MAJOR PROJECTS
MAJOR PROJECTS IN-PROGRESS
Group's Commencement Anticipated Client/Ultimate Description Interest Contract Value Date Completion Date Employer
HK$)
CONSTRUCTION WORKS
Disciplinary Staff Quarters at 60% 2,090,000,000* January 1999 September 2001 Architectural Services Lee On Road, Kwun Tong Department
IL 8969 Cyberport Development at 100% 1,251,324,000 June 2001 May 2003 Cyber-Port Limited Telegraph Bay, Pokfulam, Hong Kong Ð Contract C3/C4
Tseung Kwan O Area 73A Phase 4 100% 729,572,000 April 2001 July 2003 Hong Kong Housing Authority
Residential Development at 100% 550,189,000 April 2000 March 2002 Hong Kong Housing Society TMTL 384 Area 4C
Lai Chi Kok Phase 1 100% 511,121,000 February 1999 August 2001 Hong Kong Housing Authority
Redevelopment of Kwai Fong Estate 100% 336,811,000 February 2000 May 2002 Hong Kong Housing Authority Phase 7
Residential Development at 100% 188,953,000 November 1999 June 2001{ Dorfit Properties Limited 5±7 Blue Pool Road, Happy Valley
Development of Kwai Shing East 100% 187,203,000 November 2000 August 2002 Hong Kong Housing Authority Estate Phase 7
Shek Lei Estate Phase 12 100% 168,600,000 April 2001 June 2003 Hong Kong Housing Authority
CIVIL ENGINEERING WORKS
Sewage Treatment Plant at Cyberport 100% 178,451,000* July 2000 July 2002 Carlyle International Limited Development, Telegraph Bay
Roads and Associated Engineering 100% 65,397,000 November 2000 January 2003 Territory Development Works for Hung Shui Kiu North Department Phase 1
FOUNDATION WORKS
Bored Pile Works for Disciplinary 92.8% 98,000,000# January 1999 December 1999{ Architectural Services Staff Quarters at Lee On Road, Department Kwun Tong
Substructure Works for 92.8% 32,000,000 May 2000 April 2001{ Henderson Real Estate Proposed Redevelopment at Agency Limited 166±167 Wai Yip Street and 66 How Ming Street
Bored Pile and Pre-bored H-Pile 92.8% 30,378,000# August 2000 May 2001{ Carlyle International Limited Works for Sewage Treatment PlantattheCyberport Development, Telegraph Bay
Bored Pile Work for Development 92.8% 25,358,000 February 2000 August 2001 Great Eagle Holdings Limited/ Scheme K2 at Argyle Street/ Land Development Shanghai Street ± Site B Corporation
89 MAJOR PROJECTS continued)
MAJOR PROJECTS IN-PROGRESS continued)
Group's Commencement Anticipated Client/Ultimate Description Interest Contract Value Date Completion Date Employer
HK$)
FOUNDATION WORKS continued)
Minipile and Pre-bored H-Pile Works 92.8% 19,608,000 December 1998 September 1999{ The University of Hong Kong for Redevelopment of Lady Ho Tung Hall Phase I & II), The University of Hong Kong
Bored Pile Work for Senior Citizen 92.8% 15,300,000 September 2000 April 2001{ Hong Kong Housing Society Residence at Tseung Kwan O, Area 44, TKOTL 68
Bored Pile Works at 92.8% 12,000,000 June 2001 February 2002 Pak Hop Shing Company 377 Prince Edward Road Limited
BUILDING SERVICES WORKS
Cyberport Development at 50% 315,357,000 October 2000 July 2002 Cyber-Port Limited Telegraph Bay Contract C I Ð Building Services Installation
Design and Construction of 50% 34,153,000 February 2000 July 2001 Architectural Services Departmental Quarters for Department Towers7&8atLeeOnRoad, Kwun Tong Ð Electrical Installation
Student Hostels Phase I Development 50% 33,000,000 August 2000 March 2002 City University of Hong Kong for City University of Hong Kong Ð MVAC, Electrical and Fire Services Installation
A Primary School in Area 27 and A 50% 29,283,000 June 2000 May 2002 Architectural Services Primary School & A Secondary Department School in Area 101, Tin Shui Wai Ð MVAC and Electrical Installation
The Hong Kong Polytechnic 50% 26,936,000 May 1999 October 2001 The Hong Kong Polytechnic University Phase VI Development University Ð Electrical Installation
