OFFICE OF THE SECRETARY TO GOVERNMENT OF THE FEDERATION

PRESENTS

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)

FROM MAY 2015 TO DECEMBER 2017

BY BOSS MUSTAPHA CONTENT

1.0 INTRODUCTION Vision, Mission Statements and Core Mandate

2.0 IMPLEMENTATION OF FEDERAL EXECUTIVE COUNCIL (FEC) APPROVALS FOR:

2.1 Ecological Fund Office 2.2 Cabinet Affairs Office 2.3 Federal Road Safety Corps 2.4 National Hajj Commission of 2.5. National Pension Commission 2.6 National Population Commission 2.7 Economic and Financial Crimes Commission

2 1.0 INTRODUCTION

The Office of the Secretary to the Government of the Federation is the Secretariat of the Presidency responsible for ensuring the effective co-ordination and monitoring of the implementation of Government policies and programmes.

MANDATE Monitor and Coordinate the implementation of Government Policies and Programmes; Serve as frontline advisory institution of the Presidency; Drive Policy formulation, harmonization, and implementation; and Monitor institutions of governance.

VISION To lead and serve as an effective engine room for policy formulation, harmonisation, implementation and monitoring of the institutions of governance.

MISSION To deploy political will, administrative expertise, professionalism and the values of loyalty and commitment in support of the attainment of the goals of the Federal Government.

3 2.1 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF USER ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE PROCUREME IMPLEMENTAT APPROVAL AGENCY THE PROJECT SKILLED/ COMPLETION) NT DURATION ION (%) (%) UNSKILLED

The Scope of work include: Site clearing /earth work; Removal of Reconstruction of Weak structures/old bridge; Yola-Mubi Bridge Construction of Culverts; at Kaa'a Shiwa Ecological 1 November, 2015 7 Months N/A 100% 38 Re-construction of bridge and and Mail 30 - Fund Office Construction of mile 30 - Kwambla Kwambla Road, Road. The project is 100% Adamawa State completed. Commissioned and handed over.

The Scope of work include: Construction of Concrete Channels; Daura Township Construction of Box Culverts; Erosion Control, Ecological 2 December, 2015 9 Months N/A 100% 38 Stone-Pitching and Rock Dumps for Phase I, Daura, Fund Office each erosion Control works. The Katsina State project is 100% completed. Commissioned and handed over.

The Scope of work include: Daura Township Site clearing; Erosion And Construction of Culverts and Ecological 3 Flood Control December, 2015 11 Months N/A 100% 45 Drains; and completion of Dam's Fund Office Project, Phase II, accessories. The project is 100% Katsina State completed. Commissioned and handed over.

The Scope of work include: Site Clearing; Drains of various sizes & dimension Kaltungo Gully in different locations in the town Erosion Control Ecological 4 December, 2015 12 Months N/A 100% 38 including Culverts and 5km Road Works, Gombe Fund Office improvement. State The project is 100% completed. Awaiting commissioning and handing over. 4 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF PROJECT DATE OF USER ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROCUREME IMPLEMENTAT TITTLE APPROVAL AGENCY THE PROJECT SKILLED/ COMPLETION) NT DURATION ION (%) (%) UNSKILLED

The Scope of work include: Gully Erosion Site Clearing; Control Works Ecological Construction of Culverts; and road 5 at Veritas December, 2015 7 Months N/A 100% 38 Fund Office improvement. The project is 100% University, completed. Awaiting Bwari, Abuja. commissioning and handing over.

The Scope of work include: (i) Site Clearing Kwoi Erosion (ii)Earth work and Flood (iii) 1.5km Road Improvement; Ecological 6 Control Project February, 2017 10 Months N/A 100% 40 (iv) 5 Nos. Culverts and 725m of Fund Office at Jaba, Kaduna Drainages of various dimensions . State The project is 100% completed and awaiting commissioning and handing over.

The Scope of works include: i. Grubbing of the mapped site; ii. Excavation of the mapped site; iii. Oily Sludge treatment under aquatic condition and clean up; Remediation of iv. Site construction; Warri Refinery Ecological 7 February 2017 12 Months N/A 100% 45 v. Bio-remediation of the to its Phase II, Delta Fund Office natural state; and State vi. Restoration of the air quality free of hydrocarbon odour. Project is 100% completed and awaiting commissioning and handing over.

5 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & ACCESSED STATUS OF DATE OF USER CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE PROCUREMEN BY THE IMPLEMENTAT APPROVAL AGENCY SKILLED/ COMPLETION) T DURATION PROJECT ION (%) UNSKILLED (%)

Construction of 1.2km Drainage Channelization and Channilization. Other scope and Desilting of includes Construction of 2 Ogbagba and Ecological 8 March, 2017 12 Months N/A 100% 45 Culvents and sand filling. 100% Okoko Rivers in Fund Office Completed. Awaiting Osogbo Phase commissioning and handing I&II, Osun State over.

The Scope of work include: (i) Clear areas for access to all locations, remote all grass and tree within the 1 No. Canal (ii) Remove Top soil up to a depth not exceeding 250mm in Mubi Flood/ soft soil for all drains, outlets Erosion Control structure or as may be Works and River Ecological 9 March, 2017 11 Months N/A 80% 45 redirected by Engineers; Yalzaram Training, Fund Office The Status is 80% and it is on- Phase I Adamawa going; State Challenge: Work was suspended at site by Contractor during the raining season due to heavy downpour. However, the Contractor is back on Site and work is progressing.

6 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF USER ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE PROCUREME IMPLEMENTAT APPROVAL AGENCY THE PROJECT SKILLED/ COMPLETION) NT DURATION ION (%) (%) UNSKILLED

The scope of work include: i. Earth works; ii. Concrete drains; Erosion Control iii. Construction of culverts; Works at Nda, Ecological iv. Pavement/Surfacing. 10 Nnobi and Agbor, March, 2017 Fund 7 Months N/A 90% 38 The project is 90% and work is Idemili LGA, Office on-going. Challenge: The Anambra State progress of the project was slow due to communal issues which has been taken care of.

The Scope of work include: (i) Dredging of the River (2,1km) length (ii) De-silting of the River Adiabo Channel Okutikang Beach Ecological (iii) Construction of 2.75km 11 Gully Erosion March, 2017 Fund 14 Months N/A 90% 40 embankment. The Status is Control Works, Office 90% and it is on-going. Cross River State Challenge: Contractor not moving with the timeline and has received two warnings. However, the Contractor is back on site and work is progressing.

7 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

NO OF FUNDS CONTRACT & STATUS OF JOBS REMARKS DATE OF USER ACCESSED BY SN PROJECT TITTLE PROCUREMENT IMPLEMENTAT CREATED (PROSPECTS OF APPROVAL AGENCY THE PROJECT DURATION ION (%) SKILLED/ COMPLETION) (%) UNSKILLED

12 Erosion/Flood March, Ecological 12 Months N/A 50% 45 The Scope of work Control 2017 Fund include: Project of Rice Office (i) Clear areas for Field, Bagudu access to all LGA, Kebbi locations, remove State all grass and tree within the canal (ii)Remove Top soil up to a depth not exceeding 250mm in soft; (iii) Construction of 1.2km Access Road. The Status is 50% and it is on-going. Challenge: Contractor is not moving according to timeline and consequently has been written two letters of warning in July, 2017 and January, 2018 respectively.

8 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF & ACCESSED STATUS OF JOBS PROJECT DATE OF USER REMARKS (PROSPECTS OF SN PROCUREM BY THE IMPLEMENT CREATED TITTLE APPROVAL AGENCY COMPLETION) ENT PROJECT ATION (%) SKILLED/ DURATION (%) UNSKILLED The Scope of work include: (i) Dam/Dyke Construction; (ii) Spillway, Stilling Basin and Bottom outlet; (iii) 5 Nos Reinforced concrete Culverts construction; (iv) Canal Construction. Erosion/Flood The Status is 40% and it is On- Control Project of Ecological 13 March, 2017 15 Months N/A 50% 45 going. Rice Field, Suru Fund Office Challenge: The flood from River LGA, Kebbi State Niger due to heavy downpour at the peak of raining season forced the Contractor to suspend works at site for about 3 months. the Contractor is back on site and has submitted a new work plan which is still within the project time frame.

The Scope of works include: i. Rehabilitation of Sabke Treatment Plant; ii. Completion of Distribution Sabke/Dutsi and Fed. Min. of Network (Reticulation); Mashi Water 14 March, 2017 Water 19 Months N/A 70% 45 iii. Completion of Dutsi Water Supply Project, Resources Supply and Irrigation Plant; Katsina State iv. Completion of Mashi Water Supply and Irrigation Plant; and v. Associated Works. The Project is 59.9% On-going.

The Scope of work include: Ecological (i) Site clearance Work; Challenges at (ii) 2 Nos. Culvert and 850m length Alex Ekwueme Ecological of Drains; 15 April, 2017 8 Months N/A 100% 45 University, Ndufu Fund Office (iii) 2.7km Pavement and Surfacing . Alike Ikwo, Ebonyi The project is 100% completed. State Awaiting Commissioning and 9 Handing Over. ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF & ACCESSED STATUS OF JOBS DATE OF USER REMARKS (PROSPECTS OF SN PROJECT TITTLE PROCUREM BY THE IMPLEMENT CREATED APPROVAL AGENCY COMPLETION) ENT PROJECT ATION (%) SKILLED/ DURATION (%) UNSKILLED The Scope of work include: Gully Erosion (i) Site clearance Work; Control and (ii) Rehabilitation of 2.9km Flood Ecological Access Road and Drains . 16 Improvement April, 2017 Fund 10 Months N/A 100% 40 The Status is 100% completed. Works at Awlaw, Office Awaiting commissioning and Oji-River LGA, handing over Enugu State

Rijau, Dugge, The Scope of work include: Dukku, (i) Site Clearance and T/Magajiya and Earthworks; Genu, Rijau Local Ecological (ii) 5 Nos. Culverts and 950m 17 Government April, 2017 Fund 12 Months N/A 100% 38 length of drains; Erosion and Office (iii) Pavement and surfacing Flood Control The Status is 100% completed. Project, Niger It is yet to be commissioned State and handed over.

