APPENDIX B.1: DELMAS LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - DELMAS

Rand Water Bore Hole Bore Hole Bore Hole Connection 5,0 Ml/d Field C, D Field A, E Field B

Modder-Oos P/S Need: 30 km pipeline from Bloemendal P/s P/S Need: 5 Ml reservior P/S

Delmas Botleng Botleng 200 kl 10.0; 6.7 P/S ML 3.2 Ml 3.0 Ml

interlinked 3.18 Ml 0.25 Ml

Sundra Eloff Delmas Botleng Botleng Ext 3, 4 Botleng High

Sundra and Eloff: Municipal vacuum tanker service

PS PS PS

Delmas STP Botleng STP Extension: Botleng X5 5,5 Ml/d 4,0 Ml/d & X6 of 7500 stands

STP require additional 4 Ml/d additions Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) EMALAHLENI LM: INFRASTRUCTURE SCHEMATIC LAYOUT -

APPENDIX B.2: EMALAHLENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - WITBANK

LEGEND:

P/S Witbank Dam Point B Supply area Supply area

P/S Low pressure low pressure zone zone Critical Challenge: Quarry Witbank Water Purification Highveld Steel - Assured yield: 76,7 Ml/d; already at limit. Works - Projected demand by 2020: - Original 75 Ml/d High pressure zone Witbank Scheme: 143 Ml/d - Current extension - 15 - 25 High pressure Ml/d zone Highveld Steel: 20 Ml/d Landau Colliery

Reservoir Reservoir Require extensions by: - 2010: 25 Ml/d Future extentions: - 2020: 25 Ml/d 1) Hoëveldpark 1350 hh 2) Riverview AH, Water Tower Jackaroo Prk Ex1: 550ha 3) New Golf Estate planned: 4000 hh D P/S Pumpstation 11.14 Ml Hoëveldpark X1, Modelpark, The supply to Zone 40 Ml Jackaroopark, AHs E will soon change from Res A to Res B D: Low Sub-zone Pump Mains P/S Gravity Mains Replace and upgrade pump main Additional Storage Sewer Mains required: - 15 Ml by 2015 WTW WTW B A C P/S 11.3 Ml 20 Ml STP 64.5 Ml 20 Ml STW 2x11.3 Ml

P/S P/S Additional Storage E - Kwaquqa Phola required: 2015: 20 Ml 10 Ml 9.6 Ml

Ferrometals, SAB, 3 Ml 0.75 Ml Clewer Future extentions: Spoornet P/S P/S D, E 1) Duvhapark: 4000 hh 3x0.090 Ml 2) 500 ha between 2xP/S Reyno Ridge and Duvah park Future extentions: 3) Benfleur X2: 600hh Future extensions: 0.7 Ml 2500 hh 0.55 Ml 4) Bankenveld: 1050 hh of 13 000 stands Future extentions: C: 40+60 kl; planned for Klarinet 1)Enkanini: 13500 hh D: 20 kl

KSOK (Lynville, Ackerville, Die Heuwel, Witbank ext 27, Ferrobank, Paxton Prison Duvhapark, Tasbetpark, Witbank CBD, X8, X5, X1, Hlalanikahle X1-4; Kwa- Phola Ogies Tshusanang, 57, 23, 29; Modelpark x1; Pine Ridge, Klarinet, Kwa-Guqa X2, X7, X10, X18 Bankenveld, X16 X10; Del Judor Guqa X3-6, X9, Vosman Schoongesicht) Die Heuwel Ext4 Lynnville portion C: Low Sub-zone B: High Sub-zone B: Low Sub-zone A: High Sub-zone A: Low Sub-zone E: High Sub-zone E: Low Sub-zone

Naauwpoort STP 10 Ferrobank STP 13.3 Riverview STP 11 Klipspruit STP 10 Phola STP Ml/d Ml/d Ml/d Ml/d 4,5 Ml/d

Effluent does not comply; Close down Upgrading required by 2x10 Ml/d or refurbish; Upgrading required to Alternative supply to Highveld Steel Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.3: EMALAHLENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - KRIEL / TUBELIHLE

Source of Water from Usutu Government Water Scheme

Jericho Dam Kriel Power 3 SMtl/adtion

Kriel WTW 17 Ml/d

LEGEND: Clear Supply area Water Supply area

P/S Low pressure low pressure zone zone

Upgrade required: High pressure High pressure zone Install new 160 NB pipeline, 6,5 km zone

