APPENDIX B.1: DELMAS LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - DELMAS
Rand Water Bore Hole Bore Hole Bore Hole Connection 5,0 Ml/d Field C, D Field A, E Field B
Modder-Oos P/S Need: 30 km pipeline from Bloemendal P/s P/S Need: 5 Ml reservior P/S
Delmas Botleng Botleng 200 kl 10.0; 6.7 P/S ML 3.2 Ml 3.0 Ml
interlinked Sundra Eloff 3.18 Ml 0.25 Ml
Sundra Eloff Delmas Botleng Botleng Ext 3, 4 Botleng High
Sundra and Eloff: Municipal vacuum tanker service
PS PS PS
Delmas STP Botleng STP Extension: Botleng X5 5,5 Ml/d 4,0 Ml/d & X6 of 7500 stands
STP require additional 4 Ml/d additions Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) EMALAHLENI LM: INFRASTRUCTURE SCHEMATIC LAYOUT - WITBANK
APPENDIX B.2: EMALAHLENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - WITBANK
LEGEND:
P/S Witbank Dam Point B Supply area Supply area
P/S Low pressure low pressure zone zone Critical Challenge: Quarry Witbank Water Purification Highveld Steel - Assured yield: 76,7 Ml/d; already at limit. Works - Projected demand by 2020: - Original 75 Ml/d High pressure zone Witbank Scheme: 143 Ml/d - Current extension - 15 - 25 High pressure Ml/d zone Highveld Steel: 20 Ml/d Landau Colliery
Reservoir Reservoir Require extensions by: - 2010: 25 Ml/d Future extentions: - 2020: 25 Ml/d 1) Hoëveldpark 1350 hh 2) Riverview AH, Water Tower Jackaroo Prk Ex1: 550ha 3) New Golf Estate planned: 4000 hh D P/S Pumpstation 11.14 Ml Hoëveldpark X1, Modelpark, The supply to Zone 40 Ml Jackaroopark, AHs E will soon change from Res A to Res B D: Low Sub-zone Pump Mains P/S Gravity Mains Replace and upgrade pump main Additional Storage Sewer Mains required: - 15 Ml by 2015 WTW WTW B A C P/S 11.3 Ml 20 Ml STP 64.5 Ml 20 Ml STW 2x11.3 Ml
P/S P/S Additional Storage E - Kwaquqa Phola required: 2015: 20 Ml 10 Ml 9.6 Ml
Ferrometals, SAB, 3 Ml 0.75 Ml Clewer Future extentions: Spoornet P/S P/S Ogies D, E 1) Duvhapark: 4000 hh 3x0.090 Ml 2) 500 ha between 2xP/S Reyno Ridge and Duvah park Future extentions: 3) Benfleur X2: 600hh Future extensions: 0.7 Ml 2500 hh 0.55 Ml 4) Bankenveld: 1050 hh of 13 000 stands Future extentions: C: 40+60 kl; planned for Klarinet 1)Enkanini: 13500 hh D: 20 kl
KSOK (Lynville, Ackerville, Die Heuwel, Witbank ext 27, Ferrobank, Paxton Prison Duvhapark, Tasbetpark, Witbank CBD, X8, X5, X1, Hlalanikahle X1-4; Kwa- Phola Ogies Tshusanang, 57, 23, 29; Modelpark x1; Pine Ridge, Klarinet, Kwa-Guqa X2, X7, X10, X18 Bankenveld, X16 X10; Del Judor Guqa X3-6, X9, Vosman Schoongesicht) Die Heuwel Ext4 Lynnville portion C: Low Sub-zone B: High Sub-zone B: Low Sub-zone A: High Sub-zone A: Low Sub-zone E: High Sub-zone E: Low Sub-zone
Naauwpoort STP 10 Ferrobank STP 13.3 Riverview STP 11 Klipspruit STP 10 Phola STP Ml/d Ml/d Ml/d Ml/d 4,5 Ml/d
Effluent does not comply; Close down Upgrading required by 2x10 Ml/d or refurbish; Upgrading required to Alternative supply to Highveld Steel Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.3: EMALAHLENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - KRIEL / TUBELIHLE
Source of Water from Usutu Government Water Scheme
Jericho Dam Kriel Power 3 SMtl/adtion
Kriel WTW 17 Ml/d
LEGEND: Clear Supply area Water Supply area
P/S Low pressure low pressure zone zone
Upgrade required: High pressure High pressure zone Install new 160 NB pipeline, 6,5 km zone
Reservoir Reservoir Matla Jakaranda Tubelihle P/S P/S P/S 3.0 Ml 7.0 Ml 3.0 Ml
