 ha) RMB Chinese Yuan (Renminbi) USD United States Dollar Conversion rate: 1 USD6.8 RMB

CHEMICAL ABBREVIATIONS

BOD5 Biochemical Oxygen Demand (5 days) COD Chemical Oxygen Demand

CODMn Permanganate Index

NH3-N Ammonia Nitrogen SS Suspended Solids TP Total Phosphorus TSS Total Suspended Solids TSP Total Suspended Particulates

DRA consulting team vi January 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Introduction

GENERAL

Wenchuan Earthquake Recovery Program (WERP)

On May 12, 2008 at 2:28pm, an earthquake of magnitude 8.0 Richter and 11.0 degrees in seismic intensity struck the southwestern part of China, centered in in Sichuan province. As a result of this earthquake and its more than 20,000 significant aftershocks, more than 69,000 people have died, 374,000 have been injured, and 18,000 remain missing. Losses include: 34,000 km of highway destroyed; 1,263 reservoirs damaged; 7,444 schools and 11,028 hospitals and clinics collapsed, and 5.5 million rural houses and 860,000 urban houses destroyed or significantly damaged. Direct losses are estimated at RMB 844 billion (USD 123 billion). Approximately 34 million people live in the affected area, with almost 20 million in the severely affected area.

In response to the earthquake, the World Bank has lend USD 710 million of IBRD financing to the most highly affected provinces of Sichuan and Gansu for post-earthquake reconstruction, that is, the Wenchuan Earthquake Reconstruction Program (WERP).

The expected outcomes of the project are to restore and enhance access to essential public infrastructure and services (e.g., water supply, wastewater and drainage, solid waste, roads) and core health services in affected counties in Sichuan and Gansu prioritizing, where possible, the needs of the poor and/or newly vulnerable arising from the earthquake. In addition, the expected outcomes include the rehabilitation of education facilities and restoration of access to public education in project counties in Gansu. In both provinces, sub-projects will be designed to reduce the vulnerability of the services to seismic and flood hazards.

The proposed WERP is designed to comprise two parts: z Part 1- Sichuan Recovery Program (Bank loan US$510million)

- Infrastructure (Bank loan USD 432.4 million). This component will finance civil works and goods required for the reconstruction and appropriate expansion of infrastructure, in approximately 16 counties in the five municipalities of , , , and Ya’an. In view of the project preparation progress, the component is organised to be implemented in two batches: Batch 1 and Batch 2.

- Health (Bank loan USD 57.6 mil lion) component will finance civil works and goods required for the reconstruction and appropriate expansion of health services, in about 19 counties in the seven municipalities of Mianyang, Guangyuan, Bazhong, Nanchong, Ya’an, and .

- Project support (Bank loan USD 20.0million) will finance training, capacity building and engineering costs of sub-projects. z Part 2 - Gansu Recovery Program (Bank loan US$200.0million)

This will finance infrastructure, health and education sub-projects in 7 counties in Longnan Municipality with a focus on Cheng, Hui, and Xihe Counties.

- Infrastructure (Bank loan USD 130.3 million). This component will finance civil works and goods required for the reconstruction and appropriate expansion of infrastructure.

- Health (Bank loan USD 32.3 million) will finance civil works and goods required for the reconstruction and appropriate expansion of health services.

Sichuan PPMO 1 April 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) - Education (Bank loan USD 33.4 million) will finance facilities and equipment for the reconstruction and appropriate expansion of primary, secondary, and vocational/technical schools.

- Project support (Bank loan USD 4.0 million) will finance training, capacity Building and engineering costs of sub-projects.

Project Organization

Due to the project urgency, a strong project leading and technical support system is required at all the national, provincial/municipal and county levels to guarantee the quality of project implementation.

At the national level, the National Development and Reform Commission is responsible for the approval of Investment Application Report, and the Ministry of Finance is responsible for the signing of Loan Agreement, the supervision of loan use and the loan repayment.

For the overall project coordination of all the involved Project Implementation Units (PIUs) at the project level, there are totally three project management offices organized under the leadership of the provincial DRC, the provincial financial bureau and the provincial department of construction in the two project provinces (Sichuan and Gansu), respectively:

- The Urban Construction Project Management Office (UCPPMO) and the Health Project Management Office (HPPMO) for Sichuan Components; and

- The Longnan Municipal Project Management Office (LMPMO) for Gansu components.

The general institutional organization of the project implementation can be summarized in the following chart.

FIGURE 0-1: INSTITUTIONAL ORGANIZATION OF WERP

Government of World Bank P.R.C.

Sichuan Provincial Government Gansu Provincial Government

Longnan Municipal Government

Sichuan Urban Construction Sichuan Health PPMO Longnan Municipal PMO PPMO

7 7 19 7 7 5 16 1.30 5760 3230 3340 4.324 Infrastructure Health Projects from 19 Health Projects from Education Projects Infrastructure Projects from 16 Projects from 7 counties /districts of 7 7 counties of from 7 counties of counties/districts of 5 counties of Longnan municipalities Longnan municipality Longnan municipality municipalities (432 .4million) municipality (57.6million) (32.3million) (33.4million) (130.3million)

Sichuan PPMO 2 April 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) At local level, the Project Implementation Units (PIUs) are specifically responsible for development, implementation, operation and management of the subprojects. For the Batch 2 urban infrastructure sub-projects in Sichuan Province under WERP, the project implementation units are all the planning and consruction bureaus at the local level.

Batch 2 Infrastructure Sub-projects in Sichuan

The screening and identification of Batch 2 infrastructure sub-projects under Sichuan Recovery Program was started since June 2009 by the Sichuan urban construction PPMO, and the proposed sub-projects have been confirmed by the World Bank with Sichuan Finance Bureau and Sichuan DRC on August 2009.

FIGURE 0-2: LOCATIONS OF PROJECT COUNTIES/CITIES UNDER INFRASTRUCTURE COMPONENT (BATCH 2) IN SICHUAN

Legend NO. PROJECT COUNTY/ 1 FUCHENG DIS., MIANYANG YOUXIAN DIS., MIANYANG 2 (ALSO FOR SONGYA TOWN) 3 , MIANYANG 4 , MIANYANG 5 6 , MIANYANG 7 CHAOTIAN DIS., GUANGYUAN 8 , GUANGYUAN 9 , GUANGYUAN 10 YUANBA DIS., GUANGYUAN 11 CITY, NANCHONG 12 , BAZHONG 13 , YA’AN 14 , YA’AN 15 LUSHAN COUNTY, YA’AN

Sichuan PPMO 3 April 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) All the sub-projects are detailed in the table below. The total estimated cost of the second batch infrastructure subprojects is 2.22billion RMB, of which potentially USD 260million could be financed by the World Bank.

TABLE 0-1: LIST OF SUB-PROJECT COST

SUB-PROJECT COST WB LOAN PROJECT NO. SUB-PROJECT TYPE COUNTY/DISTRICT (MIL. RMB) (MIL. USD)

MIANYANG MUNICIPALITY 1054.95 109.90

SC2-MY-FC FUCHENG DIS. WTP, WWTP, ROADS, & DRAINAGE NETWORK 286.49 30.15

SC2-MY-YX YOUXIAN DIS. ROADS, DRAINAGE NETWORK AND WWTP 212.78 21.29

SONGYA TOWN, SC2-MY-SY EMBANKMENT 114.94 9.00 YOUXIAN DIS.

SC2-MY-ST SANTAI COUNTY ROADS, DRAINAGE NETWORK AND WTP 232.98 23.12

YANTING SC2-MY-YT ROADS, DRAINAGE NETWORK AND EMBANKMENT 108.37 10.18 COUNTY

SC2-MY-ZT ZITONG COUNTY ROADS, DRAINAGE NETWORK, WTP AND BRIDGE 214.33 25.18

GUANGYUAN MUNICIPALITY 644.92 81.60

ROADS, DRAINAGE NETWORK, WWTP, BRIDGE, SC2-GY-CT CHAOTIAN DIS. BUS STATION PLATFORM AND BUS CONTROL 99.97 14.44 CENTRE WANGCANG BRIDGES, ROADS, DRAINAGE NETWORK, AND SC2-GY-WC 207.93 25.92 COUNTY EMBANKMENT CANGXI SC2-GY-CX BRIDGE REHABILITATION AND CONSTRUCTION 139.47 13.74 COUNTY

SC2-GY-LZ LIZHOU DIS. EMBANKMENT 61.65 8.25

LANDFILL SITE, WWTP, WTP, WATER SUPPLY SC2-GY-YB YUANBA DIS. 135.91 19.25 NETWORK, ROADS AND DRAINAGE NETWORK

NANCHONG MUNICIPALITY 217.68 26.47

SC2-NC-LZ LANGZHONG CITY BRIDGE 217.68 26.47

BAZHONG MUNICIPALITY 57.94 6.94

SC2-BZ-NJ NANJIANG COUNTY BRIDGES AND EMBANKMENT 57.94 6.94

YA’AN MUNICIPALITY 246.29 35.29

SC2-YA-BX BAOXING COUNTY ROADS, WS & DRAINAGE NETWORK, BRIDGE 69.91 9.81

SC2-YA-SM SHIMIAN COUNTY WTP, BRIDGE, ROADS AND DRAINAGE NETWORK 113.55 16.55

BRIDGE, WS FACILITIES, ROAD & DRAINAGE SC2-YA-LS LUSHAN COUNTY 62.83 8.93 NETWORK

TOTAL 2221.78 260.20 Note: In this report, we will refer to WERP as “the Project” and to the local sub-projects organized by city/county as the “sub-project”. We will refer to the sectoral components of each sub-project as “components” (i.e. Roads and Bridges, Water Supply, Drainage Network, Solid Waste Management, and River Rehabilitation).

Sichuan PPMO 4 April 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) PURPOSE AND SCOPE OF THIS REPORT

In accordance with PRC National Regulations and the World Bank Operational Policy 4.01 related to Environmental Assessment, three of the subprojects under Batch 2, WERP, including Cangxi, Yuanba and Langzhong, fall under the Category A projects. Therefore, for the Batch 2 projects, the following EIA documentations are required to meet the World Bank requirements. z Volume 1: Environmental and Social Impact Assessment Summary for Cangxi Subproject z Volume 2: Environmental and Social Impact Assessment Summary for Yuanba Subproject z Volume 3: Environmental and Social Impact Assessment Summary for Langzhong Subproject z EIAs & EMPs for individual subprojects/components (in Chinese only)

In order to comply with PRC Regulation “Strengthening Environmental Impact Assessment (EIA) Management for the Construction Project Loaned by International Finance Organization” of June 21, 1993 and with World Bank Safeguards Operational Policy, the local PIUs have commissioned the local EIA consultants to prepare the Chinese EIAs for individual subprojects/components.

The DRA consulting team funded by the French Grant, which consists of Bureau Veritas, Sogreah and AREP, is responsible for preparing the above Volum 1-3 (only in English) based on the individual EIAs and collected project-related information.

Of the ten World Bank safeguard policies, Environmental Assessment (OP/BP/GP4.01) and Involuntary Resettlement (OP4.12) are applied in the EA of Batch 2, WERP. In addition, the proposed Yuanba Subproject also triggers the operational procedure of Dam Safety (OP 4.37).

LAYOUT OF THE SUMMARY EA

The Summary EA is designed to cover the following topics:

Chapter 2 Background and Description of Yuanba Subproject Provide an overview of the project context and then describe in details the Yuanba subproject.

Chapter 3 Alternative Analysis Provide the detailed information on the alternative analysis carried out during the project preparation, including the “with and without project” analysis.

Chapter 4 Environmental Baseline Situation Provide a general summary of the environmental baseline conditions within Yuanba Municipality.

Chapter 5 Impact Assessment & Mitigation Measures Present in a summarized format the different impacts associated with the project together with a series of mitigation measures.

Chapter 6 Resettlement Action Plan Present in a summarized format the resettlement action plan related to the proposed Yuanba subproject.

Sichuan PPMO 5 April 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Chapter 7 Social Assessment Present in a summarized format the key findings and conclusions of the social assessment implemented for the proposed Yuanba subproject.

Chapter 8 Public Consultation & Disclosure Summarize the results of the two public consultations and the different measures related to information disclosure.

Chapter 9 Environmental Management Plan Summarize the major elements of the EMP for Yuanba subproject.

The report is accompanied by a series of Annexes covering the following topics:

APPENDIX 1 Bibliography

APPENDIX 2 Submitted Documents Related to Dam Safety of Yuanba WTP Component

APPENDIX 3 Environmental Standards

APPENDIX 3 Figures and Drawings

Sichuan PPMO 6 April 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Background and Description of Yuanba Subproject

The Chinese EIA documentation for Yuanba subproject under Batch 2, WERP, consists of two EIA reports (respectively for the solid waste and road components) and two EIA forms (respectively for the wastewater and water supply components), which are all prepared by the Environment College of the South-West Jiaotong University (qualified as a Class B EIA consultants in China). The first draft was submitted to Sichuan urban construction PPMO on Nov. 23rd 2009, and the review comment by the DRA consulting team has been delivered to the domestic EIA consultants on Nov. 28 2009. Based on the comments and further project information, the EIA documents of Yuanba subproject have been modified twice and the two revisions were again submitted to Sichuan urban construction PPMO respectively on Dec. 7th and Dec. 11th. Among others, the latest version has been used as the key reference for this summary EIA.

PROJECT BACKGROUND

Yuanba District is one of the highly affected areas in the Wenchuan Earthquake with severe loss, especially in terms of local water supply and drainage facilities, urban roads and bridges, environmental sanitation facilities and mass transit facilities.

For example, Wangjia Town and Hongyan Town respectively in the southeast and west of Yuanba District have greatly suffered from the earthquake with great impacts on the normal operation of the towns and the daily lives of local residents. In Wangjia Town, there are 3323 rural households damaged to different extents, 443 rural houses collapsed or turning into dangerous houses, nearly 80km road damaged with road foundation subsidence and road surface cracking and 25 bridges/culverts collapsed. Even worse, the earthquake has laid almost the whole Hongyan Town flat. According to the statistic data, in Hongyan Town, the earthquake has caused the collapse of 3650m2 local office buildings and 11 rural houses, the serious damage of 408 rural houses and the partial collapse of 196 rural houses. The local power, traffic, communication and hydraulic facilities also suffered greatly from the disaster. The direct and indirect economic loss of Hongyan Town in the earthquake is up to 290million yuan.

