Proposed Naikin‐II, Bauxite, Laterite and Fire Clay Mine AT Village : Naikin; Tehsil ‐ , District: ; State: CtCountry: IdiIndia Area: 3. 417 Ha

EXECUTIVE SUMMARY (ENGLISH & Hindi)

PROJECT PROPONENT M/s. Shri Krishnadas Tikaram Name of Consultant & NABET Accreditation No

Aplinka Solutions & Technologies Pvt. Ltd. | www.aplinka.in Corp. Office : A‐48, Ground Floor, Sector‐64, Noida – 201301 NABET Accreditation No: NABET/EIA/1619/IA/0011 Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

EXECUTIVE SUMMARY 1.0 INTRODUCTION

Environmental Impact Assessment (EIA) is a process, used to identify the environmental, social and economic impacts of a project prior to decision-making. It is a decision making tool, which guides the decision makers in taking appropriate decisions for proposed projects. EIA systematically examines both beneficial and adverse consequences of the proposed project and ensure that these impacts are taken into account during the project designing. 1.1 ENVIRONMENTAL CLEARANCE

The proposed project is categorith zed under 1 (a) (<50 hectare of mining lease area) of Gazette Notification dated Sep 14 , 2006 and subsequent amendments. As per the Gazette Notification, 2006, the proposed project is under “B” category due to the lease area less than 50 Ha and general condition is not attracted. It comes under 1(a) activity of EIA Notification. 1.2 TERMS OF REFERENCE

280/PSth- The proposal was considered by the State Expert Appraisal Committee (SEAC-II) during its 71 MS/MPPCB/SEAC-II/M/TOR (71)/2017 08/05/2017. meeting held on 10/04/2017. Subsequently ToR was issued vide letter No. dated Though the lease area is less than 5 ha but being a ML of Major Mineral, the case was considered as B-1 category and standard TOR prescribed by the MOEF & CC, New Delhi along with additional TOR’s from SEAC, MP were issued. 2.0 PROJECT DESCRIPTION

This is a project for open cast other than fully mechanized method of mining of mineral like Bauxite, Laterite and Fire clay and the estimated project cost is 1.0 crores. The Mining Lease was granted by State Government for 20 years period w.e.f. 26.02.1977 to 25.02.1997 over an area of 4.247 ha. Mine lease was renewed for 20 years w.e.f. 27.02.1997 to 26.02.2017 over an area of 3.417 ha for Bauxite, Laterite and Fire clay. The lease area is extended for 50 years up to 25.02.2027 as per The MM (D & R) Amendment Act 2015. Mining plan along with progressive mine closure plan has been approved by Regional Controller of Mine, IBM vide letter No. MP/Sidhi/Bauxite/ MPLN/MOD-59/17-18 3358 dated 13/10/2017. Mailing/ Correspondence Address of Project Proponent: Consent to Operate for 25,000 Tonne/Year was granted by MPPCB till 31/12/2017.

M/s. Shri Krishnadas Tikaram Civil Lines P.O. & District: Katni (M.P.) – 483501 Phone - 07622-230076 Size of the Project

The total Mine Lease area considered is 3.417 ha. The proposed production is 25,000 TPA Anticipated Life of Project and Cost of the Project

The life of the mine is anticipated at 13 years at 25,000 TPA. Project cost is Rs. 1.0 crore.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

LOCATION

Proposed Bauxite, Laterite and Fire Clay Mine having lease area of 3.417 ha. is located at Khasra no. 609, 610/1, 610/2, Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, Madhya Pradesh. The lease area is approachable from Rewa- Sidhi road which is 2.70 km S from the lease area. The nearest railway station is Rewa Railway Station approx. 25 km NW from the lease area.

Toposheet No. - 630 H/7 0 Latitude - 24 021’14.3” to 24 021’20.9” North Details of Project Longitude - 81 23’43.6” to 81 23’54.3” East Elevation of ML area - 318 mRL to 313 mRL.

