Matsqui First Nation 5720 Julian Drive PO Box 10 Matsqui, BC V4X 3R2 P: 604-826-6145 F:604-826-7009 [email protected]
November 16, 2016 via email to: [email protected]
Natural Resource Canada Major Projects Office 580 Booth Street, 12th Floor Ottawa, ON KIA OE4
Attn: Ross Neil, Crown Consultation Lead via email to: [email protected]
Environmental Assessment Office 2nd Floor, 836 Yates Street Victoria BC V8W 9Vl
Attn: Nathan Braun, Executive Project Director
Dear Mr. Neil and Mr. Braun:
Re: Draft Consultation and Accommodation Report for the Proposed Trans Mountain Expansion Project
Thank you for your letter of November 1, 2016. We have reviewed your Revised Draft Consultation and Accommodation Report, Matsqui' s separate Appendix to the Report and Matsqui's comment table on the initial draft. Unfortunately, we were not able to access the EAO's draft Summary Assessment Report, draft proposed Table of Conditions and Certified Project Description through the links provided.
We enclose our submission ofMatsqui's key issues with the evaluation of the Trans Mountain Expansion Project ("Project") to be provided to federal and provincial decision makers for their consideration.
416 2
Despite continuing issues with the characterization of Project impacts and Matsqui's strength of claim in Appendix C. 11, we will not be providing a further revised version. We would, however, like to address one new issue with the Appendix C.11. In the Appendix, you set out "In a letter to the MPMO dated September 22, 2016 Matsqui indicated that they believe they 'have been understood by the NEB."' This is a mischaracterization of Matsqui's correspondence with the MPMO. In our September 22, 2016 letter we wrote:
Matsqui did not apply for funding at this point in the consultation process because our submission to the NEB were thorough and clear and, after many letters back and forth, we believed we had been understood by the NEB. Further, we have an agreement with the proponent with respect to the construction and operation of the Project on Matsqui reserve and through Matsqui Territory.
It is therefore deeply disappointing to review the report and to learn that having expended vast time and resources participating in a process that yielded no tangible results, we now must expend further time and resources correcting the Crown's inaccurate characterizations of our rights. And given, as noted, that these inaccuracies have implications beyond this project, Matsqui must ensure that this report accurately and fully recognizes and describes Matsqui's identity as an autonomous Tribe and our title over our territory.
The Appendix misquotes Matsqui' s letter and should be amended.
Yours truly, (lL.i ) AliceM~ Encl.
cc:
Alanya Smith - [email protected] [email protected]
417 Matsqui First Nation - Summary of Key Issues with the evaluation of the Project
Matsqui First Nation ("Matsqui") engaged in the NEB process because the proposed Trans Mountain Expansion Project (the "Project") traverses the core of Matsqui territory and across Matsqui Main Reserve 2 (IR2). Matsqui also engaged in a limited process with Canada and British Columbia, purportedly designed to consider issues not sufficiently or fully addressed through the NEB process,
Matsqui's critique of the review process falls into two primary categories:
1. Failure to recognize and respect Matsqui jurisdiction, and 2. Failure to appropriately characterize and assess impacts.
1. Jurisdiction a. Matsqui Land Code and Environmental Assessment Law
Matsqui is Land Code operational under the First Nation Land Management Act (FNLMA) and Framework Agreement. Matsqui has adopted an Environmental Assessment Law to review projects proposed on or through its reserves. As the Project was being proposed to traverse Matsqui's reserve, authorisation for the Project required Matsqui approval pursuant to the Land Code, and a completed environmental assessment under the Environmental Assessment Law. Despite Matsqui's jurisdiction on reserve, and despite the direction in both CEAA, 2012 and Matsqui's Environmental Assessment Law to seek harmonization of assessments, the NEB first failed to recognize Matsqui's jurisdiction, and second, provided no mechanism, other than the sharing of information, for the assessments to be coordinated.
Despite the fact that the proponent was seeking approval for a Project on reserve, and despite Matsqui's repeated advice through its evidence for the NEB to recognize its jurisdiction, the NEB's recommended conditions for approval of the Project did not include Matsqui's consent. Further, Canada's consultation has lacked the requisite understanding and recognition of the powers and jurisdictions provided for through the FNLMA and Framework Agreement. Given the legal requirements for Matsqui's approval for the Project to go forward, the lack of full consideration of Matsqui jurisdiction is truly alarming.
First Nations that have adopted Land Codes under the Framework Agreement have made substantial progress in land and environmental governance. Canada should be building on this successful program by ensuring that federal agencies understand the Framework Agreement and encouraging its application in the assessment of major projects and in other government-to-government interactions with indigenous communities. First Nations should not be responsible for explaining the Framework Agreement to regulatory bodies and Federal agencies and persuading them to apply First Nations laws to the assessment of major projects.
This failure to recognize Matsqui's jurisdiction is not only inconsistent with legislation, but it is inconsistent with the spirit of reconciliation. In the future, it is important that the Federal and Provincial Government recognize Matsqui's jurisdiction and work with Matsqui to ensure a streamlined process for proponents looking to develop on and adjacent to our reserve lands.
b. Matsqui Aboriginal Title
Matsqui's aboriginal title includes an important jurisdictional component - the right to determine the uses of its title land. Still, and despite the strong advice from the highest court to obtain the consent of indigenous title holders prior to approval of projects, First Nations title holders, including Matsqui, are
418 relegated to the role of intervenors in project assessments, required to provide evidence backed by limited funding, to attempt to influence the recommendations of the regulator.
Prior even to the commencement of the NEB hearing, Matsqui voiced its concerns to Canada about the insufficiency of the NEB process to properly assess impacts on aboriginal rights, and in particular aboriginal title, and, in 2014, asked Canada to provide its preliminary assessment of Matsqui's strength of claim in order to inform the extent of consultation owed by the Crown. Matsqui was not provided with an assessment until the fragmented and incomplete information included in the Consultation and Accommodation Report (the Report) of August 17, 2016.