On the other hand, the infrastructure of Yuanba District falls short as the local urban construction goes on. For example, currently the whole Yuanba District has only one simple dump site and two solid waste transfer stations for the collection, transportation and disposal of all the domestic solid waste from the urban area of the district. In addition, these facilities have all been damaged to some extent in the earthquake and remain unable for normal use. As for Wangjia Town and Hongyan Town, the infrastructure conditions are even poor: The existing WTPs are poorly equipped with only the simple settling tank, and since the current water treatment capacity could not meet the water demand of the towns, most of their residents have to rely on the groundwater from their own wells; the water distribution network has been worn down by the years without repair, it goes without saying the earthquake damage; there is no wastewater treatment facilities in the two towns, and all the domestic wastewater is randomly discharged without treatment which has resulted in the deterioration of local surface water and groundwater quality.

Generally speaking, the low road grade, poor drainage and serious damage of roads, bridges and culverts have badly impacted the daily lives of local residents and the progress of post-earthquake reconstruction.

DRA CONSULTING TEAM 7 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) In this context, the reconstruction of damaged or absent water supply and wastewater facilities, solid waste collection and disposal facilities, roads and bridges for the urban areas and the towns of Yuanba District has been proposed under this subproject in order to lay a solid foundation for the implementation of other post- earthquake reconstruction projects in Yuanba District.

COMPLIANCE WITH LOCAL PLANNING

As proposed in the “Post-earthquake Reconstruction Implementation Plan for Yuanba District of Guangyuan Municipality”, the post-earthquake reconstruction of Yuanba District will cover 22km of urban roads, 5 bridges, 14 bus stations, the WTPs with treatment capacity of 25000m3/d, 76km of water supply network, one LNG delivering station, 15km of LNG network, the WWTPs with treatment capacity of 15000m3/d, 56km of sewage network, and 80t/d solid waste treatment capacity with the transfer system. All the proposed components of Yuanba subproject have been included in the reconstruction plan; at the same time, they are also compliant with the “Urban Master Plan for Yuanba District of Guangyuan Municipality”.

PROJECT COMPOSITION

The proposed Yuanba subproject consists of four components in the urban area, Wangjia Town and Hongyan Town of Yuanba District, namely solid waste, road, water supply and wastewater treatment. The project details are presented in the table below.

TABLE 0-1: DETAILED PROJECT COMPOSITION OF YUANBA SUBPROJECT

Estimated Name of Cost Yuanba urban area Wangjia Town Hongyan Town Component (million RMB) One sanitary landfill site Capacity: 77t/d Component included: 1) Landfill area, including refuse dam, seepage control system, leachate collection and drainage system, landfill gas exhaust system, flood intercepting trench, environmental monitoring system Solid waste and site closure system; / / 45.57 2) Office building, gard room and metering room, service rack, garage and maintenance room; 3) Leachate treatment system; Reconstruction of one solid waste transfer station Capacity: 40t/d

7 Roads 7 Roads Total length: 2808m Total length: 2725m 4 Roads Width: 8m~12m Width: 4m~16m Total length: 2113m Location: Oujiahe area Associated works: Width: 12m~14m Associated works: Road Associated works: Sewer of Water supply pipe of 64.96 2839m (DN300~DN500) and 2995m, sewer of Sewer of 2105m and drainage pipe of 2924m 2994m and drainage drainage pipe of (DN500~DN600). pipe of 3000m 2185m.

DRA CONSULTING TEAM 8 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Estimated Name of Cost Yuanba urban area Wangjia Town Hongyan Town Component (million RMB) One new WTP One new WTP Short-term capacity: Short-term capacity: 900m3/d 250m3/d Long-term capacity: Long-term capacity: 2000m3/d 400m3/d 10.02 Population served: Population served: (Wangjia 4000 300 Town) + Process: Integrated Process: Integrated Water 3.76 / water treatment water treatment Supply (Hongyan equipment equipment Town) Raw water pipe: 12400m (D219X4.5) Clean water transmission pipe: 2600m (D273X6)

One new WWTP One new WWTP Short-term capacity: Short-term capacity: 8.60 500m3/d 120m3/d (Wangjia Long-term capacity: Long-term capacity: Town) Wastewater / 1300m3/d 240m3/d +3.00 Process: A/A/O Process: A/A/O (Hongyan Standard effluent Standard effluent Town) quality: Class IB quality: Class IB

Total 135.91

The layouts of the above components are attached in Appendix 3.

LINKAGE PROJECTS

In order to improve the investment efficiency of the involved components, the composition of the subproject has been proposed by considering the adaptability to the overall road, water supply, wastewater and solid waste system of the project district/towns. The component linkage has been summarized in the table below.

TABLE 0-2: PROJECT LINKAGE FOR YUANBA SUBPROJECT

Name of Yuanba urban area Wangjia Town Hongyan Town Component The proposed component will cover the construction of landfill site, production management area, leachate treatment system, roads to Solid waste the site and in the site, a / / transfer station and the purchase of necessary equipment and vehicle.

DRA CONSULTING TEAM 9 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Name of Yuanba urban area Wangjia Town Hongyan Town Component The construction of The construction of The construction of proposed roads will proposed roads will proposed roads will complete the road system in complete the road system in complete the road system in Road the resettlement area for the resettlement area for the resettlement area for earthquake-affected people earthquake-affected people earthquake-affected people in Yuanba urban area. in Wangjia Town. in Hongyan Town.

The proposed water supply The proposed water supply component has covered component has covered Water water intake, raw water water intake, raw water / Supply pipes, WTP and distribution pipes, WTP and distribution network. network.

The sewers connecting with The sewers connecting with the proposed Wangjia the proposed Hongyan WWTP have been included WWTP have been included in the road component in the road component under the same subproject, under the same subproject, Wastewater / and the construction of the and the construction of the proposed sewers is proposed sewers is expected to be put into use expected to be put into use in June 2011 together with in June 2011 together with the WWTP. Hongyan WWTP.

Total

DRA CONSULTING TEAM 10 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Alternative Analysis

During the project development, various alternatives have been proposed, screened and compared with technical, economic as well as environmental criteria. In terms of the environmental comparison for the alternatives, the primary objective was to identify and adopt options with the least adverse environmental impacts and maximum environmental benefits.

As presented above, this subproject consists of four components; therefore, the alternative analysis for the subproject will accordingly be organized by component. Additionally, in response to the WB requirements, there will be a special section analyzing potential impacts if without the subproject.

WITH AND WITHOUT YUANBA SUBPROJECT

Compared to the "With" project scenario, "Without" the Yuanba subproject the result would be: • Without the solid waste component, the municipal solid waste collection, transfer and the transportation system efficiency would remain low and, community based sanitation and hygiene would continue to be poor, affecting the heath and living environment, as well as the standard of living for the residents. The sanitation conditions would further deteriorate without the project, resulting in increased solid waste volumes due to urban population growth and rising living standards. • Without the road component, the urban roads damaged in the earthquake will remain at a low grade and the local urban road network will remain incomplete, which will affect the daily commuting of local residents and fall short of the local economic development and the efforts to resume the production and lives of earthquake-affected residents; • Without the water supply component, the concerned towns will not meet the future water demand necessary to achieve the social and economic development targets and a part of the population will continue to rely on polluted underground water for drinking. • Without the wastewater component, the increased volumes of untreated domestic and industrial wastewater along with the rapid industrialization, urbanization and population growth in the area, will be discharged to the water receptors directly. The surface water and groundwater quality would continue to deteriorate, threatening drinking water safety, groundwater quality, local ecosystem, agricultural production relying on irrigation, and thus the living standard of the residents in the project areas and those downstream, and eventually weakening the ability for sustainable economic development in the district.

SOLID WASTE

For the proposed solid waste sanitary landfill site and solid waste transfer station for the urban area of Yuanba District, various alternatives have been analyzed in terms of project location, leachate treatment and mode of solid waste transfer system.

DRA CONSULTING TEAM 11 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Project Location

Two options have been proposed for the location of the solid waste landfill site of Yuanba District, as presented below:

TABLE 0-1: ALTERNATIVE ANALYSIS FOR THE LOCATION OF YUANBA LANDFILL SITE

Site 1 Site 2

Site Photo

No.4 Community of Xingshu No.1 Community of Guihua Village, Location Village, about 4.5km from the about 1km from the urban area of urban area of Yuanba District, not Yuanba District. within the urban planning area.

Electricity and Convenient Convenient Water Supply With existing road to connect with With existing road to connect with Traffic the proposed site the proposed site Conditions

Relationship with Local Downwind Downwind Dominant Wind Direction 4 abandoned houses, no Resettlement A few households resettlement Involved

Type of Land Forestland with little farmland Forestland with little farmland Occupation

Available Less than 12 years 12 years Capacity Lack of groundwater Lack of groundwater Groundwater There is a drain outside the site No surface water around the site Surface Water but with small cross-section.

Relationship Downstream of local water intake Downstream of local water intake with Local Water Intake Above the 1:100 years flood Above the 1:100 years flood Flood Control control level control level

Geologic Stable Stable Stability

DRA CONSULTING TEAM 12 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Site 1 Site 2 Thick soil layer, easy to get Thick soil layer, easy to get Foundation of covering soil covering soil the Site

Conclusion Site 1 is located in the planned urban area of Yuanba District, which will affect the urban development, and there is no space for future development. Therefore, Site 2 is more suitable for the proposed landfill site. Leachate Treatment

Two options have been proposed for the leachate treatment for the proposed solid waste landfill site, as presented below:

TABLE 0-2: ALTERNATIVE ANALYSIS FOR LEACHATE TREATMENT OF YUANBA LANDFILL SITE

Advantages Disadvantages

Option 1: - Good and stable effluent - Complicated process; Ammonia quality, able to meet current - High investment and operation Stripping leachate discharge requirements cost; +MBR of “Pollution Control Standard for - Require more equipment. +Nanofiltration Domestic Solid Waste Landfill Site” (GB16889-2008);

Option 2: - Wide application in China, - Complicated process; Medium - mature technology and high - High energy consumption, high temperature treatment efficiency; equipment loss and thus high +MBR+Reverse - Good and stable effluent operation cost; Osmosis quality, able to meet current - High maintenance and leachate discharge requirements management requirements. of “Pollution Control Standard for Domestic Solid Waste Landfill Site” (GB16889-2008).

Based on the above analysis, Option 2: Medium -temperature +MBR+ Reverse Osmosis, is economically and technically more reasonable and feasible, and thus it is recommended as the treatment process for the leachate from the proposed landfill site. Type of Solid Waste Transfer Station

According to the process flow and the compacting degree of solid waste, the transfer stations could be classified as direct transfer and compacting transfer, whose characteristics are listed in the table below.

TABLE 0-3: COMPARISON OF DIFFERENT MODES OF SOLID WASTE TRANSFER SYSTEM Mode of Mode of Direct Compacting Transfer Transfer Pushing force on No High garbage

DRA CONSULTING TEAM 13 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Mode of Mode of Direct Compacting Transfer Transfer Garbage Compactness in Low Higher Container Adaptability to properties of Good Good transferred garbage Airtightness during Relatively good Relatively good transportation Equipment Investment and Low High Operational Cost Efficiency of Low High Transfer Operation

The selected mode of transfer stations is closely related to the local economical development level. In view of the economic level of Yuanba District and the selected mode of transfer stations for other similar counties in Sichuan, the mode of direct transfer is recommended for Yuanba subproject, that is, the garbage is collected in the container in the transfer station and the full container is sent to the landfill site for disposal. The garbage will not be compacted in the container.

WTP

For the two proposed WTPs under this subproject, in view of their small treatment capacity, two kinds of treatment processes have been compared, as presented in the table below:

TABLE 0-4: COMPARISON OF TWO WATER TREATMENT PROCESSES Option 1: Option 2: Inclined-tube settling tank + Integrated Water Clarifier Pressure Filter - With good precipitation effects; - Low project cost; - No need for large valve; fully - Short construction period; automatic flushing; - Integrate the processes of Advantages - Easy operation; sedimentation and filtration; - No negative hydraulic head during - Little land occupation; filtration. - Stable treated water quality. - Relatively complicate tank structure; - Difficult for the loading and unloading of filter media; - Insufficient back-flushing with the flushing water tank on top of the filter; - Difficult for the general elevation layout of the treatment structures due - Anti-corrosion treatment is Disadvantages to higher effluent elevation and thus required for steel tank. higher elevation of the settling tank before the filtration; - Instable treatment effects, especially in view of the small capacity of proposed WTPs; - High difficulty for filter construction.

DRA CONSULTING TEAM 14 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Based upon the above comparison, although additional anti-corrosion treatment is required, Option 2 still has several advantages over Option 1, such as short construction period, low project cost and little land occupation. Especially in view of the very limited land available in the project towns for WTP construction, the integrated water clarifier could significantly save the land use. In addition, the process has been widely applied to many small-scale WTP projects in recent years with stable treated water quality proved. Therefore, for the proposed Wangjia WTP and Hongyan WTP, the integrated water clarifier is recommended as the water treatment process.

WWTP Project Location

For the proposed Wangjia Town Wastewater Treatment Plant, two optional locations have been compared, as detailed below:

TABLE 0-5: COMPARISON OF PROPOSED LOCATIONS FOR WANGJIA TOWN WWTP

Option 1 Option 2

Location Shiban River, in No.1 Community of Zhushi Ditch, in No.1 Community of Hongmiao Village, Wangjia Town Hongmiao Village, Wangjia Town

Description Just neighboring the river bed on the Covering an area about 4mu; about downstream of Shiban River; only 70m away from the residential area; about 1mu; only about 20m away from the ground elevation of the site is about the residential area; and most of all the 25m lower than other areas; and all the wastewater from the town collects wastewater from the planned urban here. area collects here.