The scope of work include: . i. Site Clearance; ii. Earthworks and Excavation; Erosion Control iii. Construction of Concrete Works at Odo Ecological Drains and Culverts; and 18 Alaamo, April, 2017 Fund 10 Months N/A 100% 40 iv. Road work and Pavement Ogbomoso, Oyo Office Construction. State The project is 100% completed and awaiting commissioning and handing over.

10 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF & ACCESSED STATUS OF JOBS PROJECT DATE OF USER REMARKS (PROSPECTS OF SN PROCUREM BY THE IMPLEMENT CREATED TITTLE APPROVAL AGENCY COMPLETION) ENT PROJECT ATION (%) SKILLED/ DURATION (%) UNSKILLED The Scope of work include: (i) Site Clearance; (ii) Construction of 150m Erosion Control Spillway; on the Drainage (iii) Desilting of reservoir; Basin of Ecological (iv) Reinstatement of Dam 19 Ahmadu Bello April, 2017 Fund 8 Months N/A 95% 38 Embankment; University, Office (v) Provision of 275m Toe Lake/Dam, Drain; (vi) Provision of intake structure. The Status is 95% and it is on- going. The Scope of work include: Nkari Erosion (i) Site clearance Work; Control and (ii) Rehabilitation of 2.5km Ecological Road Access Road and Drains . 20 April, 2017 Fund 9 Months N/A 72% 40 Improvement The Status is 72% and it is on- Office Works, Ini LGA, going. Communal clashes Akwa Ibom State slowed down the progress of work.

The Scope of work include: Gully Erosion (i) Construction of Drains for and Road flood and racketed structures Improvement Ecological (800m) 21 Works, April, 2017 Fund 10 Months N/A 80% 40 (ii) 1.3km Road Improvement Nasarawa Town Office Works . (Phase I), The Status is 80% completed Nasarawa State and it is on-going.

11 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS STATUS OF DATE OF USER PROCUREME ACCESSED CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT APPROVAL AGENCY NT BY THE SKILLED/ COMPLETION) ION (%) DURATION PROJECT (%) UNSKILLED

The Scope of work include: (i) Site clearance Work; University of (ii) Concrete Work. Calabar (iii) Construction of 1,283m Erosion & Ecological reinforced Concrete 22 Flood Control May, 2017 Fund 9 Months N/A 100% 38 drainage; Works, Office (iv) Construction of 6 Nos. Calabar, Cross Concrete catchment pit. The River State Status is 100% completed. Awaiting commissioning and handing over. The Scope of work include: (i) Clearance and Fumigation; (ii) Shaping and compaction of cleared section; (iii) Reclamation of eroded section; Erosion (iv) Construction of draining Control and chambers; Project at Ecological (v) Construction of 350m 23 June, 2017 Fund 6 Months N/A 85% 38 State House Office length Retaining walls Presidential (vi) Embankment of Villa, Abuja protection chutes, stone pitching. The Status is 70% and it is on-going. Challenge: The Security clearance from State House delayed the early 12 commencement of the project. ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS STATUS OF PROJECT DATE OF USER PROCUREME ACCESSED CREATED REMARKS (PROSPECTS OF SN IMPLEMENTAT TITTLE APPROVAL AGENCY NT BY THE SKILLED/ COMPLETION) ION (%) DURATION PROJECT (%) UNSKILLED Flood And Erosion The Scope of work include: Control Of (i) Excavation Ecological Damaturu- (ii) 7,250m Concrete Drains and 24 June 2017 Fund 9 Months N/A 50% 45 Balmari- 7 Nos. of Culvert . Office Gashua Road, The Status is 50% and it is on- Damaturu LGA, going. Yobe State

The Scope of work include: Ondo (i) Site Clearance and Township Ecological Earthworks; November, Contractor 25 Erosion Fund 9 Months N/A 40 (ii) Culverts and drains; 2017 Mobilized Control Works, Office (iii) Pavement and surfacing. Ondo State Construction work is on-going. The project is 15% Ongoing.

Erosion Control and Road The Scope of work include: Improvement (i) Site clearing Work; Ecological Works of November, (ii) Culvert and Drains; 26 Fund 9 Months N/A 45% 40 OORA/AAYO 2017 (iii) Pavement and Surfacing . Office River, Oke- Construction work is on-going. Ayo Area, The project is 45% Ongoing. Ilesha, Osun State

13 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS STATUS OF PROJECT DATE OF USER PROCUREME ACCESSED CREATED REMARKS (PROSPECTS OF SN IMPLEMENTAT TITTLE APPROVAL AGENCY NT BY THE SKILLED/ COMPLETION) ION (%) DURATION PROJECT (%) UNSKILLED

Project Development The Scope of work include: Institute (i) Excavation Enugu Ecologica (ii) 765m Concrete Drains (PRODA) November, 27 l Fund 8 Months N/A 50% 40 and 5 Nos. Culvert. Federal 2017 Office Construction work is on- Ministry of going. Science & The project is 50% Ongoing. Technology, Enugu State

Gandu, The Scope of work include: Tukuntawa (i)Site clearance and earth and Zoo Road Ecologica November, Contractor work 28 Erosion and l Fund 6 Months N/A 40 2017 Mobilized (ii) Culverts and drains; Flood Control Office (iii) Pavement and surfacing. Project, Kano The project is 15% Ongoing. State

14 ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF & ACCESSED STATUS OF JOBS PROJECT DATE OF USER REMARKS (PROSPECTS OF SN PROCUREM BY THE IMPLEMENT CREATED TITTLE APPROVAL AGENCY COMPLETION) ENT PROJECT ATION (%) SKILLED/ DURATION (%) UNSKILLED

The Scope of work include: (i)Construction of Old Cemetery Drains; Tundun (ii)Construction of new Magayaki/Ce Cemetery Drains; metery/ Gully (iii) Construction of Drains Erosion and Ecologica November, Contractor along Dallatu Road. 29 Flood l Fund 6 Months N/A 40 2017 Mobilized (iv)Repair to completed Control, Office section of main drain; Sokoto (v)Extending of drains from South LGA, other roads to main drains Sokoto State Construction of main drain at Magayaki, The project is 15% Ongoing.

The Scope of work include: i. 100m Shoreline Shoreline protection; and Ecologica Protection, November, ii sand filling. 30 l Fund 8 Months N/A 70% 45 Alebiri, 2017 Dredging Machine moved to Office Bayelsa State site and work has began in earnest. The project is 70% Ongoing.

15 ECOLOGICAL FUND OFFICE (EFO) PROJECTS BELOW FEDERAL EXECUTIVE COUNCIL (FEC) THRESHHOLD FROM MAY 2015 TO DECEMBER 2017 ARE IN ANNEX (I)

Total Numbers of Projects : 64 Numbers of Completed Projects: 55 Numbers of Ongoing Projects: 9

JOB CREATION ➢ Skilled Jobs 357 ➢ Unskilled Jobs 1,350

16 ESTIMATED NUMBER OF JOBS CREATED BY EFO PROJECTS FROM MAY 2015 TO DECEMBER 2017

▪ Though the projects are short termed but during the period, several jobs were created ▪ The following are the types of Skilled and Unskilled Employees employed by Contractors/Consultants;

Skilled Unskilled ➢ Civil Engineers Labourers ➢ Structural Engineers ➢ Highway Engineers ➢ Water Engineers ➢ Mechanical/Electrical Engineers ➢ Technicians ➢ Welders ➢ Carpenters ➢ Masons ➢ Painters

17 ▪ In addition, these projects also impacted lives in the Communities in many ways; ➢ Increase in economic productivity ➢ Safety of lives and properties ➢ Improvement in the standard of living ➢ Access to Farmlands and Markets ➢ Reduction in prices of food items ➢ Increased Inter-Communal relationship and peace ➢ Reduction in cost of transportation ➢ Federal Government’s presence being felt ➢ Improved security within the Communities ➢ Value of properties improved/enhanced ➢ Communities have extended appreciation to Federal Government

▪ For Small and Medium size projects, about 90 lives are impacted which translate to about 5,760 lives in 64 projects executed ▪ For Bigger projects, about 120 lives are impacted which translate to about 3,600 lives in 30 projects executed ▪ About 8,820 lives were directly impacted and empowered 18 ESTIMATED NUMBER OF JOBS CREATED BY EFO PROJECTS FROM MAY 2015 TO DECEMBER 2017

▪ Out of 64 projects which fall within the EFO Tenders Board approval limit, about 357 skilled employees were engaged ▪ The Unskilled labours were about 1,409 Labourers

▪ Out of 30 projects which fall within the Federal Executive Council (FEC) approval, 270 skilled employees were engaged The Unskilled labour were about 1,350

▪ 3,386 Professionals and Unskilled labour were created

19 ESTIMATED NUMBER OF JOBS CREATED BY EFO PROJECTS FROM MAY 2015 TO DECEMBER 2017

Nos of Jobs Created by EFO Projects from May, 2015 to Dec., 2017

Key: 2759 Skilled Employees Civil Engineers Structural Engineers Highway Engineers Water Engineers Mechanical Engineers Technicians Welders Carpenters Painters Masons

Unskilled Labour Labourers

627

20 Skilled Unskilled 2.2 CABINET AFFAIRS OFFICE PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM THE CABINET AFFAIRS OFFICE (CAO)