As expected, the NEB review demonstrated no capacity or willingness to even identify the characteristics of aboriginal title, let alone assess the potential impacts on title. Worse, the Crown, despite its inability to delegate the ultimate responsibility to consult and accommodate, and despite extensive evidence filed by Matsqui on its use and occupation of the proposed Project areas, appears to misapprehend the nature of title and its responsibility to title holders.
For example, the Report begins its assessment of the impacts on Aboriginal Title by describing the disruption of subsistence activities including hunting, trapping, fishing and plants gathering. No mention is made of the two fundamental components of Title - the right to choose the uses of land and the right to benefit for those lands. This despite the recognition by the Crown of the need to engage in deep consultation.
The insufficiency of the Crown's approach is further highlighted in Appendix C.ll's inaccurate assessment of Matsqui's strength of claim. The initial draft contained several errors indicative of a rushed process that appeared not to consider evidence provided by Matsqui to the NEB. Some of these errors were corrected by Matsqui. However, the final version of the Appendix still arrives, with insufficient basis, at the blanket conclusion that Matsqui strength of claim weakens where territory is shared, and promotes a site specific as opposed to territorial approach to title. This conclusion is inconsistent with the law and with evidence provided in Keith Carlson's report.
Not only are the Crown's finding incorrect in substance, but the urgency of the process, coming in a finite period post-NEB recommendation and prior to the decision, does not allow for sufficient time to address issues and concerns that arise. This further illustrates the impact of the Crown not producing or providing its strength of claim assessment at an advanced enough stage so as to facilitate meaningful consultation.
2. Impact Assessment a. NEB Review
Of the myriad shortcomings of the NEB review (set out in Matsqui submissions), the most glaring omission was the lack of assessment of the impacts of a significant spill event.
In its evidence, Matsqui submitted an impact assessment which clearly set out that:
a. The probability of a major spill was higher than what was being forecasted; b. Such a spill would have potentially catastrophic impacts on the Matsqui community, particularly in the event of a spill affected the Fraser River fishery; and c. Such impacts could be assessed and indeed quantified.
Not only does this evidence appear to have been entirely ignored by the NEB, but the impacts of a major oil spill were not even considered by the regulator. That is because the NEB accepted a definition of "significance" to be in relation to the probability of an event occurring. That it, an impact was only said
419 to be significant if it had a high probability of occurring. As such, most impacts were characterized as not significant without even considering the magnitude of the impact. Incredibly, a review of an oil pipeline was completed absent an assessment of the magnitude of the impact of a catastrophic spill because of the (largely unsubstantiated) view there was not a high probability of that kind of spill occurring.
The failure to analyse the impacts of a spill event leaves massive gaps in the NEB assessment. Indeed, that an assessment of an oil pipeline would not demand a rigorous review of the impacts of spill events effectively delegitimizes the entire process.
b. Matsqui's Review
Matsqui's review of the Project included an impact assessment (included in evidence at the NEB), an environmental assessment pursuant to the Environmental Assessment Law, and a community approval process pursuant to the Land Code.
Importantly, our impact assessment identified the significance of a spill event, and our environmental assessment required that these impacts be fully considered, regardless of the likelihood of such a spill to occur. This assessment was absolutely essential for our community, and was crucial in the decision of community to provide conditional approval for the construction and operation of the Project on Matsqui IR 2.
The difficult reality is that had the Project not been proposed on reserve, providing Matsqui with the authority to exercise its jurisdiction under the Land Code and Environmental Assessment Law, Matsqui would be reliant upon a regulator that fails to recognize the jurisdiction of First Nations to their title lands and fails to assess the true impacts of a project, and a Federal Crown that firstly, relies upon the flawed assessment by the regulator, and secondly, conducts a rushed, incomplete process after the recommendations have been made and in advance of a pending decision.
This is not a recipe for reconciliation. Matsqui expects that the Crown carefully consider the means by which it approaches the review of major projects, and in particular the means by which it supports and works with indigenous governments with jurisdiction to assess and decide whether or not these projects proceed.
420 421 MUSQUEAM INDIAN BAND 6735 SALISH DRIVE VANCOUVER, B.C. CANADA V6N 4C4 TELEPHONE: 604 263-3261Emailed to: Alayna Smith FAX: 604 263-4212 Friday, November 18, 2016
Kinder Morgan Trans Mountain Expansion Project – Musqueam Indian Band Separate Submission to the Ministers
The outstanding major issues highlighted in this submission are a mere summary of the many significant concerns raised by Musqueam with the Crown throughout the NEB process and the Post-NEB Consultation Phase, including our detailed comments on the draft CAR and EAO documents. The major issues summarized here should not be construed as negating or superseding any of the previous comments and concerns raised by Musqueam. The Crown’s Continued Refusal to Provide a Justification Analysis as required by Sparrow Musqueam has a proven Aboriginal Right to fish within our territory, which in the Sparrow case the Supreme Court of Canada accepted as including the Fraser River Estuary extending from the north shore of Burrard Inlet to the south shore of the Main Channel of the Fraser River. Fishing is integral to Musqueam’s economy, culture, and survival, and we presented ample evidence during the NEB hearings that the proposed Project will significantly infringe upon Musqueam’s Aboriginal right to fish. The Crown, therefore, is required to fully discharge its constitutional obligation to justify this infringement according to the test set out in Sparrow. Musqueam has also repeatedly requested that the Crown respond to our concerns regarding the lack of jurisdiction of the NEB to make a recommendation to issue a certificate under section 52 of the NEB Act without first making an initial determination of whether or not the Crown had satisfied its duty to have both meaningful consultations and to justify the significant infringements of Musqueam’s Aboriginal Right to fish. The Crown has refused to date to provide the required justification analysis or engage with us in a meaningful dialogue respectful of the fact that our right to fish for food, social and ceremonial purposes is an established right that is put at risk by this project. The CAR, which the Crown is relying on as their vehicle to provide responses to Musqueam regarding justification, fails to acknowledge the need for a justification analysis. The Crown has continued to attempt to divert a discussion of justification by focussing on mitigation and minimization of impacts, while ignoring evidence presented by Musqueam that the infringement of Musqueam’s Aboriginal right has already passed a critical tipping point, and therefore any and all new infringements must be justified. In response to Musqueam’s recurring question regarding the jurisdiction of the NEB, the Crown has similarly continued to dodge the issue of justification by focussing their responses on consultation and accommodation only. The proven nature of our fishing right and the justification requirement have to be factored into the Governor in Council’s decision. To date there has been no dialogue between Musqueam and the Crown reflecting Musqueam’s unique circumstances, namely that our proven right stands to be infringed and that the Crown must justify any infringement. The absence of such dialogue leaves the Governor in Council with insufficient information to assess infringement and justification.