Conclusion Based on the following reasons, Option 2 is recommended as the location for the proposed Wangjia Town WWTP. 1) It is relatively far away from the planned residential areas, and the project completion will have no obvious environmental impacts; 2) There is enough space for long-term expansion; 3 The local traffic is convenient for construction implementation and management; 4) There is no resident and other sensitive receptor within 70m around the proposed site, and it will involve no resettlement. Wastewater Treatment Process

For the two proposed WWTPs under this subproject, three options of treatment processes have been compared, as presented in the table below:

TABLE 0-6: COMPARISON OF WASTEWATER TREATMENT PROCESS Option 1 Option 2 Option 3 Aspect Item A/0 or A2/O Oxidation Ditch CAST Widely applied Widely applied Technolo in China and Applied in some Application in China and gy Abroad, with Chinese cities abroad much experience

DRA CONSULTING TEAM 15 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Option 1 Option 2 Option 3 Aspect Item A/0 or A2/O Oxidation Ditch CAST Adaptability to treatment Adaptable Adaptable Adaptable capacity Adaptability to Greatly impacted Greatly impacted Greatly impacted wastewater by low by low by low quality temperature temperature temperature Adaptability to Normal Normal Normal low temperature Could satisfy the Could satisfy the Could satisfy the Class IB Class IB Class IB Effluent quality discharge discharge discharge standard standard standard Quantity of Normal, Normal, Normal, residual sludge relatively stable relatively stable relatively stable Operational Relatively Relatively Complicate management complicate simple Difficulty to resume operation Relatively Relatively Relatively after long-time difficult difficult difficult suspension Requirements of High Very high Normal automatic control Difficulty for cultivation and Difficult Difficult Difficult acclimation of microorganism Possibility of Easy to take Easy to take Not easy to take sludge bulking place place place Difficulty of phased Difficult Difficult Easy construction Number of operators Many Many Many required Capital cost Highest Higher High Operation cost Relatively high Relatively high Normal Economy Energy High High High consumption Land occupation Largest Large Large

DRA CONSULTING TEAM 16 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Option 1 Option 2 Option 3 Aspect Item A/0 or A2/O Oxidation Ditch CAST Construction Normal Normal Normal Construc difficulty tion Construction Normal Normal short duration Environ Noise impact Great Great Normal ment Odor impact Great Great Normal

In general, since the treatment capacity of the proposed WWTPs is very small with little content of heavy metals and good biodegradability, Option 1 (A2/O) is recommended as the treatment process to meet the required Class IB requirements of GB18918-2002. SLUDGE TREATMENT PROCESS

There are mainly two optional treatment processes for the sludge not requiring digestion, as presented in the table below.

TABLE 0-7: COMPARISON OF SLUDGE TREATMENT PROCESS

Option 1 Option 2 Item Gravitational concentration and Mechanical Treatment dewatering Sludge storage tank + Sludge concentrating tank + Main structures Concentrating & dewatering house Dewatering house + Sludge shed + sludge shed Sludge concentrating & Sludge scraper for concentrating Main dewatering machine + Chemical tank + Dewatering machine + equipments dosing equipment Chemical dosing machine Land Small Large occupation Total usage of 3.5 5.5kg/TgDS 3.5kg/TgDS flocculant No large-scale open structure for Open sludge concentrating tank Environmental sludge, with little environmental with unpleasant odor and great impact impact environmental impact Total cost of Low High civil works Total equipment Normal High cost Secondary pollution of No pollution With pollution phosphorus in residual sludge In terms of land occupation, environmental impact, total cost of civil Conclusions works and equipments, and secondary pollution of residual sludge,

DRA CONSULTING TEAM 17 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Option 1 Option 2 Item Gravitational concentration and Mechanical Treatment dewatering Option 1 (mechanical treatment) is advantageous over Option 2 (Gravitational concentration and dewatering), therefore, Option 1 is recommended for this project.

As for the mechanical treatment process, three options have also been considered, as detailed below:

TABLE 0-8: COMPARISON OF SLUDGE MECHANICAL TREATMENT PROCESS

Option 2: Option 3: Option 1: Mechanical Centrifugal Belt thickener + Belt integrated equipment thickening + dewatering machine for sludge thickening Centrifugal and dewatering dewatering machine

Advantages - Reasonable - Compact and single Clean operational equipment price; equipment without any environment, low labor - Produced in China transitional process; intensity, low chemical with mature operation - Good environmental dose and allow experience. conditions with the continuous operation. least chemical consumption.

Disadvantages Additional sludge High equipment cost High equipment price, storage tank and large installed capacity supporting filling and big noise; facilities are required additional sludge after thickening, which storage tank and will make the system supporting filling more complicated with facilities are required more land occupation after thickening, which and poor operational will make the system environment more complicated with more land occupation and poor operational environment.

Since the treatment capacity of both proposed WWTPs is very small, the generated residual sludge is very limited, Option 2, Mechanical Integrated Equipment for sludge thickening and dewatering is recommended for sludge treatment of this subproject.

DRA CONSULTING TEAM 18 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Environmental Baseline Situation

PHYSICAL SETTINGS

Geography

As shown in Figure 0-1, Yuanba District is located in the southern suburban area of Guangyuan Municipality in the north of Sichuan Province. It covers an area of 1440km2 with the jurisdiction over 9 towns, 19 townships and one street committee.

FIGURE 0-1: PROJECT LOCATION

Geology

Yuanba District is situated in the transitional zone from the low mountains to hills at the northern edge of . The topography is high in the north and low in the south and inclines from east to west. Topographically, the district is dominated by Da’nan Mountain Network, the low-mountain network to the east of and to the south of Nanhe River, which accounts for 84% of the land surface area of

DRA CONSULTING TEAM 19 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Yuanba District. The low-mountain network centers at Meilingguan in the north of the district and extents in the directions of east, west and south with the average elevation about 900m. In terms of geomorphology, the area consists of middle mountain, low mountain, river valley and terrace. The local earthquake intensity is VII degree.

The urban area of Yuanba is situated on the first alluvial terrace of Changtan River. The built-up urban area is developed in a belt-like zone along the river, which is surrounded by low mountains and hills with the natural geomorphic features of river valley between mountains.

The proposed landfill site is located in a valley surrounded by low mountains with low-lying valley bottom in the middle. Based on the engineering geological survey and borehole drilling findings, from the top down, the strata of the landfill site consist of:

(1) Quaternary Holocene Series gravelly soil (Q4pl): in brown yellow, loose, slightly wet, mainly consists of clay and a small amount of mudstone, sandstone gravels and detritus, occasionally mixed with plant roots and grass roots; the soil texture is very inhomogeneous; It is mainly distributed at the bottom of the valley with the thickness of 0.20 0.70m.

(2) Middle Jurassic Series Shaximiao Group mudstone (J2s): in purplish red, soft, mud structure, medium thickness seam. It mainly consists of clay-type minerals and detritus; arenaceous and muddy cementation; the surface is strongly weathered, with fragmentation along the joints; the cores are in fragments and short columns with low recovery factor, the RQD index is mostly less than 15%. The depth of strong weathering is normally between 1.0 1.5m. The cores of mudstone with medium weathering are mostly in long and short columns with the recovery factor more than 60% and the RQD index more than 55%; The rock mass is relatively complete with the basic quality of Grade IV, classified as soft rock.

Wangjia Town is located at the southern end of Da’nan Mountain in the low- mountain area, where the massifs are mostly beam-like or table-like with slow slope and spacious valley. The normal elevation is about 800m with the range between 532m and 1134m.

Hongyan Town also shows the landform of low mountain and deep valley, which is cut by Jialing River into several parallel ridges. However, most of the town is located in the valley along the river.

Climate

Yuanba District is located in the transitional zone between Sichuan Basin and Northwest Plateau. It is located in the subtropical humid monsoon climatic zone and dominated by the inland basin climate, which is also greatly affected by the continental climate of Northwest Plateau. The climate is mild and humid with plentiful rain. Late spring, long summer, cool autumn and cold winter could summarize the differentiated climatic features of four seasons in the area. The average annual temperature is 17 . It is cold and dry in winter and spring with the minimum temperature of -8.7 -10 ; and it is hot and humid in summer with the maximum temperature of 38.9 41 . The raining season is June~September, when the rainfall accounts for 75% of the annual rainfall. The average annual rainfall is 1058.4mm, and the maximum annual rainfall is 1587.2mm. The average annual sunshine duration is 1389.1 hours, and the frostless duration is 263 days by average. It is also a windy area, especially in winter and spring. The average annual evaporation is 1499mm. The dominant wind direction in winter and spring is

DRA CONSULTING TEAM 20 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) northwest with the maximum instaneous wind speed of 28.7m/s; in summer, the dominant wind direction is southeast.

Hydrology

Surface Water

The main rivers in Yuanba District (with the catchment area over 100km2) mainly include Jialing River, Bailong River, Donghe River, Xihe River, Qingjiang River and Nanhe River, which all belong to the Jialing River System.

Jialing River runs from north to south with the length of 169km within the district. Its average annual flow rate is 450m3/s, the peak flow rate is 16700m3/s, and the minimum flow rate is 11m3/s; Its water level varies between 469.89m and 472.44m, and the historical highest water level is 479.01m; Its average annual flow velocity is 2.05 3.95m/s; and it is open to the navigation of ships with the tonnage around 35t.

Changtan River is the main river in the urban area of Yuanba District with the function of flood discharge and irrigation.

Ziyun Reservoir and the upstream sections of Nanhe River and Yudong River are the planned water sources of Yuanba District with the total water supply capacity of 33000t/d for the long term.

Wangjiawan Creek is the proposed receptor for the leachate from the sanitary landfill site to be constructed under this subproject. Its main function is flood discharge. Its average flow rate is 1.4m3/s, and there is no drinking water source protection zone within 10km downstream of the treated leachate outfall on the creek.

Wangjia Town: There are totally 3 reservoirs in the town with the storage capacity of 760,000m3, which could cover the irrigation of 1450mu farmland; there are 303 mountainous ponds with the efficient storage capacity of 800,000m3 covering the irrigation of 1800mu farmland. Zhangjia River originates from the Motan Gongnong Reservoir and runs through the town from north to south. The river has the surface width of 50ü60m and the length about 13km within the town.

Hongyan Town: Jialing River runs through the town, and there are one small- scale Type 2 reservoir and 278 mountainous ponds in the town.

GROUNDWATER

In the terrace and ridges from Taigongsi to Xinchang, the groundwater is fissure shallow water in red bed detrital rock (weathering zone) and confined water in deep strata with good water yield property, and the runoff modulus more than 0.4l/s·km2. The fissure shallow water in the low-mountain areas to the south of Zhaohua and Ziyun has the medium water yield property with the runoff modulus between 0.2~0.4 l/s·km2; there is also fissure shallow water with relatively poor water yield property in the river valley area such as Yuanba Town, and its runoff modulus is less than 0.2 l/s·km2.

According to the hydro-geo survey carried out in Feb. 2010, the strata of the proposed Yuanba landfill site mainly consists of Quaternary Holocene Series gravelly soil classified as the permeable stratum and the Middle Jurassic Series Shaximiao Group mudstone (J2s) with poor water-bearing capability. The wellspring runoff is 0.01~0.05l/s, and the groundwater runoff modulus is less than 0.2l/sgkm2.

DRA CONSULTING TEAM 21 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) The permeability coefficient of the sandstone layer is normally between 0.356~0.467m/day.

Restricted by local topographic, hydrological and structural conditions, the groundwater of the site is mainly recharged by atmospheric precipitation, both the occurence space and migration passage of groundwater are sandstone interlayer. Part of the groundwater is discharged through gully, and part migrates along the stratum to the deep. The general flow direction is to the west.

Ecology

Forest covers a vast area of Yuanba District with the forest land area of 69565ha and the forest coverage rate over 49.4%. The living wood storage is in total 5.06million m3. As an important based of commodity grain for Guangyuan Municipality, the grain and oil-bearing crops of Yuanba Districts mainly include paddy, maize, rape and peanut. The local climate is suitable for mulberry plantation and sericiculture. The plantation of snow pear, grape, kiwi fruit, flue-cured tobacco and tung tree also begins to take shape.

According to the investigation, there are a lot of human activities in the project impacted areas, and there is no precious and rare animal and plants involved.

SOCIAL & ECONOMIC SETTINGS

Economic Development

With the total population of 238,000, the realized GDP of the whole Yuanba District in 2007 was 138,533yuan with the growth of 14.6% compared with the year before.

Historic Relics and Tourism Resource

As a key part of the “Shudao” (the vital communication line between two ancient kingdoms of and ) tour, Yuanba District has rich sightseeing resources such as the ancient town – Zhaohua, the No.1 Mountain of Guanyuan – Yuntai Mountain, Taigong Red Army Mountain, Baiguoxiang Mountain, Yunv Lake, Ziyun Lake, Pingle Temple and Jiangjun Mountain. However, according to the EIA investigation, the project involves no precious historic or cultural relics.

Wangjia Town and Hongyan Town

The basic socio-economic conditions of the involved project towns, Wangjia Town and Hongyan Town, are presented in the table below.

DRA CONSULTING TEAM 22 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) TABLE 0-1: SOCIO-ECONOMIC CONDITIONS OF WANGJIA TOWN AND HONGYAN TOWN

Wangjia Town Hongyan Town

Land Area (km2) 69.7 45.2 Number of 11 6 Villages Total Population 13418 5942 GDP (million 63.70 (2008 data) 24.59 (2006 data) yuan) Pure Income of Local Farmers 2531 (2008 data) 1837 (2006 data) (yuan/capgyear) Main Industry Agriculture Agriculture The earthquake has almost razed the whole urban area of Hongyan Town to the ground, and the earthquake- There are totally 3323 households of affected percentage of the rural area is farmers suffered from the earthquake Loss during 5.12 also up to 100%. According to the to different extents. The earthquake Wenchuan statistics, the direct and indirect also damaged 77.6km of roads, 25 Earthquake economic loss sums up to 290million bridges and other infrastructure of the yuan. After the earthquake, the town is town. planned to be reconstructed in five years (by 2012) in combined with the earthquake victim resettlement.

DRA CONSULTING TEAM 23 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Impact Assessment & Mitigation Measures

ANTICIPATED BENEFITS FROM YUANBA SUBPROJECT

The four proposed components of the Yuanba subproject will significantly improve the environmental conditions and quality of life in the concerned urban area and towns through the following results: • Facilitation of post-earthquake reconstruction works with easier access to the involved project areas; • Improvement of local road network to meet future traffic needs necessary to achieve the social and economic development targets of both the urban and rural areas of Yuanba District; • Improvement of current water supply to meet the future water demand necessary and thus to support the social and economic development of the project towns; • Protection of local water resource by introducing wastewater treatment for the project towns; • Improvement of municipal wastewater and solid waste collection with evident benefits in terms of urban quality of life and public health; • Enhancement of river quality and landscape in urban areas with direct effects on the quality of life of nearby residents; • Safe disposal of solid municipal waste with leachate and landfill gas control and management reducing pollution load to surface and underground water and abatement of GHG released in the atmosphere; • Improvement of public health and life quality of local residents through the provision of water supply, wastewater treatment and solid waste collection & disposal services.

POLLUTION ABATEMENT: Pollution abatement will result from the construction of new wastewater treatment facilities (Wangjia and Hongyan) and from the increased wastewater collection capacity in Yuanba urban area and the two project towns (Wangjia and Hongyan).The effluent from Wangjia WWTP will be discharged into Shiban River and finally flow into Jialing River; and the effluent from Hongyan WWTP will be discharged into Jialing River. By adopting the Class IB national standard for WWTP effluent, the two proposed WWTPs are expected to result in an annual pollution abatement of about 54.31tons of CODCR, 29.42 tons of BOD5, 40.73tons of SS and 6.79 tons NH3-N, as detailed in the table below.

