TANO NORTH DISTRICT ASSEMBLY DUAYAW-

ANNUAL PROGRESS REPORT 2016

FEBRUARY, 2017

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 1

Contents CHAPTER ONE ...... 3 1.1 Introduction ...... 3 1.2 The Key M & E Objectives for the year 2016 ...... 3 1.3 Processes Involved and Difficulties Encountered ...... 3 1.4 Status of Implementation of DMTDP ...... 4 1.4.1. Ensuring and Sustaining Macroeconomic Stability ...... 4 1.4.2. Enhanced Competitiveness of ’s Private Sector ...... 4 1.4.3. Accelerated Agricultural Modernization and Sustainable Natural Resource Management5 1.4.4. Infrastructure and Human Settlement Development ...... 5 1.4.5. Human Development, Productivity and Employment...... 6 1.4.6. Transparent and Accountable Governance ...... 7 CHAPTER TWO ...... 8 2.0 Monitoring and Evaluation Activities Report ...... 8 2.1 Programmes/Projects status for the year 2016 ...... 8 2.2 Update of funding Sources ...... 8 Receipts/Disbursement of Funds for the year 2016 ...... 9 2.3 Update on Indicators and Targets ...... 10 2.4 Update on Critical Development and Poverty Issues ...... 10 ANNEX A: STATUS OF IMPLEMENTATION REPORT 2016 ...... 14 ANNEX B: PROJECTS AND PROGRAMMES REGISTER AS AT 31ST DECEMBER, 2016 ...... 26

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 2

CHAPTER ONE

1.1 Introduction This Annual Progress Report (APR) covers an assessment of the progress made in the implementation of the government’s Medium Term National Development Policy Framework-Ghana Shared Growth and Development Agenda (GSGDA) in the district in its third year of implementation.

This report has been compiled from an assessment of the status of indicators and targets, which has been adopted for monitoring and evaluating the achievements and impacts of key policy and programme interventions undertaken during the year under review. It is based on the summary of achievements during the year. It also provides updates on the following:

• The status of implementation of MTDP GSGDA II: (2014-2017) • Update of programme/project status for the year 2016 • Receipts and disbursement from funding sources for the period 2016 • An update on the set of core indicators agreed on in the GSGDA II M & E Plan • An update on critical development and poverty issues • Participatory M & E and other studies undertaken during the period under review • Policy recommendation to address key weakness in the implementation

1.2 The Key M & E Objectives for the year 2016 This report provides information on the progress being made by the Tano North District Assembly in the implementation of the GSGDA II: MTDP (22014-2017). It seeks to monitor progress towards the attainment of targets and to demonstrate results as part of accountability and transparency to the citizenry and other stakeholders. It also defines the various weaknesses and bottlenecks that are likely to hinder the achievement of the goals and objective set in the MTDP for recommendations for addressing any shortcoming that may be identified during assessment of performances.

1.3 Processes Involved and Difficulties Encountered The preparation of the 2016 Annual Progress Report was facilitated by the DPCU with inputs from MDA’s and other stakeholders. Monitoring and Evaluation data were compiled from both primary and secondary source. Secondary data were compiled from the various quarterly and annual reports of Departments and Agencies, Development Partners, NGO’s and CSO’s as well as from the District Sub- structures.

Designed questionnaires and interviews were used in obtaining the primary data. To facilitate data collection and analysis, standard reporting formats were prepared for all sector departments. TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 3

Data collected focused on the core NDPC as well as specific District Indicators and targets identified in the M & E plan. Data was collated, analyzed and interpreted by the DPCU in collaboration with MDA’s. The draft APR was prepared by the DPCU and validated at a stakeholders workshop. Comments and suggestions emanating from the review workshop had been incorporated in this final report.

During the preparation of this report, a number of challenges were encountered with regard to data collection. These include:

‹ Inadequate capacity in M & E at MDA’s and sub-structures levels ‹ Inadequate logistical an financial support for effective and continuous M & E activities ‹ Inadequacy of updated data on socio-economic indicators ‹ Difference in M & E calendar and reporting formats ‹ Unavailability of established baselines and targets at MDAs levels, especially on many of the new indicators selected to track progress

1.4 Status of Implementation of DMTDP

1.4.1. Ensuring and Sustaining Macroeconomic Stability ‹ Public education on fee fixing ‹ Update rent ledger to collect arrears ‹ Organized capacity building workshop for revenue staff 1.4.2. Enhanced Competitiveness of Ghana’s Private Sector ‹ Support to Business Advisory Centre ‹ Organized Community sensitization and animation programme on new product development for 9 males and 56 females ‹ Group dynamic training for 53 participants (13 male, 40females) ‹ Offered Business Counseling for 110 selected SMEs (40 males, 70 females) ‹ Organized Credit Management training for 15 males and 10 females ‹ Trained 36 females and 2 males in oil palm processing ‹ Trained 20 females and 3 males in baking and confectionary at Kwasuagya ‹ Trained 20 females and 3 males in bead production ‹ Trained 20 males and 5 females in snail rearing at Subonpang ‹ Trained 2 males and 36 females in manicure and pedicure ‹ Provided advisory and extension services to 5 males and 8 females to start their own business ‹ Facilitated the registration of 10 males and 60 females in NVTI proficiency exams

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 4

‹ Visited co-operative groups in the district ‹ Audited registered and non-registered co-operative societies 1.4.3. Accelerated Agricultural Modernization and Sustainable Natural Resource Management ‹ Procured and supplied 1000 cutlasses to support farmers ‹ Procured and supplied 1000 weedicides to support farmers ‹ Supplied material for the completion of District Agric Office accommodation ‹ District farmers day celebrated ‹ Trained Fifty-one cassava farmers (21Men, 30 women) on Food hygiene and Safety programme at Abesewa ‹ Distributed 400 bundles of sika bankye and 400 bundles of bankyehemaa cassava planting material ‹ Distributed 4 bags (200kg) of seed maize “omankwa” to farmers ‹ Registered 3039 farmers for the 2016 fertilizer subsidy by electronic and manual system ‹ Distributed 1,200 kg of AGRA seed rice to Mankranho, Afrisipakrom, , Subongpang, Dwenase and Tanokrom ‹ Assisted 25 farmers to produce maize for AGRICARE ‹ Organized plant clinic for 189 farmers (155 males, 34 females) to help manage disease and pest 1.4.4. Infrastructure and Human Settlement Development ‹ Extended electricity to Nwankanso (Yamfo) and Adrobaa ‹ Extended street light to Yamfo College of Health ‹ Procured 30 electric poles ‹ Procured 100 D Iron, 10No. Stay and 2No. coil 25mm cable ‹ Procured 120mm Aluminum cables ‹ Organized planning education in major towns in the district and Charity Fm ‹ Sensitization on building regulations undertaken ‹ Completion of 3No. planning scheme ‹ Constructed Urinal and WC at Duayaw Nkwanta station ‹ Constructed 1No. 10 Seater Aqua Privy at Techire ‹ Constructed 1No. 10 Seater Aqua Privy at Techire ‹ Constructed 1No. 10 Seater Aqua Privy at Bomaa ‹ Constructed 1No. 10 Seater Aqua Privy at Afrisipakrom ‹ Constructed 1No. 10 Seater Aqua Privy at Subonpang

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 5

‹ Payment for Mechanized 1No. borehole at Abuom ‹ Mechanized of 2No. boreholes at Subonpang and Ahyiayem ‹ Drilled 1No. Borehole at Asukese ‹ Drilled 2No. Borehole at Bomaa and Abrosanase ‹ Drilled and mechanized 1No. Borehole and constructed 9m high level reinforced stand at Yamfo College of Health ‹ Evacuation of refuse dump ‹ Pushing and leveling of refuse dump at Afrisipakrom ‹ Opened up Susanso Town Roads ‹ Reshaped and maintained Nkrankrom to Abodeim road ‹ Reshaped Nkwantabisa, Onwe, Nkurakan, and Dumakwae roads ‹ Constructed 3No round culvert at Kwasuagya ‹ Supported DWST activities ‹ Organized food screening for food vendors ‹ Conducted school health education 1.4.5. Human Development, Productivity and Employment ‹ Distributed 1000 dual desk to basic schools ‹ Supported My First Day at School ‹ Support provided for Mock Exams and STME ‹ 1No. 3 unit classroom block with office and store at Duayaw Nkwanta Islamic Completed ‹ Constructed 1No. 3 unit classroom block with Office, KVIP and furniture at Kwasuagya ‹ 2No. 3 Unit classroom block at Duayaw Nkwanta and Tanokrom on-going ‹ 2No. 3 Unit classroom block at Yamfo Methodist and Twewaaho on-going ‹ Rehabilitated of 6-Unit Classroom block at Boakye Tromo Snr High ‹ 15 schools benefited from the School Feeding Programme ‹ Assisted students financially with an amount of GH¢ 42,175.00 ‹ Sponsored students with an amount of GH¢36,221.00 ‹ 2 Unit nurses quarters at Duayaw -Nkwanta completed ‹ Constructed 2No. CHPs Compound at Tanoano and Sukuum ‹ Constructed 2unit lecture hall with office and store at Yamfo college of Health ‹ Constructed 2unit lecture hall with office and store at Yamfo college of Health ‹ Completion District Health Centre with OPD on-going ‹ Support for NID activities and other Health programmes

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 6

‹ Supported Adolescent Reproductive Health programmes ‹ HIV/AIDS activities supported ‹ Supported Social Welfare and Community Development activities ‹ Disbursed GH¢ 61,500.00 to People with Disability ‹ Disbursed funds to 98 beneficiaries of LEAP 1.4.6. Transparent and Accountable Governance ‹ Rehabilitated existing markets ‹ Furnished the District Assembly Hall with furniture ‹ Procured and supplied 100 bags of cement and 30 packets of roofing sheets to support community initiated projects ‹ Purchased 2No. Nissan Hard body pickups ‹ Purchased 2No. Laptops, 4No. UPS and 1 multifunctional printer ‹ Organized capacity building workshop for staff ‹ Organized 4 quarterly DPCU meetings ‹ Held 4 plan review meetings ‹ Organized 2 quarterly stakeholders review meeting ‹ Monitoring and evaluation of projects/programmes ‹ Rehabilitated old assembly offices ‹ Maintenance of security ‹ Purchased stationary and other logistics

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 7

CHAPTER TWO

2.0 Monitoring and Evaluation Activities Report

2.1 Programmes/Projects status for the year 2016 Annex B is the project and programme register. This has been updated to reflect the status of projects and programme implementation as at 31st December, 2016.

In the year under review, the Health Sector received a capital investment with the completion of 2No. CHPs Compound (Tanoano & Sukuum) at a cost of GH¢304,496.96 and a 2 bedroom Nurses Quarters (Duayaw Nkwanta). The Completion of the District Health Centre with OPD is still ongoing.

Under Education, 3No. Classroom blocks were completed and 4No. is still on-going at a cost of GH¢334,211.64 and GH¢489,893.97 respectively. 2No. 2Unit Lecture Halls were also constructed for the Yamfo college of Health at a cost of GH¢327,082.35.

The Water and Sanitation sector saw the construction of 5No. 10 seater aqua privy toilets at Techire, Bomaa, Afrispakrom and Subonpang and the Drilling and mechanization of 1No. Borehole with construction of 9m high level reinforced stand at Yamfo College of Health. There was also the drilling of 6No. Boreholes out of which 4No were mechanized.

On roads, some feeder roads were reshaped and maintained in the district. The following roads were reshaped: Nkrankrom Junction to Abodiem, Nkwantabisa, Onwe, Nkurankan, Mampongteng, and Dumakwae. Susuanso Town Roads were also opened up. 3No. round culverts were constructed on the Kwasuagya road. Access road to the District Assembly was also reshaped.

2.2 Update of funding Sources The following shows updates on the sources of fund by the Assembly from 2014 -2016

Sources Estimated Actual 2014 Estimated Actual 2015 Estimated Actual 2016 Year 2014 GH¢ GH¢ 2015 GH¢ GH¢ 2016 GH¢ GH¢ DACF 2,692,423.00 871,874.78 3,457,,360.00 1,991,282.34 3,172,639.14 2,151,155.69 IGF 328,261.00 216,452.82 272,727.00 237,035.66 1,188,318.66 1,202,274.39 DDF 500,000.00 582,759.12 500,000.00 305,539.00 731,413.00 530,648.00 GOG 2,227,285.00 1,348,665.43 2,780,934.00 684,934.57 1,863,051 980,469.14 GRANT DONOR 780,000.00 286,534.8 1,385,000.00 509,147.43 148,625.29 185,984.53 GRANTS

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 8

TOTAL 6,577,969.00 3,301,163.12 8,396,021.00 3,727,938.96 7,104,047.09 5,050,531.75 REVENUE

DACF

The budgeted receipt of DACF for the period was GH¢ 3,172,639.14. However the amount received during the period under review was GH¢2,151,155.69 which is an increase over actual receipts of 2014 and 2015.

IGF

The IGF estimate for the period was GH¢1,188,318.66. However, GH¢1,202,274.39 was collected, this indicates an increase in the collection of IGF as compared to 2014 and 2015 where GH¢216,452.82 and GH¢237,035.66 was collected respectively.

Receipts/Disbursement of Funds for the year 2016 Table 1: Revenue

NO. REVENUE APPROVED APPROVED ACTUAL VARIANCE CUMULATIVE HEADS BUDGET BUDGET FOR THE FOR THE ACTUAL TO ESTIMATES ESTIMATES MONTH MONTH DATE FOR THE FOR THE (GH¢) (GH¢) (GH¢) YEAR (GH¢) MONTH (GH¢) 1. Rates 64,750.00 5,395.83 2,430.00 2,965.83 88,501.27 2. Lands 976,852.66 81,404.39 0.00 81,404.39 990,339.66 3. Fees 57,542.00 4,826.33 4,633.00 193.33 46,415.00 4. Fines 19,700.00 1,641.67 1000.00 641.67 14,347.00 5. Licenses 58,800.00 4,900.00 3,085.00 1,815.00 55,794.00 6. Rent 8,300.00 691.00 260.00 431.67 5,475.00 7. Grants 5,967,103.14 497,258.60 35,480.99 461,777.61 3,750,686.34 8. Investment - - 0.00 0.00 0.00 9. Miscellaneous 2,000.00 166.67 0.00 166.67 1,402.46

TOTAL 7,155,421.80 596,285.15 46,888.99 549,396.16 4,952,960.73

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 9

Table 2: Expenditure

APPROVED APPROVE NO EXPENDITUR BUDGET D BUDGET VARIANC CUMMULATIV . E HEAD ESTIMATE ESTIMATE ACTUAL E E FOR THE FOR THE FOR THE FOR THE ACTUAL TO YEAR MONTH MONTH MONTH DATE (GH¢) (GH¢) (GH¢) (GH¢) (GH¢) Compensation of 1,929,219.7 160,768.31 7,063.68 153,704.63 901,356.22 1 employees 1 Goods and 166,000.00 13,833.33 12,355.38 1,477.95 174,235.55 2 Services Consumption of 0.00 0.00 0.00 0.00 0.00 3 fixed capital 4 Interest 0.00 0.00 0.00 0.00 0.00 4,042,425.4 336,868.79 139,116.0 191,436.12 3,374,671.16 5 Grants 3 0 6 Social Benefits 1,000.00 83.33 0.00 83.33 0.00 1,016,776.6 84,731.39 25,012.00 59,719.39 1,115,903.41 7. Other Expenses 6 7,155,421.8 596,285.15 183,547.0 406,421.42 5,566,166.34 Total 0 6

2.3 Update on Indicators and Targets Annex A indicates progress made towards the achievement of the core indicators and targets under the MTDP. The statuses of core policy measures and indicators covering key thematic areas have been summarized below. Annex B is the project/programme register to reflect the implementation status as at 31st December, 2016.

2.4 Update on Critical Development and Poverty Issues School Feeding Programme

The programme continues to play a critical role in overall school enrolment and retention of pupils. At the time of reporting, the number of beneficiary Schools stood at15 with the number of pupils at 5,218. The total indebtedness of 110 day per caterer stood at 480,656.00 as at 31st December, 2016. The table below shows the details of enrolment at the beneficiary schools.

S/N Name of School Location No. of Boys No. of Girls Total 1. Techere Islamic Primary Terchere 82 56 138 2. Afrispa R/C Primary Afrisipa 217 218 435 3. Yamfo Methodist Primary A/B Yamfo 367 356 723 4. Yamfo R/C Primary ‘A’ Yamfo 212 223 435

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 10

5. Yamfo R/C Primary ‘B’ Yamfo 122 133 255 6. Yamfo Islamic Yamfo 202 203 405 7. Yamfo Anglican Primary Yamfo 232 206 438 8. Yamfo Presby Primary Yamfo 189 185 374

9. Nsuapem D/A Primary Nsuapemkrom 121 127 248 10. Dwenase D/A Primary Dwenase 192 161 353 11. Buokrukruwa R/C Primary Buokrukruwa 176 175 351 12. Krofofrom D/A Primary Krofofrom 120 84 204 13. Mankranho D/A Primary Mankranho 245 209 454 14. Sereso D/A Primary Sereso 77 66 143 15. Ponwaakrom D/A Primary Ponwaakrom 137 125 262 Grand Total 2691 2527 5218

Social Welfare

The Department of Social Welfare and Community Development carried out a number of programmes within the year. They include:

• Mass meeting - 4 organized • Study groups - 12 visits • Home science - 3 permanent groups • Child Right and Protection - 17 non-maintenance cases • Justice Administration - 5 on-going • LEAP - 98 households served • CHARH - adolescent sensitized

The District benefitted from the 45th cycle payments with 98 persons benefitting from the program. The purpose was to enable beneficiaries expand their petty trading businesses, set up trades and learn viable trade for economic support.

During the year, a total of 130 People with Disability received financial assistance to expand various livelihood activities that they are embarking upon to enable them have quality life. A total of Sixty- one Thousand Five Hundred Ghana Cedis (GH¢61,500.00) was disbursed. The amount ranges from GH¢ 300 - GH¢ 800 based on assessment of their applications received.

HIV/AIDs

During the year under review, a number of activities were carried out to help reduce the incidence of HIV/AIDs in the District. Some achievements chalked include;

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 11

• Four health Clubs in four Basic Schools were trained on HIV/AIDs to rigorously include HIV/AIDs awareness in their activities • Monitored HIV/AIDS testing for pregnant women at 3 health Centres (Bomaa Polyclinic, St John of God Hospitals and Yamfo Health Centre). The St John of God Hospital received most ANC patients • Organized Free HIV/AIDS Testing • Organized Regional AIDs Day

On HTC service for 2016, the number of people tested were 3120, 403 tested positive, 101 were screened for TB and 111 was referred into HIV care.

In relation to PMTCT, 2595 mothers were registered and 41 tested positive. PLWA on ART are 186. People who were at most risk of HIV and AIDS infections were provided with specific information to enable them access TC, treatment and other services

Malaria Control

Malaria Cases Management was organized to Health staffs. Participants were taken through protocols in managing malaria cases, drug of choice, use of Rapid Diagnostic Test, records management, signs and symptoms, severe and uncomplicated malaria.

Adolescent Reproductive Health

Activities carried out during the year include:

• Organized School based quizzes for 20 schools in the district • Planning meetings with 20 schools with Health Club • 14 School Health Club members visited the Adolescent Health Corner • Conducted ASRH outreach services to 5 deprived communities namely Atudurobesa, Rubi, Rubi-Beposo, Asukese and Dwenase • Identified 35 adolescents in six communities living with disability and linked them to ASRH services in corners, Clinics and outreach services • Organized weekly radio discussion to create awareness and provide information on adolescent Reproductive Health • Organize monthly monitoring of IPs activities • Organized quarterly District Co-ordinating Committee meetings • Organized mid-year and annual review meetings

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 12

Implementation of the M & E Plan

• Four quarterly monitoring visits undertaken • Six site meeting held • Four monitoring reports prepared • Four quarterly review meetings held • Two stakeholder meeting held • One annual Performance Review meeting held

Participatory M & E and other Studies

To ensure active participation of communities in the M & E process, the District introduced the participatory monitoring and evaluation into the implementation process. The Assembly constructed 2No. Zonal Council offices for Bomaa and Tanoso. All five town and zonal Councils were inaugurated during the year under review.

Key Issues Identified

• Lack of reliable data base for planning and budgeting • Inadequate support for M & E activities • Weak Public Private dialogue • Delay in release of Common Fund

Recommendations

• Establishment of database system for Tano North District Assembly

• Strengthening of substructures through capacity building and ceding of adequate resources to undertake approved development projects.

• Reactivation of the Public Private Dialogue group to promote active interface between MDAs and NGOs and other stakeholders

• Provision of reliable operation vehicle to DPCU to enhance monitoring activities.

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 13

ANNEX A: STATUS OF IMPLEMENTATION REPORT 2016

THEMATIC AREA: ENSURING AND SUSTAINING MACRO- ECONOMIC STABILITY

FOCUS AREA: FISCAL POLICY MANAGEMENT OBJECTIVES: 1. Improve fiscal revenue mobilization and management

2. Improve Expenditure management

NO. NAME OF PROJECT/ LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET GH¢ STATUS OF PROGRAMME (QTRS) IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Eliminate Revenue collection District wide % reduction in revenue 10,000.00 40,000 leakages collection leakages 2. Strengthen the Revenue Duayaw- Revenue Mobilization 5,000.00 150,000 100 mobilization unit of the Nkwanta Unit strengthened Completed Assembly for effective revenue through capacity collection and administration building and logistical support. 3. Strengthen the mobilization District wide IGF mobilization 20,000.00 100,000 and management of non- tax strengthened through revenue – IGF such as property proper database rate, market tolls, etc compilation and target setting.

4. Education in communities to Bomaa, Tanoso, Revenue base 500.00 100 Completed recruit commission collectors and broadened through the Terchere involvement of additional collectors

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 14

5. Update of rent ledge to collect D’Nkwanta, Rent ledge updated 500.00 100 Completed arrears Adrobaa, Subriso 6 Executive court actions on District Wide Court actions under 1,000.00 defaulters taken 7. Organize sensitization Distirct Wide Sensitization Workshop 500.00 1,500.00 100 Completed workshop on revenue organized for D/A mobilization of District members Assembly members, F.M Stations and information centers 8. Purchase of 1 No. Motor Bike Revenue 1 No. Motor Bike 3,000.00 100 Completed Department purchased

THEMATIC AREA: ENHANCING COMPETITIVENESS IN GHANA’S PRIVATE SECTOR FOCUS AREA: DEVELOP MICRO, SMALL AND MEDIUM ENTERPRISES IN THE TANO NORTH DISTRICT OBJECTIVE 1: IMPROVE EFFICIENCY AND COMPETITIVENESS OF MICRO, SMALL AND MEDIUM ENTREPRISES NO. NAME OF PROJECT/ PROGRAMME LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET STATUS OF (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Conduct Needs Assessment on SMEs in the District Needs Assessment Survey 5,000.00 100 Completed Tano North District and organize wide conducted; SME Needs Stakeholders Forums to prioritize / review identified and prioritized; Needs Interventions designed to address SME Needs. 2. Organize community based training in District No. of Training Activities 15,000.00 100 Completed soap-making, batik, tie & dye, baking and wide organized for SMEs, No. of confectionaries, beauty care, fashion SME entrepreneurs trained. designing, beekeeping, oil palm processing, cassava processing, etc for 300 SME Clients. 3. Promote the capacity building of District No. of entrepreneurs trained 100 Completed Entrepreneurs wide 10,000.00

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 15

4. Provide credit facilities to 300 District No. of entrepreneur 8,000.00 entrepreneurs Wide supported with credit facilities 5. Promote marketing of small and medium District No. of promotion 100 Completed scale product kente, pottery products Wide programmes , including Trade 5,000.00 Shows organized for medium and small scale products 6. Support for Rural Enterprise Programmes District No. of programmes 18,000.00 100 Completed Wide supported

OBJECTIVE 2: TO FACILITATE AND ENSURE THAT CO-OPERATIVE AND NON CO-OPERATIVE GROUPS OPERATE WITHIN CONDUCIVE AND ENABLING ENVIRONMENT THAT ALLOW THEM TO GROW INTO MEDIUM AND SMALL SCALE ENTERPRISE

NO. NAME OF PROJECT/ PROGRAMME LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET STATUS OF (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Organize and form cocoa farmers groups in 20 District Inadequate communities and district farmers union wide No. of groups formed 6000 10,000 date

2. Organize graduate youth in the district into District 8,000 10,000 groups for business orientation and job wide No. of youth groups identification in order to create jobs for the formed unemployed graduate youth 3. Familiarization/monitoring visit to all District No. Of groups visited 3000 3000 100 Completed registered co-operative groups in the district. wide 4. Training of co-operative group leaders in group District No. of leaders trained 4000 10,000 dynamic skills and preparation of business plan wide No. of group Action Plans prepared. 5. Organize women in the district into groups and District No. of women groups 4000 10,000 introduce them to the Rural and Agricultural wide organized and linked to Finance Project (RAFIP) to enable them have RAFIP Project for access to credit facility financial assistance.

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 16

6. Audit of registered and non- registered co- District No. Of co-operative 4000 10,000 100 Completed operatives societies and preparation of wide societies audited financial report for approval

THEMATIC AREA: ACCELERATED AGRICULTURAL MODERNZATION AND SUSTAINABLE NATURAL RESOURCE FOCUS AREA: ACCELARATED MODERNIZATION OF AGRICULTURE OBJECTIVE: Improve Agricultural Productivity NO. NAME OF PROJECT/ PROGRAMME LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET STATUS OF (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Build Capacity of Farmer – based District No. of FBOs and CBOs that 3,000.00 100 Completed organizations and Community Based wide receive capacity building Organizations (CBO’s) to facilitate training in extension services delivery of extension services to their No. of trained FBOs and CBOs members that are able to apply and impart extension skills to other farmers in their communities 2. Promote private investment in District No. of prevailed people 6,000.00 100 Completed aquaculture/ fish farming wide cultivated fish farming 3. Train poultry farmers to keep healthy District No. of health birds produced 5,000.00 100 Completed birds Wide 4. Introduce soil water conservation Duayaw No. of farmers acquire the 7,000.00 100 Completed techniques to 100 farmers in 20 Nkwanta knowledge for water farming communities conservation techniques 5. Procurement and Supply of Farm District No. of farms inputs procured 50,000.00 100 Completed Inputs to support farmers wide and supply

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 17

THEMATIC AREA: OIL AND GAS DEVELOPMENT

FOCUS AREA: ENSURE ACCESS OF HOUSEHOLDS AND RURAL INDUSTRIES TO EFFICIENT, RELIABLE ADQUATE ENERGY SUPPLY OBJECTIVE: TO IMPROVE OF ELECTRICAL COVERAGE IN THE DISTRICT NO. NAME OF PROJECT/ LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET STATUS OF PROGRAMME (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Extension of electricity- poles and District Wide No. of poles purchased 30,000.00 100 Completed bulbs 2. Extension of electricity Nwankanso No. of communities 110,000.00 100 Completed (Yamfo) and having access to Adrobaa electricity 3. Procurement of 120mm District wide No. of Aluminum cables 50,000.00 100 Completed aluminum cables, wooden and procured hand pump

THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTLEMENT DEVELOPMENT

FOCUS AREA: HUMAN SETTLEMENT DEVELOPMENT/SPATIAL DEVELOPMENT OBJECTIVE: PROMOTE RESILIENT URBAN INFRASTRUCTURE NO. NAME OF PROJECT/ LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET GH¢ STATUS OF PROGRAMME (QTRS) IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Completion of 4 sector 2 planning District No. of planning schemes 14,500.00 On-going schemes Wide completed 2. Development control District 3,200.00 100 Completed management and education Wide 3. Street Naming and property Yamfo No. houses numbered Not addressing and maintenance and streets named implemented works on old 4. Compensation of land owners and District No. of land owners 10,000.00 40,000.00 Not documentations wide compensated and implemented documented

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 18

THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTLEMENT DEVELOPMENT FOCUS AREA: WATER, ENVIROMNENT, SANITATION AND HYGEINE OBJECTIVE: ACCELERATE THE PROVISION AND IMPROVEMENT OF ENVIRONMENTAL SANITATION NO. NAME OF PROJECT/ LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET GH¢ STATUS OF PROGRAMME (QTRS) IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Construction of urinal (20%) IGF Duayaw Urinal and WC 25,000.00 100 completed Nkwanta completed and in use Station 2. Construction of 2No. 10 seater Terchire Aqua privy constructed 153,000.00 100 Completed aqua privy and in use 3. Evacuation of refuse District wide Refuse dump 50,000.00 100 Completed evacuated 4. Support activities of Community District wide No. of CWS activities 35,000.00 100 Completed Water and Sanitation supported 5. Mechanization of borehole Aboum Borehole mechanized 5,000.00 100 Completed 6. Construction of 10- seater aqua Subonpang Aqua privy constructed 80,000.00 100 Completed privy and in use 7. Construction of 10- seater aqua Bomaa Aqua privy constructed 80,000.00 100 Completed privy and in use 8. Construction of 10- seater aqua Afrisipakrom Aqua privy constructed 80,000.00 100 Completed privy and in use 9. Mechanization of 2No. Boreholes Subonpang Boreholes mechanized 45,000.00 80 1No. Ahyiayem completed 10. Drilling of 3No. boreholes Bomaa Boreholes drilling and 60,000.00 100 Completed Abrosanase fitted with hand pump Asukese 11. Capacity building programme for District wide 4,000.00 100 Not environmental and sanitation implemented staff

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 19

THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTLEMENT DEVELOPMENT FOCUS AREA: TRANSPORT INFRASTRUCTURE: ROAD, RAIL WATER AND AIR TRANSPORT OBJECTIVE: CREATE AND SUSTAIN AN EFFICIENT TRANSPORT SYSTEM THAT MEETS USER NEEDS NO. NAME OF PROJECT/ PROGRAMME LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET STATUS OF (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Gravelling of 400m access road to Duayaw Gravelling of access road 10,000.00 100 Completed administration block Nkwanta completed 2. Reshaping of town roads Duayaw Town roads maintained 45,000.00 100 Completed Nkwanta 3. Maintenance of feeder roads District wide Feeder roads maintained 40,100.00 100 Completed 4. Construction of 3No. round culvert Kwasuagya Culvert and access road 17,600.00 100 Completed and access roads constructed 5. Reshaping of town roads Susanho Town roads reshaped 49,500.00 100 completed

THEMATIC AREA: HUMAN DEVELOPMENT, PRODUCTIVITY AND EMPLOYMENT FOCUS AREA: EDUCATION OBJECTIVE: INCREASE EQUITABLE ACCESS TO AND PARTICIPATION IN EDUCATION AT ALL LEVELS NO. NAME OF PROJECT/ PROGRAMME LOCATION OUTPUT TIME FRAME ANNUAL BUDGET STATUS OF INDICATORS (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1 Construction of 1No.3- unit classroom with Kwasuagya Classroom block 170,000.00 100 Completed Office, KVIP and furniture constructed 2. Construction of 1No. 3 unit classroom block Tanokrom Classroom block 170,000.00 60 On-going with Office, store, 2 seater KVIP with urinal constructed and supply of 90 dual desk, 6No. teaches tables and chairs 3. Construction of 1No. 3 unit classroom block Duayaw Classroom block 170,000.00 75 On-going with Office, store, 2 seater KVIP with urinal Nkwanta constructed and supply of 90 dual desk, 6No. teaches tables and chairs at African Faith Primary School

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 21

4. Construction of 1No. 3 unit classroom block Yamfo Classroom block 130,000.00 55% On-going with furniture for Presby JHS constructed 5. Construction of 1No. 3 unit classroom block Asukese Classroom block 101,000.00 100 Completed constructed 6. Construction of 1No. 3 unit classroom block Twewaaho Classroom block 160,000.00 65% On-going with furniture constructed 7. Construction of 1No. 3 unit classroom block Yamfo Classroom block 160,000.00 55% On-going with furniture Methodist ‘A’ constructed Primary school 8. Construction of Pre-school Bomaa Classroom block 30,000.00 Methodist constructed 9. Cladding of pavilion Rubi-Beposo Pavillion 16,000.00 45 Abandoned Constructed 10. Construction of 1No. 3 unit classroom block at Bomaa Classroom block 120,000.00 SDA JHS constructed 11 Completion of 1No. 6 unit classroom at Islamic Duayaw- Classroom block 75,000.00 100 Completed Primary Nkwanta completed 12. Payment for Dual Desk supplied to schools District wide No. of dual desk 9,000.00 100 Completed supplied 13. Support to STME activities District wide Maths and science 5,000.00 100 Completed promoted 14. Procurement and supply of 1000 dual desk District wide No. of dual desk 100,000.00 100 Completed procured and distributed 15. Rehabilitation of 6Unit classroom block at Duayaw Classroom Block 50,000.00 25 Mobilization Boakye Tromo Nkwanta rehabilitated to site

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 22

THEMATIC AREA: HUMAN DEVELOPMENT, PRODUCTIVITY AND EMPLOYMENT

FOCUS AREA: HEALTH OBJECTIVE: BRIDGE THE EQUITY GAPS IN ACCESS TO HEALTH CARE AND NUTRITION SERVICES AND ENSURE SUSTAINABLE FINANCING ARRANGMENTS NO. NAME OF PROJECT/ LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET STATUS OF PROGRAMME (QTRS) GH¢ IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Construction of 2No. CHPs Sukuum CHPs Compound 280,000.00 100 Completed Compound Tanoano constructed 2. Construction of 2unit lecture Yamfo Lecture hall constructed 150,000.00 100 Completed hall at College of Health 3. Construction of 2 unit Lecture Yamfo Lecture hall constructed 100,000.00 100 completed Hall at College of Health 4. Completion of District Health Duayaw – Health centre completed 340,000.00 75% On-going centre with OPD Nkwanta 5. Construction of 2 Bedroom Duayaw Nurses quarters 120,000.00 100 Completed Nurses quarters Nkwanta constructed

6. Malaria prevention District wide No. of malaria prevention 10,000.00 100 Completed programmes programmes supported 7. Support HIV/ AIDS activities District wide No. HIV/AIDs activities 10,000.00 100 Completed supported 8. Support NID activities District wide No. NID activities supported 10,000.00 100 Completed 9. Support youth adolescent District wide Youth adolescent 200,000.00 100 Completed reproductive program reproductive program supported

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 23

THEMATIC AREA: TRANSPARENT AND ACCOUNTABLE GOVERNANCE

FOCUS AREA: LOCAL GOVERNANCE AND DECENTRALIZATION OBJECTIVE: ENSURE EFFECTIVE IMPLEMENTATION OF THE LOCAL GOVERNMENT SERVICE NO. NAME OF PROJECT/ LOCATION OUTPUT INDICATORS TIME FRAME ANNUAL BUDGET GH¢ STATUS OF PROGRAMME (QTRS) IMPLEMENTATION 1 2 3 4 IGF GOG/OTHERS % OF REMARKS WORK 1. Completion and furnishing of Duayaw - Assembly’ Guest House 164,000.00 70 On-going Assembly Guest House Nkwanta completed 2. Furnishing of Assembly Hall Duayaw Assembly hall furnished 20,000.00 100 Completed Nkwanta 3. Materials for the rehabilitation District wide Existing markets 30,000.00 100 Completed of existing markets rehabilitated 4. Supply of building materials to Duayaw- No. of communities 50,000.00 100 Completed support Community Initiated Nkwanta supported projects Dumakwae 6. Purchase of fuel and lubricants Duayaw - No. of field monitoring 6,000.00 10,000.00 100 Completed for monitoring Nkwanta conducted 7. Purchase of stationary and Duayaw- Stationary and other 8,000.00 12,000.00 100 Completed other logistics Nkwanta logistics purchased 8. Maintenance of official vehicles Duayaw- Official vehicles 8,000.00 12,000.00 and insurance Nkwanta maintained and insured 9. Staff capacity building and Duayaw- No. of staff acquired 10,000.00 61,413.00 100 Completed development Nkwanta new skills and knowledge 10. Support to DPCU activities Duayaw- No. of activities carried 4,000.00 6,000.00 100 Completed Nkwanta out 11. Provision towards National Duayaw National days observed 3,000.00 67,000.00 100 Completed Celebrations (independence Nkwanta day, May day, Famers day etc

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 24

12. Purchase of 2No. Pick up Duayaw – Effective and efficient 210,000.00 100 Completed Nkwanta administrative functions achieved 13. Ex-gratia for assembly Duayaw All assembly members 36,000.00 36,000.00 100 Completed members Nkwanta received end of service benefits 14. Payment of utility bills Duayaw- Effective and efficient 10,000.00 12,000.00 100 Completed Nkwanta administrative functions achieved 15. Sitting allowance for Duayaw- No. of meetings held 5,000.00 25,000.00 100 Completed assemblymen and sub- Nkwanta and allowances paid committee 16. Purchase of photocopier and Duayaw – Effective and efficient 2,000.00 5,000.00 Completed printers for official use Nkwanta administrative functions achieved 17. Goods and services for Duayaw- Effective and efficient 42,000.00 100 Completed decentralized department Nkwanta administrative functions achieved 18. Maintenance of buildings, Duayaw- Assembly buildings and 5,000.00 30,000.00 100 Completed equipment and fittings Nkwanta equipment maintained 19. Staff transfer grant/ haulage Duayaw – 4,000.00 8,000.00 100 Completed Nkwanta 20. Unplanned activities and Duayaw – 8,000.00 25,000.00 program Nkwanta 21. Support activities of social Duayaw - No. of activities carried 2,000.00 25,000.00 100 Completed welfare & Community Nkwanta out development 22. Hon. MPs Development District wide 250,000.00 100 Completed intervention 23. Maintenance of peace and District wide 60,000.00 100 Completed security 24. Other administrative recurrent 118,248.00 100 Completed expenditure

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 25

TANO NORTH DISTRICT ASSEMBLY

ANNEX B: PROJECTS AND PROGRAMMES REGISTER AS AT 31ST DECEMBER, 2016

N0 PROJECT TITLE LOCATION SECTOR/AR CONTRACTO CONTRACT SOURCE DATE OF EXPECTED PAYMENT BALANCE STATUS EA OF R SUM (GH₵ OF AWARD DATE OF TO DATE OUTSTANDIN INTERVENT FUNDIN COMPLETIO G ION G N 1. Construction of 1 No. Dumakwai Education Works 67,981.91 DACF 26/8/2010 26/11/2010 20,981.91 47,000.01 90% 3-unit classroom completed block (dwarf wall with tree planting and landscaping primary 2. Construction of Area Bomaa Administra Messrs Sages 90,848.12 DACF 12/12/201 12/6/2012 54,990.11 35,858.01 75% Council office block tion Consults GH. 1 completed with landscaping of Ltd compound 3. Construction of D/A Duayaw Housing Messrs 149,697.22 DACF 23/12/200 32/08/2010 86,527.00 63,170.22 80% Guest House Nkwanta Emmanuel 9 completed Otto Ent. Sunyani 4. Construction of Duayaw Health Messrs 338,140.06 DDF/ 3/12/2012 10/12/2012 195,000.00 143,140.00 75% District health Centre Nkwanta Jimtex DACF with OPD 5. Completion of 1 No. Duayaw Education Messrs 45,676.95 DDF 12/16/201 3/16/2014 50,244.64 (4,567.69) 100% 3-unit classroom Nkwanta JimtexEnt. 3 completed block at Anglican Ltd Primary School

6. Construction of Susuahu Education Works 50,000.00 CBRDP/ 22/08/201 22/11/2011 50,000.00 - 100% library TNDA 1 completed

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 26

7. Construction of 1 N0. Duayaw Health Joekona 171,299.12 DACF 15/12/201 April,2015 162,673.59 8,625.53 100% 2-unit lecture hall Nkwanta company Ltd. 4 completed with office and store Physiothra py school 8. Construction of 1 No. Yamfo Education Babaco 155,802.36 DACF 15/12/201 April,2015 100,498.69 55,303.67 65% 3-unit classroom Methodist Ventures 4 completed block with office, JHS store and supply of furniture 9. Construction of 1 No. Twewaaho Education Authentic 152,085.23 DACF 15/12/201 April,2015 55,000.00 97,085.23 65 % 3-unit classroom construction 4 completed block with office, hardware store and supply of enterprise furniture 10. Construction of 1 No. Asukese Education Jimtex 102,852.64 DACF 15/12/14 April,2015 102,852.64 - 100% 3-unit classroom Enterprise completed block with office and store 11. Completion of 1No. Yamfo Education Therser 115,921.82 DACF 15/12/14 April,2015 76,685.01 39,236.81 55% 5-Unit Classroom Enterprise completed block at Presby JHS

12. Gravelling of 400m Duayaw Transport Profag 58,654.00 DACF 13/12/14 March,2015 55,721.3 2,933.00 100% access road to Tano Nkwanta Company Completed North District Adrobaa Ltd. Assembly administration block and construction of culvert 13. Construction of CHPS Tanoano Health Oyina 153,082.65 DACF 15/12/14 April,2015 117,908.30 35,174.35 100% Compound Brothers Ltd completed

14. Construction of CHPS Sukuum Health Prikubis Ent. 151,414.31 DACF 15/12/14 April,2015 99,801.00 51,613.31 100% Compound completed

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 27

15. Mechanization of Duayaw- Water and Sages 40,226.55 DACF 15/12/14 March,2015 10,000.00 30,226.55 100% borehole at residency Nkwanta Sanitation Consult. completed Ghana Ltd 16. Supply of 200 No. Yamfo - Education E.Y EffahEnt. DACF 100% Mono Desk Asuadie completed

17. Construction of 1 Yamfo - Cross Above all 14,000.00 Above 19th 21st 14,000.00 - 100% borehole at Asuadie country foundation all Oct. Oct. completed water foundati 2015 2015 services on 18. Construction of 1 No. Bomaa - Cross Above all 14,000.00 Above 16th 18th 14,000.00 - 100% borehole at Appiahkro country foundation all Oct. Oct. completed m water foundati 2015 2015 services on 19. Construction of 1 No. Oforikrom Franklisa AFD/CWSA 100% 8 seater institutional Completed latrine 20. Construction of 3- Kwasuagya Education Rexhenduf 165,511.56 DDF Feb, 2016 July, 2016 152,348.00 13,162.76 100% Unit Block with Enterprise completed Office, KVIP and furniture 21. Construction of 1No. Techire Sanitation Babaco 75,020.40 DDF Feb, 2016 July, 2016 71,268.05 3,752.35 100% 10 Ventures completed Aqua Privy Toilet 22. Construction of 2 Duayaw Health Babaco 87,074.40 DDF Feb, 2016 July, 2016 82,712.9 4,361.5 100% Bedroom Nurses Nkwanta Ventures completed Quarters 23. Construction of 2 Yamfo Health Midland 157,008.60 DDF Feb. 2016 July, 2016 148,895.40 8,112.60 100% Unit Lecture Hall with Habitat completed Office, Store Consult 24. Reshaping and Nkrankrom Roads Rexhenduf 52,900.00 DDF Feb July, 2016 52,900.00 - 100% maintenance of - Abodiem Enterprise 2016 completed Nkrankrom Junction to Abodiem

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 28

25. Construction of Susanso Admi. Afoma 49,478.00 MPs 10th April 26,097.92 23,381.00 100% durbar rounds Electrical Co. Commo Feb. 2016 Completed ltd n Fund 2016 27. Rehabilitation works Duayaw Admi. Dedsah Co. 49,874.00 DACF 10th January 100% at old assembly Nkwanta Ltd Dec. 2016 2015 29. Construction of 2 Bomaa Education Jimtex ltd GETfund 60% storey 18 unit classroom for secondary school 30. Construction of 1No. Duayaw Health GETfund 65% accommodation Nkwanta block for physiotherpy school 31. Completion of 1No. 6 Duayaw Education Willsix Ent 65,847.47 DACF 10th May 50,000.00 15,847.47 100% unit classroom block Nkwanta Feb. 2016 completed with office and store 2016 at Islamic 32. Construction of 1No. Bomaa Sanitation Smart 76,165.95 Stool 22nd August 2016 71,170.53 4,145.82 100% 10 seater aqua privy General lands March completed Const. 2016 33. Construction of 1No. Afrisipa Sanitation O. J. 70,441.35 Stool 22nd August 2016 78,401.59 4,397.36 100% 10 seater aqua privy Inspirational lands March completed Consult 2016 34. Construction of 2 Yamfo Health Midland 170,073.75 Stool 22nd September 161,478.15 8,595.60 100% Unit Lecture Hall with Habitat lands March 2016 completed Office, Store IGF 2016 35. Extension of street Yamfo Health Washdan Co. 34,180.00 4th March 32,471.00 1,709.00 100% light to College of Ltd Jan. 2016 completed Health 2016 36. Cladding of 3 –Unit Nsuapemkr Education Fresh Cedi 50,762.34 DACF Nov. 2011 June 2012 30,000.00 20,762.00 50% Classroom pavilion om completed

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 29

37. Construction of 1 No. Duayaw Education M/S R- 170,442.30 DACF May 2016 Nov. 2016 55,566.35 114,875.95 75% 3-unit classroom Nkwanta Kostab Co. completed block with office, African Ltd store, 2 seater KVIP Faith with urinal and Primary supply of 90No. Dual School desk, 6 No. Teachers table and chairs

38. Construction of 1 No. Tanokrom Education M/S 174,814.00 DACF May Nov. 2016 56,222.10 118,592.00 60% 3-unit classroom Multiwave 2016 block with office, Const. works store , 2 seater KVIP with urinal and supply of 90No. Dual desk, 6 No. Teachers table and chairs 39. Construction of 1 No. Yamfo Education Fresh Cedi 89,820.98 DACF Dec. June 2015 90% 3-unit classroom 2014 completed block with office and store, 4 seater KVIP and 2 chamber urinal at R/C Primary 40. Procurement and District Education O.J 100,000.00 STL April 2016 July 2016 100,000.00 - 100% supply of 1000 dual wide Inspirational completed desk to basic schools Co. Ltd 41. Mechanization of Subonpang Water M/S O. J 44,479.05 DACF May 2016 Aug. 2016 26,671.86 17,807.19 80% 2No. Boreholes & Inspirational completed Ahyiayem Co. Ltd 42. Construction of 1No. Techire Sanitation Yaskad 76,500.00 STL April 2016 Oct. 2016 72,674.64 3,825.36 100% 10 completed Aqua Privy Toilet 43. Construction of 1No. Subonpang Sanitation M/S Princia 76,005.30 DACF May 2016 Nov. 2016 30,400.00 45,605.30 100% 10Aqua Privy Toilet Ventures completed

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 30

44. Procurement and District Admi. J. A. B. Great 42,290.00 STL May 2016 June 2016 30,000.00 12,290.00 100% supply of building wide is Jehovah completed materials to support community initiated projects 45. Reshaping of Susuanho Roads Baahbentu 49,300.00 STL April 2016 July 2016 49,300.00 - 100% Susuanso Town roads Co. Ltd completed 46. Extension of Yamfo Electricity M/S E K 108,090.00 STL April 2016 July 2016 102,685.50 5,405.00 100% electricity (Nwankwa Senkyire Ltd completed nso ) and Adrobaa 47. Drilling of 2No. Bomaa Water M/S Barfran 39,000.00 STL 19/04/16 July 2016 37,050.00 1,950.00 100% Borehole Abrosanase completed

48. Drilling and Yamfo Health Joekona Co. 80,757.02 DACF 17/08/16 17/12/16 - 80,757.02 100% mechanization of College of Ltd completed 1No. Borehole with Health construction of 9m high level reinforced stand 49. Procurement and Duayaw Admi Japan Motors 192,649.96 DACF 02/08/16 3/09/16 192,649.96 - 100% Supply of 2No. Pick- Nkwanta Trading Co. STL ups Ltd 50. Reshaping of Feeder Nkwantabi Roads M/S MYK 56,200.00 DACF 17/08/16 17/09/16 18,733.03 37,466.70 100% roads sa, Onwe, Ent. Nkurakan, Mamponte ng, Dumakwae 51. Rehabilitation of 6- Duayaw Education Willsix Ent. 50,711.85 DACF 9/09/16 9/12/16 - 50,711.85 25% Unit classroom block Nkwanta at Boakye Tromo Snr High

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 31

52. Construction of 3No. Kwasuagya Road Dedsah Co. 17,550.00 DDF Nov. 2016 Dec. 2016 16,672.5 877.5 100% round culvert Ltd completed

53. Mechanization of Asukese Water O. J 20,010.00 DDF Oct. 2016 Dec. 2016 19,009.50 1,001.00 100% borehole Inspirational completed

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 32

TANO NORTH DISTRICT ASSEMBLY 2016 ANNUAL PROGRESS REPORT Page 33