Project Name Bauxite, laterite and Fire Clay Mine (3.417 ha) by M/s. Shri Krishnadas Tikaram Location of the Project Khasra no. 609, 610/1, 610/2, Village Naikin, Tehsil-Rampur Naikin,S.No DistrictVillage-Sidhi, Madhya AreaPradesh Khasra no Mine Lease Area 3.417 Ha. Details of Villages present in Lease Area 1 Naikin 3.417 Ha 609, 610/1, 610/2

Type of Land Government waste land 0 Temperature Max: 350 C Min: 8.0 C S N Climatology (Oct to Dec 2017) Wind Speed Range 0.39 m/s to 0.95 m/s Predominant Wind Blowing from E to W Direction Project Cost 1 Crore. Man Power & Average no. of 25 personnel for 250 Days/Year. Working days Water Demand & Source 8.0 KLD, Source: Mine Pit water and drinking water from villages. Gram Panchayat permission of the same has been obtained Bauxite Laterite

Proved Mineral Reserve (111) 319410 t. -- Feasibility Mineral Resource 304724 t -- (211) Measured Mineral resource -- 10125 Total Reserve + Resources 624134 10125 Targeted Production 25,000 TPA Validity of Lease 50 years period w.e.f. 26.02.1977 to 25.02.2027 Seismic Zone Seismic Zone III as per IS-1893 (Part-1)-2002 End use of Product Mineral is intended for sale to refractory plants near Katni and cement plants in the region. Nearest Highway NH- 75, 2.7 km in SSW direction Nearest Water Bodies  Water Body – 8.10 Km in SE  Phapho Nalla- 3.9 Km in SSE  Marhawal Nalla – 3.9 km SSE  Kataha Nala -4.0 km in SE  Sughara Nala – 5.0 km in SE  Nalla – 2.20 km in SW Pond– 1.30 km South Branch Canal – 15m in SW & 341m North EnvironmentHistorical MonumentsAplinka (in 10 KmSolutionsNone & within Technologies the study Pvt. Area. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

Buffer) Status of Protected/ Other Areas The Son Ghariyal Wildlife Sanctuary ESZ is 9.750 km from the lease (in 10 Km Buffer) area. Forest NoC dated 07/09/02 and 13/01/2016 has been obtained. • • Reserve Forests within 10 km • Kaimur Hills, 1.5 Km in North radius from mine lease boundary • Gobindgarh Reserve Forest, . 1.5 Km in North • Gobindgarh Extension Reserve Forest, 3.7 Km in NE • RF, 11.7 Km in NE • Khairi RF, 8.3 Km in SE • Chandrehi RF, 9.0 Km in SE • Bardila RF, 5.8 Km in SE • Shikarganj RF, 7.2 Km in SE • Bakura Pahad, 9.5 Km in S • Khainjua Pahad, 10.2 Km in SW • Gobindgarh Town, 8.9 Km in NW Nearest Dispensary &Govt. • Govt Hospital; Rampur Naikin, 7.6km in SE Hospital J P Hospital Jaypee Vihar; Sidhi, 6.7km in WSW Primary health care facilities are present in all villages. 2.1 MINING

Opencast other than fully mechanized method of mining has been proposed at the project site. The development in mineral only will be carried out by deployment of excavator, loading will be done by loaders and transport will be done by HEMM. No drilling and blasting will be carried out.. It is proposed to use mainly excavator cum loader which will increase the recovery and grade. The lease area is almost plain having gentle slope towards south-east. The two quarries exist towards both the ends. The winning of ore and loading will be either done mechanically or manually. The transport from bottom of the quarry to the top in stacking yard will be done by Transportation Route: : tractors or dumpers of 10.0 t. capacity. 1. Two transportation routes will be followed and are as follows 2 From Katni – Rewa on NH-75 via Pakariha village to mine site, distance 4.8 km . From Katni - Rewa on NH-75 via Baghwar Village, Nakin village to mine, distance 3.6 km. 2.1.1 Mining during 1st Five Year