The Crown’s Assessment of Impacts to Musqueam’s Rights and Interests Musqueam strongly disagrees with the Crown’s assessment of Project-related impacts to Musqueam’s Aboriginal Rights and Interests. Throughout the CAR, the Crown has relied upon the findings of the National Energy Board (NEB) to assess impacts; Musqueam finds it astonishing that the Crown has not questioned the NEB’s assessment nor required further studies to be commissioned, in particular to re-assess the risk and projected impacts of a major spill. The NEB’s findings are based upon the proponent’s Application, which has been widely criticized for relying upon: faulty methodology for estimating spill response likelihood and response capacity1, insufficient scientific knowledge regarding the fate of diluted
1 See: Nuka Research and Planning Group, LLC. 2015. Technical Analysis of Oil Spill Response Capabilities and Limitations for Trans Mountain Expansion Project. Expert report prepared for: Tsleil-Waututh Nation, City of Vancouver, and Tsawout First Nation. AND Gunton, Thomas and S. Broadbent. 2015. An Assessment of Spill Risk for the Trans Mountain Expansion Project. Expert report prepared for: Tsleil-Waututh Nation. 422
bitumen in estuarine environments2, and a narrowly scoped assessment of health impacts3. Accordingly, Musqueam continues to question the conclusions of the NEB Report and maintain our significant concerns regarding the impacts of the proposed Project to both the environment and our Aboriginal Rights and Interests. In each section of the Musqueam-specific Appendix to the CAR, the Crown has seen fit to summarize and then largely set aside Musqueam’s evidence regarding the significance of impacts, particularly regarding impacts to Musqueam’s fishing and marine harvesting, traditional and cultural practices, and cumulative effects to the exercise of these Rights and Interests. In their assessment, the Crown has deemed it sufficient to rely upon general NEB and EAO conditions4 as well as vague proponent commitments (in some cases referencing commitments made by the proponent to different Aboriginal groups) to mitigate impacts. In doing so the Crown demonstrates both a remarkable incomprehension of proper cumulative effects assessment and a myopic understanding of how the tangible impacts of a project (such as barriers to access) are linked to the intangible aspects of culture. Greater loss of already limited opportunities for the transmission of location- and activity-specific cultural knowledge cannot be mitigated. In Gitxaala Nation v Canada, 2016 FCA 187 at paragraph 317, the Federal Court of Appeal states that the NEB Report is “nothing more than a guidance document” that is not binding on the Crown. Musqueam sees no evidence in the CAR that the Crown has gone beyond making generic dismissals of our concerns by relying on the Report without independent analysis. Contemplated Project-Related Crown Accommodation Measures The Crown has asked for Musqueam’s views on the proposed Indigenous Advisory and Monitoring Committee, which is presented as a primary project-specific accommodation. Notably, the roles for Aboriginal committee members as currently contemplated provide no decision-making power to Aboriginal communities over project-related decisions in their traditional territories. Nor does the proposal as worded include any commitment from the Crown to provide funding to ensure that Aboriginal Groups have the capacity to participate meaningfully in such a committee. Thus, it is Musqueam’s view that the proposal simply adds to the burden of review for Aboriginal communities while utterly failing to uphold the constitutional requirements of the Crown as described in Tshilqo’tin and the United Nations Declaration on the Rights of Indigenous Peoples’ principle of “Free, Prior, and Informed Consent”. Therefore, Musqueam can only conclude that the proposal is an effort by the Crown to improve the optics of a potential project approval. An advisory and monitoring committee certainly does not address the need to justify the infringement of our established right. Closing In closing, we express our deep disappointment that our concerns expressed repeatedly from our first meetings and communications on this Project have not been addressed. The Crown has insisted on adhering to fixed and unrealistic deadlines that have not given adequate time for it to discharge its overriding constitutional duty to us and other Aboriginal peoples. We have had inadequate opportunity to express our concerns to the Crown and have them addressed. The Crown has effectively abdicated its constitutional obligations to the proponent and to the National Energy Board although it has confirmed that no delegation has taken place to the proponent and the NEB has not purported to discharge the Crown’s constitutional obligations and is unable to do so. The Crown has failed to consider in good faith and reasonably the content and extent of our established and asserted Aboriginal rights and, in particular, the duty of justification based on the Sparrow decision. Instead, it has attempted to focus discussions on mitigation and minimization of impacts. In the words of the Federal Court of Appeal in the Gitxaala decision, it has fallen short of the mark.