Water Tower
Kriel Kriel Kriel Tubelihle Tubelihle P/S Pumpstation High Sub-zone Low Sub-zone Low Sub-zone Low Sub-zone High Sub-zone
Pump Mains
Gravity Mains P/S P/S P/S Sewer Mains New extentions: 1400 stands te be developed WTW WTW Upgrade required: Kriel STP 3 Ml/d - Construct new 7,0 Ml/d STP STP STW - New Sewage Pumpstation
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.4: STEVE TSHWETE LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - MIDDELBURG
9 Ml 0.5 Ml Emergency Water Source from Witbank Dam RMB Pienaar P/S Middelburg 36 Ml Dam Future Water Dam Klein Olifants River Sump Source from Mines P/S
Vaalbank WTW Athlone Kanhym/Mid- 44 Ml/d Dam delburg St & All Future extensions planned for mine water treatment
Skietbaan 22.5 Ml Kruge0r. 4W5 TWdia 61 M.2l/kdm AC
Future extensions planned for Aerorand
Aerorand
LEGEND:
Rietfontein Graspan Kanonkop Nasaret Vliegveld 4.5 Ml 18 Ml 13.5 Ml 18 Ml 11 Ml Reservoir Reservoir
Water Tower
Middelburg / Mhluzi / Tokologo Middelburg / Mhluzi Middelburg / Mhluzi Middelburg / Nasaret Middelburg CBD Eastdene
P/S Pumpstation
Pump Mains Gravity Mains Sewer Mains Future extensions planned for Tokologo WTW WTW Boskrans STP 30 Ml/d P/S Future extensions STP STW planned for Rockdale water and sanitation
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.5: STEVE TSHWETE LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - HENDRINA
Allocation: 1,8 Ml/d ; utilized at maximum
Old Source of Water from Komati Pipeline Connection
Nooitgedacht Dam Woestalleen P/S
New Source of Water from Pullenshope Mines
Hendrina WTW 3 Ml/d 5.4 Ml/d (Can upgrade to 6 Ml/d)
LEGEND:
Reservoir Reservoir
Hendrina Kwaza Future extensions: 1.25 Ml W ater Tower 2.0 Ml 2.5 Ml - Squatters to move to new Kwaza X7, X8
P/S Pumpstation
Hendrina Kwazamokhuhle Pump Mains Gravity Mains P/S Sewer Mains New Sewage pumping station WTW W TW Kwaza STP 3.8 Ml/d STP STW
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.6: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - BELFAST / SIYATHUTHUKA
Belfast WTW Kraai-spruit Belfast Dam 3.6 Ml/d Dam P/S P/S
P/S P/S
Need: Replace 3km
Need: Extra 2,0 Ml Siyathuthuka Belfast Reservoir 2.0; 1.8 Ml 2.75 ML
P/S P/S P/S P/S Need: Additional capacity at W/T LEGEND: 2 x 0.45Ml 45 kl 45 kl 60 kl
Reservoir Reservoir Siyathuthuka Belfast ext 1 Belfast ext 2 Belfast ext3 Water Tower
P/S P/S P/S Pumpstation Belfast 3.5 Ml/d STP
Pump Mains Need: Phases 1 & 2 Need: Phases 2 Gravity Mains - Phase out sewerpits Upgrade STP - Reticulation: Replace old pipes Sewer Mains
WTW WTW
STP STW
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.7: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - DULLSTROOM / SAKHELWE
19 l/s Dullstroom Water 2.2 Ml/d Purification Works Dullstroom Dullstroom Top Dam Bottom Dam P/S
Need: Upgrade p/s P/S P/S
Private Need: Upgrade line Dam Need: Extra 2,0 Ml Reservoir
Dullstroom 1.29 Ml
LEGEND: P/S P/S P/S Need: Additional reservoir
Reservoir Reservoir Sakhelwe 1.8 Ml General needs: - Water source W ater Tower under pressure to feed the continued extensions of the town. Application Dullstroom upper Dullstroom lower Millstream Sakhelwe P/S Pumpstation for increased abstraction currently at DWAF Pump Mains
Gravity Mains P/S Need: Dullstroom Reticulation Sewer Mains refurbishment % upgrading Dullstroom Sewerpits to be phased out Dullstroom 1.0 Ml/d WTW W TW
