PCDO

October-2018

Launched portion of Viaduct Deck Structure from S-180 (KATRA- SECTION)

Udhampur-- Rail Link Project

Northern Railway विजय शर्मा vkbZvkj,lb Vijay Sharma IRSE

No. Secy.CAO/USBRL/JAT/PCDO Dated: 05/11/2018

Sub: PCDO for the Month of Oct, 2018. 1. Highlights of the month of Oct, 2018.

1.1 General Manager, Northern Railway visited the project sites (i.e. , Br. No 39 & Tunnel T-5) on 12th & 13th October, 2018. 1.2 During this month tunneling of 2692 m was done, which is the highest ever monthly progress. This comprises of 1226m of Main Tunnel and 1466m of Escape Tunnel and also 14405m of tunnelling has been completed in this financial year.

1.3 Progress of tunneling work (Main tunnel) between Katra- Banihal Section

S/No Agency Scope (m) Progress (m) Progress during the month (m)

1 KRCL 44682 30146 486

2 IRCON 50180 26890 740

3 NR 2456 2456 Work Completed

4 Total 97318 59492 1226

1.4 Progress of tunneling work (Escape tunnel) between Katra- Banihal Section.

S/No Agency Scope (m) Progress (m) Progress during the month (m)

1 KRCL 22055 7981 533

2 IRCON 44413 23500 933

3 NR 0 0 Work Completed

4 Total 66468 31481 1466

1

1.5 Status of Bridges between Katra- Banihal Section. Agency KRCL IRCON NR Major 15 10 1 Minor 7 1 3 Total 22 11 4 Work in progress 11 6 0 Work completed 3 Major +7 Minor 3 (Major) 1 Major + 3 Minor Work yet to start 1 2 0 (Br.60) (Br. 61 & Br. 4)

Total bridges in Katra-Banihal section : 37 (26 Major + 11 Minor)

2. Important achievements during the month

2.1 Earth Work: 2.1.1 Earth work and protection work is in progress in station yard, out of 23,60,000 Cum of total quantity 22,67,183 Cum has been done so far. 2.1.2 Earthwork for excavation of Bridges foundation is in progress for Katra Banihal section, out of 16,38,639 cum quantity (i.e. except Chenab bridge) 13,81,370 cum has been completed. 2.1.3 Earthwork for excavation of Chenab Bridge foundations & slope protection is in progress, out of 10,08,545 cum quantity 9,75,697 has been completed (i.e. 97% completed).

2.2 Tunneling i. Progress of underground excavation achieved in various tunnels are as follows.

Progress of Main Tunnels (m) Progress of Escape Tunnels (m) Sr. No. Tunnel During this Cumulative During this Month Cumulative Month 1 T-1 0 2912 - - 2 T-2 90 1180 126 1196 3 T-5 139 5483 124 5352 4 T-13 257 1191 283 1433 5 T-14 0 0 66 208 5 T-15 218 1724 280 2261 6 T-48 180 5877 298 5398 7 T-49 187 7379 212 7493 8 T-74R 84 7653 77 6654 9 T-77D 71 455 - - 10 Total 1226 33854 1466 29995

2

ii. Progress of lining achieved during this month is as follows

Progress during Cumulative Progress S/No. Tunnel Scope (m) this month (m) progress (m) (%)

1 T-1 3159 165 2219 70% 2 T-5 5959 72 4157 70% 3 T-6 3493 0 3485 100% 4 T-10 1010 0 1010 100% 5 T-12 2123 0 1979 93% 6 T-48 10195 37 1012 10% 7 T-49 12758 76 888 7% 9 T-74R 8600 85 6169 72% Total Lining 47297 435 20919 44%

iii. Progress of tunnel works/agency wise is as follows,

Main Tunnel

S/No Agency Scope (m) Progress (m) Balance (m) Progress (%) 1 KRCL 44682 30146 14536 67 2 IRCON 50180 26890 23290 54 3 NR 2456 2456 0 100 4 Total 97318 59492 37826 61 Escape Tunnel S/No Agency Scope (m) Progress (m) Balance (m) Progress (%) 1 KRCL 22055 7981 14074 36 2 IRCON 44413 23500 20913 53 3 NR No scope 4 Total 66468 31481 34987 47

3

iv. Month wise Tunneling progress (2018-19)

Tunnel Progress (2018-19)