2 Trillium Environmental. 2015. Hearing Order OH-001-2014 Trans Mountain Pipeline ULC (Trans Mountain) Application for the Trans Mountain Expansion Project (Project) – Preliminary Report-Written Evidence. Prepared for Musqueam Indian Band. 3 Stand. 2016. Kinder Morgan and Public Health: the risks of Kinder Morgan’s pipeline in your community. http://www.stand.earth/kinder-morgan-and-public-health 4 As an example, the Crown’s assessment of impacts to marine fishing and harvesting relies upon NEB condition 131 and the EAO draft conditions for mitigation. NEB condition 131 requires the proponent to develop a public outreach program for marine traffic; the EAO does better by requiring the proponent in draft Condition 11 to develop a marine outreach program specific to Aboriginal Groups. However, the condition as currently drafted excludes Musqueam from being consulted as an “Aboriginal group” on the development of this plan.
Page 2 of 2 423 Nlaka'pamux Nation Tribal Council Box 430, Lytton, BC, VOK lZO Phone: 250 455-2711- Fax: 250 455-2565 Email: [email protected]
Submission to Federal and Provincial Decision Makers
Re: Trans Mountain Pipeline Expansion Project and Environmental Assessment
An NlakaJpamux Perspective
November 18, 2016
424 The current approval process for the Trans Mountain Pipeline expansion is inconsistent with Nlaka'pamux title and rights. Despite impending government imposed deadlines, there must be a process implemented which is consistent with Nlaka'pamux title and rights, including consent based decision making. The Nlaka'pamux have substantial objections with the process to date. A flawed process results in flawed decisions: What could destroy the Nlaka'pamux way of life is deemed an acceptable risk but Nlaka'pamux consent was not sought. The Nlaka'pamux perspective was not part of the decision. The Nlaka'pamux have not merely objected to the flawed process, we have provided a viable alternative.
As discussed at the May 5th 2016 meeting and outlined through an email on May 11th, 2016 to the Federal Government, the Nlaka'pamux Nation Tribal Council (the "NNTC") provided ideas about what a process of engagement between Canada and the Nlaka'pamux Nation might be going forward regarding the Kinder Morgan Trans Mountain pipeline expansion and received Canada's agreement at our meeting on October 3rd, 2016 to implement a shared decision making process, including the appointment of ex-officio board members. The Province is already part of the Board.
We note that just a few days after the May 5th meeting, Canada formally removed its permanent objection to the United Nations Declaration on the Rights of Indigenous Peoples. As part of doing that Minister Bennett spoke of the fundamental importance of seeking free, prior, and informed consent of Indigenous peoples before proceeding with projects. Along with those critical actions and statements was the re-iteration of the need for new Nation-to-Nation relationships grounded in recognition, respect, and reconciliation. We acknowledge that as this is a new moment in time - when we are finally moving beyond a focus on mere consultation, to actually seeking consent - there is a demand that we think out of the box in creative ways. We also acknowledge that it is challenging because of how broken this process has been to date. As we noted at our meeting, we did not participate in the NEB process because we saw it as fundamentally flawed and fundamentally disrespectful, and based on statutes that were put in place in a wrongheaded and dishonourable manner. An adversarial forum where there is no opportunity to discover or test information, no opportunity for fulsome input and about which there is a strong apprehension of bias, is not an appropriate forum for addressing title and rights. The Courts have agreed that the NEB process did not adequately address obligations to Indigenous Peoples. Similarly, as we discussed, we have had little engagement and communication with the proponent.
We appreciate all of the positive messages and actions coming from Canada, and it is our goal and intent to move forward together in a way that is consistent with these new directions and commitments. We see our engagement about this project as a step that can be used to put us on the path of establishing a new pattern of Nation-to-Nation relations. The Nlaka'pamux Nation has worked for many generations to move out of the legacy of colonialism and into a new future where our People - from our youngest newborn to our wisest Elder - can proudly live as Nlaka'pamux, in our Territory, in a way that honours and cherishes our culture, spirituality, and way of life. Historically, our efforts have never been reciprocated by Canada - and as such the status quo has been alienation, oppression, and suffering as our lands and resources are depleted; our connection with the land interfered with; our children and families broken up; and our culture and identity suppressed. We are hopeful that a moment of significant transition is upon us, where we will finally move into patterns of true partnership grounded in recognition. As such, it is important that we think deeply together on how to collaborate in new and creative ways so that we can operationalize and implement UN DRIP in our relationship in a way that is principled and functional, and moves out of the broken patterns of the past and current reality. With this in mind, we provided our thoughts for opening a dialogue to develop the appropriate process that was agreed to by the Province of BC and Canada.
To our dismay, the collaborative process agreed to was not followed and further it was hindered by untimely and very limited spatial data by the proponent during the expedited Shared Decision Making Board (the "SDMB") process despite undertakings to the contrary. The draft report provided by the Province and Canada fails to adequately capture and express the research and concerns expressed by NNTC including not adequately acknowledging the lack of information that was to be provided by the proponent that ultimately hindered the SDMB's ability to make informed recommendations. Informed decision making is further impeded by the inadequacy of work done as exemplified by the archaeology work, which may be just one of many areas of study not done to Nlaka'pamux standards resulting in critical information not being available to decision makers. The report serves to minimize NNTC's concerns by generalizing and unilaterally addressing these concerns by taking the liberty to add a reactive, mitigation approach to each concern. Step #6 of the agreed upon collaborative process required the SDMB to review the information report and identify 'joint recommendations' where possible and identify differences where they exist. These recommendations were to be documented in a SDMB report to be submitted to each party's respective decision-makers. This did not occur.
425 The report stripped NNTC's views, minimizes the importance of the issues to the Nlaka'pamux - issues which Canadian, International and Nlaka'pamux laws all recognize as necessary to be addressed. Nlaka'pamux title and rights have not been adequately taken into account in the decision making process either in terms of federal project approval nor the provincial environmental assessment process. Canadian and International laws are increasingly clear on obligations but those laws have not been adhered to in this process. The legal shift to recognition of title, and (free, prior, informed) consent based decision making, is being ignored. For the Nlaka'pamux, our fundamental law is, "If you take care of the land, the land will take care of you". These are not empty words. They are our legal obligation to future generations to protect Nlaka'pamux title and rights. Decisions made without due consideration of Indigenous title and rights, risk, indeed demand, legal challenge as to their validity.