S/N MEETING OF REFERENCE NUMBER AND IMPLEMENTING DECISION TAKEN IN COUNCIL DETAILS OF ACTION FEC AND SUBJECT OF MEMORANDUM MDAS TAKEN DATE 1. EC(2015)14TH AOB: CAO Conclusion 8 i. Implemented MEETING OF ii. Report on the 7 DECEMBER, Residential Accommodation for i. The President directed that Residential 2015 Ministers proposals be made to address Accommodation for Ministers’ accommodation Ministers has been challenge approved by the Federal Executive Council and awaiting implementation

2. EC(2016) 3RD 1. EC(2016)3: Report of the Cabinet CAO Conclusion 4 i. Cabinet Committee MEETING of Committee on Nigeria’s accession to Assignment 17 the (Budapest) Convention on i. Approved the recommendations completed and FEBRUARY, Cybercrime, (CET NO.185). of the Committee as highlighted in Report submitted 2016. paragraph 9 (i to iii) of the memorandum

3 EC(2017)12TH 1. EC(2017)78: Approval for the Report of CAO Conclusion 5 Cabinet Committee MEETING OF the Cabinet Committee to Resolve the 1. Approved the following Assignment 29 MARCH , Issue of Ministerial oversight of the ICT recommendations of the Cabinet completed and 2017 Sector in Nigeria Committee: Report submitted Section 148(1) of the Constitution gives the President the power to assign responsibilities and mandates to Ministers and this discretion cannot be constrained by any existing laws,

21 CABINET AFFAIRS OFFICE PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM THE CABINET AFFAIRS OFFICE (CAO)

President to direct the Business of Government should be accepted as the basis of authority for the assignment of mandates to MDAs.

The mandates of MDAs are determined by the direction of Government Policy and Extant Laws should be reviewed to support the implementation of Government policy. The Laws regulating the operations of NITDA, NIGCOMSAT Ltd. and Galaxy Backbone Ltd should be reviewed and brought in line with the policy intentions of Government

The Policy of Government on the mandates of the Ministries of Science & Technology and Communications is as stipulated in the extant circular conveying the approved responsibilities, structure and parastatals of the two Ministries which is SGF Circular ref. No. 59386/IV/760 of 15 August, 2011. This Circular should be re-issued by this Administration for the avoidance of doubt.

The mandate to drive information Technology given to the Ministry of Communications was a deliberate decision of Government to create a specialized sector to leverage the emerging potentials in ICT and this should be kept separate from the MS&T, in accordance with global best practices and the wishes of ICT professional bodies in Nigeria.

The Ministry of Communications, which is the rightful agency in which the Presidential Council proposed on e-Government is to be domiciled, should review the composition of the proposed Council and include all critical stakeholders before resubmitting the memorandum to Council. 22 CABINET AFFAIRS OFFICE PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM THE CABINET AFFAIRS OFFICE (CAO)

The Federal MS&T presently has oversight of 17 parastatals, which are mostly research Agencies. It is not optimal for its span of control and effective supervision to further increase the number of parastatals under it and therefore, the status quo should be maintained.

There is need for greater collaboration and harmonious working relationship between the Ministries of Communications and Science & Technology to ensure that the end result of innovation is applied to develop the ICT sector.

The full functional review of the mandates of all Ministries should be immediately undertaken and the report presented to the Federal Executive Council for consideration and approval.

Since the Committee did not find any reason to support the objection by the Minister

of Science & Technology that the subjects of the memoranda revolve around the statutory mandates of that Ministry, the Minister of Communications should represent the following two memoranda for Council’s consideration.

the Nigeria e-Government Master-Plan 2016-2020. the Nigeria ICT Sector Roadmap 2016-2019.

23 CABINET AFFAIRS OFFICE PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM THE CABINET AFFAIRS OFFICE (CAO) 4 EC(2017)14TH AOB: CAO Conclusion 8(ix) i. Completed . MEETING OF ii. Directory of 12 APRIL, Re-activation of the Website of i. Directed that every Ministry functional official 2017 Ministries should submit to Cabinet Affairs websites of MDAs Office the upgrade on the status already compiled of their official websites, by the Cabinet including the names of their Affairs Office with appropriate Desk Officers, for the Desk Officers presentation to Council. also listed

5 EC(2017)17TH AOB: CAO Conclusion 13(xi) Complied with . MEETING OF 10 MAY, 2017 Need to Adhere to the Rules Guiding i. Directed that, henceforth, the Processing of Council memoranda to be considered at Memoranda Council meetings must be circulated on or before Friday preceding the meeting

6 EC(2017)30TH 1. EC(2017)186: Approval for the CAO Conclusion 8 Complied with . MEETING OF 9 Award of Contract for the Engineering AUGUST, 2017 Procurement and Construction of the i. Directed the Cabinet Affairs Office 3,050mw Mambilla Hydroelectric to convey the directive of Council Power Project, Gembu, Taraba State to the AGF/MoJ to enable him propose a suitable date for the meeting with the Minister of Power, Works and Housing within a few days to resolve the likely legal issues that may arise on the matter

24 CABINET AFFAIRS OFFICE PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM THE CABINET AFFAIRS OFFICE (CAO)

7 EC(2017)33RD 1. EC(2017)184: Approval for the CAO Conclusion 5 i. Cabinet committee . MEETING OF passage into law of the: constituted and 13 Constitution (alteration) Bill, 2017: i. Stepped down Memorandum assignment is on- SEPTEMBER, Electoral Act (Amendment) Bill, EC(2017)184 to enable the Vice going 2017 2017; Political Parties and President and the Attorney Electoral Offences Commission General of the Federation & Bill, 2017; and constituency Minister of Justice to constitute delimitation centre bill, 2017 a Cabinet Committee that would examine the Bills, with a view to addressing the issues raised by the Vice president, and submit a Report to Council. 8 EC(2017)35TH 1. EC(2017)180: Approval of the CAO Conclusion 4 i. Cabinet committee . MEETING OF Draft National Policy on Internally constituted and 27 Displaced Persons In Nigeria, 2017 i. Stepped down Memorandum assignment is on- SEPTEMBER, EC(2017)180 on the Draft going 2017 National Policy on Internally Displaced Persons in Nigeria 2017, for members to further study the policy document and to enable the National Commission for Refugees, Migrants & Internally Displaced Persons to address the issues raised by members and re-present to Council within 2 weeks.

i. Directed the Ministry of Interior to put in place mechanisms for effective monitoring of the activities of all organisations assisting the IDPs, and that a Committee should be set up to 25 check the activities of those organisations CABINET AFFAIRS OFFICE 9. 2. EC(2017)209: Approval for the CAO Conclusion 5 i. Cabinet committee Report And Recommendations of the constituted and Inter-Ministerial Working Committee i. Stepped down Memorandum assignment is on- on the Status of Nigeria’s Membership EC(2017)209 to enable members to going of International Organisations and aggregate their views on the Report Associated Financial Obligations and re-present same to Council within 2 weeks.

i. Directed the Minister of Finance to include all the external statutory obligations in the budget for onward transmission to the National Assembly (NASS) for approval, to avoid the embarrassment which the non-payment of Nigeria’s assessed financial obligations to the IOs might cause the country

10 EC(2017)37TH 1. EC(2017)228: Approval of the Report CAO Conclusion 4 i. The White Paper . MEETING OF 11 of the Technical Committee on Industrial Drafting Committee is OCTOBER, 2017 Relations Matters in the Federal Public i. Directed the Acting Secretary to the chaired by Minister of Service Government of the Federation to Labour & Employment. constitute a White Paper Drafting Committee to examine the Report of i. The assignment is on- the Technical Committee on Industrial going and the Relations Matters in the Federal Public Committee would soon Service and submit its report back to Council. recommendations to Council.

i. Directed members to critically study the Report and submit their inputs to the Office of the Secretary to the Government of the Federation.

i. Directed that the Committee Report be circulated to members for their information and guidance 26 CABINET AFFAIRS OFFICE PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM THE CABINET AFFAIRS OFFICE (CAO)

11 EC(2017)44TH AOB: CAO Conclusion 9(vii) i. Complied with MEETING OF ii. Actionable 29 Need to modify the Reporting of i. Directed the Council Secretariat decisions/directive NOVEMBER, Council Discussions Under any to modify its rendition of AOB s are now reflected 2017 Other Business (AOB) in the discussions to capture under AOB Conclusions, to Reflect Actionable actionable decisions and Decisions/Directives directives of Council as appropriate.

