The World Bank Report No: ISR12803

Implementation Status & Results China: Medium Cities Urban Transport Project (P111421)

Operation Name: China: Anhui Medium Cities Urban Transport Project Project Stage: Implementation Seq.No: 4 Status: ARCHIVED Archive Date: 18-Dec-2013 (P111421)

Public Disclosure Authorized Country: China Approval FY: 2010 Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Anhui Construction Management Offices Key Dates Public Disclosure Copy Board Approval Date 20-May-2010 Original Closing Date 31-Jan-2016 Planned Mid Term Review Date 12-Aug-2013 Last Archived ISR Date 10-May-2013 Effectiveness Date 09-Nov-2010 Revised Closing Date 31-Jan-2016 Actual Mid Term Review Date 12-Aug-2013

Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the project is to improve mobility on selected main corridors of the municipalities of , , L◆ an and in Anhui Province in a safe and efficient manner. Has the Project Development Objective been changed since Board Approval of the Project?

Public Disclosure Authorized Yes No

Component(s)

Component Name Component Cost Wuhu Municipality 148.17 Anqing Municipality 35.10 Lu'an Municipality 59.38 Huaibei Municipality 58.32 Capacity Building (CB) 1.20

Overall Ratings Previous Rating Current Rating Public Disclosure Authorized Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate

Public Disclosure Copy Implementation Status Overview The project implementation at Huaibe, Luan and Anqing goes well. In spite of the progress in field, the disbursement rate is still behind the schedule. With a few goods procurement

Page 1 of 8 Public Disclosure Authorized The World Bank Report No: ISR12803

move forward, the disbursement issue should be improved in the next few months. The project implementation at Huaibe, Luan and Anqing goes well. In spite of the progress in field, the disbursement rate is still behind schedule. With a few goods procurement moving forward, the disbursement issue should be improved in the next few months. NDRC has approved the feasibility study report for the City of Wuhu. Wuhu PMO is going through domestic procedure to submit restructuring request to MOF. Therefore, the peak of implementation is expected to take place around mid-2014. With the revised project components, such as public transport corridor improvement, procurement of clean fuel buses, and the construction of public transport parking/maintenance facilities, the mobility along selected corridor can be improved due to better bus condition and operation environment at wuhu.

Locations Country First Administrative Division Location Planned Actual China Anhui Sheng Wuhu Shi Public Disclosure Copy China Anhui Sheng Lu'an Shi

China Anhui Sheng Huaibei Shi

China Anhui Sheng Anqing Shi

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target ncreased bus ridership onkey corridor and Text Value 43 31 : Lower travel times by bus between Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 selected points (min) - Wuhu North-South transport corridor (from Tianmen Road to Comments No data Available due to the Eshan Road) slow restructuring

ncreased bus ridership onkey corridor and Text Value 12 9 urban area: Llower travel times by bus between Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 selected points (min) - Lu'an North-South Transport corridor (from Dabieshan Road to Comments To be updated upon the North Meishan Road) completion of the corridor

ncreased bus ridership onkey corridor and Text Value 30 27 urban area: Lower travel times by bus between Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 selected points (min) - Huaihai-Suixi Road transport corridor (from Dongganglou Comments To be updated. Interchange to Liuqiao Line) Public Disclosure Copy

Page 2 of 8 The World Bank Report No: ISR12803

ncreased bus ridership onkey corridor and Text Value 20 19 urban area Lower travel times by bus Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 between selected points (min) - Anqing North- South Transport Corridor (from Railway station Comments To be updated upon the to Yanjiangsi station completion of the corridor.

Increased bus ridership on key corridor and Text Value 135,400 increasing 20% urban area Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Annual bus ridership (urban area)(thousand) in Wuhu Comments No data collected due to restructuring Increased bus ridership on key corrdor and Text Value 44,100 73186 increase 30% urban area Date Public Disclosure Copy 31-Dec-2008 30-Nov-2013 31-Dec-2016 Annual bus ridership (urban area)(thousand) in Lu'an Comments

Increased bus ridership on key corridor and Text Value 65850 70982 increasing 20% urban area Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Annual bus ridership(urban area)(thousand) in Huaibei Comments Data is being cross checked.

Increased bus ridership on key corridor and Text Value 38,300 59901 increasing 30% urban area Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Annual bus ridership (urban area)(thousand) in Anqing Comments to be updated.

Increased bus ridership on key corridor and Text Value 210,000 600000 increasing 15% urban area Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Daily bus ridership on Wuhu North-South transport corridor Comments to be updated.

Increased bus ridership on key corridor and Text Value 50,000 95813 increasing 15% urban area Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Daily bus ridership on Lu'an North-South transport corridor Comments

Increased bus ridership on key corridor and Text Value 120,000 125300 increasing 10% urban area Date 31-Dec-2008 25-Mar-2013 31-Dec-2016 Daily bus ridership on Huaihai-Suixi Road transport corridor Comments To be updated.