There must be early engagement beginning before options have been eliminated. Proper engagement requires that a relationship be established. Given that the Trans Mountain pipeline has been trespassing through our Nation for 63 years, there has been more than ample opportunity for Kinder Morgan to engage with the Nlaka'pamux. Kinder Morgan has chosen not to. Rather, the proponent in the approval process has stonewalled the Nlaka'pamux and both the Province and the Federal government seem willing to "own" this problem rather than calling the company to task. The Crown is our fiduciary but it appears the company is more in control than the government. Kinder Morgan's promise and then subsequent failure to provide necessary information made it impossible for the Nlaka'pamux to adequately review the proposed project within the government's timeframe. There is a totally unacceptable lack of ecological information being provided despite repeated requests to the Proponent from the Nlaka'pamux and the Crown. There is the further issue of "not knowing what you don't know" and the notion being floated that there are so many uncertainties, there is nothing to be done about it. This means, decision makers cannot possibly have all the information they need to make an informed decision. The Proponent cannot be allowed to benefit from its wrong-doing. Decision makers must deal with the fact that they are not in a position to be able to properly reach a decision.
We are being asked to trust that the proponent will follow 157 federal conditions and 35 provincial conditions. We have no grounds to trust them. Their recent conduct does not bode well for compliance. More fundamentally, these conditions reflect dealing with problems rather than avoiding the problems. The conditions are not adequate. Conditions require reporting rather than resolving, to try rather than to do. Our title and rights, our way of life and our future are too important to relegate to this ineffective approach. In Provincial condition 25, the Nlaka'pamux are to participate in the proponent's archaeological process. This despite the Province being fully aware that the Nlaka'pamux archaeology model has been proven far superior and it is our cultural property that is being studied and impacted. Nlaka'pamux are the best experts on Nlaka'pamux. We have provided a professional critique of the lack of adequacy of the archaeological work done on behalf of the proponent. There is a theme emerging - if one doesn't find the archaeological remains, one won't have to deal with them which the proponent may believe is expedient but which we will prove is not. As final decision makers, you cannot ignore that you are aware of this situation. The best possible model must be used.
Overall the report is replete with Euro-Canadian world views and cultural assumptions, such as that silence means consent; that refusal to accept funds for traditional use studies betokens a lack of interest either in traditional use or the potential impact of the pipeline; and that telephone calls, newsletters and community information meetings constitute consultation. Similarly, there are assumptions about prior disturbance of land as justification for further disturbance. For the Nlaka'pamux, prior disturbance and cumulative impacts demand there be greater caution. It is not a question of if a pipeline will leak and there will be spills. The question is when, where and how much. The approach in this process is mitigation based but there is much that can never be mitigated. Risk means very different things depending on where you stand. The language justifying decisions is of benefits and burdens. For too many years, others have attempted to tell us what is of benefit for us while denying the burdens imposed.
The report is the result of a flawed process - a process inconsistent with the nature of Nlaka'pamux title and rights. The government by deciding to proceed on a band basis ignored the legal nature of title. Bands did not exist in 1846 nor at the time of contact. They are a construct of the Indian Act and a tool of divide and conquer. They are not the holders of title and rights. Bands signing benefit agreements cannot be taken as consent to impact Indigenous rights. Only the true holder of the right can do that.
The decision making process for the Trans Mountain Expansion has been flawed in myriad ways. The result is that a just decision cannot be reached. The requisite information is not available. The Crown as our fiduciary cannot make or accept misinformed decisions. The viable process offered by the Nlaka'pamux and accepted by government provides a means to reach a fair and proper decision that moves us towards recognition and reconciliation. It may be late, but better late than never.
426 SUBMISSION(OF(PACHEEDAHT(FIRST(NATION((PACHEEDAHT)(ON(ACCOMMODATION(MEASURES( FOR(THE(PROPOSED(TRANS(MOUNTAIN(EXPANSION(PROJECT((PROJECT)! ! Pacheedaht!is!located!off!the!west!coast!of!Vancouver,!near!Port!Renfrew,!BC.!This!area!has!been! our!home!for!thousands!of!years.!We!have!never!surrendered!our!Aboriginal!title!and!other!rights.! We!rely!on!the!richness!of!resources!in!our!homeland!to!sustain!our!people,!culture,!economy!and! way!of!life,!with!marine!resources!playing!a!critical!and!central!role.!Indeed,!our!name!means! “People!of!the!Seafoam”!and!our!cultural!integrity!is!reliant!on!the!marine!environment.! ! In!the!NEB!and!consultation!processes!for!this!Project,!we!have!consistently!raised!two!serious! concerns.!First,!we!will!be!impacted!every!single!day!from!the!increase!in!oil!tankers!associated!with! the!Project!