27 2.3 FEDERAL ROAD SAFETY CORPS (FRSC) THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL FROM 2015 TO DATE

FUNDS CONTRACT & STATUS OF REMARKS DATE OF USER ACCESSED BY S/N PROJECT TITLE PROCUREMENT IMPLEMENTATION (PROSPECTS OF APPROVAL AGENCY THE PROJECT DURATION (%) COMPLETION) (%)

APPROVAL FOR THE AWARD OF CONTRACT FOR THE VEHICLES 1 DIRECT PROCUREMENT OF 23/11/2016 FRSC 30 DAYS 100 100 DISTRIBUTED AS OPERATIONAL VEHICLES ATTACHED FOR THE FEDERAL ROAD SAFETY CORPS

28 LIST OF FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

DATE OF NEW REG S/N MAKE/TYPE COMMAND CHASSIS NO PURCHASE/ CONDITION PURPOSE NO ALLOCATION

1 IVM P/UP A01 459 RS RSHQ TSD FKZSR31B2ET110079 DEC 2016 FUNCTIONAL PATROL

2 IVM P/UP A01 542 RS RS 5.14 IGARA UNIT FKZSR31B2ET030051 DEC 2016 FUNCTIONAL PATROL

3 IVM P/UP A01 79 RS RS 6.2 A ODUKPANI OUTPOST FKZSR31B2ET110039 DEC 2016 FUNCTIONAL PATROL

4 IVM P/UP A01 842 RS RS 8.36 OGORIMAGONGO UNIT FKZSR31B2ET030160 DEC 2016 FUNCTIONAL PATROL

5 IVM P/UP A01 868 RS RS 4.14 BUKURU UNIT FKZSR31B2ET110021 DEC 2016 FUNCTIONAL PATROL

6 IVM P/UP A01 869 RS RS 7.18 YANGOJI UNIT FKZSR31B2ET030022 DEC 2016 FUNCTIONAL PATROL

7 IVM P/UP A01 870 RS RS 5.12 BENIN TOLL GATE UNIT FKZSR31B2ET110128 DEC 2016 FUNCTIONAL PATROL

8 IVM P/UP A01 887 RS RS 10.31 TALATA MAFARA UNIT FKZSR31B2ET110093 DEC 2016 FUNCTIONAL PATROL

9 IVM P/UP A01 919 RS RS 8.37 OKENE UNIT FKZSR31B2ET030021 DEC 2016 FUNCTIONAL PATROL

10 IVM P/UP A01 920 RS RS 2.28 A ILARO OUTPOST FKZSR31B2ET030091 DEC 2016 FUNCTIONAL PATROL

11 IVM P/UP A01 921 RS RS 2.23 A IBAFO OUTPOST FKZSR31B2ET110092 DEC 2016 FUNCTIONAL PATROL

12 IVM P/UP A01 922 RS RS 2.23 MOWE UNIT FKZSR31B2ET030095 DEC 2016 FUNCTIONAL PATROL

13 IVM P/UP A01 923 RS RS 7.111 B BWARI OUTPOST FKZSR31B2ET030132 DEC 2016 FUNCTIONAL PATROL

14 IVM P/UP A01 924 RS RS 6.13 ISIOKPO UNIT FKZSR31B2ET110013 DEC 2016 FUNCTIONAL PATROL

15 IVM P/UP A01 925 RS RS 12.21 BIU UNIT FKZSR31B2ET110057 DEC 2016 FUNCTIONAL PATROL

16 IVM P/UP A01 926 RS RS 7.11 GWAGWALADA UNIT FKZSR31B2ET110118 DEC 2016 FUNCTIONAL PATROL

17 IVM P/UP A01 927 RS RS 5.21 WARRI UNIT FKZSR31B2ET110085 DEC 2016 FUNCTIONAL PATROL

18 IVM P/UP A01 928 RS RSHQ TSD FKZSR31B2ET030172 DEC 2016 FUNCTIONAL PATROL

29 LIST OF FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

19 IVM P/UP A01 929 RS RS 7.26 SABON WUSE UNIT FKZSR31B2ET030066 DEC 2016 FUNCTIONAL PATROL

20 IVM P/UP A01 930 RS RS 2.114 WHARF UNIT FKZSR31B2ET110162 DEC 2016 FUNCTIONAL PATROL

21 IVM P/UP A01 931 RS RS 11.37 KISI UNIT FKZSR31B2ET110129 DEC 2016 FUNCTIONAL PATROL

22 IVM P/UP A01 932 RS RS 7.1 FCT SECTOR FKZSR31B2ET030127 DEC 2016 FUNCTIONAL PATROL

23 IVM P/UP A01 933 RS RS 7.12 ABAJI UNIT FKZSR31B2ET030116 DEC 2016 FUNCTIONAL PATROL

24 IVM P/UP A01 934 RS RS 8.34 ZARIAGI FKZSR31B2ET110105 DEC 2016 FUNCTIONAL PATROL

25 IVM P/UP A01 935 RS RS 9.32 KM 78 ABA UNIT FKZSR31B2ET110005 DEC 2016 FUNCTIONAL PATROL

26 IVM P/UP A01 936 RS RS 9.23 NKALAGU FKZSR31B2ET110043 DEC 2016 FUNCTIONAL PATROL

27 IVM P/UP A01 937 RS RS 5.16 UWAN-ESIGIE UNIT FKZSR31B2ET030019 DEC 2016 FUNCTIONAL PATROL

28 IVM P/UP A01 938 RS RS 6.4 BAYELSA SECTOR FKZSR31B2ET110178 DEC 2016 FUNCTIONAL PATROL

29 IVM P/UP A01 939 RS RS 11.33 APATA UNIT FKZSR31B2ET110112 DEC 2016 FUNCTIONAL PATROL

30 IVM P/UP A01 950 RS RS 7.26 A TAFA OUTPOST FKZSR31B2ET110031 DEC 2016 FUNCTIONAL PATROL

31 IVM P/UP A01 951 RS RS 8.12 A ODO-OWA OUTPOST FKZSR31B2ET110025 DEC 2016 FUNCTIONAL PATROL

32 IVM P/UP A01 952 RS RS 8.1 A IDOFIAN OUTPOST FKZSR31B2ET110154 DEC 2016 FUNCTIONAL PATROL

33 IVM P/UP A01 953 RS RS 2.21A GATE 3 OUTPOST IJEBU-ODE FKZSR31B2ET030060 DEC 2016 FUNCTIONAL PATROL

34 IVM P/UP A01 954 RS RS 1.42 GUMEL UNIT FKZSR31B2ET110158 DEC 2016 FUNCTIONAL PATROL

35 IVM P/UP A01 955 RS RSHQ TSD COBRA FKZSR31B2ET030118 DEC 2016 FUNCTIONAL PATROL

36 IVM P/UP A01 956 RS RS 11.21 A AJEBANDELE OUTPOST FKZSR31B2ET030143 DEC 2016 FUNCTIONAL PATROL

37 IVM P/UP A01 957 RS RS 11.14 IKIRUN FKZSR31B2ET110003 DEC 2016 FUNCTIONAL PATROL

38 IVM P/UP A01 958 RS RS 10.2A YAURI OUTPOST FKZSR31B2ET110026 DEC 2016 FUNCTIONAL PATROL

39 IVM P/UP A01 959 RS RS 11.16 GBONGAN UNIT FKZSR31B2ET110161 DEC 2016 FUNCTIONAL PATROL

30 40 IVM P/UP A01 960 RS RS 11.24 ASEJERE UNIT FKZSR31B2ET110087 DEC 2016 FUNCTIONAL PATROL LIST OF FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