TABLE 0-1: POLLUTION ABATEMENT ASSESSMENT

INDICATOR CODCR BOD5 SS NH3-N Influent Quality (mg/L) 300 150 200 30

Effluent (mg/L, Class IB) 60 20 20 8

Pollution abatement 240 130 180 22 (kg/1,000 m3 ) Daily Wangjia Town 120 65 90 11 pollution

DRA CONSULTING TEAM 24 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

INDICATOR CODCR BOD5 SS NH3-N pollution Hongyan Town 28.8 15.6 21.6 2.64 abatement (kg/d) Annual Wangjia Town 43.80 23.73 32.85 4.02 pollution abatement Hongyan Town 10.51 5.69 7.88 0.96 (t/a)

Total Annual Pollution 54.31 29.42 40.73 4.98 Abatement of Yuanba Subproject (t/a)

IMPACTS AND MITIGATION MEASURES RELATED TO PROJECT LOCATION

Land Acquisition & Resettlement

According to the RAP, the implementation of the proposed Yuanba subproject will lead to the permanent land acquisition of 193.4mu (including 26.4mu farmland, 91mu forestland and 76mu land for construction), the resettlement of 18 households (54 residents) and the house demolition of 1280m3, as detailed in Chapter 6.

Physical & Cultural Heritage

According to the investigation carried out by local authorities during the preparation of the individual EIA, no physical and cultural heritage resource is recorded or observed around the involved project sites. For any potentially buried and unknown cultural resource which may be discovered during construction, appropriate protective measures will be immediately taken, as specified in Section 5.4.2.2.

Ecological Resources

All the proposed projects are implemented either in the rural areas that has been planned and will be developed soon or in the built-up urban areas. The project implementation does not involve: • Forest clearing; • Destruction of area known for sheltering protected or threatened biodiversity; • Encroachment into a protected area as a nature reserve; or • Creation of facilitated access to sensitive areas with further risks of illegal or uncontrolled encroachment.

The project will have no significant detrimental impacts on valuable ecological resources1.

Stability and Hydro-geological Conditions of Yuanba Landfill Site

According to the “Geotechnical Engineering Survey Report for Yuanba Domestic Landfill Site of Guangyuan Municipality” developed by Sichuan Tianli Engineering Design Co., Ltd. (dated November 2009), the site is of structural eroded hilly landform with a thin Quaternary covering layer only 0.2 0.7m thick. There is no fracture structure, and the integrity of rock mass is good. Most of the bed rock is exposed. The site slope is gentle, and there is no adverse geological effect like collapse, landslide and mudflow. Based on the regional seismic data, the site is about 45km from the main fault zone of Longmen Mountain Structural Zone. That is, the proposed site is located in a geologically stable region with unitary landform and far from the seismic zone.

1 It is not necessary to apply World Bank Operational Policy 4.04, on Natural Habitats

DRA CONSULTING TEAM 25 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) The project site is located on a high terrace with no large surface water and major torrential flood to scour the side slope. Currently the natural side slope of the site is under relatively stable conditions. The stability conditions of the site are good enough for the project construction.

To better understand the hydro-geo conditions of the selected Yuanba Landfill Site, the “Hydro-geo Survey Report for the Site of Yuanba Domestic Solid Waste Landfill Site in Yuanba Municipality” has been completed in February 2010. The specific conclusions are summarized as follows: • The proposed landfill site is of structural eroded hilly landform with only a thin Quaternary cover only 0.2~0.7m thick. The integrity of rock mass is good, and there is no distribution of fracture structure. The proposed site is of bag shape with the catchment area about 0.113km2. Such topography is in favour of rainfall collection, which means that the flood-preventive drainage system should be carefully designed. • The hydro-geo conditions of the proposed site are simple, and local groundwater is expected to have little impact on project construction. The site strata are developed in monocline with slow inclination angle. It mainly consists of mudstone with relatively good water insulation capability. However, it could not satisfy the requirements of impervious material standard. There is thin~medium thick fine sandstone in-between with good permeability, which will become good passage for leachate from the landfill site. • With the existing dump site which has been operated for over 10 years, the local groundwater and surface water has already been polluted to a medium extent. The proposed landfill site has to include necessary pollution control facilities in its design by strictly following the “Technical Specification for Domestic Solid Waste Transfer Station” (CJJ47-2006), “Standard for Hygienic Assessment of Domestic Solid Waste Landfill Site” (CJJ/T107-2005) and “Pollution Control Standard for Domestic Landfilling” (GB16889). • The proposed site is 4500m from the bank of Changtan River and 4500m from Yuanba Town. It is over 1000m away from the area with relatively low population density on the leeward. Its horizontal distance from the centralized groundwater water supply source of Yuanba Town is 4500m, and its distance from the main national highway 212 is 400m. The proposed project will have adverse impacts on local water environment and ecological environment. However, the impacts could be mitigated with proper measures.

As a conclusion, the selected site could generally meet the requirements for site selection of a solid waste landfill site in terms of hydro-geo conditions. However, the report has also made the following suggestions to prevent and control any potential impacts: • The existing solid waste dump should be cleared to implement the seepage prevention works on the side slope and bottom of the site by adopting both the vertical and horizontal seepage prevention measure. • A complete leachate collection system should be laid on the bottom of the site. • A separate flood and rainwater drainage system should be installed in the site, the wastewater should be separated from rainwater, and the collected water from outside the site and from the non-landfilling area within the site could be drained directly. • The flood and rainwater drainage system should be designed on the northern ridge of the landfill site. The flood control criterion of flood control works should comply with the requirements of relevant national standard such as “Flood Control Standard” (GB50201) and “Design Specification of Urban Flood Control” (CJJ50).

DRA CONSULTING TEAM 26 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) • 2-3 groundwater monitoring stations (holes or wells) and one surface water monitoring station on the upstream of Zhiqingdian Reservoir and Changtan River should be installed to implement the long-term water quality monitoring. • There is an abandoned plastics processing factory neighbouring the site in the west, which might cause hidden safety issues and should be removed.

SENSITIVE RECEPTORS

According to the project EIAs, the key sensitive receptors during the construction and operation of the proposed Yuanba Subproject are identified as follows:

TABLE 0-2: LIST OF SENSITIVE RECEPTORS FOR YUANBA SUBPROJECTS Name of Project Location and Distance relative to the Applicable Environmental Sensitive Receptor Area/Town project site Protection Target Solid Waste Component Air: Class II of Around proposed transfer station; Along GB30951996 Residents the collection and transportation route to Noise: Class II of proposed landfill site GB30962008 Urban Area of A nearby drain and Wangjiawan Surface Water: Class III of Yuanba District Downstream of proposed landfill site Creek GB38382002 Groundwater and wells of local Groundwater: Class III of farmers in No.4 Community, Within 1.0km of proposed landfill site GB/T148148-93 Xingshu Village Road Component No. 1 Community of Yuanba 30m to the right of No.2 Road Village (about 40 households) No.2 Community of Yuanba Oujiahe Residential 10m to the right of No.3 Road Village Area Jiuba No.1 Elementary School 60m to the left of No.3 Road Yuanba Town No.1 Elementary 50m to the left of No.7 Road School (under construction) Air: Class II of Family Planning Service Station GB30951996 10m to the right of No.1 Road of Wangjia Town Noise: Class II of Wangjia Town Elementary GB30962008 Wangjia Town 50m to the left of No.1 Road School Wangjia Town Central Clinic 20m to the right of No.2 Road Residents (about 60 households) 45m to the right of No.3 Road Hongyan Town Elementary 20m to the right of No.2 Road Hongyan Town School Hongyan Town Clinic 15m to the left of No.1 Road Surface Water: Class III of Urban Area Changtan River Along proposed roads and pipes GB38382002 Water Supply Component Wangjia Town Xinhua Reservoir As the water intake Air: Class II of

DRA CONSULTING TEAM 27 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Name of Project Location and Distance relative to the Applicable Environmental Sensitive Receptor Area/Town project site Protection Target Urban residents On both sides of proposed pipes GB30951996 Family Planning Service Station Noise: Class II of Beside proposed pipe of Wangjia Town GB30962008 Wangjia Town Elementary Beside proposed pipe School Wangjia Town Central Clinic Beside proposed pipe Scattered Residents 300m to the southeast of proposed WTP Surface Water: Class III of Irrigation Channel 200m to the southeast of proposed WTP GB38382002 Residents in Lijiaba Village To the east and north of proposed pipes Air: Class II of GB30951996 To the southwest of proposed pipes, Residents in Baihua Village Noise: Class II of Hongyan Town 100~200m from proposed WTP GB30962008 Surface Water: Class III of Jialing River Besides project sites GB38382002 Wastewater Component Effluent Discharge: Class IB of GB18918-2002 Shiban River For effluent discharge Surface Water: Class III of GB38382002 Wangjia Town Air: Class II of GB30951996 About 15 nearby Residents 50m to the southeast of project site Noise: Class II of GB30962008 Effluent Discharge: Class IB of GB18918-2002 Jialing River For effluent discharge Surface Water: Class III of GB38382002 Hongyan Town Air: Class II of GB30951996 Nearby Residents 60m to the northwest of project site Noise: Class II of GB30962008

IMPACTS AND MITIGATION MEASURES RELATED TO CONSTRUCTION PERIOD

General Impacts

The general adverse impacts and corresponding mitigation measures expected during the construction activities of the proposed subproject have been summarized in the following table:

DRA CONSULTING TEAM 28 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) TABLE 0-3: SUMMARY OF GENERAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES DURING CONSTRUCTION OF YUANBA SUBPROJECT

Aspect General Environmental Impacts Mitigation Measures üà Construction sites, transportation routes and Air borne dust due to excavation, materials handling sites will be water sprayed on demolition, construction vehicle dry and windy days up to 2-3 times a day, movement and materials handling, especially if these sites are near sensitive particularly downwind from the receptors, such as residential areas, hospitals construction sites. and school. Using central concrete mixing plants where possible, and transport with sealed vehicles; üà Construction materials will be stored in Air appropriate places and covered or sprayed to minimize dust; üà Construction waste will be promptly removed from the sites and transported to an appropriate disposal area approved by the PMO and the concerned municipality. Burning of construction waste will be prohibited; üà Materials will be covered during transportation to avoid spillage or leakage. üà Construction activities will be scheduled carefully Noise from construction equipment with consultation with nearby residents to and vehicular movement, potentially minimize the impact of noise from construction affecting nearby residents and machinery. Night-time (22:00 to 06:00) and noon- sensitive sites as hospital or schools. time (12:00 to 14:00) uses of certain noisy machines, such as pile-drivers and concrete vibrators, will be prohibited in the vicinity of Noise residential areas; üà Temporary noise barrier should be set up at construction site near schools and residential areas; üà Personal protection equipments or PPE (e.g., noise protection earplugs) shall be supplied to workers for protection from the intensive noise.

Wastewater discharge from Sewage and other wastewater from construction construction camps. The discharge of camps will be collected and treated at septic tanks wastewater from construction camps before discharge to avoid contamination of the Wastew could create potential new pollution surrounding areas. Where possible the wastewater ater sources, and could also be sources of will be discharged directly to the municipal sewer. sludge, solid waste and waste oil from machinery maintenance.

Excavated/spoil materials. Detailed Temporary land occupation will be planned well amounts of spoil expected from road ahead to minimize the effect of the disturbance and works, WSWW pipe laying activities, land will be reinstated to its original condition on Solid road works and WTP & WWTP completion of construction. Top soil will be removed Waste components have been respectively and stock-piled for use during land restoration, quantified in the following section, particularly on the landfill sites. which may require off-site disposal.

Removal of trees. The construction of Appropriate tree species will be selected for the proposed roads, the development of greening of affected project areas to restore local water supply and sewer network and ecological environment. Ecology the building of WTPs and WWTPs may impose the cutting of a few trees, most of which .

DRA CONSULTING TEAM 29 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Aspect General Environmental Impacts Mitigation Measures

Soil erosion. Piles of earth will be Strict measures to keep control of erosion and runoff created from time to time during on the construction sites and the spoil sites will be construction as well as bare land imposed on contractors through detailed particularly during landfill specifications, included in the Soil Erosion Control construction. In case of rain, erosion Plan. Monitoring of runoff water will also be would occur on the earth piles and conducted to ensure that the measures are effective other disturbed land such as river and that receiving water quality is not affected. slopes causing loss of soil.

Traffic congestion by road In conjunction with the relevant authority, traffic flow construction, pipeline construction regulation plans will be prepared in advance of along the existing roads, transfer construction in the congested urban built up areas. station construction and upgrading in Contractors will be required to take necessary built-up neighborhoods and increased safety measures at the construction sites to construction traffic in urban areas. protect the public, including warning signs to Roads may be fully or partially closed alert the public of potential safety hazards at during these construction activities and around the construction sites. Workers causing temporary inconvenience and Traffic delays to residents, commercial should be examined regularly and the infected operations and institutions. people should be given immediate medial attention or quarantined.

Damage to roads. Heavily laden During the raining season, limitation of load access trucks may impact on road conditions will be imposed on the contractor to reduce damage and cause road surface damage, to the roads. Also, the contractor will be required to especially during periods of rainfall rehabilitate, at the end of the construction, the section and high ground moisture content. of the roads which have been damaged by the traffic resulting from the transport activities.

Infectious diseases. During the All contractors and construction supervisors will be project construction period, floating required to participate in mandatory environmental population will work in construction and health and safety training programs prior to the Public sites throughout the city. The mobility start of construction. Health of outside people might bring external epidemic diseases to local communities.

The above mitigation measures, where appropriate, will be included in the tender documents and subsequently in the construction contracts as binding contractual requirements.

