Appendix 'A' SENSITIZING THE PUBLIC ABOUT CORRUPTION DISPLAY OF STANDARD NOTICE BOARD BY DEPARTMENTS/ORGANIZATION REG: DETAILS OF CONTRACTS COSTING MORE THAN 20 LAKHS FOR THE MONTH OF OCT 2012 HQ CE (P) SWASTIK, C/O 99 APO Srl CA NO Name of work Name of contract/Firm with address CA Amount Date of Contract WO With Date of %age Prog Reasons for No in lacs acceptance Period Date Completion as as on date delay if any per WO No. 01

FOR THE YEAR 2008-09 1 CE (P) SWTK Construction of Toe wall, RCC Retaining walls fromKm24.00 to Km 51.00 on road - M/S Shiv Shakti Enterprises, A-340/02, 1792.25 28-Aug-08 15 Months 02-Sep-08 01 Dec 2009 44.64 Due to restricted /02 /2008-09 Nathula (JNM) under 764 BRTF Sector Swastik in state Near P&T Colony, Shastri Nagar, Jodhpur (Extended up to working season, 31 March 2013 ) snow fall and slow progress by contractor. 2 CE (P) Design and construction of 50 mtr single aspan (c/c of abutment bearings) major pmt bridge with M/S Mohan Bajaj, PS Road, Gangtok 332.5 31-Oct-08 24 Months 05-Jan-09 04 Jan 2011 (31 64.00 SWTK/09 steel truss superstructure (through type) on open foundation over river Siyam Nallah at km 6.900 Dec 2012) /2008-9 on road Rangrang-Dikchu under Project Swastik in Sikkim state.

3 CE (P) Supply and stacking of GSB & WBM materials and supply & Conveyance of ready mix M/S Shiv Shakti Enterprises, A-340/02, 496.53 17-Dec-08 90 Days 02-Jan-09 01 Apr 2009 (30 74.55 Due to non SWTK/18 bituminous materials for bm 75 mm and ac 40 mm for paved shoulders on INDIRA bye pass Near P&T Colony, Shastri Nagar, Jodhpur Sep 2012) completion of /2008-09 (10.200 km) under 758 BRTF (p) Swastik in Sikkim state. PHE work by state Govt and slow progress by contractor. 4 CE (P) Providing and laying 100 mm and 75mm consolidated thick, dense bituminous macadam 60mm M/S Mohan Bajaj, PS Road, Gangtok 1873.30 17-Dec-08 15 Months 19-Jan-09 18/4/2010 (TEP 3.24 Due to restricted SWTK/19 consolidated thick and asphaltic concrete 40mm consolidated thick including prime/tack coat, sent to Dte Up to working season, /2008-09 transportation to work site and rolling/compaction as per MORT&H specifications (fourth edition) 31 Dec 2012 snow fall and between km 38.500 to km 51.385 on Gangtok – Nathula road under 764 BRTF Project Swastik duly slow progress by in Sikkim state. Recommended) contractor.

5 CE (P) Providing and laying wet mix macadam 75mm thick &100mm thick dense bituminous M/S Mohan Bajaj, PS Road, Gangtok 937.95 17-Dec-08 344 Days 19-Jan-09 28 Dec 2009 14.99 Due to restricted SWTK/20/200 macadam60 mm consolidate thick and asphaltic concrete 40mm consolidated thick including (TEP sent to Dte working season, 8-09 prime/tack coat, transportation to work site and rolling/ compaction as per MORT&H Up to 31 Dec snow fall and specifications (fourth edition) between km 0.00 to km 5.660 on Sherathang – Nathula road under 2012 duly slow progress by 764 BRTF sector of project Swastik in Sikkim state Recommended) contractor.

6 CE (P) Providing and laying 100 mm and 75mm consolidated thick, Dence Bituminous Macadam 60mm M/S Shiv Shakti Enterprises, A-340/02, 2069.98 17-Dec-08 15 Monts 19-Jan-09 18/4/2010 17.73 Due to restricted SWTK/21/200 consolidated thick and Asphaltic Concrete 40mm consolidated thick including prime/tack coat Near P&T Colony, Shastri Nagar, Jodhpur (Extended up to working season, 8-09 transportation to work site and rolling/compaction as per MORT&H specifications (forth edition) 31 March 2013 ) snow fall and between km 24.250 to km 38.500 on Gangtok – Nathula road under 764 BRTF Project Swastik slow progress by in Sikkim state contracor.

7 CE (P) Construction of HB living shelters, HB Structures, HB Sheds in 129 RCC sector under 758 BRTF M/S MK Infrastructure Pvt Ltd, 04 Agrasen roads, 115.15 23-Mar-09 80 days 04-Apr-09 22 Jun 2009 (30 75.72 Due to restricted SWTK/29/200 (against Part-I of Sch 'A') of Project Swastik on Jawahar Lal Nehru Marg (JNM Road in the state Siliguri, 734005 May 2011) working season, 8-09 of Sikkim snow fall and slow progress by contracor. 8 CE (P) Construction of HB living shelters, HB Structures, HB Sheds in 130 RCC Sector under 764 M/S MK Infrastructure Pvt Ltd, 04 Agrasen roads, 482.26 23-Mar-09 90 days 01-Apr-09 29 Jun 2009 (31 11.58 Due to restricted SWTK/30/200 BRTF (against Part-II of Sch 'A')of Project Swastik on Jawahar Lal Nehru Marg (JNM Road in Siliguri, 734005 March 2011) working season, 8-09 the state of Sikkim snow fall and slow progress by contracor. Srl CA NO Name of work Name of contract/Firm with address CA Amount Date of Contract WO With Date of %age Prog Reasons for No in lacs acceptance Period Date Completion as as on date delay if any per WO No. 01

FOR THE YEAR 2009-10 9 CE (P) SUPPLY AND STACKING OF STONE METAL 90-45 MM, STONE METAL 63-45 MM, STONE M/s Harbhaj Dass Agarwal, 10C/O 92.43 24-Jun-09 120 days 01-Jul-09 28 Sep 2009 (31 58.67 Contract SWTK/06 METAL 40MM, STONE CHIPS 20MM, STONE CHIPS 13.2 MM, STONE SCREENING Avishek Enterprises, Binda Jayanti Jan 2012) cancelled /2009-10 11.20MM, STONE CHIPS 11.2MM AND COURSE SAND FOR SURFACING AND Building 31, Sevoke Road, Siliguri West PERMANENT WORKS BETWEEN KM 0.00 AND KM 20.00 ON ROAD SEVOKE-RANIPUL IN Bengal, Pin: 734001 764 BRTF ROAD SECTOR UNDER PROJECT SWASTIK IN THE STATE OF WEST BENGALSWASTIK IN SIKKIM STATE

10 CE (P) SUPPLY AND STACKING OF STONE METAL 90-45 MM, STONE METAL 63-45 MM, STONE M/s Harbhaj Dass Agarwal, 10C/O 167.69 24-Jun-09 120 days 01-Jul-09 27/3/2010 (31 52.92 Contract SWTK/07 METAL 40MM, STONE CHIPS 20MM, STONE CHIPS 13.2 MM, STONE SCREENING Avishek Enterprises, Binda Jayanti March 2012) cancelled /2009-10 13.20MM, STONE CHIPS 11.2 MM STONE SCREENING 11.2 MM AND COURSE SAND FOR Building 31, Sevoke Road, Siliguri West SURFACING AND PERMANENT WORKS BETWEEN KM 22.65 AND KM 52.10 ON ROAD Bengal, Pin: 734001 SEVOKE-RANIPUL UNDER 764 BRTF SECTOR UNDER PROJECT SWASTIK IN THE STATE OF WEST BENGAL

11 CE (P) PROVIDING AND LAYING OF DENSE BITUMINOUS MACADAM 75 MM THICK AND M/S MK Infrastructure Pvt Ltd, 4 Agrasen 690.99 10-Oct-09 90 Days 13-Oct-09 10 Jan 2010 83.86 Slow progress SWTK/17 ASPHALTIC CONCRETE 25 MM THICK ALL CONSOLIDATED WITH HMP MIX INCLUDING Road Siliguri-734005 (West Bengal) (15 Feb 2012) by contractor /2009-10 CLEANING OF ROAD SURFACE, LAYING OF PRIME/TACK COAT LAYING BY PAVER FINISHER AND ROLLING FOR SURFACING WORKS TO SPECIFIED THICKNESS BETWEEN KM 14.00 TO KM 28.180 ON SEVOKE–GANGTOK ROAD UNDER 764 BRTF IN THE STATE OF SIKKIM

12 CE (P) EXECUTION OF FORMATION (FRESH-CUTTING), PERMANENT AND SURFACING (ONLY M/S Nar Bahadur Dahal, PO Gayzing 2618.42 14-Dec-09 18 Months 22-Dec-09 21-Jun-11 19.1 Slow progress SWTK/20 GSB LAYER) WORKS FOR APPROXIMATE LENGTH 10 KM IN HILL SECTION FROM KM 0 Bazar, West-Sikkim (2620.17) by contractor /2009-10 (KM 6.80 ON EXISTING ROAD) TO KM 10(ON RE-ALIGNMENT) ON ROAD GANGTOK- NATHULA TO NH DOUBLE LANE SPECIFICATION UNDER 758 BRTF, PROJECT SWASTIK IN SIKKIM STATE