1 PGT 301 ACCESS 06-04 RS RSHQ MVA (HEAD PLANT GWA/LADA) VF3DDHMYBDJ847434 DEC 2016 FUNCTIONAL ADMIN

2 PGT 301 ACCESS 24-04 RS RS 2.0 LAGOS ZONAL COMMAND VF3DDHMYBEJ699925 DEC 2016 FUNCTIONAL ADMIN

3 PGT 301 ACCESS 32-04 RS RS 10.2 KEBBI SECTOR VF3DDHMYBDJ877755 DEC 2016 FUNCTIONAL ADMIN

4 PGT 301 ACCESS 37-04 RS RS 12.3 YOBE SECTOR VF3DDHMYBFJ546682 DEC 2016 FUNCTIONAL ADMIN

5 PGT 301 ACCESS 52-04 RS RSHQ MVA (HOS PRINT FARM) VF3DDHMYBEJ549807 DEC 2016 FUNCTIONAL ADMIN

6 PGT 301 ACCESS 55-04 RS RS 4.3 NASARAWA SECTOR COMDR VF3DDHMYBFJ546669 DEC 2016 FUNCTIONAL ADMIN

7 PGT 301 ACCESS 57-04 RS RS 12.2 BORNO SECTOR VF3DDHMYBDJ877759 DEC 2016 FUNCTIONAL ADMIN

8 PGT 301 ACCESS 59-04 RS RS 10.1 SOKOTO SECTOR CMDR VF3DDHMYBEJ546155 DEC 2016 FUNCTIONAL ADMIN

9 PGT 301 ACCESS 60-04 RS RS 12.1 BAUCHI SECTOR VF3DDHMYBDJ877762 DEC 2016 FUNCTIONAL PATROL

10 PGT 301 ACCESS 61-04 RS RS 11.1 OSUN SECTOR VF3DDHMYBDJ819994 DEC 2016 FUNCTIONAL ADMIN

11 PGT 301 ACCESS 64-04 RS RSHQ TRG CMDT JOS VF3DDHMYBDJ887148 DEC 2016 FUNCTIONAL ADMIN

12 PGT 301 ACCESS 65-04 RS RS 10.3 ZAMFARA SECTOR CMDR VF3DDHMYBDJ877761 DEC 2016 FUNCTIONAL ADMIN

13 PGT 301 ACCESS 72-04 RS RS 9.3 ABIA SECTOR VF3DDHMYBDJ887149 DEC 2016 FUNCTIONAL ADMIN

14 PGT 301 ACCESS 73-04 RS RS 8.2 EKITI SECTOR VF3DDHMYBFJ546657 DEC 2016 FUNCTIONAL ADMIN

15 PGT 301 ACCESS 85-04 RS RS 7.1 FCT SECTOR VF3DDHMYBFJ533271 DEC 2016 FUNCTIONAL ADMIN

16 PGT 301 ACCESS 93-04 RS RS 5.3 HEAD AWKA PLANT VF3DDHMYBDJ805296 DEC 2016 FUNCTIONAL ADMIN

17 PGT 301 ACCESS 98-04 RS. RS 8.3 KOGI SECTOR VF3DDHMYBFJ539979 DEC 2016 FUNCTIONAL ADMIN

18 PGT 301 ACCESS 99-04 RS RSHQ PIO VF3DDHMYBFJ546684 DEC 2016 FUNCTIONAL ADMIN

19 PGT 301 ACCESS A01 940 RS RS 7.111 A GWARIMPA OUT POST VF3DDHMYBFJ546663 DEC 2016 FUNCTIONAL PATROL

20 PGT 301 ACCESS A01 941 RS RS 11.13 IPETU-IJESHA VF3DDHMYBDJ881229 DEC 2016 FUNCTIONAL PATROL

21 PGT 301 ACCESS A01 943 RS RS 11.35 EGBEDA UNIT VF3DDHMYBDJ881230 DEC 2016 FUNCTIONAL PATROL

22 PGT 301 ACCESS A01 945 RS RS 7.11 GWAGWALADA UNIT VF3DDHMYBFJ546674 DEC 2016 FUNCTIONAL PATROL

23 PGT 301 ACCESS A01 946 RS RSHQ TSD VF3DDHMYBDJ864528 DEC 2016 FUNCTIONAL ADMIN

24 PGT 301 ACCESS A01 947 RS RS 7.110 LUGBE UNIT VF3DDHMYBDJ805295 DEC 2016 FUNCTIONAL PATROL

25 PGT 301 ACCESS A01 948 RS RS 11.12 ILESHA VF3DDHMYBDJ873928 DEC 2016 FUNCTIONAL PATROL

26 PGT 301 ACCESS A01 949 RS RS 7.1 A MPAPE OUTPOST VF3DDHMYBFJ546675 DEC 2016 FUNCTIONAL PATROL

27 PGT 301 ACCESS HQ 96 RS RSHQ TSD VF3DDHMYBFJ546696 DEC 2016 FUNCTIONAL ADMIN

SUMMARY:

IVM PICK -UP = 40 31 PGT 301 ACCESS = 27 2.4 NATIONAL HAJJ COMMISSION OF NIGERIA (NAHCON) THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017 S/NO PROJECT COST OF DATE OF USER CONTRACT FUNDS STATUS OF REMARKS TITTLE PROJECT APPROVAL AGENCY & ACCESSD IMPLEMENT (PROSPECT (N) PROCUREM BY THE ATION (%) OF ENT PROJECT COMPLETION) DURATION 1. Acquisition, . 8TH NOVEMBER, National Hajj 2017 - 2019 ▪ Partly 75% ▪ Awaiting the and 2017. Commission of funded Completion Balance to be Renovation of Nigeria from (Properties returned to Acquired (HAHCON) Savings purchased. Hajj Account. Properties, from Un-renovated) ▪ The Funds Furnishing and Service required for Equiping the Charges to renovation Properties, Pilgrims and and Relocation and Capital Furnishing of of Office to the Budget the new Office newly Appropriati has been Acquired on Act of included in Properties 2017. the 2018 named Metrol ▪ The sum of Budget Plaza, at Plot N1.5B was Proposal 991/992 raised from Mailari Street, Hajj Central Savings Business over the District, FCT, past years; Abuja. ▪ Balance was to be funded from Year 2017 Budget Appropriati on out of which 50% had been 32 released. 2.5 NATIONAL PENSION COMMISSION THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS ACCESSED STATUS OF REMARKS S/N PROJECT COST OF PROJECT DATE OF USER AGENCY PROCUREME BY THE PROJECT IMPLEMENTATIO (PROSPECTS OF TITLE APPROVAL NT DURATION (%) N (%) COMPLETION)

1 Direct $539,130.72@N3 11/1/2017 National Within five 33.33% 70% Deployment of Procurement 04.75/$ (approved Pension (5) working (Deployment of Licenses as at and = by Federal Commission days from (N54,766,695.64) Lisenses) February 2018: Acquisition of N164,300,086.92 Executive the 1. Microsoft Microsoft to be paid in 3 no Council) execution of Office Plus Office 365 equal instalment contract Professional Enterprise over a period of 3 agreement. 2016 License years A license is (400 Licenses) 2. SharePoint given Server Enterprise 2016 (1 Server) 3. Project Professional 2013 (5 Licenses) 4. Windows Server 2016 (5 Licenses) 5. SQL Server Standard Core 2017 (1 Server) 6. Windows 10

33 2.6 NATIONAL POPULATION COMMISSION THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS ACCESSED STATUS OF REMARKS S/ PROJECT TITLE DATE OF USER AGENCY PROCUREME BY THE PROJECT IMPLEMENT (PROSPECTS N APPROVAL NT DURATION (%) ATION (%) OF COMPLETION)

1 Direct 17/05/2017 National 30 Days N308,480,000.00 100% Completed Procurement of Population Five Toyota Land Commission Cruiser Jeeps;

One Toyota Hilux Double Cabin Pick-Up

One Toyota Coaster Bus for Operational uses.

34 2.7 ECONOMIC AND FINANCIAL CRIMES COMMSSION THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS STATUS OF REMARKS S/N PROJECT TITLE DATE OF USER AGENCY PROCUREME ACCESSED BY IMPLEMENTATION (PROSPECTS APPROVAL NT DURATION THE PROJECT (%) OF (%) COMPLETION)

1 Award of 12/10/2016 EFCC 100% Completed Contracts for the Direct Procurement of Operational Vehicles for the Economic and Financial Crimes Commission (EFCC)

2 Award of Contract 26/4/2017 EFCC 80% On-going for revised estimated total cost for the Contract for the Completion of the On-going Construction of the EFCC Corporate Headquarters Office, Abuja

3 Award of Contract 6/12/2017 EFCC 8 Weeks 0% On-going for the Provision of Internet Broadband and Firewall for the EFCC Headquarters and all its Zonal Offices 35 PICTORIAL EVIDENCES OF SOME OF THE APPROVED FEDERAL EXECUTIVE COUNCIL (FEC) PROJECTS FROM MAY 2015 TO DECEMBER 2017

36 ECOLOGICAL FUND OFFICE UNIVERSITY OF CALABAR EROSION & FLOOD CONTROL WORKS, CALABAR, CROSS RIVER STATE

BEFORE

Above represents sample of parts of the ecological site before the commencement of work 37 UNIVERSITY OF CALABAR EROSION & FLOOD CONTROL WORKS, CALABAR, CROSS RIVER STATE DURING

AFTER

38 Above represents sample of parts of the on-going work at site UNIVERSITY OF CALABAR EROSION & FLOOD CONTROL WORKS, CALABAR, CROSS RIVER STATE

AFTER

39 Above represents sample of parts of completed work REMEDIATION OF THE HYDROCARBON SLUDGE AT THE WARRI REFINERY AND PETROCHEMICAL COMPANY PHASE II, WARRI SOUTH LGA, DELTA STATE.

BEFORE DURING

Above represents sample of parts of the ecological sites before the Above represents sample of parts of the on-going work at the site commencement of work

AFTER

40 Above represents sample of parts of the completed work EROSION CONTROL IN AWLAW TOWN, OJI RIVER L.G.A. ENUGU STATE

DURING

BEFORE

AFTER

41 Above represents sample of parts of the ecological site before the commencement of work EROSION CONTROL IN AWLAW TOWN, OJI RIVER L.G.A. ENUGU STATE

DURING

42 Above represents sample of parts of the on-going work at the site EROSION CONTROL IN AWLAW TOWN, OJI RIVER L.G.A. ENUGU STATE

AFTER

43 Above represents sample of parts of the completed work CHANNELISATION AND DE-SILTING OF OKOKO AND OGBAGBA RIVERS IN OSOGBO, OSUN STATE

BEFORE DURING

Above represents sample of parts of the ecological sites before Above represents sample of parts of the on-going work at the commencement of work site AFTER

44 Above represents sample of parts of the completed work RIJAU, DUGGE, DUKKU, T/MAGAJIYA AND GENU EROSION AND FLOOD CONTROL, RIJAU LGA, NIGER STATE

BEFORE

45 Above represents sample of parts of the ecological site before the commencement of work RIJAU, DUGGE, DUKKU, T/MAGAJIYA AND GENU EROSION AND FLOOD CONTROL, RIJAU LGA, NIGER STATE

DURING

46 Above represents sample of parts of the on-going work at the site RIJAU, DUGGE, DUKKU, T/MAGAJIYA AND GENU EROSION AND FLOOD CONTROL, RIJAU LGA, NIGER STATE

AFTER

47 Above represents sample of parts of the completed work DAURA TOWNSHIP EROSION CONTROL, PHASE I, DAURA, KATSINA STATE

DURING

48 Above represents sample of parts of the on-going work at the site DAURA TOWNSHIP EROSION CONTROL, PHASE I, DAURA, KATSINA STATE

AFTER

49 Above represents sample of parts of the completed work DAURA TOWNSHIP EROSION AND FLOOD CONTROL WORKS, PHASE 2, KATSINA STATE

COMMISSIONED AND HANDED OVER

50 Above represents sample of parts of the completed work KWOI EROSION AND FLOOD CONTROL WORKS, JABA, KADUNA STATE

BEFORE

51 Above represents sample of parts of the ecological site before the commencement of work KWOI EROSION AND FLOOD CONTROL WORKS, JABA, KADUNA STATE

DURING

52 Above represents sample of parts of the on-going work at the site KWOI EROSION AND FLOOD CONTROL WORKS, JABA, KADUNA STATE

AFTER

53 Above represents sample of parts of the completed work SABKE/DUTSI AND MASHI WATER SUPPLY PROJECT, KATSINA STATE AWAITING COMMISSIONING

ON-GOING

54 Above represents sample of parts of the on-going work at the site EROSION CONTROL WORKS AT ALEX EKWUEME UNIVERSITY, NDUFU ALIKE IKWO, EBONYI STATE

BEFORE DURING

AFTER

55 Above represents sample of parts of the ecological site before the commencement of work EROSION CONTROL WORKS AT ALEX EKWUEME UNIVERSITY, NDUFU ALIKE IKWO, EBONYI STATE