Specific Impacts

SPOIL DISPOSAL

Certain volumes of spoil are expected from the project construction activities, which may require off-site disposal. The overall earthwork balance for this subproject is detailed in the table below:

TABLE 0-4: EARTHWORKS BALANCE FOR THE CONSTRUCTION OF YUANBA SUBPROJECT Earthwork Earthwork Earthwork to to be Component to be refilled be borrowed Spoil (m3) Disposal Description excavated (m3)Ã (m3)Ã (m3)Ã

DRA CONSULTING TEAM 30 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Earthwork Earthwork Earthwork to to be Component to be refilled be borrowed Spoil (m3) Disposal Description excavated (m3)Ã (m3)Ã (m3)Ã Used for the construction of refuse 3 77,200(1) 4800 0 72,400 dam (10,760 m ) and as the Solid Waste landfill cover fill after proper treatment (61,640m3).(2) Urban Since the three project areas are far away from each other, Area 28,800 23,800 0 5000 therefore, the generated spoil is (Oujiahe not economical to be disposed ) across different areas. The spoil from Yuanba urban area will be Road Wangjia 75,100 135,800 60,700 0 used for backfilling of a road Town project about 1km from Oujiahe (requiring the backfilling soil of 3 Hongya 9000m ). The required borrow for 30,300 39,500 9200 0 Wangjia and Hongyan will be n Town purchased from nearby sandstone quarry. Only a small amount of generated construction waste will be timely Water Supply NA NA NA 0 transported to the landfill sites of Wangjia Town and Hongyan Town. The excavation will be used for Wastewater NA NA NA 0 backfilling within the project site, and there is no excess spoil.

Total 211,400 203,900 69,900 77,400 / Note: (1) Excluding 100,000m3 of originally dumped solid waste that will be properly transferred to the new landfill site and disposed by landfilling; (2) In this case, only 9960m3 of landfill cover soil needs to be purchased from outside during project operation.

CULTURAL HERITAGE

For any buried and unknown cultural resources that may be discovered during construction activities, corresponding mitigation measures proposed to eliminate such potential impacts are similar for all the components. Adequate training should be provided to the staff/workers on the knowledge of heritage protection. Construction will be immediately suspended if any archaeological or other cultural properties are found (chance finds). The relevant cultural authority, as well as PMO, will be notified promptly, and only after a thorough investigation (by the relevant authorities) will construction be allowed to resume.

TRANSFER OF SOLID WASTE FROM EXISTING DUMP SITE (SOLID WASTE COMPONENT)

As mentioned before, the proposed landfill site for Yuanba District is to be constructed on an existing dump site whose operation was started since 1999. With over ten years’ operation, it is estimated that there has been about 100,000m3 of solid waste dumped on the site. The construction of the new landfill site will easily lead to the landslide and collapse of the existing solid waste dump which will in turn affect the project implementation. The following mitigation measures have been considered to minimize the possible impacts: • Barriers will be set up to stabilize the solid waste dump left within the construction site to reduce the impacts on normal construction;

DRA CONSULTING TEAM 31 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) • Disinfection and odour removal measures will be taken to minimize the impacts on air quality due to the large amounts of air pollutants generated during the transfer of existing solid waste; • The leachate from existing dump will be discharged into the leachate collection tank through temporary drains to effectively reduce its impacts on local surface water.

IMPACTS AND MITIGATION MEASURES RELATED TO OPERATION PERIOD

Solid Waste

Aside general benefits from solid waste collection and management, some detrimental impacts may be observed as noise and odor nuisance, development of pests or pollution of surface or underground water resources by leachate release. • Noise: Since there is no farmer living within 500m of the proposed landfill site, and the operational activities will only be implemented during the day, it is expected that the project will result in no obvious noise impact. • Odor nuisance: The EIA report have proposed the following measures to control the odor from the landfill site during operation: (a) Spray biological deodorizer during the unloading of solid waste, and regularly clean the operational site; (b) Install odor-removing system for the sorting operation; (c) the cover soil should be compacted during landfilling by strictly following the operational procedure; (d) implement the greening works to reduce the odor impacts (e) set up 500m of the buffer zone outside the site. For the transfer station, proper odor-removing system will be installed to remove the odor, and 50m of buffer zone will reserved around the compacting workshop. In this way, no major detrimental impact is expected on the surrounding environment. • Development of pests: Compaction of waste and regular covering with soil will limit the risk of uncontrolled development of pests such as mosquitoes, flies or rats. • Leachate treatment: The total leachate generation from both the landfill site and the transfer station is estimated as 41t/d. The leachate from the landfill site will be treated by the leachate treatment system (using the process of Medium - temperature + MBR+ Reverse Osmosis) within the site to meet relevant requirements of GB16889-2008 and GB5084-92 (Effluent quality: CODcr 100mg/L, BOD5 30mg/L and NH3-N 15mg/L) before being discharged into the Wangjiawan Creek through a 650m drain. The collected leachate and other wastewater from the proposed transfer station will be regularly transported to the landfill site for treatment by suction sewage truck. • Pollution of surface water: The receiving water body of treated leachate is Wangjiawan Creek. Wangjiawan Creek is a flood-discharging river with the average flow rate of 1.4m3/s, and there is no drinking water intake within 10km downstream. With normal operation of leachate treatment system, the water quality of the creek will still be able to meet the Class III water quality target of “Surface water environmental quality standard” (GB3838-2002). However, the EIA still suggests to strengthen the seepage prevention measures on the site bottom and the daily maintenance of leachate treatment system in order to avoid any pollution resulting from accidental wastewater discharge • Pollution of groundwater: By strictly implementing the seepage prevention works consisting of soil, geotextile, HDPE membrane, geotextile and soil on the bottom and around the landfill site, the project operation will have no obvious impact on groundwater quality. In order to reduce the leachate production, drainage system will be implemented around the landfill site to divert stormwater from entering landfill cells. Also, compacted waste will be regularly

DRA CONSULTING TEAM 32 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) covered in order to limit rainwater infiltration and leachate production. For the transfer station, the leachate collection tank will be cleared day by day, therefore, there will be no impact on groundwater quality. • Pollution of downstream wells: The farmers’ residential area for the No. 4 Community of Xingshu Village is located downstream of the proposed landfill site. The drinking water of the village mainly comes from local groundwater and the upstream pond to the west of the landfill site. As revealed in the hydro-geo survey implemented for the solid waste component, the leachate from the landfill site has the possibility to pollute the western pond and the deep groundwater in the west. In addition, when the impermeable membrane is broken, the leachate from project operation could also pollute the groundwater downstream. Therefore, the drinking water source for the No.4 Community of Xingshu Village is possible to be polluted by leachate during project operation. To avoid any pollution of drinking water source for the downstream villagers, Yuanba District Planning and Construction Bureau has promised to replace the current drinking water source by installing tap water network for local villagers and introducing the water from Qingshu WTP (as the emergency water supply source for Yuanba urban area). The project is currently under design, and the construction is expected to be started by the end of June 2010. • Groundwater Monitoring wells will be implemented around the landfill site to control the efficiency of the leachate treatment system regarding the protection of the underground water. Based on the understanding of groundwater distribution within the landfill site from the project hydro-geo survey report, four monitoring wells will be implemented: one baseline monitoring well, about 30- 50m upstream of the groundwater flow direction; two pollution diffusion wells, 30m on both sides vertical to the groundwater direction; one pollution monitoring well, 30m downstream of the groundwater flow direction. In addition, the EIA consultants also request to monitor the downstream well of No.4 Community in Xingshu Village. • Passive collection of landfill gas will be implemented in the landfill with the installation of flares to automatically ignite the landfill gas when the methane content is over 5%. Landfill gas monitoring wells will be drilled at the perimeter of the landfill to monitor the methane content to minimize the risk of explosion. • Improper management of solid waste collection and transfer system will also result in the pollution of surrounding environment. Accordingly, the following mitigation measures have been proposed: a) Along the currently identified transportation route, there are mainly enterprises and shops, only a few centralized residential areas are involved, mainly along Jingzhao Road and Qingmei Road. The stay of vehicles in these areas will be reduced to minimize the environmental impacts ; b) Enclosed container and compressive collection and transfer system will be used for solid waste collection and transportation to prevent any undesirable exposure, scattering and leakage; c) Strictly separate any hazardous solid waste from the domestic solid waste; d) Strengthen the daily management of the transfer station; e) Ensure that all the solid waste from the dustbin, solid waste tank and the transfer station is collected and sent to the landfill site; f) Carefully choose proper type of vehicles for solid waste transportation, and the vehicles should be carefully cleaned after unloading; g) Regular maintenance of the vehicles should be carried out to ensure the good airtightness of the vehicles.

Road

The environmental impacts of road component during operation are mainly limited to the noise impacts on nearby sensitive receptors as identified in Section 5.3.

Since the population of Wangjia Town and Hongyan Town is very small, the EIA consultants only carried out the traffic noise projection for the urban area of Yuanba District

DRA CONSULTING TEAM 33 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) (Oujiahe Community). The results show that the residential houses beyond 10m on both sides of the project roads will be impacted by the traffic noise. Therefore, the EIA consultants has made the following suggestions to minimize the noise impacts on local residents: a) The traffic control should be strengthened for the involved project roads; it should be required that no new residential house should be planned within 10m on both sides of the roads; the locations of new sensitive buildings such as schools and hospitals should be at least 40-50m away from the sides of the roads.

Water Supply

Impacts from the operation of water supply treatment plants and associated facilities (water intake, raw water pipe and distribution network) are rather limited in number and magnitude, and generally can be easily mitigated. Most frequent impacts and mitigation to consider include: • Treatment of additional wastewater resulting from WTP construction: The proposed Wangjia and Hongyan WTPs will mobilize additional water resources for water supply (respectively 900m3/day and 250 m3/day) which will consequently result in increased wastewater treatment capacities; It is confirmed that the existing and short-term planned wastewater treatment capacities in Wangjia and Hongyan with two new WWTPs (respectively 500 m3/day and 120m3/day) under the same subproject will be sufficient to accommodate the additional flow of wastewater resulting from the new water supply components. • Production wastewater from water treatment process includes the wastewater from settling tank (52.5m3/day for Wangjia and 35m3/day for Hongyan) and the wastewater from the backflushing of filter tank (15.6m3/day for Wangjia and 10.4m3/day for Hongyan). The wastewater will be treated with settling tank to meet Class III requirements of “Wastewater Integrated Drainage Standard” (GB8978-1996) before being discharged into the urban sewage network. • Domestic wastewater from staff (4 persons per plant) will be limited for both WTPs, that is, 0.32m3 per day per plant, and the effluent will be treated with septic tank before being discharged into urban sewage network. • Appropriate disposal of generated sludge is required for the WTPs. Since the production capacities of both proposed WTPs are small, the production of sludge will be limited (5.17t/year for Wangjia WTP and 3.45t/year for Hongyan WTP, with the water content of 75% after dewatering), which is planned to be delivered to the landfill site of Yuanba District which is proposed under the same subproject and is expected to be put into operation since January 2011. • Chlorine dioxide leakage at the treatment facility. Risk is controlled by appropriate storage, handling and emergency response procedures. • Noise during the operation may affect the nearby residents. To minimize the noise impacts, the following measures have been proposed: Low noise equipments should be selected; the air blower should be equipped with mufflers; The high noise equipments, such as blower, sludge dewatering machine and centrifuge should be set in isolation booths with sound absorbing walls and roofing; Separate the WTPs from surrounding buildings with greening belts; Keep the equipments in good conditions with regular maintenance. • Dam Safety:

The proposed water intake for Hongyan WTP is Xinhua Reservoir. Xinhua Reservoir is a Type Small (I)2 Reservoir with the dam height of 23m, which is classified as a large dam according to relevant classification criteria3, and

2 The reservoirs of Type Small (I) are defined as the reservoirs with the capacity between 1-10million m3. 3 The dam with the height over 15m is defined as a large dam.

DRA CONSULTING TEAM 34 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) therefore, the World Bank Operational Procedure of Dam Safety (OP 4.37) is triggered. Required information related to the dam has been collected and submitted to the World Bank for review.

The hydraulic characteristics of Xinhua Reservoir are detailed in the table below.

TABLE 0-5: CHARACTERISTICS OF XINHUA RESERVOIR Type of Reservoir Small (I) Ordinary water level (m) 1011 Benefited Population 2360 Design flood level (m) 1012.64 Catchment Area (km2) 1.33 Exceptional flood level (m) 1012.76 Dam Height (m) 23 Dead storage capacity 25 (10,000 m3) Material of Dam Homogeneous Beneficial reservoir capacity 95 earth dam (10,000 m3) Dead water level (m) 1000 Total reservoir capacity 135 (10,000 m3)

With the inspection carried out according to the “Management Regulations on Reservoir Dam Safety in the People’s Republic of China”, Xinhua Reservoir is identified as a Class III dam. With the damage of “5.12” earthquake, the anti- sliding stability coefficient of the dam has decreased, and the rupture of the culverts for water-proof facilities and the damage of the spillway get more serious. To make the dam reach the dam safety criterion above Class II and to guarantee the operational safety of Xinhua Reservoir, the strengthening of Xinhua reservoir is currently under implementation and is expected to be completed in June this year. In this way, the water supply safety of Hongyan WTP during its operation could be guaranteed.

Wastewater Treatment

Most typical impacts of WWTPs refer to the discharge of treated effluent into local water body, to the sludge production and disposal, to noise and odor nuisances generated by the facilities (aerators, blowers, pumps etc) or during sewer maintenance: • Impacts on the quality of local surface water: There is no major detrimental impact but only beneficial impacts on local surface water from the wastewater component of Yuanba Subproject as a significant reduction of pollutant load presently discharged into the Jialing River system will be observed, as presented in Section 5.1. • Odors from aeration, sedimentation and sludge condensation tanks may affect surrounding areas of the facilities. Minimum 50m distance buffer zone away from the sources of odor (such as sludge storage tank, coarse and fine screens and sludge) will be respected; vegetation barrier will be planted; the generated sludge will be cleared day by day; and good maintenance practice will be taken in the plant to provide effective minimization of impacts. • Noise from pumps may affect the nearby residents. According to the EIA, the project operation will have no obvious impact on surrounding environment with the strict noise reduction measures taken for noise-producing equipments such as aerator, pumps, motors and dewatering machine and the setting of buffer zone (50m). • Domestic wastewater from staff (10 persons for Wangjia and 6 persons for Hongyan) will be limited for both WWTPs, that is, 3.2m3 per day per plant, and the effluent will be treated with septic tank before being discharged into the WWTP for treatment. • Sludge production, handling and disposal The project plans to use the integral sludge dewatering machine for sludge treatment. The residual sludge

DRA CONSULTING TEAM 35 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) will be dewatered within 3 hours after its generation and further processed to the water content of 60% in compliance with the national standard for solid waste landfilling. The estimated sludge generated from Wangjia and Hongyan WWTPs are respectively 0.50m3/d and 0.14m3/d, which is proposed to be delivered to the Yuanba Solid Waste Landfill Site under the same subproject for final disposal. The landfill site is about 37km from Wangjia WWTP and about 70km from Hongyan WWTP. The vehicles with enclosed container will be used for sludge transportation to prevent sludge leakage along the transportation route and the consequent environmental impacts.

