main issues report LIVE Park is your chance to really How often do we get a understand the future potential of where you live, work, play and chance to really understand invest. It sets out how planning the future of where we live, can help improve work, play and invest? & The Trossachs National Park – from housing to jobs, and everything in between, so get involved at That’s what LIVE Park is all about Inside, you’ll find our ideas – looking at what development is based on what you told us. www.ourlivepark.com needed across the 22 towns and That could mean attracting villages in Loch Lomond & The more young families to the Trossachs National Park. area, developing our tourism offering, or supporting First of all, we talked to improvements to our communities, landowners, infrastructure like roads investors and lots of other and visitor facilities. CONNECT & SHARE WITH US… people. We wanted to understand what you think And now it’s about finding and what you’re passionate out what you think, so get www.ourlivepark.com about. involved. The document you’re holding twitter.com/ourlivepark www.ourlivepark.com right now is the result – our facebook.com/ourlivepark Main Issues Report. /ourlivepark instagram.com/ourlivepark

contents

1 Introduction and Overview ...... 3 4 Identifying the Main Issues – what needs major change and what are the options? ..23 1.1 introduction ...... 5 4.1 Drivers for change ...... 24 1.2 Overview ...... 6 4.2 introducing the main issues...... 37 1.3 How can i share what i think? ...... 8 4.3 main issues, potential 1.4 Why plan? ...... 10 options and solutions ...... 38 2 National Park Partnership Plan ...... 13 5 Placemaking – what sites should be 2.1 Vision for the Park ...... 15 considered for development? ...... 69 2.2 Delivering the national Park 5.1 Town and village Partnership Plan ...... 16 development opportunities ...... 71

3 Current planning policy – the Local Plan ...17 6 More information ...... 135 3.1 strategy summary...... 18 6.1 List of accompanying documents ...... 136 3.2 Progress in delivering the strategy – key trends ...... 19 6.2 Glossary ...... 137

LIVe PaRK MAIN ISSUeS RePORT 1 2 MAIN ISSUeS RePORT LIVe PaRK introduction and overview What’s the big idea?

LIVE PARK 1 MAIN ISSUES REPORT 3 4 MAIN ISSUES REPORT LIVE PARK 1.1 INtrodUCtIoN

This report is all about the big ideas for future development in the national Park over the next 20 years. Where new homes should go, where new and existing businesses will be supported and where the environment should be protected. it shows the development that organisations, businesses and Our Local Plan, which has been in we think is needed in order landowners throughout 2013. place since December 2011, is the to support our communities, Research has also been undertaken basis for deciding where new homes, visitors and local economy while into key development issues such businesses, visitor accommodation ensuring the ongoing conservation as housing, economic development etc should go in the national Park. it and enjoyment of the area’s and tourism. is a key document in attracting the outstanding environment. right new development in the right This is drawn together in this main place. We must ensure it is up to To help establish this we have issues Report – to outline what we date. listened to many people in the think are the likely main changes national Park. We have spent required from the Local Plan, the This is your opportunity to tell us time talking and listening to our potential solutions and the options what you think before we prepare communities, we have met with for new development. the new Local Development Plan. key government agencies, partner

LIVe PaRK MAIN ISSUeS RePORT 5 1.2 oVerVIeW

What are the issues that might affect me, my family or my community?

The number of new homes and The natural, built and cultural businesses being built has been environment, including the Park’s very low in recent years overall, landscape, is the very reason that and this is a trend throughout the national Park was designated. . it is important to consider We feel the policies in our Local where our current approach to Plan that guide new development in supporting new development could relation to these topics do not need be amended to help the national to be changed. (section 3) Park’s communities and businesses. infrastructure and services are key We focus on the Rural economy, for our communities and visitors. Housing and Visitor experience to These affect how we move about explore what new options may be on the roads, paths and public available. (section 4.3) transport, where our children can go to school, and where our visitors go. Feedback from communities and businesses confirms the importance of these points. (section 4)

6 MAIN ISSUeS RePORT LIVe PaRK Turning to the Park’s Towns and Development in these locations we Additional new smaller sites Villages, the main areas where feel, will provide sustainable growth are also identified in: additional land is identified are over the longer term – an increase Aberfoyle Callander and to a lesser extent in in employment opportunities with the arrochar, Tarbet and succoth new homes that can facilitate area. new land is proposed for improvements in services and Drymen housing and existing or additional infrastructure as development is land is shown for tourism or implemented. Gartocharn economic development. Significant The same principles have been existing land for both tourism and applied when reviewing sites in housing in Balloch remains and is Balmaha other towns and villages, with proposed to be continued. the purpose of ensuring there is (section 5) enough land for housing between 2016 and 2026 but also to provide a range of options for both housing, economic development and tourism development.

LIVe PaRK MAIN ISSUeS RePORT 7 1.3 How can I share what I think?

We think it is important to provide a range of ways for all to get information on what this consultation is about, what it means, why it is important and how you can share what you think.

The consultation runs from You can access information on the Main Issues Report: Monday the 28 April until By going online at View our very short Youtube Calling 01389 722600 and Monday 7 July. Any comments ourlivepark.com summary videos ask for Hugh, Susan, Thom must be submitted to us by 5pm or Stuart in the Forward on 7 July and we are providing a By visiting your local library Visit us in person at National Planning Team range of ways for you to provide Park HQ or at a community On twitter and facebook this to us. meeting/workshop send us an email - livepark@ – you can see up to date (you can view a list of these on lochlomond-trossachs.org information on what people the ourlivepark.com) share your are saying see the posters in local twitter.com/ourlivepark attend a Youth Visioning shops, schools and comments by facebook.com/ourlivepark event - details are on community newspapers ourlivepark.com Look out for updates on your Visit the displays in the Community Notice Boards for 7 JULY 3 Villages Hall in Arrochar any local event! and Callander Youth Project

8 MAIN ISSUES REPORT LIVE PARK There are a range of ways to provide your views on the Main Issues Report: Going online at Visit us in person at National Calling 01389 722600 and send us an email or post a ourlivepark.com Park HQ or at a community ask for Hugh, Susan, Thom completed MIR response form complete an online response meeting/workshop (you can or Stuart in the Forward to us at: [email protected] or leave a comment view a list of these on the Planning Team Loch Lomond & The ourlivepark.com) Trossachs National Park Leave your comments* Headquarters, Carrochan, on twitter and facebook attend a Youth Visioning events Carrochan Road, Balloch, twitter.com/ourlivepark in Callander and Arrochar G83 8EG facebook.com/ourlivepark Text your comments* to 07860 01 71 53 CONNECT & SHARE WITH US…

* we can only treat these as non-attributable

LIVE PARK MAIN ISSUES REPORT 9 1.4 WHY pLAN?

Planning is all about guiding new development in the Park while safeguarding, and enhancing, the environment. We prepare a plan to show where, and what type of future development will be supported.

This is used as the basis for deciding planning applications for development and use of land. We have a statutory duty to prepare a development plan and the strategy and policies contained within this are key to securing delivery of the national Park’s four statutory aims. scotland’s national Parks share four aims set out by Parliament:

To conserve and enhance the natural and cultural heritage of the area;

To promote sustainable use of the natural resources of the area;

To promote understanding and enjoyment (including enjoyment in the form of recreation) of the special qualities of the area by the public;

To promote sustainable economic and social development of the area’s communities.

10 MAIN ISSUeS RePORT LIVe PaRK Community

Main Issues Proposed Examination Adoption Report Plan

Development

We must update our plan regularly (every 5 years) so that it is kept up to date and is responsive to change. The current Local plan covers the period from 2010 to 2015. The new Local development plan (Ldp) will replace the current Local Plan and will cover the period from 2016 to 2021. It will have a different format from the current Local Plan (due to changes in legislation) however the purpose and use of the LDP remains the same. While it has a lifespan of 5 years it will focus on the main development proposals for the next 10 years and also give an indication of where we think future Reproduced by permission of Ordnance survey on behalf of HmsO. © Crown development, and the likely scale of this, should be copyright and database right 2014. all rights reserved. Ordnance survey Licence located as far as 20 years ahead. number 100031883

LIVe PaRK MAIN ISSUeS RePORT 11 12 MAIN ISSUeS RePORT LIVe PaRK national park partnership plan how it fits…

LIVE PA2RK MAIN ISSUES REPORT 13 2 NAtIoNAL pArk pArtNerSHIp pLAN

The National Park Partnership Plan sets out the priorities and key outcomes for the Park for all partners to 2017. A key difference in planning within a National Park is that we must ensure that the Park’s four statutory aims are achieved collectively, and in so doing work with all public bodies to ensure their activities deliver these priorities.

14 MAIN ISSUeS RePORT LIVe PaRK 2.1 VISIoN for tHe pArk

in addition to being the basis for guiding new development, the Local Development Plan is the key development enabling tool that the Park authority has. It can influence investment in infrastructure and services. The Outcomes identified in the National Park Partnership Plan are: Conservation: Visitor Experience: Rural Development: an internationally – a high quality, in the national Park renowned landscape authentic experience businesses and where the natural for visitors, with many communities thrive and beauty, ecology and opportunities to people live and work the cultural heritage appreciate and enjoy sustainably in a high are positively managed the natural and cultural quality environment. and enhanced for heritage – within future generations. an internationally renowned landscape that compares to the best on offer around the world.

QUeStIoNS It is proposed that these form the Vision for the Local Development Plan. VISIoN Q1: Do you agree with the Vision?

LIVe PaRK MAIN ISSUeS RePORT 15 2.2 deLIVerINg tHe NAtIoNAL pArk pArtNerSHIp pLAN

The Partnership Plan outlines key challenges for each outcome, along with policies and delivery priorities.

The policies are particularly important in preparing the Local Development Plan and set the strategic framework to shape any revisions or updates to strategy and policy. The key policy provision is the spatial Development strategy, with which the Local Development Plan should be consistent. The approach in the current Local Plan is consistent with this strategy and it is not proposed to be significantly amended. Where possible changes are identified, these are outlined in the Rural economy, Housing and Visitor experience sections.

Reproduced by permission of Ordnance survey on behalf of HmsO. © Crown copyright and database right 2014. all rights reserved. Ordnance survey Licence number 100031883

16 MAIN ISSUeS RePORT LIVe PaRK current planning policy THE LOCAL PLAN

LIVE PARK3 MAIN ISSUES REPORT 17 3.1 StrAtegY SUMMArY

The current Local Plan provided the first single planning strategy and framework of policies for the national Park.

Its overall vision was to provide: “ A robust development and land-use planning framework to 2015 that will deliver high quality, sustainable development in an area of outstanding landscape and environmental quality.

New development will contribute to the Park’s special qualities, directly supporting the social and economic development of the Park’s communities and a growing rural economy, contributing to Scotland’s prosperity, improving the range and quality of opportunities to experience the National Park, and enhancing its standing as an international visitor destination.”

18 MAIN ISSUeS RePORT LIVe PaRK 3.2 progreSS IN deLIVerINg tHe StrAtegY – keY treNdS monitoring of the Local Plan has been carried out by reviewing how we have used the policies in making decisions on new development since December 2011.

This is critical to understanding The national Park authority’s 2013 The national Park authority environment progress in achieving the aims and monitoring statement, published determined 611 planning 436 applications vision. it also helps us to consider separately, is a comprehensive record applications between 13 December, Housing what our main issues might be as it of how the Development Plan has 2011 and 31st December 2013. 316 applications can highlight which sections of the performed in achieving the vision 11 applications have been refused Plan need to be updated to respond above. We have summarised the and 46 have been withdrawn. The economic development to changes in external influences. content of that report here. Later applications* can be split into the 74 applications in this document we will explore the categories associated with the Local Sustainable tourism trends behind this information. Plan strategies: and recreation 139 applications transport infrastructure 91 applications Sustainable Communities 76 applications (*Please note that applications can fall into more than one category, for example a housing application can have environmental aspects to be considered)

LIVe PaRK MAIN ISSUeS RePORT 19 the key points from the monitoring include: in the Local Plan, we allocated suitable sites However, some key sites in the Park Renewable energy and other sustainable for development. The majority of these have seen encouraging progress, community related development has been sites remain undeveloped with the largest housing site in the more positive – with a number of schemes Park. Tannochbrae, in Callander being going ahead, which has been a boost to in terms of housing, 25 of the 29 completed and the approval of the 130 many areas of the Park allocated sites have yet to be developed, bed hotel and associated development at as building rates have declined since Key transport projects in the Park are the former torpedo range near arrochar the Local Plan process began in 2009. planned on the a82 at Tarbet to arduli gaining planning permission in 2013 economic and sustainable Tourism sites and in Crianlarich which will increase show a similar picture with some notable The environmental/ built heritage policies connectivity and improve journey times exceptions. Windfall sites are providing are working well, ensuring that development While there has been an increase in vacant the large share of development activity in being approved and built is safeguarding and retail and commercial properties in our the Park enhancing the environment town and village centres, these have been in the minority

20 MAIN ISSUeS RePORT LIVe PaRK For full details please refer to the monitoring Having considered the elements that need to statement. From this, it is considered that the be reviewed, the next sections turn to identify following are the key policy and strategy areas the issues and places capable of being the that need to be reviewed: focus in this main issues Report. Housing and affordable housing policies/ requirements Economic development policies Tourism development strategy and policies

LIVe PaRK MAIN ISSUeS RePORT 21 22 MAIN ISSUeS RePORT LIVe PaRK identifying the main issues what needs major change and what are the options?

LIVE PARK4 MAIN ISSUES REPORT 23 4.1 drIVerS for CHANge

Previous sections explain the context within which the planning system operates in the national Park and show recent development trends.

This provided evidence on the performance of the Local Plan, however they only measure the actual development taking place and not the underlying reasons or issues. They also don’t tell us the potential future issues that we may need to consider.