Sewage p/s require continued STP STW high O&M Need: Upgrade
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.8: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - MACHADODORP / EMTHONJENI
Elandsriver Weir Machadodorp WTW 25 l/s 2,7 Ml/d P/S
Need: Upgrading of P/s and pipeline
P/S Need: Reservoir capacity increase
P/S Machadodorp 3 x 1.2 Ml P/S P/S
Machadodorp Emthonjeni A Emthonjeni B Machodo Ind
P/S
Machadodorp Emthonjeni STP 0.2 Ml/d STP 1.5 Ml/d
Need: STP to be demolished P/s & sewerline required
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.9: EMAKHAZENI LOCAL MUNICIPALITY: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - WATERVAL BOVEN
Elandsriver weir Waterval Boven WTW 3.0 Ml/d
Need: Additional storage and Roofs on reservoirs Waterval 2 x 1.125 ML
P/S P/S
Waterval Waterval 1.0 ML 0.5 ML
Emgwenya W Boven lower W Boven upper Hosp & resort
W Boven STP 2.4 Ml/d
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0) APPENDIX B.10: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - KUNGWINI LM / THEMBISILE LM REGIONAL SCHEME
Refurbishment required to bring back to full capacity Bronkhorstspruit Water Purification Bronkhorstspruit STP Bronkhorst- spruit P/S Works Dam Bronkhorstspruit Sub KUNGWINI LM
Zitobeni STP Bronkhorstspruit River Ekandustria res Rand Water connection from Mamelodi
Ekangala KUNGWINI LM
Ekangala STP ENKELDOORNOOG C Sub THEMBISILE LM
Growth point: E'doornoog B Moloto
E'doornoog B Tower General needs: - Refurbish bulk Growth point: meters KwaMhlanga-area - Refurbish air valves on bulk pipelines - Refurbish T'FONTEIN, K'NEK, K'MHLANGA Sub telemetry system THEMBISILE LM - O&M require assistance KwaMhlanga STP
LEGEND:
Reservoir Reservoir
Tweef'D Water Tower TWEEFONTEIN A-D Sub THEMBISILE LM
P/S Pumpstation Tweefontein K STP Major refurbishment and upgrading required
Pump Mains Gravity Mains Sewer Mains Gemsboksprt GEMSBOKSPRUIT Sub THEMBISILE LM WTW WTW
STP STW
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0)
Infrastructure~Tables and Graphs TLM 2008/04/08 APPENDIX B.11: SCHEMATIC LAYOUT OF WATER AND SANITATION INFRASTRUCTURE - DR JS MOROKA LM / SEKHUKHUNE DM / THEMBISILE LM REGIONAL SCHEME
SPITSPUNT Sub + leeukuil Dr JS MOROKA LM
Greater Marble Hall Sub SEKHUKHUNE DM
TROYA/ LODING Sub P/S Dr JS MOROKA LM
Critical Challenge: - Assured yield: 9.65 million m3/a. Greater Marble Hall Sub - Current use: approximately 22 Allemansdrif C SEKHUKHUNE DM million m3/a. Bloedfontein Bloedfontein Res Rhenosterkop Dr JS MOROKA LM
Refurbishment needs: Rhenoster-kop Dam P/S - Pump sets Elands River Bloedfontein Main
P/S
Weltevreden Water P/S Kameelrivier sub Kameelrivier Res Purification P/S Weltevreden Res Weltevreden sub Dr JS MOROKA LM Works Dr JS MOROKA LM
P/S Growth point: Walkraal Main Siyabuswa Growth point: Libangeni
SIYABUSWA Sub Siyabuswa STP Dr JS MOROKA LM
Walkraal Res
P/S
LEGEND:
KLIPPLAATDRIFT 1,2&V3 Sub Reservoir Reservoir Dr JS MOROKA LM Zoetmelk Res Greater Groblersdal Sub Water Tower SEKHUKHUNE DM
P/S P/S Pumpstation
General needs: Pump Mains - Refurbish bulk Gravity Mains meters Sewer Mains - Refurbish air Kwaggafontein Res valves on bulk pipelines WTW WTW KWAGGAFONTEIN Sub - Refurbish THEMBISILE LM telemetry system STP STW - O&M require assistance
Produced by Bigen Africa Management Services
Nkangala District Municipality Water Master Plan (Revision 0)
Infrastructure~Tables and Graphs Dr JSM 2008/04/08