DRA CONSULTING TEAM 36 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Resettlement Action Plan

PEOPLE AND NUMBER OF PEOPLE AFFECTED BY LAND ACQUISITION AND HOUSEHOLD DEMOLITION OF THIS PROJECT

This project involves Baihua Village in Hongyan Township; Hongmiao Village and Gengxin Village in Wangjia Township; Xinghua Village and Yuanba Village in Yuanba Township. All above villages are in Yuanba District. The lands of 168 households (539 people) are requisitioned permanently, and houses of 18 households (54 residents) are demolished. The 18 households are both affected by land acquisition and house demolition. The project requisitioned 193.4 mu of land externally. Among the requisitioned land, there is 26.4 mu of farmland, 91 mu of forestry land and 76 mu of construction land. The area of demolished houses is 1, 280 m2, and all of these houses are made of clay and wood. The land acquisition and household demolition of this project are legal.

The project construction does not need take over other land for temporary use, because it can scientifically take advantage of vacant land to construct and stack construction equipment and materials. Residential houses can be rented as offices and living areas, so there is no need to requisite land for temporary use specially.

Among the 193.4 mu of land requisitioned by this project, there is 26.4 mu of farmland. Among the five affected villages in Yuanba District, the farmland of two villages is requisitioned: 18.9 mu of farmland in Hongmiao Village, Wangjia Township; and 7.5 mu of farmland in Baihua Village, Hongyan Township. This land acquisition does not result in that some people have the farmland which is less than 0.3 mu.

COMPENSATION CRITERIA OF LAND ACQUISITION AND HOUSEHOLD DEMOLITION IN THIS PROJECT

In this project, the compensation for requisitioned land and resettlement subsidy are as follows: RMB 26,296 per mu in Hongyan Township and Yuanba Township; RMB 24, 472 per mu in Wangjia Township; the compensation for non-farmland is 50% of the compensation standard.

Crop Compensation: if crops on requisitioned land will be harvested in spring and early summer, the compensation is equal to the overall value of output, namely RMB 579.6 per mu in Wangjia Township and RMB 622.8 per mu in Hongyan Township; if crops on requisitioned land will be harvested in autumn and winter, the compensation is equal to the overall value of output, namely RMB 708.4 per mu in Wangjia Township and RMB 761.2 per mu in Hongyan Township.

In this project, all demolished houses are made of clay and wood, and the compensation is in accordance with the highest standard, namely RMB 380 per m2.

BUDGET OF MIGRATION EXPENDITURE IN THIS PROJECT

In this project, the expenditure on migrant resettlement is about RMB 3,046, 500 (taxation excluded). Among the expenditure, the basic compensation directly paid to the affected people is RMB 2,519,000, the expense on management, supervision and evaluation is RMB 275, 600, and the unpredictable expense is RMB 251,900.

DRA CONSULTING TEAM 37 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) RESETTLEMENT OF LAND REQUISITION

People whose agricultural income is affected are only 29.62% of the overall affected people. Besides, the amount of requisitioned land is small, and the average farmland of each person is above 0.3mu. As a result, the land requisition could not reduce the affected people’s standards of production and living. Therefore, the monetary resettlement is enough to meet the resettlement demand of the affected people.

RESETTLEMENT OF HOUSE DEMOLITION

In this project, the house demolition is mainly in Wangjia Township, Yuanba District, and two resettlement approaches are provided for households whose houses are demolished: concentrated resettlement by self-construction and sparse resettlement by self- construction. The concrete arrangement is as follows:

Concentrated Resettlement by Self-Construction: the government requisitions the new house sites which will freely allocate to the households whose houses are demolished, according to the GFF 2009 No.10 File, namely a house for a household and 30 m2 for each person. The concentrated resettlement by self-construction has to be arranged in uniformity, and it has to be planned and constructed according to the standards of the ecologically well-being village. The infrastructure is constructed by the government.

Sparse Resettlement by Self-Construction: if peasants choose to build houses by themselves, the government will provide the free land of 30m2 for each person. Peasants have to apply for the land by themselves, and the expropriation unit will handle the procedures.

All houses demolished are made of clay and wood (on the old street), and the compensation is in accordance with the highest standard, namely RMB 380 per m2. At present, it cost RMB 210 per square meter to make house of clay and wood. Thus, those households whose houses are demolished can take advantage of compensation to rebuild their houses, and there is some money left.

PUBLICATION, PUBLIC CONSULTATION AND MONITORING

It is planned to publicize and promote the migrant resettlement plan in February, 2010.

In October, 2009, the household investigation and forum were applied to 50 affected households in order to know the affect of the land acquisition and house demolition as well as their wills and suggestions on project construction and resettlement. The public participated in all processes of this project through information publication, consultation, household survey and so on.

This project will monitor the whole process of land acquisition and migrant resettlement in two ways, the internal supervision and independent external supervision of the migrant resettlement institution. The progress and supervision condition will be reported to the World Bank periodically until the migrant resettlement comes to its end.

DRA CONSULTING TEAM 38 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Social Assessment

INTRODUCTION OF THE RESETTLEMENT AREA

There are totally 4affected people resettlement areas related to the sub project loan from the World Bank in Yuanba, there into, 2 in Yuanba downtown, 1 in Hongyan Township and 1 in Wangjia Township.

Oujiahe Resettlement Community lies in Yuanba Village of Yuanba Township, covering 18.93mu. 45 households are settled here, including 139 people, mainly are the affected people of May 12 Earthquake. The community is planned, designed and constructed by the government with the funds including post-quake reconstruction subsidies and that raised by the residents themselves. The infrastructures are built by the government too.

Limin Homestead Low-rental Resettlement Community covers 10mu. The government allocates the land to build 150 low-rental suits, covering 7,500 m2, so as to help those low- income households who cannot afford to build houses. The first phase including 48 suits has been finished.

Hongyan Township Resettlement Community includes 54 mu requisitioned collective land to settle down 254 affected people households. The community covers 120 mu and is built by the affected people themselves with the governmental grant in the same architectural style.

Wangjia Resettlement Community lies at the southern bank of Shiban River at Jizhen Township. It is arranged by the government and it accommodates 49 affected people households. All infrastructures such as roads, pipe network and green area are built by the government and are for free use.

Above-mentioned 4 resettlement areas accommodate 498 households including 1,637 people, hereinto, 157 households are urban households including 469 people, 273 are rural households, including 971 people, and the rest 68 households are relocated households including 197 people.

RESETTLEMENT HOUSE CONSTRUCTION AND ALLOCATION

Yuanba resettlement houses are mainly planed and constructed by the government as a whole.

The price of the resettlement houses in the three townships is checked and ratified on the basis of cost price and is publicized. For the affected people, the unit price to buy the resettlement houses is only RMB 1,050/ m2, while the average price of the same level houses is RMB 1,800 -2,000/ m2. In the meanwhile, the affected people also enjoy preferential tax policies.

Limin Homestead Low-rental Resettlement Community was built by the government in the same style with an average area of 50 m2, mainly for the low-income households after the earthquake, at a rental price of RMB 1/ m2/month for permanent residence. The government owns the houses.

RESETTLEMENT HOUSEHOLDS’ WILLINGNESS AND ABILITIES

In the initial project stage, Yuanba Bureau of Planning and Construction has carried out a survey on the willingness of 280 people among the 1,637 people of 498 households. The surveyed people all showed their willingness of moving into the resettlement community.

DRA CONSULTING TEAM 39 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Based on the compensation standards on damaged houses in Yuanba, the affected people households can get compensation of RMB 27,000 to 32,000 thousand on average. Besides, the government provides credit loan preference, namely, RMB 30,000 thousand for each family. So the total price of the resettlement houses is between RMB 45,000 to 75,000 thousand. Due to the governmental subsidies and the far lower price that the market price, affected peoples can choose to buy the houses based on their own minds, so it can be concluded that they are affordable.

To those low-income households, 150 suits of low rental have been planed for the residence of the vulnerable group.

LAND ACQUISITION AND COMPENSATION STANDARD

The resettlement area involves 102.83 mu acquired land, including 27.4 mu farmland and 75.43 mu construction land. The compensation of the acquired land consists of three parts: land compensation. The acquired farmland is compensated on the basis of 10 times of the annual average output of 3 years ago. Resettlement subsidies, which are calculated on the following basis: as for the per capita farmland over 1 mu, each mu is compensated on the basis of 6 times of the annual average output of 3 years ago; as for the per capita farmland below 1 mu, every resettlement-involved person is compensated on the basis of 6 times of the annual average output of 3 years ago; (the annual average output of Yuanba Township and Hongyan Township 3 years ago were RMB 1,384/mu, and of Wangjia Township, it was RMB 1,288/mu). The land compensation and resettlement subsidies of requisitioned non-farmland are calculated on a half basis of the above. Crop compensation, which is fulfilled as follows: if it is winter crop to be harvested in the current season, all shall be compensated on the basis of its output: RMB 579.6/ mu in Wangjia Township and RMB 622.8/mu in Yuanba Township and Hongyan Township; if it is spring crops, all shall be compensated on the basis of its output: RMB 708.4/ mu in Wangjia Township and RMB 761.2/mu in Yuanba Township and Hongyan Township.

HOUSE DEMOLITION, RELOCATION AND SETTLEMENT

The resettlement area needs to accommodate 68 relocated households with a house demolition of 7,280 m2.

The relocated households are involved in the wholly planned resettlement community. The house area is based on per capital 35 m2 residence and 10 m2 façade. Besides, the relocated households can also buy houses on the basis of per capita 35 m2 and 10 m2 façade at the cost price of RMB 1,050/m2.

PUBLIC PARTICIPATION

In the early stage of choosing the resettlement area, Yuanba Bureau of Planning and Construction carried out survey about and indoor visits to the affected peoples. Colloquia were held with the affected peoples (Colloquia Minutes are in Table 6-2) to survey their willingness on moving into the resettlement area and whether they are satisfied about the location. In addition, it also introduced the supporting policies, subsidies policies and resettlement manners for the vulnerable groups, so that the affected peoples have participated in the preparation of the project.

This will ensure a satisfactory and legal project implementation.

DRA CONSULTING TEAM 40 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Public Consultation & Information Disclosure

PUBLIC CONSULTATION

In accordance with the World Bank policies, two rounds of public consultation have been conducted during the preparation of the environmental impact assessment. Special focus has been put on the project-affected enterprises, residents and beneficiaries of different age groups, genders, educational backgrounds and occupations as well as other stakeholders.

As indicated in the results, the investigation scope also included key sensitive receptors along the proposed bridge. Therefore, the results for this investigation were representative.

TABLE 0-1: SUMMARY OF PUBLIC CONSULTATION FOR YUANBA SUBPROJECT

Key No. Methods Organizer Date Location Results participants 1. Solid Waste Component 100% of the people investigated show their support to the project implementation; 100% of the people investigated interviewed thought that the project implementation would be good for development of local economy and improvement of natural and ecological environment. 98% persons interviewed thought 100 project Questionna 2009- that project implementation would have 1 affected ire 11 positive impacts on local economic residents Project development and 2% persons interviewed PIU, EA area in thought that project implementation might have consultants Yuanba positive impacts on local economic District development, which showed that local public in Yuanba District thought that project implementation would greatly improve the environment. The meeting participants generally show their support to the project, however, the directly Project affected 2009- 2 Meeting affected people also indicate their concern on residents 11-28 the possible environmental impacts and the implementation of proper mitigation measures. 2. Wastewater Component

DRA CONSULTING TEAM 41 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Key No. Methods Organizer Date Location Results participants 100% of the people investigated thought the project implementation is good for the improvement of local living conditions; 98% of them thought the project implementation would have positive impacts on local economic development; only 2% were not aware of the project implementation. 98% persons interviewed from Hongyan Town was dissatisfied with baseline water quality of local surface water i.e. Shiban River; 60 project 18 persons interviewed from Wangjia Town Questionna 1 affected was dissatisfied with baseline water quality of ire residents local surface water i.e. Jialing River and 14 Project persons interviewed from Wangjia Town was PIU, EA 2009- area in satisfied with baseline water quality of local consultants 11 Yuanba surface water i.e. Jialing River. District The persons interviewed from Wangjia and Hongyan Town thought that project implementation would have positive impacts on protection of local surface water bodies, which showed that the local residents in Wangjia and Hongyan Towns thought that project implementation would be good for improvement of local environment. Make the public and groups around the proposed project area informed of project Project affected 2 Meeting construction progress, potential environmental residents impacts and let them make useful comments and suggestions. 3. Water Supply Component 100% persons interviewed supported project implementation. 100% persons interviewed thought that the project implementation would be good for development of local economy and improvement of natural and ecological Wangjia 50 project environment. 100% persons interviewed Questionna 2009- Town and 1 affected thought that project implementation would ire 12-9 Hongyan residents have positive impacts on local economic Town development and improve local job conditions, PIU, EA which showed that the local residents in consultants Wangjia and Hongyan Towns though that project implementation would be good for improvement of local environment. PMO at the The meeting participants show their strong District support to the project. Project affected 2009- Planning 2 Meeting residents 11-28 and Constructi on Bureau 4. Road Component All interviewed persons were aware of importance of project implementation. 20 project Questionna 2009- 1 affected Project 80% persons interviews supported project ire 10-30 PIU, EA residents area in implementation greatly which showed that consultants Yuanba project implementation would be consistent District with the public’s wish. Project affected 2009- The meeting participants show their strong 2 Meeting residents 10-30 support to the project.

DRA CONSULTING TEAM 42 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) In conclusion, the local public supported project implementation which showed that the public would have intensive awareness of environmental protection together with developing economy.

INFORMATION DISCLOSURE

The project information, including project background, key potential environmental issues, name of local PIU and their contact information, name of EIA consultants in charge and their contact information, and and the way to make comments, has been disclosed twice, as presented below.