(from!10!transits!a!month!to!68!a!month,!for!a!total!of!696!new!transits!a!year)!because! they!will!go!through!our!key!offshore!harvesting!site!at!Swiftsure!Bank.!Second,!an!oil!spill!from!a! ProjectQassociated!tanker!would!be!catastrophic!to!our!ability!to!harvest,!the!exercise!of!our! Aboriginal!rights,!our!culture!and!our!ability!to!remain!Pacheedaht.!Although!we!entered!into!a! Mutual!Benefits!Agreement!with!the!proponent,!we!retained!our!right!to!seek!meaningful! accommodation!from!the!Crown!in!relation!to!those!two!significant!and!concerning!Project!impacts.! We!look!to!the!Crown,!in!your!decisionQmaking!processes,!to!meaningfully!address!those!impacts.! ! There!are!means!for!the!Crown!to!help!address!these!impacts;!all!that!is!required!is!the!political!will! to!implement!them.!In!the!Crown!consultation!process,!we!have!proposed!two!such!means:!! ! 1.!Movement!of!the!shipping!lanes!through!the!Strait!of!Juan!de!Fuca!to!avoid!our! harvesting!sites!at!Swiftsure!Bank;!and!! ! 2.!Installation!of!a!marine!emergency!response!centre!at!Port!Renfrew.! ! Shipping'Lanes! ! If!the!Project!is!approved,!our!people!will!have!to!contend!with!an!average!of!more!than!two!oil! tankers!each!day,!in!addition!to!all!of!the!other!existing!and!proposed!vessels!in!the!area.!This!will! seriously!impede!our!ability!to!harvest!at!Swiftsure!Bank.!Swiftsure!Bank!is!one!of!the!most! important!marine!harvesting!areas!in!our!Territory.!It!is!closed!to!commercial!fishing,!and!has!been! designated!as!an!aboriginal!harvesting!area!within!the!territories!of!Pacheedaht!and!Ditidaht.!It!is! an!incredibly!rich!and!diverse!area.!Our!people!can!often!harvest!enough!halibut!from!one!day!of! fishing!there!to!feed!their!families!for!a!year.!We!manage!this!area!through!traditional!protocols!for! the!benefit!of!our!people,!as!well!as!other!Aboriginal!harvesters!across!Canada!and!beyond.! ! Unfortunately,!our!ability!to!safely!harvest!at!Swiftsure!has!already!been!seriously!compromised! because!of!the!movement!of!shipping!lanes!2005.!The!shipping!lanes!were!moved!without!any! consultation!with!us,!despite!the!fact!that!the!new!location!of!the!outgoing!shipping!lane!goes!right! through!Swiftsure!Bank,!a!hereditary!fishing!area.!The!movement!of!the!shipping!lane!has!created! serious!risks!for!our!safety!and!has!resulted!in!loss!of!anchors!and!fishing!gear!when!we!have!to!get! out!of!the!way!for!the!large!vessels!that!now!ply!those!waters.!The!safety!concerns!are!exacerbated! by!the!fog,!high!winds!and!high!waves!that!are!common!in!this!area.!Many!times,!we!cannot!even! see!the!vessels;!we!can!only!hear!them!and!try!to!guess!from!what!direction!they!are!coming.!
! ! 427 Q!2!Q!
! With!the!significant!increase!in!tanker!traffic!every!day,!we!will!literally!have!to!take!our!lives!in!our! hands!to!harvest!at!Swiftsure.!Understandably,!many!of!our!members!will!not!be!willing!to!do!that.! Those!who!do!continue!to!harvest!at!Swiftsure!will!not!want!to!bring!their!children!there,!for!fear!of! their!safety.!This!will!have!a!serious!adverse!impact,!not!just!on!our!ability!to!harvest!there!and!feed! our!community,!but!also!on!our!ability!to!transmit!traditional!knowledge!of!fishing!practices,!and!of! Swiftsure!Bank!itself,!to!our!children,!grandchildren!and!generations!yet!unborn.!In!time,!our! profound!cultural!and!spiritual!connection!to!Swiftsure!Bank!could!be!lost.!! ! The!federal!government!has!the!ability!to!address!this!situation!by!moving!the!shipping!lanes!away! from!Swiftsure.!We!have!been!trying!to!engage!with!Canada!on!this!proposal,!but!there!have!been! no!concrete!steps!taken!to!explore!this!opportunity.!As!an!accommodation!measure!to!address! Project!impacts!to!Pacheedaht!and!other!First!Nations!that!harvest!at!Swiftsure!Bank,!we!ask! federal!decisionQmakers!to!immediately!initiate!a!process!to!work!toward!the!movement!of!the! shipping!lanes!away!from!Swiftsure.!We!also!seek!the!province’s!support!for,!and!in,!such!a!process.! ! Marine'Emergency'Response'Centre! ! Offshore!from!Port!Renfrew!is!one!of!the!highest!risk!areas!for!a!vessel!incident:!the!J!Buoy.!Oil!spill! modelling!has!shown!that!in!the!event!of!an!oil!spill!at!the!J!Buoy,!the!oil!will!wash!up!on!our!shores! at!and!near!Port!Renfrew.!An!oil!spill!on!our!shorelines!would!be!catastrophic,!impacting!our! intertidal!and!coastal!harvesting!sites!for!potentially!decades,!damaging!a!beautiful!and!sensitive! ecosystem!and!destroying!our!Treaty!vision!for!ecoQtourism.!Despite!those!facts,!there!is!currently! no!emergency!response!centre!at,!or!even!remotely!near,!Port!Renfrew.!Western!Canada!Marine! Response!Corporation!(WCRMC)!is!not!actively!planning!to!build!a!response!centre!at!Port!Renfrew.! The!closest!proposed!response!centres!are!at!Beecher!Bay,!Ucluelet!or!Port!Alberni.!These!are!far! from!the!high!risk!area!at!J!Buoy,!and!will!not!ensure!timely!emergency!response!to!the!J!Buoy!or! Port!Renfrew!areas.!Even!in!calm!seas,!it!would!take!over!3!hours!to!reach!Port!Renfrew!from!any!of! these!locations;!in!poor!conditions!it!could!take!days.!!
Prime!Minister!Trudeau’s!announcement!of!a!$1.5Qbillion!plan!to!ensure!better!protection!of! Canada’s!coasts!from!oil!spills!provides!a!mechanism!to!support!the!construction!of!an!emergency! response!centre!at!Port!Renfrew,!to!address!the!lack!of!emergency!response!in!the!vicinity,!the!level! of!vessel!traffic!(especially!if!the!Project!is!approved),!and!the!high!risk!area!at!J!Buoy.!An! emergency!response!centre!at!Port!Renfrew!would!also!help!satisfy!BC’s!condition!for!worldQclass! spill!response!and!help!address!some!of!the!marine!safety!gaps!BC!has!identified,!including!the! need!for!sufficient!capacity!to!arrive!at!spill!sites!within!three!hours.!