To build up a full current picture, we have: Invited the submission of comments, issues and land suitable for development Listened to the views of the Park’s communities, businesses, landowners, councils and partner organisations through meetings, charrettes, workshops and household/business questionnaires Undertaken research into housing, retailing, economic development and 2011 census Reviewed new legislation, emerging policies or strategies from local and national government The following section provides a short summary of the headlines identified from this review.

24 MAIN ISSUeS RePORT LIVe PaRK CoMMUNItY ANd pArtNer eNgAgeMeNt in terms of community engagement, the following is a summary of key points we heard during our programme during 2013:

Start of Green Highland Residential Experience Street Main • Continue to enhance Street and support Main Street improvements

Town Main Centre Street

Green Residential • Develop extra leisure Street and hotel Riverside opportunities to east Loop • Rationalise and Community Hub enhance existing New community resources Connection • New pedestrian/cycle and road river crossing point Natural Activity • Link road to provide options Green Hub Threshold and diversity of routes • Improve the arrival • Satellite parking and within the town experience for associated outdoor Callander activity resource Future Growth which can be used for Avoid flood plain areas and promote larger-scale outdoor best practice which accommodates long events • Identify best location for term climate change growth areas which are • Develop extra leisure sensitive to the landscape and hotel setting opportunities to east

Callander’s aspiration to be Tourism or visitor Basic infrastructure, such as New housing is needed to ensure an outdoor capital of the development should not roads, car parks, sport/leisure that young people and working National Park, with long be to the detriment of the facilities, primary schools, families can stay – and perhaps term growth favoured to character of towns and health care, community halls a more pressing reason is that the south to accommodate villages, but new development and broadband are essential to they can afford to move to the development to support is needed in Aberfoyle, community life and supporting National Park. The amount of new investment in facilities, , Blairmore, Arrochar, the visitor economy housing should relate to the need services and accommodation and Succoth. Where this and employment opportunities. can complement social Evidence of businesses There is more pressure/ demand The significant potential enterprise aspirations of struggling – increase in vacant on the south and Callander given economic benefits and these communities this is commercial, particularly the accessibility to the central opportunities from the Ben particularly supported retail, premises belt and its wider employment Arthur resort development opportunities in the Arrochar area

LIVe PaRK MAIN ISSUeS RePORT 25 The following are proposed to be our overarching themes in the Local Development Plan. While they have implications for the national Park or relate to an outcome we would like to achieve, they require a broad range of action that relates to a number of areas of development.

pLACeMAkINg achieving good design is now central to planning which is about creating successful places. This should be a collaborative process with a focus on the following six qualities for places to be: Distinctive Resource Efficient Welcoming Safe and Pleasant Adaptable Easy to Move around and Beyond These should be reflected in planning strategies, policies and decisions and be promoted through a variety of tools such as, Design Guides, masterplans and Development Briefs. it is proposed that this is an overarching theme throughout the next Local Development Plan to which all policies and proposals contribute.

26 MAIN ISSUeS RePORT LIVe PaRK popULAtIoN CHANge ageing population is an established national The key points over the projection period are: issue, however long term projections anticipate The population of the National Park is that this will be particularly acute in the national projected to fall from 14,480 to 12,820 Park, combined with an 11% reduction in (a decrease of 11%) population. When the current Local Plan was drafted the population was predicted to decline The number of children aged under 16 is by between 5 and 10% (2006 and 2008 based projected to decrease by 29% from 2,130 population projections by national Records in 2010 to 1,520 in 2035 of scotland). However, as the table below The number of people of working age is highlights, more recent projections show a projected to decrease by 23% from 8,590 worsening situation. in 2010 to 6,630 in 2035 The population of pensionable age is expected to increase by 24% from 3,760 Table 1: GRO Midyear estimates in 2010 to 4,670 in 2035 % Population change (2010 - 2035)

Scotland 10%

Stirling 16%

National Park Area -11% Perth and Kinross 32%

Argyll & Bute - 10%

West Dunbartonshire - 7%

5101520 0 5 10 15 20 25 30 35

LIVe PaRK MAIN ISSUeS RePORT 27 analysis of the 2011 census provides the following update. The population of the Park has declined slightly since 2001, while scotland as a whole has increased slightly. Both these trends are projected to continue. as the table below highlights, there is a wide variation in the local authority areas that include the Park’s area.

% population Usual resident 2001 2011 change population (2001 to 2011) Loch Lomond & The 15,600 15,168 -2.85 Trossachs national Park scotland 5,062,011 5,295,403 +4.41 86,212 90,247 +4.47 & Bute 91,306 88,166 -3.56 93,378 90,720 -2.93 Perth & Kinross 134,949 146,652 +7.98

Table 2: 2011 census summary

28 MAIN ISSUeS RePORT LIVe PaRK The trends show that, over the 35 National Park last 30 years, younger age groups 30 Scotland (0–19) have been declining and 25 older age groups (45+) have been Perth and Kinross 20 increasing, particularly the age Stirling group 65+. The percentage of 15 West Dumbartonshire resident population within the 10 core 20-29 and 30-44 age groups 5 has decreased by 8.1% over the 0 0–4 5–9 10–15 16–19 20–29 30–44 45–64 65+ last 20 years (1991 to 2011). This age group is illustrated in these two charts which provide comparisons with Figure 1: Age Structure - LLTNPA, Scotland and surrounding areas 2011 other areas and over the last four census returns. The requirement to address population change is an 35 1981 1991 overarching issue considered 30 2001 25 throughout this whole report. 2011 a separate background report 20 on our review of the 2011 census 15 is available on our website. 10 5 0 0–4 5–9 10–15 16–19 20–29 30–44 45–64 65+ age group Figure 2: Trends in the LLTNPA Age Structure

LIVe PaRK MAIN ISSUeS RePORT 29 SUStAINAbILItY sustainability and climate change it is expected that planning will remain central to public policy support these targets in various and should be a key theme in new ways – through low energy design, planning strategies. The Climate efficient use of land, buildings and Change (scotland) act sets a infrastructure, and protecting and target of reducing greenhouse gas enhancing the natural and cultural emissions by at least 80% by 2050, heritage. it is proposed that this is with an interim target of reducing an overarching theme throughout emissions by at least 42% by 2020. the new Local Development Plan which all policies and proposals contribute to.

it is recognised that section 72 of the Climate Change (scotland) act 2009 requires: ‘ A planning authority, in any Local of the projected greenhouse Development Plan prepared gas emissions from their use, by them, must include policies calculated on the basis of the requiring all developments in the approved design and plans for the Local Development Plan area specific development, through to be designed so as to ensure the installation and operation of that all new buildings avoid a low and zero-carbon generating specified and rising proportion technologies.’ it is proposed to amend the Local Plan’s policies to ensure this is met.

30 MAIN ISSUeS RePORT LIVe PaRK The following section provides a summary of the main trends “since 2008 there for discussion. have been significant tHe eCoNoMY since 2008 there have been significant changes in the changes in the economy economy that have affected the national Park area, like all parts of the country – with that have affected the dramatic changes in terms of levels of investment and public and private finance. The effects national Park area…” have included a general rise in unemployment, fewer properties being bought and sold, dramatic reduction in rates of new development, increase in vacant commercial properties, reduction in some public services/ facilities and affordable housing subsidies.

LIVe PaRK MAIN ISSUeS RePORT 31 toUrISM & VISItor experIeNCe investments help create confidence for the private sector to invest: Despite the economic downturn nationally, Significant investment in visitor accommodation and facilities; more people are holidaying at home and visitor strong investment on Loch Lomondside and - The Carrick Golf Resort pressure on Loch Lomond & The Trossachs and spa, ardgartan Hotel & Forest Holidays Lodges. Planning permission for the Ben national Park as a popular visitor destination arthur resort, close to arrochar. This is a 5 star resort that will also include a marina has continued – with indications of an increase in expenditure. Regenerated or refurbished hotels in Luss, Crianlarich and Balquhidder Key indicators include: Infrastructure and Visitor Management improvements – Over 1 million trips were made by UK established water based public transport on Loch Lomond residents to Scotland’s two National east Loch Lomondside: seasonal camping byelaw, informal camping facilities, Parks, accounting for 8% of total traffic management, improved signage, ranger/ police patrols and alcohol byelaw overnight tourism trips in Scotland and 7% of total visitor expenditure 5 Lochs management Plan – first phase of facilities in place in two locations on Loch Lubnaig Loch Lomond Shores is the second most Scenic routes – As part of a Scottish Government popular free attraction in Scotland with initiative, the first pilot schemes are due for 1,125,496 visitors in 2012 completion between April and June 2014

32 MAIN ISSUeS RePORT LIVe PaRK HoUSINg The national Park remains one of the most expensive areas in which to buy a house in scotland and external buyers continue to be a substantial presence on the housing market. There continues to be high levels of need for affordable housing within the national Park. This is particularly the case within the stirling Council area and parts of argyll and Bute Council area around Loch Lomondside. There have been very low rates of housing development over the last few years, as highlighted earlier, with little affordable housing being delivered.

LIVe PaPaRK MAIN ISSUeeSS RePORT 33 INfrAStrUCtUre ANd SerVICeS The importance of the provision, and safeguarding, of infrastructure and services has been highlighted repeatedly by local communities and businesses. This includes basic community facilities such as schools, car parks, public toilets and roads. The quality of broadband service is a key issue in many communities throughout the national Park.

34 MAIN ISSUeS RePORT LIVe PaRK The following topics reflect reNeWAbLe eNergY other important issues or The Park’s water resources have supplementary guidance has been 15 activity in the national Park. long been utilised for both drinking produced to help facilitate this water and energy generation. development. The chart opposite 10 Over the last 10 years there has illustrates the level of interest. been a significant increase in small 5 While there has been little interest run of river hydro schemes which in wind turbine proposals within demonstrate how sustainable 0 the Park, there have been an 2008 2009 2010 2011 2012 2013 development can be successfully increasing number of commercial Number of hydro applications approved delivered within a sensitive wind farm proposals close to the ecological environment and Park’s boundary. some of these landscape. The schemes are have been in locations where their being progressed by landowners, visibility from the Park and setting communities and businesses, to has been of concern. reduce their energy costs and supplement their income.

LIVe PaPaRK MAIN ISSUeeSS RePORT 35 WILd LANd fLood rISk MANAgeMeNt areas of wild land have now been mapped, The national Park was designated a (information which was not available when Responsible authority under the Flood Risk preparing the current Local Plan) and these management (scotland) act 2009 in December maps are included in the national Park 2013 on account of our planning function (the Partnership Plan. scottish natural Heritage current Local Plan requires new proposals that have prepared a national map. Together, may be at risk of flooding to be the subject of a these maps provide a clearer basis for Flood Risk assessment). Primarily this requires managing appropriate development us, in exercising our functions, to ‘act with a and activity in these areas. view to achieving the objectives set out in the flood risk management plan’ for the national and relevant flood risk management plans. The focus within this new regime is that sustainable flood risk management is central to policy and decision making.

QUeStIoNS drIVerS for CHANge Q1: Do you agree with the summary outlined? is there anything we have missed?

36 MAIN ISSUeS RePORT LIVe PaRK 4.2 INtrodUCINg tHe MAIN ISSUeS

From previous sections it is in identifying these we need to focus on what issues not outlined, particularly those relating the Local Develpment Plan can have greatest to landscape, natural and built environment clear that there are some new influence over and where there is a need to are considered to continue to be significant and continuing issues that we change the current Local Plan’s approach. considerations, but that the current framework it ideally needs to be a relatively short list, of policies in the Local Plan remain robust and need to explore. to enable a focused approach that can be effective, with only minor updates required. monitored and is realistic to deliver or improve. The separate Policy list and action summary Where no change is thought likely, or is outlines a summary of our review of current proposed, then the current policies in the policies, highlighting those that are proposed Local Plan will be continued into the Proposed to be amended or kept the same. some Plan (which is consulted upon after the main of the content will be moved into new issues Report and includes the draft policies). statutory supplementary Guidance which will accompany the Local Development Plan.

LIVe PaPaRK MAIN ISSUeeSS RePORT 37 4.3 MAIN ISSUeS, poteNtIAL optIoNS ANd SoLUtIoNS rUrAL eCoNoMY Profile The economy of the national However, the Park is an attractive agriculture, particularly sheep small scale run of the river hydro Park reflects its location as an area for people who work in these production and forestry, remain the schemes are now established as area of accessible countryside businesses to live and commute backbone of the rural economy, a being an important income for within the hinterland of the cities from, and also for small or sole with the support from Government rural landowners, with a significant and towns of central scotland. practice professional consultancies. subsidies being critical. The entire rise in both proposals and schemes This close proximity to large Rural landownership is dominated Park area is currently covered by operating. There has been a low level urban areas and its high quality by privately managed farms and the Less Favoured area support of diversification to generate income natural environment means that a number of large private estates Scheme which reflects the from tourism and leisure interests. tourism dominates. it also means along with public and third-sector challenges to farming across the that the larger towns and cities land, particularly the Forestry area – although this is currently close to the Park are typically Commission which includes large being reviewed. While not the more attractive locations for parts of the Queen elizabeth and largest employer, the importance of businesses and commercial argyll Forest Parks. Decisions their role in land management and premises as they are closer to made by land managers are key to maintaining the traditional character their customers or demand for ensuring a healthy rural economy. of the Park is significant. their services.