Reservoir Reservoir Matla Jakaranda Tubelihle P/S P/S P/S 3.0 Ml 7.0 Ml 3.0 Ml

Water Tower

Kriel Kriel Kriel Tubelihle Tubelihle P/S Pumpstation High Sub-zone Low Sub-zone Low Sub-zone Low Sub-zone High Sub-zone

Pump Mains

Gravity Mains P/S P/S P/S Sewer Mains New extentions: 1400 stands te be developed WTW WTW Upgrade required: Kriel STP 3 Ml/d - Construct new 7,0 Ml/d STP STP STW - New Sewage Pumpstation

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.4: STEVE TSHWETE LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - MIDDELBURG

9 Ml 0.5 Ml Emergency Water Source from Witbank Dam RMB Pienaar P/S Middelburg 36 Ml Dam Future Water Dam Klein Olifants River Sump Source from Mines P/S

Vaalbank WTW Athlone Kanhym/Mid- 44 Ml/d Dam delburg St & All Future extensions planned for mine water treatment

Skietbaan 22.5 Ml Kruge0r. 4W5 TWdia 61 M.2l/kdm AC

Future extensions planned for Aerorand

Aerorand

LEGEND:

Rietfontein Graspan Kanonkop Nasaret Vliegveld 4.5 Ml 18 Ml 13.5 Ml 18 Ml 11 Ml Reservoir Reservoir

Water Tower

Middelburg / / Tokologo Middelburg / Mhluzi Middelburg / Mhluzi Middelburg / Nasaret Middelburg CBD Eastdene

P/S Pumpstation

Pump Mains Gravity Mains Sewer Mains Future extensions planned for Tokologo WTW WTW Boskrans STP 30 Ml/d P/S Future extensions STP STW planned for Rockdale water and sanitation

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.5: STEVE TSHWETE LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE -

Allocation: 1,8 Ml/d ; utilized at maximum

Old Source of Water from Komati Pipeline Connection

Nooitgedacht Dam Woestalleen P/S

New Source of Water from Pullenshope Mines

Hendrina WTW 3 Ml/d 5.4 Ml/d (Can upgrade to 6 Ml/d)

LEGEND:

Reservoir Reservoir

Hendrina Kwaza Future extensions: 1.25 Ml W ater Tower 2.0 Ml 2.5 Ml - Squatters to move to new Kwaza X7, X8

P/S Pumpstation

Hendrina Kwazamokhuhle Pump Mains Gravity Mains P/S Sewer Mains New Sewage pumping station WTW W TW Kwaza STP 3.8 Ml/d STP STW

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.6: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - BELFAST / SIYATHUTHUKA

Belfast WTW Kraai-spruit Belfast Dam 3.6 Ml/d Dam P/S P/S

P/S P/S

Need: Replace 3km

Need: Extra 2,0 Ml Siyathuthuka Belfast Reservoir 2.0; 1.8 Ml 2.75 ML

P/S P/S P/S P/S Need: Additional capacity at W/T LEGEND: 2 x 0.45Ml 45 kl 45 kl 60 kl

Reservoir Reservoir Siyathuthuka Belfast ext 1 Belfast ext 2 Belfast ext3 Water Tower

P/S P/S P/S Pumpstation Belfast 3.5 Ml/d STP

Pump Mains Need: Phases 1 & 2 Need: Phases 2 Gravity Mains - Phase out sewerpits Upgrade STP - Reticulation: Replace old pipes Sewer Mains

WTW WTW

STP STW

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.7: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - / SAKHELWE

19 l/s Dullstroom Water 2.2 Ml/d Purification Works Dullstroom Dullstroom Top Dam Bottom Dam P/S

Need: Upgrade p/s P/S P/S

Private Need: Upgrade line Dam Need: Extra 2,0 Ml Reservoir

Dullstroom 1.29 Ml

LEGEND: P/S P/S P/S Need: Additional reservoir

Reservoir Reservoir Sakhelwe 1.8 Ml General needs: - Water source W ater Tower under pressure to feed the continued extensions of the town. Application Dullstroom upper Dullstroom lower Millstream Sakhelwe P/S Pumpstation for increased abstraction currently at DWAF Pump Mains