Increased bus ridership on key corridor and Text Value 5,680 21796 increasing 20% urban area Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Daily bus ridership on Anqing North-South transport corridor Comments To be updated by March,

Public Disclosure Copy 2014

Page 3 of 8 The World Bank Report No: ISR12803

Safety on the corridor Number Value 17.00 77.00 12.00 Wuhu North-South transport corridor (Fatality Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 +Injury) Comments No data available Safety on the corridor Number Value 14.00 81.00 10.00 Lu'an North-South transport corridor (Fatality Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 +Injury) Comments Data should be double checked Safety on the corridor Number Value 36.00 34.00 18.00 Huaihai-Suixi Road transport corridor (Fatality Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 +Injury) Comments Data should be double Public Disclosure Copy checked Safety on the corridor Number Value 8.00 13.00 5.00 Anqing North-South transport corridor (Fatality Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 +Injury) Comments Data should be double checked

Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Coverage % population with access to bus stop Text Value 49%/77% 75%90% 50%/90% within 300/500 meters (city propoer) - Wuhu Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Coverage % population with access to bus stop Text Value 29%/85% 50%75% 50%/90% within 300/500 meters (city propoer) - Lu'an Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Coverage % population with access to bus stop Text Value 49%/72% 60%85% 50%/90% within 300/500 meters (city proper) - Huaibei Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Coverage % population with access to bus stop Text Value 41%/63% 48%75% 50%/90% within 300/500 meters (city proper)-Anqing Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of buses off-street parking spaces - Number Value 0.00 120.00 Public Disclosure Copy Lu'an Date 31-Dec-2008 31-Dec-2016

Page 4 of 8 The World Bank Report No: ISR12803

Comments No data yet due to slow implementation of parking facility Number of buses off-street parking spaces - Number Value 0.00 248.00 Huaibei Date 31-Dec-2008 31-Dec-2016 Comments No data yet due to slow implementation of parking facility Number of bus off-street parking spaces - Number Value 0.00 229.00 Anqing Date 31-Dec-2008 31-Dec-2016 Comments

Public Disclosure Copy No data yet due to slow implementation of parking facility Number of plans/strategies adopted using Number Value 0.00 3.00 outputs of Capacity Building component Date 31-Dec-2008 31-Dec-2016 Comments To be updated. Number of people completing study tours/ Number Value 0.00 17.00 40.00 training/seminars Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of buses in service in urban area - Number Value 803.00 990.00 1000.00 Wuhu Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of buses in servic in urban area -Lu'an Number Value 260.00 347.00 400.00 Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of buses in service in urban area - Number Value 287.00 320.00 500.00 Huaibei Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of buses in services in urban area - Number Value 292.00 401.00 500.00 Anqing Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March,

Public Disclosure Copy 2014

Page 5 of 8 The World Bank Report No: ISR12803

Number of km of old road reconstruction - Number Value 0.00 7.00 Huaibei (Huaihai Road, Suixin Road) Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of km of old road reconstruction - Number Value 0.00 5.00 Anqing (huixin Road, Shguang Road) Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Nubmer of km of new road completed - Wuhu Number Value 0.00 7.00 (Third Ring Road) Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Public Disclosure Copy Comments This indicator will be dropped To be updated by March, upon project restructuring. 2014 Number of km of new road completed - Lu'an Number Value 0.00 2.60 13.00 (Bagongshan Road, Xicheng Road, Pihenan Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Road, Longhezhong Road) Comments To be updated by March, 2014 Number of km of new road comleted - Huaibei Number Value 0.00 5.77 7.00 (Tuohe Road Cuifeng South Road) Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of km of new road completed - Anqing Number Value 0.00 0.62 1.50 (East Yanjiang Road) Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of safe pedestrian crossings Number Value 0.00 0.00 50.00 implemented - Wuhu Date 31-Dec-2008 31-Dec-2016 Comments No data available due to slow restructuring Number of safe pedestrian crossings Number Value 0.00 4.00 15.00 implemented - Lu'an Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Number of safe pedestrian crossings Number Value 0.00 30.00 implemented - Huaibei Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, Public Disclosure Copy 2014.

Page 6 of 8 The World Bank Report No: ISR12803

Number of safe pedestrian crossings Number Value 0.00 3.00 10.00 implemented - Anqing Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Distance between safe crossings (m): Wuhu Number Value 800.00 350.00 North-South Transport Corridor Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014 Distance between safe crossings (m): Lu'an Number Value 810.00 300.00 North-South Transport Corridor Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Public Disclosure Copy Comments To be updated by March, 2014 Distance between safe crossings (m) - Huaihai- Number Value 900.00 300.00 Suixi Road Transport Corridor Date 31-Dec-2008 25-Nov-2013 31-Dec-2016 Comments to be updated. Distance between safe crossings (m): Anqing Number Value 500.00 300.00 North-South Transport Corridor Date 31-Dec-2008 30-Nov-2013 31-Dec-2016 Comments To be updated by March, 2014

Data on Financial Performance (as of 28-Aug-2013)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P111421 IBRD-78810 Effective 20-May-2010 31-Aug-2010 09-Nov-2010 31-Jan-2016 31-Jan-2016

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P111421 IBRD-78810 Effective USD 100.00 100.00 0.00 14.26 85.74 14.00

Disbursement Graph Public Disclosure Copy

Page 7 of 8 The World Bank Report No: ISR12803 Public Disclosure Copy

Key Decisions Regarding Implementation A supervision/mid-term review mission is conducted between Nov. 24 and 29, 2013.During the mission, some potential project changes are discussed. The decision will be reflected in aide memoire after the thoroughly discussion with clients.

Restructuring History There has been no restructuring to date.

Related Projects There are no related projects. Public Disclosure Copy

Page 8 of 8