38 MAIN ISSUeS RePORT LIVe PaRK ISSUeS ANd opportUNItIeS The Local Plan identified a range of sites and Despite this, the 2013 national Park Business Callander and surrounding area was also a supportive policy for diversifying rural space survey highlights that there is demand highlighted as the place with the highest businesses. Despite this, there has been a low for more land and new premises for business. demand for business space uptake on the development of the sites allocated The key points the survey highlighted were: for economic Development and no uptake Nearly 60% of businesses require rural land/ on the Rural activity area sites which provide 37% of business owners who responded countryside in order to expand their business opportunities for a variety of business/industry feel that they need to relocate their uses in rural locations. The numbers of planning business in order to accommodate The majority of business owners require applications for economic development uses or their business needs, 56% of those in-between 50 - 250 sq m (538 - 2691 development has also been low over the last two require space for an office and/or other sq ft) of new land in order to meet their years (excluding tourism). professional service aspirations

LIVe PaRK MAIN ISSUeS RePORT 39 some of the other barriers to growth raised by an example of this type of approach is our responders include high rents, limited choice of existing modest programme of providing land, planning & sePa restrictions, poor roads, assistance to landowners to help realise the sewage, broadband and a limited number of economic and environmental benefits through serviced units available. whole farm and estate management plans. separate to this, landowners are also increasingly These issues are not uncommon within rural looking to this more holistic approach to realise scotland. However it is perhaps not always clear, the value of their land and assets. or understood, how supportive planning policies QUeStIoNS are already of diversification – from traditional it is clear there is a common ground between the rural activities to leisure, recreation or tourism aims of landowners (to ensure they have a viable rUrAL eCoNoMY Q1: development. While there is no evidence to business, which in turn supports employment, should we provide greater suggest the current economic Development housing and generates expenditure) and the support for a broadening of policies require significant change, there is a need Vision outlined earlier. examples of our current economic activity by providing to prompt a discussion to increase activity. work with landowners include with Glen Falloch greater flexibility for new and Luss estates, Portnellan and inverlochlarig The national Park provides a unique opportunity business development in the Farms. to work towards solutions with partner countryside? organisations. it is one of the few areas in Scotland where landowners can benefit from rUrAL eCoNoMY Q2: the special landscapes and environment and the Do you agree that a pilot business opportunities that this brings to the Park approach should focus on for services and accommodation. two key areas in the Park? as outlined on page 42.

rUrAL eCoNoMY Q3: Do you agree that closer links with Land and Visitor management would be beneficial?

40 MAIN ISSUeS RePORT LIVe PaRK “it is clear there is a common ground between the aims of landowners and our Vision.”

LIVe PaRK MAIN ISSUeS RePORT 41 optIoNS ANd SoLUtIoNS preferred optIoN provide greater flexibility it is suggested that, as a pilot, two areas of the key initiatives that require co-ordination, Park are identified – Luss and its wider area in the short, medium and long term and the area between Balmaha and Drymen – proposals for partnership working where Rural Development Framework areas between landowners, the national Park, are proposed to support bespoke strategies for communities, local authorities and other development in these areas. The Frameworks, partners. These may not be new and as part of the Local Development Plan would reflect existing projects with a and supported in supplementary Planning development implication. For example Guidance, would set out: agreeing the delivery priorities for Luss estate’s strategic Development Framework development opportunities and constraints priorities for infrastructure improvements it would be location based, but not identify current deficiencies in car parking, necessarily site specific water access or other visitor management and community issues that may have a where a specific policy response is development implication required for example, where it might be appropriate detail who the lead organisation or to vary from Park wide policies on housing, landowner is and those that need to tourism or economic development in the contribute countryside – either to be more restrictive or more flexible

42 MAIN ISSUeS RePORT LIVe PaRK The purpose would be to better landowner may need to build The identification of these areas co-ordinate development, provide open market housing in order to reflects feedback at the 2013 more clarity for the landowners generate funding for affordable Charrette events for the Drymen and communities on what is housing as well as to invest in and Buchanan area and also the acceptable in planning terms existing and/or new enterprises, Luss estate Framework, published and also needed. Recognising such as sporting and tourism. by Luss estates in October 2013. that for investment in roads, There may be other areas that this Working with partner car parks, paths and affordable approach could be applied to, if organisations, such as local housing to happen there is also successful. authorities, scottish enterprise, the need for landowners to create Business Gateway, in addition to value in their land to help fund landowners and developers will such development and ensure also be critical. sustainability. For example, a

LIVe PaRK MAIN ISSUeS RePORT 43 Policy eD3 would be amended to: Alternative option 1 support more development in building groups. a. The current policy (ED3) requires new economic development to relate to This would modify (a) adjacent, to introduce the retention of an existing rural based the change to eD3 only within existing building economic activity. This would be amended groups which would be defined. to remove this key relationship which would initial research which reviewed building groups allow any economic activity or use provided in the national Park highlighted that there criteria ‘b’ in the policy is met (safeguard were approximately 485 groups (3 buildings or visual, environmental impacts etc). more that are within 100 metres of each other) with the potential of up to 122 of these having b. ED3 would also be amended to include development potential for housing, tourism or support for new development in accordance economic development. While this research with an agreed Estate Management Plan is not complete, it indicates the potential that the National Park Authority has been development potential of building groups in the a partner in preparing which provides an countryside to support rural businesses. overview of how development fits with land management and investment. This approach would require new guidance to outline the design, siting and access standards/ Our aim is to keep land in active management requirements. and by supporting rural diversification ensure that farming and forestry (which has developed Alternative option 2 the parks iconic landscape) is maintained. Retain current Local Plan approach QUeStIoNS Other economic Development Policies would optIoNS & SoLUtIoNS remain largely the same. for rUrAL eCoNoMY: What option do you prefer? Why?

44 MAIN ISSUeS RePORT LIVe PaRK Visitor Experience Profile National Parks are globally recognised tourism assets and National Park status has given Loch Lomond & The Trossachs the opportunity to add to Scotland’s tourism offer. Tourism provides the major source of income and employment within the National Park and is vital for the local economy, as well as making a significant contribution to the Scottish economy as a whole. The National Park attracts around 4 million visitors and almost 7 million visitor days a year, providing employment for 2,400 people in tourism and recreational activities, accounting for a third of all jobs in the area and supporting around 400 accommodation providers. It is primarily a leisure destination although there is a significant business tourism market with weddings being a major component. 60% of the leisure market are day visitors, mainly from central Scotland, and 40% are overnight visitors, staying on average 4.4 nights in the Park.

LIVE PARK MAIN ISSUES REPORT 45 “The Local Plan is generally considered to be providing a positive framework for guiding tourism development...”

in recent years there has been significant infrastructure including roads, local and The Local Plan is generally considered to be investment in some areas of the Park, long distance paths, piers/pontoons, visitor providing a positive framework for guiding tourism particularly Loch Lomondside and Loch Long. information (including signage), public toilets development, however there are several sites There has also been continued interest for and car parks have benefited from some identified for tourism or recreational uses that small scale accommodation development; improvements led by the national Park have seen little activity or developer interest. a significant proportion of this is for holiday authority and our partners but largely remain While this is most likely as a result of current accommodation in the countryside or on gap in poor condition or offer limited provision in economic circumstances, it may also be due to sites within villages and towns. some areas. improved water transport on Loch an increasingly competitive sector. it is timely to Lomond has successfully offered alternative review these sites and ascertain whether they means of travel to the private car for people to still represent good tourism opportunities or, if explore the Park. Whilst this is a positive start, not, whether they can then be considered for there is still much more to be done to increase alternative uses. opportunities for people to travel to, and around, the Park via boat, bike or boots.

46 MAIN ISSUeS RePORT LIVe PaRK ISSUeS ANd opportUNItIeS The National park tourism Strategy and the National park partnership plan identify the following issues and opportunities:

ISSUeS Lack of and poor quality visitor infrastructure Limited range of/ lack of high quality visitor facilities, particularly accommodation across all market sectors Lack of public transport around the Park Visitor management issues due to visitor pressure resulting in overcrowding in specific locations at peak times opportUNItIeS Additional facilities and improved infrastructure, scenic routes, viewpoints and paths which will incentivise private sector investment and provide supporting services Additional accommodation development Increased activities for visitors Event development Grow the food and drink offer, water transport and better linked walking and cycling routes (to enable more opportunities for short breaks – walking or cycling between different locations in the Park)

LIVe PaRK MAIN ISSUeS RePORT 47 This should be set within the context and range of provision, for but has different markets, each of the National Park’s Tourism accommodation this does not just looking for different things. Strategy which states that ‘with mean high star rated hotels but We must continue to cater for 7 million day visits annually in the also more affordable good quality existing markets but also consider National Park it is not necessarily self catering options as well as additional facilities and experiences about attracting greater numbers camping and motorhome provision that will meet the needs of other but about providing experiences at a range of locations to offer a markets. The challenge is to with a range of offers that appeal diverse range of experiences. do this whilst ensuring that the to targeted market segments and environment and landscape – To achieve this, the key policy encourage greater spend and more the very things that underpin the change proposed is that the overnight stays.’ visitor experience and why people National Park is now viewed as a visit the area –are conserved A high quality visitor experience whole in terms of tourism strategy, and enhanced. should be delivered across all rather than a series of sub- markets in terms of the quality destinations. It is one destination

48 MAIN ISSUeS RePORT LIVe PaRK Where should new development be supported to take Killin Tyndrum – promote advantage of these opportunities? heritage, improve public Tyndrum realm, creation of central hub

Arrochar and Tarbet – marine gateway Crianlarich St Fillans to the national Park, improve sense of Lochearnhead arrival at Tarbet & arrochar, with a focus Balquhidder Callander – a hub on arrochar 3 Villages Hall site (heritage Strathyre for family outdoor centre, new village square) and Tarbet Inverlochlarig adventure and for improved facilities and access to adventure capital of Loch Lomond, better path/safe route the national Park between arrochar & Tarbet Callander - although not mentioned Arrochar Aberfoyle Tarbet in the national Park Partnership Plan

L O as a location for strategic tourism C H development opportunities. Public realm

L Aberfoyle

O – Riverside and main street. untapped

A82 M

O Gartmore potential for forest lodge style self

N D catering for families and groups. short Carrick Luss – enhance the Castle Luss A81 break destination for those who love the visitor experience Balmaha B837 Drymen outdoors. Flooding is a key issue and address visitor management issues Croftamie Gartocharn Drymen – eastern gateway to Loch Lomond. Traffic and parking pressures. Develop better linkages with Balloch Balmaha, alternative means of travel between the two Blairmore & Strone management of visitor pressure at Balmaha

Kilmun, Strone and Blairmore – Balloch – busiest gateway into the national natural and built heritage based tourism Park, water access, Lomond shores & with promotion of water access Balloch Country Park

© Crown copyright and database right 2013. All rights reserved. Ordnance Survey Licence number 100031883

LIVe PaRK MAIN ISSUeS RePORT 49 50 MAIN ISSUES REPORT LIVE PARK it is proposed that the majority of visitor management where the new development should continue national Park authority might seek to be directed to the towns and to trial new approaches or put in QUeStIoNS villages. However there is continued additional infrastructure to tackle VISItor experIeNCe Q1: interest for tourism development visitor pressures and anti-social in the countryside, particularly behaviour. Linked to this, there Callander, Balloch, Tyndrum, Drymen, arrochar and Tarbet holiday accommodation, and is opportunity to trial alternative are identified in the National Park Partnership Plan as the the right balance is required for approaches to support new camping key locations where strategic tourism development will supporting small scale tourism provision, particularly low impact and be supported within the national Park. We think that the development as a way of sustaining informal camping experiences within Aberfoyle area also offers potential for some further tourism the rural economy and existing appropriate countryside areas of development and also that Blairmore, strone and Kilmun businesses, whilst ensuring that the Park. Camping is unlikely to be could better utilise their natural and built heritage and sea the landscape and environment are viable on its own and is most likely to access for tourism and community purposes. safeguarded from an unplanned be sustainable over the longer term Do you agree? are there any other settlements where we and uncoordinated increase in where it is linked to a rural business. should support tourism investment and development? development. This will enable people to experience the Park in new ways, thereby While the Local Development VISItor experIeNCe Q2: enhancing the overall visitor offering. Plan needs to provide clear spatial similarly, there is scope to consider We think that small scale development should be direction for this, there is also a the needs of the motorhome sector supported in appropriate countryside areas but that we desire for it to provide flexibility and recent investment for this at need to better define where these areas are in order to to allow currently unplanned and Loch Lubnaig provides a good basis provide certainty and guidance for investors, developers unforeseen developments to take for monitoring this new approach. and local communities. place. This relates especially to Do you agree?

VISItor experIeNCe Q3: Where should new provision for camping and motor-homes be supported?

LIVe PaRK MAIN ISSUeS RePORT 51 optIoNS ANd SoLUtIoNS This would be accompanied by more detailed supplementary guidance, which would provide preferred optIoN more detailed spatial planning guidance and guidance for different development types – The approved national Park Partnership Plan provides spatial guidance for example visitor accommodation, visitor for directing new tourism development, and the preferred approach facilities & infrastructure and recreation. accords with this: Alternative option (a) Continue to direct larger scale (b) Support small scale development an alternative approach would be as part (a) tourism development to within within the areas shown on map in the above Preferred Option but to consider or adjacent to settlements, (See map - section 2.2). These additional areas to part (b) within which small the sites identified above and are areas with access to a good scale development could be accommodated. in the settlement maps, in range of visitor infrastructure This would require a clear case to be made that addition identify opportunities and facilities, including cycling demonstrates the merits of a particular area of in Aberfoyle and Blairmore, and and walking routes and/or links the Park for accommodating small scale tourism with settlements providing development in terms of available infrastructure, services and transport. facilities, services and transport options. Outside these areas, development will generally only be supported where: Part of it does, or will contribute to, a visitor management plan for a specific area They improve or extend existing facilities They are part of a sustainable local transport solution or They are part of a farm diversification/wider land management QUeStIoNS plan that will help deliver wider land management benefits. This optIoNS & SoLUtIoNS will be linked to the approach for Land and Rural Economy for VISItor experIeNCe QUeStIoN 4: What option do you prefer? Why?

52 MAIN ISSUeS RePORT LIVe PaRK INfrAStrUCtUre ANd SerVICeS Profile Within the national Park, like road is closed, flooded or in poor infrastructure and services means: much of rural scotland, basic condition it has a significant impact roads infrastructure and services are on the community. similarly, there much more important than in is likely to be more than one shop sewers/wastewater treatment more urban areas, as there are or school within a bigger town or drinking water fewer alternatives or choices. For city, although only one in a small example, a community may only rural community. electricity be served by one road, whereas mobile phone reception an urban community may have several access roads. if that one broadband

LIVe PaRK MAIN ISSUeS RePORT 53 as outlined, the quality and Visitor surveys highlight the With changes in health care There is one secondary school capacity can have a significant importance of good quality provision, care and access to care within the national Park: mcLaren impact on quality of life and the facilities/services, such as has now changed. This means High, in Callander, with the economy. The condition of some toilets, car parks, information, that the elderly can receive more area serviced by 5 others in of the roads, lack of public sewers broadband and signage along with care at home – while greater larger towns close to the Park and poor broadband were issues accessible, well located car parks centralised specialist provision (Helensburgh, Vale of Leven, raised throughout the last year in and accommodation. Tourism and day surgery highlights the , and Balfron). our discussions with communities. businesses rely on well maintained need for good public transport. There are many more primary While not solely issues that pavements, paths, roads and There is now less need for large schools, which are central to the planning system can solve, piers so that visitors can visit the elderly care homes, but a greater their communities, one having it is important to ensure new area year round and easily move need for more small homes. This is closed in recent years, a small development does not make the around. The balance of tourism something the Local Development number seeing a reduction in roll situation worse and can certainly development in towns and villages Plan can directly support. and others having little additional help bring improvements – through is a concern in some communities. capacity. The number and location new development or formally of new homes, as well as where highlighting priorities for local, new businesses locate can directly central government and landowner influence the demand for schools. investment programmes.

54 MAIN ISSUeS RePORT LIVe PaRK ISSUeS ANd opportUNItIeS The following provides a summary.

ISSUeS opportUNItIeS Changing needs and demands for public services – for example, Increasing interest, and government support for, community elderly care at home and health care ownership, maintenance or operation of a range of public services Limitations in infrastructure such as poor roads (local and trunk Support, as part of work with local and central government roads), pavements, civic or community space, car parks and partners, improvements in broadband provision information in some locations. Typically, despite the high quality Increased support for community land or building ownership of the natural environment, the quality of these types of infrastructure is poor Growth in small scale hydro Many of the central areas of the towns or villages could be Increase in water based transport on Loch Lomond, with further improved in terms of the location of visitor information, car parks, opportunities in the sea lochs and Loch Katrine community space and traffic management Commercial development, contributing to improved Some schools have restricted capacity – Callander and Drymen infrastructure, can unlock investment Primary for example. In other locations, school rolls are low – New housing development can increase the demand and viability raising concerns within communities of the risk of future closure of services and infrastructure Poor broadband provision across the area East Loch Lomond and 5 Lochs visitor management Flood prevention/protection needed in key locations improvements Disposal of local authority buildings and land The programme of regional and local paths being improved Limited public sewer provision in places – for example Kilmun, Strone and Blairmore

LIVe PaRK MAIN ISSUeS RePORT 55 optIoNS ANd SoLUtIoNS preferred optIoN 1. Continue to focus new development in or QUeStIoNS adjacent to existing settlements – that will INfrAStrUCtUre help secure existing public services & SerVICeS Q1: 2. Prepare area wide policy guidance to secure Do you agree with the a better balance of tourism development opportunities listed? in particularly pressurised locations – as are there others? outlined in the preferred Rural Economy option INfrAStrUCtUre & SerVICeS Q2: 3. Identify priorities for infrastructure or service improvements that new How best to deliver improvements to development may be required to infrastructure that benefits communities contribute to each settlement in and visitors through new development? the Local Development Plan INfrAStrUCtUre 4. Secure greater planning contributions & SerVICeS QUeStIoN 3: for infrastructure, service provision, How can the retention and improvement maintenance or improvements of key community services such as 5. Support greater focus on improving village schools, healthcare, road and broadband and town centres – pavements, signage, be supported? street furniture, car parks, higher quality INfrAStrUCtUre design and use of materials. Where this is & SerVICeS Q4: particularly needed, will be highlighted in ‘Placemaking Priorities’ Do you agree with the options listed? any further suggestions?

56 MAIN ISSUeS RePORT LIVe PaRK HoUSINg Profile Housing remains a key issue for There continues to be a high level the national Park. The quality of of housing need 2 – from many the environment combined with people living and working in the “The quality of ease of access in the south and Park who experience difficulty east to central scotland makes addressing their housing needs on it a popular commuter area for the open housing market. Delivery the environment people on good income levels. it of affordable housing (either for is also popular for people retiring rent or low cost housing for sale) or seeking a lifestyle change and within the rural area is proving to be combined with consequently is one of the most challenging, particularly over recent expensive areas to buy a house in years when there have been lower scotland. analysis of house sales levels of public subsidy available. ease of access in over the recent ten year period Like many rural areas, it is common reveals that 7 out of 10 house place for young people to move buyers came from outside the away to gain further education or the south and east national Park. work experience, with some later wishing to return to raise their family. to central scotland makes it a popular commuter area…”

2 The Population and Housing background report provides information on housing need and demand across the National Park.

LIVe PaRK MAIN ISSUeS RePORT 57 in terms of the types of housing, while there ISSUeS ANd opportUNItIeS are plenty of larger homes that are owner occupied, there are far fewer cheaper (relative new housing can help attract and built, including an increase in to income levels) and smaller sized homes to retain population, and assist in affordable housing options, and that buy or rent. counteracting projected long term new housing developments should population decline. With an ageing provide more smaller sized homes in Very little new housing has been built within population projected for scotland comparison to larger ones. the national Park over recent years. While as a whole, but more acutely for the there remains strong aspirational demand We must also ensure that our national Park, housing provision for housing, the impact of the economic housing supply meets the needs across all tenure types is also critical recession has affected the ability of people to of increasing numbers of smaller in helping achieve a more balanced secure finance, which appears to have reduced and/or older households in order to age profile. demand. not that many of the housing sites help ‘shift the balance of care’ – the (which require a proportion of affordable The housing market within the Park scottish Government’s national housing) have been built and most of the mostly satisfies external demand. policy of supporting people to housing applications approved (around 80%) While in-migration is necessary and remain living at home for as long as have been individual open market houses. should continue to be encouraged, possible. The provision of attractive the housing market at present is homes for older people has wider not adequately meeting the needs benefits because it could in turn of people living and working in the help to free up much needed under- area. it is therefore important that occupied housing for families. new housing should help to better The main issues for consideration address the needs of everyone in are the number of new homes our communities, including families, required up to 2026 and whether young people starting out on the the housing policies are helping to property ladder and older people deliver the right homes to meet the wishing to downsize. We think that needs of the Parks communities and there needs to be greater diversity support the local economy. in the size and types of new housing

58 MAIN ISSUeS RePORT LIVe PaRK The current Local Plan sets The new Local Development a target of 75 new homes a Plan requires planning for the year. Over the last 6 years longer term and creating a (2008-2013) an average of 48 positive planning framework houses have received planning to facilitate and enable new permission and 23 houses have development to come forward in been built each year. the future. identifying a generous supply of land creates a range Given this, is the current target of opportunities and ensures of 75 new houses per year still that housing market recovery is appropriate? The issues that not held back by a lack of land. need to be addressed would Perhaps most importantly, when suggest it is, as considered considering the target number, earlier in terms of need, demand it should be related to where and population change. and how much development this Continuing this target is clearly would mean in our communities. ambitious, however past trends each town or village should have reflect development during a identified land to grow – both period of market depression. This for employment generating has been a period where house development and new homes building rates have been at there for the young and the old. This lowest for a generation. helps create better places – and therefore there should not be a sole focus on the target number. QUeStIoNS HoUSINg Q1: How much new housing is required? What option do you support? Why?

LIVe PaRK MAIN ISSUeS RePORT 59 optIoNS ANd SoLUtIoNS Alternative option 1 Alternative option 2 Modest reduction in housing Significant reduction in housing preferred optIoN supply targets supply targets Continue planning for 75 new houses a year An alternative option, would An alternative option would be be to lower the new housing to consider a lower target that Whilst recent development trends have been supply target to around 50- reflects recent development lower than targeted, we still consider that 60 dwellings per annum. This trends. This option is not the Local Development Plan should continue recognises, but is still in excess favoured given the key role to plan for growth in the region of 75 new of, recent development trends that new housing supply has in dwellings per annum giving an overall housing and would still allow for growth. helping to address predicted target of 750 housing units. This will ensure This will not require the Local population change and decline, a generous supply of land (as required by Development Plan to identify and the requirement to address scottish Government) and will provide a range land for additional dwellings housing needs arising within the of housing opportunities and flexibility for up to 2026, as this can be met National Park. delivery of these. There is presently enough through current land allocations land identified for around 380 houses within and windfall development. allocated housing sites within the current Local Plan, so this will require the Local Development Plan to identify additional allocated land for 160 dwellings up to 2026, with the remainder being addressed through windfall sites. This additional land can be identified, with a focus on the arrochar and Callander areas where there are also proposals for employment land. new housing can be delivered on identified sites and also on small gap sites or on land that is currently used for another purpose).

60 MAIN ISSUeS RePORT LIVe PaRK Due to the challenges of delivering There is presently no planning housing within the national Park, policy guidance or control over we think that more flexibility needs small sites, of up to three units, to be introduced to the housing except for the Loch Lomondside policies to ensure that private communities. The Local sector investment is better utilised Development Plan could include to help cross-subsidise affordable guidance for all small sites as they housing provision. contribute significantly to the housing land supply – the majority Affordable housing targets3 are of new homes built in recent not being achieved (for a range years - and could be better utilised of reasons, but primarily due to to help address communities’ high development costs and lower housing needs. funding availability) and we think that a review is needed to help bring We know that the Loch forward development. This would Lomondside area continues also be in line with recent scottish to experience strong housing Government guidance contained demand and consider that housing within the draft scottish Planning policy still needs to differentiate Policy which states that affordable between this and other areas of housing requirements should the Park. generally be no more than 25%.

QUeStIoNS HoUSINg Q2: 3 Currently the proportion of all housing required to be affordable on sites of four or more units varies from 25% to 50% in most settlements and increases to up to 100% for the Loch Lomondside How can we best deliver communities of Tarbet, Luss, Gartocharn, Drymen and Croftamie housing in the national Park?

LIVe PaRK MAIN ISSUeS RePORT 61 The main policy issues that require consideration are: Whether the affordable housing requirements should be reduced on housing sites of 4 or more units? Whether planning policy should be introduced for sites of up to 3 units, and if so what this guidance should require. For example, should small sites help provide more affordable or smaller sized houses? If not, should we require that a financial contribution is given instead to help fund affordable housing elsewhere? This would provide funding to contribute to the delivery of affordable housing, by existing registered social landlords in the National Park. What is the future role of the Loch Lomondside Local Needs Housing Policy which currently applies to small sites in the Loch Lomond settlements? How can appropriate new housing in the countryside be supported? more detailed background information is outlined in the accompanying Population and Housing background paper.

62 MAIN ISSUeeSS RePORT LIVe PaPaRK We have set out how these policy issues could be addressed in the following options.

IN tHe SettLeMeNtS: preferred optIoN Lower affordable Housing Requirement anD amend current policy approach to require financial contribution on sites up to 3 units in aLL aReas, removing current Local Housing needs Policy for Loch Lomondside a. on housing sites of 4 or more units, reduce the affordable housing requirement to a minimum of 25% for all settlements except for Loch Lomondside (Tarbet, Luss, Gartocharn, Drymen and Croftamie) where a 50% requirement would apply (with flexibility to amend this where abnormal development costs are demonstrated), and b. on housing sites of up to 3 units, require either an affordable or smaller sized house is built, or that a financial contribution is made to help fund affordable housing provision elsewhere within the local area. This new approach would apply to all communities within the National Park including Loch Lomondside communities and would replace the current Local Housing Needs policy for the Loch Lomondside area. There would be a variance in the level of financial contribution required between the Loch Lomondside area and all other communities within the Park, a higher contribution would be required in the Loch Lomondside area to reflect the more pressured demand on this area.

LIVe PaRK MAIN ISSUeS RePORT 63 Alternative option 1 Lower Affordable Housing requirement ANd amend current policy approach to require financial contribution on sites up to 3 units outside Loch Lomondside, retaining current Local Housing Needs policy for Loch Lomondside The Preferred Option and alternative Option a. on housing sites of 4 or more units, reduce 1 introduce the provision of a financial the affordable housing requirement to contribution (otherwise referred to as a a minimum of 25% for all settlements commuted sum) for single units or small sites except for Loch Lomondside (Tarbet, Luss, of under 3 units in lieu of on-site affordable/ Gartocharn, Drymen and Croftamie) where or smaller size housing provision. if supported, a 50% requirement would apply (with supplementary Planning Guidance would flexibility to amend this where abnormal require to be developed in partnership with development costs are demonstrated), and a range of stakeholders to determine the appropriate value of contribution required. at b. on housing sites of up to 3 units, require this stage we would suggest that a sliding scale either an affordable or smaller sized house is of values is used depending on house size and built, or that a financial contribution is made location which would differentiate between the to help fund affordable housing provision more highly pressured Loch Lomondside area elsewhere within the local area. This new (where a higher contribution would be required) approach would apply to all communities and all other areas of the Park. within the National Park except the Loch Lomondside communities where such sites would be reserved for either affordable or local needs housing only.

64 MAIN ISSUeS RePORT LIVe PaRK Alternative option 2 Lower Affordable Housing requirement ANd retain current policy approach

a. on housing sites of 4 or more units, reduce the affordable housing requirement to a minimum of 25% for all settlements except for Loch Lomondside (Tarbet, Luss, Gartocharn, Drymen and Croftamie) where a 50% requirement would apply (with flexibility to amend this where abnormal development costs are demonstrated), and

b. on housing sites of up to 3 units, retain the current approach of allowing open market housing on sites of up to 3 units in all settlements except for the Loch Lomondside settlements where such sites would be reserved for either affordable or local needs only.

QUeStIoNS optIoNS & SoLUtIoNS for NeW HoUSINg IN tHe SettLeMeNtS Q3: What option do you support? Why?

LIVe PaRK MAIN ISSUeS RePORT 65 oN SIteS AdJACeNt to tHe SettLeMeNt boUNdArIeS: preferred optIoN Amend the policy (current Local Plan Policy HOus3 requires 100% affordable housing where there are no available sites in the settlement) to allow for an element of open market housing to enable development, where it is demonstrated that this is necessary to cross-subsidise affordable housing provision. The percentage of open market housing would be calculated on a case by case basis depending on specific site costs. Alternative option 1 retain Local plan policy HoUS3 as currently worded. it would be hoped that cross-subsidy of public funding from commuted sums could fund this on-site 100% affordable housing. Alternative option 2 QUeStIoNS no longer continue with this Local Plan policy optIoNS & SoLUtIoNS for HOus3 and instead focus on identifying NeW HoUSINg oN SIteS sites within settlements, or via amending AdJACeNt to SettLeMeNt settlement boundaries. boUNdArIeS Q4:

What option do you support? Why?

66 MAIN ISSUeS RePORT LIVe PaRK WItHIN tHe SMALL rUrAL Alternative option 1 Alternative option 2 – Not favoured CoMMUNItIeS 4 ANd bUILdINg groUpS IN tHe CoUNtrYSIde: retain Local plan policy HoUS4 as allow open market housing in building groups currently worded and in dispersed rural communities subject to a financial contribution being made to help preferred optIoN This requires that affordable housing is fund affordable housing provision elsewhere provided and that this applies to subsequent Amend current Local plan policy HoUS4 within the national Park. While this option purchasers in perpetuity. The houses would (which supports affordable housing in is most likely to boost development rates, be expected to be small to medium sized perpetuity) to require housing that meets and could help generate funds for affordable (approximately 100 square metres) and be affordable housing needs of the first and housing provision, it is expected that it occupied as the household’s main dwelling. subsequent occupiers for a time limited period will cater mostly for external demand for of 10 years. The houses would be expected to be it is not anticipated that this approach will commuting, retirement, ‘lifestyle change’ small to medium sized (approximately 100 square deliver large volumes of housing but it does and second homes. it is not likely to meet the metres) and be used as the household’s main provide opportunities for households with needs of many people living and working in dwelling. genuine affordable housing needs in the the Park, and could exacerbate rather than rural area. This policy is relatively new and a alleviate the problem of an ageing population. This is likely to help meet the short term longer time period might help test it more This could also result in significant rise in affordable housing need within the Park, and be thoroughly. speculative building, which may have localised more attractive to some landowners to release landscape impacts if not managed carefully land and for some developers and households (further supplementary Guidance would be interested in self-build. it may also be attractive required). to developers who may wish to build to rent (at an agreed affordable level) for ten years with the option to then sell on the open market at a QUeStIoNS later date. This might assist some households optIoNS ANd SoLUtIoNS to meet their housing need via private renting. for NeW HoUSINg WItHIN it would allow open market housing, albeit after SMALL rUrAL CoMMUNItIeS 10 years, in a countryside location, which is a ANd bUILdINg groUpS IN tHe new approach for the national Park. monitoring CoUNtrYSIde Q5: of this approach would need to be undertaken and reviewed. What option do you support? Why?

4 Balquhidder, Brig O’ Turk, Milton, Kinlochard, Port of Menteith, LIVe PaRK MAIN ISSUeS RePORT 67 Balmaha and Milton of Buchanan 68 MAIN ISSUeS RePORT LIVe PaRK placemaking what sites should be considered for development?

LIVE PARK 5 MAIN ISSUES REPORT 69 5 pLACeMAkINg

This next section outlines it has been prepared following opportunities that we would like your management and was raised our ideas for where new a review of the current sites for comments on. We indicate what our by many communities through development identified in the preferred option is, and where we the charrette events. improving development is needed to Local Plan and following a review think there may be alternative sites. these central areas is important realise the proposed Vision. of proposed development sites Given there are few alternatives, for communities but also the submitted to us as well as those we some are an alternative within the businesses in these areas and identified through our own review context of the development strategy. visitors to them and have been and those highlighted during identified as Placemaking Priorities. The maps include existing sites discussions with communities. We These are different from sites as that are proposed to continue are required to identify sufficient they will need collaboration between or change – identified with their land for the next 10 years, with an public bodies and communities. Local Plan site reference – along indication of where longer term with new sites which have a ‘miR’ an explanation of how we have growth should be directed up to reference. This is to be clear what assessed all sites is included 20 years ahead. is new and what is being proposed separately in our site assessment Text is included for each town to be kept the same. Report. This includes details of sites or village that is identified as a proposed that were not included. There are a number of towns settlement in the current Local Plan or villages centres which are that provides a general update on looking tired or could benefit from new development in sites currently improvements. This could be new identified. A summary of some of or improved visitor signs, benches, the key planning issues are outlined, pavement, car parking or traffic along with the development QUeStIoNS pLACeMAkINg Q1: Do you agree with the sites identified for development and the proposed Placemaking Priority sites?

70 MAIN ISSUeS RePORT LIVe PaRK 5.1 toWN ANd VILLAge deVeLopMeNt opportUNItIeS

A Y H T Killin A827 L O C

Tyndrum

A82

A85 Crianlarich A85 St Fillans N Lochearnhead L O C H E A R BEN MORE A82 Balquhidder The following list of towns

I L V O L O C H A84 and villages follows those Strathyre Inverlochlarig identified in the Local Plan

L O C H

S L O as settlements. Balmaha Y

A83 L O C H K A T R I N L E O C H A R K L E T

E is also included, as there N B839 Callander Y B829 F A821 R A83 LO C H A H Arrochar V E N A C H B828 A84 C Tarbet is a specific development

O

L

Strachur C C H Lochgoilhead LO H proposal identified. L A886 B815 O L C Aberfoyle A873 H O Rowardennan

A814 G A82 M O O

I Gartmore

L N

D L G

O N

C O

A81 H L

Luss Main areas of change

E A811

H Balmaha C C K A817 B837 O main areas of change L G Drymen

A

R E unrealised potential Ardentinny A875

L O Gartocharn C A811 A809 Rural Development Framework areas H B832 Kilmun

Balloch A81 Blairmore Reproduced by permission of Ordnance survey on behalf of HmsO. © Crown copyright and database right 2014. all rights reserved. A814 Ordnance survey Licence number 100031883

A82

A8

LIVe PaRK MAIN ISSUeS RePORT 71 AberfoYLe summary of review of existing Development strategy (Local Plan Page 92) The only allocated demand for local tourism is being assessed and is development site remains service businesses (shops, identified as an alternative undeveloped – Housing site pubs etc). While this site site for these reasons. H1 at Old Kirk Loan. There is outside aberfoyle, it Considering the steep remain some opportunities lies on the edge of the topography on the north for small infill development. golf course, on the Rob side of Aberfoyle, the flood Roy Way and provides an risk from the Forth and the Through the 2013 opportunity to respond single narrow bridge to the Charrette and ongoing to the family market. The south (which is a constraint discussion with the area identified is indicative, on future development Community Council, with approximately 40-50 south of the Forth) the a further review of tourism accommodation sites to the east have been opportunities for new units being considered. favoured. development in or close existing recreational use to aberfoyle has been Housing Site H1 is identified and access would need to undertaken. Given as an alternative site, as be safeguarded. feedback, there is a need the landowners current to better support local The existing Forestry intentions are unclear and businesses, a site at Commission service yard also with the flood risk Braeval (miR4) has been (miR3) may also have issue it may not be prudent identified for self catering potential for workshops or to support much more visitor accommodation business units, if there is development south of the which could help increase not a risk of flooding. This Forth as highlighted above.

72 MAIN ISSUeS RePORT LIVe PaRK MIr 4 AberfoYLe New site proposed for lodge style self catering within this area (indicatively 40-50 lodges)

Safeguard existing off road path (Rob Roy Way)

MIr 3 Potential new business and industry site in existing yard area (subject to satisfactory flood risk assessment) keY (INdICAtIVe boUNdArIeS)

preferred SIteS

ALterNAtIVe SIteS

pp 1 pLACeMAkINg prIorItIeS Support improvements to main street and riverside car park propoSed USeS

H1 SUStAINAbLe toUrISM Retain site currently identified for housing (approximately 8 houses) HoUSINg eCoNoMIC deVeLopMeNt

trANSport

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

LIVe PaRKFor full site MAIN boundary ISSU details seeeS accompanying RePORT Site Assessment summary73 report ISSUeS

Risk of Flooding – 2013 Stirling Council review highlights the extent and the potential options for management There are significant constraints on availability of land free from flood risk to the south of Aberfoyle and development to the north is significantly restricted by the topography and woodland There is a need to invest in the public realm as Main Street and the main car park area would benefit from some improvement opportUNItIeS option 1 - preferred maximise investment in the village of those locations with the least likelihood of flood risk by; Supporting appropriate ‘gap-site’ housing development Encouraging public realm improvements to create a high quality shopping and leisure experience Identifying Forestry Commission land at Braeval for visitor QUeStIoNS accommodation AberfoYLe Q1: ALterNAtIVe Do you agree with the preferred option? Why? option 2 – Alternative AberfoYLe Q2: in addition to Option 1: identify the Forestry Commission Yard site (miR3) Do you have any other as a new Rural activity area for economic development uses, subject to alternative options for satisfactory Flood Risk assessment. the future of aberfoyle? Retain existing housing site - H1 - for 8 homes.

74 MAIN ISSUeS RePORT LIVe PaRK LIVE PARK MAIN ISSUES REPORT 75 ArdeNtINNY summary of review of existing Development strategy (Local Plan Page 92) There are no sites identified for development in the adopted Local Plan, however small scale infill development is encouraged to support and sustain the community. ardentinny is a small village which relies on surrounding areas for services and facilities.

ISSUeS opportUNItIeS Employment opportunities are limited, as preferred option are other services/facilities which restricts Continue to support appropriate small gap the capacity for anything but small scale site housing development new development Support improvements to foot paths, Improvement to the roads to Ardentinny street lighting and visitor signage would help businesses and the community Improve footpath and cycle path Road condition/capacity will likely limit new connections to the wider area and development space QUeStIoNS Argyll Forest Park ArdeNtINNY Q1: Do you agree with the preferred option? Why?

ArdeNtINNY Q2: Do you have any other alternative options for the future of ardentinny?

76 MAIN ISSUeS RePORT LIVe PaRK ArdeNtINNY

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 LIVe PaRK MAIN ISSUeS RePORT 77 ArroCHAr ANd SUCCotH summary of review of existing Development strategy (Local Plan Page 96) There has been no development on the sites identified in the Local Plan to date, however planning permission was issued in late 2012 for the Ben arthur resort at the former torpedo range site (sT1). Following the review of potential additional opportunities through the charrette workshops in spring 2013 and subsequently, additional options are identified for two additional housing sites and a Placemaking Priority on the land adjacent to the 3 Villages Hall. The key driver for additional land is the Ben arthur resort.

ISSUeS There is no clear centre to Arrochar and Succoth. It is seen by some as a passing through place There is limited land available for new development to meet the need for housing and commercial facilities Desire for a safe footpath/cycle path network linking with Tarbet*

*refer to the separate section on Tarbet later

78 MAIN ISSUeS RePORT LIVe PaRK Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 Long term For full site boundary details see accompanying Site Assessment summary report development keY opportunity? MIr105 (INdICAtIVe boUNdArIeS) 26 new homes with preferred SIteS upgraded access pLACeMAkINg prIorItIeS

propoSed USeS

St3 & CU2 St3 & CU2 SUStAINAbLe toUrISM Retain existing Tourism & Community development HoUSINg eCoNoMIC deVeLopMeNt

trANSport

CoMMUNItY ACtIVItY

t1 Support improvements to water access St1 St2 & CU1 Ben Arthur Resort/ Tourism & Large tourism Community development development Support safe footpath/cycle opportunity path network linking with Tarbet

pp2 Create village centre, ed1 new heritage centre Economic new public space and Development car parking. land

ArroCHAr H2 Existing housing site ANd SUCCotH MIr7b site for 6 new homes

LIVe PaRK MAIN ISSUeS RePORT 79 opportUNItIeS option 1 - preferred Identify the following additional land to that already identified in the Local Plan: Small housing site for 6 homes on Church Road (MIR 7b) to be a potential enabling development to help fund workshops being delivered on site ED1 adjacent Land for 26 homes at Succoth (MIR 105) (current planning application at the time of writing) QUeStIoNS Placemaking Priority identified on ST2/CU1, considering the work ArroCHAr & the community has been progressing for a new heritage centre along SUCCotH Q1: with their work on proposals with the Arrochar Hotel owners’ for associated new public space and car parking. This is in addition to Do you agree with the Vision? tourism and housing Why? Continue to support the implementation of the tourist development ArroCHAr & at the Ben Arthur resort site – a key inward investment opportunity SUCCotH Q2: for the National Park Do you agree with the it is proposed to prepare a masterplan Framework for succoth. This would Preferred option? Why? provide greater detail on co-ordinating and phasing future development ArroCHAr & – addressing flooding, landscape and access considerations, with the SUCCotH Q3: aim of becoming supplementary Guidance post Local Development Plan adoption. Do you think that in the future the land north of succoth should option 2 - Longer term be reviewed for development Consider the role that the area north of succoth could play in providing potential – when other land future land for development, as outlined in the 2013 Charrette report. identified is developed?