Gravity Mains P/S Need: Dullstroom Reticulation Sewer Mains refurbishment % upgrading Dullstroom Sewerpits to be phased out Dullstroom 1.0 Ml/d WTW W TW

Sewage p/s require continued STP STW high O&M Need: Upgrade

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.8: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - / EMTHONJENI

Elandsriver Weir Machadodorp WTW 25 l/s 2,7 Ml/d P/S

Need: Upgrading of P/s and pipeline

P/S Need: Reservoir capacity increase

P/S Machadodorp 3 x 1.2 Ml P/S P/S

Machadodorp Emthonjeni A Emthonjeni B Machodo Ind

P/S

Machadodorp Emthonjeni STP 0.2 Ml/d STP 1.5 Ml/d

Need: STP to be demolished P/s & sewerline required

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.9: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE -

Elandsriver weir Waterval Boven WTW 3.0 Ml/d

Need: Additional storage and Roofs on reservoirs Waterval 2 x 1.125 ML

P/S P/S

Waterval Waterval 1.0 ML 0.5 ML

Emgwenya W Boven lower W Boven upper Hosp & resort

W Boven STP 2.4 Ml/d

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.10: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - KUNGWINI LM / THEMBISILE LM REGIONAL SCHEME

Refurbishment required to bring back to full capacity Bronkhorstspruit Water Purification Bronkhorstspruit STP Bronkhorst- spruit P/S Works Dam Bronkhorstspruit Sub KUNGWINI LM

Zitobeni STP Bronkhorstspruit River Ekandustria res Rand Water connection from Mamelodi

Ekangala KUNGWINI LM

Ekangala STP ENKELDOORNOOG C Sub THEMBISILE LM

Growth point: E'doornoog B Moloto

E'doornoog B Tower General needs: - Refurbish bulk Growth point: meters KwaMhlanga-area - Refurbish air valves on bulk pipelines - Refurbish T'FONTEIN, K'NEK, K'MHLANGA Sub telemetry system THEMBISILE LM - O&M require assistance KwaMhlanga STP

LEGEND:

Reservoir Reservoir

Tweef'D Water Tower TWEEFONTEIN A-D Sub THEMBISILE LM

P/S Pumpstation Tweefontein K STP Major refurbishment and upgrading required

Pump Mains Gravity Mains Sewer Mains Gemsboksprt GEMSBOKSPRUIT Sub THEMBISILE LM WTW WTW

STP STW

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0)

Infrastructure~Tables and Graphs TLM 2008/04/08 APPENDIX B.11: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - DR JS MOROKA LM / SEKHUKHUNE DM / THEMBISILE LM REGIONAL SCHEME

SPITSPUNT Sub + leeukuil Dr JS MOROKA LM

Greater Marble Hall Sub SEKHUKHUNE DM

TROYA/ LODING Sub P/S Dr JS MOROKA LM

Critical Challenge: - Assured yield: 9.65 million m3/a. Greater Marble Hall Sub - Current use: approximately 22 Allemansdrif C SEKHUKHUNE DM million m3/a. Bloedfontein Bloedfontein Res Rhenosterkop Dr JS MOROKA LM

Refurbishment needs: Rhenoster-kop Dam P/S - Pump sets Elands River Bloedfontein Main

P/S

Weltevreden Water P/S sub Kameelrivier Res Purification P/S Weltevreden Res Weltevreden sub Dr JS MOROKA LM Works Dr JS MOROKA LM

P/S Growth point: Walkraal Main Growth point: Libangeni

SIYABUSWA Sub Siyabuswa STP Dr JS MOROKA LM

Walkraal Res

P/S

LEGEND:

KLIPPLAATDRIFT 1,2&V3 Sub Reservoir Reservoir Dr JS MOROKA LM Zoetmelk Res Greater Groblersdal Sub Water Tower SEKHUKHUNE DM

P/S P/S Pumpstation

General needs: Pump Mains - Refurbish bulk Gravity Mains meters Sewer Mains - Refurbish air Res valves on bulk pipelines WTW WTW KWAGGAFONTEIN Sub - Refurbish THEMBISILE LM telemetry system STP STW - O&M require assistance

Produced by Bigen Africa Management Services

Nkangala District Municipality Water Master Plan (Revision 0)

Infrastructure~Tables and Graphs Dr JSM 2008/04/08