TABLE 0-2: SUMMARY OF INFORMATION DISCLOSURE FOR YUANBA SUBPROJECT

No. Name of Project Documents Date Location 1. Solid Waste Component 1 Project Information on Solid Waste 2009-11-05 Website of Yuanba District Government Component of Yuanba District under of Guangyuan Municipality Batch 2, WERP http://www.gyyb.gov.cn 2 Main conclusions of the EIA Report for 2009-12-03 Website of Yuanba District Government Solid Waste Component of Yuanba of Guangyuan Municipality District under Batch 2, WERP http://www.gyyb.gov.cn 2. Road Component 1 Project Information on Road Component 2009-11-26 Website of Yuanba District Government of Yuanba District under Batch 2, WERP of Guangyuan Municipality http://www.gyyb.gov.cn/article.asp?id=1 24459 2 Main conclusions of the EIA Report for 2009-12-4 Website of Yuanba District Government Road Component of Yuanba District under of Guangyuan Municipality Batch 2, WERP http://www.gyyb.gov.cn/Article.asp?id=1 24760 3. Water Supply Component 1 Project Information on Water Supply 2009-12-01 Website of Yuanba Government Component of Yuanba District under Administration http://www.gyyb.gov.com Batch 2, WERP 2 Main conclusions of the EIA Form for 2009-12-07 Website of Yuanba Government Water Supply Component of Yuanba Administration http://www.gyyb.gov.com District under Batch 2, WERP 4. Wastewater Component 1 Project Information on Wastewater 2009-11-25 Website of Yuanba District Government Component of Yuanba District under of Guangyuan Municipality Batch 2, WERP http://www.gyyb.gov.cn/article.asp?id=1 2475 2 Main conclusions of the EIA Form for 2009-12-01 Website of Yuanba District Government Wastewater Component of Yuanba District of Guangyuan Municipality under Batch 2, WERP http://www.gyyb.gov.cn/article.asp?id=1 24458

DRA CONSULTING TEAM 43 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Environmental Management Plan

The Environmental Management Plan (EMP) covers all phases of the Project from preparation to construction and to commissioning and operation. They aim to ensure control of the environmental impacts through implementation of monitoring and mitigation activities. The full EMP of the Project will be incorporated into the construction and operation management plans of the Project as appropriate and will form part of the bidding documentation.

During project preparation and implementation, organizations with different environmental management responsibilities, such as PPMO, EPBs, Design Institutes, contractors and construction supervision companies have been or will be involved in environmental management. PPMO, contractors and IAs will be required to appoint dedicated and qualified environmental specialists to oversee environmental management activities and ensure implementation of the EMP.

ORGANIZATION

During project preparation and implementation, these various organizations with different environmental management responsibilities have been or will be involved in the environmental management activities. PMOs, contractors and IAs, will each nominate dedicated and qualified environmental specialists to undertake environmental management activities and ensure effective implementation of the EMP.

The Provincial PMOs will ensure that the Project’s progress and impacts are monitored and reported in line with WB’s requirements. The effectiveness of mitigation measures and monitoring results will be evaluated through the feedback reporting system. Corrective actions in responding to monitoring results will be taken as necessary. Concerned EPBs and PMOs will play critical roles in this feedback and corrective mechanism.

For consistency and cost management during construction activities, it is recommended that concerned cities rely on a common CSC for the environmental supervision and monitoring. In such situation, consolidation of monitoring data and dissemination of common rules and practices regarding environmental management will be strongly facilitated, and their efficiency improved.

The EMP provides detailed procedures for information exchange, reporting, data management and non-compliance resolution.

ENVIRONMENTAL MONITORING PLAN

The detailed environmental monitoring plans for the components of Yuanba Subproject for the construction and operation periods are respectively presented in the following sections:

Construction Period

TABLE 0-1: MONITORING PROGRAM DURING CONSTRUCTION Environmental Monitoring Monitoring Monitoring Location Monitoring Item Applicable Standard Element Frequency Institute Solid Waste Air Construction sites of TSP, NO2, SO2 Once/month Class II Standard of Guangyuan landfill site and waste 2 days/time GB3095-1996 Municipal transfer stations Twice/day Monitoring Noise Construction site of Leq One day a month, Standard GB12523-2008 Station landfill site once at night and once at daytime

DRA CONSULTING TEAM 44 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Environmental Monitoring Monitoring Monitoring Location Monitoring Item Applicable Standard Element Frequency Institute Wastewater Component Noise Plant boundaries of Leq One day a month, Standard GB12523-90 Guangyuan Wangjia and Hongyan once at night and Municipal Towns WWTPs once at daytime Monitoring Station Water Supply Component Air Residential areas TSP, NO2, SO2 One round for two Class II Standard of Guangyuan around construction days every two GB3095-1996 Municipal sites months, twice a day Monitoring Noise Construction sites of Leq One day a month, Standard GB12523-90 Station proposed network. once at night and once at daytime Road Component Air Residential areas TSP One round for two Class II Standard of Guangyuan around proposed roads days every two GB3095-1996 Municipal and construction sites. months, twice a day Monitoring Noise Construction site of Leq One day a month, Standard GB12523-90 Stationà proposed roads once at night and once at daytime

Operation Period

TABLE 0-2: MONITORING PROGRAM DURING OPERATION Environmental Monitoring Monitoring Monitoring Item Monitoring Frequency Applicable Standard Element Location Institute Solid Waste Three times during wet, Class I standard GB8978- Guangyuan Upstream pH, COD, dry and medium periods 1996 Municipal 200m from BOD, NH4-N, within one year after Monitoring effluent on Total P, Cr6+, operation; Station Wangjiawan Hg, Cd, As, Pb, Ditch fecal coliform, Twice during dry and Cl- wet periods after 1st year operation Surface Water Install automatic Class I standard GB8978- Outfall of pH, SS, COD, monitoring and control 1996 leachate BOD5, NH3-N, equipments and connect treatment TN with the monitoring and station control network of local environmental protection departments Once prior to operation; Standard GB16889-2008 drainage well: at least once every week after pH, total operation; 4 monitoring hardness, SS, monitoring well: at least wells around CODmn, NH4- once every two weeks site and the N, NO3-, NO2-, baseline monitoring downstream sulphate, Cl-, Groundwater well: at least once a well of No.4 Volatile phenol, month until pollutant Community in cyanide, As, Hg, concentration in Xingshu Cr6+, Pb, F, Cd, leachate to be generated Village Fe, Mn, Cu, Zn, after site disclosure is fecal coliform lower than the value specified by GB16889- 2008 for successive two years Noise 3-4 monitoring Leq Once every half year Class II standard GB points around 3096-2008 plant boundaries

DRA CONSULTING TEAM 45 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Environmental Monitoring Monitoring Monitoring Item Monitoring Frequency Applicable Standard Element Location Institute Air Proposed NH3, H2S, TSP, NH3, H2S, TSP: once Class II standard project site CH4 prior to operation, and GB16297-1996 one every season during Class II standard operation. GB14554-93 CH4: once a day Around the Once per quarter after transfer station project operation Wastewater Component Wastewater Effluents of pH, COD, 12 rounds every year, Class I standard GB8978- Guangyuan Wangjia Town BOD5, DO, twice a day 1996 Municipal and Hongyan NH4-N, SS and Monitoring WWTPs total phosphor Station Noise Leq Four rounds every year, Class II standard GB once at night and once 3096-2008 at daytime Water Supply Component Wastewater Jialing River pH , SS, DO, One round every April, Class I standard GB8978- Guangyuan CODCr, NH4-N, July and December, 1996 Municipal fecal coliform, twice a day Monitoring Petroleum Station Noise Central Health Leq Four rounds every year, Class II standard GB Guangyuan Clinic of once at night and once 3096-2008 Municipal Wangjia Town, at daytime Monitoring Wangjia Town Station Primary School, Central Health Clinic of Hongyan Town and Hongyan Town Primary School Road Component Wastewater Effluent on COD, BOD, SS, One round every April, Class I standard GB8978- Guangyuan Changtan River PH, NH4-N July and December, 1996 Municipal twice a day Monitoring Station Noise No.1 Changba Leq Four rounds every year, Class II standard GB and Yuanba once at night and once 3096-2008 Villages, at daytime Wangjia and Hongyan Towns Central Health Clinics and Primary Schools

CAPACITY BUILDING

Before commencement of construction, Technical Assistance to LUCRPO will be provided to prepare training material on (i) environmental management during construction activities (ii) environmental standards (iii) WB safeguards (iv) monitoring of water, air, noise at construction sites, and (v) reporting. The same TA will provide training to CSCs, who in turn will deliver recommendations and environmental awareness to the Contractors appointed representative(s).

During construction, specialized environmental and monitoring training will be delivered to the IAs that will be responsible for operation of the WS, WW or SW facilities (especially landfill sites).

DRA CONSULTING TEAM 46 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) BUDGET ESTIMATE AND SOURCE OF FUNDING

The budget estimate and source of funding for individual components of Yuanba Subproject are presented in the following tables.

TABLE 0-3: BUDGET OF EMP FOR SOLID WASTE COMPONENT OF YUANBA SUBPROJECT DURING CONSTRUCTION

Item Annual Budget (RMB) Budget for2 years Source of Fund (rmb) (rmb) PMU Operation (including salary, office and 30000 60000 PMC transportation expense) Water quality monitoring / / CMSC Air quality and noise monitoring 5400 10800 CMSC Monitoring of relics protection 0 / CMSC Budget for supervision engineers (on environmental 100000 200000 CMSC monitoring, including salary, office and transportation expenses) Capacity building 20000 40000 CMSC Total 155400 300800 - Note: It covers the EMP budget for both the landfill site and the transfer station.

TABLE 0-4: BUDGET OF EMP FOR SOLID WASTE COMPONENT OF YUANBA SUBPROJECT DURING OPERATION

ITEM ANNUAL BUDGET 3 YEAR BUDGET SOURCE OF FUNDS (RMB) (RMB)

PMU Operation / / / Water and Noise Quality Monitoring Laboratory analysis 30000 90000 PMC Sampling staff wages / / PMC Total WQ Monitoring 30000 90000 PMC Air and Noise Monitoring Landfill Laboratory analysis 10000 30000 PMC Site Sampling staff wages / / PMC Total Air Noise Monitoring 10000 30000 PMC Transfe Laboratory analysis 5000 15000 PMC r Sampling staff wages / / PMC Station Total Air Noise Monitoring 5000 15000 PMC Archaeological Monitoring / / Routine Follow up for WW PMC Provision for special studies PMC Total Archaeological Monitoring PMC Supervision Engineer Budget (Environmental Monitoring) Salaries CMSC Office operation costs CMSC Transportation CMSC Total SE Budget CMSC Capacity Building / / / Provision Total Operation Budget for EMP 45000 135000 -

DRA CONSULTING TEAM 47 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) TABLE 0-5: BUDGET OF EMP FOR ROAD COMPONENT OF YUANBA SUBPROJECT DURING CONSTRUCTION

ITEM ANNUAL BUDGET BUDGET FOR 2 YEARS SOURCE OF FUND (RMB) (RMB) PMU Operation (including salary, office and 30000 60000 PMC transportation expense) Water quality monitoring / / lab analysis Salary of sampler Total 0 0 Air quality and noise monitoring Lab analysis 5400 10800 CMSC Salary of sampler Total 5400 10800 CMSC Monitoring of relics protection / / Regular monitoring special study Total 0 0 Budget for supervision engineers (on environmental 100000 200000 CMSC monitoring, including salary, office and transportation expenses) Capacity building 20000 40000 TAC Total 155400 300800 -

TABLE 0-6: BUDGET OF EMP FOR ROAD COMPONENT OF YUANBA SUBPROJECT DURING OPERATION

ITEM ANNUAL BUDGET BUDGET FOR 3 YEARS SOURCE OF FUND (RMB) (RMB) PMU Operation (including salary, office and transportation expense) Water quality monitoring / / lab analysis Salary of sampler Total 0 0 Air quality and noise monitoring Lab analysis 3000 9000 PMC Salary of sampler Total 3000 9000 PMC Monitoring of relics protection / / Regular monitoring special study Total 0 0 Capacity building Total 3000 9000 -

TABLE 0-7: BUDGET OF EMP FOR WATER SUPPLY COMPONENT OF YUANBA SUBPROJECT DRURING CONSTRUCTION

DRA CONSULTING TEAM 48 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

ITEM Annual Budget (RMB) Budget for 2 years Source of Fund (rmb) PMU Operation (including salary, office and 30000 60000 PMC transportation expense) Water quality monitoring / / lab analysis Salary of sampler Total 0 0 Air quality and noise monitoring Lab analysis 5400 10800 CMSC Salary of sampler Total 5400 10800 CMSC Monitoring of relics protection / / Regular monitoring special study Total 0 0 Budget for supervision engineers (on environmental 100000 200000 CMSC monitoring, including salary, office and transportation expenses) Capacity building 20000 40000 TAC Total 155400 300800 -

TABLE 0-8: BUDGET OF EMP FOR WATER SUPPLY COMPONENT OF YUANBA SUBPROJECT DRURING OPERATION

DRA CONSULTING TEAM 49 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

ITEM Annual Budget (RMB) Budget for 3 years Source of Fund (rmb) PMU Operation (including salary, office and transportation expense) Water quality monitoring lab analysis 800 2400 PMC Salary of sampler Total 800 2400 PMC Air quality and noise monitoring Lab analysis 2000 6000 PMC Salary of sampler Total 2000 6000 PMC Monitoring of relics protection / / Regular monitoring special study Total 0 0 Capacity building Total 2800 8400 -

TABLE 0-9: BUDGET OF EMP FOR WASTEWATER COMPONENT OF YUANBA SUBPROJECT DURING CONSTRUCTION

ITEM ANNUAL BUDGET BUDGET FOR 2 YEARS SOURCE OF FUND (RMB) (RMB) (RMB) PMU Operation (including salary, office and 5000 10000 PMC transportation expense) Water quality monitoring / / lab analysis Salary of sampler Total Air quality and noise monitoring Lab analysis 1000 2000 CMSC Salary of sampler Total 1000 2000 CMSC Monitoring of relics protection / / Regular monitoring special study Total 0 0 Budget for supervision engineers (on environmental 10000 20000 CMSC monitoring, including salary, office and transportation expenses) Capacity building 5000 10000 TAC Total 22000 44000 -

DRA CONSULTING TEAM 50 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Appendix 1 Bibliography No. Name of Document Author Date 1 EIA Report for Yuanba District Solid South-West Jiaotong University Mar. 2010 Waste Project under under Batch 2, WERP Environment College

2 EIA Report for Yuanba District Road South-West Jiaotong University Mar. 2010 Environment College Project under under Batch 2, WERP

3 EIA Form for Yuanba District Water South-West Jiaotong University Mar. 2010 Supply Project under under Batch 2, Environment College WERP

4 EIA Form for Yuanba District Wastewater South-West Jiaotong University Mar. 2010 Project under under Batch 2, WERP Environment College

5 Environmental Management Plan for South-West Jiaotong University Mar. 2010 Yuanba District Solid Waste Project under Environment College under Batch 2, WERP

6 Environmental Management Plan for South-West Jiaotong University Mar. 2010 Yuanba District Road Project under under Environment College Batch 2, WERP

7 Environmental Management Plan for South-West Jiaotong University Mar. 2010 Yuanba District Water Supply Project Environment College under under Batch 2, WERP

8 Environmental Management Plan for South-West Jiaotong University Mar. 2010 Yuanba District Wastewater Project under Environment College under Batch 2, WERP

9 Hydro-geo Survey Report for the Site of Sichuan Branch of Municipal Feb. 2010 Yuanba Domestic Solid Waste Landfill Survey and Research Institute Co., Ltd. Site in Yuanba Municipality

SICHUAN PPMO APPENDIX 1-1 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Appendix 2 Submitted Documents Related to Dam Safety of Yuanba WTP Component No. Name of Document Author Date 1 Preliminary Design for the Strengthening Sichuan Nanchong Water Oct. 2008 and Renovation of Xinhua Reservoir in Conservancy, Electricity and Yuanba District, Guangyuan Municipality Archetecture Survey, Design and Research Institute

2 Approval on the Preliminary Design for the Sichuan Provincial Department 2008 Strengthening and Renovation of Xinhua of Water Resources Reservoir in Yuanba District, Guangyuan Municipality (ChuanShuiHan [2008] No.1177)

3 Notification on the Implementation Plan The People’s Government of 2009 for the Renovation of Xinhua Reservoir in Wangjia Town, Yuanba Yuanba District, Guangyuan Municipality District, Guangyuan by the People’s Government of Wangjia Municipality Town (WangFuFa [2009] No.71)

4 Evaluation Report on Dam Safety of Nanchong Water Conservancy Dec. 2007 Xinhua Reservoir and Hydropower Survey and Design Institute

SICHUAN PPMO APPENDIX 1-2 APRIL 2010 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Appendix 3 Environmental Standards 1. ENVIRONMENTAL QUALITY STANDARDS

ENVIRONMENTAL AIR QUALITY STANDARDS

Environmental Air Quality Standard (GB3095ü1996) with regulation GB3095-96 for Fluoride and standard for maximum concentration of Chlorine from Industry Designing Sanitary Standards (TJ36-1979).