The Proposed Residential 50% 25,920,000 October 1999 July 2002 Sun Hung Kai Properties DevelopmentatTKOTL51, Limited Tseung Kwan O, Phase I & II Ð Podium MVAC and Residential A/C Installation
Tung Chung Station Development 50% 21,380,000 October 1999 April 2002 Tung Chung Station Package II Site 4 Phase 1 Development Company Ð MVAC Installation Limited
The Proposed Redevelopment of 50% 20,500,000 March 2000 August 2001 Club Lusitano Club Lusitano at 16 Ice House Street Ð Design, Supply and Install U/G Drainage, P&D, HVAC, Electrical and Fire Services Installation
90 MAJOR PROJECTS continued)
MAJOR PROJECTS IN-PROGRESS continued)
Group's Commencement Anticipated Client/Ultimate Description Interest Contract Value Date Completion Date Employer
HK$)
BUILDING SERVICES WORKS continued)
Senior Citizen Residence at 50% 19,243,000 May 2001 March 2003 Hong Kong Housing Society Tseung Kwan O Area 44 Ð Electrical and MVAC Installation
Redevelopment of Lady Ho Tung Hall 50% 19,100,000 September 1999 July 2001 The University of Hong Kong Phase I & II) of The University of Hong Kong Ð MVAC and Electrical Installation
Advance Engineering Infrastructure 50% 15,197,000 April 2000 October 2001 Territory Development WorksforPakShekKok Department Development Ð E&M Installation
Australian International School at 50% 13,682,000 December 2000 September 2001 Australian International School Norfolk Road, Kowloon Tong Foundations Limited Ð MVAC and Fire Services Installation
Proposed Residential Development 50% 12,078,000 November 1999 June 2001{ Sun Hung Kai Properties Phase 1) at TKOTL 55, Tseung Limited Kwan O Ð Podium MVAC for Areas other than Club House Installation Works Contract
91 MAJOR PROJECTS continued)
MAJOR PROJECTS COMPLETED DURING THE FINANCIAL YEAR AND SUBSEQUENT TO THE YEAR END
Group's Commencement Client/Ultimate Description Interest Contract Value Date Completion Date Employer
HK$)
CONSTRUCTION WORKS
Tung Chung Area 30 Phase 2 100% 905,127,000 July 1998 January 2001 Hong Kong Housing Authority
Tin Shui Wai Area 102 Phase 6 100% 614,364,000 July 1998 December 2000 Hong Kong Housing Authority
Tin Shui Wai Area 101 Phase 1 100% 600,086,000* December 1998 May 2001 Hong Kong Housing Authority
Redevelopment of Sau Mau Ping Estate 100% 409,826,000 November 1998 January 2001 Hong Kong Housing Authority Phase 8
Redevelopment of Kwai Fong Estate 100% 308,055,000 November 1998 November 2000 Hong Kong Housing Authority Phase 6
Redevelopment of Wang Tau Hom Estate 100% 280,429,000 January 1999 January 2001 Hong Kong Housing Authority Phase 14
FOUNDATION WORKS
Bored H-Pile Foundation & Pile Cap Work 92.8% 38,484,000 August 1999 August 2000 The Hong Kong Polytechnic for Student Hostels for The Hong University Kong Polytechnic University
Bored Pile, Pre-bored H-Pile and Pile Cap 92.8% 27,022,000 September 1999 January 2001 Anbok Limited forSoKwunWat,TuenMun
H-Pile Works for Shatin Racecourse 92.8% 13,540,000 May 1998 December 1999 The Hong Kong Jockey Club Redevelopment Ð Central Complex Phase 2 & 3
BUILDING SERVICES WORKS
Customs Building at Container Port Area 50% 37,730,000 March 1999 October 2000 Architectural Services Kwai Chung Ð MVAC Electrical & Fire Department Service Installation
School of Public Health & Auditorium for 50% 24,350,000 January 2000 May 2001 The Chinese University of The Chinese University of Hong Kong Hong Kong ÐMVACElectricalandFire Services Installation
The Second Primary School in Area 31 at 50% 11,884,000 February 1999 July 2000 Architectural Services Tin Shui Wai, N.T. Ð Building Services Department Installation
* Part of the contract has been sub-contracted to group companies # Sub-contract value being awarded by group companies { Awaiting certificate of completion
92