WCMRC!has!identified!Port!Renfrew!as!an!ideal!location!for!an!emergency!response!centre,!but!the! lack!of!a!yearQround!marina!has!been!an!impediment.!A!yearQround!marina!has!now!been!built.!In! addition,!Pacheedaht!has!been!actively!exploring!an!opportunity!to!build!a!yearQround!marina!at! the!government!dock,!in!partnership!with!the!Port!Renfrew!community.!As!well!as!addressing!the! stark!need!for!emergency!response!in!Port!Renfrew,!it!would!be!a!model!of!reconciliation.! However,!Pacheedaht!needs!the!support!of!Canada!and!BC!for!this!vision!to!become!a!reality.!We! urge!Canada!and!BC!to!facilitate!the!construction!of!an!emergency!response!centre!at!Port!Renfrew,! as!an!accommodation!measure!and!Project!condition.!
! 428 Pauquachin First Nation
November 15, 20 16
Attention: Ross Neil Attention: Nathan Braun Crown Consultation Lead Executive Project Director Major Projects Management Office Enviromnental Assessment Office 800 Burrard Street, Suite 219, 5th Floor PO BOX 9426 STN PROV GOVT Vancouver, BC V6Z OB9 Victoria, BC V8W9Vl
Re: Submissions of the Pauquachin First Nation ("Pauquachin") to federal and provincial decision makers on the proposed Trans Mountain Expansion Project (the "Project")
We are in receipt of your letter dated November 1, 2016 providing Pauquachin a revised Consultation and Accommodation Repott for the Project (the "Consultation and Accommodation Report"), and inviting Pauquachin to comment on that Report and/or provide a separate submission to federal and provincial decision makers for the Project. Pauquachin has opted to provide a separate submission. Please provide a copy this letter to federal and provincial decision makers for the Project.
As you know, Pauquachin entered into a Mutual Benefits Agreement with Kinder Morgan in respect of the Project. Pursuant to that Agreement, Pauquachin suppo11 s regulatory approval of the Project subject to the right to make submissions aimed at better protecting the environment and Pauquachin culture. In the National Energy Board ("NEB") hearing for the Project (the "NEB hearing"), Pauquachin made a number of specific recommendations that it beli eves should be implemented or committed to prior to the Project being approved to better protect the environment and Pauquachin culture.
The NEB's Report fo r the Project does not adequately address these recommendations, nor have they been adequately addressed in the Crown's consultations with Pauquachin after the NEB hearing. Indeed, Pauquachin is deeply concerned with the federal and provincial govenm1ent's consultations with Pauquachin on the Project. It does not feel those consultations have been adequate, as suggested in the Consultation and Accommodation Report. The post-NEB hearing consultations have been rushed, with limited oppo1tunity for meetings with federal and provincial representatives to discuss Pauquachin's recommendations. The consultations appear to have been aimed more at checking boxes rather than engaging in meaningful consultations.
As indicated in our submissions in the NEB hearing and subsequent discussions with the Crown, Pauquachin urges implementation of, or a commitment to implement, the following recommendations prior to the Project being approved:
1. Emergency Response Towing Vessels - In addition to escort tugs for Project-related tankers, which Kinder Morgan has committed to and is ensured through the NEB proposed conditions for the Project, emergency response towing vessels should be stationed at strategic locations along
9010 West Saanich Road, Sidney BC V8L 5W4 I Phone: 250-656 -0191 I Fax: 250-656 -6134 429 the marine shipping route. This was recommended by other intervenors in the NEB hearing and Pauquachin believes is important to ensuring a world-class spill prevention system.
2. Salvage Personnel and Equipment - A resident salvor and personnel as well as salvage equipment should be stationed at strategic locations along the marine shipping route. Again, this was recommended by other intervenors in the NEB hearing and Pauquachin believes is important to ensuring a world-class spill prevention system.
3. Fate and Behavior of Diluted Bitumen - The federal government should conduct, commission, fund or require additional research on the fate and behavior of diluted bitumen in the marine environment, and should consult with Pauquachin regarding the outcome of that research. Pauquachin understands that the fate and behavior of diluted bitumen in the marine environment is still scientifically uncertain, and that there are gaps in existing research. Pauquachin acknowledges the provincial government's proposed condition #33, which would require Kinder Morgan to develop a plan to lead, jointly lead or support research on this topic; however is concerned regarding the timing and independence of that research. Pauquachin submits that this research should be undertaken ideally before the Project is approved and at a minimum before the Project is operational. To ensure independence, Pauquachin further submits that Kinder Morgan should not undertake or direct the research.
4. Spill Response Base on Saanich Peninsula - Pauquachin understands that WCMRC is currently planning to establish a new spill response base on the Saanich Peninsula to assist in improving its spill response capacity. To ensure incidents within Pauquachin's traditional territory are responded to in timely manner, Pauquachin submits that, regardless of whether or not the Project proceeds, a spill response base should be established on the Saanich Peninsula and Pauquachin should be consulted regarding the establishment of that base.
5. Spill Response Capacity- The federal government should engage in further consultations with Pauquachiu regarding WCMRC's spill response capacity, directly or through agreements with other spill response agencies, and increase the capacity required under federal law to au appropriate level. While the risk of a major oil spill may be low, Pauquachin remains concerned that such a spill may occur and that even with WCMRC's proposed improvements to its spill response capacity, it may not have sufficient capacity to respond to a major spill. To the extent this will be addressed through the federal government's Area Response Planning ("ARP") initiative, Pauquachin submits that the recommendations from that initiative should be implemented at a minimum before the Project is operational.