ENVIRONMENTAL AIR QUALITY STANDARDS

CONCENTRATION LIMITS POLLUTANTS SOURCE OF STANDARDS AND UNITS 1 HOURLY DAILY YEARLY AVERAGE AVERAGE AVERAGE

SO2 0.50 0.15 0.06 (GB3095ü1996) Nox 0.15 0.10 0.05 (mg/Nm3) TPS 0.30 0.20

Fü 7 20 (GB3095ü1996) (µg/m3)

3 Cl2 0.10* 0.03 (TJ36ü79)(mg/Nm ) Ammonia 1.20 Referring to highest allowable concentration of living quarters as per industrial design H2S 0.01 sanitation standard

ENVIRONMENTAL QUALITY STANDARDS FOR SURFACE WATER

Surface Water Quality Standards (GB3838ü2002) are presented in the following table. Some parameters not covered by this standard adopt the Class I of the Fishery Water Quality Standards (GB11607ü89) and of the Waste Water Comprehensive Emission Standards (GB8978ü1996).

ENVIRONMENTAL QUALITY STANDARDS OF SURFACE WATER (GB3838-2002) UNIT: MG/L (EXCLUDING PH)

Ref Pollutants Class I Class II Class III Class IV Class V 1 pH 6 to 9 6 to 9 6 to 9 6 to 9 6 to 9 DO 7.5 6 5 3 2 2 (or 90% sat) ≤ 3 COD Mn 2 4 6 10 15 ≤ 4 CODCr 15 15 20 30 40 ≤ 5 BOD5 3 3 4 6 10 ≤ 6 N-NH3 0.015 0.5 1.0 1.5 2.0 ≤ 7 Total Phosphorus (P) 0.02 (0.01)* 0.1 (0.025)* 0.2 (0.05)* 0.3 (0.1)* 0.4 (0.2)*

SICHUAN PPMO APPENDIX 2-1 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Ref Pollutants Class I Class II Class III Class IV Class V ≤ 8 Total Nitrogen (N) 0.2 0.5 1.0 1.5 2.0 ≤ 9 Copper (Cu) 0.01 1.0 1.0 1.0 1.0 ≤ 10 Zinc (Zn) 0.05 1.0 1.0 2.0 2.0 ≤ 11 Fluoride (F) 1.0 1.0 1.0 1.5 1.5 ≤ 12 Selenium (Se) 0.01 0.01 0.01 0.02 0.02 ≤ 13 Arsenic (As) 0.05 0.05 0.05 0.1 0.1 ≤ 14 Mercury (Hg) 0.00005 0.00005 0.0001 0.001 0.001 ≤ 15 Cadmium (Cd) 0.001 0.005 0.005 0.005 0.01 6+ ≤ 16 Chromium (Cr ) 0.01 0.05 0.05 0.05 0.1 ≤ 17 Total lead (Pb) 0.01 0.01 0.05 0.05 0.1 - ≤ 18 Total cyanide (CN ) 0.005 0.05 0.2 0.2 0.2 ≤ 19 Volatile phenol 0.002 0.002 0.005 0.01 0.1 ≤ 20 Oil 0.05 0.05 0.05 0.5 1.0 ≤ 21 Anionic detergent 0.2 0.2 0.2 0.3 0.3 ≤ 22 Sulphide 0.05 0.1 0.2 0.5 1.0 ≤ 23 Coli forms (number/L) 200 2000 10,000 20,000 40,000 *Value within bracket for lakes and reservoirs *Fishery water quality standards, ** Class 1 of Waster water comprehensive emission standards

ENVIRONMENTAL QUALITY STANDARDS FOR NOISE

Class Two standard of Urban Area Environmental Noise Standards GB3096-1995, applies to residential, commercial and industrial mixed area. Class Four of Urban Area Environmental Noise Standards GB3096-1995, applies to zones within 10 m on both sides of traffic roads.

NOISE STANDARDS OF URBAN AREA

Types Day Unit ; [Leq[dB(A)] Night [Unit ; Leq[dB(A)] 0 50 45 1 55 45 2 60 50 3 65 55 4 70 55

Standard for Noise Levels at the Boundary of Industrial Enterprises, Category II (GB12348- 90) applies to urban environmental infrastructure subprojects and environment subprojects. To the boundary close to traffic trunk lines, Category IV applies, which means the equivalent noise level at daytime is 70dBA, that at night 55dBA.

NOISE STANDARDS AT INDUSTRIAL AREA BORDER

Standard Category Applicable Zone Daytime Nightime (GB12348-90) Category II Boundaries of plants in industrial parks (dBA) 60 50 Boundaries close to traffic trunk lines in (GB12348-90) Category IV 70 55 industrial parks (dBA)

SICHUAN PPMO APPENDIX 2-2 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

2. EMISSION STANDARDS

WASTE WATER

Waste water treatment plant effluents must conform to the National Comprehensive Emission Standards of Waste Water (GB8978-1996), as presented below.

Class One shall apply to any effluent discharged into natural water bodies, and Class Three to those discharged to the sewers.

COMPREHENSIVE EMISSION STANDARDS OF WASTE WATER (UNIT MG/L EXCEPT PH)

Ref. Pollutant Class One Class Three 1 PH 6 to 9 6 to 9 2 SS ≤70 ≤400

3 CODCr ≤100 ≤500 4 BOD5 ≤20 ≤300 5 Oil ≤5 ≤20 6 P ≤0.1 ≤0.3

7 N-NH3 ≤15 ü 8 Volatile hydroxybenzene ≤0.5 ≤2.0 9 Sulfide ≤1.0 ≤1.0 10 Fluoride ≤10 ≤20 11 Total Cu ≤0.5 ≤2.0 12 Total Zn ≤2.0 ≤5.0 13 Total Mn ≤2.0 ≤5.0 14 Total Hg* ≤0.05 ≤0.05 15 Total Cd* ≤0.1 ≤0.1 16 Total Cr* ≤1.5 ≤1.5 17 Cr6+* ≤0.5 ≤0.5 18 Total As* ≤0.5 ≤0.5 *Adopts maximum acceptable emission concentration

For effluents discharged out of sewage treatment plants, Standard B of Class I in “Standard for Pollutant Discharge of Sewage Treatment Plants in Cities and Towns” (GB18918-2002) (enforced on July 1, 2003) shall apply, as shown in following Table.

SICHUAN PPMO APPENDIX 2-3 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

HIGHEST ALLOWABLE DISCHARGE CONCENTRATION OF WATER POLLUTANTS FROM SEWAGE TREATMENT PLANTS (DAILY AVERAGE) UNIT: MG/L

Grade I Standard Grade II Grade III No. Basic Controlled Item Standard A Standard B Standard Standard 1 COD 50 60 100 1201)

1) 2 BOD5 10 20 30 60 3 Suspended solid (SS) 10 20 30 50 4 Animal & plant oil 1 3 5 20 5 Petroleum 1 3 5 15 6 Negative ion surface active agent 0.5 1 2 5 7 Total nitrogen (as N) 15 20 - - 2) 8 NH3-N (as N) 5 (8) 8 (15) 25 (30) -

Total P Built before Dec., 2005 1 1.5 3 5 9 (as P) Built before Jan. 1, 2006 0.5 1 3 5 10 Color (dilution magnitude) 30 30 40 50 11 pH 6~9 12 Bacillus coli (count/l) 103 104 104 -

Notes: 1) Removal rate indicators shall be higher than 60% when inlet water COD is higher than 350mg/l, higher than 50% when BOD is higher than 350mg/l; 2) Values outside brackets refer to controlled values when water temperature is >12°C, those inside refer to controlled values when water temperature is ≤12°C.

Highest Allowable Discharge Concentration of Part of Category I No. Standard Value, mg/l Pollutants (Daily Average) 1 Total Hg 0.001 2 Total Cr 0.1 3 Hexavalent Cr 0.05 4 Total Pb 0.1

Highest Allowable Discharge Concentration of Selected Controlled No. Standard Value, mg/l Items (Daily Average) 1 Total Ni 0.05 2 Total Be 0.002 3 Total Cu 0.5 4 Total Zn 1.0 5 Total Mn 2.0 6 Volatile phenol 0.5 7 Total cyanide 0.5 8 Formaldehyde 1.0 9 Benzene 0.1

SICHUAN PPMO APPENDIX 2-4 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) 10 Toluene 0.1

AIR EMISSION

Air emission adopts Comprehensive Emission Standards of Air Pollutant (GB16297-1996).

Grade II and Standard for Pollutant Discharge of Sewage Treatment Plants in Cities and Towns (GB18918-2002), Grade II shall apply.

STANDARD FOR AIR POLLUTANT DISCHARGE

Standard, Grade Pollutant Concentration Limit, mg/m3 Pollutant Discharge Limit (mg/m3), Fume Blackness (Lingman Grade) and Stack Height (m) Standard for air pollutant discharge of SO TSP Fume Metal Rolling, Forging, 2 Stack industrial furnaces & Discharge Discharg Blacknes Reheating Furnace, Height kilns Heat Treatment Limit e Limit s Furnace 850 200 1 15 Pollutan Highest Allowable Pollutant Highest Allowable Discharge Rate, t Discharge Concentration, mg/m3 kg/h

SO2 550 2.6~170 (exhaust duct 15~100m high) Standard NOx 240 0.77~52 (exhaust duct 15~100m high) for integrated TSP 120 3.5~8.5 (exhaust duct 15~60m high) air Pollutan pollutant Monitored Uncontrolled Discharge Concentration, mg/m3 discharge, t Grade II SO2 Highest concentration outside perimeter: 0.40 NOx Highest concentration outside perimeter: 0.12 TSP Highest concentration outside perimeter: 1.0

HIGHEST ALLOWABLE WASTE GAS DISCHARGE CONCENTRATION AT THE BOUNDARY (EDGE OF PROTECTIVE BELT) OF SEWAGE TREATMENT PLANTS UNIT MG/M3

No. Controlled Item Grade I Standard Grade II Standard Grade III Standard 1 Ammonia 1.0 1.5 4.0

2 H2S 0.03 0.06 0.32 Odor concentration 3 10 20 60 (dimensionless) Methane (highest volumetric 4 0.5 1 1 percentage in the plant, %)

SICHUAN PPMO APPENDIX 2-5 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

NOISE

Construction noise adopts Limiting Values in Construction Area (GB12523ü90) standards.

NOISE LIMITING VALUES IN CONSTRUCTION AREA UNIT: LEQ(DB(A))

Limiting values Construction period Main noise sources Day Night Cubic meter of earth and Bulldozer, grab, loading truck 75 55 stone Piling Various pile driver 85 Ban Concrete mixer, vibrating tamper, Construction 70 55 electrical saw, etc. Fitting Crane, elevator, etc 65 55

SICHUAN PPMO APPENDIX 2-6 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Appendix 4 Figures and Drawings

SICHUAN PPMO APPENDIX 4-1 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 1: Land for the Resettlement of Earthquake Affected People near Road Component in Oujiahe residential area, Yuanba Subproject



SICHUAN PPMO APPENDIX 4-2 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 2: Layout of Road Component in Wangjia Town

SICHUAN PPMO APPENDIX 4-3 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 3: Layout of Road Component in Hongyan Town



SICHUAN PPMO APPENDIX 4-4 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 4: Monitoring Points in the Urban Area of Yuanba District

Surface Water Monitoring

Noise Monitoring

SICHUAN PPMO APPENDIX 4-5 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

Figure 5: Layout of Water Supply Pipes in Hongyan Town

SICHUAN PPMO APPENDIX 4-6 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 6: Location of Hongyan WTP

P Water Hongyan Original P - WTP Clean taking Water Tank

 P P 

Lijiaba Residential Village Area Road

Lijiaba Residential Area

SICHUAN PPMO APPENDIX 4-7 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 7: Location of Wangjia WTP

Reservoir

Mountai n Weiwan g Road

WTP

Residen tial Area

Town

SICHUAN PPMO APPENDIX 4-8 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 8: Location for Monitoirng Points of Wangjia WWTP

N Mountai n

Field Æ Wangjia WWTP  Æ

Æ Farmer Field House

Noise Monitoring Point

SICHUAN PPMO APPENDIX 4-9 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP) Figure 9: Location for Monitoirng Points of Hongyan WWTP

Residential N House of Pu Runyuan under

Construction Æ  Æ  -LDOLQ JÃ 5LYHU

Æ  Hongyan WWTP Æ

Noise monitoring point

SICHUAN PPMO APPENDIX 4-10 AUGUST 2009 Summary Environmental Impact Assessment for Yuanba Subproject under Batch 2 of Wenchuan Earthquake Recovery Project (WERP)

SICHUAN PPMO APPENDIX 4-11 AUGUST 2009