Main Tunnel (m) Escape Tunnel (m) Month KRCL IRCON Total KRCL IRCON Total Apr-18 293 566 859 258 569 827 May-18 335 501 836 262 477 739 Jun-18 389 500 889 374 498 872 Jul-18 459 615 1074 444 649 1093 Aug-18 510 580 1090 436 550 986 Sep-18 518 669 1187 522 738 1260 Oct-18 486 740 1226 533 934 1467 Nov-18 0 0 Dec-18 0 0 Jan-19 0 0 Feb-19 0 0 Mar-19 0 0 Total 2990 4171 7161 2829 4415 7244

v. Linear progress of tunnel excavation (main +escape) for 2018-19

Tunnel Excavation (Main Tunnel)

2018-19

740 669 615 566 580 510 518 486 501 500 459 389 335 293

KRCL IRCON

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

4

Tunnel Excavation (Escape Tunnel) 2018-19

934

738 649 569 522 533 550 477 498 444 436 374

258 262

KRCL IRCON

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

vi. Tunnel wise last three Month progress (2018-19)

Total S/No. Tunnel July August September October Progress (2018-19) 1 T-1 Main (m) 0 0 0 0 0 0 0 0 Main (m) 209 173 149 90 1180 8 T-2 421 364 302 216 Escape (m) 212 191 153 126 1196 Main (m) 130 145 108 139 792 2 T-5 240 264 253 263 Escape (m) 110 119 145 124 654 Main (m) 120 192 261 257 1017 9 T-13 242 318 485 540 Escape (m) 122 126 224 283 977 Main (m) 0 0 0 11 T-14 23 38 54 66 Escape (m) 23 38 54 66 206 Main (m) 105 106 144 218 743 7 T-15 311 275 350 498 Escape (m) 206 169 206 280 1212 Main (m) 217 205 252 181 1368 3 T-48 431 353 475 479 Escape (m) 214 148 223 298 1306.5 Main (m) 190 174 156 186 1324 4 T-49 358 316 342 398 Escape (m) 168 142 186 212 1302.9 T- Main (m) 65 48 74 84 431 6 103 101 143 161 74R Escape (m) 38 53 69 77 385 T- 10 38 38 47 47 43 43 71 71 305 77D Main (m) 2167 2076 2447 2692 12 Total (MT+ET) Total (2018-19):14399.4m

5

Ballast-less Track (BLT) 2.2.1 Tender for design of Broad Gauge BLT (Ballast less track) including supply, installation, testing and commissioning between Banihal - Arpinchalla (Approx. 16 Km.) was invited for a total value of Rs. 82.22 Cr. and the date of opening has been extended to 19.11.2018, due to demand for various prospective bidders.

2.3 Bridges Progress of bridges between Katra- Banihal section has been shown in Table 3.

2.4 Miscellaneous:

2.4.1 ESP of Kata Banihal Section: a) ESP of Sumber and Arpinchala have been submitted to Ferozpur Divison and the same was forwarded to HQ Office on 10.01.2017. Now, CTPM/NR has visited the site on 26-28th Sept.’ 2018 and plan is under approval. b) Schematic yard plan for Salal-A station was submitted to COM/NR, Baroda House for approval on 18.04.2017, approval is still pending.

2.4.2 Tender for Transportation of DEMU Power and Trailer Coaches 17 no’s and Two WDS6 Locos by Road, duly conducting feasibility study, from to Railway Station has been invited by IRCON and is scheduled for opening on 12/112018.

2.4.3 E&M (Electro and Mechanical Works) for Tunnels: a) Preliminary Design Report have been submitted by DDC for 11nos Tunnel out of total 15 no’s tunnels. b) Final design reports have been submitted by DDC for 7 no’s tunnels out of total 15 no’s tunnels. c) Financial Bid of the tender for Consultancy services for Proof checking of Design of Ventilation, Fire Escape, Emergency rescue and other related Electro-mechanical systems for Tunnel No T-77 & 78 opened on 10.10.2018. Financial TC minutes under finalization.

6

2.5 Chenab Bridge Progress of Chenab Bridge has been summarized in table below:

Progress of Chenab Bridge: 2018-19 (KRCL) Target Monthly Achieved Progress Balance Total Balance on for Progress Item Unit up to for F.Y. of Quantity 1/4/18 2018- Oct 31/03/18 2018-19 2018-19 19 2018 Earth Work in Cum 1008545 968164 40381 - 0 4283 Excavation Fabrication of Nos/MT 164/13450 67/7238 97/7607 6310 0/14 0/2716 3594 Deck Segments Fabrication of Main Arch, MT 15550 12415 3135 14 2887 Piers & Trestles Launching and Erection of Nos 164 59 105 - 0 0 - Superstructure Deck Segments Launching of Main Arch, 429 + 309+ Nos. 120 - 0 82 - Piers & Trestles Trestles Trestles Financial Cr. 1198 1071.68 126.32 110 9 95 15 Progress Total expenditure (Oct 2018) : 1166.68 Cr.

2.6 Major Contract Awarded

All major contract awarded.

2.7 Major Tender Invited/Under Finalisation/Under process

2.8.1. Tender for construction of proposed new Adit tunnel at Urnihal including Portal development at Km. 115.2 for Tunnel T-49A was opened on 26.07.2018 and one of the bidder has gone to Hon’ble High Court, J&K and the matter has become sub judices. Date of hearing in the Hon’ble High Court is expected in 2nd week of Nov.’ 2018. 2.8.2. Tender for design of Broad Gauge BLT (Ballast less track) including supply, installation, testing and commissioning between Banihal - Arpinchalla (Approx. 16 Km.) was invited for a total value of Rs. 82.22 Cr. and the date of opening has been extended to 19.11.2018, due to demand for various prospective bidders.

7

2.8 Budget and Expenditure

2.8.1 Abstract Cost = 19565 Cr 2.8.2 Last Sanctioned Cost = 27,832 Cr 2.8.3 Latest anticipated Cost = 27,832 Cr 2.8.4 Budget out lay for 2018-19 (USBRL Project) = 1600 Cr (Revised) 2.8.5 Up to date expenditure = Rs. 16834 Cr. (Since inception)

2.8.6 Break up of expenditure under major Plan heads is detailed as under

Year 2018-19

Total Booking upto Oct.'2018 Plan Expenditure Outlay (Cr.) Expenditure SN % Head up to March (Cr.) up to Oct Net (after Expenditure 2018 (Cr.) Revised 2018 (Cr.) Total ROC from PSU) New 1 Line 16175.12 1600 798.19 714.33 1389 87 (8300)

Booking details as shown by USBRL finance:

Cost (As per S/No. Section detailed Booking up to Oct-2018 estimate) 1 Udhampur- Katra 1111.43 1119 2 Katra- Banihal 21652.33 10715 3 Banihal-Quazigund 1691.88 1687 4 Quazigund- Baraumulla 3493 3313 5 Total 27948.6 16834

8

Expenditure incurred by IRCON and KRCL (2018-19)

Planning of expenditure during (2018-19)

IRCON KRCL NR Month (2018-19) Target (Cr.) Achieved (Cr.) Target (Cr.) Achieved (Cr.)

April 50 57.1 65 72.89 13.97

May 60 72.66 75 85.51 4.68

June 65 82.72 80 94.76 22.71

July 80 90.98 90 98.81 31.85

August 90 92.03 90 115.22 23.04

September 100 96.46 105 116 3.71

October 110 86.43 110 120 7.04

Total 555 578.38 615 703.19 107

Annual planning of Expenditure during 2018-19 for IRCON =1150 Cr Annual planning of Expenditure during 2018-19 for KRCL =1100 Cr. Annual planning of Expenditure during 2018-19 for NR =120 Cr.

3. Katra-Banihal Section (Progress in Details)

3.1 For construction convenience and monitoring, this section has been divided into following legs: A. Katra – Banganga (km. 25 - 30): Executed by Northern Railway and works are completed. B. Km. 30 - 100 (KRCL, except 73.78 to 91 as transferred to IRCON): Progress of underground excavation for various tunnels being executed by KRCL are shown in Table 1.

C. Km 100 – 136: Executed by M/s IRCON. Progress of underground excavation for various tunnels being executed by IRCON are shown in Table 2.

9

3.2 Chenab Bridge, Br. No. 44 (KRCL) Chenab Bridge has been divided in four parts for construction point of view, these are A. Construction of Arch Portion (S-10 to S-70) B. Construction of Viaduct Portion (S-70 to S-180) C. Slope Stabilization - Bakkal end and D. Slope Stabilization - Kauri end

A. Progress on Arch Portion (S10 to S70) :

a. Progress of the Arch:

(i) RCC work: Concreting of S10 (Except 234 Cum), S20, S30, S40, S50, S60 and S70 (Except Pier Cap) has been completed. (ii) Workshop: Main span deck fabrication at S180 & Bakkal is under progress. Arch fabrication work at wheels India Ltd., Wardha & Trestle fabrication at AIML, Raipur has been completed.

iii) Progress on Viaduct Portion (S-70 to S-180):

a. Progress:

(i) RCC Work: All completed except the pier cap of S-70.

B. Slope stabilization – Kauri end: In progress C. Slope stabilization - Bakkal end: In progress

4. Progress of bridges between Katra- Banihal section has been shown in Table 3.

10

Table 1: Tunnel Details: KRCL

KRCL Portion Progress Target Lining Length Award of Cumulative Balance Achieved S/No. Tunnel No this Remarks 2018- Progress this Cumulative Balance Target Achieved (m) Contract Progress (m) (2018-19) Scope month 19 month Progress (m) 2018-19 (2018-19) Tunnel Excavation in 1 T-1 3159 Jul-14 0 2912 247 45 0 3159 165 2219 940 1300 1072 progress

T-2 3674 Mar-16 90 1180 2494 1680 1180 3674 0 0 3674 0 0 Tunnel Excavation in 2 progress T-2 3586 Mar-16 126 1196 2390 1680 1196 3586 0 0 3586 0 0

3 T-3 3009 Nov-10 3009 Work Completed 0 Completed Completed

4 T-5 5959 Oct-10 139 5483 476 1123 793 5959 72 4157 1802 1800 855 Tunnel Excavation in T-5 progress. 4A 5959 41922 124 5352 607 951 655 5959 151 3271 2688 1063 (Escape) 5 T-6 3493 Sep-10 3493 Completed. 0 3493 0 3493 0 0

6 T-9 470 Sep-10 470 Completed 0 470 0 470 0 0

7 T-10 1010 Sep-10 1010 Completed 0 Completed 1010 0 1010 0 0

8 T-11 830 Sep-10 830 Completed 0 830 0 830 0 315 Excavation completed. 9 T-12 2123 Sep-10 2123 0 2123 0 1979 144 153 Lining in progress. 10 T-13 9368 257 1191 Work awarded to M/s 8177 2730 1017 9368 0 0 9368 2680 T-13 Jul-16 HCC on 25/7/16. Work 10A 9368 283 1433 Transferred to KRCL 7935 2730 978 9368 0 0 9368 (Escape) 11 T-14 3142 3142 210 3142 Reflect the part that is Jul-16 T-14 clubbed with T-13 11A 3142 210 3142 (Escape) 12 T-40/41 1346 Oct'05 1346 Work Completed 0 13 T- 42/43 2732 Oct'05 2732 Work Completed 0 14 T-44/45 1483 Oct'05 1483 Work Completed 0 Completed 15 T-46 654 Oct'05 654 Work Completed 0 16 T-47 2230 Oct'05 2230 Work Completed 0 Total (Main 17 44682 486 30146 67% 14536 5788 2990 11173 237 10887 286 6248 1927 Tunnel) Total 18 22055 533 7981 36% 14074 5571 2829 22055 151 3271 18784 0 1063 (Escape)

11

Table 2: Tunnel Details: IRCON

IRCON Portion Lining Progress Length Award of Cumulative Balance Target Achieved Progress Sr. No Tunnel No this Remarks Cumulative Balance Target Achieved (m) Contract Progress (m) 2018-19 (2018-19) Scope this month Progress (m) 2018-19 (2018-19) month

1 T-14 3142 - 0 Tender clubbed with that of T-13 and 3142 180 0 3142 0 3142 0 T-14 T-15. Part clubbed with T-13 1A 3142 66 208 2934 360 206 3142 0 3142 0 (Escape) transferred to KRCL 2 T-15 9829 Mar-16 218 1724 8105 2280 743 6269 0 6269 0 T-15 Work in progress. 2A 9829 Mar-16 280 2261 7568 2520 1213 9829 0 9829 0 (Escape) 3 T-48 10186 Sept,2012 180 5877 4309 2463 1368 12758 37 1012 11746 413 Work in progress T-48 3A 9788 Sept,2012 298 5398 4390 2290 1306 9788 36 156 9632 132 (Escape) 4 T-49 12758 Dec,2013 187 7379 5379 2445 1324 12758 76 888 11870 413 Work in progress T-49 4A 12755 Dec,2013 212 7493 5262 2220 1304 12758 30 30 12728 0 30 (Escape) 5 T-50 255 June,2014 255 Completed 0 0 0 255 0 175 80 100

6 T-74 R 8600 Oct,2011 84 7653 Work in progress 947 828 431 8600 85 6169 2431 869

T-74 R Escape 6A Tunnel 7413 Oct,2011 77 6654 Work in progress 759 720 386 7413 160 4718 2695 987 7 T-77 335 335 Completed 0 335 Completed 0 Completed 8 T-77 A 873 873 Completed 0 873 Completed 0

9 T-77D 1863 July,2016 71 455 Work in progress 1408 1040 305 1760 0 1760 0

10 T-78 920 920 Completed Completed 0 920 Completed 0 11 T-2 1419 1419 Completed 12 T-2 1486 1486 Total (Main 13 50180 740 26890 54% 23290 9236 4171 47670 198 8244 37298 0 1795 Tunnel) Total 14 (Escape 44413 933 23500 53% 20913 8110 4415 42930 226 4904 38026 0 1149 Tunnel)

12

Table 3: Status of bridge works between Katra-Banihal Section

A. PROGRESS OF BRIDGE WORK FOR SECTION KATRA-DHARAM (km 25-100)

S. From Br. No. To Km Type of Bridge Details of Bridge span Remarks No. Km Position of brdges from Km 25 to 30 1 32 28.011 28.265 Major 1x34+1x64+1x92+1x64m Completed 2 33 RCC Box 3x3m Completed 3 33A RCC Box 5.2x5.585m Completed 4 34 RCC Box 3x3m Completed i. Bridges with KRCL ( Km 30-100) S. From Br. No. To Km Type of Bridge Details of Bridge span Remarks No. Km

Steel open web 1 34 33.172 33.188 1*24.4 Sub structure completed. girder

Ancillary Viaduct (120mm) : Pier P1, P2,& P3 completed, 35 (Anji A1 & A2 in progress. 2 38.3 39.04024 Cable Stayed 1x38+290+80+75+28.25 & 25+35+35+25 Khad) Main Bridge : Work of Foundation A2, P2 & P1 in progress.

Composite plate Sub structure completed. 3 38 42.208 42.3325 1x24.4+1x61+1x45.7 Girder

Foundation A2, P1,P2, P3, Composite plate 4 39 42.221 42.69857 1x53.15+6x64+1x53.15 P4, P5 & P6 completed. Pier Girder P1, P2,P4 & P6 completed.

13

S. From Br. No. To Km Type of Bridge Details of Bridge span Remarks No. Km 5 40 42.894 42.906 RCC BOX 1x4x3 (minor) Completed 6 41 48.976 48.9845 RCC BOX 1*5*5 Completed 7 42 49.203 49.2775 RCC BOX 3x5x5 Completed Pier P3 to P12 and abutment Completed. 8 43 49.695 50.305 Girder Bridge 1*35+1*53+10*64+1*49 Micro Pilling for A1& P2 completed and P-3 in progress. 44(Chenab Girder and arch Work in progress, details at 9 50.42 51.6945 1*55+2*65+10*48+1*65+1*55+1*40+9*50+1*40 bridge) bridge 2.6

Composite Plate 10 53 55.432 55.54795 3x30.5m Sub structure completed.. Girder Sub structure completed. Composite Plate 11 55 56.242 56.2783 1x24.4m, Erection of Steel Girder Girder Completed. Sub structure completed. Composite Plate 12 56 57583 57607.2 1x24.4m Erection of Steel Girder Girder Completed. Sub structure completed. Composite Plate 13 57 58478 57607.2 1x24.4m Erection of Steel Girder Girder Completed.

Composite Plate 14 58 60701 60749.4 3x30.5m Sub structure completed. Girder

Composite Plate 15 59 60869 60991 1x30.5+1x45.7+1x30.5 Sub structure completed Girder

14

S. From Br. No. To Km Type of Bridge Details of Bridge span Remarks No. Km Composite Plate GT investigation completed, Girder (CPG) 2x30.5(CPG)+2x61(CT)+1x30.5 16 60 70394 70625.9 work awarded. GAD to be +composite (CPG)+1X18.3(CPG)m=231.8m, finalised. truss +CPG+CPG

17 81 92473 92467 RCC BOX 2x3x2m (minor) Completed

18 82 93078 93083.77 RCC BOX 2x(3x3) (minor) Completed

Sub structure A-1 , A-2, P-1 19 85 95993 96267.25 STEEL GIRDER 1x45.7+3x61+1x45.7 & P4 completed.

20 85A 96379 96381.5 RCC BOX 1x(3x3) m (minor) Completed Foundation A1, P1, P2 and COMPOSITE A2 completed. Sub 21 87 98127 98356 3x61.0 m+1x45.7 m GIRDER structure A-1 & A2 completed . 22 87A 98325 98355 RCC BOX 1x3x3M (minor) Completed

15

ii. Bridges with IRCON

S. Br. No. From Km To Km Type of Bridge Details of Bridge span Remarks No.

Composite Plate GT investigation completed, work 24 61 76935 77008.2 1x18.3+1x24.4+x30.5m=73.2m Girder awarded. GAD finalised.

25 1 99.98 100.01 Steel Girder 1x30.5 Excavation work in progress

Composite Steel 26 2 110.48 110.911 11x39 Well Foundation of P-2 is in progress. Girder

Composite Steel 27 3 111.3 111.635 8x39 Well Foundation of P-1 is in progress. Girder

RCC Box for rock GAD approved. Resources for 28 4 124.28 124.315 1x35.0 protection substructure is being mobilised

29 5 124.71 124.854 RCC Box 1x5 Excavation is in progress.

30 121 125.194 125.311 Steel Girder 1x30.5+1x45.7+2x30.5 Completed

34 141 147.952 Old Ch Steel Girder 1x64.00 Remark

32 142 148.439 Old Ch Steel Girder 3x30.48 Completed

33 144 149.48 Old Ch Steel Girder 2x25.6m Completed

16

5. Progress of land acquisition in various stretches of Udhampur - Srinagar- Baramulla New Line is enclosed as, Annexure-I

भवदीय

(ववजय शर्मा)

17

Annexure-1: Details of land acquisition upto the month of Oct 2018 for USBRL Project

A) Land Acquisition details for Jurisdiction of Dy. CE’s

Revenue Land Diversion Forest Land

S.No Jurisdiction Already Under Already Under Total Total Acquired Process Acquired Process

Dy.CE/Banihal 1 (Banihal- Dharam) 299.36 13.39 312.75 144.56 0.00 144.56 (Banihal- Baramulla) 857.50 0.00 857.50 0.00 0.00 0.00 2 Dy.CE/Sang 129.10 11.22 140.32 66.69 13.06 79.75 3 Dy.Ce/Reasi 206.64 39.78 246.42 240.88 0.63 241.51 4 Dy.CE/UHP 268.92 1.23 270.15 12.31 0.00 12.31 5 Dy.CE/Anji 5.96 0.75 6.71 19.87 0.00 19.87 6 Dy.CE/Chenab 13.24 0.00 13.24 12.39 0.61 13.00

Total 1780.72 66.37 1847.09 496.70 14.30 511.00

B) Abstract of Land Acquisition Status of USBRL:

Total Land Already Percentage Description Required Acquired Balance (Hectare) Balance (Hectare) (Hectare)

Revenue/ Private Land 1847 1781 66 4% Diversion of Forest Land 511 497 14 3%

Total 2358 2277 81 3%

18

Annexure-II

Financials- USBRL

Year Estimate Cost (Rs. Crore)

1994-95 Pink Book 1500

1998-99 DPR 3077

2010 CCEA Approved Cost 19565

Latest Estimate Estimated S/No. Section Cost Remarks (Cr.) 927.61 2nd Revised-2012 1 UHP- Katra 1111.43 Completion cost (with associate finance) 2 Katra (Km 25)-Km 30 183.51 Detailed estimate of 2012 3 Banihal- Quazigund 1691.88 Detailed estimate of 2012 Completion Estimate 3376.22 Cr. 4 Quazigund- Baramulla 3493 submitted to Rly.Board 5 Katra (Km 30)- Banihal 21468.82 Detailed estimate of 2015 6 USBRL Project Cost 27949 Crores

Booking up to Oct-2018

Cost (As per S/No. Section detailed Booking up to Oct-2018 estimate)

1 Udhampur- Katra 1111.43 1119

2 Katra- Banihal 21652.33 10715

3 Banihal-Quazigund 1691.88 1687

4 Quazigund- Baraumulla 3493 3313 5 Total 27948.6 16834

19