O-Train Project Update

Transportation Services Department

FEDCO April 3, 2018 2 Schedule

Monitoring RTG’s schedules and their continued adherence to November 2, 2018 RSA.

3 Maintenance Storage Facility & Assembly of Vehicles

Vehicle 32 of 34 is being assembled on the assembly line. 4 Maintenance Storage Facility & Assembly of Vehicles

5 Maintenance Storage Facility & Assembly of Vehicles

6 Construction Updates

• Concrete lining of the tunnel complete; • Rideau ventilation shaft breakthrough; • Eastbound track slab completed in Tunnel; • Installation of public art has begun; • Installation of wood ceiling at Blair started; and, • Preparations for fare equipment installations started in eastern stations.

7 Tunnel Concrete Lining Complete

8

9 Blair Station

10 Blair Station

11

12 Train Testing & Operator Training

13 St. Laurent Station

14

15 Tremblay Station

16

17 Hurdman Station

18 Hurdman Station

19

20 uOttawa Station

21 uOttawa Station

22

23 Rideau Station East Entrance

24 Rideau Station Mid-Entrance

25 Mid-Entrance

26 Parliament Station Platform

27 Platform Level

28 Lyon Station Concourse Level

29

30 Pimisi Station

31

32 Bayview Station

33 Tunney’s Pasture Station

34 Tunney’s Pasture Station

35 Trackwork Tunnel

36 OCS Installation In Tunnel

37 Upcoming works Spring construction season means several activities can begin, including:  Streetscaping on Queen and Lyon;  Landscaping at East Portal, beginning with backfilling of excavated area;  Trackwork fully installed; and  Electrification of western alignment and the tunnel. Key Milestones: Train passing through tunnel – start of testing in the system’s west side; Multiple trains operating in full CBTC mode; and Train testing – Tunney’s Pasture to Blair Station.

38 Next monthly update to FEDCO May 1