Social Monitoring Report

Project Number: 33442 (Loan 1850) September 2007

People’s Republic of : - Railway Project

Prepared by the The Research Institute of Foreign Capital Introduction and Utilization,

Southwest Jiaotong University {Firm name}

{City, country}

For {Executing agency} {Implementing agency}

This report has been submitted to ADB and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.

ADB Loan Ganzhou-Longyan Railway Project

Post Evaluation Report on Resettlement

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University

(RIFCIU-SWJTU)

September 9, 2007 Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Contents

1. Preface ...... 5 2. A Summary of Resettlement Evaluation Reports ...... 6 2.1 The External Monitoring Report on the First Phase Resettlement.... 6 2.2 Phase Two External Resettlement Monitoring Report ...... 8 2.3 Report on the Completion of Resettlement ...... 9 3. The Impact of Ganzhou-Longyan Railway Construction Project.....11

3.1 Scope of Influence of Land Acquisition, Demolition and Relocation Associated with the Project...... 11

3.2 Analysis of Data Differences between Resettlement Plan and the Implemented Land Acquisition, Building Demolition and Relocation ...... 15 4. The Progress of Resettlement ...... 16 4.1 The Whole Process of Land Acquisition and Resettlement ...... 16

4.2 Evaluation of the Match between the Progress of Resettlement and the Schedule of Project Construction ...... 17 5. Resettlement Policy ...... 21 5.1 The Resettlement Policy and Compensation Standards Actually implemented...... 21 5.2 Comparison between the Actual Resettlement Compensation Standards and Those Stated in the Resettlement Plan ...... 22 5.3 Evaluation of the Applicability of the Resettlement Policy ...... 33 6. Income and Livelihood ...... 34

6.1 The Measures Adopted to Recover the Income and Livelihood of the Affected People ...... 34 6.2 Comparative Analysis of Income Recovery...... 37 7. The Relocation and Reconstruction of Buildings ...... 63 7.1. The Purchasing Right of the Rebuilt Houses, Enterprises, Schools and Other Buildings; ...... 63 7.2. Measures Helping the Relocatees Move to Their Resettlement Quarters and Rebuild Their New Homes ...... 63 8. Rebuilding of Infrastructure ...... 65

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 2 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

8.1. Recovery of Transportation Facilities ...... 65 8.2. Recovery of the Water System ...... 65 8.3. Recovery of Power, Communication, Telephone, Television and Other Facilities...... 66 8.4. The Remaining Problems and Pending Work ...... 66 9. Resettlement Budgeting and Financing ...... 66 9.1. Cost of Resettlement and Cash Flow ...... 66 9.2. Sources of All the Funds for Land Acquisition and Resettlement and the Releasing Time of the Fund Statement ...... 67 10. Participation of the Affected People and Release of Related Information...... 74 10.1. Release of Project Information...... 74 10.2. Ways of Participation of the Affected People...... 74 10.3. Evaluation of Consultation ...... 76 11. Organization and Management...... 76 11.1. Main Tasks and Responsibilities of the Organizations ...... 76 11.2. Capability of Staff Members of Resettlement Departments...... 78 12. Monitoring and Evaluation ...... 78 12.1. Internal Monitoring ...... 78 12.2. External monitoring ...... 79 13. Experience, Lessons, Remaining Problems and Suggestions ...... 79 13.1. Experience of Resettlement ...... 79 13.2. Remaining Problems and Work to Be Done ...... 80 14. Annexes ...... 81 14.1. Sites of Resettlement for People Affected by Demolition and Relocation ...... 81 14.2. Relevant Documents on the Resettlement Policies for the Project81

14.3 The Results of Household Sample Survey Conducted During the Post-Resettlement Evaluation Investigation ...... 96

14.4 A Copy of the Agreement on Land Acquisition and Resettlement Signed between the Ministry of Railways, Province and Province...... 119 14.5 The Photocopy of a Sample Page of the Resettlement Agreement between the Implementation Agency and the Affected Household

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 3 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

123 14.6 Photos Reflecting the Work of Resettlement...... 127 14.7 The Interpretation of the Compensation Standards for Land Acquisition, Demolition and Relocation Given by the Resettlement Departments of Some of the Counties (Districts) along the Railway Line...... 135

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 4 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

1. Preface

Ganzhou-Longyan Railway Project (hereinafter referred to as “The Project”), a ADB loan project (loan number: 1850-PRC ), starts from the East Ganzhou Station of -Kowloon Railway, and meets Zhanglong Railway at Longyan Station after passing through Ganzhou City in Jiangxi Province and Longyan City in Fujian Province.The newly built railway is 290.1 kilometers in length (132.3 kilometers in Jiangxi Province and 157.8 kilometers in Fujian Province). The construction was started on December 8, 2001, and the railway was open to cargo transportation on April 1, 2005, and to passenger service on October 11, 2005. Its formal operation was initiated in January 2006, and its domestic inspection and acceptance are planned to be conducted in the second half of the year 2007.

The resettlement work for Ganzhou-Longyan railway project began in November 2001, and most of it was finished by the end of 2003. From September 19 to September 22, an inspection group from ADB conducted a field inspection along the Ganzhou-Longyan Railway line checking various aspects including resettlement work, and asked the external monitoring agency to submit a “post-resettlement evaluation report” and an “impact on poverty evaluation report” in accordance with the requirements stipulated by the loan agreement of the Project.

During the period from July 2 to 16, 2007 the post-resettlement evaluation group from the Research Institute of Foreign Capital Introduction and Utilization (the external monitoring agency for the resettlement work of the Project) of Southwest Jiaotong University carried out its evaluation mission along the Ganzhou-Longyan railway line. The field evaluation plan was worked out by the post-evaluation group in conformity with the requirements set in the ADB memorandum. Supported by the owners of projects and the local governments, the evaluation group captured a holistic view of the total situation of construction, land acquisition, demolition, relocation and resettlement, the compensation standards for land acquisition, demolition and relocation, the allocation of funds, and the implementation of the resettlement plan by interviewing the affected people, holding meetings and through field observation. The evaluation group has given an objective and fair evaluation on the basis of extensively seeking of the comments and suggestions from the relocated people, careful verification of the relocated people’s recovery of production and living conditions against the Resettlement Action Plan. In the whole process of field evaluation investigation, the field evaluation group paid special attention to the recovery of the productive and living conditions of the respondents interviewed during the stage of baseline survey.

In the whole process of post-resettlement evaluation, including the preparation phase, The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 5 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project field survey phase and report compilation phase, Railway Administration, the Key Projects Office of Ganzhou City of Jiangxi Province, the Railway Construction Supporting Office of Longyan City of Fujian Province and all the local governments along the Ganzhou-Longyan Railway line lended constant support to the post-resettlement evaluation group. We hereby extend our sincere thanks to them all.

2. A Summary of Resettlement Evaluation Reports

In accordance with the established requirements of the Project, in April 2002, the external monitoring agency submitted to the owner of the Project and Asian Development Bank “The Baseline Survey Report of 350 Sample Households for Ganzhou-Longyan Railway Project”. In April 2003 the evaluation group submitted “The External Resettlement Monitoring Report Phase One for Ganzhou-Longyan Railway Project”. In May 2004 the evaluation group submitted “The External Resettlement Monitoring Report Phase Two for Ganzhou-Longyan Railway Project”. And in May 2005 “The Report on the Completion of Resettlement for Ganzhou-Longyan Railway Project” was submitted. It is by means of those reports that the external monitoring agency reported to the project owner and Asian Development Bank the process of resettlement and the recovery of the productive and living conditions of the people affected by Ganzhou-Longyan Railway Project.

2.1 The External Monitoring Report on the First Phase Resettlement

According to the plan of the project, the land acquisition, demolition and relocation for the railway construction involve 2 prefectures, 8 counties/districts and 29 towns in Jiangxi and Fujian. The 8 counties/districts are Ganxian County, , and Ruijin City in Ganzhou City, and , Liancheng County, Shanghang County and Xinluo District in Longyan City. The total scale of land acquisition, demolition, relocation and resettlement encompasses permanently acquired land of 15,254 mu, temporarily used land of 3,000 mu, demolition and relocation of buildings of 459,972m2, and 19,337 affected people.

The phase one external monitoring report reflects the state of resettlement work by the end of December 2002 when the large scale land acquisition, demolition, relocation, resettlement and compensation work began. By that time, the total area of land acquired was 13,710 mu, accounting for 89.88% of the planned figure; the land acquired for temporary use numbered 2,863 mu, accounting for 95.64% of the planned figure; The relocated households numbered 2,413 with 351,799m2 of buildings demolished, accounting for 63.64% of the plan. In Jiangxi the land permanently acquired was 6735.991 mu in area while the land acquired for temporary use was 1009.758 mu. The demolition amounted to 218,717.34m2 involving 1530 households. In Fujian the land permanently acquired was 6,974.04 mu in area while

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 6 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project the land acquired for temporary use was 1,853.058 mu. The demolition amounted to 133081.7 m2 involving 883 households.

By the time when phase one external monitoring was being conducted, to accomplish the tasks of land acquisition, demolition, relocation and resettlement, the Ganzhou municipal government of Jiangxi Province had established its railway construction supporting office, and Longyan City of Fujian Province also had established its railway construction headquarters. At the same time, the two cities had set up railway construction supporting offices in all the counties and townships along the railway line to undertake the land acquisition, demolition, relocation and resettlement work.

(1) The policy and standards for land acquisition, demolition, relocation, compensation and resettlement for the Project, which serve as the legal guidelines for compensation and resettlement, were formulated on the basis of the relevant policies and legal regulations of Chinese government.

(2) To ensure the openness and transparency of the resettlement policy, the resettlement departments at all levels informed the affected people of the resettlement policy and plan by various means, such as meetings of all levels, newspapers, television, and the resettlement brochure.

(3)The resettlement departments at all levels, by formulating sound rules and regulations, ensured that the compensation for land acquisition was allocated according to the publicized standards to the affected villages, which would then determine the distribution and uses of the compensation for land acquisition. At the same time, those resettlement departments also ensured that the compensation for demolition and relocation was allocated in time and in batches to the affected households in form of bankbooks.

(4) Most of the villages redistributed the land among the villagers to enable the villagers whose land had been acquired to resume their original mode of living with their familiar mode of production. All the relocated households got their homesteads for new houses free of charge through either concentrated resettlement or scattered resettlement.

(5) Besides the affected rural residents, the relocated enterprises and schools along the railway line were also compensated and rebuilt.

(6) All local governments took appropriate care of the families encountering special difficulties, such as the families of old people, sick people and women as well as poor families. The special support for such difficult families was given in forms of special subsidy, labor support for the occasions of demolition and rebuilding, and other flexible assistance. Most of the villages gained income from taking part in excavation and transportation of earth, and from supplying building materials such as sand and gravel to the railway construction organizations. For more detailed information,

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 7 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project please refer to the PhaseI External Monitoring Report.

2.2 Phase Two External Resettlement Monitoring Report

Phase two external monitoring report reflects the resettlement work by the end of April 2004 when most of the work for land acquisition, demolition and relocation had been finished, and the construction of infrastructure in the late period of the project, such as the rebuilding of channels and roads, recovery of water supply aimed for the recovery of production and living facilities had been completed. Most the people affected by land acquisition had received their new cultivated land through land redistribution; most of the relocated households had been given free housing sites and had built their new houses except very few households that had some special requirements. For example, as the households relocated from the site for Yudu railway station insisted on being resettled around the square of Yudu station, they waited through a transitional period. Most of the relocated enterprises and schools had been rebuilt, and the enterprises had resumed their production. The land acquired for the construction of railway numbered 13,981.85 mu, accounting for 91.66% of the planned figure; the demolished houses added up to 458,739m2, accounting for 99.79% of the plan. In Jiangxi Province the land acquired amounted to 6894.85 mu (Paddy field and irrigated field added up to 3059.073 mu, accounting for 44.37%; dry field amounted to 305.4741 mu, accounting for 4.43%; orchards amounted to 820.36mu, accounting for 11.90%; other farming land amounted to 1695.894mu, accounting for 24.6%; land for residential quarters, factories and mines numbered 377.614, accounting for 5.48%; other non-cultivated land amounted to 636.449mu, accounting for 9.23%.) Land acquired for temporary use numbered 2,150mu; A total of 1,586 households were relocated, and the total area of demolished houses added up to 293739.405m2, of which 68875.341 m2 is contributed by brick-concrete houses, accounting for 23.45%; 28359.231 m2 is contributed by brick-tile houses, accounting for 9.65%; 158688.925m2 goes to earth-wood houses, accounting for 54.02%; 37815.908 m2 was contributed by simple houses, accounting for 12.87%. Besides, the demolished buildings of schools and enterprises amounted to 15823.9m2. The railway construction authority had paid a total compensation of 165.9 million yuan, of which 5.51588 million yuan had allocated for land acquisition compensation; 7.513928 million yuan for land for temporary use; 69.657116 million yuan for house demolition compensation; 1.42 million yuan for enterprise relocation; 32.162 million yuan for other demolition and relocation as well as compensation for standing crops and attachments. In Fujian Province 7,087mu of land was acquired for permanent use; the demolished houses amounted to 165000m2; land for earth fetching and dumping amounted to 1,421mu; the remaining fragmentary pieces of land outside the red line amounted to 133mu; The land for river-diversion and channel-diversion added up to 235mu; 464mu of irrigated field was turned into dry field; 340mu of standing crops were compensated. The total compensation for land acquisition, demolition and relocation amounted to 122.59million yuan, of which 56.7 million was allocated as compensation for land acquisition; 36.11 million yuan allocated as compensation for house demolition and relocation; 8.64million yuan allocated for the removal of structures; 8.64 million yuan for other agreed compensations; 7.95million yuan for earth fetching and dumping land; 1.06million yuan for compensation for the remaining fragmentary pieces of land outside the red line; 1.88 million yuan for diversion of rivers and channels; 1.42 million yuan for turning irrigated The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 8 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project field into dry field; 190 thousand yuan was allocated as compensation for standing crops.

2.3 Report on the Completion of Resettlement

The report on the completion of resettlement is the summary document on the external resettlement monitoring evaluation for Ganzhou-Longyan Railway Project, reflecting the holistic situation of the land acquisition, demolition, relocation and resettlement work before Ganzhou-Longyan Railway is put into operation.

By April 2005 the land acquisition for railway construction had involved 29 towns and townships, and 150 administrative villages. Within the boundary of 8 counties 14,336mu of land was acquired for permanent use; 3589mu of land was acquired for temporary use; the demolished houses amounted to 491,892m2; the affected farming households numbered 2,576, and the affected people totaled 18,300; altogether 14 schools were demolished and relocated and 22 enterprises were affected. To compensate for various impacts caused by land acquisition, building demolition and relocation, in all, the owner of the Project paid 311.58273 million yuan to the affected parties in forms of various compensations, of which 114.690637million yuan was allocated to compensate for land acquisition, 128.799295 million yuan was allocated to compensate for demolition and relocation of houses, and 68.092798 million yuan for infrastructure and the land for temporary use.

The work of land acquisition, demolition, relocation and resettlement can be divided into three phases. In phase one, namely 2001, some key construction projects and the related land acquisition, demolition, relocation and resettlement were initiated; in phase two (2002 to 2003) the construction of bridges, tunnels and subgrades was started in full scale and the land acquisition, demolition, relocation and resettlement reached their peak. In phase three (2003 to 2004), the resettlement work was completely finished. The realization of the phased targets ensured the completion of the construction of the whole railway line by the end of 2004 and the trial operation started on April 1, 2005.

The resettlement completion report summarized the working mode for the demolition, relocation, resettlement and compensation associated with the Project:

The Ministry of Railways, as the owner of the Project, provided funds for the land acquisition, demolition, relocation and resettlement and included such cost into the cost of construction, thus to ensure that the funds are in place prior to land acquisition, demolition and relocation. The representatives of the local governments at all levels along the railway line, the railway construction supporting offices and land administration bureaus undertook the specific responsibilities for land acquisition, demolition, relocation and resettlement to ensure that the land for railway construction was provided to the owner of the project in light of the schedule for civil engineering construction. All the people affected by land acquisition, demolition and relocation for The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 9 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project the construction of the project were resettled locally (in their own villages). Most of the people affected by land acquisition could regain their farming land through the redistribution of the farming land within their own villages. But for a small number of people who were affected by the large-scale land acquisition for the construction of railway stations, the right mode for their recovery of the means of production and life was the combination of redistribution of land and development of service industry. The development of service industry here means taking advantage of the development of the railway station to establish transportation teams, develop catering trade, open stores and set up agricultural markets in order to gain income outside farming and thus recover productive and living conditions. For the people affected by demolition and relocation, there were four modes of resettlement, namely, scattered resettlement, concentrated resettlement, the rarely adopted resettlement in the residential houses and the resettlement in business houses in towns. The gist of those modes of resettlement was to resettle the affected people locally, provide convenience of life, leave enough room for further development, and offer housing sites free of charge to the affected people.

Judged from the perspectives of information transparency and complaints, the compensation for land acquisition, demolition and relocation as well as the resettlement associated with the project were carried out in compliance with the principle of openness and transparency. Before land acquisition, demolition and relocation, all the affected people personally took park in the counting, verification and confirmation of their affected property jointly with the parties concerned. The resettlement department publicized twice the policy and plan for land acquisition, demolition and relocation as well as the scope of impact on the property of the affected people. First the compensation standards and resettlement policy was promulgated by various means such as loudspeaker vans, broadcast system, television, cinema, slogans on walls, bulletins and publicity brochures. Then the authority concerned publicized the quantity of the affected property of the affected persons and the amount of the compensation calculated against the compensation standards to allow the public to supervise the process. The affected people had unimpeded channels for appeals and complaints. The consultative principle was extensively adopted between the affected people and the resettlement departments at all levels for the solution of problems. The affected persons could voice their opinions and complaints about the work of land acquisition, demolition, relocation and resettlement through various channels such as resettlement departments at village, township, county and city levels, the railway construction organizations (all the railway construction administrations, project divisions, and the railway construction headquarters jointly formed by Nanchang Railway Administration and Railway Administration for this project.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 10 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

3. The Impact of Ganzhou-Longyan Railway Construction

Project

3.1 Scope of Influence of Land Acquisition, Demolition and Relocation

Associated with the Project

Table1 shows the comparison of the summarized actual scope of influence of land acquisition, demolition and relocation with the resettlement action plan of the project. In total 22,858.955 mu of land was acquired for the construction of Ganzhou-Longyan Railway, accounting for 155.64% of the plan. This number includes the area of the land for resettlement outside the red line, the land for the expansion of railway stations, the land for the access roads to stations, the land for roads outside the red line and the land for flyovers passing the railway line. As a result, the actual area of land acquired for the construction of Ganzhou-Longyan Railway was 55.64% more than the plan. The actual land acquired within the red line numbered 14,375.015mu (This figure was provided by the Headquarters of Ganzhou-Longyan Railway Construction), accounting for 94.23% of the area set in the Resettlement Action Plan. The total area of cultivated land acquired both inside and outside the red line amounted to 10872.0725mu, and the cultivated land acquired inside the red line numbered 7704.64mu, accounting for 166.23% of the RAP. On the whole, the land acquired within the railway line was a little less than the planned figure. But the cultivated land acquired for land-consuming railway stations and resettlement quarters was larger than the planned figure. The people affected by land acquisition numbered 12,280, accounting for 144.61% of the plan. The actual number of people affected by land acquisition in Ganxian County and Huichang County of Jiangxi Province exceeded by far the plan figures. Throughout the whole railway line only Ruijin City had less number of affected people than the planned figure.

The total area of demolition and relocation along the whole railway line numbered 521,901.514m2 (The figure was provided by the local governments along the railway line), accounting for 112.12% of the planned figure. The area of demolition and relocation inside the red line amounted to 495,973.5m2, accounting for 106.55% of the planned figure, with 2,684 households affected. The area of demolished and relocated farmers’ houses accounted for 96.92% of the total area of demolition and relocation, and the remaining percentage indicates the area of demolished and relocated factory buildings and buildings of other purposes. The people affected by demolition and relocation numbered 12,899 in total, accounting for only 75% of the planned figure. In Jiangxi Province the number of people affected by demolition and relocation was generally smaller than the figure planned in RAP, while in densely The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 11 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project populated areas such as Shanghang County, Xinluo District in Longyan City of Fujian Province, the numbers were higher than the figures planned in RAP.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 12 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Table 1 The Statistic Table Showing the Scope of Impact of Land Acquisition, Demolition and Relocation for Ganzhou-Longyan Railway Construction Project

Administrative Divisions Ganzhou City Longyan City Type of Unit Ganxian Yudu Huichang Ruijin Subtotal Changtin Liancheng Shanghan Xinluo Subtotal Total Impact Impact County County County City g County County g County District Actual 966.225 2981 1173.618 1950.672 7071.515 6208.36 5006.21 1437.2 3135.67 15787.44 22858.955 RAP 483 2580 1132 1918 6113 3580 2474 1022 1498 8574 14687 Total Area of Acquired Land mu Actual/Pla 209.32 200.05% 115.54% 103.68% 101.70% 115.68% 173.42% 202.35% 140.63% 184.13% 155.64% nned % Actual 3498.177 728.92 1029.513 456.947 1282.7975 2533.89 1945.445 873.99 2020.57 7373.895 10872.0725 5 Area of Acquired Cultivated land mu RAP 273 1273 495 1267 3308 1967 669 395 818 3849 7157 Actual/Pla 247.01 267.00% 80.87% 92.31% 101.25% 105.75% 128.82% 290.80% 221.26% 191.58% 151.91% nned % Actual 46491.98 283643.6 62333.3 238257.8 123282.371 65197.59 48671.7 122539.44 31079.63 22305.43 521901.514 3 44 7 7 Area of Demolished Buildings m2 RAP 28894 150020 59789 64882 303585 74285 20671 17189 49744 161889 465474 Actual/Pla 125.31 160.91% 82.18% 109.05% 75.02% 93.43% 164.96% 150.35% 129.77% 147.17% 112.12% nned % Actual 45584.98 274712.6 56324.9 231109.5 117898.411 63337.59 47891.7 121399.6 31079.63 22305.43 505822.274 3 8 3 9 Area of Demolished Farmers’ m2 RAP 28894 148960 59613 64882 302349 73618 18391 12502 43459 147970 450319 Houses Actual/Pla 129.60 157.77% 79.15% 106.25% 73.81% 90.86% 164.90% 168.99% 178.41% 156.19% 112.33% nned % Actual 907 5383.96 1860 780 8930.96 1139.84 0 0 6008.44 7148.28 16079.24 Area of Demolished Factory m2 RAP 0 1060 176 0 1236 667 2280 4687 6285 13919 15155 Buildings and Other Buildings Actual/Pla -- 507.92% 1056.82% -- 722.57% 170.89% 0.00% 0.00% 95.60% 51.36% 106.10%

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project nned Actual 1359 2889 1350 1611 7209 3179 457 296 1139 5071 12280 Population Affected by Land RAP 341 1819 569 1759 4488 2658 378 218 750 4004 8492 person Acquisition Actual/Pla 151.87 398.53% 158.82% 237.26% 91.59% 160.63% 119.60% 120.90% 135.78% 126.65% 144.61% nned % Actual 1248 2580 1703 1800 7331 1151 498 579 3340 5568 12899 Population Affected by Building RAP 1140 5876 2352 2559 11927 2653 663 451 1368 5135 17062 person Demolition Actual/Plann 244.15 109.47% 43.91% 72.41% 70.34% 61.47% 43.38% 75.11% 128.38% 108.43% 75.60% ed %

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

3.2 Analysis of Data Differences between Resettlement Plan and the

Implemented Land Acquisition, Building Demolition and Relocation

Ganxian County: The land actually acquired numbered 966.225mu, accounting for 200.05% of the plan, including 728.92mu of cultivated land, which accounted for 267% of the plan. The number of people affected by land acquisition numbered 1,359, accounting for 398.53% of the plan. The demolished buildings amounted to 46491.983m2 in area, accounting for 160.91% of the plan. The people affected by demolition and relocation numbered 1248, accounting for 109.47% of the plan. Specifically, the demolished farmers’ houses amounted to 45,584.983m2 in area, accounting for 155.77% of the plan. And the number of affected farmers is 1,248, accounting for 109.47% of the plan. Yudu County: The land actually acquired numbered 2,981mu, accounting for 115.54% of the plan, including 1,029.513mu of cultivated land, which accounted for 80.87% of the plan. The number of people affected by land acquisition numbered 2,889, accounting for 158.82% of the plan. The demolished buildings amounted to 123,282.371m2 in area, accounting for 82.18% of the plan. The people affected by building demolition numbered 520 households, totaling 2,580 people, accounting for 43.91% of the plan. Among the demolished buildings were 5,383.96m2 of non-farmer’s buildings, accounting for 509.72% of the plan. Huichang County: The land actually acquired numbered 1,173.618mu, accounting for 103.68% of the plan, including 456.947mu of cultivated land, which accounted for 92.31% of the plan. The number of people affected by land acquisition numbered 1,350, accounting for 237.26% of the plan. The demolished buildings amounted to 65,197.59m2 in area, accounting for 109.05% of the plan. The people affected by building demolition numbered 1,703, accounting for 72.41% of the plan. Specifically, the demolished farmers’ houses amounted to 63,337.59m2 in area, accounting for 106.25% of the plan. And non-farmer’s buildings were 1,860m2 in area, accounting for 1,056.82% of the plan. Ruijin City: The actual land acquisition amounted to 1,950.672mu, accounting for 101.7% of the plan, including 1,282.8mu of cultivated land, which accounted for 101.25% of the plan. The number of people affected by land acquisition numbers 1,611, accounting for 91.59% of the plan. All the demolished buildings are farmer’s houses, amounting to 48,671.7m2 in area and accounting for 75.2% of the plan. The people affected by building demolition numbered 1,800, accounting for 70.34% of the plan. Changting County: The actual land acquisition amounted to 6,208.36mu, accounting for 173.42% of the plan, including 2,533.89mu of cultivated land, which accounted for 128.82% of the plan. The number of people affected by land acquisition numbered 3,179, accounting for 119.6% of the plan. The demolished buildings amount to 122,539.44m2 in area, accounting for164.96% of the plan. The

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 15 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project people affected by building demolition numbered 1,151, accounting for 43.38% of the plan. Among the demolished buildings were farmers’ houses and factory buildings, accounting for 164.9% and 170.89% of the plan respectively. Liancheng County: The actual land acquisition amounted to 5,006.21mu, accounting for 202.35% of the plan, including 1,945.445mu of cultivated land, which accounted for 290.8% of the plan. All the demolished buildings are farmer’s houses, amounting to 31,079.63m2 in area and accounting for 150.35% of the plan. The people affected by building demolition numbered 498, accounting for 75.11% of the plan. Shanghang County: The actual land acquisition amounted to 1,437.2mu, accounting for 140.63% of the plan, including 873.99mu of cultivated land, which accounted for 221.26% of the plan. The number of people affected by land acquisition numbered 296, accounting for 135.78% of the plan. All the demolished buildings are farmers’ houses, amounting to 22,305.43m2 in area and accounting for 129.77% of the plan. The people affected by building demolition numbered 296, accounting for 135.78% of the plan. Xinluo District: The actual land acquisition amounted to 3,135.67mu, accounting for 209.32% of the plan, including 2,020.57mu of cultivated land, which accounted for 247.01% of the plan. The number of people affected by land acquisition numbered 1,139, accounting for 151.87% of the plan. The demolished buildings amounted to 62,333.37m2 in area, accounting for125.31% of the plan. The people affected by building demolition numbered 3,340, accounting for 244.15% of the plan. Among the demolished buildings were 56,324.93m2 of farmers’ houses, accounting for 129.6% of the plan, and 6,008.44m2 of factory buildings and other buildings, accounting for 95.6% of the plan.

4. The Progress of Resettlement

4.1 The Whole Process of Land Acquisition and Resettlement

The work of land acquisition, demolition, relocation, compensation and resettlement was divided into three phases: Phase one was the period for the formulation of the policies and plans for the compensation and resettlement associated with land acquisition, demolition and relocation. Specifically, phase one was from December 2000 to June 2002. On December 12th, 2000 the Ministry of Railways signed an agreement with Fujian and Jiangxi Provinces (hereinafter referred to as ministry-province agreement. Please refer to Annex 4). In January 2002 the Ganzhou-Longyan Railway Construction Project Headquarters jointly formed by Shanghai Railway Administration and Nanchang Railway Administration signed related agreements on land acquisition, demolition and relocation with Longyan City and Ganzhou City respectively. During the period from October 2001 to February 2002, Longyan City and Ganzhou City respectively issued the relevant notice documents concerning the compensation standards associated with the land acquisition, demolition and relocation for the railway construction. During the period from February to July 2002, all the counties (districts) affiliated to Ganzhou City in Jiangxi Province and Longyan City in Fujian The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 16 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Province issued their notice documents on the compensation standards for the land acquisition, demolition and relocation as well as specific resettlement plans (See Annex2). By autumn 2001, all local governments had established their Ganzhou-Longyan Railway construction supporting offices.

Phase two, which began from November 2001, was the period for implementing land acquisition, building demolition and relocation, as well as compensation distribution. In November 2001 the Ganzhou-Longyan Railway Construction Headquarters issued the order for commencing the construction of the railway. The land acquisition, building demolition and relocation for the construction of the key civil engineering structures such as tunnels and bridges were initiated first. From February 2002 on, the mobilization, policy publicity and counting of the property affected by land acquisition, demolition and relocation were initiated in large scale. After publicizing the result of property investigation, the compensation for land acquisition, building demolition and relocation was allocated partially, and the housing sites were distributed to the affected households. During the period between the summer and autumn of 2002, the land acquisition, building demolition and relocation reached their peak, and the construction of bridges, tunnels and subgrades for the project entered its full scale. By the end of 2003 the land acquisition, building demolition and relocation were largely finished.

Phase three was the period, during which the affected people were compensated, resettled and gradually recovering their level of production and living standards. In fact, this stage was initiated at the same time with the implementation phase of land acquisition, building demolition and relocation, and continued in the whole process. After receiving the prepaid partial compensation (usually 50%-60% of the total) for land acquisition, building demolition and relocation, all the affected people began moving and handing in their land. When the moving was finished, the remaining part of the compensation was paid, and the affected households began to build their new houses on the housing sites allocated to them. At the end of 2002 when the land acquisition, building demolition and relocation was largely completed, the railway construction entered its full scale phase. And the affected households finished their new houses one after another and moved in. Between the 2003 and 2004, the affected people entered their life recovery phase after completely resettled.

4.2 Evaluation of the Match between the Progress of Resettlement and the Schedule of Project Construction

The work of land acquisition, building demolition, relocation and resettlement on the whole matched the construction schedule of Ganzhou-Longyan Railway Project. In principle the compensation was in place first, then the work of land acquisition, building demolition and relocation began, and then the land for construction was provided. Though the progress of land acquisition, building demolition and relocation in different counties and districts was not the same, all the counties and districts followed that same procedure. There was not a single case that the

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 17 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project land was provided before compensation and resettlement. And there occurred no large-scale delay of funds and untimely compensation and resettlement that might hold back the progress of railway construction. For more information, please refer to table2 and 3.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 18 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Table 2 Process of Land Acquisition, Building Demolition and Relocation\Resettlement for Ganzhou-Longyan Railway Project

Description 2001 2002 2003 1 2 34567891 01 11 21234 5 67891 01 11 212345678 9 10 11 12 1 Detailed Planning, Engineering Design, Document Preparation 2 Pre-qualification and Invitation for Bids 3 Determination of Policies on Land Acquisition, Demolition, Relocation and Resettlement 4 Implementation of Land Acquisition, Demolition, Relocation and Compensation 5 Resettlement and Life Recovery of Affected People 6 Civil Engineering Construction and House Building 7 Laying of Rails

8 Telecommunication, Signaling and Electrification 9 Trial Operation

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Table 3 Process of Land Acquisition, Building Demolition and Relocation\Resettlement for Ganzhou-Longyan Railway Project (Continuation of Table 2)

Description 2004 2005 2006 2007 123 4 5 6 7 891 01 11 2123456789 10 1 11 21234567891 01 11 21 2 3 4 5 6 7 1 Detailed Planning, Engineering Design, Document Preparation 2 Pre-qualification and Invitation for Bids 3 Determination of Policies on Land Acquisition, Demolition, Relocation and Resettlement 4 Implementation of Land Acquisition, Demolition, Relocation and Compensation 5 Resettlement and Life Recovery of Affected People 6 Civil Engineering Construction and House Building 7 Laying of Rails

8 Telecommunication, Signaling and Electrification 9 Trial Operation

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

5. Resettlement Policy

5.1 The Resettlement Policy and Compensation Standards Actually

Implemented

The policy for the land acquisition, demolition, relocation, resettlement and compensation necessitated by the construction of Ganzhou-Longyan Railway is in conformity with the ADB resettlement policy and the relevant laws and regulations issued by the Chinese government. Such laws and regulations include: The Land Administration Law of the People’s Republic of China The Implementation Regulations of the Land Administration Law of the People’s Republic of China Regulations on the Demolition and Relocation of Urban Houses Issued by the People’s Republic of China The Real Estate Administration Law of People’s Republic of China Basic Farmland Protection Regulations Notice on Further Strengthening Land Administration and Guaranteeing the Protection of Cultivated Land Issued by the State Council Implementation Methods of Land Administration Law of Jiangxi Province Implementation Methods of Land Administration Law of Fujian Province The documents concerning the specific policies on compensation and resettlement are as follows: „ Agreement Reached between the Ministry of Railways, Fujian Province and Jiangxi Province on the Issues Concerning the Construction of Ganzhou-Longyan Railway (signed on December 12th, 2000) „ The Working Plan for the Land Acquisition, Demolition, Relocation and Resettlement for the Fujian Section of Ganzhou-Longyan Railway (Document 2001-344 Issued by Longyan Municipal People’s Government on October 29, 2001) „ The Compensation Standards for Land Acquisition, Building Demolition and Relocation for the Fujian Section of Ganzhou-Longyan Railway (Document 2001-345 Issued by Longyan Municipal People’s Government on October 30, 2001) „ The Compensation Standards for Land Acquisition, Demolition and Relocation for the Ganzhou Prefecture Section of Ganzhou-Longyan Railway (Document 2002-9 Issued by Ganzhou Municipal People’s Government on February 22, 2002) All the counties and districts along the Ganzhou-Longyan Railway line formulated their local policies and standards for compensation and resettlement in light of the requirements set in above documents. Those local policies stipulated specific compensation standards for various types of land and houses affected by land acquisition, building demolition and relocation. (Please refer to The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 21 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project table 4 and 5 for more detailed information.

5.2 Comparison between the Actual Resettlement Compensation

Standards and Those Stated in the Resettlement Plan

5.2.1 Comparison between the Actual Land Acquisition Compensation Standards and Those Stated in the Resettlement Plan

Table 4 shows the comparison between the actual land acquisition compensation standards and those stated in the resettlement plan. And the itemized comparison is given below in words. a. Vegetable fields on the outskirts: Ganzhou City did not set a special compensation standard for outskirt vegetable field because the land acquisition did not involve the field dedicated to the cultivation of vegetables. But Longyan municipal government set the compensation standard for vegetable fields at 15,000yuan/mu in its document 2001-345. In fact only Changting County and Xinluo District had vegetable fields, and the compensation standards actually adopted were much higher than the standard stated in the government document, thus met the requirements of RAP. b. Irrigated fields and dry fields: All the compensation standards for irrigated fields and dry fields adopted in all affected counties of Ganzhou and Longyan cities were lower than the RAP lower limit (11,700yuan/mu for irrigated field and 6500yuan/mu for dry field calculated on the basis of 1mu/person per captain cultivated land). This discrepancy was caused by the difference between the standard of productive values adopted by RAP and the standard of productive values adopted by the local governments. The productive value standards adopted by RAP (900yuan/mu for the irrigated field and 500 yuan/mu for the dry field) were higher than the actual figures. To justify their actually adopted compensation standards, all the counties gave adequate explanation.

1) Ganxian County: According to the statistic bureau of Ganxian County, the unit productive values of rice over the past three years (1999, 2000 and 2001) for the three towns transited by Ganzhou-Longyan Railway line was 639.23yuan/mu. For more information, please see table1.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 22 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Table1: Computation of Productive Values of Cultivated Land in Ganxian County

Three-Year Year 1999 2000 2001 Average Rice Output Meilin Town 347 342 334 (kilo/mu) Unit Price 0.9 .9 1.08 (yuan/kilo) Number of 2 2 2 Seasons Unit Productive 624.6 615.6 721.4 653.9 Value/Year (yuan/mu) Jiangkou Rice Output 351 342 360 Town (kilo/mu) Unit Price 0.9 0.9 1.08 (yuan/kilo) Number of 2 2 2 Seasons Unit Productive 631.8 615.6 777.6 675.0 Value/Year (yuan/mu) Maodian Rice Output 309 304 307 Town (kilo/mu) Unit Price 0.9 0.9 1.08 (yuan/kilo) Number of 2 2 2 Seasons Unit Productive 556.2 547.2 663.1 588.8 Value/Year (yuan/mu) Three-Year Average Annual Productive Value of Three 639 Towns (yuan/mu)

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 23 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Take the land acquisition compensation standards for Ganxian County as an example. The land acquisition compensation standard for irrigated field was 8,600yuan/mu, which was 13.5 times as high as the productive value (8,600yuan/mu÷639yuan/mu). And this met the requirements stipulated by the compensation standard set in the land administration law of China. Please see Annex7 for more information.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 24 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Table3: Comparison between Actual Compensation Standards for Land Acquisition and Those Stated in RAP of Ganzhou-Longyan Railway Project

RAP1 Ganzhou City Longyan City No. Description Unit Ganxian Yudu Huichang Ruijin Changting Liancheng Shanghang Xinluo Ganzhou City Longyan City County County County City County County County District Suburban 1 Vegetable yuan/mu 23400-32400 28600-39600 - - - - 26000-42000 - - 34500-53400 Filed Irrigated 2 yuan/mu 11700-16200 15600-21600 8600 8800 8800 8800 10000-16000 10000-12200 10000-12200 12500 Field 3 Dry Field yuan/mu 6500-9000 9100-12600 5300 5300 5300 5300 5000-8000 5000-8400 5000-8000 6150 4 Orchard yuan/mu 6500 9100 6400 6400 6400 6400 8000 8000 8000 8000 5 Fish Pond yuan/mu 9000 13000 8600 8800 8800 8800 13500 13500 13500 13500 6 Homestead yuan/mu 6500 9100 5300 5300 5300 5300 13000 13000 13000 13000 7 Wasteland yuan/mu 500-1000 1200 700 700 700 700 2000 2000 2000 2000 8 Forest Land yuan/mu 3000-5000 4000-7000 2800 2800 2800 2800 2000-5000 2000-5000 2000-5000 2000-5000 300 ( dry 400 ( dry field ) -400 field) Standing ( irrigated 500(irrigated 9 yuan/mu 1450 500-1000 500-1000 500-1000 600-1200 600-1200 600-1200 600-1200 Crops field ) -520 field) ( vegetable 650 field) (vegetable) 10 Land for yuan/mu 1200 2000 Land for Land for earth Land for The cultivated land which could not be reused as

1 RAP sets differentiated compensation standards for different per capita cultivated land (in the range of 0.5-1mu/person). The smaller the per capita cultivated land is the higher the compensation standards.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Temporary ( cultivated (farmland) earth fetching and earth cultivated land after being used as the site for earth Use land ) 或 500 800 fetching and dumping:1500-3500; fetching fetching and dumping or for other purposes was (wasteland) (wasteland) dumping : Land for and compensated against the standard for land acquisition. 1260-2940 ; construction detour: dumping : And the one that could be reclaimed after being acquired Land for 2500-5000 400-1500 for temporary use was compensated according to the construction standard of 1200yuan/mu. detour:4200

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Table5: Comparison between RAP Compensation Standards and Actual Compensation Standards for Demolition and Relocation for Ganzhou-Longyan Railway Project

RAP Ganzhou City Longyan City No Description Unit Longyan Huichang Changting Liancheng Shanghang Xinluo . Ganzhou City Ganxian County Yudu County Ruijin County City County County County County District Framed yuan/ 1 290-300 265-300 265-300 265-300 340 380 - 430 Structure m2 Brick-Concr yuan/ 2 280 300 230-240 225-260 225-260 225-260 220-240 220 220 330 ete m2 yuan/ 3 Brick-Wood 210 230 120-195 175-205 175-205 175-205 190-210 180 180 250 m2 yuan/ 4 Earth-Wood 170 180 100-160 140-170 140-170 140-170 145-160 160 150 170 m2 Moving 100yuan/house 100yuan/house 100yuan/hous 100yuan/hous 100yuan/house 55yuan/pers 100yuan/per 5 3yuan/m2 6yuan/m2 Subsidy hold hold ehold ehold hold on son 10yuan/ 40yuan/ Transition 10yuan/month 1000yuan/hou 6 3yuan/m2 10yuan/person·month person · mon person · mon 2yuan/m2 Subsidy ·person sehold th th

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project 2) Yudu County: The data of the productive values of Yudu County provided by the county railway construction supporting office are shown in Table 2.

Table 2: The Annual Productive Values of Rice over the Three Years (1999-2001) for Yudu County

Productive Unit Output of Price Number of Year Value Rice (kilo/mu) (yuan/kilo) Seasons (yuan/mu) 1999 342 0.9 2 615.6 2000 342 0.9 2 615.6 2001 344 1.08 2 743.04 Three-Year Average Productive Value 658.08

According to table2, the adopted land acquisition compensation standard for paddy field, 8,800yuan/mu, is 13.37 times higher than the average annual productive value of rice. And this level is in conformity with the compensation requirements of the land administration law of China.

3)Huichang County:

The data of the productive value of Huichang County provided jointly by the county statistic bureau, grain bureau and the bureau of land and resources are shown in table 3.

Table 3: The Annual Productive Value of Rice over the Three Years (1999-2001) for Huichang County

Productive Unit Price Year Rice (Output/mu) Value (yuan/kilo) (yuan/mu) 1999 730 0.9 657 2000 726 0.94 681.5 2001 728 0.94 684.32 Average Annual Productive Value from 1999 to 2001 674.3

According to table3, the land acquisition compensation standard adopted for paddy field is 13.05 times higher than the average annual productive value of rice. And this level is in conformity with the compensation requirements of the land administration law of China.

4) Ruijin City

The following method for formulating the compensation standard was provided by The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 28 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Ruijin municipal railway construction supporting office. The average productive value of cultivated land over the three-year period from 1999 to 2001 was 755yuan/mu. According to the provisions of land administration law, the compensation standards should be calculated with the following formula:

The land acquisition compensation=The average annual productive value of the previous three years×6; the laborer resettlement compensation= The average annual productive value of the previous three years×5; the compensation for standing crops (just for one season) = The average annual productive value of the previous three years×0.5. Thus the total compensation is 11.5 times higher than the average annual productive value. Hence the actual compensation standard is 8,800yuan/mu (755yuan/mu×11.5=8682.5yuan/mu).

5) Changting County:

The unit prices of rice during the three-year period from 1998 to 2000 were as follows (with the courtesy of the county grain bureau and price bureau): The average unit price of rice was 68yuan/50kilos in 1998; 63yuan/50kilos in 1999 and 43yuan/50kilos in 2000. And the average unit price of rice for that three-year period was 58yuan/50kilos. The data provided by the county statistic bureau indicated that the unit output of rice from 1998 to 2000 was 378kilos/mu in 1998, 383kilos/mu in 1999 and 386kilos in 2000. And the average unit output of the three years was 382kilos/mu. Hence the average annual productive value of rice of the three years was 886yuan/mu. As the actual compensation standard for paddy field fell in the range of 10000-16000yuan/mu, it was 11.3 to 18.06 times higher than the average annual productive value of paddy field.

Table 4: The Annual Productive Value of Rice over the Three Years (1998-2000) for Changting County

Productive Unit Output of Price Number of Year Value Rice (kilo/mu) (yuan/kilo) Seasons (yuan/mu) 1998 378 1.36 2 1028.16 2000 383 1.26 2 965.16 2001 386 0.86 2 663.92 Three-Year Average Productive Value 886

6) Liancheng County:

The office of railway construction coordinating headquarters of Liancheng County provided the productive value certificates issued by the statistic stations of all the towns and townships concerned and set the paddy field productive value at 500yuan/mu and the dry field productive value at 340yuan/mu on the basis of those The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 29 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project productive value certificates. The following formulas show the process of compensations calculation:

The total compensation standard =the productive value×13 (13=8+4+1);

(The land acquisition standard=the productive value×8;

The laborer resettlement subsidy= the productive value×4;

The standing crops compensation= the productive value×1)

Thus the productive value for paddy field was 6500yuan/mu, and the productive value for dry land was 4420yuan/mu; after putting the per capita cultivated land factor (0.75mu/person) into consideration, we get the figure 7,166.6yuan/mu for paddy land compensation and 4193yuan/mu for dry land compensation. In fact, the actual lower limit of paddy land compensation standard was 10000yuan/mu while the actual dry land compensation standard was 5000yuan/mu. Both compensation standards met the compensation requirements set in the land administration law of China.

7) Shanghang County:

The railway construction coordinating headquarters office of Shanghang County provided the productive values issued by the statistic stations of Jiaoyang Township and Gutian Town transited by Ganzhou-Longyan Railway line. Specifically the productive value was 680yuan/mu for paddy field and 460yuan/mu for dry field. The productive values of cultivated land that should be compensated in accordance with Fujian Provincial Regulations for Implementing Land Administration Methods of the People’s Republic of China.

Paddy field: land compensation=680yuan/mu × 8=5440yuan/mu; resettlement subsidy=680yuan/mu×4×1/0.8mu/person=2720yuan/mu; The sum of the two items is 8160yuan. Plus the compensation for standing crops, which is 500yuan, the actual compensation for paddy field is 10000yuan/mu.

Dry field: Compensation for land=460yuan/mu×6=2760yuan; resettlement subsidy=460yuan/mu×4×0.75mu/person=1840yuan/mu; the sum of the two items is 4600yuan/mu. And the actual compensation standard for dry field was 5000yuan/mu.

8) Xinluo District:

From the data provided by the relevant towns transited by Ganzhou-Longyan Railway line we know that the grain outputs of all the villages concerned are similar to those of the above-mentioned Changting County, Shanghang County and Liancheng County. However, as Xinluo District is adjacent to

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 30 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Longyan City, the actual compensation standard was 12500yuan/mu for paddy field and 6150yuan/mu for dry field.

a. Orchard: As is mentioned in paragraph b, because the productive values actually adopted by the resettlement departments were lower than the ones stated in RAP, the compensation standards for orchards were also lower than those stated in RAP, but higher than the compensation standards for dry fields.

b. Fish ponds: None of the counties in Ganzhou City met the requirements of RAP in terms of the compensation standards for fish ponds, but all the counties/districts in Longyan City reached the RAP standards on the scale of fish pond compensation.

c. Homestead: All the counties (cities) in Ganzhou City adopted dry field compensation standard as the standard for the compensation of homestead. Therefore their compensation standards fell short of the requirements of RAP. In contrast the homestead compensation standards adopted by all the counties (district) in Longyan City by far exceeded the standard for dry field and reached the corresponding compensation standards of RAP.

d. Wasteland: The compensation standards adopted for wasteland by all the counties (cities) in Ganzhou City fell within the range stated in RAP. In contrast the compensation standards adopted by all the counties (district) for wasteland by far exceeded the requirements of RAP.

e. Forest land: The compensation standard for forest land adopted by Ganzhou City was at least 200yuan/mu lower than the standard stated in RAP, while Longyan City reached the standard for forest land set in RAP.

f. Land for temporary use: All the counties (cities/district) along the railway line reached and even exceeded by far the requirements set in RAP for the compensation of land for temporary use.

5.2.2 Analysis of Compensation Standards for Demolition and Relocation

Table 5 Compares the RAP compensation standards for demolition and relocation with those actually adopted. As is shown in the table, all the resettlement departments of Ganzhou-Longyan Railway Project reached the RAP standards in giving compensation for the demolition and relocation of low class houses such as houses of earth-wood structure. But the compensation standards adopted by most of the counties (except Xinluo District which is adjacent to Longyan City) for the compensation of higher class houses, such as brick-concrete houses and brick-wood houses, were lower than those stated in RAP. All the counties justified their compensation standards for demolition and relocation by giving due explanation.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 31 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project 1) Ganxian County:

The county construction bureau provided the list of budget prices of the major construction materials for the second quarter and first half of the year 2001 for Meilin District of Ganxian County, and calculated the replacement prices of houses. According to the bureau’s calculation, the replacement price for brick-concrete houses was 207yuan/m2, the one for brick-wood houses was 173yuan/ m2 and the one for earth-wood houses was 141yuan/m2. As the actual compensation standards are formulated according to the upper limit of the compensation standard, the actual compensation standard for brick-concrete houses was 240yuan/m2, the one for brick-wood houses was 195yuan/m2 and the one for earth-wood houses was 160yuan/m2. The actual compensation standard for brick-concrete houses fell short of RAP standard, but it met the standard of the replacement price.

2) Yudu County, Huichang County and Ruijin County:

The three counties adopted the same compensation standards for house demolition and relocation. The railway construction supporting office of Yudu County provided the unit prices of the major building materials for 2001 verified by the construction bureau and price bureau of Yudu County, and calculated the replacement prices for farmers’ houses. According the calculation results, the replacement price for the brick-concrete houses was 225yuan/m2, the one for brick-wood houses was 168yuan/m2 and the one for earth-wood houses was 120yuan/m2. The compensation standards actually adopted reached the corresponding replacement prices, and the upper limit of the compensation standards reached and even exceeded the compensation standards of RAP. (See Annex7.)

3) Changting County:

The county’s compensation standards for brick-wood houses and earth-wood houses reached the requirements of RAP, but the one for brick-concrete houses was 40yuan lower than the RAP standard— 280yuan/m2. The resettlement department of Changting County provided the documents on the compensation standards for projects of the same type still valid then.

Provisions on the Compensation for Housing Demolition, Relocation and Resettlement for the Reconstruction of West Section of Zhaozheng Road (Document No.1998-501);

Provisions on the Land Acquisition Compensation and Resettlement for the Construction of Hongduan Reservoir and Power Plant of Changting County (Document No. 1995-3);

Provisions on the Compensation for Housing Demolition and Relocation for the Construction of Township Sections of the National Highway 319 (Document No. The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 32 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project 1993-372);

After comparing the above documents and analyzing the compensation standards thereof, the external monitoring agency found that the compensation standards for house demolition and relocation adopted by Changting County for Ganzhou-Longyan Railway Project were the highest local compensation standards for farmers’ houses.

4) Liancheng County:

Though the housing compensation standard for earth-wood houses adopted by Liancheng County reached the RAP compensation standard, those for brick-concrete and brick-wood houses failed to meet the RAP requirements. The office of railway construction coordinating headquarters of Liancheng County confirmed that the urban and rural planning and construction bureau organized professional personnel to calculate the housing compensation standards for Ganzhou-Longyan Railway Project. With the housing sites offered free of charge by the resettlement department, and with the relevant deed taxes and fees waived, the implemented standards for houses of framed structure was 380yuan/m2, the one for brick-concrete houses was 220yuan/m2 and the one for brick-wood houses was 180yuan/m2. All those standards met the local housing replacement requirements. (See Annex7.)

5) Shanghang County:

The compensation standards for housing replacement for Shanghang County was similar to those for Liancheng County. The compensation standard for earth-wood houses reached the RAP requirements, but those for brick-concrete houses and brick-wood houses fell short of RAP requirements. The certifying documents provided by the urban and rural planning and construction bureau of Shanghang County proved that the implemented compensation standards reached the market prices for housing replacement. (See Annex 7)

5.3 Evaluation of the Applicability of the Resettlement Policy

Though the actually adopted compensation standards for land acquisition, demolition and relocation for Ganzhou-Longyan Railway Project fell short of RAP requirements on the scale of some indexes, the external monitoring agency found through its monitoring investigation along the railway line that most of the affected people were satisfied with the resettlement policies adopted by their corresponding counties (district). In general two factors helped to raise the sense of satisfaction of the affected people. One is that most of the affected areas were located in comparatively remote and self-contained mountainous areas, where the productivity was low and most of the houses were of brick-wood or earth-wood structure. The other factor is that the compensation standards for land acquisition, demolition and relocation adopted for this railway

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 33 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project project were in general higher than those for other local projects.

The compensation standards for land acquisition, demolition and relocation adopted by the 8 counties/district along Ganzhou-Longyan railway line were in general higher than those for highway construction projects, equal to or slightly higher than those for local enterprise construction projects, but lower than those for the local real estate development projects and other commercial development projects. As the local projects of national highway and expressway construction were more comparable to Ganzhou-Longyan Railway construction project, the affected people were in general satisfied with the compensation standards adopted for Ganzhou-Longyan Railway Project because they were higher than those adopted for highway and expressway construction projects.

6. Income and Livelihood

6.1 The Measures Adopted to Recover the Income and Livelihood of the

Affected People

The policies of compensation and resettlement and other measures adopted by the resettlement departments of the local governments along the Ganzhou-Longyan Railway line ensured a steady income recovery of the affected people. And those measures include the following aspects: 1) Redistribution of land Most of the affected villages redistributed the land within their own villages. And this enabled the affected people to maintain their original means of income (farming) with no need to learn any new productive skills. Among the lands that were distributed to the affected people were the reserved collective land, the land uncultivated by its owners who have been working outside their hometowns, and the land of the whole group or village, which was to be redistributed among the group members or village members. If the land of the group or village is redistributed among the members, the compensation for land acquisition will be redistributed. The modes of land redistribution depend upon the actual situation of the village. 2) Training of agricultural productive skills and non-agricultural productive skills offered by the relevant departments: The external resettlement monitoring agency found through investigation that various functional departments (women’s federation, poverty reduction office, agricultural bureau, forestry bureau, animal husbandry bureau, and labor bureau, etc.) of all the counties (districts) along Ganzhou-Longyan Railway line offered rural residents, on a regular basis, trainings of skills and techniques on agricultural cultivation, breeding of domestic animals and poultry, and even non-farming productive skills and techniques to enhance the rural residents’ ability of developing production and increasing their income mainly through farming and breeding. In addition, all the counties (district) of Longyan City of Fujian Province formed some The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 34 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

enterprise-village alliances, in which the enterprises offered trainings of skills to rural residents according to the needs of enterprises. The trainees included the people affected by the Ganzhou-Longyan Railway project. At the same time, Ganzhou City of Jianxi Province formed a belt of productive bases with the investment from the nonlocal investors in agricultural cultivation and processing industry of agricultural produce. Those nonlocal investors’ renting of land, hiring and training of the agricultural production workers (who owned or lived near that rented land) not only taught them agricultural productive techniques but also increased their income. 3) The local governments took advantage of the local new countryside construction planning and poverty reduction planning, and endeavored to develop agricultural industrialization and the non-agricultural industries for towns to increase job opportunities and income of the affected people. The opening of Ganzhou-Longyan Railway has attracted many investors from different areas home and abroad, such as , , , Zhejiang, Shanghai, Hong Kong, Taiwan, Holland, and Canada, etc. Those investors come to the areas along Ganzhou-Longyan Railway line to tap the mineral resources (such as the tungsten alloys and rare earths in Ganxian County and Yudu County, the marble and limestone in Huichang County and Ruijin County, the coal in Longyan City and copper in Shanghang County.), or develop industrialized agricultural cultivation and processing industry of farm produce (such as the stevia in Ganxian County, the navel orange and pollution-free farm produces in the south of Jiangxi Province.), or even start numerous non-agricultural projects in the local industrial parks already established in the counties (district) along Ganzhou-Longyan Railway line. Those industries and the relevant service industries have created a large number of job opportunities, which have attracted a large number of surplus laborers and those who used to work in the coastal areas of China into the local non-agricultural industries. As a result, the income of those farmers has increased. (Please refer to the Report on the Impact of Poverty for more detailed information) 4) Measures Aimed at Helping Vulnerable Groups The vulnerable groups among the people affected by land acquisition, demolition and relocation for Ganzhou-Longyan Railway Project were given special assistance and support in their resettlement by the resettlement departments of the counties (district). For example, the resettlement department of Ganxian County offered the vulnerable groups assistance and support in the following three aspects: 1) Helping the vulnerable groups to build their new houses or assisting them in buying a house of the same size and quality as their original one in their village with their compensation fee after getting their permission; 2) Offering preferential credit and giving poverty-reduction discount-interest loan; 3) Going all out to help them find jobs. The external monitoring agency collected many cases evidencing the assistance and support offered by the resettlement departments to the vulnerable groups. The cases cited below are only a portion of them. „ To help an old couple originally lived in Luowu Group, Gutian Village, Gongjiang Town, Yudu County, the construction authority helped the couple demolish their old house and offered them the transitional housing free of charge. In addition, the construction authority gave the old couple 2000yuan on top of their deserved compensation as the extra subsidy. After the husband passed away in 2002, the railway construction The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 35 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

supporting office of Yudu County visited the wife several times to persuade her to move into the township rest home, but she preferred to stay in her own village. „ In Huichang County there was a disabled couple. The husband, Song Fangxing, was crippled, and the wife was suffering from dementia. As their demolished house was small in area, their sum of compensation was small, too. They suffered a shortage of fund for building their new house. To help this disabled couple, the railway construction supporting office gave them 200yuan comforting money and offered assistance in their building of new house. „ The poverty-reduction measures adopted by Ruijin City targeted all the poverty-stricken people including those affected by Ganzhou-Longyan Railway Project. Those poverty-reduction measures were as follows: The first measure was cadre to poor household assistance (abbreviated as the “321” special assistance, which means every bureau-level official assists 3 poor households, every division chief helps 2 poor households, and every section chief aids one), which aimed at helping 600 poverty-stricken households. The second poverty-reduction measure was the organization-to-household assistance. Altogether 3 province-level units in Jiangxi, 9 city-level units in Ganzhou City, and 35 county-level units in Ruijin offered assistance to their designated poverty-stricken households respectively, and each poor household received the aid of 500yuan per year. The similar campaign was also carried out in Ganxian County, Yudu County and Huichang County of Ganzhou City. „ Liao Nanhai, aged 46, was one of the relocated villagers in Meigang Village, Shazhouba, Ruijin City. He was afflicted with schizophrenia and had an aged mother to support. To help his family out, the township and the village allocated him the homestead before other households, the city-level railway construction supporting office gave him an extra compensation of 2000yuan, and the railway construction authority gave an extra compensation of 3000yuan. He had his new house built with the help of the above-mentioned three parties. „ Lai Tianfa was one of the relocated villagers in Shishan Township, Ruijin City. He was given a sum of compensation of 14 thousand yuan for his original two-room earth-wood house of over 100 m2. There were only two members in his family, namely, he and his aged mother. He was a 40-year-old bachelor and had no saving. He wanted to build a one-storey brick-concrete house, but the compensation was not enough for him to build a new house. And his cousin Lai Libin, a 50-year-old bachelor, who was living alone, was paid a compensation of 5000yuan for his original one-room house of dozens of square meters. Seeing this situation, the township, the village and their relatives persuaded them to combine their compensations to build and live in the same new house. They accepted the advice and built their common house and lived together. „ As an old woman of Meigang Village, Shazhouba, Ruijin City was living alone, and was too old to build her new house herself after her old house was demolished for the construction of Ganzhou-Longyan Railway, the resettlement department directed the village to organize the necessary resources to build the new house for her and help her move into her new house. „ As Hu Qiliang and his wife (one of the affected households of Luofang Village, Changting County) were both afflicted with serious illness, they were discriminated by The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 36 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

their daughter-in-law in the process of resettlement. In addition to establishing a harmonious relationship among them, the resettlement department allocated them an extra subsidy of 2000yuan and provided them with a set of transitional house before they moved into their new house. Another senior villager of Luofang Village, who was over 70 years old and taken care of by his daughter over a long period of time, also needed assistance. To help him solve the living difficulties during the transitional period before moving into his new house, the resettlement department allocated him a special subsidy of 2000yuan. „ As Yuan Jingao, a villager of Pingpu Village, Jiaoyang Township, Shanghang County, was disabled in his lower limbs, and his wife suffered from hematopathy, his family lacked laborers. They had a sow breeding farm of about 20 sows within the demolition range for Ganzhou-Longyan Railway. In view of their special situation, the resettlement department not only allocated them the compensation for house rebuilding but also rented a land of 3mu as their new sow breeding farm. And to help the couple continue their development of sow breeding and maintain their household income, the resettlement department also built the access road to the newly rented sow breeding farm and mounted the glass roof of the hog pen for the couple. „ As it was difficult for Yuan Fanhui, a 70-year-old widower in Shanghang County, to build his own new house, the county railway construction supporting office persuaded his nephew to let him live under the same roof. The housing site allocated to Yuan was transferred to his nephew to build their common new house with the precondition that the nephew must let Yuan to live with him under the same roof. At the same time, Yuan kept his demolition compensation of over 10 thousand yuan as his living fund. „ To help a disabled relocatee in Hongzhushan Village, Longmen Town rebuild his house, the resettlement department of Xinluo District allocated him a sum of extra subsidy of 10,000yuan.

6.2 Comparative Analysis of Income Recovery

In April 2002 the external monitoring agency finished its sample survey of living standards on 350 households affected by Ganzhou-Longyan Railway Project. And in the post-resettlement monitoring evaluation process, the external monitoring agency resampled the baseline survey households of all the affected counties (district) and traced their living situations. As some of the samples for baseline survey did not fall in the range of redline for land acquisition, or because some of the planned interviewees were not available when the external monitoring group came to visit them, the data listed below only reflect the comparative situations of those samples that were traced and interviewed during the post-resettlement monitoring survey. Table 6 shows the comparative situations of the baseline survey samples who were interviewed during the post-resettlement survey.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 37 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Table 6: Table of Post-Resettlement Baseline Survey Samples for Ganzhou-Longyan Railway Project

County Township Village Group Names of Affected People (District) (Town)( Ganxian Jiangkou Liushilidian 3 Wu Hongfu, Wu Hongxing, Wu Yunlai County Town Yudu Luoyou Yangmei 9 Liu Rongxiang, Yan Chaolin, Yan Zhaohui County Town Village Huichang Xijiang Datian 8 Xu Yunfa, Xu Chengquan, Xu Liuliu, Xu County Town Village Xianqin, Xu Jianfa Ruijin City Xianghu Nangang Xiewu Yang Ruisheng, Xie Shengbing Town Village Changting Gucheng Liangkeng 3, 7 Chen Lianxing, Zeng Jixian County Town Village Liancheng Pengkou Liangzen - Yang Dizhang County Town Village Shanghang As the baseline survey samples were mainly distributed in Jiaoyang Village while County the actual land acquisition took place in Pingpu Village, there were no comparative samples for Shanghang County. Xinluo Dachi Xiyang Wu Haojin, Wu Xincai, Wu Liping District Town Village

The survey conduced on the affected people listed in table 6 indicates that the impact of the land acquisition, demolition, relocation and resettlement for Ganzhou-Longyan Railway on the living standards of the affected people is positive. In general most of the affected people have a rise in their living standards, or at least have recovered their original level before the land acquisition. And what is more, they enjoy a great improvement in their housing conditions. For detailed information, please refer to the analysis conducted in sections from 6.2.1 to 6.2.7.

6.2.1 Gan County

1)Wu Yunlai: Investigation records in 2002: Male, aged 61, Han by ethnicity, Villager of Group 3 of Liushilidian Village, Jiangkou Township An extended family of three generations under the same roof. There are 15 members in all: the wife, three sons and their wives, a daughter and six grandchildren. Wu Yunlai has occupied the party secretary of village. Now they take charge of orchard. Three couple of sons and son’s wives do manual work in Shanghai, Zhejiang and Ganzhou.The family has 1.9 mu of cultivated land, 2 mu of woodland and 15 mu of orchard. They must purchase food supplies every year because of large population of the family. Family income and expenditure: The family annual

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 38 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

income is 35200 yuan, including 4000 yuan from agricultural production, 1200 yuan from animal raising and 30000 yuan from non-agricultural production. The average net income is 2152.1 yuan per capita annually. The family expenditure on production is 2918 yuan. The family expenditure on livelihood is 18900 yuan annual, including 13000 yuan spend on food, 2000 yuan on education, 900 yuan on transportation and communication, 2000 yuan on clothing. The family has two two-storied brick-wood structured houses with a size of 440m2. The family set up these houses in 1993 for the house demolition of Beijing-Kowloon Railway. It cost them 58000 yuan. Family durable consumables: two color TVs, a black and white TV and a telephone. The economic condition of this family is among the upper-intermediate in the village.

Investigation records in Jun 2007: Villager of group 3 of Liushilidian Village, Jiangkou Town, Gan County. There are 12 members in his family: the wife, three sons and their wives, and four grandchildren. The eldest son is 39 years old, junior college education, and works in Urban Construction Bureau where is outside their county. The eldest daughter-in-law is 37 years old, junior high school education, and farms at home. The second son is 33 years old, junior high school education, a truck driver out-of-town, and earns 1200 yuan monthly (cost-free room and board). The second daughter-in-law is 32 years old, junior high school education, does manual work in Zhejiang, and earns 1,000 yuan monthly. The third son is 29 years old, with junior high school education, trucks at home, and earns 2,000 yuan monthly. The third daughter-in-law is 29 year old, with junior high school education, does manual work locally, and earns 800 yuan monthly. Grandchildren are in school. Their former brick-wood structured house with a size of 200 m2 was compensated for more than 60,000 yuan which was paid completely. The new 4 brick-concrete structured houses are 800 m2, and each of them is 200 m2. The family has 2 mu of paddy field and 1 mu of dry land for planting vegetable now. Besides, Wu is the contractor of 25 mu of orchard, and the net income of orchard is 50,000 yuan annually. Family durable consumables: a refrigerator, a washer, a TV, a motorcycle, a truck. This family is among the upper-intermediate in the village in terms of living standards. He is satisfied with the construction of railway and resettlement.

2) Wu hongfu: Investigation records in 2002: Male, aged 40, Han by ethnicity, villager of Group 3 of Liushilidian Village, Jiangkou Township. Family members: 5 in all, the wife, two sons who are primary school pupils, the daughter who is a elementary school pupil. Wu Hongfu and his wife do manual work in Fujian. Family income and expenditure: The family has an annual income 8500 yuan main from non-agricultural job. The family expenditure on livelihood is 8280 yuan, including 3000 yuan spend on food, and 1000 yuan spend on medical treatment of his wife. Noticeable, 3500 yuan spend on education annually because the three children are all school pupils. So, the fee for education is the hugest one in family expenditure. The family house is a brick-concrete structure sized 110m2, including subsidiary house such as kitchen and water closet. The house cost them

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 39 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

40000 yuan, built in 1997. Family durable consumables: a black and white TV, a sartorius and a telephone. The family is one of the impoverished in the village.

Investigation records in Jun 2007: Villager of group 3 of Liushilidian Village, Jiangkou Town, Gan County. There are 5 members in his family, including his wife, daughter, son and father. He and his wife do manual work with annual income 20,000 yuan in Fujian. His father takes care of the children at home, and the children are pupils. The family has 2 mu of cultivated land, a brick-concrete structured house with a size of 200 m2. Family durable consumables: a color TV, a motorcycle. This family is intermediate in the village in terms of living standards. They think that now there is no changes about income, but more convenient to go home because of the Ganlong railway.

3) Wu hongxing: Investigation records in 2002: Male, aged 54, Han by ethnicity, villager of Group 3 of Liushilidian Village, Jiangkou Township. Family members: 4 in all: the wife, the son and the daughter. Wu Hongxing does odd job in spare time. The son works in a garage in Guangdong. The daughter is presently a middle school pupil. The family has 1.9 mu of cultivated land, 2 mu of woodland and 15 mu orchard. They must purchase food supplies every year. Family income and expenditure: The annual gross income is 5000 yuan, including 1500 yuan from agriculture production and 2000 yuan from non-agriculture, with an average annual income of 787.5 yuan per capita. The family expenditure on production is 1850 yuan annual. The family expenditure on livelihood is 5850 yuan annual, including 3300 yuan spent on food, 1000 yuan on education that is a huge expenditure and 500 yuan on medical treatment for his wife’s shoulder joint rheumatism. The family has a two-storied earth-wood structured house with a size of 260 m2. The house cost them 28000 yuan, built in 1994 for the house demolition of Beijing-Kowloon Railway. The cost of groundwork is higher in mountainous area than on plain so that cost them 8000 yuan. Family durable consumables: a black and white TV. The family is one of the impoverished in the village.

Investigation records in Jun 2007: Retired worker, villager of group 3 of Liushilidian Village, Jiangkou Town, Gan County. There are 5 members in his family, including his wife, son, daughter-in-law and granddaughter. The son and his wife do manual work with annual income 30,000 yuan in Guangdong. Now they have a new brick-concrete structured house with a size of 500 m2. Compared with the past, the living standards have improved. Family durable consumables: a color TV, a washer and a motorcycle. This family is among the upper-intermediate in the village in terms of living standards. They are satisfied with construction of railway and resettlement.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 40 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project 6.2.2 Yudu County

4) Yan Chaolin: Investigation records in 2002: Male, aged 46, primary school education, villager of Xin Group of Yangmei Village, Luoao Town, Yudu County. This family is one of the impoverished in the village. There are 6 family members in all, including 2 laborers. This family also has 3 mu of cultivated land, and feeds 6 livestock. The family annual production income is about 6,000 yuan, including 2,400 yuan from planting and 3,600 from breeding. The expenditure on production is 3,930 yuan, including 450 yuan on planting, 3000 yuan on breeding, and the tax 480 yuan. The family annual expenditure on livelihood is about 11,600 yuan, including 2,400 yuan on food, 500 yuan on clothing, 300 yuan on water electricity and gas, 200 yuan on medical treatment and health care, 8,000 yuan on education, and 200 yuan on others. The house is earth-wood structured in a size of 260 m2. The family durable consumables: two bicycles, a black-and-white TV, a sartorius.

Investigation records in Jun 2007: Villager of Xinyang Group of Yangmei Village, Luoao Town, Yudu County. There are 6 members in his family: the wife, three daughters and a son. The wife is 48 years old, primary school education, farms at home. The eldest daughter is 24 years old, junior college education, works in Ganzhou and earns 1,000 yuan monthly. The second daughter is 22 years old, junior high school education, does manual work in Ganzhou and earns 400 per month. The third 20-year-old daughter is a college student in Ganzhou. The son is 17 years old, will enter college soon. Yan feeds 10 head pigs at home. The former brick-wood structured house with a size of 200 m2 was compensated for more than 30,000 yuan, and now they have a brick-concrete structured house with a size of 400 m2 which costs about 70,000 yuan. This family has a liability over 30,000 yuan, and the main economic burden of this family is education fee. There is 2 mu of cultivated land. The only family durable consumable is a color TV. The railway construction firms his belief that he will give more on the education of his children, and he hopes that the children can out of rural areas, to improve their livelihood.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 41 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

5) Yan zhaohui: Investigation records in 2002: Male, aged 38, Han by ethnicity, villager of Xinyang Group of Yangmei Village, Luoao Township. Family members: 5 in all: the wife, two daughters and a son. The oldest daughter is primary school pupil and the other is in kindergarten. The youngest son is only five years old. The family was amerced of 3000 yuan because of exceeding procreation2. The family has 1.6 mu of cultivated land, 2 mu of mountain forest and 0.3 mu of fishpond. The family income and expenditure: The production gross income is 3800 yuan annual, including net income from agricultural production and that from breeding pigs and fish is 500 yuan, with the average net income is 240 yuan per capital annually. The family expenditure on livelihood is 3000 yuan. The family is one of the impoverished in the village. The revenue cannot meet the expenditure. Family livelihood mainly depends on debit and credit. There is no one durable consumable in the family. The family has a two-storied earth-wood house built in 1986, with a size of 260m2.

Investigation records in Jun 2007: Villager of Xinyang Group of Yangmei Village, Luoao Town, Yudu County. There are 5 members in this family: the couple, two sons and a daughter. Yan’s wife is 40 years old. The eldest daughter is 17 years old, and she is a student of agriculture school in Ganzhou. The second daughter is 11 years old, and she is a forth grade pupil at the village primary school. The son is 10 yeas old, and he is a forth grade pupil at the village primary school too. The couple farm at home. They feed more than 20 chickens and ducks. There is only 1 mu of paddy field because of the land acquisition and housing demolition. Yan zhaohui does manual work since lunar may of this year, and earns about 30 yuan per man-day. As job instability, the income is also very unstable. The former brick-wood structured house with a size of 160 m2 was compensated completely, including 10 yuan/month/person for the transition. The new brick-concrete structured house is two storied and 240 m2. Yan’s wife believed that it’s more convenient than before; the living standards and environment are also improved after the railway construction. But as the house is near the road, bicycles, chickens and ducks could be stolen easily. In addition, the train noise is too large. Besides, it’s a little far to the paddy field for farming.

2 The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 42 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

6) Liu Rongxiang:

Investigation records in 2002: Female, aged 41, Han by ethnicity, villager of Xinyang Group of Yangmei Village, Luoao Township. Husband got a divorce from her and abandoned his home three years ago. He left his parents and four children to Liu Rongxiang. She must carry the heavy burden of whole family under all kinds of hardships. Now the eldest 19-year-old daughter who will graduate from infant teachers college this summer and she is hope of whole family. The other two daughters are primary school pupils. The youngest son is 5 years old. The family has 2.1 mu of cultivated land. They depend on kin’s help because of shortage of labour force. The family’s lacking land and excessive members lead the shortage of food, so they must spend 1000 yuan every year for food supplies. The family net income from agricultural production is 1600 yuan, and that from breeding two pigs is 200 yuan. Beside of this, they have no other income. The family expenditure on production is 1240 yuan. The family expenditure on livelihood is rather immense (10000 yuan annual), including 2000 yuan spent on food, more than 3000 yuan spent on medical treatment for the two elder. Although the family is rather poor, they never neglect children’s education. The education fee is the hugest one in their expenditure3, including 3500 yuan spent on the oldest daughter and 600 yuan on the two daughters who are primary school pupils. The family is the typical absolute needy households along the line of GLR. There is no one durable consumable in the family. The average annual net income is only 80 yuan per capital and it is the lowest one in the sampled households of this basis investigation. The revenue cannot meet the expenditure. Family livelihood mainly depends on relief of government, help of kin, debit and credit. The family debt has exceeded 30000 yuan. The family has an old two-storied earth-wood structured house built in 1986, with a size of 180m2.

Investigation records in Jun 2007: Villager of Xinyang Group of Yangmei Village, Luoao Town, Yudu County. There are 6 members in her family: the father-in-law, three daughters and a son. The eldest 23-year-old daughter is a teacher of a kindergarten in Shenzhen, and sends money to home every festival. The second 18-year-old daughter is a second-year high school student in the forth high school of Yudu County. The third 15-year-old is a second-year junior high school student in Luoao middle school. The son is 9 years old and a third grade pupil in the village primary school. This family has only 3 mu of paddy field after land acquisition, and the agricultural income is about 1500 yuan per year. Moreover, this family feeds 4 hens and 13 ducks. Liu also does odd job occasionally besides farming. The former house is earth-wood structured in size of 120 m2, with other accidental 4-room house, including kitchen, sty and lavatory. Now this family has a two-storied brick-concrete structured house in size of 260 m2. They also get the fee for the transition 10 yuan/month/person.

3 The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 43 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Liu believed: it’s more convenient to come and go after the railway construction; the living standards and environments are also improved; the eldest daughter who does manual work outside could come back home usually. The unfavorable influence is that the house near the railway and the train noise is big. Furthermore, as the land acquisition, this family has less paddy field than before, and the agricultural income decreased severely which is the main source of family income.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 44 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

6.2.3 Huichang County

7) Xu Youfa: Investigation records in 2002: Male, aged 59, Han by ethnicity, villager of Laowu Group of Datian Village, Jiangxi Township. Family members: 8 in all: the wife, two sons and their wives, two granddaughters. The 10-year-old granddaughter is presently a primary school pupil and the other is two years old. The eldest son works at the County police station and his wife is a teacher of the Huichang Second middle school. The eldest son and his wife who live independent pay the parents’ estovers and some others. The second son and his wife do a manual job. Xu Yunfa manages a small grocer in his own house in which there is a public telephone and they mainly serve the villager. The family has 2.2 mu of cultivated land and 0.4 mu mountain forest. Food and vegetable are enough to eat and have a small surplus. Family income and expenditure: The gross income 9800 yuan (not including income of the eldest son’s family), including 2000 yuan from agricultural production, 1300 yuan from breeding, 1000 yuan from the grocer and 5500 yuan from the second son’s manual job. The family expenditure on production is 1660 yuan and that on livelihood is 4500 yuan, including 2500 yuan spent on food and 1000 yuan on clothing. Xu’s family is a typical household with an economic brain and good condition. The average net income is 1628 yuan a year per capital, so they have amassment of more than 3000 yuan every year. The family has a 13-room house in the size of 280m2, including 10-room brick-concrete structured house and 3-room earth-wood structured one. The land area of homesite is in size of 313m2. The house cost them about 60000 yuan, built in 1993. They have stuccoed the house if not knowing their house would be demolished. After the house demolition, they want to build a two-storied brick-concrete structured house. Xu said the position of the new house would decide if he continues deal in the grocer. Family durable consumable: a color TV, two black and white TVs, a telephone, a motorcycle, two bicycles and a sartorius.

Investigation records in Jun 2007: Villager of Datian Village, Xijiang Town, Huichang County. There are 7 members in this family: the couple, the second son and his wife, a 10-year-old granddaughter, a 7-year-old granddaughter and a 5-year-old grandson. The eldest son lives independently, so is not included. The daughter married and moved to Ruijin. The second son does manual work in Shishi city Fujian province, and the son’s wife works in a garment factory in Shishi city too. The grandson is in the village kindergarten. The former house was one-storied, brick-concrete structured and 200 m2. Now, they have a new two-storied brick-concrete structured house with a size of 180 m2. This new house is built on their own homesite (the grain land was taken up). The second son and his wife make money through doing manual work, and they send money to home every festival. This is the main source of family income about 2,000

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 45 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project yuan annually. Because of the busy work, they hardly come back home except spring festival. This family also feeds 5 or 6 chickens and ducks which are self-supplying. The archaeological teams who are municipal or provincial and would build the expressway hired the second floor of this family house two months and paid for 600 yuan. Xu considers: it’s more convenient to come and go than before the demolition of railway; the living standards and environments are also improved obviously; the son and daughter-in-law work outside home can often come back. But unfavorable effect is that this family has less paddy field than before as the land acquisition of railway, so the agricultural income decreased severely which was the main source of the family economic income.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 46 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

8) Xu Chengquan: Investigation records in 2002: Male, aged 67, Han by ethnicity, villager of Laowu Group of Datian Village, Jiangxi Township. Family members: 5 in all: Xu Chengquan knows the craft of weaving bamboo and he can weave some kinds of farming tool. His wife is easy to fall sick because of her weak body. The second 32-year-old son farms at home and does odd job (blowing Suona4) in slack farm season. The youngest son joined the army before graduating from technical secondary school and now he works at Huichang bus station. The youngest 18-year-old daughter does a manual job in Guangdong. She will go home in busy farm season, and she want to continue her study. The family has 4 mu cultivated land and 1 mu orchard, plant with peach and pear. Family income and expenditure: The annual net income from production is 14000 yuan, including 5200 yuan from agricultural production, 600 yuan from breeding, 300 yuan from the sale of bamboo dead stock and bamboo, 900 yuan from the second son’s blowing Suona, 6000 yuan from the youngest son’s laborage and 1000 yuan from the youngest daughter’s manual job. The family expenditure on production is 2900 yuan, including 1900 yuan spent on agricultural production, 500 yuan on breeding and 500 yuan on taxes and payments to collective units. The family expenditure on livelihood is 7640 yuan a year. The average net income is 2220 yuan annual per capital. They have amassment of more than 3000 yuan every year. The family has an old two-storied earth-wood structured house in a size of 240m2 and a new two-storied 1-room brick-concrete structured house in a size of 56m2. The old earth-wood structured house will be demolished. The family had a plan to build a new house before, so they give warm welcome to the house demolition of Ganzhou-Longyan railway. They want to build a two-storied 3-room brick-concrete structured house. Family durable consumable: a black and white TV, a telephone, a motorcycle and two bicycles. The family is among the upper-intermediate in the village in terms of economic conditions.