13 CE (P) EXECUTION OF FORMATION (FRESH CUTTING), PERMANENT AND SURFACING (ONLY Valecha Shivalaya Interdril, (JV) Madan 1991.76 15-Dec-09 15 Months 11-Jan-10 10 Apr 2011 35.71 Slow progress SWTK/21 GSB LAYER) WORKS FOR APPROXIMATE LENGTH 9.35 KM IN HILL SECTION FROM KM Kunj, Khud Cottage, Chaura Maidan (2057.71) (08 May 2012) by contractor /2009-10 10 ON REALIGNMENT TO KM 19.35 (ON EXISTING ROAD) ON ROAD GANGTOK-NATHULA Shimla-171004 TO NH DOUBLE LANE SPECIFICATION UNDER 758 BRTF PROJECT SWASTIK IN SIKKIM STATE 14 CE (P) DESIGN AND CONSTRUCTION OF 60 M SPAN (C/C OF ABUTMENT BEARINGS) MAJOR M/s Poddar construction company 414.00 17-Dec-09 24 Months 09-Jan-10 08-Jan-12 96 - SWTK/22 PERMANENT BRIDGE WITH PSC BOX GIDER SUPERSTRUCTURE ON OPEN Plot No 25/1, sector-9, Rohni, /2009-10 FOUNDATION OVER KALIKHOLA AT KM 15.985 ON ROAD SINGTHAM – DIKCHU UNDER New Delhi-110085 PROJECT SWASTIK IN SIKKIM STATE

15 CE (P) DESIGN AND CONSTRUCTION OF 45 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) M/S Mohan Bajaj, PS Road, Gangtok 270.00 18-Dec-09 24 Months 30-Dec-09 29-Dec-11 15 Case for change SWTK/23 MAJOR PERMANENT PSC BOX GIDER TYPE SUPERSTRUCTURE ON OPEN of type of /2009-10 FOUNDATION OVER RICHU NALLAH AT KM 83.170 ON ROAD GANGTOK – CHUNGTHANG foundation taken UNDER PROJECT SWASTIK IN SIKKIM STATE ISSUED VIDE LETTER NO. up with Dte. 24660/DGBR/SWTK /RITCHU/41/ E8 DATED 15 JUL 2009 AND SUBSEQUENTLY AMENDMENT ISSUED VIDE LETTER NO. 24660/DGBR/SWSTK/43/E8 DATED 31 JUL 2009 : Srl CA NO Name of work Name of contract/Firm with address CA Amount Date of Contract WO With Date of %age Prog Reasons for No in lacs acceptance Period Date Completion as as on date delay if any per WO No. 01

16 CE (P) CONCLUSION OF CONTRACT ENGAGEMENT OF CONSULTANT FOR FEASIBILITY STUDY Euphoria Engineering Solutions Pvt Ltd, 59.5 31-Dec-09 175 Days 09-Jan-10 7/2/2010 (31 Jan 35.84 CA to be SWTK/26 FOR CONSTRUCTION OF EXISTING MDR/CLASS-5/EARTHEN ROAD TO NHDLL Consultants, Contractors & Engineers, TG 2011) foreclosed due /2009-10 SPECIFICATIONS (FMN WIDTH 12 MTR AND CARRIAGE WAY WIDTH 7.00 MTR) Kaleon's Bldg, Ground Floor, Syari School to non clearence GEOMETRIC IMPROVEMENT / REALIGNMENT AND PREPARATION OF DETAILED Road, Upper Syari, Gangtok-737102 of FCLA PROJECT REPORT (DPR) FROM KM 0.00 TO KM 70.00 on road KHUNIAMORE TO TANGTA in West Bengal UNDER 764 BRTF (P) SWASTIK, OBTAINING LAND ACQUISITION & FOREST CLEARANCE (LA&FC) CLEARANCE FROM FOREST DEPARTMENT AND LAND REVENUE DEPARTMENT FROM GOVT OF WEST BENGAL ON BEHALF OF BRO FOR THIS WORK AND OBTAINING APPROVAL OF THE DPR FROM MOSRT&H

17 CE (P) ENGAGEMENT OF CONSULTANT FOR FEASIBILITY STUDY FOR CONSTRUCTION OF Euphoria Engineering Solutions Pvt Ltd, 29.25 06-Jan-09 150 Days 15-Jan-10 13/6/2010 (31 10 CA To be SWTK/27 EXISTING FOOT TRACK ROAD TO NHDL SPECIFICATIONS (FMN WIDTH 12 MTR AND Consultants, Contractors & Engineers, TG March 2011) foreclosed due /2009-10 CARRIAGE WAY WIDTH 7.00 MTR) GEOMETRIC IMPROVEMENT / REALIGNMENT AND Kaleon's Bldg, Ground Floor, Syari School to non clearance PREPARATION OF DETAILED PROJECT REPORT (DPR) FROM KM 0.00 TO KM 20.00 ON Road, Upper Syari, Gangtok-737102 of FCLA. ROAD RACHELA TO ARITAR IN SIKKIM UNDER 764 BRTF (P) SWASTIK, OBTAINING LAND ACQUISITION & FOREST CLEARANCE (LA&FC) CLEARANCE FROM FOREST DEPARTMENT AND LAND REVENUE DEPARTMENT FROM BOTH GOVT OF SIKKIM AND WEST BENGAL ON BEHALF OF BRO FOR THIS WORK AND OBTAINING APPROVAL OF THE DPR FROM MOSRT&H AND OBTAINING LAND ACQUISITION & FOREST CLEARANCE (LA&FC) CLEARANCE ONLY LAND REVENUE DEPARTMENT AND FOREST DEPARTMENT FROM BOTH GOVT OF WEST BENGAL AND OBTAINING APPROVAL OF THE DPR PREPARED BY BRO FROM MOSRT&H ON BEHALF OF BRO FROM KM 0.00 TO KM 25.00 ON ROAD TANGTA TO RACHELA IN WEST BENGAL’

FOR THE YEAR 2010-11 18 CE (P) DESIGN AND CONSTRUCTION OF 60 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) Vij Enginrring & Consultant Pvt Ltd, B-68, 369.00 21-May-10 24 Months 01-Jun-10 31-May-12 0 Existing br site SWTK/03 MAJOR PERMANENT BRIDGE WITH STEEL TRUSS SUPERSTRUCTURE (DECK TYPE) ON Swami Nagar (North), Near Chirag Delhi not feasible due /2010-11 OPEN FOUNDATION OVER NAMAK NALLAH AT KM 4.154 ON ROAD RANGRANG DIKCHU Fly Over, Outer Ring Road, New Delhi- to deep crack at UNDER PROJECT SWASTIK IN SIKKIM STATE 110017 abut fdn location. Fresh Bridge scheme 19 CE (P) DESIGN AND CONSTRUCTION OF 70 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) M/S Nar Bahadur Dahal, PO Gayzing 421.00 10-Jun-10 24 Months 25-Jun-10 10-Mar-13 68.75 -to be finalized. SWTK/04 MAJOR PERMANENT BRIDGE WITH STEEL SUPERSTRUCTURE (DECK TYPE) ON OPEN Bazar, West-Sikkim /2010-11 FOUNDATION OVER KHUMDONG KHOLA AT KM 27.395 ON ROAD DIKCHU UNDER PROJECT SWASTIK IN SIKKIM STATE 20 CE (P) SUPPLY AND STACKING OF STONE CHIPS 13.2 MM; AT HMP SITE NEAR MUNSHITHANG M/S Janam Lachenpa, Lachen, North 85.6 31-Aug-10 150 Days 10-Sep-10 06 Feb 2011 (20 83.37 Slow progress SWTK/06 ON CHUNGTHANG LACHEN ROAD FOR RESURFACING WORKS UNDER 758 BRTF OF Sikkim Feb 2012) by contractor /2010-11 PROJECT SWASTIK IN THE STATE OF SIKKIM

21 CE (P) SWTK SUPPLY AND STACKING OF DRY COARSE SAND FOR PMT WORKS AS PER TABLE 1000- M/s Anup Kumar Agarwal, 108.96 10-Sep-10 390 days 24 Sep 210 18/10/2011 ( 44.16 Slow progress /08/2010-11 2 ZONE-I OF MORTH SPECIFICATIONS FOR ROAD AND BRIDGE (FOURTH REVISION) Bazar, East Sikkim TEP Up to 20 by contractor BETWEEN KM 0.00 TO 15.600 ON ROAD CHANGU-NAKCHOK-TAMZE AND KM 0.00(KM Pin-737133 March 2013 19.80 OF EXISTING JNM) TO KM 4.355(KM 24.360 OF EXISTING JNM) ON GANGTOK- recommended NATHULA ROAD UNDER 758 BRTF PROJECT SWASTIK IN THE STATE OF SIKKIM to Dte) Srl CA NO Name of work Name of contract/Firm with address CA Amount Date of Contract WO With Date of %age Prog Reasons for No in lacs acceptance Period Date Completion as as on date delay if any per WO No. 01 22 CE (P) SWTK EXECUTION OF BUSG 75 MM THICK AND MSS TYPE ‘B’ 20 MM THICK FOR Interdril (Asia Ltd), Khud Cottage, Madan 133.55 18-Sep-10 120 days 25-Sep-10 22 Jan 2011 100 Work /09/2010-11 RESURFACING WORKS FROM KM 53.27 TO KM 56.10, KM 58.00 TO KM 66.105 AND KM Kunj, Chaura Maidan Shimla Pin-171004 (25 March Completed. 66.870 TO KM 68.00 ON ROAD GANGTOK - CHUNGTHANG UNDER 758 BRTF PROJECT 2011) SWASTIK IN SIKKIM STATE 23 CE (P) SWTK DESIGN AND CONSTRUCTION OF 50 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) M/s MP Agarwal Namchi, South Sikkim 508.50 16-Nov-10 24 months 22-Nov-10 21-Nov-12 11 - /13/2010-11 MAJOR PERMANENT WITH STEEL TRUSS TYPE SUPERSTRUCTURE (THROUGH TYPE) ON OPEN FOUNDATIONS OVER ZEEMACHU RIVER AT KM 4.100 ON ROAD LACHEN KALEP UNDER PROJECT SWASTIK IN SIKKIM STATE 24 CE (P) SWTK DESIGN AND CONSTRUCTION OF 50 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) M/s Vikash Construction Company, # 517 256.00 18-Nov-10 24 months 25-Nov-10 24-Nov-12 7.5 Slow progress /15/2010-11 MAJOR PERMANENT WITH STEEL TRUSS TYPE SUPERSTRUCTURE (DECK TYPE) ON A, VPO, Shahpur (Ambala)-133004 by contractor OPEN FOUNDATIONS OVER B-I RIVER AT KM 10.80 ON GANGTOK CHUNGTHAG UNDER PROJECT SWASTIK IN SIKKIM STATE 25 CE (P) SWTK DESIGN AND CONSTRUCTION OF 40 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) M/s Vikash Construction Company, # 517 219.10 18-Nov-10 24 Months 25-Nov-10 24-Nov-12 37.5 Slow progress /16/2010-11 MAJOR PERMANENT WITH STEEL TRUSS TYPE SUPERSTRUCTURE (DECK TYPE) ON A, VPO, Shahpur (Ambala)-133004 by contractor OPEN FOUNDATIONS OVER B-ix RIVER AT KM 36.050 ON GANGTOK CHUNGTHAG UNDER PROJECT SWASTIK IN SIKKIM STATE

26 CE (P) SWTK DESIGN AND CONSTR OF 35 M SINGLE SPAN (C/C OF ABUTMENT BEARINGS) MAJOR M/s Vikash Construction Company, # 517 166.00 18-Nov-10 24 Monhs 25-Nov-10 24-Nov-12 12 Slow progress /17/2010-11 PERMANENT WITH PSC BOX GIRDER SUPERSTRUCTURE (DECK TYPE) ON OPEN A, VPO, Shahpur (Ambala)-133004 by contractor FOUNDATIONS OVER B-V RIVER AT KM 30.00 ON GANGTOK CHUNGTHAG UNDER PROJECT SWASTIK IN SIKKIM STATE 27 CE (P) SWTK CONSTRUCTION OF 130 M MAJOR PMT BRIDGE WITH PSC CONTINUOUS/BALANCE M/s Poddar construction company Plot 1350 16-Dec-10 24 Months 23-Dec-10 22-Dec-12 42.75 - /21/2010-11 CANTILEVER SUPERSTRUCTURE AND ABUTMENT ON OPEN FOUNDATION OVER RIVER No 25/1, sector-9, Rohni, TEESTA AT KM 84.600 WITH APPROACH ROAD AND DIVERSION ROAD ON GANGTOK- New Delhi-110085 CHUNGTHANG IN SIKKIM STATE AS DETAILED IN THE TENDER ENQUIRY NO. 24757/DGBR/SWTK/B-TOONG/17/E8 DATED 12 MAY 2010

28 CE (P) SWTK SPOT TENDER FOR RISK & COST FOR SUPPLY AND STACKING OF COURSE M/s Anup Kumar Agarwal, Rhenock 71.09 21-Dec-10 120 days 28-Dec-10 4/30/2011 (30 100 CA foreclosed. /22/2010-11 AGGREGATE 40MM AND 20 MM SIZE AND SAND FOR IMPROVEMENT OF MANGAN Bazar, East Sikkim, Pin-737133 Apr 2012 TOWN AREA BETWEEN KM 66.105 AND KM 66.870 ON ROAD GANGTOK CHUNGTHANG recommended) UNDER 758 BRTF PROJECT SWASTIK IN SIKKIM STATE : CA NO. CE (P) SWTK/19/2010-11

29 CE (P) SWTK ENGAGEMENT OF CONSULTANT FOR CARRYING OUT SURVEY WITH TOTAL STATION M/s Zommah, Engineers & Consultant, 18.13 04-Jan-11 60 Days 11-Jan-11 10 Mar 2011 15 Due to /23/2010-11 AND PREPARATION OF “DETAILED PROJECT REPORT” USING ADVANCED SOFTWARE Pvt Ltd, D-84, 4th floor, Tikona Park, (TEP up to 31 interference of FOR CONSTRUCTION OF ROAD FROM IW SPECIFICATION TO NHDL SPECIFICATION Jamia Nagar, New Delhi-110025 Oct 2012 road and rail INCLUDING GEOMETRIC IMPROVEMENT/REALIGNMENT FROM KM 28.425 TO KM 52.10 recommneded to alignment, the ON SEVOKE- ROAD (NH 31A) IN WEST BENGAL STATE UNDER 764 BRTF (P) Dte) revised survey SWASTIK AND OBTAINING APPROVAL OF DPR FROM MOSRT&H. is going on.

30 CE (P) SWTK ENGAGEMENT OF CONSULTANT FOR CARRYING OUT SURVEY WITH TOTAL STATION CETEST, CE Testing Company Pvt Ltd, 21.83 04-Jan-11 90 days 11-Jan-11 09 Apr 2011(15 40 Draft DPR /24/2010-11 AND PREPARATION OF “DETAILED PROJECT REPORT” USING ADVANCED SOFTWARE 124A, NSC Bose Road Nov 2011) under FOR CONSTRUCTION OF ROAD FROM CLASS-9 SPECIFICATION TO NHDL Kolkata-700092 observations SPECIFICATION INCLUDING GEOMETRIC IMPROVEMENT/ REALIGNMENT FROM ARITAR- RANGPO (VIA KINGSTON Jn-, APPX LENGTH 37 KMS) IN SIKKIM STATE UNDER 764 BRTF (P) SWASTIK AND OBTAINING APPROVAL OF DPR FROM MOSRT&H. Srl CA NO Name of work Name of contract/Firm with address CA Amount Date of Contract WO With Date of %age Prog Reasons for No in lacs acceptance Period Date Completion as as on date delay if any per WO No. 01 31 CE (P) SWTK ENGAGEMENT OF CONSULTANT FOR CARRYING OUT SURVEY WITH TOTAL STATION CETEST, CE Testing Company Pvt Ltd, 12.6 04-Jan-11 60 days 11-Jan-11 10 Mar 2011 40 Draft DPR /25/2010-11 AND PREPARATION OF “DETAILED PROJECT REPORT” USING ADVANCED SOFTWARE 124A, NSC Bose Road (15 Nov 2011) under FOR CONSTRUCTION OF ROAD FROM CLASS-9 SPECIFICATION TO NHDL Kolkata-700092 observations SPECIFICATION INCLUDING GEOMETRIC IMPROVEMENT/ REALIGNMENT FROM DALEPCHAN - - ROLEP, APPROX LENGTH 17.50 KM IN SIKKIM STATE UNDER 764 BRTF (P) SWASTIK AND OBTAINING APPROVAL OF DPR FROM MOSRT&H.

32 CE (P) SWTK SUPPLY AND STACKING OF STONE AGGREGATES OF SIZE 26.50MM, 13.20MM, 6.70MM M/s Shivam Enterprises, 182.39 10-Feb-11 390 days 17-Feb-11 13 Mar 2012 50.84 Slow progress /29/2010-11 AND CRUSHER DUST AT MILE-8 ON JNM ROAD UNDER PART-II FOR DBM AND AC 13 PT Lane Chandmari, (17 Dec 2012) by contractor WORKS UNDER 129 RCC (GREF) UNDER 758 BRTF PROJECT SWASTIK IN THE STATE Darjeeling-734101 OF SIKKIM

33 CE (P) SWTK EXECUTION OF CONSTRUCTION OF NATIONAL HIGHWAY DOUBLE LANE M/s Abhyudaya Housing & 9755.29 24-Feb-11 36 Months 10-Feb-11 10-Jan-15 0 - /30/2010-11 SPECIFICATIONS FOR REALIGNMENT STRETCHES BETWEEN KM 20.00 TO 27.70 ON Construction Pvt Ltd, ROAD SEVOKE-GANGTOK (NH-31A) TAKE OFF POINT AT KM 20.00 (KM 0.00) AND 2nd Floor, Abhyudaya Tower, MEETING POINT AT KM 27.700 (APPROXIMATE LENGTH 16 KMS) AND CONSTRUCTION 2-Meerabaimarg, OF MAJOR PMT BRIDGE OF SPAN 70 MTR AT KM 9.625 AND FOR MINOR BRIDGES OF Lucknow-01 DIFFERENT SPAN (TOTAL 42 MTR SPAN LENGTH) AT KM 6.70, KM 7.225, KM 8.50 AND KM 14.125 ON REALIGNMENT STRETCHES BETWEEN KM 20.00 TO 27.700 (APPROXIMATE LENGTH 16.00 KM) ON SEVOKE-GANGTOK ROAD (NH-31A) IN WEST BENGAL STATE ; CA NO.CE (P) SWTK /30/2010-11

34 CE (P) SWTK SUPPLY AND STACKING OF STONE AGGREGATES(AS PER MoSRT&H TABLE 500-10 M/s Kamala Tamang, Dikchu Bazar 59.39 07-Mar-11 150 Days 14-Mar-11 11/13/2011 (11 61.62 Slow progress /33/2010-11 GRADING 2) FOR DBM WORKS AT (HMP LOC AT MUNSHITHANG) KM 8.00 ON JUN 2012) by contractor CHUNGTHANG LACHEN ROAD FOR SURFACING WORKS UNDER 758 BRTF PROJECT SWASTIK IN THE STATE OF SIKKIM

FOR THE YEAR 2011-12 35 CE (P) SWTK DESIGN AND CONSTRUCTION OF MAJOR PMT BRIDGE 120 MTR WITH BALANCE M/s Poddar Construction Company, Plot 990.00 02-Nov-11 24 Months 09-Nov-11 08-Nov-13 6.25 - /03/2011-12 CANTILEVER PSC CONTINUOUS TYPE SUPERSTRUCTURE AND ABUTMENT ON OPEN No 25/1, Sector-9, Rohni, New Delhi- FOUNDATION AND PIERS ON WELL FOUNDATION OVER B-III RIVER AT KM 23.450 ON 110085 ROAD GANGTOK CHUNGTHANG UNDER PROJECT SWASTIK IN SIKKIM STATE AS DETAILED IN THE TENDER ENQUIRY NO. 24777/DGBR/SWTK/B-III/24/E8 DATED 23 MAY 2011 AND AMENDED VIDE THIS OFFICE LETTER NO. 24777/DGBR/SWTK/B-III/42/E8 DATED 15 JUN 2011, 24777/DGBR/SWTK/B-III/45/E8 DATED 21 JUN 2011 AND 24777/DGBR/SWTK/B-III/48/E8 DATED 01 JUL 2011: (CA NO. CE (P) SWTK/03/2011-12

36 CE (P) SWTK RE-TENDER FOR SUPPLY AND STACKING OF STONE AGGREGATES SIZE 26.50 MM, M/s GL Bhutia, Burtuk, East Sikkim PIN 158.86 21-Dec-11 180 days 04-Jan-12 01 Jul 2012 (25 5.4 Slow progress /04/2011-12 SIZE 13.20 MM AND STONE DUST AT MILE 04 ON ROAD JNM FOR WMM WORKS ON JNM 737101 Dec 2012) by contractor ROAD IN BETWEEN KM 6.45 AND 9.903 UNDER 129 RCC (GREF) UNDER 758 BRTF, PROJECT SWASTIK IN THE STATE OF SIKKIM

37 CE (P) SWTK HANDLING AND CONVEYANCE OF STORES OF ANY DESCRIPTION FROM M/s Akhil Chandra Sen, 85.83 27-Dec-11 365 days 10-Jan-12 09-Jan-12 - /05/2011-12 NJP/SILIGURI/RANGAPANI RAILWAY STATION TO 532 SS&TC IN WEST BENGAL C/O Anandmoyee, Automobiles, Pronami Mandir Road, Sevoke Road, Siliguri Srl CA NO Name of work Name of contract/Firm with address CA Amount Date of Contract WO With Date of %age Prog Reasons for No in lacs acceptance Period Date Completion as as on date delay if any per WO No. 01 38 CE (P) SWTK CONSULTANCY SERVICES FOR ENGAGEMENT OF CONSULTANT FOR PREPARATION Chatanya Project Consultancy Pvt Ltd, 149 22-Mar-12 240 days 02-Apr-12 27-Nov-12 0 - /07/2011-12 OF DETAILED PROJECT REPORT FOR CONSTRUCTION OF APPROXIMATE LENGTH 1000 Sector-04, Vaishali Ghaziabad, (UP) MTR SPAN VIA DUCT AT RANGPO BETWEEN KM 51.10 (TAKE OFF POINT IN WB) TO KM 201012 53.90 (MEETING POINT IN WB) ON SEVOKE GANGTOK ROAD (NH-31A) UNDER 764 BRTF (P) SWASTIK IN THE STATE OF SIKKIM