DURING

56 Above represents sample of parts of the on-going work at the site EROSION CONTROL WORKS AT ALEX EKWUEME UNIVERSITY, NDUFU ALIKE IKWO, EBONYI STATE

AFTER

57 Above represents sample of parts of the completed work EROSION CONTROL WORKS AT ODO ALAAMO, OGBOMOSO, OYO STATE

BEFORE DURING

Above represents sample of parts of the ecological site before the Above represents sample of parts of the on-going work at the site commencement of work AFTER

58 Above represents sample of parts of the completed work FLOOD AND EROSION CONTROL WORKS , DAMATURU – BALMARI – GASHUA ROAD, DAMATURU LGA, YOBE STATE

DURING

BEFORE

59 Above represents sample of parts of the ecological site before the commencement of work FLOOD AND EROSION CONTROL WORKS , DAMATURU – BALMARI – GASHUA ROAD, DAMATURU LGA, YOBE STATE

DURING

60 Above represents sample of parts of the on-going work at the site FLOOD AND EROSION CONTROL WORKS , DAMATURU – BALMARI – GASHUA ROAD, DAMATURU LGA, YOBE STATE

ON-GOING

61 Above represents sample of parts of the on-going work at the site GULLY EROSION CONTROL WORKS AT VERITAS UNIVERSITY, BWARI, ABUJA

BEFORE DURING

Above represents sample of parts of the ecological site before the Above represents sample of parts of the on-going work at the site commencement of work

AFTER

62 Above represents sample of parts of the completed work EROSION AND FLOOD CONTROL WORKS AT PROJECT DEVELOPMENT INSTUTUTE (PRODA), FEDERAL MINISTRY OF SCIENCE & TECHNOLOGY ENUGU STATE BEFORE

63 Above represents sample of parts of the ecological site before the commencement of work EROSION AND FLOOD CONTROL WORKS AT PROJECT DEVELOPMENT INSTUTUTE (PRODA), FEDERAL MINISTRY OF SCIENCE & TECHNOLOGY ENUGU STATE

ON-GOING

64 Above represents sample of parts of the on-going work at the site DISILTING OF OGBAGBA AND OKOKO RIVERS, OSHOGBO, PHASE I & II, OSUN STATE BEFORE

65 Above represents sample of parts of the ecological site before the commencement of work DISILTING OF OGBAGBA AND OKOKO RIVERS, OSHOGBO, PHASE I & II, OSUN STATE

DURING

66 Above represents sample of parts of the on-going work at the site SHORELINE PROTECTION, ALEBIRI, BAYELSA STATE

BEFORE

67 Above represents sample of parts of the ecological site before the commencement of work SHORELINE PROTECTION, ALEBIRI, BAYELSA STATE ON-GOING

68 Above represents sample of parts of the on-going work at the site ABAJI GULLY EROSION AND FLOOD CONTROL WORKS ABAJI AREA COUNCIL, ABUJA

BEFORE

69 Above represents sample of parts of the ecological site before the commencement of work ABAJI GULLY EROSION AND FLOOD CONTROL WORKS ABAJI AREA COUNCIL, ABUJA

ON-GOING

Above represents sample of parts of the on-going work at the site 70 ABAJI GULLY EROSION AND FLOOD CONTROL WORKS ABAJI AREA COUNCIL, ABUJA

AFTER

71 Above represents sample of parts of the completed work AZARE TOWNSHIP FLOOD AND EROSION CONTROL WORKS, AZARE,

BEFORE

72 Above represents sample of parts of the ecological site before the commencement of work AZARE TOWNSHIP FLOOD AND EROSION CONTROL WORKS, AZARE, BAUCHI STATE

ON-GOING

Above represents sample of parts of the on-going work at the site 73 AZARE TOWNSHIP FLOOD AND EROSION CONTROL WORKS, AZARE, BAUCHI STATE

AFTER

74 Above represents sample of parts of the completed work CHANNELIZATION AND FLOOD CONTROL OF PONJ-AFO RIVER, IKIRUN, OSUN STATE: PICTORIALS OF SITE BEFORE COMMENCEMENT OF WORK

BEFORE

75 Above represents sample of parts of the ecological site before the commencement of work CHANNELIZATION AND FLOOD CONTROL OF PONJ-AFO RIVER, IKIRUN, OSUN STATE:

DURING

Above represents sample of parts of the on-going work at the site 76 CHANNELIZATION AND FLOOD CONTROL OF PONJ-AFO RIVER, IKIRUN, OSUN STATE:

AFTER

77 Above represents sample of parts of the completed work EROSION AND FLOOD CONTROL WORKS AT IFEDAYO/BOLUWADURO/ILA, OSUN STATE

BEFORE

Above represents sample of parts of the ecological site before the commencement of work 78 EROSION AND FLOOD CONTROL WORKS AT IFEDAYO/BOLUWADURO/ILA, OSUN STATE

DURING

79 Above represents sample of parts of the on-going work at the site EROSION AND FLOOD CONTROL WORKS AT IFEDAYO/BOLUWADURO/ILA, OSUN STATE

AFTER

80 Above represents sample of parts of the completed work FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

81 Above represents sample of parts of the acquired vehicles FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

82 Above represents sample of parts of the acquired vehicles NATIONAL HAJJ COMMISSION OF NIGERIA (NAHCON) ACQUIRED PROPERTY

83 NATIONAL PENSION COMMISSION (Volume License Agreement)

84 NATIONAL POPULATION COMMISSION PURCHASED VEHICLES

85 Above represents sample of parts of the purchased vehicles NATIONAL POPULATION COMMISSION PURCHASED VEHICLES

86 Above represents sample of parts of the purchased vehicles ECONOMIC AND FINANCIAL CRIMES COMMSSION (EFCC) PURCHASED OPERATIONAL VEHICLES

87 Above represents sample of parts of the purchased Operational Vehicles CONSTRUCTION OF THE ECONOMIC AND FINANCIAL CRIMES COMMSSION (EFCC)’S CORPORATE HEADQUARTERS

88 Above represents sample of parts of the on-going construction work at the site 89 90 ANNEX (I)

ECOLOGICAL FUND OFFICE (EFO) PROJECTS BELOW FEDERAL EXECUTIVE COUNCIL (FEC) THRESHHOLD FROM MAY 2015 TO DECEMBER 2017

91 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO APPROVAL THE PROJECT SKILLED/ COMPLETION) T DURATION N (%) (%) UNSKILLED

Provision of Public Conviniencies in (3) LGAs, Ibadan, Oyo State: i. Mogaji Market, The Scope of work include: Iyana Agbala i. Site Clearance; along New ii. Excavation of Pit; Ibadan-Ife Road, iii. Backfill and removal of Egbeda LGA; excess of soil; ii. Jonku Ecological iv. Construction of 1 July, 2015. 3 Months N/A 100% 18 Neigghbourhood Fund Office Conveniences; Market along Iwo v. Drilling of Boreholes sealed Road with overhead Steel Tank and Interchange, Ojoo Solar Panels. Expressway, The project is 100% completed. Ibadan North East Commissioned and handed over. LGA; and iii. Orita Aperin Market, Orita Aperin Ibadan South LGA.

The Scope of work include: Soil Erosion Site clearing / earth works and Control Works at November, Ecological Construction of Culverts and 2 1 Month. N/A 100% 30 Usho/Ise Road, 2015. Fund Office Drainages. The project is 100% Ondo State. completed and awaiting commissioning and handing over.

The Scope of work include: i. Site Clearance; ii. Earthworks and Excavation; Soil Erosion iii. Construction of Reinforced November, Ecological 3 Control Works At 1 Month. N/A 100% 25 Concrete Lined Channels; 2015. Fund Office Zuba iv. Construction of Concrete Culverts. 92 The project is 100% completed. Commissioned and handed over. THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED The Scope of work include: Construction of drainage channels; Demolition & removal of existing blocked/weak/inadequate stream crossing structures and Doma Flood drainages; Connection of existing Erosion Control November, Ecological Channels to the newly constructed 4 4 Months N/A 100% 25 Works, Nasarawa 2015. Fund Office Channels; Stone-Pitching and State Rock dump for erosion control works; and Construction of Access Culverts and provision of access Slabs across the drainage Channels. The project is 100% completed and handed over

The Scope of work include: Lohmak- Site clearing and Earth works; Kumkwum Reinforcement of concrete and Erosion Control November, Ecological 5 4 Months N/A 100% 25 lined channels; and Reinforcement Works, Langtang 2015. Fund Office of box culverts. North LGA, The Project is 100% completed Plateau State and handed over.

The Scope of work include: i. Site Clearance; ii. Earthworks and Excavation; Gully Erosion iii. Construction of concrete Control Works at December, Ecological drains/channels; 6 6 Month. N/A 100% 28 Magodo, Lagos 2015. Fund Office iv. Stone Pitching; and State v. Construction of concrete retaining wall. The project is 100% completed. Commissioned and handed over.

93 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

The Scope of work include: i. Site Clearance; ii. Earthworks and Excavation; Oghere Ahmed iii. Construction of Reinforced Erosion Control December, Ecological 7 6 Months. N/A 100% 25 Concrete Lined Channels; Works, Idimu, 2015. Fund Office iv. Construction of Concrete Lagos Culverts. The project is 100% completed. Commissioned and handed over.

The Scope of work include: i. Site Clearance; ii. Demolition and removal of existing blocked/weak and inadequate structures; Kudeti Flood iii. Construction of reinforced December, Ecological 8 Control Works, 5 Months. N/A 100% 28 rectangular and trapezoidal 2015. Fund Office Ibadan Oyo State drains/channels; iv. Construction of culverts and access slabs; and v. Stone Pitching. The project is 100% completed. Commissioned and handed over.