Investigation records in Jun 2007: Villager of Datian Village, Xijiang Town, Huichang County. Since the separation of sons and daughters, there is only the old couple in this family. The wife is 73 years old. The plot of this family is only about 0.7 mu, the grain yields from this plot is just enough to this old couple. He feeds more than 20 chickens which are self-supplying too. The former house with a size of 400 m2 was demolished and compensated for more than 60,000 yuan. Xu gave the money to three sons. This family also has the fee for the transition 10 yuan/month/person. The new 2-room house with a size of 240 m2 is one-storied and brick-concrete structured. The new house also was given to sons, but the old couple still lives in the remnant part of the former demolished house.

4 Suona is a kind of tradition musical instrument in Chinese. People will blow Suona at wedding and funeral in country. The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 47 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

9) Xu Liuliu: Investigation records in 2002: Male, aged 51, primary school education, villager of Xiaguangwan Group of Datian Village, Xijiang Town, Huichang County. This family has 6 members, including 3 laborers. The son does manual work in the local, and the others farm at home. There is 1.9 mu of cultivated land. The family annual gross income is about 6,000 yuan, including 1,200 yuan from planting and 5,000 yuan from other businesses. The annual expenditure on production is 1,000 yuan, including 800 yuan on agriculture and the tax 200 yuan. The family annual expenditure on livelihood is about 4,300 yuan, including 3,600 yuan on food, 300 yuan on clothing, 120 yuan on water electricity and gas, and 400 yuan on others. The house is earth-wood structured and brick-concrete structured, the construction area is 340 m2, and the homesite is 250 m2. The family durable consumables: a black-and-white TV, a telephone, a bicycle. The economic condition of this family is intermediate in the village.

Investigation records in Jun 2007: Villager of Datian Village, Xijiang Town, Huichang County. There are 6 members in this family, including his wife, a son and his wife, two grandsons. His wife is 52 years old, son is 27, daughter-in-law is 26, and all the family members do manual work in . The earth-wood structured part of the former house was 30 m2, and the brick-concrete structured part was about 70 m2. Now, this family has a two-storied brick-concrete structured house with a size of 120 m2. They have only 2 mu of paddy field and leased the field to others.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 48 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

10) Xu Xianqin: Investigation records in 2002: Male, junior high school education, villager of Xiaguangwan Group of Datian Village, Xijiang Town, Huichang County. This family is one of the impoverished in the village. There are 5 family members, including 3 laborers and 2 of them do manual work outside. This family also has 1.6 mu of cultivated land. The family annual gross income is about 7,000 yuan, of which the agricultural income is 1,000 yuan and the wage income is 6,000 yuan. The annual expenditure on production is 780 yuan, including 600 yuan on agriculture and the tax 180 yuan. This family also spends 4,900 yuan on the livelihood, including 300 yuan on food, 300 yuan on clothing, 100 yuan on water electricity and gas, 200 yuan on medical treatment and health care, 400 yuan on education, and 1,000 yuan on others. The house is earth-wood structured in a size of 340 m2, and the homesite is 200 m2. There is only a bicycle in this family.

Investigation records in Jun 2007: Villager of Datian Village, Xijiang Town, Huichang County. There 6 members in his family, including a son and his wife, two grandsons and a daughter. The son is 30 years old and his wife is 29 years old, they do manual work in Longyan city of Fujian province with monthly income about 2,000 yuan in total. The former house is earth-wood structured in a size of 50 m2. The compensation for the demolition of house was paid completely, and they also have the fee for transition 10 yuan/month/person. The new house is about 120 m2, one-storied and brick-concrete structured.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 49 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

11) Xu Jianfa: Investigation records in 2002: Male, aged 48, primary school education, villager of Xiaguangwan Group of Datian Village, Xijiang Town, Huichang County. There are 5 family members in all, including 4 laborers of which 2 do manual work outside. This family also has 2.3 mu of cultivated land. The family annual gross income is about 10,000 yuan, of which the agricultural income is 2,000 yuan and the wage income is 8,000 yuan. The annual expenditure on production is 1,200 yuan, including 900 yuan on agriculture and the tax 300 yuan. This family also spends about 8,100 yuan on the livelihood, including 4,000 yuan on food, 500 yuan on clothing, 500 yuan on water electricity and gas, 100 yuan on medical treatment and health care, 100 yuan on vehicle and communication, 2,500 yuan on education, and 400 yuan on others. The house is earth-wood structured in a size of 250 m2, and homesite is 250 m2. The family durable consumables: a color TV, a telephone, a bicycle.

Investigation records in Jun 2007: Villager of Datian Village, Xijiang Town, Huichang County. There are 5 members in his family, including the wife, a son and his wife, a grandson. The wife is 45 years old, the son and his wife are 23, and the grandson is 6. Xu is a mason in the village. The son and his wife work in a garment factory in Shishi city of Fujian province. One part of the former house is brick-concrete structured, and the construction area of which part was about 200 m2. Another part of the former house is two-storied and earth-wood structured, and the construction area of which part was about 200 m2. This family also has the fee for transition 10 yuan/month/person. They had spent over 40,000 yuan to build a new two-storied house whose construction area is over 270 m2.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 50 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project 6.2.4 Ruijin City

12) Yang Ruisheng: Investigation records in 2002: Male, aged 48, junior high school education, villager of Xiewu Group of Nangang Village, Xianghu Town, Ruijin City. There are 5 family members in all, including 4 laborers, of which 2 do manual work outside and the rest farm at home. This family has 3.5 mu of cultivated land, 0.5 mu of orchard, 0.4 mu of fish pond, 12 poultry, and 2 heads of pig. The annual gross income is about 9,900 yuan, of which the farming income is 2,100 yuan, breeding income is 1,800, and the wage income is 6,000 yuan. The annual expenditure on production is 2,550 yuan, including 700 yuan on planting, 1,300 yuan on breeding and the tax 550 yuan. This family also spends 6,580 yuan on livelihood, including 3,000 yuan on food, 950 yuan on clothing, 480 yuan on water electricity and gas, 750 yuan on medical treatment and health care, 400 yuan on vehicle, and 1,000 yuan on others. The house is earth-wood structured in a size of 130 m2, and the homesite is 65 m2. The family durable consumables: a color TV, a telephone.

Investigation records in Jun 2007: Villager of Nangang Village of Xianghu Town in Ruijin City. There are 5 members in his family, including the mother, the wife, the son and his wife. Yang’s mother is 78 years old. Yang’s wife, Gao Julan, is 48 years old. The 25-year-old son does manual work in Nan city of Fujian province, comes back home one time every year, and earns about 1500 yuan monthly. The daughter-in-law also does manual work outside usually, but this year she stays at home because of pregnancy. This family has 1.9 mu of paddy field and about 6 mu of woodland. Yang and his wife do farming at home usually and the grain is self-supplying. The main source of family income is the wages of the son and his wife. The former house was two-storied, earth-wood structured, and the construction area was 112.75 m2. The new house is two-storied, brick-concrete structured, and the construction area is about 190 m2. As the resettlement, this family rented a house as the habitation since the year 2,000. The transition fee is given to this family 40 yuan/person. Yang thinks that the inhabitancy conditions are improved obviously, the sanitation and ventilation are also better than before. But it’s a little far to the family cultivated land for farming.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 51 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

13) Xie Shengbing: Investigation records in 2002: Male, aged 50, high school education, villager of Xiewu Group of Nangang Village, Xianghu Town, Ruijin City. There are 19 family members in all, including 11 laborers, of which 6 persons farm at home, 3 persons do manual work outside, and 2 persons engage in non-agricultural work. This family has 6 mu of cultivated land and 5 mu of fish pond. The family annual gross income is about 40,000 yuan, including 5,000 yuan from planting, 5,000 yuan from breeding, and 30,000 yuan from others. The annual expenditure on production is 2,500 yuan in all, including 2,000 yuan on agriculture and the tax 500 yuan. This family also spends 29,600 yuan on livelihood, including 10,000 yuan on food, 3,000 yuan on clothing, 1,200 yuan on water electricity and gas, 1,000 yuan on medical treatment and health care, 10,000 yuan on vehicle and communication and 4,400 yuan on education. The house is brick-concrete and earth-wood structured in a size of 600 m2, and the homesite is 500 m2. Besides, this family has two trucks, 6 color TVs, 2 washers, 9 telephones, 5 motorcycles, and 7 bicycles.

Investigation records in Jun 2007: Villager of Xiewu Group of Nangang Village, Xianghu Town, Ruijin City. There are 4 members in his family, including the wife, the son and his wife. The 24-year-old son does manual work in Amoy, comes back home one time every year, and earns 1100 yuan per month. The 23-year-old daughter-in-law is out of work and stays at home. This family only has 0.2 mu of paddy field and 0.5 mu of woodland. The former house was earth-wood structured, and the construction area was about 300 m2. It was divided into 4 parts, three of them were given to the three older sons, and the elders live with their youngest son and they got the residual part of house. This former house was compensated for 140 yuan/m2, and the money was paid up already. The transition fee also is given for this family 10 yuan/month/person. The new house built in 2005 is two-storied, brick-concrete structured, and the construction area is 90 m2. During the railway demolition and resettlement, they rented a house outside near 2 years, got the transition fee 40 yuan (10 yuan/person * 4 monty) and removing fee 100 yuan. The son’s wage is a part of the family income, besides, Xie is the village group leader and could get some small projects with annual income 20,000 to 30,000 yuan. Xie said the ways lead to paddy field and woodland are less convenient than before. Moreover, there is no water source.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 52 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

6.2.5 Changting County

14) Chen Lianxing: Investigation records in 2002: Male, aged 51, Han by ethnicity, villager of Liangkeng Village of Gucheng Township, Changting County. Chen has three sons. The oldest two married sons living independent and they look after their father in every way. Now Chen lives with the youngest unmarried son. The youngest son does manual work in a costume factory in Amoy and he can pay for his own life. The family has 1.25 mu of cultivated land and vegetable land. They hire out all of their land to others and earn some food and vegetables as rent. Changting County teems with bamboo. Almost every family has bamboo grove, so bamboo is an important source of money towards many family. Chen can gain 8000kg zhuma (a good material of paper) from bamboo, with income of 2000 yuan. The family annual gross income from production is 4075 yuan. The family expenditure on production is 1100 yuan and that on livelihood is 2420 yuan. The family income and expenses are in the balance. The residential condition is poor with the family. It has an old two-storied earth-wood structured house of 56m2. Chen is very support the building of Ganzhou-Longyan railway. Knowing railway will start working in 1 April and demolished their house, the family moved to kin’s house initiatively ten days before. He feels, with the railway, it is convenience for the son to go out for manual job, and carriage of zhuma will fall. The family has no money to build a new house before. After gain the compensation, he will realized the dream of building new house. He plans to build brick-wood structured house.

Investigation records in Jun 2007: Villager of Group 3 of Liangkang Village, Gucheng Town, Changting County. There are 7 members in his family, including the wife, the parents, the eldest son and his wife, the grandson, the young son. The Chen’s wife is 43 years old, and farms with him at home. The father is 84, the mother is 75. The eldest son and his wife work in the Industrial Park of the county with monthly income over 1,000 yuan respectively. The young son is 20 years old and does manual work in Amoy. The grandson is 2 years old. This family has only 0.5 mu of paddy field now. Chen is the contractor of 20 mu of mountain, and he also rents 2 mu of other people’s field in return for 100 kg grain. He grows the bamboos at the contracted mountain, and the bamboos can be processed into many kinds of products. This village income is largely from the sale of bamboo products. So the local cultivation of bamboo is in the large-scale. After the railway built, the price of bamboo products increased; therefore, the local economy is promoted by the high value-added bamboo products very much. The demolished house was two-storied and earth-wood structured, and the construction area was 141 m2. Now, this family has a new two-storied brick-concrete structured house, and the construction area is 140 m2. In addition, this new house was built in 2002. During the housing demolition and resettlement, they rented a house six months. The transition

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 53 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

fee was also paid for this family 3 yuan/m2. This family was compensated for over 23,000 yuan in total. The family durable consumables: a TV, an electric fan, a VCD, a motorcycle. This family is intermediate in the group in terms of the living standards. It’s more convenient to work outside after the railway built. The living condition is better, and the inhabitancy conditions are improved obviously. However, this family is still in debt as building the new house.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 54 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

15) Zeng Jixian: Investigation records in 2002: Male, aged 54, primary school education, villager of Group 7 of Liangkang Village, Gucheng Town, Changting County. This family is one of the impoverished in the village. There are 4 family members in all, including 3 laborers, of which 1 person farms at home, 1 person engages in non-agricultural work, 1 person does manual work outside. This family has 1.7 mu of cultivated land, 0.15 mu of orchard. The family annual gross income is 5,050 yuan, including 900 yuan from planting, 700 yuan from breeding, and 3,450 yuan from others. The annual expenditure on production is 1,450 yuan, including 250 yuan on planting, 600 yuan on breeding, the tax 200 yuan, and 400 yuan on others. This family also spends 2,850 yuan on livelihood, including 600 yuan on food, 300 yuan on clothing, 150 yuan on water electricity and gas, 200 yuan on medical treatment and health care, 100 yuan on vehicle and communication, 300 yuan on education, and 600 yuan on others. The house is earth-wood structured in a size of 160 m2, and the homesite is 200 m2. This family has a black-and-white TV, and a bicycle.

Investigation records in Jun 2007: Villager of Group 7 of Liangkang Village, Gucheng Town, Changting County, Longyan City. There 4 members in his family, including the wife, the son and daughter. The wife is 58 years old and farms at home. The 24-year-old son does manual work in industrial park of the county and earns over 1,000 yuan per month. The 17-year-old daughter just started to do manual work in Guangdong since this year, earns about 700 yuan monthly. This family only has 0.5 mu of paddy field after the land acquisition. They also contract over 20 mu of mountain for cultivating bamboo, and the annual income from the bamboo is over 10,000 yuan. The former house was earth-wood structured, and the construction area was over 100 m2. This family compensated for 20,000 yuan in total, and the money had been paid completely. They didn’t build a new house, but bought a secondhand house in the village. The secondhand house nears road, so it’s very convenient. Moreover, it’s very cheap and has complete procedures. Zeng showed investigators of external monitoring agency the title deed, the collective land use warrant, and the approved of the building. This house is also earth-wood structured, the homesite is 246 m2, and the construction area is 160 m2. It’s convenient to transport the bamboos after the railway built, and the price of bamboo increases continually, so the villages benefited. Zeng’s family is intermediate in the group in the living conditions. There are some household appliances in this family, such as a color TV, a VCD.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 55 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

6.2.6 Liancheng County

16) Yang Dezhang Investigation records in 2002: Male, aged 45, junior high school education, villager of Liangzeng Village, Pengkou Town, Liancheng County. There are 4 family members, including the wife and two sons. This family has 0.9 mu of cultivated land (paddy field). There is an earth-wood structured house with a size of 120 m2 formerly. The main source of family income: annual wage income 2,000 yuan, annual farming income 1,200 yuan.

Investigation records in Jun 2007: Villager of Xiapinger Group of Liangzeng Village, Pengkou Town, Liancheng County, Longyan City. There are 4 members in his family, including the wife, two sons. The wife is 43 years old and farms at home. The eldest son is 22 years old, the second son is 20 years old, and they are all do manual work in Amoy and earn more than 1,000 yuan monthly. The two sons come back home only once every year. Yang has a store in the village with monthly income 300 yuan. There is 2 mu of paddy field, and the annual agricultural income is more than 2,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was 125 m2. This family was compensated more than 20,000 yuan for the house demolition. Now, they have a new brick-concrete structured house whose construction area is 110 m2. Moreover, the first floor of the new house had been built, but the second floor isn’t built yet. The transition fee for this family was paid by the Railway Office. And they rented a house for transition near 3 months. The family durable consumables: a TV, electric fans, a motorcycle. The living conditions are improved after the railway built. The son can go to do manual work outside. They are satisfied with the resettlement.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 56 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

6.2.7 Xingluo District

17) Wu Haojin Investigation records in 2002: Male, aged 52, Han by ethnicity, villager of Xiyang Village of Dachi Township, Xinluo District. Family members: 4 in all: the wife and two children. The 25-year-old son graduated from junior college began to work in Longyan engineering machine factory two years ago. The 21-year-old daughter, graduated from occupation school, works in a hotel in Amoy. Wu is good at farming and he knows several crafts such as brickie, woodworker and locksmith. Wu has been a fiend at breeding pig. He will breed pig again when the price of pig rising. The family has 12.5 mu of cultivated land, 9 mu of mountain forest and 3 mu of orchard. Several kinds of fruit planted in their orchard, such as pear, orange, persimmon, chestnut and peach. 3.5 mu cultivated land plant by other people and the rest by themselves. They plant 3 mu of cropland and 6 mu of peanut land. The income from peanut land is 1000 yuan annually. Without planting vegetable, they must buy it in market. The family annual income is 23200 yuan, including 2400 yuan from grain, 6000 yuan from cash crop and orchard, 14800 yuan from manual job. The family expenditure on production is 4300 yuan and that on livelihood is 17000 yuan. The family has debt of 40000 yuan because children’s education fee is huge for them before. Wu feels he repay the debt is no problem. The family has an old two-storied earth-wood structured house in size of 200m2, with other accidental house. Family durable consumables: a color TV, a telephone and a motorcycle. The family is a typical household of transforming from dress warmly and ear one's fill to slight wealth along the line.

Investigation records in Jun 2007: Villager of Xiyang Village, Dachi Town, Xinluo Borough. There are 5 family members, including the mother, the wife, a son and his wife. The mother is 85 years old. The wife is 52 years old, does housework and farms at home. The 30-year-old son enrolled Henan Nanyang Weapons College to study machinery manufacturing in 1995, was assigned to Lung Group after graduating in 1999, and becomes a skilled worker with monthly income 2,000-3000 yuan. The daughter-in-law is a worker of Lung Group, and earns over 1,000 yuan monthly. Furthermore, the son had bought a set of house in the city, and the construction area is over 100 m2. This family has 10 mu lands, of which 9 mu of paddy field plants double-crop rice, and the rest 1 mu of paddy field has been changed to the dry land with compensated 200-300 yuan. The agricultural costs increased, each mu field of employment is 140 yuan/person, and planting seedlings is 70 yuan/person/mu. The requisitioned land of this family was 1 mu, and the compensation was over 8,000 yuan. According to the regulations, the village committee took 20% of the compensation fee as a public welfare fund for the village road and water supply projects. The village was requisitioned 10 mu land in total, including the village’s old warehouse. This family’s house isn’t demolished, and which is earth-wood structured. The construction area is 180 m2, and the homesite The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 57 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project area is 360 m2. Furthermore, this house was built in 1980. As the railway is near, the noise and vibration are big.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 58 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

18) Wu Liping Investigation records in 2002: Male, aged 31, Han by ethnicity, party secretary of Xiyang Village of Dachi Township, Xinluo District. Wu live with his parents. Wu manages an agricultural production material store in which sale chemical fertilizer, pesticide and seed etc. The family has 12 mu of cultivated land, 9 mu of mountain forest, 10 mu of orchard and 0.8 mu fishpond. In addition, they contract in 6 mu of mountain forest. The output of 3.5 mu cropland is 2000kg every year. The other 8 mu cultivated land grown with cash crops such as peanut and ginger. Wu is very clever so the source of his family income is many. The family annual gross income is 47200 yuan, including 2000 yuan from grain, 5000 yuan from peanut, 6000 yuan from ginger, 5000 yuan from orchard, 25000 yuan from agricultural production material store, 3000 yuan from process bamboo mat and 100 yuan from the allowance for village cadre. The family expenditure on production is 8400 yuan and that on livelihood is 12100 yuan. The family is a typical household of wealth along the line. They enjoy a good economic condition. The annual average net income is 12933.3 yuan per capital and they have 30000 yuan saving every year. Engle index is 0.29, so the family is among the top in the village in terms of economic condition. The residential condition is well. It has a two-storied brick-wood structured house in size of 400m2, with other accidental house such as kitchen and washroom. Houses of him and his brother can make up of an absolute big courtyard. Family durable consumables: a color TV, a telephone, a washing machine and a motorcycle.

Investigation records in Jun 2007: Male, Party Branch Secretary of Xiyang Village, Dachi Town, Xinluo borough. There are 4 family members, including the father, the wife, and a daughter. The father is over 70 years old and skillful in farming. The 29-year-old wife helps his husband at whose agricultural supply store. The daughter is only 1 years old. This family has 10 mu lands. As Wu has an agricultural supply store, large-scale, the annual income is considerable, about 40,000-50,000 yuan. Because the village hasn’t income, the cadres almost haven’t wages, his family’s income mainly depend on the store. The house is brick-tile structured, and the construction area is over 200 m2.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 59 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

19) Wu Xincai Investigation records in 2002: Male, aged 52, high school education, villager of Xiyang Village, Dachi Town, Xinluo borough. There are 5 family members, including 3 laborers, of which 2 farm at home. This family has 5 mu of cultivated land, 7 mu of mountain forest. The family annual gross income is 18,000 yuan, of which the agricultural income is 3,000 yuan and the other income is 12,000 yuan. The expenditure on production is about 2,000 yuan, including agricultural expenditure 1,500 yuan, and the tax 500 yuan. This family also spends 26,000 yuan on livelihood, including 4,000 yuan on food, 20,000 yuan on cultural entertainment. The house is earth-wood structured in a size of 200 m2, and the homesite is 260 m2. This family has a color TV, a washer, a telephone, a motorcycle, and a sartorius.

Investigation records in Jun 2007: Villager of Xiyang Village, Dachi Town, Xinluo Borough. There are 8 family members, including the wife, the eldest son and his wife, a granddaughter, the second son, and a daughter. The 53-year-old wife farms at home. The eldest son works in the town government, the daughter-in-law works in the city WCB, and their daughter is 2 years old. The second son is 26 years old, works in the City Material Bureau. The daughter is 24 years old, works in Longyan Medicine Company. This family has about 7 mu land, and the railway requisitioned 1 mu. This family’s house is earth-wood structured, of which the homesite is allocated uniformly, and the construction area is over 200 m2.

A General Analysis of the Affected People

The per capita net income is yielded by dividing the net income with the number of people, and the net income is the amount that remains after the cost of agricultural production and that of non-agricultural production is deducted from the gross income of both agricultural and non-agricultural productions. The per capita net income is an important index reflecting the actual living standard of farmers.

As is indicated by the data collected by the external resettlement monitoring agency through its field survey for post-resettlement evaluation conducted on the affected households, the per capita net income entered the fast-growing period more than five years later. The income concentration point has been moving toward and clustering in the high-level range. In 2001, for all the areas along the whole Ganzhou-Longyan railway line, the households whose per capita net incomes fell below 1,120 yuan/person accounted for 11.7%, and those whose per capita net incomes fell in the range of 1,120-4,000 yuan/person accounted for 46%, while those whose per capita net incomes were above 4,000 yuan/person only accounted for 6%. However, in the year 2007, the households whose per capita net incomes fell below 1,120 yuan/person

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 60 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project only accounted for 1.9%; those whose per capita net incomes fell in the range of 1,120-4,000 yuan/person accounted for 34.3%, and those whose per capita net incomes were over 4,000 yuan/person accounted for 60%. The passage of time has witnessed a 4,440-yuan increase of per capita net income. The per capita net incomes of the affected people of both Ganzhou and Longyan cities also registered an increase by a large margin. Please refer to table 7 for detailed information.

Table 7 An Analytical Table of the Per Capita Net Incomes of the People Affected by Ganzhou-Longyan Railway Project All the Areas along the Longyan City Ganzhou City Annual Per Capita Whole Railway Line Net Income Classified Classified Classified Classified Classified Classified (yuan) Proportion for Proportion Proportion Proportion for Proportion for Proportion for 2001 for 2007 for2001 2007 2001 2007 ≤635 3.05 0.0 19.35 3.4 11.71 1.9 635-1120 15.24 4.3 51.61 3.4 34.57 3.8 1120-1600 26.22 4.3 21.51 3.4 23.71 3.8 1600-2500 28.66 8.7 6.45 6.9 16.86 7.7 2500-4000 14.02 13.0 1.08 24.1 7.14 19.2 >4000 12.80 69.6 0.00 58.6 6.00 63.5 Average 2345yuan 7379yuan 1015yuan 5638yuan 1638yuan 6048yuan

6.3 Evaluation of the Income and Livelihood-Earning Ability of the Affected People In general, the income and livelihood-earning ability of the affected people can ensure the recovery and even betterment of their living standard. The reasons are as follows:

„ The departments in charge of the land acquisition, demolition, relocation and resettlement for Ganzhou-Longyan Railway Project formulated resettlement plans that are in conformity with the relevant laws and regulations of the People’s Republic of China. And the local governments at all levels along the Ganzhou-Longyan Railway line adopted appropriate policies for land acquisition compensation and demolition compensation, and allocated the compensation in time.

„ As most of the affected people were resettled through land redistribution, they can go on their familiar modes of life and production with their original means of livelihood.

„ The land acquisition, demolition and relocation did not have much impact on the cash-earning modes (working as migrant workers) of the rural residents. Though the survey did reveal that some farmers complained about their The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 61 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project decrease of income from their land due to the decrease of their cultivated land in area, their total family income increased thanks to the increase of the income from their part-time jobs.

„ The resettlement departments adopted active supporting measures to aid the vulnerable groups.

„ The operation of Ganzhou-Longyan Railway improved the overall traffic conditions, which in turn promoted the industrial development along the railway line and created more job opportunities. In addition, the relevant departments at all levels offered training to the affected people. All those factors contributed to the income recovery of the affected people.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 62 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

7. The Relocation and Reconstruction of Buildings

7.1. The Purchasing Right of the Rebuilt Houses, Enterprises, Schools

and Other Buildings;

In the process of land acquisition, demolition and relocation associated with Ganzhou-Longyan Railway Project, the property rights of the affected people to their buildings were acknowledged, and the affected people were therefore compensated according to their property rights. Whether resettled concentratedly or scatteredly, all the affected rural and urban residents got their house sites and built their new houses with the compensation legally received. Generally, the relocated people can reuse free of charge the building materials removed from their old houses to make up for the deficiency of building materials for their new houses. The rural residents received their land certificates while the urban residents received their certificates of property rights (In September 2006, the ADB inspection group found in Changting that the households in Luofang Village had not received their property ownership certificates. And during its post-resettlement evaluation monitoring investigation, the external monitoring agency followed up the matter and found that the households in Luofang Village had received their property ownership certificates by then, to the support of which the resettlement department offered the photocopies of the property ownership certificates of 3 households. However, the external monitoring agency did find that some households in Pingpu Village of Jiaoyang Township of Shanghang County had not yet received their property ownership certificates. To solve the problem, the resettlement department promised to get all the property ownership certificates for those households within one month.) in proof of the validity of their ownership; besides the house compensation received legally, the affected enterprises, stores and schools also received the land to build their new factories, stores and campuses with the help from the resettlement departments.

7.2. Measures Helping the Relocatees Move to Their Resettlement

Quarters and Rebuild Their New Homes

7.2.1. Helping Measures for the Transitional Housing Period

The resettlement departments offered assistance to all the relocatees. All the resettlement policies formulated by the relevant counties and districts of Ganzhou City and Longyan City affected by the construction of Ganzhou-Longyan Railway

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 63 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project covered the compensation for the affected people for their transitional housing period. Because of the tight schedule of railway construction, some affected people had to move out of their old houses before their new houses are completed. During this transitional time from moving out of their old houses to the completion of their new houses, the affected people may move into the transitional buildings built by themselves, or turn to their relatives or neighbors for accommodation, or live in rented houses. The expenses on those transitional housing were compensated by the subsidy from the departments of resettlement. In most cases, the subsidies were sufficient to cover the expenses.

At the same time, the planning and construction of all the concentrated resettlement quarters (see Annex1) was coordinated in a unified way by the resettlement departments. Specifically, the resettlement departments coordinated “three connections and one leveling” (power supply, water supply, access roads, and leveling of construction sites) or “five connections and one leveling” (power supply, water supply, access roads, television cable, Internet connection, and ground leveling). And the fund for the construction work was raised by the resettlement departments. The affected people received subsidy for moving from their transitional houses into their new houses. All the concentrated resettlement quarters, which were visited by the investigators of the external monitoring agency, completed the above-mentioned construction tasks, and all the affected people were satisfied with the resettlement work.

7.2.2. Special Measures Aiming at Helping the Vulnerable Groups Rebuild New Homes and Some Relevant Cases

Please refer to section6.1 of this report.

7.2.3. Reemployment of Staff Members and Workers of the Affected Enterprises and Stores after the Reconstruction

All the enterprises demolished and relocated for the construction of Ganzhou-Longyan Railway have been rebuilt and the affected people have received their compensation. The standard of compensation has been set according to the market valuation. All the affected enterprises have received compensation for shutdown during their moving and transitional periods. All affected counties except Liancheng County and Shanghang County in Longyan City had demolished and relocated enterprises. Two typical examples are Yudu County in Ganzhou and Xinluo District in Longyan, where the scale of demolition and relocation ranged between 5000-7000m2. The regular employees of the affected enterprises who were skilled workers familiar with the production processes received their basic salary during the shutdown period, and went back to their original positions after their new factories had been completed.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 64 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project 7.2.4. Evaluation of Relocation and Reconstruction of Buildings

Thanks to the building of new houses, the people affected by the Ganzhou-Longyan Railway Project are enjoying good housing conditions. Altogether 2,413 households, amounting to 12,899 people built their new houses because of demolition and relocation. The newly built houses are of the best qualities among the local rural houses. Most of them are brick-concrete buildings of two or more storeys that are of better quality and environment than the original buildings. Most of the affected people, except a few who have more than one residence or choose to live elsewhere (such as towns or other cities), have moved into their new houses in the concentrated or scattered resettlement sites with satisfaction.

8. Rebuilding of Infrastructure

8.1. Recovery of Transportation Facilities

The transportation facilities affected by the construction of Ganzhou-Longyan Railway have been recovered by the relevant railway design departments and railway construction departments in time. At the same time, in view of the urban planning, railway safety and villagers’ requests, many flyovers, culverts, passages for pedestrians, such as Yanshi flyover, Shibu flyover, the extension of Longmen Bridge, traffic culverts along the railway line have been built. All those infrastructure not only recovered the original capacity of transportation but also helped to speed up the construction of central cities and the urbanization of rural areas. At the same time, the elimination of road crossings has greatly strengthened the safety of railway.

8.2. Recovery of the Water System

The resettlement departments of Ganzhou-Longyan Railway Project has been sticking to the principle that both the inlets and outlets of the irrigation and flood discharge culverts should be connected with ditches, and that the toe walls or draining ditches (The ditches should be connected with each other.) should be built in the sections where the railway line fill passes paddy fields. The railway construction headquarters that represents the interests of the owner worked together with the relevant departments of local governments and the representatives of villagers and jointly solved over 1000 problems raised by the local affected people. The solutions to those problems not only recovered the original water system, but also raised standard of water system and won favorable comments from the local affected people.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 65 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

8.3. Recovery of Power, Communication, Telephone, Television and

Other Facilities

The loan borrower of Ganzhou-Longyan Railway Project has recovered the power\communication\telephone\television and other facilities in the principle that “all the affected infrastructure must be recovered.” As a result, no complaints about the recovery of the affected infrastructure were heard by the external resettlement monitoring agency during their field investigation and evaluation.

8.4. The Remaining Problems and Pending Work

Two remaining problems mentioned by the officer in charge of land acquisition, demolition and relocation at the railway construction supporting office of Longyan City in his summary of the experience and lessons about the resettlement work are as follows:

1) There exists in a few places the hidden trouble of soil and water loss due to incomplete engineering treatment;

2) No organization has been designated to be responsible for the future maintenance and management of the temporary bridges for construction that are transferred to the local people at their request.

9. Resettlement Budgeting and Financing

9.1. Cost of Resettlement and Cash Flow

According to the data provided by the headquarters of Ganzhou-Longyan railway construction, the owner who is the borrower of the loan has supplied a total compensation of 311.58273 million yuan, of which 114.690637 million yuan was used for land acquisition, 128.799295 million yuan was used for demolition and relocation and the related compensation, the rest of the compensation, which is 68.092798 million yuan, was used for the recovery of roads, water system, power lines, communication lines and other infrastructure and as the compensation for land acquired for temporary use. For detailed information, please see table7.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 66 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Table7. Table of Compensations Paid by the Owner of the Project for Land Acquisition, Demolition and Relocation for Ganzhou-Longyan Railway Project

Longyan Ganzhou Section Type of Compensation Unit Section in Total in Jiangxi Fujian 10 Compensation for Land thousand 5720.2673 5748.8 11469.0637 Acquisition yuan 10 Compensation for thousand 8742.0595 4137.87 12879.9295 Demolition and Relocation yuan Transportation, Water Conservancy, 10 Telecommunication, thousand 3725.0198 3084.26 6809.798 Power, and Land for yuan Temporary Use 10 Total thousand 18187.343 12970.93 31158.273 yuan Notes: Three paying channels of compensation for land acquisition, demolition and relocation for Jiangxi section are as follows: 1. The Ganzhou-Longyan Railway Construction Headquarters of Nanchang Railway Administration allocated 1268.822256 million yuan to the Railway Construction Supporting Office of Ganzhou City, which then relayed the sum to the railway supporting offices at county/city level. 2. The Ganzhou-Longyan Railway Construction Headquarters of Nanchang Railway Administration allocated 1610.112 thousand yuan directly to the affected counties\cities. 3. The Ganzhou-Longyan Railway Construction Headquarters of Nanchang Railway Administration allocated 899.709 thousand yuan directly to other organizations, such as enterprises and schools, etc.

9.2. Sources of All the Funds for Land Acquisition and Resettlement and

the Releasing Time of the Fund Statement

9.2.1. Sources of Funds Ganzhou City

The Key Project Office of Ganzhou City (formerly the Office of Steering Group for

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 67 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Supporting Ganzhou-Longyan Railway Construction) provided the table showing the flows of the compensation fund of 126.88 million yuan by June 30, 2007 allocated by Ganzhou-Longyan Railway Construction Headquarters of Nanchang Railway Administration. For detailed information, please see table 8-9.

„ Funds allocated to the railway construction supporting offices of the affected counties and cities

Table 8 The Cash Flows of the Compensation for Land Acquisition, Demolition and Relocation for Ganzhou Section

County\City 2002 2004 2004 2005 Total

Ganxian County 1458 340 199.8 7.7 2005.28

Yudu County 4219 245 154.46 15 4633.46

Huichang County 2008 110 111.57 7 2236.57

Ruijin County 2431 200 137.16 30 2798.16

Total 10116 895 602.77 59.7 11573.47

„ Planning funds allocated to land administration bureaus and other functional departments at provincial, municipal and county levels

Table 9. Cash Flows of Compensation for Land Acquisition, Demolition and Relocation for Ganzhou Section of Ganzhou-Longyan Railway (continued)

Description of Jiangxi Ganzhou Ganxian Yudu Huichang Ruijin Total Fees Province City County County County County

Land 25.61 10 3.02 7.49 3.47 5.02 54.61 Administration

Land 0 0 39.22 143.14 43.66 137.13 363.15

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 68 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Reclamation

Recovery of Forest 83.96 0 0 0 0 0 83.96 Vegetation

Land Survey 0 15.33 0 0 0 0 15.33

Planning and 0 12 0 0 0 0 12 Investigation

Total 109.57 37.33 42.24 150.63 142.15 47.13 529.05

„ Other expenses a. 100,000 yuan for roads recovery at the East Ganzhou Railway Station; b. 100,000 yuan as compensation for the impact on Shahe Park; c. 4,657,000 yuan as overhead expenses for Ganzhou Railway Construction Supporting Offices.

Longyan City

The Coordinating Headquarters of Ganzhou-Longyan Railway of Longyan City has provided the data up to October 10th, 2006, showing how the compensation of 313.79309195 million yuan for land acquisition, demolition, relocation and resettlement for the construction of Ganzhou-Longyan Railway was used. Included in the compensation is 129.7093 million yuan provided by Ganzhou-Longyan Railway Construction Headquarters in accordance with the agreement between the ministry (the Ministry of Railways, which is the owner of the project) and the province (Fujian Province). The remaining sum, 184.08379195 million yuan, was contributed by Fujian Provincial Government (150 million yuan), the Longyan Municipal Government and the financial departments of related counties. For detailed information about the uses of the fund, please refer to table 10-11.

Table 10. The Cash Flows of the Compensation for Land Acquisition, Demolition and Relocation for Longyan Section of Ganzhou-Longyan Railway

Unit (10 K’s: Xinluo Shanghang Liancheng Changting Shanghai Types of Payment ten thousand Total District County County County Headquarters yuan)

Compensation for 10 K’s 4373.9822 1632.9316 2705.1922 5841.5478 0 14553.654 The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 69 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Acquisition and 19 34 6 87 Relocation inside the Red

Line

Compensation for 10 K’s 1040.2907 386.77709 808.02005 1010.4474 0 3245.535314 Acquisition and 34 4 Relocation outside the red

line

Land Application Fee 10 K’s 3334 0 13 Subsidy for Transitional 10 K’s 34.4544 13.3371 10.1434 87.4604 0 145.3953 Housing

Solatium for Relocatees 10 K’s 7.366 5.85 5.549 289.3368 0 308.1018 Resettlement Subsidy 10 K’s 269.96997000 0269.96997 Resettlement Bonus 10 K’s 11.9529 11.46195 12.582 17.4499 0 53.44675 Bonus for People 10 K’s 83.8132 35.2308 39.44858 189.1084 0 347.60098 Affected by Acquisition

and

Relocation

Relief Subsidy for 10 K’s 20 35 20 45 0 120 Typhoon-Stricken

Resettlement Quarters

Prepaid Compensation 10 K’s 2003 16 33 32 340 2424 for Acquisition and

Relocation

Fee for Auxiliary Projects 10 K’s 20 16.3 15 689.9758 0 739.2758 Total 10 K’s 7867.8294 2155.8885 3651.9352 8204.3266 340 22219.97991 23 74 9 27

Table11. The Cash Flows of the Compensation for Land Acquisition, Demolition and Relocation for Longyan Section of Ganzhou-Longyan Railway(continued)

Unit (10 K’s: ten Types of Payment Organizations Amount Subtotal thousand yuan) Longyan Land Land Use Right 10 K’s Administration 250.1524 250.1524 Leasing Fees Bureau Fujian Forestry 10 K’s 198.7409 448.8933 Compensation for Bureau Acquisition of Longyan Xingsheng Forest Land 10 K’s Forestry Technical 6 454.8933 Consultation

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 70 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Company Longyan Real 10 K’s 760.327647 1215.220947 Balance of Estate Affairs Office Construction Land Longyan Municipal and Compensation Land 10 K’s 130.62225 1345.843197 of Cultivated Land Administration Bureau Cost for Construction of Nanchang Railway 10 K’s 1603.15 2948.993197 Buildings in West Headquarters Passenger Station Longyan Municipal Auxiliary Projects 10 K’s Urban Investment 3565.010966 6514.004163 Company Cost for Relocation Longyan Municipal of Civil Defense 10 K’s Civil Defense 26.26 6540.264163 Facilities Office Local Taxation Design Cost of 10 K’s Bureau of Xinluo 0.28 6540.544163 Station Buildings District Mobile Construction Cost Telecommunication 10 K’s 3.8787 6544.422863 of Internet Company of Longyan City County-level Coach Stations for Longyan Railway Shanghang, 10 K’s 33.5557 6577.978563 Company Limited Liancheng, Changting Cost of Installation of Water Supply Longyan Railway 10 K’s 2.4649 6580.443463 System for Station Company Limited Buildings Land Acquisition Longyan Railway Fund for Station 10 K’s 51.271022 6631.714485 Company Limited Buildings Longyan Working Fund for Preparatory Office Acquisition and 10 K’s 75 6706.714485 of Railway Relocation Construction Longyan Electric Electric Power Pipe 10 K’s Power Survey and 5.5688 6712.283285 Network Design Institute

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 71 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Longyan Yili Electric Power 10 K’s 45.270976 6757.554261 Engineering Company Limited Longyan Qianqiu 10 K’s Electric Power 48.9615 6806.515761 Company Limited Longyan Panning 10 K’s 0.43 6806.945761 Consultation Center Geological Brigade 10 K’s 295 of Fujian 0.33 6807.275761 Province Longyan Municipal 10 K’s 1.2431 688.518861 Survey Brigade Longyan Railway 10 K’s 800 7608.518861 Construction of Company Limited Passenger Station Longyan Urban and 10 K’s Rural Planning 0.47683 7608.995691 Bureau No. 8 Geological 10 K’s Brigade of Fujian 1.6 7610.595691 Province The Fourth Survey 10 K’s Brigade of Ministry 70 7608.595691 of Railways Longyan Branch of Deposit for Safe 10 K’s Construction Bank 0.01 7680.605691 of China Overhead Charge of 10 K’s 1478.72319 9159.328881 Construction Unit Total 10 K’s 9159.328881

9.22. The Comparison of the Actual Costs of Land Acquisition and Resettlement with Those Stated in the Resettlement Report

Table 12. Annual Budgetary Estimate of Land Acquisition and Relocation Unit: thousand yuan Year One Year Two Year Year Total Three Four Land Acquisition 70,950 47,300 118,250 Standing Crops 506 338 844 Temporary Land 646 646 645 645 2,582 The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 72 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Demolition and Relocation of 76,351 50,900 127,251 Buildings Relocation of Roads 282 281 563

Relocation of Telecommunication 13,937 13,937 27,874

Demolition and Relocation of 3,921 3,921 7,842 Electric Power lines Other Demolition and Relocation Contingency (10%) 14,845 11,733 1,878 65 28,521 Total 163,298 129,057 20,662 710 313,727

Table 12 is the budgetary table of compensations for land acquisition and relocation included in the Resettlement Action Plan compiled by TERA company from USA in their process of providing the international technical assistance for this project. The total is 313.727 million yuan, which is based on the predicted scale of land acquisition, demolition and relocation, and the compensation that would go direct to the affected people without putting other costs into account. The analysis of the actual expenses of land acquisition, demolition, relocation, and resettlement for Ganzhou-Longyan Railway Project reveals that the compensation for land acquisition, demolition, relocation within the red line is 311.58273 million yuan (see table 6), accounting for 99.3% of the RAP budget, excluding the cost for the resettlement projects outside the red line and other ancillary projects. In addition, Longyan municipal government of Fujian Province raised a supplementary subsidy of 184.08379195 million yuan from the financial departments of all levels (from the province, the city down to counties) for the project. So the actual cost of the project was 495.66652195 million yuan, accounting for 158% of RAP.

9.2.3. Evaluation of Budgeting and Financing for Resettlement

On the whole, the resettlement budget is in conformity with the actual situation. There is just a slight difference between the RAP budget and the actual expenses after the to-be-turned-in construction expenses (such as the fee for keeping the balance between the construction land and the compensation of the arable land) is taken into consideration. The funds-raising scheme worked out jointly by the railway construction units and local governments along Ganzhou-Longyan Railway line ensured the sources of fund for land acquisition, demolition, relocation and resettlement, and offered fund guarantee for the realization of the objectives of resettlement.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 73 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

10. Participation of the Affected People and Release of Related

Information

10.1. Release of Project Information

10.1.1. Notification

All the resettlement departments of the counties along the railway line notified the affected people of the policies and plans of resettlement before land acquisition, demolition and relocation. Altogether the resettlement departments released two notifications. The first one was released to inform the affected people of the range and scale of land acquisition and demolition, and the policy and standard of compensation; the second one was to inform them of the specific scale of land acquisition, demolition and the specific amount of compensation to ensure the transparency and democracy in the whole process. The second notification also serves to find and correct any possible calculation errors.

10.1.2. Flexible and Diversified Ways of Information Dissemination

The resettlement departments released the relevant information to the affected people in various forms, through various channels and at various levels. For example, Changting County in Longyan City of Fujian Province conducted information dissemination by various means, such as loudspeaker vans, broadcasting system, television, slides played in cinemas before feature films, and slogans, newspapers, notices, village bulletin boards and brochures, etc. In much the same way, other 7 counties and districts also informed the affected people of the policies and measures taken in land acquisition, demolition, relocation, compensation and resettlement as well as the purposes and functions of the Ganzhou-Longyan Railway Project.

10.2. Ways of Participation of the Affected People

All the work of land acquisition, demolition, relocation, compensation and resettlement was done through continuous consultations. The consultation meetings were held at various levels, ranging from the highest level (between the Ministry of Railways and the two provincial governments), to the middle level (between the resettlement departments of the counties and townships) and to the lowest level (between the resettlement departments and the affected people) to ensure the participation of the affected people in the work of land acquisition, demolition and

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 74 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project relocation and seek their opinions. The resettlement departments organized village-level consultation meetings, and visited the affected people household by household to get the detailed information and win every farming household’s acceptance of and satisfaction with the resettlement policy and plan. All those activities are actually the different channels of effective participation of the affected people.

10.2.1. The Mechanism for the Investor to Participate In the Processes of Planning, Management, Monitoring and Assessment.

As the investor of Ganzhou-Longyan Railway, the Ministry of Railways accredited the Ganzhou-Longyan Railway Construction Headquarters in Fujian and Jiangxi Provinces through Shanghai Railway Administration and Nanchang Railway Administration, and set up within the headquarters the special offices in charge the affairs of land acquisition, demolition and relocation. The headquarters entrusted the work of land acquisition, demolition and relocation to the local governments of the counties or districts along the railway line. The staff members of land acquisition, demolition and relocation office of the headquarters worked together with the land acquisition and resettlement departments of local governments in measuring and confirming the impact scope of the land acquisition, demolition and relocation with the help of specialists of acquisition and relocation from the railway construction units. In addition, the staff of the special office in charge of acquisition and relocation kept an eye on the progress and problems of land acquisition, demolition, relocation and resettlement through weekly, monthly and quarterly reports and other internal monitoring means. At the same time, through the stringent monitoring procedures of fund allocation, the specila office in charge of acquisition and relocation oversaw the working quality of land acquisition, demolition, relocation and resettlement, the implementation of policies, the complaints of the affected people, to supervise and urge the local governments to compensate and resettle the affected people in accordance with the publicized resettlement policy. Besides, this special office in charge of acquisition and relocation was also entrusted to evaluate the whole resettlement work.

10.2.2. The Compilation and Distribution of the Resettlement Brochures

All the counties concerned compiled and distributed resettlement brochures to all the affected households. The brochures included the brief introduction to Ganzhou-Longyan Railway, the notice of commencement of the construction of Ganzhou-Longyan Railway, the methods of implementing land acquisition, demolition and relocation, and the compensation standards for land acquisition, demolition and relocation for Ganzhou-Longyan Railway Project. To ensure the principle of openness and transparency, all the counties concerned attached great importance to the distribution of the brochures. They printed adequate copies and

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 75 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project distributed the brochures to all the affected people. For example, Yudu County handed out 5800 copies, and Changting County distributed nearly 2000 copies.

10.3. Evaluation of Consultation

On the whole, the land acquisition, demolition, relocation, compensation and resettlement for Ganzhou-Longyan Railway embodied the principle of openness and transparency. The resettlement departments made great contributions, especially in publicizing the policies of compensation and resettlement, which was quite satisfying.

11. Organization and Management

11.1. Main Tasks and Responsibilities of the Organizations

Both the investor and constructor of Ganzhou-Longyan Railway and the relevant local governments established networks of organizations and agencies specialized in land acquisition, demolition, relocation, compensation and resettlement to ensure the realization of the objectives of resettlement work. The investor of the railway project (the Ministry of Railways) set up a special office for land acquisition, demolition and relocation in each of the two headquarters of railway construction. The Fourth Survey and Design Institute of China Railway set up an acquisition and relocation group in the on-site design headquarters. And 19 construction bureaus plus at least 50 project departments established their working groups of land acquisition, demolition and relocation. Both Ganzhou City and Longyan City set up their railway construction supporting offices for coordinating the work of land acquisition, demolition, relocation, compensation and resettlement. The affiliated 8 counties (district) also set up the corresponding railway construction supporting offices of similar functions. The acquisition and relocation working groups were also established in 29 towns and townships, and their specific tasks and responsibilities are stated in table13.

Table 13. Responsibilities of Departments in Charge of Land Acquisition, Demolition, Relocation, and Resettlement for Ganzhou-Longyan Railway

Types of Names of Number Responsibilities Organizati Organizations of Staff ons Investor(O Acquisition and 3 In charge of land acquisition, demolition, relocation, and wner) Relocation Office of resettlement; responsible for consulting with and Railway Construction contacting the prefecture-level railway construction Headquarters of supporting offices; responsible for allocating the

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 76 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Nanchang Railway resettlement funds, and in charge of the internal Administration monitoring work during the progress of the project. Acquisition and 4 Relocation Office of Railway Construction Headquarters of Shanghai Railway Administration Design Acquisition and 4 Responsible for solving the problems the affected people Institute Relocation Group of encountered and meeting their needs from the perspective the Fourth Survey and of engineering designing. Design Institute of China Railway Constructio The Acquisition and 57 Responsible for land acquisition plans, and consulting n Bureaus Relocation Groups of with county-level land administration departments and 19 Construction county-level railway construction supporting offices. Bureaus The Acquisition and 100 Relocation Groups of over 50 Project Departments Affiliated to the 19 Construction Bureaus. Railway Railway Construction 12 In charge of the coordination and management of land Constructio Supporting Office of acquisition, demolition, relocation and resettlement in n Ganzhou City their corresponding administration divisions; responsible Supporting Railway Construction 18 for cooperating with and supporting the railway Offices of Headquarters of construction authority; responsible for collecting and Local Longyan City gathering relevant data and information; in charge of Governmen coordination with and management of other parties related ts to the construction of the project. Railway Construction 50 Specifically responsible for formulating the compensation Supporting Offices of standards and resettlement plans under the leadership of 8 Counties (District) prefecture-level (or city-level) railway construction supporting offices; in charge of fund allocation, demolition, relocation and resettlement. Railway Construction 87 Undertaking the specific work of survey and verification Supporting Groups of of land, houses and their attachments, and the work of 29 Towns and relocation under the leadership of county-level railway Townships construction supporting offices.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 77 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

11.2. Capability of Staff Members of Resettlement Departments

The 8 county-level (or district-level or city-level) railway construction supporting offices and land administration bureaus along Ganzhou-Longyan Railway line jointly undertook the task of land acquisition, demolition, relocation and resettlement for the project. The staff members of those agencies were richly experienced, highly capable and professionally dedicated. Through field communication with the resettlement consultative experts from the Transportation and Economic Research Associates, Inc. based in USA during the process of pre-construction verification and justification, and thanks to the training on the resettlement policy offered by ADB experts to the resettlement agencies and their staff members during the period of loan allocation, the resettlement agencies along Ganzhou-Longyan Railway line had correct understanding of the ADB resettlement policy. The 8 county-level resettlement agencies worked hard and made outstanding achievements. They not only resettled appropriately the households affected by land acquisition, demolition and relocation before the commencement of civil engineering construction, but also transferred the acquired land to the construction units in time. At the same time, before land acquisition, demolition and relocation, they finished various preparatory work, went through the relevant formalities of application for approvals, and dealt with various procedures.

12. Monitoring and Evaluation

12.1. Internal Monitoring

The internal monitoring of Ganzhou-Longyan Railway Project was undertaken by the Center of Foreign Capital Introduction and Utilization of the Ministry of Railways. The process of the internal monitoring is as follows: The railway construction supporting offices of local governments at all levels and the land acquisition and relocation offices of construction units submit quarterly reports on the general situation of the project, the construction progress, the civil work, the procurement of equipment, finance, resettlement, environment protection, project management and implementation to the agency of the Ministry of Railways—Ganzhou-Longyan Railway Construction Headquarters, which will then summarize the incoming reports and submit reports to the Center of Foreign Capital Introduction and Utilization of the Ministry of Railways, which will then submit quarterly reports to ADB on the basis of the reports received from its agency.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 78 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

12.2. External monitoring

The independent external monitoring agency—the Institute of Foreign Capital Introduction and Utilization of Southwest Jiaotong University has submitted the following work products to its clients—the Center of Foreign Capital Introduction and Utilization of the Ministry of Railways, and ADB (Asian Development Bank):

„ The field survey along Ganzhou-Longyan Railway line was conducted in April 2002 and the baseline survey report on 350 sample households was completed, which laid a solid foundation for the external resettlement monitoring work of the project;

„ In April 2004, the phase-one external resettlement monitoring report and the social development monitoring report was completed;

„ In May 2003, the phase-two external resettlement monitoring report and the social development monitoring report was completed;

„ In May 2005 the report on the completion of resettlement for Ganzhou-Longyan Railway was provided;

„ In June 2007 the field investigation for post-resettlement evaluation and monitoring along Ganzhou-Longyan Railway line was finished.

In the process of external resettlement monitoring, the independent external monitoring agency ensured the accuracy and validity of the basic data and some of those used for internal monitoring by means of sampling survey, typical survey, survey on a selective basis, collective interview, interview of important insiders, follow-up interviews, observation, consulting documents, information retrieval from database, etc. The monitoring reports submitted to the clients reflect in an all-round way the progress of land acquisition, demolition, relocation, and resettlement as well as the implementation of the resettlement action plan.

13. Experience, Lessons, Remaining Problems and

Suggestions

13.1. Experience of Resettlement

The work of land acquisition, demolition, relocation, and resettlement for

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 79 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Ganzhou-Longyan Railway has met the objectives set in the resettlement action plan. Therefore, the resettlement work is successful. As the independent external monitoring agency, we think that the efforts made in the following aspects are the key factors contributing to the success of the resettlement work:

„ Extensive publicity and mobilization made the policies and the significance of Ganzhou-Longyan Railway construction known to the people.

„ Practicing the principle of fairness, openness and transparency by means of radio, TV, wall bulletins, publicity brochures, conferences at all levels, etc. to make sure that the policy is open and transparent, and the supervision is in place.

„ As there were complete resettlement plans and implementation agencies, the work of land acquisition, relocation, compensation and resettlement was well organized, and the resettlement plans and policies were successfully implemented.

13.2. Remaining Problems and Work to Be Done

Mr. Li Wenqian from the Railway Construction Coordination Headquarters of Longyan City, Fujian Province pointed out two remaining problems when interviewed during the post-resettlement evaluation survey:

1) Soil and water loss. In few places along Ganzhou-Longyan Railway line, there existed the hidden trouble of soil and water loss due to incomplete construction operation. And this hidden trouble calls for special treatment.

2) The second hidden trouble lies in the maintenance of the temporary bridges. The temporary roads and bridges built for railway construction were left to the local people at their request. Though such roads and bridges may facilitate the local people’s life and production, they also have some hidden troubles, especially the temporary bridges, which may have hidden trouble in safety because no one is designated to take charge of their maintenance.

The external resettlement monitoring agency holds that besides keeping on helping the affected people recover their production and life, it is a must for the departments in charge of resettlement to help the affected people like those in Pingpu Village, Jiaoyang Township, Shanghang County who have not received their new land certificates and property ownership certificates obtain those legal documents.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 80 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

14. Annexes

14.1. Sites of Resettlement for People Affected by Demolition and

Relocation

Table 14: The resettlement distribution of migrations in land acquisition and housing demolition Perfecture County Town Village Ganzhou City Ganxian Maodian Huanglong Jiangkou Jiaoling Yudu Luo’ao Maoping Zhishang Shangfeng Gongjian Yuming Huangling Shangguang Huichang Xijiang Niushui Bazhi Wanxing Ruijing Yunshishang Shibei Xianhu Nangang Shazhouba Meigang Longyan City Changting Qili Mudungxia Xixia Hetiang Yabei Nanshang Nangshang Liangcheng Pengkou Xingquang Shanghang Jiaoyang Pingpu Xingluo Xiaochi Longmeng Hongzhushang Aipi Pukou Xipi Shibu Tianshang Yangte Yangmei

14.2. Relevant Documents on the Resettlement Policies for the Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 81 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Document of Longyan Municipal Government

(Document No. 2001-344)

______

A Notice of Printing and Distributing the Plan for Land Acquisition, Demolition, Relocation and Resettlement for Fujian Section of Ganzhou-Longyan Railway Issued by Longyan Municipal Government

To the People’s Governments of Xinluo District, Shanghang County, Changting County and Liancheng County: The Ganzhou-Longyan Railway is a main East-West railway line programmed for many years for the National Railway Network. It is a key railway construction project included in the tenth five-year plan of the Ministry of Railways and in the tenth-five-year plans for the two provinces and the relevant cities. The construction of the Ganzhou-Longyan Railway is of great significance in the territorial development in the old revolutionary base areas of Southern Jiangxi and Western Fujian, in alleviating poverty and bringing about prosperity among the along-line community, and in promoting the “three direct links of trade, mail, and air and shipping services across the Taiwan Straits” and the unification of China, in perfecting the railway network and improving the railway operation performance. The Ministry of Railways initiated the railway construction in the 4th quarter of 2001. However, the land acquisition, demolition, relocation, and resettlement work is a key step of the project. To ensure the smoothness of the railway construction and to proceed with the land acquisition, demolition and relocation work in a well planned and organized way, the present plan is hereby established according to the “Land Administration Law of the People’s Republic of China”, “Fujian Provincial Measures for the Implementation of the ‘Land Administration Law of the People’s Republic of China’”, and the

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 82 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

regulations made by the relevant departments at all levels.

I. General Requirements In order to accomplish the work of land acquisition, demolition, relocation and resettlement in a healthy and appropriate manner, satisfy the needs of the Railway construction, and ensure the smooth progress of the Project, the railway construction supporting offices, the land administration bureaus, the forestry bureaus, the construction bureaus, and the construction units should take the “Three Represents Theory” as the general guidelines, abide by the relevant state laws and regulations, work closely with each other, seek support from governments of all levels, and follow the principle of frugality in land acquisition, priority-based order of acquisition, unified resettlement, and fixed expenditure package in their implementation of land acquisition, demolition, relocation and resettlement. II. Organizations of Accountability Shanghai Railway Administration is the construction proprietor and the land user. Longyan municipal government is the organizer of the work of land acquisition, demolition, relocation, and resettlement. III. Organizations, Tasks, Responsibilities and the Specific Work A. Organizations 1. A “Railway construction coordination headquarters” should be established in the Longyan municipal government, and in the governments of Xinluo District, Shanghang County, Liancheng County and Changting County respectively. And each relevant town (or township) along the railway line should set up a coordination group for the construction of Ganzhou-Longyan Railway. The county (district) headquarters are responsible to the municipal headquarters; the township (town) groups are responsible to the corresponding county (district) headquarters. The Longyan municipal headquarters for the construction of Ganzhou-Longyan Railway

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 83 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

should lead and organize in the unified way the entire work of land acquisition, demolition, relocation and resettlement citywide, and coordinate the relationship between the railway construction units and the local governments. 2. The city and county (district) headquarters are directed by the corresponding leaders of the same level. The municipal headquarters are formed by the officials from various departments such as the city government office, the committee of discipline investigation, the censorial commission, the planning commission, the railway construction supporting office, the land administration, the forestry bureau, the finance department, the audition department, planning department, the committee of construction, the agriculture bureau, the water conservation department, transportation department, highway administration department, water and electricity department, power supply department, telecommunication department, civil defense department, housing department, public security bureau, industrial and commercial administration, state tax bureau, local tax bureau, etc. Under the command of the city headquarters an office is installed in the city railway construction supporting office. A similar headquarters should be installed at the county (district) level. The headquarters offices should be stationed in the corresponding railway construction supporting offices at the corresponding levels (city, county, or district). The manning of the “coordinating groups” of the townships (towns) along the railway line is decided by the corresponding governments according to the working requirements. After the establishment of the county (district) headquarters and along-line township (town) coordinating groups, a copy of the name lists as well as the phone numbers should be handed to the city government office and the city railway construction supporting office for the convenience of liaison and coordination. B. Responsibilities and Tasks

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 84 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

1. The municipal headquarters is in charge of the organization, direction, and coordination of the citywide work of land acquisition, demolition and relocation for the construction of Ganzhou-Longyan Railway. 2. “The Compensation Standard by Longyan People’s Municipal Government for Land Acquisition, Demolition and Relocation in Fujian Section of Ganzhou-Longyan Railway” should be formulated in accordance with the ministry-province agreement, “Land Administration Law of the People’s Republic of China”, “Fujian Provincial Methods for the Implementation of the ‘Land Administration Law of the People’s Republic of China’”, and the specific circumstances of the city. And the county (district) governments should work out detailed implementation methods and compensation standards according to relevant legislation and municipal compensation standards. 3. The along-line “county (district) headquarters” are in charge of the organization and leadership of the work of land acquisition, demolition and relocation within their administrative divisions, and is responsible to the “city headquarters” for the implementation of the resettlement plans for their administrative divisions at the same time. 4. “Country (district) headquarters” should formulate and carry out a concrete implementation plan for the resettlement work according to relevant policies and regulations, and be responsible to the “city headquarters” at the same time.

C. The City Railway Construction Supporting Office Is in Charge of the Raising, Managing and Use of Fund D. Resources of Funds 1. The compensation allocated by the Ministry of Railways (the construction proprietor) according to the agreed unit price negotiated between the ministry and the province.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 85 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

2. The subsidies from the financial departments of the provinces, the cities, and the counties (districts). E. Preferential Policy According to the 3rd clause of the “Ministry-Province Agreement”, the following preferential policies are implemented: 1. Fujian Province and Jiangxi Province agrees to waive charges, such as the mineral resources compensation fee, water resources fee, the auxiliary cost of urban construction, the education surcharge, the funds of land acquisition and water conservancy, the fee of water soil conservation, etc. The abatement and remission of the taxes should be jointly applied for by both the ministry and the province to the state, to halve the sales tax of the construction enterprises, and abate the tax for the occupation of cultivated land levied upon the construction enterprises. The fees set by the provincial and the along-line local governments should be waived. The taxes and fees, which have been publicly cancelled by the decrees issued by the state and the governments of Fujian and Jiangxi provinces should not be levied. 2. In the principle of controlling the cost and save the investment, the related departments of Fujian and Jiangxi provinces, and those of Ministry of Railways should jointly set a price ceiling, introduce a market competition mechanism, adopt the lowest and most favorable prices free of local taxes and fees in the provision of the construction materials (such as sand, gravels, etc.) water, electricity and telecommunication service to the .construction units of Ganzhou-Longyan Railway Project. 3. For the utilization of parts of the along-line highways and rural roads in the railway construction areas by the railway construction units, the parties concerned should provide convenience, such issuing toll-free passes (free of road toll and bridge toll) to the construction units. Meanwhile, for the temporary acquisition of land for temporary roads and the temporary facilities for the railway construction, the railway construction authority and

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 86 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

the local governments should follow the principle of mutual benefit, and try to combine the railway construction with the development plans of the local township and towns. 4. For the relocation of the power lines, telecommunication lines, broadcast network, Fujian and Jiangxi governments are responsible for coordinating the relevant organizations and sectors to provide assistance and offer services to the railway construction units at favorable prices. 5. Local resources that are up to the quality standards should enjoy a priority of purchasing. On the condition of quality construction and reasonable prices, the local workers should enjoy a priority of employment in the ancillary projects of the railway construction if manpower is lacked. F. Implementation Measures 1. An agreement on land acquisition, demolition and relocation should be reached between the city government or the “municipal headquarters” and the proprietor —Construction Headquarters of the Ganzhou-Longyan Railway (Fujian Section) of Shanghai Railway Administration, in accordance with the “Ministry-Province Agreement”. 2. Contracts (see the relevant appendix) should be signed between the city government and the project-related county (district) governments respectively for the coordination of the railway construction; and the contracts of similar nature should also be signed between the related along-line counties (districts) and townships (towns). The contracts aim to clarify the scope of duties and responsibilities of each party. That is to say the responsibilities are contracted to the parties concerned. IV. Steps of Implementation. A. Determine the compensational units for land acquisition, demolition, relocation, and work out the resettlement plan. 1. The compensational unit prices set by the “Ministry-Province Agreement” are 8000 yuan/mu for land acquisition, and 220 yuan/m2 for demolition and

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 87 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

relocation. The unit compensation standards for land acquisition should be based on those set by the Ministry of Railways, and should be calculated by the “city headquarters” office in accordance with the new “Land Administration Law of the Republic of China” and the legislations by relevant land and forestry departments, on the basis of the types of land and the structures of houses within the red line of land acquisition, and should be publicized and implemented after being discussed and passed by the relevant municipal departments, and approved by the people’s municipal government. 2. The resettlement plan should be publicized and implemented by the county (district) governments along the railway line after a practical plan based on the actual local conditions is made by the headquarters offices of the corresponding counties (districts) and approved by the relevant municipal governments. C. The organization and the direction of the work of land acquisition, demolition and relocation should be carried out with steadfastness. The county (district) railway construction supporting offices and local land administration bureaus should give priority to the work of land acquisition, demolition and relocation in the key sections of the Railway on the basis of a comprehensive coordination and meticulous work. D. Before the implementation of the land acquisition, demolition and relocation, a mechanism of rewards and penalties should be formulated by each along-line county (district) headquarters; for the resettlement work of a county (district), early planning, constructing and relocating should be stressed, in order to ensure the smoothness of the land acquisition, demolition and relocation work. E. The along-line county (district) headquarters as well as the related townships (towns) should sign a responsibility contract with each household affected by land acquisition, demolition and relocation. The compensation should be delivered to every affected household five days after all the

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 88 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

household compensation data are publicized on the wall bulletins. F. The along-line counties (districts) are required to transfer the land in time to the railway construction authority according to the progress of the project and the order of priority. G. For the smooth proceeding of the land acquisition, demolition and relocation work, the policies should be fully and efficiently carried out, and capital should be actively raised. H. As the work of land acquisition, demolition and relocation involves various parties, calls for appropriate application of policies, and is rather complicated, leaders of all levels should pay great attention to it. A county (district) governmental responsibility system should be adopted, and the duties of each department should d be clearly defined and efficiently carried out. All parties should cooperate closely with each other to accomplish such a tough but honorable task. I. More publicity work should be done among the along-line local people to call on them to support the railway construction and consciously comply with the policies and regulations made by the upper-level authorities. Each county (district) should strengthen the public security administration, severely crack down on the illegal activities that jeopardize the railway construction, and fight against those who instigate people to interrupt and disturb the normal proceeding of the railway construction. Those demagogues should be penalized severely by the public security agency according to “The Penalty Law of Public Security Management of People’s Republic of China”. Those who break the law and commit crimes should be called to account of their criminal responsibilities by the judicial authority in order to create a stable atmosphere for the railway construction. J. Departments of all levels should perform their administrative duties and offer their services to the public according to law.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 89 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Appendix: “Responsibility Contract of the Land Acquisition, Demolition and Relocation for the Ganzhou-Longyan Railway Project of Longyan City” Longyan City Government Oct.29th, 2001

Longyan Governmental Document

Document 2001-345 Longyan Governmental Notice on Printing and Distributing the Compensation Standards for the Land Acquisition, Demolition and Relocation along the Fujian Section of Ganzhou-Longyan Railway Line

Governments of Xinluo District, Shanghang County, Changting County and Liancheng County:

The Ganzhou-Longyan Railway is a key railway construction project programmed in both the Tenth Five-Year Plan of the Ministry of Railways, and in the Five-Year Plans of Fujian Province and Longyan City. We hereby distribute to you the printed “Compensation Standards for the Land Acquisition, Demolition and Relocation along the Ganzhou-Longyan Railway Line (Fujian Section)” formulated according to the “Agreement between the Ministry of Railways, Fujian Provincial Government and Jiangxi Provincial Government on Relevant Issues Concerning the Construction of the Ganzhou-Longyan Railway”, “The Land Administration Law of the People’s Republic of China”, “Fujian Provincial Measures for the Implementation of the ‘Land Administration Law’” and “The Forest Law of the People’s Republic of China”, and in view of the practical situation of our city. Each county (district) should formulate a detailed implementation plan and compensation standards according to its practical situations and in The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 90 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

conformity with the relevant laws and regulations, and implement them conscientiously. “Compensation Standards for the Land Acquisition along the Fujian Section of Ganzhou-Longyan Railway”

No. Land Types Unit Compensation Unit Price

(10,000 yuan/mu)

1 Paddy field mu 1.3

2 Vegetable Field mu 1.5

3 Pound mu 1.35

4 Dry Field mu 0.8

5 Garden Plot mu 0.8

6 Woodland mu 0.6

7 Transportation Land mu 0.2

8 House Lot mu 1.3

9 River Runway and Waters mu 0.2

10 Unused Land mu 0.2

Notes: 1. The payments above contain the compensation for land acquisition, resettlement, and young crops, the fund for developing new vegetable fields, and the compensation for the plants on forest land and orchard, and domestic animals and poultry, etc. Taxes and fees that should be turned in to the central and provincial governments are not included. 2. All the municipal and county taxes and fees are waived. 3. The vegetable fields are the vegetable bases designated by the “Vegetable Basket Project”. Compensation Standards for the Demolition and Relocation along the Fujian Section of Ganzhou-Longyan Railway Project

Compensation Unit Price Description Unit (yuan)

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 91 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Framed Structure m2 460

Brick-Concrete m2 310

Brick-Wood m2 260

Earth-Wood m2 210

Lavatory, Hog (Ox) Pen m2 90

Simply-Built m2 60

Notes: 1. The payments above contain the expenses of the indoor and outdoor supporting facilities and the demolition management fee, but not the fees for moving and transitional expense after demolition. 2. The unit prices for other types of demolition and relocation will be determined by the negotiation among related departments.

Governmental Document by Ganzhou Government Office

Document 2002-9

______

Notice on Printing and Distributing the Compensation Standards for the Land Acquisition, Demolition and Relocation along the Ganzhou Section of Ganzhou-Longyan Railway by Ganzhou Government Office

Governments of Ganxian County, Yudu County, Huichang County and Ruijin City:

To positively support Ganzhou-Longyan Railway construction, and ensure its smooth progress, we hereby distribute to you the “Compensation Standards for the Land Acquisition, Demolition and Relocation along the Jiangxi Section of Ganzhou-Longyan Railway” formulated according to “The Land Administration Law of the People’s Republic China”, “Jiangxi Provincial The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 92 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Measures for the Implementation of the ‘Land Administration Law of the People’s Republic of China’”, “The Law of the Forestry of the People’s Republic of China”, “The Agreement between the Ministry of Railways, Fujian Provincial Government and Jiangxi Provincial Government on the Relevant Issues Concerning the Construction of Ganzhou-Longyan Railway”, “The Notice on Printing and Distributing ‘the Minutes of the Coordinating Meeting on the Relevant Issues of the Land Acquisition, Demolition and Relocation for Ganzhou-Longyan Railway Construction’ by Jiangxi Provincial Government Office” (Document 2001-153 of Ganzhou Government), the “‘Agreement on the Relevant Issues Concerning the Work of Land Acquisition, Demolition and Relocation along the Jiangxi Section of Ganzhou-Longyan Railway’ reached between the Ganzhou city government and the Nanchang Railway Administration”, the relevant requirements made by ADB on the work of land acquisition, demolition, relocation and resettlement, and the practical situations of our city. Please earnestly put it into implementation according to the requirements. Each county (city) government can make appropriate adjustments and balancing to the municipal governmental compensation standards for land acquisition, demolition and relocation according to the practical situations of land types, house structures and their degree of wear. The surplus funds derived from the adjustment should be used as special funds for the new house sites and for public utilities benefiting the resettled households. The concrete standards made by each county (city) should be submitted to the municipal government for examination and approval.

Compensation Standards for Permanent Land Acquisition and Temporarily-Acquired Land in the Jiangxi Section of

Ganzhou-Longyan Railway

Land Types Compensation Remarks

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 93 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Standards

Paddy Field 10,000 yuan/mu

Dry Field 6,200 yuan/mu Paddy land includes Orchard 7,400 yuan/mu Permanently pounds; Dry land Woodland 3,200 yuan/mu Acquired Land includes house sites.

Wasteland, Kiln Factory, Flood Land 760 yuan/mu

Land for Earth Farm Land Unused Fetching and 3,500 Land Dumping yuan/mu

Land for

Storing Including the Construction The period less than Temporarily Used Land Reclamation Facilities and 1,100 yuan/mu/year one year is counted Land Fee and Young Materials as one year. Crops Fee Land for Comprehensive Unit

Pioneer Road 5000 yuan/mu Price

Compensation Standards for Demolition and Relocation for Ganzhou Section of Ganzhou-Longyan Railway

Description Unit Compensation Standards

1. Brick and Concrete yuan/m2 280

2. Brick-Wood yuan/m2 210

3. Earth-Wood yuan/m2 170

4. Simply-Built yuan/m2 60

5. Enclosure yuan/m2 50

6. Pumping Well yuan/m2 600

7. Concrete Deep Well yuan/m2 3,000

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 94 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

8. Cement Bleachery yuan/m2 40

9. Tabia Bleachery yuan/m2 30

10. Active Adobe Kiln yuan/m2 5,000

11. Adobe Kiln Idling for yuan/m2 2500

More Than 1 Year

12. Grave yuan/tomb 260

13. Manure Storage yuan/unit 300

14. Marsh Gas Tank yuan/tank 1000

15. Transitional Fee (4 yuan/person/month 10

months)

16. Removing Indemnity yuan/household/one-off 100

17. Ordinary Trees (Less yuan/plant 15

than 30cm Perimeter)

18. Ordinary Trees (31cm or yuan/plant 40

More Perimeter)

19. Various Fruit Trees yuan/plant 26

(Less than 31cm

Perimeter)

20. Various Fruit Trees yuan/plant 70

(31cm or More

Perimeter)

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 95 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

14.3 The Results of Household Sample Survey Conducted During the

Post-Resettlement Evaluation Investigation

Wu Yunlai (13970702374): Male, aged 65, primary school education, farms at home, villager of group 3 of Liushilidian Village, Jiangkou Town, Gan County. There are 12 members in his family: the wife, three sons and their wives, and four grandchildren. The eldest son is 39 years old, junior college education, and works in Urban Construction Bureau where is outside their county. The eldest daughter-in-law is 37 years old, junior high school education, and farms at home. The second son is 33 years old, junior high school education, a truck driver out-of-town, and earns 1200 yuan monthly (cost-free room and board). The second daughter-in-law is 32 years old, junior high school education, does manual work in Zhejiang, and earns 1,000 yuan monthly. The third son is 29 years old, with junior high school education, trucks at home, and earns 2,000 yuan monthly. The third daughter-in-law is 29 year old, with junior high school education, does manual work locally, and earns 800 yuan monthly. Grandchildren are in school. Their former brick-wood structured house with a size of 200 m2 was compensated for more than 60,000 yuan which was paid completely. The new 4 brick-concrete structured houses are 800 m2, and each of them is 200 m2. The family has 2 mu of paddy field and 1 mu of dry land for planting vegetable now. Besides, Wu is the contractor of 25 mu of orchard, and the net income of orchard is 50,000 yuan annually. Family durable consumables: a refrigerator, a washer, a TV, a motorcycle, a truck. This family is among the upper-intermediate in the village in terms of living standards. He is satisfied with the construction of railway and resettlement.

Wu hongfu: Male, aged 40, junior high school education, villager of group 3 of Liushilidian Village, Jiangkou Town, Gan County. There are 5 members in his family, including his wife, daughter, son and father. He and his wife do manual work with annual income 20,000 yuan in Fujian. His father takes care of the children at home, and the children are pupils. The family has 2 mu of cultivated land, a brick-concrete structured house with a size of 200 m2. Family durable consumables: a color TV, a motorcycle. This family is intermediate in the village in terms of living standards. They think that now there is no changes about income, but more convenient to go home because of the Ganlong railway.

Wu hongxing: Male, aged 58, retired worker, villager of group 3 of Liushilidian Village,

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 96 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Jiangkou Town, Gan County. There are 5 members in his family, including his wife, son, daughter-in-law and granddaughter. The son and his wife do manual work with annual income 30,000 yuan in Guangdong. Now they have a new brick-concrete structured house with a size of 500 m2. Compared with the past, the living standards have improved. Family durable consumables: a color TV, a washer and a motorcycle. This family is among the upper-intermediate in the village in terms of living standards. They are satisfied with construction of railway and resettlement.

Chen huimin: Male, aged 35, junior high school education, villager of Jiaolin Village, Jiangkou Town, Gan County. There are 6 family members in all: the couple, 62-year-old father, 56-year-old mother, and two sons. His parents farm at home. He is a truck driver, does carrying work. The eldest 14-year-old son is a first-year high school student, and the second 11-year-old son is a second-year junior high school student. His wife is a teacher of the primary school of their village with monthly income 400 yuan. This family now has only 0.8 mu of paddy field; however they had 2 mu before land acquisition. There is a three-storied brick-concrete structured house with a size of 600 m2 instead of the former earth-wood structured house with a size of 200 m2. Chen believed that it’s more convenient than before because of the better roads and the electricity and water supply which are benefit from construction of railway and new village policy. But, there are also unfavorable things: too large train noise, the road to the paddy field of this family with a big gradient that is bad to Chen’s parents.

Zhu deying: Female, aged 50, illiterate, villager of Jiaolin Village, Jiangkou Town, Gan County. There are 6 family members in all: the couple, the aunty of her father, two sons and a daughter. The aunty of her father is a senile dementia patient. Her husband is 52 years old, the eldest son is 28, the second son is 26 and the daughter is 24. Zhu farms at home, and the two sons and daughter do manual work in Guangdong with economic independence. Zhu lives with her young brother. Now they have 3 mu of paddy field, and could get more than 2,000 kg paddy annually. The former main house was 140 m2, and the auxiliary rooms were 70 m2. Now they have a brick-concrete structured house with a size of 140 m2 which is away from the railway about 100 meters. Zhu believed that the living standards are better than before because of the more work chances, the cheaper northern fruit, the availability of water supply and the path to home. But the unfavorable thing is that it’s not easy to go to the paddy field when swelling.

Zhu kaibiao: Male, aged 65, primary school education, villager of Jiaolin Village, Jiangkou Town, Gan County. There are 8 members in his family: two sons and their wives, The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 97 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project eight grandchildren. The eldest son is 38 years old and the second son is 34 years old, and they all are junior high school education. They do manual work in Guangdong and earn 10,000 yuan per year respectively. The eldest daughter-in-law is 38 years old who has no work; the second daughter-in-law is 33 years old who has no work too. There is 3.6 mu of cultivated land now. Their former brick-wood structured house with a size of 120 m2 was compensated for more than 20,000 yuan. Now they have a new one-storied brick-concrete structured house with a size of 120 m2 which costs 30,000 yuan. Family durable consumables: a color TV, a motorcycle. This family is intermediate in the village in terms of living standards. In addition, it’s more convenient to go home than before, on the whole, they benefited from the construction of railway.

Xie shuifa: Male, aged 52, high school education, farming at home, villager of Jiaolin Village, Jiangkou Town, Gan County. There are 6 members in his family: the wife, the son and his wife, two grandchildren. His wife is 52 years old, primary school education, has no work and stays at home. The 30-year-old son who is junior high school education does manual work (car repair) in Ganzhou with monthly income 2,000 yuan. The 30-year-old daughter-in-law is junior high school education, does manual work in Ganzhou too, and earns 800 yuan per month. Grandchildren are in school. This family has 3.5 mu of cultivated land now. Besides, Xie is the contractor of 15 mu of orchard. The former house was brick-wood structured, and the new house is brick-concrete structured. Family durable consumables: a color TV, a motorcycle. This family is among the upper-intermediate in the village in terms of living standards. The construction of railway makes no difference to this family.

Yan Chaolin: Male, aged 51, primary school education, villager of Xinyang Group of Yangmei Village, Luoao Town, Yudu County. There are 6 members in his family: the wife, three daughters and a son. The wife is 48 years old, primary school education, farms at home. The eldest daughter is 24 years old, junior college education, works in Ganzhou and earns 1,000 yuan monthly. The second daughter is 22 years old, junior high school education, does manual work in Ganzhou and earns 400 per month. The third 20-year-old daughter is a college student in Ganzhou. The son is 17 years old, will enter college soon. Yan feeds 10 head pigs at home. The former brick-wood structured house with a size of 200 m2 was compensated for more than 30,000 yuan, and now they have a brick-concrete structured house with a size of 400 m2 which costs about 70,000 yuan. This family has a liability over 30,000 yuan, and the main economic burden of this family is education fee. There is 2 mu of cultivated land. The only family durable consumable is a color TV. The railway construction firms his belief that he will give more on the education of his children, and he hopes that the children can out of rural areas, to improve their livelihood.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 98 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Yan zhaohui: Male, aged 42, junior high school education, villager of Xinyang Group of Yangmei Village, Luoao Town, Yudu County. There are 5 members in this family: the couple, two sons and a daughter. Yan’s wife is 40 years old. The eldest daughter is 17 years old, and she is a student of agriculture school in Ganzhou. The second daughter is 11 years old, and she is a forth grade pupil at the village primary school. The son is 10 yeas old, and he is a forth grade pupil at the village primary school too. The couple farm at home. They feed more than 20 chickens and ducks. There is only 1 mu of paddy field because of the land acquisition and housing demolition. Yan zhaohui does manual work since lunar may of this year, and earns about 30 yuan per man-day. As job instability, the income is also very unstable. The former brick-wood structured house with a size of 160 m2 was compensated completely, including 10 yuan/month/person for the transition. The new brick-concrete structured house is two storied and 240 m2. Yan’s wife believed that it’s more convenient than before; the living standards and environment are also improved after the railway construction. But as the house is near the road, bicycles, chickens and ducks could be stolen easily. In addition, the train noise is too large. Besides, it’s a little far to the paddy field for farming.

Liu rongxiang: Female, aged 45, primary school education, villager of Xinyang Group of Yangmei Village, Luoao Town, Yudu County. There are 6 members in her family: the father-in-law, three daughters and a son. The eldest 23-year-old daughter is a teacher of a kindergarten in Shenzhen, and sends money to home every festival. The second 18-year-old daughter is a second-year high school student in the forth high school of Yudu County. The third 15-year-old is a second-year junior high school student in Luoao middle school. The son is 9 years old and a third grade pupil in the village primary school. This family has only 3 mu of paddy field after land acquisition, and the agricultural income is about 1500 yuan per year. Moreover, this family feeds 4 hens and 13 ducks. Liu also does odd job occasionally besides farming. The former house is earth-wood structured in size of 120 m2, with other accidental 4-room house, including kitchen, sty and lavatory. Now this family has a two-storied brick-concrete structured house in size of 260 m2. They also get the fee for the transition 10 yuan/month/person. Liu believed: it’s more convenient to come and go after the railway construction; the living standards and environments are also improved; the eldest daughter who does manual work outside could come back home usually. The unfavorable influence is that the house near the railway and the train noise is big. Furthermore, as the land acquisition, this family has less paddy field than before, and the agricultural income decreased severely which is the main source of family income.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 99 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

Laiju Huangsheng: He is a villager of Yangmei Village, Luoao Town, Yudu County. He and his friend Lai disheng mine in Longyan City of Fujian Province. A train ticket from Yudu to Longyan is only 17 yuan since the railway construction was finished, which is cheaper than an auto ticket very much, because an auto ticket requires about 100 yuan. Before, he came back home only when the farming is busy. Now, as the railway was finished, he could often come back home to visit his parents, and propitiates his wife and children, these makes his marriage firmly. Besides, many villagers of Tangtou Village live on flipping cotton, therefore the contact with the outside world is close, and the opening of the railway makes the contact more closely.

Xu Youfu: He is a villager of Maoping Village in Luoao Town, Yudu County, Ganzhou City, Jiangxi Province (his wife, interviewed). He has a family knitting workshop, including 8 machines, 12 workers, and his daughter gives some help sometimes. All workers are the villager of Maoping Village. This workshop is mainly materials processing, accepted orders from Yudu county, and then sell products in Shenzhen. The wage expenditure is about more than 5,000 yuan monthly, and the annual income is about over 50,000 yuan. His wife said, when it’s rain, the road from the outside to the workshop is very difficult to walk, so the business is impacted. In addition, they are willing to contribute more money to help building the roads.

Xu Xiaomao (13879752291): He is the director of Datian Village, Xijiang Town, Huichang County, Ganzhou City, Jiangxi Province. There are 21 groups, 3200 people, and 700 families in this village. The cultivated land is 1,700 mu, and the orchard is 40-50 mu. Its annual per capita income is over 2,000 yuan, and locates among upper-intermediate in the town. There is 70-80% of the workforce do manual work outside perennially, mainly distributes in Longyan and Shishi city of Fujian province. After the railway opened, they could come back home more than 10 times every year instead of twice every year before. An automobile ticket needs over 50 yuan, but a train ticket is only 13 yuan now. Obviously, the cost to back home has reduced significantly, so it’s helpful to the stability of the family and the education of children.

Yuan chunyang (13860251803): He is the party branch secretary of Pingpu Village, Shanghang County. There are 735 people, 173 families, and 7 groups in this village. In addition, Pingpu village only has 120 mu of cultivated land, and its annual per capita income is 3,700 yuan. Its 200 mu of cultivated land was requisitioned, and 45 families were involved in the housing demolition and resettlement, but there isn’t any remaining issue. After the railway opened, a number of businessmen come to invest. Furthermore, relying on The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 100 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Shanghang station, this village established Pingpu Industrial Park which had been confirmed as the second industrial park of the county. The industrial park has played a positive role in the village economy promoting.

Xu fuming: Male, aged 48, junior high school education, Xiawang Group, Datian Village, Xijiang Town, Huichang County. He does manual work in the Longyan mine, has an annual income 30,000-40,000 yuan. There are 4 family members in all. His wife does manual work at Longyan too, earns 10,000 yuan annually. Two children are still pupils. Before, he and his wife went back home only when the farming is busy or the spring festival. Now, they go home as long as holiday. The children’s academic performances are improved, and the elders get better care than before.

Liu longjiao: Female, aged 33, junior high school education, villager of Zhongting Group of Datian Village, Xijiang Town, Huichang County. She works in a garment factory in Shishi City, and his husband does manual work in the garment factory too. The family annual income is 30,000 yuan. Now, if they want to go home, they could go to Quanzhou by train, and then take the automobile to Shishi City. It’s more convenient and cheaper than before. So, they can go home 5 or 6 times every year instead of 1 or 2 times like before. The 10-year-old kid is a pupil and goes to Shishi city to look his parents every summer vacation, and this meeting makes the parents and kid closer to each other.

Xu Yunfa: Male, aged 64, junior high school education, villager of Datian Village, Xijiang Town, Huichang County. There are 7 members in this family: the couple, the second son and his wife, a 10-year-old granddaughter, a 7-year-old granddaughter and a 5-year-old grandson. The eldest son lives independently, so is not included. The daughter married and moved to Ruijin. The second son does manual work in Shishi city Fujian province, and the son’s wife works in a garment factory in Shishi city too. The grandson is in the village kindergarten. The former house was one-storied, brick-concrete structured and 200 m2. Now, they have a new two-storied brick-concrete structured house with a size of 180 m2. This new house is built on their own homesite (the grain land was taken up). The second son and his wife make money through doing manual work, and they send money to home every festival. This is the main source of family income about 2,000 yuan annually. Because of the busy work, they hardly come back home except spring festival. This family also feeds 5 or 6 chickens and ducks which are self-supplying. The archaeological teams who are municipal or provincial and would build the expressway hired the second floor of this family house two months and paid for 600 yuan. The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 101 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Xu considers: it’s more convenient to come and go than before the demolition of railway; the living standards and environments are also improved obviously; the son and daughter-in-law work outside home can often come back. But unfavorable effect is that this family has less paddy field than before as the land acquisition of railway, so the agricultural income decreased severely which was the main source of the family economic income.

Xu chengquan: Male, aged 72, primary school education, lives in Datian Village, Xijiang Town, Huichang County. Since the separation of sons and daughters, there is only the old couple in this family. The wife is 73 years old. The plot of this family is only about 0.7 mu, the grain yields from this plot is just enough to this old couple. He feeds more than 20 chickens which are self-supplying too. The former house with a size of 400 m2 was demolished and compensated for more than 60,000 yuan. Xu gave the money to three sons. This family also has the fee for the transition 10 yuan/month/person. The new 2-room house with a size of 240 m2 is one-storied and brick-concrete structured. The new house also was given to sons, but the old couple still lives in the remnant part of the former demolished house.

Xu Liuliu: Male, aged 56, primary school education, villager of Datian Village, Xijiang Town, Huichang County. There are 6 members in this family, including his wife, a son and his wife, two grandsons. His wife is 52 years old, son is 27, daughter-in-law is 26, and all the family members do manual work in Wenzhou. The earth-wood structured part of the former house was 30 m2, and the brick-concrete structured part was about 70 m2. Now, this family has a two-storied brick-concrete structured house with a size of 120 m2. They have only 2 mu of paddy field and leased the field to others.

Xu Xianqin: Male, aged 57, junior high school education, villager of Datian Village, Xijiang Town, Huichang County. There 6 members in his family, including a son and his wife, two grandsons and a daughter. The son is 30 years old and his wife is 29 years old, they do manual work in Longyan city of Fujian province with monthly income about 2,000 yuan in total. The former house is earth-wood structured in a size of 50 m2. The compensation for the demolition of house was paid completely, and they also have the fee for transition 10 yuan/month/person. The new house is about 120 m2, one-storied and brick-concrete structured.

Xu Jianfa: Male, aged 53, primary school education, villager of Datian Village, Xijiang The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 102 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Town, Huichang County. There are 5 members in his family, including the wife, a son and his wife, a grandson. The wife is 45 years old, the son and his wife are 23, and the grandson is 6. Xu is a mason in the village. The son and his wife work in a garment factory in Shishi city of Fujian province. One part of the former house is brick-concrete structured, and the construction area of which part was about 200 m2. Another part of the former house is two-storied and earth-wood structured, and the construction area of which part was about 200 m2. This family also has the fee for transition 10 yuan/month/person. They had spent over 40,000 yuan to build a new two-storied house whose construction area is over 270 m2.

Yang Fengying: Male, aged 35, junior high school education, villager of Dongnao Group of Niushui Village, Xijiang Town, Huichang County. There are 3 members in his family, including the wife and son. The son is in kindergarten. Yang does mining work in Longyan city of Fujian province, earns about 1,000 yuan monthly, and comes back home 4 or 5 times every year. The new house of this family is 2-room and earth-wood structured, and the construction area is about 5 m2. They also have the fee for transition 10 yuan/month/person. Yang is intermediate in the village in terms of the economic condition.

Chen Manxiu: Male, aged 54, primary school education, villager of Weizi Group of Niushui Villager, Xijiang Town, Huichang County. There are 14 members in her family, including three sons and their wives, six grandsons and one granddaughter. Chen takes care of children at home, and the three sons and their wives all do manual work in Shishi city of Fujian province. The sons and their wives make money through doing manual work, and that money is the main source of family income. This family is among upper-intermediate in the village in terms of the living standards. The transition fee is also provided for the family 10 yuan/month/person.

Liu Mandi: Female, aged 39, primary school education, villager of Yuzi Group of Niushui Village, Xijiang Town, Huichang County. There are 5 members in her family, including the husband, two daughters and s son. The husband is 39 years old and does manual work with Liu. They earn about 3,000 yuan monthly together. The eldest 19-year-old daughter works outside and sends money to home sometimes. The son younger daughter all are 13 years old, and they are a sixth grade pupils in the village school. After the land acquisition of railway, this family still has 2.5 mu of paddy field and 0.5 mu of dry land. The former two-storied house was earth-wood structured, and the construction area was about 200 m2. Now, this family has a new 3-storied brick-concrete structured The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 103 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project house with a size of 220 m2. The transition fee is also provided for them 10 yuan/month/person. Liu thinks the living standards and environments are better than before, but then the way lead to family paddy field is further than before. This family is among upper-intermediate in the village in terms of the living standards.

Hu Nianfa: Male, aged 76, primary school education, villager of Niushui Village, Xijiang Town, Huichang County. There are 6 members in his family, including the wife, the son and his wife, the granddaughter. The son mines in Longyan city of Fujian province. The daughter-in-law farms at home. There is only 2 mu of paddy field after the land acquisition of railway. The son’s wage is the main source of family income. The former house was near 100 m2. The new house is brick-concrete structured, and the construction area is about 200 m2. The transition fee is also provided for this family 10 yuen/month/person. The daughter-in-law goes to meeting his husband in Fujian much more times after the railway was built. Furthermore, a train ticket is cheaper than an automobile ticket.

Hu Tianfu: Male, aged 47, high school education, villager of Niushui Village, Xijiang Town, Huichang County. There are 5 members in his family, including the wife, two sons and a daughter-in-law. The eldest 25-year-old son and his wife do manual work in Wenzhou. The second 23-year-old son has a small supermarket in the village. There is only 1 mu of paddy field after the land acquisition of railway, and the couple of Hu farms the paddy field. The former house of this family was two-storied and earth-wood structured, and the construction area was over 200 m2. The new house is four-storied and brick-concrete structured, and the construction area is over 200 m2 too. The transition fee is also provided for the family 10 yuan/month/person. The annual income from the second son’s small supermarket is 10,000 yuan almost, and the eldest son earns about 9,000 yuan annually. This family is among upper-intermediate in the village in terms of the living standards.

Hu Nanchang: Male, aged 52, junior high school education, villager of Niushui Villager of Xijiang Town in Huichang County, Ganzhou City, Jiangxi Province. There are 7 members in his family, including the wife, the eldest son and his wife, the daughter, two grandsons. The wife is 51 years old, primary school education, and stays at home. The eldest son is 28 years old, junior high school education, and does manual work in Shishi city. The eldest daughter-in-law is 29 years old, junior high school, and does manual work in Shishi city too. They earn 40,000 yuan annually in total. The younger The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 104 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project daughter and grandchildren are in school. There is 3 mu of cultivated land. The former earth-wood structured house was over 100 m2, and now this family has a new brick-concrete structured house with a size of 130 m2. The son comes back home much more times than before the Gan-Long railway built. Furthermore, the grandchildren can go to Shishi city meeting their parents in summer vacation, so the livelihood is improved.

Chen Xiaoqun (13607976667): She is the Party Branch Secretary of Banjing Village, Huichang County, Ganzhou City, Jiangxi Province. There are 2,256 people divided by 16 groups in the village. The cultivated land is 1,746 mu, and the mountain land is over 900 mu. There are 48 party members also. This village is the cradle of “pigs-biogas-fruits” model. Introduced orange since 1992, established the biogas pits in the 1970s, and introduced the new technology of biogas pits since 1985. Developed the fruit industry next to the 323 National Road in 1997, established an ecological corridor, requisitioned over 500 mu land to plant fruits. The orchard of this village was amounted to over 800 mu in 2003, and had taken initial scale. By 2006, there were over 2100 mu of orchard, 326 pits of biogas, and 80% of the population of the village with the biogas pits. In 2005, in light of the new rural construction, this village was advocated to establish 58 households eco-village, and implemented the “4 1”, a column pigs, a biogas pit, an orchard, and a house. Placed, no tree felling, no pond filling, advocate every household to plant 5 to 10 mu of orchard, land-based, so that the villagers can live on the land. The new rural construction of this village is mainly on ecological construction, “water electricity road”, and the infrastructure costs are from the government and the villagers. The villagers raised over 70,000 yuan to build road, and the government granted 100,000 yuan per km, therefore they could have built a 3.5 m wide cement road. There is only 45% of the villagers do manual work outside, and the elders don’t have to work outside the home. Most of the villagers are local residents; also there are some people from the outside. The local residents guide the people from the outside to plant the fruit trees. In general, the fruit trees would have the output in the second year, and the output of 1 mu orchard could reach over 5,000 yuan, the highest price reached 1.5 yuan/kg. The output of Chen’s orchard was over 3,000 kg navel oranges, and he hired more than 20 persons to help managing the orchard. The Party member, Zhong Jiandi, moved from another village, takes the lead in planting fruit trees with achieved in a considerable scale, and becomes a role model on getting rich.

Yang Ruisheng: Male, aged 53, junior high school education, villager of Nangang Village of Xianghu Town in Ruijin City. There are 5 members in his family, including the mother, the wife, the son and his wife. Yang’s mother is 78 years old. Yang’s wife, Gao Julan, is 48 years old. The 25-year-old son does manual work in Nan city of Fujian province,

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 105 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project comes back home one time every year, and earns about 1500 yuan monthly. The daughter-in-law also does manual work outside usually, but this year she stays at home because of pregnancy. This family has 1.9 mu of paddy field and about 6 mu of woodland. Yang and his wife do farming at home usually and the grain is self-supplying. The main source of family income is the wages of the son and his wife. The former house was two-storied, earth-wood structured, and the construction area was 112.75 m2. The new house is two-storied, brick-concrete structured, and the construction area is about 190 m2. As the resettlement, this family rented a house as the habitation since the year 2,000. The transition fee is given to this family 40 yuan/person. Yang thinks that the inhabitancy conditions are improved obviously, the sanitation and ventilation are also better than before. But it’s a little far to the family cultivated land for farming.

Xie Shengbing: Male, aged 55, high school education, villager of Xiewu Group of Nangang Village, Xianghu Town, Ruijin City. There are 4 members in his family, including the wife, the son and his wife. The 24-year-old son does manual work in Amoy, comes back home one time every year, and earns 1100 yuan per month. The 23-year-old daughter-in-law is out of work and stays at home. This family only has 0.2 mu of paddy field and 0.5 mu of woodland. The former house was earth-wood structured, and the construction area was about 300 m2. It was divided into 4 parts, three of them were given to the three older sons, and the elders live with their youngest son and they got the residual part of house. This former house was compensated for 140 yuan/m2, and the money was paid up already. The transition fee also is given for this family 10 yuan/month/person. The new house built in 2005 is two-storied, brick-concrete structured, and the construction area is 90 m2. During the railway demolition and resettlement, they rented a house outside near 2 years, got the transition fee 40 yuan (10 yuan/person * 4 monty) and removing fee 100 yuan. The son’s wage is a part of the family income, besides, Xie is the village group leader and could get some small projects with annual income 20,000 to 30,000 yuan. Xie said the ways lead to paddy field and woodland are less convenient than before. Moreover, there is no water source.

Liu Houbo: Male, aged 53, primary school education, villager of Xiewu Group of Nangang Village, Xianghu Town, Ruijin City. There are 6 members in this family, including the wife, the son and his wife, the daughter, the grandson. The wife is 51 years old and does housework at home. The 27-year-old son worked in a mold factory formerly, but now at home. The 28-year-old dahghter-in-law is a typist in Ganzhou city and earns 400 yuan monthly. The 3-year-old grandson is a slight disability. The 16-year-old The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 106 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project daughter is in high school. This family has 1.2 mu of paddy field and 0.2 mu of woodland. Formerly, this family had an earth-wood structured house whose construction area was about 100 m2, and they also got a part of progenitor housing with a size of 6 m2. These housings belong to this family were compensated for over 10,000 yuan in total. The new house is three-storied, brick-concrete structured, and the construction area is 90 m2. Liu has a small store on the ground floor of the new house. During the housing demolition and resettlement, this family rented a house near 3 years, and got the transition fee over 200 yuan, the house moving fee 100 yuan. Besides, 260 yuan was compensated for the progenitor grave relocation. Because the grandson has a slight disability, Liu has not a good mind always, and when he rode a motorcycle, he fell from the motor and injured. Since the treatment spent a lot of money, the living standard of this family is not very good.

Qiu Muqing: Male, aged 54, junior high school education, villager of Xiewu Group of Nangang Village, Xianghu Town, Ruijin City. There are 6 members in his family, including the wife, the eldest son, the second son and his wife, the grandson. The wife is 49 years old, and does odd job with 20-30 yuan per day. The eldest son is 29 years old, does manual work in city, and earns about 1,000 yuan monthly. The second son is a mason, and works in the village with about 60 yuan per day. The second son’s wife is 25 years old, and takes care of the child at home. The grandson is 2 years old. This family only has 0.6 mu of paddy field after the land acquisition. The former house was earth-wood structured, the land of which was 181 m2. They have got all the money that was compensated for the house demolition and resettlement. The transition fee is also provided for this family 10 yuan/month/person. This family has two new brick-concrete structured houses, and the construction area of each house is 90 m2. Liu, his wife and his eldest son have one, and anther one belongs to the young son and his wife. Because of his poor health, he must spend 5 or 6 hundreds yuan for the medicines. This family is impoverished in the village. Qiu could farm and feed livestock before, but now he can’t. The grain and many other supplies need to buy, not like previous self-support.

Yang Jiahuo (13507070872): Male, aged 59, junior high school education, villager of Meigang Village, Shazhouba Town, Ruijin City. There are 4 family members, including the son and his wife, the grandson. The son is 27 years old, and does manual work in Guangdong with annual income 10,000 yuan. The daughter-in-law is 28 years old, and takes care of the child at home. The grandson was just born soon. After the adjustment of village land, this family only has 0.9 mu of paddy field, and leases the field to others. Yang is a carpenter and earns 4 or 5 thousand yuan per year.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 107 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project The former house was earth-wood structured, and the construction area was 46 m2. They have got 4,000 yuan already that was compensated for the housing demolition. The transition fee was also paid for this family with 10 yuan/month/person. Now, this family has a new brick-concrete structured house which had been built in 2003. Moreover, the construction area is 120 m2. Yang said the railway demolition and resettlement didn’t impact on their living very much. But, the living condition is better, and the inhabitancy conditions are also improved obviously.

Liao Yuanlu: Male, aged 45, junior high school education, villager of Meigang Village, Shazhouba Town, Ruijin City, Jiangxi Province. There are 4 members in his family, including the wife, two daughters. The wife is 35 years old, and does housework at home. The eldest daughter is 16 years old and a second-year student in the village high school. The young daughter is 12 years old and a second grade pupil in the village primary school. Now, this family only has over 2 mu of paddy field, they lease a part of the field to others as a nursery and cultivate the other part themselves. Liao does odd job sometimes, and earns 600 yuan monthly, but it’s unstable. The former house was earth-wood structured, and the construction area was 114 m2. This family was compensated for 13,000 yuan which had been paid completely. The transition fee was also paid for this family 10 yuan/month/person. The new house is brick-concrete structured, and they have built only one floor. The economic condition of this family is not very well, so they have the peanut oil that was pressed by themselves. Besides, this family feeds two head cattle. The daughter goes to school free, but have to pay some books. The vegetables they eat are grown by themselves. Furthermore, there was not enough money to bury Liao’s mother when she died, so he borrowed some money, and this family is still in debt yet.

Chen Lianxing: Male, aged 45, junior high school education, villager of Group 3 of Liangkang Village, Gucheng Town, Changting County. There are 7 members in his family, including the wife, the parents, the eldest son and his wife, the grandson, the young son. The Chen’s wife is 43 years old, and farms with him at home. The father is 84, the mother is 75. The eldest son and his wife work in the Industrial Park of the county with monthly income over 1,000 yuan respectively. The young son is 20 years old and does manual work in Amoy. The grandson is 2 years old. This family has only 0.5 mu of paddy field now. Chen is the contractor of 20 mu of mountain, and he also rents 2 mu of other people’s field in return for 100 kg grain. He grows the bamboos at the contracted mountain, and the bamboos can be processed into many kinds of products. This village income is largely from the sale of bamboo products. So the local cultivation of bamboo is in the large-scale. After the railway built, the price of bamboo products increased; therefore, the local economy is The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 108 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project promoted by the high value-added bamboo products very much. The demolished house was two-storied and earth-wood structured, and the construction area was 141 m2. Now, this family has a new two-storied brick-concrete structured house, and the construction area is 140 m2. In addition, this new house was built in 2002. During the housing demolition and resettlement, they rented a house six months. The transition fee was also paid for this family 3 yuan/m2. This family was compensated for over 23,000 yuan in total. The family durable consumables: a TV, an electric fan, a VCD, a motorcycle. This family is intermediate in the group in terms of the living standards. It’s more convenient to work outside after the railway built. The living condition is better, and the inhabitancy conditions are improved obviously. However, this family is still in debt as building the new house.

Zeng Jixian (0597-6718538): Male, aged 59, primary school education, villager of Group 7 of Liangkang Village, Gucheng Town, Changting County, Longyan City. There 4 members in his family, including the wife, the son and daughter. The wife is 58 years old and farms at home. The 24-year-old son does manual work in industrial park of the county and earns over 1,000 yuan per month. The 17-year-old daughter just started to do manual work in Guangdong since this year, earns about 700 yuan monthly. This family only has 0.5 mu of paddy field after the land acquisition. They also contract over 20 mu of mountain for cultivating bamboo, and the annual income from the bamboo is over 10,000 yuan. The former house was earth-wood structured, and the construction area was over 100 m2. This family compensated for 20,000 yuan in total, and the money had been paid completely. They didn’t build a new house, but bought a secondhand house in the village. The secondhand house nears road, so it’s very convenient. Moreover, it’s very cheap and has complete procedures. Zeng showed investigators of external monitoring agency the title deed, the collective land use warrant, and the approved of the building. This house is also earth-wood structured, the homesite is 246 m2, and the construction area is 160 m2. It’s convenient to transport the bamboos after the railway built, and the price of bamboo increases continually, so the villages benefited. Zeng’s family is intermediate in the group in the living conditions. There are some household appliances in this family, such as a color TV, a VCD.

Fu Yisheng (0597-68812487): Male, aged 76, primary school education, villager of Group 1 of Guangming Village, Datong Town, Changting County, Longyan City. There are 6 members in his family, including the wife, the son and his wife, two grandsons and a granddaughter. The wife is 78 years old and farms at home. The son is 50 years old, does manual job in the town with monthly income 1200 yuan. The daughter-in-law is 48 years old and farms at home. The eldest grandson is 25 years old, does manual work in The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 109 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project city of Fujian province, and earns over 700 yuan per month. The young grandson is a student in Jimei University, and the tuition is over 10,000 yuan per year. The granddaughter is 19 years old and works in Amoy with monthly income 600 yuan. Now, this family has over 3 mu of paddy field, and contract 30 mu of woodland. They grow tobacco, and the annual income is about 10,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was 200 m2. Now, this family has a new three-storied brick-concrete structured house and the construction area is 118 m2. They spent 70,000-80,000 yuan to build the new house that has a collective land use warrant. After the house demolition and resettlement, the living conditions are better and the inhabitancy condition is also improved. The household appliances: a TV, a VCD, a water heater and so on. The living standard of this family is middle class in the group.

Liao lvchang (0597-6801161): Male, aged 45, high school education, villager of Group 1 of Guangming Village, Datong Town, Changting County, Longyan City. There are 4 members in his family, including the wife, the son and the daughter. He is a tractor driver. The wife is 44 years old, primary school education. The 21-year-old son is a soldier in Tibet. The 23-year-old daughter is a student in Zhangzhou Normal College, and the tuition is over 10,000 yuan per year. Now, there is over 2 mu of paddy field and 10 mu of retained hill. In addition, he contract 25 mu of woodland. The annual income is more than 10,000 yuan. The construction area of the former two-storied house was 120 m2, and about 40 m2 of which was earth-wood structured, the rest part of which is brick-concrete structured. This family was compensated for 37,000 yuan. Now, there is a new 2.5-storied brick-concrete structured house, and the construction area is 100 m2. They spent 150,000 yuan to build and decorate the new house. The living conditions are improved, the inhabitancy condition is also better than before. The household appliances: a TV, a VCD, electric fans and so on. The living standard of this family is middle class in the group.

Fu Zixin: Male, aged 69, primary school education, villager of Group 1 of Guangming Village, Datong Town, Changting County, Longyan City. There are 4 members in his family, including the wife, two sons. The wife is 69 years old. The second son is 38 years old and has intellectual disability. The third son builds road in Zhangzhou city of Fujian province, and does odd job sometimes. Now, there is 0.5 mu of paddy field, over 20 mu of woodland, subcontract to others, and the annual income is about 6,000 yuan. The construction area of the former house was over 200 m2, two-storied, which was compensated for 30,000 yuan. Now, they have a new 2-storied brick-concrete house, and the construction area is 67.5 m2. They spent over 30,000 yuan on building The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 110 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project this new house. There is no big change about the living after the house demolition and resettlement. But the separation of the eldest son affected the family living in some degree.

Rao Mulin (0597-6818601): Male, aged 38, junior high school education, villager of Group 1 of Guangming Village, Datong Town, Changting County, Longyan City. There are 5 members in his family, including the mother, the wife, the son, the daughter. The wife is 38 years old; the mother is 78 years old. The son and daughter just graduated from the primary school, and they are all 14 years old. The tuition was more than 200 yuan each semester. Rao is a carpenter and works in the county seat. There is about 2 mu of paddy field. In addition, this family contracts 30 mu of woodland and subcontracts to others. The annual income is more than 20,000 yuan, and that the income from planting vegetables is 5,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was 120 m2. That house was compensated more than 20,000 yuan for the demolition. Now, they have a new 3.5-storied brick-concrete structured house, and the land of this house is 100 m2. The new house cost 100,000 yuan. The household appliances: a TV, an electric cooker, an electric fan and so on. The living standard of this family is intermediate in the group. After the demolition and resettlement of railway, the living and inhabitancy conditions are also better than before.

Rao Rongsheng (0597-6827796): Male, aged 49, high school education, villager of Group 1 of Guangming Village, Datong Town, Changting County, Longyan City. There are 6 members in his family, including the mother, the wife, two daughters and a son. The wife is 51 years old; the mother is 64 years old. The eldest 25-year-old daughter married and moved to Zhangzhou. The 21-year-old son is a driver and works in county seat, and earns more than 2,000 yuan each month. The young daughter is 22 and a student in Quanzhou Medical College, the tuition is more than 10,000 yuan every year. Rao is a truck driver. The family annual income is more than 60,000 yuan. Now, there is 0.5 mu of paddy field and 40 mu of woodland that had been subcontracted to others. Rao and his two young brothers are the co-owners of the former two-storied house. 90 m2 of the former house was brick-concrete structured and the rest part was earth-wood structured. This family was compensated more than 90,000 yuan for the house demolition. Now, they have a new 3.5-storied brick-concrete structured house, and the land are of which is 120 m2. They spent 150,000 yuan to build and decorate the new house. The family durable consumables: a TV, a washer, electric fans, a VCD and two motorcycles. This family is among upper-intermediate in the group in terms of the The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 111 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project living conditions. The living conditions are better than before, and the inhabitancy condition is also improved obviously. They are satisfied with the resettlement.

Yang Dezhang (0597-8365193): Male, aged 50, junior high school education, villager of Xiapinger Group of Liangzeng Village, Pengkou Town, Liancheng County, Longyan City. There are 4 members in his family, including the wife, two sons. The wife is 43 years old and farms at home. The eldest son is 22 years old, the second son is 20 years old, and they are all do manual work in Amoy and earn more than 1,000 yuan monthly. The two sons come back home only once every year. Yang has a store in the village with monthly income 300 yuan. There is 2 mu of paddy field, and the annual agricultural income is more than 2,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was 125 m2. This family was compensated more than 20,000 yuan for the house demolition. Now, they have a new brick-concrete structured house whose construction area is 110 m2. Moreover, the first floor of the new house had been built, but the second floor isn’t built yet. The transition fee for this family was paid by the Railway Office. And they rented a house for transition near 3 months. The family durable consumables: a TV, electric fans, a motorcycle. The living conditions are improved after the railway built. The son can go to do manual work outside. They are satisfied with the resettlement.

Yang Mingxing (0597-8368645): Male, aged 52, primary school education, villager of Xiapinger Group of Liangzeng Village, Pengkou Town, Liancheng County, Longyan City. There are 5 members in this family, including the wife, the son and his wife, the grandson. Yang drives, builds road, and does odd job in Shanghang County. The wife is 52 years old and farms at home. The 33-year-old son is a teacher in Pengkou Town High School. The 33-year-old daughter-in-law does housework at home. The 6-year-old grandson is in kindergarten. Now this family has more than 2 mu of paddy field, plants double-crop rice, the output of the paddy field is more than 1,000 kg. The former house was brick-concrete structured, two-storied, and the construction area was more than 200 m2. This family was compensated 30,000 yuan for the house demolition. They rented a house outside near 3 months after the house demolition. The transition fee was paid by the Railway Office. Now they have a new brick-concrete structured house, tow-storied, and the construction area is 110 m2. The family durable consumables: a fridge, a TV, an electric fan and a motorcycle. The inhabitancy conditions are improved obviously, but the way to their paddy field is far.

Yang Qinshui (0597-8369785): The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 112 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Male, aged 58, primary school education, villager of Xiapinger Group of Liangzeng Village, Pengkou Town, Liancheng County, Longyan City. There are 13 family members. The wife, Fu Dongxiu, is 55 years old. The mother-in-law is 80. The second son is 34 years old, and farms at home since he demobilized. The second daughter-in-law is 34 years old and farms at home too. The third son and his wife are teachers and work in Pengkou High School with monthly income 700 yuan respectively. The forth son is 28 years old, and does manual work in Longyan. The forth daughter-in-law is 21 years old, and does housework at home. The granddaughter is 6 years old, the eldest grandson is 2, and the young grandson is 1. The nephew, Yang Hongsheng, is 19 years old, and learning to become a cook in Amoy. The demolished house belongs to Yang Hongsheng, as the death of his father, he lives with his uncle Yang Qingshui. There is 4 mu of paddy field, and the annual income is about 3,000 yuan. Yang plants oranges, and the annual income is about 5,000 yuan. The demolished house was earth-wood structured, two-storied, and the construction area was 80 m2. This family was compensated more than 10,000 yuan for the house demolition. The new house is one-storied, brick-concrete structured, and the construction area is 80 m2.

Wang Chuxun (0597-8368594): Male, aged 63, primary school education, villager of Group 2 of Wangcheng Village, Pengkou Town, Liancheng County, Longyan City. There 4 family members, including the wife, tow sons. The wife is 61 years old, and farms at home. The eldest son is 30 years old, the younger son is 27 years old; they are all do manual work in Amoy, and come back home twice every year. They have 3 mu of paddy field, plants double-crop rice, and the grains supply themselves. In addition, this family feed more than 20 chickens. The construction area of the former house was 380 m2, the earth-wood structured part of that house was two-storied with a size of 200 m2, and the brick-concrete structured part of that house was one-storied with a size of 180 m2. This family was compensated more than 50,000 yuan for the house demolition in total. Moreover, the transition fee was near 10,000 yuan. Now, there are 2 tow-storied new houses, and each of them covers 160 m2. They spent more than 120,000 yuan to build and decorate the new houses. In addition, they rents out one of the new houses to others as a shop, and the rent is 300 monthly. The living standard is better than before, and the inhabitancy conditions are also improved obviously. The family durable consumables: a TV, an electric fan, an electric cooker, a motorcycle.

Yuan Zengsong (0597-362347): Male, aged 55, high school education, villager of Pingpu Village, Shanghang County, Longyan City. There are 8 family members, including the wife, the eldest son The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 113 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project and his wife, the younger son and his wife, the grandson and granddaughter. The wife is 55 years old and farms at home. The eldest son is 33 years old. He is the amanuensis of the village and the director of Fengnong Food Factory, earns more than 10,000 yuan annually. The eldest daughter-in-law is 33 years old, and she works in the food factory with monthly income 400 yuan. The younger son is 25 years old, and he is the director of Office in Sichuan, Zhejiang Yongnong Chemical Co., monthly income 1,200 yuan. The younger daughter-in-law is 24 years old, and she is an ordinary worker of Office in Sichuan, Zhejiang Yongnong Chemical Co. The granddaughter is 8 years old and a pupil in Pingpu Primary School. The grandson is only 3 years old. 6 mu of paddy field was requisitioned from this family, now they have only 0.8 mu of dry land. Due to the compensation standard that 6,000 yuan for each mu of paddy field, this family was compensated for 36,000 yuan in total. The former house was earth-wood structured, two-storied, and the construction area was 140 m2. The new house is brick-concrete structured, 2.5-storied, and the construction area is 125 m2. They spent more than 110,000 yuan to build and decorate the new house. The transition fee was 280 yuan, then there were 7 family members, and they rented a house near 11 months. The family durable consumables: a TV, an electric fan, a motorcycle. This family is among upper-intermediate in the group in terms of the living conditions.

Yuan Wenbing (15959739746): Male, aged 31, junior high school educations, villager of Pingpu Village, Shanghang County, Longyan City. There are 6 family members, including the parent, the wife, the son, the young brother and his wife. His father is 63 years old; the mother is 57; and they all farms at home. The wife is 26 years old and does housework at home. The son is 5 years old and a pupil in the village kindergarten. The young brother and his wife all do manual work in Amoy with monthly income 1,000 yuan and 800 yuan respectively. Now, this family has 0.5 mu of paddy field and 0.2 mu of dry land. The family annual income is 7,000 to 8,000 yuan. This family was compensated 12,000 yuan for the requisitioned 2 mu of paddy field. The former house was earth-wood structured, two-storied, and the construction area was 150 m2. The demolished house was also compensated for about 35,000 yuan. Now, there is a new brick-concrete structured house, two-storied, and the construction area is 100 m2. In addition, they spent more than 50,000 yuan to build and decorate the new house. There are 5 members in this family, and they rented a house near 10 months before the new house built. During that time, the transition fee was given 200 yuan/month. As the cultivated land was requisitioned mostly, the annual agricultural income is only more than 1,000 yuan now, instead of former 4,000-5,000 yuan.

Yuan Yanmu (0597-3623900): The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 114 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Male, aged 57, primary school education, villager of Pingpu Village, ShanghangCity (his son, Yuan Zhigao, interviewed). There are 6 family members, including the wife, the eldest son and his wife, the granddaughter, and the daughter. The wife is 51 years old, primary school education. The eldest son, Yuan Zhigao, is 28 years old, and works in Guangming Oxygen Manufactory with monthly income 800 yuan. The daughter-in-law is 25 years old and does housework at home. The daughter is 17, and a second-year student in Jiaoyang High school. The granddaughter is 2 years old. This family has 1 mu of paddy field, plants single-crop rice, and the food can be self-sufficient. The family annual income is about 10,000 yuan. This family was compensated more than 30,000 yuan for the requisitioned 4 mu of paddy field. The former house was earth-wood structured, two-storied, and the construction area was 120 m2. Now, this family has a new brick-concrete structured house, 2.5-storied, and the construction area is 125 m2. The new house with no decoration cost them 70,000 yuan. The family durable consumables: a TV, a fridge, an electric fan and a motorcycle. The living standard is improved obviously, and the inhabitancy conditions are also better than before.

Yuan Huanyang (13559971212): Male, aged 32, junior high school education, villager of Pingpu Village, Shanghang County. There are 5 family members, including the mother, the wife, a daughter and a son. Yuan is a worker in Guangming Oxygen Manufactory and earns 700 yuan monthly. His mother is 58 years old and farms at home. The wife is 32 years old and does housework at home. The 7-year-old daughter is in kindergarten. The son is 1 year old. This family was compensated 12,000 yuan for the requisitioned 2 mu of paddy field. Now, they have only 0.5 mu of dry land, plants single-crop rice, the output is about 200 kg, and the food can be self-sufficient. The family annual income is bout 8,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was more than 80 m2. They got more than 10,000 yuan for the compensation of the house demolition. The new house is brick-concrete structured, 2.5-storied, and the construction area is 200 m2. This undecorated new house cost them more than 60,000 yuan. They rented a house near 11 months before the new house built, and the transition fee was paid 160 yuan ( 4 person * 40 yuan). This family has a TV and motorcycle. The living condition of this family is intermediate in the village.

Qiu Binglin (0597-3623971): Male, aged 41, villager of Pingpu Village of Shanghang County. There are 4 family members, including the wife, a daughter and a son. The wife is 41 years old and farms at home. The 15-year-old son is a first-year student in Jiaoyang Junior High school, and the tuition is 800 yuan per year. The 17-year-old daughter is a first-year student in Gutian High School, and the tuition is 2000 yuan per year. Now, this family The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 115 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project has 0.8 mu of paddy field, plants single-crop rice, the output is about 400 kg, and the food can be self-sufficient. Qiu farms and does odd job; the family annual income is about 6,000-7,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was over 200 m2. This family got more than 20,000 yuan for the compensation of the house demolition. The new house is brick-concrete structured, 2.5-storied, and the construction area is over 200 m2. They had spent over 120,000 yuan to build and decorate the new house. This family also rented a house near 14 months before the new house built, and they got the transition fee completely. This family has a TV, an electric fan and a motorcycle. The living standard is middle.

Qiu Jinming (1399061479): Male, aged 43, junior high school education, villager of Pingpu of Shanghang County. There are 4 family members, including the wife, a son, and a daughter. The wife is 38 years old and farms at home. The 16-year-old son is a first-year student in Jiaoyang Junior High School, and the tuition is over 800 yuan every year. The daughter is only 2 years old. Now, this family only has 0.8 mu of paddy filed, plants single-crop rice, the output is about 400 kg, and the food can be self-sufficient. The family annual income is about 5,000 yuan. The former house was earth-wood structured, two-storied, and the construction area was over 100 m2. They had got over 20,000 yuan for the compensation. The new house is brick-concrete structured, two-storied, and the construction area is 160 m2. The new house cost them 6,000-7,000 yuan. They rented a house for 14 months before the new house built, and they got the transition fee completely. This family has a TV, an electric fan, and a motorcycle. The living standard is middle in the village.

Yuan chunyang (13860251803): He is the party branch secretary of Pingpu Village, Shanghang County. There are 735 people, 173 families, and 7 groups in this village. In addition, Pingpu village only has 120 mu of cultivated land, and its annual per capita income is 3,700 yuan. Its 200 mu of cultivated land was requisitioned, and 45 families were involved in the housing demolition and resettlement, but there isn’t any remaining issue. After the railway opened, a number of businessmen come to invest. Furthermore, relying on Shanghang station, this village established Pingpu Industrial Park which had been confirmed as the second industrial park of the county. The industrial park has played a positive role in the village economy promoting.

Wu Baihua (0597-2556596): Male, aged 36, junior high school education, villager of Xinghui Village of The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 116 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project Xiaochi Town, Xinluo Borough. There are 4 family members, including the mother, the wife, and a son. Wu manages a hotel in the village. The mother is 56 and farms at home. The 35-year-old wife helps Wu managing the hotel. The 11-year-old son is a third grade pupil in the village primary school. The former house was brick-concrete structured, three-storied, and the construction area was 400 m2. They had got over 140,000 yuan for the compensation. The new house is brick-concrete structured, four-storied, which built in 2004, and occupied in June 2005. They rented a house outside about more than 1 year. Because the hotel is near the railway, noisy, and the economy of Xiaochi Town is not very good, the hotel business is in general.

Zhang Yinglin (15959703793): Male, aged 42, junior high school education, villager of Group 2 of Xinghui Village, Xiaochi Town, Xinluo Borough. The wife is 40 years old, primary school education. The 15-year-old son is a first-year student in a local junior high school, and the tuition is over 500 yuan per year. Now, this family has no land, so they rent and cultivate other person’s land. The family income mainly depends on weaving bamboo mats, and annual income is about 10,000 yuan. As the family land is all requisitioned, the food source is lost, and they can not raise pigs. There are some difficulties in the family life. The former house was brick-earth structured, and the construction area was 50 m2. They had got over 10,000 yuan for the compensation, including 10 months of the transition fee. The new house is brick-concrete structured, three-storied, and the construction area is 60 m2. They spent over 7,000-8,000 yuan to build and decorate the new house.

Zhang Qiumei (0597-2129835): Female, aged 56, junior high school education, villager of Group 2 of Huixing Village, Xiaochi Town, Xinluo borough. There are 5 family members. The husband, Rong Cun, is 63 years old, works at Longhua Cement Plant, and earns about 1,000 yuan monthly. The 44-year-old son, high school education, has a store in Longyan. The 33-year-old daughter-in-law helps his husband managing the store. The 16-year-old grandson is a second-year student in Xiao Junior High School. The former house was earth-wood structured, two-storied, and the construction area was over 100 m2. The new house is brick-concrete structured, 3.5-storied, and the construction are is 80 m2. In addition, the compensation and transition fees had been paid already.

Wu Haojin (0597-2580772): Male, aged 56, primary school education, villager of Xiyang Village, Dachi Town, Xinluo Borough. There are 5 family members, including the mother, the wife, a The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 117 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project son and his wife. The mother is 85 years old. The wife is 52 years old, does housework and farms at home. The 30-year-old son enrolled Henan Nanyang Weapons College to study machinery manufacturing in 1995, was assigned to Lung Group after graduating in 1999, and becomes a skilled worker with monthly income 2,000-3000 yuan. The daughter-in-law is a worker of Lung Group, and earns over 1,000 yuan monthly. Furthermore, the son had bought a set of house in the city, and the construction area is over 100 m2. This family has 10 mu lands, of which 9 mu of paddy field plants double-crop rice, and the rest 1 mu of paddy field has been changed to the dry land with compensated 200-300 yuan. The agricultural costs increased, each mu field of employment is 140 yuan/person, and planting seedlings is 70 yuan/person/mu. The requisitioned land of this family was 1 mu, and the compensation was over 8,000 yuan. According to the regulations, the village committee took 20% of the compensation fee as a public welfare fund for the village road and water supply projects. The village was requisitioned 10 mu land in total, including the village’s old warehouse. This family’s house isn’t demolished, and which is earth-wood structured. The construction area is 180 m2, and the homesite area is 360 m2. Furthermore, this house was built in 1980. As the railway is near, the noise and vibration are big.

Wu Liping (13507535818): Male, aged 32, high school education, Party Branch Secretary of Xiyang Village, Dachi Town, Xinluo borough. There are 4 family members, including the father, the wife, and a daughter. The father is over 70 years old and skillful in farming. The 29-year-old wife helps his husband at whose agricultural supply store. The daughter is only 1 years old. This family has 10 mu lands. As Wu has an agricultural supply store, large-scale, the annual income is considerable, about 40,000-50,000 yuan. Because the village hasn’t income, the cadres almost haven’t wages, his family’s income mainly depend on the store. The house is brick-tile structured, and the construction area is over 200 m2.

Wu Xincai (0597-2585282): Male, aged 57, high school education, villager of Xiyang Village, Dachi Town, Xinluo Borough. There are 8 family members, including the wife, the eldest son and his wife, a granddaughter, the second son, and a daughter. The 53-year-old wife farms at home. The eldest son works in the town government, the daughter-in-law works in the city WCB, and their daughter is 2 years old. The second son is 26 years old, works in the City Material Bureau. The daughter is 24 years old, works in Longyan Medicine Company. This family has about 7 mu land, and the railway requisitioned 1 mu. The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 118 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project This family’s house is earth-wood structured, of which the homesite is allocated uniformly, and the construction area is over 200 m2.

14.4 A Copy of the Agreement on Land Acquisition and Resettlement

Signed between the Ministry of Railways, Jiangxi Province and

Fujian Province

Agreement on Issues Concerning the Construction of Ganzhou-Longyan Railway between the Ministry of Railways and the Provincial Governments of Fujian and Jiangxi

To promote the progress of the Ganzhou-Longyan Railway construction, and to ensure its smooth implementation, an agreement has been reached between the Ministry of Railways and the Provincial Governments of Fujian and Jiangxi after thorough consultation, and the agreement in detail is as follows: 1. On the Joint Construction of the Railway The construction of Ganzhou-Longyan Railway is promotive to the territorial development, to casting off poverty and setting out on the road to prosperity in the South Jiangxi and West Fujian regions (originally the Central Soviet Area), and to the economic development of Fujian and Jiangxi Provinces. In addition, the railway is critical to the improvement of Fujian’s coastal defense transportation conditions, to the enhancement of the economic connections of the East, the Middle and the West of China. As the investment for the project is huge, and the prospect of economic benefit is not so lucrative, it is necessary for the Central Government and the Local Governments to join hands to create necessary construction conditions and build the railway with concerted efforts. Specifically, the Ministry of Railways should be responsible for the construction and running of the railway, while Fujian and Jiangxi provinces should be responsible for land acquisition and house demolition, and for practicing favorable policies in taxation and prices of the local building materials, so that a good external environment is created for the railway construction.

2. On Land Acquisition, House Demolition and Relocation The comprehensive unit price for the land permanently acquired by railway construction (including land compensation, resettlement compensation, young crops compensation, the fund for developing new vegetable fields, compensation for plants such as wood trees and fruit trees, etc, the expense of land reclamation, and the “Forestry Law”-prescribed The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 119 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project compensation for forest acquisition, resettlement compensation, the compensation for restoration of forest vegetation, the compensation for forest, the management expenses and the contingency allowance) is 8000 yuan/mu. The price of earth fetching land and earth dumping land (including reclamation fee and young crops fee) is 3500 yuan/mu for farmland, and 1500 yuan/mu for unused land. And the compensation standards of various land types are determined by the provincial government through adjustment and negotiation. The comprehensive unit compensation price for the demolished buildings (including permanent one-story or multi-story buildings of brick-concrete, brick-tile, brick-wood, or earth-wood structures, owned by organizations or individuals, is 220 yuan/m2. And the compensation standards of various house types are determined by the provincial government through adjustment and negotiation. The unit compensation prices of other structures, such as brick and tile kilns, cultivating facilities, graves, water wells or motor-pumped wells, etc., will be determined through further consultation in conformance with the principle of adopting the ceiling of the low prices for other structures. The land acquisition, house demolition and relocation are implemented by Longyan people’s government in Fujian, and Ganzhou people’s government in Jiangxi in a unified way in accordance with “The Land Administration Law of the People’s Republic of China”. The fund for the work of land acquisition, demolition and relocation is fixed, and the cost beyond this fixed fund will be borne by the local governments. The amount of acquired land and the area of demolished houses should be calculated on the basis of the construction plan (including design alteration) and verified by the field survey jointly conducted by the railway authority and the local governments. The land acquired for the station square and the station facilities should be compensated according to this comprehensive unit price, and should be transferred in time and in phases to the construction units according to the progress of the construction in order to meet the needs of land for railway construction.

3. On Preferential Policies To ensure the smooth progress of the project, the following agreement is reached between the two parties through bilateral consultation: A. Fujian and Jiangxi provinces agree to waive the compensation for mineral resources, the charge for water resources, the charge for auxiliary projects of urban construction, the surcharge of education, the charge for funds of land acquisition and water conservancy, the fee of water soil conservation, and some other charges. The abatement and remission of the taxes should be jointly applied for by both the ministry and the province to The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 120 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

the state, to halve the sales tax of the construction enterprises, and abate the tax for the occupation of cultivated land levied upon the construction enterprises. The fees set by the provincial and the along-line local governments should be waived. The taxes and fees, which have been publicly cancelled by the decrees issued by the state and the governments of Fujian and Jiangxi provinces should not be levied. B. In the principle of controlling the cost and save the investment, the related departments of Fujian and Jiangxi provinces, and those of Ministry of Railways should jointly set a price ceiling, introduce a market competition mechanism, adopt the lowest and most favorable prices free of local taxes and fees in order to provide the construction materials (such as sand, gravels, etc.) water, electricity and telecommunication service to the construction units of Ganzhou-Longyan Railway Project.

C. For the utilization of parts of the along-line highways and rural roads in the railway construction areas by the railway construction units, the parties concerned should provide convenience, such issuing toll-free passes (free of road toll and bridge toll) to the construction units. Meanwhile, for the temporary acquisition of land for temporary roads and the temporary facilities for the railway construction, the railway construction authority and the local governments should follow the principle of reciprocity, and try to combine the railway construction with the development plans of the local township and towns. The related departments of Fujian, Jiangxi, and the Ministry of Railways in charge of the management of the local constructional materials, such as sand, gravels, etc., water, electricity and telecom required by the Project should jointly draw a price ceiling in conformance with the principle of investing frugality, and introduce in a market competition mechanism. The prices should be favorably low and free of charge of extra local taxes and fees. D. For the relocation of the power lines, telecommunication lines, broadcast The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 121 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

network, Fujian and Jiangxi governments are responsible for coordinating the relevant organizations and sectors to provide assistance and offer services to the railway construction units at favorable prices.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 122 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

14.5 The Photocopy of a Sample Page of the Resettlement Agreement

between the Implementation Agency and the Affected Household

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 123 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 124 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 125 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 126 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

14.6 Photos Reflecting the Work of Resettlement

Resettlement 2(R2) Guanzhishan Rail Station of Liancheng County

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 127 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

R 3 Investigators of External Monitoring Agency are having an Informal Discussion with Wu Yunlai’s Family, a Household to be relocated from Jiangkou Town of Ganxian County

R 4 Resettlement Site in Niushui Village of Xijiang Town, Huichang County

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 128 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

R 5 The New Home of Xu Yunfa from Datian Village of Xijiang Town, Huichang County

R 6 Seminar on Resettlement by Ganxian County Railway Construction Supporting Office

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 129 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

R 7 Yan Chaolin’s Land Deed of His New House, Yangmei Village of Luoao Town, Yudu County

R 8 Chen Lian’s House under Demolition, Hehe Village, Yudu County

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 130 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

R 9 Chen Lian’s New House, Hehe Village, Yudu County

R 10 Yang Ruisheng’s Old House under Demolition, Nangang Village of Xianghu Town, Ruijin City.

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 131 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

R 11 Yang Ruisheng’s New House, Nangang Village of Xianghu Town, Ruijin City.

R 12 Zeng Jixian’s Second-hand House after the Demolition of His Old House, 7th Group of Liangkeng Village of Gucheng Town, Changting County

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 132 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

R 13 Yang Dezhang’s New House, 2nd Xiaping Group of Liangzeng Village, Pengkou Town, Liancheng County

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 133 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project R 14 Newly Built Concentrated Resettlement Site in Pingpu Village of Jiaoyang Township, Shanghang County

R 15 Wu Baihua’s New House, Xinghui Village of Xiaochi Town, Xinluo District

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 134 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

14.7 The Interpretation of the Compensation Standards for Land

Acquisition, Demolition and Relocation Given by the Resettlement

Departments of Some of the Counties (Districts) along the Railway

Line

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 135 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 136 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 137 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 138 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 139 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 140 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 141 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 142 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 143 ADB Loan Project

Post-Resettlement Evaluation Report by the External Independent Monitoring Group for Ganzhou-Longyan Railway Construction Project

The Research Institute of Foreign Capital Introduction and Utilization, Southwest Jiaotong University 144 ADB Loan Project