Coleshill to Footpath closure for work in your area December 2019 to Summer 2020

Lea Marston Nether A444 Whitacre Coleshill Substation Galley Common Hams Hall Common A446 LichfieldLichfield Rd Rd Station Road Road Ansley Distribution Park Furnace Shustoke Coleshill End Road Arley New Arley

Blythe Road Astley Coleshill Maxstoke Park Golf Club

Wood End

Fillongley Bedworth Maxstoke Smorrall M6 Lane Newdigate Ash Primary School Corley Ash A444 KEY Goodyers End M6 Lane Full refurbishment of the line Corley Ash Green (January-March 2020) Corley Moor Exhall

Earthwire replacement only Neal’s Green M6 (February and March 2020) Keresley Substation

Overhead line refurbishment work between Hams Hall substation near Coleshill and Coventry substation near Bedworth. The pylon Why are we doing it? route passes through Hams Hall National Distribution Park in To keep the network in first class working order and meet future Lea Marston, Shustoke, Fillongley, Wood End, Bedworth West, electricity demands Goodyers End and Exhall. Footpath closures What are we doing? This footpath is closed for the duration of our work to allow us • Work across a 20km (12.5 mile) route from substation to to access the pylon sites for netting, scaffolding and wire pulling. substations. This is in the interest of safety for users while our works take place. • Engineers working overhead The majority of the work is being done when the power supply • Your electricity supply will not be affected by the work is switched off between January to March 2020. The project is expected to be complete by summer 2020. • Full refurbishment of 60 pylons including the replacement of the wires, insulators and fittings and painting For more information visit https://www.nationalgridet.com/coleshill-bedworth

Keeping you informed If you have any questions about the essential maintenance work taking place, please call our Community Relations team on 0800 073 1047 or email [email protected] The Community Relations team is available seven days a week between 7am- 7pm.