Scope of work include: Construction of one side Umudiato Flood trapezoidal concrete drains; Control Works, February 4th, Ecological Construction of appropriately sized 9 4 Months N/A 100% 25 Orlu LGA, Imo 2016 Fund Office box culverts; and Road State improvement works. The project is ‘100% completed and awaiting commissioning. 94 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS COST OF DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED PROJECT (N) APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

Scope of work include: Umuoki- Construction of 2.4km drains; Umuowasi Provision of concrete drains Erosion Control Ecological and culverts; and Road 10 200,382,392.19 March, 2016 4 Months N/A 100% 28 and Road Fund Office improvement works. Improvement The project is 100% completed. Works. Commissioned and handed over.

Scope of work include: Owalla Avuvu Earth works; Concrete Erosion Control Ecological Drains/Culverts; Box Culverts 11 N176,504,612.81 March, 2016 5 Months. N/A 100% 25 Works, Imo Fund Office and Stone-pitching. State The project is 100% completed and handed over.

The Scope of work include: i. Construction of Solar Powered Borehole; Model Village ii. 5000 Liters Overhead Development, Ecological Water Supply Tank; 12 July, 2016. 10 Months N/A 100% 25 Adamawa and N168,147,104.52 Fund Office iii. 50 Seating Capacity Gombe States. Community Viewing Centre. The project is 100% completed. Awaiting commissioning and handing over.

95 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO APPROVAL THE PROJECT SKILLED/ COMPLETION) T DURATION N (%) (%) UNSKILLED

Scope of work include: Reconstruction Construction of earth Dam; of Maska Earth Construction of Spillway, November, Ecological 13Dam, Maska 3 Months N/A 100% 28 Embankment and Surface 2016 Fund Office Funtua, dressed road. The project is Katsina State 100% completed and handed over

Scope of work include the following: Contract for i. Construction of 2 No. Erosion Culverts length 18m, andFlood March 6th, Ecological 14 6 Months N/A 100% 28 ii. Construction of Walkway control Work in 2017. Fund Office Access Road of 700m. Bogoro LGA Project is 100% Completed. Bauchi State Awaiting commissioning and handing over.

Soil Erosion The Scope of work include: Control Works Concrete Retaining wall and at Nigerian Ecological 15 March, 2017 4 Months N/A 100% 28 earth works. The Contract is Police Housing Fund Office 100% completed and handed Estate Kurudu, over Abuja, FCT.

96 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

Scope of work include: Gadan Toro to Site Clearance and Earth work; Market Road Concrete works/Retaining wall; Erosion Control Ecological 16 March, 2017 9 Months N/A 100% 28 and Rehabilitation of Eroded Works, Toro Fund Office Road. The project is 100% LGA, Bauchi completed and awaiting State. commissioning.

Scope of work include: Construction and Rehabilitation of Dam Erosion/Flood embankment; Control Project Expansion of Spillway; March 9th, Ecological 17 of Rice Field, 4 Months N/A 100% 18 Construction of Discharge 2017 Fund Office Shanga LGA, Channels and flood control Kebbi State Dyke. The project is 100% completed and awaiting commissioning and handing over.

97 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

Scope of work include: Gully Erosion Removing of blocked Control Works drains/Culverts and Earth at Federal Ecological 18 March, 2017 4 Months N/A 100% 25 works. The project is 100% Government Fund Office completed and awaiting College, Otobi, Commissioning and Handing Benue State Over

Scope of work include: Site clearing; Channelization Construction of Culverts; and Flood Carting away of all loosed Control of Ponj- March 4th, Ecological 19 6 Months N/A 100% 30 materials & debris; and Afo River, 2017 Fund Office asphalt overlay road. Ikirin, Osun The project is 100% completed State and awaiting commissioning and handing over.

Scope of work include: Construction of earth road; Construction of concrete drain Ganye-Yelwa 800m long; Road Erosion Construction of 5No. and Flood March 3rd, Ecological 20 10 Months N/A 100% 28 Reinforced concrete Culverts, Control Works, 2017 Fund Office double cell/single cell; and Ganye LGA, Stone-Pitching of road/drain Adamawa State side 500m. The project is 100% completed. Awaiting commissioning. 98 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS STATUS OF DATE OF USER PROCUREME ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT APPROVAL AGENCY NT THE PROJECT SKILLED/ COMPLETION) ION (%) DURATION (%) UNSKILLED

Ganye-Dabora- Daksam Road Scope of work include: Erosion and Construction of concrete drains; Flood Control Concrete culverts; Works, Ganye Ecological Earth works; and 21 March, 2017 7 Months N/A 100% 30 LGA and Fund Office rehabilitation of water supply. Reconstruction of The project is 100% completed and Jada Water Works awaiting Commissioning and System, Handing Over. Adamawa State

Scope of work include: Site Clearance; Azare Township Concrete Drains at GDSS Azare; Flood and Matsago Low Cost Housing; Ecological 22 Erosion Control March, 2017 5 Months N/A 100% 28 Old Airport and Cemetery; Culverts Fund Office Works, Bauchi and Access Slabs. State. The project is 100% completed. To be commissioned and handed over.

Scope of work include: Site clearance and earth works; Tsoho Gwaram Concrete works; Erosion and Ecological Reinforced concrete drainages, 23 Flood Control March, 2017 10 Months N/A 100% 28 Fund Office culverts and access slabs. The Project, Gwaram project is 100% completed. LGA, Jigawa State Awaiting commissioning and handing over. 99 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED Scope of work include: Kumo Gully Construction of concrete drains Erosion Site, and culverts; and Ecological 24 Anguwan Jauro March, 2017 5 Months N/A 100% 30 Stone-Pitching of embankment. Fund Office Musa, Akko LGA, The project is 100% completed and Gombe State awaiting Commissioning and Handing Over

Scope of work include: Kumo Gully Construction of concrete drains Erosion Site, and culverts; and Ecological 25 Anguwan Jauro March, 2017 6 Months N/A 100% 28 Stone-Pitching of embankment. Fund Office Sabo, Akko LGA, The project is 100% completed. Gombe State Awaiting commissioning and handing over.

Scope of work include: Amper Flood Construction of concrete drains; Hazards and Ecological Concrete culverts; and Stone- 26 March, 2017 6 Months N/A 100% 28 Erosion Control Fund Office Pitching. The project is 100% Works, Tarka LGA completed. Awaiting commissioning and handing over.

Scope of work include: Site Clearance and earth works; East of Kumo Excavation for side drains and General Hospital Culverts; to Jauro Musa Ecological Construction of trapezoidal 27 March, 2017 4 Months N/A 100% 28 Stream Gully Fund Office concrete lined drains; Erosion Control Concrete cover Slaps.. Project. The project is 100% completed. Awaiting commissioning and 10 handing over. 0 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED Scope of work include: Flood Control and Dredging and De-silting; De-silting of Construction of Concrete Ogbagba in Ecological 28 March, 2017 6 Months N/A 100% 30 embankment. Oshogbo Fund Office The project is 100% completed. Township, Osun Awaiting commissioning and State handing over. Scope of work include: Site Clearance; Reclamation of half of the gully; Construction of Road 1; Abaji Gully Construction of drainage along Erosion and Ecological 29 March, 2017 6 Months N/A 100% 28 Road 1; Flood Control, Fund Office Provision of Collector drain to FCT, Abuja connect to the reclaimed gully. The project is 100% completed. Awaiting commissioning and handing over. Scope of work include: Construction of concrete Erosion & Flood drains/Culverts; Control at Ecological Retaining wall; 30 Ifedayo/Boluwadu May, 2017 8 Months N/A 100% 30 Fund Office Earth work; and ro/Ila in Osun Asphalt pavement. The project is State 100% Completed. Awaiting commissioning and handing over.