For Development/TABLE working-: PITo fWISE deposit TONNAGE year wise AND givenGRADE below OF PRODUCTION Year Total Soil OB/ IB ROM (cum) Mineral Prodn. Of ROM/Waste tentative (cum) (cum)SB/ Bauxite Reject (cum) Bauxite in ratio Excavation tonnes ** (Cum)

st 1nd Year 12665.5 580 1208.55 10876.95 Nil 25016.99 1:0.16 2rd Year 12767 817 1195 10755 Nil 24736.5 1:0.19 3th Year 12125 0 1212.5 10912.5 Nil 25098.75 1:0.11 4th Year 12257 176 1208.1 10872.9 Nil 25007.67 1:0.13 Source:5 Year-Mine plan12208 127 1208.1 10872.9 Nil 25007.67 1:0.12 Total 62022.5 1700 6032.25 54290.25 Nil 124867.6 1:0.14

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

Disposal of Waste Nature of waste, its rate of yearly generation and proposals for disposal of waste:

The (1) Municipal Solid waste of workers: mine waste is in the form of following:- - Very insignificant, toilets will be provided to the (2) Soil: - workers followed by septic tank. The same will be cleaned on monthly basis by vendors. (3) Over burden/ Mine waste: - The soil is sandy in nature mixed with grit and pebbles. This is in the form of lateritic soil and weathered sandstone . pebbles. The quantity to be generatedYEAR WISEduring WASTE proposal GENERATION period is given below Year Top Soil (cum) OB/Mine waste Mineral Rejects (cum)

Reuse/ Storage Stacking Backfilling Backfilling Storage Blending Beneficiation spreading st 580 - - 1208.55 1 Year - - - - nd 817 - - 1195 2 Year - - - - rd 0 - - 1212.5 3 Year - - - - th 176 - - 1208.1 4 Year - - - - th 127 - - 1208.1 5 Year - - - - Total 1700 - - 6032.25 - - - - 2.1.2 Use of Mineral and Beneficiation

The Bauxite of the lease area is of cement grade as well as refractory grade. The mineral is intended for sale to refractory plants near Katni and cement plants in the region. 2.3 General Features I) Topography and Drainage Pattern Topography:

Topography of the applied area is almost plain having gentle slope towards south-east. The highest elevation is 318m RL towards north-west and the lowest elevation is Drainage: about 313 m RL towards south-east. The Son River is main drainage of the study area. The important man made drainages of study area are Sihawal Main Canal; Keotii Main Canal; Common water carrier canal. The natural pond is Katara Talab on the northern aspect of central high hills. The project site is surrounded by an irrigation canal from the northern region and crop land from the south. The lease area is on the western side approx 30 meter of a primary drainage of Katha Nala. This ii). Beneficiation/Processing primary drainage meets with Katha Nala near Shankarpur Village. iii). Infrastructure and Basic Amenities No processing of mineral will be done in the mine. Only simple sizing and sorting will be done.

Basic amenities like rest room shelter/tents, first aid facility, temporary office and water for 2.5drinking Water and Requirementtoilets will be provided during operational phase. Activity Water requirement, KLD

Dust suppression /allied mining activity 4.0 Plantation 2.0 Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

Total 8.0 Domestic 2.0 2.6 MANPOWER REQUIREMENT

3.0 DESCRIPTION OF ENVIRONMENT About 25 persons will be getting direct and indirect employment in this mine.

” This section contains the description of baseline studies of the 10 km radius of the area surrounding “Bauxite, Laterite and Fire Clay Mine . The data collected has been used to understand the existing environment scenario around the proposed mining project against which the potential impacts of the project can be assessed. Details of Environmental data has been collected in relation to propose mining is given below (a) Land Use

: The land-use of the study area is divided into crop land, forest or tree cover, scrub land; water bodies,Land open Use land, Pattern fallow of land,the Study builtArea up area (within etc. 10 km Buffer ) S.NO Land Cover class Area (acres) Percentage

1 Water Bodies 2051 3 2 Forest 17987 25 3 Open land 8066 11 4 Scrub Land 6714 9 5 Built-up 4000 5 6 Crop Land 31229 43 7 Fallow Land 2569 3 8. Waste land 492 1 Results of Analysis of theTotalSoil 73108 100

The analysis results show that soil is neutral to slightly alkaline in nature as the pH value ranges from 7.36 to 7.69. The electrical conductivity was observed to be in the range from 188.0 to 385.0 μmhos/cm. The TKN values range from 0.03 to 0.070 %. The nitrogen content in the study area is very less. The phosphorus values range from 8.39 to 12.40 (mg/kg), indicating that the phosphorus content in the study area falls in medium category. The potassium values range from 179.39 to 335.40 (mg/kg). It was observed that the soil quality- does not indicate any noticeable pollution and contamination. The soil quality can be improved by application of fertilizers in order to grow vegetation / plantation. (b) WATER ENVIRONMENT

Ground water samples were collected from six different locations while the surface water samples were collected from 8 locations within the buffer zone. The analysis results at the six Ground water: ground water locations and eight surface water locations are given below: The analysis results indicate that pH of the groundwater is in range of 7.43 to 8.02. Total hardness was observed to be ranging from 138.99– 254.10 mg/l. Chlorides were found to be in the range of 39.57 – 46.63 mg/l. Fluorides were found to be in the range of 0.12 mg/l to 0.23 mg/l. Sulphates were found to be in the range of 21.96 mg/l –30.16 mg/l. Total Dissolved Solids (TDS) concentrations were found to be ranging in between 288.70 mg/l – 355.43 mg/l. All the values were found to be within the permissible limits for both core and Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

buffer zone. Hence, it can be concluded that the ground water analysis in the study area does Surface Water: not indicate any contamination The analysis results indicate that the pH value is 7.02 to 7.88 which is well within the specified standard of 6.5 to 8.5; TDS was observed as 110.3 to 350.7 mg/l. The chlorides were found as 29.50 mg/l to 78.10mg/l, Total hardness ranges between 104.03 to 166.10 mg/l. It is observed that hardness of surface water is within permissible limits of IS: 10500"Specifications for Drinking Water". Iron is found in between 0.115-0.401 mg/l." It can be observed that the surface water quality does not indicate any industrial pollution. Surface water of 10 km study area comes under Class B i.e Outdoor bathing and Ground water comes under Class A i.e Drinking water source without Conventional Treatment but after disinfection. (c) AMBIENT AIR QUALITY

As per National Ambient Air Quality Standards (revised on 16th November 2009) the quality of air is found to be well within the prescribed standards.  The Ambient Air Quality Monitoring reveals3 that of 10 monitoring stations the minimum 3 concentrations of PM10 are 31.43 g/m at project site and maximum 65.12 g/m near3 Baghwar Village. The results of PM2.5 reveal that the minimum concentration of3 12.91 g/m at Nearer settlement above canal while maximum concentration of 28.83 g/m is found Near Baghwar3 village. These3 values for PM10 and PM2.5 are within prescribed CPCB limit of 100 g/m and 60 g/m respectively for residential and rural areas at all stations. 2 2 3 The gaseous pollutants SO and NO are within the prescribed CPCB limit of 80 g/m for residential and rural areas at3 all stations. The minimum 3 & maximum concentrations of SO2 were found to be 5.15 g/m at project site & 14.73 g/m Near Baghwar village3 respectively.3 The minimum & maximum concentrations of NO2 were found to be 7.32 g/m & 23.22 g/m (d)respectively. NOISE ENVIRONMENT

Noise in the core and buffer zone varies from 45.81 dB (A) to 60.44 dB (A) during day time and during night noise levels ranges from 34.87 dB (A) to 41.82 dB (A). Thus noise levels at all locations were observed to be within the prescribed limits as prescribed by CPCB. (e) BIOLOGICAL ENVIRONMENT