80 MAIN ISSUeS RePORT LIVe PaRK LIVE PARK MAIN ISSUES REPORT 81 bALLoCH St4 Continue to support development of Balloch Castle that safeguards the building and enhances visitor attraction at Balloch Country Park. summary of review of existing Development strategy t3 (Local Plan Page 99) Improve water transport links

There has been little development overall in Balloch on existing sites. St6 Construction has commenced on the former garage site – however, Retain current local plan tourism / recreation sites planning permission has been issued for a hotel on the former site (ST 5, 6, 7 & 8) compound (H6). St19 The boundary of sT6 which included Loch Lomond shores and West Remove housing site to change to tourism / commercial Riverside has been amended to reflect the main area available for development. The Old Station area is identified as a Placemaking Priority. St5 Support opportunities to add to Loch Lomond Shores ISSUeS H5 There are a number of opportunities which need to be realised Retain current local planning site for 8 units through both public and private investment Key sites remain to be implemented, in order to improve the tourism H4 & ed2 offer on the waterfront at Loch Lomond and on the River Leven and Retain current local plan housing / commercial site (22 flats) to develop links with Balloch Castle Country Park H3 Retain current local plan housing site for 23 units

pp3 Support improvements to the public realm around the old station

82 MAIN ISSUeS RePORT LIVe PaRK St4

bALLoCH

New infrastructure to support water transport

St6

t3 St8

Small retail/service or Small service or activity businesses keY activity businesses (INdICAtIVe boUNdArIeS) H3 preferred SIteS

pLACeMAkINg prIorItIeS

propoSed USeS H4 & t2 & ed2 St7 SUStAINAbLe toUrISM pp3 HoUSINg H5 St19 eCoNoMIC deVeLopMeNt

trANSport St5

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 LIVe PaRKFor full siteMAIN boundary ISSU detailseS see accompanying RePORT Site Assessment summary83 report opportUNItIeS preferred option

Establish a Placemaking Priority to continue to support improvements to the public realm in Balloch including the environs around the former railway station building

Strengthen connections to the water front at Loch Lomond Shores to include improved water based transport connections from a new pontoon and improvements to recreational facilities Continue to support new tourist accommodation at West Riverside, with the potential for smaller retail or tourist development close to Loch Lomond Shores. Ensure areas of high amenity woodland are safeguarded Support development at Balloch Castle that safeguards the building and provides a visitor attraction within the Country Park Continue with existing Local Plan sites for new housing development in Balloch

84 MAIN ISSUeS RePORT LIVe PaRK QUeStIoNS bALLoCH Q1: Do you agree with the preferred option? Why? bALLoCH Q2: Do you have any other alternative options for the future of Balloch?

LIVe PaRK MAIN ISSUeS RePORT 85 bALMAHA summary of review of existing Development strategy (Local Plan Page 102)

Balmaha is identified in the current local plan as a small rural settlement due to its size, dispersed and low density development pattern as well as its sensitive landscape setting. No formal settlement boundary is identified in order to retain its rural characteristics and ensure that infill development does not erode these. Whilst no sites are formally identified for development in the current local plan, there are several sites within Balmaha with planning permission for tourism related developments which remain unimplemented.

86 MAIN ISSUeS RePORT LIVe PaRK LIVE PARK MAIN ISSUES REPORT 87 ISSUeS

Visitor pressures at peak times Community concerns over imbalance between holiday accommodation and housing for local community QUeStIoNS Need for improved water access and infrastructure to support modal bALMAHA QUeStIoN 1: shift from car based to water transport Do you agree with the preferred Need for walking and cycling links between Balmaha and Drymen to option? Why? reduce traffic pressures at peak times opportUNItIeS bALMAHA QUeStIoN 2: Do you have any other alternative preferred option options for the future of Balmaha? Identify a site for housing on Forestry Commission owned land (MIR 24) located on the northern side of the main road to the west of Fir Tree Cottage (approximately 10 units to be delivered by Rural Stirling Housing Association) Retain current local plan proposal for improved infrastructure to support water transport Continue to support small scale improvements to existing tourism and visitor facilities in Balmaha Support improved footpath and cycle path connections to Drymen Prepare a Masterplan Framework to help better co-ordinate new development

88 MAIN ISSUeS RePORT LIVe PaRK Support better linkage between Drymen and bALMAHA Balmaha for walking and cycling

MIr24 New site proposed Prepare for housing masterplan (approximately framework 10 houses)

t4 Retain current local plan proposal for improvement infrastructure to support water transport keY (INdICAtIVe boUNdArIeS)

preferred SIteS

propoSed USeS

SUStAINAbLe toUrISM

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 HoUSINg

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 89 rA1 Retain current Rural Activity Area

H9 Retain current housing site

CALLANder H10 Change to retail use

H12 summary of review of existing Development strategy Gap site for housing

(Local Plan Page 99) H13 The main development activity While there is capacity on some of Retain current housing site in Callander has been on the the undeveloped sites mentioned Tannochbrae housing site, (which above, there is need to ensure MIr35 Retain Economic development site is now complete and has delivered there is a sufficient future supply (with amended boundary) 68 new homes) and the consent of development land. This of a supermarket on the site that reflects the aspiration identified MIr36 was identified for housing close by the community at the 2011 Amend existing site to mixed use to Tannochbrae. Housing sites in Charrette and additional land is Pearl Street, Churchfields and the considered to be required. The MIr37a old telephone exchange remain preferred option reflects the Site for 60 new homes, new hotel, economic undeveloped. The Rural activity outcome of the Charrette and development and community uses area at Callander east and the focuses new development to the auchenlaich tourism site are both south, in phases, to ensure that MIr37b undeveloped, as is the majority improvements in public services and Land next to the River Teith for tourism or housing of the Lagrannoch economic the road network are progressed Development site. in tandem. There is also a need MIr39 & ed3 to ensure a focus remains on the Safeguard for potential road new access regeneration of the town centre. to Callander south

St9 Tourism allocation at Auchenlaich

pp4 Focus on Town Centre Regeneration and 90 MAIN ISSUeS RePORT LIVe PaRK public realm improvements MIr 36

H13 CALLANder

pp4

St9 H9 keY H12 (INdICAtIVe boUNdArIeS)

preferred SIteS MIr39 & ed3 ALterNAtIVe SIteS

pLACeMAkINg prIorItIeS H10

propoSed USeS

SUStAINAbLe toUrISM MIr35 HoUSINg

eCoNoMIC deVeLopMeNt

trANSport MIr 37a rUrAL ACtIVItY AreA MIr 37b

CoMMUNItY ACtIVItY rA1 NeW roAd ACCeSS opportUNItY?

Long term tourism Long term development opportunity development once existing quarrying ends? Contains Ordnance Survey data © Crown copyright and database right 2014. opportunity? Aerial Photography © Getmapping plc 2011 For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 91 92 MAIN ISSUES REPORT LIVE PARK ISSUeS opportUNItIeS

Restricted capacity in the nursery, schools Continued support for the regeneration of the town centre, which it and road network (particularly the A81/A84 is proposed should be identified as a Placemaking Priority. This would junction) beyond current identified level of seek to promote community, business and government collaboration development in the Local Plan) to improve signage, pavement, street furniture and Ancaster Square. Finding a successful new use for St. Kessogs is a key priority Need for long term investment in schools, roads and paths to support any additional options - Short term development strategy (2016-2021) development option 1 – preferred: Consolidate Flood risk from both the small watercourses Support development on gap Focus on town centre that drain from the Callander Crags and the sites (H9, H12, H13) within regeneration including a change River Teith settlement boundary and of use for station car park Sensitive landscape, built and natural heritage continue Callander East Rural provided there is an agreed Activity Area. revised approach to car parking – amend existing allocation ST10 Change H10 to be for retail, to to reflect this (MIR 36). reflect planning permission for a supermarket Identify additional development land at Callander south (MIR 37a) Reduce area of ED3 to follow for 60 new homes, new hotel, existing developed area. economic development and community uses

1a. Alternative – retain existing Tourism allocation at Auchenlaich (ST9) in addition to the above preferred option 1b. Alternative – include land adjacent to the River Teith (MIR 37b) that is free of flood risk for tourism or housing in addition in addition to the above preferred options

LIVe PaRK MAIN ISSUeS RePORT 93 option 2 - Alternative: option 3 - Longer term other comments Minor Change development strategy (2021+) Re-use of Cambusmore Quarry, No additional land identified - Preferred – Long term growth once existing quarrying ends support development on gap focused south of the River Teith, (expected to be 2023) may sites (H9, H12, H13) within including areas south of miR 37a. provide an opportunity for settlement boundary and This is dependent on the provision a large scale tourism resort. continue Callander East Rural of a new road bridge, without which This is currently included in the Activity Area. access from Callander east is a key Local Plan as a potential long constraint. Potential access routes term opportunity Change H10 to be for retail, would need to be safeguarded – to reflect planning permission It would be intended to potential access through existing for a supermarket progress Masterplan site eD3 or further east as shown Framework documents as Retain existing Tourism in the Charrette report (please see supplementary Guidance allocation at Auchenlaich (ST9) background papers). for the station car park area, Focus on Town Centre Callander east and south. These Regeneration including a change would provide greater detail of use for station car park on co-ordinating and phasing provided there is an agreed future development revised approach to car parking It is proposed to designate – amend existing allocation ST10 Callander’s retailing and servicing to reflect this (MIR 36). central area as a town centre Reduce area of ED3 to follow existing developed area.

94 MAIN ISSUeS RePORT LIVe PaRK QUeStIoNS CALLANder Q1: Do you agree with the preferred options, or would you support the alternative? Why?

CALLANder Q2: are there other options you think should be supported? Why?

CALLANder Q2: any additional comments or options?

LIVe PaRK MAIN ISSUeS RePORT 95 summary of review of existing Development strategy (Local Plan Page 114) There is one site identified for housing in the current local plan (H14 former Hotel site, 8 units) which remains undeveloped. There also remain some opportunities for small scale infill development.

ISSUeS opportUNItIeS The Lochgoil Community preferred option Action Plan identifies the lack Continue to support housing of a place to meet/community development on the site of the facility within Carrick Castle former hotel as an issue which the local community wishes to address. Continue to support infill development within the settlement boundary, including QUeStIoNS community meeting place/ CArrICk CAStLe Q1: facility. Do you agree with the preferred option? Why? CArrICk CAStLe Q2: Do you have any other alternative Options for the future of Carrick Castle?

96 MAIN ISSUeS RePORT LIVe PaRK CArrICk CAStLe

H14 Retain current local plan site for housing keY (INdICAtIVe boUNdArIeS)

preferred SIteS

propoSed USeS

HoUSINg

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 97 CrIANLArICH summary of review of existing Development strategy (Local Plan Page 116)

The main development activity has been the ISSUeS opportUNItIeS approval and start of the construction of the new To improve identity for Crianlarich through option 1 - preferred by-pass (T5) promoting opportunities to upgrade Support improvements to the public realm The Community’s aspirations for the village have the public realm including visual clutter, in the village been set out in 2011 ‘Crianlarich into action’ footpath improvements including disabled process to establish the communities priorities. access to the station and fencing repairs Identify a small site at Willowbrae for aspirations include: 6 homes (MIR 52) To allocate development opportunities for Creating housing, leisure and employment housing Retain the economic development (ED4) opportunities site to the west of the station should it be To support employment generating new required for the needs of the local forest To develop Crianlarich as a visitor development industry destination Potential flood risk option 2 - Longer term To capitalise on the riverside landscape and links to local and long distance footpaths Review the potential for development between such the West Highland Way the settlement and the Crianlarich by-pass route. Identify further development land to be made available resulting from the Crianlarich by-pass

98 MAIN ISSUeS RePORT LIVe PaRK CrIANLArICH

Support public realm improvements MIr52 in village New site proposed for Consider development potential on approximately 6 houses land between village and new bypass

new by–pass under construction

QUeStIoNS keY (INdICAtIVe boUNdArIeS)

CrIANLArICH Q1: preferred SIteS Do you agree with the preferred option? Why? propoSed USeS ed4 CrIANLArICH Q2: HoUSINg Retain site Do you have any other currently identified eCoNoMIC deVeLopMeNt for economic alternative options for the development future of Crianlarich?

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 LIVe PaRKFor full site MAIN boundary ISSU details seeeS accompanying RePORT Site Assessment summary99 report CroftAMIe summary of review of existing Development strategy (Local Plan Page 118) There has been no development on the sites identified in the current Local Plan.

ISSUeS No mains sewer - may constrain additional development Flood risk from the Catter Burn opportUNItIeS option 1 - preferred Continue to support the existing housing site H15 at Buchanan Crescent for 5 homes QUeStIoNS Continue to support development at Pirniehall (ST11) that secures this redundant building, with enabling housing development along CroftAMIe Q1: other uses such as tourism Do you agree with the preferred option? option 2 - Alternative Why?

In addition or instead of H15, identify the existing long term housing CroftAMIe Q2: opportunity LH2 on the Main Street Do you have any other alternative options for the future of Croftamie?

100 MAIN ISSUeS RePORT LIVe PaRK CroftAMIe

St11 Retain site currently identified for hotel/ education uses but also propose support for housing as enabling development

H15 Retain site currently identified for housing (5 houses)

keY (INdICAtIVe boUNdArIeS)

preferred SIteS

ALterNAtIVe SIteS

propoSed USeS

SUStAINAbLe toUrISM

HoUSINg

LoNg terM HoUSINg LH2 Potential alternative of additional housing site to H15

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 101 drYMeN summary of review of existing Development strategy (Local Plan Page 120) There has been no progress with development Following a review of potential future housing on the housing site identified in the current Local opportunities through the charrette workshops Plan at Gartness Road (Local Plan reference H16 in spring 2013, it was clear there was a desire to & T7) however planning permission is in place, focus new development on remaining gap and and has recently been renewed. some small infill sites within the village including the Salmon scale housing has been approved on infill sites on Leap site and the site north of the cemetery. Balmaha Road. Public realm improvements to the village square were also highlighted as being important – again as identified by the community at the charrette and the Community action Plan.

102 MAIN ISSUeS RePORT LIVe PaRK Support better linkage between Drymen and Balmaha for walking and cycling drYMeN Long term development pp5 opportunity? keY Support improvements to (INdICAtIVe boUNdArIeS) the village square

preferred SIteS pLACeMAkINg prIorItIeS H16 & t7 Retain current local plan site for housing / parking (36 houses) propoSed USeS

SUStAINAbLe toUrISM t6 Retain existing site for HoUSINg car parking on majority trANSport of site H17 & ed5 Identify former Salmon leap for housing eCoNoMIC deVeLopMeNt / commercial development. Consider linkage beyond site boundary rUrAL ACtIVItY AreA

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 MIr 62 For full site boundary details see accompanying Site Assessment summary report Identify new site for housing (approximately 16 units)

rA2 St12 Retain current local plan Retain current local site identified for business / plan site identified for industry tourism / recreation. LIVe PaRK MAIN ISSUeS RePORT 103 ISSUeS

Potential limitations in capacity Need for improved traffic/on of primary school due to new street car parking management housing in the school’s wider Safeguard village character and catchment improve public realm Limited car parking at peak tourist season opportUNItIeS option 1 - preferred Support improvements to Continue to identify Drumbeg village square – identify as a Quarry, to support its Placemaking Priority regeneration Redevelopment of Salmon Leap Identify additional housing site site (H17 & ED5) on land north of the cemetery for 16 homes (MIR 62) QUeStIoNS Support improving non-vehicle drYMeN Q1: access with Balmaha Do you agree with the preferred option 2 - Longer term options 1 and 2? Why? Preferred – Once sites identified are complete, it is proposed that the future drYMeN Q2: focus for housing should be at the eastern approach on the south side of Stirling Road (this is the same area identified in the Charrette report) Do you have any other alternative options for the future of Drymen?

104 MAIN ISSUeS RePORT LIVe PaRK LIVE PARK MAIN ISSUES REPORT 105 gArtMore summary of review of existing Development strategy (Local Plan Page 124) No sites were identified with little new development taking place. The community has successfully started a programme of improvement and repairs to the Village Hall, which is due for completion in spring 2014.

ISSUeS Development opportunities remain limited due to the prominent setting within the wider landscape Limited opportunity for gap site development opportUNItIeS No new opportunities have been identified Seek opportunities to maintain and enhance the built heritage, recognised through the Conservation Area. The recent National Park QUeStIoNS Built Heritage Repair Grant Scheme has provided an opportunity for gArtMore Q1: assistance Do you agree with the above issues Address locally arising housing needs through appropriate small and opportunities? Why? scale development on land close to the village gArtMoreQ2: Do you have any alternative options for the future of Gartmore?

106 MAIN ISSUeS RePORT LIVe PaRK gArtMore

Maintain current development strategy Limited opportunities for new development Support small scale housing adjacent to settlement boundary, where access is possible

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

LIVe PaRK MAINFor full site ISSU boundaryeS details Re seePORT accompanying Site Assessment107 summary report gArtoCHArN summary of review of existing Development strategy (Local Plan Page 126) The development strategy seeks to retain the traditional character of the village and protect its sensitive landscape setting. Development opportunities include small scale development on infill sites within the settlement boundary and an allocated housing site at France Farm. This has an estimated capacity for 6 housing units.

ISSUeS opportUNItIeS It is important to protect the wider agricultural landscape around option 1 - preferred Gartocharn and to retain the existing village character Maintain village character and continue to support infill development A Local Housing Survey for Kilmaronock (undertaken in 2011) on remaining gap sites within the settlement highlighted that there is a small degree of unmet housing need and Retain France Farm (H18) as an identified housing site considering it is demand (around 9 houses required) a suitable site There is general interest for tourism development (mainly self Indentify a new site for housing at Burnbrae Farm (MIR 73b) catering accommodation) in the wider countryside area around for around 10 units to provide greater flexibility for housing land the village. The approved National Park Partnership Plan steers allocation in the village such development to alternative areas of the National Park (cross reference to map in Visitor Experience section) option 2 - Alternative Remove France Farm as an identified housing site, but retain it within the settlement boundary to allow scope for infill development in line with the development strategy.

108 MAIN ISSUeS RePORT LIVe PaRK gArtoCHArN

Sensitive village H18 edge due to Retain current local lanscape plan site for housing (approximately 6 units)

QUeStIoNS keY gArtoCHArN Q1: (INdICAtIVe boUNdArIeS) Do you agree with the preferred SIteS preferred option? Why? propoSed USeS gArtoCHArN Q2: MIr 73b New site proposed for HoUSINg Do you have any other housing (approximately alternative options for the 10 units) future of Gartocharn? Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 109 kILLIN summary of review of existing Development strategy (Local Plan Page 128) One of the two identified small housing sites has been developed (Ballechroisk Terrace). There remains capacity for 4 houses at Lyon Road. There has been no take up of the currently identified (ED6) economic development site and this land is being used for the foreseeable future as a roads depot. 12 flats have been built on the site of the former Cost Cutter shop, providing housing to meet local community needs.

ISSUeS The Station Road area around the road depot There is a need to support and encourage hosts a number of different uses which do not tourism investment in the village and to sit well together. The site is both an industrial draw visitors into the village from the Falls area and an arrival point for visitors (bus of Dochart turning circle and footpath access to Loch Tay The recent housing development appears and the disused railway line) to have helped meet housing need and There are constraints to land for business, demand for the immediate term – however, commercial and general industrial options for future housing land are very development within the village and limited constrained due to topography and flooding opportunities constraints. No further housing sites have been identified for the next plan period

110 MAIN ISSUeS RePORT LIVe PaRK opportUNItIeS preferred option A key opportunity exists around the Station Road depot area, including the land to the south of this. This overall site could accommodate a range of uses and could help address visitors needs via parking, toilets, information and signage QUeStIoNS The approved biomass plant at Acharn, with an kILLIN Q1: anticipated commissioning date of 2017, offers scope Do you agree with the to accommodate other land uses, such as employment, preferred option? Why? business and industry. There may also be scope for horticultural activities using residual heat from the kILLIN Q2: biomass plant. It is proposed that an area – Site MIR 80 - is identified as a Rural Activity Area Do you have any other alternative options for the future of Killin?

LIVe PaRK MAIN ISSUeS RePORT 111 112 MAIN ISSUES REPORT LIVE PARK kILLIN ed6 Retain current local plan site and review H19 use of land to Retain existing the south for housing site for community 4 houses economic development use

keY (INdICAtIVe boUNdArIeS)

preferred SIteS MIr 80 New site proposal for biomass plant , employment, business, industry and horticulture. propoSed USeS

HoUSINg

eCoNoMIC deVeLopMeNt

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 113 kILMUN, StroNe ANd bLAIrMore summary of review of existing Development strategy (Local Plan Page 130) The only development on identified sites has been on the Finnartmore Housing site (H21).

ISSUeS Limited opportunities for new development land The condition of High Road is a constraint to further development off the road, particularly at Blairmore. Considerable investment is required to bring High Road up to adoptable standard There is no mains public sewer Bringing redundant piers back into use QUeStIoNS kILMUN, StroNe & Need to consider how best to sustain local services bLAIrMore Q1: Do you agree with the preferred option? Why? kILMUN, StroNe & bLAIrMore Q2: Do you have any other alternative options for the future of Kilmun, strone and Blairmore?

114 MAIN ISSUeS RePORT LIVe PaRK pp6 kILMUN, StroNe Safeguard retail ANd bLAIrMore frontage Blairmore pier key asset for water access St13 Retain current local plan site Argyll Support for tourism/ community uses Mausoleum recreation / key new access to Kilmun / visitor Blairbeg hill area attraction

Over the longer term review development opportunities to support improvement to the high road.

H22 Retain current local plan keY site for housing (10 units) H21 (INdICAtIVe boUNdArIeS) Retain current preferred SIteS local plan site for housing pLACeMAkINg prIorItIeS (13 units) propoSed USeS

SUStAINAbLe toUrISM

HoUSINg Strone pier key asset Contains Ordnance Survey data © Crown copyright and database right 2014. for water access Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 115 opportUNItIeS option 1 - preferred Following the recent community initiative by the Blairmore Village Continue to support Trust to secure ownership of development within the Blairmore Green, with support from settlement in existing identified the national Park authority and the sites (H21 and H22) and gap scottish Government, proposals are sites being developed to provide Identify Blairmore and Strone Year round visitor Piers as key assets for water accommodation access Car parking and a bus lay-by Highlight the informal adjacent to the village hall recreational Kilmun/Blairbeg Hill area A wildflower garden Seek to safeguard the retail A community facility related to frontage in Blairmore the village hall Promote improvements in the option 2 - Longer term path network, car parking and Review opportunities to make play park provision more use of Kilmun Pier Focus tourism development Seek to improve linkage with around Blairmore Pier/Green Benmore Botanic Gardens (ST13) Review development Seek opportunities to capitalise opportunities to support on the improvements to the improvements to the High Road Argyll Mausoleum

116 MAIN ISSUeS RePORT LIVe PaRK LIVE PARK MAIN ISSUES REPORT 117 LoCHeArNHeAd summary of review of existing Development strategy (Local Plan Page 136) There has been no development on identified sites.

ISSUeS Flooding issues for low lying locations around the loch limit the extent of village expansion and infill development Potential for more all year round tourism related development opportUNItIeS preferred option QUeStIoNS LoCHeArNHeAd Q1: a. Continue support for new housing on the site at Lochearnhead Holiday Centre (H23) Do you agree with the preferred option? Why? b. Promote mixed uses on the allocated Local Plan site ED7 – tourism in addition to LoCHeArNHeAd Q2: economic development. Do you have any other alternative options for the future of Lochearnhead?

118 MAIN ISSUeS RePORT LIVe PaRK LoCHeArNHeAd

ed7 Support mixed use in this site including tourism and economic development

keY (INdICAtIVe boUNdArIeS) H23 preferred SIteS Retain current local plan site for housing (12 units) propoSed USeS

HoUSINg

eCoNoMIC deVeLopMeNt

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011 LIVe PaRK MAIN ISSUeS RePORT 119 For full site boundary details see accompanying Site Assessment summary report LoCHgoILHeAd summary of review of existing Development strategy (Local Plan Page 138) 18 houses have been constructed and are occupied run by both Dunbritton and argyll Community Housing Associations (social-rented 100% affordable housing) on housing site H24. There is permission to build a further 6 houses on this site.

ISSUeS The single track roads that link Lochgoilhead to the A83/A815 will constrain significant new development in the future, however these roads provide an approach that is part of the character of the area The un-adopted road along east side of the loch is a constraint to new development opportUNItIeS There is remaining capacity More widely, the Lochgoil There has been a small for 6 units on the existing Community Action Plan number of planning QUeStIoNS H24 housing site which 2012-2017 identified applications approved LoCHgoILHeAd Q1: could be developed to priorities, some of which for upgrade works to Do you agree with the issues provide further housing to are directly relevant existing hotels or outdoor and opportunities identified the area. This is considered to planning including centres, which highlights above? Why? sufficient for the 2016- a new hydro scheme, the investments by local 2021 period community shop, village businesses LoCHgoILHeAd Q2: improvements, and a new Do you have any other jetty to accommodate alternative options for the larger boats future of Lochgoilhead?

120 MAIN ISSUeS RePORT LIVe PaRK LoCHgoILHeAd

H24 Retain current local plan site with retaining capacity for 6 houses

keY Support village improvements and new jetty to accommodate larger boats (INdICAtIVe boUNdArIeS)

preferred SIteS propoSed USeS

HoUSINg

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

LIVe PaRK MAINFor full site ISSU boundaryeS details Re seePORT accompanying Site Assessment121 summary report LUSS summary of review of existing Development strategy (Local Plan Page 140) Part of the current Local Plan housing site H25 is now a car park following the refurbishment of the Loch Lomond arms Hotel.

ISSUeS Generally, considering that There is a risk of flooding from There is a need to improve Luss is located between the the loch and the Luss Water management of visitors, loch and A82 there are limited at the southern end of the through signage, car parking development opportunities in settlement and the public realm the area opportUNItIeS preferred option Retain the balance of housing Support economic or tourism Support additional car parking site H25 for 4 homes development on the former and a potential new Village QUeStIoNS petrol station and land north of Square on the southern LUSS Q1: Identify land north of Hawthorn the primary school (MIR 93 & 94) approach Cottage (MIR 92) for 10 homes Do you agree with the Vision Support improvements to car for Luss? Why? parking, signage and visitor LUSS Q2: facilities Do you have any other alternative options for the future of Luss?

122 MAIN ISSUeS RePORT LIVe PaRK Support improvements MIr 93&94 to car parking, signage LUSS Support for and visitor facilities economic or tourism development

H25 Retain current local plan site for housing (4 units)

Potential area for village square keY (INdICAtIVe boUNdArIeS) Potential area for car parking

preferred SIteS

propoSed USeS

SUStAINAbLe toUrISM

HoUSINg

eCoNoMIC deVeLopMeNt

MIr 92 New site proposed for housing

Contains Ordnance Survey data © Crown copyright and database right 2014. (approximately 10 units) Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 123 St fILLANS summary of review of existing Development strategy (Local Plan Page 148) Local Plan housing site station Road (H26) has been completed which provided 6 homes.

ISSUeS st Fillans is a picturesque lochside village in which a significant portion of the settlement is designated as a Conservation area. new development should reflect the character of the built heritage. opportUNItIeS Continue support for the current Local Plan housing site H27 QUeStIoNS Future benefits for the local community and St fILLANS Q1: businesses from the new foot/cycle path Do you agree with the preferred option? Why? between Lochearnhead and Strathfillan St fILLANS Q2: Do you have any other alternative options for the future of st Fillans?

124 MAIN ISSUeS RePORT LIVe PaRK St fILLANS

Opportunities to capitalise on path network improvement

H27 Retain current local plan keY site for housing ( 16 units) (INdICAtIVe boUNdArIeS)

preferred SIteS

propoSed USeS

HoUSINg

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 125 StrAtHYre summary of review of existing Development strategy (Local Plan Page 150) No development sites were identified and there has been no notable development since 2011. There has been some infill development, in terms of small housing and tourism development.

ISSUeS There are limited development opportunities in the village due to flooding constraints, and topography. opportUNItIeS No new opportunities are identified. There are some small gap sites within or adjacent to the settlement boundary which may provide development opportunities Improvements to the foot/cycle path network will improve the existing NC7 route

126 MAIN ISSUeS RePORT LIVe PaRK StrAtHYre

QUeStIoNS StrAtHYre Q1: Do you agree with the issues and opportunities? Why? StrAtHYre Q2: Do you have any other alternative options for the future of strathyre?

LIVe PaRK MAIN ISSUeS RePORT 127 and database right 2014. copyright data © Crown Ordnance Survey Contains © Getmapping plc 2011 Aerial Photography tArbet summary of review of existing Development strategy (Local Plan Page 152) There has been no development on allocated Local Plan sites.

ISSUeS opportUNItIeS Tarbet is a busy roadside settlement preferred option dominated by heavy traffic on A82/A83 Retain the opportunities allocated for roads with growth constrained by Loch tourist development in the Local Plan Lomond and the topography (ST14 to ST18) There is no discernible village centre – The Allocate a new housing development loch side park provides short stay car opportunity on land to the south of parking but pedestrian access to the village the A83 (MIR 106b) requires crossing the . There is a need to improve links between the village Longer term option QUeStIoNS and the car park Explore the management of the A83 tArbet Q1: Strengthening the community could be road through Tarbet and encourage the facilitated by provision of affordable housing preparation of a Masterplan for the village Do you agree with the preferred and long term There is potential to improve links to the train options? Why? station and encourage more visitors coming to the National Park by public transport tArbet Q2: Do you have any other alternative options for the future of Tarbet?

128 MAIN ISSUeS RePORT LIVe PaRK tArbet

St16 Retain current local plan site Support establishment or safe walking / cycling link St17 between Tarbet and Arrochar Retain current local plan site

St18 Retain current local plan site

MIr 106b New site proposal for housing (10 units) keY (INdICAtIVe boUNdArIeS) t8 preferred SIteS Retain current local plan proposal pLACeMAkINg prIorItIeS for infrastructure to support water transport propoSed USeS St15 Retain current SUStAINAbLe toUrISM local plan site

HoUSINg St14 pp7 Support preparation of trANSport Retain current local plan site a master plan for Tarbet to explore management options of the A83 through Tarbet. Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 129 tYNdrUM summary of review of existing Development strategy (Local Plan Page 154) There has been no development on identified Local Plan sites.

ISSUeS How to make more visitors stop and spend more time and money in the village rather than short stops passing through to other destinations The trunk road is inhospitable to pedestrians which discourages people from visiting the village The proposed gold mine has the potential to bring jobs and visitors to Tyndrum and create increased demand for new housing. There is uncertainty when the gold mine development is likely to commence development

130 MAIN ISSUeS RePORT LIVe PaRK tYNdrUM

Over the longer term Capitalise on the potential benefits from the goldmine development and provide visitor facilities Identify new commercial/ tourism related developments Review housing land requirements (currently long term housing site to the north of Tyndrum)

keY (INdICAtIVe boUNdArIeS) ed8 Support preferred SIteS commercial pp8 or tourism Support public pLACeMAkINg prIorItIeS development realm improvement

propoSed USeS

SUStAINAbLe toUrISM

HoUSINg

eCoNoMIC deVeLopMeNt

Contains Ordnance Survey data © Crown copyright and database right 2014. Aerial Photography © Getmapping plc 2011

For full site boundary details see accompanying Site Assessment summary report LIVe PaRK MAIN ISSUeS RePORT 131 132 MAIN ISSUES REPORT LIVE PARK opportUNItIeS

option 1 - preferred establish a Key initiative to support improvements to the public realm in Tyndrum including pedestrian /cycle routes improvements including The footway along the A82 road and a safe crossing on the A82 road General improvements to the townscape and public realm Footpath connections between the village, the railway stations and the West Highland Way Support commercial/ tourism related developments on Site ED8 particularly to provide a range and quality of accommodation to meet the identified tourist markets i.e. from low cost accommodation to good quality hotels and self catering facilities Realise improvements to the cycle path infrastructure option 2 - Longer term QUeStIoNS a) To capitalise on the potential benefits from the gold mine development and to provide appropriate visitor facilities tYNdrUM Q1: b) Identify commercial / tourism related developments particularly to Do you agree with the provide a range and quality of accommodation to meet the demand preferred option? Why? from low cost accommodation to higher quality hotels and self catering facilities tYNdrUM Q2: c) Review housing development land options at the northern edge of Do you have any other Tyndrum – currently a long term Local Plan housing site (LH4) alternative options for the future of Tyndrum?

LIVe PaRK MAIN ISSUeS RePORT 133 134 MAIN ISSUES REPORT LIVE PARK more information PLANNING TERMS EXPLAINED Accompanying documents

LIVE PARK6 MAIN ISSUES REPORT 135 6.1 ACCoMpANYINg doCUMeNtS accompanying documents published on www.ourlivepark.com

Draft Environment Report Landscape Capacity Assessment – Strategic Environmental of Callander Assessment Report of Housing Market Monitoring Statement – Overview Research Site Assessment - Summary Business Survey Report Report Retail Survey Report Equality Impact Assessment – Housing Land Audit Screening Report Employment Land Audit Report of Pre-Main Issues Report Engagement 2014 Population and Housing Background Report Charrette and Workshop Reports Gartocharn and Drymen Policy List and Action Summary Landscape Capacity Assessment 2014 Gartocharn Landscape Capacity Assessment update

136 MAIN ISSUeS RePORT LIVe PaRK 6.2 gLoSSArY

AffordAbLe HoUSINg bUILt eNVIroNMeNt CoNSerVAtIoN AreA HoUSINg MArket AreAS Housing that is available to Buildings and structures made an area of special architectural (HMAS) people on modest incomes who by people, as opposed to natural or historic interest designated Relatively self-contained areas generally cannot afford to buy or features. by the national Park authority in within which most people move rent accommodation on the open consultation with local communities. house when their needs or market. CHArrette circumstances change. a charrette is an interactive deVeLopMeNt ALterNAtIVe optIoNS design workshop, in which the The carrying out of building, INfILL SIteS Options which the national Park public, relevant professionals and engineering, mining or other sites which are located within a authority consider as a viable stakeholders work directly with a operations in, over, or under land, or settlement boundary. alternative to the preferred option. specialised design team to generate the making of a material change in a specific community masterplan the use of any buildings or other land INfrAStrUCtUre AMeNItY and operation of a marine fish farm. Refers to transport and domestic a positive element or elements that CLIMAte CHANge services, such as water and contribute to the overall character Changes to the global climate that deVeLopMeNt brIef electricity to support development or enjoyment of an area. For evidence suggests is mainly a result a document prepared to show and allow it to take place. example, open land, trees, historic of human behavior. in some detail, how best to buildings and the inter-relationship develop a site, and can include LeSS fAVoUred AreA between them, or less tangible CoMMUNItY ACtIoN pLAN details of infrastructure, stages of areas in which farmers are entitled factors such as tranquility. is a statement of the of the type of development and design proposals. to financial compensation due to place in which a community aims a natural handicap (such as high bIodIVerSItY to be and what needs to be done in eVIdeNCe bASe altitude, difficult climate or poor Diversity or richness of plant and order to achieve this. The evidence base is the soil). animal life and their habitats. information we gather in order CoMMUted SUM to have a balanced view on what LANdSCApe CHArACter bIodIVerSItY ACtIoN pLAN a payment by developers to the development should be allowed ASSeSSMeNt Identifies priority species and Park authority, or Local authority, where. it contains information a method of analysing and habitats where action to conserve to provide a service or facility, rather relating to the Park’s demographics describing the landscape. and enhance is required. than the developer providing it and what development has taken directly themselves. place over the last number of years

LIVe PaRK MAIN ISSUeS RePORT 137 LISted bUILdINg MoNItorINg StAteMeNt opeN SpACe reNeWAbLe eNergY a building or structure of a document which contains data Green space consisting of any Those sources of energy which architectural or historic interest which forms the evidence base and vegetated land or structure, water are naturally occurring within the included on the list of buildings evaluates the performance of the or geological features in an urban environment and which can either compiled by Historic scotland on current Local Plan. areas, including trees, woodlands be tapped without consuming the behalf of scottish ministers. and paths and ‘civic space’ resource , or where the resource NAtIoNAL pArk pArtNerSHIp consisting of squares, market places can renew itself on a human LoCAL deVeLopMeNt pLAN pLAN (2012-2017) and other paved or hard landscaped timescale. examples include wind, (Ldp) The Partnership Plan sets out the areas with a civic function (source: solar, hydro, wave and tidal. The adopted version of the policy for the management of the sPP11 Physical activity and Open Proposed Plan will become the national Park and the space). reSIdeNtIAL AMeNItY Local Development Plan and will The benefit enjoyed from physical co-ordination of activities of public provide the framework against pLACeMAkINg prIorItY external space which forms part of bodies and office-holders so far as which planning applications are an area highlighted in the main the private home. affecting the Park. assessed, it will be reviewed every issues Report which there is a five years to ensure an up to date particular focus on improved the rUrAL bUSINeSS NAtIoNAL pLANNINg Plan is in place to guide future overall public space through design. Business associated with a rural frAMeWork (Npf) development in the area. location such as agriculture, forestry is the scottish Government’s preferred optIoNS or tourism related activities. strategy for scotland’s long term LoCAL NeedS HoUSINg Options for development which at spatial development. Housing that meets the needs of this moment in time are preferred rUrAL deVeLopMeNt people currently living in the area by the national Park authority. This frAMeWork AreA Not preferred SIteS with a form of housing need and/ opinion is based on the information is an area suggested in the main sites which the main issues Report or households that require to live in we have at present and may be issues Report where through is proposing are not allocated in the the area for employment or social subject to change during the partnership working, a clear strategy Local Development Plan. reasons. consultation stage. would be put in place for the development of these areas.

138 MAIN ISSUeS RePORT LIVe PaRK rUrAL dIVerSIfICAtIoN SCottISH NAtUrAL HerItAge SUStAINAbLe deVeLopMeNt The establishment of new (SNH) Development that meets the enterprises in rural locations. This its role is to look after the natural social, economic and environmental can mean existing businesses heritage, help people to enjoy and need of the present without entering into new areas of activity value it, and encourage people to compromising the ability of future or the creation of entirely new use it sustainably. generations to meet their own enterprises. needs. StrAtegIC eNVIroNMeNtAL SCottISH pLANNINg poLICY ASSeSSMeNt (SeA) WAter eNVIroNMeNt (Spp) involves assessing and taking into all inland surface water, groundwater is the statement of scottish account the environmental effects and wetlands; as well as coastal Government Policy on nationally of a plan or programme. waters. important land use planning matters. SUppLeMeNtArY pLANNINg WILd LANd gUIdANCe/SUppLeMeNtArY areas of mountain and moorland SeCtIoN 75 AgreeMeNt gUIdANCe and remote coast, which mostly also known as a planning obligation Guidance on planning matters lie beyond contemporary human more recently. This is a legal which supplement the development artefacts such as roads or other agreement between a developer plan and which may be a material development. and a local authority which consideration for planning purposes guarantees that certain works and usually published by the WINdfALL SIteS will be carried out, or financial planning authority in connection Development that is granted contributions are paid in accordance with a structure plan or local plan. consent on land or buildings with a planning permission. not specifically identified in the SUStAINAbILItY Development Plan. . examples SCottISH eNVIroNMeNt The capacity to carry out an activity could include development on proteCtIoN AgeNCY (SepA) over time. Often used in the context small gap sites within settlements Public body with a remit for of sustainable development. or development on sites currently environmental protection. used for other purposes.

LIVe PaRK MAIN ISSUeS RePORT 139 140 MAIN ISSUeS RePORT LIVe PaRK LIVe PaRK MAIN ISSUeS RePORT 141 www.ourlivepark.com twitter.com/ourlivepark facebook.com/ourlivepark

instagram.com/ourlivepark Published by: Loch Lomond & The Trossachs National Park Authority April 2014

142 MAIN ISSUeS RePORT LIVe PaRK