Scope of work include: Erosion Control Dredging and De-silting; and Construction of Concrete Channelization of Ecological 31 May 17th , 2017. 6 Months N/A 100% 30 embankment. Okoko River, Fund Office The project is 100% completed. Oshogbo, Osun Awaiting commissioning and State handing over. 10 1 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED Scope of work include: Bagole-Kofare Construction of concrete drains/ Erosion Control Ecological culverts; and Earth work. The 32 Works, Yola May, 2017 6 Months N/A 100% 30 Fund Office project is 100% completed and North, Adamawa awaiting Commissioning and State. Handing Over. Scope of work include: Mitigation of Dredging; Concrete Flooding into drains/culverts; and Retaining Uburu Salt Lake wall. As at January, 2018, the And Over 20,000 Ecological project is 45% on-going. 33 May, 2017 7 Months N/A 45% 30 HA of Rice Farm Fund Office Challenge: Community at Asu-Umunaga, disagreement posed a challenge Ubulu, Ebonyi but resolved already with State. extension granted to the Contractor Scope of work include: Site Clearance and earth work; Amachara Flood Retaining wall and drainages; and And Erosion Ecological 34 May 3rd , 2017 7 Months N/A 100% 28 slope protection. The project is Control Works, Fund Office 100% ongoing. The Contractor has Abia State. been instructed to speed up the work. Contract for Scope of work include: Erosion control i. Construction of 1,235m Works at Makinde Ecological Reinforced Concrete Channel. 35 June 1st ,2017. 7 Months N/A 85% 28 way and Environs Fund Office ii. Construction of 2 Culverts; idimu Lagos iii. Pavement and Surfacing. State Project is 85% on-going. The scope of work include: Contract for i. Construction of 1.2 km Walkway Erosion and flood and Drainage; control Project Ecological ii. Interlocking Pavement; 36 June 1st ,2017. 7 Months N/A 100% 30 Aiyeotoro Fund Office iii. Construction of 5 Box Community Ondo Culverts. Project is 100% State completed. Awaiting 10 commissioning and handing over. 2 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO APPROVAL THE PROJECT SKILLED/ COMPLETION) T DURATION N (%) (%) UNSKILLED Contract for Erosion Construction of 204m Reinforced and flood control Concrete Channel and Construction Ecological 37Works in Eruwa, June 1st ,2017. 3 Months N/A 100% 25 of 2 Culverts. 100% Completed. Fund Office Ibarapa East LGA Awaiting commissioning and handing Oyo State over. Scope of work include: Contract for Erosion i. Construction of 1,777m of and flood control Reinforced Concrete Drains with Works Medical Ecological backfilling and Compaction; 38School, Bauchi June 1st ,2017. 6 Months N/A 100% 28 Fund Office ii. Construction of 2 Box Culverts. Town, Bauchi Project is 100% completed and Metropolis LGA awaiting Commissioning and Handing Bauchi State Over. Scope of work include: i. Construction of 982m Drainage; Contract for Erosion ii. Earthworks; and flood control Ecological iii. Surfacing Work, 39Works in Tarka and June 1st ,2017. 6 Months N/A 88% 28 Fund Office iv. Construction of 4 Box Culverts, Guma LGA Benue v. Bridge Works. State The project is 88% completed and Ongoing. Status of work done are: i. Excavation and desilting of all the existing drains and culverts including the drains within the roundabout; Jalingo Metropolis ii. Access slabs were provided as (Kofar Fada) required in the BEME; Shetima and Ecological iii. Double Cell Culvert has been 40 June 1st ,2017. 6 Months N/A 100% 30 Kasuwan Yelwa Fund Office constructed; Areas, Turaki A iv. Pot holes and failed part of Wards, Taraba State Shetimma Central Mosque road has been rehabilitated. The project has achieved 100% completed. Awaiting commissioning and handing over. Scope of work include: Site Clearing; Erosion Control Construction of Drainages of various Works in Uvu, Ecological sizes & dimensions; Culverts, Slabs 44 June 1st ,2017. 6 Months N/A 100% 30 Askira Uba LGA, Fund Office and Borno State. Road Improvements Works etc. The 10 project is 100% completed. Awaiting commissioning and handing over 3 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO APPROVAL THE PROJECT SKILLED/ COMPLETION) T DURATION N (%) (%) UNSKILLED

Scope of work include: Site Clearing; Tambuwal- Ecological reclamation works and construction of 45 Dogondaji Erosion June 1st ,2017. 7 Months N/A 100% 30 Fund Office drains at Bashire, Dogondaji and Road Works, Sokoto State improvement works at Jabo town. The project is 85% ongoing. Scope of work include: Odolu Community Construction of concrete drains; Soil Erosion and Ecological dredging; 46 June 1st ,2017. 12 Months N/A 100% 30 Flood Control Fund Office Stone-Pitching of the bridge area. The Project, Kogi State project is 100% completed and awaiting Commissioning.. Scope of work include: Site clearing and earth works; Gully Erosion and Drainages and Culverts; Flood Control, Ecological 47 June 1st ,2017. 6 Months N/A 100% 28 Road Improvement works and Surface Idumu Osigbudu Fund Office dressing. The project is 100% Street, Delta State. completed and awaiting commissioning and handing over Scope of work include: Gully Erosion and Site Clearance & earth works; Culverts Flood Control Works and Drains as well as Pavement Ecological 48 at Akpene Eket and June, 2017. 7 Months N/A 100% 30 Surfacing. Fund Office Its Environs, Akwa The project is 100% completed. Ibom State. Awaiting commissioning and handing over.

Scope of work include: Construction of type 1 rectangular Magama LGA drains at Ibeto; Erosion and Flood Ecological Construction of 2 drains (Trapezoid 49 June,2017. 9 Months N/A 89% 30 Control Project, Fund Office 2.3m base) at Ibeto; Construction of Niger State. type 1 drains at Salka; and Construction of a 3 cell box culverts at Busra. The project is 89% Ongoing.

Soil Erosion Control Scope of work include: and Road Site Clearing and earth works; 16m Improvement Works, Ecological Culvert of 3m high; 50 June , 2017. 6 Months N/A 90% 30 Yalenguruza, Fund Office 4 No. side drains and Road Gombe, Gombe improvement including retaining wall 10 StAte. etc. The project is 90% ongoing. 4 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS CONTRACT & STATUS OF DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO APPROVAL THE PROJECT SKILLED/ COMPLETION) T DURATION N (%) (%) UNSKILLED

Scope of work include: Soil Erosion and Site clearing; Flood Control Earth works; Project at Ecological Concrete drainages, culverts and Slabs; 51 June, 2017. 5 Months N/A 100% 28 Agenebode/Fugar Fund Office Agronomic measures; and Erosion Site, Edo soil conservation. The project is 100% State completed and awaiting Commissioning and Handing Over.

Flood, Scope of work include: Channelization and Channelization of River Owa; Reconstruction of Ecological Reconstruction of failed structures; and 52 Failed Structures June ,2017. 6 Months N/A 50.16% 30 Fund Office Road Construction. along Ijebu-Ode/ The project was Stopped at 50.16% Ilese Road Via Owa completion by Ogun State government. River, Ogun State

Scope of work include: Site Clearance; Reclamation of part of the gully; Abaji Gully Erosion Construction of Road 2; Construction of and Flood Control Ecological a reinforced concrete drain along the 53 June ,2017. 6 Months N/A 100% 30 Works, Phase II, Fund Office Road 2; Provision of Collector drain to FCT. Abuja connect to the reclaimed gully. the project is 100% completed. Awaiting commissioning and handing over.

Scope of work include: Site Clearance; Earth works; Culverts & Jikwoyi Erosion and Ecological Line Drains; Pavement and Surfacing. 54 Flood Control October, 2017 4 Months N/A 100% 28 Fund Office The project is 100% completed. Works, AMAC Awaiting commissioning and handing over.

Gully Erosion/Flood Scope of work include: Control & Road Site Clearing and earth works; Culverts Improvement works October 11th, Ecological and Drains; and Pavement and 55 at Sokale 3 Months N/A 100% 25 2017 Fund Office Surfacing. The project is 100% Community, Dutse completed and awaiting commissioning Alhaji, Bwari Area and handing over 10 Council, FCT 5 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

Erosion Control Works along Scope of work include: Bauchi-Ningi Site Clearance and Earth work; Road Junction to Concrete works as Drains and Ecological 56 the Main Campus October, 2017 4 Months N/A 65% 30 Culverts; Fund Office of Abubakar Stone-Pitching; and Tafawa Balewa Pavement Surfacing. University, The project is 65% ongoing. Bauchi State

Scope of work include: Burga - Site Clearing; Gwammadaji Construction of culverts; Flood and Ecological 57 6 Months N/A 65% 26 Earth works; Erosion Control Fund Office Drains and Concrete walls; Works, Bauchi Pavement and Surfacing. The State project is 65% Ongoing. October, 2017.

Stream Erosion Control at Chief The Scope of work include: Ogungbo Road i. Site Clearance/Preparation; One River along ii. Earthworks and Excavation; Ecological 58 Olabisi Onabanjo 7 Months N/A 80% 30 iii. Dredging; October, 2017. Fund Office University Road, iv. Channel Ago Iwoye, Ijebu Preparation/Rehabilitation works. North LGA, Phase The project is 80% ongoing. 1, Ogun State

10 6 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

Scope of work include: i. Site Clearing and Rehabilitation of Earthworks Eroded Road and ii. Culverts and Drains Drain in Apo Ecological 59 October 2017 5 Months N/A 100% 26 iii. Road Works; and Resetlement, Apo Fund Office iv. Auxillary Works District, AMAC, The project is 100% completed. Abuja Awaiting commissioning and handing over.

Scope of work include: i. Site Clearing and Flood and Earthworks; Erosion Control Ecological ii. Culverts and Drains; 60 October 2017 6 Months N/A 100% 28 at Karshi Town in Fund Office iii. Pavement and Surfacing FCT, Abuja The project is 100% completed and awaiting commissioning

Gully Erosion/Flood Scope of work include: Control and Road i. Site Clearing and Ecological 61 Improvement October 2017 3 Months N/A 100% 25 Earthworks; Fund Office Works at Durumi ii. Culverts and Drains; Mpape, FCT. iii. Road Improvement Works Abuja

10 7 THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF CONTRACT & FUNDS STATUS OF JOBS DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF SN PROJECT TITTLE IMPLEMENTAT CREATED APPROVAL AGENCY NT THE PROJECT COMPLETION) ION (%) SKILLED/ DURATION (%) UNSKILLED

Ratification of the Scope of work include: Award of Contract i. Site Clearing and Earthworks; for the ii. Culverts and Drains; Reconstruction of Ecological iii. Road Improvement Works; 62 Damaged Culverts October 2017 3 Months N/A 100% 28 Fund Office iv. Pavement and Surfacing and Road The project is 100% completed and Improvement awaiting commissioning and handing Works at Kapwa over Road, Lugbe, Abuja

Contract for the Reconstruction of Scope of work include: 3,125m2 Colapsed i. Site Clearing and Earthworks; Boundary Fence at Ecological ii. Concrete and Block works; 63 October 2017 N/A 100% 25 Federal Fund Office iii. Reinforcement and Formworks Government The project is 100% completed and College, Malali, awaiting commissioning. Kaduna State

Scope of work include: Reconstruction of i. Site Clearing and Earthworks; Damaged Culvert ii. Culverts, Drains and Concrete and Road Ecological works; 64 October 2017 4 Months N/A 100% 28 Improvement Fund Office iii. Pavement and Surfacing Works at Saburi, iv. The project is 100% completed AMAC, FCT. Abuja and awaiting commissioning and handing over

10 8