Alupar Investimento S.A. Corporate Taxpayer’s ID (CNPJ/MF): 08.364.948/0001-38 Publicly Held Company

Notice to the Market

ALUPAR INVESTIMENTO S.A. (“Company”), a publicly held company registered with the CVM under number 2149-0, informs its shareholders and the market in general the obtainment of the environmental licenses of its subsidiaries, as follows:

(i) Empresa de Transmissão Agreste Potiguar S.A. (“ETAP”), received the Operation License ("OL") from the Institute of Sustainable Development and Environment of Rio Grande do Norte (IDEMA) for the João Câmara III Substation, according to Administrative Act number 2018-130390/TEC/LO-0357, dated of March 13, 2019.

ETAP is responsible for implementing Lot I, of the 1st Stage of Transmission Auction No. 013/2015, held in April 2016. Alupar holds 100% in the asset. The deadline set by ANEEL to implemented ETAP is December 2019.

(ii) Empresa de Transmissão Baiana S.A. (“ETB”), received the Installation License ("IL"), of the 500 kV Transmission Line, II – II, from the Institute of Environment and Water Resources (INEMA), according to Ordinance number 17,916, of March 14, 2019, published on the same date at the Diário Oficial of the State of .

ETB is responsible for implementing Lot E, of the 1st Stage of Transmission Auction No. 013/2015, held in April 2016. Alupar holds a 50.0% interest in the asset. The deadline set by ANEEL to implemented ETB is June 2020.

Projects in Deployment in Licensing Status Operation RAP* Lot State km PL IL License (R$ MM) ETB (Lot E) BA 446 134.8 III – Ourolândia II BA 186 Issued Issued 52.3 Bom Jesus da Lapa II – Gentio do Ouro II BA 260 Issued Issued 82.5 ETAP (Lot I) RN 20 -1 Issued Issued 53.8 ETC (Lot T) ES - Issued Issued 31.2 EDTE (Lot M) BA 170 Issued Issued 66.1 TPE (Lot 2) MG/BA 541 Issued On hold 228.0 TCC (Lot 6) MG/ES 288 Issued On hold 155.0 ESTE (Lot 22) MG/ES 236 Issued On hold 107.3 TSM (Lot 19) SP/RJ 330 On hold On hold 104.2 *Cycle 2018/2019 | IL = Installation License | PL = Preliminary License | SL = Simplified License (PL, IL and OL) 1 Substation - there was no need to issue PL. It was issued directly to IL, since it is an extension of an existing Substation. Transmission Line - due to being a project of low environmental impact, was issued directly the LS.

In this way, Alupar reinforces its focus on execution and on-time delivery of its projects under construction, demonstrating commitment to sustainable growth, financial discipline, operational efficiency and generation of value to its shareholders.

São Paulo, March 14, 2019

José Luiz de Godoy Pereira Investor Relations Director