There is no national park within 10 km radius of mine lease; Son Ghariyal Wildlife Sanctuary ESZ is at 9.75 km SE from the lease area. No Schedule –I species were found within the study area. (F) SOCIO- ECONOMIC

The study area comprises parts of Tehsil- of Shahdol District, Tehsil- Ramnagar of District, Tehsil-Huzur & Gurh of District Rewa, Tehsil-Rampur Naikin of Madhya Pradesh. The study area involves 77 rural villages and 2 urban area namely Rampur Niken and Gobindpur; however it comes under Revenue village Niken, Tehsil: Rampur Niken, District: Sidhi; State: Madhya Pradesh. The percentage distribution of number of villages in 0 to 2 Km; 2 to 5 Km; 5 to 7 Km & 7 to 10Km are 4, 19, 25 & 31 respectively. There are three uninhabited villages namely Kuswari; Madwani & Basahara.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

(G) DEMOGRAPHIC COMPOSITION

According to Census 2011, Core zone doesn’t have any human habitation. The buffer zone comprises of about 28004 household with 1, 25,563 Individuals having male & female percentages 51 & 49 % respectively. The average sex ratio of study area is 899 females per thousand male. (H) SOCIAL STRUCTURE

There are about 106 tanks water bodies and ponds in study area and 46 % of them go dry during summer. Son River is the important river in the study area. The average percentage drinking water source in the study area in descending is hand pump; uncovered open well; Tube well and bore well; spring and Tap-water from untreated source are 56.8; 34.3; 2.7; 2.1 and 1.5 percent respectively. About 18.6 percent household have drinking water source within premises and 47.9 percent have near the premises (less than 1 Km) in the study area. About 33.5 percent household still has to travel a lot to fetch the drinking water. The study area is dominated by higher caste, currently there is a wave of change of occupation. There by other worker are increasing in the study area. The immediate surroundings of the project lack the amenities. The villagers are very optimist by the setup of Proposed Mine Project. 4.0 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES 4.1 IMPACT ON AMBIENT AIR QUALITY

The air borne particulate matter generated by ore and handling operations as well as 2 transportation is the main air pollutant. The emissions of Sulphur dioxide (SO ), Oxides of x Nitrogen (NO ) contributed by vehicles plying on haul roads are marginal. Prediction of impacts on air environment has been carried out taking into consideration proposed production and net increase in emissions. The maximum incremental value of PM10 is found due to transportation activity, loading and unloading operation ad excavation work as drilling and blasting is not proposed on the project site. The same has been predicted by using softwares for modelling. It s seen that the GLC’s obtained at various locations for the study period are well within the CPCB Mitigation Measuresth standards (dated 18 November,2009).

 Stationary water sprinklers will be installed at the entrances and exit of ML area with  provision of water recirculation. Water sprinkling will be done on the haul roads twice in a day.  The dust generated during the process will be minimized by water spray at the working  faces before and after the activity. Plantation will be carried out on approach roads and in Lease boundary.  Planning transportation routes of mined material so as to reach the nearest paved roads by shortest route. (minimize transportation over unpaved road);  Personal Protection Equipments (PPE) like dust masks, ear plugs etc. will be provided to mine workers.  Rock breaker will be used for breaking over size boulders in order to reduce dust and  noise generation. Speed limit will be enforced to reduce airborne fugitive dust from vehicular traffic. EnvironmentDeploying PUCAplinka certified Solutions vehicles & Technologies to reduce their Pvt. noiseLtd, Noida emission. Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

  Spillage from the trucks will be prevented by covering tarpaulin over the trucks.  Ambient Air Quality Monitoring will be conducted on regularly basis to assess the quality of ambient air.  Proper maintenance of machines improves combustion process & makes reduction in the pollution. Good maintenance and monitoring of fuel and oil will not allow significant addition in the gaseous emission. 4.2 NOISE ENVIRONMENT

Noise generated at the mine is due to other than fully mechanized mining operations and truck transportation activities. The noise generated by the mining activity dissipates within the mine. There is no major impact of the mining activity on the nearby villages. However, pronounced effect of above noise levels is felt only near the active working area. The impact of noise on the villagesS.No isImpact negligible Prediction as the villages are far located fromMitigation the mine Measures workings. Since there is no involvement1 of major machinery, the impact of noise levels will be minimal.

Noise Impact due toThe noise levels from all the sources are periodical and restricted to 2 mining activities. particular operation.

Noise impact due to Proper maintenance, oiling and greasing of machines at regular vehicular movement. intervals will be done to reduce the generation of noise. Plantation along the sides of approach roads, around office building and mine area will be done to minimize the propagation of noise. Plants with fleshy leaves and other with branches / dense foliage in uniform vertical distribution would mask and absorb noise. Such  measures for afforestation expected to curb high-level noise at the source point would be objectively undertaken; Personal Protective Equipments (PPE) like earmuffs/earplugs will be provided to all operators and employees working near mining machineries or at higher noise zone. Periodical noise level monitoring will be done. 4.3 BIOLOGICAL ENVIRONMENT S.No Impact Predicted Suggestive measure

  1 Mining activity is likely to Mining activities will be restricted to day hours only. affect the movement of the Poaching of animals by laborers will be strictly prohibited. It may animal and birds be ensured by the mine management that no hunting is practiced  at the site by any of the workers. Ward and watch for the animal movement in and around the  project area during mining operation will be provided. Environment and Wildlife Conservation awareness program will  be organized for both work force and surrounding villages. 2 Increase in noise may affect Care will be taken so that noise produced during vehicular the feeding, breeding and movement for carrying OB and ore materials are within the movement of animals permissible noise level.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

3 Likely settling of dust to be All the vehicles delivering materials to the site shall be covered  generated by movement of to avoid spillage of material. vehicles on leaves may Approach road used by vehicles shall be kept clean and clear of results in to stunted  dust. growth of vegetation and may also affect the capacity All earth work shall be protected to minimize dust generation. of production 

4 Harvesting of flora  No tree cutting, chopping, lumbering, uprooting of shrubs and herbs should be allowed. Collections of economically important plants will be fully 4.4 LAND ENVIRONMENT restricted S.No Impact Prediction Mitigation Measures

1 Change in the The proposed mining activity is carried out in almost plain region and Topography of the waste land. After removal of ore body, a undulating portion will be Land / Land created. Part of broken area (2.90ha) will be reclaimed by systematic Degradation backfilling (0.70ha) and rehabilitated by afforestation so that landscape of the area is improved. The reaming area (2.20ha) will be converted in water reservoir with proper fencing around it. It will be source of water to nearby villagers. 2 Solid waste The OB / mine waste will be utilized for backfilling. No external dump generation will remain at the end of mine lease.

3 Change in Drainage Water flow / course will not be obstructed and natural drains or nallahs Pattern will not be disturbed. No water body passing through ML area. Perennial Run-off from mine and mineral stack will be prevented to being discharged to surroundings, particularly to agricultural land. Garland drains and, catch pits will help in preventing run off affecting the surrounding agricultural land. Green belt is being developed around the boundary area. 4 Impact on the Agriculture activities are practiced nearby areas may impacted because Agricultural of dust generation but mitigative measures such as regular water Practice at nearby sprinkling on active areas for example haul roads, excavation sites will area due to dust be strictly followed so that impact is minimized. 4.5 WATERgeneration ENVIRONMENT S.No Impact Prediction Mitigation Measures

1 Effect on the Ground The surface level varies from 313 mRL to 318 mRL. The working depth Water Table will be 15 m below ground level (313mRl) upto 298 m above Mean Sea Level (MSL). Ground Water table varies from 30 mbgl to 35mbgl. Mining operation will be carried out 15 m above ground water table. 2 Wash off from the Adequate drainage systems will be planned in the mining, for allowing dumps the water to flow in the pre-determined path. The drainage system will be designed in such a way even to meet excess rainfall. No water will be allowed to flow across the temporary waste dumps. However, few check dams will be constructed to arrest wash out from the waste dumps during rainy season. 3 Soil Erosion The working area will be protected by making a bund around the working face and slope of the back filling/dump yard will be covered with plants & grass to avoid the land sliding & soil erosion. 4 Waste Water Portable Bio-toilets will be used; hence no sewage / liquid effluent will generation/ be generated and contamination is also not expected due to percolation. EnvironmentDischarge Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

5 Siltation in nearby Garland drain and bund will be prepared towards the sloping side in agriculture field south and west to prevent siltation of low lying areas. The bund will be of size 5.5 m x 1.5m while the drain will be of size 2m x 1.5m. Settling tanks of size 15m x 5m x 3m will also be constructed at corners of sloping side of ML area. The settling tank will be de-silted regularly and especially after rains. Green belt will be developed in barrier zone. 6. Rain Water Runoff To prevent the Rain Water going out of the mine lease area Safety Bund, Garland Drains and Sump will be prepared. This sump will be followed 5.0 ANALYSIS OF ALTERNATIVESby the sedimentation tank.

Mining is a site specific activity and mine is located in the hill of the lease area. In the proposed project, opencast other than fully mechanized mining will be carried out. For that, no other methodology is going to be changed, depending upon the geological set up, strata of the rock 6.0 ENVIRONMENTAL MONITORING PROGRAMME and its structural behavior. The stripping ratio is also low.

The monitoring of the environment parameters within mine and surrounding villages will be out sourced and carried by the lab of SPCB or a lab approved by MoEF&CC/NABL. A budget of 7.0Rs 1.ADDITIONAL0 lac per annumSTUDIES has been allocated for the purpose. DISASTER MANAGEMENT PLAN

In order to avoid any danger in the mine site at the end of life of mine a disaster management cell headed by local authority District Collector will be constituted. Police department health authorities, including doctor, ambulances and so on will have a vital part to play following a disaster along with the mine management, and they will be an integral part of the disaster management plan. The disaster management plan is aimed to ensure safety of human life and property and protection of environment. Following are the objective of the disaster management plan. (i) First Aid to injured. (ii) Rescue operation and provision of adequate medical facilities to the injured. (iii) Safety of the human life in the buffer zone if needed. (iv) Protecting and minimizing damage to property and the environment. (v) Initially restrict and ultimately bring the incident under control. (vi) Identify any dead. (vii) Inform to the administration, DGMS and statutory persons as per Rules. 8.0 PROJECT BENEFITS AND COSTS EVALUATION

The project will improve the physical infrastructure, social infrastructure like improvement of road conditions water supply during dry season, drainage, educational institutions and improved environmental conditions, etc. The project also provides direct employment to 25 persons and much more indirect employment. The project will contribute to district mineral fund which will directly provide aid to the local authority to fund the development projects. The management will provide free saplings of fruit bearing and other trees, etc. to locals during rain for plantation. This will increase the consciousness in workers and near-by villagers for greenery. Fruit trees can contribute towards their financial gains. Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

In the visit made to the site, it was found that around the proposed mining site is developing fast. There is an urgent need to address the drinking water problems. The proponent M/s Shri Krishnadas Tikaram proposes to support the development activities, to a budget of about Rs 2/- lacs under its corporate social responsibility. CSR Implementation Area:

The Corporate Social Responsibility Programmes will be implemented in the Naikin, Birpur and Godha Tola; CSR Programme:

Hand pumps installation and Environment Sustainability. Hand pump will be installed in the primary schools of villages. Separate villages will be selected for next year. Environment Sustainability (ESP): The environmental sustainability is ensured by the activities of CSR programmes such as Plantation of Trees & Maintenance; Providing solar lights to nearby peoples; Water Supply maintenance and Restoration of ponds & water bodies. The last year all the activities will be implemented on a larger scale. S.No Activities Capital Cost (Lakh Recurring Cost Total CSR cost The brief budget outline of annual CSRRs) cost is as follows: (Lakh Rs) (Lakh Rs)

1 Hand pumps installation; 0.5 0.3 0.8 Water supply system, 2 Environment Sustainability 1.0 0.2 1.2 TOTAL 1.5 0.5 2.0 9.0 ENVIRONMENTAL MANAGEMENT PLAN

Budget for Environmental Protection S.No. Capital cost Annual recurring cost

1. Pollution Control 3.0 Lakhs (Dust suppression - 1.0 Lakhs (Separately provide break-up) Fixed type Sprinkler 1.0 Lakhs(Tarpaulin and 0.50 Lakhs cover for stack of ore) 2. Pollution Monitoring 0 Air – 60,000/- Water – 40,000/-

3. Occupational Health 100,000/- 50,000

4. Green Belt 0 100,000/- 5. Construction and maintenance of road 50,000 25,000/- 6. Fencing 1,00,000 50,000/- 7. Personal protective equipments 1,00,000/- 1,00,000/- 8. Others (specify) Garland Drain and settling 50,000 tank:. 2,00,000 Total Onsite Rs.disaster9.50 managementLakhs Rs1.007.25 LakhsLakhs

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES Project Name Naikin II Bauxite, Laterite and Fire Clay Mine Project Proponent M/s. Shri Krishnadas Tikaram 1(a)(i) Project Address Village- Naikin, Tehsil- Rampur Naikin, District- Sidhi, State- MP

BUDGET FOR OCCUPATIONAL HEALTH Particulars Capital Cost (Rs.)

For routine checkup 50,000 Medical aid as per ESI Scheme 75,000 Total 1,75,000/- Training 50,000

BUDGET FOR WATER, SHELTER AND SANITATION FOR MINE WORKER Scheme Capital Cost (In Rs) Recurring Cost (In Rs)

Drinking water facility 50,000 15,000 Rest shelter 50,000 10,000 Total 1,50,000 40,000 Sanitation (Urinal and Toilet ) 50,000 15,000

9.1 IMPORTANT ASPECTS OF THE ENVIRONMENTAL MANAGEMENT PLAN STAGE-WISE PLANTATION, & POST MINING LAND USE

The stage wise plantation and its areasStage are given wise Plantation in table below: Year Total Area covered during the year Survival rate % Plantation BF Area Nos. Green belt Nos. Area (sqm) Area (sqm)

1st year 520 0 520/5170 80 During Lease 700 700/7000 Nil 80 Period Total 1220 700/7000 520/5170 Afforestation of native species such as Karanj, Khamer, Neem, Gulmohar, Mango, Shisham, Kachnar, Gamhar, Jamun, Pipal, Mahua, Eucaluptus etc. is proposed in the barrier zone as well 9.1 IMPORTANT ASPECT OF ENVIRONMENTAL MONITORING PROGRAMME as backfilled area.

The monitoring of the environment parameters will be out sourced and carried by the lab of 10.0SPCBSUMMARY or a lab approved & CONCLUSION by MoEF/NABL.

As discussed, it is safe to say that the proposed facilities are not likely to cause any significant impact to the ecology of the area, as adequate preventive measures will be adopted to keep the various pollutants within the permissible limits. Green belt development around the area will also be taken up as an effective pollution mitigative technique, as well as to serve as biological indicators for the pollutants released from the premises of “Bauxite, Laterite and Fire clay Mine”. 11.0 DISCLOSURE OF CONSULTANTS ENGAGED

Aplinka Solutions & Technologies Pvt. Ltd., a NABET accredited Environment consulting organization has been appointed as Environment Consultant for preparation of Report and presentation in front of Concerned Authority.

Environment Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh Consultant ES