39 CE (P) SWTK SUPPLY AND STACKING OF DRY COARSE SAND FOR PERMANENT WORKS AND M/s GL Bhutia, Burtuk East Sikkim 45.71 30-Mar-12 180 days 04-Apr-12 08-Oct-12 18.77 Slow progress /08/2011-12 SURFACING WORKS ON NH-31A IN BETWEEN ROAD SECTOR RANGPO-RANIPUL (KM by contractor 54.00 AND KM 80.60) UNDER 87 RCC (GREF) UNDER 764 BRTF PROJECT SWASTIK IN THE STATE OF SIKKIM: (CA NO. CE (P) SWTK/ 08/2011-12

FOR THE YEAR 2012-13 40 CE (P) SWTK SUPPLY AND STACKING OF STONE METAL 53 MM DOWN GRADED, STONE CHIPS 22.40 M/S Shree Karni Traders, of Bikaner 395.43 09-Apr-12 270 days 11-Apr-12 10-Jan-13 31.48 - /01/2012-13 MM DOWN GRADED BOTH AS PER TABLE 500-7 OF MORT&H SPECIFICATIONS FOR (Rajsthan), Pin-334001 ROAD AND BRIDGE WORKS FOR BUSG WORKS BETWEEN KM 80.400 AND 92.666 ON ROAD SEVOKE GANGTOK (NH-31A AND STONE AGGREGATES OF 25 MM (NOMINAL SIZE) FOR DBM 60 MM AS PER TABLE 500-10 OF MORT&H SPECIFICATIONS AND 13 MM (NOMINAL SIZE) FOR AC 40 MM AS PER TABLE 500-18 OF MORT& H SPECIFICATIONS FOR ROAD AND BRIDGE WORKS AT HMP SITE AT MILE-08 ON JNM ROAD AND AT HMP SITE AT KM 73.00 (MARTHAM) ON NH-31 A SEVOKE GANGTOK ROAD FOR IMPROVEMENT AND STRENGTHENING OF ROAD BETWEEN KM 80.400 AND 92.666 ON ROAD SEVOKE GANGTOK (NH-31A) UNDER 758 BRTF PROJECT SWASTIK IN THE STATE OF SIKKIM.

41 CE (P) SWTK HANDLING A& CONVEYANCE OF GOODS FROM 532 SS&TC TO VAROUS LOCS UNDER The Sikkim Nationalised Transport (SNT), L/S 21-Apr-12 344 days 21-Apr-12 31-Mar-13 38 - /MOT-02/2012-758/764 BRTF (P) SWTK IN SIKKIM STATE. Govt of Sikkim, 13 Gangtok – 737101 42 CE (P) SWTK SUPPLY AND STACKING OF STONE METAL SIZE 40MM, STONE CHIPS SIZE 20MM & M/s Gyatsola Bhutia 303.17 23-Jul-12 270 days 01-Aug-12 27-Apr-13 0 /03/2012-13 COARSE SAND DRY FOR PERMANENT WORKS FOR WIDENING AND STRENGTHENING Burtuk, OF ROAD BETWEEN KM 4.475 AND KM 14.075 ON SEVOKE GANGTOK (NH-31A) ROAD, Gangtok East Sikkim UNDER PHASE ‘A’ OF SARDP-NE UNDER 764 BRTF, PROJECT SWASTIK IN THE STATE PIN-737101 OF WEST BENGAL

43 CE (P) SWTK SUPPLY OF VARIOUS SIZES OF TYRES, TUBES & FLAP RUSTS MAKE CEAT/ APOLLO/ M/s. RS Trade & Agency, Thakuria 182.56 04-Aug-12 90 days 20-Nov-12 18-Nov-12 0 /04/2012-13 MRF/GOOD YEAR/JK TYRE/BIRLA/BRIDGE STONE FROM ORIGINAL MANUFACTURERS / Building 3rd Floor, F.A. Road, AUTHORIZED DEALERS AT 532 SS & TC, SILIGURI (WEST BENGAL) UNDER PROJECT Kumarpara, Guwahati (Assam), Pin – SWASTIK 781001

44 CE (P) SWTK SUPPLY AND STACKING OF SAND FOR PMT WORKS FOR IMPROVEMENT / UP M/s Anup Kumar Agarwak, Rhenok Bazar 49.66 06-Oct-12 180 days 20-Nov-12 13-Apr-13 0 /05/2012-13 GRADATION OF ROAD GANGTOK CHUNGTHANG FROM MANGAN KM 66.870 TO TOONG E/Sikkim. KM 84.600 UNDER 758 BRTF UNDER PROJECT SWASTIK IN THE STATE OF SIKKIM

(PN Yadav) SE (Civ) Dir (Contract) For Chief Engineer