6. Planning and Training - Canada should assess any deficiencies in the responses to the May 2016 diesel spill in Esquimalt Harbour and the 2015 oil spill in English Bay and either implement or recommend improvements to address those deficiencies. Canada should also consult or require consultation with Pauquachin regarding the possibility of training one or more Pauquachin members in spill response measures. Pauquachin understand that there are lessons to be learned from the Esquimalt Harbour and English Bay oil spills, and that First Nations could play an important role in early response to any oil spill within their respective traditional territories if they are equipped with appropriate training and gear.
430 9010 West Saanich Road, Sidney BC VBL 5W4 I Phone: 250-656-0191 I Fax: 250-656-6134 7. Spill Compensation Regime - The federal government should engage in further consultations with Pauquachin regarding the spill compensation regime for marine-based oil spills. While the federal government has provided Pauquachin some information in respect of this regime, Pauquachin remains concerned that the amount available may not be adequate in the event of a major oil spill and that any damages to Pauquachin's culture and aboriginal and treaty rights may not be sufficiently compensated under the regime.
8. Salish Sea Environmental Foundation - Pauquachin urges the federal government to shift its focus from this Project alone to the cumulative impacts of development on the Salish Sea. Pauquachin is deeply concerned regarding the long term health of the Salish Sea as a result of existing and future development. Pauquachin has suggested to the federal government on multiple occasions that one tool to help understand, discuss and address those cumulative impacts would be the establishment of a Salish Sea Environmental Foundation. There are several existing models that could be drawn upon when establishing such a Foundation. Kinder Morgan and multiple other First Nations support its establishment. Pauquachin again seeks confirmation from the federal government that it will support this initiative and funding to support the research and discussions necessary to establish it.
9. Environmental and Regulatory Processes - Pauquachin remains concerned that environmental and regulatory processes in respect of the Project were flawed for a number of reasons, including the lack of cross-examination in and the scope of the NEB hearing. Pauquachin acknowledges that these processes are currently under review by the federal government, and looks forward to making submissions to the federal government on how they can be improved.
Again, Pauquachin urges implementation of, or a commitment to implement, the above recommendations prior to the Project being approved. If you have any questions or wish to discuss any of the recommendations, please do not hesitate to contact the writer.
Sincerely,
Chief Rebecca Harris
431 9010 West Saanich Road, Sidney BC V8L 5W4 I Phone: 250-656-0191 I Fax: 250-656-6134
November 15, 2016
Mark Youden VIA EMAIL Direct 604-891-2793 [email protected] File No. V41382 Alanya Smith, Project Assessment Officer Environmental Assessment Office P.O. Box 9426 Stn Prov Govt Victoria, BC V8W 9V1 Email: [email protected] [email protected]
Dear Ms. Smith:
Re: Revised Draft Consultation and Accommodation Report for the Proposed Trans Mountain Expansion Project
Thank you for your letter dated November 1, 2016 and accompanying documents. We write to provide comments with regards to the revised draft Consultation and Accommodation report, specifically the Peters First Nation’s appendix to the report and the Proposal for the Indigenous Advisory and Monitoring Committee. We also attach in a separate document our comments to the Crown’s responses to Peters First Nation’s comment table.
1. Peters First Nation comments regarding the draft Consultation and Accommodation Report Appendix C.12
Peters First Nation acknowledges the following comment found on page 5 of appendix C. 12:
“On July 22, 2016, the MPMO replied to correspondence received from Peters and Shxw'ōwhámel First Nation expressing interest in receiving a draft protocol and budget to showcase the type of Nation-to-Nation agreement Peters and Shxw'ōwhámel First Nation were seeking. To date, the Crown has not received any further correspondence on the matter, nor did Peters (or Shxw'ōwhámel First Nation) respond to the Crown’s invitation to arrange a second Phase III consultation meeting in Fall 2016.”
Shxw'ōwhámel First Nation and Peters First Nation will reply to this correspondence in due course.
“Potential Impacts of the Project on Peters’ Aboriginal Interests”
Peters First Nation rejects the Crown’s assessment of the “Potential Impacts of the Project on Peters’ Aboriginal Interests”. The level of impacts assessed by the Crown in this appendix does not reflect the level of impacts assessed in the TUS study prepared by the firelight group (May 2015).
As stated in the TUS study prepared by the firelight group:
GOWLING WLG (CANADA) LLP T +1 (416) 862-7525 Gowling WLG (Canada) LLP is a member of Gowling WLG, an international law firm 1 First Canadian Place, 100 King Street West, F +1 (416) 862-7661 which consists of independent and autonomous entities providing services around the Suite 1600, Toronto, Ontario M5X 1G5 Canada gowlingwlg.com world. Our structure is explained in more detail at gowlingwlg.com/legal.
VAN_LAW\ 2179601\1 432
“The residual effects of the Project on Peters Band knowledge and use are likely to be adverse and of very high environmental consequence. This is largely because the proposed Project will have impacts on areas of intense Peters Band use, including areas that are highly important for habitation, cultural, and subsistence activities around the Peters Band reserves. There will likely be higher levels of impact during the construction phase due to noise, contamination events (and fear and uncertainty over contamination events), and increasing numbers of workers, vehicles, and traffic around the reserves. However, many impacts will also be ongoing during the lifetime of the pipeline and may continue after the life of the pipeline. Residual effects on Peters Band knowledge and use from the Project are anticipated to be significant based on the information collected in the Study, analysis of proposed mitigation measures, and consideration of existing cumulative impacts to Peters Band knowledge and use within the Project footprint, LSA, and RSA. This prediction is made with a high degree of confidence.” (Page 14)
More specifically, we have concerns with the following assessments: